Ductility of Welded Steel Column to Cap Beam Connections Phase 2

Size: px
Start display at page:

Download "Ductility of Welded Steel Column to Cap Beam Connections Phase 2"

Transcription

1 Ductility of Welded Steel Column to Cap Beam Connections Phase 2 Test 2 Summary Report 1 June Executive Summary Prepared for: Alaska Department of Transportation and Public Facilities Alaska University Transportation Center UAF Prepared by: Steven J. Fulmer Mervyn J. Kowalsky James M. Nau North Carolina State University, Raleigh, NC The test 2 specimen consisted of a composite connection configuration utilizing shear stud connectors placed on the outside the pile section which was inserted into a larger stub pile section that contained a matching pattern of shear studs as shown in Figure 4. The annular space formed between the two components was filled with flowable grout allowing for composite action to develop the moment connection by transferring forces from the pile to the cap beam via the stub pile, while avoiding inelasticity in critical welded regions. The results of experimental testing showed the connection capable of successfully developing a flexural hinging mode of failure in the form of pile wall local buckling at the intended region. All regions which were considered to be in critical need of remaining elastic were shown through data analysis to remain within the intended elastic range as the full flexural hinging capacity of the piles developed. Ultimately, the limit state of pile wall local buckling was shown to control at a reliable displacement ductility level of 3 associated with 8.44 of displacement or 8.1% drift. Although associated with large levels of damage and loss of strength, the specimen was able to remain in-tact at a displacement ductility of 6 associated with of displacement. 1

2 2. Introduction The second test of the second phase of this project was aimed at evaluating the capability of a composite connection between the pile and cap beam elements of the steel pier, to effectively isolate damage in the form of flexural hinging within the pile section while protecting connection and cap beam elements as the pier was subjected to lateral loading. More specifically, the connection consisted of a 24 x0.500 stub pipe pile section that was connected to the cap beam by a complete joint penetration weld (CJP) with a 3/8 reinforcing fillet weld. The inner diameter of the stub pile contained 12 lines of welded 3/4 diameter 2-1/2 long shear stud connectors located at 30 degrees on centers around the pipe with 4 shear studs in a given line. Similarly the top of the HSS16x0.500 pile section had 12 lines of 4 matching shear studs welded at 30 degrees on centers around the cross section offset by 15 radially and 2-1/2 vertically from the studs inside the larger stub pile. The shear stud pocket, shown in Figure 1, was grouted utilizing non-shrinking flowable grout to complete the moment resisting connections of the bent as shown in Figure 2. Further design and construction details are provided in subsequent sections of this report. Figure 1. Annular Shear Stud Pocket 2

3 Figure 2. Steel Bent with Composite Connections 3. Bent and Connection Design Similar to past configurations, ASTM A500 Gr. B HSS16x0.500 piles were chosen as the column elements of the bent to produce reasonable aspect and D/t ratios. The construction of the cap beam consisted of double ASTM A572 HP14x117 sections to provide both a capacity protected cap beam as well as adequate bearing seat width for single span girders, should a designer choose not to utilize continuous spans. A 24 x0.500 pipe section manufactured to the material standards of ASTM A500 Gr. B was utilized as the stub pile element to provide an adequate gap for the placement of shear studs as well as to accommodate construction tolerances. The design of the composite connection was based on the assumption that the total nominal strength of the shear stud connectors, on the pile side, should be capable of developing yielding of the HSS16x0.500 gross cross section. From known, or anticipated, material properties a required number of 3/4 diameter shear studs could be determined and distributed around the cross section in an even pattern. A matching number of studs were then placed on the stub pile side to facilitate load transfer in a truss mechanism between the studs on either side of the connection. The nominal capacity of a single shear stud was determined utilizing the provisions of AASHTO LRFD Bridge Design Specifications (2007) Section as well as the AISC 13 th Edition Specifications Section I3 both of which provide the same model shown in Eq. 1. As indicated in 3

4 Eq. 1, the model is a function of concrete compressive strength as well as the cross sectional area of the shear stud with an upper bound of stud shear rupture. Although the model is intended for use (in both codes) for composite construction between beams and a slab or bridge deck, it has been assumed conservative for use in this design given the highly confined nature of the annular grout pocket maintaining a logical upper bound of shear rupture of the stud.. Q n = 0.5A sc (f c E c ) 0.5 A sc F u E c =1746(f c ) 0.5 AISC, 1820(f c ) 0.5 AASHTO Eq. 1a (ksi) Eq. 1b (NWC) Utilizing this model along with expected material properties of the grout and specified material properties of ASTM A108 shear stud connectors, it was found that a minimum of 43 shear stud connectors were necessary based on an anticipated yield stress of 54 ksi for the HSS16x0.500 ASTM A500 Gr. B piles. To generate a symmetrical condition, 12 lines of 4 shear studs at 30 on centers were utilized providing 48 shear studs on the pile side or 96 total per connection as shown in Figure 3. The details of the connection are provided in Figure 4. It should also be noted that the 24 x0.500 stub pile section, acting non-compositely at the cap beam connection, was designed to remain elastic at the full flexural over strength capacity of the piles. Figure 3. Pile Side Shear Studs (48 per pile) 4

5 Figure 4. Composite Shear Stud Connection Details 4. Construction Process The welding of the cap beam elements, stub piles to the cap beam, and shear stud connectors was conducted by the fabricator to eliminate the necessity of any field welding. Hence, only grout placement was necessary to complete the connection at the laboratory. To ensure adequate workability as well strength capacity, an extended working time non-shrining grout product, BASF Masterflow 928, was chosen. Emphasis was also placed in the selection process to ensure that a widely available material was selected. 5

6 To assist in minimizing the possibility of air voids within the annular grout pocket, the decision was made to pump grout vertically from the bottom of the connection to the top where 1 diameter holes had been left in the cap beam flange to allow air to escape the connection. A hand operated pumping system was utilized along with shut off valves that were cast into place and later removed to facilitated pumping of the grout as shown in Figure 5 and Figure 6. In addition to the pocketed connections, (12) 4 x8 cylinders were also cast for testing to ensure a minimum compressive strength of 5-6 ksi was obtained by the grout prior to testing of the specimen. Figure 5. Grout Pumping System 6

7 Figure 6. Cast In Place Shut-Off Valve 5. Load History and Instrumentation The test specimen was laterally loaded using a 440 kip MTS hydraulic actuator at North Carolina State University s Constructed Facilities Laboratory as shown in Figure 7. The applied load history, termed a three cycle set history, consisted of an initial elastic portion based on the anticipated yield force of the system and a second section based on the experimentally determined yield displacement of the system. More specifically, single reverse cyclic load controlled cycles of ¼ first yield force increments were applied until a full first yield force cycle was conducted where the first yield force is determined in accordance with Eq. 2. In Eq. 2, S represents the section modulus of the HSS 16x0.500 pile, f y represents the anticipated yield stress of the pile material, and X represents shear span from the pinned supports to the critical section. In the case of test 2, the average material yield strength was found to be 56.5 ksi for the A500 Gr. B pile material based on in-house material testing. This value, combined with the shear span of 8.65 from the pinned supports to the base of the composite connection, resulted in a first yield force of 93.3 kips. The second section of the load history was defined by displacement controlled incremental ductility levels where ductility 1, or effective yield, is defined by Eq. 3 and subsequent displacement ductility levels are defined by Eq. 4. In Eq. 3, Δ y represents the experimentally determined first yield displacement while M p and M y represent the full plastic moment capacity and the first yield 7

