Auctions preparation, course, wins. Katarzyna Szwed Lipińska, counsellor at law Director, Department of Support Systems Energy Regulatory Office

Size: px
Start display at page:

Download "Auctions preparation, course, wins. Katarzyna Szwed Lipińska, counsellor at law Director, Department of Support Systems Energy Regulatory Office"

Transcription

1 Katarzyna Szwed Lipińska, counsellor at law Director, Department of Support Systems Energy Regulatory Office Warsaw, March 2015

2 Installations subject to the auction procedure: existing including modernised after the effective date of Section 4, new where electricity has been first produced after the auction closure date; Article 72 in conjunction with Article 71 of the RES Act

3 Subjects eligible for participation in an auction: a producer of electricity from renewable energy sources in a mircoinstallation being an entrepreneur pursuant to the Freedom of Business Activity Act, a producer of electricity from renewable energy sources in a small installation an entry in the register of regulated activity register of producers of energy in a small installation, a producer of electricity from agricultural biogas in installations other than a microinstallation an entry in the register of regulated activity register of producers of agricultural biogas, a producer conducting business activity in the area of production of electricity from renewable energy sources on the basis of a license issued by the President of the ERO; Article 72 in conjunction with Article 71 of the RES Act

4 Objective exemptions existing installations, including modernised after the effective date of Section 4 The following installations may not participate in an auction: 1) multifuel combustion installations, with the exception of dedicated multifuel combustion installations, 2) renewable energy source installations with total installed electrical capacity higher than 5 MW, using hydropower to produce electricity, 3) renewable energy source installations with total electrical capacity higher than 50 MW, using biomass, bioliquids, biogas or agricultural biogas to produce electricity, with the exception of renewable energy source installations using biomass, bioliquids, biogas or agricultural biogas combusted in high efficiency cogeneration with maximum thermal capacity not higher than 150 MWt to produce the electricity; Article 71(2) of the RES Act

5 Article 74(1) and 74(4) premises for the purchase of electricity first produced after the auction closure date new installations, including modernised after the effective date of Section 4; Article 74(2) premises for the purchase of electricity produced in an installation modernised after the effective date of Section 4 applicable to each modernisation, including modernisation of an installation where the first production occurred after the auction closure date; Article 74(3) special cases of modernisation and the right to sell electricity by way of an auction applicable to each modernisation, including modernisation of an installation where the first production occurred after the auction closure date;

6 General principle: modernisation The sale of electricity from renewable energy sources produced in a modernised renewable energy source installation shall apply to electricity produced in proportion to the increase in total installed electrical capacity of that installation; First sentence of Article 74(5) of the RES Act

7 The President of the ERO shall announce, organise and hold auctions at least once per year; The subject of the auctions shall be the production of electricity from renewable energy sources; Article 73(1) and 73(2) of the RES Act

8 Declaration of participation in an auction: existing installations, a statement pursuant to Article 233 of the Penal Code; Formal assessment: installations that commence the production of electricity for the first time after the auction closure date, a statement pursuant to Article 233 of the Penal Code;

9 The President of the ERO shall hold a separate auction for the sale of electricity produced in the renewable energy source installations referred to in Article 72 of the Act; The auctions shall be held separately for the sale of electricity produced from renewable energy sources produced in renewable energy source installations with total installed eleactrical capacity: 1) not higher than 1 MW, 2) higher than 1 MW; Article 73 of the RES Act

10 The President of the ERO may hold subsequent auctions in a particular year; No less than 25% of electricity produced from renewable energy sources produced in the installations referred to in Article 72(2), sold by way of an auction shall be produced in renewable energy source installations with total installed electrical capacity not higher than 1 MW; Article 73 of the RES Act

11 Formal assessment Stage I: initial classification a certificate A producer of electricity from renewable energy sources that intends to participate in an auction shall be subject to a formal assessment procedure of preparation for the production of electricity in a particular installation; The application for the issuance of the certificate of admission to participation in an auction shall include: 1) the name and surname and place of residence or name, registered office and address of the producer, 2) the location and installed electrical capacity of the renewable energy source installation, 3) the signature of the producer or a person duly authorised to represent it, including attached original or certified copy of a document certifying the authorisation of such a person to act on behalf of the producer, 4) in the case of an installation using biomass, biogas, agricultural biogas or bioliquids to produce electricity a statement of non-use of specific types of fuels (substrates) and the compliance with the share of agro (exception: micro and small installations); Article 75 of the RES Act

12 The following originals or certified copies shall be attached to the application for the issuance of the certificate of admission to participation in an auction: 1) documents confirming the admissibility of location of a particular renewable energy source installation on the area subject to the planned investment: a) an extract from a local spatial development plan, b) an outline planning permission in the case of absence of the plan referred to in Article 76(5)(1)(a), if such is required pursuant to the provisions on spatial planning and development, c) a final permission to build and operate artificial islands, structures and devices in Polish maritime areas for projects located in the exclusive economic zone in the case of a renewable energy source installation using offshore wind to produce electricity, 2) a document confirming: a) the issuance of connection conditions for the connection of a renewable energy source installation to a transmission network or a distribution network or b) the conclusion of an interconnection agreement for the connection of a renewable energy source installation to a transmission network or a distribution network; Article 75(5) of the RES Act

13 The following originals or certified copies shall also be attached to the application for the issuance of the certificate of admission to participation in an auction: 3) a final building permit issued for the planned renewable energy sources installation or modernisation thereof, if required pursuant to the Building Code, 4) a final decision on environmental determinants in the case of a renewable energy source installation using offshore wind to produce electricity, 5) a schedule and budget for the implementation of the planned construction or modernisation of the renewable energy source installation or a statement of completion of an investment; Validity period of the documents; Article 75(5) of the RES Act

14 The President of the ERO shall issue the certificate of admission to participation in an auction or refuse to issue it within 30 days from the date when the application for the issuance of the certificate is filed; The President of the ERO shall refuse, by way of a decision, to issue a certificate of admission to participation in an auction. The decision may be appealed against; The a certificate of admission to participation in an auction shall be valid for 12 months from the date of issue of the certificate. The certificate cannot be valid longer than the validity of the documents referred to in Article 75(5)(1)(c), 75(5)(2)(a), 75(5)(3) and 75(5)(4); Article 76 of the RES Act

15 The President of the ERO shall specify the by-laws of an auction; The by-laws of an auction shall specify: the course and settlement of the auction, the terms and conditions for processing the data concerning the auction participants, the technical requirements for access to the internet auction platform, the procedure for ensuring security and correct course of the auction, the terms and conditions for suspending access to the internet auction platform; Article 78(9) of the RES Act

16 The auction by-laws shall be approved by a minster competent for the matters of economy; The auction by-laws shall be announced in the Public Information Bulletin of the ERO; Article 78 of the RES Act

17 The President of the ERO shall publish an announcement of the auction in the Public Information Bulletin of the ERO no later than 30 days before the day of its commencement; The announcement of an auction shall include: 1) the date of the auction session, 2) opening and closing hours of the auction session, 3) the specification of the maximum amount and value of electricity from renewable energy sources that may be sold by way of the auction; Article 39(5); Article 78 of the RES Act

