Supplemental Guide V-Feasibility Study Guidance Document CONTENTS

Size: px
Start display at page:

Download "Supplemental Guide V-Feasibility Study Guidance Document CONTENTS"

Transcription

1 Supplemental Guide V-Feasibility Study Guidance Document CONTENTS Introduction...1 Purpose...2 Scoring Method...2 Feasibility Study Matrix... 3 Feasibility Study Narrative... 3 Categories, Decision Criteria and Data Requirements...3 Examples...6 Introduction One requirement of source water protection planning is to develop a contingency plan and to assess whether a secondary source is available. If no secondary source is available, water systems are expected to include an examination and analysis of the technical and economic feasibility of each of the following options to provide continued safe and reliable public water service in the event the primary source of supply is detrimentally affected by contamination, release, spill or other event ( i). These options include: a) Constructing or establishing a secondary or backup intake which would draw water supplies from a substantially different location or water source; b) Constructing additional raw water storage capacity and/or treated water storage capacity, to provide at least two days of additional system storage based on the plant s maximum level of production experienced within the last year and demand throughout the distribution system; NOTE: Studies examining the alternative of additional raw and/or treated water must comply with existing design standards regulating treated water storage, including minimum storage capacity and adequate turn-over requirements ( a, ). Storing two days of additional treated water based on maximum level of production, may not allow adequate turn-over of the treated water during average production. Therefore, it is likely that all or a portion of the two days additional stored water will be raw water. 1

2 c) Creating or constructing an operational interconnection(s) between the public water supply utility (PWSU) with other plants on the PWSU or another PWSU to allow the utility to receive its water from a different source of supply during a period its primary water supply becomes unavailable or unreliable due to contamination, release, spill event or other circumstance; d) Any other alternative which is available to the PWSU to secure safe and reliable alternative supplies during a period it primary source of supply is unavailable or negatively impacted for an extended period. If one or more alternative set forth in items (a) through (d) above is determined to be technologically or economically feasible, the public water utility shall submit an analysis of the comparative costs, risks and benefits of implementing each of the described alternatives. Purpose This document provides the data requirements and guidance to score alternatives for a feasibility study. The feasibility study process is designed to identify the viable alternatives available to public water utilities. The process is developed with three goals in mind: 1. Eliminate any obvious non-feasible alternatives 2. Allow for the presentation and development of alternatives 3. Provide a relative ranking system to compare each alternative The analysis develops a numerical score, whereby the higher the score, the more feasible the alternative. The score is obtained by evaluating the alternatives across a series of relevant decision criteria and providing a relative numerical score for each. The decision criterion scores for each alternative are then added to provide a total feasibility score. After ranking, the selection of which alternatives should be considered for further analysis can be determined in a number of ways. At a minimum, one alternative should be selected regardless of the score, however, if there are multiple alternatives that are close in ranking, all feasible alternatives should be considered. Scoring Method The scoring methodology includes a numerical scale for each criterion. Scoring for the criteria occurs on a scale of 1 to 3 with least feasible being assigned a 1 and most feasible being assigned a 3. In addition there is a 0 score which represents a non-feasible score. 0- Not feasible. Data provided for this criterion indicates that the alternative cannot be accomplished. 2

3 1- Somewhat Feasible. Date provided for this criterion represents a significant barrier to successful implementation. Accomplishing this alternative is unlikely. 2- Feasible. Data provided for this criterion indicates that accomplishing this alternative would encounter a high level of complexity and difficulty, but is feasible. 3- Very Feasible. Data provided for this criterion indicates that accomplishing this alternative would encounter a typical level of complexity and difficultly. Feasibility Study Matrix Scoring should be based on best professional judgment as supported by the presentation of the required data. In order to document and calculate scores that are provided for each alternative, WVBPH has developed a Feasibility Study Matrix. This matrix is an Excel spreadsheet that performs calculations to weight scores for criteria, described below. Those alternatives with the highest final scores are considered the most feasible and may be considered in future engineering studies to develop an alternative source of water. Note: The Feasibility Study Matrix is a password protected Excel spreadsheet. The spreadsheet can be obtained from the WVDHHR SWAP Program website, To unlock the spreadsheet to enter scores, click on cell C4 on the Alternatives tab and type swap when prompted for a password. This will allow data entry into white and gray cells. The Feasibility Matrix tab will be automatically populated based on the scores provided for each alternative. Feasibility Study Narrative In addition to completing the Feasibility Study Matrix spreadsheet, water systems should prepare a brief narrative that identifies one or more feasible alternative, provides a summary of data used to make this determination, and briefly summarizes the results of the matrix. The data required to properly assess each category may extend beyond the space provide in the Feasibility Study Matrix. If so, these data should also be summarized in the narrative and attached to the source water protection plan. Categories, Decision Criteria and Data Requirements The approach to the feasibility study process identifies three major categories: 1. Economic 2. Technical 3. Environmental 3

4 Decision criteria for each category encompass the major feasibility issues for the alternatives. The decision criteria are shown in Table 1. Each criterion is described below and presents several data requirements that should be considered and scored on the Feasibility Study Matrix (Table 2). Table 1. Decision Criteria for Major Feasibility Categories Economic Criteria Technical Criteria Environmental Criteria Operation and Maintenance Costs Permitting Environmental Impacts Capital Cost Flexibility Aesthetic Impacts Resilience Stakeholder Issues Institutional Requirements Economic Criteria Economic criteria consider the impact of the cost of the alternative. The costs developed should be inclusive of all expenses. The data should be based on planning level estimates. The Economic Criteria score in the feasibility matrix is automatically weighted at 40% of the total score. A. Operation and Maintenance Costs Consider the additional estimated operations and maintenance (O&M) costs to operate the alternative. The cost should include not only the cost to operate when the alternative is in use but also the stand-by O&M costs when the alternative is not in use. The O&M costs should also include any additional costs from the existing treatment and distribution facilities incurred as a result of implementing the alternative. This criterion should be presented in normalized terms (cost per gallon per day) for a comparison with other alternatives. Provide the total current budget year cost to operate and maintain the public water system (current budget year). This will be used to compare O&M and capital costs for each alternative. Describe the major O&M cost requirements for the alternative Provide the incremental cost ($/gal) to operate and maintain the alternative Compare the incremental O&M cost to the current budgeted costs (%). This field will be automatically calculated on the Feasibility Study Matrix. B. Capital Cost Consider the cost to plan, design, permit and construct the alternative. Capital Costs also include any other capital requirements to the existing treatment and distribution facilities that may be required as a result of implementing the alternative. Capital cost should be annualized over the expected life of the improvements using an acceptable amortization factor. As with O&M costs, the annualized capital cost be presented on a normalized basis ($/gal) for comparison with other alternatives 4

