Liquid Waste Coordination Committee
|
|
- Kerry Strickland
- 6 years ago
- Views:
Transcription
1 Annacis Island Wastewater Treatment Plant Outfall Project Liquid Waste Coordination Committee FOR LWCC BY KEN MASSÉ. 19 JANUARY 2017 Ken Massé, P.Eng. METRO VANCOUVER April 3, 2017 CONTRACTOR INFORMATION SESSION John Newby, P.E. CDM SMITH
2 INTRODUCTIONS Metro Vancouver Project Delivery Division of the Liquid Waste Services Department Ken Massé & Nancy Bonham Purchasing: Gary Mui CDM Smith (Design Engineering Consultant) John Newby Hatch (Construction Manager) Tim Langmaid, 2
3 AGENDA Metro Vancouver Project rational, requirements and overview Permitting & property Project details, construction challenges Insurance, bonding, safety requirements Pre-qualification Schedule Questions 3
4 METRO VANCOUVER REGIONAL DISTRICT Annacis Outfall Project 4
5 Annacis Island Wastewater Treatment Plant 5
6 Existing Outfall
7 Existing Outfall 7
8 REQUIREMENTS FOR THE NEW OUTFALL 1. Capacity to discharge 25.3 m 3 /s 2. Dilution ratio of 20:1 in the river at slack tide 3. Remain operational after an earthquake ( Post-disaster performance level) 8
9 Chlorine Contact Tanks Diffuser Manifold 9
10 Launch Shaft 10
11 SEISMIC RESILIENCY New Stage 5 Clarifiers 11
12 Post-Disaster Bypass Conduit to Outfall (PDBCO) PDBCO New Stage 5 Clarifiers 12
13 Post-Disaster Bypass Conduit to Outfall (PDBCO) Deep, tunneled section PDBCO New Stage 5 Clarifiers Shallow buried section 13
14 The Outfall Construction Contract 14
15 REGULATORY & PERMITTING ISSUES Port of Vancouver Ministry of Environment (MoE) Ministry of Forest, Lands & Natural Resources Operations (FLNRO) Department of Fisheries & Oceans (DFO) Transport Canada Corporation of Delta Environment and Climate Change Canada 15
16 DISPOSAL AT SEA Contractor may opt to dispose the dredged material at sea Requires permit from ECCC (contractor to obtain) Permit requires sampling of the sediment prior to dredging MV conducting the sediment sampling 16
17 PROPERTY & RIGHT OF WAY Launch Shaft and Future Effluent Pump Stn Property Purchase 17
18 Design Decisions / Drivers Hydraulic gradient River bathymetry and geomorphology Seismic ground displacements Minimize impacts on the surrounding community 18
19 Project Setting 19
20 Annacis Island WWTP Setting 20
21 Subsurface Conditions 21
22 Diffuser Location Fraser River Setting Navigation Channel 22
23 Diffuser Location River Bathymetry and Geomorphology 23
24 Diffuser Location 24
25 Maximum Minimum Actual Fisheries Closure Fraser River Flow 25
26 Fraser River Currents 26
27 Item Elevation GD (m) Chart Datum Description Chlorine Contact Tanks Maximum Stage VIII water surface elevation in CCTs Design River Stage Design river level, 200-yr peak winter flood level High Water High water datum at Alex Fraser Bridge Geodetic Datum (GD) CVD28GVRD Geodetic Datum Chart Datum Per Port of Vancouver; varies +/ m across area Dredging Grade Navigation channel minimum depth +/ m Dredging Subgrade Maintenance dredging elevation +/ m Elevations / Water Depth 27
28 Project Elements 28
29 Project Main Elements CCTs / Level Control Structure Effluent Shaft and Effluent Tunnel PDBCO Shaft and PDBCO Tunnel Outfall Shaft and Outfall Tunnel Riser Shaft and River Diffuser Future Effluent Pump Station 29
30 Overview of System Hydraulics 30
31 Level Control Structure 31
32 Click here to view animation : 32
33 Click here to view animation: 33
34 Level Control Structure Gate Details 34
35 Treatment Plant Shafts 35
36 Shaft Details Outfall Shaft Serves as tunnel launch shaft 16 m final ID; m deep 3.75 m thick base slab Effluent and PDBCO Shafts Serve as tunnel receiving shafts 7 m final ID; m deep 2.25 m thick base slab 36
37 Shaft Excavation Support Water-tight (No GW drawdown allowed) Independent of permanent structure Slurry wall technology (assumed) ~ 1,220 by 3,000 mm panels 56.5 m total panel depth Contractor options: Alternate support technologies Larger ID (> finished ID + 2 m) 37
38 Excavation and Base Slab Excavation Method In the Dry Slurry wall depth selected for base stability Contractor to confirm suitability for alternate technology Contingency plan for tremie method, if conditions require Base Slab / Breakout Structure Base slab reinforced with shear key into slurry walls Launch shaft design includes breakout structure External 12+ m ground improvement zone around tunnel alignment 38
39 Final Lining and Top Structure Reinforced Concrete Lining 1.0 m thick Additional 1.5 m thick dividing wall in Outfall Shaft Top Structure Level control structure above Effluent Shaft + pile support Buried conduit connection on PDBCO Shaft Pre-cast Panels on Outfall Shaft for future pump station 39
40 Conveyance Tunnels 40
41 Tunnels Tunnel Dimensions 4.2 m finish ID Effluent Tunnel (220 m) PDBCO Tunnel (410 m) Outfall Tunnel (580 m) TBM Requirements Pressurize face (EPB or SPB) New or manufacturer reconditioned Allow for some oversize for machine selection 41
