NYU CORE Construction Presentation

Similar documents
NYU CORE Construction Presentation

DRAFT ENVIRONMENTAL IMPACT STATEMENT AND DRAFT SECTION

BACKGROUND: Prepared by: Giovanni Mastrogiacomo Page 1

BACKGROUND: Prepared by: Giovanni Mastrogiacomo Page 1

New Stadium Project. Construction Activity Mitigation Program. January 22, 2014

BACKGROUND: Prepared by: Giovanni Mastrogiacomo Page 1

B. OVERVIEW OF CONSTRUCTION ACTIVITIES

A. INTRODUCTION AND SUMMARY OF FINDINGS B. CONSTRUCTION SCHEDULE

Noise Assessments for Construction Noise Impacts

PRINCIPAL CONCLUSIONS

BACKGROUND: Prepared by: Giovanni Mastrogiacomo Page 1

Appendix H Mitigation Monitoring Plan

Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING Oak Avenue. Evanston, IL 60201

13.1 INTRODUCTION 13.2 CONSTRUCTION METHODS

Cumulative and Secondary Impacts

B. DESCRIPTION OF CONSTRUCTION ACTIVITIES

Transformer Vault Placement and Space Requirements

A. INTRODUCTION B. LAND USE, ZONING, AND PUBLIC POLICY C. SOCIAL CONDITIONS

CHAPTER 21: COMMITMENT OF RESOURCES

Hamilton Green. Draft Environmental Impact Statement (DEIS)

Mitigation Monitoring Program Campus Master Plan 2015

PLANNED UNIT DEVELOPMENT & PLANNING APPROVAL STAFF REPORT Date: February 7, 2013

A. LAND USE, ZONING AND PUBLIC POLICY

Naim Rasheed, NYCDOT Shakil Ahmed, NYCDOT Luigi Casinelli, HDR. July 18, 2012 ITE Technical Conference

Q. CONSTRUCTION IMPACTS

Indirect and Cumulative Effects

OPTIONAL STATIONAVIATION/MANCHESTER

Evaluation of Alternatives

APPENDIX C NOISE STUDY TECHNICAL REPORT

Lynnwood Link Extension 2013 Draft EIS Comments and Responses

Draft Environmental Impact Statement (DEIS) Public Hearing

Indirect and Cumulative Effects

Albany Park Stormwater Diversion Tunnel

Albany Park Stormwater Diversion Tunnel

Chapter 21. Noise BACKGROUND

PRINCIPAL CONCLUSIONS

PRINCIPAL CONCLUSIONS

A. INTRODUCTION OVERVIEW

Exhibit G. Construction Mitigation Plan

OVERVIEW. Work Progress to Date Action Items Follow Up Community Relations Update Construction Phasing

NYU Core: Post-EIS Façade Improvement Acoustical Assessment

A. INTRODUCTION OVERVIEW

COMMERCIAL WASTE MANAGEMENT STUDY VOLUME III CONVERTED MARINE TRANSFER STATIONS - Commercial Waste Processing and Analysis of Potential Impacts

APPENDIX A Final Scope of Work

NEPA and Design Public Hearings

14: INTRODUCTION

Alternatives Assessment for the Quebec Street Improvements, Denver County

SouNDThANsIr. Sunmer Access Improvements Project MITIGATED DETERMINATION OF NONSIGNIFICANCE

Noise October 22, Noise Existing Conditions. Noise Characteristics

BARRY S CORNER. Draft Construction Management Plan

APPENDIX C NOISE STUDY TECHNICAL REPORT

University Corridor Draft Environmental Impact Statement (DEIS)

RECORD OF DECISION A. DESCRIPTION OF THE SELECTED PROJECT HALLETTS POINT REZONING QUEENS, NEW YORK

Welcome and thank you for spending time with us today to talk about the 75 th Street Corridor Improvement Project.

Preliminary Project Assessment

11 Joint Development Regulatory Context and Methodology

VOLUME 1 Foreword...F-1 Executive Summary... S-1

IV. ADVERSE IMPACTS THAT CANNOT BE AVOIDED

Indirect and Cumulative Effects

A. INTRODUCTION B. AIRBORNE NOISE

Second Avenue Subway (SAS) Project. Construction on Second Avenue. Interim Report. Prepared for: MTA Capital Construction.

