BIM METHODOLOGY AS A SUPPORT TO THE QUANTITY TAKE-OFF. Extended Abstract Master s Degree in Civil Engineering

Size: px
Start display at page:

Download "BIM METHODOLOGY AS A SUPPORT TO THE QUANTITY TAKE-OFF. Extended Abstract Master s Degree in Civil Engineering"

Transcription

1 BIM METHODOLOGY AS A SUPPORT TO THE QUANTITY TAKE-OFF Bernardo Ferreira e Silva Extended Abstract Master s Degree in Civil Engineering Supervisors Profª. Alcínia Zita de Almeida Sampaio Jury President: Supervisor: Member: Profª. Alcínia Zita de Almeida Sampaio October 2016

2 1. Introduction The Quantity Take-Off (QTO) is an essential process in project, because it allows to manage the costs involved in construction, supporting the investment analysis, as well as the decision-making and resources planning [1]. QTO can be applied through the construction process, where valid results can be obtained in the early stages that will assist the estimation of a preliminary cost. Before construction, it can be used as a planning tool with the construction activities. The BIM model guarantees the automatic update of results obtained in QTO after any change in the model [2]. During the works, it can be used to control the economic part of the construction. The traditional quantity take-off, through manual measurement of the different project elements, is based on 2D drawings, that can present inconsistencies and, therefore, might produce errors on the results obtained [3]. The level of automation in the industry has been a major concern over the last years with the academic community working hard to raise it [3]. Nowadays, BIM technology presents a valid alternative to the traditional process, allowing better results to the quantity takeoff process and raising the automation present in the project, while facilitate the information management in construction [4]. BIM is an automated tool based on a virtual model where information is automatically generated from it. BIM tools allow various uses, like visualization and clash detection, based on the automation and transfer of information using the virtual model. Using BIM to create bills of quantities will reduce the time spent on obtaining them and, therefore, will reduce costs on the project [5]. Despite these considerations, this feature is overlooked and BIM is mainly used to visualization. The utilization of BIM in QTO process is still target of reservations in the industry, due to some lack of information about the advantages provided in BIM utilization as a QTO tool. The strengths of using BIM in a QTO process are: Faster execution; QTO in design phase; Costs analysis through the project; Reliable Results; Competitive Advantage. But there are some problems identified, such as: Lack of technical standards; Insufficient interoperability between systems; Changes in the company, due to the necessity of collaborative work and new work methods; Additional work in obtaining quantities that can t be obtained automatically. This work aims to contribute to the knowledge of the BIM utilization in the QTO process, while demonstrating that it has more advantages and provide some solutions to the problems. Particularly, it compares both methods, traditional and BIM, used in the process, applied to a real structural project. 1

3 2. Case Study 2.1. Guidelines to BIM modelling The 3D model is the base of the QTO process with BIM. The modeling should follow certain guidelines, suitable for the objective of the model. In order to guarantee that the BIM model will provide reliable results, the following standards should be applied to the modeling process: It is important that all the objects and components of the model are modeled under the same circumstances and standards. Consistency of the model is necessary to ensure homogeneity on the results; Each object should be created using the appropriate tool, depending on which software is used. All the information relevant to the QTO should be entered on the tool, such as dimensions and materials. Some objects can have two function types: structural and non-structural. Is important to differentiate the layers by type to obtain bills of quantities classified in function types; Interoperability is a main concern when exchanging information between different software. The person responsible for the QTO need to know the limitations of the file format used and be able to overcome them, in order to maintain the results quality; Clash Detection is important to ensure the quality of the model, and the model should be adapted accordingly to that analysis. This tool is available in most of the software available Case Study Modelling In this research, a real case study was used: a project of a school in Faro, Portugal. The documents provided consists in 2D drawings of the structural foundations (Footings, Columns and Lintels) with rebar detailing. The modeling process was divided in phases, listed on the Table 1 Table 1 - Modeling phases Activity 1º Creation of levels and grids 2º Column insertion 3º Footing placement 4º Lintel definition 5º Footing rebar detailing 6º Model Checking 2

4 Before modeling, it s necessary to import, through Revit, the 2D drawing from AutoCAD with the elements that will be modeled, to be used as a basis for the BIM model. The first step is to create levels and grids that will support the 3D modeling. The levels are useful to limit the height of columns and footings, as it is possible to pin the top of the columns to the level and change the height of those columns automatically. The grids provide a place to attach columns and assist their placement. The Figure 1 shows a representation of the grids defined. Figure 1 - Grids Defined As it can be observed, the intersection between grids normally coincide in the center of the columns, to ease the placement. Next step is to create the different columns as a parametric object, duplicating a standard concrete column and adapting the dimensions. With the help of grids and the layout imported from AutoCAD, inserting the columns is an easy process, where the level that limits the column height is chosen in the software. For this work, all the columns have the same height (3 meters). The Figure 2 shows a representation of the columns on Revit. The process to create footings is analogous to the column process. Standard footing is duplicated and all the footings with different dimensions are created. To facilitate the placement of footings, the columns were created first so it is possible to use them as a reference. The software identifies the base of the column and place it correctly. Revit has the capability to facilitate the modeling and to place adjacent elements in a simple way. 3

5 Figure 2 - Columns representation The way to create and place lintels is, equally, based on the standard element duplication. Taking into account that all the lintels have a square section and do not exist, in Revit, a tool to create lintels, the beam tool was used due to the similarity between those elements. After creating the different types of section, the lintels were placed 1.25 meters above the top of the footings, to ensure that no lintel conflicted with the footings. For quantity take-off results, the columns pass through the lintel. The Figure 3 shows a 3D model of the foundations. Even using the columns as a reference to place the lintels, each individual placement was checked to guarantee that there weren t errors in the alignment. Figure 3 - Foundations 3D model To illustrate and study the rebar detailing in structural elements only the footings were considered. An add-on from Revit was used in this process, Reinforcement. This allows an automatic detailing, after providing measurements and information like steel grade. The add-on calculates the number of bars and the spacing between them, placing them inside the element. 4

6 This process needs to be executed on each case and a manual verification is needed to ensure the correct rebar bending and placement. The Figure 4 illustrates a footing rebar. Figure 4 - Footing rebar detailing To finish, is necessary to check the model to verify that all the elements are modeled with the correct dimensions and in the correct location, based on the drawings provided. This way, the results from the automatic quantity take-off are rigorous and represent the reality. This process guarantees the reliability of the model, and is the last step to finish the modelling process. The Figure 5 represents the final model of the foundations, with all the elements modelled. Figure 5 Foundations BIM Model The creation of the BIM model is simplified by the advanced modelling capabilities of Revit, however, some limitations were identified, particularly on the rebar detailing. Despite the 5

