1 Alexander Graham Bell House Case Study produced by the A+DS Sust. Programme.
2 A new office building for BT which promotes flexibility in its structuring and configuration in response to the changing demographics of work and changing communications technology. Detail of front elevation at night BACKGROUND BT was in a process of transformation from public sector utility to an organisation that had to operate in an intensely competitive environment characterised by relentless technical innovation. In such a commercial climate, the adaptability of the company to make links across what was before a rather hermetic departmental structure creates a demand for a more responsive management structure, a more flexible workforce and more adaptive workplaces. Sustainable agendas have traditionally not embraced business communities but given pressure from both government and public opinion, companies have attempted to construct frameworks relevant to commercial imperatives. Concepts such as the triple bottom line have been common parlance when discussing sustainability in a business context. This refers to a new imperative for companies to communicate their worth in financial, social and environmental spheres. These concepts often manifest themselves in companies who respond quickly to change, embrace technological innovation, encourage lifelong learning, value intellectual capital and promote virtual working. BT realised these issues were important before they were necessarily incorporated into a wider sustainable agenda. However, more important was the clear understanding by the organisation that such a change of culture could only be achieved through clear, considered and innovative architectural design of the workplace. Front elevation of building BT s existing property portfolio in eastern Scotland was dispersed, fragmented and did not reflect the changing priorities of the company - with a high incidence of cellular offices perpetuating a rigid organisational hierarchy. Alexander Graham Bell House was commissioned by British Telecom as part of a strategy to transform their working environments and rationalise existing building stock in Edinburgh as well as create a new building that would form the focus of BT s presence in eastern Scotland. The building is located in Edinburgh Park, close to the capital s major transport arteries; it forms part of a carefully implemented sequence of buildings situated within a framework of a masterplan created by the architect Richard Meier.
3 APPROACH As part of the process of transforming itself BT produced Workstyle This document outlined key criteria for the procurement of new buildings. It included a commitment to flexible, open, non-hierarchical working patterns to suit both the changing requirements of the organisation and the employee. In addition to this, the document stipulated the maximum depth of workspaces so as to allow for daylighting wherever possible and encouraged the use of energy conservation measures and, where appropriate, the capacity to implement a natural ventilation strategy. What this briefing document demonstrates clearly is that an environmentally responsive building has characteristics that are seen as desirable by a client organisation in the creation of a building brief. Terminology of the new workplace Open Zone Team Zone Break Out Area Touch Down Area Description An area for informal business interaction, study, social use or refreshment. Usually includes catering facilities. A breakdown of the workplace into project based teams rather than static departmental structures. Characterised by the facility for easy verbal and visual communication between team members. A separate space to the team zone allowing a complimentary environment for group meetings and workshops. Must have close proximity to team zones. The key activity area for nomadic workers to allow swift transmission and updating of information. Should allow for ad-hoc meetings, IT access and some refreshment facility to meet varying requirements. As an organisation, BT realised that its business transformation could be facilitated through a radical reappraisal of its building stock. The innovative nature of sustainable building techniques reinforces such positive change. The design of less generic workplaces that accommodate a variety of working interactions engenders a more responsive organisation. Simultaneously, this enables staff to work more flexibly both in terms of time and location. Such strategies have beneficial outcomes in terms of a wider agenda that addresses the triple bottom line of sustainable accountability in social, business and environmental spheres.
4 Environmentally responsive buildings are less energy intensive in use and thus are characterised by lower recurring maintenance costs. In the case of Alexander Graham Bell House, a predicted reduction of between one half and one third in energy consumption was envisaged in relation to comparable developments. Through careful design, the integration of building structure, skin and orientation can contain the capital cost, capacity and complexity of the services installation. Bennetts Associates were invited to participate in a limited design competition. The architects had developed considerable expertise in the design of environmentally responsive buildings that dealt with the workplace in a sophisticated manner. PROCESS The organisational structure of the building had to have the flexibility to allow for work patterns as in the table below: Key work characteristics Work Activity Building requirement Homeworkers Based at residential address with broadband/telecoms link Meeting, conferencing facilities, open zones Nomads Ground based Highly mobile, often client based Office is main workplace Meeting, conferencing and touch down facilities Meeting, conferencing, hot desking, team zones Bennetts Associates had had wide experience of intelligent office design. Since its formation, the practice sought to use building projects as vehicles to develop expertise in the design of environmentally responsive environments. The firm had already completed the John Menzies building at Edinburgh Park, which was also designed to facilitate change in the organisation. Bennetts had also designed the Powergen Headquarters in Nottingham. Internal street design allows building to be quickly read This building is characterised by the use of exposed concrete soffits to the ceiling providing a degree of thermal mass to the building structure. The function of the concrete is to dampen temperature swings in the building caused by factors such as excessive solar gain through windows and incidental gains from computers, machinery and people. It is a good example of how intelligent sustainable design is about making the building envelope and structure proactive in the mediation of the internal climate rather than having exclusive reliance on mechanical services, for example, air conditioning.
