Supplementary Report

Size: px
Start display at page:

Download "Supplementary Report"

Transcription

1 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Technical Assistance for Environmental and Social Impact Assessment (EIA / SIA) Jakarta Urgent Flood Mitigation Project (JUFMP) Grant TF# IND Ancol Updated RKL/RPL Supplementary Report SEPTEMBER 2011

2 Contents Glossary... 1 Summary Introduction Context Purpose and scope of Status Report Adequacy of 2009 Ancol Updated RKL / RPL Specific review of the 2009 Ancol Updated RKL / RPL Indonesian requirements Broader considerations Additional information and developments Approval of the JUFMP Phase 1 AMDAL and Supplementary Report Additional baseline environmental information Sediment quality Community Consultation Commencement of Ancol CDF Construction Offsite impacts from Ancol CDF Overall assessment Ancol CDF Safeguards Institutional arrangements PT. PJA Ancol Construction Contractors (ACC) JUFMP Supervision Consultant (SC) PIUs PMU Construction Contractors (CC) DKI BPLHD Enhanced safeguards Integration of JUFMP and Ancol CDF activities Good practice construction and supervision Sediment and other fill / cover material Traffic management Appendix 1 Detailed review of Ancol AMDAL and Ancol Updated RKL/RPL Appendix 2 Development of Ancol CDF and interaction with JUFMP project Appendix 3 Ancol integrated Environment Management and Monitoring Matrix List of Tables Table A - 1 : Detailed review of Ancol 2006 AMDAL and 2009Ancol Updated RKL/RPL Table A - 2 : Development of Ancol CDF and interaction with JUFMP project (Schedule subject to periodic adjustments) Table A - 3 : Ancol CDF Supplementary EMP Matrix i

3 Glossary Institutional Functional English names BBWS CC Regional Office for the Ciliwung-Cisadane River Basin (Balai Besar Wilayah Sungai Ciliwung-Cisadane, BBWS-CC) DKI BPLHD Environmental Management Agency of Jakarta Provincial Government DGCK Directorate General Human Settlements, Ministry of Public Works DGWR Directorate General Water Resources, Ministry of Public Works DKI Jakarta Jakarta Provincial Government PMU Project Management Unit PIU Project Implementation Unit PT. PJA PT. Pembangunan Jaya Ancol, the concessionaire and operator of the Ancol reclamation project Environmental documentation: AMDAL Environmental Assessment (Analisis Mengenai Dampak Lingkungan, AMDAL, it includes ANDAL plus RKL / RPL) ANDAL Environmental Impact Assessment/Statement (Analisis Dampak Lingkungan, ANDAL) RKL Environmental Management Plan (Rencana Pengelolaan Lingkungan, RKL) RPL Environmental Monitoring Plan (Rencana Pemantauan Lingkungan, RPL) Updated RKL / RPL Product resulting process whereby there is a substantive change in project scope from an already approved AMDAL sufficient to warrant an updating of the environmental and social management and monitoring plans, but the change is not so large as to require a completely new AMDAL. As will be seen this approach was adopted by DKI BPLHD and the AMDAL Commission to enable the disposal of JUFMP dredge material at the already approved Ancol reclamation site. The Updated RKL / RPL supersedes the earlier AMDAL, but does not necessarily have to re-address issues that were considered to have been adequately considered in the earlier AMDAL and for which there will be no substantial changed effects JUFMP Project-specific terminology B3 Waste (or B3) Hazardous and Toxic Waste (Limbah Bahan Berbahaya dan Beracun) JUFMP Jakarta Urgent Flood Mitigation Project. [in various project documents, used synonymously with Jakarta Emergency Dredging Initiative (JEDI) ] Phase 1 Set of project sites for initial implementation of overall JUFMP. The Phase 1 sites were chosen because of their critical importance with respect to flood relief, and also because resettlement will not be required. A single AMDAL has been prepared for this set of Phase 1 activities Phase 2 The remainder of project sites to be undertaken under JUFMP. RPF Resettlement Policy Framework; a policy document to be followed by JUFMP for resettlement activities associated with the project. There is no resettlement for Phase 1 project sites. The RPF is based on World Bank policy / practice and Indonesian law Project Sites Identified individual components of JUFMP; either a defined length of drain/river / floodway, or a defined size of waduk (reservoir/flood 1

4 retention basin). Engineering designs have been based on each site; AMDAL preparation has been or will be for individual project site Terminology arising from JUFMP Contractual and implementation aspects Construction Contractor Contractor Detailed ESMP Contractor ESM Plan Contractor Preliminary ESMP ESM Supervision Consultant The contractor whose Construction Contract under the PIU will undertake dredging, embankment works, sediment transport and associated activities for construction of JUFMP An Environmental and Social Management Plan (ESMP) to be prepared on award of Contract by the Construction Contractor with detailed information on ESM practices to be followed. This must be based on the Construction Contract conditions, the AMDAL, this Supplementary Report, and other reports referred to in bidding documents. It must also follow all relevant laws and regulations. Community consultation prior to submission of the ESMP for Supervision Consultant formal approval is mandated Generic term used to include both the Contractor General ESMP and the Contractor Detailed ESM Plan An ESM Plan to be prepared as part of the Technical Bid. It will include similar contents as per Contractor Detailed ESMP, but to a lesser degree of detail. Community consultation is recommended as part of preparation Environmental and Social Management (includes environmental and social monitoring as appropriate) Consultant under contract to PMU. The Supervision Consultant will undertake day-to-day supervision of Construction Contracts the role normally identified as Engineer (as principal s representative). The Supervision Consultant will also have a substantive role in environmental and social management and monitoring, with main focus on Construction Contractor s ESM but also including specific duties in relation to public communication / grievances, to resettlement (for some of the Phase 2 site activities) and to monitoring and reporting to DKI BPLHD on behalf of the project proponents (i.e. PIUs) 2

5 Summary PT. PJA had an AMDAL prepared and approved in 2006 for reclamation of a near-shore area in Jakarta Bay based on filling with sand derived from regional sources (the Ancol AMDAL). Following the announcement of the Jakarta Urgent Flood Mitigation Project (JUFMP), an Ancol Updated RKL / RPL was prepared and approved in 2009, to enable part filling of the area with JUFMP dredged material. Other changes in design were an increased channel width separating the reclamation area from the main shoreline from about 80 m to 200m and slight changes to overall shape and area. Inherent but not explicit in the Ancol Updated RKL / RPL was that the facility was to be designed, constructed and operated as a Confined Disposal Facility (hence the term Ancol CDF is commonly used to refer to the facility). An independent review of the Ancol AMDAL and Ancol Updated RKL / RPL (based largely on a World Bank supplied-checklist) was undertaken in 2009 by ERM (a consultancy firm). This current supplementary report further reviews the Ancol Updated RKL / RPL, and considers progress in JUFMP planning and design and in other factors that have occurred in the interim. The original Ancol AMDAL and Ancol Updated RKL / RPL followed appropriate and standard Indonesian practices such as preparation by independent certified AMDAL specialists, specified consultations during preparation and assessment by the AMDAL Commission. The overriding conclusion from the reviews and consideration of progress in JUFMP planning and design is that the Ancol CDF site and Ancol Updated RKL / RPL integrates well with the JUFMP project. Some aspects that might be expected to be addressed in an environmental assessment are missing or only very briefly addressed in the Ancol Updated RKL/RPL and/or earlier AMDAL - this probably arose because during scoping it was considered that they were of little or no relevance considering the specific project situation. This report identifies these aspects and concurs that they are of little or no relevance. Additionally it could be argued that greater consideration should have been given to future land use implications at the Ancol CDF site. The Ancol Updated RKL/RPL is specific to the filling / reclamation activity, and almost any type of future land use would require separate environmental assessment at the time. Furthermore, all indications are that the filling with JUFMP dredged sediment would not limit future land uses. This supplementary report concludes that some additional management and monitoring would be a prudent assurance to strengthen the implementation of safeguards measures. Based on this assessment, a supplementary EMP is presented in this supplementary report. This complements the Ancol Updated RKL / RPL and focuses mostly on the management and monitoring of environmental and social issues during the development of the Ancol CDF. Costs are mostly related to normal engineering / site management supervision, a need to integrate activity with the JUFMP Supervision Consultant and for some post-filling soil chemical analysis. 3

6 1 Introduction 1.1 Context The owner / proponent of the Ancol reclamation site in the near shore area of Jakarta Bay is PT. Pembangunan Jaya Ancol (PT. PJA). Environmental approvals to reclaim the area were granted in 2006 following standard Indonesian AMDAL requirements, with fill material mostly based on sand. Following a very severe flood that inundated Jakarta in February 2007, the concept of a Jakarta Urgent Flood Mitigation Project (JUFMP) evolved and has been in preparation since then. The JUFMP involves dredging accumulated sediment in the selected key floodways, canals and waduks (retention basins) within the Jakarta urban area and transporting the dredged material to a suitable disposal location. Several options were assessed and it was concluded that the Ancol reclamation site was the most appropriate facility for the disposal of the JUFMP dredge material 1 since: It is central to the JUFMP project sites; It already had environmental approvals for development; By being in a nearshore area the social effects would be minimal (there would be no resettlement); and It represented a wise use of resources, replacing sand with dredged material as part filling material for reclamation. Interaction with the Environmental Management Agency of Jakarta Provincial Government (DKI BPLHD) and the associated AMDAL Commission determined that the change of fill material would require that there be an Ancol Updated RKL / RPL to address issues associated with change of fill material. This was prepared in accordance with local requirements including scoping, preparation, consultations, specific consideration of social issues and AMDAL Commission hearing. The updated RKL / RPL was approved by DKI BPLHD in The area approved was +/- 119 ha site, and slight changes to physical boundaries eventuated, especially in relation to widening the distance between the existing shoreline (itself reclaimed) and the Ancol CDF reclamation site. Recognising different ownership but also the need for integration, the approved Ancol Updated RKL / RPL specifically identifies the physical and administrative boundaries between Ancol CDF and the JUFMP project. Since approval of the Ancol Updated RKL / RPL: JUFMP project preparation has progressed significantly, especially in relation to: o Selection of a set of JUFMP sub-projects for JUFMP Phase 1 activities, with associated detailed design and preparation and approval of an AMDAL for these sub-projects. o On-going detailed design and studies for environmental approvals for other JUFMP sub-projects and studies into necessary resettlement at some of these sub-project sites. o Establishing project institutional and implementation arrangements. There has been on-going review of the Ancol Updated RKL / RPL, especially in relation to interaction with JUFMP requirements. 1 Excepting solid wastes (which will be separated and disposed at the existing Bantar Gebang landfill), and hazardous material if these are found (which is planned to be disposed at an existing commercial licensed existing hazardous material landfill, i.e., PPLi) 4

