1 The Challenges & Experiences of an Enterprise Level PLM Migration Glenn Gise Sr. Technology Manager Black & Decker May 18, 2009 May 2009, Glen Gise, 1

2 Black & Decker is the Worlds Largest Power Tool Producer Products marketed in over 100 countries Manufacturing operations in 11 countries World headquarters located in Baltimore, Maryland $6.1 Billion in 2008 Sales Divided into 3 major business segments May 2009, Glen Gise, 2

3 Black & Decker Business Profile Fastening & Assembly Systems 12% $700 M Hardware & Home Improvement 15% $897 Million 73% $4.37 Billion Power Tools & Accessories May 2009, Glen Gise, 3

4 May 2009, Glen Gise, 4

5 May 2009, Glen Gise, 5

6 Overview Black & Decker PDM history How it evolved to meet business need Choosing the replacement PLM The configuration, data migration & training to deploy the new system On-going issues and future plans May 2009, Glen Gise, 6

7 Early adopter of PDM in 94 Implemented (ProductManager ) for the traditional reasons Reduce Product Development Cycle Time; improve Design Quality; lowering costs Stayed current with all software releases Leveraged most of the functionality within ProductManager Added some smart document replication features. Evolved thru CATIA V4 and V5 May 2009, Glen Gise, 7

8 Fayetteville 1995 First PDM Deployment Easton Hampstead NAPT NAPT STDS Tarboro May 2009, Glen Gise, 8

9 Fayetteville Easton Hampstead (Prod. Serv) 2002 Perspective Shelbyville STPT Reynosa Perugia NAPT NAPT NAA CNDA STDS Uberaba Suzhou Usti SPMD EUPT GRMY Spennymoor Marshall Acquisitions Tampa Ft. Mill Nashville BDCI May 2009, Glen Gise, 9

10 Updating our system because.. Concurrent engineering was occurring China was evolving into a design role 3D model collaboration as mentoring tool eased language differences End to End PLM was more vital Capture early development phase womb to tomb Broadening the scope of project participation Moving from the PDM Engineering centric mindset to an Enterprise PLM system May 2009, Glen Gise, 10

11 Planning for One system single source of product & process knowledge Web based, secure Internet architecture on high-performing technology Improved & integrated collaboration tools Integrating key suppliers was important Capturing more non-cad product data May 2009, Glen Gise, 11

12 Moving steadily ahead with Homogeneous CAD environment Developing & documenting Best Practices Focusing on 3D model quality Evaluating replacements for our now 9 year old system PDM system But.. May 2009, Glen Gise, 12

13 May 2009, Glen Gise, 13

14 Black & Decker Announces Pentair Acquisition Summer 04 Porter Cable, Delta Tools, & DeVilbiss Air Tools Different CAD System, Three additional PDM systems, Totally different Change Management processes Majority of manufacturing co-located with design engineering very different And ASAP.. integrate this huge acquisition into Black & Decker May 2009, Glen Gise, 14

15 PLM Selection Process Reorganization provided different views May 2009, Glen Gise, 15

16 I know best ask me! May 2009, Glen Gise, 16 Smart Numbers Too many System Slow Approvals

17 PLM Selection Process Reorganization provided different views Senior management insisted on end user participation May 2009, Glen Gise, 17

18 Pepsi Challenge or PLM Shootout? Team P Team C B&D May 2009, Glen Gise, 18

19 PLM Selection Process Reorganization provided different views Senior management insisted on end user participation Side by side challenges over a 5 day evaluation period Participants chosen from various sites 2 vendors earlier selected from larger list Each participant completed the same project and evaluation form - group discussions votes tallied Result Drinking from the fire hose? How much functionality do they evaluate? May 2009, Glen Gise, 19

20 Change vs. Transition PLM Implementation Success Re-engineered processes Re-engineered processes May 2009, Glen Gise, 20

21 Change vs. Transition Change: To make radically different; to give a different position, course or direction, to undergo a modification Transition: a movement, development, or evolution from one form, stage or style to another May 2009, Glen Gise, 21

22 Configuring the System This is the best opportunity to re-engineer some processes Don t just automate the existing process - CHANGE Once in place they will be very difficult to change. Strive for standardized processes with divisional variants Referencing your documented best practices and processes is the key Current process + software capability = optimal configuration workflows are best example Time well spent in having CAD modeling and PLM practices Don t deploy until all current business needs are met Dedicated environments to manage development, testing and training. Migration had to be added. May 2009, Glen Gise, 22

23 Migration Roadmap Big Bang approach was out of the question Which meant we migrated by product portfolios Which dictated what design centers were affected Which then determined affected manufacturing sites Which identified affected supply chain people But we had thousands of shared parts Parts used in products all over the world So parts residing in multiple systems needed clear identification May 2009, Glen Gise, 23

24 Identifying and updating shared data was crucial Legacy B&D Euro Professional Legacy B&D NA Professional New Windchill IPG Porter Cable/Delta Woodworking Business DeVilbiss Equipment Business Black & Decker Worldwide Consumer Tools May 2009, Glen Gise, 24

25 Migration Roadmap Big Bang approach was out of the question Which meant we migrated by product portfolios Which dictated what design centers were impacted Which then determined affected manufacturing sites Which identified additional supply chain people But we had thousands of shared parts Parts used in many products all over the world So parts residing in more than one system needed clear identification Shared data between systems was unavoidable Our users happily volunteered to duplicate CN/EC s in all the shared systems!! May 2009, Glen Gise, 25

