3D core replacement method applied to support design on drift next to large excavation

Size: px
Start display at page:

Download "3D core replacement method applied to support design on drift next to large excavation"

Transcription

1 3D core replacement method applied to support design on drift next to large excavation J. Verdugo, A. Merino & V. Buscaglione Hatch Chile, Chuquicamata Underground Mine Project, Chile A. Russo CODELCO, Chuquicamata Underground Mine Project, Chile ABSTRACT: For reinforcement design of large excavations, explicit 3D models are commonly used and their results have been proven accurate and empirically validated. This design process usually requires several iterations for every excavation of the system, which in general consists of one large excavation and a number of secondary drifts. Numerical process takes time, it is common to run several models in order to reduce or increase the support design depending on its results. For this reason time reduction remains one of the major challenges of this kind of modeling. This paper describes the reinforcement design of a crusher cavern from Chuquicamata Mine Underground Project and the use and validation of a Core Replacement modeling on a secondary drift, in order to optimize its reinforcement simulation. Taking into account the quality shown by the rock mass, the analyzed method has given acceptable results and a significant save of time in the process. 1 INTRODUCTION The CODELCO Chuquicamata Underground Mine Project considers a block caving exploitation divided into 20 macro blocks. The crusher system assessed at the feasibility level is based on two Sizer crushers below each macro block, connected to the production level by four raise bored ore pass. Each Sizer crusher is located on a cavern with a section of 12.5 m 13 m. Several drifts are previously excavated next to the Sizer Room, so the geomechanical interaction between them and the main excavation have to be considered. The support design of the system is validated by a FLAC 3D (Itasca 2009) model, which is optimized by using a core replacement method for the drifts. 2 NUMERICAL MODELING 2.1 Geotechnical properties Considering the variability of the mine geology, two models of the excavations are achieved according to the rock mass quality. The first one is excavated on the Basic Geotechnical Unit (UGTB) called PES (Pórfido Este Sericítico), and it is representative of the North Sector of the mine. The second one is excavated on the UGTB Q=S (Cuarzo Igual Sericita) and it is representative of the Center Sector. The design obtained for the Center Sector will also be used for the South Sector which is considered of a better quality. These sectors and their geology can be observed in Figure 1. The rock mass is modeled as a continua Generalized Hoek & Brown material. Intact rock properties were obtained from Russo (2010) and the GSI values from Russo & Gajardo (2012). These parameters are presented in Table 1. Rock mass properties were scaled by using equations

2 described in Hoek, Carranza-Torres & Corkum (2002), and the Young s Modulus values were also scaled with the relation from Hoek & Diederichs (2006). ( ( ( Figure 1. Blocks model at meters above sea level for the three Sectors with their Geotechnical Units, the Sizer Room s location and the macro blocks. (a) Northern Sector (b) Center Sector (c) Southern Sector. Table 1. Hoek & Brown properties of the rock mass. Sector UGTB Domain γ GSI σci mi Em ν kn/m 3 MPa GPa North PES Americana Norte Center Q=S Americana Central South Q>S Americana Sur The field stress is obtained from a mine-scale 3D model that takes into account the mining stresses redistribution. These values were taken from Board & Poeck (2009) and are presented in Table 2.

3 Table 2. Field stress considered. Sector σ NS σ EW σ Z MPa MPa MPa North Center Geometrical description and excavation sequence In order to obtain results that considers the overall behavior of the excavations and their interaction, the model have been constructed including several drifts, which dimensions are presented in Table 3. The geometrical design of the Sizer Room and its associated drifts was completed using Maptek Vulcan software and exported as a DXF file. The meshing process was done using Gambit software. The result is a 200 m 200 m 200m mesh with seven million tetrahedral elements. The FLAC 3D mesh is presented in the Figure 2. Table 3. Excavations considered in the numerical modeling and their dimensions Level Excavation denomination Dimension (B H) Ore pass level Ore pass Station Access Drift 4 m 4 m Ore pass Level Access Drift 4 m 4 m Ore passes φ3.5 m Crusher level Ore pass Discharge Station Access 4 m 4 m Sizer Plant Access 5.5 m 5.0 m Plate feeder Room 7.0 m 13.0 m Sizer Room 12.5 m 13.0 m Haulage Level Intermediate Haulage Drift 6.5 m 5.0 m Figure 2. Overview of the model s mesh.

4 The excavation sequence is explicitly achieved into 172 steps using FLAC 3D. For each step the structural elements are defined. Drifts are excavated in 3 m steps. The Sizer Room is excavated starting with a roof pilot tunnel which is then laterally excavated to complete the roof arch. A slot is after achieved to start the benching of the room. Finally the Sizer Room is connected to the Intermediate Haulage Drift and the ore pass are excavated. Relevant steps of this sequence are presented in the Figure 3. Figure 3. Relevant steps of the excavation sequence. 2.3 Support design The support sections are defined based on empirical criteria: drifts are designed in accordance to the Barton & Grimstad (1993) chart, while the Plate Feeder Room and Sizer Room are designed considering the pattern recommended by these authors, but the bolts are replaced by minicaged cables which length is defined by the US Army Corps (1980) criteria. The support design obtained by this method is presented in Table 4.

5 Table 4. Support design obtained by empirical methods. Excavation Sector Pattern of bolt/cable Length Shotcrete thickness Drifts North 1.5 m x 1.5 m 2.5 m - Center 1.3 m x 1.3 m 2.5 m - Plate Feeder Room North 2.01 m x 2.1 m 6.0 m 10 cm Center 1.7 m x 1.7 m 8.0 m 10 cm Sizer Room North 2.1 m x 2.1 m 6.0 m 10 cm Center 1.7 m x 1.7 m 8.0 m 10 cm Several cables were also installed in different zones of confinement loss in order to prevent wide plastic behavior. Those support elements are explicitly modeled, bolt and cable are taken as cable elements which properties are define according to their strength and grout stiffness. The tension strength is 160 kn for the bolts and 350 kn for minicaged cable. Shotcrete is modeled as shell elements, the time hardening is considered changing stiffness property at each step of installation, according to the excavation sequence estimated at this feasibility level. The final compression strength of the shotcrete is assumed to be 30 MPa. Each model was run in a HP Workstation with an Intel Xeon CPU W3565@3.2 GHz processor and 30 Gb Ram, in approximately 5300 minutes. 2.4 Results In the Northern Sector, the rock mass around the Sizer Room shows stress concentration of about 40 MPa, and locally 60 MPa at the corners. The plastic zone has an extent of less than 1.0 m, greater displacement are 1.2 cm at the East wall of the room. Cables present a maximum force of 75 kn and the shotcrete shows a compression of about 800 kn per unit length. At the drifts, force in the bolts is variable depending on the distance from the tunnel front at which they are installed. Maximum forces are located at the nearest bolts from the front and are about 30 kn. In the Southern Sector, stress concentrations at the roof of the Sizer Room are about 20 to 30 MPa, and 60 at the corners. The plastic zone extent varies between 1.7 m to 2.0 m. Maximum displacement are located at the northern wall and are about 3.0 cm. Cables present a maximum force of 230 kn and shotcrete shows a compression of 1600 kn per unit length. At the drifts, maximum forces on the cable are about 75 kn. In Figure 4 graphical results of support for Southern Sector are presented. In Figure 5, the capacity plots of the shotcrete are shown for a factor of 1.5. Figure 4. Graphical results of the structural elements.

