Fukushima-Daiichi - a radiochemical view of the evolving situation in Summer 2011.
|
|
- Blake Townsend
- 6 years ago
- Views:
Transcription
1 Fukushima-Daiichi - a radiochemical view of the evolving situation in Summer Kath Morris. Research Centre for Radwaste and Decommissioning The University of Manchester With thanks to Dr Edward Blandford, Stanford University. Prof. Francis Livens & Dr John Roberts, The University of Manchester.
2 Nuclear reactors The Great East Japan Earthquake and Tsunami The series of evolving events as we understand them at Fukushima- Daiichi Environmental information Implications Talk Structure.
3 Nuclear Reactor UO 2 MP 2865 C Zircaloy MP 1850 C
4 BWR Fukushima Daiichi Units 1, 2, 3, 4, 5, 6
5
6 Fuel storage pond Principal Containment 3. Drywell containment structure ( cm concrete) 2. Reactor Vessel (15 cm steel) 1. Zircaloy cladding Suppression pool Zircaloy MP 1850 C UO 2 MP 2865 C
7 Courtesy Edward Blandford The Earthquake Aerial view of Fukushima-Daiichi NPP - before & after Before the Earthquake and Tsunami After the Earthquake and Tsunami Unit 5 Unit 6 Unit 1 Unit 4 Unit 3 Unit 2 Photo Source: TEPCO Photo Source: Air Photo Service Inc (Myoko, Niigata Japan)
8 Earthquake and aftershocks Ground motion of Fukushima NPP Earthquake time: 2:46 pm March 11, 2011 Location: Offshore Sanriku coast, 24 km in depth, M9.0 Earthquakes: M quake (March 11) M - 7 class 5 times M - 6 class 72 times M - 5 class 423 times Unit MWe Observed (max. gal) Design Basis (max. gal) N-S E-W Vert. N-S E-W Vert TOKYO tokyo.ac.jp/eqvolc/201103_to hoku/eng/#mesonet Earthquake Research Institute, University of Tokyo, Prof. Takashi Furumura and Project Researcher Takuto Maeda F-D NOTE: Scram set points by acceleration Horizontal= gal, Vertical=100 gal Seismometers were located in the basement of reactor building gal is a unit of acceleration cm / s 2 Courtesy Edward Blandford
9 14 NPPs along eastern Honshu coast affected by Tsunami Time sequence of Units 1-3 immediately following earthquake: Earthquake followed by Reactor SCRAM, LOOP, EDGs start, IC/RCIC in operation Tsunami followed by complete (AC/DC) blackout and (mostly) isolation from the Ultimate Heat Sink Earthquake Research Institute, University of Tokyo, Prof. Takashi Furumura and Project Researcher Takuto Maeda Source: A. Omoto, Fukushima Accident : An overview, ICAPP 2011, 3 May 2011; Courtesy Edward Blandford
10 Initial impact on plant reactor safety systems Shutdown was secured by automatic shutdown of all control rods Transmission line was damaged by the earthquake Emergency diesel generators started but subsequently were lost due to Tsunami Station blackout Most of the cooling function of reactor and spent fuel pool were lost by the loss of power supply caused by Tsunami High level contaminated water found in turbine buildings loss of containment function Source: TEPCO presentation, The Great East Japan Earthquake and Current Status of Nuclear Power Stations, April 25, 2011
11 Intense heating (10 days ), steam, contamination Dumping Excess Heat
12 Sequence of Events: Unit 1 Unit 1 Sequence of Events March 11 14:47 Earthquake, loss of offsite ac power, and plant trip 14:52 Isolation condenser operated to cool reactor 15:03 Isolation condenser stopped operating 15:37 Tsunami and total loss of ac power SBO 15:37 Loss of ability to inject water to the reactor ~17:00 Water level below top of fuel --:-- Partial core damage (several hours after tsunami) March 12 14:30 Vent primary containment 15:36 Explosion results in damage to the reactor building At high T: Zr + 2H 2 O ZrO 2 + 2H 2 + HEAT Onwards Inject seawater / freshwater to cool
13 Unit 2 & Unit 3 Unit 2 explosion 15 th March 6.20am coupled to pressure loss in TORUS Containment damage assumed (Weightman, May 2011) Unit 3 explosion 14 th March 11.01am Damage is extensive - containment?
