STARTUP OF ANAEROBIC MESOPHILIC DIGESTERS
|
|
- Susan Horn
- 6 years ago
- Views:
Transcription
1 STARTUP OF ANAEROBIC MESOPHILIC DIGESTERS Marialena Hatzigeorgiou P.E./CH2M HILL Brian Owsenek P.E./Upper Occoquan Sewage Authority Tom Alkema/CH2M HILL Ronald Sieger P.E. BCEE/CH2M HILL and Karen Pallansch P.E./Alexandria Sanitation Authority *Ron Sieger passed away on May 3 26 ABSTRACT Many operators have started up mesophilic digesters but everyone has differing stories and experiences. This paper is a combination of the startup of several mesophilic anaerobic digesters with very low seeding to fully seeded conditions. Upper Occoquan Sewage Authority (UOSA) operates the Millard H. Robbins Water Reclamation Plant. UOSA started three anaerobic digesters between August 2 and March 21 as part of a major expansion which brought the permitted capacity of the facility from 32 to 54 million gallons per day (mgd). Alexandria Sanitation Authority (ASA) operates the ASA Advanced Wastewater Treatment Plant with an average plant influent flow of 54 mgd. ASA started four anaerobic digesters between May and October 25 as part of a solids upgrade that added pre-pasteurization and two new anaerobic digesters. This paper will provide a useful roadmap for digester startups for all operators. KEYWORDS Mesophilic anaerobic digestion biosolids solids startup. INTRODUCTION Case Studies. The plant expansion for UOSA involved conversion of one unheated unmixed secondary digester (8/1) to a primary digester by installation of mixing cannons heating equipment digester gas system and foam separation equipment. In addition the floating cover was fixed in place and new gas purifier systems and other miscellaneous instrumentation and automation equipment were installed. Digester 8/1 along with the retrofitted digesters 7/1 and 7/2 were startup as primary digesters between August 2 and March 21. The plant upgrade for ASA involved addition of a pre-pasteurization system two new anaerobic digesters and the retrofit of the two existing anaerobic digesters. For all four anaerobic digesters the work included installation of mixing cannons heating equipment digester gas collection and utilization system foam separation equipment and instrumentation and automation equipment. In addition the floating cover of the one existing digester was fixed and the two new mesophilic anaerobic digesters were built with structural thermophilic capability. The startup discussions for the pasteurization system and the anaerobic digesters were initiated in early fall of 24. The pasteurization system was performance tested on water and then operated on water during winter of By early spring of 25 a detailed startup plan 415
2 was provided for the startup of the anaerobic digesters with pasteurized solids (PSLDG) in order to achieve Class A biosolids pathogen density levels. The four digesters were started up as primary digesters between May and October 25. Tables 1 and 2 below provides the digesters information for UOSA and ASA respectively. Table 1 UOSA Anaerobic Digesters Parameter Dig. # 8/1 Dig. # 7/1 & 7/2 Maximum Capacity (gal) Diameter (ft) 8 8 Heat Exchangers (MBtu/hr) Spiral 2. Spiral 2. Sludge Recirculation (gpm) Type of Cover Fixed Metal Fixed Concrete Mixing System IDI Gas Cannons IDI Gas Cannons Mixing Capacity (gpm) Target Temperature (C) Table 2 ASA Anaerobic Digesters Parameter Dig. # Maximum Capacity (gal) 15 Diameter (ft) 95 Heat Exchangers MBtu/hr Sludge Recirculation (gpm) Type of Cover Mixing System Mixing Capacity Concentric tube counter flow gpm Fixed Concrete IDI Gas Cannons 564 gpm Target Temperature (C) 35 Paper Objectives. Mesophilic anaerobic digestion is a biological process which during startup requires time and careful management. Good planning continuous monitoring and slow changes are the three key factors for a successful startup. This paper provides a comparison in terms of 416
3 % TS increase stability and performance of anaerobic digesters started up from very low to fully seeded. It can be used as a guide for starting digesters at any plant. METHODS AND MATERIALS General. Anaerobic digestion seed includes raw sludge (primary sludge or scum) digested solids and pasteurized solids. Digested solids are preferred but raw sludge can be used when there is no other operating digester on site or close by from a nearby wastewater treatment plant. Pasteurized solids have not been used either in the United States or in Europe. Theoretically pasteurized solids will work for digesters seed but the startup time is expected to be far more lengthy and operational intensive. Upper Occoquan Sewage Authority (UOSA) VA. Solids processing at UOSA consists of feeding waste activated (WAS) and primary sludge (PSD) to the digesters. The stabilized solids are then get dewatered and dried. Alternatively WAS can be mechanically thickened dewatered dried and disposed after lime addition. The project was phased such that the secondary digester (8/1) was taken out of service first retrofitted and returned to service as a primary digester. Once the biological processes had stabilized an existing primary digester (7/1) was taken out of service retrofitted and returned to service. Finally the remaining primary digester (7/2) was retrofitted and returned to service. Startup conditions for the two operations differed substantially. In startup of digester 8/1 the digester was filled with plant water heated to 36C seeded from another digester and then fed with primary sludge. For the second startup that of digester 7/1 the digester was filled with primary sludge and seed. Unfortunately there are no data available on the exact amount of seed used for this startup. All that is available is the monitoring data during the startup that indicate that the amount of seed used was not adequate for the feed rates to that digester. Alexandria Sanitation Authority (ASA) VA. The normal operation solids processing at ASA consists of: Primary (PSD) and tertiary (TSD) sludge to gravity thickeners Waste activated sludge (WAS) to mechanical thickeners Gravity and mechanically thickened sludges blended and pasteurized Pasteurized solids (PSLDG) to anaerobic digesters Digested solids (DS) to dewatering At the time of the start up of the four high rate mesophilic digesters of 1.5 mgd capacity each ASA had no operating digesters to seed the new digesters and the plant was in operation at all times so there could be minimum interruption to the daily solids process. In addition the volume of seed hauled in from a nearby plant had to be minimum in order not to contaminate the volume of the newly built digesters with other than Class A pathogen levels. The digesters were started one at a time. The very first digester required the most attention and took the longest. It was filled to the top of the canon mixers with plant effluent that was then 417