18 Conditions for admission to participation in an auction: declaration of participation in an auction, a certificate of admission to participation in an auction, a bank guarantee or a proof of submission of a deposit on a dedicated bank account of the President of the ERO in the amount of PLN 30 per 1 kw of installed electrical capacity of the installation; Article 75(1) and 75(2) in conjunction with Article 78(3) and 78(4) of the RES Act

19 An auction shall be held if no less than three valid bids meeting the requirements laid down herein are submitted; An auction shall be held electronically through an internet auction platform; Article 78 of the RES Act

20 Bid elements course of the auction From the opening hour to the closing hour of the auction session the producer being auction participant shall submit a bid using the form published on the internet auction platform; One bid for electricity to be produced in a particular installation; Article 79 of the RES Act

21 Bid elements the type and installed electrical capacity of a renewable energy source installation, the amount in MWh and the price in PLN with an accuracy of 1/100 PLN per 1 MWh the specification of the obligated vendor, on whose area of activity the installation will be located (installations below 500 kw); Article 79 of the RES Act

22 Bid elements a statement of compliance with the premises laid down in Article 42(6) 42(8) applicable to producers, for installations modernised after the effective date of Section 4, the amount of electricity from renewable energy sources in MWh, which the auction participant is planning to produce in the renewable energy source installation in subsequent calendar years, the point of connection of the renewable energy source installation to a distribution network or a transmission network specified in connection conditions or an interconnection agreement; Article 79 of the RES Act

23 Bid elements the auction participant's commitment to produce for the first time within a specific deadline electricity from renewable energy sources in a renewable energy source installation that will be created or modernised after the day when the auction is held; Article 79 of the RES Act

24 Bid elements the auction participant's commitment to commence production of electricity from renewable energy sources in a renewable energy source installation no later than on the first day of the month following the lapse of a month from the month when the auction was closed in the case of the producer referred to in Article 71(1); [Article 80(9); Article 92(6) of the RES Act]; Article 79 of the RES Act

25 Bid elements a statement of non-use of specific types of fuels (substrates) and the compliance with the share of agro in the case of an installation using biomass, biogas, agricultural biogas or bioliquids to produce electricity (exception: micro and small installations); Article 79 of the RES Act

26 Bid elements a statement that the total value of the public aid referred to in Article 39(2)(2) Article 39(2)(4), received before the date the statement is made, converted into unit price of electricity after considering the planned amount of electricity produced in that renewable energy source installation as submitted in the producer s bid and the period of 15 years when the aid is granted amounts to... PLN per 1 MWh; Article 79 of the RES Act

27 Bid elements a statement that the bid sale price of electricity from renewable energy sources, increased by the unit public aid in the amount specified in Article 39(2)(2)-39(2)(4) will not exceed the reference price applicable as of the day when the bid is placed by that producer; Article 79 of the RES Act

28 The bids shall be certified by a secure electronic signature verified by a qualified certificate or by a signature confirmed by an epuap certified profile; An auction shall be held during one auction session; The bid of each auction participant shall be unavailable to other auction participants; A bid submitted one hour before the closure of an auction session shall be binding for the auction participant until the end of a particular auction session and cannot be withdrawn; Bids including prices exceeding the reference price shall be rejected; Article 79 of the RES Act

29 The producer of electricity from a renewable energy source in the renewable energy source installation referred to in Article 72 shall provide the President of the ERO with a statement confirming the fulfilment of the condition referred to in Article 39(1) on the day when the bid is placed; The President of the ERO may demand the producer of electricity to present any and all information and documents confirming the fulfilment of the condition referred to in Article 39(1) within 14 days before the auction session closure date; If non-compliance of the statement made, referred to in Article 39(4), with the facts is found, the President of the ERO shall issue a decision rejecting the bid before the auction settlement date; Article 39(4)-39(6) of the RES Act

30 An auction shall be won by auction participants that bid the lowest sale price of electricity until the amount and value of electricity from renewable energy sources specified in the announcement of the auction is exhausted; When several auction participants bid the same lowest sale price of electricity produced from renewable energy sources, and the total amount and value of electricity whose production was declared by these auction participants exceeds the amount and value specified in the announcement of the auction, the sale of electricity shall be decided on a first come, first served basis; When the amount and value of electricity produced from renewable energy sources remaining for sale is lower than the amount and value specified in the bid of the next auction participant in order, the amount of electricity attributed to this participant shall not be subject to the sale in this auction; Article 80 of the RES Act

31 Supplementary auction If during an auction for the production of electricity from RES produced in RES installations with total installed electrical capacity not higher than 1 MW the submitted bids did not match the maximum amount and value of electricity that may be sold during the auction by at least 10%, the President of the ERO shall announce the sale of that electricity in a supplementary auction; The supplementary auction may be participated by the producer referred to in Article 72(1), producing electricity in a RES installation with total installed electrical capacity higher than 1 MW, but with total installed electrical capacity not higher than 2 MW and installed electrical capacity factor higher than 4000 MWh/MW/year; Article 80(4) and 80(5) of the RES Act

32 Supplementary auction The reference price of electricity from renewable energy sources applicable in the supplementary auction shall be the weighted average of bids submitted by producers producing electricity in renewable energy source installations with total installed electrical capacity not higher than 1 MW that won the auction, in PLN per 1 MWh; Article 80(6) of the RES Act

33 Phasing out of the old support scheme ; Exclusion of feed in tariff ; Article 80(9) of the RES Act

34 Actions of the President of the ERO after auction closure Immediately after the auction closure the President of the ERO shall publish on its website the information on the results of the auction, including: the producers, whose bids have won the auction, the minimum and maximum price at which electricity has been sold by way of the auction, the total amount and value of electricity with regard to subsequent calendar years, or invalidation of the auction; Article 81 of the RES Act

35 Actions of the President of the ERO after auction closure Immediately after the closure of an auction the President of the ERO shall provide the information including the data of producers of electricity from renewable energy sources, whose bids have won the auction, and the data concerning the amount and price of electricity produced from renewable energy sources, with regard to subsequent calendar years: 1) to the relevant obligated vendors and Operator Rozliczeń Energii Odnawialnej S.A., which the obligated vendor is obligated to purchase in the case of producers of electricity in a renewable energy source installation with total installed electrical capacity lower than 500 kw; 2) to Operator Rozliczeń Energii Odnawialnej S.A. in the case of producers of electricity in a renewable energy source installation with total installed electrical capacity no less than 500 kw; Article 81 of the RES Act

36 Premises for invalidation of an auction: all bids have been rejected, the auction cannot be held for technical reasons; Article 81 of the RES Act

37 Article 82 of the RES Act duties of producers < 500 kw; Article 93 of the RES Act duties of producers 500 kw;

38 The producer of electricity in a renewable energy source installation with total installed electrical capacity lower than 500 kw, referred to in Article 72(1) and 72(2), within a month and 6 months from the auction closure date accordingly, shall conclude a power purchase agreement with a relevant obligated vendor (...); Article 82(1) of the RES Act

39 A producer of electricity whose bid has won an auction shall be provide the President of the ERO with: information on the execution status of the schedule referred to in Article 75(5)(5) within 30 days from the end of each calendar year, an information on the date of the first production of electricity from renewable energy sources certified by the power transmission system operator or a power distribution system operator within 30 days from the date of the first production of that electricity, information on the amount of electricity produced from renewable energy sources in MWh produced by it in the previous calendar year within 30 days from the end of each calendar year; The obligation to produce electricity by a producer that won an auction, in the amount specified by it in the bid, shall be settled after the end of each period of three full years when it was eligible for the aid and from the end of the aid period; Article 83 of the RES Act

