Decommissioning of Dairyland Power s Lacrosse Boiling Water Reactor
|
|
- Alexis Natalie Gardner
- 5 years ago
- Views:
Transcription
1 Decommissioning of Dairyland Power s Lacrosse Boiling Water Reactor
2 Dairyland Power Cooperative The plant achieved initial criticality in July, Full power was reached in August, 1969 and was declared for commercial use in February of The plant was permanently shut down in April of 1987 and placed in SAFSTOR for decommissioning at a later date. Due to the pending closure of the disposal site for the reactor vessel, decommissioning was started in 2005.
3 The Decommissioning Challenge An experienced decommissioning team was selected to provide design engineering and on-site decommissioning services to remove the reactor vessel and ship to the disposal site. Bluegrass Concrete Cutting, Inc was responsible for providing access for the vessel removal. Four major activities were required to provide the required access including: 1.Cutting an opening in the reactor containment building. 2.Segmentation and removal of the reactor shield plugs. 3.Cutting for removal a section of the biological shield wall surrounding the vessel. 4.Cutting free from the vessel the reactor nozzles, control rod drive tubes and all other vessel attachments. Of significant concern for the project was the spent reactor fuel that was still contained in the spent fuel pool located approximately 2 meters from where some of the work would take place.
4 Cut An Opening in the Reactor Containment Building The initial activity was to cut an opening in the containment building of sufficient size for the reactor vessel to pass through. The containment wall consisted of 9 (230 mm) of concrete, a small air gap and a 1 (25 mm) steel plate. The opening to be cut was 60 feet (18 meters) high and 16 feet (4,870 mm) wide.
5 Cutting An Opening in the Reactor Containment Building Diamond core drilling for diamond wire access. Diamond wire saw set up for cutting of containment opening. The use of diamond tools was critical to maintaining required tolerances and to smoothly cut through the steel plate liner and refractory bars.
6 Cutting An Opening in the Reactor Containment Building The access opening for removal of the reactor vessel was cut through the reactor containment building wall in eight separate sections.
7 Removal of Reactor Containment Building Wall Access Opening would eventually be 60 feet high by 16 feet wide.
8 Cutting and Removal of Reactor Shield Plugs The reactor shield plug consisted of three separate plugs approximately 1 3 (380 mm) thick and 15 (4,570 mm) in diameter made from high density concrete and lined with steel plate. Each of the three plugs was cut into six sections each with a diamond wire saw for sufficient size reduction to fit through the very small containment hatch opening.
9 Segmentation and Removal of Reactor Plugs The reactor shield plug consisted of three separate plugs made from high density concrete and lined with steel plate. The plugs were housed for cutting and sectioned into six sections each.
10 Removal of a Portion of the Bio Shield Wall Access to the reactor vessel meant removing a significant portion of the bio shield wall.
11 Removal of a Portion of Bio Shield Wall Access to the Bio Shield required removal of sections of the operating floor and support beams.
12 Removal of a Portion of Bio Shield Wall The biological shield wall had significant challenges due to very tight tolerances. Precise wire access and rigging holes had to be diamond core drilled at compound angles through up to 10 feet (3,650 mm) of concrete and steel plate in order to penetrate the circular edge of the shield wall without touching the vessel. With precision layout and specially designed angle brackets all holes were drilled in the proper orientation. Cutting then proceeded from the top down, cutting the shield wall into 20 ton sections. In all, 23 separate sections of biological shield wall were cut and removed to provide access for the vessel removal.
13 Removal of a Portion of Bio Shield Wall Drawing of the (23) sections of bio shield wall to be removed.
14 Removal of a Portion of Bio Shield Wall Access through Bio shield wall would require 23 individual sections to be cut and removed.
15 Removal of a Portion of Bio Shield Wall View of concrete core, with liner plate attached, illustrating the compound angles required to penetrate the circular shield wall, while not touching the reactor vessel.
16 Removal of a Portion of Bio Shield Wall Typical diamond wire saw setups required to reach cuts with limited access.
17 Removal of a Portion of Bio Shield Wall Diamond wire saw set-ups for sectioning bio shield wall into pieces small enough to fit through the small containment hatch opening.
18 Removal of a Portion of Bio Shield Wall Core drilling of biological shield wall. View of a section of biological shield wall after cutting with rigging attachments installed for lifting and removal.
19 Sectioning and Removal of the Bio Shield Wall The biological shield wall that had to be cut in unusual shapes in order to provide clearance for the reactor vessel.
20 Sectioning and Removal of the Bio Shield Wall
21 Sectioning and Removal of the Bio Shield Wall The tight tolerances and the curved inside edge of the biological shield wall required precision cuts.
22 Sectioning and Removal of the Bio Shield Wall Section of biological shield wall wrapped and ready to be removed from containment.