7 A further subsequent proposed change in design of the northern boundary (dyke) of the Ancol CDF was reviewed and approved by DKI BPLHD. This proposed design change was also review by the World Bank, and the recommendations of this review was acknowledged and adopted prior to the approval of DKI BPLHD. It is stressed that the 2006 Ancol AMDAL and the 2009 Ancol Updated RKL / RPL were specifically focussed on the reclamation activity itself at the Ancol site in line with Indonesian requirements. The fact that the reclamation site itself was in conformity with the long term spatial plan precluded detailed evaluation of land use issues, especially because the site is currently a near shore area. Boundaries were drawn in relation to the JUFMP activities. The 2009 Ancol Updated RKL / RPL included detailed evaluation of the result of bringing JUFMP dredge material to the Ancol CDF site. The actual dredging activities themselves and transport of the JUFMP dredge material to the Ancol CDF site is addressed in the JUFMPspecific AMDALs. Evaluation of future land use activities was effectively left to postreclamation AMDALs or similar environmental permitting which will be known only when there are specific proposals for the use of the area. 1.2 Purpose and scope of Status Report This supplementary report: Assesses whether the earlier Ancol AMDAL and the Ancol Updated RKL / RPL adequately address the social and environmental issues associated with the use of the site for JUFMP dredge material disposal (Section 2) including: o Considering the Ancol Updated RKL / RPL as a stand-alone document (Section 2.1) o Addressing new and updated information (Section 2.2) o Making an overall assessment, integrating the earlier Ancol Updated RKL / RPL and the new and updated information (Section 2.3) o Overall conclusions Identifies the current status of use of the Ancol site for JUFMP dredge material disposal (Section 3) addressing: o Institutional arrangements (Section 3.1) o Initial construction o Enhanced safeguards (Section 3.2) Appendices present: Nominal schedule of Ancol CDF development and interaction with JUFMP (Appendix 1) Supplementary EMP for Ancol CDF. (Appendix 2) 2 Adequacy of 2009 Ancol Updated RKL / RPL Review of a document such as the 2009 Ancol Updated RKL / RPL could be undertaken for any one or more of the following reasons: 1. To check conformity with particular guidelines, legislation etc. 2. To assess the quality of the document and information contained therein. 3. To determine what requirements arising from the 2009 Ancol Updated RKL / RPL might influence how the JUFMP project could be implemented. 4. To assess whether conditions have changed since the 2009 Ancol Updated RKL / RPL was prepared and approved that might result in the document and associated RKL / RPL being at least partially invalid. 5

8 These reasons are not mutually exclusive and it is a matter of judgement as to the relative importance placed on these different reasons. In this current report, focus is on the reasons identified as 1, 3 and 4 above. The World Bank has specifically required assessment against its own provided checklist. This addresses reason 1 in part. Another check related to reason 1 is whether the document conforms to the Government of Indonesia (GOI) requirements. In relation to reason 2 the Consultants 2 believe there is little to be gained by what must be a judgemental view of the quality of the document and how information is presented. However, the quality and completeness of the information can be and is partially considered in relation to conformity with the World Bank checklist. This report will not specifically address reason 2 again. At this stage of the project it important to be clear as to how the 2009 Ancol Updated RKL / RPL enables the JUFMP project to proceed, and what restrictions it might place on the implementation of the JUFMP project. This requires focus on reasons 3 and 4 above. 2.1 Specific review of the 2009 Ancol Updated RKL / RPL This Section focuses on Reason 1 identified at the beginning of this section, focussing on whether the 2009 Ancol Updated RKL / RPL conforms to regulations, policies etc Indonesian requirements While the 2009 Ancol Updated RKL / RPL effectively supersedes the earlier 2006 Ancol AMDAL, both documents and processes should be considered together. The decision to require an updated RKL / RPL rather than a complete new AMDAL is made based on the consideration of whether the earlier document adequately addressed aspects that might have a fundamental bearing on whether the project should proceed or not. By proceeding with the updated RKL / RPL approach, DKI BPLHD and the AMDAL Commission inherently determined that such aspects had been adequately addressed and what was required was a focus to ensure that adequate environmental management would be in place for the Ancol site to receive and dispose of JUFMP dredge material. The 2009 Ancol Updated RKL / RPL was prepared on behalf of the owner, PT. PJA: Proponent Name : PT. Pembangunan Jaya Ancol, Tbk. Office Address : Jl. Pasir Putih Raya Kav. 5 Ancol, North Jakarta Telephone Number : (021) Facsimile number : (021) Responsible : Ir. Maleakhi John Position : Head of the Department of Licensing and Special Projects Project Name : Development of Eastern Regions of West Ancol for ±119Ha. Preparation was undertaken by AMDAL-certified consultants, informed by: the earlier 2006 Ancol AMDAL; specific engineering studies associated with formation of the outer retaining dike, current studies, and soil investigations; and the ERM 2008 sediment quality studies undertaken in the JUFMP drains and waduks; 2 The consultants retained by the PMU to prepared this supplementary report. 6

9 what would be involved with the JUFMP project. Assessment of the Ancol Updated RKL / RPL was done by DKI BPLHD / AMDAL Commission, which included a series of meetings in February / March 2009 before final approval was given. Reports from these meetings indicated extensive consideration by DKI BPLHD / AMDAL Commission on a range of social and environmental concerns, with the finally approved Ancol Updated RKL / RPL addressing these aspects. A notable aspect of the Ancol Updated RKL / RPL was the implication of the reclamation being developed as a Confined Disposal Facility (CDF), but this specific term was never used in the document. Additionally, typical drawings indicated sequencing of development of outer confining dikes, although there was no detailed written explanation of the whole sequencing and timing of development from initial outer dike construction, filling with dredged sediment and final covering. It is concluded that the process was properly conducted according to GOI requirements, that DKI BPLHD and the AMDAL Commission were detailed in their assessment and ensuring safeguards and that social matters were addressed in detail. The Ancol Updated RKL / RPL is very clear and specific about the scope and division of responsibilities between PT. PJA and JUFMP. In particular at Section 2.5.d the document states: In the context of the activities of JUFMP, the Ancol project site is a dumping site. JUFMP is the responsible party: o To ensure the dredged material does not contain B3 (hazardous and toxic waste) as per Government Regulation No. 85/ (This item further notes that based on the ERM 2008 sediment quality study, sediments do meet the criteria and can be accommodated at the Ancol reclamation site) o For dredging and transportation of materials to the Ancol location. o For selection of transportation route and carrier traffic arrangements. The responsibility of PT. PJA starts when a vehicle enters from Jl. RE Martadinata to the Ancol area. PT. PJA s obligation is to: o Provide access road in from Jl. RE Martadinata to the dumping site o Provide a means of laundering carrier (vehicle washing) as it leaves the Ancol area Broader considerations This subsection is based on two separate consultants (ERM in 2009, PPA in 2010) independently reviewing the 2009 Ancol Updated RKL / RPL with some reference back to the 2006 Ancol AMDAL. Both reviews were made with assistance of a World Bank checklist, examination of the Ancol documents including notes made at the DKI BPLHD / AMDAL Commission meetings and with site visits. This detailed consolidated review is found in Appendix 1. Certain assessments and comments from these reviews require further additional s and considerations. These additional s and considerations are discussed in further detail in this and following sub-sections. The need for additional assessment / consideration arises because of one or more of the following: Contextual aspects. This relates to either standard check-list items being of limited relevance in relation to the project considering the context of the site itself, or of what 3 Note that the term of B3 in the 2009 Ancol Updated RKL/RPL refers to hazardous wastes as categorized and defined in the standards stipulated in Government Regulations no 85/1999 on Hazardous and Toxic Waste Management. 7

10 the Ancol AMDAL and Ancol Updated RKL / RPL ( Ancol permitting ) actually addresses. The documentation is non-specific about certain key aspects, especially in relation to the staging of reclamation activities and actually defining the activity as a Confined Disposal Facility. The evaluation of potential issues associated with use of JUFMP dredged material is limited. Mitigation measures do not necessarily consider the context of the site nor do they necessarily align with how site management will be arranged. Context of site The Ancol reclamation site is a near-shore site, located in a central position off Jakarta in Jakarta Bay. The Ancol CDF facility will be separated by a channel of some 200m width from a shoreline that itself has been subject to past filling / reclamation and accretion. Furthermore, under current spatial planning reclamation of the site has been formally identified since a 1995 government regulation. Considering this context: Long term planning issues are predetermined. The interaction with the closest residential communities (minimum of 200 m distant) would be limited during the reclamation period. The polluted nature of the immediate site reduces inherent pristine environmental quality (water and biological) and there are no nearby areas of biological value such as mangroves. Nevertheless this is not taken as a reason not to implement appropriate mitigation measures. Context of Ancol permitting As noted earlier, the scope of environmental permitting is limited to the reclamation stage of Ancol itself, notably excluding post-reclamation activities (to be addressed through future environmental permitting which will be known only when there are specific proposals for the use of the area) and JUFMP dredging and sediment transport activities (addressed in the JUFMP-specific AMDALs). Additionally, the sourcing of cover sand and topsoil would assume that those extractive industries themselves have appropriate environmental clearances, but assurances of the same are not specified in the Ancol mitigation measures. Staging of reclamation activities Drawings and in the 2009 Ancol Updated RKL / RPL infer that the site will be developed as a Confined Disposal Facility (CDF), with enclosing outer dikes internally lined with geotextile developed prior to the filling with dredge material. The timing of sand and topsoil cover-layer development is not defined. Potential issues arising from the use of JUFMP dredged material There is an inherent assumption that the requirement that JUFMP-transported sediment be not B3 adequately covers the potential issues arising from the use of JUFMP dredge material. While this may be reasonable in many circumstances, additional evaluation and more specific mitigation measures would increase the safeguards. Mitigation measures Mitigation (including monitoring) measures as proposed do not necessarily consider the context of the site nor do they necessarily align with how site management will be arranged. While potential pollution from, for example, workforce sanitation is possible, it is not addressed in relation to the context that the numbers of workers would be limited, that Jakarta Bay is already polluted and that surrounding infrequent water quality testing would not be able to distinguish whether workforce sanitation was being adequately managed. As another example, for a construction activity much of the mitigation and monitoring should be 8