6 Figure 5. Capacity plots of the shotcrete. Factor of safety = MODELING OPTIMIZATION 3.1 Core Replacement method As said before, the explicit modeling used in the design takes a long time to be done. In fact, it is common to run several models in order to reduce or increase the support design depending on its results. For this reason time reduction remains one of the major challenges of this kind of numerical modeling. The Core Replacement method is chosen in order to find an improvement for this subject by simplifying the modeling. This method is described in Appendix 1 of the Kersten Lecture by Hoek et al. (2008) and involves determining the longitudinal closure profile for the excavation, and replacement of the core of the excavation by an elastic material that in equilibrium allows a closure similar to that which is generated at a certain distance from the front, where bolts are installed. This method allows solving an entire drift in only two steps, the first one generates the amount of deformation prior to support, and the second one solves the force on the support after completing drift excavation. 3.2 Core replacement applied to the Intermediate Haulage Drift The Core Replacement Method is applied to the Intermediate Haulage Drift at the Southern Sector. At a first stage, the relation between displacement at the edge of the excavation and the modulus of replacement material of the core is obtained by a 2D relaxing model, which is achieved reducing the Young modulus of the core from the rock mass modulus to zero. The mesh of this model is presented on Figure 6, and the results on Figure 7. The relation between the distance from the front and the closure of the excavation can be obtained by equations proposed by Vlachopoulos & Diederichs (2009) that involve the maximum tunnel wall displacement and the radius of the plastic zone far from the tunnel face. Nevertheless, in this case, the radius of the plastic zone is neglected due its value is less than twice the tunnel radius and the wall and face yield zones do not interact. Therefore the relationship for the longitudinal displacement profile derived by Panet (1995) in Equation 1, can be used: u u r max * d t where is the average radial displacement at a specified longitudinal position, is the maximum short term radial displacement distant from the face and corresponding to plane strain (1)

7 Displacement [m] analysis of a tunnel cross section, and is the quotient between a specified longitudinal position ( ) and the tunnel equivalent radius ( ). This relationship is based on elastic analysis. This relationship is applied for a distance of 70 cm which is the lowest distance between the bolt installation and the front of the drift in the explicit model. The average radial displacement obtained is 4.1 mm which in Figure 7 is equivalent to a Young s modulus of 3.44 GPa. Figure 6. Final view of the 2D relaxation model E E E+10 Young s Modulus [Pa] Figure 7. Results of the relaxation model as a relationship between Young s modulus and roof displacement. 3.3 Results of the Core Replacement method The 3D model shown in Figure 2 is solved by replacing the core of the Intermediate Haulage drift by an elastic material with a Young s modulus of 3.44 GPa. After the equilibrium is reached, support bolt are installed and the material excavated. The final displacement obtained by this method has a similar behavior compared to the one from the explicit modeling. The main difference between both of them is that the explicit modeling locally shows more displacement on the walls than the Core Replacement method. This can be explained by the fact that this displacements occur in a location far from the front, while the Core Replacement was applied to represent a closer section. This can be observed on Figure 8.

8 Force [kn] ( ( Figure 8. Total displacement by applying each method. (a) Core Replacement (b) Explicit modeling. The average force obtained at the overall length of the bolts of the roof is 41.6 kn while in the explicit model this value is of 41.2 kn. For both models, the results through the length of the bolts are presented in Figure 9, where segment 1 is the nearest from the excavation and segment 8 the farthest. For each segment, maximum and minimum values of the force are represented by the black lines for the explicit model. Despite the difference observed in the first segment of the rockbolt, the second and the third have very similar values, and between the fourth and the eighth the curves have a regular profile. It is presumed that the difference found between both behaviors is due to the in situ stress asymmetry, which is not considered in this method. This is significant because this asymmetry generates a different response at walls and the roof, and therefore the relationship between Young s modulus and closure of the drift should be analyzed differently for each direction. For that reason, future works may apply anysotropic material to the core replacement method in order to obtain more realistic results. The average forces obtained earlier for both methods are very similar, and it is important to notice that the Core Replacement method has given a slightly higher value, in addition the segment closest to the excavation (that in both cases is the maximum force) also presents higher values, which means that this method is more conservative, and can be applied for this types of drifts in this rockmass Rockbolt Segment Explicit Modeling Core Replacement (E=3.44) Figure 9. Average roof bolts forces obtained with explicit and core replacement models. For the first, maximum and minimum values can be seen for each segment of the bolts.

9 3.4 Time saving As said before, the overall model takes approximately 5300 minutes to run. The Intermediate Haulage Drift explicit model which is excavated into 24 steps, takes 745 minutes to run. The 2D relaxation model runs in less than one minute and the core replacement model takes only 205 minutes. In other words, the core replacement method applied to this Intermediate Haulage Drift saves 540 minutes which represents a 10% of improvement. By simple extrapolation, by applying this method to all secondary drifts, the overall time saving can be estimated in 2260 minutes which represent a 42% of the total time. Although it is difficult to estimate time taken in programming the explicit model, clearly core replacement model requires less time since excavations does not need to be discretized, and all structural elements are declared in the same excavation step. 4 CONCLUSIONS The reinforcement design for large excavations must be done cautiously due the importance these tunnels have in the main system. An explicit 3D modeling is very important in these cases, due the accuracy their results have shown, despite the time that it takes to provide results. Nevertheless, when a change is done in the first design and the modeling must be run again, the time that this process takes is not minor, and it is for that reason that it is interesting to search for another method that helps by saving time in the secondary drifts reinforcement design. In this case, the core replacement method has proven been acceptable while designing secondary drifts reinforcement, and shown an important save of time: The explicit modeling provided results in the order of 745 minutes, and if something is altered on the design it must be redone; on the other hand, the Core Replacement method took 205 on obtaining the rock bolt s forces. The core replacement results are considered acceptable at an engineering project feasibility level, but while the project studies requires more detailed analysis, it may be carefully used until this method is improved and its results are more accurate. REFERENCES Board M. & Poeck E Chuquicamata Underground Project 2009 Geotechnical Update. Itasca Denver, Inc. Grimstad, E. & Barton, N Updating the Q-System for NMT. In Proc. Int. Symp. On sprayed concrete - modern use of wet mix sprayed concrete for underground support, pp Oslo: Norwegian Concrete Assn. Hoek, E., Carranza-Torres, C., & Corkum B Hoek-Brown failure criterion 2002 Edition. In R. Hammah, W. Bawden, J. Curran, and M. Telesnicki (Eds.), Proceedings of NARMS-TAC 2002, Mining Innovation and Technology. Toronto, 10 July 2002, pp University of Toronto. Hoek, E., Carranza-Torres, C., Diederichs, MS. & Corkum, B Kersten Lecture: Integration of geotechnical and structural design in tunnelling. Proceedings University of Minnesota 56th Annual Geotechnical Engineering Conference. Minneapolis, 29 February 2008, pp Hoek, E. & Diederichs M.S Empirical estimation of rock mass modulus. International Journal of Rock Mechanics and Mining Sciences. 43: CrossRef, ISI. Itasca Consulting Group, Inc FLAC 3D Fast Lagrangian Analysis of Continua in 3 Dimensions, Ver Minneapolis: Itasca. Panet, M Le calcul des tunnels part la methode convergence-confinement. Paris: Presses de l ENPC. Russo, A Estimaciones propiedades geotécnicas de la roca intacta y del macizo rocoso en los dominios geotécnicos, Ingeniería básica PMCHS. CODELCO Proyecto mina Chuquicamata subterránea. Chile Russo, A. & Gajardo, D Calibración y validación del índice GSI, 1er nivel de explotación. CODELCO Proyecto mina Chuquicamata subterránea. Chile US Army Corps of Engineers Rock reinforcement. Washington, DC. Vlachopoulos,N. & Diederichs, M.S., Improved Longitudinal Displacement Profiles for Convergence Confinement Analysis of Deep Tunnels. Rock Mech.& Rock Eng.. Vol 42:2 Pgs