14 Unit 4, 5 and 6 TEPCO. Unit 4 reactor de-fuelled, SNF in storage pond. Active cooling required / explosion (hydrogen) possibly from Reactor 3 (venting) Unit 5 and 6 Sequence of Events (both units were shut down for periodic inspection) March 11 14:46 15:41 March 20 Earthquake and loss of offsite ac power Tsunami and total loss of ac power at site SBO 14:30 Unit 5 enters cold shutdown 19:27 Unit 6 enters cold shutdown
15 Source of hydrogen Delayed Release of Heat After Shutdown Zirconium cladding reaction with steam to produce hydrogen becomes substantial at temperatures above 1000 C Volatile fission products released as noble gases (e.g. Kr) or aerosols (e.g. I, Cs) Fuel pellets melt at 2600 C Zr, Fe, UO 2 melt - corium Flammability limit of hydrogen gas Source: 1) TEPCO presentation, The Great East Japan Earthquake and Current Status of Nuclear Power Stations, April 25, 2011, 2) MIT NSE webpage
16 Situation After Explosions Sea water (then fresh water) pumped into the core to lower the temperature Situation steady state injection stable - highly radioactive cooling water top up needed to maintain level and minimise further damage The earthquake has damaged containment leading to release of some radioactivity Ongoing effort on dust inhibition / water control / containment
17 Current status according to TEPCO as of 17/7 Source: TEPCO Roadmap Towards Restoration from the Accident at Fukushima Daiichi Nuclear Power Station Revised Version, Append 1-3,July 19, 2011
18 Unit 1 current situation Image:TEPCO
19 Environmental Situation Fukushima INES Level 7 People & Environment Chernobyl, 1986 External release of a significant fraction of reactor core inventory Consequence Major release of radioactive material with widespread health and environmental effects 6 Kyshtym, Russia, 1957 Significant release of radioactive material to environment from explosion of high activity waste tank Significant release of radioactive material Fukushima 5 Windscale Pile, UK, 1957 Radioactive material release to environment following fire in the core Limited release of radioactive materials 4 Tokai Mura, Japan 1999 Criticality event led to fatal overexposures of workers Minor release of radioactive materials Source: OECD Nuclear Energy Agency
20 Environmental Situation Source: OECD Nuclear Energy Agency
21 Environmental Situation Source: Nature Web Blog, Sept 7 th 2011 Source: TEPCO The Great East Japan Earthquake and Current Status, of Nuclear Power Stations, Sept 2011
22 Environmental Situation
23 Implications One in a thousand year events are possible Ongoing effort by Japanese to deal with consequences of earthquake and tsunami Fukushima-Daiitchi one aspect of that: Total = $300 billion Fukushima Daiitchi = $100 billion Global reassessment of nuclear - stress-tests Germany no; Switzerland no(ish); UK proceed Decommissioning and waste management radiochemistry (again) needed to assist
24 Thank you for your attention
The 2011 Tohoku Pacific Earthquake and Current Status of Nuclear Power Stations
The 2011 Tohoku Pacific Earthquake and Current Status of Nuclear Power Stations March 31, 2011 Tokyo Electric Power Company Tohoku Pacific Ocean Earthquake Time: 2:46 pm on Fri, March 11, 2011. Place:
More informationThe Nuclear Crisis in Japan
The Nuclear Crisis in Japan March 21, 2011 Daniel Okimoto Alan Hanson Kate Marvel The Fukushima Daiichi Incident 1. Plant Design 2. Accident Progression 3. Radiological releases 4. Spent fuel pools " Fukushima
More informationTEPCO s Nuclear Power Plants suffered from big earthquake of March 11,2011
TEPCO s Nuclear Power Plants suffered from big earthquake of March 11,2011 Follow up prepared at 4pm of March 23, revised April 13 Yoshiaki Oka Waseda university Recovery action is in progress. The presentation
More informationPreliminary Lessons Learned from the Fukushima Daiichi Accident for Advanced Nuclear Power Plant Technology Development
Preliminary Lessons Learned from the Fukushima Daiichi Accident for Advanced Nuclear Power Plant Technology Development A. Introduction The IAEA Report on Reactor and Spent Fuel Safety in the Light of
More informationIsolation Condenser; water evaporation in the tank and steam into the air. Atmosphere (in Severe Accident Management, both P/S and M/S)
Loss of Ultimate Heat Sink ANS AESJ AESJ Fukushima Symposium, March h4, 2012 Hisashi Ninokata, Tokyo Institute of Technology Available ultimate heat sinks at 1F1~3 1F1 (Fukushima Dai ichi Unit 1) Sea water