40 The producer of electricity whose bid has won an auction, who does not fulfil the obligation laid down in Article 79(3)(8) within the deadline laid down therein may participate in an auction for the purchase of electricity produced in a particular renewable energy source installation again after 3 years from the day when the obligation was due; Article 83 of the RES Act

41 An obligated vendor shall purchase electricity produced in a renewable energy source installation with total installed electrical capacity lower than 500 kw from the producer of that electricity who won an auction at a fixed price specified during the auction, settled no later than by 30 June 2021, and only in the amount specified by a particular producer in the bid placed by it, referred to in Article 79; Article 92(1) of the RES Act

42 A producer of electricity from renewable energy sources produced in a renewable energy source installation with total installed electrical capacity not less than 500 kw, who won an auction settled no later than by 30 June 2021 shall have the right to cover the negative balance referred to in Article 93(2)(3); Article 92(5) of the RES Act

43 Support period under auctions for existing installations or installations modernised after the effective date of Section 4 The sale of electricity from renewable energy sources produced in the renewable energy source installation referred to in Article 72(1) shall occur from the when the production of the electricity started no later than on the first day of the month following the lapse of a month from the month, when the auction has been closed, and shall be performed for a period of 15 years from the day when electricity is first produced in the renewable energy source installation or the modernised renewable energy source installation after the effective date of Section 4, no longer than until 31 December 2035; the period shall be counted from the day when electricity is first produced as confirmed by the issued certificate of origin; Article 92(6) of the RES Act

44 Support period under auctions for installations first producing after the auction closure date (including installations modernised after the effective date of Section 4) The sale of electricity from renewable energy sources produced in the renewable energy source installation referred to in Article 72(2) shall occur from the day when the electricity is first fed into a distribution or transmission network and shall be performed for a period of 15 years from the day when electricity is first produced in the renewable energy source installations or the modernised renewable energy source installation, no longer than until 31 December 2035; the period shall be counted from the day when electricity is first sold after the auction closure date; Article 92(7) of the RES Act

45 The amount of electricity produced from renewable energy sources in a renewable energy source installation fed into a network, which: 1) an obligated vendor is obligated to purchase in the case of a producer of electricity from renewable energy sources in a renewable energy source installation with total installed electrical capacity lower than 500 kw, 2) shall be settled with Operator Rozliczeń Energii Odnawialnej S.A. in the case of a producer of electricity from renewable energy sources in a renewable energy source installation with total installed electrical capacity not less than 500 kw shall be specified on the basis of actual readouts of metering and settlement devices in a particular month; Article 92(11) of the RES Act

46 Article 168(15) of the RES Act penal sanctions Whoever: fails to produce the electricity referred to in Article 72 in the amount higher than or equal to 85% of the amount specified in the bid of the producer who won an auction in the settlement periods specified in Article 83(2) shall be subject to a financial penalty;

47 Transitory provisions Article 210 the first auction: date Schedule of actions;

48 Schedule The specification by the Council of Ministers of the maximum amount and value of electricity produced from renewable energy sources, referred to in Article 72 how to be sold by way of an auction in 2016 for the first time to be specified by 31 May 2015 Article 208(2) of the RES Act; The specification by a minister competent for the matters of economy, by way of a regulation, of the maximum amount and value of electricity produced in renewable energy source installations with total installed electrical capacity not higher than 1 MW that shall be sold after an auction is held in 2016 by 15 June 2015 Article 209(1) of the RES Act;

49 Schedule The announcement by the President of the ERO of the average electricity sales price on the competitive market in the previous quarter, referred to in Article 23(2)(18a) of the Energy Law in the wording established by Article 179 of the Renewable Energy Sources Act for the first time by 30 September 2015, no sooner than 30 days after the effective date of the Act due to the effective date of Article 179(20), which amends the Energy Law in that respect Article 195 of the RES Act; The specification by a minister competent for the matters of economy of the reference price referred to in Article 77(1) of the Act by 31 December 2015 Article 209(2) of the RES Act;

50 Schedule Technical support for ToR issues in the area of the tender for the delivery of the internet auction platform; The specification of ToR; The specification and approval of auction by-laws; Announcement of a tender for the delivery of the internet auction platform; Final settlement of the tender (having considered appeal instances) conclusion of an agreement; Testing of the internet auction platform Q1 2016;

51 Thank you for attention

POLISH INCENTIVE SCHEMES FOR RENEWABLE ENERGY GENERATION

POLISH INCENTIVE SCHEMES FOR RENEWABLE ENERGY GENERATION 25 July 217 POLISH INCENTIVE SCHEMES FOR RENEWABLE ENERGY GENERATION I. General overview of existing legal framework... 2 [Applicability of the main incentive schemes]... 2 II. Certificate-based incentive

More information

DRAFT. Renewable Energy Sources

DRAFT. Renewable Energy Sources Renewable Energy Sources Financial parameters of auctions for renewable energy sources Legal Alert April 2017 On 3 April 2017 two regulations were published in the Journal of Laws which set out the financial

More information

Wind Energy Investments Act 1)

Wind Energy Investments Act 1) No. of pages: 13 Date: 2016-04-04 File name: 1.04.2016_ENG 1 Wind Energy Investments Act 1) of... 2016 Draft Section 1 General provisions Article 1 1. The Act lays down the conditions and the procedure

More information

Wind Energy Investments Act 1)2)

Wind Energy Investments Act 1)2) Draft Wind Energy Investments Act 1)2) of... 2016 Section 1 General provisions Article 1 1. The Act lays down the conditions and the procedure for the location, construction and operation of wind turbines

More information

8.1. GENERAL RULES OF CAPACITY BOOKING

8.1. GENERAL RULES OF CAPACITY BOOKING 8.1. GENERAL RULES OF CAPACITY BOOKING (a) Pursuant to the provisions of the Gas Supply Act and the Implementation Decree the free capacities of the natural gas network may and shall be offered to network

More information

No. 180/2005 Coll. PART ONE PROMOTION OF ELECTRICITY PRODUCTION FROM RENEWABLE ENERGY SOURCES TITLE I GENERAL PROVISIONS

No. 180/2005 Coll. PART ONE PROMOTION OF ELECTRICITY PRODUCTION FROM RENEWABLE ENERGY SOURCES TITLE I GENERAL PROVISIONS No. 180/2005 Coll. ACT of 31 March 2005 on the promotion of electricity production from renewable energy sources and amending certain acts (Act on Promotion of Use of Renewable Sources) The Parliament

More information

(Non-legislative acts) REGULATIONS

(Non-legislative acts) REGULATIONS 15.6.2013 Official Journal of the European Union L 163/1 II (Non-legislative acts) REGULATIONS COMMISSION REGULATION (EU) No 543/2013 of 14 June 2013 on submission and publication of data in electricity

More information

PARTICULARS OF THE COMPANY

PARTICULARS OF THE COMPANY TEASER 2015/2016 PARTICULARS OF THE COMPANY Company history Selected areas of operations Group structure Laws and regulations concerning renewable energy in Poland Renewable Energy in Poland Subsidy programs