CORPORATE OFFICE BUILDING, C-11, URBAN ESTATE-II CITY CENTRE SECTOR 29, GURUGRAM, HARYANA

4. ENVIRONMENTAL IMPACT ANALYSIS 8. NOISE

Northern Branch Corridor CLC Meeting. June 30, 2008

COMMUNITY BOARD EIGHT

NOISE GOALS / POLICIES / MEASURES

NOISE GOALS / POLICIES / MEASURES

STATE ENVIRONMENTAL QUALITY REVIEW ACT STATEMENT OF FINDINGS HUDSON RIVER PARK TRUST. Block 675 East Project June 28, 2018

52 North Broadway DEIS Scoping Outline

ENVIRONMENTAL ASSESSMENT for. Village of Williamsburg. SR 133 Sewer Expansion Project Loan Number CS

ARTICLE 13 SITE PLAN REVIEW

Jobsite Specifications The A standard provides jobsite specifications for each of the following hazards:

Mitigation Monitoring Program

MAINE MEDICAL CENTER

Edmonton Public School District No. 7

ENVIRONMENT MANAGEMENT PLAN

Green Line extension Project Fall 2009

ENVIRONMENTAL MANAGEMENT PLAN

ADDENDUM TO THE SEPA CHECKLIST. For the HAMILTON INTERNATIONAL MIDDLE SCHOOL RENOVATION PROJECT. June 2009

Wyandanch Intermodal Transit Facility

Indirect and Cumulative Effects

Crossrail. Environmental Statement. Volume 9c. Appendices. Westbourne Park Bus Garage Extension. Volume 2 Appendices

FIFTH ADDENDUM TO THE CIVIC CENTER SPECIFIC PLAN EIR APRIL 2015

22.1 INTRODUCTION 22.2 ANALYSIS METHODOLOGY REGULATORY CONTEXT

Corridor Residential Traditional District Regulations City of St. Petersburg City Code Chapter 16, Land Development Regulations

5.0 ALTERNATIVE VARIATIONS

A. INTRODUCTION AND METHODOLOGY

CONSTRUCTION TRAFFIC MANAGEMENT PLAN for LEICHHARDT PARK CHILDCARE CENTRE

ZAB Hearing May 14, 2015

Preferred Elevated Tank Site

Corridor Commercial Traditional District Regulations City of St. Petersburg City Code Chapter 16, Land Development Regulations

RUNWAY 7L/25R RUNWAY SAFETY AREA (RSA) AND ASSOCIATED IMPROVEMENTS PROJECT MITIGATION MONITORING AND REPORTING PROGRAM 2017 PROGRESS REPORT

PREPARED TESTIMONY OF LEE LISECKI. Q. Please state your name, professional position, and business address.

6 ALTERNATIVES 6.1 INTRODUCTION

SUMMARY OF MITIGATION OF CONCERNS RAISED IN FINAL ENVIRONMENTAL IMPACT STATEMENT

Sidewalk Regulations. Table of Contents

PUBLIC HEARINGS June 6 & 7, 2018

WELCOME IL 47. Community Advisory Group Meeting #5 Waubonsee Community College Wednesday, May 31, 2017

15.1 INTRODUCTION CONTEXT

Transcription:

NYU CORE Construction Presentation Prepared for Community Board 2 January 18, 2012 1

Construction Impacts Chapter 20 of the DEIS Transportation o Traffic o Transit o Pedestrians o Parking Air Quality Noise and Vibration Other Technical Areas o Historic and Cultural Resources o Hazardous Materials o Natural Resources o Open Space o Socioeconomic Conditions o Community Facilities o Land Use and Neighborhood Character 2

