1 "Nuts & Bolts How fast can wind destroy a home? Simple construction tips to keep yours standing The 23 rd Advanced Severe Weather Seminar March 15, 2014

2 Gone in Seconds

3 95 mph Straight Line Winds

4 EF-2 and EF-3 tornadoes with 111 mph-165 mph winds can destroy a property in four seconds. Flying debris shatters windows and other openings and create holes in exterior walls. Once an opening is created, air rushes inside the structure and pressurizes it like inflating a balloon. The internal pressures build up and put pressure on ceilings and the roof, which is also getting uplift pressures from external wind forces. If the connections between the roof and walls are weak, these wind forces will drive the roof and walls to give way. Once the roof blows off the entire structure can collapse within seconds.

5 1st Second Flying debris shatters windows and pounds exterior walls. Winds blowing over the roof exert uplift, like an airplane. Roof shingles and pieces of the roof decking tear away,

6 2 nd Second Air rushes into the home through the busted windows, filling the structure with pressure like a balloon being inflated. Internal pressure pushes up against the ceiling, joining the uplift on the roof from the gales outside in putting pressure on the roof. The relatively weak connections between the roof and the walls give way and the roof blows off.

7 3 rd Second Roof is gone, walls are next. Unless there are a lot of interior walls bracing and going into them, the exterior walls are typically flimsy and not well attached to each other at the corners. Though tornadoes spin in a cyclical motion, the fact that they're so big with a typical footprint measuring 500 feet wide means that a house is effectively hammered by straight-line winds. The side walls parallel to the direction of these winds will typically go first because they feel the most suction. The front, windward wall then gets pushed in by the tornado, and finally the back wall blows out, all within about a second.

8 4 th Second The last bits of a house that a tornado strike sweeps away are the interior walls Without exterior walls or a roof to brace them these inner walls can easily collapse or get blown over in the twister's fury.

9 This Applies to Commercial Structures

10 FORTIFIED homes need fewer repairs after disaster strikes. FORTIFIED homes are better for the environment because they are not likely to end up as debris in landfills following disasters. FORTIFIED homes may also be eligible for financial benefits such lower insurance rates.

11 FORTIFIED Home is a national, third-party verification program designed by the Insurance Institute for Business & Home Safety (IBHS) to help you assess the condition of your home, and then strengthen your home through an evaluation, inspection, and retrofitting process that is tailored to meet the challenges of specific, regional natural hazards. FORTIFIED Home has three levels. Bronze, Silver and Gold, with Gold representing the highest level of achievement and the greatest disaster protection.

12 Something to Consider When Replacing Roof IBHS wants you to know for less than $1,000, you can strengthen the roof of an average 2,000-square-foot house when replacing the roof. Re-nailing the roof deck with 8d ring shank nails for better attachment. Sealing the roof deck to keep water out of the attic if the roof cover blows off.

13 The Roof Makes A Difference "Homes are not designed to withstand tornadoes," says Timothy Marshall, principal engineer at Haag Engineering Co. and an expert on tornado damage. Building codes in non-hurricane designated areas call for two 16-penny (3 1/2 inch) nails connecting roof trusses to exterior wall top plates. These connections are intended to gird homes against gusts up to 90 mph for 3 seconds at a height of 33 feet. But even an EF-1 tornado is capable of more punishment.

14 It s All about Connecting

15 Spend Now or Pay Later Widespread use of effective strapping would create houses that are significantly more resistant to all kinds of severe wind events. Estimated additional 2% of Framing Cost

16 1 st Manmade Hail Storm.

17 IBHS 90 Acre Test Facility

18 In Chester County South Carolina There are 105 fans, each 350 horsepower and 5 ft. 6 in tall. They draw equivalent of 9,000 individual homes and 30 megawatts of power. Each fan can push 230,000 cubic feet of air per minute. This flow volume is 20 times the flow going over Niagara Falls. The top speed of the wind generated in the test chamber is 130 mph. Later renovations to the facility could increase that speed to 175 mph. The turntable that holds the houses has a 55 ft. diameter and a surface area of 2,375 square feet with 52 anchor points embedded for bolting down test buildings.

19 For more Information on Fortified Homes

20 Contact Me Tammie Souza TammieSouzTV

Why FORTIFIED? Tier 1: FORTIFIED Bronze. FORTIFIED Silver. Tier 2: FORTIFIED Gold

Why FORTIFIED? Tier 1: FORTIFIED Bronze. FORTIFIED Silver. Tier 2: FORTIFIED Gold The goal of the FORTIFIED for Existing Homes program is to strengthen your home against specific regional natural hazards through a retrofitting process. Depending on the natural hazard, the program may

More information

Hurricane- Resistance. designations: WHY FORTIFIED? DESIGNATION PROCESS

Hurricane- Resistance. designations: WHY FORTIFIED? DESIGNATION PROCESS Hurricane- Resistance Designation The goal of the FORTIFIED for Existing Homes program is to strengthen your home against specific regional natural hazards through a retrofitting process. Depending on

More information

Builders, Realtors, Roofers and Yourself

Builders, Realtors, Roofers and Yourself What to Ask Builders, Realtors, Roofers and Yourself About Protecting Your Home from Hurricanes, High Winds and Hail. Texas Department of Insurance Asking the following questions will help protect your