4 heated to mesophilic digestion temperature. At the same time the headspace was purged with nitrogen gas as was the associated digester gas piping. Once purged and heated the digester was seeded with digested biosolids from the Upper Occoquan Sewage Authority (UOSA) plant. The volume of the seed solids was equal to 4.5% of the total volume of one digester. Once the digester was seeded PSLDG was added at a very slow rate. The digester had to be carefully managed in order for the slow-growing methane formers to populate the digester and to balance the acid formers. The digester parameters (temperature total solids volatile solids volatile acids alkalinity ph VSR) along with the feed parameters (total and volatile solids) were monitored and evaluated based on the ranges provided below: Temperature between 34.5 and 35.5 C with 35 C target value. Ratio of volatile acids/alkalinity less than.35 ph between 6.5 and 8. with target value of 7.1 VSR higher than 4% Ratio of TS feed/ts in digester between.5 to.1 Ratio of VS feed/vs in digester between.3 to.1 Digester gas methane concentration higher than 55% by volume concentration Every time the digester feed rate was modified a new period of the startup began. Each period was based upon an average week. There were specific goals for feed loading and digester results. Decisions on whether to proceed to the next period or not were made based on the monitored parameters. It took a couple of periods longer to start the first digester than anticipated because the desirable solids concentration of the feed PSLDG was not achieved until later in the startup. Table 3 is the planned table for the first digester to start up (Digester 4) provided with the startup plan in March of 25. The digested solids in (lb/day) calculated in the digester at the end of the period includes the volatile solids reduction plus the solids lost from the digester through the transfer. Table 3 - Feed Rates and Time from Startup to Achieve Solids Concentration in Digester Period Vol in start (gal) Feed Vol/day (gal/day) Feed Rate (gal/hr) Vol in Dig after 7 days DS in start (lbs) DS added per day (lbs) DS in Dig after 7 days (lbs) DS in Dig after 7 days with VSR + Transfer (lbs) % TS in DS after 7 days Adjustable Values Seed Volume fed Digester volum % Solids in seed Digester deten % Volatile solids % Volatile solids full % Solids in PSLD Once the first digester reached the overflow level digested solids were then transferred to the next dormant digester for startup. Solids were transferred every day from the first digester to the 418
5 dormant digester equal to the daily feed to the first digester. The dormant digester headspace was isolated from the rest of the digester gas piping and did not require purging. Once the dormant digester level reached the cannon mixers temperature was confirmed mixing started and raw solids were fed to the digester at much higher feed rates. Once the second digester reached the overflow level the same concept as above was applied to the third dormant digester by transferring from the first two digesters that were now in service. Finally the dormant digester concept was applied to the last digester by transferring digested solids from the other three digesters in service. Table 4 is one of the tables created during startup to assess the current period based on the parameters monitored and calculate the next period s feed rate (this is the table created during periods 17 and 18 for the first digester). The actual test analysis results for the % TS and % VS are used for both the digesters feed and the digesters contents in order to plan the next period s feed rate and calculate the expected % TS by the end of that period. Similar tables were created for the other three digesters as well. Table 4 - Actual Feed Rates and Time from Startup to Achieve Desired Solids Concentration in Digester Period Days in start of Period Vol in start (gal) Feed Vol/day (gal/day) DS in Vol in start of end of period period (lbs) TS in seed/feed per period (%) VS in seed/feed per period (%) TS added per day (lbs) Actual DS Actual % TS in Adjustable in end end of Values of period period (lbs) Seed % 6.2% % % 75.7% % % 74.1% % Dig vol. gal % 73.9% % % 73.9% % % 72.9% % 6 full % 71.5% % 7 ovflow % 71.3% % 8 ovflow % 73.9% % 9 trsfr % 75.5% % % 75.4% % % 74.9% % % 74.6% % /16/ % 75.4% % /25/ % 75.9% % /2/ % 75.7% % /6/ % 76.8% % /13/ % 78.6% % Planning Feedrates and Time from Startup to Achieve Desired % Solids in Digester (With VSR) Period Days in Period Vol in start (gal) Feed Vol/day (gal/day) Actual DS in Vol in start end of period of period (lbs) DS added per day (lbs) DS in of period (lbs) Calculated DS in end of period with VSR + Transfer (lbs) Calculated % TS in end of period Adjustable Values 14 trsfer % 15. Dig SRT day 15 trsfer 4 9/2/ % 78.6% VS in feed 16 trsfer 7 9/6/ % 61.6% VS in digeste 17 trsfer 1 9/13/ % 56% VSR 17 trsfer 1 9/14/ % 18 prg/dwtr 7 9/24/ % 4.48% TS in feed 19 dwtr 7 1/1/ % 2 dwtr 7 1/8/ % There was a series of items or obstacles that had to be considered or overcome respectively. In reference to the digester gas (DG) system the purging of the digester headspace with nitrogen had to be scheduled and coordinated so that the required amount of nitrogen was pressurized in the digester in a timely manner. A leaking gasket of the liquid relief port was not detected during the tank air test and was addressed during startup. As a result the liquid relief port for the first digester that was started up had to be clamped down and was no longer an effective means 419
6 of digester s roof structural safety device. This liquid relief port gasket was changed to the appropriate one at a later date when the digester was taken out of service for maintenance. The enclosed flares operating parameters had to be modified in order to burn the initial low flow DG produced. Safety was the first priority for all actions and especially for when handling digester gas (DG) equipment. In reference to the solids operation all activities had to be coordinated based on continuous plant operation. The operation of the pasteurization facility was coordinated such that to efficiently and effectively ensure the production of the required daily digester feed. The ASA digesters temperature is controlled with the daily PSLDG feed temperature. The digester heat exchangers are not in service under normal operation. Upstream solids processes were operated such that PSLDG feed to the digesters was high in % TS (between 4.5 and 5.5 %TS). Purging and cleaning of equipment downstream of the digestion process were conducted in order to achieve Class A biosolids pathogen levels throughout. The moderate foaming that was developed after high filament activity in the biological reactors and high digester feed rate (see period 13 under Table 4) made it necessary to decrease the digester feed rate relative to the initial planned feed rate. RESULTS Alexandria Sanitation Authority (ASA) VA. For all four digesters volatile acids and alkalinity have remained well within appropriate ranges demonstrating that the digesters had no signs of difficulty such as foaming or low ph. The first digester was put in service (started feeding PSLDG) on June 3rd 25 and reached 2.3% total solids (TS) by the time we started transferring digested solids (DS) to dewatering which was the last week of September from all four digesters. The second digester was put in service on August 3th 25 and reached 2.2% total solids (TS) by the time we started transferring DS to dewatering. The third digester was put in service on September 14th 25 and reached 1.9% total solids (TS) by the time we started transferring DS to dewatering. The fourth digester was put in service on September 24th 25 and reached 1.8% total solids (TS) by the time we started transferring DS to dewatering. The success of the ASA digesters startup was a result of detailed preparation thorough equipment testing and operation of equipment with plant effluent water before start up training and working as a team with the operators often monitoring and evaluating the digesters in service and patience. DISCUSSION The charts below provide a comparison and information on anaerobic digesters start up based on the case studies seed and feed total solids concentration summarized in Table 5. 42