42 Tunneling Ground Conditions Fraser River Sands Flowing ground conditions w/ unsupported face Face pressure / excavation volume control critical EPB: Muck conditioning to control and for minimizing tool wear/abrasion SPB: Slurry line and plant sand removal critical, wear/abrasion significant Deformation Monitoring / Geotechnical Instrumentation Structural settlement monitoring in advance of construction Surface settlement points Multi-point borehole extensometers Utility monitoring points 42
43 Precast Segmental Lining Concrete segments 254 mm (10 in.) thick by 1,510 mm (5 ft.) Drawings present preliminary design Contractor to prepare final design for means and methods Secondary Lining Typically first 30 m from shafts, maybe longer in Outfall Tunnel 3,820 mm ID; 25.4 mm thick w/ 50 mil PE lining Tunnel weld one-side with backing plate 43
44 River Riser and Diffuser 44
45 Riser and Diffuser 45
46 River Riser Requirements Safe Haven for tunnel completion Resistance to lateral forces Seal against water pressure Temporary excavation support Independent of permanent structure Drawings prepared assuming combi-wall technology Contract to allow for contractor selection of alternate Must provide separation of internal work area from river 46
47 Click here to view animation: 47
48 Diffuser Pipeline Pipeline Requirements Accommodate post-disaster deformation Buried in river bed with armor rock protection Installation Requirements Shop assembly in sections (welding / PE coating) Installed in sections (bolted flanges) Clam shell dredging At-sea or on-land disposal Contractor options to limit dredging / back fill 48
49 Dredge Prism 49
50 Diffuser Riser Cross Section 50
51 Existing Outfall 51
52 Existing Outfall Will continue to serve as influent emergency bypass Cleaning and repair Installation of duckbill ports 52
53 Construction Area 53
54 Outfall Contract Construction Site Limits 54
55 2019 Construction Site Plan 55
56 Site Preparation Contract Site Preparation Building demolition Utility relocation Gravel surfacing Construction Power On-Site 2 MVA power substation (12.4 kv and 600 V) Contractor provided generation (diesel or natural gas) for TBM 56
57 Site Access Tunnels, Outfall Shaft, Effluent Shaft Truck access via Derwent Way and Eaton Place Worker parking near north access gate PDBCO Shaft Truck access via Cliveden Avenue and Eaton Way River Riser and Diffuser Barge access via Fraser River Off-site staging/assembly/parking provided by contractor 57
58 2.0 PDBCO Shaft 3.4 Acres Tunnel Launch Shaft Site Limits 58
59 Riser and Diffuser Construction Site Limits 59
60 Excavation and Dredge Spoil On-Land Sites Disposal via truck to contractor selected land-disposal site Native soil and groundwater analytical data provided in contract Other disposal site requirements to be met by contractor River Riser and Diffuser Site Disposal via barge to at-sea or offloading/land-disposal site Native dredge material analytical data provided in contract Other disposal site requirements to be met by contractor 60
61 Schedule 61
62 Design and Tender Schedule Q1 2017: 60% Design Complete Q3 2017: RFQ Issued Q3 2017: 90% Design Complete Q1 2018: 100% Design Complete, RFP Issued, Site preparation start Q4 2018: Site preparation complete Q1 2019: New Outfall System contract NTP 62
63 Construction Schedule 63
64 INSURANCE REQUIREMENTS Commercial General Liability (CGL) Insurance for at least $10 million per occurrence (including coverage for underground shaft and tunnel work, and in-river work) additional insureds: Greater Vancouver Sewerage and Drainage District, Metro Vancouver Regional District, Vancouver Fraser Port Authority, Her Majesty the Queen in right of Canada, Southern Rail of British Columbia 64
65 INSURANCE Continued Automobile Liability Insurance - $5 million per occurrence Contractor s Pollution Liability Insurance - $5 million per occurrence or claim (additional insureds as in the CGL insurance) Marine Liability Insurance - $5 million per occurrence (additional insureds as in the CGL insurance) Course of Construction Insurance - For the dollar value of the contract Contractor s Equipment Insurance (including tunnel boring equipment) 65
66 BONDING REQUIREMENTS Bid Bond 10% of the dollar value of the tender price Performance Bond - 50% of the dollar value of the contract Labour and Materials Bond - 50% of the dollar value of the contract 66
67 WORKSAFE BC REQUIREMENTS Must be a registered employer Clearance Letter Prime Contractor designation 67
68 PRE-QUALIFICATION Contractors to demonstrate experience & qualifications in: Tunneling and Shafts in similar conditions Marine works of similar scope Request of Qualifications (RFQ) ~ Q Target completion of pre-qualification process ~ Q
69 REQUEST FOR PROPOSALS Pre-qualified contractors will be invited to submit proposals Evaluated on technical and financial criteria RFP Late Q Target for Notice to Proceed: Early Q
70 GENERAL CONDITIONS & RISK Metro Vancouver s Standard General Conditions Supplemental Conditions to address tunneling issues such as Differing Site Conditions, Dispute Resolution Board, & Escrow documents RFP will include: Geotechnical Data Report Geotechnical Baseline Report 70
