JAPAN EARTHQUAKE/TSUNAMI UPDATE
|
|
- Todd Johnson
- 6 years ago
- Views:
Transcription
1 Thursday 28 April 2011 REPORT # SOR JAPAN EARTHQUAKE/TSUNAMI UPDATE Updated reporting on corrective measures being taken by TEPCO still top the headlines as TEPCO releases its latest data concerning radiation levels measured near the plant. Relief operations have been scaled down while Maritime and Air Self-Defense forces return to their original roles in intelligence gathering and surveillance. Regional reporting was minimal with countries lifting radiation alerts and easing the food restrictions.
2 Japan Nuclear Reactor and Radiation Concerns Radiation detected in Fukushima fish, vegetable... 3 TEPCO to rid 200,000 tons of radioactive water... 3 TEPCO monitoring No.1 reactor... 4 TEPCO: Water isn't leaking from No. 4 reactor pool... 4 TEPCO unveils plan to process contaminated water... 5 TEPCO revises nuclear fuel damage ratios... 5 TEPCO worker may have inhaled radioactive material... 6 Japan to scrap workers' annual radiation dose limit at normal times... 6 Radiation measured in the waters and air ( Fukushima Plant )... 7 Recovery/ Relief Operations Defense force quake relief operations to be downsized... 8 Regional Reactions Nuclear Reactor and Radiation Concerns Russia Russia's Far East lifts radiation alert over Japan's nuke plant... 8 Japan will overcome crisis Putin... 9 Malaysia Ease on Japan food products... 9
3 Japan Nuclear Reactor and Radiation Concerns Radiation detected in Fukushima fish, vegetable NHK (4/28/2011) Radioactivity exceeding safety limits has been detected in fish and spinach from Fukushima Prefecture, where the battle to stabilize a disaster-hit nuclear power plant continues. On Tuesday, 2,600 to 3,200 becquerels per kilogram of radioactive cesium was detected in 2 samples of a fish species called the sand lance caught off Iwaki City. That's 5 to 6 times higher than the permissible level. Spinach harvested in Otama Village on Sunday was also found to contain 960 becquerels of cesium. 510 becquerels of cesium was detected in spinach from Tamura City on Monday. The government set the safety standard for the leafy vegetable at 500 becquerels. The government has already banned shipments of some kinds of vegetables and fish harvested or caught in Fukushima Prefecture and is warning people not to eat them. TEPCO to rid 200,000 tons of radioactive water NHK (4/28/2011) The operator of the crippled Fukushima Daiichi nuclear power plant says it aims to begin disposing of highly radioactive water starting in June. The contaminated water is hampering efforts to reactivate the cooling systems in the plant's reactors. On Wednesday, Tokyo Electric Power Company announced it would set up the treatment system to eliminate radioactive materials. The utility firm says 87,500 tons of contaminated water has accumulated in the No.1 to 4 reactors. becomes highly radioactive. It estimates that up to 200,000 tons of highly contaminated water will be produced by the year end if all the water used to cool the reactors The company says it plans to start installing the system in early May and begin operating in June.
4 It hopes to dispose of 1,200 tons of highly contaminated water per day once the system is in place. TEPCO monitoring No.1 reactor NHK (4/28/20011) Tokyo Electric Power Company is monitoring one of the reactors at the Fukushima Daiichi nuclear plant to determine whether more water could be pumped inside to cool the fuel rods. Tokyo Electric plans to submerge the fuel rods at 2 reactors in water by July this year. On Wednesday morning, the utility increased the amount of water injected into the No.1 reactor from 6 tons per hour to 10 tons per hour on an experimental basis. As a result, the temperature at the top of the reactor was degrees Celsius Thursday morning, down 24.7 degrees from before the water increase. The temperature at the bottom of the reactor had dropped 12 degrees to 98.5 degrees Celsius. Pressure inside the reactor containment vessel was also down. Tokyo Electric says it's not yet known how deep the water inside the reactor container is, but that no leakage outside the reactor building has been confirmed. The utility had initially planned to increase the amount of water injected to 14 tons per hour on Wednesday, but it says it will continue to monitor temperatures and pressure through Thursday evening. TEPCO: Water isn't leaking from No. 4 reactor pool NHK (4/28/20011) Tokyo Electric Power Company now says it is unlikely that water is leaking from the spent fuel rod pool of the Fukushima Daiichi power plant's No.4 reactor. Water is being injected into the pool to replace coolant that is evaporating due to the high temperature of its 1,535 spent fuel rods. Despite sporadically injecting 140 to 210 tons of water a day, the company says the water level in the storage pool is still 10 to 40 centimeters lower than estimated. TEPCO initially believed that the pool could have suffered damage in an explosion soon after the March 11th quake and tsunami disaster.
5 But the company said on Wednesday that it now believes that the water has been evaporating at a rate in line with calculations by experts. The storage pool is to be reinforced by July. TEPCO unveils plan to process contaminated water NHK (4/27/2011) Tokyo Electric Power Company has unveiled details of its plan to process radioactive wastewater at its damaged Fukushima Daiichi nuclear power plant. The wastewater has been hampering efforts to restore the reactors' cooling systems. Tokyo Electric announced on Wednesday it would start building early next month, together with US and French firms, a storage and processing facility for nearly 70,000 tons of highly radioactive water. The utility firm aims to begin operating the system in June of this year. The contaminated water is believed to be pooled inside turbine buildings and utility tunnels at the plant's 1, 2 and 3 reactors. Tokyo Electric had earlier said it aims to set up by July of this year a system to remove radioactive substances from the water and reuse it to cool the reactors. Contaminated water will be put through an oil filter, and the density of radioactive material would be lowered using a mineral called zeolite. Salt would then be removed from the water so that it could be used to cool the reactors again. Radioactive waste from this process would be stored inside the nuclear complex, but the utility has yet to consider methods for its final disposal. TEPCO revises nuclear fuel damage ratios NHK (4/27/2011) The operator of the troubled Fukushima Daiichi nuclear plant in northeastern Japan has reassessed its estimates of fuel damage in reactors No.1 to No.3. Tokyo Electric Power Company on Wednesday announced new estimates of damage after the country's nuclear safety agency questioned the accuracy of the initial assessments. The utility has revised the estimated fuel damage in the No.1 reactor from 70 percent to 55 percent, saying radiation levels were not correct. TEPCO also says that it acted inappropriately in excluding fuel damage of less than 5 percent in calculating total damage ratios for the No.2 and No.3 reactors.