5 Describe the capital improvements required to implement the alternative What is the annualized capital cost to implement the alternative, including land and easement costs ($/gal). (Note: In some instances interconnections require convenience fees to connect to neighboring systems. When considering interconnection as an alternative these convenience fees should be included.) Cost comparison of the alternatives annualized capital cost to the current budgeted costs of the PWSU (%).This field will be automatically calculated on the Feasibility Study Matrix. Technical Criteria Technical criteria evaluate the engineering, operations and management issues associated with the alternatives. The Technical Criteria score is automatically weighted at 40% of the total score. A. Permitting Consider the permits and permitting agencies that are required to implement the alternative. Permitting criteria consider the likelihood of successfully obtaining the permits, including studies, design reports, public hearings, etc. The criteria also consider the projected amount of time to obtain the permits. Provide a listing of the expected permits required and the permitting agencies involved in their approval. What is the timeframe for permit approval for each permit? Describe the major requirements in obtaining the permits (environmental impact studies, public hearings, etc.) What is the likelihood of successfully obtaining the permits? Does the implementation of the alternative require regulatory exceptions or variances? B. Flexibility The amount of operational flexibility or lack thereof the public water system can expect as a result of implementing the alternative. Will the alternative be needed on a regular basis or only used intermittently? How will implementing the alternative affect the water system s current method of treating and delivering potable water including meeting Safe Drinking Water Act regulations? (Note: In the case of treated water storage, will the alternative increase the likelihood of disinfection byproducts?) C. Resilience The degree to which the alternative is resistant to changes in demand. This considers not only daily and seasonal changes, but also expandability in response to long term demand due to customer and usage growth. Will the alternative provide any advantages or disadvantages to meeting seasonal changes in demand? How resistant will the alternative be to extreme weather conditions such as drought and flooding? Will the alternative be expandable to meet the growing needs of the service area? 5

6 D. Institutional Requirements Identify any agreements or other legal instruments with governmental entities, private institutions or other public water utilities required to implement the alternative (ex. mutual aid agreements). Are development/planning restrictions in place that can act as a barrier to the implementation of the alternative? Identify potential land acquisition and easements requirements. Environmental Criteria- Environmental criteria evaluate the environmental, aesthetic, and stakeholder issues associated with the alternatives. The Environmental Criteria score is automatically weighted at 20% of the total score. A. Environmental Impacts Identify how the alternative will affect local ecosystems. Identify any environmentally protected areas or habitats that might be impacted by the alternative (streams, wetlands, endangered species habitat, historic or archeological site, etc.) B. Aesthetic Impacts Addresses how the alternative impacts the residents and businesses in the surrounding area. Identify any visual or noise issues caused by the alternative that may affect local land uses? Identify any mitigation measures that will be required to address aesthetic impacts? C. Stakeholder Issues Identifies stakeholders and stakeholder values with respect to the alternatives. Identify the potential stakeholders affected by the alternative. Identify the potential issues with stakeholders for and against the alternative. Will stakeholder concerns represent a significant barrier to implementation (or assistance) of the alternative? Examples Economic Criteria An interconnect with an adjacent utility is expected to add $1.25/kgal to the O&M cost of the PWSU. This cost includes the purchase of water. This cost represents a 20% increase over the existing $/kgal cost of the utility but would only occur in an emergency situation when water is purchased. Since the increase would only occur on an intermittent basis it is not expected to greatly affect the cost of service and therefore is scored as a 3. The piping and pumping for the interconnect would have an annualized cost of $2.50/kgal, which is 40% over the existing public water utility operating cost. This would have to be paid regardless of usage and represent a 6

7 significant increase to the customers. However, with supplemental grant funding this cost may be reduced. Based on this information the score for the capital cost criterion would be a 1. Technical Criteria Constructing a raw water storage reservoir is required to provide raw water storage and a second intake. There is available land nearby but it is owned by a private party and is partially wetlands. Additional permits will be required to address the disruption of the wetland so the permit criterion would be scored as a 2. The reservoir will provide for some increased flexibility and improve the facility s ability to meet demands during periods of low source water availability. The reservoir will not negatively impact the operations of the treatment facility so both of these criteria are scored as 3. Although the land is adjacent to the treatment facilities it has some very restrictive land use requirements due to its wetland status. The public water utility will have to seek a variance from the local planning authority to construct the reservoir. There is a lengthy review and approval process with no guarantee of approval. Therefore this criterion is scored as a 1. Environmental Criteria A water storage tank will be constructed in a park that is vital to the community for recreation and tourism. Because preparing for tank construction will require removing a stand of trees thought to be habitat for endangered species and obtaining Endangered Species Act concurrence will restrict construction periods and species surveys, the environmental criterion would be scored a 2. The vital nature of the area and the fear of an unsightly tank in the area would be of concern to many residents and business in the area. However, it is expected that with decorative plantings and painting the visual impact of the tank could be minimized. Therefore the aesthetic criterion would be scored a 2. If there happens to be a very vocal community or business group that has historically been very effective preventing projects in the area the stakeholder criterion might be ranked a 1. 7

8 Table 2. Feasibility Study Matrix Economic Criteria Technical Criteria Environmental Criteria Alternative Strategy Description Operation and Maintenance Costs Capital Costs Total Total % Weighted Total Permitting Flexibility Resilience Institutional Requirements Total Total % Weighted Total Environmental Impacts Aesthetic Impacts Stakeholder Issues Total Total % Weighted Total Final Score Capital Cost Comments Backup Intake Interconnect Treated water storage Raw Water Storage Other Scoring: 0 Not feasible. Criterion cannot be met by this alternative and removes the alternative from further consideration. 1 Feasible but difficult. Criterion represents a significant barrier to successful implementation but does not eliminate it from consideration. 2 Feasible. Criterion can be met by the alternative. 3 Very Feasible. Criterion can be easily met by the alternative 8

THRASHER PROJECT No. 101-010-1046.805 Prepared By: Project Engineer THE THRASHER GROUP, INC. 600 White Oaks Boulevard Bridgeport, West Virginia 26330 www.thrashereng.com Phone: 304-624-4108 Fax: 304-624-7831

More information

Environmental Aspects, Impacts, and Risk ISO 14001:

Environmental Aspects, Impacts, and Risk ISO 14001: 1. PURPOSE: This document describes the procedure for identification of environmental risks, opportunities, aspects and impacts for the City of Dallas (City) Environmental Management System (EMS) and determining

More information

7 Management of Existing Supplies

7 Management of Existing Supplies 7 Management of Existing Supplies 7.1 Lake Belton to Lake Stillhouse Hollow Pipeline 7.1.1 Description of Option A pipeline is proposed to connect Lake Belton to Lake Stillhouse Hollow (Figure 7.1-1) to

More information

Project Name: St. Johns River/Taylor Creek Reservoir

Project Name: St. Johns River/Taylor Creek Reservoir Project Name: St. Johns River/Taylor Creek Reservoir Project Location: Osceola and Orange counties Project Number: 126 Project Type: Surface Water Description of project: The proposed St. Johns River/Taylor

More information

ALTERNATE WATER SOURCES

ALTERNATE WATER SOURCES ALTERNATE WATER SOURCES EPD Guidance Document August 2007 TABLE OF CONTENTS Part 1: Evaluating Alternate Water Sources 3 Criteria for Consideration 4 Financial 4 Environmental 4 Scoring potential water

More information

Model Riparian Buffer Ordinance.