11 focussed on aligning to Construction Contract conditions and oversight by a supervising engineer. These are addressed later in this Supplementary Report. 2.2 Additional information and developments Since the 2009 Ancol Updated RKL / RPL there has been: Approval of the JUFMP Phase 1 AMDAL by the AMDAL Commission in March Preparation of a JUFMP Phase 1 Supplementary Report, which includes further safeguards-related recommendations beyond the JUFMP Phase 1 AMDAL, and which will also be applicable to the JUFMP project. Detailed baseline data collection for the JUFMP Phase 2 AMDALs that are being prepared through Additional consideration of sediment quality issues, especially to incorporate additional information from the JUFMP Phase 2 primary data collection and to consider the most appropriate manner to satisfy the DKI BPLHD JUFMP Phase 1 requirement for on-going sediment monitoring. Additional consultations with stakeholders. Commencement of the construction of the Ancol outer confining walls (which will form the confined disposal facility) Further consideration of potential offsite impacts from the sourcing of sand and laterite material (in addition to JUFMP dredge material) for the construction of the Ancol CDF Approval of the JUFMP Phase 1 AMDAL and Supplementary Report The JUFMP Phase 1 AMDAL was prepared for the 5 JUFMP sites for which construction is expected to commence soon after the approval of the project. This JUFMP Phase 1 AMDAL was formally approved by DKI BPLHD in March The most significant issue in this report related to the Ancol site is a requirement for additional B3 monitoring at the JUFMP sites prior to and post dredging. A JUFMP Phase 1 Supplementary Report was prepared and this provided new information arising from JUFMP detailed design, addressed the sediment quality issues arising from the JUFMP AMDAL approval conditions, re-estimated transport traffic volumes, and produced a supplementary EMP based on the JUFMP institutional arrangements with emphasis on the Construction Contractor and Supervision Consultant arrangements (which were not yet defined in detail at the time of the JUFMP Phase 1 AMDAL) Additional baseline environmental information Additional baseline environmental information has been collected for the JUFMP Phase 1 and Phase 2 sub-project areas, with information most relevant to Ancol being: Confirmation that baseline levels for various environmental parameters (especially noise, some air quality and many water qualities) already exceed environmental standards from time to time. Additional sediment samples have been collected 4 and had the quality tested see next subsection. 4 In addition to the earlier sediment quality study (conducted by ERM consultants in 2008) which was the first comprehensive and detailed primary sediment quality study for Jakarta s drains and waduks, and which supported much of the initial planning for the JUFMP project including the ANCOL Updated RKL / RPL and the JUFMP Phase 1 AMDAL. 9

12 Observations of the performance of an earlier Dutch-funded pilot project 5 dredgedsludge at different times after disposal Sediment quality The additional assessments and consideration of sediment quality issues undertaken since the 2009 Ancol Updated RKL / RPL: Demonstrated that the results of additional sediment sample analysis (done for JUFMP Phase 2 sites) all support the earlier sampling and analysis that none of the material is classified as B3 (i.e., hazardous and toxic waste) 6. Identified a testing protocol to be used to check sediment quality prior to dredging and on JUFMP project completion in the JUFMP drains and waduks. Identified the need to ensure that JUFMP transport trucks could not be used for illegal transport of any non-jufmp material (whether B3 or otherwise) to Ancol. Assessed all sediment quality results in terms of land use using appropriate local standards and concluded that for a confined disposal facility, all sampling and testing to date supported a conclusion that there would be no constraint to future land use. Some additional confirmatory monitoring at Ancol during and after JUFMP sediment deposition is identified. Undertook a health assessment and concluded that the health-related risks from the JUFMP dredge material are low for Ancol construction workers and for any future residents of the Ancol site Community Consultation Community consultations have continued in JUFMP locations especially as part of the preparation of the JUFMP AMDAL and JUFMP social safeguards instruments. The clear and dominant and consistent themes arising from these consultations are: Broad support for the JUFMP project, recognising the benefits of flood mitigation, acknowledging that there will be some disturbance but stressing that communities want better environmental management than for many previous projects around Jakarta. Wish for ongoing and meaningful consultation between the project and the local communities. A very strong wish for local employment Commencement of Ancol CDF Construction The construction of the outer confining walls of the Ancol CDF facility commenced in the second quarter of There was significant including JUFMP project engineers and environmental specialists about the construction of the outer confining walls, including a subsequent change in the design of the northern boundary (dyke) of the CDF, for which the recommendations of the World Bank review of the proposal was acknowledged and adopted prior to the approval of DKI BPLHD. Monitoring inspections of the work has also been carried out by DKI BPLHD Offsite impacts from Ancol CDF In addition to the JUFMP dredged material, the construction of the perimeter walls and the filling of Ancol CDF will require sand (about 8.6 million m 3 ). According to the approved Ancol Updated RKL and RPL, this sand is to be obtained from a marine source, in the Banten Area 5 A pilot project undertaken by DKI Jakarta with Dutch government funding support to pilot dredge a minor drain in Jakarta (not part of the JUFMP project). 6 Referring to Indonesian standards, which is based on international practice. 7 In November 2010, with the participation of the World Bank during the inspection. 10

13 of the coast from North Jakarta. This location where the sand will be obtained from already has an approved Environmental Permit 8. The engineering design shows that the sediment material would form the bottom most layer of the filled area, which will then be overlaid by the sand layer which will in turn be capped with laterite soil material. The volume of laterite material required is estimated at 400,000m 3 to be obtained from land based sources near Bekasi, West Java that is also operating under environmental permits. The environmental impacts at the marine sources of sand and the land based source of laterite are not mentioned in the Ancol ANDAL, RKL and RPL 9. All that is mentioned is that these sites have an approved AMDAL and are operating under environmental permits. PT. PJA has agreed that the JUFMP Supervision Consultant will supervise and monitor the activities at these offsite locations (for the sourcing of the sand and the laterite). 2.3 Overall assessment Considering the s in this section above, the following overall assessment and conclusions are made: Project need is adequately established. Although the JUFMP project considered various options for dredged material disposal, this consideration has no bearing on whether the Ancol reclamation proceeds or not. The reclamation site was planned and approved prior to the proposal for JUFMP and has a completely different objective to that of JUFMP. The use of JUFMP dredge material to part fill the Ancol CDF site is an efficient utilization of resources (reducing sand requirement in Ancol CDF) and is a win-win situation for PT. PJA as well as JUFMP. The positive benefits are further reinforced by removing and confining sediment from the JUFMP waterways from where it is liable to be flushed into Jakarta Bay and contribute to already elevated pollution loads. The distinction in responsibilities between JUFMP and PT. PJA with regard to the development / reclamation period is well defined and appropriate. The distinction between the 2009 Ancol Updated RKL/RPL and future environmental approvals (AMDALs) needed for any future land use is unstated, but it is important to acknowledge this distinction exists and that the 2009 Ancol Updated RKL / RPL is adequate for its purposes. Explicit development of the reclamation site as a Confined Disposal Facility (CDF) is central to the environmental assessment and mitigation. Additional sediment collection and analysis and assessment confirms the earlier assessment that JUFMP sediment is most unlikely to be classified as B3; the AMDAL-Commission future monitoring will provide additional safeguards; health risk from the sediment to workers and the general community is low; and with the AMDAL-required post reclamation covering with sand and topsoil there are unlikely to be any long term adverse effects. The construction of the Ancol CDF facility will cause the associated physical loss of near-shore polluted marine habitat, which has no conservation significance. There are no close-by areas of habitat / ecosystem significance. There will likely be some marginal deterioration in local sea water quality from time to time, even with mitigation measures which are based on maintaining confinement and normal site sanitation. This has limited significance because of the already 8 According to the approved RKL and RPL, the environment permits for the Banten marine area to provide sand are (i) Serang Regency Number 666/750/LKH dated April 13, 2005 issued to PT. Gora Gahana and (ii) The Mining and Energy Central Amdal Commission Number 5038/0115/SJ.T/199 dated December 5, 1994 issued to PT. SAC Nusantara. The permit allows the company to exploit about 10 million m3 of sand from an area of 1,056 ha in the position of 5o o South and 106o o East. 9 Although this issue was reviewed by DKI BPLHD during the approval of the change in the design of the northern boundary (dyke) of the CDF. 11

