1 PRECAST PANEL STAY-IN-PLACE DECK FORMS FABRICATION Item No. PRECAST PANEL STAY-IN-PLACE DECK FORMS DELIVERY Item No. PRECAST PANEL STAY-IN-PLACE DECK PANELS ERECTION Item No. Special Provision No. 999S28 June 2010 CONSTRUCTION SPECIFICATION FOR PRECAST PANELS FOR USE AS STAY-IN-PLACE DECK FORMS 1.0 SCOPE This Special Provision covers the requirements for the fabrication, transportation and installation of precast concrete panels for use as stay-in-place forms for cast-in-place deck slabs supported by girders. 2.0 REFERENCES This Special Provision references the following standards, specifications, and publications: Ontario Provincial Standard Specifications, Construction: OPSS 904 OPSS 905 OPSS 929 OPSS 932 Concrete Structures Steel Reinforcement for Concrete Abrasive Blast Cleaning Concrete Construction Crack Repair - Concrete Ontario Provincial Standard Specifications, Material: OPSS 1202 OPSS 1350 Bearings Elastomeric Plain and Steel Laminated Concrete - Materials and Production American Society for Testing and Materials Standards: ASTM C ASTM C Standard Test Method For Microscopic Determination of Parameters of the Air-Void System in Hardened Concrete Standard Test Method for Electrical Indication of Concrete s Ability to Resist Chloride Ion Penetration Canadian Standards Association Standards: CAN/CSA A /A CAN/CSA A CSA G40.20/G CSA G164-M92 (R1998) Concrete Materials and Methods of Concrete Construction/Methods of Test for Concrete Precast Concrete Materials and Construction General Requirements for Rolled or Welded Structural Quality Steel/Structural Quality Steels Hot Dip Galvanizing of Irregularly Shaped Articles 3.0 DEFINITIONS For the purpose of this Special Provision, the following definitions apply: June 2010 Pg. 1 of 10 SSP999S28

2 Member: means a precast concrete prestressed girder. Lot: means all members in one bed which are of the same type. 4.0 DESIGN AND SUBMISSION REQUIREMENTS 4.01 Design Requirements Lifting Loops The Precaster is responsible for the design of the lifting loops for the panels. Lifting loops shall be stainless steel and shall have adequate capacity and be located such that the stresses in the panel due to stripping and handling are minimized. Lifting loops shall not project above the top layer of reinforcing in the cast-in-place portion of the completed deck slab. Lifting loops shall remain in place after the panels have been erected Support System for the Panels Angles or timbers, when used as support system for the panels, shall be designed by the Contractor or Precaster and shall support a temporary construction live load of 2.4 kpa applied to the top surface of the deck panel Reinforcing Steel Reinforcing steel shall be as detailed on the Contract Drawings Prestressing Strand Prestressing strands shall be placed at a uniform spacing and at the mid-depth of the panel. When releasing the strands, the prestressing force shall be applied uniformly and in a symmetrical manner to ensure that the panels do not crack. For prestressed panels, the ratio of panel thickness to strand diameter shall not be less than Submission Requirements Working Drawings The Contractor shall submit 3 sets of fabrication Working Drawings to the Contract Administrator at least 7 Days prior to commencement of fabrication of the panels, for information purposes only. Prior to making a submission, the seals and signatures of a design Engineer and a design-checking Engineer shall be affixed on the Working Drawings verifying that the drawings are consistent with the Contract Documents. Where multi-discipline engineering work is depicted on the same Working Drawing and the design or designchecking Engineer or both are unable to seal and sign the Working Drawing for all aspects of the work, the drawing shall be sealed and signed by as many additional design and design-checking Engineers as necessary. The Working Drawings shall include the following information: a) Panel dimensions, panel layout, and panel markings for the total bridge. b) Prestressing strand and/or reinforcement for the panels. June 2010 Pg. 2 of 10 SSP999S28

3 c) Jacking force, when prestressing is used. d) Lifting loops. e) Bearing strips. f) Support system, when used. g) All other applicable details. The supporting documents shall include stamped calculations for handling and erection procedures Modifications to Bridge Components At least one (1) week prior to commencement of fabrication of the components requiring modification, the Contractor shall submit to the Contract Administrator three (3) sets of drawings, for information purposes only, signed and sealed by an Engineer. The drawings shall show details of any required modifications to bridge components that are shown in the Contract Drawings, including but not limited to the following: a) Revised bearing seat elevations and/or bridge profile grade. b) Revised girder stirrup heights or shear connector spacing and heights. c) Revised reinforcement details for the deck slab Concrete Mix Design The Contractor shall be responsible for the concrete mix design and shall submit the concrete mix design to the Contract Administrator according to the Mix Design requirements of OPSS 1350 along with the certificate of ready mix concrete facilities when concrete is supplied by an external concrete supplier. The Contractor shall demonstrate, at the time of submission of the concrete mix design(s), that the proposed mix design(s) and materials are capable of meeting the requirements of this Special Provision. To demonstrate this, the Contractor shall submit test data for the following: a) 28-Day compressive strength. b) Air void system in the hardened concrete. c) For high performance concrete, rapid chloride permeability at 28 days. The precast concrete plant certificate as required by CAN/CSA A23.4 shall be submitted to the Contract Administrator as part of the concrete mix design submission Certificate of Conformance Upon completion of the panels and prior to delivery, the Quality Verification Engineer (QVE) shall conduct an interim inspection to verify that the fabrication of the panels has been carried out in general conformance with the Working Drawings, supporting documents and Contract Documents. June 2010 Pg. 3 of 10 SSP999S28

4 Upon completion of fabrication, delivery and erection and prior to placing the concrete for the cast-in-place portion of the deck slab, the Contractor shall submit to the Contract Administrator a Certificate of Conformance, sealed and signed by the Quality Verification Engineer. The certificate shall state that the fabrication, handling and erection of the panels have been carried out in general conformance with the Working Drawings, supporting documents, and Contract Documents. 5.0 MATERIAL 5.01 Concrete Concrete materials and production shall be according to OPSS 1350 with the following exceptions: a) The requirements for hardened air void system parameters, rapid chloride permeability and compressive strength do not apply. b) Compressive strength shall be as specified elsewhere in the Contract Documents. c) The air void system in hardened concrete when tested according to ASTM C 457 shall be: i. Air Content: 3.0% minimum ii. Spacing Factor: mm maximum d) Rapid chloride permeability of high performance concrete at 28 days shall be equal to or less than 1000 coulombs. e) Slag aggregate shall not be used. f) Superplasticizer may be added to the mix at the time of batching Bearing Strips The bearing strips used to support the precast panels shall be compressible, durable and designed to stay in place. Bearing strips shall be elastomeric, according to the requirements of OPSS Miscellaneous Steel Miscellaneous structural steel elements used with members and are to be left in place shall be hot-dipped galvanized according to CAN/CSA G164-M91 and meet the requirements of CSA G40.21 Grade 350W. 6.0 EQUIPMENT 6.01 Pretensioning Pretensioning equipment shall be according to CSA A CONSTRUCTION 7.01 Fabrication of Stay-in-Place Deck Panels June 2010 Pg. 4 of 10 SSP999S28

5 Plant Certification Stay-in-place deck panels shall be fabricated by a plant certified according to CAN/CSA A23.4 in the appropriate category Construction Requirements Panels shall be cast flat. Strands or reinforcing steel bars shall be continuous across the top of the members or projecting beyond the end of the panel and lapped. Sufficient support chairs shall be provided such that the strands and/or reinforcing steel bars are not vertically displaced between chair support locations. Chairs shall be durable and made of a non-ferrous metal or plastic. Panel lengths in the completed structure shall be as shown on the Contract Drawings. Initial panels lengths as cast, shall include an allowance for reduction in length due to elastic shortening caused by prestressing as well as creep and shrinkage effects prior to placing the cast-in-place topping Surface Finish The top surface of all panels shall have a rough surface, with vertical indentations of 3 mm amplitude spaced at 15 mm Curing Top surface curing compounds shall not be used. The panels shall be cured according to OPSS Storage Deck panels shall be stored for a minimum length of time after casting. Panels that have lengths less than 2500 mm shall be at least 15 days old before installation. Panels with lengths equal to or greater than 2500 mm shall be at least 30 days old prior to installation. Precast panels shall be kept in a horizontal position during storage, transportation and at the site Erection Panels shall not be lifted by attaching lifting devices to any strand or reinforcing steel bar projecting beyond the edges of the panel. Leakage shall be kept to a minimum. No leakage shall be permitted to fall onto the roadway below or into environmentally sensitive waterways Tolerances for Panels Precast panels shall meet the following tolerances: a) Panel lengths: ± 5 mm b) Panel widths: ± 10 mm June 2010 Pg. 5 of 10 SSP999S28

