WEF Residuals and Biosolids Conference Piloting to Establish Performance Criteria at Miami s South District WWTP

Size: px
Start display at page:

Download "WEF Residuals and Biosolids Conference Piloting to Establish Performance Criteria at Miami s South District WWTP"

Transcription

1 Piloting to Establish Performance Criteria at Miami s South District WWTP Terry Goss 1 ; Brian, Stitt 1 ; Manuel Moncholi 2 ; Mohammad Abu-Orf 3 ; Ismael Diaz 4 1 AECOM Water, 2 Miami-Dade Water and Sewer Department, 3 Formally AECOM Water, 4 Gannett Fleming ABSTRACT A six-month centrifuge thickening, digestion and centrifuge dewatering pilot study was conducted at Miami-Dade s South District Wastewater Treatment Plant (SDWWTP). The pilot study was set up to simulate future thickening, digestion and dewatering operating conditions to establish future thickening and dewatering performance criteria. Full scale piloting was conducted in three phases. Phase 1 operation, focusing on thickening performance began in November The testing showed that the centrifuge could reliably produce thickened solids at 5-6% total solids (TS) and achieve greater than 95% solids recovery. Testing was conducted using both dry and emulsion polymers. The dry polymer required 2.5 to 3.5 gram per dry kilogram (g/kg) or 5-7 pound per dry ton (lb/dt) active compared to g/kg (1-3 lb/dt) active emulsion. It was also possible to thicken the sludge to 5-6% TS without the use of polymer but this reduced hydraulic throughput by about 50% to allow solids recoveries to remain above 90%. During Phase 2 operation, which began in December 2015, the sludge feed to the thickening centrifuge was switched to thickened sludge from the gravity concentrators to increase centrifuge solids throughput. The centrifuge thickened sludge was fed to Digester 9 which was isolated to receive only mechanically thickened biosolids at 5-7% TS. The solids content in Digester 9 was increased from approximately 2% to approximately 3.5% TS and the volatile solids reduction (VSR) in Digester 9 averaged 46%. Phase 3 of the pilot operation focused on the centrifuge dewatering of the digested biosolids from Digester 9. Testing was conducted using both dry and emulsion polymers with multiple polymer injection points. The testing showed that 16-18% TS cake could be achieved with 10 to 15 g/kg (20-30 lb/dt) active dry polymer. The pilot testing showed that the dewatered cake solids was lower than the preliminary design value of 20% TS with a presumed 12.5 g/kg (25 lb/dt) active dry polymer dose. Dryer cake at 20-22% TS could be produced using emulsion polymer but required higher active polymer dosages above 20 g/kg (40 lb/dt). KEYWORDS Biosolids, Thickening, Dewatering, Anaerobic Digestion, Centrifuges, Pilot Testing INTRODUCTION As part of the Consent Decree Project for Miami Dade s South District Wastewater Treatment Plant (SDWWTP), the Program Management and Construction Management (PMCM) team conducted pilot testing of centrifuge thickening prior to anaerobic digestion and centrifuge dewatering post anaerobic digestion. The pilot dewatering testing used digested biosolids from the digester receiving only mechanically thickened biosolids at high solids input concentration after steady state operation was achieved. The pilot testing established performance criteria to be used for the design build documents and associated process performance guarantee. 613

2 SDWWTP is located in the southeastern portion of Miami-Dade County and serves the southern and southwestern portion of the county. The SDWWTP is a high purity activated sludge secondary treatment facility with a permitted capacity of million gallons per day (mgd) or 17,740 cubic meters per hour (m 3 /h). SDWWTP produces only waste activated sludge (WAS) and wasting is controlled using a modulating valve and flow meter that is tapped off the return activated sludge pumps. The WAS is mixed with polymer in the piping and sent to four 55 feet (16.8 meter) diameter gravity thickeners with a 13 feet (4.0 meter) side-water depth. The gravity thickeners thicken the solids to 2-3% total solids (TS) before being stabilized in twelve 105 feet (32 meter) diameter anaerobic digesters each with a nominal operating volume of 1.5 million gallons (5,700 cubic meters). The digesters are arranged in three clusters of four digesters per cluster, where two digesters per cluster operate as primary digesters and two operate as secondary digesters. Digester Cluster 3 normally operates with two of the digesters acting as sludge storage tanks before dewatering. Digester 9 is located in Cluster 3 and acts as a primary digester that discharges to Digester 10 which acts as a secondary digester. The digested biosolids are further dewatered using four (4) Alfa Laval PM centrifuges which achieve 18-22% TS. The sludge fed to the centrifuges is currently conditioned using a dry polymer type system. SDWWTP is replacing the existing gravity thickeners with new centrifuge thickeners which are expected to improve the performance and increase the capacity in the existing digestion complex. The existing dewatering centrifuges are also near the end of their useful service life and the design includes replacing the system with a new centrifuge dewatering complex. PILOT STUDY OVERVIEW AND OBJECTIVES To better establish performance criteria for the new thickening and dewatering centrifuges, a sixmonth centrifuge thickening, digestion and centrifuge dewatering pilot study was conducted at Miami-Dade s SDWWTP. The pilot study was set up to simulate future thickening, digestion and dewatering operating conditions to establish thickening and dewatering performance criteria. Figure 1 shows a plan view layout of the site and identifies the locations for the centrifuge thickening and dewatering pilot trailers. Figure 2 provides photos of the pilot testing trailers provided by Centrisys which were selected after a competitive bidding process. The PMCM team oversaw the piloting effort with outstanding support from the SDWWTP staff. Periodic samples collected throughout the pilot operation were all analyzed for TS. During Phase 2 and Phase 3, the PMCM team regularly monitored the volatile solids (VS) content of the thickened sludge fed to the digester and digested biosolids samples. Digested biosolids ph was also measured. The centrate samples were also analyzed for total suspended solids (TSS). College interns were trained to perform the sampling and laboratory analysis throughout the duration of pilot testing period. The pilot operation began in November 2015, and was conducted in three distinct Phases as outlined in Table

3 Figure 1: Site Plan Showing Centrifuge Installation, Overall (top), Zoomed In (bottom) 615

4 Figure 2: Photos of Pilot Equipment, Thickening (left), Dewatering (right) Table 1: Summary of Pilot Testing Phases Pilot Phase Objective Duration Sample measurements Phase 1: Thickening pilot operating with unthickened waste activated sludge (WAS) Phase 2: Thickening pilot operating with gravity thickened WAS Phase 3: Dewatering pilot operating with anaerobically digested biosolids following Phase 2 Thickening Determine centrifuge WAS thickening performance criteria Simulate high rate anaerobic digestion to monitor performance and prepare sludge for Phase 3 Determine centrifuge dewatering performance criteria with centrifuge thickened anaerobically digested WAS 4 weeks TS all TSS - centrate 5 months TS all VS/TS digester feed & digested biosolids ph digested biosolids 4 weeks TS all TSS - centrate PHASE 1: THICKENING PILOT TESTING Phase 1 piloting operation was based on feeding unthickened WAS to the pilot thickening centrifuge. The purpose of Phase 1 operation was to determine the optimum polymer design conditions and performance of the centrifuge thickening. The overall target for the centrifuge thickening performance, as stated in the basis of design and specifications, was to thicken the WAS to 5.5% TS while maintaining greater than 95% solids recovery. Determining the necessary polymer dose to achieve this performance is also important. Parameters that were adjusted for the centrifuge thickening included the pool depth, bowl speed and differential scroll speed. Thickening Pilot Testing - No Polymer Operation The system initially started up on lower sludge flows with no polymer injection. Figure 3 summarizes the operation without polymer for a medium bowl speed equal to 2,590 revolutions 616

5 per minute (RPM) and differential speed of 12 RPM with flow rates ranging from 40 to 100 gallons per minute (gpm) or 151 to 379 liters per minute (L/min). This operation showed that it was possible to thicken the sludge up to 6% TS without the use of polymer, but at higher throughputs (above 60 gpm or 227 L/min), the solids recovery was sacrificed. The tests were conducted at a deep pool depth, a medium pool depth and a shallow pool depth. The trend shows that at the shallowest pool depth solids recovery improved but total thickened solids was sacrificed. The thickened solids concentration at the deepest and medium pool depths were nearly the same but it should be noted that the feed solid content was lower when testing the deepest pool depth (0.9% TS) while the feed solids were closer to 1.4% solids when testing the medium pool depth. If testing was done on the same feed solids concentration, it would be expected that the solids would be thicker at the deepest pool depth. Results of the testing without polymer indicated that it is possible to maintain the desired thickened TS concentrations without the use of polymer. Although the operation without polymer may sacrifice solids recovery, future operation at this condition may be desired when sludge production is below design capacity as it could reduce operation and maintenance costs associated with polymer consumption. Figure 3: No Polymer Operation, Medium Bowl Speed (2,590 RPM) 617

