Liquid Waste Coordination Committee

Size: px
Start display at page:

Download "Liquid Waste Coordination Committee"

Transcription

1 Annacis Island Wastewater Treatment Plant Outfall Project Liquid Waste Coordination Committee FOR LWCC BY KEN MASSÉ. 19 JANUARY 2017 Ken Massé, P.Eng. METRO VANCOUVER April 3, 2017 CONTRACTOR INFORMATION SESSION John Newby, P.E. CDM SMITH

2 INTRODUCTIONS Metro Vancouver Project Delivery Division of the Liquid Waste Services Department Ken Massé & Nancy Bonham Purchasing: Gary Mui CDM Smith (Design Engineering Consultant) John Newby Hatch (Construction Manager) Tim Langmaid, 2

3 AGENDA Metro Vancouver Project rational, requirements and overview Permitting & property Project details, construction challenges Insurance, bonding, safety requirements Pre-qualification Schedule Questions 3

4 METRO VANCOUVER REGIONAL DISTRICT Annacis Outfall Project 4

5 Annacis Island Wastewater Treatment Plant 5

6 Existing Outfall

7 Existing Outfall 7

8 REQUIREMENTS FOR THE NEW OUTFALL 1. Capacity to discharge 25.3 m 3 /s 2. Dilution ratio of 20:1 in the river at slack tide 3. Remain operational after an earthquake ( Post-disaster performance level) 8

9 Chlorine Contact Tanks Diffuser Manifold 9

10 Launch Shaft 10

11 SEISMIC RESILIENCY New Stage 5 Clarifiers 11

12 Post-Disaster Bypass Conduit to Outfall (PDBCO) PDBCO New Stage 5 Clarifiers 12

13 Post-Disaster Bypass Conduit to Outfall (PDBCO) Deep, tunneled section PDBCO New Stage 5 Clarifiers Shallow buried section 13

14 The Outfall Construction Contract 14

15 REGULATORY & PERMITTING ISSUES Port of Vancouver Ministry of Environment (MoE) Ministry of Forest, Lands & Natural Resources Operations (FLNRO) Department of Fisheries & Oceans (DFO) Transport Canada Corporation of Delta Environment and Climate Change Canada 15

16 DISPOSAL AT SEA Contractor may opt to dispose the dredged material at sea Requires permit from ECCC (contractor to obtain) Permit requires sampling of the sediment prior to dredging MV conducting the sediment sampling 16

17 PROPERTY & RIGHT OF WAY Launch Shaft and Future Effluent Pump Stn Property Purchase 17

18 Design Decisions / Drivers Hydraulic gradient River bathymetry and geomorphology Seismic ground displacements Minimize impacts on the surrounding community 18

19 Project Setting 19

20 Annacis Island WWTP Setting 20

21 Subsurface Conditions 21

22 Diffuser Location Fraser River Setting Navigation Channel 22

23 Diffuser Location River Bathymetry and Geomorphology 23

24 Diffuser Location 24

25 Maximum Minimum Actual Fisheries Closure Fraser River Flow 25

26 Fraser River Currents 26

27 Item Elevation GD (m) Chart Datum Description Chlorine Contact Tanks Maximum Stage VIII water surface elevation in CCTs Design River Stage Design river level, 200-yr peak winter flood level High Water High water datum at Alex Fraser Bridge Geodetic Datum (GD) CVD28GVRD Geodetic Datum Chart Datum Per Port of Vancouver; varies +/ m across area Dredging Grade Navigation channel minimum depth +/ m Dredging Subgrade Maintenance dredging elevation +/ m Elevations / Water Depth 27

28 Project Elements 28

29 Project Main Elements CCTs / Level Control Structure Effluent Shaft and Effluent Tunnel PDBCO Shaft and PDBCO Tunnel Outfall Shaft and Outfall Tunnel Riser Shaft and River Diffuser Future Effluent Pump Station 29

30 Overview of System Hydraulics 30

31 Level Control Structure 31

32 Click here to view animation : 32

33 Click here to view animation: 33

34 Level Control Structure Gate Details 34

35 Treatment Plant Shafts 35

36 Shaft Details Outfall Shaft Serves as tunnel launch shaft 16 m final ID; m deep 3.75 m thick base slab Effluent and PDBCO Shafts Serve as tunnel receiving shafts 7 m final ID; m deep 2.25 m thick base slab 36

37 Shaft Excavation Support Water-tight (No GW drawdown allowed) Independent of permanent structure Slurry wall technology (assumed) ~ 1,220 by 3,000 mm panels 56.5 m total panel depth Contractor options: Alternate support technologies Larger ID (> finished ID + 2 m) 37

38 Excavation and Base Slab Excavation Method In the Dry Slurry wall depth selected for base stability Contractor to confirm suitability for alternate technology Contingency plan for tremie method, if conditions require Base Slab / Breakout Structure Base slab reinforced with shear key into slurry walls Launch shaft design includes breakout structure External 12+ m ground improvement zone around tunnel alignment 38

39 Final Lining and Top Structure Reinforced Concrete Lining 1.0 m thick Additional 1.5 m thick dividing wall in Outfall Shaft Top Structure Level control structure above Effluent Shaft + pile support Buried conduit connection on PDBCO Shaft Pre-cast Panels on Outfall Shaft for future pump station 39

40 Conveyance Tunnels 40

41 Tunnels Tunnel Dimensions 4.2 m finish ID Effluent Tunnel (220 m) PDBCO Tunnel (410 m) Outfall Tunnel (580 m) TBM Requirements Pressurize face (EPB or SPB) New or manufacturer reconditioned Allow for some oversize for machine selection 41

42 Tunneling Ground Conditions Fraser River Sands Flowing ground conditions w/ unsupported face Face pressure / excavation volume control critical EPB: Muck conditioning to control and for minimizing tool wear/abrasion SPB: Slurry line and plant sand removal critical, wear/abrasion significant Deformation Monitoring / Geotechnical Instrumentation Structural settlement monitoring in advance of construction Surface settlement points Multi-point borehole extensometers Utility monitoring points 42

43 Precast Segmental Lining Concrete segments 254 mm (10 in.) thick by 1,510 mm (5 ft.) Drawings present preliminary design Contractor to prepare final design for means and methods Secondary Lining Typically first 30 m from shafts, maybe longer in Outfall Tunnel 3,820 mm ID; 25.4 mm thick w/ 50 mil PE lining Tunnel weld one-side with backing plate 43