Model Riparian Buffer Ordinance. Model Riparian Buffer Ordinance. This is a sample riparian buffer ordinance written as an amendment to an existing zoning ordinance. This ordinance complies with the state minimum standards for river corridor

More information

Planning Today For Water Tomorrow

Planning Today For Water Tomorrow Planning Today For Water Tomorrow Planning ahead is always smart, especially when it comes to something as important as drinking water. The Tampa Bay region expects to gain half a million people by 2030,

More information

Compensatory Mitigation Plan Requirements For Permittee Responsible Mitigation Projects St. Louis District, Corps of Engineers May 2010

Compensatory Mitigation Plan Requirements For Permittee Responsible Mitigation Projects St. Louis District, Corps of Engineers May 2010 Compensatory Mitigation Plan Requirements For Permittee Responsible Mitigation Projects St. Louis District, Corps of Engineers May 2010 The U.S. Army Corps of Engineers (Corps) and U.S. Environmental Protection

More information

City of Guelph Transfer of Review Procedures 7 March, 2017

City of Guelph Transfer of Review Procedures 7 March, 2017 Step 1-Determine where the project is located on the City of Guelph Vulnerability Map If the project is found not to be located in a vulnerability area with a vulnerability score of 8 or higher (See Attachment

More information

BURKE WATER STATION TREATMENT, PUMPING AND STORAGE CLASS ENVIRONMENTAL ASSESSMENT

BURKE WATER STATION TREATMENT, PUMPING AND STORAGE CLASS ENVIRONMENTAL ASSESSMENT Welcome to the City of Guelph BURKE WATER STATION TREATMENT, PUMPING AND STORAGE CLASS ENVIRONMENTAL ASSESSMENT PUBLIC INFORMATION CENTRE NO. 1 Wednesday, November 7, 2012 from 6:30 PM to 8:30 PM Please

More information

Santa Clara Valley Water District 2017 Water Supply Master Plan Planning Objectives

Santa Clara Valley Water District 2017 Water Supply Master Plan Planning Objectives Santa Clara Valley Water District 2017 Water Supply Master Plan Planning Objectives The purpose of the Water Supply Master Plan (Water Master Plan) is to present the District s strategy for ensuring a

More information

Water. For Our Future. Open House. Rural Potable Water. May 4, pm 9 pm. Bonanza Recreation Hall

Water. For Our Future. Open House. Rural Potable Water. May 4, pm 9 pm. Bonanza Recreation Hall Water For Our Future Rural Potable Water Open House May 4, 2017 7 pm 9 pm Bonanza Recreation Hall Purpose Studies Access to good quality potable water, in any community, encourages economic growth, enhances

More information

8.4 West Central Brazos Water Distribution System

8.4 West Central Brazos Water Distribution System 8.4 West Central Brazos Water Distribution System 8.4.1 Description of Option The West Central Brazos Water Distribution System (WCBWDS) is a relatively unused system that could potentially provide raw

More information

City of Wimberley. Public Hearing January 8, Proposed Central Wastewater Project Modifications

City of Wimberley. Public Hearing January 8, Proposed Central Wastewater Project Modifications City of Wimberley Public Hearing January 8, 2019 Proposed Central Wastewater Project Modifications One of the Purposes of this Hearing is to Discuss the Potential Impacts of the Project Changes and Alternatives

More information

TOWN OF RICHMOND PRELIMINARY ENGINEERING REPORT UPDATES FOR WATER STORAGE IMPROVEMENTS DECEMBER, 2013

TOWN OF RICHMOND PRELIMINARY ENGINEERING REPORT UPDATES FOR WATER STORAGE IMPROVEMENTS DECEMBER, 2013 TOWN OF RICHMOND PRELIMINARY ENGINEERING REPORT UPDATES FOR WATER STORAGE IMPROVEMENTS DECEMBER, 2013 Prepared by: Green Mountain Engineering 1438 South Brownell Road Williston, VT 05495 Phone: (802) 862-5590

More information

New Jersey Department of Environmental Protection Site Remediation Program RECEPTOR EVALUATION FORM INSTRUCTIONS

New Jersey Department of Environmental Protection Site Remediation Program RECEPTOR EVALUATION FORM INSTRUCTIONS New Jersey Department of Environmental Protection Site Remediation Program RECEPTOR EVALUATION FORM INSTRUCTIONS General instructions 1. Applicability. The purpose of this Receptor Evaluation Form is to

More information

A. POTABLE WATER SUB-ELEMENT GOAL I-1: STRIVE TO PROVIDE HIGH QUALITY POTABLE WATER TO CURRENT AND FUTURE RESIDENTS AND VISITORS.

A. POTABLE WATER SUB-ELEMENT GOAL I-1: STRIVE TO PROVIDE HIGH QUALITY POTABLE WATER TO CURRENT AND FUTURE RESIDENTS AND VISITORS. A. POTABLE WATER SUB-ELEMENT GOAL I-1: STRIVE TO PROVIDE HIGH QUALITY POTABLE WATER TO CURRENT AND FUTURE RESIDENTS AND VISITORS. Objective I-1.1 Water Supply Planning Walton County shall develop and maintain

More information

6.6 RESIDENTIALLY-SCALED, LAND-BASED WIND ENERGY CONVERSION FACILITIES

6.6 RESIDENTIALLY-SCALED, LAND-BASED WIND ENERGY CONVERSION FACILITIES 6.6 RESIDENTIALLY-SCALED, LAND-BASED WIND ENERGY CONVERSION FACILITIES 6.6.1 Purpose and Intent It is the express purpose of this Section to accommodate residentially-scaled, land-based wind energy conversion