7 Table 5 UOSA/ASA Digesters Startup Seed Summary Parameter by Digester ASA UOSA Dig. 4 Dig. 3 1 Dig. 8/1 Dig. 7/1 Seed DS (% digester volume) n/a Feed (type) PSLDG PSLDG PSD PSD Feed (gal/day) Feed % TS % TS in digester /3/5 6/18/5 7/3/5 7/18/5 8/2/5 8/17/5 9/1/5 9/16/5. Feed % TS Feed: 7 day avg % TS: 7 day avg Figure 1 ASA digester 4 startup feed rates and % TS % TS Feed (gal/day) Feed % TS in digester /24/5 1/9/5 1/24/5 11/8/5 11/23/5 12/8/5 12/23/5 Feed % TS Feed: 7 day avg % TS: 7 day avg Figure 2 ASA digester 1 startup feed rates and % TS 421
8 Feed (gal/day) % TS Feed % TS in digester /1/ 8/16/ 8/31/ 9/15/ 9/3/ 1/15/ 1/3/ 11/14/ 11/29/ Feed % TS Feed: 7 day avg % TS: 7 day avg Figure 3 UOSA digester 8/1 startup feed rates and % TS The feed rate increase through the start up of ASA digester 4 is considerable less than the ones indicated for ASA digester 1 and UOSA digester 8/1 because of the small amount of seed solids that this digester received (only 4.5% of total volume). In addition the feed rate in UOSA digester 8/1 is higher than the feed rate of ASA digester 1. UOSA feed solids had an over 1% less concentration than the ASA feed solids therefore higher feed rates were acceptable. UOSA generally tends to be more aggressive in reference to the digesters startup feed rates Alkalinity (mg/l) ph Alaklinity ph 6 3 VAs 6/3/5 6/18/5 7/3/5 7/18/5 8/2/5 8/17/5 9/1/5 9/16/ Figure 4 ASA digester 4 startup stability Alkalinity VAs ph ph: 7 day avg Alkalinity: 7 day avg VAs: 7 day avg. 422
9 Alaklinity Alkalinity (mg/l) ph ph VAs /24/5 1/9/5 1/24/5 11/8/5 11/23/5 12/8/5 12/23/5 Alkalinity VAs ph Alkalinity: 7 day avg VAs: 7 day avg. ph: 7 day avg Figure 5 ASA digester 1 startup stability Alkalinity Alkalinity (mgl/l) ph ph VAs /1/ 8/16/ 8/31/ 9/15/ 9/3/ 1/15/ 1/3/ 11/14/ 11/29/ Alkalinity TOAs ph ph: 7 day avg Alkalinity: 7 day avg TOAs: 7 day avg Figure 6 UOSA digester 8/1 startup stability The slow increase in alkalinity for ASA digester 4 along with the ph stabilizing is indicated on figure 4. ASA digester 1 and UOSA digester 8/1 indicate a more stable operation from the beginning of startup. ASA tests their samples for volatile acids versus the total organic acids that UOSA perform analysis for. Both perform the analysis based on the recent standard methods. The total organic acids include the volatile acids along with crotonic adipic pyruvic phthalic fumaric lactic succinic malonic gallic aconitic and oxalic acids. For both plants the indicated acids do not raise any concerns. For UOSA digester 8/1 ph actually reached a minimum of 6.56 S.U. while TOA was decreasing from its peak. A ph at this level is normally 423
10 considered undesirable and potentially inhibitory of methanogens but no obvious ill effects were observed DG Produced x 1 ft3/day %VSR DG % VSR /3/5 6/18/5 7/3/5 7/18/5 8/2/5 8/17/5 9/1/5 9/16/5 4 DG Produced %VSR % VSR: 7 day avg DG produced: 7 day avg Figure 7 ASA digester 4 startup performance DG Produced x 1 ft3/day %VSR DG % VSR /24/5 1/9/5 1/24/5 11/8/5 11/23/5 12/8/5 12/23/5 DG Produced %VSR % VSR: 7 day avg DG produced: 7 day avg Figure 8 ASA digester 1 startup performance 424
11 % VSR 45 4 %VSR /1/ 8/16/ 8/31/ 9/15/ 9/3/ 1/15/ 1/3/ % VSR % VSR: 7 day avg Figure 9 UOSA digester 8/1 startup performance The performance for the digesters start up was evaluated based on the percent volatile solids reductions (% VSR) and the DG production. Once the digester reached its loading capacity the % VSR stabilized between a range of high 4s and low 6s. For UOSA digester 8/1 there is an indication of some low % VSR values at the end of September 2 that are not supported by the available data. The DG production indicated for ASA digester 4 actually commenced before August 25. DG was produced as early as the third day of startup but actual data were not available before August 25. The amount of DG produced represent the total amount produced daily by all digesters in service. Data in reference to DG produced from the UOSA digesters during startup are not available. 425
12 % TS Feed (gal/day) Feed % TS in digester /6/1 3/21/1 4/5/1 4/2/1 5/5/1 5/2/1 6/4/1 6/19/1. Feed % TS Feed: 7 day avg % TS: 7 day avg Figure 1 UOSA digester 7/1 startup feed rate and % TS ph Alkalinity (mgl/l) Alkalinity VAs /6/1 3/21/1 4/5/1 4/2/1 5/5/1 5/2/1 6/4/1 6/19/1. Alkalinity TOAs ph ph: 7 day avg Alkalinity: 7 day avg TOAs: 7 day avg Figure 11 UOSA digester 7/1 startup stability 426
13 %VSR 5 % VSR /5/ 3/2/ 4/4/ 4/19/ 5/4/ 5/19/ 6/3/ % VSR % VSR: 7 day avg Figure 12 UOSA digester 7/1 startup performance Figures 1 through 12 provide information on the startup of UOSA digester 7/1. The exact quantity of seed provided for the startup of digester 7/1 back in Spring of 21 is not available. Based on the steep slope of the % TS along with the high amounts of total organic acids as shown in Figure 11 and the low %VSR it is seen that digester 7/1 was overloaded at the beginning of April 21. Digester 7/1 was started under emergence conditions; there was not sufficient time for planning and monitoring the results were the overloaded digester. A total of 33 lbs of sodium bicarbonate were added between April 4 th and April 6 th 21. The sodium bicarbonate provided the required buffering for the digester to establish stable conditions (total organic acids decreased and VSR % increased). CONCLUSIONS Whether a digester is being put in service for first time or back in service after maintenance planning monitoring and patience are the key factors for its startup. A digester can be started up with minimum seed (less than 5% of total volume) or a lot of seed (over 5% of total volume) the less the seed the longer it takes and the more careful management it requires. If multiple digesters are to be started up the best practice is to start up one at a time and to use the dormant digester concept. Per the dormant digester concept when the starting up digester reaches the normal operating level then digesting solids equal to the daily feed of the seed digester are transferred to the next digester to start up. During filling the dormant digester is not being mixed neither fed. Anaerobic digesters react slowly to any adverse changes but also require time in order to correct any missteps. Chemicals like sodium bicarbonate are available in order to add buffering 427
14 capacity but they should be applied only when really needed and not as means to speed up the start up. ACKNOWLEDGMENTS Credits. The authors thank the operators and lab personnel of the two wastewater treatment plants who performed the start up and collected the data that formed the basis of this document. Authors. A big thank you to Ron Sieger for his assistance with the ASA startup. He is greatly missed. REFERENCES U.S. Environmental Protection Agency (23) Environmental Regulations and Technology Control of Pathogens and Vector Attraction in Sewage Sludge; EPA-625/R Water Environment Federation (1998) Design of Municipal Wastewater Treatment Plants 4th ed.; Manual of Practice No. 8; Alexandria Virginia. Standard Methods Committee (1996) 556 Organic and Volatile Acids 428
Codigestion Case Studies Enhancing Energy Recovery From Sludge
Codigestion Case Studies Enhancing Energy Recovery From Sludge Dale Gabel, PE, BCEE MWRD PWO Seminar 1 May 23, 2012 What is Codigestion? Direct addition of high-strength organic wastes to municipal wastewater
More informationDIGESTER FOAMING. Maintenance for Biosolids Systems. Steve Walker Senior Operations Specialist. September 13, sw510s1.pptx/1
DIGESTER FOAMING CAUSES AND SOLUTIONS CWEA Math, Operations, and Maintenance for Biosolids Systems Seminar September 13, 2011 Steve Walker Senior Operations Specialist sw510s1.pptx/1 LEARNING OBJECTIVES
More informationEnergy Optimized Resource Recovery Project Presented By: Curtis Czarnecki, P.E.