5 Timber pergola House type plan
6 RESULT The building has three stories and accommodates up to 1050 workstations. The final design of the building related to the needs of the staff to work effectively and to journey through the space. A key aspect of the design was the inclusion of an internal street that allows the building to be read almost instantly, making it easier to find your way around. The café becomes a social hub of the development as well as a place for informal business transactions. Meeting rooms are located in upper floors above the street and are fully glazed to allow for a transparency of activity. The client subsequently identified a need for an additional touch down space, a flexible area where informal business interactions could take place. The building is organised simply around the principles of providing flexible accommodation and easily adaptable spaces. A key requirement of the client was to nurture a variety of meeting points that encouraged contact and collaboration between employees. The corner of the building is marked with a rotunda containing the cafe and meeting rooms and which clearly marks the building in relation to the main access to Edinburgh Park. The internal street serves a set of work areas that are divided through a set of top lit atria. Three are integrated into the office environment whilst the remaining two feature an internal garden and the main reception and entrance sequence. A major priority both of architect and client was the maximisation of daylighting to the building, not only because of the reduction in energy costs but also because of subjective qualities such as providing a link between the occupant and the external environment. This was achieved through the top lit atria and large areas of glazing, in particular to the main access street. A parallel requirement in the control of light levels led to a series of sensor controlled motorised blinds to the east. This is necessary where the need for a view out through the street from the work areas precludes the use of fixed louvres. Elsewhere the building facade is articulated through the expressive use of external shading devices to reduce glare and excessive passive solar gain. An early decision was taken to mechanically ventilate the building. Although this may seem at odds with accepted sustainability criteria, the aggressive external environment, with a lot of noise from traffic and nearby industrial activity, precluded any other approach. In addition to this, the need to allow for flexible working environments meant factors such as incidental gain could not be predicted to a degree where the client could accept a naturally vented solution. The building is serviced through displacement ventilation. Fresh air is introduced into the work place at floor level slightly below room ambient temperature. As it warms it takes up internal pollutants and breathed CO2, then by thermal displacement the stale air rises and is extracted at ceiling level. Office buildings can suffer from extreme internal temperature swings especially in summer where there is a constant level of heat gains from users and equipment combined with higher external temperatures and an increased incidence of solar gain through glazing. Unlike most developments
7 Flexible internal work spaces Alexander Graham Bell House illuminated
8 featuring expanses of lightweight, suspended ceiling panels, the building favours a rhythm of beautifully cast floor slabs exposed at the ceiling. There is a continuous coffer in the casting to carry lighting and extract venting but otherwise the exposed concrete absorbs heat during the day and then emits it at night when the building is unoccupied. The concrete acts as a piece of thermal inertia damping what would otherwise be extremes in temperature. Simulation of the building s predicted behaviour was vitally important to the design development. For instance, it demonstrated that in Scotland, as opposed to South East England, the provision of night purging of the floorslabs would not be required to cool the building. The atria play an important role in the building design, breaking down the floorplate into a series of more flexible spaces with the added advantage of daylighting brought deep into the building. They have a variety of uses, with some being used as breakout and meeting areas. The garden atrium has perhaps been less effective: it has no clearly defined function. Unlike the remainder of the building, it is not tightly linked with surrounding workspaces and is not well utilised for formal and informal interactions between building users. KEY LESSONS The sustainability agenda encompasses both social and economic criteria. The provision of workspaces that can adapt to a wide range of patterns allows for greater flexibility for the employee as to where and how they choose to work. This can reduce transportation impacts and allows greater freedom to increase the distance between work and home as well as to work remotely from other locations including home. More flexible working methods give rise to a need for more areas for break out and touch down which have specific characteristics that cannot necessarily be accommodated by generic speculative office spaces. The design of sustainable spaces can deliver good working environments especially in relation to daylighting and appropriate servicing strategies. Designing sustainable buildings needs to be done in an integrated manner: the thermal inertia of the structure, the ventilation strategy, the building orientation and façade design all need to work together to provide a responsive internal environment. Good practice in the design of sustainable buildings should include the constant reassessment of completed work and a willingness to innovate incrementally. Detailed simulation and post occupancy surveys are vitally important in making informed design decisions.
9 Project Information Location: Lochside View, Edinburgh Park, Edinburgh EH12 9DH Client: BT Group plc Date completed: 1999 Project Value: 18.17m Gross Internal floor area: 13,935 sq. m. Architect: Structural Engineer: Quantity Surveyor + Project Management: Services Engineer: Landscape Architect: Specialist Consultant: Main contractor: Bennetts Associates Blyth & Blyth Tozer Capita Roberts and Partners Ian White Associates Aukett Associates (space planners) Balfour Beatty Awards: RIBA Award 2000 British Council for Offices Award 2000 Scottish Design Award Corporate Building 2000 Scottish Design Award Chairman s Award 2000 Architecture and Design Scotland Bakehouse Close, 146 Canongate Edinburgh EH8 8DD Level 2, The Lighthouse, 11 Mitchell Lane, Glasgow, G1 3NU T: +44 (0) F: +44 (0) E: info@ads.org.uk
Loch Lomond Shores Visitor Centres. Case Study produced by the A+DS Sust. Programme.