7 limitations, modelling in BIM brings unique advantages that compensate the initial difficulty of working with BIM. 3. Bill of quantities 3.1. Traditional method The traditional quantity take-off consists in measuring all the elements of the building manually, using the technical drawings. In this paper, the measurement regulations used were from Laboratório Nacional de Engenharia Civil, Medições em Construção de Edifícios [6]. The elements of the case study are simple, with common geometric shapes, so the volume formula is multiplying the three dimensions (length, width and height). By analyzing the foundation plan, the quantity of concrete needed to build the footings, columns and lintels was obtained. To obtain the steel quantities from the footing rebar, it is necessary to measure the length of the bar, taking into account the overlaps and hooks. This process takes a lot of time due to the necessity of measuring both rebar (superior and inferior) and guarantee the correct quantity take-off. The time taken and the quantities measured can be observed on the Table 2. Table 2 - Quantities and time taken Element Time spent (min) Quantities measured (m 3 ) Material Footings ,52 m 3 Columns 35 33,31 m 3 Concrete Lintels ,53 m 3 Footing Rebar kg Steel Total 210 Related to rebar modelling, due to the difficulties found in the BIM modelling process of the footing rebar, only this rebar was quantified. The process of modelling the columns and lintels would require a great amount of time and the results would be different between the traditional method and BIM BIM method Using a Revit functionality, called Schedules, a list of quantities is created based on the element type chosen and the properties needed, such as area, volume or material. It is possible to require a sum of quantities of the same property, represented on the list, that will facilitate the delivery of results like quantity of concrete needed to build the footings. The Table 3 represents a list of footings classified by type, showing the number of footings of each type, the material and the volume. This information is useful to support the planning of formwork. The process to obtain this table took 5 minutes. 6

8 Table 3 - Footings Schedule To obtain the other elements, the process is analogous. After the modelling phase, the quantity take-off is a simple process and the results obtain are trustworthy if the modelling was correctly executed. 4. Results Analysis The Table 4 presents the values obtained through both methods. The footings and columns returns the same result due to simplicity of the take-off in the traditional method. Table 4 - Quantity take-off (Traditional and BIM) Element Traditional method (m 3 ) BIM method (m 3 ) Difference (m 3 ) Footings 119,52 m3 119,52 m3 0,00 m3 Lintels 102,53 m3 103,11 m3 0,58 m3 Columns 33,31 m3 33,31 m3 0,00 m3 Rebar (Footings) 4239 kg 4199,03 kg 39,97 kg In the case of the Lintels, the difference is not significant. The justification to this result is that the project has some uncommon intersections between columns and lintels, where the lintel wraps the column and, per measurement rules, it is not accounted in the column, as is seen in the Figure 6. 7

9 Figure 6 - Intersection zone between column and lintel Regarding the footing rebar, the difference verified is due to the length of the bending, confirmed with the manual comparison between both methods. It is possible to correct this situation on Revit, but the increase in time spent doesn t compensate the difference of less than 1%, considering the steel wastes in rebar. Constraints and Limitations The production of a BIM model requires training to the modeler to acquire knowledge and experience to conceive proposals, manipulate information and obtain results. This training requires a great amount of time to adapt to a new methodology and the results aren t visible initially, a situation that can move away potential interested parties. The initial investment, that requires software licenses, new hardware and training is a constraint that will limit the successful implementation of BIM. The modelling process requires good practice and experience to return reliable results, and a model created to QTO may not be an accurate representation to 3D visualization. The rebar modelling in Revit is a difficult process and not user-friendly, although all the applications developed and incorporated in BIM software. The results obtained aren t reliable and the rebar modelling is a limitation to BIM and a point to improve to the software companies. 8

10 5. Conclusions This document presents an experimental study in order to evaluate the advantages of using BIM on the QTO process, and make a comparison between the traditional method and BIM. The results obtained in this research allows drawing the following general conclusions: 1) The results obtained from the BIM model are, in most cases, reliable and easily obtained, reducing the time spent on the QTO process. 2) The results obtained with BIM are as accurate as traditional method and aren t affected by the human error in the QTO process, if the modelling process was well executed. 3) The study of alternatives to the project is almost instant and automatic, allowing to evaluate a wide variety of options and choose the less expensive, reducing costs. 4) The rebar modelling needs further development by the software companies and the results returned should only be representative of the quantities required. 5) Even with the initial constraints, such as a high up-front investment and training required to the professionals, the utilization of BIM in the QTO process is beneficial, in place of the traditional method. References [1] Doloi, H.K., Understanding stakeholders perspective of cost estimation in project management, International Journal of Project Management, 29, pp , [2] Forgues, D. et al, Rethinking the Cost Estimating Process through 5D BIM: a Case Study, Construction Research Congress, ASCE, [3] Monteiro, A., Martins, J.P., A survey on modeling guidelines for quantity takeoff-oriented BIM-based design, Automation in Construction, 35, pp , [4] Parreira, J.P., Implementação BIM nos processos organizacionais em empresas de construção um caso de estudo, Dissertação Mestrado. Faculdade de Ciências e Tecnologia, Universidade Nova de Lisboa, [5] Shen, Z., Issa, R.R.A., Quantitative evaluation of the BIM-assisted construction detailed cost estimates, Journal of Information Technology in Construction (ITcon), Vol.15, pp , [6] Laboratório Nacional de Engenharia Civil, Medições em Construção de Edifícios, LNEC, Lisboa,

GA2016 XIX Generative Art Conference

GA2016 XIX Generative Art Conference THE INTRODUCTION OF BIM METHODOLOGY IN EDUCATION (Paper) Topic: Architecture, Advanced Teaching Author(s): Alcinia Zita Sampaio Portugal, University of Lisbon, Department of Civil Engineering and Architecture

More information

Building maintenance supported by BIM model

Building maintenance supported by BIM model Building maintenance supported by BIM model Diogo Gonçalves Simões Instituto Superior Técnico Technical University of Lisbon, Av. Rovisco Pais 1, 1049-001 Lisbon, Portugal Abstract Building maintenance