26 Synchronizing Shared Data End User works in the system they are trained to use Administrative team updates data in any shared system May 2009, Glen Gise, 26

27 Data Migration Analyze & Fix Integrity checks & error reports, iterative migration passes Design teams resolve CAD problems beyond what admin team could fix In process changes were addressed - pay me now/pay me later Freeze & Move Target data frozen, Black or White - development or released lifecycle state only Data mapping finalized use KISS principle Marking Parts Noted as either shared or locked perhaps you can avoid Eventual lock read only of all legacy systems Audit & Correcting Migrated data validated using various tools (and interns) Most corrections minor, easily fixed and performed by admin personal May 2009, Glen Gise, 27

28 Migration Lessons Access to licenses from different CAD/PDM suppliers was not always forthcoming Licenses were eventually purchased and used for subsequent migrations and upgrades. Third party software will be needed for CAD files not authored by the PLM vendor Pay close attention to data replication schemes Smart replication can be challenge. Mini migration planning what falls through the cracks May 2009, Glen Gise, 28

29 Training We looked at web based training We looked at out-sourcing the training We looked at providing all the training from within the team We looked at a combination of all the above May 2009, Glen Gise, 29

30 Training Training was most often the critical path Number of students was balanced with the migration data sets 2 weeks at each site was allotted ½ day Post training on site support is vital Attempting to train in regions to limit travel Train the trainer concept quickly adopted. Super Users from sites soon to be trained were recruited into earlier classes These users remained engaged with tasks Enabled real assistance for future training. May 2009, Glen Gise, 30

31 Training OOTB material vs. tailored training material OOTB was too button pushing and didn t address our specific process needs very CAD specific Internal training material was created and managed in a training library Language concerns Having the software in the local language could have helped adoption Translation problems were eased with Super User assistance and on-site translators At this stage we have 10 different training classes tailored to the needs of approximately 900 users May 2009, Glen Gise, 31

32 Collaboration False start with ProjectLink the Windchill supplier collaboration portal Internal team stretched too thin adhoc systems persist outside PLM WebEx, erooms Starting collaboration with key suppliers within PLM using sealed projects Managing security & roles to control supplier access Out-sourcing key design elements is increasing Awaiting planned software upgrade & team availability Small steps to transform into a collaborate culture Better use of markup and annotation Advanced training with internal viewing tools May 2009, Glen Gise, 32

33 Heterogeneous. Step CATIA ProE May 2009, Glen Gise, 33

34 Heterogeneous? Struggling with managing and using different CAD models in an assembly Good news we don t have that many today Bad news more and more are occurring Simple approach is taken not 1 st prize Step file created from native it s master is noted Sometimes file is converted to other CAD Could have 2 different CAD models and a Step file. CAD plug-ins Many models are CAD versions not supported by the plug-ins Both primary CAD environments are working toward and testing true heterogeneous usage May 2009, Glen Gise, 34

35 Plodding Ahead It s taken 3 years to migrate all Documents and BoM s from legacy systems into new PLM environment 500 heavy users total, 425 CATIA users; 59 ProE users Maintain a global team encompassing all systems. Disbanding into separate system teams will hinder the integration Well organized & trained CA (Change Administrator) team Pool of global workers vs. regionally dedicated (working from home) Audits performed to assure data integrity and identify training needs Super User bi weekly meetings sharing ideas, suggestions and how to tips Dozens of small projects as users see ways to exploit the system May 2009, Glen Gise, 35

36 Where to be cautious System performance issues throughout the deployment New network routes and data priority Stay current with the software upgrades Vendor support and happier end users Aligning CAD versions to enable PLM version upgrades Future SAP integration? Are your ERP systems standardized enough to allow an integration? May 2009, Glen Gise, 36

37 Hindsight & Opportunities Have your current design and change processes well documented Clearly defined processes will help promote meaningful CHANGE Provide all PLM core team with business admin capability/training Enable more efficient interaction within team Promoted more robust configurations in all areas of the software Geometry driven BoM active link to part make it mandatory assures accuracy May 2009, Glen Gise, 37

38 The Five C s Commitment Champion Challenge Cultural Change Communicate May 2009, Glen Gise, 38

CONNECT ALL OF YOUR DATA

CONNECT ALL OF YOUR DATA CONNECT ALL OF YOUR DATA Cross-Domain Vendor Neutral Integration 7.14.2016, Schouten Webinar Overview Integrating your TDM systems (CAD) with your parts (PLM) and your materials (ERP) between different

More information

COTS VS. CUSTOM THE CONTINUOUS STRUGGLE. Laxmi Sivashankar Senior Manager, Global Process, Methods, Tools and Information & Systems Engineering

COTS VS. CUSTOM THE CONTINUOUS STRUGGLE. Laxmi Sivashankar Senior Manager, Global Process, Methods, Tools and Information & Systems Engineering COTS VS. CUSTOM THE CONTINUOUS STRUGGLE Laxmi Sivashankar Senior Manager, Global Process, Methods, Tools and Information & Systems Engineering As a big OEM, there are constant pressures to buy software

More information

Comparison Table for PTC PDM/PLM Solutions

Comparison Table for PTC PDM/PLM Solutions Comparison Table for PDM/PLM Solutions Functionalities Creo E/D V. 19.0 PDM Essentials MCAD data management V V V ECAD data management Optional Document management V V V Search management Not Full Text

More information

Windchill ProductPoint 2.0 External FAQs May What is Windchill ProductPoint?

