This paper will described the preparation, execution, achievement and lessons learned from this 4 wells pilot project in offshore South China Sea.

Size: px
Start display at page:

Download "This paper will described the preparation, execution, achievement and lessons learned from this 4 wells pilot project in offshore South China Sea."

Transcription

1 SPE Case History: Pilot Project with Coiled Tubing Drilling in Offshore South China Sea A.A. Abdul Rahman, SPE;, N.E. Hamzah, SPE; N. Ahmad Fauzi; N. Safiin, SPE; M.Z. Khalid, SPE; N. Syaifullah, SPE; PETRONAS Carigali Sdn. Bhd; J.R. Jenie, SPE; H.E. Hariry, SPE; Schlumberger Copyright 2012, Society of Petroleum Engineers This paper was prepared for presentation at the SPE/ICoTA Coiled Tubing & Well Intervention Conference & Exhibition held in The Woodlands, Texas, USA, March This paper was selected for presentation by an SPE program committee following review of information contained in an abstract submitted by the author(s). Contents of the paper have not been reviewed by the Society of Petroleum Engineers and are subject to correction by the author(s). The material does not necessarily reflect any position of the Society of Petroleum Engineers, its officers, or members. Electronic reproduction, distribution, or storage of any part of this paper without the written consent of the Society of Petroleum Engineers is prohibited. Permission to reproduce in print is restricted to an abstract of not more than 300 words; illustrations may not be copied. The abstract must contain conspicuous acknowledgment of SPE copyright. Abstract The sustained and relatively high value of oil and natural gas has resulted in an unprecedented level of drilling activity and implementation of innovative methods to recover as much hydrocarbon as possible, and as quickly as possible. The resulting demand for conventional drilling rigs for programs has forced the rates high and the availability low, making use of the units difficult to justify for use in declining fields with less significant amounts of recoverable product. The by-passed reserves remaining accessible in these depleted fields exist in volumes worthy of pursuit, but must be done economically. In many fields, operators, either intentionally or unintentionally, bypass pay zones during initial development by focusing only on the best zones. Accessing bypassed thinly laminated formations can be economically attractive but poses several challenges, especially due to aged platforms and completion string in place, also offshore environment is adding its own challenges. Coiled Tubing Drilling (CTD) has yet to establish itself in an offshore environment. Numerous one-off projects have been tried, but commitment was never made to a number of wells to see through the learning curve and realize the potential of the application. Offshore South China Sea have a huge quantity of candidates on existing installations, installations that, due to water depths and sub sea conditions require large, expensive rigs to drill or re-enter wells. Technically the wells can be accessed with coiled tubing with drilling parameters seen regularly in other projects. The challenges for this pilot project will be equipment specification and set up, efficiently exiting the casing, and management of wellbore stability in open hole drilling and completion techniques. The main objective of this pilot project is to bring proven technology to offshore environment to access small bypassed reserves economically and provide an alternative to conventional drilling. The well candidates were selected with strict work scope to avoid going beyond the regular CTD application to ensure learning curve and lessons learned can be implemented throughout the project and achieve the objective. This paper will described the preparation, execution, achievement and lessons learned from this 4 wells pilot project in offshore South China Sea. Introduction PETRONAS Carigali Sdn Bhd operates a vast network of oil and gas producing fields, facilities and infrastructures in Offshore South China Sea, consist of more than 70 oil producing fields and more than 40 gas producing fields, specifically for Malaysia s production network.

2 2 SPE The main producing fields, notably in offshore Peninsular Malaysia have been in production for an average of years from over 100 platform structures. However, during recent years, the rate of production from these matured fields has decline. As the oil demand keeps increasing, the operators are continuously trying to find ways to boost up the performance of these fields. However, cost-effective development strategy of mature offshore fields has been a challenging objective in Malaysia. Conventional drilling and production techniques have not been able to produce the reserves at commercial rates because of the small and highly compartmentalized reserves. Drilling a new well to access small hydrocarbon pockets has proven uneconomical due to requiring offshore drilling rigs to drill or re-enter wells. Furthermore, the ageing platform and wells increase the risks and costs associated to safely drain the hydrocarbon. Hence, the initiative of utilizing an alternative drilling technology and techniques which involves minimum intervention on the existing wells and facilities were assessed and valued against the economic limit of the field. Re-entry drilling using existing wellbores was determined to be the best option to access those unexploited, compartmentalized pockets of hydrocarbon and coiled tubing (CT) drilling applications were evaluated. CTD, a pilot project of PETRONAS Carigali Sdn Bhd intends to maximize ultimate oil recovery by adding new drainage points in existing main producing reservoir by tapping directly to the undrained / bypassed reserves, with reduced time and costs to achieve targets. By benchmarking the performance from a similar project done in other parts of the world, this project was executed in a successful manner, and proven the feasibility of the technology to access the bypassed oil, offshore Malaysia. Overview of Coiled Tubing Drilling CTD was started in 1991 with a horizontal sidetrack re-entry drilled by Oryx Energy in the Austin Chalk of Texas. CTD can be described as drilling through exixting completion and allows the CT conduit to directly access the pay zones. CTD has proven track record over 600 directionally drilled wells, successfully completed in Alaska, USA. CTD experience is also being shared around the world and successfully being implemented in Canada, US Land, Russia, North Africa, Middle East and recently South East Asia. The application of CTD had an enormous growth over the last 10 years, moving from what was considered a niche market to mainstream drilling operation in several geographic locations. The re-entry work, the initial driver for the application, still exists and is thriving. The offshore application of CTD has been attempted for numerous years, with several projects done in South America, the North Sea and the Gulf of Mexico. While some of these projects met with qualified success, a sustained program has not been realized. This was primarily been due to one-well pilots with no chance for learning curves to materialize. Cyclic conventional rig rates have also been the contributing factor in the lack of progress in CTD application in an offshore environment. The drilling with CT has evolved from an experimental technique to a proven technology now used for nearly half of new wells on the North Slope of Alaska, USA. Alaskan Operators recognized the value in the lower cost/bbl for the CTD unit being able to sidetrack without a workover unit. Building on the Alaska success, other re-entry projects were started in the Middle East system moving within several United Arab Emirates fields, Saudi Arabia and eventually in South East Asia. All re-entry projects benefit from similar types of well design, utilizing exisiting surface facilities and the learning curves from continuous operations. Project Definition and Set Up This section will cover the candidate selection process, reservoir target selection, downhole and surface equipment selection, and operational risks based on the lessons learned and experiences from other similar ongoing CTD projects. Candidate selection The objective of the CTD re-entry campaign is to introduce the CTD as a cost effective solution to improve hydrocarbon recovery from area A. This process will evaluate and rank candidate wells based on CTD operating envelope from other ongoing projects that have similarities with these wells. This is to minimize the risk involved, both mechanically and financially to help justify the continuity of the application.

3 SPE In ensuring the level of success of this pilot project is positively high, the selection criteria were developed based on similar projects in other part of the world. The criterias were as follows: 1. Remaining reserves limit > 0.5mmstb 2. Field maturity and accessibility to areas of undrained / bypassed reservoir 3. Formation thickness > 10m 4. Reservoir target reachability < 1000m from kick off point to total depth 5. Completion tubing size > 3-1/2 6. Mechanical condition of existing tubing 7. Platform condition and readiness Fig. 1: Candidate selection method From 2 fields in Area A, field X and Y, theree were initially a total of 17 wells which passed through the first screening, and these were the pool of candidates that went through further assessment. The candidates then divided into 3 types of completions which dictate the complexity of the casing exit operations (Fig. 2): 1. Thru tubing and set in casing exit. This will require thru tubing whipstock which the anchor will expand and set inside the casing. There is limitation of the anchor expansion, such as 3 ½ tubing and 7 casing, for that scenario, cement kick off or set the whipstock inside pilot hole is the options. 2. Tubing exit with monobore whipstock. This category will require setting the whipstock inside the tubing and milling window thru tubing and casing (dual exit). 3. Dual completion, exit thru short string and casing. Fig. 2: Types of casing exits