23 Cutting Reactor Nozzles, Control Rod Drive Tubes and All Other Vessel Attachments. The last item was to cut all nozzles pipes and other welded attachments from the vessel at precise tolerances so the vessel would fit in the transport package. In all, there were 10 steam and recirculation inlet and outlet nozzles, 29 stainless steel control rod drive tubes, 2 large support trunions and 25 other smaller nozzles of various size and materials. The recirculation inlet and outlet nozzles along with the control rod drive tubes were especially difficult due to very limited access and high radiation and contamination levels. Special brackets were fabricated to guide the diamond wire through the maze of pipes. Controls were located remotely to keep exposures to a minimum. The diamond wire successfully cut every nozzle and metal attachment eliminating any need for thermal cutting.
24 Cutting Reactor Nozzles, Control Rod Drive Tubes and All Other Vessel Attachments. Note the limited space available to access cutting of the control rod drive tubes. Additional challenges included the requirement to cut the control rod drive tubes flush to the bowl shaped bottom of the vessel so the vessel would fit into its specially designed transport package.
25 Cutting Reactor Nozzles, Control Rod Drive Tubes and All Other Vessel Attachments. Very limited access was available for installation of equipment and guide pulleys and to make cutting operations as remote as possible.
26 Cutting Reactor Nozzles, Control Rod Drive Tubes and All Other Vessel Attachments. Pulley set-ups used to access nozzle cuts with very limited access.
27 Cutting Reactor Nozzles, Control Rod Drive Tubes and All Other Vessel Attachments. Cutting the reactor nozzles, control rod drive tubes, and all other vessel attachments free from the vessel. In each case, the metal and/or concrete structures were cut at a precise location. Radiation dose was reduced significantly by operating the equipment from a remote location. The cuts were very smooth and completed on schedule.
28 Reactor Vessel Removal Reactor vessel being removed and placed in encapsulation and transport canister.
29 Reactor Vessel Removal Cut reactor nozzles after removal of vessel. Complete package being loaded onto trailer for transport to barge slip.
30 Reactor Vessel Removal Package loaded and ready for transport to burial site.
31 Reactor Vessel Removal Package at burial site. All phases of the project were successfully performed with no injuries or accidents. For all of the work, cooling water for the diamond wire was controlled, captured and in some instances recycled to reduce overall volume.
FIG. 1. Fort St. Vrain Nuclear Generation Station.
Invited Paper XA9848067 FORT ST. VRAIN DECOMMISSIONING PROJECT M. FISHER Public Service Company of Colorado, Denver, Colorado, USA Abstract Public Service Company of Colorado (PSCo), owner of the Fort
More informationNEW TREATMENT CONCEPT FOR STEAM GENERATORS- TECHNICAL ASPECTS
NEW TREATMENT CONCEPT FOR STEAM GENERATORS- TECHNICAL ASPECTS Anders Lindström, Bo Wirendal and Maria Lindberg Studsvik Nuclear AB Department RadWaste SE 611 82 Nyköping Sweden ABSTRACT The project that
More informationReactor Vessel Removal: Improving Performance Big Rock Point Lessons Learned
Reactor Vessel Removal: Improving Performance Big Rock Point Lessons Learned P.T. Daly BNG America, D&D Operations 804 South Illinois Avenue, Oak Ridge, TN 37830 USA ABSTRACT The Big Rock Point (BRP) reactor
More informationRadiation Control in the Core Shroud Replacement Project of Fukushima-Daiichi NPS Unit #2
General Radiation Control in the Core Shroud Replacement Project of Fukushima-Daiichi NPS Unit #2 Yasunori Kokubun, Kazuyuki Haraguchi, Yuji Yoshizawa, Yasuo Yamada Tokyo Electric Power Co, 22 Kitahara
More informationPRR-1 Decommissioning: Preparing for Dismantling and Decontamination. R2D2 Project Meeting, Manila, Philippines September
PRR-1 Decommissioning: Preparing for Dismantling and Decontamination R2D2 Project Meeting, Manila, Philippines 15-19 September 2008 1 Presented by Leonardo S. Leopando Philippine Nuclear Research Institute
More informationLessons learned from ongoing decommissioning project of Fugen NPS
Workshop on "Current and Emerging Methods for Optimizing Safety and Efficiency in Nuclear Decommissioning, Sarpsborg, Norway, 7th 9th February 2017 Lessons learned from ongoing decommissioning project
More informationAREVA: Experience in Dismantling and Packing of Pressure Vessel and Core Internals
AREVA: Experience in Dismantling and Packing of Pressure Vessel and Core Internals Jan Hendrik Bruhn GmbH/ IBRZ-G Varna, June 10 th 2010 Content General Requirements for Dismantling Projects Stade NPP
More informationBest practices for preparing vessel internals segmentation projects
Best practices for preparing vessel internals segmentation projects Joseph BOUCAU a*, Per SEGERUD b, Moisés SANCHEZ c a Westinghouse Electric Company, 43 rue de l Industrie, 1400 Nivelles, Belgium b Westinghouse
More informationOregon State University s Small Modular Nuclear Reactor Experimental Program
Oregon State University s Small Modular Nuclear Reactor Experimental Program IEEE Conference on Technologies for Sustainability August 1, 2013 Portland, Oregon Brian Woods Oregon State University brian.woods@oregonstate.edu,
More informationSan Onofre Unit 1 Decommissioning
San Onofre Unit 1 Decommissioning Eric M. Goldin, Ph.D., CHP Southern California Edison P. O. Box 128 San Clemente, CA 92674-0128 USA Introduction Nuclear plant decommissioning presents several challenges
More informationRemote-Controlled Dismantling of the Thermal Isolation and Preparations for the Primary Shield Removal
Remote-Controlled Dismantling of the Thermal Isolation and Preparations for the Primary Shield Removal A. Graf, J. Fleisch, S. Neff, WAK GmbH, Eggenstein-Leopoldshafen, Germany S. Klute, E. Koselowski,
More informationThe following considerations are taken into account for designing the NUHOMS MP197 packaging.