Windchill ProductPoint 2.0 External FAQs May What is Windchill ProductPoint? Windchill ProductPoint 2.0 Eternal FAQs May 2010 What is Windchill ProductPoint? Windchill ProductPoint is a PDM solution for small and medium sized businesses to enable teams to manage and share comple

More information

big data & business analytics Unleash the power of real-time insights With HCL s Next Gen BI solution

big data & business analytics Unleash the power of real-time insights With HCL s Next Gen BI solution big data & business analytics Unleash the power of real-time insights With HCL s Next Gen BI solution Bi not running at the speed of business? Are your senior managers frustrated with the amount of time

More information

The Aras PLM Platform

The Aras PLM Platform 2 THE ARAS PLM PLATFORM Table of Contents ENABLING THE BUSINESS OF ENGINEERING... 3 THE PRODUCT INNOVATION PLATFORM... 4 THE ARAS PLM PLATFORM... 5 DOING BUSINESS WITH ARAS... 6 TECHNOLOGY... 7 Architecture...7

More information

Teamcenter Express. The fast track to cpdm

Teamcenter Express. The fast track to cpdm Teamcenter Express The fast track to cpdm UGS www.ugs.com/teamcenterexpress Small- and mid-size manufacturing organizations face increasing demands to deliver new products to market faster and with best-in-class

More information

Windchill : Managing the complete product lifecycle from concept to service

Windchill : Managing the complete product lifecycle from concept to service Windchill : Managing the complete product lifecycle from concept to service Streamline product development and service information processes Engage your enterprise throughout the product s lifecycle with

More information

ACI 3DEXPERIENCE ARAS INNOVATOR INTEGRATION

ACI 3DEXPERIENCE ARAS INNOVATOR INTEGRATION 1 ACI 3DEXPERIENCE ARAS INNOVATOR INTEGRATION ACI 3DEXPERIENCE ARAS INNOVATOR INTEGRATION CHARACTERISTICS ACI as PDM system integration runs asynchronously in the background. To allow a flexible usage

More information

PROSTEP INTRO TO CANADIAN MARINE INDUSTRY

PROSTEP INTRO TO CANADIAN MARINE INDUSTRY PROSTEP INTRO TO CANADIAN MARINE INDUSTRY Matthias Grau, Account Manager Shipbuilding Industry Sep 2017, MGR We are an independent company specializing in PLM consultancy services and engineering solutions.

More information

Time-to-market for new products. Warranty expenses. Product development costs

Time-to-market for new products. Warranty expenses. Product development costs Case Studies, M. Light Research Note 5 March 2003 HP Program to Reinvent Product Development Management Hewlett-Packard's Imaging and Printing Group has standardized its tools, processes, procedures and

More information

5 Pitfalls and 5 Payoffs of Conducting Your Business Processes in the Cloud

5 Pitfalls and 5 Payoffs of Conducting Your Business Processes in the Cloud 5 Pitfalls and 5 Payoffs of Conducting Your Business Processes in the Cloud Keith Swenson VP R&D, Chief Architect Fujitsu America, Inc. April 2014 Fujitsu at a Glance Headquarters: Tokyo, Japan Established:

More information

How PLM is Being Applied to Support Today s Dynamic Enterprises

How PLM is Being Applied to Support Today s Dynamic Enterprises How PLM is Being Applied to Support Today s Dynamic Enterprises Characteristics and Issues of Today s Global Enterprises Over the last several years, Product Lifecycle Management (PLM) has emerged as the

More information

PDM Workbench NX for. Aras Innovator

PDM Workbench NX for. Aras Innovator PDM Workbench NX for Aras Innovator T-Systems PLM Solutions Our Partners Aras Corp. Siemens PLM Software Aras Business Partner Aras Solution Partner Reseller Agreement Development Partnership Reseller

More information

A Product Innovation Platform and Its Impact on Successful PLM Deployments

A Product Innovation Platform and Its Impact on Successful PLM Deployments A Product Innovation Platform and Its Impact on Successful PLM Deployments CIMdata Commentary Key takeaways: Product innovation platforms are the foundation upon which functional capabilities, data, and

More information

Connecting Manufacturing Engineering and the Shop Floor

Connecting Manufacturing Engineering and the Shop Floor Connecting Manufacturing Engineering and the Shop Floor A manufacturer's signature of efficiency By: Peter Thorne, Cambashi Presented By: Hyla Soft Introduction This paper is written for engineers and

More information

GETRAG FORD TRANSMISSIONS

GETRAG FORD TRANSMISSIONS GETRAG FORD TRANSMISSIONS Aras Accelerates Innovation at GETRAG FORD Transmissions The Aras platform is used not just to automate, but to develop new business processes at GETRAG FORD Transmissions. The

More information

TCI 3DEXPERIENCE TEAMCENTER INTEGRATION

TCI 3DEXPERIENCE TEAMCENTER INTEGRATION TCI 3DEXPERIENCE TEAMCENTER INTEGRATION PRESENTATION T-SYSTEMS PARTNERSHIPS Sales-/Service- Partnership Strategic SI partner ISV Partnership (CAD integration CATIA, NX; Enterprise integration with PDM,

More information

Upgrade Strategies for Small and Midsize Businesses

Upgrade Strategies for Small and Midsize Businesses Upgrade Strategies for Small and Midsize Businesses Pat Hickey, Director, mysap All-in-One Solutions Michael Labriola, VP of IT, TriVirix International November 2003 Agenda 1. Reasons for an Upgrade 2.