44 River Riser and Diffuser 44

45 Riser and Diffuser 45

46 River Riser Requirements Safe Haven for tunnel completion Resistance to lateral forces Seal against water pressure Temporary excavation support Independent of permanent structure Drawings prepared assuming combi-wall technology Contract to allow for contractor selection of alternate Must provide separation of internal work area from river 46

47 Click here to view animation: 47

48 Diffuser Pipeline Pipeline Requirements Accommodate post-disaster deformation Buried in river bed with armor rock protection Installation Requirements Shop assembly in sections (welding / PE coating) Installed in sections (bolted flanges) Clam shell dredging At-sea or on-land disposal Contractor options to limit dredging / back fill 48

49 Dredge Prism 49

50 Diffuser Riser Cross Section 50

51 Existing Outfall 51

52 Existing Outfall Will continue to serve as influent emergency bypass Cleaning and repair Installation of duckbill ports 52

53 Construction Area 53

54 Outfall Contract Construction Site Limits 54

55 2019 Construction Site Plan 55

56 Site Preparation Contract Site Preparation Building demolition Utility relocation Gravel surfacing Construction Power On-Site 2 MVA power substation (12.4 kv and 600 V) Contractor provided generation (diesel or natural gas) for TBM 56

57 Site Access Tunnels, Outfall Shaft, Effluent Shaft Truck access via Derwent Way and Eaton Place Worker parking near north access gate PDBCO Shaft Truck access via Cliveden Avenue and Eaton Way River Riser and Diffuser Barge access via Fraser River Off-site staging/assembly/parking provided by contractor 57

58 2.0 PDBCO Shaft 3.4 Acres Tunnel Launch Shaft Site Limits 58

59 Riser and Diffuser Construction Site Limits 59

60 Excavation and Dredge Spoil On-Land Sites Disposal via truck to contractor selected land-disposal site Native soil and groundwater analytical data provided in contract Other disposal site requirements to be met by contractor River Riser and Diffuser Site Disposal via barge to at-sea or offloading/land-disposal site Native dredge material analytical data provided in contract Other disposal site requirements to be met by contractor 60

61 Schedule 61

62 Design and Tender Schedule Q1 2017: 60% Design Complete Q3 2017: RFQ Issued Q3 2017: 90% Design Complete Q1 2018: 100% Design Complete, RFP Issued, Site preparation start Q4 2018: Site preparation complete Q1 2019: New Outfall System contract NTP 62

63 Construction Schedule 63

64 INSURANCE REQUIREMENTS Commercial General Liability (CGL) Insurance for at least $10 million per occurrence (including coverage for underground shaft and tunnel work, and in-river work) additional insureds: Greater Vancouver Sewerage and Drainage District, Metro Vancouver Regional District, Vancouver Fraser Port Authority, Her Majesty the Queen in right of Canada, Southern Rail of British Columbia 64

65 INSURANCE Continued Automobile Liability Insurance - $5 million per occurrence Contractor s Pollution Liability Insurance - $5 million per occurrence or claim (additional insureds as in the CGL insurance) Marine Liability Insurance - $5 million per occurrence (additional insureds as in the CGL insurance) Course of Construction Insurance - For the dollar value of the contract Contractor s Equipment Insurance (including tunnel boring equipment) 65

66 BONDING REQUIREMENTS Bid Bond 10% of the dollar value of the tender price Performance Bond - 50% of the dollar value of the contract Labour and Materials Bond - 50% of the dollar value of the contract 66

67 WORKSAFE BC REQUIREMENTS Must be a registered employer Clearance Letter Prime Contractor designation 67

68 PRE-QUALIFICATION Contractors to demonstrate experience & qualifications in: Tunneling and Shafts in similar conditions Marine works of similar scope Request of Qualifications (RFQ) ~ Q Target completion of pre-qualification process ~ Q

69 REQUEST FOR PROPOSALS Pre-qualified contractors will be invited to submit proposals Evaluated on technical and financial criteria RFP Late Q Target for Notice to Proceed: Early Q

70 GENERAL CONDITIONS & RISK Metro Vancouver s Standard General Conditions Supplemental Conditions to address tunneling issues such as Differing Site Conditions, Dispute Resolution Board, & Escrow documents RFP will include: Geotechnical Data Report Geotechnical Baseline Report 70

71 QUESTIONS? Outside of today s session, send questions to: Gary Mui, Buyer, Metro Vancouver Purchasing Gary.Mui@metrovancouver.org 71

Special Committee on Bay-Delta Item 3b January 24, 2017

Special Committee on Bay-Delta Item 3b January 24, 2017 Special Committee on Bay-Delta Item 3b January 24, 2017 January California WaterFix Overview Review Other Mega-Projects Cost Schedule Lessons Learned February Construction Risk Management Special Committee

More information

Stevens & Associates, Inc. Tunnel Construction Projects. Fact Sheets

Stevens & Associates, Inc. Tunnel Construction Projects. Fact Sheets Stevens & Associates, Inc. Tunnel Construction Projects Fact Sheets Stevens & Associates, Inc. 4 Knights Court Newbury, MA 01951 978-764-9886 glen@stevensai.com Massachusetts Water Resources Authority

More information

VTA s BART Silicon Valley Phase II Extension

VTA s BART Silicon Valley Phase II Extension VTA s BART Silicon Valley Phase II Extension Santa Clara Community Working Group December 3, 2015 1 Agenda Follow-up Items and Work Plan New Starts Project Development & Schedule Update Construction Methods

More information

6 Preliminary Assessment of Construction Method and Constructability Issues

6 Preliminary Assessment of Construction Method and Constructability Issues 6 Preliminary Assessment of Construction Method and Constructability Issues 6.1 Construction Approach Appendix C includes conceptual designs of the alternatives discussed below. Generally, the conceptual

More information

Hudson River Tunnels, Mega Projects, and Risk A Designer s Perspective

Hudson River Tunnels, Mega Projects, and Risk A Designer s Perspective Purdue Geotechnical Society Workshop Digging Deep April 8, 2011 Hudson River Tunnels, Mega Projects, and Risk A Designer s Perspective David Chapman, P.E. Lachel & Associates, Inc. Morristown, NJ Hudson