Study of Rock-Lining Interaction for Circular Tunnels Using Finite Element Analysis

Study of Rock-Lining Interaction for Circular Tunnels Using Finite Element Analysis Study of Rock-Lining Interaction for Circular Tunnels Using Finite Element Analysis Modern Academy for Engineering and Technology, Cairo, Egypt ABSTRACT Finite element technique is used to model two phases

More information

by Dr. Evert Hoek prepared for RocNews - Spring 2011

by Dr. Evert Hoek prepared for RocNews - Spring 2011 by Dr. Evert Hoek prepared for RocNews - Spring 2011 Cavern Reinforcement and Lining Design by Evert Hoek 2 April 2011 Introduction This note has been prepared in response to a technical support question

More information

Combination of undrained and drained analysis to design the temporary supports of a large diameter tunnel

Combination of undrained and drained analysis to design the temporary supports of a large diameter tunnel 16 TH Australasian Tunnelling Conference 2017 30 October 1 November 2017 Combination of undrained and drained analysis to design the temporary supports of a large diameter tunnel R. Mahinroosta CSU Engineering,

More information

11 Multistage Tunnel Excavation and Support

11 Multistage Tunnel Excavation and Support Multistage Tunnel Excavation and Support 11-1 11 Multistage Tunnel Excavation and Support 11.1 Problem Statement Construction of large railroad, subway and road tunnels often involves multiple stages of

More information

8 Displacements near the Face of an Advancing Shaft

8 Displacements near the Face of an Advancing Shaft Displacements near the Face of an Advancing Shaft 8-1 8 Displacements near the Face of an Advancing Shaft 8.1 Problem Statement A circular shaft is excavated in chalk and lined with monolithic precast

More information

Numerical Analysis of Lining Hinge in Tunnels

Numerical Analysis of Lining Hinge in Tunnels International Journal of Science and Engineering Investigations vol. 4, issue 39, April 2015 ISSN: 2251-8843 Numerical Analysis of Lining Hinge in Tunnels Vahid Hosseinitoudeshki Department of Civil Engineering,

More information

Three-dimensional analysis of tunnel intersections for a train tunnel under Stockholm

Three-dimensional analysis of tunnel intersections for a train tunnel under Stockholm Three-dimensional analysis of tunnel intersections for a train tunnel under Stockholm J. Sjöberg & F. Perman SwedPower AB, Luleå, Sweden M. Leander SwedPower AB, Ludvika, Sweden D. Saiang Luleå University

More information

15 Lined Tunnel Construction in Saturated Ground

15 Lined Tunnel Construction in Saturated Ground Lined Tunnel Construction in Saturated Ground 15-1 15 Lined Tunnel Construction in Saturated Ground 15.1 Problem Statement A circular tunnel with an excavated radius of 6 m, and with its center at a depth

More information

Design and construction of NATM underground station tunnel by using the forepoling method in difficult conditions for Athens Metro

Design and construction of NATM underground station tunnel by using the forepoling method in difficult conditions for Athens Metro Design and construction of NATM underground station tunnel by using the forepoling method in difficult conditions for Athens Metro P. Kontothanassis, N. Koronakis, A. Karinas & S. Massinas Omikron Kappa

More information

International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: Issue 10, Volume 5 (October 2018)

International Journal of Innovative Research in Advanced Engineering (IJIRAE) ISSN: Issue 10, Volume 5 (October 2018) COMPARISON BETWEEN THIN SPRAY-ON LINERS AND SHOTCRETE AS SURFACE SUPPORT MECHANISMS IN TUNNELS Samuel Jjuuko * Department of Civil Engineering, University of Cape Town, South Africa sjjuuko1@gmail.com

More information

Tunnel Lining Design and Construction

Tunnel Lining Design and Construction Tunnel Lining Design and Construction Verya Nasri, PhD, PE 10 th Annual Breakthroughs in Tunneling Short Course August 15, 2017 Cast-in-Place Final Lining Design Considerations Strength Serviceability

More information

Estimation of Lateral Earth Pressure on Cantilever Sheet Pile using Flat Dilatometer Test (DMT) Data: Numerical Study

Estimation of Lateral Earth Pressure on Cantilever Sheet Pile using Flat Dilatometer Test (DMT) Data: Numerical Study Estimation of Lateral Earth Pressure on Cantilever Sheet Pile using Flat Dilatometer Test (DMT) Data: Numerical Study Kousik Deb Indian Institute of Technology Kharagpur, Kharagpur, India. E-mail: kousik@civil.iitkgp.ernet.in

More information

EOSC 547: Tunnelling & Underground Design

EOSC 547: Tunnelling & Underground Design EOSC 547: Tunnelling & Underground Design Topic 6: Sequential Excavation & Ground Control 1 of 54 Tunnelling Grad Class (2016) Dr. Erik Eberhardt Ground Reaction - Convergence A key principle in underground

More information

Structurally controlled instability in tunnels

Structurally controlled instability in tunnels 5 Structurally controlled instability in tunnels 5.1 Introduction In tunnels excavated in jointed rock masses at relatively shallow depth, the most common types of failure are those involving wedges falling

More information

LOAD SHARING IN TWO-PASS LINING SYSTEMS FOR NATM TUNNELS

LOAD SHARING IN TWO-PASS LINING SYSTEMS FOR NATM TUNNELS LOAD SHARING IN TWO-PASS LINING SYSTEMS FOR NATM TUNNELS Yiming Sun Jacobs Associates Mike McRae Jacobs Associates Jan Van Greunen Jacobs Associates ABSTRACT Generally, two-pass lining systems are used

More information

Example Application 11. Multistage Tunnel Excavation and Support

Example Application 11. Multistage Tunnel Excavation and Support Example Application 11 Multistage Tunnel Excavation and Support 1 Multi-Stage Tunnel Construction 2 Multistage Tunnel Conditions Rock Mass Properties Mohr-Coulomb Model unit weight 27,000 N/m 3 bulk modulus

More information

Numerical Analysis of Pipe Roof Reinforcement in Soft Ground Tunnelling

Numerical Analysis of Pipe Roof Reinforcement in Soft Ground Tunnelling Numerical Analysis of Pipe Roof Reinforcement in Soft Ground Tunnelling W.L.Tan and P.G. Ranjith School of Civil & Environmental Engineering, Nanyang Technological University, Singapore 639798 Phone: 65-67905267,

More information

Convergence-Confinement Method

Convergence-Confinement Method Ground Relaxation relaxation in in Segmental segmental Lining lining design Design using Using the the Convergence-Confinement Method E. Almog & M. Mangione Arup, London, United Kingdom G. Cachia Vinci