More information

Automated Clash Resolution of Steel Rebar in RC Beam Column Joints using BIM and GA

Automated Clash Resolution of Steel Rebar in RC Beam Column Joints using BIM and GA Automated Clash Resolution of Steel Rebar in RC Beam Column Joints using BIM and GA M. Mangal a, Q. Wang a and J.C.P. Cheng a a Department of Civil and Environmental Engineering, The Hong Kong University

More information

BIM model management in the design of structures

BIM model management in the design of structures BIM model management in the design of structures João Pedro Diniz Flor de Oliveira Instituto Superior Técnico University of Lisbon, Av. Rovisco Pais 1, 1049-001 Lisbon, Portugal ABSTRACT Building Information

More information

VIRTUAL REALITY TECHNOLOGY TO REPRESENT CONSTRUCTION ACTIVITIES

VIRTUAL REALITY TECHNOLOGY TO REPRESENT CONSTRUCTION ACTIVITIES 17 th International Conference on the Applications of Computer Science and Mathematics in Architecture and Civil Engineering K. Gürlebeck and C. Könke (eds.) Weimar, Germany, 12 14 July 2006 VIRTUAL REALITY

More information

Table of contents. EC3 Steel Design - Class 4 calculation of effective characteristics... 5

Table of contents. EC3 Steel Design - Class 4 calculation of effective characteristics... 5 What's New 2018 R2 Table of contents NEW OPTIONS & IMPROVEMENTS... 5 EC3 Steel Design - Class 4 calculation of effective characteristics... 5 Optimization of theoretical reinforcement according to EC2

More information

Lintel Tables Design Notes and Limitations

Lintel Tables Design Notes and Limitations LINTEL TABLES Lintel Tables Design Notes and Limitations 1. These tables apply to one and two family residential structures only that conform to the requirements of the 2006, 2009 or 2012 International

More information

Building Technology III New York City College of Technology. Course Day 13 Revit Day 05 (Project Day 2)

Building Technology III New York City College of Technology. Course Day 13 Revit Day 05 (Project Day 2) Building Technology III New York City College of Technology Course Day 13 Revit Day 05 (Project Day 2) The New Academic Building Concrete Foundations, & Slabs Professor Paul C. King, RA, AIA, ARA Prof.Paul.King@Gmail.com

More information

This article proposes an intriguing method for automated

This article proposes an intriguing method for automated CONCRETE: FORMWORK BIM and Concrete Formwork: The Paradigm Shift in Formwork Industry M.Ramesh Kannan & M.Helen Santhi Division of Structural Engineering, School of Mechanical & Building Sciences, VIT

More information

Cast-in-Place Concrete Industry

Cast-in-Place Concrete Industry Cast-in-Place Concrete Industry Adoption of Information Technology Chang-sun Chin Contents 1. Existing processes and business environment. 2. Available and suitable information technologies. 3. A framework

More information

Next Generation Solution for Building Analysis and Design

Next Generation Solution for Building Analysis and Design Next Generation Solution for Building Analysis and Design MIDAS FAMILY PROGRAMS Building midas Gen Integrated System for Building and General Structures midas DShop Auto-Drawing Module to generate Structural

More information

Introduction to Exactal and CostX

Introduction to Exactal and CostX Introduction to Exactal and CostX CostX Presentation Ken Leung Exactal Limited 3D BIM MODEL REVIEW 3D BIM MODEL REVIEW 3D BIM MODEL REVIEW 3D BIM MODEL REVIEW Review Questions How does the QS utilize the

More information

PENTABLOCK Technical Information 190mm Series

PENTABLOCK Technical Information 190mm Series PENTABLOCK Technical Information 190mm Series The PENTABLOCK Walling System was developed in consultation with masonry construction stakeholders with an aim of reducing labor time and material costs required

More information

DEVELOPMENT OF SCHEMATIC ESTIMATION SYS- TEM THROUGH LINKING QTO WITH COST DB

DEVELOPMENT OF SCHEMATIC ESTIMATION SYS- TEM THROUGH LINKING QTO WITH COST DB S. Chien, S. Choo, M. A. Schnabel, W. Nakapan, M. J. Kim, S. Roudavski (eds.), Living Systems and Micro-Utopias: Towards Continuous Designing, Proceedings of the 21st International Conference of the Association

More information

MEP21252 Revit Plug-in: Automated Hanger and Seismic Bracing Layout and Design for MEP Systems

MEP21252 Revit Plug-in: Automated Hanger and Seismic Bracing Layout and Design for MEP Systems MEP21252 Revit Plug-in: Automated Hanger and Seismic Bracing Layout and Design for MEP Systems Alan Espinoza MMC Contractors Jake Olsen, PE DEWALT Learning Objectives Learn how Revit can be used to efficiently

More information

Advance Concrete. PROFESSIONAL AND EASY-TO-USE 3D STRUCTURAL CONCRETE BIM SOFTWARE THAT AUTOMATES THE PRODUCTION OF DRAWINGS, BOMs AND NC FILES

Advance Concrete. PROFESSIONAL AND EASY-TO-USE 3D STRUCTURAL CONCRETE BIM SOFTWARE THAT AUTOMATES THE PRODUCTION OF DRAWINGS, BOMs AND NC FILES ADAGP Franck Hammoutène Architecte / photo : Luc Boegly Advance Concrete PROFESSIONAL AND EASY-TO-USE 3D STRUCTURAL CONCRETE BIM SOFTWARE THAT AUTOMATES THE PRODUCTION OF DRAWINGS, BOMs AND NC FILES www.graitec.com

More information

Construction management supported in a BIM model: Practical case study applied to an energy recovery center from solid waste

Construction management supported in a BIM model: Practical case study applied to an energy recovery center from solid waste Construction management supported in a BIM model: Practical case study applied to an energy recovery center from solid waste Daniel Santos da Silva DECivil, Instituto Superior Técnico, Universidade de

More information

Autodesk Revit Structure 2013 Fundamentals

Autodesk Revit Structure 2013 Fundamentals Autodesk Revit Structure 2013 Fundamentals SDC P U B L I C AT I O N S Schroff Development Corporation Better Textbooks. Lower Prices. www.sdcpublications.com Chapter 7 Adding Foundations In this chapter

More information

The Development of BIM Model-based Construction Project Performance Evaluation Mechanism