14 polluted status; normal intermittent sea water quality monitoring would be unable to detect other than gross pollution from the Ancol CDF construction and filling activities. Adequate site supervision and observation would provide appropriate and cost-effective monitoring. Air quality related effects are likely to be localised and of short duration, potentially involving dust and windborne plastic etc., if site management is inadequate. Indications from other dredging activities in Jakarta are that odour problems are most unlikely, with the sediment being effectively odourless within a few hours of being disposed. Local communities are inherently separated from the reclamation site by a +/- 200 m channel. There is unlikely to be any significant disturbance to these communities, though under certain conditions they would hear operations at the site and if site management is poor they could be affected by dust and windborne rubbish. Optimal environmental and social outcomes from the reclamation / development stage would occur with a focus on o good engineering practice by PT. PJA and its contractors at the Ancol CDF and associated sites. o o o adherence to the confined disposal facility ( CDF ) principles close supervision by the PT. PJA and its supervising engineers and consultants to ensure that environmental and social safeguards are being followed, and close consultation and integration with JUFMP project implementation. Section 3 addresses the safeguards in more detail, with a particular focus on issues not detailed in the Ancol Updated RKL / RPL 3 Ancol CDF Safeguards This section considers safeguards relevant to the development and filling of the Ancol CDF during the period when JUFMP dredge material will be transported to the Ancol CDF. Many safeguards measures are already required by the 2009 Ancol Updated RKL / RPL and these will not be addressed further. The focus is therefore on additional measures, and the institutional arrangements to ensure that they are implemented. 3.1 Institutional arrangements Institutional arrangements and responsibilities for JUFMP sub-projects are well defined. The following sub-sections identify similar institutional arrangements for the Ancol CDF reclamation activity, and the necessary interactions between various parties PT. PJA PT. PJA is the concessionaire for the Ancol CDF reclamation site. It is also the proponent of the 2009 Ancol Updated RKL/RPL. PT. PJA has: Specific legal responsibility to implement the 2009 Ancol Updated RKL / RPL. General responsibility to ensure good environmental and social management at the Ancol CDF site, regardless of specific requirement in the 2009 Ancol Updated RKL / RPL. Agreed to implement any additional measures identified in this supplementary report and include reports of the implementation of these additional measures in the quarterly implementation reports of the RKL and RPL to DKI BPLHD. Interests in the long term use of the Ancol site. 12

15 The equivalent entity for the JUFMP project are the various PIUs (Section 3.1.4), though the JUFMP PMU (Section 3.1.5) has a co-ordinating role on behalf of the PIU s. Although the legal responsibility remains with PT. PJA for implementation of specified and general environmental and social management at the Ancol site, this does not limit the possibility that implementation of specific aspects could be contracted to other entities. Note that in order to further ensure the compliance to the 2009 Ancol Updated RKL / RPL: the World Bank s no-objection to any given JUFMP dredging contract will be subject to the World Bank being satisfied with the adequacy of the Ancol CDF (including having received satisfactory evidence of PT. PJA s compliance with the Ancol AMDAL and this Ancol Updated RKL/RPL Supplementary Report requirements, and compliance with the approved Detailed Engineering Drawings for the construction of the Ancol CDF), and the JUFMP legal agreements will include provision to require the Jakarta Provincial Government (DKI Jakarta) to exercise its rights, as a shareholder, to cause PT. PJA to implement the requirements (including mitigation measures) stated in the Ancol AMDAL and this Ancol Updated RKL/RPL Supplementary Report requirements Ancol Construction Contractors (ACC) This is a generic term adopted for this Supplementary Report to cover any Contractor, subcontractors, etc., engaged by PT. PJA at the Ancol CDF site for such works as, but not necessarily limited to: Construction and / or maintenance of external confining dikes Construction and / or maintenance of internal separating or temporary confining dikes, if any are needed Development and / or maintenance of internal roads or tracks to facilitate movement of JUFMP sediment delivery trucks Providers of sand, topsoil etc that might be used as specified final cover or for any other purpose. This includes entities other than JUFMP that may be used to deliver fill material to the Ancol CDF site. Internal drainage or similar Providers and operators of the vehicle washing facility as required under the 2009 Ancol Updated RKL / RPL. PT. PJA itself as it undertakes any works using its own resources or, for example, day contract labour. The equivalent entity for the JUFMP project is the (JUFMP) Construction Contractors (Section 3.1.6) engaged by the PIUs. The supervision of the ACC is being carried out by PT. PJA through its Property Development Unit (including supervising the environmental aspects of the ACC contracts). Additionally, PT. PJA has recruited a consulting firm to carry out quarterly compliance monitoring of the ongoing construction works. PT. PJA, in compliance with the Indonesian AMDAL requirements, is preparing and submitting to the DKI BPLHD quarterly implementation reports of the RKL and RPL JUFMP Supervision Consultant (SC) PT. PJA has agreed to allow the JUFMP Supervision Consultant (SC) to have access to the Ancol CDF and all it offsite locations (including source locations for the sand and laterite fill material) for the purposes of carrying out supervision of the approved RKL and RPLs, the Ancol Updated RKL/RPL Supplementary Report, PT. PJA s quarterly RKL and RPL 13

16 Progress reports and any other tasks as specified in the Terms of Reference (TOR) of the SC. The TOR for the SC will include these responsibilities PIUs The PIU s (DKI Jakarta, DGCK and DGWR) are in effect the current owners of the JUFMP drains and waduks which fall under their respective responsibility. Therefore they have specific ownership of the associated JUFMP AMDALs and hence responsibility for implementation of the JUFMP AMDALs, and will retain effectively sole control of the JUFMP drains and waduks once the JUFMP projects have been signed off after completion of construction contracts PMU The PMU within DGWR has been designated as the major unit with overall GOI responsibility for implementation of the JUFMP project. PMU has management responsibility for the JUFMP Supervision Consultant (SC), and via the SC the coordination responsibility for the Construction Contract execution for the JUFMP sub-projects and for implementing the associated AMDALs and submitting environmental monitoring reports to DKI BPLHD. The PMU is also closely associated with defining requirements for the JUFMP Construction Contracts and for the Terms of Reference of the SC Construction Contractors (CC) The Construction Contractors will be responsible for the dredging of the JUFMP drains and waduks and transport of the dredge material from the dredging sites to the Ancol CDF in accordance with Construction Contracts. Conditions of these contracts address, inter alia, environmental and social management. The Construction Contractors will have specific responsibilities in relation to preventing illegal transport and disposal of B3 (i.e., hazardous) waste (if any are found) to the Ancol CDF site DKI BPLHD DKI BPLHD is directly involved in the assessment and approval of AMDALs (including RKL / RPL) and will have an ongoing role in monitoring implementation of the RKL / RPL. Monitoring reports for the implementation of the RKL / RPL (including the Ancol Updated RKL / RPL submitted by PT. PJA) will be assessed by DKI BPLHD. With respect to Ancol CDF, DKI BPLHD has started monitoring the ongoing construction works and invited the World Bank to participate in the supervision and monitoring. It is expected that these joint supervision and monitoring will continue. In the future, DKI BPLHD would also be the authority involved in the assessment and approval of any AMDALs related to any proposed land use of the Ancol CDF site. 3.2 Enhanced safeguards Considering the review and assessments above, this subsection presents enhanced safeguards for the Ancol CDF site to be implemented during the period of construction (construction of the CDF confining walls and the reclamation filling including sand and topsoil covering) that will: Complement the environmental and social management and monitoring required in the 2009 Ancol Updated RKL / RPL. 14

17 Integrate with the ESM for the JUFMP project, as established by the AMDALs and / or by later contract or requirement. Address some issues not clearly or specifically identified in the 2009 Ancol Updated RKL / RPL. Provide additional security to ensure that all deposited material, cover material, etc., conforms to the requirement that no B3 waste is disposed at the Ancol CDF site, and to ensure that there are no constraints to future land use. For each defined mitigation / monitoring activity responsibilities are allocated. The table in Appendix 3 summarises this information Integration of JUFMP and Ancol CDF activities Activity PT. PJA shall provide DKI Jakarta and the PMU updates on the progress of the construction of the Ancol CDF facility, and provide documents confirming the completion of the confinement dykes. PT. PJA will cooperate with DKI Jakarta, PMU or World Bank review of the adequacy of the confined facility for dredge material disposal (including providing satisfactory evidence of compliance with the Ancol AMDAL and the Ancol Updated RKL/RPL Supplementary Report requirements, and compliance with the approved Detailed Engineering Drawings for the construction of the Ancol CDF). Responsibilities PT. PJA to provide information and documentation DKI Jakarta, PMU and World Bank to carry out review and assessments Activity PT. PJA shall meet as frequently as required with PMU and / or SC to enable smooth integration of JUFMP and Ancol CDF activities. One tool to be used will be the development of (and the review and updating as necessary) a detailed schedule (an outline is given at Table A - 2) of the integrated operations Responsibilities Primary Secondary PT. PJA and PMU to implement regular coordination meetings SC, ACC and CC to participate in coordination meetings as necessary Good practice construction and supervision Activity PT. PJA will ensure that all Ancol Construction Contractors (ACC) will have work plans which include environmental and social management plans. These should include such aspects as provision of workforce sanitary arrangements, health and safety, identification and proposed management of site specific environment and social management, training for workforce in relevant environment and social management. The detail of any Work Plan and ESMP shall be tailored to the particular activity; for example whereas a long term contract for disposal and levelling of deposited sediment would require a reasonably detailed ESMP, one for restricted activity such as vehicle washing for trucks prior to leaving the site might be 15