More information

Regulations Regarding the Energy Efficiency Monitoring and Applicable Energy Management System Standard

Regulations Regarding the Energy Efficiency Monitoring and Applicable Energy Management System Standard Republic of Latvia Cabinet Regulation No. 668 Adopted 11 October 2016 Regulations Regarding the Energy Efficiency Monitoring and Applicable Energy Management System Standard Issued pursuant to Section

More information

Energie-Control Austria Executive Board Ordinance on Provisions for the Gas Market Model (Gas Market Model Ordinance 2012) Title 1 Principles

Energie-Control Austria Executive Board Ordinance on Provisions for the Gas Market Model (Gas Market Model Ordinance 2012) Title 1 Principles Energie-Control Austria Executive Board Ordinance on Provisions for the Gas Market Model (Gas Market Model Ordinance 2012) In exercise of section 41 Gaswirtschaftsgesetz (Natural Gas Act) 2011, BGBl. (Federal

More information

UNMIK REGULATION NO. 2004/22 ON THE PROMULGATION OF A LAW ADOPTED BY THE ASSEMBLY OF KOSOVO ON ELECTRICITY

UNMIK REGULATION NO. 2004/22 ON THE PROMULGATION OF A LAW ADOPTED BY THE ASSEMBLY OF KOSOVO ON ELECTRICITY UNITED NATIONS United Nations Interim Administration Mission in Kosovo UNMIK NATIONS UNIES Mission d Administration Intérimaire des Nations Unies au Kosovo UNMIK/REG/2004/22 30 June 2004 REGULATION NO.

More information

Act Revising the Legislation on Renewable Energy Sources in the Electricity Sector and Amending Related Provisions *)

Act Revising the Legislation on Renewable Energy Sources in the Electricity Sector and Amending Related Provisions *) 1 Translation Act Revising the Legislation on Renewable Energy Sources in the Electricity Sector and Amending Related Provisions *) of 2008 The Bundestag has adopted the following Act: Article 1 Act on

More information

Jammu and Kashmir State Electricity Regulatory Commission

Jammu and Kashmir State Electricity Regulatory Commission DRAFT NOTIFICATION INVITING OBJECTIONS / COMMENTS /SUGGESTIONS Jammu and Kashmir State Electricity Regulatory Commission NOTIFICATION (Draft) No: JKSERC/ Dated: Jammu, In exercise of the power conferred

More information

ATTACHMENT DD. Reliability Pricing Model

ATTACHMENT DD. Reliability Pricing Model OF NEW SERVICE REQUESTS; R - OATT ATTACHMENT DD ATTACHMENT DD Reliability Pricing Model References to section numbers in this Attachment DD refer to sections of this Attachment DD, unless otherwise specified.

More information

RATE 665 RENEWABLE FEED-IN TARIFF

RATE 665 RENEWABLE FEED-IN TARIFF NORTHERN INDIANA PUBLIC SERVICE COMPANY Third Revised Sheet No. 104 Superseding Second Revised Sheet No. 104 TO WHOM AVAILABLE No. 1 of 11 Sheets This is a rate that is a voluntary offer available to any

More information

Long Island Power Authority Seventh Revised Leaf No. 16

Long Island Power Authority Seventh Revised Leaf No. 16 Seventh Revised Leaf No. 16 I. General Information (continued): B. Abbreviations and Definitions (continued): Demand Customer: A Customer who is billed for Demand charges. Demand Meter: The device that

More information

European Parliament plenary vote, 17 January this Directive have the sole function of showing

European Parliament plenary vote, 17 January this Directive have the sole function of showing Overview of final draft text of Renewable Energy Directive (REDII) Comparing proposals from the EU Commission, Council and Parliament as of January 17th, 2018 - Includes only text elements which comprises

More information

Headline Germany - Experiences with implementing RES E auctions

Headline Germany - Experiences with implementing RES E auctions Headline Germany - Experiences with implementing RES E auctions Dr. Aike Müller Federal Ministry for Economic Affairs an Energy, Division: Renewable Energy in the Electricity Sector (IIIB5) Overview Background

More information

Casework Technical Support (Social Welfare - Project Management)

Casework Technical Support (Social Welfare - Project Management) Casework Technical Support (Social Welfare - Project Management) Request for Tenders for Services to MABS NATIONAL DEVELOPMENT The latest date for receipt of tenders is 09 June 2017 Commercial House Westend

More information

(proliferated in FLG II no 171/2012, as amended in 2016, FLG II no XXX/2016; as of 1 October 2016)

(proliferated in FLG II no 171/2012, as amended in 2016, FLG II no XXX/2016; as of 1 October 2016) Energie-Control Austria Executive Board Ordinance on Provisions for the Gas Market Model as amended in 2016 (2016 Gas Market Model Amendment Ordinance 2012) (proliferated in FLG II no 171/2012, as amended

More information

Renewable Energy Sources Albania. Ministry of Energy and Industry 2016

Renewable Energy Sources Albania. Ministry of Energy and Industry 2016 Renewable Energy Sources Albania Ministry of Energy and Industry 2016 RES production Albania NREAP projection A RES to GFEC during 2009-2014 % 31.2% B Target of RES to 2020 % 38.0% C RES production to

More information

Renewable Energy Sources and Combined Heat and Power. Paweł Płachecki Department of Energy Enterprises RES and CHP Unit

Renewable Energy Sources and Combined Heat and Power. Paweł Płachecki Department of Energy Enterprises RES and CHP Unit Renewable Energy Sources and Combined Heat and Power Paweł Płachecki Department of Energy Enterprises RES and CHP Unit Poznań 2009 Introduction 1) legislative background, 2) targets for consumption of

More information

Outline of the Revised Renewable Energy Act

Outline of the Revised Renewable Energy Act ENERGY PRACTICE LEGAL UPDATE August 2017 Outline of the Revised Renewable Energy Act Eiji Kobayashi / Kunihiro Yokoi / Kunitaro Yabuki On 1 April 2017 (the Effective Date ), the Act for the Partial Revision

More information

Notice of Capacity Self-Supply Alternative for Qualifying Competitive Service Providers

Notice of Capacity Self-Supply Alternative for Qualifying Competitive Service Providers Notice of Capacity Self-Supply Alternative for Qualifying Competitive Service Providers NOTICE OF CAPACITY SELF-SUPPLY ALTERNATIVE FOR QUALIFYING COMPETITIVE SERVICE PROVIDERS On October 1, 2013, Appalachian

More information

MICRO AGRICULTURAL BIOGAS PLANTS IN POLAND

MICRO AGRICULTURAL BIOGAS PLANTS IN POLAND MICRO AGRICULTURAL BIOGAS PLANTS IN POLAND National Energy Conservation Agency NAPE (Poland) Schwäbisch Hall 24/06/2014 How is a micro agricultural biogas plant defined in Poland? connected to the grid

More information

Non-exclusive right to handle the marketing and distribution for sale of reference materials from the JRC world-wide

Non-exclusive right to handle the marketing and distribution for sale of reference materials from the JRC world-wide EUROPEAN COMMISSION DIRECTORATE-GENERAL JOINT RESEARCH CENTRE Directorate F Health, Consumers & Reference Materials Unit F.6 Reference Materials Non-exclusive right to handle the marketing and distribution