6 As a result, the utility revised upward its estimates of damaged fuel in the No.2 and No.3 reactors by 5 percentage points each to 35 percent and 30 percent respectively. The company released its initial estimates as of March 15th, based on radiation levels in the reactors and their containment vessels. Earlier this month, the Nuclear and Industrial Safety Agency raised the crisis level at the Fukushima plant to the highest 7 on the international scale, based on its estimate of the volume of released radioactive substances. TEPCO says the corrected estimates will not affect the agency's crisis rating. TEPCO worker may have inhaled radioactive material NHK (4/28/2011) The Tokyo Electric Power Company says a female employee who was exposed to radiation levels of more than 3 times the safety limit at the Fukushima Daiichi nuclear plant may have inhaled radioactive substances when indoors. The woman, in her 50s, was in charge of material management at the plant. She was found to have been exposed to millisieverts of radiation. This is more than triple the 3-month limit for a female worker, which is set at 5 millisieverts. Closer examination has revealed that the woman suffered 13.6 millisieverts of internal radiation exposure. The woman was in a building which was contaminated by high-level radioactive substances following a hydrogen explosion on March 12th. She may have inhaled some of the airborne radioactive material as she wasn't wearing a protective mask. TEPCO has apologized for its lack of precautions against internal radiation exposure. Two more female workers who were in the same building may have also exceeded their exposure limit. The government's nuclear safety agency has demanded that the utility find out why this happened and draw up prevention measures. Japan to scrap workers' annual radiation dose limit at normal times Mainichi Daily (4/28/2011) The health ministry plans to scrap the annual radiation dose limit for nuclear power plant workers at normal times for the meantime to secure enough workers for maintenance and checkups of nuclear power plants other than the crisis-hit Fukushima power station, sources close to the matter said Wednesday.
7 Under Japanese law, nuclear workers cannot be exposed to more than 50 millisieverts in one year and more than 100 millisieverts over five years. The ministry, however, is expected to maintain the 100-millisievert rule, as there is medical evidence that exposure to radiation exceeding 100 millisieverts could increase the risk of developing leukemia and cancer, according to the sources. The move comes as many nuclear workers are being sent to deal with the emergency situation at the radiation-leaking Fukushima Daiichi nuclear power plant, although there are only 70,000 people nationwide who can engage in work at such plants. As workers would not be able to work at other plants once they exceed their radiation dose limit by dealing with the Fukushima crisis, the industry ministry has been calling on the Ministry of Health, Labor and Welfare to ease the limit to prevent a possible shortage of such workers. To cope with the Fukushima crisis, the health ministry raised the legal limit on the amount of radiation to which each worker could be exposed in an emergency situation to 250 millisieverts from 100 millisieverts on March 15. But the limit for nuclear workers at normal times was not changed. In the United States, the limit for civilians is 100 millisieverts in an emergency situation. Civilians should not be exposed to more than 50 millisiverts annually in normal times and more than 100 millisieverts over five years. Tokyo Electric Power Co., which owns the crippled Fukushima Daiichi power station, said that 30 people who worked at the plant were exposed to 100 millisieverts or more. Radiation measured in the waters and air ( Fukushima Plant ) NHK Science & Culture Blog (4/27/2011) Radiation measured in the waters and air near the No.1 Fukushima Nuclear Power Plant (Source: Tokyo Electric Power Co. TEPCO) No.1 Plant : Radioactive substances detected in the waters From samples collected 30 meters north of the outlets of the Unit 5-6 at 14:30 April 26. Iodine 131: Bq/cc (2.2 times the limit) Cesium 134: 0.21 Bq/cc (3.5 times the limit) Cesium 137: 0.23 Bq/cc (2.6 times the limit) From samples collected 330 meters south of the outlets of the Unit 1-4 at 14:10 April 26. Iodine 131: Bq/cc (0.68 times the limit) Cesium 134: 0.13 Bq/cc (2.2 times the limit) Cesium 137: 0.13 Bq/cc (1.4 times the limit)
8 Recovery/ Relief Operations Defense force quake relief operations to be downsized Kyodo News (4/28/2011, No Link Available) Defense Minister Toshimi Kitazawa said Thursday the Defense Ministry will scale back disaster relief operations by Maritime and Air self-defense forces personnel while maintaining the strength of ground force teams. ''The MSDF and ASDF will have to return to their original roles in intelligence gathering and surveillance as the need for them to transport supplies and rescue people is slightly changing,'' Kitazawa told a news conference. On the Ground Self-Defense Force troops engaged in providing support to the victims and searching for the missing people, Kitazawa said, ''I will not let disaster-hit victims lose the sense of security provided by having uniformed SDF personnel near them.'' In the largest-ever deployment of SDF personnel, around 100,000 were mobilized for relief efforts in the wake of the 9.0-magnitude earthquake and tsunami on March 11 that devastated Japan's northeastern and eastern regions, and the ensuing nuclear crisis at the Fukushima Daiichi plant. Regional Reactions Nuclear Reactor and Radiation Concerns Russia Russia's Far East lifts radiation alert over Japan's nuke plant Kyodo, Japan (4/27/2011) The governor of Russia's Pacific Maritime region said Wednesday the region has lifted an alert issued in the wake of an accident at Japan's Fukushima Daiichi nuclear power plant. Sergei Darkin, the territory's governor, announced the lifting of the alert, saying abnormal levels of radioactive materials have yet to be measured in the Far East of Russia. The governor said he can say with confidence that the radiation level in the territory poses no threat to human health, adding that the territory will continue to measure the level of radioactive materials. The Fukushima Daiichi nuclear plant, located about 220 kilometers from Tokyo, was damaged by the March 11 massive earthquake and tsunami, and the severity level of the emergency at the plant was recognized as the maximum level 7 on an international scale, matching the 1986 Chernobyl catastrophe.