More information

Rehoboth Beach Effluent Disposal Study. Evaluation of Wastewater Discharge Alternatives. Center for the Inland Bays STAC Meeting January 13, 2006

Rehoboth Beach Effluent Disposal Study. Evaluation of Wastewater Discharge Alternatives. Center for the Inland Bays STAC Meeting January 13, 2006 Rehoboth Beach Effluent Disposal Study Evaluation of Wastewater Discharge Alternatives Center for the Inland Bays STAC Meeting January 13, 2006 1 Agenda Background Objectives/Goals Land Search Discharge

More information

Vulnerability of Metro Vancouver Wastewater Infrastructure to Climate Change

Vulnerability of Metro Vancouver Wastewater Infrastructure to Climate Change Vulnerability of Metro Vancouver Wastewater Infrastructure to Climate Change Andrew Boyland, P.Eng. Kerr Wood Leidal Associates Arash Masbough, M.A.Sc., PMP, P.Eng. Associated Engineering Today s Presentation

More information

Kiewit Approach for Tunnel Stabilization and Sewer Pipeline Replacement Project

Kiewit Approach for Tunnel Stabilization and Sewer Pipeline Replacement Project South Coast Water District Kiewit Approach for Tunnel Stabilization and Sewer Pipeline Replacement Project Board of Directors January 14-15, 2013 Overview of Construction Plan Highlights of Kiewit s Construction

More information

UPDATE ON THE WATERFIX TUNNELS PROJECT. Breakthroughs in Tunneling September 2018

UPDATE ON THE WATERFIX TUNNELS PROJECT. Breakthroughs in Tunneling September 2018 UPDATE ON THE WATERFIX TUNNELS PROJECT Breakthroughs in Tunneling September 2018 PRESENTATION OVERVIEW Need for WaterFix Proposed Facilities Tunnel Design Challenges Engaging Innovation Current Status

More information

February 7, Purpose. Background. the BDCP. needs the project. Discussion. Facilities 1. plants) 1, October 1, 2013,

February 7, Purpose. Background. the BDCP. needs the project. Discussion. Facilities 1. plants) 1, October 1, 2013, February 7, 2014 Attention: Imported Water Committee Bay-Delta Conservation Plan: Infrastructu ure Review.. (Discussion) Purpose The purpose of this memo is to provide an assessment off the Bay-Delta Conservation

More information

CONSTRUCTION SPECIFICATION FOR PIPELINE INSTALLATION BY TUNNELLING

CONSTRUCTION SPECIFICATION FOR PIPELINE INSTALLATION BY TUNNELLING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 415 NOVEMBER 2013 CONSTRUCTION SPECIFICATION FOR PIPELINE INSTALLATION BY TUNNELLING TABLE OF CONTENTS 415.01 SCOPE 415.02 REFERENCES 415.03 DEFINITIONS

More information

Take Me to the Other Side:

Take Me to the Other Side: Take Me to the Other Side: The Importance of Trenchless Crossings in Routing Water Supply Transmission Brooke Barry, E.I.T., Mark Havekost, P.E. 2014 HDR, all rights reserved. PURPOSE: Develop an additional

More information

VTA s BART Silicon Valley Phase II Extension

VTA s BART Silicon Valley Phase II Extension VTA s BART Silicon Valley Phase II Extension Downtown-Diridon Community Working Group December 1, 2015 1 Agenda Follow-up Items and Work Plan New Starts Project Development & Schedule Update Construction

More information

APPENDIX 8-A. Valued Component Selection Rationale

APPENDIX 8-A. Valued Component Selection Rationale APPENDIX 8-A Valued Component Selection Rationale This page is intentionally left blank A list of candidate s was compiled based on issues identified through the scoping process described in Section 8.1.2

More information

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo. Pipe Jacking/Microtunnelling Dr. Mark Knight Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo 1 New Installations New Installations Non-Steering Methods Steering Methods

More information

Design and Implementation of the South Hartford CSO Tunnel

Design and Implementation of the South Hartford CSO Tunnel Design and Implementation of the South Hartford CSO Tunnel Brian Canterbury, P.E., AECOM James Sullivan, P.E., AECOM Andrew Perham, The Metropolitan District The Metropolitan District NEWEA January 22,

More information

DESIGN OF TEMPLETON OVERPASS FOR THE CANADA LINE. Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng.,P.Eng., SNC-Lavain Inc.

DESIGN OF TEMPLETON OVERPASS FOR THE CANADA LINE. Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng.,P.Eng., SNC-Lavain Inc. DESIGN OF TEMPLETON OVERPASS FOR THE CANADA LINE Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng.,P.Eng., SNC-Lavain Inc. Roger Woodhead, PhD, P.Eng., SNC-Lavain Inc. Paper prepared for

More information

Pushing the Envelope For 100 Years

Pushing the Envelope For 100 Years Pushing the Envelope For 100 Years Tunneling under the Chesapeake Bay The Parallel Thimble Shoal Highway Tunnel Presented by: Kevin Abt, PE Chesepeake Bay Bridge and Tunnel District Mike Kling, PE, PTOE

More information

Experts in tunneling with Tunnel Boring Machines

Experts in tunneling with Tunnel Boring Machines www.eurohinca.com www.terratest.es Experts in tunneling with Tunnel Boring Machines info@eurohinca.com EUROHINCA Europea de Hincas Teledirigidas, S.A., EUROHINCA, was incorporated in 1996 for the execution

More information

Physical Works Terms of Reference

Physical Works Terms of Reference Peace Project Water Use Plan Physical Works Terms of Reference District of Mackenzie Effluent Discharge Feasibility and Design Study GMSWORKS #28a 23 November 2009 Terms of Reference for the Peace Water

More information

An Introduction to. By Michael L. Schumaker, P.E. An Introduction to Shaner Industries Metal Foundation System

An Introduction to. By Michael L. Schumaker, P.E. An Introduction to Shaner Industries Metal Foundation System An Introduction to Metal Foundation System By Michael L. Schumaker, P.E. Introduction Various types of deep foundations are routinely used to support structures. Selection of the appropriate type of deep

More information

DFI DEEP FOUNDATIONS. Aerial View of a Flood Control Project in San Juan, Puerto Rico: An OPA Finalist F E