14th International Symposium on the Packaging and Paper # 164 Transportation of Radioactive Materials (PATRAM 2004), Berlin, Germany, September 20-24, 2004 NUHOMS - MP197 Transport Cask Peter Shih, TRANSNUCLEAR,
More information1-(866)
WELCOME TO SIOUX RUBBER. WE PROTECT IT WITH RUBBER & URETHANE Your Rubber & Urethane Partner Sioux Rubber & Urethane is proud of our ability to help design and manufacture custom solutions to your abrasion,
More informationK. ASTM F436- Standard Specification for Hardened Steel Washers; 2011.
DIVISION 05 METALS 05 12 00 STRUCTURAL STEEL FRAMING PART 1 GENERAL 1.1 SECTION INCLUDES A. Structural steel framing members, support members. 1.2 RELATED REQUIREMENTS A. Section 05 50 00 - Metal Fabrications:
More informationF. BODIN 1, Ph. FOURNIER 1, L. MARTIN 2 1 COGEMA La Hague BEAUMONT HAGUE Cedex - France 2 SALVAREM BEAUMONT HAGUE Cedex - France
COGEMA EXPERIENCE ON DECONTAMINATION AND UNDERWATER AUTOMATICALLY REMOTE CUTTING USING ULTRA HIGH PRESSURE WATER DURING NUCLEAR DECOMMISSIONING OPERATIONS THE AQUARAD ROBOT F. BODIN 1, Ph. FOURNIER 1,
More informationBest practices for preparing vessel internals segmentation projects
PREDEC 2016: Title of the communication, February 16 18, Lyon, France Best practices for preparing vessel internals segmentation projects Joseph BOUCAU a*, Per SEGERUD b, Moisés SANCHEZ c a Westinghouse
More informationWM2015 Conference, March 15 19, 2015, Phoenix, Arizona, USA
Fukushima Inspection Manipulator 15485 Matt Cole, Kurion Takashi Mitsui, Yuji Morigaki * 1, Toshinori Dekura* 2, * 3 *1: IHI Corporation, Yokohama, Kanagawa, Japan *2: International Research Institute
More informationRESEARCH REACTOR FRJ-1 (MERLIN) THE CORE STRUCTURES OF THE REACTOR BLOCK ARE DISMANTLED
RESEARCH REACTOR FRJ-1 (MERLIN) THE CORE STRUCTURES OF THE REACTOR BLOCK ARE DISMANTLED B. Stahn, R. Printz, K. Matela, C. Zehbe Forschungszentrum Jülich GmbH 52425 Jülich, Germany J. Pöppinghaus Gesellschaft
More informationMaintenance Technologies for SCC which Support Stable Operations of Pressurized Water Reactor Power Plants
Maintenance Technologies for which Support Stable Operations of Pressurized Water Reactor Power Plants KOJI OKIMURA* 1 MASAYUKI MUKAI* 1 KAZUHIKO KAMO* 2 NOBUYUKI HORI* 1 KOICHIRO MASUMOTO* 1 MASAAKI KUROKAWA*
More informationDiffused Aeration Piping Equipment
1.0 General 1.1. The specifications in this section include all components of the Diffused Aeration System with the exception of the individual diffuser units. Refer to additional specification sections
More informationInnovative Approaches to Large Component Packaging. A. Freitag, M, Hooper, E, Posivak, J. Sullivan WMG, Inc. Peekskill, NY USA
Innovative Approaches to Large Component Packaging A. Freitag, M, Hooper, E, Posivak, J. Sullivan WMG, Inc. Peekskill, NY 10566 USA ABSTRACT Radioactive waste disposal often times requires creative approaches
More informationReactor Internals Segmentation Experience in the Nordic Region
Reactor Internals Segmentation Experience in the Nordic Region - 14267 Per Segerud, Stefan Fallström, and Lennart Nilsson Westinghouse Electric Sweden AB ABSTRACT The Nordic region has a long history of
More informationThe ACR : Advanced Design Features for a Short Construction Schedule
Transactions of the 17 th International Conference on Structural Mechanics in Reactor Technology (SMiRT 17) Prague, Czech Republic, August 17 22, 2003 Paper # S01-3 The ACR : Advanced Design Features for
More informationGerhart Grinanger, NOELL GmbH, Postfach 6260, D-8700 Wizrzburg, Germany
861 REMOTELY-OPERATED DISMANTLING OF THE REACTOR INTERNALS AT NIEDERAICHBACH POWER PLANT USING MANIPULATORS Gerhart Grinanger, NOELL GmbH, Postfach 6260, D-8700 Wizrzburg, Germany ABSTRACT The joint venture
More informationThe paper includes design and licensing status of the MAGNASTOR system, and prototyping development that NAC has performed to date.
