FAA AC 150/ H Draft Principal Changes
|
|
- Asher Sullivan
- 5 years ago
- Views:
Transcription
1 FAA AC 150/ H Draft Principal Changes 2018 Indiana Chapter ACPA Workshop Indianapolis, IN Gary L. Mitchell, P.E. Vice President American Concrete Pavement Association
2 Credits Doug Johnson and Greg Cline FAA pavement engineers Slides based on a presentation Doug Johnson gave at the ACPA Annual Meeting in 2017 Based on collaboration with Doug and Greg during drafting the proposed specification Industry acknowledges their willingness to work with numerous associations
3 Overview Updated References Extensive technical and editorial edits Added New Specs Added payment for Contractor Quality Control Control Strips with most all P specs 501 numerous changes
4 Collaboration with Industry Collaboration with Industry American Concrete Paving Association (ACPA) Airports Consultant Council (ACC) National Stone Sand Gravel Association (NSSGA) Geosynthetic Materials Association (GMA) American Society of Civil Engineers (ASCE) Asphalt Institute (AI)
5 Part 1: General Provisions Section 10 New Definitions Certificate of Analysis (COA) Certificate of Compliance (COC) Modification of Standards (MOS) Contractor Laboratory now Contractors Quality Control (QC)Facilities Laboratory now Quality Assurance (QA)Laboratory
6 Part 2: General Construction Item 100 Contractor Quality Control Program (CQCP) Encouraged for all projects Required >$500K in paving Assure continuous monitoring of quality of materials and production Establish corrective action plans (NEW) Pay Item for CQCP
7 Item C-100
8 Item C-100
9 Contractor Quality Control Program More than test results: Materials, equipment, workmanship, Inspection and QC testing and documentation Corrective Action Plans Plan ahead of what to do when QC & QA criteria not met
10 Control Strips Control Strip all P Specs Earthwork, Aggregates, Surface Courses Demonstrate Material, Equipment and Construction Processes meet requirements of the specification Best interest of everyone
11 Part 3: Sitework P154 Clarified how to use RAP in subbase as well as recycled concrete pavement Control Strip P Lime Treated Subgrade Control Strip to demonstrate materials, equipment and process
12 Part 3: Sitework P156 Cement Treated Subgrade New specification for modification of subgrade P157 [Cement][Lime] Kiln Dust Treated Subgrade Added option for use of either CKD or LKD
13 Part 4: Base Courses P207 Full Depth Reclamation (FDR) Recycled Asphalt Aggregate Base Course New Specification How it will perform f(amt HMA, Condition HMA, Amt Aggregate, Use of Stabilizing Agent) Better P154, Maybe than 209 (if stabilizing agent) Control Strip In response to most common MOS
14 Part 4: Base Courses P Added Table of Required Material Properties P Fraction passing No 200 shall not exceed 2/3 the fraction passing No 40 P Option for Separation Fabric P Control Strip
15 Part 4: Flexible Base Courses P Material Properties in Table Format P Fraction passing No 200 shall not exceed 2/3 the fraction passing the No QC for Gradation by lot Option for Separation Fabric P Control Strip
16 Part 5: Rigid Base Courses P301 Cement Treated Soil-Aggregate Subbase Course New Title P Control Strip P304 Cement Treated Aggregate Base Course (CTB) New title P Control Strip
17 Part 5: Rigid Base Courses P Control Strip P (econocrete) Added option to test thickness by survey P307 Cement Treated Permeable Base Course (CTPB) New specification Size 67 (or 57) aggregate stabilized with cement ~ 1000 ft/day permeability (Model as variable stabilized base in FAARFIELD)
18 Part 7: Rigid Pavement P a Reactivity tests representative of material sources for project 1260 and 1567 may be run concurrent P b Follow ASTM C33 for fine aggregate deleterious No 200 no longer counted toward deleterious Total deleterious limited to 1.0%
19 Part 7: Rigid Pavement P c Engineer selects maximum size aggregate based upon thickness and what is available in area Deleterious Material finer No 200 up to 1.5 if material is dust of fracture Methylene blue or Xray diffraction Max deleterious 3.8% (fracture dust)
20 Part 7: Rigid Pavement P d Combined Aggregate Gradation Contractor submits PCC combined Gradation P Proportions w/c between by weight Slump 2 Slip Form 3 Fixed Form 4 Hand Placement
21 Part 7: Rigid Pavement P Mix Design Generally 3 mix designs Slip Form Fixed Form Hand Placement Contractor selects Air Content needed based upon maximum aggregate size and environmental condition
22 Part 7: Rigid Pavement P Control Strip Initial 250 feet Demonstrate materials, equipment and Construction Process P Equipment Rate of vibration sufficient to consolidate without segregation or voids American Concrete Institute (ACI) 309R