Loch Lomond Shores Visitor Centres Case Study produced by the A+DS Sust. Programme. Two visitor centres created for the Loch Lomond and Trossachs National Park, developed following sustainable principles
More informationWinner of CIBSE Building Performance Award Project of the Year (Public use) 2017 Keynsham Civic Centre
Winner of CIBSE Building Performance Award Project of the Year (Public use) 2017 Keynsham Civic Centre Keynsham civic centre Sustainability objectives The Keynsham Civic Centre has completely transformed
More informationSOUTH LANARKSHIRE COLLEGE LOW CARBON TEACHING BUILDING TECHNICAL CASE STUDY
SOUTH LANARKSHIRE COLLEGE LOW CARBON TEACHING BUILDING TECHNICAL CASE STUDY PROJECT INTRODUCTION For this project our brief from South Lanarkshire College was a very simple one to design a new eight classroom
More informationFor all those with the ability to influence the design, layout or indoor air quality of buildings
Natural Selection For all those with the ability to influence the design, layout or indoor air quality of buildings By the end of this presentation you will:- Understand what Natural Ventilation is. Know
More informationCapturing the Stakeholder Values of a Construction Project
Capturing the Stakeholder Values of a Construction Project Ken Dooley Sustainability Consultant Olof Granlund Oy Finland ken.dooley @granlund.fi Piia Sormunen Manager, Energy and Environment Olof Granlund
More informationNovartis Pharmaceuticals UK Ltd - Frimley Business Park
Novartis Pharmaceuticals UK Ltd - Frimley Business Park construction industry as a whole and Facilities Managers themselves more aware of the benefits of drawing on facilities management expertise during
More informationTHE DAVID ATTENBOROUGH BUILDING. The New Museums Site, University of Cambridge
THE DAVID ATTENBOROUGH BUILDING The New Museums Site, University of Cambridge The refurbishment of a fine example of 1960s architectural brutalism will demonstrate the highest levels of environmental sustainability
More informationOur Aim. There is a misconception that daylighting is a numerical exercise requiring expensive modelling not so.
There is a misconception that daylighting is a numerical exercise requiring expensive modelling not so. Our Aim Daylight is the source of energy that drives the growth and activity of all living things.
More informationDouble Skin Walls & Dynamic Façades
Double Skin Walls & Dynamic Façades Le Corbusier called them "mur neutralisant," a system of ventilated double glazing that at that time was deemed too expensive and inefficient to be built. Villa Turque
More informationNau mai, Haere Mai, Whakatau mai
TE RAUKURA WHAREWAKA VENUE AND CONFERENCE CENTRE Located amongst the hub of Wellingtons Waterfront, Te Raukura - Wharewaka o Poneke is a brand new, purpose built conference center. A unique mix of tradition
More informationGreen Building Pay: Design. Productivity and Ecology
Green Building Pay: Design. Productivity and Ecology Professor Brian W Edwards PhD, MSc, RIBA, RIAS Emeritus Professor of Architecture, ECA, University of Edinburgh Author of: Green Buildings Pay: Design,
More informationWhat you need to know about 6 Star. 6 Star. for new homes, home renovations, alterations, additions and relocations
What you need to know about 6 Star 6 Star for new homes, home renovations, alterations, additions and relocations Introduction From 1 May 2011, all new homes, home renovations, additions, alterations and
More information23-28 = -5. Zero Net Energy Case Study WEST BERKELEY PUBLIC LIBRARY OVERVIEW. Planning & Design Approach. Measured Energy Stats
Zero Net Energy Case Study Photos Mark Luthringer Photography OVERVIEW Building Size: 9,400 SF Location: Berkeley, CA Construction Type: New Construction Completion Date: December 2013 Building Type: Public
More informationTimber Building in the City of Tomorrow
7 e Forum International Bois Construction FBC 2017 Timber Building in the City of Tomorrow A. Thistleton 1 Timber Building in the City of Tomorrow Anthony Thistleton Waugh Thistleton Architects London,
More informationATRIA IN SHOPPING CENTRES, OFFICE BUILDINGS AND HOSPITALS. E.Ph.J. de Ruiter. Adviesbureau Peutz & Associés BV., The Hague, Holland
ATRIA IN SHOPPING CENTRES, OFFICE BUILDINGS AND HOSPITALS E.Ph.J. de Ruiter Adviesbureau Peutz & Associés BV., The Hague, Holland 1 Introduction A growing number of buildings are being provided with large,
More informationTD CANADA TRUSTCREDIT VALLEY TOWN PLAZA
TD CANADA TRUSTCREDIT VALLEY TOWN PLAZA 6051 CREDITVIEW RD, MISSISSAUGA, ON 2016 CANADIAN CONSULTING ENGINEERING AWARD SUBMISSION Submitted by: Integral Group 1 PROJECT INFORMATION Project Name: TD Canada
More informationCase Study: Bio-Climatic Building Design for Tropical Climates
Case Study: Bio-Climatic Building Design for Tropical Climates The project is located in a Development Zone and the objectives include: opening the city towards the sea, to reinvigorate the city centre,
More informationEvaluating Appropriate Residential Ventilation Strategies in Dense Urban Environments and the Challenges for Passive Design
Evaluating Appropriate Residential Ventilation Strategies in Dense Urban Environments and the Challenges for Passive Design Ashley Bateson CEng CEnv MCIBSE MEI Partner, Hoare Lea Chair, CIBSE Homes for
More informationDaylight, Solar Gains and Overheating Studies in a Glazed Office Building
Issue 2, Volume 2, 2008 129 Daylight, Solar Gains and Overheating Studies in a Glazed Office Building Hasim Altan, Ian Ward, Jitka Mohelníková, František Vajkay Abstract The Glazed envelopes represent
More informationEXTREME. Makeover. Nu Skin Enterprises Utah campus gets a fresh new look.