More informationChapter 3 Accident of Fukushima Daiichi Nuclear Power Plant: Sequences, Fission Products Released, Lessons Learned
Chapter 3 Accident of Fukushima Daiichi Nuclear Power Plant: Sequences, Fission Products Released, Lessons Learned Jun Sugimoto Abstract The nuclear accident that occurred at the Fukushima Daiichi Nuclear
More informationSafety Implication for Gen-IV SFR based on the Lesson Learned from the Fukushima Dai-ichi NPPs Accident. Ryodai NAKAI Japan Atomic Energy Agency
Safety Implication for Gen-IV SFR based on the Lesson Learned from the Fukushima Dai-ichi NPPs Accident Ryodai NAKAI Japan Atomic Energy Agency Contents Introduction Japanese Government Report to the IAEA
More informationSafety Enhancement of Nuclear Power Plant Post Fukushima. Kumiaki Moriya
International Conference on Nuclear Governance Post-Fukushima Marina Bay Sands, Singapore, 31 October 2013 Safety Enhancement of Nuclear Power Plant Post Fukushima October 31,2013 Kumiaki Moriya Hitachi-GE
More informationLessons Learned from Fukushima Daiichi Nuclear Power Station Accident and Consequent Safety Improvements
Hitachi Review Vol. 62 (2013), No. 1 75 Lessons Learned from Fukushima Daiichi Nuclear Power Station Accident and Consequent Safety Improvements Masayoshi Matsuura Kohei Hisamochi Shinichiro Sato Kumiaki
More informationIV. Occurrence and Development of the Accident at the Fukushima Nuclear Power Stations
IV. Occurrence and Development of the Accident at the Fukushima Nuclear Power Stations 1. Outline of Fukushima Nuclear Power Stations (1) Fukushima Daiichi Nuclear Power Station Fukushima Daiichi Nuclear
More informationImprovements Needed in Nuclear Power Plant Probabilistic Risk Assessments: Lessons Learned from Fukushima
Improvements Needed in Nuclear Power Plant Probabilistic Risk Assessments: Lessons Learned from Fukushima Mohammad Modarres Professor of Nuclear Engineering Department of Mechanical Engineering University
More informationSummary. LOCA incidents: Gas and liquid metal cooled reactors. List of LOCA incidents: 3-4
Summary NTEC Module: Water Reactor Performance and Safety Lecture 13: Severe Accidents II Examples of Severe Accidents G. F. Hewitt Imperial college London List of LOCA incidents: 3-4 Water cooled reactors
More informationNuclear Power after Fukushima
Nuclear Power after Fukushima Michael Corradini American Nuclear Society President: http://ans.org UW Energy Institute Chair: http://www.energy.wisc.edu 1 ANS Special Committee on Fukushima The special
More informationContents of summary. 1. Introduction
Contents of summary 1. Introduction 2. Situation regarding Nuclear Safety Regulations and Other Regulatory Frameworks in Japan before the Accident 3. Disaster Damage in Japan from the Tohoku District -
More informationSpent Fuel and Spent Fuel Storage Facilities at Fukushima Daiichi
Spent Fuel and Spent Fuel Storage Facilities at Fukushima Daiichi The National Academies Lessons Learned from the Fukushima Nuclear Accident for Improving Safety and Security of U.S. Nuclear Plants: Phase
More informationTHE FUKUSHIMA ACCIDENT: IMPLICATIONS FOR NUCLEAR SAFETY. Edwin Lyman Union of Concerned Scientists May 26, 2011
THE FUKUSHIMA ACCIDENT: IMPLICATIONS FOR NUCLEAR SAFETY Edwin Lyman Union of Concerned Scientists May 26, 2011 The accident: many unknowns Many of the details of the Fukushima Daiichi accident are still
More informationCorium debris configurations in course of accident
РОССИЙСКАЯ АКАДЕМИЯ НАУК Институт проблем безопасного развития атомной энергетики RUSSIAN ACADEMY OF SCIENCES Nuclear Safety Institute (IBRAE) Corium debris configurations in course of accident Valery
More informationRadionuclide Release at Fukushima
Radionuclide Release at Fukushima Peter F. Caracappa, Ph.D., CHP American Nuclear Society Connecticut Section November 16, 2011 Overview Accident Review Radioactive Material Releases Transport and Deposition
More informationPost-Fukushima Assessment of the AP1000 Plant
ABSTRACT Post-Fukushima Assessment of the AP1000 Plant Ernesto Boronat de Ferrater Westinghouse Electric Company, LLC Padilla 17-3 Planta 28006, Madrid, Spain boronae@westinghouse.com Bryan N. Friedman,
More informationFrequently Asked Questions: Japanese Nuclear Energy Situation
NUCLEAR ENERGY INSTITUTE Frequently Asked Questions: Japanese Nuclear Energy Situation 1. What will be the impact of the Fukushima Daiichi accident on the U.S. nuclear program? It is premature to draw
More informationThe Accident at Fukushima: What Happened?