More information

THE COST OF RECOVERY COST EFFECTIVE IMPROVEMENTS FOR AFFORDABLE RESILIENCY

THE COST OF RECOVERY COST EFFECTIVE IMPROVEMENTS FOR AFFORDABLE RESILIENCY THE COST OF RECOVERY COST EFFECTIVE IMPROVEMENTS FOR AFFORDABLE RESILIENCY Construction Technologies 10/15/2015 1 Introductions Tiffani Irwin Mgr. Partners in Sustainable Building Habitat for Humanity

More information

RESIDENTIAL RE-ROOFING PERMIT APPLICATION

RESIDENTIAL RE-ROOFING PERMIT APPLICATION RESIDENTIAL RE-ROOFING PERMIT APPLICATION Effective date: October 1, 2007. Note: These requirements apply to residential structures built prior to implementation of the FBC on March 1, 2002. I. LEGAL DESCRIPTION:

More information

Protecting YOUR EXISTING HOME FROM Wind Damage

Protecting YOUR EXISTING HOME FROM Wind Damage Protecting YOUR EXISTING HOME FROM Wind Damage Blueprint for Safety... A Blueprint for Life When severe weather threatens, protecting life and property automatically becomes top priority for millions of

More information

Wall bracing panel requirements

Wall bracing panel requirements Wall bracing panel requirements Building Inspections Exterior and interior walls must be braced in accordance with Minnesota State Building Code section R602 to resist wind loads and racking. Locations,

More information

POST FRAME BUILDING STANDARDS

POST FRAME BUILDING STANDARDS CASS COUNTY, MISSOURI BUILDING CODES, ENVIRONMENTAL HEALTH AND ZONING DEPARTMENT 30508 S. West Outer Road, Harrisonville, MO 64701 P- (816) 380-8134 F- (816) 380-8130 POST FRAME BUILDING STANDARDS 201.3

More information

Pulaski County, Virginia Practical Wall Bracing

Pulaski County, Virginia Practical Wall Bracing Pulaski County, Virginia Practical Wall Bracing Based on the 2012 Virginia Residential Code The information herein provides guidelines for complying with the most common Practical Wall Bracing provisions

More information

GARAGES/ONE-STORY City of Grand Rapids Building Safety Division

GARAGES/ONE-STORY City of Grand Rapids Building Safety Division GARAGES/ONE-STORY City of Grand Rapids Building Safety Division 218-326-7601 www.cityofgrandrapidsmn.com This handout is intended only as a guide and is based in part on the 2015 Minnesota State Building

More information

TABLE OF CONTENTS INTRODUCTION CHAPTER 1 ROOF SYSTEMS 2

TABLE OF CONTENTS INTRODUCTION CHAPTER 1 ROOF SYSTEMS 2 TABLE OF CONTENTS INTRODUCTION I CHAPTER 1 ROOF SYSTEMS 2 Roof Coverings 2 1.1. Roof Shingles 2 1.1.1. Retrofit Technique For Shingles Adhesive Under Shingle Tabs 2 1.2. Re-Roofing 2 1.2.1. Retrofit Techniques

More information

Florida Building Code 6th Edition (2017) High-Velocity Hurricane Zone Uniform Permit Application Form

Florida Building Code 6th Edition (2017) High-Velocity Hurricane Zone Uniform Permit Application Form Are there Gas Vent Stacks? Yes No Type: Natural LPGX FBC SECTION 1524 HIGH-VELOCITY HURRICANE ZONES REQUIRED OWNER S NOTIFICATION FOR ROOFING CONSIDERATIONS 1524.1 Scope. As it pertains to this section,

More information

Advanced Wind Mitigation Methodologies, Pt. 1- Internet Course (5th Edition)

Advanced Wind Mitigation Methodologies, Pt. 1- Internet Course (5th Edition) CODE Specifications TAB: Course Title: Advanced Wind Mitigation Methodologies, Pt. 1- Internet Course (5th Edition) Code Edition: Florida Building Code, Existing Building, 5th Edition (2014) Number of

More information

RESIDENTIAL DETACHED ACCESSORY STRUCTURES

RESIDENTIAL DETACHED ACCESSORY STRUCTURES RESIDENTIAL DETACHED ACCESSORY STRUCTURES *A Building permit is required for any alteration or addition to any existing building or structure. MN State Building Code Section 1300.0120 Subpart 1 Permit

More information

PRACTICAL ENGINEERING. RESISTING Tornado Damage. by Bryan Readling, P.E.

PRACTICAL ENGINEERING. RESISTING Tornado Damage. by Bryan Readling, P.E. PRACTICAL ENGINEERING RESISTING Damage by Bryan Readling, P.E. Wood-frame buildings can take the brunt of all but the biggest storms, but the connections have to be strong On May 4, 2003, a severe weather

More information

Building Division Informational Handout

Building Division Informational Handout CITY OF SAN JOSÉ, CALIFORNIA Building Division Informational Handout Conventional Light Frame Construction Design Provisions 2007 CBC Handout No. 2-21 Published: 1/1/08 Page 1 of 3 This document summarizes

More information

ASCE 7 10 Wind Code Understanding

ASCE 7 10 Wind Code Understanding RE: ASCE-7-10 / 60 + Building Coastal Medical Center 123 Carolina Dr Coastal, NC To Whom It May Concern: ASCE 7 10 Wind Code Understanding There is no test in the roofing industry that blows 110 mph winds

More information

FORTIFIED Home High Wind. Bronze New Roof Requirements

FORTIFIED Home High Wind. Bronze New Roof Requirements THE DECK (PREP MATERIAL, FASTENING) THE ROOF DECK SEALING THE ROOF DECK All existing roof cover and flashings shall be removed; deck shall be a clean, workable surface free from debris. Damaged or rotten