4 4 SPE Reservoir target selection The Company reservoir team had few target formations considered for the pool of candidates and with those formations, the vertical depth requirements allowed the estimation of where the well was to be exited for accessing the target zones. The positioning of gas lift valves, packers, centralizers, blast joint and casing set depths were all reviewed to determine if window placement could be done without overwhelming challenges such as triple casing exits (windows). The first consideration for the selection of a prospective casing exit point within the well is to view the well completion schematic and determine the least complicated means of exiting the casing. Multiple methods are possible to accommodate the design of a trajectory to target, but with the casing exit being a critical component within the program, selection of a method that minimizes the amount of effort, hardware, cost and risk is important. After initial designation of a casing exit point has been made, the second concern is the formation to be accessed upon milling of the window. By viewing gammaray logs from the original drilling of the well, the point chosen on the mechanical criterion is viewed, noting the gammaray results for presence of less desirable components such as unstable or problematic shale section. The design of the trajectory required consideration of several different items. As mentioned above, the exit point was determined with respect to the mechanical status of the existing completion, quality of cement behind casing, casing / production tubing collar locations and the formation to be entered behind casing. Having chosen a casing exit point, the next step in the process is to determine if the vertical depth target can be attained from the chosen point with a reasonable rate of build with the drilling assembly. Build up rates as high as 60 /100 feet are within the operating envelope of CTD operation; however, these require a thorough understanding of the behavior of the bottom hole assembly in the given formation, an understanding that comes only with experience. This candidate selection will keep the designed build up rate to less than 40 /100 feet, with most of the wells being in the 20s or 30s. Surface Equipment Selection Selection of CTD surface equipment is based on several considerations, as described below; 1. Zoned requirement Working on platform requires zoned equipment which escalates the complexity, availability and compatibility between parties. 2. Size and weight restriction Very important considerations were given to ensure load distribution to platform was not exceeded and HSE requirement is priority when planning equipment layout. 3. Platform readiness (structural study and modification) Aged platform may require platform strengthening and integrity check on the existing flow lines. 4. CT Pipe size selection and CT Injector capability Given the reservoir target depth and existing completion limitation, 2 CT with specific tapered design is selected based on all candidates to optimize Weight on Bit (WOB), overpull and hydraulic requirement. 5/16 monocable is required to control the CTD Bottom Hole Assembly (BHA) and data transmission. An injector head with maximum pulling capacity of 80,000 lbs is selected based on CT forces simulation. 5. Hydraulic horsepower requirement for mud pumps From hydraulic simulation, hydraulic horsepower is determined and CTD pump is selected based on the job characteristic, low flow rate and high pressure, and also continuous pumping. 6. CTD Sub structure or tower A CTD Sub Structure serves multiple purposes in a coiled tubing drilling operation, including support the coiled tubing injector head without crane attachment, to provide a platform for personnel to work (rig floor), act as a platform for safe working on pressure control and injector components, to provide three dimensional movement of the injector head for deployment and retrieval of the BHAs. 7. Drilling Fluids handling surface equipment Lower drilling fluids volume and lower pumping rate requirement, compared to conventional drilling activities, has allowed smaller footprint of surface equipment to be used for CTD. However, solid control in drilling mud is very crucial in maintaining hole cleaning and also as this will significantly affect the applicable WOB transferred to the end of CT BHA, those will limit the reach-ability. An integrated fit-for-purpose modular system especially developed for CTD application is proposed for this pilot project. In general, the surface equipment handling consists of shaker assembly, centrifuge, mud gas separator and compartmentalized active tanks (total 150bbls).

5 SPE CTD Bottom Holes Assembly (BHA) Selection All the selected wells have 3-1/2 completions, therefore 2 3/8 OD wired-ctd BHA is chosen for this pilot project. Casing exit BHA, whichever casing exit method used, will be done with CT milling assembly with diamond speed mill as the bit. The selection of diamond speed mill is based on success history where non aggressive surface of the bit is more forgiving when attempting to initiate the window. For build and lateral section of openhole drilling, 2.7 x 3 Bi-Center bit is chosen to maximize openhole size to allow running 2-3/8 completion liner afterwards. This drilling BHA includes Gamma ray, directional sensor, electric controlled orienter, and resistivity sub (as required basis). Openhole logging BHA is using CT logging head and Reservoir Saturation Tool (with 2 knuckle joints to assist in high dogleg section). The completion BHA includes hydraulic release, liner top, swellable packer, and 2-3/8 pre-drilled liner with flush joint connection. Drilling Mud Selection of drilling mud is based on below requirements and considerations: Weight Transfer to Bit Given the limited available forces when drilling with CT, the lubricity of a drilling fluid is critical for a successful well. Minimizing solids in the fluids and maximizing the lubricity factor by addition of friction reduction agents has proven highly successful Hole Cleaning Capability - The inability to rotate the string results in a higher risk of solids bedding while drilling with CT, and the fluid properties must take this in to account. Additionally, because higher circulation pressures translate to less CT pipe life, the lower circulation pressures help in minimizing costs, and the fluids must balance solids suspension capability with friction pressures. Minimizing Formation Damage A fluid used to drill the reservoir is either formulated with a minimum amount of solids or incorporates properly sized bridging agents to ensure minimal adverse effect on reservoir permeability. Borehole Stability A suitable drilling fluid properties need to be formulated to provide enough overbalance to ensure borehole stability while drilling and tripping without compromising the differential sticking risks. Based on the above requirements and also considerations of previous CTD history at other locations with similar formation and scope of works, a solids-free mud system was chosen for this pilot project. Offshore Structure / Platform Assessment One of the important parameters during candidates selection is the existing offshore structure to support all equipment required, especially the crane and deck limitation. These criterias were established to minimize the complexity of the equipment set up and simplify the job execution method. After detailed evaluation on several platforms, only two (2) platforms are considered meeting the objectives with some minor modification required. Both platform diagrams are shown on fig. 3 and 4.

6 6 SPE Platform North Reel w/ CT Pipe basket 0.5m MWD tool Mud Lab Cabin BHA basket Escape Route MWD tool Pipe basket Mud logging Container Platform North compressor Reel w/ CT A-04 CT shop Reel Back Control Interf ace Up Cabin HPU & HPU Escape Route Mud Gas Separ ator Pumps Skid Choke Panel Panel Charge Pump Shale Shakers and Tanks Mixer MWD cabin Power Mixer Pack 4.2m Platform West Alternative Escape Route Pump Pump Mixer Power Pack Pumps Skid Shale Shakers and Tanks Mud Gas Separ ator Charge Pump Panel Panel Choke Mixer Platform East Mud logger Office 4.2m CTD Office MWD cabin Mud Logging Genset Mud Lab Genset Genset Fluid tank Fluid tank Fluid tank Fig. 3 and 4: Platform A and B equipment layout Project team set up Finding the right people to do this pilot project was essential and not available within the South East Asia region as it is the first project of its kind in the area. Resources were mobilized from other CTD Projects around the world. As other projects had their resources requirement, a customized plan was put in place to bridge the knowledge gap by having a full dedicated team with specific experience with the technology and operations, supported with customized classroom and safety training done on specifc requirement basis. Prior to actual job execution, a mock up test for the equipment was done in the onshore base to simulate the actual set up offshore for crews familiarization and serves as a pre-mobilization integration between project team members. With all the design and operational aspects accounted for in the feasibility study, and supported by the successful pre-job evaluation and set up, the CTD pilot project was ready to commence drilling 4 wells in 2 fields in the South China Sea within 6 months from the initial mobilization from around the world. Execution Execution phase is divided into 2 programs, pre-ctd and the CTD program. The pre-ctd program is designed to prepare the CTD candidate wells to be ready for sidetrack. This pre-ctd was done while mobilizing the CTD package in to the country. The well preparations utilize the conventional CTU, slickline and eline equipment to Plug and Abandon (P&A) the well and set the whipstock. The scope of work to prepare the candidate wells mainly are: 1. Coiled Tubing Unit: clean out, pumping cement, milling cement, milling nipple profile 2. Slickline equipment: Tubing integrity, caliper run, drift run, impression block 3. Eline equipment: orient and set whipstock, set bridge plug or TT bridge plug, set cement retainer, 1-11/16 Cement Bond Log (CBL)