23
24 Part 7: Rigid Pavement P Limitations on Mixing and Placing ACI 306R Cold Weather Concreting ACI 305R Hot Weather Concreting Temperature Management Program FHWA HIPERPAV 3 Example of TMP P Placing concrete Rate of vibration sufficient to consolidate without segregation, voids or vibrator trails Excessive edge slump remove area the full width of the slip form lane
25 P Joints vertical alignment Part 7: Rigid Pavement Tie and dowel bars within ¼ per foot Dowels in hardened concrete Spalling beyond grout retension ring must modify equipment and operations reapply curing compound after sawing joints. P Finishing Straightedge testing QC
26 Part 7: Rigid Pavement P Repair, removal or replacement of slabs How bad is bad Shrinkage cracks < 1/3 slab depth cleaned and repaired with high molecular weight methacrylate (HMWM) or expoxy resin in presence of engineer Cracks > 1/3 slab in interior remove and replace Spalls < ½ slab < 25% joint length Spall repair payment for that slab reduced by 5% Grinding over 50% of slab 5% reduction in payment
27 Part 7: Rigid Pavement P Contractor Quality Control Gradation Moisture Slump Air Unit Weight and Yield Temperature Smoothness
28 Part 7: Rigid Pavement P Control Charts Fine and Coarse Aggregate Gradation Slump and Air Combined Gradation CF and WF
29 Part 7: Rigid Pavement
30 Part 7: Rigid Pavement P Corrective Action CQCP shall indicate appropriate action P Acceptance Sampling and Testing Samples transported in molds Curing by immersion (after 24 hours) P Lot Size 2000 cubic yards Sublots equal cubic yards
31 Part 7: Rigid Pavement P Acceptance Criteria Strength Thickness Grade Profiograph Adjustments for Repairs P Payment Rejected PCC may stay in place at 50% pay with concurrence of Engineer and FAA
32
AC 15/ H UPDATE
FAA Airport Construction Guide Specifications AC 15/5370-10H UPDATE Gary L. Mitchell, P.E. Vice President Airports Acknowledgement Doug Johnson Greg Cline Why Update Scheduled 3 5 years Update References
More informationCONSTRUCTION SPECIFICATION FOR CONCRETE PAVEMENT AND CONCRETE BASE
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 350 MARCH 1998 CONSTRUCTION SPECIFICATION FOR CONCRETE PAVEMENT AND CONCRETE BASE 350.01 SCOPE 350.02 REFERENCES 350.03 DEFINITIONS TABLE OF CONTENTS
More informationKeys to Success. for Airfield Concrete Paving ICPA 53 rd Annual Concrete Paving Workshop Altoona, Iowa
Keys to Success for Airfield Concrete Paving 2017 ICPA 53 rd Annual Concrete Paving Workshop Altoona, Iowa Gary L. Mitchell, P.E. Vice President American Concrete Pavement Association Attaining Expectations
More informationPavement Update Track: Engineering
Pavement Update Track: Engineering 2017 ACC Airports Technical Workshop June 21-22, 2017 Arlington, VA Gregory D. Cline, P.E. FAA Airport Engineering AAS-100 gregory.cline@faa.gov (202) 267-8814 Pavement
More informationCONCRETE PAVEMENT THE INSPECTORS PERSPECTIVE. SWIFT 2015 Workshop - Chris Olidis, P.Eng.
CONCRETE PAVEMENT THE INSPECTORS PERSPECTIVE SWIFT 2015 Workshop - Chris Olidis, P.Eng. PRESENTATION OUTLINE Quality management Concrete pavement distress Select types of premature deterioration What to
More informationAirfield Concrete Mixture Optimization
Airfield Concrete Mixture Optimization SWIFT Conference Calgary, Alberta Gary L. Mitchell, P.E. Director of Airports and Pavement Technology Aknowledgement John R. Anderson, Ph.D., P.E. 4 Lawn Street Oviedo,
More informationMatthew W. Singel, PE
Matthew W. Singel, PE RCC is No Slump No reinforcing steel No finishing Consolidated with vibratory rollers Concrete pavement placed in a different way! What Is RCC? Which Sample is RCC? RCC Pavement Usage
More informationMinnesota Concrete Flatwork Specifications for Local Government Agencies
Minnesota Concrete Flatwork LTAP Concrete Flatwork Specifications Mn Concrete Flatwork Specifications for Local MN Concrete Flatwork Agencies Approved for use on Local Government Agency Projects and State
More informationOPTIMIZED GRADATION FOR CONCRETE PAVING MIXTURES BEST PRACTICES WORKSHOP
OPTIMIZED GRADATION FOR CONCRETE PAVING MIXTURES BEST PRACTICES WORKSHOP 1 Concrete 101 Outline Optimized Gradation Why should I care? What is it? Historical Perspective Best Practices Conclusions 2 Concrete
More informationRaising the Quality Bar- Everyone Wins!
Quality in the Concrete Paving Process Raising the Quality Bar- Everyone Wins! Jim Grove, PE Federal Highway Administration/Global Consulting Inc. Office of Infrastructure Virginia Concrete Conference
More informationSECTION RIGID PAVEMENT. 1. Portland Cement Concrete (PCC) pavement. 2. Section Aggregate Base Course.