9 Japan will overcome crisis Putin Voice of Russia, Russia (4/27/2011) Russia is confident that Japan will overcome the consequences of the earthquake, tsunami and the disaster at the Fukushima nuclear power plant, Prime Minister Vladimir Putin said in Moscow Wednesday. Speaking at the opening ceremony of Figure Skating World Championship he said We are confident that the Japanese people and government will overcome this hard way with courage and dignity and resolve all the problems, he said. In Russia we know firsthand what a nuclear disaster is, Putin said meaning the terrible disaster on the Chernobyl NPP, which 25 anniversary was marked earlier this week. Moscow took over Japan to host Figure Skating World Championship after it became impossible for Japan following the disaster at Fukushima-1 nuclear power plant. Malaysia Ease on Japan food products The Star, Malaysia (4/28/2011) Malaysia will accept food products from Japan certified by the Japanese Competent Authority. Health Minister Datuk Seri Liow Tiong Lai said the decision, effective yesterday, was in tandem with the improving situation at the Fukushima nuclear reactor following the March 11 tsunami disaster in Japan. The certification would state that the food was harvested or processed before March 11 and that it is from prefectures other than Fukushima, Gunma, Ibaraki, Tochigi, Miyagi, Yamagata, Niigata, Kanagawa, Saitama, Tokyo and Chiba. If the food comes from these areas, samples and analyses (test results) for radioactive Iodine- 131, Cesium-134, Cesium-137 have to adhere to the Codex (Alimentarius) standards stated in the certificate, Liow said. The move followed discussions between the two countries on control measures, he said, adding that other countries had also reduced their surveillance levels. On March 16, the ministry implemented Level 5 surveillance checks on food imported from Japan. On April 15, it adopted radioactivity certification on all food items from Japan.
10 Liow said up to now, 229 food samples from Japan had been taken and they all adhered to the Codex standards. On another issue, Liow clarified he did not say that nasi lemak would not be allowed in school canteens. What I mentioned in the past was for students to go for a healthy balanced diet and not just one type of food, he said. He added that a committee comprising representatives from his ministry and the Education Ministry was looking into the kind of food to be served in school canteens. Meanwhile, outgoing Japanese ambassador Masahiko Horie said he was glad Malaysia had accepted the certification from Japan. He also said those who had booked to travel to Japan should not cancel their plans. They can travel anywhere except Fukushima and its surrounding areas. The government checks on food products and will dispose them if they are found to be unsafe, said Horie during his farewell lunch attended by Liow yesterday. Horie, who turns 65 in July, will be leaving Malaysia today to take up the post of adviser with the Japanese foreign ministry.
Information on Status of Nuclear Power Plants in Fukushima
Information on Status of Nuclear Power Plants in Fukushima Japan Atomic Industrial Forum, Inc. Policy on information and compilation This JAIF-compiled information chart represents the situation, phenomena,
More informationInformation on Status of Nuclear Power Plants in Fukushima
Information on Status of Nuclear Power Plants in Fukushima Japan Atomic Industrial Forum, Inc. Policy on information and compilation This JAIF-compiled information chart represents the situation, phenomena,
More informationInformation on Status of Nuclear Power Plants in Fukushima
Information on Status of Nuclear Power Plants in Fukushima Japan Atomic Industrial Forum, Inc. Policy on information and compilation This JAIF-compiled information chart represents the situation, phenomena,
More informationInformation on Status of Nuclear Power Plants in Fukushima
Information on Status of Nuclear Power Plants in Fukushima Japan Atomic Industrial Forum, Inc. Policy on information and compilation This JAIF-compiled information chart represents the situation, phenomena,
More informationInformation on Status of Nuclear Power Plants in Fukushima
Information on Status of Nuclear Power Plants in Fukushima Japan Atomic Industrial Forum, Inc. Policy on information and compilation This JAIF-compiled information chart represents the situation, phenomena,
More informationOverview of Events at Fukushima Dai-ichi Nuclear Power Plant
Overview of Events at Fukushima Dai-ichi Nuclear Power Plant 23 March 2011 Luis Echávarri Javier Reig John Nakoski Ted Lazo 2011 Organisation for Economic Co-operation and Development 1 Outline of Presentation
More informationFukushima Daiichi Status Report
Fukushima Daiichi Status Report 24 November 2011 The IAEA issues regular status reports to the public on the current status of the Fukushima Daiichi Nuclear Power Plant, including information on environmental
More informationGreat East Japan Earthquake and the seismic damage to the NPSs
Great East Japan Earthquake and the seismic damage to the NPSs As of 12:00 May 10th, 2011 (JST) Ministry of Economy, Trade and industry Earthquake and automatic shut-down of nuclear reactors The Great
More informationResponse to Nuclear Emergency Situation - Viewpoints of Crisis Management -