The Development of BIM Model-based Construction Project Performance Evaluation Mechanism Civil Engineering and Architecture 3(5): 128-135, 2015 DOI: 10.13189/cea.2015.030505 http://www.hrpub.org The Development of BIM Model-based Construction Project Performance Evaluation Mechanism Yi-Jao

More information

BIM Support for the Construction Project from a Suppliers POV

BIM Support for the Construction Project from a Suppliers POV CS10324 BIM Support for the Construction Project from a Suppliers POV Dr. Nils Krönert Hilti AG, Schaan, Liechtenstein Connor Christian Lead Designer, Kiewit Learning Objectives The possibilities of project

More information

Stepping into Variable Height Retaining Walls

Stepping into Variable Height Retaining Walls Stepping into Variable Height Retaining Walls Eric Cylwik Sundt Construction, Inc. CR 2499 - Mechanically-stabilized earth (MSE) walls are inherently complex shapes; smoothly curving in all 3 dimensions

More information

Dimensionamento Estrutural de uma Ponte Canal. Structural Design of a Canal Bridge. Francisco Barbosa Alves de Moura. Introduction

Dimensionamento Estrutural de uma Ponte Canal. Structural Design of a Canal Bridge. Francisco Barbosa Alves de Moura. Introduction Dimensionamento Estrutural de uma Ponte Canal Structural Design of a Canal Bridge Francisco Barbosa Alves de Moura IST, Technical University of Lisbon, Portugal Key Words: Structural Design, Canal Bridge,

More information

TABLE OF CONTENT. Equipment kit Description of the technology Installation of equipment Start of construction...

TABLE OF CONTENT. Equipment kit Description of the technology Installation of equipment Start of construction... TABLE OF CONTENT Equipment kit.... 6 Description of the technology.... 8 Installation of equipment.... 10 Start of construction.... 14 Erection of walls and partitions.... 17 Second floor printing....

More information

Simulation-based Construction and Logistics Planning using Building Information Modeling. BMW Welt, Munich

Simulation-based Construction and Logistics Planning using Building Information Modeling. BMW Welt, Munich Simulation-based Construction and Logistics Planning using Building Information Modeling Prof. Dr.-Ing. Markus König Ruhr-Universität Bochum Motivation Construction projects are getting more and more complex

More information

Rehabilitation of the Ramalho Ortigão Viaduct

Rehabilitation of the Ramalho Ortigão Viaduct Rehabilitation of the Ramalho Ortigão Viaduct Edited by Kelly M. Page The Ramalho Ortigão Viaduct is an overpass carrying a high volume of traffic. The viaduct goes over one of the main Lisbon, Portugal,

More information

Effective Application of Building Information Modeling in Construction

Effective Application of Building Information Modeling in Construction Volume-7, Issue-2, March-April- 2017 International Journal of Engineering and Management Research Page Number: 52-57 Effective Application of Building Information Modeling in Construction Akhilasree D

More information

CHAPTER 7 Building Information Modeling

CHAPTER 7 Building Information Modeling CHAPTER 7 Building Information Modeling Dr Nabil Elsawalhi Associate Professor of Construction Management 1 Information and Communication Technology/ Building Information Modeling New approaches to construction

More information

Alexis Pacella Structural Option Dr. Schneider Lexington II, Washington D.C. Technical Report #3 November 21,

Alexis Pacella Structural Option Dr. Schneider Lexington II, Washington D.C. Technical Report #3 November 21, 1 Executive Summary: Lateral System Analysis and Confirmation Design is an depth look at the lateral system of Lexington II and the loads of which it must carry. The structural system of Lexington II is

More information

INTERNATIONAL JOURNAL OF CIVIL AND STRUCTURAL ENGINEERING Volume 3, No 2, 2012

INTERNATIONAL JOURNAL OF CIVIL AND STRUCTURAL ENGINEERING Volume 3, No 2, 2012 INTERNATIONAL JOURNAL OF CIVIL AND STRUCTURAL ENGINEERING Volume 3, No 2, 2012 Copyright 2010 All rights reserved Integrated Publishing services Research article ISSN 0976 4399 Optimizing the use of swimmer

More information

Applying Object-oriented Analysis and Design to Digital Construction Logistics Planning from a Material Flow Perspective

Applying Object-oriented Analysis and Design to Digital Construction Logistics Planning from a Material Flow Perspective Applying Object-oriented Analysis and Design to Digital Construction Logistics Planning from a Material Flow Perspective Ningshuang Zeng a, Markus König a and Chao Mao b a Department of Civil and Environmental

More information

A Computational Framework for Estimating the Carbon Footprint of Construction

A Computational Framework for Estimating the Carbon Footprint of Construction The 31st International Symposium on Automation and Robotics in Construction and Mining (ISARC 2014) A Computational Framework for Estimating the Carbon Footprint of Construction Z.S. Moussavi Nadoushani

More information

Study on BIM Family Self-create for Steel Reinforcing Bar Detail Construction Design and Information Extraction

Study on BIM Family Self-create for Steel Reinforcing Bar Detail Construction Design and Information Extraction Study on BIM Family Self-create for Steel Reinforcing Bar Detail Construction Design and Information Extraction L.C. Lien a,b, P.C. Zhang b, S.B Chen c, Z.C. Liao b and Y.N. Liu b a Department of Civil

More information

Tips For Designing Constructable Concrete Buildings

Tips For Designing Constructable Concrete Buildings Tips For Designing Constructable Concrete Buildings by Clifford Schwinger, P.E. The Harman Group, Structural Engineers King of Prussia, Pa. Structural Engineers Association of Ohio Annual Conference Presentation

More information

Application of BIM on Documenting Construction Defects

Application of BIM on Documenting Construction Defects Application of BIM on Documenting Construction Defects Ying-Mei Cheng Abstract This study aims to establish a system prototype using Autodesk Revit API to code the add-ins which display 3D elements with

More information

Structural Design of a Building

Structural Design of a Building Structural Design of a Building Pedro Oliveira Gonçalves de Almeida Machado Extended Abstract October 2010 ABBREVEVIATIONS LIST LATIN CAPITAL LETTERS A Area Total cross-sectional área of a concrete section

More information

Thesis Proposal 12/13/06

Thesis Proposal 12/13/06 Photo courtesy of OTO Development, http://www.otodevelopment.com/ Dr. Memari Thesis Advisor Thesis Proposal 12/13/06 Executive Summary Structural System The in, is an eleven story hotel complex which reaches