More information

FaithPLM Solutions. About Client

FaithPLM Solutions. About Client About Client Our client is a full line supplier of small hydro power plants. One of the Leading manufacturer of hydraulic turbines and turnkey supplier of mechanical packages for hydro power projects.

More information

7 things to ask when upgrading your ERP solution

7 things to ask when upgrading your ERP solution Industrial Manufacturing 7 things to ask when upgrading your ERP solution The capabilities gap between older versions of ERP designs and current designs can create a problem that many organizations are

More information

COM M. Halpern

COM M. Halpern M. Halpern Research Note 31 October 2003 Commentary Using a PLM Framework to Structure Software Diversity Implementing a five-layer framework can enable you to deploy and manage the broad array of diverse

More information

Aras Accelerates Innovation at GETRAG FORD Transmissions

Aras Accelerates Innovation at GETRAG FORD Transmissions Aras Accelerates Innovation at GETRAG FORD Transmissions Aras is used as our PLM platform to not just automate, but to develop new business processes at GETRAG FORD Transmissions. The upshot is that because

More information

Teamcenter Rapid Start

Teamcenter Rapid Start Teamcenter Rapid Start Specifications for a preconfigured PDM deployment Benefits Simplifies common tasks Controls and shares mechanical (MCAD) and electronic (ECAD) data Collaborate on MCAD designs using

More information

WCI 3DEXPERIENCE Windchill. Integration

WCI 3DEXPERIENCE Windchill. Integration WCI 3DEXPERIENCE Windchill Integration WCI 3DEXPERIENCE Windchill Integration Characteristics WCI runs asynchronously in the background and offers a process controlled data exchange. To allow a flexible

More information

Ways to Not Derail An ERP Implementation

Ways to Not Derail An ERP Implementation 9 Ways to Not Derail An ERP Implementation An introductory guide to keep your ERP Implementation on track. www.westerncomputer.com ERP Implementations are a huge undertaking and without the right knowledge

More information

Topic : Product Lifecycle Management- Implementing Successful Transformational Changes

Topic : Product Lifecycle Management- Implementing Successful Transformational Changes New Product Commercialization Improvement Topic : Product Lifecycle Management- Implementing Successful Transformational Changes Director of R&D and Remote Service Application Development & Support I am

More information

Reprint from No. 5 September Clean data provides the drive

Reprint from No. 5 September Clean data provides the drive Reprint from No. 5 September 2015 www.plm-it-business.de Clean data provides the drive Practical application Clean data provides the drive Drive technology specialist, GKN Driveline, integrates the software

More information

Meeting FDA Standards For Medical Device Quality: An Outof-the-box

Meeting FDA Standards For Medical Device Quality: An Outof-the-box Meeting FDA Standards For Medical Device Quality: An Outof-the-box PLM Approach PTC s Medical Device Value-Ready Deployment TM Offering: Overview May 2016 Companies perceive that the regulatory framework

More information

TRANSISTION FACTORY. Julien Lapointe DASSAULT SYSTÈMES INDUSTRY SERVICES

TRANSISTION FACTORY. Julien Lapointe DASSAULT SYSTÈMES INDUSTRY SERVICES DASSAULT SYSTÈMES INDUSTRY SERVICES TRANSISTION FACTORY Julien Lapointe DASSAULT SYSTÈMES INDUSTRY SERVICES GPDIS_2012.ppt 1 Customizations A cost effective Successful Customer Transition to ENOVIA V6

More information

En Pointe Technologies

En Pointe Technologies En Pointe Technologies Entrenched with Experience, Armed with Technology Flexibility in doing business your way En Pointe has served as a national I.T. service provider since 1993. We specialize in fulfillment

More information

Overview and Frequently Asked Questions

Overview and Frequently Asked Questions Overview and Frequently Asked Questions Overview Oracle Buys Demantra: Setting the New Standard in Today s Demand-Driven Planning Solutions On June 1, 2006, Oracle announced our agreement to buy Demantra,

More information

DIY ENOVIA PLM MIGRATION. Brian Schouten PROSTEP

DIY ENOVIA PLM MIGRATION. Brian Schouten PROSTEP DIY ENOVIA PLM MIGRATION Brian Schouten PROSTEP DIY ENOVIA 3D EXPERIENCE PLM MIGRATION Requirements & Planning Strategy Risks Technical Considerations Final Thoughts Company Overview A vendor neutral /

More information

REFERENCE Simulation and PLM Interoperability using SimMgr and PROSTEP OpenPDM Cross Domain Integration and Exchange in Real Time

REFERENCE Simulation and PLM Interoperability using SimMgr and PROSTEP OpenPDM Cross Domain Integration and Exchange in Real Time REFERENCE Simulation and PLM Interoperability using SimMgr and PROSTEP OpenPDM Cross Domain Integration and Exchange in Real Time Paul W. Downing / VP / PROSTEP Inc. paul.downing@prostep.com / www.prostep.com

More information

Oracle Fusion Human Capital Management

Oracle Fusion Human Capital Management Oracle Fusion Human Capital Management STRATEGIC GLOBAL HUMAN CAPITAL MANAGEMENT KEY FEATURES Support for multiple work relationships that employees or contingent workers may have with multiple legal employers,

More information

Content and Process Management Software

Content and Process Management Software SERVICES & SUPPORT PROCESSES & INITIATIVES SOFTWARE PRODUCTS INDUSTRY SOLUTIONS Content and Process Software To Optimize Product Windchill Better products. More products. Faster. At lower cost. As a manufacturer,