6 Thickening Pilot Testing Emulsion Polymer Setup and Initial Testing The pilot unit was set up to allow injection of polymer at two locations as illustrated in Figure 4; either directly into the bowl of the unit (internal injection) or in the sludge feed line upstream of the centrifuge inlet (external injection). Polymer flow was measured during each sampling event using a calibration column located on the pilot trailer. The initial polymer used was PRAESTOL K144-L which is a cationic, high molecular weight emulsion polymer. Polymer dosage, using internal injection, was slowly increased at a constant throughput of 100 gpm (379 L/min) while visually monitoring the clarity of the centrate. The testing was conducted at the shallowest pool depth and a differential speed of 12 RPM. Once polymer was added, the bowl speeds were reduced from 2,590 RPM to between 1,900 to 2,100 RPM to keep the thickened solids from being too thick. The results showed that with the increased polymer dosages and reduction in bowl speed, the thickened solid content remained steady but the solids recovery improved. Once relatively clear centrate was achieved, the flowrate to the machine was increased to maximize throughput while optimizing solids recovery (based on visual observations of centrate quality). In addition, other cationic, high molecular weight emulsion polymers were tested in the machine. Optimization testing showed that the PRAESTOL K144L polymer worked the best. Internal Polymer Injection Point External Polymer Injection Point Figure 4: Thickening Polymer Injection Point Thickening Pilot Testing Dry Polymer Setup The Centrisys thickening unit contains an emulsion polymer system and is not set up with the provisions to operate on dry polymer so a creative solution was required to facilitate testing dry polymer in the pilot Centrifuge. In order to allow the testing, one of SDWWTP polymer make up systems, which was not currently in use, was used to make up the dry polymer solution which was pumped to a tote that was connected to a dedicated portable pump to meter the dry polymer 618

7 solution into the centrifuge. Photos of set up are provided in Figure 5. The pump on the trailer used for emulsion polymer was too small to pump the dry polymer solution. Figure 5: Temporary Dry Polymer Set Up A calibration curve was developed for the polymer pump by a series of bucket tests conducted at different pump speeds and the curve was compared to the theoretical zero psi pump curve showing good convergence. The dry polymer used for testing was Polydyne C-3283 which is the polymer the plant currently uses in their dewatering centrifuges. Thickening Pilot Testing Results Pilot tests were run to further determine results for the centrifuge thickening operation. The results from the optimization trials showed that good performance could be achieved with medium bowl speeds of 2,400 to 2,600 RPM. At a lower flow rate of 100 gpm (379 L/min), an emulsion polymer dose of 1 pound per dry ton (lb/dt) or 0.5 grams per dry kilogram (g/kg) showed good results but as the flow was increased to 150 gpm (568 L/min), at least 2 lb/dt (1 g/kg) was needed. The higher polymer dose requirements at higher flows also correlated to the point where external polymer injection provided better results than internal polymer injection. The polymer curves and flow curves conducted during the performance testing period was to further test the limits for the operational parameters. Additional performance testing was conducted in March of 2016 using the plants dry polymer, which is Polydyne C The purpose was to repeat the November testing but with the dry polymer that more closely represents future operation. Thickening Pilot Testing Polymer Curve Results Polymer curve tests were conducted by maintaining a constant volumetric throughput of sludge feed to the centrifuge but changing the polymer dose to measure the impact. With the exception of changing polymer dose, all other parameters on the centrifuge remained the same for each polymer curve test. In November 2015, three different polymer curves were generated for the 144-L emulsion polymer at 100 gpm (379 L/min), 150 gpm (568 L/min) and 170 gpm (644 L/min) WAS flow rates through the pilot centrifuge. In March 2016, an additional 144-L 619

8 emulsion polymer curve was conducted at 130 gpm (492 L/min) and several dry polymer curves were conducted at 130, 150 and 170 gpm (492, 568, and 644 L/min). Figure 6 also shows the data for emulsion polymer curves at the 130 gpm (492 L/min) and 150 gpm (568 L/min) WAS feed, conducted at medium bowl speed (2,400 2,600 RPM). At 130 gpm (492 L/min) WAS feed, the curve was conducted with internal polymer injection and at 150 gpm (568 L/min) WAS feed, the curve was conducted with external polymer injection. The concentration of the WAS during this testing ranged from 1.1% to 1.5% TS. Figure 6: Emulsion Polymer & 150 gpm WAS feed, Medium Bowl Speed As shown in Figure 6, at 130 gpm (492 L/min) WAS feed with internal emulsion polymer injection and a deep pool depth, good performance is obtained for polymer doses greater than 1 lb/dt (0.5 g/kg) active achieving close to 6% TS. At polymer doses greater than 1 lb/dt (0.5 g/kg) active, close to 100% solids recovery was also achieved. Exceeding 1.0 lb/dt or 0.5 g/kg (up to 1.6 lb/dt or 0.8 g/kg active) did not have much of an impact on the solids concentration or the solids recovery. 620

9 At 150 gpm (568 L/min) WAS feed with external emulsion polymer injection and a shallow pool depth, greater than 5% TS was achieved for all polymer doses tested. The solids recovery exceeded 95% for the two highest dosing points when active dosing was greater than 2.3 lb/dt (1.2 g/kg). The dry polymer curve for the WAS flow rate of 130 gpm (492 L/min) with both internal and external dry polymer injection is shown in Figure 7 for a medium bowl speed of 2,586 RPM and deep pool depth. The polymer concentration during these tests was approximately 0.8% TS. An additional 130 gpm (492 L/min) WAS polymer curve, also shown in Figure 7, used a 0.4% TS polymer solution (with internal dry polymer injection) at a bowl speed of 2,408 RPM and deep pool depth. For all tests, the feed averaged 1.2 to 1.4% TS. Figure 7: Dry Polymer gpm WAS Feed, Internal and External Injection, Medium Bowl Speed For internal dry polymer injection with a 0.8% TS polymer solution, greater than 5.5 % TS was achieved for all polymer doses tested, however, only greater than 95% recovery was achieved at polymer doses greater than 5 lb/dt (2.5 g/kg). For external dry polymer injection with a 0.8% TS polymer solution, the active polymer dose ranging from 4.3 to 6.7 lb/dt (2.2 to 3.4 g/kg) did not show significant differences in centrifuge performance in terms of solids content. The thickened solids content ranged from 6.5 to 6.6 % TS and the solids recoveries were greater than 95% for all samples. The TSS sample analyzed for 4.3 lb/dt (2.4 g/kg) may also have had an error and it was noted that the centrate was visually dirtier than the samples with high polymer dosages. For internal dry polymer injection with a 0.4% polymer solution, greater than 5.5 % TS 621

10 was achieved for all polymer doses tested and at polymer doses greater than 3.8 lb/dt (1.9 g/kg), the solids recovery was near the 95% target. The thickening pilot results show that at 130 gpm (492 L/min) WAS feed, approximately 5 lb/dt (2.5 g/kg) of the dry polymer is required to maintain greater than 95% recovery but at the settings tested, the thickened sludge exceeds the needed solids content and approaches 7% TS. Further optimization would be required to maintain the target of 5.5% TS such as lowering the pool depth. The dry polymer curves for the WAS flow rate of 150 gpm (568 L/min) with both internal and external dry polymer injection is shown in Figure 8 for a medium bowl speed of approximately 2,585 RPM and deep pool depth. The polymer concentration during these tests ranged between 0.7 to 0.8% TS. For all tests, the feed averaged 1.2 to 1.3% TS. Figure 8: Dry Polymer gpm, Internal and External Injection, Medium Bowl Speed For internal dry polymer injection, greater than 5% TS was achieved for all polymer doses tested, however, none of the points achieved greater than 95% recovery. Flocs were observed in the centrate for the external polymer injection testing so it was evident that this flow was too high for the internal polymer injection to work efficiently. For external injection, greater than 6% TS was achieved for all polymer doses tested. The solids recovery, however, was only greater than 95% for the highest active polymer dose which was 5.3 lb/dt (2.7 g/kg). It may have been possible to get more optimal performance (closer to 5.5 % TS with greater than 95% solids recovery) with a shallower pool depth. 622

11 Thickening Pilot Testing - Extended Operation Results After generating the polymer, flow and bowl speed curves, the unit was operated several days at a constant flowrate with optimized settings to test the stability of operation throughout the course of a day. During November 2015, these tests were conducted using the 144-L emulsion polymer at a WAS flow rate of 135 gpm (511 L/min), 165 gpm (625 L/min) and 200 gpm (757). In March 2016, the extended operation testing with dry polymer was repeated twice at 135 gpm (511 L/min). Samples were collected during these trials approximately once every hour. The results with emulsion polymer were stable throughout the course of a run but the results with the dry polymer showed more fluctuation with solid recovery degradation over time (see Figure 9). It was planned to again repeat the 135 gpm (511 L/min) extended operation testing using the dry polymer, however, the gearbox on the progressing cavity thickened sludge pump failed before this testing was completed. Due to the lead time to repair, it was not possible to conduct the additional testing in the schedule for the project. It is believed that limitations in the set-up and lack of mixing on the polymer tote contributed to the poor performance for the extended operation testing with dry polymer. The concentration of polymer samples collected throughout the extended run varied between 20 to 40% on both days tested. A comparison of the extended operation at 135 gpm (511 L/min) with emulsion and dry polymer is depicted in Figure 9. The runs with dry polymer at 4-7 lb/dt (2-3.5 g/kg) active polymer dosages were conducted with a deeper pool depth than the run with emulsion polymer conducted at 2-3 lb/dt (1-1.5 g/kg) active polymer dosages. The deeper pool depth is likely the reason the solid content was higher with the dry polymer testing than the emulsion polymer testing. The feed WAS concentration during all three runs ranged from 1.1 to 1.5% TS. Figure 9: Extended Thickening Operation at 135 gpm 623