More information

New York City College of Technology Division of Continuing Education

New York City College of Technology Division of Continuing Education New York City College of Technology Building Information Modeling with Revit 2014 Module 06 : FH.03 Firehouse Beams, Trusses, Structure & Slabs Professor Paul C. King, RA, AIA, ARA Prof.Paul.King@Gmail.com

More information

Sustainable Design Services

Sustainable Design Services Point. Advisory Sustainable Design Services Building Information Modeling (BIM) Step 1. Download.bimar App p on Google Play or scan the QR code. Step 2. Point device at cover to view it in 3D augmented

More information

Design and Estimation of Reinforced Building: A Case Study

Design and Estimation of Reinforced Building: A Case Study Design and Estimation of Reinforced Building: A Case Study Akshay Chaudhary 1, Payal Sachdeva 2, Maninderpal Singh 3 1, 2 (Assistant Professor, Department of Civil Engineering, CGC Technical Campus, Jhanjeri,

More information

Technical control activities in waterproofing systems of flat roofs

Technical control activities in waterproofing systems of flat roofs Technical control activities in waterproofing systems of flat roofs Fábio Luís Arruda Fagundes Abstract Flat roof systems have associated with them several anomalies related to their waterproofing system

More information

Simulation of a bridge deck construction using precast beams supported in Virtual Reality technology

Simulation of a bridge deck construction using precast beams supported in Virtual Reality technology Simulation of a bridge deck construction using precast beams supported in Virtual Reality technology Luís Filipe Duarte Viana Technical University of Lisbon IST. Dep. Civil Engineering and Architecture

More information

Autodesk BIM solutions for construction. Get started >

Autodesk BIM solutions for construction. Get started > Autodesk BIM solutions for construction Get started > Introduction Today s successful construction firms are adopting new practices that help them improve all areas of their business and create a competitive

More information

Rules of measurement in building construction

Rules of measurement in building construction Rules of measurement in building construction Proposed model for application in Portugal for secondary elements of stonework, carpentry and metalwork Rui Miguel Alves Mestre Extended Abstract October 2010

More information

Optimizing Construction Planning and Scheduling through Combined Virtual Prototyping Technology and Building Information Models

Optimizing Construction Planning and Scheduling through Combined Virtual Prototyping Technology and Building Information Models Optimizing Construction Planning and Scheduling through Combined Virtual Prototyping Technology and Building Information Models Neo Chan The Hong Kong Polytechnic University, Hong Kong (email: neo.kychan@polyu.edu.hk)

More information

2.7 LOGIX WALL CONSTRUCTION

2.7 LOGIX WALL CONSTRUCTION 2.7 LOGIX WALL CONSTRUCTION INTERLOCK The mechanism that holds successive courses of forms together. BARS The spaces between the lines. LINES The lines between the bars allow cuts to be easily made that

More information

USING 3 D LASER SCANS TO DEFINE PT LOCATIONS FOR TENANTS. By FLORIAN AALAMI. Authorized reprint from: December 2018 issue of the PTI Journal

USING 3 D LASER SCANS TO DEFINE PT LOCATIONS FOR TENANTS. By FLORIAN AALAMI. Authorized reprint from: December 2018 issue of the PTI Journal PTI Journal Technical Session Paper USING 3 D LASER SCANS TO DEFINE PT LOCATIONS FOR TENANTS By FLORIAN AALAMI Authorized reprint from: December 2018 issue of the PTI Journal Copyrighted 2018, Post Tensioning

More information

The Use of Bolted U-Link Swimmer Bars in the Reinforced Concrete Beams

The Use of Bolted U-Link Swimmer Bars in the Reinforced Concrete Beams IOSR Journal of Engineering (IOSRJEN) e-issn: 2250-3021, p-issn: 2278-8719 Vol. 3, Issue 10 (October. 2013), V5 PP 26-32 The Use of Bolted U-Link Swimmer Bars in the Reinforced Concrete Beams Moayyad M.

More information

Table of Contents. What's New in GRAITEC Advance BIM Designers 2019 R2 UPDATES... 4 IMPROVEMENTS & CORRECTIONS... 6

Table of Contents. What's New in GRAITEC Advance BIM Designers 2019 R2 UPDATES... 4 IMPROVEMENTS & CORRECTIONS... 6 What's New 2019 R2 Table of Contents UPDATES... 4 NEW VERSION OF THE ITALIAN CODE NTC 2018... 4 Modification of load coefficients for non-structural permanent loads... 4 New concrete class available...

More information

BIM and Concrete Formwork Repository

BIM and Concrete Formwork Repository BIM and Concrete Formwork Repository Pavan Meadati, Ph.D., LEED AP Southern Polytechnic State University Marietta, Georgia Javier Irizarry, Ph.D., PE. Georgia Institute of Technology Atlanta, Georgia Amin

More information

The Detailed Estimate

The Detailed Estimate The Detailed Estimate Stages of the Detailed Estimate 1. Quantity Take-off: The project work is measured in accordance with standard rules of measurement 2. Recap Quantities: The quantities taken off are

More information

TechniCom, Inc. 66 Mt. Prospect Avenue Clifton, NJ USA (973)

TechniCom, Inc. 66 Mt. Prospect Avenue Clifton, NJ USA (973) TechniCom, Inc. 66 Mt. Prospect Avenue Clifton, NJ 07013 USA (973) 470 9110 http://www.technicom.com staff@technicom.com think3's Product Configurator Powers Mass Customization June, 2003 Prepared by TechniCom,

More information

Introduction of a Japan Concrete Institute Guideline: Practical Guideline for Investigation, Repair and Strengthening of Cracked Concrete Structures

Introduction of a Japan Concrete Institute Guideline: Practical Guideline for Investigation, Repair and Strengthening of Cracked Concrete Structures Journal of Civil Engineering and Architecture 9 (2015) 213-224 doi: 10.17265/1934-7359/2015.02.010 D DAVID PUBLISHING Introduction of a Japan Concrete Institute Guideline: Practical Guideline for Investigation,

More information

Installation GUIDE STEEL DECKING SOLUTIONS FOR CONCRETE SLABS

Installation GUIDE STEEL DECKING SOLUTIONS FOR CONCRETE SLABS STEEL DECKING SOLUTIONS FOR CONCRETE SLABS Installation GUIDE Please take time to read this Truedek Installation Guide prior to site work commencing. It contains important delivery and installation information