DFI DEEP FOUNDATIONS. Aerial View of a Flood Control Project in San Juan, Puerto Rico: An OPA Finalist F E U N DAIONS IN O F P D DFI S I U DP FOUNDAIONS Mar/Apr 2012 he Magazine of the Deep Foundations Institute Aerial View of a Flood Control Project in San Juan, Puerto Rico: An OPA Finalist op slab construction

More information

APPENDIX J ENVIRONMENTAL STUDIES

APPENDIX J ENVIRONMENTAL STUDIES APPENDIX J ENVIRONMENTAL STUDIES J.2: Co structio E iro e tal Ma age e t Pla A acis Isla d WWTP Ne Outfall Syste Va cou er Fraser Port Authority Project a d E iro e tal Re ie Applicatio This page intentionally

More information

WESTRIDGE MARINE TERMINAL UPGRADE AND EXPANSION PROJECT APPLICATION TO VANCOUVER FRASER PORT AUTHORITY

WESTRIDGE MARINE TERMINAL UPGRADE AND EXPANSION PROJECT APPLICATION TO VANCOUVER FRASER PORT AUTHORITY WESTRIDGE MARINE TERMINAL IN WATER EXCAVATION REPORT WESTRIDGE MARINE TERMINAL UPGRADE AND EXPANSION PROJECT APPLICATION TO VANCOUVER FRASER PORT AUTHORITY Trans Mountain Pipeline ULC Kinder Morgan Canada

More information

STANDARD SPECIFICATIONS SECTION BORING AND JACKING. A. Section includes requirements for boring and jacking casing pipe.

STANDARD SPECIFICATIONS SECTION BORING AND JACKING. A. Section includes requirements for boring and jacking casing pipe. STANDARD SPECIFICATIONS SECTION 02445 BORING AND JACKING PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for boring and jacking casing pipe. 1.2 DEFINITIONS A. Carrier Pipe: Sewer or water

More information

Immersed Tunnels. Richard Lunniss and Jonathan Baber. CRC Press. Taylor & Francis Group. Taylor & Francis Group, A SPON BOOK

Immersed Tunnels. Richard Lunniss and Jonathan Baber. CRC Press. Taylor & Francis Group. Taylor & Francis Group, A SPON BOOK Immersed Tunnels Richard Lunniss and Jonathan Baber CRC Press Taylor & Francis Group Boca Raton London New York CRC Press is an imprint of the Taylor & Francis Group, an informa business A SPON BOOK Contents

More information

Alternative Construction Methods and Pipe Material provide Solutions for Cleveland WWTP Project

Alternative Construction Methods and Pipe Material provide Solutions for Cleveland WWTP Project Alternative Construction Methods and Pipe Material provide Solutions for Cleveland WWTP Project Bernie Ashyk 1, Christopher Lucie, P.E. 2, Jeffrey LeBlanc, P.E. 3 1 Shook Walbridge JV, Project Manager;

More information

Appendix J Effluent Pump Station

Appendix J Effluent Pump Station Appendix J Effluent Pump Station TECHNICAL MEMORANDUM Salmon Creek Treatment Plant Effluent Pump Station Hydraulics and Phasing Analysis for the Phase 5A Project Columbia River Outfall and Effluent Pipeline

More information

John Hart Generating Station Replacement Project. December January 2014 Community Construction Update Report #8

John Hart Generating Station Replacement Project. December January 2014 Community Construction Update Report #8 John Hart Generating Station Replacement Project December 2013 - January 2014 Community Construction Update Report #8 Prepared by: Stephen Watson, BC Hydro (O) 250-755-4795 or (C) 250-616-9888 steve.watson@bchydro.com

More information

Hampton Roads Bridge Tunnel Expansion: Overview of Tunnel Construction Methods

Hampton Roads Bridge Tunnel Expansion: Overview of Tunnel Construction Methods Hampton Roads Bridge Tunnel Expansion: Overview of Tunnel Construction Methods February 21, 2018 James S. Utterback HRBT Project Director Virginia Department of Transportation Ten Hampton Roads Tunnels

More information

3.12 UTILITIES Introduction Environmental Setting

3.12 UTILITIES Introduction Environmental Setting 3.12 UTILITIES 3. Affected Environment and Environmental Analysis 3.12 UTILITIES 3.12.1 Introduction This section addresses the potential for impacting public utilities within the Port, the Main Channel,

More information

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION BY JACKING AND BORING

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION BY JACKING AND BORING ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 416 NOVEMBER 2013 CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION BY JACKING AND BORING TABLE OF CONTENTS 416.01 SCOPE 416.02 REFERENCES

More information

Lower San Joaquin River Feasibility Study PLAN FORMULATION ADDENDUM

Lower San Joaquin River Feasibility Study PLAN FORMULATION ADDENDUM PLAN FORMULATION ADDENDUM Non-Structural Measure Descriptions Elevate Critical Infrastructure This measure would raise at-risk critical structures above the design inundation level. Elevation would be

More information

Soft Ground Tunneling through Contaminated Groundwater

Soft Ground Tunneling through Contaminated Groundwater 5 th Annual Technical Forum GEOHAZARDS IN TRANSPORTATION IN THE APPALACHIAN REGION Soft Ground Tunneling through Contaminated Groundwater Nasri Munfah P.E. and Subal Sarkar P.E. Parsons Brinckerhoff, New

More information

EAST CENTRAL REGIONAL WATER RECLAMATION FACILITY PROCESS WATER SYSTEM PROJECT

EAST CENTRAL REGIONAL WATER RECLAMATION FACILITY PROCESS WATER SYSTEM PROJECT EAST CENTRAL REGIONAL WATER RECLAMATION FACILITY PROCESS WATER SYSTEM PROJECT Addendum No. 2 Attachment B Contract Document Revisions Specifications: TABLE OF CONTENTS ADDENDUM NO. 2 Attachment B Contract

More information

ITEM 432 TUNNEL CONSTRUCTION

ITEM 432 TUNNEL CONSTRUCTION AFTER MARCH 1, 2012 ITEM 432 TUNNEL CONSTRUCTION 432.1 Description. This Item shall govern for tunnel lines under railroads, state highways, and concrete paved streets or other obstructions indicated.