7 SPE The CTD program was planned with 4 main steps with each step has key objective: window milling, drill build and tangent section, openhole logging, and completion and well reinstatement. 1. Window milling The objective is to provide access to the formation. The plan was to make two runs, the first one was to create window in tubing and or casing and the second one is to dress or ream the window. 2. Drill build and tangent section This drilling openhole was planned with 2 drilling BHA: 1 st BHA is to drill build section to landing point with bent housing. Second BHA is for tangent section, which is to drill to planned final depth with reduced angle bent housing. 3. Openhole logging. To determine the Gas Oil Contact (GOC) and swellable packer placement, an additional RST tool run is needed and also 1 additional clean out run with drilling BHA to prepare the openhole for liner running. 4. Completion and well reinstatement The plan was to make up pre drilled liner with pre-determined depth for swellable packers for isolation, run it to total depth and release the liner in the openhole. Drilling mud will be displaced with diesel and slick line will open the gas lift mandrels prior handing over to production. Well No. 1 The first well selected was based on the complexity casing exit method and drilling trajectory to ensure high degree of success and confidence. This well is also located in the larger platform of the two to reduce the potential set up issues due to first mobilization. With the existing well configuration is 3 ½ tubing and the target Kick Off Point (KOP) is inside 4 ½ casing, this require thru tubing whipstock to set inside 4 ½ casing. The plan is to set cement plug on the existing perforation in 4 ½ casing and leave Top Of Cement (TOC) below KOP (Fig. 5). Pre CTD program: Using a conventional CTU, the No-go nipple was milled from 2.69 to 2.8 ID to allow window milling assembly to pass through. Eline run with thru tubing CBL was then done 20m above and below planned KOP to evaluate the cement quality behind the 4 1/2 casing. Then, the Plug and Abandon of the perforation inside 4 ½ casing commenced, where cement was spot squeezed as necessary. With the top of cement (TOC) was slightly higher than planned, milling cement was performed with underreamer. Using E-line, the thru tubing whipstock with oriented setting tool was set to 10deg high side. Window milling: The window in 4 ½ casing (single exit) was planned to be milled with straight motor and speed mill, however had trouble to start milling due to off-centered whipstock setting position. Decisions made to set second thru tubing whipstock with CTD BHA, and confirmed the correct placement with slickline Lead Impression Block (LIB). Milled the 4 ½ casing with straight motor and speed mill without any issue using seawater. Performed Leak Off Test (LOT) and swap to water based mud system prior Pulling Out Of the Hole (POOH). Drill build and tangent section: The first build drilling BHA was planned with 0.8 bent motor and bicenter bit 2.7 x 3 PDC. Upon drilling 20m openhole, experienced stuck pipe which prognosed due to differential sticking. Displace the annulus with lighter density fluid, diesel and got free. Continued drilling with lower Equivalent Circulating Density (ECD) and experienced another stuck pipe, freed with same method to get unstuck. Decision was made to swap to Synthetic Based Mud (SBM) to achieve lower ECD. Continued drilling, however experienced 2 stuck pipe incidents, which led to hole packed off. Total openhole drilled was 167m, with total 4 BHA changeout due to electronic malfunction. After several attempts made to to free the pipe, decision was made to chemical cut CT string. Cut the CT string at surface, pull the e-line cable from inside CT string, ran 6 tubing punches to re-gain circulation, swapped fluid to water based, performed chemical cut and rig down.

8 8 SPE Fig. 5, 6 and 7: Well 1, 2, and 3 diagrams Well No. 2 The second well was located on smaller platform in another field Y with different set up due to the limitation of crane capacity and layout. The existing well configuration is 3 ½ tubing inside 7 casing, with the perforation are below lower production packer and in between upper and below production packers. The planned KOP is above the upper production packer, which needs to mill the 3 ½ tubing and 7 casing (dual exit window). The plan is Plug and Abandon (P&A) both perforation with cement to provide isolation, then set monobore whipstock inside 3 ½ tubing above upper production packer for window milling (Fig. 6). Pre CTD program: First cement plug thru CT was to sealed the lowest perforation inside 7 casing, confirmed TOC and pressure tested. For the lower cement packer job, a bridge plug was set with eline inside tubing right above the lower production packer and performed tubing punch to gain circulation to tubing-casing annulus. A cement retainer was set above the tubing punch and CT was run in hole with stinger to perform cement job. Upon successful the first cement packer job and tested, the same sequence was perform for the upper production packer. This cement packer was evaluated using slimhole Cement Bond Log (CBL) for isolation and TOC to ensure compliance with companys abandonment policy. Final step was setting the whipstock using eline orienting tool. Window milling: First run was with straightt motor to eliminate the bottom lip. The window milling went slight deeper without signs of exiting the casing ( tracking down the casing tubing annulus) and it was corrected with 2.5deg bent motor on subsequent run and successfully exit the tubing and casing. Drill build and tangent section: The build section was planned for 40 deg/100ft using 2.5 deg/100ft bent housing. During drilling build section, it was noticed descrepancies on the toolface and update the well trajectory. Upon assessment the revised trajectory, it was determined that the bottom shale will be penetrated if continue, therefore decision was made to place cement plug in the openhole and re-do the build section. Several attempts were made to place cement plug inside the openhole due to the presence of short rat hole between tubing and casing from previous window milling activity. Upon cement plug placement inside openhole, drilling build section commenced and successfully landed the build section with 60 deg/100ft DLS. Continue drilling the openhole with lateral drilling BHA including resistivity sub with total openhole drilled was 927m long. Three differential stuck pipe events encountered, which were successfully released with pumping lower density fluid. Openhole logging: An openhole Reservoir Saturated Tool (RST) was run with eline CT in the openhole to obtain the Gas Oil Contact (GOC) depth for swellable packer placement in the completion string. A heavier mud pill was placed inside tubing in the clean out run after logging to replace the loss of annular friction during making up the completion string. Completion and well reinstatement: Final completion string configuration with 2 swellable packers to isolate the gas zone with blank tubing, and flush joint pre-drilled liner to cover oil zone, was run in hole. After 282m of completion string went inside openhole, the CT was stopped and unable to run in further, suspected due to differential sticking. Several attempts were made to reduce hydrostatic including pumping nitrogen without success. Decision was made to release the liner, set in place and displace the well with diesel and re-instatee the well.

9 SPE Well No. 3 The 3 rd well was located in the opposite side of the the 2 nd well on the same platform. There is only 1 production packer and the planned KOP is above the packer, which requires milling of the 3 ½ tubing and 7 casing (dual exit window). It is required to place cement plug across existing perforation and cement packer above the production packer prior setting the monobore whipstock inside tubing (Fig. 7). Pre CTD program: A cement plug was set with CTU to seal off the perforation and pressure tested. A bridge plug inside the tubing was set using E-line just above the production packer, then punched tubing, followed by setting cement retainer above it. Continued cement job using CTU, thru cement retainer and circulate to tubing-casing annulus. On slimhole CBL data, the cement interpretation was not solid all the way and there was indication of small leak during pressure test. Decision was made to re-do the cement packer job with CTD unit due time constraint. Window milling: Prior setting the whipstock, remedial cement job need to be done following the pre CTD program. By using E-line performed tubing punch in the lowest poor bonding area and CTD package placed the balanced cement plug into the tubing-casing annulus to ensure uniformity of cement plug. The cement inside tubing was milled to 20m below planned KOP and eline ran the slimhole CBL to evaluate the cement bonding, which showed good result and the TOC was more than adequate to satisfy the isolation in the annulus. The whipstock was set using Eline CT and orienting BHA, facing 10deg right. The position of the whipstock was confirmed with slickline LIB run. Window milling was done with 2 runs, first with straight motor to mill the tubing and second with 2 deg bent motor to mill the casing and rat hole. Drill build and tangent section: The build section was planned for 40 deg/100ft DLS using 2.6deg bent motor. Drilling build section was slight ahead of the plan, obtained 55 deg/100ft DLS with the last several meters were projected to landing point. Drilling the lateral section commenced for few meters and realized the discrepancy on the projection angle at landing point was not as expected, decision was made to change with build BHA with 2.6deg bent motor. Continue build angle for few meters and swap back with lateral BHA to continue drilling to TD. Two differential stuck pipe events were encountered, which were successfully released with pumping lower density fluid. Decision was made to call TD early due to the changes in lithology expected, adding to difficulty to initiate drilling beyond 3,100m MD. Furthermore, few differential stuck pipe were encountered in the last 60m of open hole drilled. Total openhole drilled is 640m from window Openhole logging: The plan was to run RST tool in the openhole to obtain the GOC for swellable packer placement. The first logging run had intermitten data transfer and the logging was completed in the 2 nd run. After that, CT performed clean out run with drilling assembly prior making up the completion string. While POOH, lay drill beads inside openhole to reduce friction during completion run. Completion and well reinstatement: Final completion string configuration with 2 swellable packers to isolate the gas zone with blank tubing, and flush joint pre-drilled liner to cover oil zone, was run in hole. The completion run was smooth, went thru build section and lateral, but started to experienced high friction ~190m from TD. Continue ran in hole and finally stopped 134m from TD. The completion was not stuck differentially, but could not gain any footage from the initial hold up depth. Decision was made to release the liner and displace the tubing with diesel, re-instate well, rig down and move to next well. Well No. 4 Well no. 4 was anticipated to be the most challenging and was left to be drilled last from all due to existing completion schematic which dictates the casing exit scenario. Iit has 3 ½ tubing and the KOP is inside 7 casing. The plan is to mill nogo nipple, placed cement plug inside 7 casing all the way to approximately 20m inside production tubing, drill pilot hole and set monobore whipstock inside pilot hole then mill the 7 casing. Pre CTD program: A milling run was performed with conventional CTU to mill the no-go nipple to 2.8 ID to allow milling assembly to go thru. Drift run with slickline to check the ID of the no-go nipple, followed by slimhole CBL to confirm the cement isolation behind casing, especially in the +/-20m of KOP. Then pumped cement to plug existing perforation and also provide support for the whipstock.conventional CTU milled the cement inside tubing until 34m below end of tubing to ensure the cement placement and isolation. Window milling: CTD unit milled the remaining pilot hole with straight motor and 2.8 speed mill, then the last 10m with 1deg bent motor to high side, to ensure the whipstock is touching the 7 casing. Slickline ran multi finger caliper to confirm the ID of the pilot hole inside casing to ensure that the hole size is within the specification of the whipstock. The whipstock