More information

ON THERMAL ENERGY. Based on Article 65 (1) of the Constitution of the Republic of Kosovo, LAW ON THERMAL ENERGY CHAPTER I GENERAL PROVISIONS

ON THERMAL ENERGY. Based on Article 65 (1) of the Constitution of the Republic of Kosovo, LAW ON THERMAL ENERGY CHAPTER I GENERAL PROVISIONS LAW No. No. 05/L 05/L -058-052 ON ON INDUSTRIAL THERMAL ENERGY DESIGN LAW No. 05/L -052 ON THERMAL ENERGY Assembly of the Republic of Kosovo, Based on Article 65 (1) of the Constitution of the Republic

More information

Research RES LEGAL Support system Country: Germany

Research RES LEGAL Support system Country: Germany Research RES LEGAL Support system Country: Germany 1. Overview of support system Overview of support system Support schemes Promoted technologies Statutory provisions In Germany, electricity from renewable

More information

The legal framework of electricity generation from biomass/biogas in Greece

The legal framework of electricity generation from biomass/biogas in Greece The legal framework of electricity generation from biomass/biogas in Greece Eva Keki / LL.M. Bonn / Lawyer at the First Instance Court in Athens, Associate MStR Law Sofia Deligianni / LL.B. University

More information

Electricity Market Code

Electricity Market Code Electricity Market Code Chapter 1 Definitions Version 2.0 This documents contains a partial translation of the Austrian Electricity Market Code from German into English. It is provided for the reader s

More information

where implicit capacity allocation methods are applied, national regulatory authorities may decide not to apply Articles 8 to 37.

where implicit capacity allocation methods are applied, national regulatory authorities may decide not to apply Articles 8 to 37. System Operator's METHODOLOGY OF GAS TRANSMISSION CAPACITY ALLOCATION AND CONGESTION MANAGEMENT PROCEDURE AND STANDARD TERMS FOR ACCESSING THE CROSS-BORDER INFRASTRUCTURE 30 th June 2017 1. General provisions...

More information

REPUBLIC OF LITHUANIA LAW ON ELECTRICITY 20 July, 2000, No. VIII 1881 as amended by 26 June, 2001, No. IX-408 Vilnius CHAPTER ONE GENERAL PROVISIONS

REPUBLIC OF LITHUANIA LAW ON ELECTRICITY 20 July, 2000, No. VIII 1881 as amended by 26 June, 2001, No. IX-408 Vilnius CHAPTER ONE GENERAL PROVISIONS Official translation REPUBLIC OF LITHUANIA LAW ON ELECTRICITY 20 July, 2000, No. VIII 1881 as amended by 26 June, 2001, No. IX-408 Vilnius CHAPTER ONE GENERAL PROVISIONS Article 1. Purpose of the Law This

More information

Renewable Energy Sources: National Targets and Legal Framework

Renewable Energy Sources: National Targets and Legal Framework MINISTRY OF ENVIRONMENT ENERGY & CLIMATE CHANGE Renewable Energy Sources: National Targets and Legal Framework P. Karatzias Renewable Energy Sources Ministry of Environment and Energy Directorate of Renewable

More information

Keep-on-Track! Project National Report: Poland

Keep-on-Track! Project National Report: Poland Keep-on-Track! Project National Report: Poland 02.02.2015 Contract No: IEE/11/842 Authors: Anna Pobłocka-Dirakis, eclareon Beata Wiszniewska, PIGEOR (The Polish Economic Chamber of Renewable and Distributed

More information

A Roadmap for Photovoltaic Auctions in Israel Targets and vision Honi Kabalo - Head of Renewable Energy, Electricity Regulatory Authority

A Roadmap for Photovoltaic Auctions in Israel Targets and vision Honi Kabalo - Head of Renewable Energy, Electricity Regulatory Authority A Roadmap for Photovoltaic Auctions in Israel Targets and vision Honi Kabalo - Head of Renewable Energy, Electricity Regulatory Authority The evolution of Israel s Renewable Energy Scheme 2017-2020: Solar

More information

Danish Offshore Wind Tender Model

Danish Offshore Wind Tender Model Energy Law Group 22, Warsaw Michael Meyer, Partner Christoffer Fode, Partner Gorrissen Federspiel, Denmark Agenda 1. The Danish Political targets and the road map 2. Focus on wind energy 3. Focus on offshore

More information

What will be the new scenario in Italy with the approval of the regulation on biomethane? Davide Valenzano - Federica Ceccaroni

What will be the new scenario in Italy with the approval of the regulation on biomethane? Davide Valenzano - Federica Ceccaroni What will be the new scenario in Italy with the approval of the regulation on biomethane? Davide Valenzano - Federica Ceccaroni Regulatory Affairs Unit GSE Italian Energy Services Operator Agriculture

More information

450 Compendium of Regulations & Tariff Orders Issued by Regulatory Commissions for Renewable Energy Sources in India

450 Compendium of Regulations & Tariff Orders Issued by Regulatory Commissions for Renewable Energy Sources in India 450 Compendium of Regulations & Tariff Orders Issued by Regulatory Commissions for Renewable Energy Sources in India WEST BENGAL ELECTRICITY REGULATORY COMMISSION Cogeneration and Generation of Electricity

More information

S 2185 S T A T E O F R H O D E I S L A N D

S 2185 S T A T E O F R H O D E I S L A N D LC00 0 -- S S T A T E O F R H O D E I S L A N D IN GENERAL ASSEMBLY JANUARY SESSION, A.D. 0 A N A C T RELATING TO PUBLIC UTILITIES AND CARRIERS -- RENEWABLE ENERGY Introduced By: Senators Sosnowski, Conley,

More information

H 7413 S T A T E O F R H O D E I S L A N D

H 7413 S T A T E O F R H O D E I S L A N D LC000 0 -- H S T A T E O F R H O D E I S L A N D IN GENERAL ASSEMBLY JANUARY SESSION, A.D. 0 A N A C T RELATING TO PUBLIC UTILITIES AND CARRIERS -- RENEWABLE ENERGY Introduced By: Representatives Ruggiero,

More information

Energy from Renewable Sources Act

Energy from Renewable Sources Act Energy from Renewable Sources Act Promulgated, State Gazette No. 35/3.05.2011, effective 3.05.2011, amended and supplemented, SG No. 29/10.04.2012, effective 10.04.2012, SG No. 54/17.07.2012, effective

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination of Ancillary Service Standards... 4 8.2.2 Time-Frame for Revising Ancillary Service

More information

Capacity Booking Platform Regulation

Capacity Booking Platform Regulation Capacity Booking Platform Regulation Operational Rules of the Regional Booking Platform Version 1.6. Applicable from 1 October 2018 FGSZ Zrt. 1 Table of Contents Preamble... 5 1. Definitions... 5 2. General

More information

Part 1 Introduction and Overview

Part 1 Introduction and Overview Part 1 Introduction and Overview A. Applicability: This Application for Customer Generation Cost Responsibility Surcharge (CRS) Tariff Exemptions (Application) is for the purpose of requesting an exemption

More information

Renewables Decree Focus on other renewable plants

Renewables Decree Focus on other renewable plants ANTITRUST ENERGY Renewables Decree Focus on other renewable plants Contents 1. The new incentive tariffs 2. The ranking lists procedure 3. Rebate auctions 4. Power plant fed by sustainable bioliquids,