6 c) The maximum difference in plan view diagonal dimensions (squareness) of rectangular panels: Not greater than 3.5 mm per metre of diagonal length d) Thickness of panel: +5 mm, -3 mm e) For prestressed panels, strands shall be located at the mid-depth of the panel with a vertical tolerance of +0 mm, -3 mm, measured from the soffit, and a horizontal tolerance of ± 10 mm. f) Deviation from straightness of panel edges along the transverse joint between adjacent panels shall not exceed 1.5 mm per metre length (panels with greater deviation will be rejected). g) Vertical bowing of panels out of plane, after casting and immediately prior to erection, shall not be greater than the panel length /360, the panel width/360, or 10 mm maximum Quality Control Sampling and Testing Slump, Air and Temperature The Contractor shall be responsible for all aspects of sampling and testing the plastic concrete for slump, air content and temperature according to OPSS 1350 and the results of these tests recorded. The minimum frequency of testing shall be at least once for every 7 m 3 of concrete or each truck load of concrete Compressive Strength General The Contractor shall be responsible for all aspects of preparation, storage and transportation of cylinders to determine compressive strength. Moulds for all specimens shall be supplied by the Contractor and shall be made of plastic according to CAN/CSA A23.2-1D, with a lid. The lids shall be chemically and physically compatible with the concrete and shall provide a watertight seal for the moulds. The compressive strength of normal concrete shall be determined from 150 mm x 300 mm cylinders, with one set consisting of two cylinders. The compressive strength of high performance concrete and concrete with strengths greater then 50 MPa shall be determined from 100 mm x 200 mm cylinders, with one set consisting of three cylinders Transfer Strength Cylinders for the determination of transfer strength shall be cured under the same conditions as the concrete in the panels. The cylinders shall be tested at the Precaster s plant laboratory; otherwise it will be tested at an external CSA certified laboratory. The prestressing force shall not be transferred to the panels until two consecutive compressive strength results for normal concrete or three consecutive strength results for high performance concrete are greater than or equal to the specified transfer strength. It is the Contractor s responsibility to cast sufficient cylinders for determination of transfer strength. June 2010 Pg. 6 of 10 SSP999S28

7 Day Compressive Strength The Contractor shall cast one (1) set of cylinders for each lot to determine the compressive strength at 28 days. When the specified compressive strength is reached earlier, the lot shall be considered to have met the compressive strength requirements of this Special Provision. The cylinders shall be cured according to the requirements of OPSS Concrete cylinders shall be transported and delivered according to CAN/CSA A23.2-3C. The forms, on which the field data for the cylinders is recorded, shall be submitted to the laboratory with the concrete cylinders. A compressive strength result shall be the average of two cylinders for normal concrete and the average of three cylinders for high performance concrete Air in Hardened Concrete For evaluation of air void system parameters, the Contractor shall cast cylinders and shall test the cylinders according to ASTM C 457, except that a magnification of 100 to 125 shall be used. Testing shall be carried out by a Laboratory and operator(s) which are on the Ministry s list of qualified laboratories and operators for this test. One set of cylinders shall be cast for each lot according to CAN/CSA A23.2. The set shall consist of two 100 mm x 200 mm cylinders. The cylinders shall be cured under the same environmental conditions as the concrete in the members. Immediately following completion of curing of the members, the cylinders shall be transported to the testing laboratory. Cylinders shall be cut lengthwise into two halves, with one half to be tested by the Contractor and the other forwarded to the Ministry (Head, Concrete Section, Building C, Room 15, Wilson Avenue, Downsview, Ontario, M3M 1J8) within two weeks of casting the cylinders. Both cylinder halves shall be marked with a unique identification number. The portion forwarded to the Ministry shall have an information sheet securely attached to it detailing the contract number; lot number and Form A of the Concrete mix design for the component. Air void cylinder samples shall be retained by the Contractor until expiry of the one year general warranty, as defined elsewhere in the Contract Documents and shall be provided to the Contract Administrator upon request Rapid Chloride Permeability for High Performance Concrete For evaluation of rapid chloride permeability for high performance concrete, the Contractor shall cast and test cylinders according to ASTM C1202. Testing shall be carried out by a laboratory, which is on the Ministry s list of qualified laboratories for this test. One (1) set of cylinders shall be cast for each lot. Each set shall consist of two (2) 100 mm x 200 mm cylinders. The cylinders shall be cast from concrete sampled at the time the members are being manufactured and made according to CSA A23.2. Immediately following casting, the cylinders shall be stored at a temperature of 20 ± 5 C and shall be covered to prevent evaporation of water according to CAN/CSA A23.2-3C. The specimens shall be transported to the testing laboratory within 20 ± 4 hours of having been cast, then demoulded and stored at 23 ± 2 C in a moist condition until time of testing. A 10 mm thick slice shall be cut June 2010 Pg. 7 of 10 SSP999S28

8 off from the top of each cylinder before test specimens are cut from it. Two 50 mm long samples shall be cut from each cylinder and tested when the concrete is 28 to 32 days of age. Rapid chloride permeability cylinder samples and laboratory worksheets shall be retained by the Contractor until expiry of the one year general warranty, as defined elsewhere in the Contract Documents and shall be provided to the Contract Administrator upon request Defects and Deficiencies General The Contractor shall notify the Contract Administrator in writing immediately if any defects are present in the work, with an explanation of the cause and extent. Repairable defects shall be repaired at the Contractor s expense. The Contractor shall not proceed with the cast-in-place slab until the Contract Administrator has accepted all remedial work. Defects and deficiencies are classified as follows: a) Defects and deficiencies causing rejection b) Defects and deficiencies repairable by standard methods c) All other defects and deficiencies Defects and Deficiencies Causing Rejection A panel having any one of the following defects or deficiencies will be rejected: a) Panels not meeting the requirements of this Special Provision. b) Panels with honeycombing, voids, cavities, spalls and delaminations when the depth exceeds 45 mm or when the area of the defect exceeds 300 mm x 300 mm. c) Panels with cracks located parallel to or over the strands or reinforcing steel. d) Panels with cracks at the edges and /or with cracks at the bottom. e) Panels with cracks that are deeper than 25 mm and/or wider than 0.5 mm Defects and Deficiencies Repairable by Standard Methods A panel having one or more of the defects or deficiencies identified below shall be repaired according to the method specified: a) Panels with honeycombing, voids, cavities, spalls and delaminations when the depth does not exceed 45 mm or when the area of the defect is less than 300 mm x 300 mm shall be repaired as follows: i. Square all sides of the repair area. ii. Sawcut perimeter of removal area to a depth of 10 mm or to the depth of reinforcing steel or strands, whichever is less. iii. Remove all loose concrete using a chipping hammer or hand tools. June 2010 Pg. 8 of 10 SSP999S28