10 10 SPE was set with CT and oriented to 20deg right as planned and confirmed with slickline LIB that the top of whipstock was in correct position. Window milling was done in 1 run with straight motor and speed + string mill without any problem. Before pulling out of hole, performed FIT and swap to SBM for openhole drilling. Drill build and tangent section: Build section was planned with 35 deg/100ft DLS and 2.1deg bent motor. Drill the build section and landed close to the plan (achieved 34 deg/100ft DLS) and followed by lateral drilling BHA with 0.7deg bent motor all the way to TD. Total openhole length was 603m. No stuck pipe incident experienced during openhole drilling. Openhole logging: The openhole RST run was completed in 1 run and followed by clean out run including laying drill beads in the openhole with drilling BHA prior running completion string. Completion and well reinstatement: Make up completion string assembly with 2 swellable packers and flush joint pre-drilled liners with total length of 580.5m (fig. 8). Displaced the tubing with diesel prior POOH, re-instate well and demobilization of the CTD package. Fig. 8: Well 4 final completion Project Highlights and Lessons Learned Summary Pre CTD program: Performing pre-ctd with conventional CTU, slick line and eline units are considered successful, however, it needs to be done earlier to accommodate any changes encountered during the well preparation, allowing any remedial job to be done sooner than CTD package arrival Window milling: Establishment of suitable and practicle techniques for single casing exit, dual casing exit, and also setting whipstock inside cement pilot hole which were successfully done in single attempt. Proven the suitability of using either an E-line or CT Eline to set and orient whipstock an required for drilling Drill build and tangent section: The practice of drilling relatively faster (up to 60m/hour) with frequent wiper trips proven to minimize differential stuck situation in the wells

11 SPE Hole cleaning schedules were monitored closely and improved whenever necessary according to hole condition With CTD, Real Time constant bottomhole pressure (ECD) technique can be applied whenever needed by using choke Uniform annular profile helps avoid pockets where solids can settle and jeorpardize the hole cleaning ability Maintaining borehole stability is critical in CTD and needs to be plan accordingly, balancing the off risk of mud lossess in depleted formation versus borehole instability Openhole logging: Openhole logging equipment (1-11/16 in size) successfully being ran thru up to 60 deg/100ft DLS without failures Clean out run with drilling BHA prior making up completion string is highly recommended to ensure high success rate of running the 2-3/8 pre-drilled liner to bottom Completion and well reinstatement: In the effort to increase the chances of getting the liner down to bottom, drill beads were used, however, the impact was not significantly noticed in the open hole friction reduction, however a recommendation to use higher concentration beads and placed it in the tubing is worth to be experimented in similar operation Conclusions CTD is proven to be feasible as an alternative re-development option to access bypassed reserves in mature offshore oilfields economically Early detailed engineering planning, including candidate selection, basis of design, equipment selection and offshore structure / platform assessment is very important and proves as a very critical stage to ensure high rate of success of the project. The flexibility to make changes to the drilling program in response to operational challenges is a must. As a result the learning curve developed will be very steep and re-currence of problem can be eliminated. This pilot project captures a significant improvements in the learning curves from one well to another, covering the novel drilling practices to the successful implementation of rare operations such as the monobore whipstock placed inside cement pilot hole and cementing through CT Eline job. Having good team integration offshore and at the office, is the key success factor for this first pilot project in Malaysia. Acknowledgements The authors would like to thank PETRONAS, PETRONAS Carigali Sdn Bhd and Schlumberger management for their support and approval to publish the paper. References 1. Goodrich, G.T., Smith, B.E., Larson, E.B., Coiled Tubing Drilling Practices at Prudhoe Bay ; IADC/SPE Rixse, M., Johnson, M.O., High Performance Coil Tubing Drilling in Shallow North Slope Heavy Oil ; IADC/SPE DeWitt, Ron, Technical Feasibility Assessment for Coiled Tubing Drilling 4. D.E. Venhaus, SPE, and C.G. Blount, SPE, ConocoPhillips Alaska Inc.; K.E. Dowell, SPE, Schlumberger, L.L. Gantt, SPE, ConocoPhillips Alaska Inc.; J.G. Sarber, SPE, and A.J. Worthington, SPE, BP Exploration (Alaska) Inc.; and M.G. Rixse, SPE, Baker Hughes Inteq., Overview of the Kuparuk CTD Program and Recent Record-Setting Operations ; SPE Conversion Factors bbl x E-01 =m 3 ft x E-01 =m O F (of-32)/1.8 = O C in. x 2.54 E+00 =cm lbm x E-01 =kg psi x E+00 =kpa

Practical Cementing Technique to Repair Severe Casing Damage David Cirer, Erick Arze, Juan Manuel Moggia, Ruben Hector Soto, Pan American Energy.

Practical Cementing Technique to Repair Severe Casing Damage David Cirer, Erick Arze, Juan Manuel Moggia, Ruben Hector Soto, Pan American Energy. SPE 154241 Practical Cementing Technique to Repair Severe Casing Damage David Cirer, Erick Arze, Juan Manuel Moggia, Ruben Hector Soto, Pan American Energy. Copyright 2012, Society of Petroleum Engineers

More information

Seal 9 barrier verification by xlot and Communication test

Seal 9 barrier verification by xlot and Communication test Seal 9 barrier verification by xlot and Communication test P&A Forum 18 th Oktober 2017 Daniel Tomczak and Roar Flatebø Content Valhall overview and P&A Strategy Qualifying External Barriers Coil Tubing

More information

Plugs and Profiles. Types Running Pulling Problems

Plugs and Profiles. Types Running Pulling Problems Plugs and Profiles Types Running Pulling Problems Plugs are set for many reasons but mostly for isolation of pressures. Not all plugs are a permanent seal. Sand plugs, cement plugs and inflatables have

More information

Drilling-with-Liner (DwL ) System Drill the Undrillable

Drilling-with-Liner (DwL ) System Drill the Undrillable Drilling-with-Liner (DwL ) System Drill the Undrillable One-trip liner system cuts cost and risk. Drill, run, set and cement your liner system all in one trip as you mitigate drilling hazards, increase

More information

Solid-Expandable Systems. The Key to Economical Recovery in Mature Fields

Solid-Expandable Systems. The Key to Economical Recovery in Mature Fields Solid-Expandable Systems The Key to Economical Recovery in Mature Fields A White Paper November 2013 Solid-expandable technology provides a low-cost, permanent alternative to cement squeezes. 2013 Weatherford.

More information

Remotely Operated Cementing Methods for Drilling with Liner Installations. Steve Rosenberg, Global Drilling Reliability Manager

Remotely Operated Cementing Methods for Drilling with Liner Installations. Steve Rosenberg, Global Drilling Reliability Manager Remotely Operated Cementing Methods for Drilling with Liner Installations Steve Rosenberg, Global Drilling Reliability Manager Outline Valhall Field history Drilling and completion challenges Drilling

More information

Overview of Completions

Overview of Completions Overview of Completions PESA Oil & Gas 101 21 May 2015 Nick Clem, Applications Engineering Director Ganesh Subbaraman, Engineering Manager Outline Background Drivers affecting selection of completion types

More information

Tubing-Conveyed Perforating Systems

Tubing-Conveyed Perforating Systems WIRELINE SERVICES Tubing-Conveyed Perforating Systems Full-Service Support, Complete Optimization Delivering downhole perforating solutions through our expertise, innovation, and collaboration Onshore

More information

WESTERN ENERGY PRODUCTS & SERVICES (WEPS) SWELLABLE PACKERS

WESTERN ENERGY PRODUCTS & SERVICES (WEPS) SWELLABLE PACKERS WESTERN ENERGY PRODUCTS & SERVICES (WEPS) SWELLABLE PACKERS Table of Contents Concept Design WEPS Advantages Testing and QA WEPS Swellable Packer Oil Swell Rubber Element Water Swell Rubber Element Robust

More information

Optimising Cementing. Rev: /04/01. Author: Peter Aird Ref:

Optimising Cementing. Rev: /04/01. Author: Peter Aird  Ref: Optimising Cementing Rev: 1.0 21/04/01 Purpose To ensure minimal operational time and risk exposure to personnel, process, production and equipment during cementing operations The following operational