More information

SETTLEMENTS DUE TO TUNNEL CONSTRUCTION

SETTLEMENTS DUE TO TUNNEL CONSTRUCTION 5 SETTLEMENTS DUE TO TUNNEL CONSTRUCTION In this tutorial the construction of a shield tunnel in medium soft soil and the influence on a pile foundation is considered. A shield tunnel is constructed by

More information

Rock support testing in Luossavaara-Kiirunavaara AB s underground mines, Sweden

Rock support testing in Luossavaara-Kiirunavaara AB s underground mines, Sweden Deep Mining 2014 M Hudyma and Y Potvin (eds) 2014 Australian Centre for Geomechanics, Perth, ISBN 978-0-9870937-9-0 https://papers.acg.uwa.edu.au/p/1410_07_swedberg/ Rock support testing in Luossavaara-Kiirunavaara

More information

A simplified approach of the rock-bolting design based on the principles of NATM

A simplified approach of the rock-bolting design based on the principles of NATM 2 nd Eastern European Tunnelling Conference Athens, Greece Tunnelling in a Challenging Environment 28 September - 01 October 2014 Making tunnelling business in difficult times Greek Tunnelling Society

More information

12 Multi-Stage Tunnel Excavation and Support

12 Multi-Stage Tunnel Excavation and Support Multi-Stage Tunnel Excavation and Support 12-1 12 Multi-Stage Tunnel Excavation and Support 12.1 Problem Statement Construction of large railroad, subway and road tunnels often involves multiple stages

More information

Static Response of Reinforced Soil Retaining Walls with Modular Block Facing

Static Response of Reinforced Soil Retaining Walls with Modular Block Facing Static Response of Reinforced Soil Retaining Walls with Modular Block Facing Morteza Sabet 1, Amir M. Halabian 2, Kazem Barkhordari 3 1 Graduate Student, Department of Civil Engineering, Yazd University

More information

Corrugate Fiber Reinforced Plastic Sheet in Repairing Tunnel Linings

Corrugate Fiber Reinforced Plastic Sheet in Repairing Tunnel Linings Journal of Civil Engineering and Architecture 9 (2015) 684-690 doi: 10.17265/1934-7359/2015.06.006 D DAVID PUBLISHING Corrugate Fiber Reinforced Plastic Sheet in Repairing Tunnel Linings Takashi Hara Department

More information

Design of Concrete Lining for Head Race Tunnel using STAAD

Design of Concrete Lining for Head Race Tunnel using STAAD Design of Concrete Lining for Head Race Tunnel using STAAD Singh Adarsh Department of Civil Engineering, CBS Group of Institutions, Fatehpui, Jhajjar, Haryana, India Affilated to Maharishi Dayanand University,

More information

Performance of primary tunnel support systems under seismic loads in weak rock masses

Performance of primary tunnel support systems under seismic loads in weak rock masses Recent Advances in Rock Engineering (RARE 2016) Performance of primary tunnel support systems under seismic loads in weak rock masses RB Jishnu, Ahmed Shaz, Chayan Patra and Salu Ghosh Larsen and Toubro

More information

An example of finite element modelling of progressive collapse

An example of finite element modelling of progressive collapse COST Action TU0601 Robustness of Structures 2nd and 3rd of March 2009 Coimbra, Portugal An example of finite element modelling of progressive collapse Leslaw KWASNIEWSKI Marian A. GIZEJOWSKI Faculty of

More information

Durability Modelling of Behaviour of Different Concrete Types as Tunnel Lining Elements

Durability Modelling of Behaviour of Different Concrete Types as Tunnel Lining Elements Durability Modelling of Behaviour of Different Concrete Types as Tunnel Lining Elements Marijan Skazlic 1 Nenad Gucunski 2 Dubravka Bjegovic 3 T 11 ABSTRACT Development of novel building materials based

More information

CROWN PILLAR ON VENTILATION DRIFT AT DEEP MILL LEVEL ZONE (DMLZ) PT FREEPORT INDONESIA

CROWN PILLAR ON VENTILATION DRIFT AT DEEP MILL LEVEL ZONE (DMLZ) PT FREEPORT INDONESIA CROWN PILLAR ON VENTILATION DRIFT AT DEEP MILL LEVEL ZONE (DMLZ) PT FREEPORT INDONESIA Rian Nugroho, PT Freeport Indonesia, DMLZ Engineering, Papua, Indonesia Andrew Parhusip, PT Freeport Indonesia, DMLZ

More information

Numerical Study on Structural Behavior of Arched Shotcrete Liner Reinforced with Steel Supports

Numerical Study on Structural Behavior of Arched Shotcrete Liner Reinforced with Steel Supports Numerical Study on Structural Behavior of Arched Shotcrete Liner Reinforced with Steel Supports Jeehwan Yu 1, Jeongsoo Kim 2,Moonok Kim 3,Moon Kyum Kim 1 1 Department of Civil and Environmental Engineering,

More information

Development of the effective segmental tunnel lining with flexible elements

Development of the effective segmental tunnel lining with flexible elements Development of the effective segmental tunnel lining with flexible elements DMITRY POLIAKOV Department of bridges, tunnels and construction Moscow State Automobile and Road Construction University 64 Leningradsky

More information

Numerical Modeling of Slab-On-Grade Foundations

Numerical Modeling of Slab-On-Grade Foundations Numerical Modeling of Slab-On-Grade Foundations M. D. Fredlund 1, J. R. Stianson 2, D. G. Fredlund 3, H. Vu 4, and R. C. Thode 5 1 SoilVision Systems Ltd., 2109 McKinnon Ave S., Saskatoon, SK S7J 1N3;

More information

New approach to improving distortional strength of intermediate length thin-walled open section columns

New approach to improving distortional strength of intermediate length thin-walled open section columns New approach to improving distortional strength of intermediate length thin-walled open section columns R. S. Talikoti 1, K. M. Bajoria 2 1 Research Scholar (Email: rstalikoti@iitb.ac.in) 2 Associate Professor

More information

DESIGN OBJECTIVES AND METHODS FOR BEYOND DESIGN CONDITION

DESIGN OBJECTIVES AND METHODS FOR BEYOND DESIGN CONDITION BEYOND DESIGN CONSIDERATIONS FOR BONDED AND UN-BONDED TENDONS IN NUCLEAR CONTAINMENTS Pentti Varpasuo 1 1 Senior Engineer, Fortum Power and Heat Oy, Finland ABSTRACT The objective of this paper is to assess

More information

Three-dimensional computer simulation of soil nailing support in deep foundation pit

Three-dimensional computer simulation of soil nailing support in deep foundation pit Three-dimensional computer simulation of soil nailing support in deep foundation pit Abstract Chang Zhi Zhu 1,2*, Quan Chen Gao 1 1 School of Mechanics & Civil Engineering, China University of Mining &

More information

THE APPLICATION OF NEW GENERATION SUPPORT PRODUCTS IN A TYPICAL SUB-LEVEL BLOCK CAVE MINING METHOD TO REDUCE SAFETY RISKS AND ENHANCE PRODUCTIVITY