More information

Drinking-water Assistance Programme

Drinking-water Assistance Programme Drinking-water Assistance Programme Criteria for Capital Assistance for Small Drinking-water Supplies Citation: Ministry of Health. 2006. Drinking-water Assistance Programme: Criteria for capital asisstance

More information

Infrastructure Element

Infrastructure Element Infrastructure Element 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 INFRASTRUCTURE ELEMENT GOAL 1: To provide for environmentally

More information

Figure 1 Demands on Lake Athens

Figure 1 Demands on Lake Athens Table 1 Projected Demands for Athens MWA and Lake Athens Water User Group Demand on Lake Athens 2010 2020 2030 2040 2050 2060 Comments City of Athens 2,326 2,832 3,431 4,111 5,003 6,108 Henderson Co. Irrigation

More information

Boone County Regional Sewer District User Rate Regulations Revised April 21, 2015

Boone County Regional Sewer District User Rate Regulations Revised April 21, 2015 Boone County Regional Sewer District User Rate Regulations Revised April 21, 2015 3.1 Title - This regulation including appendixes and tables shall be known, referred to and cited as the User Rate Regulation.

More information

TITLE 9. ENVIRONMENT STATE WATER CONTROL BOARD

TITLE 9. ENVIRONMENT STATE WATER CONTROL BOARD November 2, 2005 TITLE 9. ENVIRONMENT STATE WATER CONTROL BOARD Title of Regulation: 9 VAC 25-780. Local and Regional Water Supply Planning (adding 9 VAC 25-780-10 through 9 VAC 25-780-190). Statutory

More information

About the RRC. February

About the RRC. February Resource Recovery Centre (RRC) and Conveyance Pipe About the RRC Siting of the RRC Resource Recovery and Biosolids Management Odour, Noise, Traffic and Safety About the Residual Solids Pipe Spill Protection

More information

JOINT PUBLIC NOTICE Savannah District/State of Georgia

JOINT PUBLIC NOTICE Savannah District/State of Georgia UEPARTMENT OF THE ARMY SAVANNAH DISTRICT, CORPS OF ENGINEERS 100 W. OGLETHORPE AVENUE SAVANNAH, GEORGIA 31402-0889 Regulatory Branch 200003600 JOINT PUBLIC NOTICE Savannah District/State of Georgia The

More information

River Network s Drinking Water Guide: A Resource for Community Engagement

River Network s Drinking Water Guide: A Resource for Community Engagement River Network s Drinking Water Guide: A Resource for Community Engagement Presenter: Chi Ho Sham, Ph.D. Eastern Research Group, Lexington, MA AWWA Technical & Educational Council, Denver, CO Kansas City,

More information

Conn. Agencies Regs d-2 Preparation of plans and schedule for submission

Conn. Agencies Regs d-2 Preparation of plans and schedule for submission As of February 1, 2012 Conn. Agencies Regs. 25-32d-2 Preparation of plans and schedule for submission (a) Each water company supplying water to 1,000 or more persons or 250 or more consumers, and any other

More information

Implementing the New Ocean Plan Desalination Amendments

Implementing the New Ocean Plan Desalination Amendments Implementing the New Ocean Plan Desalination Amendments Claire Waggoner Statewide Policies and Planning Unit Chief Division of Water Quality State Water Resources Control Board Presentation Overview Background

More information

ENVIRONMENTAL ASSESSMENT. Steubenville Isolation Valve Replacement and Rehabilitation

ENVIRONMENTAL ASSESSMENT. Steubenville Isolation Valve Replacement and Rehabilitation ENVIRONMENTAL ASSESSMENT Project Identification Project: Applicant: Steubenville Isolation Valve Replacement and Rehabilitation Honorable James S. Mavromatis, Mayor City of Steubenville 115 South Third

More information

Incremental Recycled Water Program 2007 ADDENDUM TO PROGRAM ENVIRONMENTAL IMPACT REPORT

Incremental Recycled Water Program 2007 ADDENDUM TO PROGRAM ENVIRONMENTAL IMPACT REPORT SANTA ROSA SUBREGIONAL WATER REUSE SYSTEM Incremental Recycled Water Program 2007 ADDENDUM TO PROGRAM ENVIRONMENTAL IMPACT REPORT SCH #2002072046 March 2007 SANTA ROSA SUBREGIONAL WATER REUSE SYSTEM 2007

More information

NOTICE OF ADOPTION OF RULES OHIO ENVIRONMENTAL PROTECTION AGENCY. Rules Governing. Water Pollution Control Loan Fund

NOTICE OF ADOPTION OF RULES OHIO ENVIRONMENTAL PROTECTION AGENCY. Rules Governing. Water Pollution Control Loan Fund NOTICE OF ADOPTION OF RULES OHIO ENVIRONMENTAL PROTECTION AGENCY Rules Governing Water Pollution Control Loan Fund Notice is hereby given that the Director of the Ohio Environmental Protection Agency (Ohio

More information

SECTION TEMPORARY ENVIRONMENTAL CONTROLS

SECTION TEMPORARY ENVIRONMENTAL CONTROLS SECTION 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS PART 1 GENERAL 1.01 SECTION INCLUDES A. CONTRACTOR shall provide environmental controls consistent with regulatory requirements throughout the duration

More information

5.0 Water Supply Element

5.0 Water Supply Element 5.0 Water Supply Element The 2012 Wilsonville Water System Master Plan covers a 20-year planning period from 2010 to 2030. The following pages of this chapter summarize pertinent information contained

More information

Ordinances of the Plainview Water District Town of Oyster Bay, Nassau County, New York ARTICLE VII CONTROL OF BACKFLOW AND CROSS-CONNECTIONS

Ordinances of the Plainview Water District Town of Oyster Bay, Nassau County, New York ARTICLE VII CONTROL OF BACKFLOW AND CROSS-CONNECTIONS ARTICLE VII CONTROL OF BACKFLOW AND CROSS-CONNECTIONS Section 7.1 STATEMENT OF POLICY It is the policy of the Water District to protect the public water system by containing potential contamination within

More information

DRAFT FINDING OF NO SIGNIFICANT IMPACT. for. Tioga Sports Park

DRAFT FINDING OF NO SIGNIFICANT IMPACT. for. Tioga Sports Park DRAFT FINDING OF NO SIGNIFICANT IMPACT for Tioga Sports Park The U.S. Fish and Wildlife Service (USFWS) prepared an Environmental Assessment (EA) to analyze the potential effects of the proposal by the

More information

August 19, Subject: IBT Report for Dear Ms. Nimmer:

August 19, Subject: IBT Report for Dear Ms. Nimmer: August 19, 2016 Ms. Kim Nimmer Water Supply Planning Branch N.C. Division of Water Resources 1611 Mail Service Center Raleigh, North Carolina 27699-1611 Subject: IBT Report for 2015 Dear Ms. Nimmer: We

More information

Revision to the Schedule of Rates and Charges for the Furnishing of Water and Water Service

Revision to the Schedule of Rates and Charges for the Furnishing of Water and Water Service Revision to the Schedule of Rates and Charges for the Furnishing of Water and Water Service Amended by Resolution No. 889, 2018, effective September 15, 2018 Schedule for September 15, 2018 June 30, 2019

More information

APPLICATION FOR LANDUSE RESOURCE CONSENT

APPLICATION FOR LANDUSE RESOURCE CONSENT (Section 88 of the Resource Management Act 1991) Form 9 APPLICATION FOR LANDUSE RESOURCE CONSENT I,.. (full name) being the applicant residing at the below address, apply to the Waitaki District Council

More information

DEPARTMENT OF ENVIRONMENTAL PROTECTION BUREAU OF MINING AND RECLAMATION. Coal Refuse Disposal - Site Selection

DEPARTMENT OF ENVIRONMENTAL PROTECTION BUREAU OF MINING AND RECLAMATION. Coal Refuse Disposal - Site Selection DEPARTMENT OF ENVIRONMENTAL PROTECTION BUREAU OF MINING AND RECLAMATION DOCUMENT NUMBER: 563-2113-660 TITLE: Coal Refuse Disposal - Site Selection EFFECTIVE DATE: February 8, 1999 AUTHORITY: The Coal Refuse

More information

Matrix of Major Environmental Laws and Regulations Provisions Related to Components of an Indirect and Cumulative Impact Analysis 1 2

Matrix of Major Environmental Laws and Regulations Provisions Related to Components of an Indirect and Cumulative Impact Analysis 1 2 Matrix of Major Environmental Laws and Regulations Provisions Related to s of an Indirect and Cumulative Impact 1 2 Law or Definitions Indirect Impacts Cumulative Impacts Those effects caused by the action

More information

208 Plan Amendment Process for New Wastewater Treatment Facilities. Pima Association of Governments

208 Plan Amendment Process for New Wastewater Treatment Facilities. Pima Association of Governments 208 Plan Amendment Process for New Wastewater Treatment Facilities Pima Association of Governments The following packet includes the PAG 208 amendment process, a copy of ADEQ s 208 Amendment Checklist,

More information

SGMA and GSPs: Three Years of Planning 20 Years of Action

SGMA and GSPs: Three Years of Planning 20 Years of Action SGMA and GSPs: Three Years of Planning 20 Years of Action December 2016 PRESENTERS Enrique Lopezcalva Leslie Dumas, P.E. SGMA Timeline is Prescriptive GSA deadline: June 30, 2017 for high and medium priority

More information

Columbia River Treaty: Recommendations December 2013

Columbia River Treaty: Recommendations December 2013 L O CA L G O V E R N M E N TS CO M M I TTEE Columbia River Treaty: Recommendations The BC Columbia River Treaty Local Governments Committee (the Committee) has prepared these Recommendations in response

More information

APPLICANT INSTRUCTIONS

APPLICANT INSTRUCTIONS DOMESTIC WATER SUPPLY PERMIT APPLICANT INSTRUCTIONS I. BACKGROUND One of the more significant threats to health and safety is the purity and quality of the water consumed by the public. Widespread waterborne

More information

INSTRUCTIONS FOR FILING A WATER ALLOCATION PERMIT APPLICATION

INSTRUCTIONS FOR FILING A WATER ALLOCATION PERMIT APPLICATION STATE OF DELAWARE DEPARTMENT OF NATURAL RESOURCES & ENVIRONMENTAL CONTROL DIVISION OF WATER RESOURCES 89 KINGS HIGHWAY DOVER, DELAWARE 19901 INSTRUCTIONS FOR FILING A WATER ALLOCATION PERMIT APPLICATION

More information

Potable Reuse as an Alternative Water Supply. AWRA Conference Orlando, FL

Potable Reuse as an Alternative Water Supply. AWRA Conference Orlando, FL Potable Reuse as an Alternative Water Supply AWRA Conference Orlando, FL Who We Are New Port Richey Tampa St. Petersburg 100 percent groundwater pumped from 13 wellfields Tampa Bay Water History Integrated,

More information

Pajaro River Watershed Integrated Regional Water Management Plan Update Project Solicitation Form

Pajaro River Watershed Integrated Regional Water Management Plan Update Project Solicitation Form Pajaro River Watershed Integrated Regional Water Management Plan Update PROJECT OVERVIEW General Project Information Project Title: South County Recycled Water Pipeline - Short-Term CIP Implementation

More information

WATER SUPPLY ASSESSMENT AND RANKING OF WATERSHED DAMS IN GEORGIA

WATER SUPPLY ASSESSMENT AND RANKING OF WATERSHED DAMS IN GEORGIA WATER SUPPLY ASSESSMENT AND RANKING OF WATERSHED DAMS IN GEORGIA Charles D. Absher, P.E., CFM 1, and David M. Ashley, RLA 2 AUTHORS: 1 Senior Water Resources Engineer; and 2 Vice President, respectively,

More information

EXECUTIVE SUMMARY. The capital improvements costs through Year 2025 have been summarized as follows: RECOMMENDED IMPROVEMENTS (Ref.

EXECUTIVE SUMMARY. The capital improvements costs through Year 2025 have been summarized as follows: RECOMMENDED IMPROVEMENTS (Ref. EXECUTIVE SUMMARY This report evaluates the ability of the Dothan Water System to adequately meet the City s short range and future water supply, infrastructure and maintenance needs. The report evaluated

More information

A Guide for Ecosystem Based Adaptation Planning in Ontario

A Guide for Ecosystem Based Adaptation Planning in Ontario A Guide for Ecosystem Based Adaptation Planning in Ontario Al Douglas Ontario Centre for Climate Impacts and Adaptation Resources Adaptation Planning Next Steps for Northern Ontario Conservation Authorities

More information

CHAPTER 10 NATURAL GROUNDWATER AND AQUIFER RECHARGE ELEMENT

CHAPTER 10 NATURAL GROUNDWATER AND AQUIFER RECHARGE ELEMENT CHAPTER 10 NATURAL GROUNDWATER AND AQUIFER RECHARGE ELEMENT Page 1 of 7 G:\Comp\Adopted Comprehensive Plans\15. Cylce 16-2 and 16-3\Elements not changed\ Groundwater & Aquifer A. OVERVIEW CHAPTER 10 NATURAL