8 moment capacity of the pile section respectively. In the case of test 2, the experimentally determined first yield displacement of 2.15 resulted in a ductility 1 displacement of The load and displacement histories resulting from this testing method are provided in Figure 8 and Figure 9 respectively. South Positive Load North Negative Load 440 Kip Actuator Strong Wall Pinned Supports Strong Floor Figure 7. Laboratory Set-Up F y = 2(S)(f y )/(X) Eq. 2 Δ y = (M p /M y )Δ y = µ 1 Eq. 3 µ i = i(µ 1 ) Eq. 4 8

9 Displacement (in) Displacement (cm) Force (kip) Force (kn) F y /4 F y /2 F y μ 1.5 μ 2 μ 1 μ 3 μ 4 μ Figure 8. Test 2 Load History μ 3 μ1.5 μ 2 μ 1 μ 4 μ Figure 9. Test 2 Displacement History 9

10 The instrumentation utilized in test 2 consisted of traditional laboratory instrumentation as well as the Optotrak motion sensing system that tracks the location of LED markers, which was also utilized in phase 1. The traditional equipment consisted of inclinometers located 8 above the center line of the pinned bases to monitor drift magnitudes, linear string potentiometers attached to the bases to monitor any unanticipated base sliding, and strain gauges located on the extreme fibers of each pile cross section as shown in Figure 10. As was mentioned, in addition to the traditional instrumentation, a 2 spaced grid of Optotrak LED markers was placed on the east face of each pile in both the composite connection and critical pile regions as shown in Figure 11. Post processing of the local deformation data recorded by the Optotrak system allows for additional strain calculations over a larger area and at higher levels of strain than is allowed by the traditional electric resistance strain gauges. Figure 10. Strain Gauge Layout Figure 11. Optotrak Marker Grid 6. Experimental Summary The results of experimental testing showed the specimen to perform in an adequate manner with no appreciable signs of damage that could be related to strength loss or any upper bound limit state throughout the second ductility level as is shown in Figure 12 and Figure 13. However, minor signs of inconsequential damage were experienced as early as the first yield cycles where cracking was observed at the base of the grout pocket as shown in Figure 14. Throughout the ductility 1 and 2 cycles, more small cracks developed in addition to the formation of small gaps between the grout block and the pile and/or stub pile walls on the tensile faces of each column as shown in Figure 15. However, this observed damage was not associated any significant recognizable limit state or strength loss. 10

11 Force (kip) Force (kn) Force (kip) Force (kn) Displacement (cm) μ μ μ μ 3 μ μ Displacement (in) Figure 12. Test 2 Force-Displacement Hysteresis Displacement (cm) μ 1.5 μ μ 2 μ 3 1 μ Displacement (in) Figure 13. Test 2 Force-Displacement Envelopes μ 6 Cycle 1 Cycle 2 Cycle

12 Figure 14. North Pile North Face, -Fy Cycle, kips, Small Cracks Figure 15. North Pile South Face, Ductility 2 Cycle 1, 134 kips, 5.62 in 12

13 The first signs of the development a critical limit state occurred in third positive cycle of the ductility 2 loading stage where a small magnitude of pile wall local buckling began to develop on the north side (compression face) of the south HSS16x0.500 pile along with a small amount of slip between the grout block and the stub pile wall. Upon reversal to the third negative cycle of ductility 2, a similar magnitude of local buckling developed on the south side (compression face) of the north pile as well as grout block slipping as shown in Figure 16. In neither case was the buckling significant enough to produce any noticeable strength loss in either the full force-displacement response or the force-displacement response envelopes. Figure 16. North Pile South Face, Ductility 2 Cycle -3, -132 kips, in Progressing into the first positive and negative cycle of ductility 3, 8.44 of displacement as shown in Figure 17, led to an increase in the magnitude of local buckling on both piles but again no recognizable strength loss in the system. However, the second and third cycles of the ductility 3 level produced propagation of the pile wall local buckling which consequently led to strength reductions of approximately 10% and 15% respectively. Additionally during these cycles, grout located below the first row of shear studs began to spall as shown in Figure

14 As the test progressed into the ductility 4 cycles, of displacement as shown in Figure 19, intense local buckling developed inducing strength reduction magnitudes of approximately 25% to 40% throughout the ductility level. As the magnitude of the local buckling increased, small cracks began to develop in these regions of the pile wall as shown in Figure 20. As is also shown, grout began to spall to the depth of the first row of shear studs at this ductility level. Although at the completion of the ductility 4 cycles the damage, as well as the associated strength loss, was signification the bent remained in-tact and did not exhibited any complete wall cracking. The test was therefore continued to a ductility level of 6. Figure 17. Ductility 3 Cycle 1, 134 kips, 8.44 in 14

15 Figure 18. Ductility 3 Cycle 2, 126 kips, 8.44in Figure 19. Ductility 4 Cycle 1, 103 kips, in 15

16 Figure 20. Ductility 4 Cycle 3, North Pile South Face, 85 kips, in As the test progressed to the first positive cycle of the ductility 6 level, associated with of displacement as shown in Figure 21, pile wall cracking developed in the south face of the north column and propagated until the ductility 6 displacement was reached. Similarly, as the specimen was displaced towards the first negative cycle, pile wall cracking developed on the north face of the south column at the location of prior buckling. This cracking propagated until the ductility 6 displacement was reached as shown in Figure 22. At this point, approximately 60% strength loss had been experienced so the specimen was returned to a neutral position and the test was assumed to be concluded. 16

17 Figure 21. Ductility 6 Cycle 1, 75 kips, in Figure 22. Ductility 6 Cycle -1, -54 kips, in 17

18 Distance Below Cap Beam (in) Following testing, Optotrak data analysis was conducted to evaluate the effectiveness of the connection configuration to reduce strain demands within the connection itself and appropriately relocate damage. As is shown in Figure 23 through Figure 26, the connection did remain in the elastic range while large inelastic demands were forced below the bottom of the connection which terminated at 23 below the cap beam. As was intended in the design of the connection, a critical region developed immediately below the capacity protected connection on both extreme fibers of the south pile in both directions of loading. Strains in the approximate region of (µε) were developed in this critical region prior to the formation of local buckling at the ductility 3 stage of loading. Although not shown in this report for brevity, nearly identical response was experienced on the north pile. It should be noted that in some cases, such as Figure 23, the vertical strain profile appears to enter the positive range on a face that should be experiencing negative strains or vice versa. This condition is generated in a region where significant local buckling has occurred and the orientation of the Optotrak marker is no longer correctly indicative of engineering strains. Micro-Strain (µε) ε y ε y Fy 5 µ1 µ µ2 Cycle 1 µ3 15 µ4 µ6 20 Connection Base Figure 23. Test 2 South Column North Face Positive Cycle 1 Vertical Strain Profile 18

19 Distance Below Cap Beam (in) Distance Below Cap Beam (in) Micro-Strain (µε) ε y ε y Fy 5 µ1 µ µ2 µ3 15 µ4 µ6 20 Connection Base Cycle 1 50 Figure 24. Test 2 South Column South Face Positive Cycle 1 Vertical Strain Profile Micro-Strain (µε) ε y ε y Fy 5 µ1 µ µ2 µ3 15 µ4 µ6 20 Connection Base Cycle 1 Figure 25. Test 2 South Column North Face Negative Cycle 1 Vertical Strain Profile 19