71 QUESTIONS? Outside of today s session, send questions to: Gary Mui, Buyer, Metro Vancouver Purchasing Gary.Mui@metrovancouver.org 71
Special Committee on Bay-Delta Item 3b January 24, 2017
Special Committee on Bay-Delta Item 3b January 24, 2017 January California WaterFix Overview Review Other Mega-Projects Cost Schedule Lessons Learned February Construction Risk Management Special Committee
More informationStevens & Associates, Inc. Tunnel Construction Projects. Fact Sheets
Stevens & Associates, Inc. Tunnel Construction Projects Fact Sheets Stevens & Associates, Inc. 4 Knights Court Newbury, MA 01951 978-764-9886 glen@stevensai.com Massachusetts Water Resources Authority
More informationVTA s BART Silicon Valley Phase II Extension
VTA s BART Silicon Valley Phase II Extension Santa Clara Community Working Group December 3, 2015 1 Agenda Follow-up Items and Work Plan New Starts Project Development & Schedule Update Construction Methods
More information6 Preliminary Assessment of Construction Method and Constructability Issues
6 Preliminary Assessment of Construction Method and Constructability Issues 6.1 Construction Approach Appendix C includes conceptual designs of the alternatives discussed below. Generally, the conceptual
More informationHudson River Tunnels, Mega Projects, and Risk A Designer s Perspective
Purdue Geotechnical Society Workshop Digging Deep April 8, 2011 Hudson River Tunnels, Mega Projects, and Risk A Designer s Perspective David Chapman, P.E. Lachel & Associates, Inc. Morristown, NJ Hudson
More informationRehoboth Beach Effluent Disposal Study. Evaluation of Wastewater Discharge Alternatives. Center for the Inland Bays STAC Meeting January 13, 2006
Rehoboth Beach Effluent Disposal Study Evaluation of Wastewater Discharge Alternatives Center for the Inland Bays STAC Meeting January 13, 2006 1 Agenda Background Objectives/Goals Land Search Discharge
More informationVulnerability of Metro Vancouver Wastewater Infrastructure to Climate Change
Vulnerability of Metro Vancouver Wastewater Infrastructure to Climate Change Andrew Boyland, P.Eng. Kerr Wood Leidal Associates Arash Masbough, M.A.Sc., PMP, P.Eng. Associated Engineering Today s Presentation
More informationKiewit Approach for Tunnel Stabilization and Sewer Pipeline Replacement Project
South Coast Water District Kiewit Approach for Tunnel Stabilization and Sewer Pipeline Replacement Project Board of Directors January 14-15, 2013 Overview of Construction Plan Highlights of Kiewit s Construction
More informationUPDATE ON THE WATERFIX TUNNELS PROJECT. Breakthroughs in Tunneling September 2018
UPDATE ON THE WATERFIX TUNNELS PROJECT Breakthroughs in Tunneling September 2018 PRESENTATION OVERVIEW Need for WaterFix Proposed Facilities Tunnel Design Challenges Engaging Innovation Current Status
More informationFebruary 7, Purpose. Background. the BDCP. needs the project. Discussion. Facilities 1. plants) 1, October 1, 2013,
February 7, 2014 Attention: Imported Water Committee Bay-Delta Conservation Plan: Infrastructu ure Review.. (Discussion) Purpose The purpose of this memo is to provide an assessment off the Bay-Delta Conservation
More informationCONSTRUCTION SPECIFICATION FOR PIPELINE INSTALLATION BY TUNNELLING
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 415 NOVEMBER 2013 CONSTRUCTION SPECIFICATION FOR PIPELINE INSTALLATION BY TUNNELLING TABLE OF CONTENTS 415.01 SCOPE 415.02 REFERENCES 415.03 DEFINITIONS
More informationTake Me to the Other Side:
Take Me to the Other Side: The Importance of Trenchless Crossings in Routing Water Supply Transmission Brooke Barry, E.I.T., Mark Havekost, P.E. 2014 HDR, all rights reserved. PURPOSE: Develop an additional
More informationVTA s BART Silicon Valley Phase II Extension
VTA s BART Silicon Valley Phase II Extension Downtown-Diridon Community Working Group December 1, 2015 1 Agenda Follow-up Items and Work Plan New Starts Project Development & Schedule Update Construction
More informationAPPENDIX 8-A. Valued Component Selection Rationale
APPENDIX 8-A Valued Component Selection Rationale This page is intentionally left blank A list of candidate s was compiled based on issues identified through the scoping process described in Section 8.1.2
More informationPipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.
Pipe Jacking/Microtunnelling Dr. Mark Knight Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo 1 New Installations New Installations Non-Steering Methods Steering Methods
More informationDesign and Implementation of the South Hartford CSO Tunnel
Design and Implementation of the South Hartford CSO Tunnel Brian Canterbury, P.E., AECOM James Sullivan, P.E., AECOM Andrew Perham, The Metropolitan District The Metropolitan District NEWEA January 22,
More informationDESIGN OF TEMPLETON OVERPASS FOR THE CANADA LINE. Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng.,P.Eng., SNC-Lavain Inc.