More information

Labour Productivity Measurement method using 3D BIM of a Commercial Project

Labour Productivity Measurement method using 3D BIM of a Commercial Project Labour Productivity Measurement method using 3D BIM of a Commercial Project M Archana Menon 1, Prof. Shibi Varghese 2 1 Student, Dept. of Civil Engineering, Mar Athanasius College of Engineering Kothamangalam,

More information

THE CUPOLEX SOLUTION EXPANSIVE SOILS. www. cupolex.ca

THE CUPOLEX SOLUTION EXPANSIVE SOILS. www. cupolex.ca THE CUPOLEX SOLUTION EXPANSIVE SOILS www. cupolex.ca EXPANSIVE SOILS IDENTIFYING THE PROBLEM The problem of expansive soils is well known to engineers and builders. It affects construction sites throughout

More information

CIVIL ENGINEERING BENEFITS OF BIM. Helping Civil Engineers do more with BIM

CIVIL ENGINEERING BENEFITS OF BIM. Helping Civil Engineers do more with BIM CIVIL ENGINEERING BENEFITS OF BIM Helping Civil Engineers do more with BIM CIVIL ENGINEERING BENEFITS OF BIM WHAT S INSIDE: 1 BENEFITS Keep constructability top-of-mind Improve project margins Make better

More information

THE BIM-BASED INFORMATION INTEGRATION SPHERE FOR CONSTRUCTION PROJECTS

THE BIM-BASED INFORMATION INTEGRATION SPHERE FOR CONSTRUCTION PROJECTS THE BIM-BASED INFORMATION INTEGRATION SPHERE FOR CONSTRUCTION PROJECTS Chung-Wei Feng 1 *, Osama Mustaklem 1, and Yi-Jao Chen 2 1 Department of Civil Engineering, National Cheng Kung University, Tainan,

More information

International Research Journal of Engineering and Technology (IRJET) e-issn: Volume: 03 Issue: 01 Jan p-issn:

International Research Journal of Engineering and Technology (IRJET) e-issn: Volume: 03 Issue: 01 Jan p-issn: Contribution Of Building Information Modeling (BIM) To Solve Problems In Architecture, Engineering and Construction (AEC) Industry and Addressing Barriers to Implementation of BIM Vinay Kushwaha Assistant

More information

Office Building-G. Thesis Proposal. Carl Hubben. Structural Option. Advisor: Dr. Ali Memari

Office Building-G. Thesis Proposal. Carl Hubben. Structural Option. Advisor: Dr. Ali Memari Office Building-G Thesis Proposal Structural Option December 10, 2010 Table of Contents Executive Summary... 3 Introduction... 4 Gravity System...4 Lateral System:...6 Foundation System:...6 Problem Statement...

More information

03 CONCRETE TAKEOFF SUMMARY REPORT Takeoff and Items Cost Summary. Ryan Manocchio

03 CONCRETE TAKEOFF SUMMARY REPORT Takeoff and Items Cost Summary. Ryan Manocchio 03 CONCRETE TAKEOFF SUMMARY REPORT Takeoff and Items Cost Summary Ryan Manocchio rmanocchio@stackct.com Concrete Takeoff Summary Report The STACK To Go Team is capable of performing takeoff for concrete

More information

A PRELIMINARY BIM IMPLEMENTATION FRAMEWORK FOR CONSULTANT QUANTITY SURVEYOR FIRMS IN A DEVELOPING COUNTRY

A PRELIMINARY BIM IMPLEMENTATION FRAMEWORK FOR CONSULTANT QUANTITY SURVEYOR FIRMS IN A DEVELOPING COUNTRY A PRELIMINARY BIM IMPLEMENTATION FRAMEWORK FOR CONSULTANT QUANTITY SURVEYOR FIRMS IN A DEVELOPING COUNTRY Soon, Lam Tatt 1, Leong, Boon Tik 2 and Ang, Fuey Lin 3 and Hasnanywati Hassan 4 1 Associate Dean,

More information

EPS. Organization Chart. Civil Sector Head. Steel Structures Dept. Manager. Supervision Dept. Manager. Concrete structures Dept.

EPS. Organization Chart. Civil Sector Head. Steel Structures Dept. Manager. Supervision Dept. Manager. Concrete structures Dept. Civil Sector EPS Organization Chart Civil Sector Head Steel Structures Dept. Manager Concrete structures Dept. Manager Supervision Dept. Manager Head of Steel Structures Section Head of Concrete Structures

More information

BIM enhances structural analysis regardless of project size. By Doug Fitzpatrick, P.E., LEED AP and Jeffrey Yoders

BIM enhances structural analysis regardless of project size. By Doug Fitzpatrick, P.E., LEED AP and Jeffrey Yoders BIM enhances structural analysis regardless of project size By Doug Fitzpatrick, P.E., LEED AP and Jeffrey Yoders MARCH 2013 BIM enhances structural analysis regardless of project size By Jeffrey Yoders

More information

Technical Report #2. Matthew R Peyton

Technical Report #2. Matthew R Peyton Technical Report #2 This Document is Technical Report #2 for 5th year senior thesis in the Architectural Engineering Departments at The Pennsylvania State University. This Report is to prepare a study

More information

CHAPTER 11 Bar Cutoff

CHAPTER 11 Bar Cutoff page 188 CHAPTER 11 11.1. Anchorage of Tension Bars by Hooks In the event that the desired tensile stress in a bar cannot be developed by bond alone, it is necessary to provide special anchorage at the

More information

P2Xe: compact hybrid panel bender. Perfect balance between space and consumption, productivity and flexibility. Within everybody s reach.