3 rd meeting, material 6 Response to Nuclear Emergency Situation - Viewpoints of Crisis Management - February 2015 Nuclear Regulation Authority Material 3 Response to nuclear disasters Act on Special Measures
More informationTohoku Pacific Earthquake and the seismic damage to the NPSs
Tohoku Pacific Earthquake and the seismic damage to the NPSs As of 15:30 March 30th, 2011 (JST) Ministry of Economy, Trade and industry Earthquake and automatic shut-down of nuclear reactors The Tohoku
More information1. Situation of radiation exposure concerning radiation workers and other related workers
VII. Situation regarding Radiation Exposure 1. Situation of radiation exposure concerning radiation workers and other related workers (1) Dose limit for radiation workers 1) Provision of dose limit prior
More informationStatus of the Fukushima Daiichi Nuclear Power Plant Updated information ( at 1300hrs) (Prepared by Health Safety & Environment Group)
Status of the Fukushima Daiichi Nuclear Power Plant Updated information (21-04-2011 at 1300hrs) (Prepared by Health Safety & Environment Group) 1. Current Situation Overall, the situation at the Fukushima
More informationDr. Keiji Kijima Secretary General IPEC Japan
Dr. Keiji Kijima Secretary General IPEC Japan * *I wish to express my gratitude to the good will sent to the Tohoku and Kanto earthquake. The Japanese Pharmacopoeia 16 th Edition was promulgated in March
More informationFukushima-Daiichi Accident Information note n 2 of the 8 April 2011
Fukushima-Daiichi Accident Information note n 2 of the 8 April 2011 This information note, intended for French citizens in Japan, was drawn up by IRSN, the French Institute for Radiological Protection
More informationInformation on Status of Nuclear Power Plants in Fukushima
Information on Status of Nuclear Power Plants in Fukushima Japan Atomic Industrial Forum, Inc. Policy on information and compilation This JAIF-compiled information chart represents the situation, phenomena,
More informationInformation on Status of Nuclear Power Plants in Fukushima
Information on Status of Nuclear Power Plants in Fukushima Japan Atomic Industrial Forum, Inc. Policy on information and compilation This JAIF-compiled information chart represents the situation, phenomena,
More informationTEPCO s Nuclear Power Plants suffered from big earthquake of March 11,2011
TEPCO s Nuclear Power Plants suffered from big earthquake of March 11,2011 Follow up prepared at 4pm of March 23 in Japan Yoshiaki Oka Waseda university Recovery action is in progress. The presentation
More informationInformation on Status of Nuclear Power Plants in Fukushima
Information on Status of Nuclear Power Plants in Fukushima Japan Atomic Industrial Forum, Inc. Policy on information and compilation This JAIF-compiled information chart represents the situation, phenomena,
More informationInformation on Status of Nuclear Power Plants in Fukushima
Information on Status of Nuclear Power Plants in Fukushima Japan Atomic Industrial Forum, Inc. Policy on information and compilation This JAIF-compiled information chart represents the situation, phenomena,
More informationInformation on Status of Nuclear Power Plants in Fukushima
Information on Status of Nuclear Power Plants in Fukushima Japan Atomic Industrial Forum, Inc. Policy on information and compilation This JAIF-compiled information chart represents the situation, phenomena,
More informationPresentation Outline. Basic Reactor Physics and Boiling Water Design Sequence of Events Consequences and Mitigation Conclusions and Lessons Learned
Response of the Fukushima Dai-ichi Nuclear Plant to the March 11, 2011 Earthquake in Japan Dr. George Flanagan Oak Ridge National Laboratory Presented to the EERI/NEC Meeting April 12, 2012 Presentation
More informationFukushima Accident Summary(4) 2011-August-02, Ritsuo Yoshioka
No.58 Fukushima Accident Summary(4) 2011-August-02, Ritsuo Yoshioka 3.4 Fukushima-4 Reactor When the earthquake and tsunami occurred on March 11th, Fukushima Unit 4 (F4) was in its periodic shut-down stage,
More informationExperience feedback on the Fukushima NPS accident- Sanitary and environmental consequences
Experience feedback on the Fukushima NPS accident- Sanitary and environmental consequences Harald Thielen (GRS), Olivier Isnard (IRSN), Kurt Couckvyt (BelV), Harutaka Hoshi (JNES), Serge Lobach (SSTC NRS)
More informationTohoku Pacific Earthquake and the seismic damage to the NPSs
Tohoku Pacific Earthquake and the seismic damage to the NPSs As of 8:00am April 5th, 2011 (JST) Ministry of Economy, Trade and industry Earthquake and automatic shut-down of nuclear reactors The Tohoku
More informationReport to the Foreign Academies from Science Council of Japan on the Fukushima Daiichi Nuclear Power Plant Accident
Report to the Foreign Academies from Science Council of Japan on the Fukushima Daiichi Nuclear Power Plant Accident May 2, 2011 Great East Japan Earthquake Taskforce Science Council of Japan http://www.scj.go.jp/en/index.html
More informationTEPCO s Nuclear Power Plants suffered from big earthquake of March 11,2011
TEPCO s Nuclear Power Plants suffered from big earthquake of March 11,2011 Follow up prepared at 4pm of March 23, revised 1pm of March 31 Yoshiaki Oka Waseda university Recovery action is in progress.