EXTREME Makeover Nu Skin Enterprises Utah campus gets a fresh new look. BY RON KLEMENCIC, S.E., P.E. THE NU SKIN INNOVATION CENTER brings a new face to Nu Skin Enterprises. The anti-aging product company
More informationWork Package 2: Performance of naturally ventilated buildings
Work Package 2: Performance of naturally ventilated buildings Detailed Monitoring Report BRF-kredit Headquarters (DK2) Niels C. Bergsøe Danish Building Research Institute, SBI Energy and Indoor Climate
More informationIMPORTANT (Please read this before using the checklist).
PRE-ASSESSMENT ESTIMAT IMPTANT (Please read this before using the checklist). This pre-assessment checklist allows a quick evaluation of the rating, that could be achieved, under a formal BREEAM Offices
More informationBioclimatic Design Approach Integration into Architectural Design: a Library Case Study
PLEA 2016 Los Angeles - 36 th International Conference on Passive and Low Energy Architecture. Cities, Buildings, People: Towards Regenerative Environments Bioclimatic Design Approach Integration into
More informationThermal comfort in a 21st century climate
CIBSE Briefing Thermal comfort in a 21st century climate Addressing the impact of climate change on the built environment Summary This briefing summarises the key findings of research* commissioned by
More informationBullitt Center s Energy Performance
Bullitt Center s Energy Performance Introduction In 2007 Congress created a Zero Net Energy Commercial Buildings Initiative with a goal of achieving a market transition to Zero Net Energy for new commercial
More informationEcole Connaught Community School Welcomes. CaGBC Sask Chapter Members & Colleagues
Ecole Connaught Community School Welcomes CaGBC Sask Chapter Members & Colleagues Who we Are as the Comets We are a Dual Track French Immersion School and with an enrollment of 435 students, 43 staff and
More informationStadtwerke Konstanz Customer Centre, Constance
Concepts Products Service Stadtwerke Konstanz Customer Centre, Constance 1 Project Report Stadtwerke Konstanz Customer Centre, Constance In summer 2010, we were commissioned to build a new innovative customer
More informationFM TEAMS. Health, Wellbeing & Productivity in Offices A BITESIZE GUIDE FOR... FACILITIES MANAGERS. Merchant Square, JLL. With thanks to our sponsor
Health, Wellbeing & Productivity in Offices A BITESIZE GUIDE FOR... FACILITIES MANAGERS With thanks to our sponsor FM TEAMS Merchant Square, JLL Introduction Key points for a healthy office This briefing
More informationUBA builds answers Positive energy building in Dessau
EXTENSION IN DESSAU UBA builds answers Positive energy building in Dessau Sustainable construction Environmental qualities are paramount The holistic assessment system for sustainable construction was
More informationBRE Lighthouse. 2. Background and Context:
BRE Lighthouse 1. Project Basics: Location: Watford, UK Latitude/Longitude: 51 40 N, 0 24 W, alt. 110m Annual Precipitation: 23 inches Building type: Residential Square footage 2000; Stories: 2 story Completion:
More informationPARTNER PRO SEKCI ELEKTROMOBILITA ELECTROMOBILITY PARTNER
ORGANIZÁTOR / ORGANISER PARTNEŘI / PARTNERS GENERÁLNÍ PARTNER / GENERAL PARTNER HLAVNÍ PARTNEŘI / MAIN PARTNERS MEDIÁLNÍ PARTNEŘI / MEDIA PARTNERS PARTNER PRO SEKCI ELEKTROMOBILITA ELECTROMOBILITY PARTNER
More informationFACADE OPTIMIZATION. Architect Mike Matson Project Manager, Ratcliff. DE ANZA COLLEGE MEDIAL + LEARNING CENTER Photography David Wakely
There are a handful of passive downdraft buildings in service worldwide, but we believe the execution of the system at De Anza College s Media + Learning Center to be on a scale and level of sophistication
More informationModelling Analysis of Thermal Performance of Internal Shading Devices for a Commercial Atrium Building in Tropical Climates
Modelling Analysis of Thermal Performance of Internal Shading Devices for a Commercial Atrium Building in Tropical Climates Kittitach Pichatwatana, and Fan Wang Abstract This paper examines the TAS computer
More informationBaleHaus by White Design Architects
BaleHaus by White Design Architects BaleHaus - A domestic carbon bank Living more sustainably requires us to develop ways to: live within our environmental means - especially in relation to our carbon
More informationFacade Design for Super High- Rise Building in Subtropic Region in China
Facade Design for Super High- Rise Building in Subtropic Region in China Super high-rise building will always be iconic elements at any location. Accompanied by the growth of building technology and urbanization,
More informationWhat do we learn for our buildings users?