More information

The main features of the Act on granting priority to renewable energy sources (Renewable Energy Sources Act) of 21 July 2004

The main features of the Act on granting priority to renewable energy sources (Renewable Energy Sources Act) of 21 July 2004 Federal Ministry for the Environment, Nature Conservation and Nuclear Safety Public Relations Division 11055 Berlin Tel.: 01888/305-0. Fax: 01888/ 305-2044 E-Mail: service@bmu.bund.de http://www.bmu.de

More information

H 7413 SUBSTITUTE A ======== LC004207/SUB A ======== S T A T E O F R H O D E I S L A N D

H 7413 SUBSTITUTE A ======== LC004207/SUB A ======== S T A T E O F R H O D E I S L A N D 0 -- H 1 SUBSTITUTE A LC000/SUB A S T A T E O F R H O D E I S L A N D IN GENERAL ASSEMBLY JANUARY SESSION, A.D. 0 A N A C T RELATING TO PUBLIC UTILITIES AND CARRIERS -- RENEWABLE ENERGY Introduced By:

More information

Firm Transmission Feasibility Study: A study conducted by the Transmission Provider in accordance with Section 36.4 of the Tariff.

Firm Transmission Feasibility Study: A study conducted by the Transmission Provider in accordance with Section 36.4 of the Tariff. Firm Transmission Feasibility Study: A study conducted by the Transmission Provider in accordance with Section 36.4 of the Tariff. Upgrade Feasibility Study: A study conducted by the Transmission Provider

More information

Regulations Regarding Participation of Stationary Technological Installations in the Emission Allowance Trading Scheme of the European Union

Regulations Regarding Participation of Stationary Technological Installations in the Emission Allowance Trading Scheme of the European Union Republic of Latvia Cabinet Regulation No. 769 Adopted 13 November 2012 Regulations Regarding Participation of Stationary Technological Installations in the Emission Allowance Trading Scheme of the European

More information

Warsaw. Polish Wind Energy Association

Warsaw. Polish Wind Energy Association 20.10.2016 Warsaw remarks to the draft Minister for Energy Regulation on the adjustment of the quantitative share of the sum of electricity stemming from cancelled certificates confirming the production

More information

GOVERNMENT RAJASTHAN POLICY FOR PROMOTING GENERATION THROUGH NON-CONVENTIONAL ENERGY SOURCES Sl. No 1 Order Energy Deptt. letter no. F.

GOVERNMENT RAJASTHAN POLICY FOR PROMOTING GENERATION THROUGH NON-CONVENTIONAL ENERGY SOURCES Sl. No 1 Order Energy Deptt. letter no. F. GOVERNMENT RAJASTHAN POLICY FOR PROMOTING GENERATION THROUGH NON-CONVENTIONAL ENERGY SOURCES Sl. No Description Summary 1 Order Energy Deptt. letter no. F.20 (4) Energy/2004 dated 25.10.2004 and amended

More information

Resource Capability Testing

Resource Capability Testing Resource Capability Testing Amount of Capacity Available Joe Nieminski ICAP Market Operations Engineer, NYISO Intermediate ICAP Course November 7-8, 2017 Rensselaer, NY 1 Objectives Participants will be

More information

ROMANIAN GREEN CERTIFICATES SYSTEM

ROMANIAN GREEN CERTIFICATES SYSTEM ROMANIAN GREEN CERTIFICATES SYSTEM STATUS QUO AND PROSPECTS Radu Regman Deputy General Director Energy Efficiency Department- ANRE TABLE OF CONTENTS I. Background of E-RES Promoting System in Romania II.

More information

Relevant changes will be made to corresponding sections of OA and RAA.

Relevant changes will be made to corresponding sections of OA and RAA. PJM Interconnection - Intra-PJM Tariffs - OPEN ACCESS TRANSMISSION TARIFF PJM OPEN ACCESS TRANSMISSION TARIFF Relevant changes will be made to corresponding sections of OA and RAA. Effective Date: 9/17/2010

More information

Competitive bidding procedures in the 2017 Renewable Energy Sources Act

Competitive bidding procedures in the 2017 Renewable Energy Sources Act CLIENT UPDATE Competitive bidding procedures in the 2017 Renewable Energy Sources Act August 2016 On 8 July 2016, the lower and upper chambers of the German parliament passed a fundamental reform of the

More information

Energy Efficiency Law

Energy Efficiency Law The Saeima 1 has adopted and the President has proclaimed the following Law: Energy Efficiency Law Section 1. Terms Used in this Law Chapter I General Provisions (1) The following terms are used in this

More information

Application Guide. Ver 1.5

Application Guide. Ver 1.5 Renewable Application Guide Ver 1.5 IMPORTANT NOTICE SEI shall bear no responsibility for the quality, specification or standard of the product or its suitability for the application for which it is installed,

More information

Labelling provision in Directive 2003/54/EC

Labelling provision in Directive 2003/54/EC NOTE OF DG ENERGY & TRANSPORT ON DIRECTIVES 2003/54 AND 2003/55 ON THE INTERNAL MARKET IN ELECTRICITY AND NATURAL GAS THIS DOCUMENT IS NOT BINDING ON THE COMMISSION Labelling provision in Directive 2003/54/EC

More information

An evaluation of the Irish Remote Interpreting Service (IRIS) Request for Tenders

An evaluation of the Irish Remote Interpreting Service (IRIS) Request for Tenders An evaluation of the Irish Remote Interpreting Service (IRIS) 2018. Request for Tenders The latest date for receipt of tenders is Thursday 30 th August 2018 at 4 pm July 2018 Sign Language Interpreting

More information

The Vermont Statutes Online

The Vermont Statutes Online VERMONT GENERAL ASSEMBLY The Vermont Statutes Online Title 30: Public Service Chapter 89: Renewable Energy Programs Subchapter 1: General Provisions 8001. Renewable energy goals (a) The General Assembly

More information

CHAPTER SMALL POWER PRODUCTION AND COGENERATION Definitions. As used throughout this chapter, except where otherwise indicated:

CHAPTER SMALL POWER PRODUCTION AND COGENERATION Definitions. As used throughout this chapter, except where otherwise indicated: CHAPTER 69-09-07 SMALL POWER PRODUCTION AND COGENERATION Section 69-09-07-01 Definitions 69-09-07-02 Scope - Applicability - Negotiated Rates or Terms 69-09-07-03 Qualifying Facilities - General Requirements

More information

This document is a translation of an original text in Spanish. In case of any discrepancy between both texts, the Spanish version will prevail.