20 Distance Below Cap Beam (in) Micro-Strain (µε) ε y ε y Fy 5 µ1 µ µ2 Cycle 1 µ3 15 µ4 µ6 20 Connection Base Figure 26. Test 2 South Column South Face Negative Cycle 1 Vertical Strain Profile 7. General Conclusions The physical results of experimental testing, as well as the results of data analysis, indicate that the composite connection design considered in this test was effective in producing a desirable failure mode in the form of flexural hinging of the HSS16x0.500 pile wall. Consequently, undesirable failure modes such weld cracking or tearing the pile wall prior to local buckling were avoided. Although some damage did develop within the grout block at the base of the connection in the form of cracking and spalling, no adverse consequences were induced on the structural response due to these actions. Although these actions may be considered as low level response limit states such as a serviceability limit state (hence some repair after seismic loading would be necessary) they would not constitute an ultimate limit state. As has been noted, the ultimate limit state in this case would be considered pile wall local buckling likely corresponding to a reliable displacement ductility level of 3 depending on the exact allowable level of strength loss. It should also be noted that, although associated with large levels of damage and loss of strength, the specimen was able to remain in-tact at displacement ductility of 6 associated with of displacement. This is largely due to the development of a stable failure mode while avoiding more brittle failure mode such as welded connection cracking. From the results presented in this report, the design methodology of developing the axial yield capacity of the pile to determine the required number shear stud connectors appears to be adequate and no optimization options are immediately evident. 20

21 8. Project Direction Following the completion of test 2, progress began on the construction of the test 3 specimen which consists of a semi-dog-bone column capital configuration designed to relocate damage by developing flexural hinging in a reduced section region as shown in Figure 27 and Figure 28. To date, the construction, including all weld inspections, has been completed allowing for instrumentation of the specimen to begin. Provided the anticipated desirable failure mode of flexural hinging in the form of local buckling within the reduced region is shown to control the response of the specimen, the test will serve as validation to and improvement upon a similar design evaluated in test 6 of the first phase of this project. The design evaluated in that test utilized a capital with a single bevel that had no specific reduced section to precisely locate damage. Figure 27. Semi-Dog-Bone Capital Connection Detail 21

22 Figure 28. Semi-Dog-Bone Capital Connection Again, assuming the test 3 specimen performs as anticipated, two viable alternatives to develop the desirable flexural hinging failure will have been developed. These would include the composite shear stud connection discussed in this report and the column capital. The tests following test 3 could include the following options: Test 4: evaluation of composite shear stud connection with construction tolerance offsets (see Figure 29) Test 5: verification of optimal composite shear stud connection if poor performance is exhibited by the evaluation of the construction tolerance offsets Test 5 (or 6) 9: composite connection with other mechanical shear connectors (i.e. bolts) truss system evaluation shake table testing of composite shear stud connection and/or capital connection 22

23 Figure 29. Composite Shear Stud Connection with Construction Tolerance Offset 9. References AASHTO LRFD Bridge Design Specifications, American Association of State Highway and Transportation Officials, 4 th Edition, AISC Specifications for Structural Steel Buildings, American Institute of Steel Construction, March,

Seismic Performance of Steel Bridge Piers Containing Composite Connections

Seismic Performance of Steel Bridge Piers Containing Composite Connections Seismic Performance of Steel Bridge Piers Containing Composite Connections S.J. Fulmer, M.J. Kowalsky & J.M. Nau Department of Civil, Construction and Envinronmental Engineering, North Carolina State University,

More information

In-plane testing of precast concrete wall panels with grouted sleeve

In-plane testing of precast concrete wall panels with grouted sleeve In-plane testing of precast concrete wall panels with grouted sleeve P. Seifi, R.S. Henry & J.M. Ingham Department of Civil Engineering, University of Auckland, Auckland. 2017 NZSEE Conference ABSTRACT:

More information

Strain Limits for Concrete Filled Steel Tubes in AASHTO Seismic Provisions. PIs: Mervyn Kowalsky and James Nau RA: Nicole King

Strain Limits for Concrete Filled Steel Tubes in AASHTO Seismic Provisions. PIs: Mervyn Kowalsky and James Nau RA: Nicole King Strain Limits for Concrete Filled Steel Tubes in AASHTO Seismic Provisions PIs: Mervyn Kowalsky and James Nau RA: Nicole King Project Overview Seismic behavior of reinforced concrete filled steel pipe

More information

Pile to Slab Bridge Connections

Pile to Slab Bridge Connections Pile to Slab Bridge Connections Mohamed I. Ayoub 1, David H. Sanders 2 and Ahmed Ibrahim 3 Abstract Slab bridges are a common bridge type, where the pile extends directly from the ground to the superstructure.

More information

CFT Column-to-Cap Beam Connections for. Accelerated Bridge Construction in Seismic Regions. Lisa Marie Berg. Master of Science in Civil Engineering

CFT Column-to-Cap Beam Connections for. Accelerated Bridge Construction in Seismic Regions. Lisa Marie Berg. Master of Science in Civil Engineering CFT Column-to-Cap Beam Connections for Accelerated Bridge Construction in Seismic Regions Lisa Marie Berg A thesis submitted in partial fulfillment of the requirements for the degree of Master of Science

More information

Bijan Khaleghi, Ph, D. P.E., S.E.

Bijan Khaleghi, Ph, D. P.E., S.E. 0 Submission date: July, 0 Word count: 0 Author Name: Bijan Khaleghi Affiliations: Washington State D.O.T. Address: Linderson Way SW, Tumwater WA 0 INTEGRAL BENT CAP FOR CONTINUOUS PRECAST PRESTRESSED

More information

Survey and Testing of Pre-1988 Braced Frame Structures From The West Coast of the United States

Survey and Testing of Pre-1988 Braced Frame Structures From The West Coast of the United States Survey and Testing of Pre-1988 Braced Frame Structures From The West Coast of the United States Dan Sloat 1, Charles W. Roeder 2, Dawn E. Lehman 3, and Jeffrey W. Berman 4 1 Graduate Student, Dept. of

More information

Seismic Performance of Precast Concrete Bents used for Accelerated Bridge Construction. Bijan Khaleghi 1

Seismic Performance of Precast Concrete Bents used for Accelerated Bridge Construction. Bijan Khaleghi 1 Seismic Performance of Precast Concrete Bents used for Accelerated Bridge Construction Bijan Khaleghi 1 Abstract Ductility of precast prestressed girder bridges can be achieved by proper detailing of pier

More information

FINITE ELEMENT ANALYSIS OF REINFORCED CONCRETE BRIDGE PIER COLUMNS SUBJECTED TO SEISMIS LOADING

FINITE ELEMENT ANALYSIS OF REINFORCED CONCRETE BRIDGE PIER COLUMNS SUBJECTED TO SEISMIS LOADING FINITE ELEMENT ANALYSIS OF REINFORCED CONCRETE BRIDGE PIER COLUMNS SUBJECTED TO SEISMIS LOADING By Benjamin M. Schlick University of Massachusetts Amherst Department of Civil and Environmental Engineering

More information

EXPERIMENTAL RESULTS

EXPERIMENTAL RESULTS Chapter 4 EXPERIMENTAL RESULTS 4.1 Introduction This chapter presents the results from the half scale interior Corcon rib beam-column subassemblage and the FRP repaired subassemblage. As described in chapter

More information

Moment curvature analysis of concrete flexural members confined with CFRP grids

Moment curvature analysis of concrete flexural members confined with CFRP grids Materials Characterisation V 131 Moment curvature analysis of concrete flexural members confined with CFRP grids A. Michael & P. Christou Department of Civil Engineering, Frederick University, Cyprus Abstract

More information

Hybrid System Using Precast Prestressed Frame with Corrugated Steel Panel Damper

Hybrid System Using Precast Prestressed Frame with Corrugated Steel Panel Damper Journal of Advanced Concrete Technology Vol. 7, No. 3, 297-36, October 29 / Copyright 29 Japan Concrete Institute 297 Scientific paper Hybrid System Using Precast Prestressed Frame with Corrugated Steel