More informationProposals for Reducing the Danger of Spent Fuel Pool Fires: The U.S. Nuclear Regulatory Commission s (NRC s) Response
Proposals for Reducing the Danger of Spent Fuel Pool Fires: The U.S. Nuclear Regulatory Commission s (NRC s) Response Frank von Hippel Program on Science and Global Security, Princeton University Tokyo,
More informationFukushima Daiichi Disaster. Facts and lessons learned. July Takashi Shoji Programme Director of WANO
Fukushima Daiichi Disaster Facts and lessons learned July 13 2011 Takashi Shoji Programme Director of WANO 7/12/2011 1 Earthquake occurrence and automatic shut-down of nuclear reactors The Tohoku Pacific
More informationThe Great East Japan Earthquake and Efforts to ensure the Safety of Food
The Great East Japan Earthquake and Efforts to ensure the Safety of Food June 30, 2011 Government of Japan 1 Japan Faces an Unprecedented Challenge (Enormous Earthquake, Tsunamis and Nuclear Accident)
More informationJapan s Nuclear Emergency - Update - April 6, 2011 Ministry of Economy, Trade and Industry Government of Japan
Japan s Nuclear Emergency - Update - April 6, 2011 Ministry of Economy, Trade and Industry Government of Japan Table of Contents A. Japan Faces an Unprecedented Challenge (Enormous Earthquake, Tsunamis
More informationInformation on Status of Nuclear Power Plants in Fukushima
Information on Status of Nuclear Power Plants in Fukushima Japan Atomic Industrial Forum, Inc. Policy on information and compilation This JAIF-compiled information chart represents the situation, phenomena,
More informationJapan s Activities for Environmental Remediation after Fukushima Daiichi Nuclear Power Plant Accident
Japan s Activities for Environmental Remediation after Fukushima Daiichi Nuclear Power Plant Accident Radioisotope Association Kenkich ISHIGURE 1. Situation at Fukushima Daiichi NPP 2. Environmental Remediation
More informationFukushima Accident Summary(3) 2011-July-17, Ritsuo Yoshioka (Text in blue are Yoshioka s comments) 1) Earthquake and Tsunami
Fukushima Accident Summary(3) 2011-July-17, Ritsuo Yoshioka (Text in blue are Yoshioka s comments) 1) Earthquake and Tsunami 14:46 March 11th 2011 (Please see Summary-1 report for detail.) Tohoku Pacific
More informationInformation on Status of Nuclear Power Plants in Fukushima
Information on Status of Nuclear Power Plants in Fukushima Japan Atomic Industrial Forum, Inc. Policy on information and compilation This JAIF-compiled information chart represents the situation, phenomena,
More informationOn the issue of the reconstruction, the government is considering the big picture of
Press Conference by Noriyuki Shikata, Deputy Cabinet Secretary for Public Relations of the Prime Minister s Office for members of the foreign press 24 March 2011 Mr. Noriyuki Shikata, Deputy Cabinet Secretary
More informationThe Fukushima Daiichi Nuclear Power Plant Accident: A Provisional Analysis and Survey of the Government s International & Domestic Response
The Fukushima Daiichi Nuclear Power Plant Accident: A Provisional Analysis and Survey of the Government s International & Domestic Response Kanami Ishibashi 1 On March 11, 2011 at 14:46, Japan was hit
More information30 May 2013, Villingen- Schwenningen, Germany
Statement by IPPNW Board of Directors on the ongoing nuclear disaster in Japan and the report of the UN Special Rapporteur on the right to health to the UN Human Rights Council 30 May 2013, Villingen-
More informationInformation on Status of Nuclear Power Plants in Fukushima
Information on Status of Nuclear Power Plants in Fukushima Japan Atomic Industrial Forum, Inc. Policy on information and compilation This JAIF-compiled information chart represents the situation, phenomena,
More informationReflecting on the three years after 3/11
Reflecting on the three years after 3/11 Wim C. Turkenburg Copernicus Institute - Utrecht University - The Netherlands w.c.turkenburg@uu.nl Symposium Hope Step Japan, Amsterdam 8 March 2014 Copernicus
More information1. What happened at Fukushima Daiichi five years ago on 11 March 2011?
On 11 March 2011, at 2:46 p.m. local time (6.46 a.m. CET), an earthquake measuring 9 on the Richter scale hit the east coast of Japan. The quake caused a tsunami, with waves as high as 38 metres, which
More informationRadioactive water from Japan nuclear plant leaks in sea
2 April 2011 Last updated at 08:55 GMT Radioactive water from Japan nuclear plant leaks in sea Please turn on JavaScript. Media requires JavaScript to play. Click to play Japan's PM Naoto Kan made his
More informationIAEA International Missions (2013) to Japan on Fukushima-D NPP decommissioning and on off-site remediation
IAEA/UNESCO Technical Meeting on Groundwater Contamination following the Fukushima Nuclear Accident ----- IAEA International Missions (2013) to Japan on Fukushima-D NPP decommissioning and on off-site
More informationInformation on Status of Nuclear Power Plants in Fukushima
Information on Status of Nuclear Power Plants in Fukushima Japan Atomic Industrial Forum, Inc. Policy on information and compilation This JAIF-compiled information chart represents the situation, phenomena,
More informationInformation on Status of Nuclear Power Plants in Fukushima
Information on Status of Nuclear Power Plants in Fukushima Japan Atomic Industrial Forum, Inc. Policy on information and compilation This JAIF-compiled information chart represents the situation, phenomena,
More informationResponse to the Nuclear Emergency at TEPCO s Fukushima Nuclear Power Stations
Response to the Nuclear Emergency at TEPCO s Fukushima Nuclear Power Stations Nuclear Emergency Response Headquarters Government of Japan June 20-24, 2011 IAEA Ministerial Conference on Nuclear Safety
More informationGreat East Japan Earthquake and the seismic damage to the NPSs
Great East Japan Earthquake and the seismic damage to the NPSs As of 12:00am June 29th, 2011 (JST) Ministry of Economy, Trade and industry Earthquake and automatic shut-down of nuclear reactors The Great
More informationRadiation in Japan Seas: Risk of Animal