SECTION 02750 RIGID PAVEMENT PART 1 GENERAL 1.1 SUMMARY A. Section Includes: 1. Portland Cement Concrete (PCC) pavement. B. Related Sections: 1.2 REFERENCES 1. Section 02315 Excavation. 2. Section 02721
More informationITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS
ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS 6.1 DESCRIPTION This work shall consist of constructing curbs, gutters, sidewalks, ramps, local depressions and driveways of the form and dimensions shown
More informationSECTION RIGID PAVEMENT
SECTION 02750 PART 1 GENERAL RIGID PAVEMENT 1.1 SUMMARY A. Section Includes: 1. Concrete sidewalks. 2. Concrete stair steps. 3. Concrete integral curbs gutters. 4. Concrete parking areas and roads. B.
More informationBest Practices for Airfield Concrete Pavement Design and Construction
Best Practices for Airfield Concrete Pavement Design and Construction Presented to: Summer Winter Integrated Field Technologies (SWIFT) Conference Banff, Alberta Gary L. Mitchell, P.E. Vice President Airports
More informationPervious Pavement Placement
Pervious Pavement Placement Test Panel - Prior to Placement Prior to construction, test panel(s) shall be placed and approved by the Architect/Engineer. 1. The contractor shall place a test panel of at
More informationMSCAA /04 ITEM P-219 RECYCLED CONCRETE CRUSHED AGGREGATE BASE COURSE DESCRIPTION MATERIALS
219-1.1 ITEM P-219 RECYCLED CONCRETE CRUSHED AGGREGATE BASE COURSE DESCRIPTION This item consists of a base course composed of crushed recycled concrete aggregate, crushed to meet a particular gradation,
More informationIntegrated Pavement Solutions
Integrated Pavement Solutions 1 Product Solutions for Every Paving Need Application Solution Mainline highways Commercial airports General aviation airports PCC pavement Heavy-duty industrial Concrete
More informationSECTION ASPHALT PAVING
SECTION 321216 ASPHALT PAVING PART 1 - GENERAL 1.1 SUMMARY A. Section Includes: 1. Hot-mix asphalt paving. 1.2 PRE-INSTALLATION MEETINGS A. Pre-installation Conference: Conduct conference at Project site.
More information150/ G Versus 150/ H Contractor Quality Control Program
AC 150/5370-10G AC 150/5370-10H 1 Part 1 of General Provisions Part 2 of General Construction Items 2 Section 100 Item C-100 3 Quality Control Program (CQCP) 4 100-01 General. When the specification requires
More informationPrescription to Performance --The Search for the Holy Grail-- Michael F. Praul, P.E. Construction & Materials Engineer FHWA--Maine
Prescription to Performance --The Search for the Holy Grail-- Michael F. Praul, P.E. Construction & Materials Engineer FHWA--Maine Topics Variability Discuss different types of specifications Discuss Maine
More informationSECTION CONCRETE CURBS, GUTTERS AND SIDEWALKS
SECTION 32 16 13 CONCRETE CURBS, GUTTERS AND SIDEWALKS PART 1 GENERAL 1.1 DESCRIPTION A. Scope: 1. CONTRACTOR shall provide all labor, materials, equipment, and incidentals as shown, specified, and required
More informationROAD COMMISSION FOR OAKLAND COUNTY SPECIAL PROVISION FOR QUALITY CONTROL AND ACCEPTANCE OF PORTLAND CEMENT CONCRETE
ROAD COMMISSION FOR OAKLAND COUNTY SPECIAL PROVISION FOR QUALITY CONTROL AND ACCEPTANCE OF PORTLAND CEMENT CONCRETE RCOC/CONST:SH/JO PAGE 1 OF 9 a. Description. This special provision establishes Portland
More informationA. Texas Department of Transportation 2004 Standard Specifications for Construction and Maintenance of Highways, Streets and Bridges (TxDOT).
SECTION 32 01 16 ASPHALT OVERLAY PART 1 - GENERAL 1.1 SCOPE OF WORK A. This Section specifies the requirements for scarifying, grinding, sweeping and repair of existing asphalt concrete pavement to establish
More informationFULL DEPTH RECLAMATION. FDR Candidates STABILIZER DESIGN. Benefits. Benefits LOCAL ROADS PROGRAM What is Full Depth Reclamation (FDR)?
FULL DEPTH RECLAMATION Presented to: LOCAL ROADS PROGRAM 2012 What is Full Depth Reclamation (FDR)? Full Depth Reclamation is a pavement rehabilitation technique in which the full flexible pavement section
More informationGaining a Better Understanding of FAA and Military Airport Pavement Specifications
Gaining a Better Understanding of FAA and Military Airport Pavement Specifications May 19 th, 2015 Gary L. Mitchell P.E. Vice President Airports and Pavement Technology American Concrete Pavement Association
More information1. Concrete pavers, with ungrouted joints, over sand base. a. Large precast sections in random mix with smaller concrete pavers
SECTION 32 14 00 - PART 1 - GENERAL 1.01 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specifications Sections, apply
More informationB. Reinforcing. Materials shall be as specified in Section 2000 Concrete or as indicated on the plans.