The Accident at Fukushima: What Happened? February 27, 2012 Takao Fujie President and Chief Executive Officer (JANTI) Copyright 2012. All Rights Reserved. The Accident at Fukushima: What Happened? Foreword
More informationPower Generation. Ronaldo Jenkins Electrical Engineering Branch Chief Office of New Reactors (NRO)
Power Generation Ronaldo Jenkins Electrical Engineering Branch Chief Office of New Reactors (NRO) Agenda Overview Design Considerations 10 Code of Federal Regulations (CFR) 50 10 CFR 50, General Design
More informationBWR Safety Improvement as a Lesson Learned from Fukushima Accident
BWR Safety Improvement as a Lesson Learned from Fukushima Accident M. M. Zaky and S. A. Kotb ETRR-2, Atomic Energy Authority, Cairo, Egypt Received: 20/5/2016 Accepted: 15/7/2016 ABSTRACT The serious accident
More informationStress tests specifications Proposal by the WENRA Task Force 21 April 2011
Stress tests specifications Proposal by the WENRA Task Force 21 April 2011 Introduction Considering the accident at the Fukushima nuclear power plant in Japan, the Council of the European Union declared
More informationDevelopment of technologies for the processing and disposal of radioactive waste
Development of technologies for the processing and disposal of radioactive waste International Experts' Symposium on the Decommissioning of TEPCO's Fukushima Daiichi Nuclear Power Plant Unit 1-41 March
More informationMeasures against Earthquakes and Tsunamis in View of the Accident at Fukushima Daiichi Nuclear Power Station
Nuclear and Industrial Safety Agency Ministry of Economy, Trade and Industry IEM 3: International Expert s Meeting (Earthquakes / Tsunamis) 4-7 September, 2012 Vienna Measures against Earthquakes and Tsunamis
More informationFUKUSHIMA DAIICHI BWR REACTOR SPRAY AND FEED WATER SYSTEMS EVALUATION FOR EARLY FAILURE Dean Wilkie
FUKUSHIMA DAIICHI BWR REACTOR SPRAY AND FEED WATER SYSTEMS EVALUATION FOR EARLY FAILURE Dean Wilkie The BWR reactor vessel spray(core spray) and feed water spray systems are designed to inject water into
More informationNuclear accident in Fukushima-I nuclear power plant: Critical Analysis
Nuclear accident in Fukushima-I nuclear power plant: Critical Analysis Sara Silva Pinto Wahnon Under supervision of José Joaquim Gonçalves Marques and Carlos António Abreu Fonseca Varandas Instituto Superior
More informationStudy on Severe Accident Progression and Source Terms in Fukushima Dai-ichi NPPs
Study on Severe Accident Progression and Source Terms in Fukushima Dai-ichi NPPs October 27, 2014 H. Hoshi, R. Kojo, A. Hotta, M. Hirano Regulatory Standard and Research Department, Secretariat of Nuclear
More informationIntroduction to the Accident at Fukushima Dai-ichi Nuclear Power Station
Introduction to the Accident at Fukushima Dai-ichi Nuclear Power Station Richard Wakeford Professor in Epidemiology, Institute of Population Health and Dalton Nuclear Institute, The University of Manchester,
More informationNuclear Power Plants and Earthquakes
Nuclear Power Plants and Earthquakes (August 2009) Japanese, and most other, nuclear plants are designed to withstand earthquakes, and in the event of major earth movement, to shut down safely. In 1995,
More informationThe Future of Nuclear Power After Fukushima
The Future of Nuclear Power After Fukushima Michael Corradini American Nuclear Society Vice President / President-Elect http://ans.org University of Wisconsin Energy Institute Chair http://www.energy.wisc.edu
More informationOVER VIEW OF ACCIDENT OF FUKUSHIMA DAI-ICHI NPSs AND FUTURE PLANNING TOWARD D&D
OVER VIEW OF ACCIDENT OF FUKUSHIMA DAI-ICHI NPSs AND FUTURE PLANNING TOWARD D&D 16 NOVEMBER, 2011 Hiroshi RINDO JAPAN ATOMIC ENERGY AGENCY Table of Contents 1. What s happened at Fukushima Dai-Ichi NPSs
More informationRegulatory Actions and Follow up Measures against Fukushima Accident in Korea
Int Conference on Effective Nuclear Regulatory Systems, April 9, 2013, Canada Regulatory Actions and Follow up Measures against Fukushima Accident in Korea Seon Ho SONG* Korea Institute of Nuclear Safety
More informationEnhancement of Nuclear Safety
Enhancement of Nuclear Safety Soon Heung Chang Handong Global University May 6, 2015 Contents 1 2 3 4 Importance of Energy Fundamentals of Nuclear Safety How to Enhance Nuclear Safety Closing Remarks 2
More informationSafety enhancement of NPPs in China after Fukushima Accident
Safety enhancement of NPPs in China after Fukushima Accident CHAI Guohan 29 June 2015, Brussels National Nuclear Safety Administration, P. R. China Current Development of Nuclear Power Mid of year 2015
More informationMajor Influential Issues on the Accident Progressions of Fukushima Daiichi NPP
1/12 Major Influential Issues on the Accident Progressions of Fukushima Daiichi NPP Summary M. Naitoh, M. Pellegrini. H. Suzuki, H. Mizouchi, and H. Okada The Institute of Applied Energy, Japan This paper
More informationTsunami Countermeasures at Hamaoka Nuclear Power Station
Tsunami Countermeasures at Hamaoka Nuclear Power Station Reference Reactor No. 5 Reactor No. 4 Reactor No. 3 Reactor No. 2 Reactor No. 1 March 16, 2012 2011 Chubu Electric Power Co., Inc. All rights reserved.
