1 S-1 REVISED SCHEDULE OF MATERIALS CONTROL FOR CERTIFIED READY-MIX CONCRETE PLANT PRODUCTION NEW WRITE-UP 02/11/19 DO NOT REMOVE THIS NEW WRITE-UP DATE. IT NEEDS TO STAY IN FOR THE CONTRACTORS. Always use this write-up with SP (STRUCTURAL CONCRETE). SP S-1.1 Pages of the MnDOT SD-15 June, 2017 (Rev. Nov., 2017) Schedule of Materials Control for 2018 Standard Specifications shall be deleted and replaced with the following:

2 IV. Concrete Construction Items (cont.) ( Certified Ready-Mix - Concrete Plant Production Remarks: (1) All gradation and quality tests require companion samples. Samples taken at location identified on Contact Report located. (2) Perform Aggregate Quality testing as directed by the Concrete Engineer. (3) When <20 yd 3 of concrete is produced in a week, plant monitoring is not required with the exception of monthly aggregate quality testing. Minimum Sample Sizes: Gradation: 3/4 Plus, #4: 30 lb. 3/4 Minus, #67: 10 lb. #7, CA-70: 6 lb. CIA, FIA: 1000 g CS, FS: 500 g #89, CA-80: 500 g Fine Aggregate: 500 g Companion Required, Double Sample Sizes Pay Item 2301** Moisture: Fine Aggregate: Intermediate Aggregate: Coarse Aggregate: 500 g 500 g 2000 g Aggregate Quality: 3/4 Plus, #4: 50 lb. 3/4 Minus, #67: 30 lb. #7, CA-70: 30 lb. #89, CA-80: 30 lb. Intermediate Agg: 30 lb. Fine Aggregate: 30 lb. Companion Required, Double Sample Sizes Test Type Spec. Producer/Contractor Testing Agency Testing Form Gradation (QC/QA) All JMFs and Bridge Deck mix designs Daily Concrete Quantity: yd 3 : 1 per fraction per source >400 yd 3 : 2 per fraction per source Take second gradation after daily total exceeds 400 yd 3. Passing aggregate gradations are required prior to the start of bridge deck pours. All other mix designs Weekly Concrete Quantity: yd 3 : 1 per fraction per source >400 yd 3 : 2 per fraction per source Take second gradation after weekly total exceeds 400 yd 3. Notes: Washing the fine aggregate gradation (QC) sample is not required when the result on the -#200 sieve of the unwashed sample is less than 1.0%. Hold QA (QC companion) samples until they are picked up by the Agency monitor. Discard after 14 calendar days. Performing testing on representative material at the end of the most recent day of production is allowed. All mix designs Weekly Concrete Quantity 20 yd 3 : 1 QA (QC Companion) sample per fraction per source per week Include QC Companion results on Sample ID Card. QC Workbook Aggregate Gradation Control Charts Workbook

3 IV. Concrete Construction Items (cont.) ( Certified Ready-Mix - Concrete Plant Production (cont.) Pay Item 2301** Test Type Gradation (Verification/ Verification Companion) Aggregate Quality including Coarse Aggregate Percent Passing - #200 Aggregate Moisture (QC) Spec Producer/Contractor Testing Agency Testing Form Test the Verification Companion sample. Complete on the day the sample was taken. Wash all fine aggregate Verification Companion samples. Test at Contractor s Discretion 2461 Daily Concrete Quantity 20 yd 3 : 1 per fraction per source completed every 4 hours. Complete the initial moisture content and adjust the batch water prior to the start of concrete production each day. If weather conditions allow, performing moisture testing on representative material at the end of production the prior evening is allowed. In this event, the four-hour rate will commence with the first pour of the day, regardless if it is placed in Agency or private work. Weekly Concrete Quantity 100 yd 3 : 1 per fraction per source Include Verification Companion results on Sample ID Card. 1 per fraction per source per month. Bridge Deck Concrete: 1 per fraction per source per month tested for D.2 Identify quality samples with a Q on the Sample ID Card and the Quality companion sample. None QC Workbook Weekly Certified Ready-Mix Plant Report or QA Workbook 2410 Sample ID Card QC Workbook

4 IV. Concrete Construction Items (cont.) ( Concrete Pavement - Concrete Plant Production Remarks: (1) Use Certified Ready-Mix - Concrete Plant Production testing rates schedule when: a) The entire concrete paving project is < 3,500 cu. yd. b) A secondary plant is used to provide minor work. (2) When w/c incentives apply: a) Contractor QC Technician and Agency Plant Monitor are required to be present during the entire pour. If w/c incentives do not apply, the Agency Plant Monitor shall monitor as necessary to ensure compliance with the requirements of the Contract. b) A certified ready-mix plant shall be dedicated (provides concrete only to the concrete paving project). (3) Take gradation samples in the presence of the Agency unless otherwise authorized by the Engineer. Take samples off the belt leading to the weigh hopper unless otherwise approved by the Engineer. All gradation and quality tests require companion samples. (4) Perform Quality testing as directed by the Concrete Engineer. Minimum Sample Sizes: Gradation: 3/4 Plus, #4: 30 lb. 3/4 Minus, #67: 10 lb. #7, CA-70: 6 lb. CIA, FIA: 1000 g CS, FS: 500 g #89, CA-80: 500 g Fine Aggregate: 500 g Companion Required, Double Sample Sizes Moisture: Fine Aggregate: Intermediate Aggregate: Coarse Aggregate: 500 g 500 g 2000 g Aggregate Quality: 3/4 Plus, #4: 50 lb. 3/4 Minus, #67: 30 lb. #7, CA-70: 30 lb. #89, CA-80: 30 lb. Intermediate Agg: 30 lb. Fine Aggregate: 30 lb. Companion Required, Double Sample Sizes -#200 Coarse Aggregate: 3/4 Plus, #4: 12 lb. 3/4 Minus, #67: 6 lb. #7, CA-70: 6 lb. CIA, FIA: 1000 g CS, FS: 500 g #89, CA-80: 500 g Pay Item Test Type Spec. Producer/Contractor Testing Agency Testing Form 2301 Gradation (QC/QA) Concrete paving batch plant: Daily Concrete Quantity 250 yd 3 : 1 per 2500 yd 3 per fraction per source Take initial samples for aggregate gradation testing within the first 250 yd 3. Certified ready-mix plant: Daily Concrete Quantity: yd 3 : 1 per fraction per source >400 yd 3 : 2 per fraction per source Take second gradation after daily total exceeds 400 yd 3. Concrete paving batch plant: Daily Concrete Quantity 100 yd 3 : 1 QA (QC Companion) sample per fraction per source per week Certified ready-mix plant: Weekly Concrete Quantity 20 yd 3 : 1 QA (QC Companion) sample per fraction per source per week JMF Concrete Aggregate Workbook JMF Moving Average Summary Workbook 2410 Sample ID