14th International Symposium on the Packaging and Paper # 108 Transportation of Radioactive Materials (PATRAM 2004), Berlin, Germany, September 20-24, 2004 NAC's Modular, Advanced Generation, Nuclear All-purpose
More informationSECTION ENTRANCE FLOOR GRILLES STAINLESS STEEL GRATING
7160 Krick Rd., Walton Hills, OH 44146 800-321-3827 - Tel 440-439-8650 - Fax 440-439-6889 SECTION 12 48 16 ENTRANCE FLOOR GRILLES STAINLESS STEEL GRATING PART 1. GENERAL 1.01 SUMMARY: This section includes
More informationRANCHO SECO TRANSITION TO FULL DECOMMISSIONING. Dennis E. Gardiner, Decommissioning Project Manager, SMUD John M. Newey, CHP, President, NewRad, Inc.
ABSTRACT RANCHO SECO TRANSITION TO FULL DECOMMISSIONING Dennis E. Gardiner, Decommissioning Project Manager, SMUD John M. Newey, CHP, President, NewRad, Inc. The Rancho Seco Nuclear Generating Station
More informationTrex Commercial Products page Metal Railing
SECTION 05520 HANDRAILS AND RAILINGS PART 1 GENERAL 1.1 SECTION INCLUDES A. Classic Railings (Picket). B. GridGuard Railings (Mesh). C. Post Rail (Glass). D. Tensiline Railings (Cable). E. Track Rail (Glass).
More informationSECTION ENTRANCE FLOOR GRILLES STAINLESS STEEL GRATING
7160 Krick Rd., Walton Hills, OH 44146 800-321-3827 - Tel 440-439-8650 - Fax 440-439-6889 SECTION 12 48 16 ENTRANCE FLOOR GRILLES STAINLESS STEEL GRATING PART 1. GENERAL 1.01 SUMMARY: This section includes
More informationPROCESS GAS WASTE HEAT BOILERS WITH THIN FLEXIBLE TUBESHEET DESIGN
PROCESS GAS WASTE HEAT BOILERS WITH THIN FLEXIBLE TUBESHEET DESIGN BORSIG The Company BORSIG Process Heat Exchanger GmbH, a member of the BORSIG Group, is the international leading manufacturer of pressure
More informationDeveloping a Low Power/Shutdown PRA for a Small Modular Reactor. Nathan Wahlgren
Developing a Low Power/Shutdown PRA for a Small Modular Reactor Nathan Wahlgren NuScale Power, LLC June 23, 2014 1 Non-Proprietary Overview Probabilistic risk assessment (PRA) has traditionally focused
More informationLarge Cask, Small Building, AREVA s Safe MLLW Disposal Solution Despite Facility Limitations 16295
Large Cask, Small Building, AREVA s Safe MLLW Disposal Solution Despite Facility Limitations 16295 Ronnie T. Broughton*, PE, PMP, Adam Jones*, PE, Paul Scott** *AREVA Federal Services, LLC Ronnie.Broughton@areva.com
More informationJOSEPH OAT CORPORATION. We Make Metal Work FABRICATION, DESIGN, AND CONSULTING SERVICES FOR THE NUCLEAR INDUSTRY.
JOSEPH OAT CORPORATION We Make Metal Work FABRICATION, DESIGN, AND CONSULTING SERVICES FOR THE NUCLEAR INDUSTRY. JOSEPH OAT CORPORATION Joseph Oat Corporation, a family owned and operated business for
More informationWM 00 conference, February 27 March 2, 2000, Tucson, AZ
WM 00 conference, February 27 March 2, 2000, Tucson, AZ REACTOR PRESSURE VESSEL REMOVAL AT A BOILING WATER REACTOR WITH SPENT FUEL IN THE ADJACENT FUEL POOL By Albert A. Freitag, WMG, Inc Greg Harttraft,
More informationReactor Core Internals Replacement of Ikata Units 1 and 2
IAEA-CN-194-1P51 Reactor Core Internals Replacement of Ikata Units 1 and 2 K. Ikeda,T. Ishikawa,T. Miyoshi,T. Takagi Shikoku Electric Power Co., Inc., Takamatsu City, Japan Abstract. This paper presents
More informationSECTION ALUMINUM HANDRAIL SYSTEMS
SECTION 05520 ALUMINUM HANDRAIL SYSTEMS PART 1 - GENERAL 1.01 SUMMARY A. Section includes aluminum handrails and railings. B. Related Work: 1. Section 03300 - Cast-in-Place Concrete C. References: 1. American
More informationPush a Button and the Work Gets Done
EPRI JOURNAL July/August 2018 No. 4 1 Push a Button and the Work Gets Done EPRI Examines Robotics and Automation for Nuclear Plant Decommissioning By Brent Barker The Resident Farmer Scenario describes
More informationESS Target Facility Design. John Haines for the ESS Target Project Team