More informationDr. Martin Sonnenkalb & Dr. Manfred Mertins GRS Cologne. Severe Accident Mitigation in German NPP - Status and Future Activities -
Dr. Martin Sonnenkalb & Dr. Manfred Mertins GRS Cologne Severe Accident Mitigation in German NPP - Status and Future Activities - Content History and status of implementation of Severe Accident Management
More informationSafety design approach for JSFR toward the realization of GEN-IV SFR
Safety design approach for JSFR toward the realization of GEN-IV SFR Advanced Fast Reactor Cycle System R&D Center Japan Atomic Energy Agency (JAEA) Shigenobu KUBO Contents 1. Introduction 2. Safety design
More informationNuScale SMR Technology
NuScale SMR Technology UK IN SMR; SMR IN UK Conference - Manchester, UK Tom Mundy, EVP Program Development September 25, 2014 Acknowledgement & Disclaimer This material is based upon work supported by
More informationJapan s Nuclear Emergency - Update - April 6, 2011 Ministry of Economy, Trade and Industry Government of Japan
Japan s Nuclear Emergency - Update - April 6, 2011 Ministry of Economy, Trade and Industry Government of Japan Table of Contents A. Japan Faces an Unprecedented Challenge (Enormous Earthquake, Tsunamis
More informationThe Fukushima Nuclear Accident: Insights on the Safety Aspects
World Journal of Nuclear Science and Technology, 2015, 5, 169-182 Published Online July 2015 in SciRes. http://www.scirp.org/journal/wjnst http://dx.doi.org/10.4236/wjnst.2015.53017 The Fukushima Nuclear
More informationBelgian Stress Test Nuclear Power Plants (BEST)
Belgian Stress Test Nuclear Power Plants (BEST) 2013-08-26 TM IAEA: Belgian Stress Tests Stress Test Specifications Technical scope Initiating events Earthquake Flooding Other extreme natural events (extreme
More informationNuclear Power Plant Safety Basics. Construction Principles and Safety Features on the Nuclear Power Plant Level
Nuclear Power Plant Safety Basics Construction Principles and Safety Features on the Nuclear Power Plant Level Safety of Nuclear Power Plants Overview of the Nuclear Safety Features on the Power Plant
More informationThe international program Phebus FP (fission
1The safety of nuclear reactors 1 6 Results of initial Phebus FP tests FPT-0 and FPT-1 S. BOURDON (IRSN) D. JACQUEMAIN (IRSN) R. ZEYEN (JRC/PETTEN) The international program Phebus FP (fission products)
More informationVVER-440/213 - The reactor core
VVER-440/213 - The reactor core The fuel of the reactor is uranium dioxide (UO2), which is compacted to cylindrical pellets of about 9 height and 7.6 mm diameter. In the centreline of the pellets there
More informationThe Great Tohouku Earthquake and the Fukushima Disaster: Incident Management from a Physical Control Standpoint
The Great Tohouku Earthquake and the Fukushima Disaster: Incident Management from a Physical Control Standpoint CAROLA CRUZ MOLINA POLYTECHNIC UNIVERSITY OF PUERTO RICO NRC FELLOWSHIP PROGRAM CMOLINA.CAROLA@GMAIL.COM
More informationModule 06 Boiling Water Reactors (BWR)
Module 06 Boiling Water Reactors (BWR) 1.10.2015 Prof.Dr. Böck Vienna University oftechnology Atominstitute Stadionallee 2 A-1020 Vienna, Austria ph: ++43-1-58801 141368 boeck@ati.ac.at Contents BWR Basics
More informationBrazilian Operator s Response to Fukushima Daiichi Accident Luiz Soares Technical Director
Simposyum Siting of New Nuclear Power Plants and Irradiated Fuel Facilities Buenos Aires Argentina 24-28 June 2013 Panel Fukushima Daiichi s Impact in Nuclear Power Programs Worldwide Brazilian Operator
More informationLessons learned from the accident at the Fukushima Daiichi Nuclear Power Plant
May 9, 2011 Lessons learned from the accident at the Fukushima Daiichi Nuclear Power Plant Technical Analysis Subcommittee Committee for Investigation of Nuclear Safety Atomic Energy Society of Japan We
More informationFundamental Research Program for Removal of Fuel Debris
International Symposium on the Decommissioning of TEPCO s Fukushima Daiichi Nuclear Power Plant Unit 1-4 1 Fundamental Research Program for Removal of Fuel Debris March 14, 2012 Tadahiro Washiya Japan
More informationEFFICIENCY OF FORTUM'S CSTREAT AND SRTREAT IN CESIUM AND STRONTIUM REMOVAL IN FUKUSHIMA DAIICHI NPP ABSTRACT
EFFICIENCY OF FORTUM'S CSTREAT AND SRTREAT IN CESIUM AND STRONTIUM REMOVAL IN FUKUSHIMA DAIICHI NPP ESKO TUSA Fortum Power and Heat Oy PO Box 100, 00048 Fortum, Finland ABSTRACT After the accident of March
More informationHPR1000: ADVANCED PWR WITH ACTIVE AND PASSIVE SAFETY FEATURES
HPR1000: ADVANCED PWR WITH ACTIVE AND PASSIVE SAFETY FEATURES D. SONG China Nuclear Power Engineering Co., Ltd. Beijing, China Email: songdy@cnpe.cc J. XING China Nuclear Power Engineering Co., Ltd. Beijing,