5 Performing testing on representative material at the end of the most recent day of production is allowed. If well-graded aggregate incentives apply: Use the Contractor s gradation results for well-graded aggregate incentive calculations as verified by Agency testing Include the JMF Number and the QC Gradation/Verification Companion results on the Sample ID Card. Card when samples are submitted to MnDOT Laboratory 2301 Gradation (Verification/ Verification Companion) Test the Verification Companion sample. Complete on the day the sample was taken. Concrete paving batch plant: Daily Concrete Quantity 250 yd 3 : Certified ready-mix plant: Weekly Concrete Quantity 100 yd 3 : 1 per fraction per source per day If well-graded aggregate incentives apply: 1 per fraction per source per day If well-graded aggregate incentives do not apply: 1 per fraction per source per week Include the JMF Number and the QC Gradation/ Verification Companion results on the Sample ID Card. If Coarse Aggregate Quality Incentive/Disincentives apply: The Agency may use the Verification gradation sample for the Coarse Aggregate Quality incentive/disincentive testing.

6 S-1.2 The following shall be added to the bottom of the Table on Page 35 of the MnDOT SD-15 June, 2017 (Rev. Nov., 2017) Schedule of Materials Control for 2018 Standard Specifications:

7 IV Concrete Construction Items (cont.) ( Colored Concrete Membrane Curing Compound 3752 Visual Inspection Only curing compound for colored concrete from qualified sources is allowed. Refer to the approved products list of curing compounds for qualified manufacturers

8 S-1.3 Page 39 of the MnDOT SD-15 June, 2017 (Rev. Nov., 2017) Schedule of Materials Control for 2018 Standard Specifications shall be deleted and replaced with the following:

9 IV. Concrete Construction Items (cont.) ( Concrete Field Testing Concrete Pavement (cont.) Pay Item Test Type Spec. Contractor Testing Agency Testing Form 2301 Concrete Pavement Texture 2301 Perform texture testing at locations determined by the Engineer in accordance with the Contract. Determine texture testing locations using random numbers. Observe Contractor testing when possible. Probing Coring Texture and MIT- SCAN T2 Report 2301 Thickness (QC/Verification) 2301 Surface Smoothness 2301 Dowel Bar and Tie Bar Steel Location 2301 Probe and core at locations determined by the Engineer in accordance with the Contract Measure smoothness of the final concrete as required by the Contract. Perform all profiling in the presence of the Engineer unless otherwise approved by the Engineer For concrete projects greater than 3,500 cu. yd. On the first day and each day of slip form pavement placement: (1) Verify the adequacy of the dowel bar anchoring by scanning seven (7) random doweled contraction joints in each sublot. (2) Verify the presence and alignment of tie bar steel by scanning 75 lin. ft. in each sublot. If the Engineer determines the first days dowel bar anchoring and tie bar placement processes are acceptable, the Engineer may allow a reduction in scanned joints in each sublot as follows: (1) Verify the adequacy of the dowel bar anchoring by scanning four (4) random doweled contraction joints per sublot. (2) Verify the presence and alignment of tie bar steel by scanning 25 lin. ft. out of every sublot. Initial pavement at core locations and reinitial the sides of specimens after coring. Field measure to the nearest 1/8 Transport to the MnDOT Office of Materials and Road Research for final thickness determination. Observe Contractor testing when possible. Observe Contractor steel location testing when possible. Probing Coring Texture and MIT- SCAN T2 Report Field Probing Report Field Coring Report Concrete Profile Summary Worksheet Probing Coring Texture and MIT- SCAN T2 Report

10

< ~ -n~rtz, Concrete Engineer Office of Materials

< ~ -n~rtz, Concrete Engineer Office of Materials Minnesota Department of Transportation MEMO Office of Materials Mailstop 645 1400 Gervais Avenue Maplewood, MN 55109 'stribution 57, 612, 618, 650 ~ < ~ -n~rtz, Concrete Engineer Office of Materials Implementation

More information

Minnesota Concrete Flatwork Specifications for Local Government Agencies

Minnesota Concrete Flatwork Specifications for Local Government Agencies Minnesota Concrete Flatwork LTAP Concrete Flatwork Specifications Mn Concrete Flatwork Specifications for Local MN Concrete Flatwork Agencies Approved for use on Local Government Agency Projects and State

More information

MINNESOTA DEPARTMENT OF TRANSPORTATION OFFICE OF MATERIALS ENGINEERING

MINNESOTA DEPARTMENT OF TRANSPORTATION OFFICE OF MATERIALS ENGINEERING Mn/DOT SD-15 (Rev. 4-2006) MINNESOTA DEPARTMENT OF TRANSPORTATION OFFICE OF MATERIALS ENGINEERING Federal Aid, State Funds, County/Municipal Federal Aid Projects and State Aid Projects This schedule outlines

More information

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 888 PORTLAND CEMENT CONCRETE PAVEMENT USING QC/QA.

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 888 PORTLAND CEMENT CONCRETE PAVEMENT USING QC/QA. STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 888 PORTLAND CEMENT CONCRETE PAVEMENT USING QC/QA April 15, 2011 888.01 General 888.02 Materials 888.03 Concrete Proportioning 888.04

More information

MINNESOTA DEPARTMENT OF TRANSPORTATION OFFICE OF MATERIALS ENGINEERING

MINNESOTA DEPARTMENT OF TRANSPORTATION OFFICE OF MATERIALS ENGINEERING Mn/DOT SD-15 (Rev. 2-2001) MINNESOTA DEPARTMENT OF TRANSPORTATION OFFICE OF MATERIALS ENGINEERING Federal Aid, State Funds, County and Municipal Federal Aid Projects This schedule outlines the minimum

More information

2016 SALT Schedule of Materials Control - Local Government Agency

2016 SALT Schedule of Materials Control - Local Government Agency This Schedule of Materials Control (SMC) outlines the minimum testing requirements for State Aid Funded and/or federal aid Projects off the National Highway and Trunk Highway System. Optional to this SMC

More information

2. Determine Random Numbers: Determine random numbers for testing locations using the Probing, Coring, Texture and MIT-SCAN T2 Report.