More information

Dry structural excavation is usually done with front-end loaders, bulldozers or backhoes.

Dry structural excavation is usually done with front-end loaders, bulldozers or backhoes. 1.1 Excavation - General Excavation is the removal of all material (including ice, water, etc.) required for the construction of foundations or substructures as indicated on the drawings or as determined

More information

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION BY JACKING AND BORING

CONSTRUCTION SPECIFICATION FOR PIPELINE AND UTILITY INSTALLATION BY JACKING AND BORING ONTARIO PROVINCIAL STANDARD SPECIFICATION OPSS.MUNI 416 NOVEMBER 2018 (Formerly OPSS 416, November 2013) Note: The MUNI implemented in November 2018 replaces OPSS 416 COMMON, November 2013 with no technical

More information

Gilmerton Bridge Replacement Project Virginia Society of Professional Engineers (VSPE) March 27, 2013

Gilmerton Bridge Replacement Project Virginia Society of Professional Engineers (VSPE) March 27, 2013 1 Gilmerton Bridge Replacement Project Virginia Society of Professional Engineers (VSPE) March 27, 2013 PRESENTERS: Marc Papini Parsons Brinckerhoff, Project Manager Jim Holtje, P.E. PCL Civil Constructors,

More information

Capital Expenditure Summary

Capital Expenditure Summary Capital Expenditure Summary UTILITIES COMMITTEE PRESENTATION Frank Huber DIRECTOR, MAJOR PROJECTS, MANAGEMENT SYSTEMS AND UTILITY SERVICES WATER SERVICES July 12, 2018 http://orbit.gvrd.bc.ca/orbit/llisapi.dll/properties/25601136

More information

RFP Questions and Answers 1 (Pre-Bid Meeting)

RFP Questions and Answers 1 (Pre-Bid Meeting) RFP 40860 Questions and Answers 1 (Pre-Bid Meeting) Amendment to Page 8 of 99 of the Proposal for RFQ 40860 to change from 120 days stated to 270 days for completion of project. Clarifications of drawings:

More information

Evergreen Line Rapid Transit Project

Evergreen Line Rapid Transit Project Evergreen Line Rapid Transit Project Burnaby, Port Moody, and Coquitlam, BC Completed in December 2016 Canadian Consulting Engineering Awards 2017 Project Category: B. Transportation Canadian Consulting

More information

GEOTECHNICAL INVESTIGATION PROPOSED OUTFALL LOCATION CITY OF MORGAN S POINT DRAINAGE HARRIS COUNTY, TEXAS REPORT NO

GEOTECHNICAL INVESTIGATION PROPOSED OUTFALL LOCATION CITY OF MORGAN S POINT DRAINAGE HARRIS COUNTY, TEXAS REPORT NO GEOTECHNICAL INVESTIGATION PROPOSED OUTFALL LOCATION CITY OF MORGAN S POINT DRAINAGE HARRIS COUNTY, TEXAS REPORT NO. 1140198001 Reported to: SIRRUS ENGINEERS, INC. Houston, Texas Submitted by: GEOTEST

More information

City of Columbus Wet Weather Management Plan Update. Dax J. Blake, P.E. Administrator City of Columbus, Ohio Division of Sewerage and Drainage

City of Columbus Wet Weather Management Plan Update. Dax J. Blake, P.E. Administrator City of Columbus, Ohio Division of Sewerage and Drainage City of Columbus Wet Weather Management Plan Update Dax J. Blake, P.E. Administrator City of Columbus, Ohio Division of Sewerage and Drainage City of Columbus, Ohio Population served ~ 1 Million 22 satellite

More information

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES

204 - EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES SECTION 204 EXCAVATION AND BACKFILL FOR STRUCTURES 204.1 DESCRIPTION Excavate for the structures as shown in the Contract Documents. Unless specified otherwise, backfill the completed structures to the

More information

Esquimalt Graving Dock Waterlot Remediation Mega-Site (Phase 1B): Design, Contracting, and Construction Challenges

Esquimalt Graving Dock Waterlot Remediation Mega-Site (Phase 1B): Design, Contracting, and Construction Challenges Esquimalt Graving Dock Waterlot Remediation Mega-Site (Phase 1B): Design, Contracting, and Construction Challenges Presented by Dan Berlin and Tom Wang, Anchor QEA, LLC Andrew Mylly and Rae-Ann Sharp,

More information

PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV

PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV NORTH SHORE CONNECTOR TUNNELS AND STATION SHELL LIGHT RAIL PROJECT PAUL ZICK, PE NORTH SHORE CONSTRUCTORS JV North Shore Connector Alignment 7300 lf Extension to existing 25 mile system 18 Contracts $435

More information

Proposed Maplewood Marine Restoration Project Discussion guide and feedback form

Proposed Maplewood Marine Restoration Project Discussion guide and feedback form Vancouver Fraser Port Authority Habitat Enhancement Program Proposed Maplewood Marine Restoration Project Discussion guide and feedback form Public consultation September 24 October 12, 2018 Feedback form

More information

REPORT. ~bhot s ford. f~.j./ ;\11SSJ{)11 \\';trc r & Scwer' S c f\'icc ~

REPORT. ~bhot s ford. f~.j./ ;\11SSJ{)11 \\';trc r & Scwer' S c f\'icc ~ ~bhot s ford f~.j./ ;\11SSJ{)11 \\';trc r & Scwer' S c f\'icc ~ REPORT To: Abbotsford/Mission Water Sewer Commission (WSC) From : Tony Seibert, P.Eng., Wastewater Project Engineer Date: April 8, 2011 Subject:

More information

Amendment to OPSS 416 (Nov 2013) Construction Specification for Pipeline and Utility Installation by Jacking and Boring

Amendment to OPSS 416 (Nov 2013) Construction Specification for Pipeline and Utility Installation by Jacking and Boring Engineering & Construction Services Division Standard Specifications for Sewers and Watermains TS 416 September 2017 Amendment to OPSS 416 (Nov 2013) Construction Specification for Pipeline and Utility

More information

Thermal and Hydro Power Plant Maintenance Deer Island Treatment Plant

Thermal and Hydro Power Plant Maintenance Deer Island Treatment Plant Massachusetts Water Resources Authority Presentation to MWRA Board of Directors Thermal and Hydro Power Plant Maintenance Deer Island Treatment Plant March 12, 2014 On-Site Thermal/Power Plant Built in