DESIGN OF TEMPLETON OVERPASS FOR THE CANADA LINE Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng.,P.Eng., SNC-Lavain Inc. Roger Woodhead, PhD, P.Eng., SNC-Lavain Inc. Paper prepared for
More informationPushing the Envelope For 100 Years
Pushing the Envelope For 100 Years Tunneling under the Chesapeake Bay The Parallel Thimble Shoal Highway Tunnel Presented by: Kevin Abt, PE Chesepeake Bay Bridge and Tunnel District Mike Kling, PE, PTOE
More informationExperts in tunneling with Tunnel Boring Machines
www.eurohinca.com www.terratest.es Experts in tunneling with Tunnel Boring Machines info@eurohinca.com EUROHINCA Europea de Hincas Teledirigidas, S.A., EUROHINCA, was incorporated in 1996 for the execution
More informationPhysical Works Terms of Reference
Peace Project Water Use Plan Physical Works Terms of Reference District of Mackenzie Effluent Discharge Feasibility and Design Study GMSWORKS #28a 23 November 2009 Terms of Reference for the Peace Water
More informationAn Introduction to. By Michael L. Schumaker, P.E. An Introduction to Shaner Industries Metal Foundation System
An Introduction to Metal Foundation System By Michael L. Schumaker, P.E. Introduction Various types of deep foundations are routinely used to support structures. Selection of the appropriate type of deep
More informationDFI DEEP FOUNDATIONS. Aerial View of a Flood Control Project in San Juan, Puerto Rico: An OPA Finalist F E
U N DAIONS IN O F P D DFI S I U DP FOUNDAIONS Mar/Apr 2012 he Magazine of the Deep Foundations Institute Aerial View of a Flood Control Project in San Juan, Puerto Rico: An OPA Finalist op slab construction
More informationAPPENDIX J ENVIRONMENTAL STUDIES
APPENDIX J ENVIRONMENTAL STUDIES J.2: Co structio E iro e tal Ma age e t Pla A acis Isla d WWTP Ne Outfall Syste Va cou er Fraser Port Authority Project a d E iro e tal Re ie Applicatio This page intentionally
More informationWESTRIDGE MARINE TERMINAL UPGRADE AND EXPANSION PROJECT APPLICATION TO VANCOUVER FRASER PORT AUTHORITY
WESTRIDGE MARINE TERMINAL IN WATER EXCAVATION REPORT WESTRIDGE MARINE TERMINAL UPGRADE AND EXPANSION PROJECT APPLICATION TO VANCOUVER FRASER PORT AUTHORITY Trans Mountain Pipeline ULC Kinder Morgan Canada
More informationSTANDARD SPECIFICATIONS SECTION BORING AND JACKING. A. Section includes requirements for boring and jacking casing pipe.
STANDARD SPECIFICATIONS SECTION 02445 BORING AND JACKING PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for boring and jacking casing pipe. 1.2 DEFINITIONS A. Carrier Pipe: Sewer or water
More informationImmersed Tunnels. Richard Lunniss and Jonathan Baber. CRC Press. Taylor & Francis Group. Taylor & Francis Group, A SPON BOOK
Immersed Tunnels Richard Lunniss and Jonathan Baber CRC Press Taylor & Francis Group Boca Raton London New York CRC Press is an imprint of the Taylor & Francis Group, an informa business A SPON BOOK Contents
More informationAlternative Construction Methods and Pipe Material provide Solutions for Cleveland WWTP Project
Alternative Construction Methods and Pipe Material provide Solutions for Cleveland WWTP Project Bernie Ashyk 1, Christopher Lucie, P.E. 2, Jeffrey LeBlanc, P.E. 3 1 Shook Walbridge JV, Project Manager;
More informationAppendix J Effluent Pump Station
Appendix J Effluent Pump Station TECHNICAL MEMORANDUM Salmon Creek Treatment Plant Effluent Pump Station Hydraulics and Phasing Analysis for the Phase 5A Project Columbia River Outfall and Effluent Pipeline
More informationJohn Hart Generating Station Replacement Project. December January 2014 Community Construction Update Report #8
John Hart Generating Station Replacement Project December 2013 - January 2014 Community Construction Update Report #8 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 steve.watson@bchydro.com
More informationHampton Roads Bridge Tunnel Expansion: Overview of Tunnel Construction Methods
Hampton Roads Bridge Tunnel Expansion: Overview of Tunnel Construction Methods February 21, 2018 James S. Utterback HRBT Project Director Virginia Department of Transportation Ten Hampton Roads Tunnels
More information3.12 UTILITIES Introduction Environmental Setting
3.12 UTILITIES 3. Affected Environment and Environmental Analysis 3.12 UTILITIES 3.12.1 Introduction This section addresses the potential for impacting public utilities within the Port, the Main Channel,
More informationCONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION BY JACKING AND BORING
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 416 NOVEMBER 2013 CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION BY JACKING AND BORING TABLE OF CONTENTS 416.01 SCOPE 416.02 REFERENCES
More informationLower San Joaquin River Feasibility Study PLAN FORMULATION ADDENDUM
PLAN FORMULATION ADDENDUM Non-Structural Measure Descriptions Elevate Critical Infrastructure This measure would raise at-risk critical structures above the design inundation level. Elevation would be
More informationSoft Ground Tunneling through Contaminated Groundwater
5 th Annual Technical Forum GEOHAZARDS IN TRANSPORTATION IN THE APPALACHIAN REGION Soft Ground Tunneling through Contaminated Groundwater Nasri Munfah P.E. and Subal Sarkar P.E. Parsons Brinckerhoff, New
More informationEAST CENTRAL REGIONAL WATER RECLAMATION FACILITY PROCESS WATER SYSTEM PROJECT
EAST CENTRAL REGIONAL WATER RECLAMATION FACILITY PROCESS WATER SYSTEM PROJECT Addendum No. 2 Attachment B Contract Document Revisions Specifications: TABLE OF CONTENTS ADDENDUM NO. 2 Attachment B Contract
More informationITEM 432 TUNNEL CONSTRUCTION
AFTER MARCH 1, 2012 ITEM 432 TUNNEL CONSTRUCTION 432.1 Description. This Item shall govern for tunnel lines under railroads, state highways, and concrete paved streets or other obstructions indicated.