2. Determine Random Numbers: Determine random numbers for testing locations using the Probing, Coring, Texture and MIT-SCAN T2 Report. JOB GUIDE CONCRETE PAVING INSPECTION 1. Review Contract and Plans: Obtain plans and special provisions and study them in detail. Attend the pre-construction meeting. Attend the pre-paving meeting. 2. Determine

More information

MINNESOTA DEPARTMENT OF TRANSPORTATION OFFICE OF MATERIALS ENGINEERING

MINNESOTA DEPARTMENT OF TRANSPORTATION OFFICE OF MATERIALS ENGINEERING Mn/DOT SD-15 (Rev. 3-2005) MINNESOTA DEPARTMENT OF TRANSPORTATION OFFICE OF MATERIALS ENGINEERING Federal Aid, State Funds, County/Municipal Federal Aid Projects and State Aid Projects This schedule outlines

More information

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR QUALITY CONTROL AND ACCEPTANCE OF STRUCTURAL PRECAST CONCRETE

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR QUALITY CONTROL AND ACCEPTANCE OF STRUCTURAL PRECAST CONCRETE MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR QUALITY CONTROL AND ACCEPTANCE OF STRUCTURAL PRECAST CONCRETE STR:MJF 1 of 8 APPR:JFS:POJ:01-04-19 FHWA:APPR:01-10-19 a. Description. The Contractor

More information

Modified Concrete Mixes and Optimized Aggregate Gradations. Ethan Bahmer MDOT s Statewide Concrete Construction Engineer

Modified Concrete Mixes and Optimized Aggregate Gradations. Ethan Bahmer MDOT s Statewide Concrete Construction Engineer Modified Concrete Mixes and Optimized Aggregate Gradations Ethan Bahmer MDOT s Statewide Concrete Construction Engineer Modified Concrete Mixtures (High Performance) 12SP-604A-09 and 12SP-604B-10 Modified

More information

Concrete Paving Association of Minnesota CPAM Annual Workshop March 11, Gordy Bruhn- Senior Engineering Specialist

Concrete Paving Association of Minnesota CPAM Annual Workshop March 11, Gordy Bruhn- Senior Engineering Specialist Concrete Paving Association of Minnesota CPAM Annual Workshop March 11, 2016 Gordy Bruhn- Senior Engineering Specialist FDR Removals I-94 Monticello, MN FDR Removals TH 2 Erskine, MN Revised Reinforcing

More information

MnDOT SD-15 June, 2015 (Rev. Sept., 2015) Schedule of Materials Control for 2016 Standard Specifications. Schedule of Materials Control 2016

MnDOT SD-15 June, 2015 (Rev. Sept., 2015) Schedule of Materials Control for 2016 Standard Specifications. Schedule of Materials Control 2016 Schedule of Materials Control 2016 Contents Introduction Page... 1 SCHEDULE OF MATERIALS CONTROL (For usewith the 2016 Standard Specifications for Construction): I. Grading, Base and Reclamation Construction

More information

500 Rigid Pavement. 502 Portland Cement Concrete Pavement (Non-QC/QA) Concrete Pavement (**)(**)(**) 501-1

500 Rigid Pavement. 502 Portland Cement Concrete Pavement (Non-QC/QA) Concrete Pavement (**)(**)(**) 501-1 500 Rigid Pavement Plate 501 Portland Cement Concrete Pavement (QC/QA) Concrete Pavement (**)(**)(**) 501-1 Quality Control Testing Concrete Pavement (**)(**)(**) 501-2 Record of Tested Material Received

More information

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 888 PORTLAND CEMENT CONCRETE PAVEMENT USING QC/QA.

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 888 PORTLAND CEMENT CONCRETE PAVEMENT USING QC/QA. STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 888 PORTLAND CEMENT CONCRETE PAVEMENT USING QC/QA April 18, 2008 888.01 General 888.02 Materials 888.03 Concrete Proportioning 888.04

More information

SPECIAL PROVISION FOR FURNISHING AND PLACING MARSHALL HMA MIXTURE (WITH SAMPLING BEHIND THE PAVER)

SPECIAL PROVISION FOR FURNISHING AND PLACING MARSHALL HMA MIXTURE (WITH SAMPLING BEHIND THE PAVER) MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR FURNISHING AND PLACING MARSHALL HMA MIXTURE (WITH SAMPLING BEHIND THE PAVER) C&T:JWB 1 of 10 C&T APPR:KPK:CJB:08-02-06 FHWA:APPR:08-21-06 a.

More information

Raising the Quality Bar- Everyone Wins!

Raising the Quality Bar- Everyone Wins! Quality in the Concrete Paving Process Raising the Quality Bar- Everyone Wins! Jim Grove, PE Federal Highway Administration/Global Consulting Inc. Office of Infrastructure Virginia Concrete Conference

More information

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR FURNISHING AND PLACING MARSHALL HOT MIX ASPHALT MIXTURE (WITH SAMPLING BEHIND THE PAVER)

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR FURNISHING AND PLACING MARSHALL HOT MIX ASPHALT MIXTURE (WITH SAMPLING BEHIND THE PAVER) MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR FURNISHING AND PLACING MARSHALL HOT MIX ASPHALT MIXTURE (WITH SAMPLING BEHIND THE PAVER) CFS:JWB 1 of 9 APPR:KPK:CJB:11-02-15 FHWA:APPR:11-02-15

More information

ROAD COMMISSION FOR OAKLAND COUNTY SPECIAL PROVISION FOR QUALITY CONTROL AND ACCEPTANCE OF PORTLAND CEMENT CONCRETE

ROAD COMMISSION FOR OAKLAND COUNTY SPECIAL PROVISION FOR QUALITY CONTROL AND ACCEPTANCE OF PORTLAND CEMENT CONCRETE ROAD COMMISSION FOR OAKLAND COUNTY SPECIAL PROVISION FOR QUALITY CONTROL AND ACCEPTANCE OF PORTLAND CEMENT CONCRETE RCOC/CONST:SH/JO PAGE 1 OF 9 a. Description. This special provision establishes Portland

More information

CONSTRUCTION SPECIFICATION FOR CONCRETE PAVEMENT AND CONCRETE BASE

CONSTRUCTION SPECIFICATION FOR CONCRETE PAVEMENT AND CONCRETE BASE ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 350 MARCH 1998 CONSTRUCTION SPECIFICATION FOR CONCRETE PAVEMENT AND CONCRETE BASE 350.01 SCOPE 350.02 REFERENCES 350.03 DEFINITIONS TABLE OF CONTENTS

More information

FAA AC 150/ H Draft Principal Changes

FAA AC 150/ H Draft Principal Changes FAA AC 150/5370-10H Draft Principal Changes 2018 Indiana Chapter ACPA Workshop Indianapolis, IN Gary L. Mitchell, P.E. Vice President American Concrete Pavement Association Credits Doug Johnson and Greg

More information

SECTION RIGID PAVEMENT

SECTION RIGID PAVEMENT SECTION 02750 PART 1 GENERAL RIGID PAVEMENT 1.1 SUMMARY A. Section Includes: 1. Concrete sidewalks. 2. Concrete stair steps. 3. Concrete integral curbs gutters. 4. Concrete parking areas and roads. B.

More information

Contact the Mn/DOT District Independent Assurance Inspector when project starts to provide the proper servicing of your project.