More information

IEEE 18-May Intake. Tunnel. Outlet

IEEE 18-May Intake. Tunnel. Outlet IEEE 18-May-2011 Intake Tunnel Outlet 1 Increase water diversion capacity at the Sir Adam Beck complex by 500 m 3 /s (+27%) Increase average annual energy output at the Sir Adam Beck complex by 1.6 billion

More information

czc= r&:ob ;0_ City of Richmond Report to Committee J2f J2( ""'"::::>

czc= r&:ob ;0_ City of Richmond Report to Committee J2f J2( '::::> City of Richmond Report to Committee To: From: Public Works and Transportation Committee John Irving, P.Eng. MPA Director, Engineering Date: August 25, 2017 File: 10-6060-03-01/2017- Vol 01 Re: Metro Vancouver

More information

King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle s Ship Canal

King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle s Ship Canal North American Society for Trenchless Technology (NASTT) NASTT s 2013 No-Dig Show Sacramento, California March 3-7, 2013 TA-T1-03 King County Uses Trenchless Methods to Construct a Large Siphon Under Seattle

More information

B.4 Preliminary Feasibility Cost Estimate

B.4 Preliminary Feasibility Cost Estimate B.4 Preliminary Feasibility Estimate Introduction This section presents preliminary feasibility-level cost estimates for NODOS/Sites Reservoir Project Alternatives A, B, C, and D, described in Section

More information

Misan University - College of Engineering Civil Engineering Department

Misan University - College of Engineering Civil Engineering Department CHAPTER 2 Soil and Excavations Soil investigation including two phases: surface investigation and subsurface investigation Surface investigation involves making a preliminary judgment about the site s

More information

SEMMERING BASE TUNNEL LOGISTIC CHALLENGES

SEMMERING BASE TUNNEL LOGISTIC CHALLENGES SEMMERING BASE TUNNEL LOGISTIC CHALLENGES Dipl.-Ing. Michael Proprenter ic consulenten ZT GmbH Vienna, Austria Mail: m.proprenter@ic-group.org Dipl.-Ing. Oliver K. Wagner ÖBB - Austrian Federal Railways

More information

TBM Selection and Specification

TBM Selection and Specification By Bradford F. Townsend and Paul E. Jenkins Date: 13 June 2009 TBM Selection - Challenges to be met TBM Technology Auxiliary Measures and Backup New Developments Summary of Selection Process Procurements

More information

Regulation 18 August 2009 NO Operations and Maintenance LEVEE ENCROACHMENT STANDARDS AND PROCEDURES

Regulation 18 August 2009 NO Operations and Maintenance LEVEE ENCROACHMENT STANDARDS AND PROCEDURES CENWP-EC DEPARTMENT OF THE ARMY PDR 30-2-5 Portland District, Corps of Engineers (Draft) P.O. Box 2946 Portland, Oregon 97208 Regulation 8 August 2009 NO. 30-2-5 Operations and Maintenance LEVEE ENCROACHMENT

More information

Challenges and results of Using hand mining to tunnel the mcalpine creek relief sewer

Challenges and results of Using hand mining to tunnel the mcalpine creek relief sewer 96 th Annual NC AWWA-WEA Conference Chuck Shue, PE McKim & Creed, Inc. Senior Project Manager Challenges and results of Using hand mining to tunnel the mcalpine creek relief sewer OUTLINE Project overview

More information

Moncton Watermain Relocation Moncton, New Brunswick. TRS 2010 Dr Mark Knight University of Waterloo

Moncton Watermain Relocation Moncton, New Brunswick. TRS 2010 Dr Mark Knight University of Waterloo Moncton Watermain Relocation Moncton, New Brunswick TRS 2010 Dr Mark Knight University of Waterloo Presentation Outline Overview of the project Design and construction Issues Trenchless construction Lessons

More information

SECTION DRILLED CONCRETE PIERS AND SHAFTS

SECTION DRILLED CONCRETE PIERS AND SHAFTS SECTION 31 63 29 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply

More information

The last update was March 4, 2016.

The last update was March 4, 2016. From: To: Subject: Date: Long Lake Stewardship longlakesudbury@gmail.com LONG LAKE STEWARDSHIP - Gold Mine Site Reclamation Work - Project Update May 29, 2017 6:14:57 PM Hello - Some of you will remember

More information

(#' John Irving, P.Eng. Director, Engineering ( )

(#' John Irving, P.Eng. Director, Engineering ( ) City of Richmond Report to Committee To: From: Public Works and Transportation Committee John Irving, P.Eng. MPA Director, Engineering Re: Flood Protection Update 2014 Date: June 23,2014 File: 10-6060-04-01/2014-

More information

UNDERGROUND UTILITY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION

UNDERGROUND UTILITY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION UNDERGROUND UTILITY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION Effective September 9, 2014 The General Trade Knowledge portion of the examination is administered daily in Computer

More information

COPYRIGHTED MATERIAL. Contents PART ONE: THEORY...1. Preface to the Third Edition xiii. About the Authors xv. Acknowledgements xvii

COPYRIGHTED MATERIAL. Contents PART ONE: THEORY...1. Preface to the Third Edition xiii. About the Authors xv. Acknowledgements xvii Preface to the Third Edition xiii About the Authors xv Acknowledgements xvii Contents PART ONE: THEORY...1 1. Groundwater in Construction...3 1.1 Groundwater in the Hydrologic Cycle 3 1.2 Origins of Dewatering

More information

Plessis Road Twinning and Grade Separation at CN Redditt Subdivision: Design Challenges and Innovative Solutions

Plessis Road Twinning and Grade Separation at CN Redditt Subdivision: Design Challenges and Innovative Solutions Plessis Road Twinning and Grade Separation at CN Redditt Subdivision: Design Challenges and Innovative Solutions Tanya D. Worms, P.Eng. M.Sc., Project Manager, M.D. Steele Construction Ltd. Paper prepared

More information

The work required for this project includes, but is not limited to, the following items, not listed in order of execution.