More information

In accordance with the Department of Labor and Industry s statute , Subd. 11,

In accordance with the Department of Labor and Industry s statute , Subd. 11, In accordance with the Department of Labor and Industry s statute 326.0981, Subd. 11, This educadonal offering is recognized by the Minnesota Department of Labor and Industry as sadsfying 1.5 hours of

More information

Home Not Anchored to Foundation

Home Not Anchored to Foundation IDENTIFY WEAKNESSES Home Not Anchored to Foundation Houses that are not bolted to the foundation can move off their foundations during earthquakes. Go down into the crawl space the area between the first

More information

Healing the Hurt: Hurricane Restoration

Healing the Hurt: Hurricane Restoration Healing the Hurt: Hurricane Restoration a presentation by: George M. Fletcher President/CEO Adache Group Architects, Inc. Ft. Lauderdale and Pensacola, FL Healing the Hurt The past couple of hurricane

More information

STRUCTURAL ISSUES IN RESIDENTIAL CONSTRUCTION. Presented by: Susan L. Lasecki P.E., S.E.

STRUCTURAL ISSUES IN RESIDENTIAL CONSTRUCTION. Presented by: Susan L. Lasecki P.E., S.E. STRUCTURAL ISSUES IN RESIDENTIAL CONSTRUCTION Presented by: Susan L. Lasecki P.E., S.E. Presentation Outline Gravity Design Load Paths from Roof to Foundation Roof Framing Floor Framing Wall Framing Lateral

More information

This public resource is maintained by Smart Home America and is available at: SmartHomeAmerica.org/resources/details/code-supplement

This public resource is maintained by Smart Home America and is available at: SmartHomeAmerica.org/resources/details/code-supplement The Coastal Construction Code Supplement was created and adopted by community leaders and Building Code Officials in Coastal Alabama, in partnership with Smart Home America, after being impacted by both

More information

Understanding Wind Uplift Ratings

Understanding Wind Uplift Ratings Page 1 of 5 Home Understanding Wind Uplift Ratings By Stan Choiniere September 1, 2006 What is an FM Approvals wind test, and what do the various wind uplift ratings mean? This question is frequently asked,

More information

Safe Site 1 RUMÖH LÖEN SYURGA LÖEN

Safe Site 1 RUMÖH LÖEN SYURGA LÖEN Safe Site 1 It is not always possible to choose where we live, but understanding the site will help you to make the desicions that will help keep your family safe and protect your house from damage. THINK

More information

TEXAS RESIDENTIAL ROOFS

TEXAS RESIDENTIAL ROOFS INSURANCE INSTITUTE FOR BUSINESS & HOME SAFETY BEST PRACTICES GUIDE Use this guidance to improve the long-term performance of your rf. In the spring of 2016, severe storms ripped through Texas, substantially

More information

NCMA TEK RESIDENTIAL DETAILS FOR HIGH WIND AREAS. TEK 5-11 Details (2003)

NCMA TEK RESIDENTIAL DETAILS FOR HIGH WIND AREAS. TEK 5-11 Details (2003) NCM TEK National Concrete Masonry ssociation an information series from the national authority on concrete masonry technology RESIDENTIL DETILS FOR HIGH WIND RES TEK 5-11 Details (2003) Keywords: architectural

More information

RESIDENTIAL DETACHED STORAGE STRUCTURES (GARAGE)

RESIDENTIAL DETACHED STORAGE STRUCTURES (GARAGE) City Of Austin 500 Fourth Avenue N.E. Austin, Minnesota 55912-3773 Building Department 507-437-9950 Fax 507-437-7101 RESIDENTIAL DETACHED STORAGE STRUCTURES (GARAGE) *A Building permit is required for

More information

High Winds & Tornadoes March 3, 2010

High Winds & Tornadoes March 3, 2010 Town of High Winds & Tornadoes March 3, 2010 Plan Update Flanagan & Associates, LLC Consultants Tulsa, OK www.rdflanagan.com rdflanagan@rdflanagan.com Plan can be reviewed at: www.rdflanagan.com/canadian.html

More information

DESIGNING SAFE ROOMS AND SAFE HOMES WITH LOGIX.

DESIGNING SAFE ROOMS AND SAFE HOMES WITH LOGIX. . Actual ICF-Built Home That Survived Katrina Table of Contents Section Page Overview Logix Wind Resistance Advantages...3 Logix Wall Engineering To 300 MPH Wind Rating...6 Fema-Compliant Design Specifications

More information

Uniform Mitigation Verification Inspection Form Maintain a copy of this form and any documentation provided with the insurance policy

Uniform Mitigation Verification Inspection Form Maintain a copy of this form and any documentation provided with the insurance policy Uniform Mitigation Verification Inspection Form Maintain a copy of this form and any documentation provided with the insurance policy Inspection Date: 04/01/2015 Owner Information Owner Name: JACK AND

More information

ACCESSORY STRUCTURE Building permit information For 1 & 2-family dwellings

ACCESSORY STRUCTURE Building permit information For 1 & 2-family dwellings ACCESSORY STRUCTURE Building permit information For 1 & 2-family dwellings Building Safety Department 400-2 nd Street South St. Cloud, MN 56301 (320) 255-7239 A building permit is required for any accessory

More information

Steel Corrugated Grain Bins

Steel Corrugated Grain Bins Steel Corrugated Grain Bins Tuesday, July 23, 2013, 1:50 p.m. Rob Danielson Associate Engineer Haag Engineering Burnsville, Minn. Robert Danielson is an associate engineer at Haag Engineering Co. in Burnsville,

More information

The Loss Mitigation Grant Program Grants for Home Retrofits using Wind Resistive Devices Saturday June 2, 2007

The Loss Mitigation Grant Program Grants for Home Retrofits using Wind Resistive Devices Saturday June 2, 2007 The Loss Mitigation Grant Program Grants for Home Retrofits using Wind Resistive Devices Saturday June 2, 2007 OUTLINE Introduction to the Loss Mitigation Grant Program Hurricane Probabilities in Hawaii

More information

The following preliminary issues may need to be addressed prior to an application for a building permit.