Contact the Mn/DOT District Independent Assurance Inspector when project starts to provide the proper servicing of your project. Mn/DOT SD-15 April 2, 2012 Schedule of Materials Control P a g e 1 Minnesota Department of Transportation Schedule of Materials Control (SMC) Introduction Page (Federal Aid, State Funds, County/Municipal

More information

WYOMING DEPARTMENT OF TRANSPORTATION. SUPPLEMENTARY SPECIFICATION FOR STRUCTURAL CONCRETE WITH QUALITY CONTROL and QUALITY ACCEPTANCE

WYOMING DEPARTMENT OF TRANSPORTATION. SUPPLEMENTARY SPECIFICATION FOR STRUCTURAL CONCRETE WITH QUALITY CONTROL and QUALITY ACCEPTANCE WYOMING DEPARTMENT OF TRANSPORTATION SUPPLEMENTARY SPECIFICATION FOR STRUCTURAL CONCRETE WITH QUALITY CONTROL and QUALITY ACCEPTANCE SS-500G Page 1 of 18 This supplementary specification supplements, amends,

More information

Aggregate Testing Recertification. Quality Control / Quality Assurance

Aggregate Testing Recertification. Quality Control / Quality Assurance Aggregate Testing Recertification Quality Control / Quality Assurance DOT Employee Timesheet Information Charge to Office Overhead AFE- 71B4 Function- 1174 **IMPORTANT** Recertification is only for individuals

More information

GUIDE FOR QUALITY CONTROL AND ACCEPTANCE REQUIREMENTS FOR HMA

GUIDE FOR QUALITY CONTROL AND ACCEPTANCE REQUIREMENTS FOR HMA 5.2.7.2. GUIDE FOR QUALITY CONTROL AND ACCEPTANCE REQUIREMENTS FOR HMA 1. Purpose The purpose of this guide is to establish minimum requirements for the Contractor's quality control system and KDOT's QC/QA

More information

Section 2. Procedures and Tests

Section 2. Procedures and Tests Section 2 Procedures and Tests -Plant- Job Guide Concrete Paving Plant Monitor Contact Report Paving Contractor Mix Designs JMF Concrete Aggregate Worksheet JMF Moving Average Summary JMF Adjustment Worksheet

More information

MATERIALS DIVISION MEMORANDUM SIGNATURE:

MATERIALS DIVISION MEMORANDUM SIGNATURE: MATERIALS DIVISION MEMORANDUM GENERAL SUBJECT: Modified Acceptance Program for Fine, Coarse Open-Graded and Crusher Run Aggregates SPECIFIC SUBJECT: Materials Manual of Instructions: Section 204.02(b)

More information

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR QUALITY CONTROL AND ACCEPTANCE OF PORTLAND CEMENT CONCRETE

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR QUALITY CONTROL AND ACCEPTANCE OF PORTLAND CEMENT CONCRETE MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR QUALITY CONTROL AND ACCEPTANCE OF PORTLAND CEMENT CONCRETE CFS:JFS 1 of 28 APPR:TES:DBP:07-11-17 FHWA:APPR:07-13-17 a. Description. The Contractor

More information

PAVING SLABS ON AGGREGATE BED FOR ROOF PLAZA DECKS

PAVING SLABS ON AGGREGATE BED FOR ROOF PLAZA DECKS SECTION 32 14 13.16 PAVING SLABS ON AGGREGATE BED FOR ROOF PLAZA DECKS (1995 MasterFormat Section 02784) Note: This guide specification for the U.S. is for paving slabs used as ballast and/or paving on

More information

MICHIGAN DEPARTMENT OF TRANSPORTATION

MICHIGAN DEPARTMENT OF TRANSPORTATION MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR QUALITY CONTROL AND ACCEPTANCE OF PORTLAND CEMENT CONCRETE (FOR LOCAL AGENCY PROJECTS ONLY) CFS:JFS 1 of 20 APPR:TES:DBP:06-30-17 FHWA:APPR:07-11-17

More information

Section 2. Procedures and Tests

Section 2. Procedures and Tests Section 2 Procedures and Tests -Plant- Job Guide Concrete Paving Plant Monitor Contact Report Paving Contractor Mix Designs JMF Concrete Aggregate Worksheet JMF Moving Average Summary JMF Adjustment Worksheet

More information

MICHIGAN DEPARTMENT OF TRANSPORTATION

MICHIGAN DEPARTMENT OF TRANSPORTATION MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR QUALITY CONTROL AND ACCEPTANCE OF PORTLAND CEMENT CONCRETE (FOR LOCAL AGENCY PROJECTS ONLY) CFS:JFS 1 of 21 APPR:TES:DBP:06-11-18 FHWA:APPR:06-14-18

More information

MICHIGAN DEPARTMENT OF TRANSPORTATION

MICHIGAN DEPARTMENT OF TRANSPORTATION MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR OPEN-GRADED DRAINAGE COURSE, MODIFIED FOR JOB NUMBER 110616 (PORTLAND CEMENT-TREATED PERMEABLE BASE USING CRUSHED CONCRETE) CFS:JFS 1 of 5 APPR:ARB:TES:11-06-14

More information

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION OF 1990

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION OF 1990 Sheet 1 of 14 KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION OF 1990 NOTE: This special provision is generally written in the imperative mood. The subject,

More information

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR QUALITY CONTROL AND ACCEPTANCE OF PORTLAND CEMENT CONCRETE

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR QUALITY CONTROL AND ACCEPTANCE OF PORTLAND CEMENT CONCRETE MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR QUALITY CONTROL AND ACCEPTANCE OF PORTLAND CEMENT CONCRETE CFS:JFS 1 of 39 APPR:TES:JAB:07-30-13 FHWA:APPR:08-02-13 a. Description. The Contractor

More information

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR QUALITY CONTROL AND ACCEPTANCE OF PORTLAND CEMENT CONCRETE

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR QUALITY CONTROL AND ACCEPTANCE OF PORTLAND CEMENT CONCRETE MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR QUALITY CONTROL AND ACCEPTANCE OF PORTLAND CEMENT CONCRETE CFS:JFS 1 of 29 APPR:TES:JAB:07-18-14 FHWA:APPR:07-30-14 a. Description. The Contractor

More information

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS 2007 EDITION

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS 2007 EDITION Sheet 1 of 6 KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS 2007 EDITION Add a new SECTION to DIVISION 400: LOW-CRACKING HIGH-PERFORMANCE CONCRETE 1.0 DESCRIPTION

More information

Workshop Introduction

Workshop Introduction Quality in the Concrete Paving Process Workshop Introduction Module 8-21 Instructors Dennis Dvorak Jim Grove Mike Praul FHWA Resource Center (708) 283-3542 dennis.dvorak@dot.gov ATI Inc. / FHWA Office

More information

INDOT/ACPA Technical Committee 2009 Specification Revisions 2009 Test Method Revisions Studies

INDOT/ACPA Technical Committee 2009 Specification Revisions 2009 Test Method Revisions Studies PCCP Workshop INDOT INDOT/ACPA Technical Committee 2009 Specification Revisions 2009 Test Method Revisions Studies INDOT/ACPA Technical Committee Materials Management FHWA Construction Management District

More information

A. Provide all labor, materials, and equipment as necessary to complete all work as indicated on the Drawings and specified herein.