9 iv. Insert corrosion resistant wires and anchors. v. Abrasive blast clean all concrete surfaces to be patched according to OPSS 929. vi. Remove all dust and loose material from the prepared surface by using compressed air. vii. Moisten area to be repaired viii. Fill repair area with concrete or a proprietary patching material acceptable to the Owner. ix. Cure concrete according to OPSS 904 or cure proprietary patching material according to the manufacturer s recommendations. b) Panels with cracks other than those specified under defects and deficiencies causing rejection shall be repaired by epoxy injection according to OPSS 932. A proposal for the remedial work for the above defects shall be submitted to the Contract Administrator for review. The Contractor shall not proceed with repairs until approval of the proposal has been received All other Defects and Deficiencies For panels with defects or deficiencies not identified as rejectable or repairable by standard methods, the Contractor shall submit a proposal for repair to the Contract Administrator (CA) for review. The CA shall respond to the Contractor within seven Business Days of receipt of the complete repair proposal. If the Owner deems the repair proposal acceptable, the panel(s) shall be repaired according to the proposal. The Contractor shall not carry out any repairs without the acceptance of the proposal by the Contract Administrator. If the Owner deems the repair proposal unacceptable, the panels(s) shall be rejected and shall not be incorporated into the work. The repair proposal, signed and sealed by an Engineer, shall include as a minimum: a) Description of the panel. b) Assessment of any impact of the repaired defect(s) on durability, structural adequacy and integrity of the panel or on the structure. c) A detailed repair plan including materials, method and equipment to be used. d) Verification that the repair plan complies with the applicable standards for the type of work. e) All relevant supporting information, including material test results, field measurements and observations, production records, photographs, and structural analysis calculations, used for determining that the performance and function originally expected from the member will be met. f) Cause(s) of the defect and corrective action to be taken to prevent recurrence of the defect in future production, delivery or erection. The repair proposal for panels containing defects shall also include detailed sketches, width, length, depths, location and nature and frequency of any defects. 8.0 QUALITY ASSURANCE 8.01 Steel Reinforcement June 2010 Pg. 9 of 10 SSP999S28

10 The sampling and testing of steel reinforcement will be according to OPSS 905 and the Quality Control requirements of this Special Provision Acceptance The acceptance of the panels will be according to the Contract Documents including satisfactory completion of all repairs if applicable. Only panels meeting the requirements of the Contract Documents shall be incorporated into the Work BASIS OF PAYMENT Precast Panel Stay-in-place Deck Forms - Fabrication - Item Precast Panel Stay-in-place Deck Forms - Delivery - Item Precast Panel Stay-in-place Deck Forms - Erection - Item Payment at the Contract price for the above tender item(s) shall be full compensation for all labour, Equipment, and Material to do the work. June 2010 Pg. 10 of 10 SSP999S28

CONSTRUCTION SPECIFICATION FOR NON-PRESTRESSED PRECAST CONCRETE BRIDGE ELEMENTS TABLE OF CONTENTS. 9.0 MEASUREMENT FOR PAYMENT - Not Used

CONSTRUCTION SPECIFICATION FOR NON-PRESTRESSED PRECAST CONCRETE BRIDGE ELEMENTS TABLE OF CONTENTS. 9.0 MEASUREMENT FOR PAYMENT - Not Used PRECAST CONCRETE BRIDGE ELEMENTS, FABRICATION - Item No. PRECAST CONCRETE BRIDGE ELEMENTS, DELIVERY - Item No. PRECAST CONCRETE BRIDGE ELEMENTS, INSTALLATION - Item. No. Special Provision No. 999F31 February

More information

Special Provision No. 999F31 February 2016 CONSTRUCTION SPECIFICATION FOR NON-PRESTRESSED PRECAST CONCRETE BRIDGE ELEMENTS TABLE OF CONTENTS

Special Provision No. 999F31 February 2016 CONSTRUCTION SPECIFICATION FOR NON-PRESTRESSED PRECAST CONCRETE BRIDGE ELEMENTS TABLE OF CONTENTS PRECAST CONCRETE BRIDGE ELEMENTS, FABRICATION - Item No. PRECAST CONCRETE BRIDGE ELEMENTS, DELIVERY - Item No. PRECAST CONCRETE BRIDGE ELEMENTS, INSTALLATION - Item. No. Special Provision No. 999F31 February

More information

MATERIAL SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS

MATERIAL SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 1821 APRIL 2004 MATERIAL SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS AND BOX SEWERS TABLE OF CONTENTS 1821.01 SCOPE 1821.02 REFERENCES

More information

MATERIAL SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS

MATERIAL SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 1821 NOVEMBER 2015 MATERIAL SPECIFICATION FOR PRECAST REINFORCED CONCRETE BOX CULVERTS TABLE OF CONTENTS 1821.01 SCOPE 1821.02 REFERENCES 1821.03 DEFINITIONS

More information

CONSTRUCTION SPECIFICATION FOR PRESTRESSED CONCRETE - PRECAST MEMBERS

CONSTRUCTION SPECIFICATION FOR PRESTRESSED CONCRETE - PRECAST MEMBERS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 909 APRIL 2012 CONSTRUCTION SPECIFICATION FOR PRESTRESSED CONCRETE - PRECAST MEMBERS TABLE OF CONTENTS 909.01 SCOPE 909.02 REFERENCES 909.03 DEFINITIONS

More information

CONSTRUCTION SPECIFICATION FOR PRESTRESSED CONCRETE - PRECAST MEMBERS

CONSTRUCTION SPECIFICATION FOR PRESTRESSED CONCRETE - PRECAST MEMBERS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.MUNI 909 APRIL 2017 (Formerly OPSS 909, April 2012) Note: The MUNI implemented in April 2017 replaces OPSS 909 COMMON, April 2012 with no technical

More information

Special Provision No. 599S23 August 2018 REQUIREMENTS FOR RETAINED SOIL SYSTEMS (RSS)

Special Provision No. 599S23 August 2018 REQUIREMENTS FOR RETAINED SOIL SYSTEMS (RSS) RETAINED SOIL SYSTEM, TRUE ABUTMENT - Item No. RETAINED SOIL SYSTEM, FALSE ABUTMENT - Item No. RETAINED SOIL SYSTEM, WALL/SLOPE, HIGH PERFORMANCE - Item No. RETAINED SOIL SYSTEM, WALL/SLOPE, MEDIUM PERFORMANCE

More information

Special Provision No. 109S17 June 2017

Special Provision No. 109S17 June 2017 AMENDMENT TO OPSS 905, NOVEMBER 2014 Special Provision No. 109S17 June 2017 OPSS 905, November 2014 Construction Specification for Steel Reinforcement for Concrete is deleted in its entirety and replaced

More information

CONSTRUCTION SPECIFICATION FOR STRUCTURE REHABILITATION - CONCRETE REMOVAL

CONSTRUCTION SPECIFICATION FOR STRUCTURE REHABILITATION - CONCRETE REMOVAL ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 928 NOVEMBER 2006 CONSTRUCTION SPECIFICATION FOR STRUCTURE REHABILITATION - CONCRETE REMOVAL TABLE OF CONTENTS 928.01 SCOPE 928.02 REFERENCES 928.03

More information

Special Provision No. 799F01 March 2012 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF NOISE BARRIER TABLE OF CONTENTS

Special Provision No. 799F01 March 2012 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF NOISE BARRIER TABLE OF CONTENTS ... m NOISE BARRIER - Item No.... m NOISE BARRIER INCLUDING PRECAST NOISE/TRAFFIC BARRIER - Item No.... m NOISE BARRIER ON STRUCTURES - Item No.... m SALVAGEABLE NOISE BARRIER - Item No.... m SALVAGEABLE

More information

MATERIAL SPECIFICATION FOR CONCRETE - MATERIALS AND PRODUCTION

MATERIAL SPECIFICATION FOR CONCRETE - MATERIALS AND PRODUCTION ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.PROV 1350 APRIL 2010 MATERIAL SPECIFICATION FOR CONCRETE - MATERIALS AND PRODUCTION TABLE OF CONTENTS 1350.01 SCOPE 1350.02 REFERENCES 1350.03 DEFINITIONS

More information

Special Provision No. 599F01 May 2004 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF NOISE BARRIER TABLE OF CONTENTS

Special Provision No. 599F01 May 2004 CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF NOISE BARRIER TABLE OF CONTENTS ... m NOISE BARRIER - Item No.... m NOISE BARRIER INCLUDING PRECAST NOISE/TRAFFIC BARRIER - Item No.... m NOISE BARRIER ON STRUCTURES - Item No.... m SALVAGEABLE NOISE BARRIER - Item No.... m SALVAGEABLE