More information

DEPARTMENT OF THE ARMY U.S. ARMY CORPS OF ENGINEERS - MOBILE DISTRICT BIRMINGHAM FIELD OFFICE 218 SUMMIT PARKWAY, SUITE 222 HOMEWOOD, AL 35209

DEPARTMENT OF THE ARMY U.S. ARMY CORPS OF ENGINEERS - MOBILE DISTRICT BIRMINGHAM FIELD OFFICE 218 SUMMIT PARKWAY, SUITE 222 HOMEWOOD, AL 35209 DEPARTMENT OF THE ARMY U.S. ARMY CORPS OF ENGINEERS - MOBILE DISTRICT BIRMINGHAM FIELD OFFICE 218 SUMMIT PARKWAY, SUITE 222 HOMEWOOD, AL 35209 CESAM-RD-I-N December 7, 2012 PUBLIC NOTICE NO. SAM-2012-01506-LCB

More information

INFRASTRUCTURE ELEMENT SANITARY SEWER SUB-ELEMENT

INFRASTRUCTURE ELEMENT SANITARY SEWER SUB-ELEMENT INFRASTRUCTURE ELEMENT SANITARY SEWER SUB-ELEMENT GOALS, OBJECTIVES & POLICIES GOAL, OBJECTIVES & POLICIES GOAL SS. SANITARY SEWER PUBLIC SERVICE. It is the goal of the City of Casselberry to provide,

More information

4B.6 Desalination 4B Description of Option. Desalination of Lake Granbury Water for Johnson County Regional Plan.

4B.6 Desalination 4B Description of Option. Desalination of Lake Granbury Water for Johnson County Regional Plan. 4B.6 4B.6.1 Description of Options Water demands in Johnson County are increasing at a very significant rate, while the existing supply from the Surface Water and Treatment System (SWATS) water treatment

More information

Safe Water Depends on Us.

Safe Water Depends on Us. DRINKING WATER PROTECTION A Citizen s Guide to Getting Involved Safe Water Depends on Us. Learn What You Can Do. SAFE WATER FOR WEST VIRGINIA 1 WHERE DOES YOUR DRINKING WATER COME FROM? source water Source

More information

AGENDA ITEM SUMMARY February 21, 2017 City Council

AGENDA ITEM SUMMARY February 21, 2017 City Council Agenda Item 21 AGENDA ITEM SUMMARY February 21, 2017 City Council STAFF John Stokes, Natural Resources Director SUBJECT Resolution 2017-024 Directing the City Manager or His Designees to Meet with the

More information

Jordan River Basin. Planning for the Future. Salt Lake County Watershed Symposium (August 11, 2011) Todd Stonely Utah Division of Water Resources

Jordan River Basin. Planning for the Future. Salt Lake County Watershed Symposium (August 11, 2011) Todd Stonely Utah Division of Water Resources Jordan River Basin Planning for the Future Todd Stonely Utah Division of Water Resources Salt Lake County Watershed Symposium (August 11, 2011) 8/12/2011 Jordan River Basin Planning for the Future Slide

More information

CHAPTER 1 INTRODUCTION

CHAPTER 1 INTRODUCTION CHAPTER 1 INTRODUCTION The Comprehensive Environmental Response, The goal of the Superfund human health Compensation, and Liability Act of 1980, as evaluation process is to provide a framework for amended

More information

10:00 a.m. Public Hearing #1

10:00 a.m. Public Hearing #1 10:00 a.m. Public Hearing #1 Charlotte County Board Of County Commissioners Agenda Item Summary 1 DEPARTMENT MAKING REQUEST 2 MEETING DATE Utilities 7/22/2014 9:00:00 AM 3 REQUESTED MOTION/ACTION a)conduct

More information

Capital Facilities Element

Capital Facilities Element Capital Facilities Element Purpose The Growth Management Act requires cities to prepare a capital facilities element consisting of: 1. An inventory of current capital facilities owned by public entities,

More information

Guidelines for Preparing an Alternatives Analysis

Guidelines for Preparing an Alternatives Analysis Policy Number: Policy No. 2017-01 Title: Guidelines for Preparing an Alternatives Analysis Effective Date: September 7, 2017 Authority: Policy: Public Law 91-575, 84 Stat. 1509 et seq., Sections 3.1, 3.4(2),

More information

11. Prioritizing Farmlands for Future Protection

11. Prioritizing Farmlands for Future Protection 11. Prioritizing Farmlands for Future Protection Identification of Important Farmlands in Putnam County I n order to implement this Plan successfully, Putnam County decision-makers will have to take advantage

More information

our Water A Watershed and Aquifer Planning Model for Saskatchewan

our Water A Watershed and Aquifer Planning Model for Saskatchewan Protecting our Water A Watershed and Aquifer Planning Model for Saskatchewan Introduction Saskatchewan needs to ensure it has an adequate supply of quality water for the future. In 2002, the provincial

More information

Public Information Meeting July 25, 2018

Public Information Meeting July 25, 2018 Public Information Meeting July 25, 2018 Agenda Project Background Class EA Process The Problem Alternative Solutions Facilities Sites Scoring System Scoring Outcome Next Steps 2 Project Background EA

More information

DRAFT FOR CONSIDERATION AT THE NOVEMBER 1, 2007 MEETING OF THE HIGHLANDS COUNCIL

DRAFT FOR CONSIDERATION AT THE NOVEMBER 1, 2007 MEETING OF THE HIGHLANDS COUNCIL JON S. CORZINE Governor State of New Jersey Highlands Water Protection and Planning Council 100 North Road (Route 513) Chester, New Jersey 07930-2322 (908) 879-6737 (908) 879-4205 (fax) www.highlands.state.nj.us

More information

ENVIRONMENTAL ASSESSMENT For Choctaw Utilities, Inc. Water Plant Replacement Loan Number FS

ENVIRONMENTAL ASSESSMENT For Choctaw Utilities, Inc. Water Plant Replacement Loan Number FS ENVIRONMENTAL ASSESSMENT For Choctaw Utilities, Inc. Water Plant Replacement Loan Number FS391083-0002 Applicant: David Lohrer, President, Board of Directors Choctaw Utilities, Inc. 2005 Itawamba Trail

More information

The following words and terms shall have the following meanings unless the context indicates otherwise:

The following words and terms shall have the following meanings unless the context indicates otherwise: SUBCHAPTER 6. WATER SUPPLY MANAGEMENT ACT RULES 7:19-6.1 Scope and Authority (a) The Statewide Water Supply Master Plan represents the planning mechanism by which the State approaches its water needs.