P2Xe: compact hybrid panel bender. Perfect balance between space and consumption, productivity and flexibility. Within everybody s reach. P2Xe: compact hybrid panel bender. Perfect balance between space and consumption, productivity and flexibility. Within everybody s reach. P2Xe: Perfect balance between space and consumption, productivity

More information

ON THE USE OF BUILDING INFORMATION MODELING IN INFRASTRUCTURE BRIDGES

ON THE USE OF BUILDING INFORMATION MODELING IN INFRASTRUCTURE BRIDGES ON THE USE OF BUILDING INFORMATION MODELING IN INFRASTRUCTURE BRIDGES Mohamed Marzouk, Associate Professor, mm_marzouk@yahoo.com Mohamed Hisham, Graduate Student, mohamed1984_h@hotmail.com Construction

More information

Fz LLC. Exclusive Distributor in the Middle East for CSI Software licensing, technical support and training solutions

Fz LLC. Exclusive Distributor in the Middle East for CSI Software licensing, technical support and training solutions Exclusive Distributor in the Middle East for CSI Software licensing, technical support and training solutions www.techiesoft.com For Sales: sales@techiesoft.com For Technical Support: support@techiesoft.com

More information

IMPACT

IMPACT www.strusoft.com Project Project Management Scheduling Erection Planning Erection Simulation Design Production AutoCAD - Revit Precast Cast/Bed Planning Resource Handling Design - Detailing Shop Drawings

More information

Replacement of Conventional Rebar With Non-Conventional Prefabricated Cage System in RC Column

Replacement of Conventional Rebar With Non-Conventional Prefabricated Cage System in RC Column SSRG Journal of Civil Engineering- (ICRTCETM-7) - Special Issue - April 7 Conference on Recent Trends in Civil Engineering, Technology and Management (ICRTCETM-7) Replacement of Conventional Rebar With

More information

Revit 2018 Architectural Command Reference

Revit 2018 Architectural Command Reference Daniel John Stine CSI, CDT Jeff Hanson Autodesk Revit 2018 Architectural Command Reference SDC P U B L I C AT I O N S Better Textbooks. Lower Prices. www.sdcpublications.com ACCESS CODE UNIQUE CODE INSIDE

More information

Technology Transforms Existing Building Into 21st Century Workspace

Technology Transforms Existing Building Into 21st Century Workspace Project Overview Technology Transforms Existing Building Into 21st Century Workspace The Northwestern Mutual - Van Buren Office Building project included the complete remodel of a seven-story, 162,087-square-foot

More information

TUTORIALS. BIM Workflow in Advance Design

TUTORIALS. BIM Workflow in Advance Design TUTORIALS BIM Workflow in Advance Design About GRAITEC Tutorials GRAITEC technology evolution is driven by years of practical experience and combined with user feedback to provide the most intelligent

More information

Estimating Process Agenda

Estimating Process Agenda Estimating Process Agenda Definition of estimating What is estimating in construction? Cost variable in construction Types of estimates Conceptual estimate Detailed estimate Avoiding Errors in Estimates

More information

Torsion in tridimensional composite truss bridge decks

Torsion in tridimensional composite truss bridge decks Torsion in tridimensional composite truss bridge decks André B. Almeida Instituto Superior Técnico Technical University of Lisbon Lisbon, Portugal e-mail: branco.almeida.a@gmail.com Abstract Torsion stiffness

More information

EBOOK BIM ASSESSMENT GUIDE TAKE THE FIRST STEP TOWARDS CRAFTING A BIM IMPLEMENTATION PLAN

EBOOK BIM ASSESSMENT GUIDE TAKE THE FIRST STEP TOWARDS CRAFTING A BIM IMPLEMENTATION PLAN EBOOK BIM ASSESSMENT GUIDE TAKE THE FIRST STEP TOWARDS CRAFTING A BIM IMPLEMENTATION PLAN Better understand your current conditions and business objectives THE IMPLEMENTATION OF BIM FOR INFRASTRUCTURE

More information

RESILIENCE OF WATER SUPPLY SYSTEMS CASE STUDY OF QUINTA DO LAGO

RESILIENCE OF WATER SUPPLY SYSTEMS CASE STUDY OF QUINTA DO LAGO 41 st IAHS WORLD CONGRESS Sustainability and Innovation for the Future 13-16 th September 2016 Albufeira, Algarve, Portugal RESILIENCE OF WATER SUPPLY SYSTEMS CASE STUDY OF QUINTA DO LAGO João Caetano

More information

PROJECT NAME. Duke University. Architect (Specify Design Vs. AOR If Multiple) Construction Manager. Civil Engineer. Structural Engineer

PROJECT NAME. Duke University. Architect (Specify Design Vs. AOR If Multiple) Construction Manager. Civil Engineer. Structural Engineer PROJECT NAME By signature below, this Execution Plan is herewith adopted and incorporated into the Agreement, dated, for Professional Design Services between and Duke University. Duke University Architect

More information

Application of Building Information Modeling Tool for Building Project

Application of Building Information Modeling Tool for Building Project Application of Building Information Modeling Tool for Building Project Amol A. Metkari 1, Dr. A. C. Attar 2 1 PG Student, Department of Civil Engineering, Rajarambapu Institute of Technology, Sangli-415

More information

THE ORIGINAL solid, pinned retaining wall systems

THE ORIGINAL solid, pinned retaining wall systems www.versa-lok.com THE ORIGINAL solid, pinned retaining wall systems Tiered walls, integrated stairs, freestanding walls and columns are all possible with VERSA-LOK Weathered Mosaic. No matter how challenging

More information

BIM Execution Plan. Copyright 2009 Rights Reserved - The Trustees of Indiana University and SHP

BIM Execution Plan. Copyright 2009 Rights Reserved - The Trustees of Indiana University and SHP BIM Execution Plan Copyright 2009 Rights Reserved - The Trustees of Indiana University and SHP By signature below, this BIM Execution Plan is herewith adopted and incorporated into the Agreement, dated,

More information

Topology Optimization of Reinforced Concrete Plane Frames

Topology Optimization of Reinforced Concrete Plane Frames Topology Optimization of Reinforced Concrete Plane Frames Moacir Kripka 1, Juliana Triches Boscardin 2, Sauro Dias Casteli 3 Abstract The definition of the number of columns, as well as their positions

More information

GEOGRID CONNECTION DETAIL OLYMPIA RADIUS UNIT

GEOGRID CONNECTION DETAIL OLYMPIA RADIUS UNIT PLACE TWO STANDARD CONNECTORS IN EACH UNIT AS SHOWN (VERTICAL ORIENTATION) INSERT TWO CONNECTORS PER HORIZONTALLY ORIENTED BLOCK; INSERT ONE CONNECTOR PER VERTICALLY ORIENTED BLOCK SHIM BETWEEN BLOCK COURSES

More information

TEACHING BUILDING INFORMATION MODELLING IN AN ARCHITECTURAL SCHOOL

TEACHING BUILDING INFORMATION MODELLING IN AN ARCHITECTURAL SCHOOL F. Madeo and M. A. Schnabel (eds.), Across: Architectural Research through to Practice: 48 th International Conference of the Architectural Science Association 2014, pp. 421 432. 2014, The Architectural