More information

IMPROVEMENT OF THE DEFORMATION CAPACITY BY THE USE OF FIBERS

IMPROVEMENT OF THE DEFORMATION CAPACITY BY THE USE OF FIBERS IMPROVEMENT OF THE DEFORMATION CAPACITY BY THE USE OF FIBERS Kenji Kosa and Hiroki Goda Department of Civil Engineering, Kyushu Institute of Technology, Japan Abstract To improve the seismic resistance

More information

Effect of Reinforcement Grade and Ratio on Seismic Performance of Reinforced Concrete Columns

Effect of Reinforcement Grade and Ratio on Seismic Performance of Reinforced Concrete Columns ACI STRUCTURAL JOURNAL TECHNICAL PAPER Title No. 113-S77 Effect of Reinforcement Grade and Ratio on Seismic Performance of Reinforced Concrete Columns by David Trejo, Timothy B. Link, and André R. Barbosa

More information

4.6 Procedures for Connections

4.6 Procedures for Connections 4.6 Procedures for Connections This section provides Tier 2 evaluation procedures that apply to structural connections: anchorage for normal forces, shear transfer, vertical components, interconnection

More information

Cold-Formed Steel Special Bolted Moment Frames: Cyclic Testing and Numerical Modeling of Moment Connections

Cold-Formed Steel Special Bolted Moment Frames: Cyclic Testing and Numerical Modeling of Moment Connections Cold-Formed Steel Special Bolted Moment Frames: Cyclic Testing and Numerical Modeling of Moment Connections by Chia-Ming Uang 1, Jong-Kook Hong 2, Atsushi Sato 3 and Ken Wood 4 ABSTRACT Cyclic tests on

More information

MIDAS Training Series

MIDAS Training Series MIDAS midas Civil Title: All-In-One Super and Sub Structure Design NAME Edgar De Los Santos / MIDAS IT United States 2016 Substructure Session 1: 3D substructure analysis and design midas Civil Session

More information

DUCTILITY REQUIREMENTS FOR BUILDINGS

DUCTILITY REQUIREMENTS FOR BUILDINGS DUCTILITY REQUIREMENTS FOR BUILDINGS Prof. P. C. Vasani, Applied Mechanics Department, L. D. College of Engineering, Ahmedabad 380015. profvasani@rediffmail.com Bhumika B. Mehta M. E. CIVIL - (CASAD) Sem

More information

Seismic Evaluation and Retrofit of Bridge Joints

Seismic Evaluation and Retrofit of Bridge Joints Seismic Evaluation and Retrofit of Bridge Joints Nicholas J. Ereckson 1 Pedro F. Silva 2 Genda Chen 3 ABSTRACT A research program was initiated at the University of Missouri Rolla (UMR) to accomplish the

More information

by Dr. Mark A. Ketchum, OPAC Consulting Engineers for the EERI 100 th Anniversary Earthquake Conference, April 17, 2006

by Dr. Mark A. Ketchum, OPAC Consulting Engineers for the EERI 100 th Anniversary Earthquake Conference, April 17, 2006 Principles of Earthquake Engineering of Bridges Part 1: Principles & Approach by Dr. Mark A. Ketchum, OPAC Consulting Engineers for the EERI 100 th Anniversary Earthquake Conference, April 17, 2006 Presentation

More information

RESILIENT INFRASTRUCTURE June 1 4, 2016

RESILIENT INFRASTRUCTURE June 1 4, 2016 RESILIENT INFRASTRUCTURE June 1 4, 216 ENHANCING THE DEFORMATION CAPACITY OF CONCRETE SHEAR WALLS REINFORCED WITH GFRP BARS Ahmed Hassanein Doctoral student, Université de Sherbrooke, Canada Nayera Mohamed

More information

Structural Glossary. ARCH 631 Structural Glossary F2014abn

Structural Glossary. ARCH 631 Structural Glossary F2014abn Structural Glossary Allowable strength: Nominal strength divided by the safety factor. Allowable stress: Allowable strength divided by the appropriate section property, such as section modulus or cross

More information

Self-Centering Bridge Piers with Structural Fuses

Self-Centering Bridge Piers with Structural Fuses Self-Centering Bridge Piers with Structural Fuses Mark C. Currie Department of Civil, Construction, and Environmental Engineering Iowa State University 176 Town Engineering Ames, IA 511 mcurrie@iastate.edu

More information

SEISMIC PERFORMANCE OF FLAT-SLAB SHEAR REINFORCEMENT

SEISMIC PERFORMANCE OF FLAT-SLAB SHEAR REINFORCEMENT SEISMIC PERFORMANCE OF FLAT-SLAB SHEAR REINFORCEMENT Ian N ROBERTSON 1, Tadashi KAWAI, James LEE 3 And Brian ENOMOTO SUMMARY The intent of this research program was to study the response of slab-column

More information

CYCLIC LOADING TEST OF REINFORCED CONCRETE COLUMN WITH HOLLOW SECTION AND HIGH LONGITUDIAL STEEL RATIO UNDER HIGH AXIAL LOADING

CYCLIC LOADING TEST OF REINFORCED CONCRETE COLUMN WITH HOLLOW SECTION AND HIGH LONGITUDIAL STEEL RATIO UNDER HIGH AXIAL LOADING CYCLIC LODING TEST OF REINFORCED CONCRETE COLUMN WITH HOLLOW SECTION ND HIGH LONGITUDIL STEEL RTIO UNDER HIGH XIL LODING Hitoshi YTSUMOTO 1, Junichi SKI 2, Jun-ichi HOSHIKUM 3 bstract Reinforced concrete

More information

RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO

RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO QUARTERLY REPORT October 1, 2016 to December 31, 2016 Period Year 1 Project Development and Seismic Evaluation of Pier Systems w/ Pocket Connections and Square

More information

RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO

RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO QUARTERLY REPORT October 1, 2017 to December 31, 2017 Period Year 2 Project Shake Table Studies of a Bridge System with ABC Connections Submitted by M. Saiidi,

More information

Seismic Retrofit Of RC Columns With Inadequate Lap-Splice Length By External Post-Tensioned High-Strength Strips

Seismic Retrofit Of RC Columns With Inadequate Lap-Splice Length By External Post-Tensioned High-Strength Strips Seismic Retrofit Of RC Columns With Inadequate Lap-Splice Length By External Post-Tensioned High-Strength Strips M. Samadi Department of civil engineering., Mashhad Branch, Islamic Azad University, Mashhad,

More information

Overview of Presentation. SCBFs are Conceptually Truss Structures

Overview of Presentation. SCBFs are Conceptually Truss Structures Ultimate Strength and Inelastic Behavior of Braced Frame Gusset Plate Connections Charles W. Roeder University of Washington Department of Civil and Environmental Engineering Seattle, WA 98195 Structural

More information

SHAKE TABLE TESTING OF BRIDGE REINFORCED CONCRETE COLUMNS UNDER COMBINED ACTIONS

SHAKE TABLE TESTING OF BRIDGE REINFORCED CONCRETE COLUMNS UNDER COMBINED ACTIONS SHAKE TABLE TESTING OF BRIDGE REINFORCED CONCRETE COLUMNS UNDER COMBINED ACTIONS Juan G. Arias Acosta, Graduate Student David H. Sanders, Professor and Project PI University of Nevada, Reno NEESR SG 53737

More information

Supplemental Structural Correction Sheet Steel Moment Frame Design (2017 LABC)

Supplemental Structural Correction Sheet Steel Moment Frame Design (2017 LABC) Supplemental Structural Correction Sheet Steel Moment Frame Design (2017 LABC) Plan Check/PCIS Application No.: Checked By: Your feedback is important, please visit our website to complete a Custom Survey

More information

Contents. Tables. Notation xii Latin upper case letters Latin lower case letters Greek upper case letters Greek lower case letters. Foreword.