ESS Target Facility Design John Haines for the ESS Target Project Team www.europeanspallationsource.se May 7, 2015 Outline Background Status of technical systems Project status and plans 2 ESS will be
More informationSECTION ARCHITECTURAL ORNAMENTAL HANDRAILS AND RAILINGS Casino Modular Railing System
SECTION 05 5200 ARCHITECTURAL ORNAMENTAL HANDRAILS AND RAILINGS Casino Modular Railing System PART 1 GENERAL 1.01 WORK INCLUDED A. Furnish and/or install stainless steel railings and components. 1.02 REFERENCE
More informationCITY OF MOUNT DORA LIFT STATION CHAINLINK FENCE AND GATE SPECIFICATIONS
CITY OF MOUNT DORA LIFT STATION CHAINLINK FENCE AND GATE SPECIFICATIONS PART 1 - GENERAL 1.01 SUMMARY A. Section Includes furnishing and installing chain-link fabric fence, gate, and appurtenances. 1.02
More informationNORTH HARRIS COUNTY REGIONAL WATER AUTHORITY PIPE HANGERS, Section PIPE HANGERS, SUPPORTS, AND RESTRAINTS
PART 1 GENERAL 1.01 SUMMARY Section 15140 PIPE HANGERS, This Section includes the furnishing and subsequent installation of: A. Pipe and equipment hangers, supports, and associated anchors B. Equipment
More informationDemonstrative Drop Tests of Transport and Storage Full-Scale Canisters with High Corrosion-resistant
14th International Symposium on the Packaging and Paper # 149 Transportation of Radioactive Materials (PATRAM 24), Berlin, Germany, September 2-24, 24 Demonstrative Drop Tests of Transport and Storage
More informationCollectors. Water Treatment & Chemical Processing
Water Treatment & Chemical Processing Collectors Screen Services Specialty screens and equipment for industrial, petrochemical, mining, and water treatment applications Page 2 Collector/Distributors fabricated
More informationSECTION HANDRAILS AND RAILINGS. Display hidden notes to specifier. (Don't know how? Click Here)
SECTION 05520 HANDRAILS AND RAILINGS PART 1 GENERAL 1.1 SECTION INCLUDES Display hidden notes to specifier. (Don't know how? Click Here) A. Classic Railings (Picket). B. GridGuard Railings (Mesh). C. Post
More informationMODEL SPECIFICATIONS: Hydraulically Driven Steel Underpinning Pile Specifications
MODEL SPECIFICATIONS: Hydraulically Driven Steel Underpinning Pile Specifications Mar/2008 v1.0 SECTION 02255 HYDRAULICLY DRIVEN STEEL UNDERPINNING PILES PART 1 GENERAL 1.01 SCOPE OF WORK The work shall
More informationCEILING MOUNTED ARTICULATING JIB CRANE
SECTION 14657 CEILING MOUNTED ARTICULATING JIB CRANE ***** Gorbel, Inc. manufacturers a broad range of material handling cranes including monorail, bridge, gantry, and jib cranes. Numerous work station
More informationFOOD AND BEVERAGE PROCESSING
BILFINGER WATER TECHNOLOGIES FOOD AND BEVERAGE PROCESSING COMPREHENSIVE SOLUTIONS FOR BIO-FUELS, BREWING, CORN WET MILLING, ETHANOL, MALTING, STARCH, SUGAR TREATMENT AND WINE PRODUCTION 2 FOOD AND BEVERAGE
More informationChapter 12. Flux Cored Arc Welding Equipment, Setup, and Operation Delmar, Cengage Learning
Chapter 12 Flux Cored Arc Welding Equipment, Setup, and Operation Objectives Explain the FCA welding process Describe what equipment is needed for FCA welding List the advantages of FCA welding, and explain
More informationStairpans Stair Treads Landing Pans Carrier Angles Nosings Infill Panels U-Edging Hems
Stairpans Stair Treads Landing Pans Carrier Angles Nosings Infill Panels U-Edging Hems STAIR SYSTEMS CATALOG stairpans.com 2 Serving the Needs of Our Customers Since 1923 Eberl Iron Works, Inc. Founded
More informationReplacement Works for the Steam Generator and the Reactor Pressure Vessel Upper Head
Unit 2, Genkai Nuclear Power Plant Replacement Works for the Steam Generator and the Reactor Pressure Vessel Upper Head Replacement works for the above components were conducted at Unit 2 of the Genkai
More informationRADIOACTIVE GRAPHITE MANAGEMENT AT UK MAGNOX NUCLEAR POWER STATIONS. G. HOLT British Nuclear Fuels plc, Berkeley, United Kingdom 1.