A. Provide all labor, materials, and equipment as necessary to complete all work as indicated on the Drawings and specified herein. PAGE 321216-1 SECTION 321216 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification sections,

More information

Special Provision No. 199S53 February 2005

Special Provision No. 199S53 February 2005 QUALITY CONTROL COMPLIANCE INCENTIVE Special Provision No. 199S53 February 2005 1.0 SCOPE This special provision covers the financial incentive available to the Contractor for compliance with the quality

More information

CHAPTER 5 BLENDING AGGREGATES

CHAPTER 5 BLENDING AGGREGATES CHAPTER 5 BLENDING AGGREGATES A good asphalt concrete pavement requires more than asphalt, aggregates and equipment. It also requires knowledge, skill, and workmanship. Part of this knowledge and skill

More information

SPECIAL SPECIFICATION 3402 Reflective Crack Relief Interlayer (RCRI)

SPECIAL SPECIFICATION 3402 Reflective Crack Relief Interlayer (RCRI) 1993 Specifications CSJ 0451-02-023, etc. SPECIAL SPECIFICATION 3402 Reflective Crack Relief Interlayer (RCRI) 1. Description. This Item shall govern for the materials and construction requirements for

More information

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR HIGH PERFORMANCE PORTLAND CEMENT CONCRETE PAVEMENT (GRADE P1M)

MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR HIGH PERFORMANCE PORTLAND CEMENT CONCRETE PAVEMENT (GRADE P1M) MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR HIGH PERFORMANCE PORTLAND CEMENT CONCRETE PAVEMENT (GRADE P1M) CFS:JFS 1 of 12 APPR:JAB:TES:07-18-14 FHWA:APPR:07-30-14 a. Description. This

More information

32.02 RESPONSIBILITIES OF THE TESTING AGENCY

32.02 RESPONSIBILITIES OF THE TESTING AGENCY 32.2 RESPONSIBILITIES OF THE TESTING AGENCY 32.2.1 General All materials and operations shall be tested in accordance with these Specifications and as directed by the Project Manager. Agencies testing

More information

SECTION RIGID PAVEMENT. 1. Portland Cement Concrete (PCC) pavement. 2. Section Aggregate Base Course.

SECTION RIGID PAVEMENT. 1. Portland Cement Concrete (PCC) pavement. 2. Section Aggregate Base Course. SECTION 02750 RIGID PAVEMENT PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Portland Cement Concrete (PCC) pavement. B. Related Sections: 1.2 REFERENCES 1. Section 02315 Excavation. 2. Section 02721

More information

SECTION CONCRETE. B. ACI 318 Building Code Requirements for Structural Concrete and Commentary

SECTION CONCRETE. B. ACI 318 Building Code Requirements for Structural Concrete and Commentary SECTION 03300 CONCRETE PART 1 GENERAL 1.01 SCOPE OF WORK Concrete foundation walls, sanitary structures, pipe encasements, thrust blocking and slabs on grade. 1.02 REFERENCES A. ACI 301 Specification for

More information

SECTION 706 AGGREGATES FOR PORTLAND CEMENT PRODUCTS SCOPE

SECTION 706 AGGREGATES FOR PORTLAND CEMENT PRODUCTS SCOPE 706 706.01.01 MATERIALS COVERED SECTION 706 AGGREGATES FOR PORTLAND CEMENT PRODUCTS SCOPE A. This specification covers the quality and size of aggregates used in Portland cement products. 706.02.01 GENERAL

More information

Regional Engineers. Jack A. Elston

Regional Engineers. Jack A. Elston Regional Engineers Jack A. Elston Special Provision for Hot-Mix Asphalt Pay for Performance Using Percent Within Limits Jobsite Sampling April 20, 2018 This special provision was developed by the Bureau

More information

SUPPLEMENTAL SPECIFICATION 898 QC/QA CONCRETE FOR STRUCTURES March 23, 2009 PROCEDURES FOR PROCESSING and CMS DATA ENTRY OF QC AND QA CYLINDERS

SUPPLEMENTAL SPECIFICATION 898 QC/QA CONCRETE FOR STRUCTURES March 23, 2009 PROCEDURES FOR PROCESSING and CMS DATA ENTRY OF QC AND QA CYLINDERS A. QC (Quality Control) CYLINDERS Create ONE Sample ID in CMS for each LOT of concrete (see Attachment A for Lot & Sublot definition) Copy [F7] the MATERIAL SAMPLE screen to create as many suffixes as

More information

MICHIGAN DEPARTMENT OF TRANSPORTATION

MICHIGAN DEPARTMENT OF TRANSPORTATION MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR QUALITY CONTROL AND ACCEPTANCE OF PORTLAND CEMENT CONCRETE (FOR LOCAL AGENCY PROJECTS ONLY) CFS:JFS 1 of 20 APPR:JAB:TES:11-03-15 FHWA:APPR:11-10-15

More information

INSTRUCTIONS FOR COMPLETING THE TE-45 FORM:

INSTRUCTIONS FOR COMPLETING THE TE-45 FORM: INSTRUCTIONS FOR COMPLETING THE TE-45 FORM: 1. SAMPLE ID - This is a number generated by CMS when sample information is inputted into the system. 2. TYPE OF INSPECTION - Typically this will be a Control

More information

2003 SPECIFICATIONS SECTION 501 DIVISION 500 RIGID PAVEMENT

2003 SPECIFICATIONS SECTION 501 DIVISION 500 RIGID PAVEMENT 2003 SPECIFICATIONS SECTION 501 DIVISION 500 RIGID PAVEMENT SECTION 501 PORTLAND CEMENT CONCRETE PAVEMENT 501.01 GENERAL. This item consists of constructing a concrete pavement (with or without reinforcement)

More information

Arlington County, VA Materials Testing Specification Reference Guide (8/18/2016) MATERIAL AND TEST (REF. - VDOT TEST METHODS MANUAL )

Arlington County, VA Materials Testing Specification Reference Guide (8/18/2016) MATERIAL AND TEST (REF. - VDOT TEST METHODS MANUAL ) MINIMUM RATE 1. Embankments SOILS AND AGGREGATES (a) Density, 303.04(h) One (1) test per 2500 yd3 or less plus: (a) for fills less than 500 ft. length one (1) test on every other 6-in. layer bottom to