LaGuardia Place Greene Street Walk Temporary LaGuardia Play Area Mercer Street Phase 1 Construction (2013-2021) Phase 1 Buildings West Third Street Temporary Gym Zipper Building Bleecker Building Phase 1 Open Space Temporary Gym (2013-2014) Temporary Mercer Entry Plaza Relocated Dog Run Temporary Mercer Entry Plaza Temporary LaGuardia Play Area Greene Street Walk Toddler Playground Bleecker Building (2018-2021) Bleecker Street Zipper Building (2014-2018) Toddler Playground Relocated Dog Run West Houston Street 3

LaGuardia Place Mercer Street Tricycle Garden Phase 2 Construction (2022-2031) Phase 2 Buildings Mercer Building LaGuardia Building North Block Below Grade Space Phase 2 Open Space Philosophy Garden and central portion of Public Lawn WSV Play Garden Mercer Entry Plaza Tricycle Garden LaGuardia Entry Plaza LaGuardia Building (2028-2031) LaGuardia Play Garden West Third Street Public Lawn Philosophy Garden WSV Play Garden Bleecker Street Mercer Building (2023-2028) Mercer Entry Plaza LaGuardia Entry Plaza West West Houston Street LaGuardia Play Garden 4

NYU Commitments to Minimize or Avoid Significant Adverse Impacts Air Emissions Reduction Program Diesel Equipment Reduction (e.g., early electrification) Clean Fuel (ultra-low-sulfur diesel [ULSD]) Best Available Tailpipe Reduction Technologies Utilization of Newer Equipment Source Location (placement of equipment away from sensitive receptors) Dust Control Idle Restriction 5

NYU Commitments to Minimize or Avoid Significant Adverse Impacts Noise Reduction Measures Source Controls (i.e., reducing noise levels at the source) Construction procedures and equipment that produce noise levels below the requirements of the New York City Noise Control Code Early electrification for certain noisy equipment (e.g., concrete vibrators, hoists, man lifts) Construction sites would be configured to minimize truck back-up alarm noise Trucks would not be allowed to idle more than three minutes Limit equipment on-site (only necessary equipment on-site) Path Controls (e.g., placement of equipment, implementation of barriers or enclosures) Noisy equipment shielded and located away from sensitive receptor locations. Path noise control measures (i.e., portable noise barriers, panels, enclosures, and acoustical tents) for certain dominant noise equipment Acoustical curtains for internal construction activities in the buildings under construction 6

NYU Commitments to Minimize or Avoid Significant Adverse Impacts Construction Protection Plan (CPP) University Village has been determined S/NR-eligible and is designated NYC Landmark Washington Square Village has been determined S/NR-eligible CPP would be developed in consultation with LPC to avoid any construction-related impacts on these architectural resources, including ground-borne vibration and damage from heavy machinery 7

NYU Commitments to Minimize or Avoid Significant Adverse Impacts Remedial Action Plan (RAP) and Construction Health and Safety Plan (CHASP) RAP would address requirements for items such as: soil stockpiling, soil disposal and transportation dust control quality assurance contingency measures should petroleum storage tanks or contamination be unexpectedly encountered CHASP would address the following items: identify potential hazards that may be encountered during construction specify appropriate health and safety measures to be undertaken to ensure that subsurface disturbance is performed in a manner protective of workers, the community, and the environment (including a Community Air Monitoring Program) 8

NYU Commitments to Minimize or Avoid Significant Adverse Impacts Rodent Control Before start of construction, contractor would survey and bait the appropriate areas and provide for proper site sanitation During construction phase, as necessary, contractor would carry out a maintenance program Coordination would be maintained with appropriate public agencies Only EPA and NYSDEC registered rodenticides would be permitted Contractor would be required to perform rodent control programs in a manner that avoids hazards to persons, domestic animals, and non-target wildlife 9

Significant Adverse Impacts During Construction Identified for: Transportation o Traffic o Transit o Pedestrians o Parking Air Quality Noise Vibration Other Technical Areas o Historic and Cultural Resources o Hazardous Materials o Natural Resources o Open Space o Socioeconomic Conditions o Community Facilities o Land Use and Neighborhood Character 10