More information

Cased Hole Sand Control Essentials. Fluids, Equipment, Tools, and Displacement Services

Cased Hole Sand Control Essentials. Fluids, Equipment, Tools, and Displacement Services Cased Hole Sand Control Essentials Fluids, Equipment, Tools, and Displacement Services Cased Hole Sand Control Essentials Fluids, Equipment, Tools, and Displacement Services The essentials of cased hole

More information

Shale Projects Becoming Globally Important U.S. Shale Oil & Gas Experience Extrapolates Globally

Shale Projects Becoming Globally Important U.S. Shale Oil & Gas Experience Extrapolates Globally Shale Projects Becoming Globally Important U.S. Shale Oil & Gas Experience Extrapolates Globally Global Shale Gas Estimated Reserves Shale Projects are Going Global Source: EIA Potential projects are developing

More information

Sand control case histories: Shape memory polymers, resins, shunt tubes

Sand control case histories: Shape memory polymers, resins, shunt tubes Sand control case histories: Shape memory polymers, resins, shunt tubes BY DIANE LANGLEY, EDITORIAL COORDINATOR Sand, a familiar adversary for drilling and completion engineers, continues to present a

More information

Isolating Potential Flow Zones During Well Construction

Isolating Potential Flow Zones During Well Construction Isolating Potential Flow Zones During Well Construction API Standard 65 Part 2 Glen Benge http://publications.api.org/ API Standard 65-2 Document highlights industry recommended cementing and well construction

More information

Across the industry, ways are being sought to

Across the industry, ways are being sought to F O C U S Questioning the Way We Drill Across the industry, ways are being sought to find and extract oil and gas more cost-effectively, while improving safety and environmental performance. Drilling is

More information

MetalSkin Cased-Hole Liner System

MetalSkin Cased-Hole Liner System MetalSkin Cased-Hole Liner System Using advanced solid expandable technology to reduce costs, optimize completion size and ultimately maximize production and ROI Reducing Operating Costs over the life

More information

WELL CONTROL THE RISING EAST NOVEMBER/DECEMBER INTERNATIONAL ASSOCIATION OF DRILLING CONTRACTORS Drilling

WELL CONTROL THE RISING EAST NOVEMBER/DECEMBER INTERNATIONAL ASSOCIATION OF DRILLING CONTRACTORS Drilling OFFC MGZN OF H NRNON SSOCON OF DRNG CONRCORS Drilling C O N R C O R NOVMBR/DCMBR 2013 D R W CONRO N G W W W. D R N G C O N R C O R. O R G C O M P xpanded containment system under development for GOM; study

More information

SPE Copyright 2012, Society of Petroleum Engineers

SPE Copyright 2012, Society of Petroleum Engineers SPE 152530 Impact of Completion System, Staging, and Hydraulic Fracturing Trends in the Bakken Formation of the Eastern Williston Basin Randy F. LaFollette, SPE, William D. Holcomb, SPE, and Jorge Aragon,

More information

SteadyState Continuous Flow System

SteadyState Continuous Flow System SteadyState Continuous Flow System Ultimate Wellbore Protection. Achieve greater control through continuous circulation of drilling fluids. Continuous Pressure, Along the Entire Wellbore Managing downhole

More information

Injection Wells for Liquid-Waste Disposal. Long-term reliability and environmental protection

Injection Wells for Liquid-Waste Disposal. Long-term reliability and environmental protection Injection Wells for Liquid-Waste Disposal Long-term reliability and environmental protection ACHIEVE MULTIPLE GOALS FOR LIQUID-WASTE DISPOSAL INJECTION WELLS Expertly located, designed, constructed, and

More information

Cementing Tool Supports Cement Plug in Large Diameter Geothermal Well Casing

Cementing Tool Supports Cement Plug in Large Diameter Geothermal Well Casing GRC Transactions, Vol. 39, 2015 Cementing Tool Supports Cement Plug in Large Diameter Geothermal Well Casing Ozgur Balamir 1, Wm. M. Rickard 1, Fred Wilson 1, Kristian Harestad 2, and Per Arild Årebråt

More information

Coiled Tubing for Downhole Applications

Coiled Tubing for Downhole Applications Coiled Tubing for Downhole Applications Tenaris Tubular technologies. Innovative services. Tenaris is the leading global manufacturer and supplier of tubular products and services used in the drilling,

More information

INTERNATIONAL PERFORATING SYMPOSIUM 2014

INTERNATIONAL PERFORATING SYMPOSIUM 2014 INTERNATIONAL PERFORATING SYMPOSIUM 2014 Completion evolution: The role of perforating in horizontal shale wells Kerry Daly, Global BD Manager- DST TCP WELL FLOW MANAGEMENT TM Introduction The first horizontal

More information

COMPLETIONS WFXØ VØ-RATED OPENHOLE GRAVEL- PACK SYSTEM

COMPLETIONS WFXØ VØ-RATED OPENHOLE GRAVEL- PACK SYSTEM COMPLETIONS WFXØ VØ-RATED OPENHOLE GRAVEL- PACK SYSTEM Improving multizone gravel-pack reliability with single-trip efficiency REDUCE RIG TIME, ENHANCE SAFETY, AND ADD FLEXIBILITY IN YOUR OPENHOLE GRAVEL-PACKING

More information

Screenless Sand Control Completions. New dimensions in sand management

Screenless Sand Control Completions. New dimensions in sand management Screenless Sand Control Completions New dimensions in sand management Applications Primary sand control completion for new wells expected to produce formation sand Remedial sand control completion for

More information

C H E M I X. Delivering Cesium Formate to the Oil & Gas Industry. Stocks available immediately for direct sale S.G. 2.20

C H E M I X. Delivering Cesium Formate to the Oil & Gas Industry. Stocks available immediately for direct sale S.G. 2.20 Delivering Cesium Formate to the Oil & Gas Industry Stocks available immediately for direct sale S.G. 2.20 Monovalent, non-scaling & solids free Reduce drilling & completion costs Increase reservoir productivity

More information

USR DRILLING SERVICES

USR DRILLING SERVICES USR DRILLING SERVICES Effective Reservoir Development Innovative Well Intervention Ultra Short Radius (USR) Drilling and Completion Technologies Providing Innovative Drilling and Completion Technologies

More information

New Vision In Drilling

New Vision In Drilling HWD Horizontal Well Drillers New Vision In Drilling Newsletter Date - 01/01/09 News Flash: Recent studies have shown that 43.16% of all hydrocarbons are at a depth of 3,000lf and less Special points of

More information

2015 Global Petroleum Technologies Limited.

2015 Global Petroleum Technologies Limited. CONCEPTUAL DOCUMENT The GPT US - ARTIFICIAL LIFT SYSTEM PERMANENT DEPLOYED ON UMBILICAL OR CONCENTRIC PIPE INSTALLATION AND REMOVAL METHOD (PAT-Pending). The information provided in this document ( Information

More information

Petroleum Production Optimization

Petroleum Production Optimization Petroleum Production Optimization Petroleum Production Optimization Fundamentals Production Optimization refers to the various activities of measuring, analyzing, modelling, prioritizing and implementing

More information

Best Practices for Cementing Job Software

Best Practices for Cementing Job Software Drilling Software Sophisticated Yet Simple White Paper Best Practices for Cementing Job Software CONTENTS I. Introduction... 3 II. Modeling... 1. Hydraulics modeling... 2. Displacement efficiency... 3.

More information

Big Lake Infill Pad Pilot

Big Lake Infill Pad Pilot DrillWell Adelaide 2010 Big Lake Infill Pad Pilot Gas Exploitation: R. Shrivastava, S. Cheong, A. Carey, C. Oviawe, S. Chipperfield Drilling: G. Cernev, M. Gilmour, Mahbub Hoq Completions: S. Brooks, M.

More information

PowerFlex PowerEcho. Annular barrier evaluation services

PowerFlex PowerEcho. Annular barrier evaluation services PowerFlex PowerEcho Annular barrier evaluation services Powering Well Integrity Reliable barrier evaluation for assuring well integrity 1 Assuring the integrity of the well from well construction to abandonment

More information

AADE-05-NTCE-77. Preventing Annular Flow After Cementing: Pulse It! John Aslakson, W&T Offshore; Dale Doherty, BJ Services and Ed Smalley, CTES, L.P.