18 a 1-2 page document. Some activities would likely require no such specific plan. PT. PJA will supervise its ACC (through its Property Development Unit). Given the JUFMP interests in Ancol CDF, the SC s supervision and monitoring activities at Ancol CDF will include reviews of the ACC s environmental and social management of their activities. Responsibilities ACC for day-to-day activity at Ancol site PT. PJA (through it Property development Unit) for direct supervision of ACC SC for supervising and monitoring Ancol activities for JUFMP PMU to oversee SC activity and receive SC reports Sediment and other fill / cover material Activity The PMU (with assistance from the SC) will provide PT. PJA with information as they become available of the results of the prior dredge testing of JUFMP sites / sections (see section 2.2.1). For sections where the sediment has been cleared as suitable for delivery to and disposal at Ancol CDF, PT. PJA will allow the material to be delivered to and disposed at Ancol CDF. For sections where the sediment is not cleared as suitable for delivery to Ancol CDF (e.g., if it is determined to be B3 waste, or determined to need further additional testing and interpretation), the PMU (with assistance of the SC) will ensure that these material are not delivered to Ancol CDF. The PMU (with assistance of the SC) will keep PT. PJA fully informed of the handling of any B3 waste found in JUFMP sites. PT. PJA may review and monitor the testing process in JUFMP. Responsibilities PMU (through SC) to provide information and documentation, and cooperate with any PT. PJA review PT. PJA to allow non-hazardous, cleared material, to be delivered to Ancol CDF Activity PT. PJA shall ensure that material (other than JUFMP dredged material) to be delivered to and disposed of or used at Ancol CDF by any ACC has received appropriate environmental clearance and is in accordance with the Ancol Updated RKL / RPL which limits non-jufmp material to sand (from a defined location) and laterite. For example, this will require receiving copies of an AMDAL clearance letter prepared for sand or soil extraction operation, or a certified laboratory clearance of material. Qualified professional judgement shall be applied as the necessary type of clearance considering the nature of the material and the quantity that could be delivered. Given the JUFMP interests in Ancol CDF, the SC s supervision and monitoring activities at Ancol CDF will include reviews of these material sourcing and delivery, including reviews of potential offsite impacts at the source locations of these materials. Responsibilities ACC for day-to-day activity at Ancol site PT. PJA (through it Property development Unit) for direct supervision of ACC SC for supervising and monitoring Ancol activities for JUFMP PMU to oversee SC activity and receive SC reports Activity 16

Environmental and Social Management. Supplementary Report

Environmental and Social Management. Supplementary Report Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Technical Assistance for Environmental and Social Impact Assessment (EIA / SIA) Jakarta

More information

DRAFT JAKARTA URGENT FLOOD MITIGATION PROJECT (JUFMP) CONSOLIDATED SUMMARY OF THE ENVIRONMENTAL IMPACT ASSESSMENT

DRAFT JAKARTA URGENT FLOOD MITIGATION PROJECT (JUFMP) CONSOLIDATED SUMMARY OF THE ENVIRONMENTAL IMPACT ASSESSMENT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized DRAFT JAKARTA URGENT FLOOD MITIGATION PROJECT (JUFMP) CONSOLIDATED SUMMARY OF THE ENVIRONMENTAL

More information

REPUBLIC OF INDONESIA. Jakarta Urgent Flood Mitigation Project (JUFMP) Environmental and Social Management Framework. (Draft 24 December 2010)

REPUBLIC OF INDONESIA. Jakarta Urgent Flood Mitigation Project (JUFMP) Environmental and Social Management Framework. (Draft 24 December 2010) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized REPUBLIC OF INDONESIA Jakarta Urgent Flood Mitigation Project (JUFMP) Environmental and

More information

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE

INTEGRATED SAFEGUARDS DATASHEET APPRAISAL STAGE Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized I. Basic Information Date prepared/updated: 11/09/2011 INTEGRATED SAFEGUARDS DATASHEET

More information

Indonesia - Jakarta Urgent Flood Mitigation Project (Jakarta Emergency Dredging Initiative) Project Appraisal Document

Indonesia - Jakarta Urgent Flood Mitigation Project (Jakarta Emergency Dredging Initiative) Project Appraisal Document Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized FROM: The Acting Corporate Secretary OFFICIAL USE ONLY R2011-0276/1 December 27, 2011

More information

1 Environmental and Social Action Plan

1 Environmental and Social Action Plan 1 and Social Plan The table below constitutes the ESAP. It identifies the required actions during pre-construction, construction and operation of the project. of the actions is the responsibility of Koridori

More information

Ibstock plc. (the Company) Audit Committee - Terms of Reference

Ibstock plc. (the Company) Audit Committee - Terms of Reference Ibstock plc (the Company) Audit Committee - Terms of Reference 1. PURPOSE 1.1 The role of the Audit Committee (the Committee) is to: monitor the integrity of the financial statements and related announcements

More information

SAMOA ENVIRONMENTAL AND SOCIAL SCREENING AND ASSESSMENT FRAMEWORK FOR A POST-TSUNAMI RECOVERY PROJECT

SAMOA ENVIRONMENTAL AND SOCIAL SCREENING AND ASSESSMENT FRAMEWORK FOR A POST-TSUNAMI RECOVERY PROJECT Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized SAMOA ENVIRONMENTAL AND SOCIAL SCREENING AND ASSESSMENT FRAMEWORK FOR A POST-TSUNAMI

More information

The Gym Group plc. (the Company ) Audit and Risk Committee - Terms of Reference. Adopted by the board on 14 October 2015 (conditional on Admission)

The Gym Group plc. (the Company ) Audit and Risk Committee - Terms of Reference. Adopted by the board on 14 October 2015 (conditional on Admission) The Gym Group plc (the Company ) Audit and Risk Committee - Terms of Reference Adopted by the board on 14 October 2015 (conditional on Admission) 1. BACKGROUND The board of directors of the Company (the

More information

Advice on Terms of Reference for the EIA for the Jakarta Urgent Flood Mitigation -Indonesia- 4 June 2008 / 081 / ISBN

Advice on Terms of Reference for the EIA for the Jakarta Urgent Flood Mitigation -Indonesia- 4 June 2008 / 081 / ISBN Advice on Terms of Reference for the EIA for the Jakarta Urgent Flood Mitigation -Indonesia- 4 June 2008 / 081 / ISBN 978-90-421-3007-4 TABLE OF CONTENTS 1. INTRODUCTION... 3 1.1 The Initiative: Jakarta

More information

The Corporate Governance Statement is accurate and up to date as at 30 June 2018 and has been approved by the board.

The Corporate Governance Statement is accurate and up to date as at 30 June 2018 and has been approved by the board. Rules 4.7.3 and 4.10.3 1 Appendix 4G Key to Disclosures Corporate Governance Council Principles and Recommendations Name of entity: Catalyst Metals Limited ABN / ARBN: Financial year ended: 54 118 912

More information

Guidance Note: Corporate Governance - Audit Committee. January Ce document est aussi disponible en français.

Guidance Note: Corporate Governance - Audit Committee. January Ce document est aussi disponible en français. Guidance Note: Corporate Governance - Audit Committee January 2018 Ce document est aussi disponible en français. Applicability The Guidance Note: Corporate Governance Audit Committee (the Guidance Note

More information

E1184 v1. 6. Environmental Management Plan (EMP)

E1184 v1. 6. Environmental Management Plan (EMP) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized 6. Environmental Management Plan (EMP) This EMP reviews the potential negative impacts

More information

Consent Steps Assessing the Application and Assessment of Environmental Effects

Consent Steps Assessing the Application and Assessment of Environmental Effects 2017 Consent Steps Assessing the Application and Assessment of Environmental Effects Assessing the Application and Assessment of Environmental Effects This guidance has been updated to include the changes

More information

Specifications. Level 1 Essential Energy Works for the Warialda Truck Wash

Specifications. Level 1 Essential Energy Works for the Warialda Truck Wash Specifications Request for Quotation (RFQ) RFQ Title RFQ Number Level 1 Essential Energy Works for the Warialda Truck Wash GWY_1819_Q03 Issue Date 21st December 2018 This document contains the specification

More information

Mining Environmental Impact Assessment Guidelines. May 2018

Mining Environmental Impact Assessment Guidelines. May 2018 Mining Sector Environmental and Social Impact Assessment Guidelines Mining Environmental Impact Assessment Guidelines May 2018 Background Mining EIA Guidelines Working Group established by Minister of

More information

ADES International Holding Ltd (the Company )

ADES International Holding Ltd (the Company ) ADES International Holding Ltd (the Company ) Terms of Reference of the Audit Committee (The Committee ) (approved at a meeting of the board of directors (the Board ) held on 9 May 2017) 1. Introduction

More information

INTERNATIONAL STANDARD ON AUDITING 260 COMMUNICATION WITH THOSE CHARGED WITH GOVERNANCE CONTENTS

INTERNATIONAL STANDARD ON AUDITING 260 COMMUNICATION WITH THOSE CHARGED WITH GOVERNANCE CONTENTS Introduction INTERNATIONAL STANDARD ON AUDITING 260 COMMUNICATION WITH THOSE CHARGED WITH GOVERNANCE (Effective for audits of financial statements for periods beginning on or after December 15, 2009) +

More information

EBRD Environmental and Social Action Plan

EBRD Environmental and Social Action Plan PR 1 Assessment and Management of Environmental and Social Impacts and Issues 1.1 to establish PIU and dedicate a responsible person (head of PIU) for coordination between the various departments so as

More information

Guidance Note: Corporate Governance - Audit Committee. March Ce document est aussi disponible en français.

Guidance Note: Corporate Governance - Audit Committee. March Ce document est aussi disponible en français. Guidance Note: Corporate Governance - Audit Committee March 2015 Ce document est aussi disponible en français. Applicability The Guidance Note: Corporate Governance Audit Committee (the Guidance Note )

More information

Chapter 22: Environmental and Social Management

Chapter 22: Environmental and Social Management Chapter 22: Environmental and Social Management URS-EIA-REP-204635 Table of Contents 22 Environmental and Social Management... 22-1 22.1 Introduction... 22-1 22.2 Environmental and Social Commitments...