More information

CONSTRUCTION SPECIFICATION FOR CRACK REPAIR - CONCRETE

CONSTRUCTION SPECIFICATION FOR CRACK REPAIR - CONCRETE ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 932 MARCH 1998 CONSTRUCTION SPECIFICATION FOR CRACK REPAIR - CONCRETE 932.01 SCOPE 932.02 REFERENCES 932.03 DEFINITIONS TABLE OF CONTENTS 932.04 SUBMISSION

More information

CONSTRUCTION SPECIFICATION FOR CONCRETE PAVEMENT AND CONCRETE BASE

CONSTRUCTION SPECIFICATION FOR CONCRETE PAVEMENT AND CONCRETE BASE ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 350 MARCH 1998 CONSTRUCTION SPECIFICATION FOR CONCRETE PAVEMENT AND CONCRETE BASE 350.01 SCOPE 350.02 REFERENCES 350.03 DEFINITIONS TABLE OF CONTENTS

More information

CONSTRUCTION SPECIFICATION FOR CONCRETE BARRIERS

CONSTRUCTION SPECIFICATION FOR CONCRETE BARRIERS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 553 FEBRUARY 1991 CONSTRUCTION SPECIFICATION FOR CONCRETE BARRIERS 553.01 SCOPE 553.02 REFERENCES 553.03 DEFINITIONS TABLE OF CONTENTS 553.04 SUBMISSION

More information

TABLE OF CONTENTS. Use of this specification or any other specification shall be according to the Contract Documents.

TABLE OF CONTENTS. Use of this specification or any other specification shall be according to the Contract Documents. ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.PROV 920 November 2016 CONSTRUCTION SPECIFICATION FOR DECK JOINT ASSEMBLIES, PREFORMED SEALS, JOINT FILLERS, JOINT SEALS, JOINT SEALING COMPOUNDS,

More information

Special Provision No. 599S22 March 2001

Special Provision No. 599S22 March 2001 RETAINED SOIL SYSTEM, TRUE ABUTMENT - Item No. RETAINED SOIL SYSTEM, FALSE ABUTMENT - Item No. RETAINED SOIL SYSTEM, WALL/SLOPE, HIGH RETAINED SOIL SYSTEM, WALL/SLOPE, MEDIUM RETAINED SOIL SYSTEM, WALL/SLOPE,

More information

CONSTRUCTION SPECIFICATION FOR NOISE BARRIER SYSTEMS

CONSTRUCTION SPECIFICATION FOR NOISE BARRIER SYSTEMS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 760 NOVEMBER 2014 CONSTRUCTION SPECIFICATION FOR NOISE BARRIER SYSTEMS TABLE OF CONTENTS 760.01 SCOPE 760.02 REFERENCES 760.03 DEFINITIONS 760.04 DESIGN

More information

MATERIAL SPECIFICATION FOR CONCRETE - MATERIALS AND PRODUCTION

MATERIAL SPECIFICATION FOR CONCRETE - MATERIALS AND PRODUCTION ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.PROV 1350 NOVEMBER 2014 MATERIAL SPECIFICATION FOR CONCRETE - MATERIALS AND PRODUCTION TABLE OF CONTENTS 1350.01 SCOPE 1350.02 REFERENCES 1350.03 DEFINITIONS

More information

TABLE OF CONTENTS. Appendices are not a mandatory part of this specification unless invoked by the Owner.

TABLE OF CONTENTS. Appendices are not a mandatory part of this specification unless invoked by the Owner. ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 920 NOVEMBER 2005 CONSTRUCTION SPECIFICATION FOR DECK JOINT ASSEMBLIES, PREFORMED SEALS, JOINT FILLERS, JOINT SEALS, JOINT SEALING COMPOUNDS, AND WATERSTOPS

More information

SPECIFICATIONS FOR BRIDGE CONSTRUCTION SECTION 5 REINFORCING STEEL. 5.1 General Certification Fabrication...

SPECIFICATIONS FOR BRIDGE CONSTRUCTION SECTION 5 REINFORCING STEEL. 5.1 General Certification Fabrication... SPECIFICATIONS FOR BRIDGE CONSTRUCTION SECTION 5 REINFORCING STEEL TABLE OF CONTENTS 5.1 General...5-1 5.2 Certification...5-1 5.3 Fabrication...5-1 5.4 Handling and Storage...5-1 5.5 Field Repair of Epoxy

More information

CONSTRUCTION SPECIFICATION FOR CONCRETE CROSSWALK INDEX TS SCOPE...3

CONSTRUCTION SPECIFICATION FOR CONCRETE CROSSWALK INDEX TS SCOPE...3 CITY OF TORONTO TS 3.65 TRANSPORTATION SERVICES STANDARD CONSTRUCTION SPECIFICATIONS June 2001 CONSTRUCTION SPECIFICATION FOR CONCRETE CROSSWALK INDEX TS 3.65.01 SCOPE...3 TS 3.65.02 TS 3.65.03 REFERENCES...3

More information

This specification refers to the following standards, specifications, or publications:

This specification refers to the following standards, specifications, or publications: PRECAST CONCRETE SLAB REPAIR - Item No. Special Provision No 363S01 February 2013 Amendment to OPSS 363, April 2008 OPSS 363, Construction Specification for Repairing Rigid Pavement with Precast Concrete

More information

CONSTRUCTION SPECIFICATION FOR STEEL REINFORCEMENT FOR CONCRETE

CONSTRUCTION SPECIFICATION FOR STEEL REINFORCEMENT FOR CONCRETE ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 905 APRIL 2007 CONSTRUCTION SPECIFICATION FOR STEEL REINFORCEMENT FOR CONCRETE TABLE OF CONTENTS 905.01 SCOPE 905.02 REFERENCES 905.03 DEFINITIONS

More information

Special Provision No. 999S31 March 2018 REQUIREMENTS FOR PRECAST CONCRETE BRIDGE ELEMENTS (NON-PRESTRESSED AND PRESTRESSED)

Special Provision No. 999S31 March 2018 REQUIREMENTS FOR PRECAST CONCRETE BRIDGE ELEMENTS (NON-PRESTRESSED AND PRESTRESSED) PRECAST CONCRETE BRIDGE ELEMENTS, FABRICATION - Item No. PRECAST CONCRETE BRIDGE ELEMENTS, DELIVERY - Item No. PRECAST CONCRETE BRIDGE ELEMENTS, INSTALLATION - Item. No. Special Provision No. 999S31 March

More information

MATERIAL SPECIFICATION FOR BEARINGS - ELASTOMERIC PLAIN AND STEEL LAMINATED

MATERIAL SPECIFICATION FOR BEARINGS - ELASTOMERIC PLAIN AND STEEL LAMINATED ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 1202 NOVEMBER 2003 MATERIAL SPECIFICATION FOR BEARINGS - ELASTOMERIC PLAIN AND STEEL LAMINATED TABLE OF CONTENTS 1202.01 SCOPE 1202.02 REFERENCES 1202.03

More information

Special Provision No. 999S02 June 2017 CONSTRUCTION SPECIFICATION FOR GLASS FIBRE REINFORCED POLYMER (GFRP) REINFORCING BAR TABLE OF CONTENTS

Special Provision No. 999S02 June 2017 CONSTRUCTION SPECIFICATION FOR GLASS FIBRE REINFORCED POLYMER (GFRP) REINFORCING BAR TABLE OF CONTENTS GLASS FIBRE REINFORCED POLYMER REINFORCING BAR - Item No. Special Provision No. 999S02 June 2017 CONSTRUCTION SPECIFICATION FOR GLASS FIBRE REINFORCED POLYMER (GFRP) REINFORCING BAR 1.0 SCOPE 2.0 REFERENCES

More information

Special Provision No. 999S02 March 2018 REQUIREMENTS FOR GLASS FIBRE REINFORCED POLYMER (GFRP) REINFORCING BAR

Special Provision No. 999S02 March 2018 REQUIREMENTS FOR GLASS FIBRE REINFORCED POLYMER (GFRP) REINFORCING BAR GLASS FIBRE REINFORCED POLYMER REINFORCING BAR - Item No. Special Provision No. 999S02 March 2018 REQUIREMENTS FOR GLASS FIBRE REINFORCED POLYMER (GFRP) REINFORCING BAR 1.0 SCOPE This Special Provision