More informationDry structural excavation is usually done with front-end loaders, bulldozers or backhoes.
1.1 Excavation - General Excavation is the removal of all material (including ice, water, etc.) required for the construction of foundations or substructures as indicated on the drawings or as determined
More informationCONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION BY JACKING AND BORING
ONTARIO PROVINCIAL STANDARD SPECIFICATION OPSS.MUNI 416 NOVEMBER 2018 (Formerly OPSS 416, November 2013) Note: The MUNI implemented in November 2018 replaces OPSS 416 COMMON, November 2013 with no technical
More informationGilmerton Bridge Replacement Project Virginia Society of Professional Engineers (VSPE) March 27, 2013
1 Gilmerton Bridge Replacement Project Virginia Society of Professional Engineers (VSPE) March 27, 2013 PRESENTERS: Marc Papini Parsons Brinckerhoff, Project Manager Jim Holtje, P.E. PCL Civil Constructors,
More informationCapital Expenditure Summary
Capital Expenditure Summary UTILITIES COMMITTEE PRESENTATION Frank Huber DIRECTOR, MAJOR PROJECTS, MANAGEMENT SYSTEMS AND UTILITY SERVICES WATER SERVICES July 12, 2018 http://orbit.gvrd.bc.ca/orbit/llisapi.dll/properties/25601136
More informationRFP Questions and Answers 1 (Pre-Bid Meeting)
RFP 40860 Questions and Answers 1 (Pre-Bid Meeting) Amendment to Page 8 of 99 of the Proposal for RFQ 40860 to change from 120 days stated to 270 days for completion of project. Clarifications of drawings:
More informationEvergreen Line Rapid Transit Project
Evergreen Line Rapid Transit Project Burnaby, Port Moody, and Coquitlam, BC Completed in December 2016 Canadian Consulting Engineering Awards 2017 Project Category: B. Transportation Canadian Consulting
More informationGEOTECHNICAL INVESTIGATION PROPOSED OUTFALL LOCATION CITY OF MORGAN S POINT DRAINAGE HARRIS COUNTY, TEXAS REPORT NO
GEOTECHNICAL INVESTIGATION PROPOSED OUTFALL LOCATION CITY OF MORGAN S POINT DRAINAGE HARRIS COUNTY, TEXAS REPORT NO. 1140198001 Reported to: SIRRUS ENGINEERS, INC. Houston, Texas Submitted by: GEOTEST
More informationCity of Columbus Wet Weather Management Plan Update. Dax J. Blake, P.E. Administrator City of Columbus, Ohio Division of Sewerage and Drainage
City of Columbus Wet Weather Management Plan Update Dax J. Blake, P.E. Administrator City of Columbus, Ohio Division of Sewerage and Drainage City of Columbus, Ohio Population served ~ 1 Million 22 satellite
More information204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES
SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES 204.1 DESCRIPTION Excavate for the structures as shown in the Contract Documents. Unless specified otherwise, backfill the completed structures to the
More informationEsquimalt Graving Dock Waterlot Remediation Mega-Site (Phase 1B): Design, Contracting, and Construction Challenges
Esquimalt Graving Dock Waterlot Remediation Mega-Site (Phase 1B): Design, Contracting, and Construction Challenges Presented by Dan Berlin and Tom Wang, Anchor QEA, LLC Andrew Mylly and Rae-Ann Sharp,
More informationPAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV
NORTH SHORE CONNECTOR TUNNELS AND STATION SHELL LIGHT RAIL PROJECT PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV North Shore Connector Alignment 7300 lf Extension to existing 25 mile system 18 Contracts $435
More informationProposed Maplewood Marine Restoration Project Discussion guide and feedback form
Vancouver Fraser Port Authority Habitat Enhancement Program Proposed Maplewood Marine Restoration Project Discussion guide and feedback form Public consultation September 24 October 12, 2018 Feedback form
More informationREPORT. ~bhot s ford. f~.j./ ;\11SSJ{)11 \\';trc r & Scwer' S c f\'icc ~
~bhot s ford f~.j./ ;\11SSJ{)11 \\';trc r & Scwer' S c f\'icc ~ REPORT To: Abbotsford/Mission Water Sewer Commission (WSC) From : Tony Seibert, P.Eng., Wastewater Project Engineer Date: April 8, 2011 Subject:
More informationAmendment to OPSS 416 (Nov 2013) Construction Specification for Pipeline and Utility Installation by Jacking and Boring
Engineering & Construction Services Division Standard Specifications for Sewers and Watermains TS 416 September 2017 Amendment to OPSS 416 (Nov 2013) Construction Specification for Pipeline and Utility
More informationThermal and Hydro Power Plant Maintenance Deer Island Treatment Plant
Massachusetts Water Resources Authority Presentation to MWRA Board of Directors Thermal and Hydro Power Plant Maintenance Deer Island Treatment Plant March 12, 2014 On-Site Thermal/Power Plant Built in
More informationIEEE 18-May Intake. Tunnel. Outlet