What do we learn for our buildings users? Quentin Jackson 1 Abstract This paper presents a case study of users responses to two commercial office buildings in NZ. The Meridian Building is a four storey
More informationWhen the London Borough of Camden decided
18 social housing special report Andy Matthews Photography Passivhaus is a standard for insulating buildings to such high levels that energy bills fall to a fraction of their normal cost. A development
More informationPost Tower Bonn, Germany
Winner 10 Year Award Post Tower Bonn, Germany The design single-handedly changed the way we look at façade and office design to date. It has become an exemplar sustainable icon in contemporary architecture.
More informationDesigning carbon neutral schools: The Victor Miller Building, a critical review
Designing carbon neutral schools: The Victor Miller Building, a critical review Daniela BESSER 1 Lucelia RODRIGUES 1 Benson LAU 1 1 School of the Built Environment UK ABSTRACT: Nowadays, one of the UK
More informationTHERMAL MASS IMPACT ON ENERGY PERFORMANCE OF A LOW, MEDIUM, AND HEAVY MASS BUILDING IN BELGRADE
S447 THERMAL MASS IMPACT ON ENERGY PERFORMANCE OF A LOW, MEDIUM, AND HEAVY MASS BUILDING IN BELGRADE by Bojan V. ANDJELKOVIĆ *,a, Branislav V. STOJANOVIĆ b, Mladen M. STOJILJKOVIĆ b, Jelena N. JANEVSKI
More informationARPAN JOHARI. Architect. 13/08/10 AW Design. Ahmedabad
ARPAN JOHARI. Architect THERMAL MASS Thermal mass (or thermal capacitance) is defined as the ability of a body to store heat THERMAL MASS Thermal mass is also known as Fabric Energy Storage, FES (The Concrete
More informationTHE MODULAR HOUSE - PLOT 15 - SCOTLAND S HOUSING EXPO
THE MODULAR HOUSE - PLOT 15 - SCOTLAND S HOUSING EXPO by David Keith Bracewell Stirling Consulting A state-of-the-art, carbon neutral living space as natural as the environment, which considers carbon
More informationTHERMAL MASS IMPACT ON ENERGY PERFORMANCE OF A LOW, MEDIUM AND HEAVY MASS BUILDING IN BELGRADE
Andjelković, V., B.et. al.: Thermal Mass Impact on Energy Performance of A Low, Medium and Heavy S507 THERMAL MASS IMPACT ON ENERGY PERFORMANCE OF A LOW, MEDIUM AND HEAVY MASS BUILDING IN BELGRADE by Bojan
More informationProject Description. Projected build start date 01 Mar 2010 Projected date of occupation 31 May Aberdare, Rhondda Cynon Taff, Wales
http://lowenergybuildings.org.uk Project name Self Heating Social Housing- the zero carbon retrofit Project summary The target for this project is to create the first UK PassivHaus retrofit using low/zero
More informationGeneral guidelines for using thermal mass in concrete buildings
General guidelines for using thermal mass in concrete buildings 1 THERMAL MASS - BEST PRACTICE GUIDELINES FOR HOUSING In warm climates, the thermal mass in concrete and masonry helps provide a comfortable
More informationMartin Ratcliffe Visiting Research Fellow, Centre for Energy Studies at LSBU Head of Roger Preston Environmental
REAPING THE BENEFITS AVOIDING THE PITFALLS Martin Ratcliffe Visiting Research Fellow, Centre for Energy Studies at LSBU Head of Roger Preston CIBSE/ASHRAE Meeting LSBU May 12th 2004 1 Show that glazing
More informationINTEGRAL BUILDING AND ENERGY DESIGN OF AN OFFICE BUILDING COMPARISON OF INITIAL DESIGN IDEAS WITH MONITORED RESULTS
INTEGRAL BUILDING AND ENERGY DESIGN OF AN OFFICE BUILDING COMPARISON OF INITIAL DESIGN IDEAS WITH MONITORED RESULTS Andreas Wagner, Mathias Wambsganß, Thomas Gropp, Harry Schindler University of Karlsruhe
More informationUsing street surveys to establish Air Conditioning incidence in UK s commercial offices stock
Using street surveys to establish Air Conditioning incidence in UK s commercial offices stock Jorge Caeiro, Bartlett School of Graduate Studies, University College London, 1-16 Torrington Place Site, Gower
More informationTHE USE OF LIGHT PIPES FOR DEEP PLAN OFFICE BUILDINGS A case study of Ken Yeang's bioclimatic skyscraper proposal for KLCC, Malaysia
THE USE OF LIGHT PIPES FOR DEEP PLAN OFFICE BUILDINGS A case study of Ken Yeang's bioclimatic skyscraper proposal for KLCC, Malaysia Veronica Garcia Hansen*, Ian Edmonds**, Richard Hyde*** *School of Design
More informationLOW ENERGY CERTIFICATE - PROPOSAL FOR A BUILDING ENERGY EFFICIENCY CERTIFICATE
LOW ENERGY CERTIFICATE - PROPOSAL FOR A BUILDING ENERGY EFFICIENCY CERTIFICATE Hans-Peter Leimer, Prof. Dr.-Ing., BBS INSTITUT Germany University of Applied Sciences and Arts - HAWK Hildesheim - Germany
More informationTECHNICAL SPECIFICATION
TECHNICAL SPECIFICATION STRUCTURAL FRAME Imperial House is an 8 storey office building with a single basement built in 1913. The building is a steel-framed structure with concrete floors spanning between
More informationPassivhaus Project Documentation Wrexham Passivhaus
Passivhaus Project Documentation Wrexham Passivhaus Design/Architecture: Simmonds Mills Architects Structural ngineer: Bob Johnson Structural ngineers, Shrewsbury Building Services: Alan Clarke Passivhaus
More informationWhat can we do with the office?