The following preliminary issues may need to be addressed prior to an application for a building permit. INTRODUCTION Several types of structures are commonly utilized for detached residential accessory and agricultural buildings. The three most common types of structures are conventional light wood framing,

More information

Administrative Changes

Administrative Changes Revised 11/29/06 Knox County Residential Building Codes Significant Changes From The 1995 CABO One And Two Family Dwelling Code To The 2006 International Residential Code All one and two family dwellings

More information

Fortified For Safer Living

Fortified For Safer Living Fortified For Safer Living Module 1: Construction Failure and Damage from Wind and Water Introduction: The Fortified Code Plus Program The Fortified For Safer Living standards is a Code Plus program that

More information

Supplemental Plan Correction Sheet for LA Residential Code Prescriptive Design (2011 LARC)

Supplemental Plan Correction Sheet for LA Residential Code Prescriptive Design (2011 LARC) Supplemental Plan Correction Sheet for LA Residential Code Prescriptive Design (2011 LARC) Plan Check Submittal Date: Plan Check #: Permit App.# Job Address: Applicant: Phone: ( ) P.C. Engineer: Phone:

More information

City of Pembroke Pines 601 City Center Way, Pembroke Pines, FL Tel# Fax# Cover Sheet for Permits Submitted Online

City of Pembroke Pines 601 City Center Way, Pembroke Pines, FL Tel# Fax# Cover Sheet for Permits Submitted Online City of Pembroke Pines 601 City Center Way, Pembroke Pines, FL 33025 Tel#954-435-6502 Fax#954-435-6749 Cover Sheet for Permits Submitted Online All permits Submitted online Must include this completed

More information

Supplemental Plan Correction Sheet for LA Residential Code Prescriptive Design (2014 LARC)

Supplemental Plan Correction Sheet for LA Residential Code Prescriptive Design (2014 LARC) Supplemental Plan Correction Sheet for LA Residential Code Prescriptive Design (2014 LARC) Plan Check Submittal Date: Plan Check #: Permit App.# Job Address: Applicant: Phone: ( ) Plan Check Engineer:

More information

Fortified For Safer Living

Fortified For Safer Living Fortified For Safer Living Module 5: Windborne Debris and Opening Protection In this module we re going to look at windborne debris. It s one of the issues that comes up in situations with high winds.

More information

Above the Flood: Elevating Your Floodprone House. FEMA 347/ May 2000 FEMA

Above the Flood: Elevating Your Floodprone House. FEMA 347/ May 2000 FEMA Above the Flood: Elevating Your Floodprone House FEMA 347/ May 2000 FEMA Cover photograph provided by The Weather Channel. Table of Contents Chapter 1 Introduction...1-1 Chapter 2 Homeowner Options...2-1

More information

Pole Barns. Guides For Homeowners. Why Do I need a Permit? DID YOU KNOW? Charles Abbott Associates. Tips on hiring contractors.

Pole Barns. Guides For Homeowners. Why Do I need a Permit? DID YOU KNOW? Charles Abbott Associates. Tips on hiring contractors. Charles Abbott Associates Pole Barns Guides For Homeowners DID YOU KNOW? No permit is required on structures less than 120 square feet. As owner-builder you are the responsible party of record on such

More information

Details for Exterior Brick Masonry Veneer Supported by Metal Plate Connected Wood Trusses

Details for Exterior Brick Masonry Veneer Supported by Metal Plate Connected Wood Trusses Details for Exterior Brick Masonry Veneer Supported by Metal Plate Connected Wood Trusses Released May 20, 2009 Updated March 9, 2011 Introduction: Wood frame structures with attached brick masonry veneer

More information

Framing & Building Basics. Architectural Drawing & Interior Design

Framing & Building Basics. Architectural Drawing & Interior Design Framing & Building Basics Architectural Drawing & Interior Design Introduction to Framing Once you have your floor plan design, you are now ready to plan for building. In order to accomplish this, you

More information

There have been many instances of aircraft hangars roof systems

There have been many instances of aircraft hangars roof systems Photo 1: A substantial amount of roof deck material blew off these hangars. At one hangar, many trusses also were blown away. Two nearby fighter aircraft appeared to be damaged, as well. There have been

More information

STRUCTURAL DESIGN CRITERIA

STRUCTURAL DESIGN CRITERIA CHAPTER 3 STRUCTURAL DESIGN CRITERIA SECTION 301 GENERAL 301.1 Scope. Loads and load combinations shall be determined in accordance with ASCE 7 unless otherwise noted. Structural elements of the storm