IEEE 18-May-2011 Intake Tunnel Outlet 1 Increase water diversion capacity at the Sir Adam Beck complex by 500 m 3 /s (+27%) Increase average annual energy output at the Sir Adam Beck complex by 1.6 billion
More informationczc= r&:ob ;0_ City of Richmond Report to Committee J2f J2( ""'"::::>
City of Richmond Report to Committee To: From: Public Works and Transportation Committee John Irving, P.Eng. MPA Director, Engineering Date: August 25, 2017 File: 10-6060-03-01/2017- Vol 01 Re: Metro Vancouver
More informationKing County Uses Trenchless Methods to Construct a Large Siphon Under Seattle s Ship Canal
North American Society for Trenchless Technology (NASTT) NASTT s 2013 No-Dig Show Sacramento, California March 3-7, 2013 TA-T1-03 King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle
More informationB.4 Preliminary Feasibility Cost Estimate
B.4 Preliminary Feasibility Estimate Introduction This section presents preliminary feasibility-level cost estimates for NODOS/Sites Reservoir Project Alternatives A, B, C, and D, described in Section
More informationMisan University - College of Engineering Civil Engineering Department
CHAPTER 2 Soil and Excavations Soil investigation including two phases: surface investigation and subsurface investigation Surface investigation involves making a preliminary judgment about the site s
More informationSEMMERING BASE TUNNEL LOGISTIC CHALLENGES
SEMMERING BASE TUNNEL LOGISTIC CHALLENGES Dipl.-Ing. Michael Proprenter ic consulenten ZT GmbH Vienna, Austria Mail: m.proprenter@ic-group.org Dipl.-Ing. Oliver K. Wagner ÖBB - Austrian Federal Railways
More informationTBM Selection and Specification
By Bradford F. Townsend and Paul E. Jenkins Date: 13 June 2009 TBM Selection - Challenges to be met TBM Technology Auxiliary Measures and Backup New Developments Summary of Selection Process Procurements
More informationRegulation 18 August 2009 NO Operations and Maintenance LEVEE ENCROACHMENT STANDARDS AND PROCEDURES
CENWP-EC DEPARTMENT OF THE ARMY PDR 30-2-5 Portland District, Corps of Engineers (Draft) P.O. Box 2946 Portland, Oregon 97208 Regulation 8 August 2009 NO. 30-2-5 Operations and Maintenance LEVEE ENCROACHMENT
More informationChallenges and results of Using hand mining to tunnel the mcalpine creek relief sewer
96 th Annual NC AWWA-WEA Conference Chuck Shue, PE McKim & Creed, Inc. Senior Project Manager Challenges and results of Using hand mining to tunnel the mcalpine creek relief sewer OUTLINE Project overview
More informationMoncton Watermain Relocation Moncton, New Brunswick. TRS 2010 Dr Mark Knight University of Waterloo
Moncton Watermain Relocation Moncton, New Brunswick TRS 2010 Dr Mark Knight University of Waterloo Presentation Outline Overview of the project Design and construction Issues Trenchless construction Lessons
More informationSECTION DRILLED CONCRETE PIERS AND SHAFTS
SECTION 31 63 29 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply
More informationThe last update was March 4, 2016.
From: To: Subject: Date: Long Lake Stewardship longlakesudbury@gmail.com LONG LAKE STEWARDSHIP - Gold Mine Site Reclamation Work - Project Update May 29, 2017 6:14:57 PM Hello - Some of you will remember
More information(#' John Irving, P.Eng. Director, Engineering ( )
City of Richmond Report to Committee To: From: Public Works and Transportation Committee John Irving, P.Eng. MPA Director, Engineering Re: Flood Protection Update 2014 Date: June 23,2014 File: 10-6060-04-01/2014-
More informationUNDERGROUND UTILITY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION
UNDERGROUND UTILITY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION Effective September 9, 2014 The General Trade Knowledge portion of the examination is administered daily in Computer
More informationCOPYRIGHTED MATERIAL. Contents PART ONE: THEORY...1. Preface to the Third Edition xiii. About the Authors xv. Acknowledgements xvii
Preface to the Third Edition xiii About the Authors xv Acknowledgements xvii Contents PART ONE: THEORY...1 1. Groundwater in Construction...3 1.1 Groundwater in the Hydrologic Cycle 3 1.2 Origins of Dewatering
More informationPlessis Road Twinning and Grade Separation at CN Redditt Subdivision: Design Challenges and Innovative Solutions
Plessis Road Twinning and Grade Separation at CN Redditt Subdivision: Design Challenges and Innovative Solutions Tanya D. Worms, P.Eng. M.Sc., Project Manager, M.D. Steele Construction Ltd. Paper prepared
More informationThe work required for this project includes, but is not limited to, the following items, not listed in order of execution.