What can we do with the office? Contents 1.0 Introduction Page 4.0 Case Study Summaries Page 6.0 What if? Page 1.1 Aims, task and scope 1.2 Outcomes 2.0 Context 2.1 Why are we changing? 2.2 How are we
More informationKey Success Factors for Internal Coaching
Issue No. 1 Key Success Factors for Internal Coaching lifetimeswork The Green House 41 St. Bernards Crescent Edinburgh EH4 1NR jenny.campbell@lifetimeswork.com Copyright 2007 Jenny Campbell All Rights
More informationPOST OCCUPANCY DESIGN INERVENTION TO IMPROVE COMFORT AND ENERGY PERFORMANCE IN A DESERT HOUSE
POST OCCUPANCY DESIGN INERVENTION TO IMPROVE COMFORT AND ENERGY PERFORMANCE IN A DESERT HOUSE Vidar Lerum Arizona State University P O Box 871605, Tempe, AZ, 85287-1605, USA vidar.lerum@asu.edu Venkata
More informationSUMMER THERMAL COMFORT IN TYPICAL FRENCH RESIDENTIAL BUILDINGS: IMPACT ASSESSMENT OF BUILDING ENVELOPE INSULATION ENHANCEMENT
13th Conference of International Building Simulation Association, Chambéry, France, August 26-28 SUMMER THERMAL COMFORT IN TYPICAL FRENCH RESIDENTIAL BUILDINGS: IMPACT ASSESSMENT OF BUILDING ENVELOPE INSULATION
More informationConstructing Excellence: The SME s quick guide to Sustainability
Constructing Excellence: The SME s quick guide to Sustainability Why was this guide created? Sustainability is not just about protecting the environment and improving ones reputation, but is increasingly
More informationAttached Solar Greenhouse Plans for a solar heated greenhouse attached to your home
Attached Solar Greenhouse Plans for a solar heated greenhouse attached to your home Designed and built by New Mexico landscape architect John Mosely for his own Santa Fe home. The solar greenhouse shown
More informationPassive House Project documentation
Passive House Project documentation Architecture: CadViz: Building physics: ehaus, Cyril Vibert Building Services: ehaus, Cyril Vibert Craftsperson: ehaus A compact two level family home with 4 bedrooms
More informationLooking for a new investment angle? A developer s guide to environmentally smart buildings
Looking for a new investment angle? A developer s guide to environmentally smart buildings Benefits Investing in environmentally smart buildings means investing in the future. Smart buildings are highly
More informationUK-GBC ON SITE LEARNING CASE STUDY EBURY STREET
UK-GBC ON SITE LEARNING CASE STUDY - 119 EBURY STREET INTRODUCTION In September 2016, the UK Green Building Council (UK-GBC) with Grosvenor and David Morley Architects, invited a group of members to 119
More informationIconography. KAPSARC Mosque
Iconography As node and center of the KAPSARC residential community, the mosque creates an iconic and contemplative space of worship, reflection and repose. A unique and contemporary space, the design
More informationDesign and Access Statement
Design and Access Statement Environmentally responsible housing Queens Road, Stourbridge Black Country Housing Association Kier Partnership Homes Axis Design Collective January 2007 The following design
More informationARCHITECTURAL ENGINEERING STUDIO
ARCHITECTURAL ENGINEERING STUDIO Energy strategy of my proposal can be arranged in a 4-step pyramid that also follows the procedure of design process. Layout and Flow 4 Steps Strategy Cleanest Cheapest
More informationAchieving Zero Carbon for Buildings in a Densely Populated City and a Subtropical Climate. Guiyi LI Construction Industry Council
Achieving Zero Carbon for Buildings in a Densely Populated City and a Subtropical Climate Guiyi LI Construction Industry Council Construction Industry Council Set up under the Construction Industry Council
More informationColumbia Skylights may qualify your project for LEED points in the following categories: Columbia Skylights - Potential Contribution to LEED projects
3.0 Statement Columbia Skylights Statement for New Construction (NC) Version 3.0 Credit Documentation The Leadership in Energy and Environmental Design () Green Building Rating System promotes the adoption