Page 1 of 5 Radiation in Japan Seas: Risk of Animal Death, Mutation? More radiation from nuclear plant could cause "bizarre mutations." Aboard a boat pulling a barge with water for Japan's overheating
More informationProgress Status Classified by Countermeasures
Progress Status Classified by :Progressed (Legend color changed) Legend Implemented Under construction Field work started, but construction not started Appendix 2 Field work not started yet Areas Issues
More informationProgress of Medium- and Long-term Efforts to Decommission Fukushima Dai-ichi NPP of TEPCO (Statement)
Progress of Medium- and Long-term Efforts to Decommission Fukushima Dai-ichi NPP of TEPCO (Statement) November 27, 2012 Japan Atomic Energy Commission Tokyo Electric Co., Ltd. (TEPCO) announced the Roadmap
More informationX. Future Efforts to Settle the Situation regarding the Accident
X. Future Efforts to Settle the Situation regarding the Accident 1.The current status of reactors etc. of Fukushima Dai-ichi NPS In reactors of Fukushima Dai-ichi NPS in Units 1, 2 and 3, fresh water has
More informationPress briefing at the Prime Minister s Office for members of the foreign press
Press briefing at the Prime Minister s Office for members of the foreign press 20 April 2011 Mr. Noriyuki Shikata, Deputy Cabinet Secretary for Public Relations: Good evening, we are starting this evening
More informationImmediate Countermeasures
September 3, 2013 Agency for Natural Resources and Energy, METI of Japan 2 nd Fact sheet: Overview of Contaminated Water Issue at TEPCO s Fukushima Daiichi NPS On June 19, 2013, TEPCO announced that ground
More informationThe Nuclear Crisis in Japan
The Nuclear Crisis in Japan March 21, 2011 Daniel Okimoto Alan Hanson Kate Marvel The Fukushima Daiichi Incident 1. Plant Design 2. Accident Progression 3. Radiological releases 4. Spent fuel pools " Fukushima
More informationThe Fukushima Daiichi Incident Dr. Matthias Braun - 19 May p.1
Dr. Matthias Braun - 19 May 2011 - p.1 The Fukushima Daiichi Incident 1. Plant Design 2. Accident Progression 3. Radiological releases 4. Spent fuel pools 5. Sources of Information Matthias Braun PEPA4-G,
More informationImplementation Plan of the measures to be taken at Fukushima Daiichi Nuclear Power Station designated as a Specified Reactor Facility (outline)
Implementation Plan of the measures to be taken at Fukushima Daiichi Nuclear Power Station designated as a Specified Reactor Facility (outline) December 7, 2012 Tokyo Electric Power Company 1 1. Post-Earthquake
More information-Update - Ministry of Economy, Trade and Industry Government of Japan
Japan s Nuclear Emergency -Update - April 6, 2011 Ministry of Economy, Trade and Industry Government of Japan Table of Contents A. Japan Faces an Unprecedented Challenge (Enormous Earthquake, Tsunamis
More informationInformation on Status of Nuclear Power Plants in Fukushima
Information on Status of Nuclear Power Plants in Fukushima Japan Atomic Industrial Forum, Inc. Policy on information and compilation This JAIF-compiled information chart represents the situation, phenomena,
More informationOVER VIEW OF ACCIDENT OF FUKUSHIMA DAI-ICHI NPSs AND FUTURE PLANNING TOWARD D&D
OVER VIEW OF ACCIDENT OF FUKUSHIMA DAI-ICHI NPSs AND FUTURE PLANNING TOWARD D&D 16 NOVEMBER, 2011 Hiroshi RINDO JAPAN ATOMIC ENERGY AGENCY Table of Contents 1. What s happened at Fukushima Dai-Ichi NPSs
More informationEfforts to Decommission the TEPCO Fukushima Daiichi Nuclear Power Station
Efforts to Decommission the TEPCO Fukushima Daiichi Nuclear Power Station By Nuclear Accident Response Office, Agency for Natural Resources & Energy, Ministry of Economy, Trade & Industry Introduction
More informationTEPCO s Nuclear Power Plants suffered from big earthquake of March 11,2011
TEPCO s Nuclear Power Plants suffered from big earthquake of March 11,2011 Follow up prepared at 4pm of March 23, revised April 13 Yoshiaki Oka Waseda university Recovery action is in progress. The presentation
More informationII.-1. Major nuclear power facilities in Japan
II.-1. Major nuclear power facilities in Japan In Japan, there are 50 operable nuclear reactors in nuclear power plants in 17 locations and 6 reactors which are under decommissioning. In addition to these
More informationThe Fukushima Daiichi Incident Dr. Matthias Braun - 16 November p.1
Dr. Matthias Braun - 16 November 2012 - p.1 The Fukushima Daiichi Incident 1. Plant Design 2. Accident Progression 3. Radiological releases 4. Spent fuel pools 5. Sources of Information Matthias Braun
More informationLessons from Fukushima
Connecting the Dots on Energy Issues May 16, 2011 Vol. 4 Issue 6 1111 19 th St. NW Suite 406 Washington, DC 20036 tel: 202-461-2360 fax: 202-461-2379 secureenergy.org Lessons from Fukushima SUMMARY Even
More informationHOW TO FACE CONCERNS OF RADIATION EFFECTS
1 Provisional Translation Document 2 Second Meeting Working Group on Voluntary Efforts and Continuous Improvement of Nuclear Safety, Advisory Committee for Natural Resources and Energy HOW TO FACE CONCERNS
More informationMasahiro SHIZU Deputy Director Arms Control and Disarmament Division Ministry of Foreign Affairs, JAPAN
CEG Workshop on Predisposal of Legacy Radioactive Waste : Treatment, Conditioning and Storage,17-19 May 2011, Heringsdorf, Germany Masahiro SHIZU Deputy Director Arms Control and Disarmament Division Ministry
More informationCurrent Situation of Ports and Shipping in Japan after the Fukushima Dai-ichi Nuclear Power Plant Accident
Current Situation of Ports and Shipping in Japan after the Fukushima Daiichi Nuclear Power Plant Accident 25th April, 2011 Maritime Bureau/Ports and Harbors Bureau Ministry of Land, Infrastructure, Transport
More informationEmployment Policy in Areas Devastated by the Great East Japan Earthquake
Employment Policy in Areas Devastated by the Great East Japan Earthquake December 5, 2011 The Special Session by the Japanese Government Yoshio Maki Senior Vice-Minister for Health, Labor and Welfare,
More informationThe Cost of Power: Is a Carbon Neutral Society Feasible?