More information

FINAL REPORT OCTOBER 2, 2006

FINAL REPORT OCTOBER 2, 2006 HAZARD MITIGATION TECHNICAL ASSISTANCE PROGRAM CONTRACT NO. EMW-2000-CO-0247 TASK ORDER # 007 STONE HIGH SCHOOL STRUCTURAL WIND RETROFIT ASSESSMENT REPORT FEMA-1604-MS FINAL REPORT OCTOBER 2, 2006 SUBMITTED

More information

4 Structural Performance

4 Structural Performance Section 4 STRUCTURAL PERFORMANCE 4 Structural Performance The BPAT inspected the structural performance of three primary construction types: reinforced concrete, reinforced masonry, and wood-frame. Inspections

More information

hurricane resilient wooden houses safer building and retrofitting guidelines

hurricane resilient wooden houses safer building and retrofitting guidelines hurricane resilient wooden houses safer building and retrofitting guidelines hurricane resilient wooden houses safer building and retrofitting guidelines Author of text and drawings Arch. Celia Izquierdo

More information

EMERGENCY MANAGEMENT PREPAREDNESS AND ASSISTANCE TRUST FUND ARC 4496 Evaluation Questionnaire

EMERGENCY MANAGEMENT PREPAREDNESS AND ASSISTANCE TRUST FUND ARC 4496 Evaluation Questionnaire EMERGENCY MANAGEMENT PREPAREDNESS AND ASSISTANCE TRUST FUND ARC 4496 Evaluation Questionnaire Additional Instructions and Clarifications 1. Please review ARC 4496 before beginning the project identification

More information

Go Green Thermal Imaging, LLC P.O. Box 1523 Hobe Sound, FL Phone: GGTI (4484)

Go Green Thermal Imaging, LLC P.O. Box 1523 Hobe Sound, FL Phone: GGTI (4484) Go Green Thermal Imaging, LLC P.O. Box 1523 Hobe Sound, FL 33475 Phone: 888-984-GGTI (4484) E-mail:CPlaia@GGTISolutions.com Wind Mitigation Walt Leary 637 NE 12th Ter, Unit 7 Boynton Beach, FL 33435 September

More information

Uniform Mitigation Verification Inspection Form Maintain a copy of this form and any documentation provided with the insurance policy

Uniform Mitigation Verification Inspection Form Maintain a copy of this form and any documentation provided with the insurance policy Inspection Date: Uniform Mitigation Verification Inspection Form Maintain a copy of this form and any documentation provided with the insurance policy Owner Information Owner Name: Contact Person: Address:

More information

Uniform Mitigation Verification Inspection Form Maintain a copy of this form and any documentation provided with the insurance policy

Uniform Mitigation Verification Inspection Form Maintain a copy of this form and any documentation provided with the insurance policy Inspection Date: Uniform Mitigation Verification Inspection Form Maintain a copy of this form and any documentation provided with the insurance policy Owner Information Owner Name: Contact Person: Address:

More information

STRUCTURAL DESIGN CRITERIA

STRUCTURAL DESIGN CRITERIA CHAPTER 3 STRUCTURAL DESIGN CRITERIA SECTION 301 GENERAL 301.1 Scope. Loads and load combinations shall be determined in accordance with ASCE 7 unless otherwise noted. Structural elements of the storm

More information

Prescriptive Design for Pole Barns Using the Larimer County Prescriptive Handout

Prescriptive Design for Pole Barns Using the Larimer County Prescriptive Handout Prescriptive Design for Pole Barns Using the Larimer County Prescriptive Handout Building Department 200 W. Oak Street 3 rd Floor Fort Collins, CO 80521 970-498-7700 DEFINITIONS High Wind Areas Those areas

More information

Performance of the Acrylife Roof Vent

Performance of the Acrylife Roof Vent Performance of the Acrylife Roof Vent Murray J. Morrison, PhD, Anne D. Cope, PhD, P.E., Timothy A. Reinhold, PhD, P.E. Report: IBHS-12XX01 August 31, 2012 Prepared for: Acrylife 1165 Stafford Umberger

More information

Keri M. Rayborn Silver Rayborn Consultants P.O. Box 1565 Tallahassee, FL P F

Keri M. Rayborn Silver Rayborn Consultants P.O. Box 1565 Tallahassee, FL P F To: Subject: Cindy Walden RE: To Be Read Into the Record: Notice of Propose Rule Development regarding 690-170.0155 (OIR-B1-1802 "Uniform Mitigation Verification Inspection Form" From: Keri Rayborn [mailto:krayborn@earthlink.net]

More information

You CAN Keep Your Family Safe In Future Earthquakes and Typhoons

You CAN Keep Your Family Safe In Future Earthquakes and Typhoons You CAN Keep Your Family Safe In Future Earthquakes and Typhoons For masonry construction, follow these 7 tips to make your house safer in earthquakes and more resistant to typhoons. 1 2 3 4 5 6 7 1. Build

More information

Andy Schreder CBO Building Official for St Francis, Nowthen

Andy Schreder CBO Building Official for St Francis, Nowthen Andy Schreder CBO Building Official for St Francis, Nowthen Voluntary Compliance Webster says: Voluntary means from one s own choice or consent. Of their own free will Compliance is conformity in fulfilling

More information

PA 201 Impact Test Procedures (written by the Miami-Dade Building Code Compliance Office)

PA 201 Impact Test Procedures (written by the Miami-Dade Building Code Compliance Office) Ask FLASH FLASH Researches your Safety Questions: What should I look for when shopping for window and door protection? It s important to know what to look for before you start shopping. The Florida Alliance