THE APPLICATION OF NEW GENERATION SUPPORT PRODUCTS IN A TYPICAL SUB-LEVEL BLOCK CAVE MINING METHOD TO REDUCE SAFETY RISKS AND ENHANCE PRODUCTIVITY THE APPLICATION OF NEW GENERATION SUPPORT PRODUCTS IN A TYPICAL SUB-LEVEL BLOCK CAVE MINING METHOD TO REDUCE SAFETY RISKS AND ENHANCE PRODUCTIVITY P H FERREIRA Pr. Eng (Mining), Managing Director, Minova

More information

IJMGE Int. J. Min. & Geo-Eng. Vol.48, No.2, December 2014, pp

IJMGE Int. J. Min. & Geo-Eng. Vol.48, No.2, December 2014, pp IJMGE Int. J. Min. & Geo-Eng. Vol.48, No.2, December 2014, pp.147-157. Numerical Modelling of the Segmental Lining of Underground Structures Akbar Salemi 1*, Farhang Sereshki 1, Morteza Esmaeili 2 1 Department

More information

Prediction of Crack-width and Crack-pattern

Prediction of Crack-width and Crack-pattern Prediction of Crack-width and Crack-pattern Gerd-Jan Schreppers, Chantal Frissen, Hee-Jeong Kang, November 2011 Abstract: This paper explains the stiffness adaptation analysis procedure in DIANA. The stiffness

More information

Modelling issues for numerical analysis of deep excavations

Modelling issues for numerical analysis of deep excavations Modelling issues for numerical analysis of deep excavations Helmut F. Schweiger Computational Geotechnics Group, Institute for Soil Mechanics und Foundation Engineering Graz University of Technology, Austria

More information

Modelling of Sheared Behaviour Bolts Across Joints

Modelling of Sheared Behaviour Bolts Across Joints University of Wollongong Research Online Coal Operators' Conference Faculty of Engineering and Information Sciences 2004 Modelling of Sheared Behaviour Bolts Across Joints H. Jalalifar University of Wollongong

More information

DEVELOPMENT AND APPLICATION OF STRESS CONTROLLERS SYSTEM HONEYCOMB IN MODERN TUNNELLING

DEVELOPMENT AND APPLICATION OF STRESS CONTROLLERS SYSTEM HONEYCOMB IN MODERN TUNNELLING Proceedings Shotcrete for Underground Support XI Engineering Conferences International Year 2009 DEVELOPMENT AND APPLICATION OF STRESS CONTROLLERS SYSTEM HONEYCOMB IN MODERN TUNNELLING Rudi Podjadtke Dipl.-Ing.

More information

Coupled Stress-Seepage Numerical Design of Pressure Tunnels

Coupled Stress-Seepage Numerical Design of Pressure Tunnels IAHR-HK Student Research Forum, November 17, 2012 Coupled Stress-Seepage Numerical Design of Pressure Tunnels Afis Olumide BUSARI, Prof. C.W. LI Department of Civil and Environmental Engineering, the Hong

More information

Effects of Wall Embedded Length Ratio and Wall Thickness Ratio on Undrained Stability of Cantilever Piled Walls

Effects of Wall Embedded Length Ratio and Wall Thickness Ratio on Undrained Stability of Cantilever Piled Walls Engineering and Physical Sciences Effects of Wall Embedded Length Ratio and Wall Thickness Ratio on Undrained Stability of Cantilever Piled Walls Boonchai UKRITCHON *, Kant TEERAVONG and Suraparb KEAWSAWASVONG

More information

PRACTICAL DISCUSSION ON THE INTERPRETATION OF GEOMONITORING MEASUREMENTS AND THEIR INFLUENCE ON TUNNEL SUPPORT DESIGN.

PRACTICAL DISCUSSION ON THE INTERPRETATION OF GEOMONITORING MEASUREMENTS AND THEIR INFLUENCE ON TUNNEL SUPPORT DESIGN. PRACTICAL DISCUSSION ON THE INTERPRETATION OF GEOMONITORING MEASUREMENTS AND THEIR INFLUENCE ON TUNNEL SUPPORT DESIGN. A CASE STUDY G. Angistalis, I. Papadatos, I. Rentzeperis, E. Saridou Egnatia Odos

More information

Hoek Brown m i estimation a comparison of multistage triaxial with single stage triaxial testing

Hoek Brown m i estimation a comparison of multistage triaxial with single stage triaxial testing APSSIM 2016 PM Dight (ed.) 2016 Australian Centre for Geomechanics, Perth, ISBN 978-0-9924810-5-6 https://papers.acg.uwa.edu.au/p/1604_15_venter/ Hoek Brown m i estimation a comparison of multistage triaxial

More information

Siren, Topias; Uotinen, Lauri Kalle Tapio; Ström, Jesse; Lehmusjärvi, Riitta; Rinne, Mikael Spalling prediction methods in high stress conditions

Siren, Topias; Uotinen, Lauri Kalle Tapio; Ström, Jesse; Lehmusjärvi, Riitta; Rinne, Mikael Spalling prediction methods in high stress conditions Powered by TCPDF (www.tcpdf.org) This is an electronic reprint of the original article. This reprint may differ from the original in pagination and typographic detail. Siren, Topias; Uotinen, Lauri Kalle

More information

Analysis of Shear Wall Transfer Beam Structure LEI KA HOU

Analysis of Shear Wall Transfer Beam Structure LEI KA HOU Analysis of Shear Wall Transfer Beam Structure by LEI KA HOU Final Year Project report submitted in partial fulfillment of the requirement of the Degree of Bachelor of Science in Civil Engineering 2013-2014

More information

BEARING CAPACITY IMPROVEMENT USING MICROPILES A CASE STUDY

BEARING CAPACITY IMPROVEMENT USING MICROPILES A CASE STUDY BEARING CAPACITY IMPROVEMENT USING MICROPILES A CASE STUDY G.L. Sivakumar Babu 1, B. R.Srinivasa Murthy 2, D.S. N. Murthy 3, M.S. Nataraj 4 ABSTRACT Micropiles have been used effectively in many applications

More information

This is an electronic reprint of the original article. This reprint may differ from the original in pagination and typographic detail.

This is an electronic reprint of the original article. This reprint may differ from the original in pagination and typographic detail. Powered by TCPDF (www.tcpdf.org) This is an electronic reprint of the original article. This reprint may differ from the original in pagination and typographic detail. Ström, Jesse; Hakala, Matti; Suikkanen,

More information

Using EPS Buffers for Diaphragm Walls

Using EPS Buffers for Diaphragm Walls Using EPS Buffers for Diaphragm Walls Beshoy M. FAKHRY1, Salem A. AZZAM2, and Sherif S. ABDELSALAM1 1 Graduate Student, the British University in Egypt, beshoy115377@bue.edu.eg 2 Teaching Assistant, the

More information

Comparison of geotechnic softwares - Geo FEM, Plaxis, Z-Soil

Comparison of geotechnic softwares - Geo FEM, Plaxis, Z-Soil Comparison of geotechnic softwares - Geo FEM, Plaxis, Z-Soil Comparison du logiciel géotechnique Geo FEM, Plaxis, Z-Soil J. Pruška CTU in Prague FCE Department of Geotechnics, Prague, Czech Republic, Pruska@fsv.cvut.cz

More information

Structural Analysis of Pylon Head for Cable Stayed Bridge Using Non-Linear Finite Element Method

Structural Analysis of Pylon Head for Cable Stayed Bridge Using Non-Linear Finite Element Method Structural Analysis of Pylon Head for Cable Stayed Bridge Using Non-Linear Finite Element Method Musthafa Akbar a,* and Aditya Sukma Nugraha b a) Department of Mechanical Engineering, Faculty of Engineering,