12 The thickening pilot testing showed that the centrifuge could reliably produce solids at 5-6% TS and achieve greater than 95% solids recovery. Testing was conducted using both dry and emulsion polymers. The dry polymer required 5-7 lb/dt ( g/kg) active dosing compared to 1-3 lb/dt ( g/kg) active based on the emulsion. It was also possible to thicken the sludge to 5-6% TS without the use of polymer but this reduced hydraulic throughput by about 50% to allow solids recoveries to remain above 90%. PHASE 2 CONTINUOUS THICKENING PILOT OPERATION During Phase 2 operation, mechanically thickened sludge was fed to Digester 9 to simulate future high rate digestion conditions and to increase the solids content of the digested biosolids for the Phase 3 dewatering pilot operations. The feed to the thickening pilot was switched to gravity thickened sludge to increase solids loading through the thickener to increase the turnover rate in Digester 9. This mode of operation started in December 2015, continued through March 2016, and remained running in parallel with the dewatering piloting conducted in Phase 3. During Phase 2 operation, the thickening centrifuge was fed approximately 100 to 150 gpm (379 to 568 L/min) of sludge from the gravity concentrator and operated continuously. Figure 10 summarizes the centrifuge performance during the Phase 2 operation. On March 21, 2016 the feed was switched back to the unthickened WAS when the additional thickening testing using dry polymer was conducted. During Phase 2 operation, the feed from the gravity concentrators averaged 2.2% TS but ranged between 1.5 to 3% TS. The concentration in the gravity concentrator measured by the pilot staff compared closely with the concentration based on the plant records. The thickened solids content averaged 6.2% TS but fluctuated between 5 to 7% TS. During the Phase 1 operation, it was found that the hydraulic pressures inside the machine would increase overtime, likely due to grit building up in the machine, and would shut down on an alarm if pressures reached too high of a level. In order to mitigate this, the machine was operated at a lower speed with higher polymer doses for most of the Phase 2 operation which allowed for the unit to operate continuously. Weekly cleaning and routine maintenance was conducted throughout operation. Throughout Phase 2 operation, the solids content in Digester 9 was increased to approximately 3.5% TS. In comparison during this period, the other operational digesters operated at 1.5 to 2% TS as shown in Figure

13 Figure 10: Phase 2 Continuous Thickening Operation Figure 11: Digester Concentration Comparison, Digester 9 vs. Plant Records 625

14 During the Phase 2 operation period, Digester 9 averaged approximately 46% volatile solids reduction (VSR) with raw undigested sludge averaging 87% VS/TS and digested biosolids averaging 77% VS/TS. Gas production averaged 16 ft 3 /lb VSR (1 m 3 /kg VSR) throughout the four months of operation. The Solids Retention Time (SRT) in the digesters averaged a little more than 30 days and solids loading rate (SLR) averaged 0.11 lb VS/ft 3 -d (1.8 kg VS/m 3 ). When comparing the pilot data to the plant s other digesters, the volatile solids feed matched the plant records but the digester SRT was shorter at approximately 20 days and digested biosolids volatile solids content was slightly lower with the plants VSR during this period averaging approximately 42%. Thus, it appears that operating digestion with longer SRT and higher thickened sludge increased the VSR by about four percentage points, reducing the biosolids for downstream dewatering and beneficial use. It was desired to have Digester 9 at a new steady state before starting the dewatering piloting, so dewatering was targeted to start after approximately 3 digester SRT s have been achieved. Figure 12 confirms that the dewatering performance testing was conducted after three digester turnovers were achieved in Digester 9. The data in Figure 11 showed that the concentration in Digester 9 reached a consistent value of approximately 3.5% TS by March Figure 12: Digester 9 Turnover Progress during Phase 2 Operation PHASE 3 DEWATERING PILOT TESTING The purpose of Phase 3 operation was to determine the optimal design conditions and performance of the dewatering centrifuge using the thickened biosolids fed from Digester 9. The overall target for the centrifuge dewatering performance as stated in the basis of design and 626

15 specifications was to dewater the thickened digested biosolids to 20% TS while maintaining greater than 95% solids recovery. The necessary polymer dose to achieve this performance is also important to determine. The draft specifications indicate that active polymer dose should be less than 25 lb/dt. Textbook values for anaerobically digested WAS only biosolids are not readily available as most anaerobic digesters in industry digest WAS blended with primary sludge. Metcalf and Eddy 5 th edition lists 16 to 25% TS expected for untreated WAS and lists 22 to 25% TS expected for anaerobically digested combined WAS and primary. For both untreated WAS and anaerobically digested WAS and primary, the polymer consumption is expected to be 15 to 30 lb/dt (7.5 to 15 g/kg) active and solids recoveries are expected to be 95% or greater (M&E 5 th edition, 2014). Dewatering Pilot Testing Emulsion Polymer Initial Testing The initial testing started with emulsion polymers on March 2, Five cationic, high molecular weight emulsion polymers were tested in order to select the most effective two polymer types for further testing. The emulsion polymers were able to achieve 22 to 25% TS. Based on visual observation of cake dryness and centrate quality, Centrisys proceeded with purchasing more of the two candidate emulsion polymers (PRAESTOL 274 FLX and 290 FLX emulsion polymers). Dewatering Pilot Testing Dry Polymer Setup The centrifuge trailer has a dry polymer feeding system that was rarely used and required some effort to make it functional. The polymer blending system did not provide adequate mixing of the dry polymer and left unmixed and residual portions of polymer in the tank. The dry polymer feed pump, however, provided suitable control to deliver a dry polymer solution to the centrifuge. SDWWTP also had a dry polymer make up system that was no longer used, however, was functional. Initially, dry polymer solution was metered from the plant s make-up system directly to the dewatering centrifuge, however, the plant s polymer pumps could not adequately control the polymer feed for testing. In order to conduct the testing, a hybrid of both systems was used. Polymer solution made up using the plant s system was pumped into the dry polymer solution hopper on the Centrisys pilot dewatering centrifuge. The Centrisys pump was then used to meter the polymer to the centrifuge. The dry polymer used for the dewatering testing was Polydyne C-3283 which is currently used for the SDWWTP dewatering centrifuges. Dewatering Pilot Testing Polymer Injection Location Optimization Polymer injection location in the biosolids is important in getting proper biosolids flocculation for the desired dewatering. Several injection locations were tested using the plant s dry polymer. A mixed injection system, which included dosing a portion of the polymer in a static mixer in the interconnecting hose and the rest of the polymer injected at the grinder on the pilot trailer, was initially found to be the best method for polymer injection based on visual observations of the centrate clarity. However, later testing found that injecting polymer directly into the feed tube of the centrifuge provided better centrate quality. The first few weeks of testing were based primarily on the mixed polymer injection and the later testing was conducted using primarily the feed tube injection point. 627

16 Dewatering Pilot Testing Polymer Curve Results Polymer curve tests were conducted by maintaining a constant volumetric throughput of digested biosolids feed to the centrifuge but changing the polymer dose to measure the impact. With the exception of changing polymer dose, most of the other parameters on the centrifuge remained the same for each polymer curve test. During some of the tests, however, the differential speed was adjusted to increase cake solids while still trying to maintain good quality centrate based on visual observations. Testing showed that reducing the differential speed would increase cake solids but could sacrifice centrate quality and solids recovery. Polymer curve tests were conducted using both emulsion and dry polymer with both mixed and feed tube polymer injection. All of the dry polymer curves conducted on thickened biosolids from Digester 9 are presented in Figure 13 and the data depicts the injection point and polymer concentration. Figure 13: Compiled Dry Polymer Curves from Digester mix represents mixed polymer injection and FT represent feed tube polymer injection 628

17 For the majority of the dry polymer testing, the targeted polymer concentration was 0.8%, however, actual concentrations were measured daily throughout testing and solution concentration appeared to vary from day to day. In addition, the team conducted testing with a more dilute dry polymer concentration. The red circle on Figure 13 denotes the area targeted for optimization with dry polymer. All of the emulsion polymer curves conducted on thickened biosolids from Digester 9 is presented in Figure 14. Figure 14: Compiled Emulsion Polymer Curves from Digester 9 The polymer testing curves showed that SDWWTP s digested biosolids did not dewater to the level anticipated in the preliminary design (> 20% TS) at active polymer doses of 25 lb/dt (12.5 g/kg). Using the plant s dry polymer (Polydyne C-3283), it was difficult to dewater to greater than 18% TS unless the active polymer dose was above 50 lb/dt (25 g/kg). Dryer cake could be produced using emulsion polymer but high polymer doses were also required. For the dry 629

18 polymer, using feed tube injection verses the external or mixed injection allowed for lower polymer doses while still maintaining recoveries above 95%. Dewatering Pilot Testing - Extended Operation Results In addition to polymer curve tests, the dewatering centrifuge was operated several days at a constant flowrate to test the stability of operation throughout the course of a day. Three tests were conducted at 50 gpm (189 L/min), two with dry polymer and one with 274-FLX emulsion polymer. Two tests were also conducted at 75 gpm (284 L/min), one with dry polymer and one with 274-FLX emulsion polymer. The extended runs using dry polymer are shown in Figure 15. The data showed stable performance with high recoveries (>98%) for lower active polymer doses of 19 to 23 lb/dt (9.5 to 11.5 g/kg) as compared to results from the polymer curve testing. The dewatered cake solids during the extended operation tests averaged 17 to 17.5% TS at 50 gpm (189 L/min) feed flow with 19 to 22 lb/dt (9.5 to 11 g/kg) active polymer dose. At 75 gpm (284 L/min) with an active polymer dose of 23 lb/dt (11.5 g/kg), the dewatered cake solids averaged 16 to 16.5% TS. Figure 15: Extended Operation using Dry Polymer The extended runs using emulsion 274 FLX polymer are shown in Figure 16. The data showed stable performance with high recoveries (>96%) for active polymer doses of 37 to 44 lb/dt (18.5 to 22 g/kg). The dewatered cake solids during this tests averages 20.5 to 21% TS at 50 gpm (189 L/min) feed flow with 44 lb/dt (22 g/kg) active polymer dose. At 75 gpm (284 L/min) with an active polymer dose of 37 lb/dt (18.5 g/kg), the dewatered cake solids averaged 19.3 to 19.6% TS. 630

