Presented By: Jeffrey T. Folden, P.E. Chief, Innovative Contracting Division

Similar documents
Construction Management at Risk (CMAR) INFORMATIONAL MEETING July 18, 2013

Design-Build (DB) and Construction Manager / General Contractor (CMGC)

Procurement Documents for Progressive Design-Build Projects

Progressive Design Build

APPENDIX D Forms for the Analytical Delivery Decision Approach (Tier 1)

Time to Build! What to Expect On Your Upcoming Design and Construction Journey PRESENTED TO

Partnering for Alternative Delivery Projects

Project Delivery Selection Matrix If the Project Delivery Approach Fits, Use It

PROGRESSIVE DESIGN-BUILD. Praful M. Kulkarni, AIA Iraj Ghaemi, P.E. J. Brandon Dekker, M.S., DBIA

Fairfax County Government Construction Management At Risk (CMAR)

Report on Effectiveness of the Construction Manager at Risk Project Delivery Method

Design/Build Institute of America Rocky Mountain Region Water/Wastewater Committee. Project Delivery Selection Approach

CM/GC Contracting Lessons Learned from Portland and San Francisco

PWCSA CONSTRUCTION MANAGEMENT AT RISK (CMAR) PROJECT DELIVERY

APPENDIX D Forms for Analytical Delivery Decision Approach (Tier 1)

Progressive Design-Build

Alternate Project Delivery Experience at UOSA and PWCSA

Public Building Commission of Chicago Terms and Tools for Public Capital Development and Financing

Additional information summarizing the alternatives and development of this recommendation by staff is attached.

Trinity Well Field and Production Facilities Project Management Using CMAR

CMAA has met the standards and requirements of the Registered Continuing Education Program. Credit earned on completion of this program will be

TOWN OF WINTER PARK REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER / GENERAL CONTRACTOR

AN OWNER S GUIDE TO PROJECT DELIVERY METHODS: CONSTRUCTION MANAGEMENT ASSOCIATION OF AMERICA

Progressive Design-Build

Date: January 28, TriMet Contract Review Board. Daniel W. Blocher, P.E.

A Primer Indianapolis, Indiana June 16, 2010

The RTD FasTracks Plan

CONSTRUCTRION MANAGEMENT AT RISK ASHE December 13, 2011 Julio Alvarado Construction State Engineer

ECI: Two-Stage Contracts

SCADA System Procurement Alternatives

Comparison of Conventional and Alternative Project Delivery Methods: What s in an Acronym? PNWS AWWA May, 2013

Recommended AASHTO Design-Build Procurement Guide

PROJECT DELIVERY METHODS

Alternative Project Delivery Methods and Procurement

Integrated Project Delivery

FEATURES FOR SUCCESS DESIGN-BUILD- OPERATE WASTEWATER PROJECTS

Pioneering Alternative Project Delivery in Ohio

Is Your District Ready For the New Law?

Rick Carr, Arcadis U.S., Inc. Tim O Malley, The O Malley Group Bill Brannen, Mohave Educational Services Cooperative

REQUEST FOR QUALIFICATIONS CONSTRUCTION MANAGEMENT at RISK SERVICES FOR THE BECKER COUNTY JAIL DETROIT LAKES, MN

CM AT RISK VS. DESIGN BID BUILD

Project Delivery Systems

Alternative Delivery Methods in the Post-Davis World

EVOLUTION OF DESIGN BUILD IN THE W/WW INDUSTRY

1/4/2014. Alternative Project Delivery Methods 1. Agenda

Construction Family of Documents

WATERTOWN ELEMENTARY SCHOOLS SCHOOL BUILDING COMMITTEE MEETING: OCTOBER 3, 2018

VDOT DESIGN-BUILD PROGRAM

JOB ORDER CONTRACTING / JOC A LEAN Best Management Practice for Efficient Construction Project Delivery