More information

PDM Workbench for. Aras Innovator

PDM Workbench for. Aras Innovator PDM Workbench for Aras Innovator T-Systems PLM Solutions Our Partners Aras Corp. Dassault Systèmes Aras Business Partner Aras Solution Partner Reseller Agreement CAA V5 Gold Partner DS V6 apps Community

More information

PLM Solutions V5.16 Empower your innovation network

PLM Solutions V5.16 Empower your innovation network Software Announcement November 8, 2005 PLM Solutions V5.16 Empower your innovation network Overview Collaborate across the value chain: Using IBM/Dassault Systemes (IBM/DS) Product Lifecycle Management

More information

Enterprise Product-Level Information. on Aras Innovator. Chris Kapell Carestream Health Project Manager

Enterprise Product-Level Information. on Aras Innovator. Chris Kapell Carestream Health Project Manager Enterprise Product-Level Information Development and Deployment on Aras Innovator Chris Kapell Carestream Health Project Manager Abstract This presentation outlines the approach, process, and methods that

More information

Beyond ERP: Advanced Applications Can Deliver Rapid Payback and Competitive Edge

Beyond ERP: Advanced Applications Can Deliver Rapid Payback and Competitive Edge Beyond ERP: Advanced Applications Can Deliver Rapid Payback and Competitive Edge October 2004 Industry Directions Inc. www.industrydirections.com Many manufacturers and distributors need to find new ways

More information

In Support of (Business) Intelligence. A Technical Solution Paper from Saama Technologies, Inc.

In Support of (Business) Intelligence. A Technical Solution Paper from Saama Technologies, Inc. In Support of (Business) Intelligence A Technical Solution Paper from Saama Technologies, Inc. June 10, 2013 Business Intelligence A Growing Need Business Intelligence is one of the fastest growing segments

More information

An Overview of the AWS Cloud Adoption Framework

An Overview of the AWS Cloud Adoption Framework An Overview of the AWS Cloud Adoption Framework Version 2 February 2017 2017, Amazon Web Services, Inc. or its affiliates. All rights reserved. Notices This document is provided for informational purposes

More information

From configuration management database (CMDB) to configuration management system (CMS)

From configuration management database (CMDB) to configuration management system (CMS) From configuration management database (CMDB) to configuration management system (CMS) Utilizing an integrated CMDB to enable service asset and configuration management Table of contents Introduction....3

More information

ACI 3DEXPERIENCE Aras. Innovator Integration

ACI 3DEXPERIENCE Aras. Innovator Integration ACI 3DEXPERIENCE Aras Innovator Integration 1 ACI 3DEXPERIENCE Aras Innovator Integration Characteristics ACI as PDM system integration runs asynchronously in the background. To allow a flexible usage

More information

aligned Product Lifecycle Management The Core Strategy for Product Innovation Welcome to the new R&D network.

aligned Product Lifecycle Management The Core Strategy for Product Innovation Welcome to the new R&D network. aligned Welcome to the new R&D network. Today, global R&D networks have to thrive on a complex innovation ecosystem that includes captives, vendors and partners spread across geographies. Does this affect

More information

CAD INTRODUCTION TO MODEL BASED DEFINITION (MBD) WITH CREO PARAMETRIC 4.0 UPDATE TO CREO PARAMETRIC 4.0 FROM CREO PARAMETRIC 3.

CAD INTRODUCTION TO MODEL BASED DEFINITION (MBD) WITH CREO PARAMETRIC 4.0 UPDATE TO CREO PARAMETRIC 4.0 FROM CREO PARAMETRIC 3. CAD MASTERCLASS INTRODUCTION TO MODEL BASED DEFINITION (MBD) WITH CREO PARAMETRIC 4.0 & Thursday May 25th LEVEL: Advanced/Expert TOPICS: Product Design (Modeling, MBD, Collaboration, Tips & Tricks) PRODUCT

More information

GUIDEBOOK ADAPTIVE INSIGHTS

GUIDEBOOK ADAPTIVE INSIGHTS GUIDEBOOK ADAPTIVE INSIGHTS December 2013 July 2013 Document NX THE BOTTOM LINE Although corporate performance management (CPM) solutions have been in the market for some time, a new set of vendors such

More information

The Path to S/4HANA: Transition Scenarios and Best Practices

The Path to S/4HANA: Transition Scenarios and Best Practices The Path to S/4HANA: Transition Scenarios and Best Practices Overview Transition Scenarios Transition to SAP S/4HANA Three different approaches to move to SAP S/4HANA System Conversion SAP ERP System SAP

More information

PLM Market Requires Best-of-Breed and ERP Capabilities

PLM Market Requires Best-of-Breed and ERP Capabilities Markets, M. Halpern, K. Brant Research Note 20 March 2003 PLM Market Requires Best-of-Breed and ERP Capabilities Best-of-breed and enterprise resource planning vendors share space on the Product Life Cycle

More information

Secure information access is critical & more complex than ever

Secure information access is critical & more complex than ever WHITE PAPER Purpose-built Cloud Platform for Enabling Identity-centric and Internet of Things Solutions Connecting people, systems and things across the extended digital business ecosystem. Secure information

More information

Costing Across Global Value Chains: SAP Product Lifecycle Costing

Costing Across Global Value Chains: SAP Product Lifecycle Costing Costing Across Global Value Chains: SAP Product Lifecycle Costing CIMdata Commentary Key takeaways: Global value chains are a fact of life in most industries today, and developing accurate cost estimates