Kenosha Wastewater Treatment Plant Energy Optimized Resource Recovery Project Presented By: Curtis Czarnecki, P.E. Kenosha Water Utility March 22, 2016 WWTP Service Area Overview Population: 110,000 Service
More informationAnaerobic Digestion- opportunities to optimize the process
Northeast Residuals and Biosolids Conference 2016, Cromwell, Connecticut Anaerobic Digestion- opportunities to optimize the process October13, 2016 Acknowledgements Brown and Caldwell Tom Chapman (Tucson),
More informationANAEROBIC SLUDGE DIGESTION PROCESS. Prepared By Michigan Department of Environmental Quality Operator Training and Certification Unit
ANAEROBIC SLUDGE DIGESTION PROCESS Prepared By Michigan Department of Environmental Quality Operator Training and Certification Unit WASTEWATER Water used to carry waste products away from homes, schools,
More informationApplication of the AGF (Anoxic Gas Flotation) Process
Application of the AGF (Anoxic Gas Flotation) Process Dennis A. Burke Environmental Energy Company, 6007 Hill Road NE, Olympia, WA 98516 USA (E-mail: dennis@makingenergy.com http//www.makingenergy.com)
More informationStruvite Harvesting: Creating Value From Wastewater?
STRUVIA Sustainable Recovery of Phosphorus from Wastewater Struvite Harvesting: Creating Value From Wastewater? NC WEA/AWWA Annual Conference November 13, 2017 Luke Wood, PE Kruger, Inc In recent years,
More informationKenosha Wastewater Treatment Plant - Energy Optimized Resource Recovery Project
Kenosha Wastewater Treatment Plant - Energy Optimized Resource Recovery Project Prepared By: Curt Czarnecki, P.E. Kenosha Water Utility Presented By: Joseph Hughes, P.E. Centrisys Corporation MIWEA June
More informationAPPENDIX A. 1. Background. 1.1 Existing Facilities. Page 1
APPENDIX A PRELIMINARY TECHNICAL SPECIFICATIONS FOR BIOSOLIDS MANAGEMENT SERVICES JEA Buckman Residuals Management Facility 1. Background JEA is seeking biosolids management services from experienced biosolids
More informationAdvanced Aerobic Digestion. ThermAer. Autothermal Thermophilic Aerobic Digestion. Biosolids Treatment. Thermal Process Systems ThermAer Process
8 0 6 0 4 0 Advanced Aerobic Digestion ThermAer Autothermal Thermophilic Aerobic Digestion 2 0 Biosolids Treatment 0 Thermal Process Systems ThermAer Process ThermAer System Aerobic Process High Rate
More informationThermal Hydrolysis The Next Generation
Thermal Hydrolysis The Next Generation Peter Loomis, P.E. (CDM Smith) Tom Jacobs, P.E. (Trinity River Authority) Samir Mathur, P.E. (CDM Smith) Engin Guven, Ph.D., P.E. (CDM Smith) Danny Hurtado, P.E.
More informationPost-Aerobic Digester with Bioaugmentation Pilot Study City of Meridian, ID WWTP PNCWA 2010
Post-Aerobic Digester with Bioaugmentation Pilot Study City of Meridian, ID WWTP by: William Leaf Adrienne Menniti Bruce Johnson CH2M HILL, Inc. Clint Dolsby Tracy Crane City of Meridian October 26, 21
More informationSIMPLE and FLEXIBLE ENERGY SAVINGS And PERFORMANCE ENHANCEMENT for OXIDATION DITCH UPGRADES
SIMPLE and FLEXIBLE ENERGY SAVINGS And PERFORMANCE ENHANCEMENT for OXIDATION DITCH UPGRADES Oxidation ditches are very popular wastewater treatment processes for small to medium sized municipalities that
More informationHarrisburg Advanced Wastewater Treatment Facility Biosolids Facilities Improvement Plan Existing Conditions Report. February 2017
Harrisburg Advanced Wastewater Treatment Facility Biosolids Facilities Improvement Plan Existing Conditions Report February 2017 Harrisburg Advanced Wastewater Treatment Facility Biosolids Facilities Improvement
More informationIntegrated Activated Sludge and Biosolids Treatment to Conserve Energy & Waste Solids Disposal
Integrated Activated Sludge and Biosolids Treatment to Conserve Energy & Waste Solids Disposal Nathan Antonneau, P.E. Presentation Outline Typical Flowsheet Configurations Process Reconfiguration - ISBR
More informationAssessment of Operating Challenges of Digester Foaming. by Ralph B. Rusty Schroedel, Jr., BCEE Brown and Caldwell
Assessment of Operating Challenges of Digester Foaming by Ralph B. Rusty Schroedel, Jr., BCEE Brown and Caldwell Based Partially on a Survey and Workshops by the Central States Water Environment Association
More informationHonouliuli WWTP Start Up and Operation of the New Anaerobic Digesters
2011 HWEA 33 rd Annual Conference Honouliuli WWTP Start Up and Operation of the New Anaerobic Digesters Presentation by Peter B. Melnyk PhD, P.E. B. Kainani Andrade, P.E. Wagdy A. Guirguis, P.E. OVERVIEW
More informationTaking the Waste out of WAS: Sludge Pretreatment for Beneficial Uses
Taking the Waste out of WAS: Sludge Pretreatment for Beneficial Uses December 5, 2013 Matt Van Horne, P.E. 1 1 Agenda Why Sludge Pretreatment? What is OpenCel? Case Study #1: Philadelphia Water Department
More informationPrepared by the Operation of Municipal Wastewater Treatment Plants Task Force of the Water Environment Federation
Operation of Municipal Wastewater Treatment Plants WEF Manual of Practice No. 11 Chapter 31 Aerobic Digestion Sixth Edition Prepared by the Operation of Municipal Wastewater Treatment Plants Task Force
More informationAnaerobic Sludge Digestion
Chapter 8 Anaerobic Sludge Digestion Sludge digestion AD is used to stabilize both primary & secondary sludges having a solids content of between 2-6% (20-60 gts/l). About 70% of the mixed sludge is degradable
More informationAnaerobic Digestion The New Frontier Ohio WEA Biosolids Specialty Workshop 11 December 2014 J. Hunter Long
Anaerobic Digestion The New Frontier Ohio WEA Biosolids Specialty Workshop 11 December 2014 J. Hunter Long Outline Process Basics Digester Component Parts Anaerobic Digester Process Configurations 21 st
More informationEVALUATION OF ENERGY RECOVERY OPTIONS FOR CONVERSION OF AEROBIC DIGESTERS TO ANAEROBIC DIGESTION