More informationWestinghouse Small Modular Reactor. Passive Safety System Response to Postulated Events
Westinghouse Small Modular Reactor Passive Safety System Response to Postulated Events Matthew C. Smith Dr. Richard F. Wright Westinghouse Electric Company Westinghouse Electric Company 600 Cranberry Woods
More informationELETRONUCLEAR s Response to the Fukushima Dai-ichi Nuclear Accident
s Response to the Fukushima Dai-ichi Nuclear Accident Rio de Janeiro, July 3 rd, 2012 Paulo Vieira First Actions Taken by Eletronuclear Establishment of a Corporate Working group Follow up of the event,
More information-Update - Ministry of Economy, Trade and Industry Government of Japan
Japan s Nuclear Emergency -Update - April 6, 2011 Ministry of Economy, Trade and Industry Government of Japan Table of Contents A. Japan Faces an Unprecedented Challenge (Enormous Earthquake, Tsunamis
More informationPresent Status of Kyoto University Research Reactor, KUR
18th IGORR conference/iaea Technical Meeting 3-7 Dec. 2017, Sydney, Australia Present Status of Kyoto University Research Reactor, KUR Ken NAKAJIMA Research Reactor Institute, Kyoto University 1 Accident
More informationSide Event of IAEA General Conference. Severe Accident Analyses of Fukushima-Daiich Units 1 to 3. Harutaka Hoshi and Masashi Hirano
Side Event of IAEA General Conference Severe Accident Analyses of Fukushima-Daiich Units 1 to 3 Harutaka Hoshi and Masashi Hirano Japan Nuclear Energy Safety Organization (JNES) September 17, 2012 Side
More informationLessons learned from the Fukushima Daiichi Nuclear Power Plant Accident
2012 Begell House, Inc. Lessons learned from the Fukushima Daiichi Nuclear Power Plant Accident T. Narabayashi 1 1 Division of Energy and Environmental Systems, Hokkaido University, Kita 13, Nishi 8, Kita-ku,
More informationIndia s HWR Activities S.G.Ghadge Executive Director (Reactor Safety & Analysis) Nuclear Power Corporation of India Limited
India s HWR Activities S.G.Ghadge Executive Director (Reactor Safety & Analysis) Nuclear Power Corporation of India Limited 13 th Meeting of the Technical Working Group on Advanced Technologies for HWRs
More informationCorium Retention Strategy on VVER under Severe Accident Conditions
NATIONAL RESEARCH CENTRE «KURCHATOV INSTITUTE» Corium Retention Strategy on VVER under Severe Accident Conditions Yu. Zvonarev, I. Melnikov National Research Center «Kurchatov Institute», Russia, Moscow
More information4. Current Status (1) Fukushima Daiichi Nuclear Power Station
4. Current Status (1) Fukushima Daiichi Nuclear Power Station 0 Plant Parameters (Fukushima Daiichi) as of October 12, 2012 at 5:00 RPV Water Injection [m 3 /h] FW Unit 1 2.9 Unit 2 2.1 Unit 3 2.1 CS 2.0
More informationJapanese earthquake and tsunami: Implications for the UK nuclear industry
Japanese earthquake and tsunami: Implications for the UK nuclear industry Final Report HM Chief Inspector of Nuclear Installations September 2011 Crown copyright 2011 ONR Report ONR FR REP 11 002 Revision
More informationThe Risk of Nuclear Power
13 th International Conference on Probabilistic Safety Assessment and Management [PSAM13] The Risk of Nuclear Power Soon Heung Chang Handong Global University Oct 4, 2016 Contents 1 2 3 4 Introduction:
More informationXII. Lessons Learned From the Accident Thus Far
XII. Lessons Learned From the Accident Thus Far The Fukushima NPS accident has the following aspects: it was triggered by a natural disaster; it led to a severe accident with damage to nuclear fuel, Reactor
More informationActivities of Toshiba for Fukushima restoration
Activities of Toshiba for Fukushima restoration - WM2016 Panel Session #091 - March 9,2016 TOSHIBA Corporation Nuclear Chemical Engineering and Design Masamichi Obata 2016 Toshiba Corporation Contents
More informationPDHonline Course E438 (3 PDH) Nuclear Accidents. Charles A. Patterson, P.E. PDH Online PDH Center
PDHonline Course E438 (3 PDH) Nuclear Accidents Charles A. Patterson, P.E. 2014 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA 22030-6658 Phone & Fax: 703-988-0088 www.pdhonline.org www.pdhcenter.com
More informationJapan Nuclear Energy Safety Organization (JNES)
Japan Nuclear Energy Safety Organization (JNES) A summary of missions, organization and activities November 2004 Hideki Nariai President, JNES 0 JNES was established in Oct. 2003 as an expert organization
More informationTopics on Current Nuclear Regulation in Japan
Topics on Current Nuclear Regulation in Japan Commissioner Toyoshi Fuketa Nuclear Regulation Authority(NRA 26 th Annual Regulatory Information Conference Bethesda North Marriott Hotel & Conference Center
More information1. What happened at Fukushima Daiichi five years ago on 11 March 2011?