The Cost of Power: Is a Carbon Neutral Society Feasible? We are often presented with economic cost of power graphs: how should we interpret these? What sorts of questions should we ask? Education = Learning
More informationWHAT HAPPENED, WHAT IS GOING ON IN FUKUSHIMA NO.1 NUCLEAR POWER STATION?
WHAT HAPPENED, WHAT IS GOING ON IN FUKUSHIMA NO.1 NUCLEAR POWER STATION? Yoichiro Shimazu Research Institute of Nuclear Engineering University of Fukui WHERE IS FUKUSHIMA NUCLEAR POWER STATION? Sapporo
More informationFukushima: Contaminated Water Out of Control
Background:April22,2014 Irradiatednuclearfuelmustbecooledforseveralyearstoprevent itfromoverheatingandreleasingradioactivematerialsintothe atmosphere.theirradiatedfuelitselfhasbecomesointensely radioactivethatitcontinuouslygeneratesheatfromthe
More informationBackground and Current Situation of Restricted Areas and Areas to Which Evacuation Orders Have Been Issued
Basic Concept and Issues to be Challenged for Rearranging the Restricted Areas and Areas to which Evacuation Orders Have been Issued where Step 2 has been Completed December 26, 2011 Nuclear Emergency
More informationAttachment XI-1. I. Emergency Safety Measures, etc.
Specific Countermeasures in Japan Based on the Lessons Learnt from the Accident at Fukushima Dai-ichi Nuclear Power Station of Tokyo Electric Power Co. Inc. I. Emergency Safety Measures, etc. 1. Emergency
More informationSTATUS OF THE FUKUSHIMA DAIICHI SITE AND THE REMAINING RISKS
STATUS OF THE FUKUSHIMA DAIICHI SITE AND THE REMAINING RISKS NURIS 2015 1 st INRAG Conference on Nuclear Risk 16-17.04.2015 BOKU, Vienna Dr. G. Kastchiev Member of INRAG 1 STATUS OF THE FUKUSHIMA SITE
More informationDeconstructing the Nuclear Accident at the Fukushima-Daiichi Plant: What Went Wrong and What are the Prospects of Recovery?
Deconstructing the Nuclear Accident at the Fukushima-Daiichi Plant: What Went Wrong and What are the Prospects of Recovery? Goldschmidt Conference 2011 Fukushima Review Session Prague, Czech Republic Edward
More informationJapan s Challenge Towards Recovery
2011/SMEMM/006 Agenda Item: 2.3 Japan s Challenge Towards Recovery Purpose: Information Submitted by: Japan 18 th Small and Medium Enterprises Ministerial Meeting Big Sky, United States 21 May 2011 Japan
More informationA Liquidation Strategy of Fukushima Daiichi Nuclear Power Plant: A new In-Situ Entombment Plan proposed
A Liquidation Strategy of Fukushima Daiichi Nuclear Power Plant: A new In-Situ Entombment Plan proposed May 27, 2011 Satoshi Sato satoshi@sato@iacdc.com International Access Corporation Abstract I studied
More informationGovernment Actions to Ensure the Safety of Beef and Other Food
Government Actions to Ensure the Safety of Beef and Other Food August 29, 2011 The Government of Japan Table of Contents I. The Detection of Radioactive cesium which exceeds the provisional regulation
More informationMEXT Nuclear Energy R&D
Tokyo, 1 th November 2011 MEXT Nuclear Energy R&D Masaaki NISHIJO Director, Office for Nuclear Fuel Cycles, Ministry of Education, Culture, Sports, Science and Technology (MEXT) 1 Future Nuclear Energy
More informationXII. Lessons Learned From the Accident Thus Far
XII. Lessons Learned From the Accident Thus Far The Fukushima NPS accident has the following aspects: it was triggered by a natural disaster; it led to a severe accident with damage to nuclear fuel, Reactor
More informationNUCLEAR ENERGY AND THE GLOBAL URANIUM MARKET POST FUKUSHIMA
6 June 2011 Dear Toro Energy shareholder, NUCLEAR ENERGY AND THE GLOBAL URANIUM MARKET POST FUKUSHIMA I write to you to provide an update to Toro Energy s view of the impact on the nuclear power industry
More informationKNOWLEDGE NOTE 1-5. Protecting Significant and Sensitive Facilities. CLUSTER 1: Structural Measures. Public Disclosure Authorized
KNOWLEDGE NOTE 1-5 CLUSTER 1: Structural Measures Protecting Significant and Sensitive Facilities Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure
More informationThe Fukushima Nuclear Tragedy. by Clifford Hampton
The Fukushima Nuclear Tragedy by Clifford Hampton Table of contents I. History of the Fukushima Nuclear Tragedy II. Basic technical aspects of the nuclear reactor and its history III. Safety culture of
More informationRevised Mid-and-Long-Term Roadmap towards the Decommissioning of TEPCO s Fukushima Daiichi NPP Units 1-4
Revised Mid-and-Long-Term Roadmap towards the Decommissioning of TEPCO s Fukushima Daiichi NPP Units 1-4 Tatsuya Shinkawa Director, Nuclear Accident Response Office, Agency for Natural Resources and Energy,
More informationJAPAN EARTHQUAKE/TSUNAMI UPDATE
Wednesday 23 March 2011 REPORT # SOR-009-11 JAPAN EARTHQUAKE/TSUNAMI UPDATE Work progress on the reactors still top the headlines as media reactions on the spread of radiation and its effects remain highly