More information

CONSTRUCTION SPECIFICATION FOR CONCRETE SIDEWALK AND CONCRETE RAISED MEDIAN INDEX TS SCOPE...3 TS DEFINITIONS...3

CONSTRUCTION SPECIFICATION FOR CONCRETE SIDEWALK AND CONCRETE RAISED MEDIAN INDEX TS SCOPE...3 TS DEFINITIONS...3 CITY OF TORONTO TS 3.70 TRANSPORTATION SERVICES STANDARD CONSTRUCTION SPECIFICATIONS June 2001 CONSTRUCTION SPECIFICATION FOR CONCRETE SIDEWALK AND CONCRETE RAISED MEDIAN INDEX TS 3.70.01 SCOPE...3 TS

More information

CONSTRUCTION SPECIFICATION FOR CRACK REPAIR - CONCRETE

CONSTRUCTION SPECIFICATION FOR CRACK REPAIR - CONCRETE ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 932 NOVEMBER 2009 CONSTRUCTION SPECIFICATION FOR CRACK REPAIR - CONCRETE TABLE OF CONTENTS 932.01 SCOPE 932.02 REFERENCES 932.03 DEFINITIONS 932.04

More information

MATERIAL SPECIFICATION FOR DECK JOINT ASSEMBLIES

MATERIAL SPECIFICATION FOR DECK JOINT ASSEMBLIES ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.PROV 1210 NOVEMBER 2014 MATERIAL SPECIFICATION FOR DECK JOINT ASSEMBLIES TABLE OF CONTENTS 1210.01 SCOPE 1210.02 REFERENCES 1210.03 DEFINITIONS 1210.04

More information

CONSTRUCTION SPECIFICATION FOR STEEL REINFORCEMENT FOR CONCRETE

CONSTRUCTION SPECIFICATION FOR STEEL REINFORCEMENT FOR CONCRETE ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 905 MAY 1994 CONSTRUCTION SPECIFICATION FOR STEEL REINFORCEMENT FOR CONCRETE 905.01 SCOPE 905.02 REFERENCES 905.03 DEFINITIONS TABLE OF CONTENTS 905.04

More information

CONSTRUCTION SPECIFICATION FOR STRUCTURAL WOOD SYSTEMS

CONSTRUCTION SPECIFICATION FOR STRUCTURAL WOOD SYSTEMS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 907 NOVEMBER 2006 CONSTRUCTION SPECIFICATION FOR STRUCTURAL WOOD SYSTEMS TABLE OF CONTENTS 907.01 SCOPE 907.02 REFERENCES 907.03 DEFINITIONS 907.04

More information

CONSTRUCTION SPECIFICATION FOR PRESTRESSED CONCRETE - PRECAST GIRDERS

CONSTRUCTION SPECIFICATION FOR PRESTRESSED CONCRETE - PRECAST GIRDERS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.PROV 909 November 2016 CONSTRUCTION SPECIFICATION FOR PRESTRESSED CONCRETE - PRECAST GIRDERS TABLE OF CONTENTS 909.01 SCOPE 909.02 REFERENCES 909.03

More information

SPECIFICATIONS FOR INSTALLATION OF PRECAST PRESTRESSED CONCRETE DECK PANELS

SPECIFICATIONS FOR INSTALLATION OF PRECAST PRESTRESSED CONCRETE DECK PANELS SPECIFICATIONS FOR INSTALLATION OF PRECAST PRESTRESSED CONCRETE DECK PANELS 1.0 DESCRIPTION The Work shall consist of:.1 Transportation, unloading, erection and grouting of precast prestressed concrete

More information

MATERIAL SPECIFICATION FOR SPUN CONCRETE POLES

MATERIAL SPECIFICATION FOR SPUN CONCRETE POLES ONTARIO PROVINCIAL STANDARD SPECIFICATION OPSS.MUNI 2421 NOVEMBER 2017 (Formerly OPSS 2421, November 2012) Note: The MUNI implemented in November 2017 replaces OPSS 2421 COMMON, November 2012 with no technical

More information

Special Provision No. 599S22 March 2018 REQUIREMENTS FOR RETAINED SOIL SYSTEMS (RSS)

Special Provision No. 599S22 March 2018 REQUIREMENTS FOR RETAINED SOIL SYSTEMS (RSS) RETAINED SOIL SYSTEM, TRUE ABUTMENT - Item No. RETAINED SOIL SYSTEM, FALSE ABUTMENT - Item No. RETAINED SOIL SYSTEM, WALL/SLOPE, HIGH PERFORMANCE - Item No. RETAINED SOIL SYSTEM, WALL/SLOPE, MEDIUM PERFORMANCE

More information

MATERIAL SPECIFICATION FOR DECK JOINT ASSEMBLIES

MATERIAL SPECIFICATION FOR DECK JOINT ASSEMBLIES ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.MUNI 1210 NOVEMBER 2014 MATERIAL SPECIFICATION FOR DECK JOINT ASSEMBLIES TABLE OF CONTENTS 1210.01 SCOPE 1210.02 REFERENCES 1210.03 DEFINITIONS 1210.04

More information

Special Provision No. 904S11 July Section of OPSS 904, January 1995 is amended by the addition of the following:

Special Provision No. 904S11 July Section of OPSS 904, January 1995 is amended by the addition of the following: CONCRETE IN STRUCTURE - Item No. CONCRETE IN SUBSTRUCTURE - Item No. CONCRETE IN APPROACH SLAB - Item No. CONCRETE IN DECK - Item No. CONCRETE IN BARRIER WALLS - Item No. CONCRETE IN PARAPET WALLS - Item

More information

MATERIAL SPECIFICATION FOR DECK JOINT ASSEMBLIES

MATERIAL SPECIFICATION FOR DECK JOINT ASSEMBLIES ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 1210 NOVEMBER 2008 MATERIAL SPECIFICATION FOR DECK JOINT ASSEMBLIES TABLE OF CONTENTS 1210.01 SCOPE 1210.02 REFERENCES 1210.03 DEFINITIONS 1210.04

More information

CONSTRUCTION SPECIFICATION FOR TEMPORARY PROTECTION SYSTEMS

CONSTRUCTION SPECIFICATION FOR TEMPORARY PROTECTION SYSTEMS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.PROV 539 NOVEMBER 2014 CONSTRUCTION SPECIFICATION FOR TEMPORARY PROTECTION SYSTEMS TABLE OF CONTENTS 539.01 SCOPE 539.02 REFERENCES 539.03 DEFINITIONS

More information

CONSTRUCTION SPECIFICATION FOR STRUCTURE REHABILITATION - SHOTCRETE

CONSTRUCTION SPECIFICATION FOR STRUCTURE REHABILITATION - SHOTCRETE ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 931 NOVEMBER 2013 CONSTRUCTION SPECIFICATION FOR STRUCTURE REHABILITATION - SHOTCRETE TABLE OF CONTENTS 931.01 SCOPE 931.02 REFERENCES 931.03 DEFINITIONS

More information

MATERIAL SPECIFICATION FOR DECK JOINT ASSEMBLIES

MATERIAL SPECIFICATION FOR DECK JOINT ASSEMBLIES ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.PROV 1210 NOVEMBER 2016 1210.01 SCOPE 1210.02 REFERENCES 1210.03 DEFINITIONS MATERIAL SPECIFICATION FOR DECK JOINT ASSEMBLIES TABLE OF CONTENTS 1210.04

More information

Special Provision No. 904S13 May 2005

Special Provision No. 904S13 May 2005 HIGH PERFORMANCE CONCRETE IN SUBSTRUCTURE Item No. HIGH PERFORMANCE CONCRETE IN STRUCTURE Item No. HIGH PERFORMANCE CONCRETE IN APPROACH SLAB - Item No. HIGH PERFORMANCE CONCRETE IN DECK Item No. HIGH