Contents. Tables. Notation xii Latin upper case letters Latin lower case letters Greek upper case letters Greek lower case letters. Foreword. Tables x Notation xii Latin upper case letters Latin lower case letters Greek upper case letters Greek lower case letters xii xiv xvi xvi Foreword xviii 1 Introduction 1 1.1 Aims of the Manual 1 1.2 Eurocode

More information

THE BRACE CONNECTION THE BOLTED OPTION FIGURE 1 MODEL SHOWING THE BOILER AND THE STRUCTURAL SUPPORT SYSTEM (BOILER BUILDING)

THE BRACE CONNECTION THE BOLTED OPTION FIGURE 1 MODEL SHOWING THE BOILER AND THE STRUCTURAL SUPPORT SYSTEM (BOILER BUILDING) Comparative Study of Bolted versus Welded SCBF Connections Authors: Robert P. Krumpen III P.E., Bechtel Corporation, rpkrumpe@bechtel.com Dr. Peter J. Carrato P.E. S.E., Bechtel Corporation, pcarrato@bechtel.com

More information

DIAPHRAGM BEHAVIOR OF DECONSTRUCTABLE COMPOSITE FLOOR SYSTEMS

DIAPHRAGM BEHAVIOR OF DECONSTRUCTABLE COMPOSITE FLOOR SYSTEMS DIAPHRAGM BEHAVIOR OF DECONSTRUCTABLE COMPOSITE FLOOR SYSTEMS Jerome F. Hajjar, Lizhong Wang Department of Civil and Environmental Engineering Northeastern University Mark D. Webster Simpson Gumpertz and

More information

SEISMIC RETROFITTING OF REINFORCED CONCRETE COLUMNS USING CARBON FIBER REINFORCED POLYMER (CFRP)

SEISMIC RETROFITTING OF REINFORCED CONCRETE COLUMNS USING CARBON FIBER REINFORCED POLYMER (CFRP) Asia-Pacific Conference on FRP in Structures (APFIS 7) S.T. Smith (ed) 7 International Institute for FRP in Construction SEISMIC RETROFITTING OF REINFORCED CONCRETE COLUMNS USING CARBON FIBER REINFORCED

More information

NON-LINEAR FEM ANALYSIS FOR CES SHEAR WALLS

NON-LINEAR FEM ANALYSIS FOR CES SHEAR WALLS 1NCEE Tenth U.S. National Conference on Earthquake Engineering Frontiers of Earthquake Engineering July 21-25, 214 Anchorage, Alaska NON-LINEAR FEM ANALYSIS FOR CES SHEAR WALLS S. SUZUKI 1, H. KURAMOTO

More information

HIGH PERFORMANCE CONCRETE. by John J. Roller CTLGroup

HIGH PERFORMANCE CONCRETE. by John J. Roller CTLGroup HIGH PERFORMANCE CONCRETE by John J. Roller CTLGroup Early Louisiana HPC Research Law & Rasoulian (1980) Adelman & Cousins (1990) Bruce, Russell & Roller (1990-1993) Law & Rasoulian (1980) Concrete strengths

More information

22. DESIGN OF STEEL BRACED FRAMES Eccentrically Braced Steel Frames

22. DESIGN OF STEEL BRACED FRAMES Eccentrically Braced Steel Frames 22. DESIGN OF STEEL BRACED FRAMES 22.1 Eccentrically Braced Steel Frames Objective is to dissipate energy in the shear or moment links and to protect the remainder of the frame from inelastic action, including

More information

RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO

RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO QUARTERLY REPORT October 1, 2016 to December 31, 2016 Period Year 2 Project Shake Table Studies of a Bridge System with ABC Connections Submitted by M. Saiidi,

More information

BUILDING RETROFITS: BREATHING NEW LIFE INTO EXISTING BUILDING STRUCTURES

BUILDING RETROFITS: BREATHING NEW LIFE INTO EXISTING BUILDING STRUCTURES BUILDING RETROFITS: BREATHING NEW LIFE INTO EXISTING BUILDING STRUCTURES CLIFFORD SCHWINGER Clifford Schwinger Clifford Schwinger, P.E. is Vice President and Quality Assurance Manager at Cagley Harman

More information

CYCLIC PERFORMANCE OF RC BEAMS WITH WEB OPENINGS

CYCLIC PERFORMANCE OF RC BEAMS WITH WEB OPENINGS CYCLIC PERFORMANCE OF RC BEAMS WITH WEB OPENINGS Luis HERRERA 1 and Anne LEMNITZER 2 ABSTRACT The introduction of web openings in reinforced concrete beams enables the passage of utility services and avoids

More information

ST7008 PRESTRESSED CONCRETE

ST7008 PRESTRESSED CONCRETE ST7008 PRESTRESSED CONCRETE QUESTION BANK UNIT-I PRINCIPLES OF PRESTRESSING PART-A 1. Define modular ratio. 2. What is meant by creep coefficient? 3. Is the deflection control essential? Discuss. 4. Give

More information

INNOVATIVE DESIGN AND TESTING OF A SEISMIC RETROFITTED STEEL DECK TRUSS BRIDGE

INNOVATIVE DESIGN AND TESTING OF A SEISMIC RETROFITTED STEEL DECK TRUSS BRIDGE INNOVATIVE DESIGN AND TESTING OF A SEISMIC RETROFITTED STEEL DECK TRUSS BRIDGE Dr. Majid Sarraf, P.E., P.Eng Dr. Michel Bruneau, P.Eng Dr. Sarraf is a Senior Project Engineer and Seismic Specialist at

More information

RESILIENT INFRASTRUCTURE June 1 4, 2016

RESILIENT INFRASTRUCTURE June 1 4, 2016 RESILIENT INFRASTRUCTURE June 1 4, 2016 MOMENT REDISTRIBUTION OF GFRP-RC CONTINUOUS T-BEAMS S. M. Hasanur Rahman M.Sc. Student, University of Manitoba, Canada Ehab El-Salakawy Professor and CRC in Durability

More information

Modelling of RC moment resisting frames with precast-prestressed flooring system

Modelling of RC moment resisting frames with precast-prestressed flooring system Modelling of RC moment resisting frames with precast-prestressed flooring system B.H.H. Peng, R.P. Dhakal, R.C. Fenwick & A.J. Carr Department of Civil Engineering, University of Canterbury, Christchurch.