More information

Carroll County Bureau of Permits and Inspection Residential Code Compliance Guidelines Detached Garage

Carroll County Bureau of Permits and Inspection Residential Code Compliance Guidelines Detached Garage Carroll County Bureau of Permits and Inspection Residential Code Compliance Guidelines Detached Garage The following list of code requirements is intended to assist you in complying with the Code of Public

More information

Custom 22' x 40' - 16' Tall Garage Plan #g227 By SDS-CAD Specialized Design Systems

Custom 22' x 40' - 16' Tall Garage Plan #g227 By SDS-CAD Specialized Design Systems P O Box 34 Mendon, Utah Custom 22' x 40' - 16' Tall Garage Plan #g22 By Page 1 Title Page Page 2 Main Floor Plan Page 3 Foundation Plan Page 4 Elevation Views Page 5 Framing and Details Page 6 Typical

More information

hurricane resilient wooden houses safer building and retrofitting guidelines

hurricane resilient wooden houses safer building and retrofitting guidelines hurricane resilient wooden houses safer building and retrofitting guidelines hurricane resilient wooden houses safer building and retrofitting guidelines Publisher Habitat for Humanity International (HFHI).

More information

Residential Plan Review for New One and Two Family Dwellings

Residential Plan Review for New One and Two Family Dwellings The following is a list of items that are normally included in a set of construction drawings for one and two family dwellings. The items in bold depict those items that will be reviewed for during the

More information

2001 COMPANY Co., ASCE 7 98 Wind Uplift Evaluation Form (Ask for Form - ASCE7dpi.doc)

2001 COMPANY Co., ASCE 7 98 Wind Uplift Evaluation Form (Ask for Form - ASCE7dpi.doc) 2001 COMPANY 2001 Co., ASCE 7 98 Wind Uplift Evaluation Form (Ask for Form - ASCE7dpi.doc) To determine a roof s wind uplift PSF (pounds per square foot) Pressure requirement for building code compliance.

More information

Custom 30 x 48-14' Tall Garage Plan #g226 By SDS-CAD Specialized Design Systems

Custom 30 x 48-14' Tall Garage Plan #g226 By SDS-CAD Specialized Design Systems P O Box 34 Mendon, Utah Custom 30 x 48-14' Tall Garage Plan #g226 By Page 1 Title Page Page 2 Main Floor Plan Page 3 Foundation Plan Page 4 Elevation Views Page 5 Framing and Details Page 6 Typical Section

More information

MAIN FLOOR PLAN. #G x 14 x 8 Shed - Chicken Coop By SDS-CAD Specialized Design Systems 10'-0" 3'-0" 1'-0" 14'-0" 14'-0" 1'-0" 6'-0" 3'-0"

MAIN FLOOR PLAN. #G x 14 x 8 Shed - Chicken Coop By SDS-CAD Specialized Design Systems 10'-0 3'-0 1'-0 14'-0 14'-0 1'-0 6'-0 3'-0 10'-0" BUILDING CONTRACTOR/HOME OWNER TO REVIEW AND VERIFY ALL DIMENSIONS, SPECS, AND CONNECTIONS BEFORE CONSTRUCTION BEGINS. BARN TO BE BUILT AS PER LOCAL CODE REQUIREMENTS 14'-0" BWP BWP BWP ABWP 101

More information

Uniform Mitigation Verification Inspection Form Maintain a copy of this form and any documentation provided with the insurance policy

Uniform Mitigation Verification Inspection Form Maintain a copy of this form and any documentation provided with the insurance policy Inspection Date: 12/07/2018 Uniform Mitigation Verification Inspection Form Maintain a copy of this form and any documentation provided with the insurance policy Owner Information Owner Name: The Oaks

More information

HUMBOLDT COUNTY BUILDING & SAFETY DEPARTMENT CITY OF WINNEMUCCA BUILDING DEPARTMENT

HUMBOLDT COUNTY BUILDING & SAFETY DEPARTMENT CITY OF WINNEMUCCA BUILDING DEPARTMENT HUMBOLDT COUNTY BUILDING & SAFETY DEPARTMENT CITY OF WINNEMUCCA BUILDING DEPARTMENT FOR PRIVATE THREE-SIDED POST FRAMED (NON-ENGINEERED) OUTBUILDINGS LOCATED ON RESIDENTIAL LOTS ONLY Buildings must meet

More information

DATE:6/18/2013 INSPECTOR: ELEVATION

DATE:6/18/2013 INSPECTOR: ELEVATION DATE:6/18/2013 INSPECTOR: C ELEVATION DATE:6/18/2013 ROOF DECK ATTACHMENT ROOF TO WALL OPENING PROTECTION NA DOCUMENTS/ PERMITS, TITUSVILLE 32780 Permit #12-768 Applied: 5.14.12 Issued: 5.14.12 Final:

More information

Owner Information. Inspection Date:

Owner Information. Inspection Date: Draft Proposed Near-Term Changes for OIR Review Applied Research Associates, F. Lavelle, 5/27/11 Uniform Mitigation Verification Inspection Form Maintain a copy of this form with the insurance policy Inspection

More information

Hurricane wind shelter retrofit room standards for existing houses

Hurricane wind shelter retrofit room standards for existing houses Safety and Security Engineering 653 Hurricane wind shelter retrofit room standards for existing houses N. Yazdani 1, T. Townsend 1 & D. KilCollins 2 1 Florida A & M University- Florida State College of