19 Figure 16: Extended Operation using Emulsion Polymer The Phase 3 dewatering testing showed that 16-18% TS cake could be achieved with lb/dt (10 to 15 g/kg) active dosing of dry polymer. The pilot testing showed that the dewatered cake solids were lower than the preliminary design value of 20% TS with a presumed 25 lb/dt (12.5 g/kg) active polymer when using dry polymer. Dryer cake at 20-22% TS could be produced using emulsion polymer but required higher dosages above 40 lb/dt active (20 g/kg). CONCLUSIONS The Phase 1 thickening testing showed that the centrifuge could reliably produce solids at 5-6% TS and achieve greater than 95% solids recovery. Testing was conducted using both dry and emulsion polymers. The dry polymer required 5 to 7 lb/dt (2.5 to 3.5 g/kg) active dosing compared to 1 to 3 lb/dt (0.5 to 1.5 g/kg) based on the emulsion. It was also possible to thicken the sludge to 5 to 6% TS without the use of polymer but this reduced hydraulic throughput by about 50% to allow solids recovery to remain above 90%. During Phase 2, the solids content in Digester 9 was increased from approximately 2% to approximately 3.4 to 3.5% TS and the VSR in Digester 9 averaged 46% with a digester SRT of approximately 30 days. During the same period of time, the other digesters at the plant received gravity concentrated sludge at 1.5% to 3% TS and averaged approximately 42% VSR with a digester SRT of approximately 20 days. The increase in VSR was likely due to the longer SRT and higher solids concentration. The Phase 3 dewatering testing showed that 16 to 18% TS cake could be achieved with 20 to 30 lb/dt (10 to 15 g/kg) active dosing of dry polymer. The pilot testing showed that the dewatered cake solids were lower than the preliminary design value of 20% TS with a presumed 25 lb/dt (12.5 g/kg) active polymer when using dry polymer. Dryer cake at 20 to 22% TS could be produced using emulsion polymer but required higher dosages above 40 lb/dt (20 g/kg) active. The pilot dewatering results highlight the importance of piloting to refine design performance criteria. 631

20 ACKNOWLEDGEMENTS The team would like to thank all of the plant staff at SDWWTP, especially Leo Pou and Mike Garcia for the outstanding support during this pilot testing. The team would also like to thank the staff from Centrisys and CNP for their commitment to making the testing a success. We also thank the interns Andres McEwen, Yareliz Negron, and Kate Ireland who helped make this project possible by monitoring pilot operations, collecting samples and running numerous laboratory tests. REFERENCES S SDWWTP SLUDGE THICKENING & DEWATERING BLDG CD 1.06, 1.08, Specification Section CENTRIFUGES, MWH, January 20, American Public Health Association, American Water Works Association, Water Environment Federation, Standard Methods for the Examination of Water and Wastewater 20 th ed., 1999 Metcalf & Eddy. (2014). Wastewater Engineering Treatment and Reuse. 5 th Edition. 632

Report on Piloting of the Volute Dewatering Press at the Boonsboro WWTP in Boonsboro, MD July 25 th - July 29 th, 2016

Report on Piloting of the Volute Dewatering Press at the Boonsboro WWTP in Boonsboro, MD July 25 th - July 29 th, 2016 Report on Piloting of the Volute Dewatering Press at the Boonsboro WWTP in Boonsboro, MD July 25 th - July 29 th, 2016 Process Wastewater Technologies, LLC. 9004 Yellow Brick Road, Suite D, Rosedale, MD21237

More information

Energy Optimized Resource Recovery Project Presented By: Curtis Czarnecki, P.E.

Energy Optimized Resource Recovery Project Presented By: Curtis Czarnecki, P.E. Kenosha Wastewater Treatment Plant Energy Optimized Resource Recovery Project Presented By: Curtis Czarnecki, P.E. Kenosha Water Utility March 22, 2016 WWTP Service Area Overview Population: 110,000 Service

More information

EVALUATING ALTERNATIVES FOR DISPOSING OF WATER PLANT SOLIDS INTO A WASTEWATER PLANT

EVALUATING ALTERNATIVES FOR DISPOSING OF WATER PLANT SOLIDS INTO A WASTEWATER PLANT EVALUATING ALTERNATIVES FOR DISPOSING OF WATER PLANT SOLIDS INTO A WASTEWATER PLANT Matthew Valade, P.E. July 25, 2014 Barboe.pptx Presentation Outline Project Background Why Dewater Croton Residuals Offsite?

More information

World Pulp & Paper THE INTERNATIONAL REVIEW FOR THE PULP AND PAPER INDUSTRY

World Pulp & Paper THE INTERNATIONAL REVIEW FOR THE PULP AND PAPER INDUSTRY World Pulp & Paper THE INTERNATIONAL REVIEW FOR THE PULP AND PAPER INDUSTRY 2014 MIXING & INJECTION TECHNOLOGY Mixing innovation delivers value By Brian Duffy, Tim Nahley, David sirois and Ruben Manzanares,

More information

Thickening and Dewatering Optimization Matt Van Horne, PE Hazen and Sawyer July 14, 2016

Thickening and Dewatering Optimization Matt Van Horne, PE Hazen and Sawyer July 14, 2016 Thickening and Dewatering Optimization Matt Van Horne, PE Hazen and Sawyer July 14, 2016 Agenda Equipment Specific Modifications Chemicals Feeding Cleaning and Maintenance Pretreatment 2 1 Optimization

More information

Kenosha Wastewater Treatment Plant - Energy Optimized Resource Recovery Project

Kenosha Wastewater Treatment Plant - Energy Optimized Resource Recovery Project Kenosha Wastewater Treatment Plant - Energy Optimized Resource Recovery Project Prepared By: Curt Czarnecki, P.E. Kenosha Water Utility Presented By: Joseph Hughes, P.E. Centrisys Corporation MIWEA June

More information

PRIMARY DRINKING WATER FROM WASTEWATER EFFLUENT: PILOT TEST EXPERIENCE AT THE MIAMI DADE SOUTH DISTRICT WWTP

PRIMARY DRINKING WATER FROM WASTEWATER EFFLUENT: PILOT TEST EXPERIENCE AT THE MIAMI DADE SOUTH DISTRICT WWTP PRIMARY DRINKING WATER FROM WASTEWATER EFFLUENT: PILOT TEST EXPERIENCE AT THE MIAMI DADE SOUTH DISTRICT WWTP Paul J. Vinci, P.E. 1, Richard Cisterna, P.E. 1, Robert Harris 1, John Chorlog, P.E. 2, Joseph

More information

INFORMATION TO CONSULTANTS for. (C3) RFP E CBJ Biosolids Belt Dryer System. 155 South Seward Street Juneau, Alaska 99801

INFORMATION TO CONSULTANTS for. (C3) RFP E CBJ Biosolids Belt Dryer System. 155 South Seward Street Juneau, Alaska 99801 INFORMATION TO CONSULTANTS for ENGINEERING DEPARTMENT (C3) RFP E15-263 CBJ Biosolids Belt Dryer System ISSUED BY: City and Borough of Juneau ENGINEERING DEPARTMENT 155 South Seward Street Juneau, Alaska

More information

Are You Getting Your Money s Worth?

Are You Getting Your Money s Worth? Are You Getting Your Money s Worth? Dividends of Performance-Based Polymer Procurement Keller Schnier, PE April 2016 Asheville, NC Acknowledgements Maggie Macomber, PE Charlotte Water Jackie Jarrell, PE

More information

A STRUVITE CONTROL AND PHOSPHORUS REMOVAL PROCESS FOR CENTRATE: FULL-SCALE TESTING. 850 Pembina Highway Winnipeg, MB

A STRUVITE CONTROL AND PHOSPHORUS REMOVAL PROCESS FOR CENTRATE: FULL-SCALE TESTING. 850 Pembina Highway Winnipeg, MB A STRUVITE CONTROL AND PHOSPHORUS REMOVAL PROCESS FOR CENTRATE: FULL-SCALE TESTING Simon Baker 1, Yoomin Lee 1, Wang Li 1 1 Earth Tech Canada Inc 850 Pembina Highway Winnipeg, MB ABSTRACT The North End

More information

Chapter 2: Description of Treatment Facilities

Chapter 2: Description of Treatment Facilities 2020 Facilities Plan Treatment Report 2.1 Introduction Chapter 2: Description of Treatment Facilities This chapter defines the Milwaukee Metropolitan Sewerage District (MMSD) service area. It also describes

More information

Solids Dewatering Modernization

Solids Dewatering Modernization Solids Dewatering Modernization Replacing Plate & Frame Press Dewatering with Centrifuge at a Food Production Plant NEWEA Annual Conference, January 25, 2016 Carl Wilcox, P.E., Partner, Woodard & Curran,

More information

Application of the AGF (Anoxic Gas Flotation) Process

Application of the AGF (Anoxic Gas Flotation) Process Application of the AGF (Anoxic Gas Flotation) Process Dennis A. Burke Environmental Energy Company, 6007 Hill Road NE, Olympia, WA 98516 USA (E-mail: dennis@makingenergy.com http//www.makingenergy.com)

More information

Codigestion Case Studies Enhancing Energy Recovery From Sludge

Codigestion Case Studies Enhancing Energy Recovery From Sludge Codigestion Case Studies Enhancing Energy Recovery From Sludge Dale Gabel, PE, BCEE MWRD PWO Seminar 1 May 23, 2012 What is Codigestion? Direct addition of high-strength organic wastes to municipal wastewater

More information

APPENDIX D MECHANICAL DEWATERING EVALUATION (ADDENDUM 4)