ESTIMATE OF QUANTITIES SPECIFICATIONS Construction Specifications: South Dakota Standard Specifications for Roads and Bridges, 2004 Edition and Required Provisions, Supplemental Specifications and/or Special
More informationFLOODPLAIN MANAGEMENT STRATEGY FEASIBILITY PLAN. EB3679 February 2011
FLOODPLAIN MANAGEMENT STRATEGY FEASIBILITY PLAN EB3679 February 2011 FLOODPLAIN MANAGEMENT STRATEGY FEASIBILITY PLAN Prepared for: The City of Westminster 511 Royal Avenue Westminster, BC V3L 1H9 Prepared
More informationSTANDARD SPECIFICATIONS SECTION TUNNELING. A. Section includes requirements for constructing tunnels 48-inch and larger diameter.
STANDARD SPECIFICATIONS SECTION 02420 TUNNELING PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for constructing tunnels 48-inch and larger diameter. 1.2 DEFINITIONS A. Carrier Pipe: Sewer
More informationEXPERT PANEL ON DIVERSION PLANNING AND IMPLEMENTATION SEDIMENT DIVERSIONS UPDATE
EXPERT PANEL ON DIVERSION PLANNING AND IMPLEMENTATION SEDIMENT DIVERSIONS UPDATE August 31, 2016 MISSISSIPPI RIVER SEDIMENT DIVERSIONS: PROCESS 2 RECOMMENDATIONS FROM LAST MEETING: BEYOND THE FALL 2015
More informationCONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT
ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 616 NOVEMBER 2008 CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT TABLE OF CONTENTS 616.01 SCOPE 616.02 REFERENCES 616.03
More informationGeo24h. Buiding Service
Geo24h Buiding Service Sheet pile wall metallic and composite Special Foundations Dredging canals, rivers, lakes and quarries Dewatering with wells Wellpoint sistems Types of application The sheet pile
More informationSELECTION OF TUNNEL METHODS. By: Dr. Gary S. Brierley
SELECTION OF TUNNEL METHODS By: Dr. Gary S. Brierley Successful Tunnel Design 2 Produce a satisfactory finished facility for no more money and in no more time than is required for the existing ground conditions.
More informationWell Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E.
Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E. Presentation Outline Project History Project Scope Construction Alternatives Plan
More informationPresented by: Frank Guyamier
FTBA Orlando Tuesday, March 20, 2012 Presented by: Frank Guyamier Project Engineer P3 PROJECT PARTNERS Public Sponsors 90% Equity Partner Design/Build Contractor 10% Equity Partner VMS Operator Federal
More informationCONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL
CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL CS 3-01 GENERAL: A. The foundation, bedding and backfill for all trenches shall conform with the requirements of the City Standard
More informationChapter 3: Permit Procedures and Requirements
Chapter 1: General Provisions 1 1 Short Title 1 2 Jurisdiction 1 3 Amendments and Revisions 1 4 Enforcement Responsibility 1 5 Review Process 1 6 Prior Approval 1 7 Relationship to Other Standards 1 8
More informationSR 710 North Study. Technical Advisory Committee Meeting No. 16 August 13, 2014 Stakeholder Outreach Advisory Committee Meeting No. 12 August 14, 2014
SR 710 North Study Technical Advisory Committee Meeting No. 16 August 13, 2014 Stakeholder Outreach Advisory Committee Meeting No. 12 August 14, 2014 1 1 1 Agenda Public Outreach Activities Project Report
More information2 EARTHWORKS AND GEOTECHNICAL REQUIREMENTS
Section 2 Earthworks and Geotechnical Requirements 2 EARTHWORKS AND GEOTECHNICAL REQUIREMENTS CONTENTS 2 EARTHWORKS AND GEOTECHNICAL REQUIREMENTS... I 2.1 Introduction... 2-1 2.1.1 Objectives... 2-1 2.1.2
More informationTunnelling under the Fraser River at 6 bar Design and Construction of the Port Mann Main Water Supply Tunnel
Tunnelling under the Fraser River at 6 bar Design and Construction of the Port Mann Main Water Supply Tunnel Stephanie Fekete McMillen Jacobs Associates Steve Skelhorn McNally Construction Inc. Tim Langmaid
More informationCHAPTER 11: WALLS.
CHAPTER 11: WALLS MODULAR BLOCK WALL (DRY CAST) Rather than being pre-approved as systems, the components of Modular block walls (dry cast) are pre-approved separately. The approved MBW components are
More informationSPECIFICATION FOR PIPE CULVERT CONSTRUCTION
SPECIFICATION FOR PIPE CULVERT CONSTRUCTION 1. SCOPE Pipe culverts shall be constructed in accordance with this specification and in conformity with the lines, levels and cross-sections shown on the drawings.
More informationDepartment of Administration State Construction Office SITE PREPARATION AND GRADING CRITERIA
Revised May 17, 2011 Department of Administration State Construction Office SITE PREPARATION AND GRADING CRITERIA INTRODUCTION These criteria are established to provide uniform construction practices and
More informationAnswer: Yes additional labor classifications can be added to the Staff and Fee Schedule (Exhibit 2-6). Yes all rates are to be completed.