More information

AEU-81. Being able to locate the curing rames close to the field reduces transport time at the busy harvest time. Possibly filling directly from

AEU-81. Being able to locate the curing rames close to the field reduces transport time at the busy harvest time. Possibly filling directly from Moveable Curing Frames Low cost, low labor, moveable, sturdy, dependable and easily covered -- is this an ideal curing structure? Can it be done? Seeking such a design is the aim of ongoing studies using

More information

Uniform Mitigation Verification Inspection Form Maintain a copy of this form and any documentation provided with the insurance policy

Uniform Mitigation Verification Inspection Form Maintain a copy of this form and any documentation provided with the insurance policy Inspection Date: Uniform Mitigation Verification Inspection Form Maintain a copy of this form and any documentation provided with the insurance policy Jul 16, 2012 Owner Information Owner Name: John Miller

More information

ACCESSORY STRUCTURES (Garages/Sheds) BUILDING AND ZONING REQUIREMENTS (REVISED 4/21/16)

ACCESSORY STRUCTURES (Garages/Sheds) BUILDING AND ZONING REQUIREMENTS (REVISED 4/21/16) ACCESSORY STRUCTURES (Garages/Sheds) BUILDING AND ZONING REQUIREMENTS (REVISED 4/21/16) NOTE: No building permit shall be issued for the construction of more than one (1) detached accessory building on

More information

Uniform Mitigation Verification Inspection Form Maintain a copy of this form and any documentation provided with the insurance policy

Uniform Mitigation Verification Inspection Form Maintain a copy of this form and any documentation provided with the insurance policy Inspection Date: 05/24/2017 Uniform Mitigation Verification Inspection Form Maintain a copy of this form and any documentation provided with the insurance policy Owner Information Owner Name: Banana Bay

More information

R Code and Commentary for 2012 NC Residential Code final 03/06/13

R Code and Commentary for 2012 NC Residential Code final 03/06/13 R602.10 Code and Commentary for 2012 NC Residential Code final 03/06/13 Commentary italicized and printed in red 1. Section R602.10 -- provides charging language for two simplified bracing approaches (isolated

More information

#G445 Plans, 48'x28' x 10' detached garage with bonus room By SDS-CAD Specialized Design Systems

#G445 Plans, 48'x28' x 10' detached garage with bonus room By SDS-CAD Specialized Design Systems Architectural asphalt shingles and horizontal True Wood 7" Reveal siding over structural panel. Nailing schedule is 6" on ends 12" on centers 6d nails. Trusses are engineered on Bonus attic trusses 24"

More information

FIELD COPY ATTACHMENT

FIELD COPY ATTACHMENT FIELD COPY ATTACHMENT The released plans for the project must be on site and available to the inspectors at all times. No inspection will be done without the released field plans. If you have any questions,

More information

Heel Blocking Requirements and Capacity Analysis. Overview Revised 3/22/2017

Heel Blocking Requirements and Capacity Analysis. Overview Revised 3/22/2017 Heel Blocking Requirements and Capacity Analysis Overview Revised 3/22/2017 SBCA has been the voice of the structural building components industry since 1983, providing educational programs and technical

More information

Minimizing Water Intrusion Through Roof Vents in High-Wind Regions

Minimizing Water Intrusion Through Roof Vents in High-Wind Regions Minimizing Water Intrusion Through Roof Vents in High-Wind Regions http://www.fema.gov HURRICANE IKE RECOVERY ADVISORY Purpose: To recommend practices for minimizing water intrusion through roof vent systems

More information

Christopher North Builders, INC.

Christopher North Builders, INC. Christopher North Builders, INC. 239-825-9155 Naples, Florida 34108 chrisnorthnaples@gmail.com Inspection Date: Uniform Mitigation Verification Inspection Form Maintain a copy of this form and any documentation

More information

Can we build disaster resilient communties? A new look at wind effects on houses

Can we build disaster resilient communties? A new look at wind effects on houses Can we build disaster resilient communties? A new look at wind effects on houses Can we build disaster resilient communties? A new look at wind effects on houses Gregory A. Kopp Boundary Layer Wind Tunnel

More information

Safety on Heights: Our Policy

Safety on Heights: Our Policy 11/17/14 Safety on Heights: Our Policy Only volunteers over the age of 18 are allowed to work on heights of more than six feet off the ground. This includes all work on scaffolds. Only volunteers who are

More information

Christopher North Builders INC

Christopher North Builders INC Christopher North Builders INC Naples, Florida 239-825-9155 chrisnorthnaples@gmail.com Inspection Date: Uniform Mitigation Verification Inspection Form Maintain a copy of this form and any documentation

More information

Go Green Thermal Imaging, LLC P.O. Box 1523 Hobe Sound, FL Phone: GGTI (4484)

Go Green Thermal Imaging, LLC P.O. Box 1523 Hobe Sound, FL Phone: GGTI (4484) Go Green Thermal Imaging, LLC P.O. Box 1523 Hobe Sound, FL 33475 Phone: 888-984-GGTI (4484) E-mail:CPlaia@GGTISolutions.com Wind Mitigation Richard & Andrea Freedman 182 Eagle Dr. Jupiter, FL 33477 March

More information

SECTION WOOD FRAMING. A. Includes But Not Limited To 1. Furnish and install wood framing and blocking as described in Contract Documents.