SECTION 1400 - CONCRETE PAVEMENT 1401 SCOPE. This section governs the furnishing of all labor, equipment, tools, and materials and the performance of all work necessary to construct concrete pavement.
More informationCITY OF LETHBRIDGE SECTION INFRASTRUCTURE SERVICES Page 1 of 7 GRANULAR BASE PREP
INFRASTRUCTURE SERVICES Page 1 of 7 1.0 GRANULAR BASE AND SUB-BASE 1.1 DESCRIPTION.1 This section specifies requirements for supplying, producing, hauling placing and compacting processed gravel or quarried
More informationConstruction Specification 62 Grouted Rock Riprap
Construction Specification 62 Grouted Rock Riprap 1. Scope The work consists of furnishing, transporting, and the installation of grouted rock riprap revetments and blankets, including filter or bedding
More information2. Determine Random Numbers: Determine random numbers for testing locations using the Probing, Coring, Texture and MIT-SCAN T2 Report.
JOB GUIDE CONCRETE PAVING INSPECTION 1. Review Contract and Plans: Obtain plans and special provisions and study them in detail. Attend the pre-construction meeting. Attend the pre-paving meeting. 2. Determine
More informationStanford University Facilities Design Guidelines SECTION ASPHALT UNIT PAVING. A. ASTM C-33 Standard Specification for Concrete Aggregates.
SECTION 32 14 23 ASPHALT UNIT PAVING PART 1 GENERAL 1.1 DESCRIPTION Work Included: All labor, materials, appliances, tools, equipment, facilities, transportation, and services for and incidental to performing
More informationUNIVERSITY SERVICES ANNEX James Madison University Harrisonburg, Virginia State Project Code: Architect s Project Number:
SECTION 321610 - CURBING PART 1 - GENERAL 1.1 DESCRIPTION A. This Section specifies requirements for furnishing and installing all types of curbing including the following: granite curb, concrete and bituminous
More informationSECTION PORTLAND CEMENT CONCRETE PAVEMENT. All subsurface utilities must be inspected, tested, and accepted prior to any paving.
SECTION PORTLAND CEMENT CONCRETE PAVEMENT 1. DESCRIPTION This specification shall govern for the construction of Portland cement concrete pavement on a prepared subgrade or base course, in accordance with
More information(STRUCTURAL CONCRETE).
S-1 REVISED SCHEDULE OF MATERIALS CONTROL FOR CERTIFIED READY-MIX CONCRETE PLANT PRODUCTION NEW WRITE-UP 02/11/19 DO NOT REMOVE THIS NEW WRITE-UP DATE. IT NEEDS TO STAY IN FOR THE CONTRACTORS. Always use
More informationITEM 252 IN-PLACE FULL DEPTH COLD FLEXIBLE PAVEMENT RECYCLING
AFTER NOVEMBER 1, 2008 ITEM 252 IN-PLACE FULL DEPTH COLD FLEXIBLE PAVEMENT RECYCLING 252.1 Description. This work shall consist of a stabilized base course composed of a mixture of the existing bituminous
More information9 Concrete Pavement Patching
9 Concrete Pavement Patching Materials Concrete Mix Design Concrete Mix Criteria Trial Batch Demonstration of CMD Acceptance Removal of Concrete Partial Depth Patches Full Depth Patched Placement of Patching
More informationHow to Select the Appropriate Pavement Rehabilitation Option. David Rettner, PE American Engineering Testing, Inc.
1 How to Select the Appropriate Pavement Rehabilitation Option David Rettner, PE American Engineering Testing, Inc. 2 Pavement Rehabilitation Selection Understanding the Problem 3 Pavement Assessment Pavement
More informationConstruction Specification for Concrete Bus Pad
Engineering & Construction Services Division Standard Specifications for Road Works TS 3.41 June 2017 for Concrete Bus Pad Table of Contents SCOPE... 3 REFERENCES... 3 DEFINITIONS... 3 DESIGN AND SUBMISSION
More informationCONSTRUCTION SPECIFICATION FOR CONCRETE ROAD BASE
CITY OF TORONTO STANDARD CONSTRUCTION SPECIFICATIONS FOR ROADS TS 3.40 November 2009 CONSTRUCTION SPECIFICATION FOR CONCRETE ROAD BASE INDEX TS 3.40.01 SCOPE... 3 TS 3.40.02 REFERENCES... 3 TS 3.40.03
More information2003 SPECIFICATIONS SECTION 501 DIVISION 500 RIGID PAVEMENT
2003 SPECIFICATIONS SECTION 501 DIVISION 500 RIGID PAVEMENT SECTION 501 PORTLAND CEMENT CONCRETE PAVEMENT 501.01 GENERAL. This item consists of constructing a concrete pavement (with or without reinforcement)
More informationMICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR QUALITY CONTROL AND ACCEPTANCE OF STRUCTURAL PRECAST CONCRETE
MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR QUALITY CONTROL AND ACCEPTANCE OF STRUCTURAL PRECAST CONCRETE STR:MJF 1 of 8 APPR:JFS:POJ:01-04-19 FHWA:APPR:01-10-19 a. Description. The Contractor
More informationMaria Masten, PE MnDOT Concrete Engineer. Research Pays Off September 20, 2016
Maria Masten, PE MnDOT Concrete Engineer Research Pays Off September 20, 2016 Durability Materials Workmanship Smoothness What the travelling public cares about Prescriptive Thinking outside the prescriptive
More informationCITY OF SAN ANGELO ITEM 360 CONCRETE PAVEMENT
ITEM 360 360.1. DESCRIPTION. CITY OF SAN ANGELO ITEM 360 This item shall govern for the construction of Portland Cement Concrete pavement with or without monolithic curbs on a prepared subgrade or sub-base
More informationSection CONCRETE SIDEWALKS. 1. Payment for concrete sidewalks is on square foot basis.