RADIOACTIVE GRAPHITE MANAGEMENT AT UK MAGNOX NUCLEAR POWER STATIONS G. HOLT British Nuclear Fuels plc, Berkeley, United Kingdom Abstract. The UK nuclear power industry is predominantly based on gas-cooled,
More informationChapter 7. Drains and cleanouts. Drains and cleanouts 34. Topics. Notes. 7.1 Existing rectangular or square drains and floor sinks 35
Drains and cleanouts 34 Chapter 7 Drains and cleanouts Topics 7.1 Existing rectangular or square drains and floor sinks 35 7.2 Altro Gulley Angle/Edge strips with Altro safety flooring 35 7.3 Visedge VR
More informationSECTION VIBRATION CONTROLS FOR HVAC PIPING AND EQUIPMENT
SECTION 230548 - PART 1 - GENERAL 1.1 SUMMARY A. This Section includes the following: 1. Elastomeric Isolation pads. 2. Elastomeric Isolation mounts. 3. [Freestanding] [Restrained] [Freestanding and restrained]
More informationDe Montfort Mark 7 Incinerator (Flatpack)
De Montfort Mark 7 Incinerator (Flatpack) Introduction This design is specially for those occasions when a large number of incinerators are to be built at one location and transported to the places where
More informationSECTION ARCHITECTURAL ORNAMENTAL HANDRAILS AND RAILINGS Summit tm Modular Railing System
SECTION 05720 ARCHITECTURAL ORNAMENTAL HANDRAILS AND RAILINGS Summit tm Modular Railing System PART 1 GENERAL 1.01 WORK INCLUDED A. Furnish and/or install supported glass stainless steel railings, glass
More informationSECTION STRUCTURAL METAL FRAMING
SECTION 05100 STRUCTURAL METAL FRAMING PART 1 GENERAL 1.01 SUMMARY A. Section Includes: Structural steel framing including lintels, shelf angles, bearing plates, anchor bolts and other items as shown on
More informationWALL CANTILEVER WORK STATION JIB CRANE
SECTION 14662 WALL CANTILEVER WORK STATION JIB CRANE ***** Gorbel, Inc. manufactures a broad range of material handling cranes including monorail, bridge, gantry, and jib cranes. Numerous work station
More informationConsiderations for Disposition of Dry Cask Storage System Materials at End of Storage System Life
Considerations for Disposition of Dry Cask Storage System Materials at End of Storage System Life Nuclear Fuels Storage & Transportation Planning Project Office of Fuel Cycle Technologies Nuclear Energy
More information1. Base plates, setting plates and anchor rods for columns. 8. Lintels if connected to structural steel columns.
PAGE 051200-1 SECTION 051200 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification sections,
More informationnalcofabtech.com A Nalco Champion Company
nalcofabtech.com A Nalco Champion Company 2 CONTENTS Goal Zero - Safety Culture...4 About Us...6 Capabilities...8 Services...24 Equipment and Facilities... 36 3 4 At Nalco FabTech, our programs ensure
More information.1 American Institute of Steel Construction (AISC) Specifications for Steel Buildings AISC
05 12 00 STRUCTURAL STEEL FRAMING Page 1 of 3 1 General 1.1 SECTION INCLUDES.1 Structural steel framing and support members 1.2 RELATED SECTIONS.1 Section 05 50 00 Metal Fabrications 1.3 REFERENCES.1 American
More informationA-Series Aluminum Gantry Crane
SPANCO PRODUCT SPECIFICATIONS 1 A-Series Aluminum Gantry Crane This guide can be used to prepare a bid specification for the incorporation of an A-Series Gantry Crane into a competitive bid project or
More informationHandling of Reactor Internals at Forsmark Nuclear Power Plant
Handling of Reactor Internals at Forsmark Nuclear Power Plant Presented at the Studsvik seminar on Decommissioning of Nuclear Facilities 14-16 September 2010, Nyköping, Sweden Jennifer Möller Henrik Algotsson
More informationMETHODOLOGY FOR ENSURING THE INTEGRATION OF ALARA INTO THE DESIGN OF
METHODOLOGY FOR ENSURING THE INTEGRATION OF ALARA INTO THE DESIGN OF THE AP1000 TM REACTOR Erik Slobe slobeed@westinghouse.com Westinghouse Electric Company LLC 1000 Westinghouse Drive Cranberry Township,
More informationMinimizing Activation, Size and Costs and yet Maximizing Efficiency
Minimizing Activation, Size and Costs and yet Maximizing Efficiency An Engineering Challenge for Neutron Research Instruments Elbio Calzada MLZ is a cooperation between: Outline Introduction: Neutron Source
More informationHow To Construct a Ferro Cement Tank
How To Construct a Ferro Cement Tank Be Advised The following power point presentation assumes that individuals using it to construct ferro-cement tanks have a basic knowledge of geometry and calculating
More informationSECTION DECORATIVE METAL AND GLASS RAILING
SECTION 05 73 00 DECORATIVE METAL AND GLASS RAILING PART 1 GENERAL 1.1 SUMMARY A) This section includes both standard and custom handrails as shown in the contract drawings. B) These include aluminum,
More informationSampling of Reactor Pressure Vessel and Core Internals Ralf Oberhäuser
Sampling of Reactor Pressure Vessel and Core Internals Ralf Oberhäuser Decommissioning & Dismantling Projects GmbH, Erlangen, Germany Content Introduction and Motivation Main Aspects Sampling Techniques
More informationValmont Newmark is your single source for steel, concrete or hybrid structures for power delivery
Valmont Newmark is your single source for steel, concrete or hybrid structures for power delivery Valmont Newmark is your single source for steel, A Tradition of Meeting Needs. Building on its steel pole
More informationSECTION VIBRATION CONTROLS FOR PLUMBING PIPING AND EQUIPMENT
Page 220548-1 SECTION 220548 - PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,
More informationThis guide can be used to prepare a specification for incorporating wall bracket jib cranes into a competitively bid construction project.