EVALUATION OF ENERGY RECOVERY OPTIONS FOR CONVERSION OF AEROBIC DIGESTERS TO ANAEROBIC DIGESTION Jody B. Barksdale, P.E MWH; Juan R. Oquendo, P.E. MWH; Bruce A. Petrik, P.E. - MWH ABSTRACT. The threshold
More informationVILLAGE OF ALGONQUIN 2014 WASTEWATER FACILITY PLAN UPDATE EXECUTIVE SUMMARY
EXECUTIVE SUMMARY EXECUTIVE SUMMARY INTRODUCTION AND BACKGROUND The Village of Algonquin, located along the Fox River in McHenry County, provides wastewater collection and treatment services to the entire
More informationANAEROBIC DIGESTION IMPROVING ENERGY EFFICIENCY WITH MIXING
ANAEROBIC DIGESTION IMPROVING ENERGY EFFICIENCY WITH MIXING Neil Massart 1*, James Doyle 2, Jackson Jenkins 2, James Rowan 1, Cindy Wallis-Lage 1 1 Black & Veatch 8400 Ward Parkway Kansas City, MO 64114Missouri
More informationStartup of Virginia's Newest Organics Co-Digestion Facility. Dennis Clough, Energy Systems Group George Bevington, Gerhardt, LLC
Startup of Virginia's Newest Organics Co-Digestion Facility Dennis Clough, Energy Systems Group George Bevington, Gerhardt, LLC FWSA the Next 20 Years $14,000,000.00 $12,000,000.00 $10,000,000.00 $8,000,000.00
More informationBENEFITS OF THERMOPHILIC DIGESTION AT CHRISTCHURCH WASTEWATER TREATMENT PLANT
BENEFITS OF THERMOPHILIC DIGESTION AT CHRISTCHURCH WASTEWATER TREATMENT PLANT R W Bouman CH2M Beca Ltd and J Feary Christchurch City Council, Treatment Plant Manager ABSTRACT In 2010, two 7,000m³ anaerobic
More informationENHANCING THE PERFORMANCE OF OXIDATION DITCHES. Larry W. Moore, Ph.D., P.E., DEE Professor of Environmental Engineering The University of Memphis
ENHANCING THE PERFORMANCE OF OXIDATION DITCHES Larry W. Moore, Ph.D., P.E., DEE Professor of Environmental Engineering The University of Memphis ABSTRACT Oxidation ditches are very popular wastewater treatment
More informationResiduals, Biosolids and Sludge Processing Practice Questions
Residuals, Biosolids and Sludge Processing Practice Questions 1. As an operator of a gravity thickener, you notice floating sludge rising throughout the thickener. Which of the following would NOT be a
More informationExcellence in Engineering Since 1946
Excellence in Engineering Since 1946 Today s Outline Operations and Planning Incident Planning/Design Construction Commissioning Operation Plant Aerial DAF/Blended Sludge Tanks Anaerobic Digestion Secondary
More informationFull scale and laboratory scale results from the trial of MicroSludge at the Joint Water Pollution Control Plant at Los Angeles County
Full scale and laboratory scale results from the trial of MicroSludge at the Joint Water Pollution Control Plant at Los Angeles County R.J. Stephenson, S. Laliberte, P. M. Hoy, and D. Britch Paradigm Environmental
More informationAnaerobic Digester Optimization with Bio-Organic Catalyst. NYWEA 81 st Annual Meeting February 3, 2009 One Year Study November 07 - November 08
Anaerobic Digester Optimization with Bio-Organic Catalyst NYWEA 81 st Annual Meeting February 3, 2009 One Year Study November 07 - November 08 Municipal Anaerobic Digester Optimization Program Index! Overview
More informationOperating Experience with Ostara Struvite Harvesting Process
Operating Experience with Ostara Struvite Harvesting Process Authors: Steve Reusser 1, Alan Grooms 1, Aaron Dose 1, Ahren Britton 2, Ram Prasad 2 1. Madison Metropolitan Sewerage District 2. Ostara Nutrient
More informationTotal Makeover for Biosolids Handling at DC Water s Blue Plains Advanced Wastewater Treatment Plant. February 2015
Total Makeover for Biosolids Handling at DC Water s Blue Plains Advanced Wastewater Treatment Plant February 2015 Today s Makeover Will Include Recent History of Blue Plains Solid Handling Processes Evolution
More informationOptimizing the Performance of Anaerobic Digestion
Optimizing the Performance of Anaerobic Digestion Marialena Hatzigeorgiou, P.E. Senior Technologist Marialena.Hatzigeorgiou@ch2m.com 703-376-5113 1 2015_WWGST_RRR_PPT_Template_01.pptx Agenda Basics of
More informationThe Biosolids Odor Reduction Roadmap (BORR): A Decision Tool to Reduce Cake Odors
The Biosolids Odor Reduction Roadmap (BORR): A Decision Tool to Reduce Cake Odors Presented at Dewatering 201: Technology, Evolutions, and Trends A webinar sponsored by the Water Environment Association
More informationOptimization of Anaerobic Digestion with Bio- Organic Catalyst Compositions (BOCs)
CASE STUDY bio-organic.com Optimization of Anaerobic Digestion with Bio- Organic Catalyst Compositions (BOCs) 14th Annual European Biosolids and Organic Resources Conference and Exhibition - November 2009
More informationAnaerobic Digester Optimization with Bio-Organic Catalyst
Anaerobic Digester Optimization with Bio-Organic Catalyst NYWEA 81 st Annual Meeting February 3, 2009 One Year Study November 07 - November 08 2/2/09 1 Municipal Anaerobic Digester Optimization Program
More informationThermal Hydrolysis Comes to Texas!
Thermal Hydrolysis Comes to Texas! Samir Mathur PE, BCEE CDM Smith Summer Seminar July 25, 2014 Presentation Outline Thermal Hydrolysis fundamentals TRA solids masterplan overview Testing objectives Testing
More informationEvaluation of Energy Recovery Options for Conversion of Aerobic Digesters to Anaerobic Digestion
Evaluation of Energy Recovery Options for Conversion of Aerobic Digesters to Anaerobic Digestion Jody B. Barksdale, Juan R. Oquendo, and Bruce A Petrik his article discusses a case study in Florida for
More informationEVALUATING ALTERNATIVES FOR DISPOSING OF WATER PLANT SOLIDS INTO A WASTEWATER PLANT
EVALUATING ALTERNATIVES FOR DISPOSING OF WATER PLANT SOLIDS INTO A WASTEWATER PLANT Matthew Valade, P.E. July 25, 2014 Barboe.pptx Presentation Outline Project Background Why Dewater Croton Residuals Offsite?