More information

Additional Information Requirements for Wastewater Treatment Projects

Additional Information Requirements for Wastewater Treatment Projects Version 04-11-25 Page 1 of 6 Additional Information Requirements for Wastewater Treatment Projects Pursuant to Section 5(2) of the Environmental Impact Assessment Regulation of the Clean Environment Act,

More information

North Monterey County Drought Contingency Plan

North Monterey County Drought Contingency Plan North Monterey County Water Total Water Management Evaluating Options for a Reliable Water Future North Monterey County Drought Contingency Plan May 31, 2018 Meeting Topics Overview of Drought Contingency

More information

3 RELATED PLANS, AGREEMENTS, AND POLICIES

3 RELATED PLANS, AGREEMENTS, AND POLICIES 3 RELATED PLANS, AGREEMENTS, AND POLICIES The District s process of water delivery to its customers has been developed over many years in the context of various agreements, plans, and policies that address

More information

Division: Number: Category: Status: Issued: DDAGW WQ Water Quality Guidance Final December 2, 2010

Division: Number: Category: Status: Issued: DDAGW WQ Water Quality Guidance Final December 2, 2010 Guidance for Ground Water Rule Triggered Source Water Monitoring (TSWM) Plans and Options for Reducing Samples Division: Number: Category: Status: Issued: DDAGW WQ-17-001 Water Quality Guidance Final December

More information

Document 523 ALTERNATIVES ANALYSIS REPORT

Document 523 ALTERNATIVES ANALYSIS REPORT Document 523 ALTERNATIVES ANALYSIS REPORT CHAPTER: COUNTRY: Honduras COMMUNITY: Guaimaca PROJECT: Potable Water System for Colonna, Maraquito, and Aguacatillo PREPARED BY Names of report authors Submittal

More information

UWMP Standardized Tables. Salinas District Urban Water Management Plan Appendix H

UWMP Standardized Tables. Salinas District Urban Water Management Plan Appendix H UWMP Standardized Tables Salinas District 2015 Urban Water Management Plan Appendix H Table 2-1 Retail Only: Public Water Systems Public Water System Number Public Water System Name Number of Municipal

More information

San Francisco Public Utilities Commission Citizen s Advisory Committee, Wastewater Subcommittee June 14, Triple Bottom Line (TBL) Analysis

San Francisco Public Utilities Commission Citizen s Advisory Committee, Wastewater Subcommittee June 14, Triple Bottom Line (TBL) Analysis San Francisco Public Utilities Commission Citizen s Advisory Committee, Wastewater Subcommittee June 14, 2012 Triple Bottom Line (TBL) Analysis 1 Presentation Overview TBL Overview Process Overview Where

More information

Environmental Review and Aspects Register. Procedure

Environmental Review and Aspects Register. Procedure Environmental Review and Aspects Register Procedure 1. Purpose & Scope 1.1 The Purpose of this procedure is to: a) Define a method for identifying and assessing environmental Aspects. b) Identify how an

More information

OAKLAND COUNTY HEALTH DIVISION SANITARY CODE ARTICLE II - GROUNDWATER PROTECTION

OAKLAND COUNTY HEALTH DIVISION SANITARY CODE ARTICLE II - GROUNDWATER PROTECTION OAKLAND COUNTY HEALTH DIVISION SANITARY CODE ARTICLE II - GROUNDWATER PROTECTION INDEX OF CODE SECTION 1 SECTION 2 SECTION 3 SECTION 4 SECTION 5 SECTION 6 DEFINITIONS RESIDENTIAL BUILDING SITES COMMERCIAL

More information

Groundwater Protection and Management Critical to the Global Climate Change Discussion

Groundwater Protection and Management Critical to the Global Climate Change Discussion The National Ground Water Association, founded in 1948, is a not-for-profit professional society and trade association for the groundwater industry. Our international membership includes some of the leading

More information

Tahoe Basin Climate Action Database Guidance Memo

Tahoe Basin Climate Action Database Guidance Memo Tahoe Basin Climate Action Database Guidance Memo US Army Corps of Engineers Climate Change Project Date: 2/11/2011 CONTE NTS Purpose & Use 1 Users & Roles 1 Implementing Entity Staff 1 Implementing Entity

More information

Good morning, Chairman Yaw, Chairman Yudichak, Chairman Vulakovich, Chairman Costa,

Good morning, Chairman Yaw, Chairman Yudichak, Chairman Vulakovich, Chairman Costa, Testimony of Patrick McDonnell, Secretary Pennsylvania Department of Environmental Protection Joint Hearing on Flooding and Emergency Response Senate Environmental Resources & Energy and Veterans Affairs

More information

Table of Contents. Planning & Governmental Relations Capacity Enhancement & Concurrency Mitigation Agreements

Table of Contents. Planning & Governmental Relations Capacity Enhancement & Concurrency Mitigation Agreements Table of Contents Planning & Governmental Relations Capacity Enhancement & Concurrency Mitigation Agreements August 28, 2014 Page Number BACKGROUND 2 OBJECTIVE 2 SCOPE AND METHODOLOGY 2 COMMENDATION 3

More information

Apart from the major cities along the Rio Grande corridor, much of New

Apart from the major cities along the Rio Grande corridor, much of New Water Matters! Rural Water Systems 12-1 Rural Water Systems Many western rural areas have never had adequate water supplies and have a need for a reliable water supply to attract and maintain rural economic

More information

UWMP Standardized Tables. Dominguez District Urban Water Management Plan Appendix H

UWMP Standardized Tables. Dominguez District Urban Water Management Plan Appendix H UWMP Standardized Tables Dominguez District 2015 Urban Water Management Plan Appendix H Table 2-1 Retail Only: Public Water Systems Public Water System Number Public Water System Name Number of Municipal

More information

Colorado Climate Plan

Colorado Climate Plan Colorado Climate Plan Colorado Parks and Wildlife Commission Mtg. March 9, 2016 Taryn Finnessey Climate Change Risk Management Specialist Colorado Water Conservation Board Released in Sept. 2015 by Governor

More information

Developing Evaluation Criteria

Developing Evaluation Criteria ART SUPPLY: HOW-TO GUIDE Design Your Project Step 7: Evaluate Responses Developing Evaluation Criteria ADAPTING TO RISING TIDES PROGRAM This guide helps with Developing and using a set of criteria for

More information

Identification of adaptation measures and options (IWRM tools) for the Health Sector based on the impact and vulnerability assessment results

Identification of adaptation measures and options (IWRM tools) for the Health Sector based on the impact and vulnerability assessment results Identification of adaptation measures and options (IWRM tools) for the Health Sector based on the impact and vulnerability assessment results (Chapter 4) Involve those at risk Provide financial assistance