More information

ELASTIC AND ELASTO-PLASTIC BUCKLING ANALYSIS OF PERFORATED STEEL PLATES

ELASTIC AND ELASTO-PLASTIC BUCKLING ANALYSIS OF PERFORATED STEEL PLATES ELASTIC AND ELASTO-PLASTIC BUCKLING ANALYSIS OF PERFORATED STEEL PLATES MAURO DE VASCONCELLOS REAL 1, LIÉRCIO ANDRÉ ISOLDI 2, ALEXANDRA PINTO DAMAS 3, DANIEL HELBIG 4 ABSTRACT Many steel structures such

More information

On the Quasi-Static Perforation Resistance of Circular AA5083-H116 Aluminium Plates

On the Quasi-Static Perforation Resistance of Circular AA5083-H116 Aluminium Plates 9 th International LS-DYNA Users Conference Technology (2) On the Quasi-Static Perforation Resistance of Circular AA5083-H116 Aluminium Plates F. Grytten 1, T. Børvik 1,2, O.S. Hopperstad 1 and M. Langseth

More information

Analysis of Buried Arch Structures; Performance Versus Prediction

Analysis of Buried Arch Structures; Performance Versus Prediction Analysis of Buried Arch Structures; Performance Versus Prediction D.A. Jenkins: Reinforced Earth Pty Ltd, Somersby, NSW, Australia Synopsis: The Reinforced Earth Group introduced the TechSpan arch system

More information

De-bonding of FRS Linings. E.S. Bernard and S.G. Reid

De-bonding of FRS Linings. E.S. Bernard and S.G. Reid De-bonding of FRS Linings E.S. Bernard and S.G. Reid Characteristics of FRS Linings in Sydney Most FRS linings are arch-shaped but may include regions of flat-roof. The ground surface is generally smooth

More information

M.C. Christianson Itasca Consulting Group, Inc., Minneapolis, Minnesota, USA

M.C. Christianson Itasca Consulting Group, Inc., Minneapolis, Minnesota, USA UDEC Simulation of Triaxial Testing of Lithophysal Tuff UDEC Simulation of Triaxial Testing of Lithophysal Tuff M.C. Christianson Itasca Consulting Group, Inc., Minneapolis, Minnesota, USA 7 M.P. Board

More information

Passage under Lövstavägen at Bypass Stockholm From Design to Realization

Passage under Lövstavägen at Bypass Stockholm From Design to Realization Passage under Lövstavägen at Bypass Stockholm From Design to Realization Roslin Mattias 1, Borio Luca 2 and Tomas Hellström 3 1 Swedish Transport Administration, Solna Strandväg 98, 171 54 Solna, mattias.roslin@trafikverket.se

More information

Strut and tie. Betongbyggnad VBKN05

Strut and tie. Betongbyggnad VBKN05 Strut and tie Betongbyggnad VBKN05 Strut and Tie Design the deep beam (hög balk) in the figure. qd = 200 kn/m 3 m 3 m Strut and Tie Strut and Tie Describe the stresses in a concrete structure with a strut

More information

Use of Concrete Cross Walls to Reduce Movements Induced by Deep Excavation

Use of Concrete Cross Walls to Reduce Movements Induced by Deep Excavation The 2012 World Congress on Advances in Civil, Environmental, and Materials Research (ACEM 12) Seoul, Korea, August 26-30, 2012 Use of Concrete Cross Walls to Reduce Movements Induced by Deep Excavation

More information

Tunnel Support Design

Tunnel Support Design Tunnel Support Design Eric Wang, PE University of Denver Tunneling Short Course September 11, 2018 Agenda 1.0 Introduction 2.0 Tunnel Support Design Principles 3.0 Input for Design 4.0 Tunnel Support Systems

More information

Todd F. Shupe Associate Professor School of Renewable Natural Resources Louisiana State University AgCenter Baton Rouge, LA 70803

Todd F. Shupe Associate Professor School of Renewable Natural Resources Louisiana State University AgCenter Baton Rouge, LA 70803 FINITE ELEMENT ANALYSES OF WOOD LAMINATED COMPOSITE POLES 1 Cheng Piao Postdoctoral Research Associate USDA Forest Service Forest Products Laboratory Madison, WI 53726 Todd F. Shupe Associate Professor

More information

A Finite Element Model for Optimum Design of Plain Concrete Pressure Tunnels under High Internal Pressure

A Finite Element Model for Optimum Design of Plain Concrete Pressure Tunnels under High Internal Pressure International Journal of Engineering and Technology Volume 2 No. 4, April, 2012 A Finite Element Model for Optimum Design of Plain Concrete Pressure Tunnels under High Internal Pressure Busari Afis Olumide

More information

Rock support in the Kiirunavaara Mine

Rock support in the Kiirunavaara Mine Ground Support 2013 Y. Potvin and B. Brady (eds) 2013 Australian Centre for Geomechanics, Perth, ISBN 978-0-9806154-7-0 https://papers.acg.uwa.edu.au/p/1304_26_jacobsson/ Rock support in the Kiirunavaara

More information

Evaluation of negative skin friction on sheet pile walls at the Rio Grande dry dock, Brazil

Evaluation of negative skin friction on sheet pile walls at the Rio Grande dry dock, Brazil Geotechnical Aspects of Underground Construction in Soft Ground Viggiani (ed) 2012 Taylor & Francis Group, London, ISBN 978-0-415-68367-8 Evaluation of negative skin friction on sheet pile walls at the

More information

STABILITY STUDY ALONG VRASNA TUNNEL EXCAVATION

STABILITY STUDY ALONG VRASNA TUNNEL EXCAVATION STABILITY STUDY ALONG VRASNA TUNNEL EXCAVATION CHATZIANGELOU M. 1,2, CHRISTARAS B. 2 1 J & P / AVAX Co, Frangoklissias 9, 11 2 Maroussi, Athens, mcha@geo.auth.gr 2 School of Geology, Aristotle University,

More information

Numerical Simulation of Soil Nailing Wall in Deep Foundation Pit

Numerical Simulation of Soil Nailing Wall in Deep Foundation Pit 2017 2 nd International Conference on Architectural Engineering and New Materials (ICAENM 2017) ISBN: 978-1-60595-436-3 Numerical Simulation of Soil Nailing Wall in Deep Foundation Pit Xiao Jie Geng ABSTRACT

More information

Stability of a Mechanically Stabilized Earth Wall

Stability of a Mechanically Stabilized Earth Wall Stability of a Mechanically Stabilized Earth Wall GEO-SLOPE International Ltd. www.geo-slope.com 1400, 633-6th Ave SW, Calgary, AB, Canada T2P 2Y5 Main: +1 403 269 2002 Fax: +1 403 266 4851 Introduction

More information

Tunnelling Instrumentation Support Design, Optimization and Testing

Tunnelling Instrumentation Support Design, Optimization and Testing OCT 4 6, 2015 Queens University Kingston, ON Canada Tunnelling Instrumentation Support Design, Optimization and Testing Nicholas Vlachopoulos, PhD, CD, PEng, PE Associate Professor Civil Engineering Department