More information

MATERIAL SPECIFICATION FOR PRECAST REINFORCED CONCRETE COMPONENTS FOR MAINTENANCE HOLES, CATCH BASINS, DITCH INLETS, AND VALVE CHAMBERS

MATERIAL SPECIFICATION FOR PRECAST REINFORCED CONCRETE COMPONENTS FOR MAINTENANCE HOLES, CATCH BASINS, DITCH INLETS, AND VALVE CHAMBERS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 1351 NOVEMBER 2009 MATERIAL SPECIFICATION FOR PRECAST REINFORCED CONCRETE COMPONENTS FOR MAINTENANCE HOLES, CATCH BASINS, DITCH INLETS, AND VALVE CHAMBERS

More information

MATERIAL SPECIFICATION FOR BEARINGS - ELASTOMERIC PLAIN AND STEEL LAMINATED

MATERIAL SPECIFICATION FOR BEARINGS - ELASTOMERIC PLAIN AND STEEL LAMINATED ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.PROV 1202 NOVEMBER 2016 MATERIAL SPECIFICATION FOR BEARINGS - ELASTOMERIC PLAIN AND STEEL LAMINATED TABLE OF CONTENTS 1202.01 SCOPE 1202.02 REFERENCES

More information

CONCRETE FORMWORK. .2 CSA , Supplement No.1 to CAN/CSA , Engineering Design in Wood. .4 CSA O151, Canadian Softwood Plywood.

CONCRETE FORMWORK. .2 CSA , Supplement No.1 to CAN/CSA , Engineering Design in Wood. .4 CSA O151, Canadian Softwood Plywood. CITY OF BRAMPTON LANDSCAPE SPECIFICATIONS SECTION 03100-1 PART 1 GENERAL 1.1 Related Work.1 All Division 1 Specification Sections.2 Section 02233 Granular Base.3 Section 02311 Site Grading.4 Section 03200

More information

CONSTRUCTION SPECIFICATION FOR REPAIRING RIGID PAVEMENT WITH PRECAST CONCRETE SLABS

CONSTRUCTION SPECIFICATION FOR REPAIRING RIGID PAVEMENT WITH PRECAST CONCRETE SLABS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.PROV 363 NOVEMBER 2014 CONSTRUCTION SPECIFICATION FOR REPAIRING RIGID PAVEMENT WITH PRECAST CONCRETE SLABS TABLE OF CONTENTS 363.01 SCOPE 363.02 REFERENCES

More information

MATERIAL SPECIFICATION FOR SECTIONAL STEEL HIGH MAST LIGHTING POLES

MATERIAL SPECIFICATION FOR SECTIONAL STEEL HIGH MAST LIGHTING POLES ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.PROV 2471 November 2016 MATERIAL SPECIFICATION FOR SECTIONAL STEEL HIGH MAST LIGHTING POLES TABLE OF CONTENTS 2471.01 SCOPE 2471.02 REFERENCES 2471.03

More information

CONSTRUCTION SPECIFICATION FOR STRUCTURAL WOOD SYSTEMS

CONSTRUCTION SPECIFICATION FOR STRUCTURAL WOOD SYSTEMS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 907 APRIL 2011 CONSTRUCTION SPECIFICATION FOR STRUCTURAL WOOD SYSTEMS TABLE OF CONTENTS 907.01 SCOPE 907.02 REFERENCES 907.03 DEFINITIONS 907.04 DESIGN

More information

SPECIFICATION FOR REINFORCED SOIL WALL

SPECIFICATION FOR REINFORCED SOIL WALL SPECIFICATION FOR REINFORCED SOIL WALL 1.0 EXTENT OF WORK The work shall consist of Reinforced Soil walls built in accordance with this specification and in conformity with the lines, levels and details

More information

DIVISION 4.3 CITY OF SARNIA CONCRETE SIDEWALKS, CURBS AND DRIVEWAYS STANDARDS 2018

DIVISION 4.3 CITY OF SARNIA CONCRETE SIDEWALKS, CURBS AND DRIVEWAYS STANDARDS 2018 DIVISION 4.3 CITY OF SARNIA CONCRETE SIDEWALKS, CURBS AND DRIVEWAYS STANDARDS 2018 1 CONCRETE MATERIALS, CONSTRUCTION METHODS AND TESTING PROCEDURES A. MATERIALS... 3 1. CONCRETE FOR SIDEWALK AND CURBS

More information

5 Concrete Placement

5 Concrete Placement 5 Concrete Placement Testing Entrained Air Slump Strength Water/Cementitious Ratio Mixing Placing Concrete Compressive Test Specimens Curing De-Tensioning Multiple Strand Release Single Strand Release

More information

CONSTRUCTION SPECIFICATION FOR STRUCTURAL STEEL

CONSTRUCTION SPECIFICATION FOR STRUCTURAL STEEL ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 906 FEBRUARY 1993 CONSTRUCTION SPECIFICATION FOR STRUCTURAL STEEL 906.01 SCOPE 906.02 REFERENCES 906.03 DEFINITIONS TABLE OF CONTENTS 906.04 SUBMISSION

More information

SECTION ARCHITECTURAL PRECAST CONCRETE. A. American Society for Testing and Materials (ASTM):

SECTION ARCHITECTURAL PRECAST CONCRETE. A. American Society for Testing and Materials (ASTM): SECTION 03450 ARCHITECTURAL PRECAST CONCRETE PART 1 GENERAL 1.01 SUMMARY A. Related Sections: 1. 03100 - Concrete Formwork 2. 03200 - Concrete Reinforcement 3. 03300 - Cast-in-Place Concrete 4. 03600 -

More information

SPECIAL SPECIFICATION 4491 Type CAC Concrete

SPECIAL SPECIFICATION 4491 Type CAC Concrete 2004 Specifications SPECIAL SPECIFICATION 4491 Type CAC Concrete 1. Description. Remove unsound concrete and replace with Type CAC, calcium aluminate concrete for ultra high early strength concrete repairs.

More information

CONCRETE REINFORCEMENT. 1. Supplementary Conditions, General Conditions, General Requirements, shall govern Work of this Section.

CONCRETE REINFORCEMENT. 1. Supplementary Conditions, General Conditions, General Requirements, shall govern Work of this Section. CITY OF BRAMPTON LANDSCAPE SPECIFICATIONS SECTION 03200-1 PART 1 GENERAL 1.1 General Requirements 1. Supplementary Conditions, General Conditions, General Requirements, shall govern Work of this Section.

More information

CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT

CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 616 NOVEMBER 2008 CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT TABLE OF CONTENTS 616.01 SCOPE 616.02 REFERENCES 616.03

More information

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF SECTIONAL STEEL HIGH MAST LIGHTING POLES

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF SECTIONAL STEEL HIGH MAST LIGHTING POLES ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 630 NOVEMBER 2011 CONSTRUCTION SPECIFICATION FOR INSTALLATION OF SECTIONAL STEEL HIGH MAST LIGHTING POLES TABLE OF CONTENTS 630.01 SCOPE 630.02 REFERENCES

More information

ALBERTA TRANSPORTATION SPECIFICATION FOR CONCRETE PATCHING MATERIALS

ALBERTA TRANSPORTATION SPECIFICATION FOR CONCRETE PATCHING MATERIALS ALBERTA TRANSPORTATION TECHNICAL STANDARDS BRANCH B391 JANUARY 2013 SPECIFICATION FOR CONCRETE PATCHING MATERIALS SCOPE - This specification contains approval procedures and requirements necessary for

More information

SPECIAL SPECIFICATION 4703 Repair Of Impact Damaged Prestressed Concrete Bridge Beams

SPECIAL SPECIFICATION 4703 Repair Of Impact Damaged Prestressed Concrete Bridge Beams 1993 Specifications CSJ 0162-01-080, etc. SPECIAL SPECIFICATION 4703 Repair Of Impact Damaged Prestressed Concrete Bridge Beams 1. Description. This Item shall govern for the repair of impact damaged prestressed

More information

1. Cast-in-place concrete is specified in Section

1. Cast-in-place concrete is specified in Section SECTION 03 38 00 PART 1 - GENERAL 1.01 DESCRIPTION A. This Section describes the requirements for furnishing and installing post-tensioned slabs, jacks, jacking and anchors at Parking Structure, and record