More information

78th OREGON LEGISLATIVE ASSEMBLY Regular Session. House Bill 3470 SUMMARY

78th OREGON LEGISLATIVE ASSEMBLY Regular Session. House Bill 3470 SUMMARY Sponsored by Representative BARNHART th OREGON LEGISLATIVE ASSEMBLY--0 Regular Session House Bill 0 SUMMARY The following summary is not prepared by the sponsors of the measure and is not a part of the

More information

Special Publication SJ2004-SP27. Affordability Analysis of Alternative Water Supply

Special Publication SJ2004-SP27. Affordability Analysis of Alternative Water Supply Special Publication SJ2004-SP27 of Alternative Water Supply of Alternative Water Supply Technical Memorandum February 9, 2004 TABLE OF CONTENTS Section Page EXECUTIVE SUMMARY i A. Background and Scope

More information

NOTICE OF DECISION BEFORE THE SKAGIT COUNTY HEARING EXAMINER Worline Road Bow, WA Collins Road Sedro Woolley, WA 98284

NOTICE OF DECISION BEFORE THE SKAGIT COUNTY HEARING EXAMINER Worline Road Bow, WA Collins Road Sedro Woolley, WA 98284 NOTICE OF DECISION BEFORE THE SKAGIT COUNTY HEARING EXAMINER Applicant: Contact: Request: Location: Shoreline Designation: Zoning Designation: Summary of Proposal: SEPA Compliance: Public Hearing: Decision:

More information

CITY OF LAGRANGE, GEORGIA UTILITY DEPARTMENT WATER CONSERVATION AND DROUGHT CONTINGENCY PLANS

CITY OF LAGRANGE, GEORGIA UTILITY DEPARTMENT WATER CONSERVATION AND DROUGHT CONTINGENCY PLANS CITY OF LAGRANGE, GEORGIA UTILITY DEPARTMENT WATER CONSERVATION AND DROUGHT CONTINGENCY PLANS Modified: May 2012 WATER CONSERVATION PLAN SYSTEM MANAGEMENT AND SALES Permit Information. The City of LaGrange

More information

Water Safety Plan Guide Surface Water Abstraction Rivers, Streams and Infiltration Galleries Version 1, Ref P1.1

Water Safety Plan Guide Surface Water Abstraction Rivers, Streams and Infiltration Galleries Version 1, Ref P1.1 Water Safety Plan Guide Surface Water Abstraction Rivers, Streams and Infiltration Galleries Version 1, Ref P1.1 January 2014 Citation: Ministry of Health. 2014. Water Safety Plan Guide: Surface Water

More information

AESTHETIC AND NOISE CONTROL REGULATIONS

AESTHETIC AND NOISE CONTROL REGULATIONS 801. INTRODUCTION AESTHETIC AND NOISE CONTROL REGULATIONS The rules and regulations in this section are promulgated to control aesthetics and noise impacts during the drilling, completion and operation

More information

ELECTRICAL TRANSMISSION LINES & SUBSTATIONS

ELECTRICAL TRANSMISSION LINES & SUBSTATIONS TERMS OF REFERENCE ELECTRICAL TRANSMISSION LINES & SUBSTATIONS Notes for NEPA for Generic Terms of Reference This generic Terms of Reference (TOR) is applicable to development projects involving the construction

More information

Global Sustainable Tourism Criteria for Destinations (GSTC-D) version November Preamble

Global Sustainable Tourism Criteria for Destinations (GSTC-D) version November Preamble (GSTC-D) version 1.0 1 November 2013 Preamble Sustainable tourism is on the rise: consumer demand is growing, travel industry suppliers are developing new green programs, governments and international

More information

Chapter 1. Introduction

Chapter 1. Introduction Chapter 1 Introduction James P. Heaney, Robert Pitt, and Richard Field Introduction Stormwater has traditionally been considered a nuisance, requiring rapid and complete drainage from areas of habitation.

More information

* For applicants utilizing bank for compensatory mitigation requirements, information below is not applicable.

* For applicants utilizing bank for compensatory mitigation requirements, information below is not applicable. Mitigation Plan (33 CFR 332.4(c)/40 CFR 230.92.4(c)) A mitigation plan is required for all forms of compensatory mitigation, whether permittee-responsible mitigation, mitigation banks, or in-lieu fee mitigation

More information

PROPOSAL. To Christopher Fernandes Sun Valley Ranch, Inc Sundown Rd Sun Valley, AZ

PROPOSAL. To Christopher Fernandes Sun Valley Ranch, Inc Sundown Rd Sun Valley, AZ PROPOSAL To Christopher Fernandes Sun Valley Ranch, Inc. 7561 Sundown Rd Sun Valley, AZ For Development Plans of Sun Valley Water & Wastewater Systems By Solutions & Advancements in Water & Wastewater

More information

BLACK BUSINESS LOAN PROGRAM APPLICATION EVALUATION FORM

BLACK BUSINESS LOAN PROGRAM APPLICATION EVALUATION FORM BLACK BUSINESS LOAN PROGRAM APPLICATION EVALUATION FORM Form OTTED 7102-2 (5/10)- Page 1 of 11 Instructions for Use The Office and its designees use this form to review and evaluate applications from New

More information

TIER 2 EIS SCOPING MEETING WELCOME TO THE FEDERAL AVIATION ADMINISTRATION SCOPING MEETING

TIER 2 EIS SCOPING MEETING WELCOME TO THE FEDERAL AVIATION ADMINISTRATION SCOPING MEETING TIER 2 EIS SCOPING MEETING WELCOME TO THE FEDERAL AVIATION ADMINISTRATION SCOPING MEETING TIER 2 EIS OVERVIEW SOUTH SUBURBAN INAUGURAL AIRPORT ENVIRONMENTAL IMPACT STATEMENT The proposed, (SSA) will require

More information

PROJECT CONCEPT PRELIMINARY QUESTIONAIRE PART I: GENERAL INFORMATION. GEF: OTHER(S) (Specify)

PROJECT CONCEPT PRELIMINARY QUESTIONAIRE PART I: GENERAL INFORMATION. GEF: OTHER(S) (Specify) PROJECT CONCEPT PRELIMINARY QUESTIONAIRE PART I: GENERAL INFORMATION Interested Organization Name: Project Location: Projected amount of required project funding ($ /USD): TOTAL: Project Sector or Similar:

More information

Alternatives Analysis

Alternatives Analysis CHAPTER 6 Alternatives Analysis 6.1 Introduction The National Environmental Policy Act (NEPA) and the California Environmental Quality Act (CEQA) require that an Environmental Impact Statement (EIS) and

More information