More informationInformation on the earthquake in Japan on 11 March Compilation by GRS. as at 25 March 2011, 10:00 h (CET)
Information on the earthquake in Japan on 11 March 2011 Compilation by GRS as at 25 March 2011, 10:00 h (CET) All times local time unless otherwise indicated (CET = local time minus 8 hours) Updated compilation
More informationIntroduction to the Accident at Fukushima Dai-ichi Nuclear Power Station
Introduction to the Accident at Fukushima Dai-ichi Nuclear Power Station Richard Wakeford Professor in Epidemiology, Institute of Population Health and Dalton Nuclear Institute, The University of Manchester,
More information24 MARCH :00 UTC. Incident and Emergency Centre
24 MARCH 2011 17:00 UTC Incident and Emergency Centre Subject: Status of the Fukushima Daiichi nuclear power plant The Incident and Emergency Centre (IEC) is continuing to monitor the status of the nuclear
More informationEliminating Negative Reputation Impact
Eliminating Negative Reputation Impact ~ Reconstruction from Nuclear Disaster & the History of Safety and Revitalization of Fukushima ~ October, 217 New Stage towards Reconstruction & Revitalization Changes
More informationJapanese Nuclear Accident And U.S. Response. Ellen Anderson Senior Project Manager Radiation Safety & Environmental Protection May 20, 2011
Japanese Nuclear Accident And U.S. Response Ellen Anderson Senior Project Manager Radiation Safety & Environmental Protection May 20, 2011 Overview Introduction to NEI Fukushima Daiichi The Events Environmental
More informationNuclear Accident at Fukushima #1Nuclear Power Station
Nuclear Accident at Fukushima #1Nuclear Power Station By Prof. Dr. Yoichi Fuji-ie, Representative Director of Nuclear Salon Fuji-ie 1. Brief Observation of Fukushima#1 Nuclear Accident On March 11 2011,
More information15 April 2015 Nuclear Regulation Authority, Japan. 1. Overview
Evaluation of the report of Tokyo Electric Power Company regarding the inflow of water that accumulated in the process main building into the incineration building at the Fukushima Daiichi Nuclear Power
More informationDevelopment of technologies for the processing and disposal of radioactive waste
Development of technologies for the processing and disposal of radioactive waste International Experts' Symposium on the Decommissioning of TEPCO's Fukushima Daiichi Nuclear Power Plant Unit 1-41 March
More informationThe Fukushima Daiichi Incident
The data and information contained herein are provided solely for informational purposes. None of the information or data is intended by AREVA to be a representation or a warranty of any kind, expressed
More informationMid-and-long-Term Roadmap towards the Decommissioning of Fukushima Daiichi Nuclear Power Station Units 1-4, TEPCO
(Provisional translation) Mid-and-long-Term Roadmap towards the Decommissioning of Fukushima Daiichi Nuclear Power Station Units 1-4, TEPCO December 21, 2011 Nuclear Emergency Response Headquarters Government
More informationNuclear energy - four months after Fukushima
Institut»Jožef Stefan«Odsek za reaktorsko tehniko Nuclear energy - four months after Fukushima Iztok Tiselj "Jožef Stefan Institute", Reactor Engineering Division & Chair of Nuclear Engineering, Faculty
More informationInformation on the current status of the plants in Japan damaged by the earthquake and the subsequent tsunami on 11 March Compilation by GRS
Information on the current status of the plants in Japan damaged by the earthquake and the subsequent tsunami on 11 March 2011 Compilation by GRS as at 15 April 2011, 12:30 h (CEST) All times local time
More informationImmediate Countermeasures
September 3, 2013 Agency for Natural Resources and Energy, METI of Japan 2 nd Fact sheet: Overview of Contaminated Water Issue at TEPCO s Fukushima Daiichi NPS On June 19, 2013, TEPCO announced that ground
More informationJoint ISTC/STCU Chernobyl Fukushima Symposium held in Japan
Joint ISTC/STCU Chernobyl Fukushima Symposium held in Japan In Tokyo and Fukushima on February 3 rd and 4 th ISTC/ STCU held a joint Symposium and Seminar with Japanese nuclear experts on The Experience
More informationThe 2011 Tohoku Pacific Earthquake and Current Status of Nuclear Power Stations
The 2011 Tohoku Pacific Earthquake and Current Status of Nuclear Power Stations March 31, 2011 Tokyo Electric Power Company Tohoku Pacific Ocean Earthquake Time: 2:46 pm on Fri, March 11, 2011. Place:
More informationFukushima-Daiichi - a radiochemical view of the evolving situation in Summer 2011.
Fukushima-Daiichi - a radiochemical view of the evolving situation in Summer 2011. Kath Morris. Research Centre for Radwaste and Decommissioning The University of Manchester With thanks to Dr Edward Blandford,
More information