LB 889 The Political Subdivisions Construction Alternatives Act

THE MUNICIPAL WATER AND WASTEWATER DESIGN-BUILD HANDBOOK. Third Edition Expanded to Include Design-Build-Operate

EXHIBIT 6 Preconstruction Work

Construction Manager as Constructor (CMc) Manual

Alternative Project Delivery for America s Water Infrastructure

Construction Manager /General Contractor

Design Process 101. Michael Barnard, AIA, NCARB. animalsheltering.org/expo #AnimalCareExpo. Copyright

DESIGN BUILD: CHARLOTTE-MECKLENBURG UTILITIES DEPARTMENT PROCESS FOR THE MCALPINE CREEK WWMF EFFLUENT FILTER UPGRADE AND EXPANSION

ALTERNATE FORMS OF PROJECT DELIVERY

Lease-Leaseback Project Delivery Method

PROVING OUR PROFESSIONALISM

Community Workshop October 17, 2015

Risks Associated with Alternative Delivery Methods. Managing Expectations. Presented by Dan Becker, CCM, PMP, CCE

I-90 Pavement Rehab VE Study

Alternative Delivery for Municipal Water & Wastewater Projects in 2012

Tampa Bay Water is a wholesale water

WASHINGTON METROPOLITAN AREA TRANSIT AUTHORITY. Attachment# 1

AN OVERVIEW OF DESIGN-BUILD. Presented by: David Umstot, PE, CEM Umstot Project and Facilities Solutions, LLC January 20, 2014

Progressive Design-Build Discussion

Session THREE. Face 2 Face (4 hours) Stage 1 Initial actions & appraisals: Self-directed (6 hours)

Finalize Implementation Plan Conduct Introductory Campus Meetings Kickoff Several Comprehensive Projects Secured Program Managers

School Construction: Contract Basics OSBA BONDS, BALLOTS AND BUILDINGS CONFERENCE FEBRUARY 09, 2018

Project Delivery Method

Nancy Daubenberger, MnDOT Assistant Commissioner Engineering Services

ConsensusDocs. Catalog. Updated Docs Inside

ConsensusDocs. ConsensusDocs CONTRACTS CATALOG. Updated Docs Inside. ou Ah. ead o f the Cur v. e K

Construction Documents Education Program

Pre Proposal Proposal Meeting

NO FINGER-POINTING DURING CONSTRUCTION

Legal Issues Related to Design Build

Commissioners Mital, Simpson, Helgeson, Manning, and Brown Mel Damewood, Engineering Manager; Mike McCann, Generation Manager

DEFINING THE SPECTRUM OF PROJECT DELIVERY OPTIONS AND THEIR IMPLICATIONS FOR YOUR PROJECT 2017 Airport Construction Strategy Summit

Riverbend Water Reclamation Plant Expansion Using the CMAR Delivery Method

JOB ORDER CONTRACTING (JOC)

Project Delivery Method Selection Workshop

PENINSULA CORRIDOR JOINT POWERS BOARD STAFF REPORT. Executive Officer, Caltrain Modernization Program

REQUEST FOR PROPOSALS. Construction Manager CM Services Pre-Construction and Construction Services

Construction Project Delivery Methods Overview and Comparison. Operations Division

Design-Build Data Sourcebook

Construction & Engineering 1845 East Russell Road Suite 300 Las Vegas, NV 89119

Design-Build Overview Alternate Project Delivery Office. Jeff Roby, P.E., DBIA Design-Build Program Manager Alternate Project Delivery Office

Alternative Delivery Methods for Construction Projects at WATER AND WASTEWATER SUMMIT 2012 LAS VEGAS, NV MAY 3, 2012

Yerba Buena Island (YBI) Westside Bridges Project and YBI Southgate Road Realignment Improvements

Jim Porter is the Director of Public Works for the County of San Mateo. The Department of Public Works has a staff of over 300 and performs a wide