More information

Content and Process Management Software

Content and Process Management Software SERVICES & SUPPORT PROCESSES & INITIATIVES SOFTWARE PRODUCTS INDUSTRY SOLUTIONS Content and Process Software To Optimize Product Windchill Better products. More products. Faster. At lower cost. As a manufacturer,

More information

Codex of PLM Openness

Codex of PLM Openness Codex of PLM Openness Windchill Self-Assessment PTC is committed to PLM openness. In addition to acknowledging the value of openness to our customers, we view it as a competitive advantage. We recognize

More information

Product Innovation Platform Assessment

Product Innovation Platform Assessment CIMdata ebook Platform Assessment Aras PLM Platform Global Leaders in PLM Consulting www.cimdata.com What You Need To Know Enterprise Infrastructure Utilization Availability End-to-End Lifecycle Support

More information

FUJITSU Application Modernization Database

FUJITSU Application Modernization Database FUJITSU Application Modernization Database Contents Challenges and Benefits 4 Fujitsu Global Application Modernization - Data Migration 6 Database Migration 8 Data Management 10 Donors and Targets 11 2

More information

Machinery Edition. Electrical and fluid design software for the machinery market. Machinery

Machinery Edition. Electrical and fluid design software for the machinery market. Machinery Machinery Edition Electrical and fluid design software for the machinery market Machinery Introduction Introduction In contrast to the general trend towards large corporate players, companies in the global

More information

Rapid Delivery Predictable Outcomes Your SAP Data Partner

Rapid Delivery Predictable Outcomes Your SAP Data Partner Rapid Delivery Predictable Outcomes Your SAP Data Partner We are We are a global, UK-based solution provider with offices covering mainland Europe, North and Latin America and India. Since 2004, we have

More information

Configuration Overview

Configuration Overview Configuration Overview Introduction This document outlines: Workbench s capabilities for data management How different types of users should connect to Workbench How to use Workbench in conjunction with

More information

Pro/INTRALINK Data Migrator Migrating from 3.x to 8.0. Steve Shaw Product Manager

Pro/INTRALINK Data Migrator Migrating from 3.x to 8.0. Steve Shaw Product Manager Pro/INTRALINK Data Migrator Migrating from 3.x to 8.0 Steve Shaw Product Manager 2 Agenda Evolution of Pro/INTRALINK 8.0 Introducing the Pro/INTRALINK Data Migrator Supported data Early success Performance

More information

ORACLE SYSTEMS MIGRATION SERVICES FOR IBM ENVIRONMENTS

ORACLE SYSTEMS MIGRATION SERVICES FOR IBM ENVIRONMENTS ORACLE SYSTEMS MIGRATION SERVICES FOR IBM ENVIRONMENTS SAFELY MIGRATE TO A NEW IT INFRASTRUCTURE WITH THE RIGHT TOOLS AND EXPERTISE KEY FEATURES Effectively address issues such as endof-life, unpredictable

More information

We re not just good on paper.

We re not just good on paper. IT Services We re not just good on paper. You might know us as a print company. That s only part of the story. We re big on IT too, with products and services that can help your business thrive. ricoh.co.uk

More information

Mathcad : Optimize your design and engineering process.

Mathcad : Optimize your design and engineering process. Mathcad : Optimize your design and engineering process. Where engineering excellence begins. ENGINEERING CALCULATION SOFTWARE Solve, document, share and reuse vital engineering calculations. Engineering

More information

Mathcad : Optimize your design and engineering process.

Mathcad : Optimize your design and engineering process. Mathcad : Optimize your design and engineering process. Where engineering excellence begins. ENGINEERING CALCULATION SOFTWARE Solve, document, share and reuse vital engineering calculations. Engineering

More information

Enterprise PLM Solutions Advanced PLM Platform

Enterprise PLM Solutions Advanced PLM Platform Enterprise PLM Solutions Advanced PLM Platform The Aras Innovator Model-based SOA for Enterprise PLM Advantages of combining the Model-based Approach with a Service-Oriented Architecture Updated Edition

More information

Oracle Cloud Blueprint and Roadmap Service. 1 Copyright 2012, Oracle and/or its affiliates. All rights reserved.

Oracle Cloud Blueprint and Roadmap Service. 1 Copyright 2012, Oracle and/or its affiliates. All rights reserved. Oracle Cloud Blueprint and Roadmap Service 1 Copyright 2012, Oracle and/or its affiliates. All rights reserved. Cloud Computing: Addressing Today s Business Challenges Business Flexibility & Agility Cost

More information

PLM Frustrations Aras White Paper

PLM Frustrations Aras White Paper The product lifecycle management (PLM) world is divided into two categories: The frustrated PLM veterans who have tried and failed to implement a successful PLM system, and the PLM novices who are blind

More information

OUTGROWING MICROSOFT DYNAMICS GP

OUTGROWING MICROSOFT DYNAMICS GP OUTGROWING MICROSOFT DYNAMICS GP Why Companies Move Up to Microsoft Dynamics 365 AN ARMANINO WHITE PAPER ARE YOU TOO SUCCESSFUL FOR YOUR CURRENT ERP SYSTEM? Whether you re expanding your product lines,

More information

EGUIDE: 9 Steps to a Healthy Salesforce Org

EGUIDE: 9 Steps to a Healthy Salesforce Org EGUIDE: 9 Steps to a Healthy Salesforce Org Your CRM system has the potential to completely transform your company s sales and marketing efforts. But with so many moving parts before, during and after