The work required for this project includes, but is not limited to, the following items, not listed in order of execution. ESTIMATE OF QUANTITIES SPECIFICATIONS Construction Specifications: South Dakota Standard Specifications for Roads and Bridges, 2004 Edition and Required Provisions, Supplemental Specifications and/or Special

More information

FLOODPLAIN MANAGEMENT STRATEGY FEASIBILITY PLAN. EB3679 February 2011

FLOODPLAIN MANAGEMENT STRATEGY FEASIBILITY PLAN. EB3679 February 2011 FLOODPLAIN MANAGEMENT STRATEGY FEASIBILITY PLAN EB3679 February 2011 FLOODPLAIN MANAGEMENT STRATEGY FEASIBILITY PLAN Prepared for: The City of Westminster 511 Royal Avenue Westminster, BC V3L 1H9 Prepared

More information

STANDARD SPECIFICATIONS SECTION TUNNELING. A. Section includes requirements for constructing tunnels 48-inch and larger diameter.

STANDARD SPECIFICATIONS SECTION TUNNELING. A. Section includes requirements for constructing tunnels 48-inch and larger diameter. STANDARD SPECIFICATIONS SECTION 02420 TUNNELING PART 1 GENERAL 1.1 DESCRIPTION A. Section includes requirements for constructing tunnels 48-inch and larger diameter. 1.2 DEFINITIONS A. Carrier Pipe: Sewer

More information

EXPERT PANEL ON DIVERSION PLANNING AND IMPLEMENTATION SEDIMENT DIVERSIONS UPDATE

EXPERT PANEL ON DIVERSION PLANNING AND IMPLEMENTATION SEDIMENT DIVERSIONS UPDATE EXPERT PANEL ON DIVERSION PLANNING AND IMPLEMENTATION SEDIMENT DIVERSIONS UPDATE August 31, 2016 MISSISSIPPI RIVER SEDIMENT DIVERSIONS: PROCESS 2 RECOMMENDATIONS FROM LAST MEETING: BEYOND THE FALL 2015

More information

CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT

CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 616 NOVEMBER 2008 CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT TABLE OF CONTENTS 616.01 SCOPE 616.02 REFERENCES 616.03

More information

Geo24h. Buiding Service

Geo24h. Buiding Service Geo24h Buiding Service Sheet pile wall metallic and composite Special Foundations Dredging canals, rivers, lakes and quarries Dewatering with wells Wellpoint sistems Types of application The sheet pile

More information

SELECTION OF TUNNEL METHODS. By: Dr. Gary S. Brierley

SELECTION OF TUNNEL METHODS. By: Dr. Gary S. Brierley SELECTION OF TUNNEL METHODS By: Dr. Gary S. Brierley Successful Tunnel Design 2 Produce a satisfactory finished facility for no more money and in no more time than is required for the existing ground conditions.

More information

Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E.

Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E. Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E. Presentation Outline Project History Project Scope Construction Alternatives Plan

More information

Presented by: Frank Guyamier

Presented by: Frank Guyamier FTBA Orlando Tuesday, March 20, 2012 Presented by: Frank Guyamier Project Engineer P3 PROJECT PARTNERS Public Sponsors 90% Equity Partner Design/Build Contractor 10% Equity Partner VMS Operator Federal

More information

CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL

CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL CS 3-01 GENERAL: A. The foundation, bedding and backfill for all trenches shall conform with the requirements of the City Standard

More information

Chapter 3: Permit Procedures and Requirements

Chapter 3: Permit Procedures and Requirements Chapter 1: General Provisions 1 1 Short Title 1 2 Jurisdiction 1 3 Amendments and Revisions 1 4 Enforcement Responsibility 1 5 Review Process 1 6 Prior Approval 1 7 Relationship to Other Standards 1 8

More information

SR 710 North Study. Technical Advisory Committee Meeting No. 16 August 13, 2014 Stakeholder Outreach Advisory Committee Meeting No. 12 August 14, 2014

SR 710 North Study. Technical Advisory Committee Meeting No. 16 August 13, 2014 Stakeholder Outreach Advisory Committee Meeting No. 12 August 14, 2014 SR 710 North Study Technical Advisory Committee Meeting No. 16 August 13, 2014 Stakeholder Outreach Advisory Committee Meeting No. 12 August 14, 2014 1 1 1 Agenda Public Outreach Activities Project Report

More information

2 EARTHWORKS AND GEOTECHNICAL REQUIREMENTS

2 EARTHWORKS AND GEOTECHNICAL REQUIREMENTS Section 2 Earthworks and Geotechnical Requirements 2 EARTHWORKS AND GEOTECHNICAL REQUIREMENTS CONTENTS 2 EARTHWORKS AND GEOTECHNICAL REQUIREMENTS... I 2.1 Introduction... 2-1 2.1.1 Objectives... 2-1 2.1.2

More information

Tunnelling under the Fraser River at 6 bar Design and Construction of the Port Mann Main Water Supply Tunnel

Tunnelling under the Fraser River at 6 bar Design and Construction of the Port Mann Main Water Supply Tunnel Tunnelling under the Fraser River at 6 bar Design and Construction of the Port Mann Main Water Supply Tunnel Stephanie Fekete McMillen Jacobs Associates Steve Skelhorn McNally Construction Inc. Tim Langmaid

More information

CHAPTER 11: WALLS.

CHAPTER 11: WALLS. CHAPTER 11: WALLS MODULAR BLOCK WALL (DRY CAST) Rather than being pre-approved as systems, the components of Modular block walls (dry cast) are pre-approved separately. The approved MBW components are

More information

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION SPECIFICATION FOR PIPE CULVERT CONSTRUCTION 1. SCOPE Pipe culverts shall be constructed in accordance with this specification and in conformity with the lines, levels and cross-sections shown on the drawings.

More information

Department of Administration State Construction Office SITE PREPARATION AND GRADING CRITERIA

Department of Administration State Construction Office SITE PREPARATION AND GRADING CRITERIA Revised May 17, 2011 Department of Administration State Construction Office SITE PREPARATION AND GRADING CRITERIA INTRODUCTION These criteria are established to provide uniform construction practices and

More information

Answer: Yes additional labor classifications can be added to the Staff and Fee Schedule (Exhibit 2-6). Yes all rates are to be completed.