More information

CLINICAL & PROFESSIONAL SUPERVISION POLICY (replacing 033/Workforce)

CLINICAL & PROFESSIONAL SUPERVISION POLICY (replacing 033/Workforce) CLINICAL & PROFESSIONAL SUPERVISION POLICY (replacing 033/Workforce) POLICY NUMBER 051/Workforce POLICY VERSION 1 RATIFYING COMMITTEE HR Policy Review Group DATE RATIFIED December 2010 NEXT REVIEW DATE

More information

IAASB Main Agenda (December 2008) Page Agenda Item

IAASB Main Agenda (December 2008) Page Agenda Item IAASB Main Agenda (December 2008) Page 2008 2669 Agenda Item 2-C PROPOSED INTERNATIONAL STANDARD ON AUDITING 265 COMMUNICATING DEFICIENCIES IN INTERNAL CONTROL (Effective for audits of financial statements

More information

CORPORATE GOVERNANCE STATEMENT

CORPORATE GOVERNANCE STATEMENT CORPORATE GOVERNANCE STATEMENT The Directors and management of Afterpay Touch Group Limited ACN 618 280 649 (APT or the Company) are committed to conducting the business of the Company and its controlled

More information

Republic of Croatia HRVATSKE AUTOCESTE (Motorway Maintenance Department) RIJEKA GATEWAY PROJECT Rehabilitation works on the big arch of Krk Bridge

Republic of Croatia HRVATSKE AUTOCESTE (Motorway Maintenance Department) RIJEKA GATEWAY PROJECT Rehabilitation works on the big arch of Krk Bridge Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Republic of Croatia HRVATSKE AUTOCESTE (Motorway Maintenance Department) RIJEKA GATEWAY

More information

APPENDIX A DEFINITION OF PROFESSIONAL ENGINEERING CONSULTING SERVICES

APPENDIX A DEFINITION OF PROFESSIONAL ENGINEERING CONSULTING SERVICES Appendix A RFP No. 894-2014 Page 1 of 1 Template Version: SrC120131129 - Consulting Services RFP APPENDIX A DEFINITION OF PROFESSIONAL ENGINEERING CONSULTING SERVICES Revision: 2014-09-22 DEFINITION OF

More information

Audit, Risk and Compliance Committee Terms of Reference. Atlas Mara Limited. (The "COMPANY") Amendments approved by the Board on 22 March 2016

Audit, Risk and Compliance Committee Terms of Reference. Atlas Mara Limited. (The COMPANY) Amendments approved by the Board on 22 March 2016 Audit, Risk and Compliance Committee Terms of Reference Atlas Mara Limited (The "COMPANY") Amendments approved by the Board on 22 March 2016 1. OVERVIEW 1.1 The primary objective of the committee is to

More information

Final May Corporate Governance Guideline

Final May Corporate Governance Guideline Final May 2006 Corporate Governance Guideline Table of Contents 1. INTRODUCTION 1 2. PURPOSES OF GUIDELINE 1 3. APPLICATION AND SCOPE 2 4. DEFINITIONS OF KEY TERMS 2 5. FRAMEWORK USED BY CENTRAL BANK TO

More information

SA 265 COMMUNICATING DEFICIENCIES IN INTERNAL CONTROL

SA 265 COMMUNICATING DEFICIENCIES IN INTERNAL CONTROL Part I : Engagement and Quality Control Standards I.169 SA 265 COMMUNICATING DEFICIENCIES IN INTERNAL CONTROL TO THOSE CHARGED WITH GOVERNANCE AND MANAGEMENT (EFFECTIVE FOR ALL AUDITS RELATING TO ACCOUNTING

More information

For personal use only

For personal use only ASX ANNOUNCEMENT 1 November 2016 Corporate Governance Statement 30 June 2016 The Board of Directors is committed to improving and achieving good standards of corporate governance and has established corporate

More information

ECS ICT Berhad (Company No H) Board Charter

ECS ICT Berhad (Company No H) Board Charter 1. Introduction In achieving the objectives of transparency, accountability and effective performance for ECS ICT Berhad ( ECS or the Company ) and its subsidiaries ( the Group ), the enhancement of corporate

More information

Swiss Federal Banking Commission Circular: Audit of Banks and Securities Firms. 29 June 2005 (Latest amendment: 24 November 2005)

Swiss Federal Banking Commission Circular: Audit of Banks and Securities Firms. 29 June 2005 (Latest amendment: 24 November 2005) SFBC Circular 05/1 Audit Page 1 Swiss Federal Banking Commission Circular: Audit of Banks and Securities Firms (Audit) 29 June 2005 (Latest amendment: 24 November 2005) Contents I. Introduction A. Scope

More information

CANADA-NEWFOUNDLAND AND LABRADOR BENEFITS PLAN GUIDELINES (DRAFT)

CANADA-NEWFOUNDLAND AND LABRADOR BENEFITS PLAN GUIDELINES (DRAFT) CANADA-NEWFOUNDLAND AND LABRADOR BENEFITS PLAN GUIDELINES (DRAFT) January 2016 Comments on the proposed draft Guidelines can be submitted in writing to the address below or via email to: information@cnlopb.ca

More information

E767 May 2003 ISLAMIC REPUBLIC OF IRAN EARTHQUAKE EMERGENCY RECOVERY PROJECT. Objectives

E767 May 2003 ISLAMIC REPUBLIC OF IRAN EARTHQUAKE EMERGENCY RECOVERY PROJECT. Objectives Objectives ENVIRONMlENT AND SOCIAL SAFEGUARD FRAMEWORK ISLAMIC REPUBLIC OF IRAN EARTHQUAKE EMERGENCY RECOVERY PROJECT E767 May 2003 The environmental and social safeguards framework provides general policies,

More information

SRI LANKA AUDITING STANDARD 260 COMMUNICATION WITH THOSE CHARGED WITH GOVERNANCE CONTENTS

SRI LANKA AUDITING STANDARD 260 COMMUNICATION WITH THOSE CHARGED WITH GOVERNANCE CONTENTS SRI LANKA AUDITING STANDARD 260 COMMUNICATION WITH THOSE CHARGED WITH GOVERNANCE Introduction (Effective for audits of financial statements for periods beginning on or after 01 January 2012) CONTENTS Paragraph

More information

Terms of Audit Engagements

Terms of Audit Engagements Issued July 2008 International Standard on Auditing Terms of Audit Engagements The Malaysian Institute of Certified Public Accountants (Institut Akauntan Awam Bertauliah Malaysia) INTERNATIONAL STANDARD

More information

ROYAL DUTCH SHELL PLC AUDIT COMMITTEE TERMS OF REFERENCE

ROYAL DUTCH SHELL PLC AUDIT COMMITTEE TERMS OF REFERENCE ROYAL DUTCH SHELL PLC AUDIT COMMITTEE TERMS OF REFERENCE Purpose The Royal Dutch Shell plc (the Company ) Audit Committee (the Committee ) assists the Board of the Company (the Board ) in fulfilling its

More information

Source of requirement EBRD. - Each six months during construction - Annually during operation. Best practice EBRD PR 1

Source of requirement EBRD. - Each six months during construction - Annually during operation. Best practice EBRD PR 1 0 Submit report to the Bank on environmental, social, health and safety performance, including status of each ESAP element and other agreed activities. EBRD - Each six months during construction - Annually

More information

NCICD From planning to Implementation

NCICD From planning to Implementation NCICD From planning to Implementation Delta s in Times of Climate Change Delta session 25 September 2014 1. NCICD: The ultimate urban flood management case Mr Sutanto Soehodho, deputy Governor of DKI Jakarta

More information

RIO TINTO. AUDIT COMMITTEE (the Committee ) TERMS OF REFERENCE

RIO TINTO. AUDIT COMMITTEE (the Committee ) TERMS OF REFERENCE RIO TINTO AUDIT COMMITTEE (the Committee ) TERMS OF REFERENCE Adopted by the Board of Rio Tinto plc and Rio Tinto Limited (collectively, the Group ) on 26 February 2019 1. Purpose 2. Scope The objective

More information

REGISTERED CANDIDATE AUDITOR (RCA) TECHNICAL COMPETENCE REQUIREMENTS

REGISTERED CANDIDATE AUDITOR (RCA) TECHNICAL COMPETENCE REQUIREMENTS REGISTERED CANDIDATE AUDITOR (RCA) TECHNICAL COMPETENCE REQUIREMENTS 1. Context After completion of the recognised training contract, a period of specialisation is required, appropriate to the level required

More information

Public Disclosure Authorized EXECUTIVE SUMMARY

Public Disclosure Authorized EXECUTIVE SUMMARY Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized EXECUTIVE SUMMARY Introduction Georgia is an important transport corridor connecting

More information

SMITH & NEPHEW PLC TERMS OF REFERENCE OF THE AUDIT COMMITTEE

SMITH & NEPHEW PLC TERMS OF REFERENCE OF THE AUDIT COMMITTEE SMITH & NEPHEW PLC TERMS OF REFERENCE OF THE AUDIT COMMITTEE MEMBERSHIP 1. Members of the Audit Committee shall be appointed by the Board subject to annual re-election by shareholders at the AGM on the

More information

Performance Requirements

Performance Requirements Environmental and Social Policy 15 Performance Requirements PR 1: Environmental and Social Appraisal and Management Introduction 1. The EBRD considers it important that all companies receiving EBRD financing

More information

Guidance Note: Corporate Governance - Board of Directors. January Ce document est aussi disponible en français.