SECTION WOOD FRAMING. A. Includes But Not Limited To 1. Furnish and install wood framing and blocking as described in Contract Documents. SECTION 06110 WOOD FRAMING PART 1 GENERAL 1.1 SUMMARY A. Includes But Not Limited To 1. Furnish and install wood framing and blocking as described in Contract Documents. B. Products Installed But Not Supplied

More information

COMMERCIAL WINDSTORM MITIGATION INSPECTION REPORT Prepared for: Boca Vista Condominium Association, Inc th Avenue Madeira Beach, FL 33708

COMMERCIAL WINDSTORM MITIGATION INSPECTION REPORT Prepared for: Boca Vista Condominium Association, Inc th Avenue Madeira Beach, FL 33708 Insurance Appraisals Reserve Studies Wind Mitigation COMMERCIAL WINDSTORM MITIGATION INSPECTION REPORT Prepared for: Boca Vista Condominium Association, Inc. 401 150th Avenue Madeira Beach, FL 33708 As

More information

Success with 2012 NC Energy Conservation Code in North Carolina: Tech Tips for Builders. insulation

Success with 2012 NC Energy Conservation Code in North Carolina: Tech Tips for Builders. insulation Success with 2012 NC Energy Conservation Code in North Carolina: Tech Tips for Builders insulation Copyright 2014 Advanced Energy. All Rights Reserved TEch Tips: 1. Install insulation to meet the 2012

More information

PRODUCT: Structural Insulated Panels (SIPs) DIVISION: Wood, Plastics, and Composites (06) SECTION: Structural Panels ( )

PRODUCT: Structural Insulated Panels (SIPs) DIVISION: Wood, Plastics, and Composites (06) SECTION: Structural Panels ( ) PRODUCT: Structural Insulated Panels (SIPs) DIVISION: Wood, Plastics, and Composites (06) SECTION: Structural Panels (06 12 00) Report Holder ACME Panel Company 1905 West Main St. Radford, VA 24141 Manufacturing

More information

STRUCTURAL CONDITION ASSESSMENT

STRUCTURAL CONDITION ASSESSMENT STRUCTURAL CONDITION ASSESSMENT ALLEN JAY ROCK GYM 1201 FAIRFIELD ROAD HIGH POINT, NC Prepared for: Prepared by: Guilford County Schools 617 West Market Street Greensboro, NC Adrian S. Durham, PE, SE,

More information

SUBJECT: NEW 2000 INTERNATIONAL RESIDENTIAL CODE (IRC) DATE:

SUBJECT: NEW 2000 INTERNATIONAL RESIDENTIAL CODE (IRC) DATE: IRC CODE UPDATES TO: RESIDENTIAL BUILDING CONTRACTORS FROM: GARY STABER, BUILDING OFFICIAL SUBJECT: NEW 2000 INTERNATIONAL RESIDENTIAL CODE (IRC) DATE: 6/1/2003 INTERNATIONAL RESIDENTIAL CODE (IRC) APPLICABILITY:

More information

GARAGE MAIN FLOOR PLAN

GARAGE MAIN FLOOR PLAN BUILDING CONTRACTOR/HOME OWNER TO REVIEW AND VERIFY ALL DIMENSIONS, SPECS, AND CONNECTIONS BEFORE CONSTRUCTION BEGINS. SHED TO BE BUILT AS PER IRC, UBC OR CURRENT LOCAL CODE To the best of my knowledge

More information

SECTION R614 STRUCTURAL INSULATED PANEL WALL CONSTRUCTION

SECTION R614 STRUCTURAL INSULATED PANEL WALL CONSTRUCTION Section R614 Add new section to read as shown: (RB34-06/07) SECTION R614 STRUCTURAL INSULATED PANEL WALL CONSTRUCTION R614.1 General. Structural insulated panel (SIP) walls shall be designed in accordance

More information

Kerry S. Lee, MBA, P.E., MASCE 1 Jessica M. Caffey, M.S. 2 Daniel M. Killian, B.S., P.E. 3

Kerry S. Lee, MBA, P.E., MASCE 1 Jessica M. Caffey, M.S. 2 Daniel M. Killian, B.S., P.E. 3 Structural Evaluation Procedures and Case Studies of Damage Related to Wind Storms, Tornadoes, and Hurricanes Kerry S. Lee, MBA, P.E., MASCE 1 Jessica M. Caffey, M.S. 2 Daniel M. Killian, B.S., P.E. 3

More information

1. Asphalt / Fiberglass Shingle / / 2. Concrete / Clay Tile 05_/_01 /_ Metal / / 4. Built Up / / 5. Membrane / / 6.

1. Asphalt / Fiberglass Shingle / / 2. Concrete / Clay Tile 05_/_01 /_ Metal / / 4. Built Up / / 5. Membrane / / 6. Uniform Mitigation Verification Inspection Form Maintain a copy of this form and any documentation with the insurance policy Inspection Date: 14-Aug-14 Owner Information Owner Name: Contact Person: Brett

More information

STRUCTURAL ENGINEERING S TOP TEN LIST

STRUCTURAL ENGINEERING S TOP TEN LIST STRUCTURAL ENGINEERING S TOP TEN LIST #1. Two Story Commercial Building Collapsed After 2 Years We investigated a 2 story commercial building collapse. The entire building collapsed to the ground. Fortunately

More information

ACCESSORY BUILDING. Building Permit Requirements: (must be completed before submitting application)

ACCESSORY BUILDING. Building Permit Requirements: (must be completed before submitting application) ACCESSORY BUILDING Before your application can be deemed complete and ready for processing you will need the following: (Please hand in entire application package including this cover sheet) Zoning- check

More information