APPENDIX D MECHANICAL DEWATERING EVALUATION (ADDENDUM 4) ONONDAGA LAKE PDI: PHASE IV DATA SUMMARY REPORT APPENDIX D MECHANICAL DEWATERING EVALUATION (ADDENDUM 4) PARSONS P:\Honeywell -SYR\444540-Phase IV PDI\09 Reports\Phase IV DSR\1-11 Final\PDI IV Summary

More information

Enviro Voraxial Technology

Enviro Voraxial Technology Enviro Voraxial Technology 821 NW 57 th Place, Fort Lauderdale, FL 33309 Phone 954.958.9968 Fax: 954.958.8057 sales@evtn.com www.evtn.com EVTN VORAXIAL GRIT SEPARATOR HILLSBOROUGH COUNTY DEMONSTRATION

More information

Taking the Waste out of WAS: Sludge Pretreatment for Beneficial Uses

Taking the Waste out of WAS: Sludge Pretreatment for Beneficial Uses Taking the Waste out of WAS: Sludge Pretreatment for Beneficial Uses December 5, 2013 Matt Van Horne, P.E. 1 1 Agenda Why Sludge Pretreatment? What is OpenCel? Case Study #1: Philadelphia Water Department

More information

Biosolids Monthly Report

Biosolids Monthly Report July-September 217 Biosolids Monthly Report Submitted By: Biosolids Management Program Team Wastewater Treatment Facility 14 Brander St. Richmond, VA 23224 Figure 1: the deputy director Ms. Rosemary Green

More information

Sonix for Enhanced Anaerobic Digestion: Final Report (15 July 2002)

Sonix for Enhanced Anaerobic Digestion: Final Report (15 July 2002) Sonix for Enhanced Anaerobic Digestion: Final Report (15 July 2002) [Note: OCSD tested an ultrasonic device for improving the efficiency of digesting thickened waste activated sludge (TWAS) in anaerobic

More information

Improvements in Screen-Bowl Centrifuge Performance

Improvements in Screen-Bowl Centrifuge Performance Improvements in Screen-Bowl Centrifuge Performance T. Burchett K. McGough G. Luttrell Mining & Minerals Engineering Virginia Tech Blacksburg, VA 24061 E-Mail: luttrell@vt.edu Solid-Liquid Separations All

More information

January 25, Utility of the Future One City s Journey

January 25, Utility of the Future One City s Journey Wastewater Administrators Conference January 25, 2018 Utility of the Future One City s Journey Nathan Cassity, Utility of the Future 2013 Utility of the Future Clean water utilities are undergoing a remarkable

More information

The city of Venice hired Camp

The city of Venice hired Camp Concentrate Post-Treatment For Hydrogen Sulfide And Dissolved Oxygen Vipin Pangasa, Laura Andrews, and William Green The city of Venice hired Camp Dresser & McKee, Inc., to design an effective concentrate

More information

ANAEROBIC DIGESTION IMPROVING ENERGY EFFICIENCY WITH MIXING

ANAEROBIC DIGESTION IMPROVING ENERGY EFFICIENCY WITH MIXING ANAEROBIC DIGESTION IMPROVING ENERGY EFFICIENCY WITH MIXING Neil Massart 1*, James Doyle 2, Jackson Jenkins 2, James Rowan 1, Cindy Wallis-Lage 1 1 Black & Veatch 8400 Ward Parkway Kansas City, MO 64114Missouri

More information

Alternatives to Coal Mine Tailings Impoundment - Evaluation of Three Dewatering Methods at Rockspring Coal Mine

Alternatives to Coal Mine Tailings Impoundment - Evaluation of Three Dewatering Methods at Rockspring Coal Mine Alternatives to Coal Mine Tailings Impoundment - Evaluation of Three Dewatering Methods at Rockspring Coal Mine Charles Murphy, Alpha Natural Resources, Logan County, West Virginia, USA Christopher Bennett,

More information

CNP NUTRIENT RECOVERY TECHNOLOGIES

CNP NUTRIENT RECOVERY TECHNOLOGIES CNP NUTRIENT RECOVERY TECHNOLOGIES MWEA Sustainability Seminar Josh Gable Regional Sales Manager Discussion Outline AirPrex Deep Dive How it works Review of data Review of key benefits CNP CalPrex Basics

More information

The Municipality of North Grenville

The Municipality of North Grenville A solution is required to increase the peak flow capacity of the Kemptville WPCP, a conventional activated sludge process, within a small footprint while maintaining good effluent quality. Location: Kemptville

More information

Value Added Products. Tulane University New Orleans. August 2003 Summit Conference. Charting the Future Direction of Bioenergy Technologies

Value Added Products. Tulane University New Orleans. August 2003 Summit Conference. Charting the Future Direction of Bioenergy Technologies Value Added Products Tulane University New Orleans August 2003 Summit Conference Charting the Future Direction of Bioenergy Technologies AUTOMATING SOLIDS HANDLING & THERMAL PROCESSES James E. Welp Black

More information

First Let s Define some Terms the most important terms used with these concepts are:

First Let s Define some Terms the most important terms used with these concepts are: Primer - Working With Total Solids, Fixed Solids and Volatile Solids in Sludge and Biosolids Michael D. Doran, DEE Professor of Practice Department of Civil & Environmental Engineering University of Wisconsin-Madison

More information

POREX Tubular Membrane Filter Modules For Metal Contaminated Wastewater Treatment & Reclamation

POREX Tubular Membrane Filter Modules For Metal Contaminated Wastewater Treatment & Reclamation POREX Tubular Membrane Filter Modules For Metal Contaminated Wastewater Treatment & Reclamation Background Industrial processes can often result in waste water contaminated with heavy metals (Hg, Pb, Zn,

More information

HIGH RATE TREATMENT AS PART OF THE SOLUTION FOR WET WEATHER FLOWS JUNE

HIGH RATE TREATMENT AS PART OF THE SOLUTION FOR WET WEATHER FLOWS JUNE City of Newark, Ohio HIGH RATE TREATMENT AS PART OF THE SOLUTION FOR WET WEATHER FLOWS JUNE 22, 2011 High Rate Treatment Tanks/UV Wet Weather Screen Building JC2/Wet Weather Pump Station Wet Weather Control

More information

Dewatering Optimization Near-Term Savings and Long-Term Capital Planning

Dewatering Optimization Near-Term Savings and Long-Term Capital Planning Dewatering Optimization Near-Term Savings and Long-Term Capital Planning Outline Robert W. Hite Treatment Facility in Denver, CO Phosphorus Regulations and Impacts Dewatering Optimization: Why We Care

More information

SHAFDAN (Greater Tel Aviv Wastewater Treatment Plant) - Recent Upgrade and Expansion

SHAFDAN (Greater Tel Aviv Wastewater Treatment Plant) - Recent Upgrade and Expansion SHAFDAN (Greater Tel Aviv Wastewater Treatment Plant) - Recent Upgrade and Expansion Messing A. 1, Sela Y. 2 Abstract Figure 1: 1 Balasha-Jalon Infrastructure Systems, Haifa, Israel 2 Igudan-Dan Region

More information

Full scale and laboratory scale results from the trial of MicroSludge at the Joint Water Pollution Control Plant at Los Angeles County

Full scale and laboratory scale results from the trial of MicroSludge at the Joint Water Pollution Control Plant at Los Angeles County Full scale and laboratory scale results from the trial of MicroSludge at the Joint Water Pollution Control Plant at Los Angeles County R.J. Stephenson, S. Laliberte, P. M. Hoy, and D. Britch Paradigm Environmental

More information

Comprehensive Biosolids and Bioenergy Planning Authors: Cameron Clark* 1, Irina Lukicheva 1, Anna James 1, Kathy Rosinski 1, Dave Parry 1

Comprehensive Biosolids and Bioenergy Planning Authors: Cameron Clark* 1, Irina Lukicheva 1, Anna James 1, Kathy Rosinski 1, Dave Parry 1 Comprehensive Biosolids and Bioenergy Planning Authors: Cameron Clark* 1, Irina Lukicheva 1, Anna James 1, Kathy Rosinski 1, Dave Parry 1 1 CH2M *Email: Cameron.Clark@ch2m.com KEYWORDS: biosolids, bioenergy,

More information

HOW TO SAVE COSTS AND IMPROVE SUSTAINABILITY WHILE REDUCING EFFLUENT NITROGEN

HOW TO SAVE COSTS AND IMPROVE SUSTAINABILITY WHILE REDUCING EFFLUENT NITROGEN HOW TO SAVE COSTS AND IMPROVE SUSTAINABILITY WHILE REDUCING EFFLUENT NITROGEN Introduction Donna Kaluzniak, CEP, Utility Director, City of Atlantic Beach, Florida John E. Collins, Jr., P.E., J. Collins

More information

Screw Press Dewatering Optimization. Kelly Brown, BDP Industries, Inc.