More informationCHAPTER 4 DESCRIPTION OF EXISTING FACILITIES
CHAPTER 4 DESCRIPTION OF EXISTING FACILITIES Santa Clarita Valley Joint Sewerage System SCVJSS Conveyance System Solids Processing and Biosolids Management CHAPTER 4 DESCRIPTION OF EXISTING FACILITIES
More informationSonix for Enhanced Anaerobic Digestion: Final Report (15 July 2002)
Sonix for Enhanced Anaerobic Digestion: Final Report (15 July 2002) [Note: OCSD tested an ultrasonic device for improving the efficiency of digesting thickened waste activated sludge (TWAS) in anaerobic
More informationCenter Sanitation District
EHLS Center Sanitation District EHLS Engineering Erik Jorgensen Suzanne Givler Heath Anderson Leryn Gorlitsky Outline of Presentation Background Current and Future Conditions Decision Matrix Description
More informationSHAFDAN (Greater Tel Aviv Wastewater Treatment Plant) - Recent Upgrade and Expansion
SHAFDAN (Greater Tel Aviv Wastewater Treatment Plant) - Recent Upgrade and Expansion Messing A. 1, Sela Y. 2 Abstract Figure 1: 1 Balasha-Jalon Infrastructure Systems, Haifa, Israel 2 Igudan-Dan Region
More informationES.1 Solids Master Planning Background and Goals
Executive Summary The Arlington County Water Pollution Control Plant (WPCP) treats incoming wastewater flows for residents, businesses, and government agencies in the Arlington County sewer service area
More informationDESIGN AND OPERATIONAL CONSIDERATIONS TO AVOID EXCESSIVE ANAEROBIC DIGESTER FOAMING
DESIGN AND OPERATIONAL CONSIDERATIONS TO AVOID EXCESSIVE ANAEROBIC DIGESTER FOAMING ABSTRACT Neil Massart*, Black & Veatch Robert Bates, Louisville and Jefferson County Metropolitan Sewer District Blair
More information2017 Annual Performance Report
Newcastle Water Pollution Control Plant The Regional Municipality of Durham Newcastle Water Pollution Control Plant Environmental Compliance Approval (ECA): 3-2189-87-946 Dated July 26, 1994 Amendments:
More informationAn Odor Odyssey: Review of Scientific Progress toward Eliminating Odorant Emissions from Philadelphia s Biosolids
An Odor Odyssey: Review of Scientific Progress toward Eliminating Odorant Emissions from Philadelphia s Biosolids W.E. Toffey*, M.J. Higgins** * Philadelphia Water Department, 1101 Market St., Philadelphia,
More informationPERMIT TO OPERATE SILVER CLOUD CT., MONTEREY, CA TELEPHONE (831) FAX (831)
FFR MONTEREY BAY UNIFIED AIR POLLUTION CONTROL DISTRICT PERMIT TO OPERATE 24580 SILVER CLOUD CT., MONTEREY, CA 93940 TELEPHONE (831) 647-9411 FAX (831) 647-8501 15018 OPERATION UNDER THIS PERMIT MUST BE
More informationCOMMISSION MEETING. April 18, Engineering and Construction Team. Piscataway WWTP Bio-Energy Commissioners Status Briefing
COMMISSION MEETING April 18, 2018 Engineering and Construction Team Piscataway WWTP Bio-Energy Commissioners Status Briefing Item Number: Table of Contents 1. Commission Summary P. 1-2 2. Presentation
More informationWWTP Side Stream Treatment of Nutrients Considerations for City of Raleigh s Bioenergy Recovery Project. Erika L. Bailey, PE, City of Raleigh
WWTP Side Stream Treatment of Nutrients Considerations for City of Raleigh s Bioenergy Recovery Project Erika L. Bailey, PE, City of Raleigh LNBA / NRCA 2017 Wastewater Treatment Plant Operators Training
More informationTechnical Memorandum. 201 N. Civic Drive, #115 Walnut Creek, CA Tel: Fax:
201 N. Civic Drive, #115 Walnut Creek, CA 94596-3867 Tel: 925.937.9010 Fax: 925.937.9026 Technical Memorandum Prepared for: City of Sunnyvale, Sunnyvale, CA Project Title: Sunnyvale Strategic Infrastructure
More informationSludge Co-Thickening and Biogas Cogeneration in the Electric City
Sludge Co-Thickening and Biogas Cogeneration in the Electric City by Vincent Apa Electricity and the Light Bulb In 1879, Thomas Edison produced a reliable, long-lasting source of light using lower current
More informationPerformance Evaluation of the Moores Creek Advanced Water Resource Recovery Facility
Performance Evaluation of the Moores Creek Advanced Water Resource Recovery Facility Richard W. Gullick, Ph.D. Director of Operations Timothy Castillo Wastewater Manager Presented to the Albemarle County
More informationPalmer Wastewater Treatment Plant 6.7 Alternative 7: Upgrade Existing Lagoons with New Percolation Bed
6.7 Alternative 7: Upgrade Existing Lagoons with New Percolation Bed 6.7.1 Description This alternative considers expanding the capacity of the existing lagoon treatment facility and changing the discharge
More informationModule 22 : Sludge Management
1 P age Module 22 : Sludge Management Lecture 36 : Sludge Management 2 P age 22.1 Introduction In the context of wastewater treatment residual is used to refer sludge. The term sludge refers to the solids
More informationBiosolids Monthly Report
July-September 217 Biosolids Monthly Report Submitted By: Biosolids Management Program Team Wastewater Treatment Facility 14 Brander St. Richmond, VA 23224 Figure 1: the deputy director Ms. Rosemary Green
More informationPILOT SCALE TESTS OF A UNIQUE APPROACH FOR BNR UPGRADE OF A SHORT SRT HIGH PURITY OXYGEN SYSTEM AT PIMA COUNTY, AZ
PILOT SCALE TESTS OF A UNIQUE APPROACH FOR BNR UPGRADE OF A SHORT SRT HIGH PURITY OXYGEN SYSTEM AT PIMA COUNTY, AZ ABSTRACT Ron Riska,: Pima County Wastewater Management Division Joseph A. Husband, P.E.,
More informationNew England s First Linear Motion Sludge Mixer A Success Story. Northeast Residuals and Biosolids Conference Cromwell, CT
New England s First Linear Motion Sludge Mixer A Success Story Northeast Residuals and Biosolids Conference Cromwell, CT October 13, 2016 Agenda 1 Background 2 Process Evaluation 3 Recommended Alternative
More informationLEMNA BIOLOGICAL TREATMENT PROCESS LEMTEC TM TECHNOLOGIES, INC.