More information

Reducing Complexity in Connected and Autonomous Vehicles

Reducing Complexity in Connected and Autonomous Vehicles Reducing Complexity in Connected and Autonomous Vehicles Bill Bone CTO, Automotive October 2, 2017 Agenda 1. Increasing Product Complexity 2. Business of Engineering 3. Product Innovation Platform 4. Aras

More information

ERP System for the Higher Education Sector with Uniface

ERP System for the Higher Education Sector with Uniface ERP System for the Higher Education Sector with Uniface 1 CUSTOMER SECTOR Education COUNTRY UK CHALLENGE Provide and support full-strength ERP system for the dynamic Higher Education sector, providing

More information

Understanding the Business Benefits of an Open Source SOA Platform

Understanding the Business Benefits of an Open Source SOA Platform Understanding the Business Benefits of an Open Source SOA Platform A Hurwitz white Paper Hurwitz White Paper Copyright 2009, Hurwitz & Associates All rights reserved. No part of this publication may be

More information

AVEPOINT CLIENT SERVICES

AVEPOINT CLIENT SERVICES Services Catalog AVEPOINT CLIENT SERVICES AvePoint s Client Services teams provide world-class business and technical experts required to fully maximize your enterprise-wide collaboration technology investments.

More information

Pathways to the cloud. A quick guide for higher education institutions

Pathways to the cloud. A quick guide for higher education institutions Pathways to the cloud A quick guide for higher education institutions Choosing your path to the cloud If you re like most college leaders, you re under great pressure to modernize campus systems; to create

More information

V6. Contents

V6. Contents 2015 Training@ENOVIA V6 30D, Jalan PJS 1/46, Petaling Utama, Petaling Jaya, 46000 Selangor Darul Ehsan Tel: +603-7783 3459 Fax: +603-7781 6818 Email : training@mawea.com.my Website : Course Subject Code

More information

Information Services and Technology FY Performance Plan

Information Services and Technology FY Performance Plan I. MISSION STATEMENT The Information Systems and Technology Department assists county departments in achieving their stated business goals by effectively deploying information management services and providing

More information

The Accenture/ Siemens PLM Software Alliance

The Accenture/ Siemens PLM Software Alliance The Accenture/ Siemens PLM Software Alliance Enabling Efficient Product Lifecycle Management Companies in a wide range of industries rely upon Product Lifecycle Management (PLM) to grow their business,

More information

Pro/INTRALINK Curriculum Guide

Pro/INTRALINK Curriculum Guide Pro/INTRALINK 10.0 Curriculum Guide Live Classroom Curriculum Guide Introduction to Pro/INTRALINK 10.0 Business Administration of Pro/INTRALINK 10.0 Update to Windchill 10.0 for System Administrators System

More information

Using ClarityTM for Application Portfolio Management

Using ClarityTM for Application Portfolio Management WHITE PAPER: Application Portfolio Management February 2012 Using CA PPM ClarityTM for Application Portfolio Management David Werner CA Service & Portfolio Management agility made possible table of contents

More information

Master Data Governance & SAP Information Steward Integration. Jens Sauer, SAP Switzerland September 25 th, 2013

Master Data Governance & SAP Information Steward Integration. Jens Sauer, SAP Switzerland September 25 th, 2013 Master Data Governance & SAP Information Steward Integration Jens Sauer, SAP Switzerland September 25 th, 2013 Agenda Enterprise Master Data Management Trends & Functions SAP Enterprise MDM Product Portfolio

More information

WHAT TO LOOK FOR IN A CMMS/EAM SOLUTION

WHAT TO LOOK FOR IN A CMMS/EAM SOLUTION WHAT TO LOOK FOR IN A CMMS/EAM SOLUTION A Guide to Selecting the Right CMMS/EAM Solution and Provider for Your Organization 06/07/2016 Organizations implement maintenance and asset management software

More information

How Much Will Serialization Really Cost? AN INTRODUCTION TO THE TOTAL COST OF OWNERSHIP

How Much Will Serialization Really Cost? AN INTRODUCTION TO THE TOTAL COST OF OWNERSHIP How Much Will Serialization Really Cost? AN INTRODUCTION TO THE TOTAL COST OF OWNERSHIP TABLE OF CONTENTS Introduction Breaking down the whole iceberg What is Total Cost of Ownership? Acquisition is Just

More information

Key Factors in Optimizing Complex Manufacturing Businesses

Key Factors in Optimizing Complex Manufacturing Businesses Key Factors in Optimizing Complex Manufacturing Businesses Survey of executives across functional areas provides insight into boosting revenue and improving operations with Enterprise Resource Planning

More information

Electronic document management offers many advantages

Electronic document management offers many advantages Electronic document management offers many advantages Improves engineering productivity Fast Forward: Database-centric electrical computer-aided engineering (E-CAE) enhances productivity. In using E-CAE

More information

SYSTEM SOLUTIONS. Connecting systems, people and processes. Systems Integration Application Development Workflow Automation

SYSTEM SOLUTIONS. Connecting systems, people and processes. Systems Integration Application Development Workflow Automation SYSTEM SOLUTIONS Connecting systems, people and processes Systems Integration Application Development Workflow Automation Our commitment is to identify, deliver and integrate IT efficiencies. The integration

More information

Niagara 4 + JACE our newest products are open 4

Niagara 4 + JACE our newest products are open 4 Niagara 4 + JACE 8000 our newest products are open 4 NIAGARA FRAMEWORK connecting minds and machines niagara framework For more than 15 years, the Niagara Framework has fundamentally changed the way devices

More information

Self-driving ERP TM. Experience the power of people-centric ERP solutions designed for the speed of business. In business for people.