On 11 March 2011, at 2:46 p.m. local time (6.46 a.m. CET), an earthquake measuring 9 on the Richter scale hit the east coast of Japan. The quake caused a tsunami, with waves as high as 38 metres, which
More informationAre We Safer Now? The Future of Nuclear Power in the Northwest 3.5 Years After Fukushima
Are We Safer Now? The Future of Nuclear Power in the Northwest 3.5 Years After Fukushima Edwin S. Lyman Senior Scientist Union of Concerned Scientists October 2014 Fukushima: Why should we care? Because
More informationSummary SUMMARY. Contents of Summary
SUMMARY Contents of Summary 1. Introduction 2. Further Developments regarding the Nuclear Accident 3. Efforts to Settle the Accident 4. Responses to people suffering as a result of the nuclear accident
More informationFukushima Daiichi Status Report
Fukushima Daiichi Status Report 24 November 2011 The IAEA issues regular status reports to the public on the current status of the Fukushima Daiichi Nuclear Power Plant, including information on environmental
More informationImmediate Countermeasures
September 3, 2013 Agency for Natural Resources and Energy, METI of Japan 2 nd Fact sheet: Overview of Contaminated Water Issue at TEPCO s Fukushima Daiichi NPS On June 19, 2013, TEPCO announced that ground
More informationPost Fukushima actions in India. Mukesh Singhal, Chief Engineer, Reactor Safety & Analysis Directorate NPCIL
Post Fukushima actions in India Mukesh Singhal, Chief Engineer, Reactor Safety & Analysis Directorate NPCIL 14 th Meeting of IAEA-TWG on advance technologies, IAEA, Vienna, June 18-20, 2013 Presentation
More informationNRA s Regulatory Perspectives on Decommissioning of TEPCO Fukushima Daiichi Nuclear Power Station
NRA s Regulatory Perspectives on Decommissioning of TEPCO Fukushima Daiichi Nuclear Power Station September 18, 2017 Yutaka HARA Nuclear Regulation Authority (NRA), Japan 1 Contents Approach in NRA s Regulation
More informationAssessing and Managing Severe Accidents in Nuclear Power Plant
Assessing and Managing Severe Accidents in Nuclear Power Plant Harri Tuomisto Fortum, Finland IAEA Technical Meeting on Managing the Unexpected - From the Perspective of the Interaction between Individuals,
More informationNuclear Power and Nuclear Safety Post Fukushima
Nuclear Power and Nuclear Safety Post Fukushima C. Pistner, M. Englert, Öko-Institut e.v. DPG AKE AGA: Nuclear Energy and Security Münster, 29.03.2017 Agenda 1 2 3 4 5 Status of Nuclear Power Today Review
More informationNUCLEAR ENERGY. Prepared by Engr. JP Timola Reference: Nuclear Energy by Dr. Lana Aref
NUCLEAR ENERGY Prepared by Engr. JP Timola Reference: Nuclear Energy by Dr. Lana Aref How is Nuclear Energy Produced? Nuclear energy is produced when an atom's nucleus is split into smaller nuclei by the
More informationDesign, Safety Technology and Operability Features of Advanced VVERs
Technical Cooperation Project INT/4/142 Interregional Workshop on Advanced Nuclear Reactor Technology for Near Term Deployment IAEA Headquarters, Vienna, Austria, 4-8 July 2011 Design, Safety Technology
More informationDr. Keiji Kijima Secretary General IPEC Japan
Dr. Keiji Kijima Secretary General IPEC Japan * *I wish to express my gratitude to the good will sent to the Tohoku and Kanto earthquake. The Japanese Pharmacopoeia 16 th Edition was promulgated in March
More informationChapter VI. VI.Situation regarding efforts to address lessons learned (28 items)
VI.Situation regarding efforts to address lessons learned (28 items) Japan is making its greatest possible efforts to address the 28 lessons learned indicated in the June report. The state of progress
More informationPost-Fukushima Actions in Korea
Post-Fukushima Actions in Korea IAEA TWG-LWR Vienna, June 18-20, 2013 Presented by Jong-Tae Seo 1. Impacts on National Energy Policy and NPP Plan 2. Actions Taken after Fukushima Accident 3. Findings and
More informationAttachment VIII-1. July 21, 2011 Nuclear and Industrial Safety Agency
Assessment Procedures and Implementation Plan Regarding the Comprehensive Assessments for the Safety of Existing Power Reactor Facilities Taking into Account the Accident at Fukushima Dai-ichi Nuclear