More informationTHERMAL MASS CHAPTER 6. Understanding thermal mass. Seasonal effects of thermal mass
CHAPTER 6 THERMAL MASS mud brick concrete block brick The contents of this chapter explain the effect of thermal mass and provide guidelines for its location and extent. Summer and winter effects of thermal
More informationAssessment of the energy demand in energy-saving office buildings from the viewpoint of variations of internal heat gains
Assessment of the energy demand in energy-saving office buildings from the viewpoint of variations of internal heat gains Andrzej Baranowski 1,2 and Joanna Ferdyn-Grygierek 1,2 1 Silesian University of
More informationStudent Modeling Competition
Student Modeling Competition Design and Simulation of a Laboratory Building Building Simulation 2017 Briefing Document Zahraa Saiyed Ben Brannon Anna Brannon Christina Hopfe Gerhard Zweifel Student Modeling
More informationCAMBRIDGE PUBLIC LIBRARY
PROJECT Cambridge, MA SIZE Total: 103,900 sqft Addition: 76,700 sqft Renovation: 27,200 sqft CLIENT City of Cambridge ARCHITECT WILLIAM RAWN ASSOCIATES ASSOCIATE ARCHITECT ANN BEHA ARCHITECTS LANDSCAPE
More informationBUILDING DESIGN AND THERMAL INERTIA: WHEN, WHY, WHERE
Int. Journal for Housing Science, Vol.34, No.4 pp. 221-231, 2010 Published in the United States BUILDING DESIGN AND THERMAL INERTIA: WHEN, WHY, WHERE R. Albatici, S. Penasa Department of Civil and Environmental
More informationUCI Natural Sciences Unit 2 Irvine, CA
PROPOSAL UCI Natural Sciences Unit 2 Irvine, CA Updated Thesis Proposal Apr 04, 2008 Grant W. Kightlinger Lighting / Electrical Option Advisors Dr. Kevin Houser Prof. Ted Dannerth Grant W. Kightlinger
More informationAN INTEGRATED APPROACH TO ENERGY ANALYSIS IN BUILDING DESIGN THE RELOCATABLE CLASSROOM PROJECT. James Pow Chew Wong 1, Usha Iyer-Raniga 1,2.
AN INTEGRATED APPROACH TO ENERGY ANALYSIS IN BUILDING DESIGN THE RELOCATABLE CLASSROOM PROJECT James Pow Chew Wong 1, Usha Iyer-Raniga 1,2 1 Centre for Design, RMIT University, Melbourne, Victoria, Australia
More information71 kwh/(m²a) Project Documentation. 1 Abstract. Single family house in Bellbrae, Victoria, Australia. 1.1 Data of building. Year of construction
Project Documentation 1 Abstract Single family house in Bellbrae, Victoria, Australia 1.1 Data of building Year of construction U-value external wall 2015 Space heating 0.220 W/(m²K) 16 kwh/(m²a) U-value
More informationStage 6 & 7 Design Guidelines
Stage 6 & 7 Design Guidelines DESIRED CHARACTER/VISION The new release at Emerald Park Private Estate presents the opportunity to create a high quality and contemporary living environment. These Design
More informationApplication and management of environmental technologies in UK schools: A case study
SET211, 1 th International Conference on Sustainable Energy Technologies, İstanbul, TÜRKİYE, 4-7 Sep. 211 Application and management of environmental technologies in UK schools: A case study Masoud Malekzadeh
More informationStage 10 Design & Building Guidelines
Stage 10 Design & Building Guidelines DESIRED CHARACTER/VISION The development of The Rivergums presents the opportunity to create a high quality and more sustainable living environment by providing an
More informationIntroduction to basics of energy efficient building design
Introduction to basics of energy efficient building design Pierre Jaboyedoff Seminar on Energy Efficient & Thermally Comfortable Buildings in Amravati For CRDA, Andhra Pradesh May 2 nd 2017 Indo-Swiss
More informationGreat Ocean Rd Ice Creamery
Great Ocean Rd Ice Creamery BCA Section J - JV3 Compliance Report Revision: 01 Job No: 2171 Date: 7 July 2015 ADP Consulting Pty Ltd Level 10, 10 Queens Rd, Melbourne Vic 3004 www.adpconsulting.com.au
More informationThe Centre for Sustainable Building (ZUB) * A Case Study
The Centre for Sustainable Building (ZUB) * A Case Study Dietrich Schmidt Tekn. Lic. 1,2 1 KTH-The Royal Institute of Technology. Division of Building Technology. Brinellvägen 34. SE-100 44 Stockholm.