REQUEST FOR QUALIFICATIONS FOR CONSTRUCTION MANAGER AT RISK (CMAR) SERVICES WITH GUARANTEED MAXIMUM PRICE

ALTERNATIVE CONTRACTING METHODS

EXHIBIT A. 1) General:

Subcontractor Pre-Qualification Form

Procurement Guidelines

Choosing a Project Delivery Method. A Design-Build Done Right Primer

EJCDC Contract Documents for America s Infrastructure Buy online at

Transcription:

Presented By: Jeffrey T. Folden, P.E. Chief, Innovative Contracting Division

Project Delivery Methods Design-Bid-Build (DBB) Indefinite Delivery/Indefinite Quantity (ID/IQ) Construction Management at Risk (CMAR) (Construction Manager/General Contractor (CM/GC)) Design-Build (DB) Traditional (Bridging) Design-Build Progressive Design-Build Public Private Partnerships (P3)

Design-Bid- Build CMAR / CM/GC Design-Build Traditional & Progressive

Design-Bid-Build Preliminary Design Detailed/Final Design Bid Construction CMAR / CM/GC Preliminary Design Detailed/Final Design CMAR Procurement Construction Traditional Design-Build Preliminary Design Design-Build Procurement Detailed/Final Design Construction

Shorten Project Delivery Maximize Dollars/Better Cost Certainty Provides Opportunities for Innovation Better Risk Allocation Informed Owner Decision Making Early Contractor Involvement Highly Qualified Teams Group Cohesion and Team Integration

Owner s desire to be involved throughout design process Direct contractual relationship with designer Interest in making all design decisions Owner s ability to quickly respond to design submittals Owner s need to have design fully completed before construction Cost and time of a competitive, price-based, procurement Owner s inherent ability to trust the contractor

Construction Management at Risk (CMAR) A project delivery method where the owner utilizes a two-phase construction contract with a General Contractor: Phase 1 - Provide Preconstruction Services, which may include, but are not limited to, constructability analysis, value analysis, scheduling, site assessments, and cost estimating. Phase 2 - Construct the project based on final design plans (or design packages) at an agreed GMP.

Began developing CMAR process in 2013 Three projects have been selected for delivery using CMAR MD 24 Slope Stabilization Construction Complete MD 97 Brookeville Bypass Preconstruction Phase Construction planned to begin in Fall 2016 I-95 Greenbelt Metro Access Preconstruction Phase Construction planned to begin in Spring 2017

One Step Process Technical Ratings - Adjectival Method of Selection Best Value Technical Proposal Qualifications/Past Performance & Project Approach Price Proposal Preconstruction Fee/Other Elements Technical Proposal is significantly more important than Price MD 24 CMAR Project

CMAR Design Team Owner Engineer Contractor Independent Cost Estimator (ICE) Other Stakeholders Cost Validation Owner Contractor ICE MD 24 CMAR Project

Cost Model Elements Profit & Overhead Equipment Types & Rates Labor Materials Subcontractor Items of Work Risk Agreement & Assignment Schedule Agreement on which bucket costs go to MD 24 CMAR Project Opinion of Probable Construction Costs Submitted at Milestones (30/65/90%) Independent Quantity Takeoffs/Pricing Blind Estimate Comparison Discuss items out of tolerance Reconcile differences in assumptions

Design is Complete Contract Documents collaboratively developed Typical Standards/Specifications Minimum 50% Self-Performance DBE Requirements Guaranteed Maximum Price (GMP) Submission Contractor & ICE Independently Price Price Reconciliation Meetings as needed Up to 3 GMP Submissions MD 24 CMAR Project Accept GMP and award construction Terminate contract and bid as DBB ( Off Ramp ) Project Construction Typical SHA-Contractor Roles Payment of GMP through approved Work Breakdown Structure

Design-Bid-Build Preliminary Design Detailed/Final Design Bid Construction CMAR / CM/GC Preliminary Design Detailed/Final Design CMAR Procurement Construction Traditional Design-Build Preliminary Design Design-Build Procurement Detailed/Final Design Construction Progressive Design-Build Preliminary Design Detailed/Final Design Design-Build Procurement Construction

Progressive Design-Build (PDB) A project delivery method where the owner utilizes a two-phase Design-Build contract with a Design- Builder (Contract-Engineer Team): Phase 1 - Provide Design and Preconstruction Services to develop design packages to level necessary to establish a Guaranteed Maximum Price (GMP). Phase 2 - Construct the project based on design packages at an agreed GMP.