Significant Impact Criteria During Construction per CEQR Technical Manual Traffic For congested intersection movements, increase in delay of as little as 3 seconds Transit For congested subway station stairways, required widening of as little as 2 inches Pedestrians For congested sidewalks, increase of as little as 0.6 pedestrians per minute per foot For congested corners and crosswalks, reduction in pedestrian space of as little as 0.2 square feet per pedestrian 11

Significant Impact Criteria During Construction per CEQR Technical Manual Noise Increase of 3-5 decibels at a sensitive receptor (residential and open space locations) for more than two years Open Space Direct Effects: Substantial displacement of public and private open space resources without replacement Significant adverse air quality, noise, shadows etc., impacts on open space resources Indirect Effects: Over 1% reduction in study area open space ratios (in an underserved area), accounting for changes in population and open space 12

Construction Schedule for Buildings Figure 20-1 of the DEIS 13

Temporary Gym Construction (2013-2014 for a 9-month period) Curb Lane Closures and Staging Net Change in Publicly Accessible Open Space: -0.10 acres No Significant Adverse Impacts during this period Temporary LaGuardia Play Area 14

Zipper Building Construction (2014-2018) Curb Lane Closures and Staging 15

Zipper Building Construction (2014-2018) Open Space Analysis Net Change in Publicly Accessible Open Space: +0.29 acres Significant Adverse Impacts Noise impacts on Temporary Mercer Entry Plaza Mitigation Measures In addition to existing noise reduction commitments, between DEIS and FEIS, additional options will be explored 16

Noise Analysis Receptor Sites 73 receptor sites analyzed Directly adjacent to project area or on streets Noise Sources Operation of on-site construction equipment Movement of construction-related vehicles Noise Reduction Measures NYU commitment to proactive approach Source and path controls 17

Zipper Building Construction (2014-2018) Noise Analysis Significant Adverse Impacts At adjacent receptors indicated in Orange Mitigation Measures Washington Square Village buildings: offer storm windows and re-caulking offer new air conditioning units, or offer to insulate/seal existing air conditioning units and provide an interior cover Silver Tower buildings: offer storm windows and re-caulking offer to replace existing PTAC units with high-attenuation PTAC units Off-site buildings: offer to provide storm windows and /or window air conditioning units for buildings without double-glazed windows and/or alternative ventilation 18

Bleecker Building Construction (2018-2021) Curb Lane Closures and Staging LaGuardia Place Staging Option Bleecker Street Staging Option 19

Bleecker Building Construction (2018-2021) Open Space Analysis Net Change in Publicly Accessible Open Space: +0.73 acres Significant Adverse Impacts Temporary displacement of LaGuardia Corner Gardens (LaGuardia Place Staging Option only) Significant adverse shadows impact on LaGuardia Corner Gardens (Bleecker Street Staging Option only) Mitigation Measures Between DEIS and FEIS, options will be explored to relocate LaGuardia Corner Gardens. If relocation space cannot be identified, options will be explored to refine construction staging and logistics 20

Bleecker Building Construction (2018-2021) Noise Analysis Significant Adverse Impacts At adjacent receptors indicated in Orange Mitigation Measures Washington Square Village buildings: offer storm windows and re-caulking offer new air conditioning units, or offer to insulate/seal existing air conditioning units and provide an interior cover Silver Tower buildings: offer storm windows and re-caulking offer to replace existing PTAC units with high-attenuation PTAC units Off-site buildings: offer to provide storm windows and /or window air conditioning units for buildings without double-glazed windows and/or alternative ventilation 21

Phase 1 Construction Period (2013-2021) Transportation Analyses No significant adverse impacts identified for: Traffic Transit Pedestrians 22

Mercer Building Construction Below Grade (2022-2023) Curb Lane Closures and Staging 23

Mercer Building Construction Below Grade (2022-2023) Open Space Analysis Net Change in Publicly Accessible Open Space: +0.10 acres Significant Adverse Impacts Temporary significant adverse impact due to decreases in open space ratios in residential (1/2 mile) study area Mitigation Measures Between the DEIS and FEIS, in coordination with NYC Dept. of Parks and Recreation, investigate the feasibility of full or partial mitigation. 24