AADE-05-NTCE-77. Preventing Annular Flow After Cementing: Pulse It! John Aslakson, W&T Offshore; Dale Doherty, BJ Services and Ed Smalley, CTES, L.P. AADE-05-NTCE-77 Preventing Annular Flow After Cementing: Pulse It! John Aslakson, W&T Offshore; Dale Doherty, BJ Services and Ed Smalley, CTES, L.P. This paper was prepared for presentation at the AADE

More information

Cement Plug Placement and Integrity Mechanical Cementing Service

Cement Plug Placement and Integrity Mechanical Cementing Service Cement Plug Placement and Integrity Mechanical Cementing Service Technology, Technique, Trust When it becomes necessary to plug and abandon a well or sections of the wellbore with multiple cement barriers,

More information

ENDURA DUAL-STRING SECTION MILL. Set a rock-to-rock barrier and know that it s done right. WELL ABANDONMENT

ENDURA DUAL-STRING SECTION MILL. Set a rock-to-rock barrier and know that it s done right. WELL ABANDONMENT WELL ABANDONMENT ENDURA DUAL-STRING SECTION MILL Set a rock-to-rock barrier and know that it s done right. DRILLING & FORMATION EVALUATION WELL CONSTRUCTION COMPLETION PRODUCTION MILL ADJACENT STRINGS

More information

DEEPA TM Stimulation of Natural Fracture Networks in Austin Chalk

DEEPA TM Stimulation of Natural Fracture Networks in Austin Chalk DEEPA TM Stimulation of Natural Fracture Networks in Austin Chalk Contents 1. Background 2. Laboratory Tests 3. Field Test - Vertical Well 4. Field Test - Horizontal Well Summary DEEPA TM in-situ acidizing

More information

HOLE CLEANING IN DIRECTIONAL WELLS

HOLE CLEANING IN DIRECTIONAL WELLS HOLE CLEANING IN DIRECTIONAL WELLS 1 ❶ Welcome to this presentation about Hole Cleaning in Directional Wells. It has been prepared by Sedco Forex, to give you a better understanding of the cuttings-transport

More information

Well abandonment procedures and perforation with a slotted charge for cement squeeze applications

Well abandonment procedures and perforation with a slotted charge for cement squeeze applications Well abandonment procedures and perforation with a slotted charge for cement squeeze applications European and West African Perforating Symposium (EWAPS) 7 9 th November 2012 Presented by Co-Author Frank

More information

Joint Development Project Delivers Step Change to Drilling Efficiency by Breaking Temperature Barriers in the Gulf of Thailand

Joint Development Project Delivers Step Change to Drilling Efficiency by Breaking Temperature Barriers in the Gulf of Thailand Joint Development Project Delivers Step Change to Drilling Efficiency by Breaking Temperature Barriers in the Gulf of Thailand 2015 SPE Thailand E&P Annual Awards, Document Submission Chevron Thailand

More information

HIGH-SALINITY, HIGH-PERFORMANCE PACKERS

HIGH-SALINITY, HIGH-PERFORMANCE PACKERS HIGH-SALINITY, HIGH-PERFORMANCE PACKERS LEADING THE PACK IN COMPLETIONS Nothing is predictable in the oilfield. Maximizing production and minimizing costs is a balancing act. In challenging, unconventional

More information

Colorado Oil and Gas Conservation Commission

Colorado Oil and Gas Conservation Commission Colorado Oil and Gas Conservation Commission http://cogcc.state.co.us/ FORM 5 Drilling Completion Report INDUSTRY TRAINING Denver, Colorado November 27, 2012 Form 5 Drilling Completion Report Introduction

More information

CT Reverse Circulating - Basics

CT Reverse Circulating - Basics CT Reverse Circulating - Basics Reverse circulating with aqueous fluid to unload frac sand from large wellbores If sufficient annular velocities are possible with normal circulation, usually don t use

More information

Thema. Drilling Operations Support and Analysis Service

Thema. Drilling Operations Support and Analysis Service Drilling Operations Support and Analysis Service Drilling Operations Support and Analysis Service Benefits Real-time integrated information for effective decision making Proactive and informed responses

More information

Open Access A Novel Approach to Detect Tubing Leakage in Carbon Dioxide (CO 2 ) Injection Wells via an Efficient Annular Pressure Monitoring

Open Access A Novel Approach to Detect Tubing Leakage in Carbon Dioxide (CO 2 ) Injection Wells via an Efficient Annular Pressure Monitoring Send Orders for Reprints to reprints@benthamscience.ae 8 The Open Petroleum Engineering Journal, 2015, 8, 8-15 Open Access A Novel Approach to Detect Tubing Leakage in Carbon Dioxide (CO 2 ) Injection

More information

HTHP Gas Production Casing Cementing Michael Davis, SPE, Drill Science Corp.

HTHP Gas Production Casing Cementing Michael Davis, SPE, Drill Science Corp. HTHP Gas Production Casing Cementing Michael Davis, SPE, Drill Science Corp. Abstract A good cement bond on the production casing of a new wellbore is always the desired result yet until now there hasn

More information

Multilateral Stimulation Technology - A New Approach to Stimulating/Revitalizing Production in Carbonate Reservoirs*

Multilateral Stimulation Technology - A New Approach to Stimulating/Revitalizing Production in Carbonate Reservoirs* Multilateral Stimulation Technology - A New Approach to Stimulating/Revitalizing Production in Carbonate Reservoirs* Kevin Rice 1 Search and Discovery Article #80524 (2016)** Posted April 4, 2016 *Adapted

More information

Laboratory Apparatus Improves Simulation of Lost Circulation Conditions

Laboratory Apparatus Improves Simulation of Lost Circulation Conditions AADE-13-FTCE-09 Laboratory Apparatus Improves Simulation of Lost Circulation Conditions Matthew L. Miller, Dale Jamison, and Robert J. Murphy, Halliburton Copyright 2013, AADE This paper was prepared for

More information

AADE-04-DF-HO-13. The main areas of the PFM process include: Contract People Performance measures (GWSI-Scorecard) Well construction Common tools

AADE-04-DF-HO-13. The main areas of the PFM process include: Contract People Performance measures (GWSI-Scorecard) Well construction Common tools AADE-04-DF-HO-13 Performance Fluids Management: A New Work Method for Achieving Performance Excellence J.C. Rojas, AADE, BP; W. Duran, AADE, and G. Rachal, AADE, Halliburton This paper was prepared for

More information

DEEPCLEAN. A powerful spacer that cleans your well to water-wet in less time, even under extreme conditions

DEEPCLEAN. A powerful spacer that cleans your well to water-wet in less time, even under extreme conditions DEEPCLEAN A powerful spacer that cleans your well to water-wet in less time, even under extreme conditions DEEPCLEAN: The powerful single-product spacer pill for multi-stage displacements Historically,

More information

COPYRIGHT PETROSKILLS LLC

COPYRIGHT PETROSKILLS LLC LEARNING OBJECTIVES RESISTIVITY LOGGING TOOLS AND INTERPRETATION CORE Open Hole Well Logging Refresher Discuss wireline logging concepts and describe surface and subsurface systems Explain how depths are

More information

Thermal Recovery Status and Development Prospect for Heavy Oil in China

Thermal Recovery Status and Development Prospect for Heavy Oil in China UNITAR Centre for Heavy Crude and Tar Sands 1998 1 No.1998.198 Thermal Recovery Status and Development Prospect for Heavy Oil in China Liu Wenzhang Research Institute of Petroleum Exploration and Development,

More information

Benefits of Aluminum Drill Pipe FuchsRohr AluDrill in Deviated Wells

Benefits of Aluminum Drill Pipe FuchsRohr AluDrill in Deviated Wells Benefits of Aluminum Drill Pipe FuchsRohr AluDrill in Deviated Wells OTTO FUCHS Drilling Solutions August, 2014 1 Outline of the presentation Problematic Torque & Drag Basics Friction & Contact Forces

More information

ALTERNATIVE APPROACHES TO WELL P&A

ALTERNATIVE APPROACHES TO WELL P&A 16 th November 2016 ALTERNATIVE APPROACHES TO WELL P&A Case Study 1 Overview Introduction to Petrofac Late Life Asset Management & Decommissioning Solutions Horne & Wren: Rig-less NUI Well P&A Summary

More information

An Evaluation of Well Construction/Drilling/Conversion Methodologies Associated with Gas Storage Depleted Field Operations in the United States

An Evaluation of Well Construction/Drilling/Conversion Methodologies Associated with Gas Storage Depleted Field Operations in the United States An Evaluation of Well Construction/Drilling/Conversion Methodologies Associated with Gas Storage Depleted Field Operations in the United States Presented at: GWPC 2016 Annual Forum, September 11-14, 2016,

More information

Appraising the Performance of Cyclic Production Scheme through Reservoir Simulation, a Case Study Tariq Al-Zahrani, Saudi Aramco

Appraising the Performance of Cyclic Production Scheme through Reservoir Simulation, a Case Study Tariq Al-Zahrani, Saudi Aramco SPE 152151 Appraising the Performance of Cyclic Production Scheme through Reservoir Simulation, a Case Study Tariq Al-Zahrani, Saudi Aramco Copyright 2012, Society of Petroleum Engineers This paper was