Answer: Yes additional labor classifications can be added to the Staff and Fee Schedule (Exhibit 2-6). Yes all rates are to be completed. SOUTH BROOKLYN RESILIENCY PROJECTS Project #6253/ Contract # 62530001 Questions & Answers August 18, 2016 1. Relative to the Staff and Fee Schedule (Exhibit 2-6) - Can we supplement the list of labor classifications

More information

Slurry MTBM in Alluvial Soils and 25k Rock Chris L. Windley, P.E. McKim & Creed Inc. Stephen D. Leitch, P.E. Hazen and Sawyer, P.C. Joshua P.

Slurry MTBM in Alluvial Soils and 25k Rock Chris L. Windley, P.E. McKim & Creed Inc. Stephen D. Leitch, P.E. Hazen and Sawyer, P.C. Joshua P. Slurry MTBM in Alluvial Soils and 25k Rock Chris L. Windley, P.E. McKim & Creed Inc. Stephen D. Leitch, P.E. Hazen and Sawyer, P.C. Joshua P. Farmer, P.E. Hazen and Sawyer, P.C. Project Background City

More information

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Michigan Department Of Transportation 3703C (11/06) 1 Materials 1.1 Pipe SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006 Page 1 of 5 The type of pipe used for the pipe jacking method shall be capable

More information

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS Implenia Spezialtiefbau GmbH Robert Bosch Straße 25 D-63225 Langen Phone: +49 6103 988 345 Fax: +49 6103 988 277 Email: info.spezialtiefbau@implenia.com

More information

All Tunnel Alignment & Option Comparisons. Presented to: BDCP Steering Committee. December 3, 2009 DRAFT

All Tunnel Alignment & Option Comparisons. Presented to: BDCP Steering Committee. December 3, 2009 DRAFT All Tunnel Alignment & Option Comparisons Presented to: BDCP Steering Committee December 3, 2009 Option Comparison Alignment of Options Major Features Comparison Tables Pros & Cons Mitigation Environmental

More information

F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it.

F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it. Section 3 F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it. 3.8 Highway Crossings The design engineer shall, prior to the design of any highway

More information

The Manitoba Water Services Board SECTION Standard Construction Specifications September 2013 Page 1 of 5

The Manitoba Water Services Board SECTION Standard Construction Specifications September 2013 Page 1 of 5 September 2013 Page 1 of 5 Part 1 General 1.1 DESCRIPTION OF WORK.1 The work described herein shall consist of the construction of a water intake including: The supply and installation of pipe and appurtenances

More information

PREQUALIFICATION APPLICATION INSTRUCTIONS

PREQUALIFICATION APPLICATION INSTRUCTIONS PREQUALIFICATION APPLICATION INSTRUCTIONS Please read the following instructions carefully as incomplete applications will not be processed. COMPLETE AND RETURN ALL SECTIONS OF THE APPLICATION PACKAGE.

More information

SEATTLE S BRIGHTWATER UNDERGROUND CONVEYANCE SYSTEM TUNNELING & UNDERGROUND CONSTRUCTION

SEATTLE S BRIGHTWATER UNDERGROUND CONVEYANCE SYSTEM TUNNELING & UNDERGROUND CONSTRUCTION TUNNELING & UNDERGROUND CONSTRUCTION THE OFFICIAL PUBLICATION OF UCA OF SME WWW.TUCMAGAZINE.COM VOLUME 1 NO 2 JUNE 2007 SEATTLE S BRIGHTWATER UNDERGROUND CONVEYANCE SYSTEM Tunnel Demand Forecast Ground

More information

SECTION 39 - MANHOLES TABLE OF CONTENTS

SECTION 39 - MANHOLES TABLE OF CONTENTS Section SECTION 39 - MANHOLES TABLE OF CONTENTS Page 39-1 GENERAL... 39.1 39-2 CONCRETE MANHOLES... 39.1 39-2.01 NOT USED... 39.1 39-2.02 Concrete Storm Drain Manholes... 39.1 39-3 SADDLE SEWER MANHOLES...

More information

BILL OF QUANTITY ENGINEERING & MANAGEMENT CONSULTING CENTRE. "Beit Hanoun Emergency Water Supply Project"

BILL OF QUANTITY ENGINEERING & MANAGEMENT CONSULTING CENTRE. Beit Hanoun Emergency Water Supply Project "Beit Hanoun Emergency Water Supply Project" " Rehabilitation and Construction of Beit Hanoun Water Network " BILL OF QUANTITY ENGINEERING & MANAGEMENT CONSULTING CENTRE Bill of Quantities PREAMBLE TO

More information

FACSIMILE/ MAIL TRANSMISSION. Date: December 2, 2011 File:

FACSIMILE/ MAIL TRANSMISSION. Date: December 2, 2011 File: PUAR Engineering Consultants Inc #200-100 Park Royal South W.Vancouver, BC, Canada V7T 1A2 Fax: 604-922-5054; Tel: 604-913-7827 FACSIMILE/ MAIL TRANSMISSION Date: December 2, 2011 File: 07-2-256 To: BRIAN

More information

Change of Coordinating Registered Professional (CRP) or Registered Professional (RP)

Change of Coordinating Registered Professional (CRP) or Registered Professional (RP) January, 2019 BUILDING DIVISION Change of Coordinating Registered Professional (CRP) or Registered Professional (RP) General Information In the event that there is a change of the Coordinating Registered

More information

4. FISH PASSAGE CONCEPTS

4. FISH PASSAGE CONCEPTS Feasibility Study for Restoration of Titlow Lagoon Fish Passage South Puget Sound Salmon Enhancement Group 4. FISH PASSAGE CONCEPTS Fish passage could be improved by rehabilitating the existing fish passage,

More information

CLARIFICATIONS TO TECHNICAL SPECIFICATIONS SECTIONS

CLARIFICATIONS TO TECHNICAL SPECIFICATIONS SECTIONS C-44 Reservoir/STA System Discharge Project RFB: 6000000620 Addendum No. 1 March 2014 CLARIFICATIONS TO TECHNICAL SPECIFICATIONS SECTIONS HDR Engineering, Inc. SECTION 02401 DEWATERING, COFFERDAM AND BYPASS

More information

Cost Estimating Framework

Cost Estimating Framework Cost Estimating Framework Water and Wastewater Master Study Prepared by: GM BluePlan Engineering for: Project No. 717022 TABLE OF CONTENTS 1 Introduction... 1 2 Cost Estimation Framework... 2 2.1 Approach

More information