This document is a translation of an original text in Spanish. In case of any discrepancy between both texts, the Spanish version will prevail. PARQUES REUNIDOS SERVICIOS CENTRALES, S.A. RULES GOVERNING THE RIGHT OF ATTENDANCE, PROXY REPRESENTATION AND REMOTE VOTING RIGHT OF ATTENDANCE Shareholders may attend the General Shareholders Meeting whatever

More information

PIGEO s Detailed Position. on Oversupply of Green Certificates

PIGEO s Detailed Position. on Oversupply of Green Certificates Warsaw, 20 th February 2013 PIGEO s Detailed Position on Oversupply of Green Certificates The Polish Economic Chamber of Renewable Energy (PIGEO), representing a broad range of entrepreneurs from all RES

More information

THE EUROPEAN PARLIAMENT AND THE COUNCIL OF THE EUROPEAN UNION,

THE EUROPEAN PARLIAMENT AND THE COUNCIL OF THE EUROPEAN UNION, Regulation (EC) No 1071/2009 of the European Parliament and of the Council of 21 October 2009 establishing common rules concerning the conditions to be complied with to pursue the occupation of road transport

More information

Long Island Power Authority Seventh Revised Leaf No. 16

Long Island Power Authority Seventh Revised Leaf No. 16 Seventh Revised Leaf No. 16 I. General Information (continued): B. Abbreviations and Definitions (continued): Demand Customer: A Customer who is billed for Demand charges. Demand Meter: The device that

More information

Country profiles: Finland

Country profiles: Finland Country profiles: Finland Last updated: 20/02/2014 1 Implementation of Tracking Systems 1.1 Electricity Disclosure Electricity disclosure in Finland is implemented by the law Laki sähkön alkuperän varmentamisesta

More information

ARN2016 Procurement Regulations Utility Sectors 2016

ARN2016 Procurement Regulations Utility Sectors 2016 ARN2016 Procurement Regulations Utility Sectors 2016 Preamble - Special sector companies are obliged to award assignments in accordance with the provisions of the Aanbestedingswet 2012 (Netherlands Procurement

More information

Call for Tenders for Positive Load Flow Commitments for the time period to

Call for Tenders for Positive Load Flow Commitments for the time period to Call for Tenders for Positive Load Flow Commitments for the time period 01.01.2018 to 01.01.2019 Preamble: terranets bw GmbH (terranets bw) conducts a call for tenders based on 9 Section 3 Sentence 2 No.

More information

AUCTION OF THE BUNDLED PRODUCT AT IP LASÓW

AUCTION OF THE BUNDLED PRODUCT AT IP LASÓW AUCTION OF THE BUNDLED PRODUCT AT IP LASÓW SHIPPE ERS MANUAL for information purposes only Warsaw/ Leipzig, March 2013 PAGE 1 / 15 CONTENTS: I. GENERAL INFORMATION... 3 II. DEFINITIONS... 3 III. REQUIREMENTS

More information

UNOFFICIAL TRANSLATION

UNOFFICIAL TRANSLATION UNOFFICIAL TRANSLATION REPUBLIC OF LATVIA PUBLIC UTILITIES COMMISSION COUNCIL RESOLUTION Riga, 13.04.2017 No. 1/16 (Minutes No. 15, para. 4) Rules of Use of the Natural Gas Transmission System 1. The regulations

More information

LAW ON ENERGY EFFICIENCY

LAW ON ENERGY EFFICIENCY Pursuant to article 82 paragraph 1 clause 2 and article 91 paragraph 1 of the Constitution of Montenegro, the Parliament of Montenegro during its 24th electoral term, on the fifth sitting in the first

More information

AGENDA March 26, :30 P.M. City Council Chambers

AGENDA March 26, :30 P.M. City Council Chambers 03-26-12 Committee of the Whole Meeting http://www.darien.il.us/government/minutes/2012/council/120326/age... 1 of 1 1/19/2015 9:26 PM AGENDA March 26, 2012 6:30 P.M. City Council Chambers 1. CALL TO ORDER

More information

REPUBLIC OF LITHUANIA LAW ON PUBLIC ADMINISTRATION. 17 June 1999 No VIII-1234 Vilnius. (As last amended on 3 June 2014 No XII-903)

REPUBLIC OF LITHUANIA LAW ON PUBLIC ADMINISTRATION. 17 June 1999 No VIII-1234 Vilnius. (As last amended on 3 June 2014 No XII-903) REPUBLIC OF LITHUANIA LAW ON PUBLIC ADMINISTRATION 17 June 1999 No VIII-1234 Vilnius (As last amended on 3 June 2014 No XII-903) CHAPTER I GENERAL PROVISIONS Article 1. Purpose of the Law This Law shall

More information

New market mechanisms for renewables in Poland. Opportunity or threat?

New market mechanisms for renewables in Poland. Opportunity or threat? New market mechanisms for renewables in Poland. Opportunity or threat? Adam Jodłowski Deloitte Legal, Pasternak, Korba i Wspólnicy Kancelaria Prawnicza sp. k. Vienna 6 June 2013 Agenda I Overview of Polish

More information

GRENLEC s Renewable Standard Offer

GRENLEC s Renewable Standard Offer GRENLEC s Renewable Standard Offer Version: 1.1 Last Updated: September 10 th, 2011 This document provides as a general overview of the Customer-owned Renewable Generation Standard Offer, for the purchase

More information

Subject: State aid N 47/2008 Austria Modification of feed-in tariffs for electricity from renewable sources under the Austrian Green Electricity Act

Subject: State aid N 47/2008 Austria Modification of feed-in tariffs for electricity from renewable sources under the Austrian Green Electricity Act EUROPEAN COMMISSION Brussels, 10.VI.2008 C(2008)2749 PUBLIC VERSION WORKING LANGUAGE This document is made available for information purposes only. Subject: State aid N 47/2008 Austria Modification of

More information

Disable friendly Washrooms at hostel blocks (A & E)

Disable friendly Washrooms at hostel blocks (A & E) Telephone: 080-26993580 080-26993360 Fax:080- :26584050 Email: anil.sj@iimb.ernet.in : shivakumar.k@iimb.ernet.in TENDER NOTICE: 16 th February 2015 E.M.D (Rs.) TO BE SUBMITTED ALONG WITH TENDER Tender

More information

November Explanatory memorandum for CERC Regulations for implementation of REC mechanism in India

November Explanatory memorandum for CERC Regulations for implementation of REC mechanism in India Explanatory Memorandum for Central Electricity Regulatory Commission Regulations on Recognition and Issuance of Renewable Energy Certificate (REC) for Renewable Energy Generation November 2009 Explanatory

More information

COMMISSION DELEGATED REGULATION (EU) No /.. of XXX

COMMISSION DELEGATED REGULATION (EU) No /.. of XXX EUROPEAN COMMISSION Brussels, XXX [ ](2014) XXX draft COMMISSION DELEGATED REGULATION (EU) No /.. of XXX supplementing Directive 2013/36/EU of the European Parliament and of the Council with regard to

More information

Contract notice. Services

Contract notice. Services 1/6 This notice in TED website: http://ted.europa.eu/udl?uri=ted:notice:65706-2015:text:en:html Germany-Frankfurt-on-Main: ECB - Provision of travel services and handling of travel expenses 2015/S 039-065706

More information

The Austrian E-Government Act

The Austrian E-Government Act The Austrian E-Government Act Federal Act on Provisions Facilitating Electronic Communications with Public Bodies (Bundesgesetz über Regelungen zur Erleichterung des elektronischen Verkehrs mit öffentlichen

More information

Danish Act on Clinical Trials of Medicinal Products 1

Danish Act on Clinical Trials of Medicinal Products 1 This is a translation of an extract of the Danish Act on Clinical Trials of Medicinal Products (Danish title: Lov om kliniske forsøg med lægemidler). Only the Danish version has legal validity. Adopted