More information

PRODUCTION WELL WATER SHUT-OFF TREATMENT IN A HIGHLY FRACTURED SANDSTONE RESERVOIR

PRODUCTION WELL WATER SHUT-OFF TREATMENT IN A HIGHLY FRACTURED SANDSTONE RESERVOIR WRI-01-R010 PRODUCTION WELL WATER SHUT-OFF TREATMENT IN A HIGHLY FRACTURED SANDSTONE RESERVOIR Final Report By Lyle A. Johnson Jr. July 2001 Work Performed Under Cooperative Agreement DE-FC26-98FT40323

More information

Number 19, 1997 Middle East Well Evaluation Review 3

Number 19, 1997 Middle East Well Evaluation Review 3 2 Number 9, 997 Middle East Well Evaluation Review 3 Excessive water production is a serious issue in many Middle East oil fields. Until recently, efforts to improve water control were hampered by the

More information

Liner Hanger Selection. A Guide for Drilling and Completion Engineers

Liner Hanger Selection. A Guide for Drilling and Completion Engineers Liner Hanger Selection A Guide for Drilling and Completion Engineers Disclaimer This document has been developed to help drilling and completion engineers identify the liner hanger equipment best suited

More information

FUNDAMENTALS OF THE PETROLEUM INDUSTRY CERTIFICATION

FUNDAMENTALS OF THE PETROLEUM INDUSTRY CERTIFICATION FUNDAMENTALS OF THE PETROLEUM INDUSTRY CERTIFICATION CORPORATE COLLEGE SEMINAR SERIES Date: November 1 December 15 In partnership with: For more information, contact: Michael Burns Director Michael.Burns@LoneStar.edu

More information

Hydraulic Diaphragm Insert Pump

Hydraulic Diaphragm Insert Pump Gas Well Deliquification Workshop Adams Mark Hotel, February 25-27, 2008 Hydraulic Diaphragm Insert Pump Jared Mangum, Smith Lift Dave Brewster, ConocoPhillips Outline Project Needs Background Solutions

More information

Frequently Asked Questions

Frequently Asked Questions Frequently Asked Questions Directive 083: Hydraulic Fracturing Subsurface Integrity January 2016 Q1. How does the AER differentiate between a dual- and single-barrier system? A1. A dual-barrier system

More information

Overview of Offshore Well Completions

Overview of Offshore Well Completions Overview of Offshore Well Completions Dennis McDaniel Offshore Operators Committee NASEM Workshop: Offshore Well Completion and Stimulation using Hydraulic Fracturing and Other Technologies October 2,

More information

SPE Abstract. Copyright 2011, Society of Petroleum Engineers

SPE Abstract. Copyright 2011, Society of Petroleum Engineers SPE 149441 A Parametric Study and Economic Evaluation of Drilling Patterns in Deep, Thick CBM Reservoirs Ali Omran Nasar, Shahab D. Mohaghegh, Vida Gholami, Department of Petroleum and Natural gas Engineering,

More information

PAF Workshop Thursday 9thJune2011

PAF Workshop Thursday 9thJune2011 PAF Workshop Thursday 9thJune2011 Topside solutions for safe & efficient P&A 2010 Rolls-Royce plc The information in this document is the property of Rolls-Royce plc and may not be copied or communicated

More information

Deepwater: Drilling Trouble Zones and Well Integrity. Ron Sweatman HALLIBURTON RPSEA Forum at University of Southern California November 29, 2006

Deepwater: Drilling Trouble Zones and Well Integrity. Ron Sweatman HALLIBURTON RPSEA Forum at University of Southern California November 29, 2006 Deepwater: Drilling Trouble Zones and Well Integrity Ron Sweatman HALLIBURTON RPSEA Forum at University of Southern California November 29, 2006 What is Drilling Trouble Zones? Hole Problems - Hole related

More information

Well Abandonment & Intervention Services, Gulf Coast Region. Plug into a New Approach

Well Abandonment & Intervention Services, Gulf Coast Region. Plug into a New Approach Well Abandonment & Intervention Services, Gulf Coast Region Plug into a New Approach Get it Right the First Time Permanent Solutions to Your Well Abandonment Challenge Thousands of wells await safe and

More information

Well Pad Automation Improves Capital Efficiency and Reduces Fiscal Risk Michael Machuca* Emerson Process Management

Well Pad Automation Improves Capital Efficiency and Reduces Fiscal Risk Michael Machuca* Emerson Process Management URTeC: 1874921 Well Pad Automation Improves Capital Efficiency and Reduces Fiscal Risk Michael Machuca* Emerson Process Management Copyright 2014, Unconventional Resources Technology Conference (URTeC)

More information

RELIEF WELL SERVICES Solving challenges.

RELIEF WELL SERVICES Solving challenges. RELIEF WELL SERVICES Solving challenges. Why should Boots & Coots be your preferred choice for Relief Well Contingency Planning, Project Management and Execution? Boots & Coots Services, provides unparalleled

More information

Recommendations to Ensure Proper Cement Placement. Bryce London Tech. Professional-Lead

Recommendations to Ensure Proper Cement Placement. Bryce London Tech. Professional-Lead Recommendations to Ensure Proper Cement Placement Bryce London Tech. Professional-Lead Ideal Conditions 6 Market Challenge 7 Market Challenge 8 Industry Best Practices Top Five: 1. Condition the drilling

More information

Nodal Analysis Approach in Minimizing Pressure Losses to Improve Well Productivity

Nodal Analysis Approach in Minimizing Pressure Losses to Improve Well Productivity Journal of Emerging Trends in Engineering and Applied Sciences (JETEAS) 6(5): 353-359 Scholarlink Research Institute Journals, 2015 (ISSN: 2141-7016) jeteas.scholarlinkresearch.com Journal of Emerging

More information

Halliburton Reservoir Description Tool (RDT ) Formation Tester

Halliburton Reservoir Description Tool (RDT ) Formation Tester Halliburton Reservoir Description Tool (RDT ) Formation Tester OVERVIEW When flexibility and versatility are required, the Halliburton Reservoir Description Tool (RDT ) tool collects in a single deployment

More information

Barrier verification and leakage risk. Dave Gardner, IRIS Norwegian Oil and Gas Plug & Abandonment Seminar October 18 th 2017

Barrier verification and leakage risk. Dave Gardner, IRIS Norwegian Oil and Gas Plug & Abandonment Seminar October 18 th 2017 Barrier verification and leakage risk Dave Gardner, IRIS Norwegian Oil and Gas Plug & Abandonment Seminar October 18 th 2017 Barrier verification and leakage risk 1. DrillWell; Drilling and Well Centre

More information

SPE Introduction. Objectives. There are three primary objectives of this new pumping method:

SPE Introduction. Objectives. There are three primary objectives of this new pumping method: SPE 109141 Using a New Artificial-Lift System in Mexican Mature Oil Fields Vann Roy R./Vann Pumping, Gachuz-Muro Heron/Pemex E&P, Alcazar-Cancino Luis O./Pemex E&P, Guerra-López Mauricio/LLEGAR EOR International

More information

Well-Based Monitoring

Well-Based Monitoring Rick Chalaturnyk Petroleum Geomechanics Research Group Department of Civil and Environmental Engineering University of Alberta Well-Based Monitoring IEA MONITORING and VERIFICATION NETWORK Meeting 2006

More information

Appendix A. 6-3 SPE

Appendix A. 6-3 SPE Appendix A. 6-3 SPE 122267 Advanced Well Flow Control Technologies can Improve Well Cleanup F. T. Al-Khelaiwi*, K. M. Muradov*, D. R. Davies* and D. K. Olowoleru*, Heriot Watt University, Edinburgh, U.K.