More information

RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO

RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO RESEARCH PROJECT AT UNIVERSITY OF NEVADA, RENO QUARTERLY REPORT Oct. 1, 2015 to December 31, 2015 Period Submitted by M. Saiidi, A. Itani, and A. Mohebbi Department of Civil and Environmental Engineering

More information

In-Plane and Out-of-Plane Performance of the MINI-MC Flange Connector

In-Plane and Out-of-Plane Performance of the MINI-MC Flange Connector Lehigh University Lehigh Preserve ATLSS Reports Civil and Environmental Engineering 7-1-2009 In-Plane and Out-of-Plane Performance of the MINI-MC Flange Connector Clay Naito Ruirui Ren Follow this and

More information

Deformation Capacity of RC Structural Walls without Special Boundary Element Detailing

Deformation Capacity of RC Structural Walls without Special Boundary Element Detailing Proceedings of the Tenth Pacific Conference on Earthquake Engineering Building an Earthquake-Resilient Pacific 6-8 November 2015, Sydney, Australia Deformation Capacity of RC Structural Walls without Special

More information

Seismic design of braced frame gusset plate connections

Seismic design of braced frame gusset plate connections Earthquake Resistant Engineering Structures V 105 Seismic design of braced frame gusset plate connections C. W. Roeder, D. E. Lehman, A. Christopolus, I. Gunnarson, S. Johnson & J. H. Yoo Department of

More information

PEER Tall Building Seismic Design Guidelines

PEER Tall Building Seismic Design Guidelines PEER Tall Building Seismic Design Guidelines Analysis, Modeling and Acceptance Criteria Ronald O. Hamburger Senior Principal Simpson Gumpertz & Heger Inc. SEAW November 30, 2010 Purpose of Analysis Demonstrate

More information

There are countless ways to improve constructability on your next project. Here are 50 of them. the need for it or specify it on the design drawings.

There are countless ways to improve constructability on your next project. Here are 50 of them. the need for it or specify it on the design drawings. There are countless ways to improve constructability on your next project. Here are 50 of them. Tips to Take your Team to the Top By Matthew D. Brady, P.E., and Cliff Schwinger, P.E. We hear the word constructability

More information

Bjorhovde, R. Stub Girder Floor Systems Structural Engineering Handbook Ed. Chen Wai-Fah Boca Raton: CRC Press LLC, 1999

Bjorhovde, R. Stub Girder Floor Systems Structural Engineering Handbook Ed. Chen Wai-Fah Boca Raton: CRC Press LLC, 1999 Bjorhovde, R. Stub Girder Floor Systems Structural Engineering Handbook Ed. Chen Wai-Fah Boca Raton: CRC Press LLC, 1999 Stub Girder Floor Systems Reidar Bjorhovde Department of Civil and Environmental

More information

A STUDY ON RESTORABLE PRECAST PRESTRESSED HYBRID PIERS. Akio Kasuga 1 Shigeki Unjo 2 Yoshihiko Taira 1 Hiroshi Asai 1

A STUDY ON RESTORABLE PRECAST PRESTRESSED HYBRID PIERS. Akio Kasuga 1 Shigeki Unjo 2 Yoshihiko Taira 1 Hiroshi Asai 1 A STUDY ON RESTORABLE PRECAST PRESTRESSED HYBRID PIERS Akio Kasuga 1 Shigeki Unjo 2 Yoshihiko Taira 1 Hiroshi Asai 1 1.Introduction Column members such as bridge piers that resist seismic forces are generally

More information

AISI S E1 AISI STANDARD. Errata to North American Specification. for the Design of Cold-Formed. Steel Structural Members.

AISI S E1 AISI STANDARD. Errata to North American Specification. for the Design of Cold-Formed. Steel Structural Members. AISI S100-12-E1 AISI STANDARD Errata to North American Specification for the Design of Cold-Formed Steel Structural Members 2012 Edition Amendment on August 16, 2013 Errata to North American Specification

More information

1/26/2015 DETAILS CIP DETAIL EXAMPLES WHY SIMPLIFY DETAILS? CIP DETAIL EXAMPLES DETAILING FOR SIMPLICITY

1/26/2015 DETAILS CIP DETAIL EXAMPLES WHY SIMPLIFY DETAILS? CIP DETAIL EXAMPLES DETAILING FOR SIMPLICITY Detailing of ABC Bridges for Simplicity and Durability Michael P. Culmo, P.E. CME Associates, Inc. East Hartford, CT DETAILS This presentation contains many preferred details My favorite details will be

More information

CYCLIC BEHAVIOR OF SLENDER R/C COLUMNS WITH INSUFFICIENT LAP SPLICE LENGTH

CYCLIC BEHAVIOR OF SLENDER R/C COLUMNS WITH INSUFFICIENT LAP SPLICE LENGTH CYCLIC BEHAVIOR OF SLENDER R/C COLUMNS WITH INSUFFICIENT LAP SPLICE LENGTH S.Eshghi 1 and V.Zanjanizadeh 2 1 Assistant Professor of International Institute of Earthquake Engineering and Seismology (IIEES),

More information

BEHAVIOR OF FRP SANDWICH PANELS FOR TRANSPORTATION INFRASTRUCTURE

BEHAVIOR OF FRP SANDWICH PANELS FOR TRANSPORTATION INFRASTRUCTURE IV ACMBS MCAPC 4 th International Conference on Advanced Composite Materials in Bridges and Structures 4 ième Conférence Internationale sur les matériaux composites d avant-garde pour ponts et charpentes

More information

PACIFIC EARTHQUAKE ENGINEERING RESEARCH CENTER

PACIFIC EARTHQUAKE ENGINEERING RESEARCH CENTER PACIFIC EARTHQUAKE ENGINEERING RESEARCH CENTER Unbonded Pre-Tensioned Columns for Bridges in Seismic Regions Phillip M. Davis Todd M. Janes Marc O. Eberhard John F. Stanton Department of Civil and Environmental

More information

EFFECTS OF LOADING HISTORY ON CYCLIC PERFORMANCE OF STEEL RBS MOMENT CONNECTIONS

EFFECTS OF LOADING HISTORY ON CYCLIC PERFORMANCE OF STEEL RBS MOMENT CONNECTIONS EFFECTS OF LOADING HISTORY ON CYCLIC PERFORMANCE OF STEEL RBS MOMENT CONNECTIONS C M UANG 1, Q S YU 2 And C S GILTON 3 SUMMARY The cyclic response of steel reduced beam section moment connections under

More information

Proposed Modifications to the LRFD Design of U-Beam Bearings

Proposed Modifications to the LRFD Design of U-Beam Bearings Proposed Modifications to the LRFD Design of U-Beam Bearings Charles D. Newhouse, Scott A. Bole, W. R. Burkett, Phillip T. Nash, Mostafa El-Shami Performed in Cooperation with the Texas Department of Transportation

More information

Reinforced Concrete Column Design

Reinforced Concrete Column Design Reinforced Concrete Column Design Compressive Strength of Concrete f cr is the average cylinder strength f c compressive strength for design f c ~2500 psi - 18,000 psi, typically 3000-6000 psi E c estimated

More information

Encased Beam with Variable Upper Steel Flange Position

Encased Beam with Variable Upper Steel Flange Position Encased Beam with Variable Upper Steel Flange Position Ahmed Youssef Kamal Civil Engineering Department, Benha Faculty of Engineering, Benha University, Egypt. ABSTRACT Encased beam composite construction

More information

CHAPTER III METHODS AND MATERIALS

CHAPTER III METHODS AND MATERIALS CHAPTER III METHODS AND MATERIALS 3.1: Tensile Tests 3.1.1: Introduction The first phase of testing for the experimental program, was to conduct tensile tests of No. 4, No. 5, and No. 6 nominal diameter

More information

Seismic Behavior, Analysis and

Seismic Behavior, Analysis and UNIVERSITY of ILLINOIS NEES Small-Group Research Project: Seismic Behavior, Analysis and Design of Complex Wall Systems (NSF Grant CMMI-0421577) Laura Lowes, Dawn Lehman, Jake Turgeon, Anna Birely, Joshua

More information

Structural Upgrade of Reinforced Concrete Column-Tie Beam Assembly using FRP Composites

Structural Upgrade of Reinforced Concrete Column-Tie Beam Assembly using FRP Composites SP-258 4 Structural Upgrade of Reinforced Concrete Column-Tie Beam Assembly using FRP Composites by A.S. Mosallam Synopsis: The paper discusses the potential use of fiber reinforced polymer composites

More information

Tests of Concrete Bridge Columns with Interlocking Spiral Reinforcement

Tests of Concrete Bridge Columns with Interlocking Spiral Reinforcement TRANSPORTATION RESEARCH RECORD 1393 133 Tests of Concrete Bridge Columns with Interlocking Spiral Reinforcement GRANT C. BucKINGHAM, DAVID I. McLEAN, AND C. ERNEST NELSON The behavior of concrete bridge

More information

INCORPORATING BUCKLING RESTRAINED BRACES (BRB) AS PART OF THE AUBURN-FORESTHILL BRIDGE SEISMIC RETROFIT. Mark L. Reno, P.E. 1. Martin N. Pohll, S.E.