PART 1 GENERAL 1.01 SUMMARY A. This Section includes the following: Section 02775 1. Reinforced concrete sidewalks. 2. Wheelchair Ramps. 1.02 MEASUREMENT AND PAYMENT A. Unit Prices. 1. Payment for concrete
More informationArlington County, VA Materials Testing Specification Reference Guide (8/18/2016) MATERIAL AND TEST (REF. - VDOT TEST METHODS MANUAL )
MINIMUM RATE 1. Embankments SOILS AND AGGREGATES (a) Density, 303.04(h) One (1) test per 2500 yd3 or less plus: (a) for fills less than 500 ft. length one (1) test on every other 6-in. layer bottom to
More informationArlington County, VA Materials Testing Specification Reference Guide (8/18/2016) MATERIAL AND TEST (REF. VDOT TEST METHODS MANUAL )
1. Embankments SOILS AND AGGREGATES (a) Density, 303.04(h) One (1) test per 2500 yd3 or less plus: (a) for fills less than 500 ft. length one (1) test on every other 6-in. layer bottom to top of fill starting
More information1.02 RELATED WORK: Refer to the following sections for related work:
SECTION 4200 - CONCRETE STRUCTURES PART 1 - GENERAL 1.01 SCOPE: This Section covers installation of header curb, retaining walls, energy dissipation structures for drainage channels, reinforced concrete
More informationWorkshop Introduction
Quality in the Concrete Paving Process Workshop Introduction Module 8-21 Instructors Dennis Dvorak Jim Grove Mike Praul FHWA Resource Center (708) 283-3542 dennis.dvorak@dot.gov ATI Inc. / FHWA Office
More informationCONSTRUCTION SPECIFICATION FOR CONCRETE CURB AND GUTTER SYSTEMS
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 353 NOVEMBER 2006 CONSTRUCTION SPECIFICATION FOR CONCRETE CURB AND GUTTER SYSTEMS TABLE OF CONTENTS 353.01 SCOPE 353.02 REFERENCES 353.03 DEFINITIONS
More informationMICHIGAN DEPARTMENT OF TRANSPORTATION
MICHIGAN DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR OPEN-GRADED DRAINAGE COURSE, MODIFIED FOR JOB NUMBER 110616 (PORTLAND CEMENT-TREATED PERMEABLE BASE USING CRUSHED CONCRETE) CFS:JFS 1 of 5 APPR:ARB:TES:11-06-14
More informationSECTION CAST IN PLACE CONCRETE FOR FLOOR SLABS ON GRADE THAT WILL RECEIVE SEMI-PERMEABLE OR IMPERMEABLE FLOOR FINISHES
GUIDE SPECIFICATION SECTION CAST IN PLACE CONCRETE FOR FLOOR SLABS ON GRADE THAT WILL RECEIVE SEMI-PERMEABLE OR IMPERMEABLE FLOOR FINISHES PART 1 - SCOPE 1.01 WORK INCLUDED: 1.1.1 This guide covers the
More informationSECTION CAST-IN-PLACE CONCRETE
SECTION 03300 CAST-IN-PLACE CONCRETE PART 1 GENERAL 1.01 SUMMARY A. Furnish equipment, materials, and labor required for the supply, casting, finishing, curing, and testing of cast-in-place concrete, as
More informationA. Provide all labor, materials, and equipment as necessary to complete all work as indicated on the Drawings and specified herein.