More information

CEMENT EVALUATION ITS NOT JUST ABOUT A BOND LOG GLEN BENGE SENIOR ADVISOR CEMENTING PRESSURE PUMPING

CEMENT EVALUATION ITS NOT JUST ABOUT A BOND LOG GLEN BENGE SENIOR ADVISOR CEMENTING PRESSURE PUMPING CEMENT EVALUATION ITS NOT JUST ABOUT A BOND LOG GLEN BENGE SENIOR ADVISOR CEMENTING PRESSURE PUMPING CEMENT EVALUATION OBJECTIVES Is the material behind the pipe a solid or liquid - Solids can t be fixed

More information

SHARING TO BE BETTER Background

SHARING TO BE BETTER Background SHARING TO BE BETTER Background Sharing to be better Under the direction of OLF, a joint industry task force of Operator and Drilling Contractor personnel has been formed to recommend ways to reduce the

More information

GeoBalance Optimized Pressure Drilling Services TWO TECHNOLOGIES. ONE SOLUTION. UNDERBALANCED AND MANAGED PRESSURE DRILLING SYSTEMS

GeoBalance Optimized Pressure Drilling Services TWO TECHNOLOGIES. ONE SOLUTION. UNDERBALANCED AND MANAGED PRESSURE DRILLING SYSTEMS 2017 Halliburton. All Rights Reserved. GeoBalance Optimized Pressure Drilling Services TWO TECHNOLOGIES. ONE SOLUTION. UNDERBALANCED AND MANAGED PRESSURE DRILLING SYSTEMS GEOBALANCE OPTIMIZED PRESSURE

More information

Capillary Injection Tubing Anchor Technologies

Capillary Injection Tubing Anchor Technologies Capillary Injection Tubing Anchor Technologies Patent Pending Randy Matthews- Weatherford Shad Frazier- SandRidge Energy ABSTRACT There are many oil and gas fields across the United States which have been

More information

Debris Management and Cleanout

Debris Management and Cleanout Debris Management and Cleanout Debris Categorization Solids Gunk (sludges, emulsions, viscous liquids, PIPE DOPE!) Junk introduced into the hole www.gekengineering.com Source: Wellcert 1 Photograph (from

More information

TYPICAL INSTALLATION INSTRUCTIONS

TYPICAL INSTALLATION INSTRUCTIONS TYPICAL INSTALLATION INSTRUCTIONS Environment One Grinder Pump Feature Identification 1. Grinder Pump Basin High density polyethylene (HDPE) 2. Accessway Cover Painted Steel 3. Electrical Quick Disconnect

More information

Down Hole Flow Assurance

Down Hole Flow Assurance Down Hole Flow Assurance Ferhat Erdal Senior Advisor - Flow Assurance Steve Cochran Senior Advisor - Flow Assurance SPE GCS Annual Drilling Symposium Spring, TX April 13, 2017 Flow Assurance Key Words

More information

Technological Enhancement of PC Pumps for Heavy Oil Production. Courtney Ward P.Eng.

Technological Enhancement of PC Pumps for Heavy Oil Production. Courtney Ward P.Eng. Technological Enhancement of PC Pumps for Heavy Oil Production Courtney Ward P.Eng. April 28, 2008 Development and Test Area * Lloydminster 1 History Initial PC Pump Installations Initial install occurred

More information

3/5/2014. Key Topics for Consideration

3/5/2014. Key Topics for Consideration Hole Cleaning in Deviated Wellbores Terry Hemphill Global Advisor, Wellbore Management Halliburton-Baroid Houston, Texas AADE Fluids Management Group 27 February 2014 terry.hemphill@halliburton.com Key

More information

WELL RECORD INSTRUCTIONS (Unconventional Operators only)

WELL RECORD INSTRUCTIONS (Unconventional Operators only) COMMONWEALTH OF PENNSYLVANIA DEPARTMENT OF ENVIRONMENTAL PROTECTION OFFICE OF OIL AND GAS MANAGEMENT WELL RECORD INSTRUCTIONS (Unconventional Operators only) Pursuant to 58 Pa C.S. 3222(b)(1) and 3222(b)(2),

More information

Challenges of Cementing Olkaria Geothermal Field

Challenges of Cementing Olkaria Geothermal Field GRC Transactions, Vol. 39, 2015 Challenges of Cementing Olkaria Geothermal Field Nahashon Karanja KenGen Olkaria Geothermal Projects, Naivasha nnzioka@kengen.co.ke Keywords Thickening time, ECD (equivalent

More information

6 DRILLING AND COMPLETIONS

6 DRILLING AND COMPLETIONS Cenovus FCCL Ltd. 6-1 Drilling and Completions 6 DRILLING AND COMPLETIONS 6.1 OVERVIEW This section contains information about the drilling and completion of wells within the CLTP. Well counts, locations

More information

Horizontal Well Spacing and Hydraulic Fracturing Design Optimization: A Case Study on Utica-Point Pleasant Shale Play

Horizontal Well Spacing and Hydraulic Fracturing Design Optimization: A Case Study on Utica-Point Pleasant Shale Play URTeC: 2459851 Horizontal Well Spacing and Hydraulic Fracturing Design Optimization: A Case Study on Utica-Point Pleasant Shale Play Alireza Shahkarami*, Saint Francis University; Guochang Wang*, Saint

More information

Multi-Level VW Piezometer

Multi-Level VW Piezometer Multi-Level VW Piezometer 52611199 Copyright 2013 DGSI. All Rights Reserved. This equipment should be installed, maintained, and operated by technically qualified personnel. Any errors or omissions in

More information

Rule 326: Mechanical Integrity Guidance

Rule 326: Mechanical Integrity Guidance COGCC OPERATOR GUIDANCE RULE 326: MECHANICAL INTEGRITY GUIDANCE Document Control: Created Date: May 15, 2015 Last Updated Date: May 15, 2015 Last Updated By: Dave Kulmann Review Cycle: Yearly Review Systems

More information

SHALE FACTS. Production cycle. Ensuring safe and responsible operations

SHALE FACTS. Production cycle. Ensuring safe and responsible operations SHALE FACTS Production cycle Ensuring safe and responsible operations Statoil is committed to developing our shale projects in a safe, responsible and open manner. Statoil takes a long term perspective

More information

IKATAN AHLI TEKNIK PERMINYAKAN INDONESIA. Ikatan Ahli Teknik Perminyakan Indonesia Simposium Nasional IATMI 2009 Bandung 2-5 Desember 2009

IKATAN AHLI TEKNIK PERMINYAKAN INDONESIA. Ikatan Ahli Teknik Perminyakan Indonesia Simposium Nasional IATMI 2009 Bandung 2-5 Desember 2009 IKATAN AHLI TEKNIK PERMINYAKAN INDONESIA Ikatan Ahli Teknik Perminyakan Indonesia Simposium Nasional IATMI 2009 Bandung 2-5 Desember 2009 Makalah Professional IATMI 09-032 Improving ESP Run Life thru Application

More information

IPS More than just Penetration: Perforation Design for Naturally Completed and Stimulated Wells

IPS More than just Penetration: Perforation Design for Naturally Completed and Stimulated Wells IPS 14-14-11 More than just Penetration: Perforation Design for Naturally Completed and Stimulated Wells John Hardesty, PE Principal Research Engineer, GEODynamics, Inc. john.hardesty@perf.com More than

More information

Shale Development: Understanding and Mitigating Risks Associated with Well Construction and Hydraulic Fracturing

Shale Development: Understanding and Mitigating Risks Associated with Well Construction and Hydraulic Fracturing Shale Development: Understanding and Mitigating Risks Associated with Well Construction and Hydraulic Fracturing Kris J. Nygaard Sr. Stimulation Consultant ExxonMobil Production Company National Academy

More information

SECTION GRAVEL PACKED WATER WELL

SECTION GRAVEL PACKED WATER WELL SECTION 02520 GRAVEL PACKED WATER WELL PART 1 GENERAL 1.01 SECTION INCLUDES A. Gravel packed water well includes drilling, installing, cleaning, developing, testing, videoing, abandoning, and site clean

More information

Dynamic MudCap Drilling in the Granite Wash Formation. Kurt A. Shipley

Dynamic MudCap Drilling in the Granite Wash Formation. Kurt A. Shipley Dynamic MudCap Drilling in the Granite Wash Formation Kurt A. Shipley Presentation Outline LINN Energy Overview Mid-Continent Drilling Program Extreme Lost Circulation Challenges MudCap and Dynamic MudCap

More information

Case Study of Drillstring Failure Analysis

Case Study of Drillstring Failure Analysis Case Study of Drillstring Failure Analysis Dave Bert, Chesapeake Energy Nanjiu Zheng,, T H Hill Associates Inc., Houston AADE Mid-Continent Symposium January 20, 2010 Summary Three drillstring fatigue

More information

BlueCrest Energy Activity Update, J. Benjamin Johnson CIRCAC Board of Directors Meeting Kodiak, 9/12/2014

BlueCrest Energy Activity Update, J. Benjamin Johnson CIRCAC Board of Directors Meeting Kodiak, 9/12/2014 BlueCrest Energy Activity Update, J. Benjamin Johnson CIRCAC Board of Directors Meeting Kodiak, 9/12/2014 September 12, 2014 BlueCrest Energy Overview Business Highlights Small privately-held oil and gas

More information

Logging solutions for optimizing field development. Well Evaluation for Coalbed Methane

Logging solutions for optimizing field development. Well Evaluation for Coalbed Methane Logging solutions for optimizing field development Well Evaluation for Coalbed Methane Logging solutions for optimizing field development Maximizing the net present value (NPV) from coalbed methane (CBM)

More information