More informationSUMMARY OF SE NNEGC ENERGOATOM PERFORMANCE IN POST-FUKUSHIMA PERIOD
МИНИСТЕРСТВО ЭНЕРГЕТИКИ И УГОЛЬНОЙ ПРОМЫШЛЕННОСТИ УКРАИНЫ НАЦИОНАЛЬНАЯ АТОМНАЯ ЭНЕРГОГЕНЕРИРУЮЩАЯ КОМПАНИЯ SUMMARY OF SE NNEGC ENERGOATOM PERFORMANCE IN POST-FUKUSHIMA PERIOD D.V. Biley Inspector General
More informationModule 06 Boiling Water Reactors (BWR) Vienna University of Technology /Austria Atominstitute Stadionallee 2, 1020 Vienna, Austria
Module 06 Boiling Water Reactors (BWR) Prof.Dr. H. Böck Vienna University of Technology /Austria Atominstitute Stadionallee 2, 1020 Vienna, Austria Contents BWR Basics Technical Data Safety Features Reactivity
More informationNuclear Energy. Frontiers of Physics Lecture 2 (F4) Dan Protopopescu
Nuclear Energy Frontiers of Physics Lecture 2 (F4) Dan Protopopescu Summary of Lecture I Nuclear power around the world Costs, comparisons, advantages Public perception Radiation and radioactive material
More informationResponse to Nuclear Emergency Situation - Viewpoints of Crisis Management -
3 rd meeting, material 6 Response to Nuclear Emergency Situation - Viewpoints of Crisis Management - February 2015 Nuclear Regulation Authority Material 3 Response to nuclear disasters Act on Special Measures
More informationCNE Cernavoda Response to Fukushima Event/EU Stress Test Requirements
CNE Cernavoda Response to Fukushima Event/EU Stress Test Requirements Sorin Holostencu IAEA Technical Meeting on Operational Experience with Implementation of Post-Fukushima Actions in Nuclear Power Plants,
More informationSafety Review Models on Radioactive Source Term Design For PWR Waste Treatment Systems
Safety Review Models on Radioactive Source Term Design For PWR Waste Treatment Systems Xu Mingxia Waste Management Division, Nuclear Safety center, State Environmental Protection Administration, Beijing
More informationMasahiro SHIZU Deputy Director Arms Control and Disarmament Division Ministry of Foreign Affairs, JAPAN
CEG Workshop on Predisposal of Legacy Radioactive Waste : Treatment, Conditioning and Storage,17-19 May 2011, Heringsdorf, Germany Masahiro SHIZU Deputy Director Arms Control and Disarmament Division Ministry
More informationSafety Design Requirements and design concepts for SFR
Safety Design Requirements and design concepts for SFR Reflection of lessons learned from the Fukushima Dai-ichi accident Advanced Nuclear System Research & Development Directorate Japan Atomic Energy
More informationStation Blackout Accident at Fukushima SAFETY
Year 31 Nº 122 2011 Station Blackout Accident at Fukushima SAFETY An analysis of the phenomenology of the earthquake and tsunami-induced station blackout accident at the Fukushima Daiichi plant, Japan
More informationNuclear Accidents. William M. Murphy. Professor of Geological and Environmental Sciences California State University, Chico
Nuclear Accidents William M. Murphy Professor of Geological and Environmental Sciences California State University, Chico A Month After the Earth Moved: The Science Behind the Japan Disaster April 11,
More informationResearch and Development Programs for Decommissioning of Fukushima Daiichi Nuclear Power Station
WRFPM 2014 Sendai, Japan Research and Development Programs for Decommissioning of Fukushima Daiichi Nuclear Power Station September 15, 2014 KENDA Hirofumi International Research Institute for Nuclear
More informationStatus of Radioactive Waste Management in Japan
Status of Radioactive Waste Management in Japan Regional Meeting on the Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management Gyeongju, 5-8 November,
More information3 Steps Approach : KHNP s Implementation of Post Fukushima Actions. ST(Sung-Tae) Yang. General Manager Corporate Safety Department KHNP
3 Steps Approach : KHNP s Implementation of Post Fukushima Actions ST(Sung-Tae) Yang General Manager Corporate Safety Department KHNP Status of Nuclear Power Plants (As of Jan 2016) In Operation Under
More informationComprehensive Safety Assessment for Kashiwazaki Kariwa NPS
Comprehensive Safety Assessment for Kashiwazaki Kariwa NPS International Experts Meeting on Reactor and Spent Fuel Safety in the Light of the Accident at the Fukushima Daiichi Nuclear Power Plant IAEA,
More information