PAGE 321216-1 SECTION 321216 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification sections,
More information3.70 Portland Cement Concrete Pavement - End Product Specification TABLE OF CONTENTS
3.70 Portland Cement Concrete Pavement - End Product Specification TABLE OF CONTENTS 3.70.1 GENERAL 3.70.1.1 Description 3.70.1.2 Definitions 3.70.1.2.1 Acceptance Limits 3.70.1.2.2 Bridge Construction
More informationFAA Update: Construction Materials Engineering and Testing. Past, Present, Possibilities, & Probabilities
FAA Update: Construction Materials Engineering and Testing Past, Present, Possibilities, & Probabilities Standards for Specifying Construction of Airports ACIL 2013 Policies & Practices Conference March
More informationMethod of Test For In-Place Density of Treated and Untreated Soils and Aggregates
Rev. 04-12-17 Aggregates and Soils T102H T103G T104D T106B T107B T108C T111D T112F T115D T116A T200E T203G T206G T209C T210J T211J& T212J T224C T227I T228C T230D T235B Method of Test For In-Place Density
More informationSECTION CONTROLLED LOW STRENGTH MATERIAL
SECTION 03300 CONTROLLED LOW STRENGTH MATERIAL PART 1 GENERAL 1.1 DESCRIPTION A. This Section specifies Controlled Low Strength Material (CLSM) to be used as described in this specification, including
More informationMix Design Issues for. In-Place Recycling Products
CIR Definition Mix Design Issues for Cold in-place recycling (CIR) is the on-site recycling process to a typical treatment depth of 3 to 5 inches, using a train of equipment (tanker trucks, milling machines,
More informationSpecial Provision No. 335S03 April 2015
COLD IN-PLACE RECYCLED EXPANDED ASPHALT MIX Item No. Special Provision No. 335S03 April 2015 Amendment to OPSS 335, November 2009 OPSS 335, November 2009, Construction Specification for Cold In-Place Recycling
More informationConcrete Pavement Preservation Partial Depth Repairs
Concrete Pavement Preservation Partial Depth Repairs National Concrete Pavement Technology Center North Dakota Ready Mix and Concrete Products Association Dan Frentress P.E. IGGA 1 Partial-Depth Repair
More informationOPTIMIZED 3/4" GRADATION LIGHTWEIGHT AGGREGATE REPORT
OPTIMIZED 3/4" GRADATION LIGHTWEIGHT AGGREGATE REPORT PREPARED BY: JODY WALL, P.E. DIRECTOR OF RESEARCH AND DEVELOPMENT CAROLINA STALITE COMPANY RESEARCH LAB GOLD HILL, NORTH CAROLINA Optimized 3/4" Gradation
More informationGeneral Information for Joints
Design Manual Chapter 5 - Roadway Design 5G - PCC Pavement Joints 5G-1 General Information for Joints A. General Information The need for a jointing system in concrete pavements results from the desire
More informationCONSTRUCTION SPECIFICATION FOR CONCRETE BARRIERS
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 553 FEBRUARY 1991 CONSTRUCTION SPECIFICATION FOR CONCRETE BARRIERS 553.01 SCOPE 553.02 REFERENCES 553.03 DEFINITIONS TABLE OF CONTENTS 553.04 SUBMISSION
More informationA. Texas Department of Transportation 2004 Standard Specifications for Construction and Maintenance of Highways, Streets and Bridges (TxDOT).
SECTION 32 12 16 ASPHALT CONCRETE PAVING PART 1 GENERAL 1.1 SCOPE OF WORK A. This Section specifies the requirements for placing a hot laid plant mix asphalt surface course upon either an asphalt stabilized
More informationCONSTRUCTION SPECIFICATION FOR CONCRETE UNIT PAVERS
CITY OF TORONTO STANDARD CONSTRUCTION SPECIFICATIONS FOR ROADS TS 3.80 November 2010 CONSTRUCTION SPECIFICATION FOR CONCRETE UNIT PAVERS INDEX TS 3.80.01 SCOPE... 2 TS 3.80.02 REFERENCES... 2 TS 3.80.03
More informationASPHALTIC CONCRETE PAVING SECTION
SECTION 31 50 00 PART 1: GENERAL 1-01 SECTION INCLUDES: A. Asphaltic concrete paving. B. Seal Coat. 1-02 RELATED SECTIONS: A. Division 31 Earthwork B. Section 31 60 00 Aggregate Base Course. C. Section
More informationRigid Pavement Design
Rigid Pavement Design FAARFIELD 1.3 Workshop New Rigid Example Set-Up Create a new section in job PROJECT by dragging section NewRigid in Samples to PROJECT. Presented to: VI ALACPA Airport Pavements Seminar
More informationSECTION CAST-IN-PLACE CONCRETE
SECTION 03300 CAST-IN-PLACE CONCRETE PART 1 GENERAL 1.01 SUMMARY A. Furnish equipment, materials, and labor required for the supply, casting, finishing, curing, and testing of cast-in-place concrete, as
More informationSPECIAL SPECIFICATION 2042 Decorative Colored Pattern Concrete Paving
2004 Specifications CSJ 0196-02-120 SPECIAL SPECIFICATION 2042 Decorative Colored Pattern Concrete Paving 1. Description. This Item shall govern for the furnishing and placing of colored concrete wave
More informationDusit Roongsang, P.E. Presented at. PNWS AWWA Conference Bellevue, WA May 1, 2015
Dusit Roongsang, P.E. Presented at PNWS AWWA Conference Bellevue, WA May 1, 2015 Not waterproof structures Leakage rate is suitable for intended use Contain water Prevent contamination of contents Prevent
More informationSTATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 888 PORTLAND CEMENT CONCRETE PAVEMENT USING QC/QA.
STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 888 PORTLAND CEMENT CONCRETE PAVEMENT USING QC/QA April 15, 2011 888.01 General 888.02 Materials 888.03 Concrete Proportioning 888.04
More informationRigid Overlay Design. FAARFIELD 1.3 Workshop. Federal Aviation Administration
Rigid Overlay Design FAARFIELD 1.3 Workshop Presented to: IX ALACPA Seminar on Airport Pavements Ciudad de Panamá, Panamá By: David R. Brill, P.E., Ph.D. Date: September 13, 2012 FAARFIELD Overlay Design
More informationLONG TERM PAVEMENT PERFORMANCE PROGRAM DIRECTIVE. Program Area: General Operations Directive Number: GO-09. Date: September 14, 1998 Supersedes: S-2
LONG TERM PAVEMENT PERFORMANCE PROGRAM DIRECTIVE For the Technical Direction of the LTPP Program Program Area: General Operations Directive Number: GO-09 Date: September 14, 1998 Supersedes: S-2 Subject:
More informationItem P-219 Recycled Concrete Aggregate Base Course
Item P-219 Recycled Concrete Aggregate DESCRIPTION 219-1.1 This item consists of a base course composed of recycled concrete aggregate, crushed to meet a particular gradation, constructed on a prepared
More informationSECTION INTERLOCKING PRECAST CONCRETE UNIT PAVERS
SECTION 321413.13 INTERLOCKING PRECAST CONCRETE UNIT PAVERS PART 1 - GENERAL 1.1 SUMMARY A. This Section includes the following: 1. Interlocking concrete paver units. 2. Sand setting bed. 3. Sand joint
More informationDIVISION 2400 CONCRETE
DIVISION 2400 CONCRETE SECTION 2405 CAST-IN-PLACE CONCRETE PART 1 - GENERAL 1.01 SCOPE This section covers cast-in-place concrete, including, joints, reinforcing steel, forms, finishing, curing, weather
More informationDIVISION 4400 CONCRETE
DIVISION 4400 CONCRETE SECTION 4405 CAST-IN-PLACE CONCRETE PART 1 - GENERAL 1.01 SCOPE This section covers cast-in-place concrete, including, joints, reinforcing steel, forms, finishing, curing, weather
More informationFULL DEPTH RECLAMATION
FULL DEPTH RECLAMATION PART 1 - GENERAL 1.01 SECTION INCLUDES Full depth reclamation of asphalt roadways 1.02 DESCRIPTION OF WORK Includes pulverizing and mixing of existing asphalt and underlying materials;
More informationSECTION CONCRETE PAVING
PART 1 GENERAL 1.1 SECTION INCLUDES SECTION 32 13 13 CONCRETE PAVING A. Extent of concrete curbs, walks, and paving as show on drawings B. Earthwork and prepared sub-base C. Concrete and related materials
More informationComparison of Airport Paving Specification Requirements in Canada & USA
Comparison of Airport Paving Specification Requirements in Canada & USA Ludomir Uzarowski, Ph.D., P.Eng. Rabiah Rizvi, P.Eng. Golder Associates Ltd., Ontario, Canada Susan Tighe, Ph.D., P.Eng., University
More information2003 SPECIFICATIONS SECTION 301 DIVISION 300 BASES AND GRANULAR SURFACES
2003 SPECIFICATIONS SECTION 301 DIVISION 300 BASES AND GRANULAR SURFACES SECTION 301 LIME TREATED SUBGRADE 301.01 GENERAL (a) Control of Materials. As with all materials incorporated into a project, the
More informationAsphalt Guidelines. Courtney Rousseau, P.E. Lloyd Consulting Group, LLC
Asphalt Guidelines Courtney Rousseau, P.E. Lloyd Consulting Group, LLC Objectives Review typical asphalt sections and other key components to ensure optimal material usage for your project Review hot mix
More informationTECHNICAL SPECIFICATION
TECHNICAL SPECIFICATION ITEM 00252 IN-PLACE FULL DEPTH COLD FLEXIBLE PAVEMENT RECYCLING 252.1 Description. This work shall consist of a stabilized base course composed of a mixture of the existing bituminous
More informationSECTION 434 HIGH PERFORMANCE CONCRETE (HPC)
SECTION 434 HIGH PERFORMANCE CONCRETE (HPC) 434.01 DESCRIPTION. This work shall consist of the construction of portland cement concrete deck slabs, headblocks, bridge sidewalks, unsurfaced bridge approach
More informationStanford University Facilities Design Guidelines SECTION Pervious Concrete Paving
SECTION 32 13 43 Pervious Concrete Paving PART 1 GENERAL 1.1 RELATED WORK Current Caltrans Standard Specification Sections A. SECTION 31 10 00 Site Preparation B. SECTION 31 00 00 Earthwork C. SECTION
More informationConcrete Overlays. ACPA Pennsylvania Chapter. ACPA Pennsylvania Chapter. Versatile & Sustainable Solutions. Reasons to Consider a Concrete Overlay
Overlays February 22, 2012 ACPA Pennsylvania Chapter Overlays John M. Becker, P.E. ACPA Penn Chapter February 22, 2012 One of 25 state paving associations affiliated with ACPA National Comprised of approximately
More informationBeyond Water-Cement Ratio and Strength. Patrick Harrison Vice President Structural Services, Inc.