INCORPORATING BUCKLING RESTRAINED BRACES (BRB) AS PART OF THE AUBURN-FORESTHILL BRIDGE SEISMIC RETROFIT. Mark L. Reno, P.E. 1. Martin N. Pohll, S.E. INCORPORATING BUCKLING RESTRAINED BRACES (BRB) AS PART OF THE AUBURN-FORESTHILL BRIDGE SEISMIC RETROFIT Mark L. Reno, P.E. 1 Martin N. Pohll, S.E. 2 ABSTRACT The Foresthill Bridge was built by the Bureau

More information

Upgrading the shear strength of non-ductile reinforced concrete frame connections using FRP overlay systems

Upgrading the shear strength of non-ductile reinforced concrete frame connections using FRP overlay systems Upgrading the shear strength of non-ductile reinforced concrete frame connections using FRP overlay systems Mohamad J. Terro Associate Professor. Civil Engineering Department, Kuwait University. Sameer

More information

Seismic Behavior of Ultra-High-Performance Fiber- Reinforced Concrete Moment Frame Members

Seismic Behavior of Ultra-High-Performance Fiber- Reinforced Concrete Moment Frame Members Seismic Behavior of Ultra-High-Performance Fiber- Reinforced Concrete Moment Frame Members Shih-Ho Chao, Associate Professor, University of Texas at Arlington, TX Venkatesh Kaka, Graduate Student, University

More information

Reinforced Concrete Design. A Fundamental Approach - Fifth Edition

Reinforced Concrete Design. A Fundamental Approach - Fifth Edition CHAPTER REINFORCED CONCRETE Reinforced Concrete Design A Fundamental Approach - Fifth Edition Fifth Edition REINFORCED CONCRETE A. J. Clark School of Engineering Department of Civil and Environmental Engineering

More information

PEER Tall Building Seismic Design. Purpose of Analysis. Service Level and MCE Analysis. Ronald O. Hamburger

PEER Tall Building Seismic Design. Purpose of Analysis. Service Level and MCE Analysis. Ronald O. Hamburger PEER Tall Building Seismic Design Guidelines Service Level and MCE Analysis Ronald O. Hamburger Senior Principal Simpson Gumpertz & Heger Inc. SEAONC April 19, 2010 Purpose of Analysis Demonstrate that

More information

STRENGTHENING STEEL-CONCRETE COMPOSITE BRIDGES WITH HIGH MODULUS CARBON FIBER REINFORCED POLYMER (CFRP) LAMINATES

STRENGTHENING STEEL-CONCRETE COMPOSITE BRIDGES WITH HIGH MODULUS CARBON FIBER REINFORCED POLYMER (CFRP) LAMINATES Composites in Construction 2005 Third International Conference, Hamelin et al (eds) 2005 ISBN xxxxx Lyon, France, July 11 13, 2005 STRENGTHENING STEEL-CONCRETE COMPOSITE BRIDGES WITH HIGH MODULUS CARBON

More information

Seismic Detailing of RC Structures (IS: )

Seismic Detailing of RC Structures (IS: ) Seismic Detailing of RC Structures (IS:13920-1993) Sudhir K Jain Indian Institute of Technology Gandhinagar November 2012 1 Outline This lecture covers: Covers important clauses of IS13920 With particular

More information

Item 442 Metal for Structures

Item 442 Metal for Structures Item 442 Metal for Structures 1. DESCRIPTION 2. MATERIALS Provide structural steel, high-strength bolts, forgings, steel castings, iron castings, wrought iron, steel pipe and tubing, aluminum castings

More information

Seismic Evaluation and Retrofit of Beam- Column Joints of Mid-America Bridges Part 2: Steel Sheet and Plate Retrofit

Seismic Evaluation and Retrofit of Beam- Column Joints of Mid-America Bridges Part 2: Steel Sheet and Plate Retrofit Seismic Evaluation and Retrofit of Beam- Column Joints of Mid-America Bridges Part 2: Steel Sheet and Plate Retrofit Genda Chen, Ph.D., P.E. Associate Professor of Civil Engineering Department of Civil,

More information

STRENGTHENING WITH WING WALLS FOR SEISMICALLY SUBSTANDARD R/C BEAM-COLUMN JOINTS

STRENGTHENING WITH WING WALLS FOR SEISMICALLY SUBSTANDARD R/C BEAM-COLUMN JOINTS 10NCEE Tenth U.S. National Conference on Earthquake Engineering Frontiers of Earthquake Engineering July 21-25, 2014 Anchorage, Alaska STRENGTHENING WITH WING WALLS FOR SEISMICALLY SUBSTANDARD R/C BEAM-COLUMN

More information

EXPERIMENTAL STUDY ON THE SEISMIC PERFORMANCE OF EXTERNALLY CONFINED REINFORCED CONCRETE COLUMNS

EXPERIMENTAL STUDY ON THE SEISMIC PERFORMANCE OF EXTERNALLY CONFINED REINFORCED CONCRETE COLUMNS 13th World Conference on Earthquake Engineering Vancouver, B.C., Canada August 1-6, 2004 Paper No. 578 EXPERIMENTAL STUDY ON THE SEISMIC PERFORMANCE OF EXTERNALLY CONFINED REINFORCED CONCRETE COLUMNS Munawar

More information

Interaction between ductile RC perimeter frames and floor slabs containing precast units

Interaction between ductile RC perimeter frames and floor slabs containing precast units Interaction between ductile RC perimeter frames and floor slabs containing precast units R. C Fenwick,. J. Davidson and D.. N. Lau Department of Civil and Environmental Engineering, University of uckland.

More information

OHIO DEPARTMENT OF TRANSPORTATION CENTRAL OFFICE, 1980 W. BROAD ST., COLUMBUS, OHIO

OHIO DEPARTMENT OF TRANSPORTATION CENTRAL OFFICE, 1980 W. BROAD ST., COLUMBUS, OHIO OHIO DEPARTMENT OF TRANSPORTATION CENTRAL OFFICE, 1980 W. BROAD ST., COLUMBUS, OHIO 43216-0899 July 21, 2017 To: Users of the Bridge Design Manual From: Tim Keller, Administrator, Office of Structural

More information

Section 906. STRUCTURAL STEEL

Section 906. STRUCTURAL STEEL 906.01 Section 906. STRUCTURAL STEEL 906.01. General Requirements. Finished rolled shapes must be free from imperfections that affect strength and durability in accordance with ASTM A 6. Rolled shapes

More information

SEISMIC PERFORMANCE AND RETROFIT OF BRIDGE FOOTINGS. David I. McLean 1

SEISMIC PERFORMANCE AND RETROFIT OF BRIDGE FOOTINGS. David I. McLean 1 Abstract SEISMIC PERFORMANCE AND RETROFIT OF BRIDGE FOOTINGS David I. McLean 1 This study investigated retrofitting measures for improving the seismic performance of the foundations of existing bridges.