Self-driving ERP TM. Experience the power of people-centric ERP solutions designed for the speed of business. In business for people. OVERVIEW Unit4 Business World On! Self-driving ERP TM Experience the power of people-centric ERP solutions designed for the speed of business. In business for people. The digital revolution. Reshaping

More information

Built for Success: Building a Foundation for Industry 4.0 with an Integrated PLM Platform

Built for Success: Building a Foundation for Industry 4.0 with an Integrated PLM Platform Built for Success: Building a Foundation for Industry 4.0 with an Integrated PLM Platform David Ewing Jr. 2017 Aras aras.com Industry 4.0 Smart Factory Digital transformation Interoperability Capabilities

More information

DocAve Governance Automation

DocAve Governance Automation Governance Automation Technical Overview DocAve Governance Automation for Microsoft SharePoint & Office 365 Governance Your Policy. Our Automation. Platforms Supported SharePoint Server 2016, 2013 & 2010

More information

Network maintenance evolution and best practices for NFV assurance October 2016

Network maintenance evolution and best practices for NFV assurance October 2016 Network maintenance evolution and best practices for NFV assurance October 2016 TECHNOLOGY BUSINESS RESEARCH, INC. 2 CONTENTS 3 Introduction: NFV transformation drives new network assurance strategies

More information

You can plan and execute tests across multiple concurrent projects and people by sharing and scheduling software/hardware resources.

You can plan and execute tests across multiple concurrent projects and people by sharing and scheduling software/hardware resources. Data Sheet Application Development, Test & Delivery Performance Center Micro Focus Performance Center software is an enterprise-class performance engineering software, designed to facilitate standardization,

More information

Simplifying and Sustaining Global Process Transformation. Mike Bonfiglio, Business Process Management Lead June 22, 2010

Simplifying and Sustaining Global Process Transformation. Mike Bonfiglio, Business Process Management Lead June 22, 2010 Simplifying and Sustaining Global Process Transformation Mike Bonfiglio, Business Process Management Lead June 22, 2010 Agenda Rockwell Automation at a Glance Global Process Transformation Business Process

More information

REQUIREMENTS ANALYSIS IN THE IMPLEMENTATION OF INTEGRATED PLM, ERP AND CAD SYSTEMS

REQUIREMENTS ANALYSIS IN THE IMPLEMENTATION OF INTEGRATED PLM, ERP AND CAD SYSTEMS Proceedings of the 11 th International Conference on Manufacturing Research (ICMR2013), Cranfield University, UK, 19th 20th September 2013, pp 45-50 REQUIREMENTS ANALYSIS IN THE IMPLEMENTATION OF INTEGRATED

More information

data sheet ORACLE ENTERPRISE PLANNING AND BUDGETING 11i

data sheet ORACLE ENTERPRISE PLANNING AND BUDGETING 11i data sheet ORACLE ENTERPRISE PLANNING AND BUDGETING 11i Oracle Enterprise Planning and Budgeting provides finance and business managers with the right information and self-service tools to help them understand

More information

KNIGHT POINT S NETWORK MANAGED SERVICES DELIVERING COMMUNICATIONS AS A SERVICE TO THE FEDERAL GOVERNMENT

KNIGHT POINT S NETWORK MANAGED SERVICES DELIVERING COMMUNICATIONS AS A SERVICE TO THE FEDERAL GOVERNMENT KNIGHT POINT S NETWORK MANAGED SERVICES DELIVERING COMMUNICATIONS AS A SERVICE TO THE FEDERAL GOVERNMENT Background: A Changing Environment Current trends in government and industry are driving dramatic

More information

Windchill Quality Management

Windchill Quality Management Windchill Quality Management Closed-Loop Quality for Medical Device Innovators Windchill Quality Management is purpose-built for medical device makers who seek to accelerate delivery of breakthrough medical

More information

PDT Europe 2016 Data Standards: A Strategic Lever for Boeing Commercial Airplanes Brian Chiesi, Boeing Commercial Airplanes

PDT Europe 2016 Data Standards: A Strategic Lever for Boeing Commercial Airplanes Brian Chiesi, Boeing Commercial Airplanes PDT Europe 2016 Data Standards: A Strategic Lever for Boeing Commercial Airplanes Brian Chiesi, Boeing Commercial Airplanes The statements contained herein are based on good faith assumptions are to be

More information

DELMIA V5.17 extends the IBM Product Lifecycle Management solutions portfolio

DELMIA V5.17 extends the IBM Product Lifecycle Management solutions portfolio IBM Europe Announcement ZP07-0453, dated October 16, 2007 DELMIA V5.17 extends the IBM Product Lifecycle Management solutions portfolio Description...2 Product positioning... 5 Reference information...

More information

Managing Multi- CAD Complexity on a Budget By : Jim Brown President Tech-Clarity

Managing Multi- CAD Complexity on a Budget By : Jim Brown President Tech-Clarity 1 Managing Multi- CAD Complexity on a Budget By : Jim Brown President Tech-Clarity Tech-Clarity 2015 Can a Simpler Data Management Approach Still Work in a Multi-CAD Environment? 2 Tech-Clarity s The Basics

More information

INSIDE THIS ISSUE. Whitepaper

INSIDE THIS ISSUE. Whitepaper Whitepaper INSIDE THIS ISSUE This whitepaper explains why Microsoft Dynamics AX is particularly well-suited for supporting the needs of large enterprise-class organizations with a broad international presence.

More information