More information

Arlington County, VA Materials Testing Specification Reference Guide (8/18/2016) MATERIAL AND TEST (REF. VDOT TEST METHODS MANUAL )

Arlington County, VA Materials Testing Specification Reference Guide (8/18/2016) MATERIAL AND TEST (REF. VDOT TEST METHODS MANUAL ) 1. Embankments SOILS AND AGGREGATES (a) Density, 303.04(h) One (1) test per 2500 yd3 or less plus: (a) for fills less than 500 ft. length one (1) test on every other 6-in. layer bottom to top of fill starting

More information

WYOMING DEPARTMENT OF TRANSPORTATION SUPPLEMENTARY SPECIFICATION FOR PORTLAND CEMENT CONCRETE PAVEMENT

WYOMING DEPARTMENT OF TRANSPORTATION SUPPLEMENTARY SPECIFICATION FOR PORTLAND CEMENT CONCRETE PAVEMENT WYOMING DEPARTMENT OF TRANSPORTATION SUPPLEMENTARY SPECIFICATION FOR PORTLAND CEMENT CONCRETE PAVEMENT SS-400G Page 1 of 3 This supplementary specification replaces Section 414, Portland Cement Concrete

More information

SPECIAL SPECIFICATION 3157 Cold Processed - Recycled Paving Material (RPM) for Use as Aggregate Base Course

SPECIAL SPECIFICATION 3157 Cold Processed - Recycled Paving Material (RPM) for Use as Aggregate Base Course 1993 Specifications SPECIAL SPECIFICATION 3157 Cold Processed - Recycled Paving Material (RPM) for Use as Aggregate Base Course 1. Description. This Item, Cold Processed - Recycled Paving Material (RPM),

More information

CONCRETE TILE PAVERS

CONCRETE TILE PAVERS Section 32 14 13 CONCRETE TILE PAVERS (1995 MasterFormat Section 02780) Note: This guide specification for the U.S. is for the installation of concrete tile paving units whose thickness are less than the

More information

Regional Engineers. Maureen M. Addis. Special Provision for Hot-Mix Asphalt Pay for Performance Using Percent Within Limits Jobsite Sampling

Regional Engineers. Maureen M. Addis. Special Provision for Hot-Mix Asphalt Pay for Performance Using Percent Within Limits Jobsite Sampling Regional Engineers Maureen M. Addis Special Provision for Hot-Mix Asphalt Pay for Performance Using Percent Within Limits Jobsite Sampling September 29, 2017 This special provision was developed by the

More information

S-26 (2360) PLANT MIXED ASPHALT PAVEMENT (LOCAL AGENCY) (2013 version )

S-26 (2360) PLANT MIXED ASPHALT PAVEMENT (LOCAL AGENCY) (2013 version ) S-26 (2360) PLANT MIXED ASPHALT PAVEMENT (LOCAL AGENCY) (2013 version ) MnDOT 2360 is hereby deleted from the MnDOT Standard Specifications and replaced with the attached 2360 (Plant Mixed Asphalt Pavement)

More information

Special Provision No. 199S64 July 2016

Special Provision No. 199S64 July 2016 GENERAL REQUIREMENTS FOR REFEREE TESTING Special Provision No. 199S64 July 2016 1.0 Scope This Special Provision describes the common requirements for referee testing related to laboratory and field testing

More information

AMENDMENT TO OPSS 313, MARCH 1993 AND OPSS 1149, MARCH Special Provision No. 103F34 March 2006

AMENDMENT TO OPSS 313, MARCH 1993 AND OPSS 1149, MARCH Special Provision No. 103F34 March 2006 AMENDMENT TO OPSS 313, MARCH 1993 AND OPSS 1149, MARCH 1993 Special Provision No. 103F34 March 2006 End Result Specification for Acceptance of Hot Mix (Aggregate Gradation, Asphalt Cement Content, Air

More information

LTRC Seminar - Building Quality Pavements QUALITY. What It Is and How to Get It

LTRC Seminar - Building Quality Pavements QUALITY. What It Is and How to Get It LTRC Seminar - Building Quality Pavements QUALITY What It Is and How to Get It LTRC Seminar - Building Quality Pavements Quality in General What is it? Who s Quality? How do we get it? LTRC Seminar - Building

More information

FIELD IMPLEMENTATION OF PERFORMANCE RELATED SPECIFICATIONS. T.H.E. Conference Sarah Kilroy, P.E. February 28, 2017

FIELD IMPLEMENTATION OF PERFORMANCE RELATED SPECIFICATIONS. T.H.E. Conference Sarah Kilroy, P.E. February 28, 2017 FIELD IMPLEMENTATION OF PERFORMANCE RELATED SPECIFICATIONS T.H.E. Conference Sarah Kilroy, P.E. February 28, 2017 1 2 $2.5 billion of capital program 62 miles of roadway Western section completed in 2014

More information

Concrete Office Updates Spring MEO Meeting Maria Masten April 19, 2012

Concrete Office Updates Spring MEO Meeting Maria Masten April 19, 2012 Concrete Office Updates 2012 Spring MEO Meeting Maria Masten April 19, 2012 Concrete Mix Designs Do you still want to receive copies of MnDOT mix concrete mix designs? 2012 Special Provisions 2461.4D7

More information

Make copies of all test results and control charts readily available to the Engineer at the project site.

Make copies of all test results and control charts readily available to the Engineer at the project site. 5.2.7.4 CONCRETE: CONTRACTOR S QUALITY CONTROL PLAN NOTE: This document is generally written in the imperative mood. The subject, "the Contractor" is implied. Also implied in this language are "shall",

More information

PCC Pavement Mix Proportioning and Strength

PCC Pavement Mix Proportioning and Strength Supplemental Technical Specification for PCC Pavement Mix Proportioning and Strength SCDOT Designation: SC-M-501 (03/08) 1. SCOPE 1.1. This supplemental technical specification describes materials and

More information

Prescription to Performance --The Search for the Holy Grail-- Michael F. Praul, P.E. Construction & Materials Engineer FHWA--Maine

Prescription to Performance --The Search for the Holy Grail-- Michael F. Praul, P.E. Construction & Materials Engineer FHWA--Maine Prescription to Performance --The Search for the Holy Grail-- Michael F. Praul, P.E. Construction & Materials Engineer FHWA--Maine Topics Variability Discuss different types of specifications Discuss Maine

More information

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENT 1098 PROCEDURE FOR ESTIMATING CONCRETE STRENGTH BY THE MATURITY METHOD.