Guidance Note: Corporate Governance - Board of Directors. January Ce document est aussi disponible en français. Guidance Note: Corporate Governance - Board of Directors January 2018 Ce document est aussi disponible en français. Applicability The Guidance Note: Corporate Governance - Board of Directors (the Guidance

More information

Review of the Class Environmental Assessment for Waterpower Projects Ontario Waterpower Association

Review of the Class Environmental Assessment for Waterpower Projects Ontario Waterpower Association Ministry of the Environment Review of the Class Environmental Assessment for Waterpower Projects Ontario Waterpower Association Review prepared pursuant to subsection 7(1) of the Environmental Assessment

More information

Agreeing the Terms of Audit Engagements

Agreeing the Terms of Audit Engagements SINGAPORE STANDARD SSA 210 ON AUDITING Agreeing the Terms of Audit Engagements SSA 210, Agreeing the Terms of Audit Engagements superseded SSA 210, Terms of Audit Engagements in January 2010. The Companies

More information

6 Risk assessment methodology

6 Risk assessment methodology Risk assessment methodology 6 Risk assessment methodology 6.1 Introduction INPEX has committed to a systematic risk assessment process as a means of achieving best practice in environmental management

More information

Life Cycle Analysis Methods on Environmental Impact Assessment (EIA) Procedures in the Perspective of Sustainable Development

Life Cycle Analysis Methods on Environmental Impact Assessment (EIA) Procedures in the Perspective of Sustainable Development Life Cycle Analysis Methods on Environmental Impact Assessment (EIA) Procedures in the Perspective of Sustainable Development Andreas Pramudianto 1, * 1 School of Environmental Science, University of Indonesia,

More information

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are:

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are: 4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES 4.1 POTENTIAL ENVIRONMENTAL IMPACTS 4.1.1 Impacts during Construction Phase Negative or adverse impacts during the construction phase are: Land environment:

More information

AMDAL Procedure. Flowchart of Indonesian Environmental Clearance 1

AMDAL Procedure. Flowchart of Indonesian Environmental Clearance 1 AMDAL Procedure (This is only indicative and for reference purposes. This is not exhaustive and therefore, the Consultants are requested to familiarize themselves with all the laws, rules, regulations,

More information

AUDIT COMMITTEE REPORT

AUDIT COMMITTEE REPORT AUDIT COMMITTEE REPORT Dear Shareholder As chairman of the Audit Committee, I am pleased to report below on the work of the Committee in 2015. This year saw the appointment to the Committee of Coline McConville

More information

ONE WINDOW COORDINATION PROCESS for Mineral Development Projects in Ontario

ONE WINDOW COORDINATION PROCESS for Mineral Development Projects in Ontario ONE WINDOW COORDINATION PROCESS for Mineral Development Projects in Ontario Page 1 of 30 Table of Contents 1. INTRODUCTION AND PURPOSE... 3 Introduction... 3 Interpretation... 3 Definitions... 4 Objectives...

More information

(Adopted by the Board of Directors on 13 May 2009 and amended on 24 September 2009, 13 September 2012 and 27 November 2013)

(Adopted by the Board of Directors on 13 May 2009 and amended on 24 September 2009, 13 September 2012 and 27 November 2013) Thomas Cook Group plc THE AUDIT COMMITTEE TERMS OF REFERENCE (Adopted by the Board of Directors on 13 May 2009 and amended on 24 September 2009, 13 September 2012 and 27 November 2013) Chairman and members

More information

Uzbekenergo: Talimarjan Thermal Power Plant 2, Uzbekistan Environmental and Social Action Plan (ESAP)

Uzbekenergo: Talimarjan Thermal Power Plant 2, Uzbekistan Environmental and Social Action Plan (ESAP) Uzbekenergo: Talimarjan Thermal Power Plant 2, Uzbekistan Environmental and Social Action Plan (ESAP) No Action Environmental Risks, Liability/ Benefits Legislative Requirement / EBRD Performance Requirement

More information

Greater Amman Municipality

Greater Amman Municipality Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized ECO Consult Municipal Solid Waste Management & Carbon Finance in Amman Greater Amman

More information

GENERAL SPECIFICATION FOR ENVIRONMENTAL PROTECTION FOR CONSTRUCTION IN AND AROUND WATERBODIES AND ON WATERBODY BANKS

GENERAL SPECIFICATION FOR ENVIRONMENTAL PROTECTION FOR CONSTRUCTION IN AND AROUND WATERBODIES AND ON WATERBODY BANKS ONTARIO PROVINCIAL STANDARD SPECIFICATION METRIC OPSS.PROV 182 APRIL 2017 GENERAL SPECIFICATION FOR ENVIRONMENTAL PROTECTION FOR CONSTRUCTION IN AND AROUND WATERBODIES AND ON WATERBODY BANKS TABLE OF CONTENTS

More information

Carbon Minerals Limited ABN Corporate governance statement

Carbon Minerals Limited ABN Corporate governance statement Carbon Minerals Limited ABN 29 001 836 586 Corporate governance statement The Board of Directors is responsible to the security holders for the performance of the Company and the implementation of corporate

More information

DRAFT FOR CONSULTATION OCTOBER 7, 2014

DRAFT FOR CONSULTATION OCTOBER 7, 2014 The Board has authorized the release of this document for consultation purposes to seek feedback on its content. It has not endorsed the content of the draft, and the Committee on Development Effectiveness

More information

1. INTRODUCTION 1.1 Contents of Engineering Specifications The Engineering Specifications contains the following sections:

1. INTRODUCTION 1.1 Contents of Engineering Specifications The Engineering Specifications contains the following sections: Schedule H to Bylaw 7452, Subdivision Bylaw Page 1 1. INTRODUCTION 1.1 Contents of Engineering Specifications 1.1.1 The Engineering Specifications contains the following sections: 1. Introduction 2. General

More information

Constraints on how the Contractor Provides the Works

Constraints on how the Contractor Provides the Works Constraints on how the Contractor Provides the Works [DELETE AS APPROPRIATE: WHERE NOTIFIABLE CDM APPLIES:] CONSTRUCTION (DESIGN AND MANAGEMENT) REGULATIONS 2007 In line with the requirements of the above

More information

Executive Summary Sri Lanka Strategic Cities Development Project (SCDP)

Executive Summary Sri Lanka Strategic Cities Development Project (SCDP) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Executive Summary Sri Lanka Strategic Cities Development Project (SCDP) Executive Summary

More information

BOARD AUDIT COMMITTEE TERMS OF REFERENCE

BOARD AUDIT COMMITTEE TERMS OF REFERENCE Appendix 9 BOARD AUDIT COMMITTEE TERMS OF REFERENCE October 2016 TABLE OF CONTENTS A. AUTHORITY...3 B. ROLE OF THE COMMITTEE...4 C. COMMITTEE COMPOSITION...4 D. COMMITTEE MEETINGS...5 E. RESPONSIBILITIES...7

More information

Terms of Reference for the Audit and Risk Committee (the Committee )

Terms of Reference for the Audit and Risk Committee (the Committee ) Terms of Reference for the Audit and Risk Committee (the Committee ) Amended and approved by the Board on 12 April 2016 Table of Contents 1. Background... 1 2. The Committee s Duties... 1 3. Composition...

More information

Bank of Ireland Group plc Compliance with the Capital Requirements Directive (CRD IV) - Governance Disclosures

Bank of Ireland Group plc Compliance with the Capital Requirements Directive (CRD IV) - Governance Disclosures Compliance with the Capital Requirements Directive (CRD IV) - Governance Disclosures Corporate Governance Statement Article 96 of the CRD IV requires institutions to set out a statement, on the institution

More information

Deliverable 2: Procedural guidelines as a recommendation to the national competent authorities

Deliverable 2: Procedural guidelines as a recommendation to the national competent authorities Deliverable 2: Procedural guidelines as a recommendation to the national competent authorities Content Introduction... 2 Procedural Guidelines... 2 1. Scope of recommended procedural guidelines... 3 2.

More information

Risk Oversight Committee - Terms of Reference

Risk Oversight Committee - Terms of Reference Risk Oversight Committee - Terms of Reference 1. SCOPE 1.1 PURPOSE The Risk Oversight Committee is responsible for reviewing and reporting its conclusions to the Board on: the Group s risk appetite (the

More information

Environmental Checklist:. 10.Ports and Harbors (1) Yes: Y No: N (a) (b) (c) (d)

Environmental Checklist:. 10.Ports and Harbors (1) Yes: Y No: N (a) (b) (c) (d) Checklist:. 10.Ports and Harbors (1) 1 Permits and Explanation 2 Pollution Control (1) EIA and Permits (2) Explanation to the Local Stakeholders (3) Examination of Alternatives (1) Air Quality (2) Water

More information

Environmental Control Plan

Environmental Control Plan Environmental Control Plan Environmental Control Plan In accordance with Watts & Hughes Construction Waikato Bay of Plenty Limited. corporate strategies the Company has an Environment Control Plan which

More information

REPORT 2016/001 INTERNAL AUDIT DIVISION

REPORT 2016/001 INTERNAL AUDIT DIVISION INTERNAL AUDIT DIVISION REPORT 2016/001 Audit of the recruitment and use of consultants and individual contractors by the Departments of Peacekeeping Operations and Field Support Overall results relating

More information

C O R P O R A T E G O V E R N A N C E S T A T E M E N T

C O R P O R A T E G O V E R N A N C E S T A T E M E N T ACN 066 153 982 2 0 1 7 C O R P O R A T E G O V E R N A N C E S T A T E M E N T C O R P O R A T E G O V E R N A N C E S T A T E M E N T The Board and management of Collaborate Corporation Limited (Collaborate

More information

ENVIRONMENTAL MANAGEMENT PLAN (EMP)

ENVIRONMENTAL MANAGEMENT PLAN (EMP) Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized ENVIRONMENTAL MANAGEMENT PLAN (EMP) BUILDING DISASTER/CLIMATE RESILIENCE IN COMMUNITIES

More information

LETTER G. City of San Diego

LETTER G. City of San Diego LETTER G City of San Diego G-1 The comment provides introductory statements and acknowledges collaboration between interested stakeholders and agency representatives in the development of the proposed

More information

APP s New Mill (OKI) General Information

APP s New Mill (OKI) General Information APP s New Mill (OKI) General Information In July 2013, APP announced the majority share acquisition of PT. OKI Pulp & Paper Mills with detail shareholders: PT. Tjiwi Kimia Tbk, PT. Pindo Deli Tbk and PT.