More information

Question & Answers on Invitation to tender for Framework Contract 2007/S

Question & Answers on Invitation to tender for Framework Contract 2007/S Question & Answers on Invitation to tender for Framework Contract 2007/S 130-158835 Impact Assessment and Evaluation (ex-ante, intermediate and ex-post) Updated: 02/08/2007 Before submitting any written

More information

ANNOUNCEMENT OF 24 MARCH 2017 OF THE MANAGEMENT BOARD OF ALIOR BANK S.A. TO CONVENE EXTRAORDINARY GENERAL MEETING

ANNOUNCEMENT OF 24 MARCH 2017 OF THE MANAGEMENT BOARD OF ALIOR BANK S.A. TO CONVENE EXTRAORDINARY GENERAL MEETING ANNOUNCEMENT OF 24 MARCH 2017 OF THE MANAGEMENT BOARD OF ALIOR BANK S.A. TO CONVENE EXTRAORDINARY GENERAL MEETING The Management Board of Alior Bank Spółka Akcyjna ( the Bank ), acting pursuant to Article

More information

Act. on the Promotion of Renewable Energies in the Heat Sector. (Erneuerbare-Energien-Wärmegesetz EEWärmeG)*) of 2008

Act. on the Promotion of Renewable Energies in the Heat Sector. (Erneuerbare-Energien-Wärmegesetz EEWärmeG)*) of 2008 Act on the Promotion of Renewable Energies in the Heat Sector (Erneuerbare-Energien-Wärmegesetz EEWärmeG)*) of 2008 The Bundestag has adopted the following Act: Contents Part 1 General provisions Article

More information

ARN Procurement Regulations Utility Sectors 2016

ARN Procurement Regulations Utility Sectors 2016 ARN 2016 Procurement Regulations Utility Sectors 2016 Preamble - Special sector companies are obliged to award assignments in accordance with the provisions of the Aanbestedingswet 2012 (Netherlands Procurement

More information

LAW OF MONGOLIA ON ENERGY CHAPTER ONE GENERAL PROVISIONS. Article 1. The Purpose of the Law

LAW OF MONGOLIA ON ENERGY CHAPTER ONE GENERAL PROVISIONS. Article 1. The Purpose of the Law LAW OF MONGOLIA ON ENERGY CHAPTER ONE GENERAL PROVISIONS Article 1. The Purpose of the Law 1.1. The purpose of this law is to regulate matters relating to energy generation, transmission, distribution,

More information

Hungary Ministry of National Development Report

Hungary Ministry of National Development Report Hungary Ministry of National Development Report on the use of renewable energy sources in Hungary in 2011 and 2012 (Reporting by a Member State pursuant to Article 22 of Directive 2009/28/EC) Budapest

More information

Chhattisgarh State Electricity Regulatory Commission

Chhattisgarh State Electricity Regulatory Commission Chhattisgarh State Electricity Regulatory Commission Irrigation Colony, Shanti Nagar, Raipur Raipur, Dated September 18, 2013 No. 48/CSERC/2013 - Section 86(1)(e) of the Electricity Act, 2003 (the Act)

More information

PRESIDENTIAL REGULATION OF THE REPUBLIC OF INDONESIA NUMBER 13 OF 2010 REGARDING

PRESIDENTIAL REGULATION OF THE REPUBLIC OF INDONESIA NUMBER 13 OF 2010 REGARDING PRESIDENTIAL REGULATION OF THE REPUBLIC OF INDONESIA NUMBER 13 OF 2010 REGARDING AMENDMENT UPON PRESIDENTIAL REGULATION NUMBER 67 OF 2005 REGARDING THE COOPERATION BETWEEN THE GOVERNMENT AND THE BUSINESS

More information

Renewable and Alternative Energy Sources and Biofuels Act. Renewable and Alternative Energy Sources and Biofuels Act

Renewable and Alternative Energy Sources and Biofuels Act. Renewable and Alternative Energy Sources and Biofuels Act Renewable and Alternative Energy Sources and Biofuels Act Renewable and Alternative Energy Sources and Biofuels Act Prom. SG. 49/19.06.2007 Chapter one GENERAL PROVISIONS Art. 1. This Act regulates the

More information

Implementation of Cogeneration Directive (2004/8/EC) in Poland

Implementation of Cogeneration Directive (2004/8/EC) in Poland Energy Department Implementation of Cogeneration Directive (2004/8/EC) in Poland Warsaw, 17 September 2009 The main points of Directive 2004/8/EC The Directive has brought into effect: harmonized definitions,

More information

Official Journal of the European Communities

Official Journal of the European Communities 13.6.2001 EN Official Journal of the European Communities L 156/9 COMMISSION REGULATION (EC) No 1148/2001 of 12 June 2001 on checks on conformity to the marketing standards applicable to fresh fruit and

More information

Country profiles: Czech Republic

Country profiles: Czech Republic Country profiles: Czech Republic Last updated: date (30/06/2015) 1 Implementation of Tracking Systems In Czech Republic, the market is fully liberalised since 2006. Numerous suppliers are present on the

More information

Tender No GSO/CED/CE/TR - 410/2011

Tender No GSO/CED/CE/TR - 410/2011 Government of India Department of Atomic Energy General Services Organisation Civil Engineering Division Tender No GSO/CED/CE/TR - 410/2011 Sealed item rate tenders in TWO Parts in the prescribed forms

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 31. Day-Ahead Market... 2 31.1 Bid Submission and Validation in the Day-Ahead Market... 2 31.2 Day-Ahead MPM Process... 2 31.2.1 The Market Power Mitigation Process... 3 31.2.2 Bid Mitigation

More information

Announcement of October 30 th, 2018 of the Management Board of Alior Bank S.A. to convene the Extraordinary General Meeting

Announcement of October 30 th, 2018 of the Management Board of Alior Bank S.A. to convene the Extraordinary General Meeting Announcement of October 30 th, 2018 of the Management Board of Alior Bank S.A. to convene the Extraordinary General Meeting The Management Board of Alior Bank Spółka Akcyjna ( the Bank ), acting pursuant

More information

Vietnam takes further steps to encourage solar energy

Vietnam takes further steps to encourage solar energy Legal Update May 2017 Vietnam takes further steps to encourage solar energy On 11 April 2017, the Prime Minister issued long-awaited regulations on solar energy in Decision No. 11/2017/QD-TTg (Decision

More information

RENEWABLE ENERGY RESOURCES ELIGIBILITY GDS TEAM RECOMMENDATION For Consideration By The STATE OF RHODE ISLAND PUBLIC UTILITIES COMMISSION

RENEWABLE ENERGY RESOURCES ELIGIBILITY GDS TEAM RECOMMENDATION For Consideration By The STATE OF RHODE ISLAND PUBLIC UTILITIES COMMISSION RENEWABLE ENERGY RESOURCES ELIGIBILITY GDS TEAM RECOMMENDATION For Consideration By The STATE OF RHODE ISLAND PUBLIC UTILITIES COMMISSION Date: June 28, 2013 Generation Unit and Contact Information: Unit

More information

EECS Electricity Domain Protocol. for Czech Republic

EECS Electricity Domain Protocol. for Czech Republic EECS Electricity for Czech Republic Prepared by OTE, a.s. Based on EECS Rules Release 7 v5 Release 3 - September 2016 Document Control Version Date Originator Reviewers 1 November 2013 OTE, a.s. Remco

More information