More information

CONSTRUCTION SPECIFICATION FOR FULL DEPTH REPAIR OF CONCRETE PAVEMENT OR CONCRETE BASE

CONSTRUCTION SPECIFICATION FOR FULL DEPTH REPAIR OF CONCRETE PAVEMENT OR CONCRETE BASE ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 360 NOVEMBER 2015 CONSTRUCTION SPECIFICATION FOR FULL DEPTH REPAIR OF CONCRETE PAVEMENT OR CONCRETE BASE TABLE OF CONTENTS 360.01 SCOPE 360.02 REFERENCES

More information

Special Provision No. 399S43 July This Special Provision deletes and replaces the following specifications:

Special Provision No. 399S43 July This Special Provision deletes and replaces the following specifications: FAST TRACK FULL DEPTH CONCRETE REPAIR Item No. FULL DEPTH CONCRETE REPAIR Item No. PARTIAL DEPTH CONCRETE REPAIR Item No. FAST TRACK PARTIAL DEPTH CONCRETE REPAIR Item No. Special Provision No. 399S43

More information

CONSTRUCTION SPECIFICATION FOR PERVIOUS CONCRETE PAVEMENT FOR LOW-VOLUME TRAFFIC APPLICATIONS

CONSTRUCTION SPECIFICATION FOR PERVIOUS CONCRETE PAVEMENT FOR LOW-VOLUME TRAFFIC APPLICATIONS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 356 NOVEMBER 2010 CONSTRUCTION SPECIFICATION FOR PERVIOUS CONCRETE PAVEMENT FOR LOW-VOLUME TRAFFIC APPLICATIONS TABLE OF CONTENTS 356.01 SCOPE 356.02

More information

REINFORCED CONCRETE MASONRY SECTION

REINFORCED CONCRETE MASONRY SECTION SECTION 04 22 02 - REINFORCED CONCRETE MASONRY PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions and Division 01 Specification

More information

CONSTRUCTION SPECIAL PROVISION FOR STRUCTURE REHABILITATION - CONCRETE PATCHES, REFACING AND OVERLAYS

CONSTRUCTION SPECIAL PROVISION FOR STRUCTURE REHABILITATION - CONCRETE PATCHES, REFACING AND OVERLAYS AMENDMENT TO OPSS 930, MAY 1994 Special Provision No. 109S50 July 2007 CONSTRUCTION SPECIAL PROVISION FOR STRUCTURE REHABILITATION - CONCRETE PATCHES, REFACING AND OVERLAYS OPSS 930, Construction Special

More information

Special Provision No. 915S03 December References, Materials, Construction, and Quality Assurance for Sign Support Structures

Special Provision No. 915S03 December References, Materials, Construction, and Quality Assurance for Sign Support Structures STEEL MONOTUBE OVERHEAD SIGN SUPPORT STRUCTURES - Item No. STEEL COLUMN BREAKAWAY SIGN SUPPORT STRUCTURES - Item No. STEEL COLUMN NON-BREAKAWAY SIGN SUPPORT STRUCTURES - Item No. CANTILEVER STATIC SIGN

More information

Construction Specification for Utility Adjustments

Construction Specification for Utility Adjustments Engineering & Construction Services Division Standard Specifications for Road Works TS 4.50 September 2017 for Utility Adjustments Table of Contents TS 4.50.01 SCOPE... 2 TS 4.50.02 REFERENCES... 2 TS

More information

GUIDE SPECIFICATIONS For STRUCTURAL PRECAST HOLLOW CORE SLABS SECTION 03410

GUIDE SPECIFICATIONS For STRUCTURAL PRECAST HOLLOW CORE SLABS SECTION 03410 GUIDE SPECIFICATIONS For STRUCTURAL PRECAST HOLLOW CORE SLABS SECTION 03410 Note to user: These guide specifications are provided by Mid- States Concrete Products as a service to you; they are NOT specific

More information

715 - PRESTRESSED CONCRETE MEMBERS SECTION 715 PRESTRESSED CONCRETE MEMBERS

715 - PRESTRESSED CONCRETE MEMBERS SECTION 715 PRESTRESSED CONCRETE MEMBERS SECTION 715 PRESTRESSED CONCRETE MEMBERS 715.1 DESCRIPTION Manufacture, cure, handle and install prestressed concrete bridge beams and panels to the dimensions specified on the Contract Documents. Manufacture

More information

CONSTRUCTION SPECIFICATION FOR GLASS FIBRE REINFORCED POLYMER REINFORCING BAR

CONSTRUCTION SPECIFICATION FOR GLASS FIBRE REINFORCED POLYMER REINFORCING BAR ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.MUNI 950 NOVEMBER 2017 CONSTRUCTION SPECIFICATION FOR GLASS FIBRE REINFORCED POLYMER REINFORCING BAR TABLE OF CONTENTS 950.01 SCOPE 950.02 REFERENCES

More information

1. Cast-in place structural concrete including footers, foundations, and other non-slab applications. 2. Formwork 3. Reinforcement

1. Cast-in place structural concrete including footers, foundations, and other non-slab applications. 2. Formwork 3. Reinforcement SECTION 03 31 00 - CAST-IN-PLACE STRUCTURAL CONCRETE PART 1 - GENERAL 1.1 SUMMARY A. Section includes: 1. Cast-in place structural concrete including footers, foundations, and other non-slab applications.

More information

***************************************************************************************************************

*************************************************************************************************************** 03450 ARCHITECTURAL PRECAST CONCRETE *************************************************************************************************************** SPECIFIER: CSI MasterFormat 2004 number 03 45 13 ***************************************************************************************************************

More information

CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT

CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT ONTARIO PROVINCIAL STANDARD SPECIFICATION OPSS.MUNI 616 APRIL 2018 CONSTRUCTION SPECIFICATION FOR FOOTINGS AND PADS FOR ELECTRICAL EQUIPMENT TABLE OF CONTENTS 616.01 SCOPE 616.02 REFERENCES 616.03 DEFINITIONS

More information

SPECIAL SPECIFICATION 4584 Segmental Concrete Bridge Unit

SPECIAL SPECIFICATION 4584 Segmental Concrete Bridge Unit 2004 Specifications CSJ: 0028-09-111 SPECIAL SPECIFICATION 4584 Segmental Concrete Bridge Unit 1. Description. Construct cast-in-place segmental concrete box girder superstructure according to the plans,

More information

MATERIAL SPECIFICATION FOR SECTIONAL STEEL HIGH MAST LIGHTING POLES

MATERIAL SPECIFICATION FOR SECTIONAL STEEL HIGH MAST LIGHTING POLES ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 2471 NOVEMBER 2008 MATERIAL SPECIFICATION FOR SECTIONAL STEEL HIGH MAST LIGHTING POLES TABLE OF CONTENTS 2471.01 SCOPE 2471.02 REFERENCES 2471.03 DEFINITIONS

More information

ALBERTA INFRASTRUCTURE AND TRANSPORTATION SPECIFICATION FOR CONCRETE PATCHING MATERIAL

ALBERTA INFRASTRUCTURE AND TRANSPORTATION SPECIFICATION FOR CONCRETE PATCHING MATERIAL ALBERTA INFRASTRUCTURE AND TRANSPORTATION TECHNICAL STANDARDS BRANCH B391- MAY 04 SPECIFICATION FOR CONCRETE PATCHING MATERIAL SCOPE - The approval procedures and requirements necessary for classifying

More information

ONTARIO PROVINCIAL STANDARD SPECIFICATION

ONTARIO PROVINCIAL STANDARD SPECIFICATION ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 539 NOVEMBER 2003 CONSTRUCTION SPECIFICATION FOR TEMPORARY PROTECTION SYSTEMS TABLE OF CONTENTS 539.01 SCOPE 539.02 REFERENCES 539.03 DEFINITIONS 539.04