More information

INLAND WATERWAYS AUTHORITY OF INDIA (Ministry of Shipping, Government of India) Head Office : A-13, Sector 1, Noida

INLAND WATERWAYS AUTHORITY OF INDIA (Ministry of Shipping, Government of India) Head Office : A-13, Sector 1, Noida Project Management Unit (World Bank Assisted Development Project for NW-1) INLAND WATERWAYS AUTHORITY OF INDIA (Ministry of Shipping, Government of India) Head Office : A-13, Sector 1, Noida - 201301 Phone

More information

4 THE ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

4 THE ENVIRONMENTAL IMPACT ASSESSMENT PROCESS 4 THE ENVIRONMENTAL IMPACT ASSESSMENT PROCESS 4.1 INTRODUCTION This Chapter provides a summary of the EIA process that is being followed for the Sasol Pipeline and FSO Project. The process is structured

More information

Procedures for Reviewing EIA Reports

Procedures for Reviewing EIA Reports These procedures are based on the work of Lee, N. and Colley, R. (1990) Reviewing the Quality of Environmental Statements. Occasional Paper Number 24. EIA Centre. University of Manchester and Boyle, J.

More information

CIRCULAR GENERAL PROVISIONS

CIRCULAR GENERAL PROVISIONS MINISTRY OF CONSTRUCTION -------- SOCIALIST REPUBLIC OF VIETNAM Independence - Freedom - Happiness --------------- No. 10/2013/TT-BXD Hanoi, July 25, 2013 CIRCULAR ON CONSTRUCTION QUALITY MANAGEMENT Pursuant

More information

Report for Agenda Item: 2

Report for Agenda Item: 2 QLDC Council 28 September 2017 Department: Planning & Development Report for Agenda Item: 2 Stage 2 Proposed District Plan Notification Purpose The purpose of this paper is to present those parts of Stage

More information

CCSD#1 Stormwater Standards

CCSD#1 Stormwater Standards SECTION 6 EROSION CONTROL STANDARDS 6.1 INTRODUCTION The policies of this section shall apply during construction and until permanent measures are in place following construction as described herein, unless

More information

B&M EUROPEAN VALUE RETAIL S.A. TERMS OF REFERENCE OF THE AUDIT AND RISK COMMITTEE

B&M EUROPEAN VALUE RETAIL S.A. TERMS OF REFERENCE OF THE AUDIT AND RISK COMMITTEE B&M EUROPEAN VALUE RETAIL S.A. TERMS OF REFERENCE OF THE AUDIT AND RISK COMMITTEE These terms of reference have been approved by the board of directors (the "Board") of B&M European Value Retail S.A. (the

More information

Alfa Financial Software Holdings PLC Terms of Reference of The Audit and Risk Committee of The Board of Directors of The Company

Alfa Financial Software Holdings PLC Terms of Reference of The Audit and Risk Committee of The Board of Directors of The Company Alfa Financial Software Holdings PLC Terms of Reference of The Audit and Risk Committee of The Board of Directors of The Company adopted by the board on 15 May 2017 1. Background 1.1 The board has resolved

More information

An Audit of Internal Control Over Financial Reporting Performed in Conjunction with An Audit of Financial Statements

An Audit of Internal Control Over Financial Reporting Performed in Conjunction with An Audit of Financial Statements Page A 1 Standard Appendix Auditing Standard No. 2 AUDITING AND RELATED PROFESSIONAL PRACTICE STANDARDS Auditing Standard No. 2 An Audit of Internal Control Over Financial Reporting Performed in Conjunction

More information

9 ENVIRONMENTAL MANAGEMENT PLAN 9.1 OVERVIEW AND SCOPE Introduction

9 ENVIRONMENTAL MANAGEMENT PLAN 9.1 OVERVIEW AND SCOPE Introduction 9 ENVIRONMENTAL MANAGEMENT PLAN 9.1 OVERVIEW AND SCOPE 9.1.1 Introduction This chapter is the provisional Environmental Management Plan (EMP) for the Jubilee Phase 1 Development project. The elements of

More information

REPORT FORM. TERMINATION OF EMPLOYMENT CONVENTION, 1982 (No. 158)

REPORT FORM. TERMINATION OF EMPLOYMENT CONVENTION, 1982 (No. 158) Appl. 22.158 158. Termination of Employment, 1982 INTERNATIONAL LABOUR OFFICE GENEVA REPORT FORM FOR THE TERMINATION OF EMPLOYMENT CONVENTION, 1982 (No. 158) The present report form is for the use of countries

More information

For personal use only

For personal use only CORPORATE GOVERNANCE STATEMENT 31 MARCH 2017 Horseshoe Metals Limited s (the Company) Board of Directors (Board) is responsible for establishing the corporate governance framework of the Company and its

More information

An Audit of Internal Control Over Financial Reporting Performed in Conjunction with An Audit of Financial Statements

An Audit of Internal Control Over Financial Reporting Performed in Conjunction with An Audit of Financial Statements AUDITING STANDARD No. 2 An Audit of Internal Control Over Financial Reporting Performed in Conjunction with An Audit of Financial Statements March 9, 2004 AUDITING AND RELATED PROFESSIONAL PRACTICE STANDARDS

More information

Circular No. 10/2013/TT-BXD of July 25, 2013, on construction quality management THE MINISTRY OF CONSTRUCTION

Circular No. 10/2013/TT-BXD of July 25, 2013, on construction quality management THE MINISTRY OF CONSTRUCTION THE MINISTRY OF CONSTRUCTION Circular No. 10/2013/TT-BXD of July 25, 2013, on construction quality management Pursuant to the Government s Decree No. 63/2012/ND-CP of August 31, 2012, defining the functions,

More information

AUDIT COMMITTEE TERMS OF REFERENCE

AUDIT COMMITTEE TERMS OF REFERENCE AUDIT COMMITTEE TERMS OF REFERENCE These terms of reference (the Terms of Reference) of the audit committee (the Audit Committee) have been established by the supervisory board (the Supervisory Board)

More information

) ) ) ) ) ) ) ) ) ) ) )

) ) ) ) ) ) ) ) ) ) ) ) 1666 K Street, N.W. Washington, DC 20006 Telephone: (202) 207-9100 Facsimile: (202) 862-8430 www.pcaobus.org PROPOSED AUDITING STANDARD RELATED TO COMMUNICATIONS WITH AUDIT COMMITTEES AND RELATED AMENDMENTS

More information

LAMPIRAN 12. Pertimbangan Lingkungan dan Sosial

LAMPIRAN 12. Pertimbangan Lingkungan dan Sosial LAMPIRAN 12 Pertimbangan Lingkungan dan Sosial APPENDIX 12. ENVIRONEMENTL AND SOCIAL CONSIDERATION 12.1 Relevant Laws and Procedures for Environmental and Social Considerations 12.1.1 Environmental Impact

More information

Aid Program Monitoring and Evaluation Standards

Aid Program Monitoring and Evaluation Standards Aid Program Monitoring and Evaluation Standards Valid from April 2014 to April 2015 Table of Contents Introduction Standard 1: Investment Design (required features for M&E) 5 Standard 2: Initiative Monitoring

More information

Environmental Management Plan Introduction Environmental Management Objectives Structure, Implementation and Review

Environmental Management Plan Introduction Environmental Management Objectives Structure, Implementation and Review Environmental Management Plan Introduction This Environmental Management Plan (EMP) has been prepared for SEF Energy Co. Ltd. for the purpose of providing a stand-alone plan for managing the potential

More information

PT INDONESIA INFRASTRUCTURE FINANCE (SEMS) Printed from llf website on 16 November 2016.

PT INDONESIA INFRASTRUCTURE FINANCE (SEMS) Printed from llf website on 16 November 2016. Public Disclosure Authorized PT INDONESIA SFG2649 SOCIAL AND ENVIRONMENTAL MANAGEMENT SYSTEM Public Disclosure Authorized (SEMS) Public Disclosure Authorized Printed from llf website on 16 November 2016.

More information

On the Revision of the Standards and Practice Standards for. Management Assessment and Audit concerning Internal Control

On the Revision of the Standards and Practice Standards for. Management Assessment and Audit concerning Internal Control (Provisional translation) On the Revision of the Standards and Practice Standards for Management Assessment and Audit concerning Internal Control Over Financial Reporting (Council Opinions) Released on

More information

International Standard on Auditing (UK) 600 (Revised June 2016)

International Standard on Auditing (UK) 600 (Revised June 2016) Standard Audit and Assurance Financial Reporting Council June 2016 International Standard on Auditing (UK) 600 (Revised June 2016) Special Considerations Audits of Group Financial Statements (Including

More information

6 IMPACT ASSESSMENT METHOD

6 IMPACT ASSESSMENT METHOD 6 IMPACT ASSESSMENT METHOD ENTER HERE BACK TO CONTENTS 6 Impact Assessment Method This chapter outlines the methods employed within the EIS specialist technical studies to undertake an assessment of potential

More information

Appendix 4G. Key to Disclosures Corporate Governance Council Principles and Recommendations

Appendix 4G. Key to Disclosures Corporate Governance Council Principles and Recommendations Rules 4.7.3 and 4.10.3 1 Key to Disclosures Corporate Governance Council Principles and Recommendations Introduced 01/07/14 Amended 02/11/15 Name of entity Jadar Lithium Limited ABN / ARBN Financial year

More information

Mapping of Original ISA 315 to New ISA 315 s Standards and Application Material (AM) Agenda Item 2-C

Mapping of Original ISA 315 to New ISA 315 s Standards and Application Material (AM) Agenda Item 2-C Mapping of to 315 s and Application Material (AM) Agenda Item 2-C AM 1. The purpose of this International Standard on Auditing (ISA) is to establish standards and to provide guidance on obtaining an understanding

More information

7. Community Consultation

7. Community Consultation 7. Community Consultation This section provides a summary of the public consultation process implemented for the Project, incorporating the Mine and Rail aspects. The consultation process has been undertaken

More information