Screw Press Dewatering Optimization. Kelly Brown, BDP Industries, Inc. Screw Press Dewatering Optimization By Kelly Brown, BDP Industries, Inc. Where should your focus be??? What is the objective of your optimization? Maximize Capacity: Solids Loading, Flow Rate Maximize

More information

Lycoming County Water and Sewer Authority WWTP Mechanical Thickened Aerobic Digester Case Study

Lycoming County Water and Sewer Authority WWTP Mechanical Thickened Aerobic Digester Case Study Lycoming County Water and Sewer Authority WWTP Mechanical Thickened Aerobic Digester Case Study Bryen Woo, P.E., Ovivo Aeration/Aerobic Digestion Product Manager Duane Martzall, Lycoming County Water and

More information

FULL SCALE PILOT STUDY USING THE VTX PROCESS FOR THE REMOVAL OF SULFIDE AT THE VIRGINIA INITIATIVE PLANT

FULL SCALE PILOT STUDY USING THE VTX PROCESS FOR THE REMOVAL OF SULFIDE AT THE VIRGINIA INITIATIVE PLANT FULL SCALE PILOT STUDY USING THE VTX PROCESS FOR THE REMOVAL OF SULFIDE AT THE VIRGINIA INITIATIVE PLANT Ghosn, S. Plant Manager, and Groszek, G. Lead Operator. Virginia Initiative Plant, Hampton Roads

More information

RECYCLING DIGESTED SLUDGE TO REDUCE FAT OIL AND GREASE BUILD-UP IN PIPES

RECYCLING DIGESTED SLUDGE TO REDUCE FAT OIL AND GREASE BUILD-UP IN PIPES RECYCLING DIGESTED SLUDGE TO REDUCE FAT OIL AND GREASE BUILD-UP IN PIPES DongHyun Lee, Nigel Sanders - Watercare Services Ltd, Auckland, New Zealand ABSTRACT The fat, oil and grease (FOG) in raw sewage

More information

IMPACTS OF THERMOCHEMICAL HYDROLYSIS ON VISCOSITY, BIOGAS & DEWATERABILITY

IMPACTS OF THERMOCHEMICAL HYDROLYSIS ON VISCOSITY, BIOGAS & DEWATERABILITY IMPACTS OF THERMOCHEMICAL HYDROLYSIS ON VISCOSITY, BIOGAS & DEWATERABILITY Josh Gable MWEA 2018 Biosolids Conference PRESENTATION FROM 20,000 FEET About Centrisys/CNP What is Thermo-Chemical Hydrolysis

More information

Harrisburg Advanced Wastewater Treatment Facility Biosolids Facilities Improvement Plan Existing Conditions Report. February 2017

Harrisburg Advanced Wastewater Treatment Facility Biosolids Facilities Improvement Plan Existing Conditions Report. February 2017 Harrisburg Advanced Wastewater Treatment Facility Biosolids Facilities Improvement Plan Existing Conditions Report February 2017 Harrisburg Advanced Wastewater Treatment Facility Biosolids Facilities Improvement

More information

APPENDIX G WASTESTREAM TECHNOLOGIES PHASE IV ADDENDUM 6 SUMMARY REPORT

APPENDIX G WASTESTREAM TECHNOLOGIES PHASE IV ADDENDUM 6 SUMMARY REPORT DRAFT ONONDAGA LAKE SEDIMENT MANAGEMENT INTERMEDIATE DESIGN APPENDIX G WASTESTREAM TECHNOLOGIES PHASE IV ADDENDUM 6 SUMMARY REPORT p:\honeywell -syr\444853 - lake detail design\09 reports\9.9 sediment

More information

Digester Mixing Test at DeKalb Illinois Sanitary District WWTP. Preliminary Test Report October 2013

Digester Mixing Test at DeKalb Illinois Sanitary District WWTP. Preliminary Test Report October 2013 Digester Mixing Test at DeKalb Illinois Sanitary District WWTP Preliminary Test Report October 2013 Background: The District operates 2 separate anaerobic digester trains; each with a nominal 60,000 ft

More information

CENTRIFUGE DECANTER AND HOW IT WORKS

CENTRIFUGE DECANTER AND HOW IT WORKS CENTRIFUGE DECANTER AND HOW IT WORKS DECANTER CENTRIFUGE In a decanter there s a continuous mechanical separation of suspended solids from a liquid or liquids You could see a centrifuge decanter like a

More information

Green River Filtration Facility Plant Overview

Green River Filtration Facility Plant Overview Green River Filtration Facility Plant Overview PNWS-AWWA Conference Bellevue, WA Gary Fox & Hilary Lorenz April 29, 2015 2 IN THE BEGINNING 3 PILOT PLANT OWNED AND OPERATED BY TACOMA WATER STAFF ALL THAT

More information

Polymer Reduction and Drier Cake Solids in Centrifuge Dewatering Result from HydroFLOW Struvite Control Investigation

Polymer Reduction and Drier Cake Solids in Centrifuge Dewatering Result from HydroFLOW Struvite Control Investigation Composed by Douglas L. Miller P.E., BCEE Polymer Reduction and Drier Cake Solids in Centrifuge Dewatering Result from HydroFLOW Struvite Control Investigation February 19, 2016 Municipal Wastewater Treatment

More information

EVALUATION OF ENERGY RECOVERY OPTIONS FOR CONVERSION OF AEROBIC DIGESTERS TO ANAEROBIC DIGESTION

EVALUATION OF ENERGY RECOVERY OPTIONS FOR CONVERSION OF AEROBIC DIGESTERS TO ANAEROBIC DIGESTION EVALUATION OF ENERGY RECOVERY OPTIONS FOR CONVERSION OF AEROBIC DIGESTERS TO ANAEROBIC DIGESTION Jody B. Barksdale, P.E MWH; Juan R. Oquendo, P.E. MWH; Bruce A. Petrik, P.E. - MWH ABSTRACT. The threshold

More information

4 Angles. Pilot-scale Evaluation of AirPrex for Phosphorus Management. Innovation Program Phosphorus Initiative JTAC 4/22/2017

4 Angles. Pilot-scale Evaluation of AirPrex for Phosphorus Management. Innovation Program Phosphorus Initiative JTAC 4/22/2017 Pilot-scale Evaluation of AirPrex for Phosphorus Management JTAC Innovation Program Phosphorus Initiative 4 Angles Liquid stream TP removal Solids TP removal 1 2 3 4 2 1 Phosphorus Initiative: Solids Stream

More information

Copies: Mark Hildebrand (NCA) ARCADIS Project No.: April 10, Task A 3100

Copies: Mark Hildebrand (NCA) ARCADIS Project No.: April 10, Task A 3100 MEMO To: Jeff Pelz (West Yost) Kathryn Gies (West Yost) Copies: Mark Hildebrand (NCA) ARCADIS U.S., Inc. 200 Harvard Mills Square Suite 430 Wakefield Massachusetts 01880 Tel 781 224 4488 Fax 781 224 3033

More information

STARTUP OF ANAEROBIC MESOPHILIC DIGESTERS

STARTUP OF ANAEROBIC MESOPHILIC DIGESTERS STARTUP OF ANAEROBIC MESOPHILIC DIGESTERS Marialena Hatzigeorgiou P.E./CH2M HILL Brian Owsenek P.E./Upper Occoquan Sewage Authority Tom Alkema/CH2M HILL Ronald Sieger P.E. BCEE/CH2M HILL and Karen Pallansch

More information

APPENDIX A. 1. Background. 1.1 Existing Facilities. Page 1

APPENDIX A. 1. Background. 1.1 Existing Facilities. Page 1 APPENDIX A PRELIMINARY TECHNICAL SPECIFICATIONS FOR BIOSOLIDS MANAGEMENT SERVICES JEA Buckman Residuals Management Facility 1. Background JEA is seeking biosolids management services from experienced biosolids

More information

Prepared by the Operation of Municipal Wastewater Treatment Plants Task Force of the Water Environment Federation

Prepared by the Operation of Municipal Wastewater Treatment Plants Task Force of the Water Environment Federation Operation of Municipal Wastewater Treatment Plants WEF Manual of Practice No. 11 Chapter 31 Aerobic Digestion Sixth Edition Prepared by the Operation of Municipal Wastewater Treatment Plants Task Force

More information

Solids Processing Challenges at WSSC Western Branch Can An Innovative Technology Offer a Solution?

Solids Processing Challenges at WSSC Western Branch Can An Innovative Technology Offer a Solution? Solids Processing Challenges at WSSC Western Branch Can An Innovative Technology Offer a Solution? Mohammad Abu-Orf* Grant Davies Yin Hong Alan Sauvageau Nikhil Shirodkar October 21 st, 2008 * AECOM Water

More information

ANAEROBIC DIGESTION WITH RECUPERATIVETHICKENING MINIMISES BIOSOLIDS QUANTITIES AND ODOURS IN SYDNEY, AUSTRALIA

ANAEROBIC DIGESTION WITH RECUPERATIVETHICKENING MINIMISES BIOSOLIDS QUANTITIES AND ODOURS IN SYDNEY, AUSTRALIA ANAEROBIC DIGESTION WITH RECUPERATIVETHICKENING MINIMISES BIOSOLIDS QUANTITIES AND ODOURS IN SYDNEY, AUSTRALIA Gokul Bharambe 1, Josef Cesca 2, Heriberto Bustamante 3, Derek van Rys 3, John Kabouris 4,

More information

Chapter 5: Treatment Assessment Future Condition

Chapter 5: Treatment Assessment Future Condition 2020 Facilities Plan Treatment Report 5.1 Introduction Chapter 5: Treatment Assessment Future Condition The future performance of the Milwaukee Metropolitan Sewerage District (MMSD) wastewater treatment

More information

Total Makeover for Biosolids Handling at DC Water s Blue Plains Advanced Wastewater Treatment Plant. February 2015

Total Makeover for Biosolids Handling at DC Water s Blue Plains Advanced Wastewater Treatment Plant. February 2015 Total Makeover for Biosolids Handling at DC Water s Blue Plains Advanced Wastewater Treatment Plant February 2015 Today s Makeover Will Include Recent History of Blue Plains Solid Handling Processes Evolution

More information

Thermal Hydrolysis The Next Generation

Thermal Hydrolysis The Next Generation Thermal Hydrolysis The Next Generation Peter Loomis, P.E. (CDM Smith) Tom Jacobs, P.E. (Trinity River Authority) Samir Mathur, P.E. (CDM Smith) Engin Guven, Ph.D., P.E. (CDM Smith) Danny Hurtado, P.E.