Mercer Building Construction Below Grade (2023-2026) Open Space Analysis Net Change in Publicly Accessible Open Space: +0.10 acres Significant Adverse Impacts Temporary significant adverse impact due to decreases in open space ratios in residential (1/2 mile) study area Mitigation Measures Between the DEIS and FEIS, in coordination with NYC Dept. of Parks and Recreation, investigate the feasibility of full or partial mitigation. 25

Mercer Building Construction Below Grade (2022-2026) Noise Analysis Significant Adverse Impacts At adjacent receptors indicated in Orange Mitigation Measures Washington Square Village buildings: offer storm windows and re-caulking offer new air conditioning units, or offer to insulate/seal existing air conditioning units and provide an interior cover Off-site buildings: offer to provide storm windows and /or window air conditioning units for buildings without double-glazed windows and/or alternative ventilation 26

Mercer Building Construction Above Grade (2026-2028) Curb Lane Closures and Staging 27

Mercer Building Construction Above Grade (2026-2028) Open Space Analysis Net Change in Publicly Accessible Open Space: +1.47 acres Significant Adverse Impacts Direct Effects Analysis Significant adverse noise impacts on new central open spaces Mitigation Measures In addition to existing noise reduction commitments, between DEIS and FEIS, additional options will be explored 28

Mercer Building Construction Above Grade (2026-2028) Noise Analysis Significant Adverse Impacts At adjacent receptors indicated in Orange Mitigation Measures Washington Square Village buildings: offer storm windows and re-caulking offer new air conditioning units, or offer to insulate/seal existing air conditioning units and provide cover Off-site buildings: offer to provide storm windows and /or window air conditioning units for buildings without double-glazed windows and/or alternative ventilation 29

LaGuardia Building Construction (2028-2031) Curb Lane Closures and Staging 30

LaGuardia Building Construction (2028-2031) Open Space Analysis Net Change in Publicly Accessible Open Space: +1.50 acres Significant Adverse Impacts No Significant Adverse Direct or Indirect Impacts on Open Space Resources 31

LaGuardia Building Construction (2028-2031) Noise Analysis Significant Adverse Impacts At adjacent receptors indicated in Orange Mitigation Measures Washington Square Village buildings: offer storm windows and re-caulking offer new air conditioning units, or offer to insulate/seal existing air conditioning units and provide an interior cover Off-site buildings: offer to provide storm windows and /or window air conditioning units for buildings without double-glazed windows and/or alternative ventilation 32

Phase 2 Construction Period (2022-2031) Transportation Analyses Traffic Analysis Significant Adverse Impacts Significant adverse traffic impacts identified during construction Significant adverse traffic impacts do not exceed those identified for the 2031 Build Analysis Traffic Mitigation Measures Advancement of 2031 Build Analysis mitigation (signal timing adjustments and/or lane restriping) 33

Phase 2 Construction Period (2022-2031) Transportation Analyses Transit Analysis Significant Adverse Impacts Identified at same stairway location as in 2021 and 2031 Build Analysis Broadway-Lafayette Station and West 4 th Street Station Potential Transit Mitigation Measures Advancement of 2031 Build Analysis mitigation (stairway widenings or new station entrance) On-going coordination with MTA NYCT on the feasibility of these mitigation measures Pedestrian Analysis Significant Adverse Impacts Identified at same corner location as in 2021 and 2031 Build Analysis Southeast corner of University Place and Waverly Place Pedestrian Mitigation Measures Advancement of 2031 Build Analysis mitigation (corner bulb-out or sidewalk extension) 34

LaGuardia Place Greene Street Walk Mercer Street Tricycle Garden Full Build Out (2031) Net Change in Publicly Accessible Open Space: +3.1 acres LaGuardia Entry Plaza LaGuardia Building (2028-2031) LaGuardia Play Garden West Third Street Public Lawn Philosophy Garden WSV Play Garden Mercer Building (2023-2028) Mercer Entry Plaza Bleecker Street Bleecker Building (2018-2021) Zipper Building (2014-2018) Toddler Playground Relocated Dog Run West West Houston Street Street 35

http://www.nyu.edu/nyu2031/nyuinnyc/ 36