LEMNA TECHNOLOGIES, INC. I n n o v a t i v e W a s t e w a t e r T r e a t m e n t S o l u t i o n s LEMTEC TM BIOLOGICAL TREATMENT PROCESS LEMNA For more than 20 years, Lemna has been the world leader
More information1/11/2016. Types and Characteristics of Microorganisms. Topic VI: Biological Treatment Processes. Learning Objectives:
Topic VI: Biological Treatment Processes Learning Objectives: 1. Discuss microbiology and relate it to wastewater treatment. 2. Describe growth kinetics of pure bacterial culture with Monod expression
More informationINTERESTINGLY ATAD: OPERATIONAL DATA FROM THE NEW ATADS IN ONTARIO
INTERESTINGLY ATAD: OPERATIONAL DATA FROM THE NEW ATADS IN ONTARIO Case Study including, the design conditions, construction, and operating data of four plant operations utilizing 2 nd Generation ATAD
More informationANAEROBIC CO-DIGESTION OF A SINGLE SOURCE OILY WASTE AND HIGH STRENGTH PET FOOD WASTEWATER: A STUDY OF FAILURE AND REVIVAL OF A FULL SCALE DIGESTER
ANAEROBIC CO-DIGESTION OF A SINGLE SOURCE OILY WASTE AND HIGH STRENGTH PET FOOD WASTEWATER: A STUDY OF FAILURE AND REVIVAL OF A FULL SCALE DIGESTER C. Acharya 1, R. Kurian 2 1 Stantec Consulting, 800-171
More informationAnaerobic Digestion Fundamentals
Anaerobic Digestion Fundamentals What are they designed for? Leonard E. Ripley, Ph.D., P.E., BCEE Senior Process Engineer / Freese and Nichols, Inc. 1 Introduction: Pancakes 2 Introduction: Eggs & Silos
More informationHIGH PERFORMANCE ANAEROBIC DIGESTION
HIGH PERFORMANCE ANAEROBIC DIGESTION Parry, D. 1 1 CH2M, 1100 112th Avenue NE, Suite 500, Bellevue, WA 98004 David Parry, Ph.D, PE, BCEE Tel. 1.425.301.4070 Email David.Parry@ch2m.com Abstract Features
More informationAquaPASS. Aqua MixAir System. Phase Separator. System Features and Advantages. Anaerobic. Staged Aeration. Pre-Anoxic.
PHASED ACTIVATED SLUDGE SYSTEM PHASED ACTIVATED SLUDGE SYSTEM Aqua-Aerobic Systems has led the industry in time-managed, biological technology since 1984. In 2004, Aqua-Aerobic applied its expertise in
More informationDELHI CHARTER TOWNSHIP
Sustainability Efforts at the Publicly Owned Treatment Plant Sandra Diorka, Director of Public Services Delhi Charter Township DELHI CHARTER TOWNSHIP Project Background 1962 first primary treatment facility
More informationFAIRMONT WASTEWATER TREATMENT PLANT
FAIRMONT WASTEWATER TREATMENT PLANT 2006 Page 1 PUBLIC UTILIES COMMISSION Bill Supalla Joe Kurtzman Andy Noll Jeff Ziemer David Kuhl SPECIAL THANKS TO CITY STAFF Jim Zarling, City Administrator Mike Humpal,
More informationSludge Management EENV 5--- Chapter 4 Sludge Stabilisation
Sludge Management EENV 5--- Chapter 4 Sludge Stabilisation Definition and objectives of Stabilisation Raw sludge is rich in pathogenic organisms, easily putrescible and rapidly developing unpleasant smell.
More informationOptimization of Biogas Production and Use for Des Moines, IA
Optimization of Biogas Production and Use for Des Moines, IA Presented by Scott Carr, P.E. March 2015 Agenda Background High-strength organic waste receiving and conveyance Managing foam production Mixing
More informationWEF Residuals and Biosolids Conference Piloting to Establish Performance Criteria at Miami s South District WWTP
Piloting to Establish Performance Criteria at Miami s South District WWTP Terry Goss 1 ; Brian, Stitt 1 ; Manuel Moncholi 2 ; Mohammad Abu-Orf 3 ; Ismael Diaz 4 1 AECOM Water, 2 Miami-Dade Water and Sewer
More informationTechnical Memorandum No. 1
To: From: Steve McGowan, P.E., BCEE Project Manager, Malcolm Pirnie, Inc. Eric Wang, P.E. Project Engineer, Malcolm Pirnie, Inc. Date: Subject: August 11, 28 (Final) Madison MSD Project No. 84251 Malcolm
More informationCity of New Ulm Wastewater Treatment Facility Improvements Class A Bio-solids Production
City of New Ulm Wastewater Treatment Facility Improvements Class A Bio-solids Production By Mitchell Swanson, Environmental Design Engineer Bolton & Menk, Inc. Background With a population of approximately
More informationDealing with Unexpected Wastewater Treatment Plant Disruptions. February 16, 2017
Dealing with Unexpected Wastewater Treatment Plant Disruptions February 16, 2017 Location Map WPCP History Original WPCP constructed on this site in 1928 consisting of primary treatment and chlorination;
More informationAgriClean Mesophilic Digester and AgriJet Flush System
AgriClean Mesophilic Digester and AgriJet Flush System FINAL REPORT For the NC Attorney General-Smithfield Foods/Premium Standard Farms/Frontline Farmers Agreements Prepared by Dr. Leonard S. Bull, PI
More informationAppendix D JWPCP Background and NDN
Appendix D JWPCP Background and NDN JWPCP Background JWPCP Water Quality Primary Clarifiers HPO Reactors Final Clarifiers Unit Influent Primary Effluent Secondary Effluent BOD mg/l 460 240
More informationSCUM A LIABILITY OR AN ASSET? Chad M. Simmons, P.E. Leonard Ripley, Ph.D., P.E., BCEE Freese and Nichols, Inc.