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENT 1098 PROCEDURE FOR ESTIMATING CONCRETE STRENGTH BY THE MATURITY METHOD. STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENT 1098 PROCEDURE FOR ESTIMATING CONCRETE STRENGTH BY THE MATURITY METHOD April 18, 2008 1098.01 Scope 1098.02 Acceptable Applications for using the Maturity

More information

OHD L-54 STANDARD METHOD OF TEST FOR MAKING, CURING, AND TESTING CEMENT-TREATED BASE FIELD SAMPLES

OHD L-54 STANDARD METHOD OF TEST FOR MAKING, CURING, AND TESTING CEMENT-TREATED BASE FIELD SAMPLES STANDARD METHOD OF TEST FOR MAKING, CURING, AND TESTING CEMENT-TREATED BASE FIELD SAMPLES Oklahoma D.O.T. Page 1 of 7 1 SCOPE 1.1 This method covers procedures for making, curing, and testing cylindrical

More information

2016 ACHD Supplemental Specifications to the ISPWC. ACHD QC-QA Procedure

2016 ACHD Supplemental Specifications to the ISPWC. ACHD QC-QA Procedure SECTION 100 General Conditions Add the following: 2016 ACHD Supplemental Specifications to the ISPWC Ada County Highway District Quality Control and Quality Assurance Procedure Definitions Quality Assurance

More information

TABLE 5.1 MINIMUM REQUIRED SAMPLES AND TESTS - PROJECT

TABLE 5.1 MINIMUM REQUIRED SAMPLES AND TESTS - PROJECT S A M P L I N G A N D T E S T I N G 5-54 TABLE 5.1 MINIMUM REQUIRED S AND S - PROJECT Borrow / Embankment 115 Resistance "R" value One per 40,000 m 3 (50,000 yd 3 ) or fraction thereof for qualifying the

More information

SECTION ASPHALT PAVING

SECTION ASPHALT PAVING PART 1 - GENERAL 1.1 DESCRIPTION SECTION 32 12 16 ASPHALT PAVING SPEC WRITER NOTE: Delete or add information between // ---- // and any other items applicable to project. Any item added to the text shall

More information

Extraction and Sieve Analysis ( µm minus) Forming Marshall Specimens, Field Method

Extraction and Sieve Analysis ( µm minus) Forming Marshall Specimens, Field Method 3.56 COLD IN-PLACE RECYCLING 3.56.1 GENERAL This specification covers the requirements for Cold In-Place Recycling (CIR) which consists of reclaiming the existing asphalt pavement; sizing the reclaimed

More information

Quality Management Review. MoDOT Dave Ahlvers P.E. Dennis Brucks P.E. Josh Kincaid P.E.

Quality Management Review. MoDOT Dave Ahlvers P.E. Dennis Brucks P.E. Josh Kincaid P.E. Quality Management Review MoDOT Dave Ahlvers P.E. Dennis Brucks P.E. Josh Kincaid P.E. Quality Management Introduction to Quality Management Dave Ahlvers, P.E. Review of Job Special Provision & Terms Dennis

More information

State of Nevada Department of Transportation Minimum Required Samples and Tests: Project January

State of Nevada Department of Transportation Minimum Required Samples and Tests: Project January M I N I M U M R E Q U I R E D S A M P L E S A N D T E S T S : P R O J E C T J A N U A R Y 2 0 1 8 MATERIAL OR Borrow / Embankment 115 Resistance "R" value One per 50,000 yd 3 or fraction thereof for qualifying

More information

CONSTRUCTION SPECIFICATION FOR COMPACTING

CONSTRUCTION SPECIFICATION FOR COMPACTING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.PROV 501 NOVEMBER 2014 CONSTRUCTION SPECIFICATION FOR COMPACTING TABLE OF CONTENTS 501.01 SCOPE 501.02 REFERENCES 501.03 DEFINITIONS 501.04 DESIGN

More information

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 2015 EDITION

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 2015 EDITION Sheet 1 of 5 KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 2015 EDITION Delete SECTION 403 and replace with the following: SECTION 403 ON GRADE CONCRETE 403.1 DESCRIPTION

More information

DIVISION 7 STRUCTURES

DIVISION 7 STRUCTURES DIVISION 7 STRUCTURES Section 701. PORTLAND CEMENT CONCRETE FOR STRUCTURES 701.01 Description. Proportion structural concrete according to this section for the various grades of concrete required on the

More information

Erect the weighing bins and hoppers on firm foundations to avoid settlement, which might affect the accuracy of the equipment.

Erect the weighing bins and hoppers on firm foundations to avoid settlement, which might affect the accuracy of the equipment. September 1, 2003 CONCRETE MANUAL 5-694.400 BATCHING AND MIXING 5-694.400 5-694.401 CHECKING BATCH PLANT OPERATION Check to ensure accuracy and dependable operation of the proposed equipment and methods

More information

SPECIAL PROVISION Portland Cement Concrete

SPECIAL PROVISION Portland Cement Concrete 1993 Specifications CSJ 0271-16-117 SPECIAL PROVISION 421---040 Portland Cement Concrete For this project, Item 421, Portland Cement Concrete, of the Standard Specifications, is hereby amended with respect

More information

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION 2007

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION 2007 Sheet 1 of 6 KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION 27 SECTION 62 HOT MIX ASPHALT (HMA) CONSTRUCTION (Quality Control/Quality Assurance (QC/QA)) Page

More information

MSCAA /04 ITEM P-219 RECYCLED CONCRETE CRUSHED AGGREGATE BASE COURSE DESCRIPTION MATERIALS

MSCAA /04 ITEM P-219 RECYCLED CONCRETE CRUSHED AGGREGATE BASE COURSE DESCRIPTION MATERIALS 219-1.1 ITEM P-219 RECYCLED CONCRETE CRUSHED AGGREGATE BASE COURSE DESCRIPTION This item consists of a base course composed of crushed recycled concrete aggregate, crushed to meet a particular gradation,

More information

Attachment 10 Detailed Specifications Group IFB (Revised December 8, 2017) Fine and Coarse Aggregates (Statewide)

Attachment 10 Detailed Specifications Group IFB (Revised December 8, 2017) Fine and Coarse Aggregates (Statewide) Attachment 10 Detailed Specifications Group 33700 IFB 23097 (Revised December 8, 2017) Fine and Coarse Aggregates (Statewide) GROUP 33700 FINE AND COARSE AGGREGATES Page 2 of 14 CONTENTS REFERENCES:...