SECTION 14654 WALL BRACKET JIB CRANE ***** Gorbel, Inc. manufacturers a broad range of material handling cranes including monorail, bridge, gantry, and jib cranes. Numerous work station and industrial
More informationDesigning, Commissioning and Monitoring of 40% Scale Bentonite Buffer Test 14260
Designing, Commissioning and Monitoring of 40% Scale Bentonite Buffer Test 14260 Harri Kivikoski*, Pieti Marjavaara* and Pasi Rantamäki** * VTT Technical Research Centre of Finland, Espoo, Finland ** Posiva
More informationNuclear Fuel Cycle Transport
WNTI W O R L D N U C L E A R T R A N S P O RT I N S T I T U T E FACT SHEET Nuclear Fuel Cycle Transport Back End Materials Dedicated to the safe, efficient and reliable transport of radioactive materials
More informationStructural Steel. Production and Applications. GWP Engineering Limited
Structural Steel Production and Applications GWP Engineering Limited Contents About Us...3 Steel Material...4 Production...6 Structural Steel Fabrication...8 Applications...10 2 About Us From offices in
More information4418 Pesson Road New Iberia, LA 70560
ASRC Energy Services Omega, LLC is a full service provider for oil and gas production, mid-stream chemical processing, drilling, refining, utility, government and manufacturing industries. Omega has construction
More informationMETAL LADDERS (LADDER SAFETY GATE FALL PROTECTION)
Page 1 of 6 SECTION 05515 METAL LADDERS (LADDER SAFETY GATE FALL PROTECTION) PART 1 - GENERAL 1.1 SECTION INCLUDES A. Specialty custom designed, spring assisted, self-closing LADDER SAFETY GATE (LSG) for
More informationSPECIFICATIONS SECTION FLOOD CONTROL GATES. A. ASTM C 39 - Standard Test Method for Compressive Strength of Cylindrical Concrete Specimens.
SPECIFICATIONS SECTION FLOOD CONTROL GATES PART 1 GENERAL 1.1 SECTION INCLUDES A. Flood Gates. 1.2 RELATED SECTIONS A. N/A. 1.3 REFERENCES A. ASTM C 39 - Standard Test Method for Compressive Strength of
More informationUNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C SAFETY EVALUATION REPORT
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 SAFETY EVALUATION REPORT Docket No. 72-1040 HI-STORM UMAX Canister Storage System Holtec International, Inc. Certificate of Compliance
More informationVVER-440/213 - The reactor core
VVER-440/213 - The reactor core The fuel of the reactor is uranium dioxide (UO2), which is compacted to cylindrical pellets of about 9 height and 7.6 mm diameter. In the centreline of the pellets there
More informationINSTALLATION GUIDE PLEASE READ ENTIRE INSTRUCTION MANUAL BEFORE PROCEEDING!
DURA - TRENCH INSTALLATION GUIDE This guide is intended to aide in the installation of Dura-Trench systems. There are many different applications and situations for the use of this product and the installation
More informationSPECIFICATION SECTION 05515: LADDERS O Keeffe s Aluminum Ladders
Welcome to the O Keeffe s Guide Specification System prepared as an aid to specify in preparing written construction documents. For specification assistance with specific product applications, please contact
More informationSECTION ARCHITECTURAL ORNAMENTAL HANDRAILS AND RAILINGS Monaco tm Modular Railing System
SECTION 05720 ARCHITECTURAL ORNAMENTAL HANDRAILS AND RAILINGS Monaco tm Modular Railing System PART 1 GENERAL 1.01 WORK INCLUDED A. Furnish and/or install supported glass stainless steel railings, glass
More information40'-0" PIPE SUPPORT (TYP.) (SEE DWG. NO. SK-2 OR DWG. NO. SK-4)
SK-1 STANDARD LENGTH 4.301 40'-0" A 6" 2'-0" 9'-0" 9'-0" 9'-0" 9'-0" 2'-0" A 3" OF EXPOSED AT EACH END OF PIPE. PIPE SUPPORT (TYP.) (SEE DWG. NO. SK-2 OR DWG. NO. SK-4) EXPOSED PIPE MINIMUM GAUGE AND THICKNESS
More informationDecommissioning the Philippine Research Reactor (Under R2D2P): Updates and Challenges
Decommissioning the Philippine Research Reactor (Under R2D2P): Updates and Challenges C.C. Bernido,, F.L. Santos, L.S. Leopando Philippine Nuclear Research Institute Philippine Research Reactor (PRR-1)
More informationWM 2013 Conference, February 24 February 28, 2013, Phoenix, AZ, USA. Removal of the Plutonium Recycle Test Reactor 13031
ABSTRACT Removal of the Plutonium Recycle Test Reactor 13031 C. Brad Herzog, CH2M HILL, Inc., cherzog@ch2m.com Rudolph Guercia, DOE, rudolph.guercia@rl.doe.gov Matt LaCome, Meier Engineering Inc., mllacome@meierinc.com