More informationEnhancing visual comfort in classrooms through daylight utilization
Enhancing visual comfort in classrooms through daylight utilization Kleo Axarli and Katerina Tsikaloudaki Laboratory of Building Construction & Physics, Aristotle University of Thessaloniki, Greece Corresponding
More informationMODELLING THE IMPACTS OF NEW UK FUTURE WEATHER DATA ON A SCHOOL BUILDING
MODELLING THE IMPACTS OF NEW UK FUTURE WEATHER DATA ON A SCHOOL BUILDING Hu Du, Jerry Edge, Chris Underwood School of Built and Natural Environment, Northumbria University, Newcastle upon Tyne, United
More informationResearch Analysis: Building Envelope and LEED Credits Introduction
: Building Envelope and LEED Credits Introduction Green buildings are no longer a new idea and are quickly becoming the trend in the slowly changing industry of building construction. Even though the essence
More informationSTA MEMBER CLIENT ARCHITECT MAIN CONTRACTOR PARTNER TECHNOLOGY
Hanham Hall Award Winning Eco Village This groundbreaking project is the first site in the government s Carbon Challenge initiative and is designed to test the Code for Sustainable Homes to its highest
More informationA new blast-mitigation solution for building facade protection with a laminated polycarbonate based system
Safety and Security Engineering V 353 A new blast-mitigation solution for building facade protection with a laminated polycarbonate based system V. Benz 1, J. Lorenzo 2, R. Pyles 2, R. Rumer 2 & K. Wiecking
More information2Beginning with BIM. Axiom Architects
2Beginning with BIM Axiom Architects jonathan reeves city perspectives 24 Chapter 2 the practice Since Axiom Architects was founded in 1986, the practice has grown from its origins in Lewes, East Sussex,
More informationTeaser Project Munich
Alistair Higgins, CEO 11 years in senior positions at Saint-Gobain Chartered Accountant, London Graduate Cambridge University Eik Bezzel, CTO & Founder First CEO of PhotoSolar 12 years with the Danish
More informationThe Officeless Office that Works
The spacious atrium is the center of the facility, providing a gathering place for staff with access to amenities including a company store, health center and cafe. The Officeless Office that Works B Y
More informationVANTAGE ENERGY HIGH PERFORMANCE WINDOWS AND DOORS FOR EFFICIENCY & COMFORT
VANTAGE ENERGY HIGH PERFORMANCE WINDOWS AND DOORS FOR EFFICIENCY & COMFORT maximise efficiency & comfort WITH HIGH PERFORMANCE WINDOWS AND DOORS Australia s largest range of high performance and thermally
More informationBox Clever Consulting. Executive Summary Project Report. July Strand Plaza. Liverpool. for. Primesite Developments
Box Clever Consulting Executive Summary Project Report July 2017 Strand Plaza Liverpool for Primesite Developments Author - Graham Flynn Issued - 05/08/17 Strand Plaza - Liverpool Status Report @ End of
More informationHEAT LOSS REDUCTION OF ENERGY-EFFICIENT HOME BY BUFFER AREAS. Alexander Dvoretsky, KseniaKlevets
MOTROL. COMMISSION OF MOTORIZATION AND ENERGETICS IN AGRICULTURE 2014, Vol. 16, No. 5, 125 130 HEAT LOSS REDUCTION OF ENERGY-EFFICIENT HOME BY BUFFER AREAS Alexander Dvoretsky, KseniaKlevets Prof. Dr.,
More informationSAMPLE ZNE PRESENTATION
SAMPLE ZNE PRESENTATION Presentation Subtitle ACHIEVEMENT What is a zero-net energy (ZNE) building? A ZNE building is highly energy efficient and produces as much energy onsite through clean, renewable
More informationReflect. Densify. Reduce. Increase. Vertimeme. VERTIMEME
Reflect. The future of the city is dense and vertical. Imagine the vertical city, where the park traverses the building towards the sky from the street, where the next generation of iconographic architecture
More informationOKO House by YOUMEHESHE architects
OKO House by YOUMEHESHE architects The OKO House The OKO House is a modular pre-fabricated design aimed initially at the European and North American housing market and to be developed for other global
More informationSustainable Building Training Guide Learning outcomes for standards, qualifications and training
Sustainable Building Training Guide Learning outcomes for standards, qualifications and training 1 This guide has been produced by the Green Construction Board with the support of CITB. We would like to
More informationModeling Energy Consumption Effects of Glazing
Modeling Energy Consumption Effects of Glazing Daniel Lu 12/7/2012 Table of Contents Introduction... 3 Design Options... 5 Option 1... 5 Option 2... 5 Preliminary Energy Simulation... 7 Objectives... 7
More informationEnabling a digital world. Quality Assurance Services. ISO 9001 Certified Assurance
Enabling a digital world Quality Services ISO 9001 Certified Exception Quality Services Introduction Against the backdrop of digital innovation, expanding regulation and dynamic markets, organisations
More informationDaylight and shading
BRE Expert Collection 6 Daylight and shading A collection of BRE expert guidance on designing for daylight and sunlight, and shading of buildings To view the full range of IHS BRE Press publications visit
More informationAluminium & PVC Windows Doors Curtain Walling
Aluminium & PVC Windows Doors Curtain Walling Aluminium & PVC Windows, Doors & Curtain Walling T urkington Windows has been successfully completing commercial window and door contracts for over 35 years
More informationAIRCOOL VENTILATORS FURTHER INFORMATION
.................................................. CI/SfB (57.7) Xy Uniclass L7563 January 2015 FURTHER INFORMATION................................................................... Services Passivent
More information