SCUM A LIABILITY OR AN ASSET? Chad M. Simmons, P.E. Leonard Ripley, Ph.D., P.E., BCEE Freese and Nichols, Inc. Farida S. Goderya, Ph.D., P.E. City of Fort Worth - Water Department, Texas ABSTRACT Until
More informationW O C H H O L Z R E G I O N A L W A T E R R E C L A M A T I O N F A C I L I T Y O V E R V I E W
Facility Overview The recently upgraded and expanded Henry N. Wochholz Regional Water Reclamation Facility (WRWRF) treats domestic wastewater generated from the Yucaipa-Calimesa service area. The WRWRF
More informationMesophilic, Thermophilic And Temperature Phased Anaerobic Digestion Of Waste Activated Sludge
Mesophilic, Thermophilic And Temperature Phased Anaerobic Digestion Of Waste Activated Sludge David Bolzonella*, Francesco Fatone**, Silvia Di Fabio**, Franco Cecchi*** *Department of Science, Technology
More informationNew high-rate plug flow anaerobic digester technology for small communities
New high-rate plug flow anaerobic digester technology for small communities C. H. Burnett* and A. P. Togna** **Total Solids Solutions, 53 Talais Drive, Little Rock, AR, 72223 USA (E-mail: cburnett@comcast.net)
More informationComprehensive Biosolids and Bioenergy Planning Authors: Cameron Clark* 1, Irina Lukicheva 1, Anna James 1, Kathy Rosinski 1, Dave Parry 1
Comprehensive Biosolids and Bioenergy Planning Authors: Cameron Clark* 1, Irina Lukicheva 1, Anna James 1, Kathy Rosinski 1, Dave Parry 1 1 CH2M *Email: Cameron.Clark@ch2m.com KEYWORDS: biosolids, bioenergy,
More informationAnaerobic Digestion and High Strength Waste Co-Digestion Panel Discussion
Anaerobic Digestion and High Strength Waste Co-Digestion Panel Discussion Cody Schoepke - Mike Penkwitz - Chris Shaw - Mary Frances Klimek - Ryan Giefer - Sharon Thieszen - Greg Markle 52nd Annual Conference
More informationA Critical New Look at Nutrient Removal Processes
A Critical New Look at Nutrient Removal Processes Thomas E. Wilson,* John McGettigan* *Earth Tech, Inc. 675 North Washington Street Alexandria, Virginia 22314 ABSTRACT This paper questions the basic practice
More informationAnaerobic process. An introduction. Ecochemicals UAB
Anaerobic process An introduction Ecochemicals UAB When anaerobic process is used? Anaerobic process is usually used for: effluents that are highly polluted with organics, usually COD (BOD) varying from
More informationAltoona Westerly Wastewater Treatment Facility BNR Conversion with Wet Weather Accommodation
Pennsylvania Water Environment Federation PennTEC Annual Technical Conference June 4, 2013 Altoona Westerly Wastewater Treatment Facility BNR Conversion with Wet Weather Accommodation Presented by: Jim
More informationWWTF Capacity Assessment Project
Wastewater Treatment Facility Evaluation The Richland WWTF was constructed in 1985 to provide primary and secondary treatment for the City's wastewater. Section 3 includes a general description of the
More informationAnaerobic Digestion of Wastewater Treatment Plant Biosolids (Sludge)
Anaerobic Digestion of Wastewater Treatment Plant Biosolids (Sludge) CIVE 1199 Water and Wastewater Treatment Civil, Environmental and Chemical Engineering RMIT 21 September 2007 Prof. Dr. Göksel N. Demirer
More informationCHEMICAL FREE PHOSPHOROUS ELIMINSTION P-UPTAKE PROCESS
CHEMICAL FREE PHOSPHOROUS ELIMINSTION P-UPTAKE PROCESS 2013 Florida Water Resources Conference Albert Bock Panama City, Florida, 32404 (407) 913 1495, info@aquaconeer.com 1 Introduction: Today Bay County
More informationTHE DEMON ANAMMOX PROCESS: RESOURCE SAVINGS THROUGH SIDE STREAM TREATMENT, AND THE STEPS TOWARDS AN ENERGY NEUTRAL WWTP PRESENTED AT: NC AWWA-WEA 97
THE DEMON ANAMMOX PROCESS: RESOURCE SAVINGS THROUGH SIDE STREAM TREATMENT, AND THE STEPS TOWARDS AN ENERGY NEUTRAL WWTP PRESENTED AT: NC AWWA-WEA 97 TH ANNUAL CONFERENCE PRESENTED ON: 13 NOVEMBER, 2017
More informationTable 1. Existing Anaerobic Digesters
Page 2 The digesters are operated in series as a high rate system, meaning the primary digester is operated as high rate fermentation process with heating and mixing. The secondary digester is used to
More informationRECYCLING DIGESTED SLUDGE TO REDUCE FAT OIL AND GREASE BUILD-UP IN PIPES
RECYCLING DIGESTED SLUDGE TO REDUCE FAT OIL AND GREASE BUILD-UP IN PIPES DongHyun Lee, Nigel Sanders - Watercare Services Ltd, Auckland, New Zealand ABSTRACT The fat, oil and grease (FOG) in raw sewage
More informationVolatile Solids Reduction (VSR): Considerations for Accurate Measurement and Reporting
Volatile Solids Reduction (VSR): Considerations for Accurate Measurement and Reporting Martyn Quinn Eastern Region Biosolids Coordinator 329-3505 martyn.quinn@ecy.wa.gov September, 2009 What are volatile
More informationMaking Waste Productive. Creating Energy from Waste
Making Waste Productive Creating Energy from Waste 1 Creating Energy Inputs from Current Waste Outputs Organic material (waste) can be converted into energy (methane) through a process called anaerobic
More informationOregon Operators Conference Operator Math Workshop Module II
Oregon Operators Conference Operator Math Workshop Module II Lance Mason, Senior Operations Specialist August 16, 2018 Conversion Math Brief Review From Module I Conversions to Remember 8.34 lbs. / gallon
More informationWEFTEC.06. **Cobb County Water System, Marietta, Georgia
CHEMICALLY ENHANCED PRIMARY TREATMENT FOR A LARGE WATER RECLAMATION FACILITY ON A CONSTRICTED SITE - CONSIDERATIONS FOR DESIGN, START-UP, AND OPERATION ABSTRACT Jeffrey A. Mills, P.E., BCEE,* Roderick
More information2015 HDR, Inc., all rights reserved.
2015 HDR, Inc., all rights reserved. Hastings Utilities Water Pollution Control Facility Improvements Brian Bakke, HDR ASCE Environmental Conference 4/6/2017 Review Existing Facilities Need for the Project
More informationSupplementary Data. Equations (S-1) and (S-2) were used to calculate dimensionless Henry s constant (K H ) at temperature T: þ 6:88 S 1
Supplementary Data Equations (S-1) and (S-2) were used to calculate dimensionless Henry s constant (K H ) at temperature T: logh T ¼ 675:74 T þ 6:88 S 1 where H T is Henry s constant [atm] at temperature
More informationThe Effect of Temperature on Methane Productivity of Municipal Solid Waste in Anaerobic Digester
The Effect of Temperature on Methane Productivity of Municipal Solid Waste in Anaerobic Digester Azadeh Babaee, 1 Jalal Shayegan, 1 Anis Roshani 2 Jalal Shayegan 1 1 Sharif University of Technology, Tehran,
More informationWhy THP Made Sense for TRA
Why THP Made Sense for TRA June 16, 2016 Central Regional Wastewater System Treatment Plant (CRWS) CRWS Solids Treatment Area 2 162-mgd ADF permitted and 125- mgd average daily flows Pre-THP Solids Process:
More informationNITROGEN REMOVAL GUIDE FOR WASTEWATER OPERATORS THE WATER PLANET COMPANY FORMS OF NITROGEN OF INTEREST TO WASTEWATER OPERATORS
NITROGEN REMOVAL GUIDE FOR WASTEWATER OPERATORS THE WATER PLANET COMPANY www.cleanwaterops.com FORMS OF NITROGEN OF INTEREST TO WASTEWATER OPERATORS Nitrogen exists in several forms. The principal nitrogen
More information