More information

xiii Preface to the Fifth Edition Preface to the Second Edition Factors for Conversion to SI Units of

xiii Preface to the Fifth Edition Preface to the Second Edition Factors for Conversion to SI Units of Structural Steel Designer's Handbook Table Of Contents: Contributors xiii Preface to the Fifth Edition xv Preface to the Second Edition xvii Factors for Conversion to SI Units of xix Measurement Chapter

More information

APPENDIX B. LOAD FRAME. This Appendix will describe the philosophy in the design and operation of the loading system.

APPENDIX B. LOAD FRAME. This Appendix will describe the philosophy in the design and operation of the loading system. APPENDIX B. LOAD FRAME This Appendix will describe the philosophy in the design and operation of the loading system. LOAD FRAME The large-scale gusset plate testing required a unique loading fixture. A

More information

PERFORMANCE-BASED SEISMIC DESIGN OF BRACED-FRAME GUSSET PLATE CONNECTIONS

PERFORMANCE-BASED SEISMIC DESIGN OF BRACED-FRAME GUSSET PLATE CONNECTIONS PERFORMANCE-BASED SEISMIC DESIGN OF BRACED-FRAME GUSSET PLATE CONNECTIONS C.W. Roeder, U. of Washington, Seattle, WA, USA D.E. Lehman, U. of Washington, Seattle, WA, USA J. H. Yoo, U. of Washington, Seattle,

More information

Supplemental Structural Correction Sheet Steel Brace Frame Design (2017 LABC)

Supplemental Structural Correction Sheet Steel Brace Frame Design (2017 LABC) Supplemental Structural Correction Sheet Steel Brace Frame Design (2017 LABC) Plan Check Submittal Date: Plan Check / PCIS App #: Job Address: Applicant: P.C. Engineer: (print first / last name) E-mail:

More information

GUIDE SPECIFICATIONS FOR SEISMIC DESIGN OF STEEL BRIDGES

GUIDE SPECIFICATIONS FOR SEISMIC DESIGN OF STEEL BRIDGES GUIDE FOR SEISMIC DESIGN OF STEEL BRIDGES First Edition State of California Department of Transportation December 2001 TABLE OF CONTENTS PREFACE i DEFINITIONS iv NOTATION vii 1. INTRODUCTION 1 1.1. Scope

More information

Non Linear Analysis of Composite Beam Slab Junction with Shear Connectors using Ansys.16

Non Linear Analysis of Composite Beam Slab Junction with Shear Connectors using Ansys.16 International Journal of Engineering Science Invention ISSN (Online): 2319 6734, ISSN (Print): 2319 6726 Volume 5 Issue 4 April 2016 PP.22-29 Non Linear Analysis of Composite Beam Slab Junction with Shear

More information

Bridge reinforced concrete column limit state definition

Bridge reinforced concrete column limit state definition Bridge reinforced concrete column limit state definition Danusa H. Tavares Authors: D. H. Tavares, L. I. Cardona and P. Paultre Earthquake Engineering and Structural Dynamics Research Center Centre de

More information

CTBUH Technical Paper

CTBUH Technical Paper CTBUH Technical Paper http://technicalpapers.ctbuh.org Subject: Paper Title: Structural Engineering Seismic Performance of Coupling Beam Damper System Author(s): Ahn, Taesang 1 Kim, YoungJu 1 Kim, SangDae

More information

Experimental study on seismic behavior of composite concrete and

Experimental study on seismic behavior of composite concrete and 6 th International Conference on Advances in Experimental Structural Engineering 11 th International Workshop on Advanced Smart Materials and Smart Structures Technology August 1-2, 215, University of

More information

Chapter 2: Strain. Chapter 3: Torsion. Chapter 4: Shear and Moment Diagram

Chapter 2: Strain. Chapter 3: Torsion. Chapter 4: Shear and Moment Diagram Chapter 2: Strain Chapter 3: Torsion Chapter 4: Shear and Moment Diagram Strain - Is defined as change in length per unit length, simply put it is unit deformation L Stress and Strain Exist concurrently

More information

STRENGTH AND DUCTILITY OF STEEL BEAMS WITH FLANGE HOLES

STRENGTH AND DUCTILITY OF STEEL BEAMS WITH FLANGE HOLES SDSS Rio 2010 STABILITY AND DUCTILITY OF STEEL STRUCTURES E. Batista, P. Vellasco, L. de Lima (Eds.) Rio de Janeiro, Brazil, September 8-10, 2010 STRENGTH AND DUCTILITY OF STEEL BEAMS WITH FLANGE HOLES

More information

The Development of Strain Penetration in Lightly Reinforced Concrete Shear Walls

The Development of Strain Penetration in Lightly Reinforced Concrete Shear Walls The Development of Strain Penetration in Lightly Reinforced Concrete Shear Walls Ali Altheeb 1, Abdulrahman Albidah 2, Nelson T. K. Lam 3 and John Wilson 4 1. Corresponding Author, PhD Candidate, Department

More information

Span Length Effect on Seismic Demand on Column Splices in Steel Moment Resisting Frames

Span Length Effect on Seismic Demand on Column Splices in Steel Moment Resisting Frames Span Length Effect on Seismic Demand on Column Splices in Steel Moment Resisting Frames B. Akbas Gebze Institute of Technology, Turkey Blank Line 9 pt O. Seker Yildiz Technical University, Turkey Blank

More information

Behavior of Concrete-Filled FRP Tubes Under Bending, Axial Loads, and Combined Loading. Amir Fam, Bart Flisak and Sami Rizkalla

Behavior of Concrete-Filled FRP Tubes Under Bending, Axial Loads, and Combined Loading. Amir Fam, Bart Flisak and Sami Rizkalla Behavior of Concrete-Filled FRP Tubes Under Bending, Axial Loads, and Combined Loading Amir Fam, Bart Flisak and Sami Rizkalla ABSTRACT Innovative hybrid systems such as the concrete-filled fiber reinforced

More information

REVIEW ON SHEAR SLIP OF SHEAR KEYS IN BRIDGES

REVIEW ON SHEAR SLIP OF SHEAR KEYS IN BRIDGES REVIEW ON SHEAR SLIP OF SHEAR KEYS IN BRIDGES Benjamin Raison R; Freeda Christy C PG student, School of Civil Engineering, Karunya University. Associate Professor, School of Civil Engineering, Karunya

More information

Substructure systems, specifically retaining walls

Substructure systems, specifically retaining walls Design principles of totally prefabricated counterfort retaining wall system compared with existing cast-in-place concrete structures Maen Farhat and Mohsen Issa An alternative to cast-in-place concrete

More information

CHAPTER 11: PRESTRESSED CONCRETE

CHAPTER 11: PRESTRESSED CONCRETE CHAPTER 11: PRESTRESSED CONCRETE 11.1 GENERAL (1) This chapter gives general guidelines required for the design of prestressed concrete structures or members with CFRM tendons or CFRM tendons in conjunction

More information

EVALUATION REPORT. PFC-5551 Reissued April 1, Filing Category: DESIGN Steel (038)

EVALUATION REPORT. PFC-5551 Reissued April 1, Filing Category: DESIGN Steel (038) ICBO Evaluation Service, Inc. 5360 WORKMAN MILL ROAD WHITTIER, CALIFORNIA 90601-2299 A subsidiary corporation of the International Conference of Building Officials EVALUATION REPORT Copyright 2001 ICBO

More information

1. Cast-in-place concrete is specified in Section

1. Cast-in-place concrete is specified in Section SECTION 03 38 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for furnishing and installing post-tensioned slabs, jacks, jacking and anchors at Parking Structure, and record

More information