More information

LIMIT EQUILIBRIUM AND CONTINUUM MECHANICS-BASED NUMERICAL METHODS FOR ANALYZING STABILITY OF MSE WALLS

LIMIT EQUILIBRIUM AND CONTINUUM MECHANICS-BASED NUMERICAL METHODS FOR ANALYZING STABILITY OF MSE WALLS LIMIT EQUILIBRIUM AND CONTINUUM MECHANICS-BASED NUMERICAL METHODS FOR ANALYZING STABILITY OF MSE WALLS Jie Han 1 (Member, ASCE) and Dov Leshchinsky 2 (Member, ASCE) ABSTRACT Limit equilibrium (LE) methods

More information

Study on the Stability and Reliability of the Whole Life Cycle of Tunnel Structure Youjiang Yang

Study on the Stability and Reliability of the Whole Life Cycle of Tunnel Structure Youjiang Yang 2nd International Conference on Machinery, Materials Engineering, Chemical Engineering and Biotechnology (MMECEB 2015) Study on the Stability and Reliability of the Whole Life Cycle of Tunnel Structure

More information

Roofex Results of Laboratory Testing of a New Concept of Yieldable Tendon

Roofex Results of Laboratory Testing of a New Concept of Yieldable Tendon Deep Mining 07 Y. Potvin (ed) 2007 Australian Centre for Geomechanics, Perth, ISBN 978-0-9804185-2-1 https://papers.acg.uwa.edu.au/p/711_28_charette/ Roofex Results of Laboratory Testing of a New Concept

More information

NUMERICAL ANALYSIS OF TUNNEL BORING MACHINE IN SOFT GROUND M. E. LEl-Kilany 1, T. A. EL-Sayed 2 *, R. A. Mohab 3

NUMERICAL ANALYSIS OF TUNNEL BORING MACHINE IN SOFT GROUND M. E. LEl-Kilany 1, T. A. EL-Sayed 2 *, R. A. Mohab 3 NUMERICAL ANALYSIS OF TUNNEL BORING MACHINE IN SOFT GROUND M. E. LEl-Kilany 1, T. A. EL-Sayed 2 *, R. A. Mohab 3 1 Associate Professor, Civil Eng. Dep., Shoubra Faculty of Eng., Zagazig University, Egypt

More information

The Rio Grande project - Argentina

The Rio Grande project - Argentina The Rio Grande project - Argentina Introduction The Rio Grande pumped storage project is located on the Rio Grande river near the town of Santa Rosa de Calamucita in the Province of Cordoba in Argentina.

More information

Comparisons to Tests on Reinforced Concrete Members

Comparisons to Tests on Reinforced Concrete Members 82 Chapter 6 Comparisons to Tests on Reinforced Concrete Members Finite element (FE) model predictions of laboratory test results of reinforced concrete members with various confinement methods are presented

More information

A Design Procedure for the Rehabilitation of Tunnel Liners

A Design Procedure for the Rehabilitation of Tunnel Liners A Design Procedure for the Rehabilitation of Tunnel Liners L. Locatelli, G. Borgonovo Golder Associates, Milan, Italy G. Gioda Department of Structural Engineering, Politecnico di Milano, Italy Keywords:

More information

EVALUATING THE USE OF ELASTOMERS IN IMPROVING BLAST RESISTANCE OF FIBRE-METAL COMPOSITES

EVALUATING THE USE OF ELASTOMERS IN IMPROVING BLAST RESISTANCE OF FIBRE-METAL COMPOSITES 18 TH INTERNATIONAL CONFERENCE ON COMPOSITE MATERIALS EVALUATING THE USE OF ELASTOMERS IN IMPROVING BLAST RESISTANCE OF FIBRE-METAL COMPOSITES R. Das 1*, D. Versalko 1, and J. Ari-Gur 2 1 Department of

More information

THE RTM-LIGHT MANUFACTURING PROCESS: EXPERIMENTATION AND MODELLING

THE RTM-LIGHT MANUFACTURING PROCESS: EXPERIMENTATION AND MODELLING THE RTM-LIGHT MANUFACTURING PROCESS: EXPERIMENTATION AND MODELLING O. Maclaren 1, J.M. Gan 2, C.M.D. Hickey 2, S. Bickerton 2, P.A. Kelly 1 1 Department of Engineering Science, 2 Centre for Advanced Composite

More information

NON-LINEAR ANALYSIS OF BURIED ARCH STRUCTURES

NON-LINEAR ANALYSIS OF BURIED ARCH STRUCTURES NON-LINEAR ANALYSIS OF BURIED ARCH STRUCTURES D.A. Jenkins Reinforced Earth Pty Ltd, Hornsby, NSW, Australia SUMMARY Groupe TAI introduced the TechSpan arch system in 1986. Since then over 5 buried precast

More information

RE-EXAMINATION OF NIST ACOUSTIC EMISSION SENSOR CALIBRATION: Part I Modeling the loading from glass capillary fracture

RE-EXAMINATION OF NIST ACOUSTIC EMISSION SENSOR CALIBRATION: Part I Modeling the loading from glass capillary fracture RE-EXAMINATION OF NIST ACOUSTIC EMISSION SENSOR CALIBRATION: Part I Modeling the loading from glass capillary fracture Abstract BRIAN BURKS Mechanical and Materials Engineering Department, University of

More information

The influence of tunnel boring on foundations and buildings in urban areas - A numerical study

The influence of tunnel boring on foundations and buildings in urban areas - A numerical study Int. Workshop on Geotechnics of Soft Soils-Theory and Practice. Vermeer, Schweiger, Karstunen & Cudny (eds.) 2003 VGE The influence of tunnel boring on foundations and buildings in urban areas - A numerical

More information

Numerical analysis of eccentric orifice plate using ANSYS Fluent software

Numerical analysis of eccentric orifice plate using ANSYS Fluent software IOP Conference Series: Materials Science and Engineering PAPER OPEN ACCESS Numerical analysis of eccentric orifice plate using ANSYS Fluent software To cite this article: D Zahariea 2016 IOP Conf. Ser.:

More information

Reeling-induced residual stress and its effect on the fracture behavior of pipes with through thickness cracks

Reeling-induced residual stress and its effect on the fracture behavior of pipes with through thickness cracks To be presented at the 4th International Conference on Pipeline Technology, Ostend, Belgium, 9-13 May 24 Reeling-induced residual stress and its effect on the fracture behavior of pipes with through thickness

More information

BOUNDARY CONDITIONS OF SHEAR WALLS IN MULTI-STOREY MASONRY STRUCTURES UNDER HORIZONTAL LOADINGS

BOUNDARY CONDITIONS OF SHEAR WALLS IN MULTI-STOREY MASONRY STRUCTURES UNDER HORIZONTAL LOADINGS BOUNDARY CONDITIONS OF SHEAR WALLS IN MULTI-STOREY MASONRY STRUCTURES UNDER HORIZONTAL LOADINGS K. ZILCH Professor, Institute of Building Materials and Structures Chair of Concrete Structures Technische

More information

Numerical modelling in tunnels

Numerical modelling in tunnels ITA - AITES WORLD TUNNEL CONGRESS 007 PRAGUE The rd Training course TUNNELLING IN URBAN AREA Prague, - th May 007 TRAINING MATERIAL PREPARED BY Ing Radko Bucek Ph.D. (Mott MacDonald, Czech Republic) Introduction

More information

Surface Subsidence Analysis Due to Longwall Underground Coal Mining Method in PT. Gerbang Daya Mandiri, Tenggarong, East Kalimantan