More information

1995 METRIC CSJ SPECIAL SPECIFICATION ITEM 3014 QUALITY CONTROL/QUALITY ASSURANCE OF ASPHALT BINDERS FOR BITUMINOUS MIXTURES

1995 METRIC CSJ SPECIAL SPECIFICATION ITEM 3014 QUALITY CONTROL/QUALITY ASSURANCE OF ASPHALT BINDERS FOR BITUMINOUS MIXTURES 1995 METRIC CSJ 0447-01-043 SPECIAL SPECIFICATION ITEM 3014 QUALITY CONTROL/QUALITY ASSURANCE OF ASPHALT BINDERS FOR BITUMINOUS MIXTURES 1. DESCRIPTION. THIS ITEM SHALL GOVERN FOR QUALITY CONTROL AND QUALITY

More information

DRAFT ITEM GP-100 ITEM GP-100 CONTRACTOR QUALITY CONTROL PROGRAM 1.1 GENERAL

DRAFT ITEM GP-100 ITEM GP-100 CONTRACTOR QUALITY CONTROL PROGRAM 1.1 GENERAL 1.1 GENERAL When the specification requires a Contractor Quality Control Program, the Contractor shall establish, provide, and maintain an effective Quality Control Program that details the methods and

More information

INDIANA. So how do you make hot mix asphalt? Basics of HMA Pavement Performance. Basics of a Good Road Hot Mix Asphalt Pavement Materials Selection

INDIANA. So how do you make hot mix asphalt? Basics of HMA Pavement Performance. Basics of a Good Road Hot Mix Asphalt Pavement Materials Selection Basics of a Good Road Hot Mix Asphalt Pavement Materials Selection Presented at 2004 Road School By M. Dudley Bonte March 10, 2004 Basics of HMA Pavement Performance Appropriate Specifications Adequate

More information

2003 SPECIFICATIONS SECTION 301 DIVISION 300 BASES AND GRANULAR SURFACES

2003 SPECIFICATIONS SECTION 301 DIVISION 300 BASES AND GRANULAR SURFACES 2003 SPECIFICATIONS SECTION 301 DIVISION 300 BASES AND GRANULAR SURFACES SECTION 301 LIME TREATED SUBGRADE 301.01 GENERAL (a) Control of Materials. As with all materials incorporated into a project, the

More information

CONSTRUCTION SPECIFICATION FOR COLD IN-PLACE RECYCLING

CONSTRUCTION SPECIFICATION FOR COLD IN-PLACE RECYCLING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 333 NOVEMBER 2003 CONSTRUCTION SPECIFICATION FOR COLD IN-PLACE RECYCLING TABLE OF CONTENTS 333.01 SCOPE 333.02 REFERENCES 333.03 DEFINITIONS 333.04

More information

*Originating pavement shall be in accordance with FRICTION SURFACE AGGREGATE (D1), the most recently dated.

*Originating pavement shall be in accordance with FRICTION SURFACE AGGREGATE (D1), the most recently dated. IL-4.75 Schaumburg Surface Friction Course: This work shall consist of constructing a 4.75 mm Hot- Mix Asphalt (HMA) surface friction course. Minimum lift thickness of this material shall be 1.0 inch.

More information

SECTION PORTLAND CEMENT CONCRETE PAVEMENT. All subsurface utilities must be inspected, tested, and accepted prior to any paving.

SECTION PORTLAND CEMENT CONCRETE PAVEMENT. All subsurface utilities must be inspected, tested, and accepted prior to any paving. SECTION PORTLAND CEMENT CONCRETE PAVEMENT 1. DESCRIPTION This specification shall govern for the construction of Portland cement concrete pavement on a prepared subgrade or base course, in accordance with

More information

Construction Specification 62 Grouted Rock Riprap

Construction Specification 62 Grouted Rock Riprap Construction Specification 62 Grouted Rock Riprap 1. Scope The work consists of furnishing, transporting, and the installation of grouted rock riprap revetments and blankets, including filter or bedding

More information

Bituminous Percent Within Tolerance (PWT)

Bituminous Percent Within Tolerance (PWT) Bituminous Percent Within Tolerance (PWT) March 30 April 1, 2015 What Does PWT Drive? Strict adherence to producing the job mix formula Strict adherence to field density spec. requirements Advantages of

More information

REINFORCED CONCRETE CULVERT STORM DRAIN AND SEWER PIPE FIELD SECTION 1026

REINFORCED CONCRETE CULVERT STORM DRAIN AND SEWER PIPE FIELD SECTION 1026 (Page 1 of 8) REINFORCED CONCRETE CULVERT STORM DRAIN AND SEWER PIPE FIELD SECTION 1026 1026.1 SCOPE. To establish procedures for the inspection of reinforced concrete pipe and the approval of modified

More information

APPENDIX D ANSWERS TO STUDY QUESTIONS/PROBLEMS

APPENDIX D ANSWERS TO STUDY QUESTIONS/PROBLEMS APPENDIX D ANSWERS TO STUDY QUESTIONS/PROBLEMS Chapter 2 Quality Assurance Program Questions 1. What determines the lot size for a specified material accepted under the Statistical QA Program? B. The discretion

More information

Aggregate Specifications

Aggregate Specifications Qualified Aggregate Technician Kentucky Specifications Aggregate Specifications State, FHWA, FAA, Contractor Kentucky Transportation Cabinet 107 Aggregate Size Designations Nominal Maximum Size The largest

More information

LABORATORY TESTING SECTION. Method of Test for DETERMINATION OF ASPHALT CONTENT AND GRADATION OF BITUMINOUS MIXTURES BY THE IGNITION METHOD

LABORATORY TESTING SECTION. Method of Test for DETERMINATION OF ASPHALT CONTENT AND GRADATION OF BITUMINOUS MIXTURES BY THE IGNITION METHOD Commonwealth of Pennsylvania PA Test Method No. 757 Department of Transportation 13 Pages 1. SCOPE LABORATORY TESTING SECTION Method of Test for DETERMINATION OF ASPHALT CONTENT AND GRADATION OF BITUMINOUS

More information

SPECIAL PROVISION TO SPECIAL SPECIFICATION Quality Control/Quality Assurance of Hot Mix Asphalt

SPECIAL PROVISION TO SPECIAL SPECIFICATION Quality Control/Quality Assurance of Hot Mix Asphalt 1993 Specifications CSJ 0018-05-062 SPECIAL PROVISION TO SPECIAL SPECIFICATION 3146--035 Quality Control/Quality Assurance of Hot Mix Asphalt For this project, Special Specification Item 3146, Quality

More information

CHAPTER 2 SIEVE ANALYSIS AND FINENESS MODULUS

CHAPTER 2 SIEVE ANALYSIS AND FINENESS MODULUS CHAPTER 2 SIEVE ANALYSIS AND FINENESS MODULUS Sampling Since the reason for sampling aggregates is to determine the gradation (particle size) of the aggregate, it is necessary that they be sampled correctly.

More information

Low 28 Day Compression Strength NOW WHAT?

Low 28 Day Compression Strength NOW WHAT? 28 Day Concrete Strength - Proactive vs. Reactive PRESENTED TO: MN CONCRETE FORUM JOH N H AU PT - N OVEMBER 8, 2 0 1 7 Low 28 Day Compression Strength NOW WHAT? Preparing for the Concrete Placement Preconstruction

More information