Overall objectives Introduce design-builder to project early in design process Work in collaboration with owner to advance design Overall project price negotiated after design is developed Single or two phase procurement process Pure qualifications-based Best value procurement with minimal price-based factors

Overall project price not meaningfully considered during procurement Open book estimating GMP/lump sum developed post-award Can establish this at 100% of design completion Normally see price commitment at 50-70% of design completion Should be no Spearin liability, as there is no design handoff

Ability to introduce design-builder to the project as early as possible Design-builder becomes a strategic partner in planning and project definition Avoids Spearin liability Facilitates having design-builder involved in permit and other development activity It may substantially reduce cost and time for procurement

Owner interest in being involved in design and procurement Development of design solutions in conjunction with design-builder Direct discussions with design-builder on O&M/life cycle costing Procurement of subcontractors and suppliers Owner access to real-time information Enhanced cost and schedule information during design development Facilitates designing to budget Open book pricing allows transparency into designbuilder s costs Process fosters collaborative relationships

Statutory restrictions Mandates that overall price be provided at time of contract Constraints on hiring and integrating subcontractors Owner interest in: Obtaining a competitive fixed price for entire project during procurement Developing detailed technical requirements prior to starting procurement Seeking different technical solutions through a competitive procurement process Owner concerns about exercising the contractual off-ramp

Benefits of CMAR Ability of Owner to have a direct contract with a designer who is independent of contractor Easier ability to exercise off-ramp Benefits of progressive DB Owner does not have to procure/manage designer May be slight schedule benefit Ability to obtain performance guarantee and other benefits of design-build Elimination of Spearin liability Enhanced relationship between contractor and designer

IS 270 Progressive Design-Build Contract

I-270 Corridor Facts Average daily traffic approaching 240 K in many segments One of the most congested corridors in MD and the Washington, DC region with strong directional peaks Strong economic development and housing activity projected along the corridor Over-saturated conditions, extended peak periods greatly impacts reliability

No identified solutions or constraints on proposed solutions to any concept Engage expertise of design and construction industries to provide innovative solutions to address goal of moving the most traffic the fastest Relevant expertise elsewhere in the world Fixed Value Contract Best Value Selection

Environmental evaluation cannot begin until after selection nor can schedule be developed until scope of improvements is known Unpredictable timeframe to begin and end construction Adequate data collection needed for price proposal preparation will be costly and time consuming. Lack of data leads to increased risk and reduced cost efficiency for improvements Time consuming process to define various project requirements Right-of-Way impacts (if any) would be unknown at time of procurement potentially leading to extended construction completion

Advantages of Progressive Design-Build Better Management of Risks than Traditional Design-Build Environmental Analysis (Noise, Air, Historical, etc.) Permitting Geotechnical and Utility Risks Right-of-Way Construction Schedule Risk Assignment/Risk Sharing Pool

Two Step Process RFQ RFP Proposed Technical Concepts (PTCs) during RFP Phase Technical Ratings - Adjectival Method of Selection Best Value Technical Proposal Design-Builder s solutions to address Contract Goals Price Proposal Fixed Value Technical Proposal is significantly more important than Price

Use similar approach to address other major congested corridors in Maryland Evaluate for consideration on other projects (DBB, DB, CM/GC) Ultimately, an additional Tool in the Tool Box for project delivery

Jeffrey T. Folden, P.E. QUESTIONS? Chief, Innovative Contracting Division Maryland Department of Transportation State Highway Administration jfolden1@sha.state.md.us 410-545-8814