More information

Full Scale Testing to Demonstrate Anaerobic Selector Effect for Low Strength Wastewater

Full Scale Testing to Demonstrate Anaerobic Selector Effect for Low Strength Wastewater OWEA State Conference June 20, 2012 Full Scale Testing to Demonstrate Anaerobic Selector Effect for Low Strength Wastewater Presenters Bill Donohue NEORSD Bob Hrusovsky MWH Don Esping BC Easterly Plant

More information

Lake County WTP Improvements and Capacity Increase. OTCO 9 th Annual Water and Wastewater Workshop. Nick Pizzi Aqua Serv

Lake County WTP Improvements and Capacity Increase. OTCO 9 th Annual Water and Wastewater Workshop. Nick Pizzi Aqua Serv 1 Lake County WTP Improvements and Capacity Increase OTCO 9 th Annual Water and Wastewater Workshop 7.31.2013 Nick Pizzi Aqua Serv Rick Douglas Lake County Presentation Agenda Some topics we will cover:

More information

HIGH PERFORMANCE SLUDGE DEWATERING FOR DRINKING WATER PLANTS WITH THE BUCHER HYDRAULIC FILTER PRESS

HIGH PERFORMANCE SLUDGE DEWATERING FOR DRINKING WATER PLANTS WITH THE BUCHER HYDRAULIC FILTER PRESS HIGH PERFORMANCE SLUDGE DEWATERING FOR DRINKING WATER PLANTS WITH THE BUCHER HYDRAULIC FILTER PRESS Abstract JeanFrançois Mischler Bucher Unipektin AG Eric Judenne, Matthieu Delahaye, JeanMichel Faccioli

More information

Flocculation Flotation Pretreatment Improves Operation of MBR Installed to Treat Snack Food Manufacturing Wastewater

Flocculation Flotation Pretreatment Improves Operation of MBR Installed to Treat Snack Food Manufacturing Wastewater Flocculation Flotation Pretreatment Improves Operation of MBR Installed to Treat Snack Food Manufacturing Wastewater *Miroslav Colic 1, Jack Hogan 1, Ariel Lechter 1 1 Clean Water Technology Inc. *To whom

More information

AMPC Wastewater Management Fact Sheet Series Page 1

AMPC Wastewater Management Fact Sheet Series Page 1 Nitrogen removal Nitrogen present in meat processing wastewater are termed a nutrient, since they are essential elements for life. They largely derive from proteins dissolved into wastewater from meat

More information

AMPC Wastewater Management Fact Sheet Series Page 1

AMPC Wastewater Management Fact Sheet Series Page 1 Nitrogen removal Nitrogen present in meat processing wastewater are termed a nutrient, since they are essential elements for life. They largely derive from proteins dissolved into wastewater from meat

More information

MEETING COLUMBUS S TREATMENT LIMITS

MEETING COLUMBUS S TREATMENT LIMITS MEETING COLUMBUS S TREATMENT LIMITS EVEN WHEN WET WEATHER CHANGES THEM Improving Quality of Life AGENDA CEPT Background CEPT Preliminary Testing CEPT Design and Construction CEPT NPDES Permit Modification

More information

Innovative technology for phosphate removal from dewatered sludge supernatant

Innovative technology for phosphate removal from dewatered sludge supernatant Innovative technology for phosphate removal from dewatered sludge supernatant Frank Gnanam, Business Manager Virotec Global Solutions Pty Ltd Peter Reberger, Plant Manager EGL Management Services Pty Ltd

More information

Evaluation of Energy Recovery Options for Conversion of Aerobic Digesters to Anaerobic Digestion

Evaluation of Energy Recovery Options for Conversion of Aerobic Digesters to Anaerobic Digestion Evaluation of Energy Recovery Options for Conversion of Aerobic Digesters to Anaerobic Digestion Jody B. Barksdale, Juan R. Oquendo, and Bruce A Petrik his article discusses a case study in Florida for

More information

Brightwater: The Design Challenges of a 39 mgd (150 MLD) Membrane Bioreactor

Brightwater: The Design Challenges of a 39 mgd (150 MLD) Membrane Bioreactor Brightwater: The Design Challenges of a 39 mgd (150 MLD) Membrane Bioreactor J. Komorita 1, P. Burke 2, B. Youker 2, and G. Crawford 2 1 King County, 2 CH2M HILL ABSTRACT Many Membrane Bioreactor (MBR)

More information

Client: City of Pontiac Project Name: Regional WWTP Feasibility Location: Pontiac, MI Project Number: Issue Date: October 23, 2006

Client: City of Pontiac Project Name: Regional WWTP Feasibility Location: Pontiac, MI Project Number: Issue Date: October 23, 2006 Client: City of Pontiac Project Name: Regional WWTP Feasibility Location: Pontiac, MI Project Number: 13649553 Issue Date: October 23, 2006 Subject: WWTP Condition Assessment Auburn Plant 1. Grit Removal:

More information

FLOQUIP. Polymer Preparation and Feed Systems. Maximize Efficiency with Custom-Engineered Solutions.

FLOQUIP. Polymer Preparation and Feed Systems. Maximize Efficiency with Custom-Engineered Solutions. FLOQUIP Polymer Preparation and Feed Systems Maximize Efficiency with Custom-Engineered Solutions www.floquipinc.com SNF THE WORLD S BEST POLYMER AND EQUIPMENT SNF FLOQUIP is the global engineering and

More information

CASE STUDY: BREAKTHROUGH CENTRATE TREATMENT AT REDCLIFFE WASTE WATER TREATMENT PLANT

CASE STUDY: BREAKTHROUGH CENTRATE TREATMENT AT REDCLIFFE WASTE WATER TREATMENT PLANT 2007 Virotec International plc All rights reserved. A COMMERCIAL APPLICATION OF VIROSEWAGE TECHNOLOGY CASE STUDY: BREAKTHROUGH CENTRATE TREATMENT AT REDCLIFFE WASTE WATER TREATMENT PLANT We had documented

More information

Appendix D JWPCP Background and NDN

Appendix D JWPCP Background and NDN Appendix D JWPCP Background and NDN JWPCP Background JWPCP Water Quality Primary Clarifiers HPO Reactors Final Clarifiers Unit Influent Primary Effluent Secondary Effluent BOD mg/l 460 240

More information

PIMPAMA WWTP DEWATERING OPTIMISATION. Joel Warnes

PIMPAMA WWTP DEWATERING OPTIMISATION. Joel Warnes PIMPAMA WWTP DEWATERING OPTIMISATION Paper Presented by: Joel Warnes Authors: Mark Wilson, Process Engineer, Joel Warnes, Operator, Charlie Suggate, Operator, Lee Davies, Operator, Dion Sleep, Supervisor,

More information

TREATMENT of liquid wastes results in the production

TREATMENT of liquid wastes results in the production Evaluation of Different Sludge Mechanical Dewatering Technologies D. MAMAIS*,1,A.TZIMAS 1, A. EFTHIMIADOU 1, J. KISSANDRAKIS 2 and A. ANDREADAKIS 1 1 Department of Water Resources, Faculty of Civil Engineering,

More information

PILOT SCALE TESTS OF A UNIQUE APPROACH FOR BNR UPGRADE OF A SHORT SRT HIGH PURITY OXYGEN SYSTEM AT PIMA COUNTY, AZ

PILOT SCALE TESTS OF A UNIQUE APPROACH FOR BNR UPGRADE OF A SHORT SRT HIGH PURITY OXYGEN SYSTEM AT PIMA COUNTY, AZ PILOT SCALE TESTS OF A UNIQUE APPROACH FOR BNR UPGRADE OF A SHORT SRT HIGH PURITY OXYGEN SYSTEM AT PIMA COUNTY, AZ ABSTRACT Ron Riska,: Pima County Wastewater Management Division Joseph A. Husband, P.E.,

More information

Anaerobic Digester Optimization with Bio-Organic Catalyst. NYWEA 81 st Annual Meeting February 3, 2009 One Year Study November 07 - November 08

Anaerobic Digester Optimization with Bio-Organic Catalyst. NYWEA 81 st Annual Meeting February 3, 2009 One Year Study November 07 - November 08 Anaerobic Digester Optimization with Bio-Organic Catalyst NYWEA 81 st Annual Meeting February 3, 2009 One Year Study November 07 - November 08 Municipal Anaerobic Digester Optimization Program Index! Overview

More information

City of Leadwood Wastewater System Engineering Report

City of Leadwood Wastewater System Engineering Report City of Leadwood Wastewater System Engineering Report DRAFT H2O C Engneering www.h2oc.com 877-22-WATER Background The purpose of this report is to describe the City of Leadwood s wastewater system (System

More information

Richard E. Beardslee City of Battle Creek. Steven L. Wordelman, P.E. Jones & Henry Engineers, Ltd.