More information

ALBERTA TRANSPORTATION TECHNICAL STANDARDS BRANCH B391 JULY 2017 SPECIFICATION FOR CONCRETE PATCHING MATERIALS

ALBERTA TRANSPORTATION TECHNICAL STANDARDS BRANCH B391 JULY 2017 SPECIFICATION FOR CONCRETE PATCHING MATERIALS ALBERTA TRANSPORTATION TECHNICAL STANDARDS BRANCH B391 JULY 2017 SPECIFICATION FOR CONCRETE PATCHING MATERIALS SCOPE - This specification contains approval procedures and requirements necessary for qualifying

More information

CONSTRUCTION SPECIFICATION FOR CONCRETE ROAD BASE

CONSTRUCTION SPECIFICATION FOR CONCRETE ROAD BASE CITY OF TORONTO STANDARD CONSTRUCTION SPECIFICATIONS FOR ROADS TS 3.40 November 2009 CONSTRUCTION SPECIFICATION FOR CONCRETE ROAD BASE INDEX TS 3.40.01 SCOPE... 3 TS 3.40.02 REFERENCES... 3 TS 3.40.03

More information

Ministry of Forests & Range

Ministry of Forests & Range Ministry of Forests & Range DRAWING SCHEDULE DRAWING No. / MODEL TYPE STD-EC-040-01 STD-EC-040-02 STD-EC-040-03 STD-EC-040-04 STD-EC-040-05 STD-EC-040-06 STD-EC-040-07 STD-EC-040-08 DESCRIPTION REV. DATE

More information

SECTION STRUCTURAL PRECAST CONCRETE

SECTION STRUCTURAL PRECAST CONCRETE SECTION 03500 STRUCTURAL PRECAST CONCRETE PART 1 GENERAL 1.01 SUMMARY A. Section Includes. This section covers Prestressed or Precast concrete member construction, including product design not shown on

More information

Special Provision No. 541S01 October OPSS 541, Construction Specifications for Chain Link Fence, is deleted and replaced with the following:

Special Provision No. 541S01 October OPSS 541, Construction Specifications for Chain Link Fence, is deleted and replaced with the following: CHAIN LINK FENCE - Item No. GATES - Item No. Special Provision No. 541S01 October 1998 AMENDMENT TO OPSS 541, DECEMBER 1990 OPSS 541, Construction Specifications for Chain Link Fence, is deleted and replaced

More information

Construction Specification for Concrete Curb and Concrete Curb and Gutter

Construction Specification for Concrete Curb and Concrete Curb and Gutter Engineering & Construction Services Division Standard Specifications for Road Works TS 3.50 September 2017 for Concrete Curb and Table of Contents TS 3.50.01 SCOPE... 3 TS 3.50.02 REFERENCES... 3 TS 3.50.03

More information

Special Provision No. 335S03 April 2015

Special Provision No. 335S03 April 2015 COLD IN-PLACE RECYCLED EXPANDED ASPHALT MIX Item No. Special Provision No. 335S03 April 2015 Amendment to OPSS 335, November 2009 OPSS 335, November 2009, Construction Specification for Cold In-Place Recycling

More information

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF UNDERPASS LUMINAIRES

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF UNDERPASS LUMINAIRES ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS 611 NOVEMBER 2013 CONSTRUCTION SPECIFICATION FOR INSTALLATION OF UNDERPASS LUMINAIRES TABLE OF CONTENTS 611.01 SCOPE 611.02 REFERENCES 611.03 DEFINITIONS

More information

CONSTRUCTION SPECIFICATION FOR REPAIRING CONCRETE PAVEMENT AND CONCRETE BASE

CONSTRUCTION SPECIFICATION FOR REPAIRING CONCRETE PAVEMENT AND CONCRETE BASE ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.PROV 366 April 2017 CONSTRUCTION SPECIFICATION FOR REPAIRING CONCRETE PAVEMENT AND CONCRETE BASE TABLE OF CONTENTS 366.01 SCOPE 366.02 REFERENCES 366.03

More information

EXPANDED POLYSTYRENE (EPS GEOFOAM) EMBANKMENT DIVISION 31 EARTHWORK

EXPANDED POLYSTYRENE (EPS GEOFOAM) EMBANKMENT DIVISION 31 EARTHWORK (Specifier Note: The purpose of this guide specification is to assist the specifier in correctly specifying AMVIC GEOFOAM products and execution. The specifier needs to edit the guide specifications to

More information

MATERIAL SPECIFICATION FOR STEEL REINFORCEMENT FOR CONCRETE

MATERIAL SPECIFICATION FOR STEEL REINFORCEMENT FOR CONCRETE ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.PROV 1440 NOVEMBER 2014 MATERIAL SPECIFICATION FOR STEEL REINFORCEMENT FOR CONCRETE TABLE OF CONTENTS 1440.01 SCOPE 1440.02 REFERENCES 1440.03 DEFINITIONS

More information

STRUCTURAL STEEL FRAMING

STRUCTURAL STEEL FRAMING SECTION 05 12 00 - STRUCTURAL STEEL FRAMING PART 1 - GENERAL 1.1 SUMMARY A. Section includes 1. Structural steel framing 2. Structural steel framing required for support and framing of rooftop mechanical

More information

MATERIAL SPECIFICATION FOR STEEL POLES, BASE MOUNTED

MATERIAL SPECIFICATION FOR STEEL POLES, BASE MOUNTED ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.MUNI 2423 APRIL 2017 MATERIAL SPECIFICATION FOR STEEL POLES, BASE MOUNTED TABLE OF CONTENTS 2423.01 SCOPE 2423.02 REFERENCES 2423.03 DEFINITIONS -

More information

Main Roads Standard Specification

Main Roads Standard Specification Main Roads MRS. Manufacture of Precast Concrete Culverts December 7 COPYRIGHT State of Queensland (Department of Main Roads) 7 Copyright protects this publication. Except for the purposes permitted by

More information

ALBERTA TRANSPORTATION SPECIFICATION FOR CONCRETE PATCHING MATERIAL

ALBERTA TRANSPORTATION SPECIFICATION FOR CONCRETE PATCHING MATERIAL ALBERTA TRANSPORTATION TECHNICAL STANDARDS BRANCH B391 DECEMBER 2008 SPECIFICATION FOR CONCRETE PATCHING MATERIAL SCOPE - The approval procedures and requirements necessary for classifying a product for

More information

UPRR INDUSTRIAL LEAD BRIDGE T-WALL RETAINING WALL SYSTEM 5.0 x 7.5 UNITS DESIGN UNIT 018 WORK PACKAGE 04

UPRR INDUSTRIAL LEAD BRIDGE T-WALL RETAINING WALL SYSTEM 5.0 x 7.5 UNITS DESIGN UNIT 018 WORK PACKAGE 04 UPRR INDUSTRIAL LEAD BRIDGE T-WALL RETAINING WALL SYSTEM 5.0 x 7.5 UNITS DESIGN UNIT 018 WORK PACKAGE 04 1. Description This work shall consist of the design, manufacture and construction of a T-WALL structure

More information

SPECIAL SPECIFICATION 4897 Repair Structural Concrete

SPECIAL SPECIFICATION 4897 Repair Structural Concrete 1993 Specifications CSJ 0331-04-045 SPECIAL SPECIFICATION 4897 Repair Structural Concrete 1. Description. This Item shall govern for the repair of delaminated, spalled and chipped areas of concrete foundations,

More information

COATING NEW STRUCTURAL STEEL SIGN SUPPORT STRUCTURES - Item No. Special Provision No. 911S09 November 2006

COATING NEW STRUCTURAL STEEL SIGN SUPPORT STRUCTURES - Item No. Special Provision No. 911S09 November 2006 COATING NEW STRUCTURAL STEEL SIGN SUPPORT STRUCTURES - Item No. Special Provision No. 911S09 November 2006 Amendment to OPSS 911, November 2004 for hot dip galvanizing and subsequent painting, where required,

More information

ITEM 435 ELASTOMERIC MATERIALS

ITEM 435 ELASTOMERIC MATERIALS ITEM 4 ELASTOMERIC MATERIALS 4.1. Description. This Item shall govern for the furnishing and installation of elastomeric materials in accordance with the details shown on the plans and the requirements