More informationUK ABWR - NEW NPP DESIGN FOR UK
IAEA PLiM2017 [IAEA-CN-246-085] UK ABWR - NEW NPP DESIGN FOR UK 25-October-2017 Kazuhiro YOSHIKAWA Masaaki HAYASHI Yasuhiro MABUCHI Daisuke TANIGUCHI Hitachi-GE Nuclear Energy, Ltd. Contents 1. Introduction
More informationfemale pipe. A Wall Support must be installed just above the tee and at least every 8 feet thereafter. If the pipe is to be run through a roof overhang then a Flashing, Storm Collar and Vertical Rain Cap
More informationSECTION ORCHESTRA PIT FILLER
PART 1 - GENERAL 1.1 SECTION INCLUDES A. Orchestra pit filler. 1.2 REFERENCES SECTION 11 61 00 ORCHESTRA PIT FILLER A. American Hardboard Association (AHA): 1. AHA A135.4-95: Basic Hardboard. B. American
More informationSTEAM GENERATOR LEAKAGE AT THE BN-350 DESALINATION PLANT
STEAM GENERATOR LEAKAGE AT THE BN-350 DESALINATION PLANT M. Ragheb 12/13/2010 INTRODUCTION The BN-350 sodium cooled fast reactor was constructed near the city of Aktau, formerly Shevchenko on the Caspian
More information2.0 Normal and customary equipment used on a core drill job include:
CSDA Specification Title: Core Drilling Specification No: CSDA-C-101 Effective Date: June 1, 1998 Revised: Mar 30, 2004 1. Codes, Standards & Definitions 1.1 Occupational Safety and Health Administration
More informationLong Reach Tooling Solutions
Long Reach Tooling Solutions Supporting Decommissioning of the PFSP at Sellafield A framework contract, with JFN as the primary interface, was established in July 2013, with the aim of developing a long
More informationMaria Taranger Foto: Kävlinge Municipality
Maria Taranger Foto: Kävlinge Municipality The icon of nuclear power in Sweden The beginning and the end Type: BWR Capacity: 1800 MWt / 615MWe First connection to the grid: May 15, 1975 / March 21, 1977
More informationStructural Design of Dam Sluice Gate Walkway Slabs: Retrofit and Replacement Options
Structural Design of Dam Sluice Gate Walkway Slabs: Retrofit and Replacement Options A local utility company issued a Request for Proposal to our university s capstone design class for structural improvements
More informationInternational Journal of Advance Engineering and Research Development
Scientific Journal of Impact Factor (SJIF): 5.71 International Journal of Advance Engineering and Research Development Volume 5, Issue 03, March -2018 e-issn (O): 2348-4470 p-issn (P): 2348-6406 Study
More informationBORSIG Process Heat Exchanger GmbH. Egellsstr. 21 Phone: +49 (0) 30 / Berlin/Germany Fax: +49 (0) 30 /
BORSIG Process Heat Exchanger GmbH www.borsig.de/pro E-mail: info@pro.borsig.de Egellsstr. 21 Phone: +49 (0) 30 / 4301-01 13507 Berlin/Germany Fax: +49 (0) 30 / 4301-2447 BORSIG Process Heat Exchanger
More informationRapid Axial Load Testing of Drilled Shafts
Supplemental Technical Specification for Rapid Axial Load Testing of Drilled Shafts SCDOT Designation: SC-M-712 (9/15) September 4, 2015 1.0 GENERAL This work shall consist of performing a rapid axial
More informationBest Practice Form. Open Air Demolition of Asbestos Gunite by Using Track Mounted Wet Cutting Saw DOE Site:
Best Practice Form Best Practice Title: Open Air Demolition of Asbestos Gunite by Using Track Mounted Wet Cutting Saw DOE Site: Lawrence Livermore National Laboratory (LLNL) Facility Name: B328 Demolition
More informationInstallation Manual For Conical Tanks. INSTALLATION and MAINTENANCE INSTRUCTIONS FOR CONICAL TANKS
INSTALLATION and MAINTENANCE INSTRUCTIONS FOR CONICAL TANKS Page 1 of 10 INDEX 1. Health & Safety 3 2. Introduction 3 3. Requirements 3 4. Working Area 3 5. Equipment 3 6. 2 and 3 metre tank above ground
More informationGreifswald Project Introduction/Experience summary Axel Bäcker
Decommissioning operation of large decommissioning projects 20 years experience Decommissioning management of five power reactors on the Greifswald site Greifswald Project Introduction/Experience summary
More informationIrradiation Facilities at the Advanced Test Reactor International Topical Meeting on Research Reactor Fuel Management Lyon, France
Irradiation Facilities at the Advanced Test Reactor International Topical Meeting on Research Reactor Fuel Management Lyon, France S. Blaine Grover Idaho National Laboratory March 12, 2007 Agenda Advanced
More information