Richard E. Beardslee City of Battle Creek. Steven L. Wordelman, P.E. Jones & Henry Engineers, Ltd. Richard E. Beardslee City of Battle Creek Steven L. Wordelman, P.E. Jones & Henry Engineers, Ltd. Past Planning Current Situation Pilot Testing Temporary Approach Future Mid 1970 Mid 1990 2007 Make no

More information

BROCKVILLE CITY OF THE 1000 ISLANDS BROCKVILLE WATER POLLUTION CONTROL CENTRE UPGRADE CLASS ENVIRONMENTAL ASSESSMENT REPORT

BROCKVILLE CITY OF THE 1000 ISLANDS BROCKVILLE WATER POLLUTION CONTROL CENTRE UPGRADE CLASS ENVIRONMENTAL ASSESSMENT REPORT BROCKVILLE CITY OF THE 1000 ISLANDS BROCKVILLE WATER POLLUTION CONTROL CENTRE UPGRADE CLASS ENVIRONMENTAL ASSESSMENT REPORT Evaluation of Sludge Treatment Needs and Options Prepared By: 1. Introduction

More information

Preparing for Technical Training: Essential Skills for Water/Wastewater Operators. Practice Tests

Preparing for Technical Training: Essential Skills for Water/Wastewater Operators. Practice Tests Practice Tests COURSE OUTLINE: Module # Name Practice Test included Module 1: Basic Math Refresher Module 2: Fractions, Decimals and Percents Module 3: Measurement Conversions Module 4: Linear, Area and

More information

Wastewater Flow Monitoring Services

Wastewater Flow Monitoring Services Wastewater Flow Monitoring Services For San Gabriel, CA July 13, 2015 through July 21, 2015 Revised October 9, 2015 Leaders in Sewer Flow Monitoring Services 601 N. Parkcenter Dr., Suite 209 Santa Ana,

More information

Grit Collection & Classification Case Studies

Grit Collection & Classification Case Studies Grit Collection & Classification Case Studies OWEA 2010 Specialty Biosolids Specialty Workshop Brian F. McNamara, HRSD Definition of Grit Metcalf & Eddy 2 nd Edition 1979 grit, consisting of sand, gravel,

More information

Comparison between two techniques for sludge dewatering trials at Sjölunda and Klagshamn WWTPs

Comparison between two techniques for sludge dewatering trials at Sjölunda and Klagshamn WWTPs VATTEN 67:71 77. Lund 2011 Comparison between two techniques for sludge dewatering trials at Sjölunda and Klagshamn WWTPs by Ivelina Dimitrova 1, Hans Carlsson 2 1 VA SYD, BOX 191, SE-201 21 Malmö, Sweden

More information

The Biosolids Odor Reduction Roadmap (BORR): A Decision Tool to Reduce Cake Odors

The Biosolids Odor Reduction Roadmap (BORR): A Decision Tool to Reduce Cake Odors The Biosolids Odor Reduction Roadmap (BORR): A Decision Tool to Reduce Cake Odors Presented at Dewatering 201: Technology, Evolutions, and Trends A webinar sponsored by the Water Environment Association

More information

Problem Statement WWTP. Biosolids Management. Biosolids 2 5/14/2013. Anaerobic Co-Digestion of FOG: Pilot Demonstration at BCUA

Problem Statement WWTP. Biosolids Management. Biosolids 2 5/14/2013. Anaerobic Co-Digestion of FOG: Pilot Demonstration at BCUA Anaerobic Co-Digestion of FOG: Pilot Demonstration at BCUA Problem Statement Air Emissions NEW JERSEY WATER ENVIRONMENT ASSOCIATION SPRING CONFERENCE ATLANTIC CITY May 14, 013 Raw Wastewater WWTP Treated

More information

INNOVATIVE TECHNOLOGY FOR PHOSPHATE REMOVAL FROM DEWATERED SLUDGE SUPERNATANT. Peter Reberger

INNOVATIVE TECHNOLOGY FOR PHOSPHATE REMOVAL FROM DEWATERED SLUDGE SUPERNATANT. Peter Reberger INNOVATIVE TECHNOLOGY FOR PHOSPHATE REMOVAL FROM DEWATERED SLUDGE SUPERNATANT Paper Presented by: Peter Reberger Authors: Peter Reberger, Plant Manager, EGL Management Services Pty Ltd Frank Gnanam, Business

More information

Excellence in Engineering Since 1946

Excellence in Engineering Since 1946 Excellence in Engineering Since 1946 Today s Outline Operations and Planning Incident Planning/Design Construction Commissioning Operation Plant Aerial DAF/Blended Sludge Tanks Anaerobic Digestion Secondary

More information

Water and Wastewater Treatment Energy Savings Guide

Water and Wastewater Treatment Energy Savings Guide Water and Wastewater Treatment Energy Savings Guide Oregon water and wastewater treatment plants face challenges of growing hydraulic demand, rising operating costs, increased regulatory requirements and

More information

Anaerobic Digestion- opportunities to optimize the process

Anaerobic Digestion- opportunities to optimize the process Northeast Residuals and Biosolids Conference 2016, Cromwell, Connecticut Anaerobic Digestion- opportunities to optimize the process October13, 2016 Acknowledgements Brown and Caldwell Tom Chapman (Tucson),

More information

2017 Annual Performance Report

2017 Annual Performance Report Duffin Creek Water Pollution Control Plant Page 1 of 17 Duffin Creek Water Pollution Control Plant Environmental Compliance Approval (ECA): 5531-9FJJT5 Dated 3, 2014 Environmental Compliance Approval (Air):

More information

Product Overview. Eco-efficient solids separation

Product Overview. Eco-efficient solids separation Product Overview Eco-efficient solids separation ABOUT SALSNES FILTER Over 25 years ago, we designed the first rotating belt filter to provide customers with a highly efficient and reliable technology

More information

Selecting the right Equipment for your Sludge. Testing in the Lab. Charles Laughton - Euroby Limited

Selecting the right Equipment for your Sludge. Testing in the Lab. Charles Laughton - Euroby Limited Selecting the right Equipment for your Sludge Testing in the Lab Charles Laughton - Euroby Limited Table of Contents Product parameters at a glance Sedimentation Spin test Analytical methods Select the

More information

A H. Marcela Velázquez-Carrillo Consultant to Mountain Systems Inc. on the application of Proficy for Water Treatment

A H. Marcela Velázquez-Carrillo Consultant to Mountain Systems Inc. on the application of Proficy for Water Treatment WASTEWATER TREATMENT IINORMATIION TECHNOLOGY SUEZ, parent company of United Water ONDEO, is one of the largest water and wastewater treatment firms in the world. On January 5 th, 1998, United Water Milwaukee

More information

Waste Water Treatment Equipment

Waste Water Treatment Equipment APEC PUMP ENTERPRISE CORP. Waste Water Treatment Equipment APEC Separator APEC Separator Compared with a sedimentation basin, the APEC separator offers a 90% saving in terms of surface area. This means

More information

BOD5 REMOVALS VIA BIOLOGICAL CONTACT AND BALLASTED CLARIFICATION FOR WET WEATHER M. COTTON; D. HOLLIMAN; B. FINCHER, R. DIMASSIMO (KRUGER, INC.

BOD5 REMOVALS VIA BIOLOGICAL CONTACT AND BALLASTED CLARIFICATION FOR WET WEATHER M. COTTON; D. HOLLIMAN; B. FINCHER, R. DIMASSIMO (KRUGER, INC. BOD REMOVALS VIA BIOLOGICAL CONTACT AND BALLASTED CLARIFICATION FOR WET WEATHER M. COTTON; D. HOLLIMAN; B. FINCHER, R. DIMASSIMO (KRUGER, INC.) Bench-scale testing was conducted to quantify the effectiveness

More information

Minimal Biosolids Stabilization for Maximum Biogas Production

Minimal Biosolids Stabilization for Maximum Biogas Production Minimal Biosolids Stabilization for Maximum Biogas Production Lauren Spink 1*, Michael Manning 1, Mark Greene 1, Michael Garland 2 1 O Brien & Gere Engineers 2 Monroe County Department of Environmental

More information

OPTIMIZATION STUDY OF THE ST. MARY'S WASTEWATER TREATMENT PLANT

OPTIMIZATION STUDY OF THE ST. MARY'S WASTEWATER TREATMENT PLANT XCG File No.: 3-167-09-02 October 26, 2016 OPTIMIZATION STUDY OF THE ST. MARY'S WASTEWATER TREATMENT PLANT Prepared for: B.M. ROSS & ASSOCIATES LIMITED 62 North Street Goderich, Ontario N7A 2T4 Prepared

More information

Abstract. 1 Introduction. Golder Associates Ltd, Canada

Abstract. 1 Introduction. Golder Associates Ltd, Canada https://papers.acg.uwa.edu.au/p/1752_05_gu/ Challenges associated with the design of a dewatering plant that will undergo a large increase in tailings throughput during the initial years of the project

More information

SCUM A LIABILITY OR AN ASSET? Chad M. Simmons, P.E. Leonard Ripley, Ph.D., P.E., BCEE Freese and Nichols, Inc.

SCUM A LIABILITY OR AN ASSET? Chad M. Simmons, P.E. Leonard Ripley, Ph.D., P.E., BCEE Freese and Nichols, Inc. SCUM A LIABILITY OR AN ASSET? Chad M. Simmons, P.E. Leonard Ripley, Ph.D., P.E., BCEE Freese and Nichols, Inc. Farida S. Goderya, Ph.D., P.E. City of Fort Worth - Water Department, Texas ABSTRACT Until

More information

Post-Aerobic Digester with Bioaugmentation Pilot Study City of Meridian, ID WWTP PNCWA 2010

Post-Aerobic Digester with Bioaugmentation Pilot Study City of Meridian, ID WWTP PNCWA 2010 Post-Aerobic Digester with Bioaugmentation Pilot Study City of Meridian, ID WWTP by: William Leaf Adrienne Menniti Bruce Johnson CH2M HILL, Inc. Clint Dolsby Tracy Crane City of Meridian October 26, 21

More information

Thermal Hydrolysis Comes to Texas!

Thermal Hydrolysis Comes to Texas! Thermal Hydrolysis Comes to Texas! Samir Mathur PE, BCEE CDM Smith Summer Seminar July 25, 2014 Presentation Outline Thermal Hydrolysis fundamentals TRA solids masterplan overview Testing objectives Testing

More information