SOUTH BROOKLYN RESILIENCY PROJECTS Project #6253/ Contract # 62530001 Questions & Answers August 18, 2016 1. Relative to the Staff and Fee Schedule (Exhibit 2-6) - Can we supplement the list of labor classifications
More informationSlurry MTBM in Alluvial Soils and 25k Rock Chris L. Windley, P.E. McKim & Creed Inc. Stephen D. Leitch, P.E. Hazen and Sawyer, P.C. Joshua P.
Slurry MTBM in Alluvial Soils and 25k Rock Chris L. Windley, P.E. McKim & Creed Inc. Stephen D. Leitch, P.E. Hazen and Sawyer, P.C. Joshua P. Farmer, P.E. Hazen and Sawyer, P.C. Project Background City
More informationSPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006
Michigan Department Of Transportation 3703C (11/06) 1 Materials 1.1 Pipe SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Page 1 of 5 The type of pipe used for the pipe jacking method shall be capable
More informationDIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS
DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS Implenia Spezialtiefbau GmbH Robert Bosch Straße 25 D-63225 Langen Phone: +49 6103 988 345 Fax: +49 6103 988 277 Email: info.spezialtiefbau@implenia.com
More informationAll Tunnel Alignment & Option Comparisons. Presented to: BDCP Steering Committee. December 3, 2009 DRAFT
All Tunnel Alignment & Option Comparisons Presented to: BDCP Steering Committee December 3, 2009 Option Comparison Alignment of Options Major Features Comparison Tables Pros & Cons Mitigation Environmental
More informationF. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it.
Section 3 F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it. 3.8 Highway Crossings The design engineer shall, prior to the design of any highway
More informationThe Manitoba Water Services Board SECTION Standard Construction Specifications September 2013 Page 1 of 5
September 2013 Page 1 of 5 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described herein shall consist of the construction of a water intake including: The supply and installation of pipe and appurtenances
More informationPREQUALIFICATION APPLICATION INSTRUCTIONS
PREQUALIFICATION APPLICATION INSTRUCTIONS Please read the following instructions carefully as incomplete applications will not be processed. COMPLETE AND RETURN ALL SECTIONS OF THE APPLICATION PACKAGE.
More informationSEATTLE S BRIGHTWATER UNDERGROUND CONVEYANCE SYSTEM TUNNELING & UNDERGROUND CONSTRUCTION
TUNNELING & UNDERGROUND CONSTRUCTION THE OFFICIAL PUBLICATION OF UCA OF SME WWW.TUCMAGAZINE.COM VOLUME 1 NO 2 JUNE 2007 SEATTLE S BRIGHTWATER UNDERGROUND CONVEYANCE SYSTEM Tunnel Demand Forecast Ground
More informationSECTION 39 - MANHOLES TABLE OF CONTENTS
Section SECTION 39 - MANHOLES TABLE OF CONTENTS Page 39-1 GENERAL... 39.1 39-2 CONCRETE MANHOLES... 39.1 39-2.01 NOT USED... 39.1 39-2.02 Concrete Storm Drain Manholes... 39.1 39-3 SADDLE SEWER MANHOLES...
More informationBILL OF QUANTITY ENGINEERING & MANAGEMENT CONSULTING CENTRE. "Beit Hanoun Emergency Water Supply Project"
"Beit Hanoun Emergency Water Supply Project" " Rehabilitation and Construction of Beit Hanoun Water Network " BILL OF QUANTITY ENGINEERING & MANAGEMENT CONSULTING CENTRE Bill of Quantities PREAMBLE TO
More informationFACSIMILE/ MAIL TRANSMISSION. Date: December 2, 2011 File:
PUAR Engineering Consultants Inc #200-100 Park Royal South W.Vancouver, BC, Canada V7T 1A2 Fax: 604-922-5054; Tel: 604-913-7827 FACSIMILE/ MAIL TRANSMISSION Date: December 2, 2011 File: 07-2-256 To: BRIAN
More informationChange of Coordinating Registered Professional (CRP) or Registered Professional (RP)
January, 2019 BUILDING DIVISION Change of Coordinating Registered Professional (CRP) or Registered Professional (RP) General Information In the event that there is a change of the Coordinating Registered
More information4. FISH PASSAGE CONCEPTS
Feasibility Study for Restoration of Titlow Lagoon Fish Passage South Puget Sound Salmon Enhancement Group 4. FISH PASSAGE CONCEPTS Fish passage could be improved by rehabilitating the existing fish passage,
More informationCLARIFICATIONS TO TECHNICAL SPECIFICATIONS SECTIONS
C-44 Reservoir/STA System Discharge Project RFB: 6000000620 Addendum No. 1 March 2014 CLARIFICATIONS TO TECHNICAL SPECIFICATIONS SECTIONS HDR Engineering, Inc. SECTION 02401 DEWATERING, COFFERDAM AND BYPASS
More informationCost Estimating Framework
Cost Estimating Framework Water and Wastewater Master Study Prepared by: GM BluePlan Engineering for: Project No. 717022 TABLE OF CONTENTS 1 Introduction... 1 2 Cost Estimation Framework... 2 2.1 Approach
More information