Surface Subsidence Analysis Due to Longwall Underground Coal Mining Method in PT. Gerbang Daya Mandiri, Tenggarong, East Kalimantan Kyushu University Global COE Program Journal of Novel Carbon Resource Sciences, Vol. 7, pp. 47-52, Feb. 2013 Surface Subsidence Analysis Due to Longwall Underground Coal Mining Method in PT. Gerbang Daya

More information

RS 3 A New 3D Program for Geotechnical Analysis

RS 3 A New 3D Program for Geotechnical Analysis RS 3 A New 3D Program for Geotechnical Analysis Rocscience is announcing the upcoming release of a brand new software program for 3-dimensional analysis and design of geotechnical structures RS 3 a general

More information

THE 25mm GARFORD BULB ANCHOR FOR CABLE BOLT REINFORCEMENT PART 1: LABORATORY RESULTS A.J. HYETT W.F. BAWDEN N. HEDRICK

THE 25mm GARFORD BULB ANCHOR FOR CABLE BOLT REINFORCEMENT PART 1: LABORATORY RESULTS A.J. HYETT W.F. BAWDEN N. HEDRICK THE 25mm GARFORD BULB ANCHOR FOR CABLE BOLT REINFORCEMENT PART 1: LABORATORY RESULTS A.J. HYETT W.F. BAWDEN Department of Mining Engineering, Queen's University Kingston, Ontario. K7L 3N6 N. HEDRICK Garford

More information

Destruction of concrete beams with metal and composite reinforcement under impulse action

Destruction of concrete beams with metal and composite reinforcement under impulse action Journal of Physics: Conference Series PAPER OPEN ACCESS Destruction of concrete beams with metal and composite reinforcement under impulse action To cite this article: A V Radchenko et al 2015 J. Phys.:

More information

Leelachai M, Benson S, Dow RS. Progressive Collapse of Intact and Damaged Stiffened Panels.

Leelachai M, Benson S, Dow RS. Progressive Collapse of Intact and Damaged Stiffened Panels. Leelachai M, Benson S, Dow RS. Progressive Collapse of Intact and Damaged Stiffened Panels. In: 5th International Conference on Marine Structures (MARSTRUCT). 2015, Southampton, UK: CRC Press. Copyright:

More information

Jurnal Teknologi EXPERIMENTAL AND NUMERICAL ANALYSIS OF INTERACTION BETWEEN SUBSOIL AND POST- ENSIONED SLAB-ON-GROUND. Full Paper

Jurnal Teknologi EXPERIMENTAL AND NUMERICAL ANALYSIS OF INTERACTION BETWEEN SUBSOIL AND POST- ENSIONED SLAB-ON-GROUND. Full Paper Jurnal Teknologi EXPERIMENTAL AND NUMERICAL ANALYSIS OF INTERACTION BETWEEN SUBSOIL AND POST- ENSIONED SLAB-ON-GROUND Petr Mynarcik, Jana Labudkova, Jiri Koktan * Faculty of Civil Engineering Department

More information

THE IMPACT OF EARTHQUAKES ON THE TUNNEL FROM HANOI METRO SYSTEM WHEN THE TUNNEL HAS A HORSESHOE SHAPE CROSS-SECTION

THE IMPACT OF EARTHQUAKES ON THE TUNNEL FROM HANOI METRO SYSTEM WHEN THE TUNNEL HAS A HORSESHOE SHAPE CROSS-SECTION International Journal of Civil Engineering and Technology (IJCIET) Volume 10, Issue 02, February 2019, pp. 79 86, Article ID: IJCIET_10_02_010 Available online at http://www.iaeme.com/ijciet/issues.asp?jtype=ijciet&vtype=10&itype=2

More information

Abstract Introduction and Background Formulation Results and Discussion Conclusion and Future Work References...

Abstract Introduction and Background Formulation Results and Discussion Conclusion and Future Work References... Table of Contents Abstract... 1 Introduction and Background... 2 Formulation... 3 Results and Discussion... 6 Conclusion and Future Work... 7 References... 8 Appendix A West Point Bridge Designer Truss

More information

PERFORMANCE STUDY OF RETROFITTED GRAVITY LOAD DESIGNED WALL FRAME STRUCTURES (SC-140)

PERFORMANCE STUDY OF RETROFITTED GRAVITY LOAD DESIGNED WALL FRAME STRUCTURES (SC-140) PERFORMANCE STUDY OF RETROFITTED GRAVITY LOAD DESIGNED WALL FRAME STRUCTURES (SC-140) *A. Ahmed 1, K. H. Tan 1 1 Department of Civil and Environmental Engineering National University of Singapore, Singapore,

More information

Finite Element Simulation of Manufacturing Process of Chassis Side Members MT05.22

Finite Element Simulation of Manufacturing Process of Chassis Side Members MT05.22 Faculty of Mechanical Engineering Computational and Experimental Mechanics Finite Element Simulation of Manufacturing Process of Chassis Side Members MT05.22 W.Blom Supervisor: dr.ir. R.H.J. Peerlings

More information

Modelling of post-tensioned precast reinforced concrete frame structures with rocking beam-column connections

Modelling of post-tensioned precast reinforced concrete frame structures with rocking beam-column connections Modelling of post-tensioned precast reinforced concrete frame structures with rocking beam-column connections H.A. Spieth, A.J. Carr, A.G. Murahidy, D. Arnolds, M. Davies, J.B. Mander University of Canterbury,

More information

CHAPTER 7 ANALYTICAL PROGRAMME USING ABAQUS

CHAPTER 7 ANALYTICAL PROGRAMME USING ABAQUS 87 CHAPTER 7 ANALYTICAL PROGRAMME USING ABAQUS 7.1 GENERAL With the advances in modern computing techniques, finite element analysis has become a practical and powerful tool for engineering analysis and

More information

Application of the strength reduction method in coal mine roof support design

Application of the strength reduction method in coal mine roof support design Paper No. 49 ISMS 2016 Application of the strength reduction method in coal mine roof support design Gabriel Esterhuizen a,*, Ihsan Berk Tulu b a Principal Research Engineer, NIOSH Office of Mine Safety

More information

FINITE ELEMENT AND LIMIT ANALYSIS OF THE LARGE SCALE MODEL OF MUSTAFA PASHA MOSQUE IN SKOPJE STRENGTHENED WITH FRP

FINITE ELEMENT AND LIMIT ANALYSIS OF THE LARGE SCALE MODEL OF MUSTAFA PASHA MOSQUE IN SKOPJE STRENGTHENED WITH FRP Asia-Pacific Conference on FRP in Structures (APFIS 2007) S.T. Smith (ed) 2007 International Institute for FRP in Construction FINITE ELEMENT AND LIMIT ANALYSIS OF THE LARGE SCALE MODEL OF MUSTAFA PASHA

More information

Behaviour of Strip Footing on Geogrid Reinforced Slope subjected to Eccentric Load

Behaviour of Strip Footing on Geogrid Reinforced Slope subjected to Eccentric Load ISSN (Print): 2347-671 (An ISO 3297: 27 Certified Organization) Behaviour of Strip Footing on Geogrid Reinforced Slope subjected to Eccentric Load Dhiraj D. Patil 1, Sunil S. Pusadkar 2, Sanjay W. Thakare

More information