Beyond Water-Cement Ratio and Strength Patrick Harrison Vice President Structural Services, Inc. High compressive strengths Low water/cementitious ratios Low slump Water Coarse Cement Fine Concrete
More informationINDIANA. So how do you make hot mix asphalt? Basics of HMA Pavement Performance. Basics of a Good Road Hot Mix Asphalt Pavement Materials Selection
Basics of a Good Road Hot Mix Asphalt Pavement Materials Selection Presented at 2004 Road School By M. Dudley Bonte March 10, 2004 Basics of HMA Pavement Performance Appropriate Specifications Adequate
More informationSECTION ASPHALTIC CONCRETE PAVING
SECTION 02742 ASPHALTIC CONCRETE PAVING PART 1 GENERAL 1.1 SUMMARY A. Includes But Not Limited To 1. Prepare pavement sub-grade as described in Contract Documents to receive pavement base and paving. 2.
More informationPAVEMENT CONSTRUCTION QA PROCEDURES RIDEABILITY TESTING CONSTRUCTION PRACTICE
PAVEMENT CONSTRUCTION QA PROCEDURES RIDEABILITY TESTING CONSTRUCTION PRACTICE Quality Assurance is not Quality Control Quality control is Contractors responsibility during construction. Quality Assurance
More informationLITHOCRETE ARCHITECTURAL CONCRETE PAVING
LITHOCRETE ARCHITECTURAL CONCRETE PAVING PART 1 GENERAL 1.1 GENERAL CONDITIONS A. Requirements of "General Conditions of the Contract" and of Division 1, "General Requirements," apply to work in this Section
More informationWould You Like Concrete With Little or No Shrinkage, Cracking, and Curling??? We Will Focus on:
Would You Like Concrete With Little or No Shrinkage, Cracking, and Curling??? We Will Focus on: Coarse Aggregates Admixtures Including Shrinkage Reducing and Shrinkage Compensating Admixtures Evaporation
More informationSPECIFICATIONS FOR BRIDGE CONSTRUCTION SECTION 17 ASPHALT CONCRETE PAVEMENT General Materials
SPECIFICATIONS FOR BRIDGE CONSTRUCTION SECTION 17 ASPHALT CONCRETE PAVEMENT TABLE OF CONTENTS 17.1 General...17-1 17.2 Materials...17-1 17.3 Asphalt Mix Design...17-1 17.4 Sampling and Testing...17-2 17.5
More informationSECTION ASPHALT INTERLAYER REINFORCEMENT SYSTEM. Display hidden notes to specifier by using Tools / Options / View / Hidden Text.
SECTION 02979 ASPHALT INTERLAYER REINFORCEMENT SYSTEM QuickTime and a TIFF (Uncompressed) decompressor are needed to see this picture. Display hidden notes to specifier by using Tools / Options / View
More informationRegional Engineers. Jack A. Elston
Regional Engineers Jack A. Elston Special Provision for Hot-Mix Asphalt Pay for Performance Using Percent Within Limits Jobsite Sampling April 20, 2018 This special provision was developed by the Bureau
More informationSpecial Provision No. 399S43 July This Special Provision deletes and replaces the following specifications:
FAST TRACK FULL DEPTH CONCRETE REPAIR Item No. FULL DEPTH CONCRETE REPAIR Item No. PARTIAL DEPTH CONCRETE REPAIR Item No. FAST TRACK PARTIAL DEPTH CONCRETE REPAIR Item No. Special Provision No. 399S43
More informationPERMEABLE INTERLOCKING PAVERS
PERMEABLE INTERLOCKING PAVERS PART 1 - GENERAL 1.01 SECTION INCLUDES A. Subgrade Preparation B. Placement of Storage Aggregate C. Placement of Filter Aggregate D. Placement of Bedding Course E. Placement
More informationSpecial Provision No. 399F02 January 2017 CONSTRUCTION SPECIFICATION FOR TEMPORARY HOT MIX PAVEMENT
TEMPORARY HOT MIX PAVEMENT - Item No. Special Provision No. 399F02 January 2017 CONSTRUCTION SPECIFICATION FOR TEMPORARY HOT MIX PAVEMENT 1.0 SCOPE This Special Provision covers the requirements for the
More informationSECTION ASPHALT PAVING
PART 1 - GENERAL 1.1 DESCRIPTION SECTION 32 12 16 ASPHALT PAVING SPEC WRITER NOTE: Delete or add information between // ---- // and any other items applicable to project. Any item added to the text shall
More information