More information

Cork Institute of Technology. Summer 2006 Structural Design & Detailing I (Time: 4 Hours)

Cork Institute of Technology. Summer 2006 Structural Design & Detailing I (Time: 4 Hours) Cork Institute of Technology Bachelor of Engineering (Honours) in Structural Engineering Stage 2 (NFQ Level 8) Summer 2006 Structural Design & Detailing I (Time: 4 Hours) Instructions: 1. The examination

More information

Elaboration of a New Packaging using the Geogebra Program Avoiding Losses and Reducing the Costs

Elaboration of a New Packaging using the Geogebra Program Avoiding Losses and Reducing the Costs Elaboration of a New Packaging using the Geogebra Program Avoiding Losses and Reducing the Costs Paula de Paula Rocha 1, Douglas Barbosa 2, Josiane Aparecida Cardoso de Souza 3 ¹Student of Industrial Engineering,

More information

APPLICATION FOR A BUILDING PERMIT (Retaining Wall/Garden Wall Construction Details)

APPLICATION FOR A BUILDING PERMIT (Retaining Wall/Garden Wall Construction Details) APPLICATION FOR A BUILDING PERMIT (Retaining Wall/Garden Wall Construction Details) City of San Jacinto 595 S. San Jacinto Ave San Jacinto CA 92583 951.487.7330 fax 951.654.9896 Must print legibly, submit

More information

INSTITUTO SUPERIOR TÉCNICO MESTRADO EM ARQUITETURA_2014/2015. Joana Alves Samúdio EXTENDED ABSTRACT

INSTITUTO SUPERIOR TÉCNICO MESTRADO EM ARQUITETURA_2014/2015. Joana Alves Samúdio EXTENDED ABSTRACT INSTITUTO SUPERIOR TÉCNICO MESTRADO EM ARQUITETURA_2014/2015 Joana Alves Samúdio EXTENDED ABSTRACT FAÇADE COVERING WITH PANELS REINFORCED WITH GLASS FIBER (GRC) The use of GRC prefabricated systems and

More information

Due Diligence Concerns When Choosing Between an Existing Structure or Greenfield Construction

Due Diligence Concerns When Choosing Between an Existing Structure or Greenfield Construction Due Diligence Concerns When Choosing Between an Existing Structure or Greenfield Construction O NEAL // DUE DILIGENCE CONCERNS WHEN CHOOSING BETWEEN AN EXISTING STRUCTURE OR GREENFIELD CONSTRUCTION //

More information

4D Model Analysis. Introduction

4D Model Analysis. Introduction 4D Model Analysis Introduction 4D models can be useful either as alternatives to CPM networks and bar charts, or as supplements to these schedules. People can more easily understand the project schedule

More information

Produkt og Procesmodeller (PPM) i byggeriet. Product and Process models in Construction. 6. Process Models

Produkt og Procesmodeller (PPM) i byggeriet. Product and Process models in Construction. 6. Process Models ICT Enhanced Buildings Potentials Produkt og Procesmodeller (PPM) i byggeriet. Product and Process models in Construction. 6. Process Models Cand. Scient. Bygningsinformatik. Semester 1, 2010. CONTENT

More information

Method Statement FM MS 09 SSCB

Method Statement FM MS 09 SSCB FMFM FM Method Statement FM MS 09 SSCB Fire Protection of structural steelwork with the FireMaster Blanket Structural Steel PFP system in accordance with the EU CPR English Rev 1: March 2018 FM CONTENTS

More information

The Art of Construction and The Design. Direct, rebar chair.

The Art of Construction and The Design. Direct, rebar chair. The Art of Construction and The Design Direct, rebar chair. Prefabricated element, made out of a thin steel rebar with plastic tipped legs in order to prevent corrosion of the support area between the

More information

SIMULATE CONSTRUCTION SCHEDULES USING BIM 4D APPLICATION TO TRACK PROGRESS

SIMULATE CONSTRUCTION SCHEDULES USING BIM 4D APPLICATION TO TRACK PROGRESS SIMULATE CONSTRUCTION SCHEDULES USING BIM 4D APPLICATION TO TRACK PROGRESS 1 SAGAR M MALSANE, 2 AMEY Z SHETH 1 Assistant Professor, National Institute of Construction Management & Research, India 2 phd

More information

Design Calculator for Quick Estimation of Concrete and Reinforcement in the Flat Plate Slab. Abstract

Design Calculator for Quick Estimation of Concrete and Reinforcement in the Flat Plate Slab. Abstract Session TC4-1 Design Calculator for Quick Estimation of Concrete and Reinforcement in the Flat Plate Slab Mr. Vardhaman V. Bora Dr. Mohammed E. Haque Department of Construction Science Texas A&M University,

More information

NEVI Light modular formwork

NEVI Light modular formwork NEVI Light modular formwork // Heavy duty, versatile and easily handled without a crane // Table of content Features Advantages Solutions Basic components 2 4 5 7 // Features Innovative range of panels

More information

Customizable and Integrated Configuration. Modeling Environment. Advanced Meshing Tools

Customizable and Integrated Configuration. Modeling Environment. Advanced Meshing Tools Model, analyze and design structures regardless of geometric complexity, material type, loading conditions, nonlinear effects, or design codes. Easy enough for simple projects, powerful enough for the

More information

Public Procurement Contract Management

Public Procurement Contract Management FLASH April 13, 2018 Public Procurement Contract Management The "Contract Manager" was one of the great innovations of the ninth amendment to the Public Contracts Code, and it is an important tool to promote

More information

BIM FOR CULTURAL HERITAGE

BIM FOR CULTURAL HERITAGE BIM FOR CULTURAL HERITAGE Matteo Del Giudice 1, Anna Osello 1 1 Department of Structural, Geotechnical and Building Engineering (DISEG) Politecnico di Torino, C.so Duca degli Abruzzi 24, 10100, Torino,

More information

Precast Concrete Hollow Core Slabs in Fire. By Tom Lennon, Principal Consultant, BRE

Precast Concrete Hollow Core Slabs in Fire. By Tom Lennon, Principal Consultant, BRE Precast Concrete Hollow Core Slabs in Fire By Tom Lennon, Principal Consultant, BRE Synopsis Following concerns expressed in the media in relation to the performance of hollow core slabs in fire two full-scale

More information