Golpu Pre-Feasibility Study and Reserve Announcement (all figures in United States dollars and in 100% terms unless stated otherwise)

Size: px
Start display at page:

Download "Golpu Pre-Feasibility Study and Reserve Announcement (all figures in United States dollars and in 100% terms unless stated otherwise)"

Transcription

1 NEWS RELEASE ASX: NCM POMSOX: NCM TSX: NM Golpu Pre-Feasibility Study and Reserve Announcement (all figures in United States dollars and in 100% terms unless stated otherwise) Melbourne, Australia, August 29, 2012 Newcrest Mining Limited (Newcrest) announces the results of a Pre-Feasibility Study (PFS) on the Golpu deposit, which forms part of the Wafi-Golpu project located in Morobe Province, Papua New Guinea (PNG). This announcement includes a new Ore Reserve estimate for the Golpu deposit containing 12.4 million ounces of gold and 5.4 million tonnes of copper. This is an increase of 11.0 million ounces of gold and 4.7 million tonnes of copper compared with the previous estimate. The updated Ore Reserve estimate for the Golpu deposit demonstrates the size and potential of this mineral province. The development of Wafi-Golpu aligns with the Company s strategy of investing in large, low cost, long life gold and gold-copper assets. Newcrest and Harmony Mining Company Limited (Harmony) each currently own 50% of Wafi-Golpu through the Wafi-Golpu Joint Venture (WGJV). The PNG Government retains the right to purchase, at any time up to the date of the commencement of mining and at a price equal to the sunk costs as at the date of acquisition, up to a 30% interest in any mineral discovery at Wafi-Golpu. If the PNG Government chooses to take-up the full 30% interest, the interests of Newcrest and Harmony would each be 35%. The PFS technical and commercial analysis undertaken by the project team is complete and sufficient to report a substantially increased Ore Reserve estimate for Golpu. Block caving is the mining method proposed for Golpu, with two lifts (Lifts 1 and 2) to an aggregate depth of approximately 1.45km. Drilling beneath Lift 2 has returned significant high grade intersections and mineralisation remains open at depth below this drilling. The development capital costs and resulting preliminary valuations demonstrate a sound business case that supports the updated Ore Reserves estimate associated with developing Lifts 1 and 2 at Golpu. The Golpu project is not yet in the Feasibility Study phase. Newcrest and Harmony are engaging with key stakeholders (including the PNG and provincial governments, landholders and community representatives) to ensure clear alignment on the objectives and requirements for the project development and key elements of the next phase of work. In addition, capital costs which have been estimated to PFS level are now being closely evaluated to assess what opportunities exist to further refine them given the continuing weaker global economic conditions. It is anticipated that, subject to satisfactory resolution on these outstanding matters, Newcrest and Harmony will progress the Golpu project into the Feasibility Study phase during the first half of calendar Highlights of the Golpu Pre-Feasibility Study Excellent potential for further mineral discoveries in the region. Golpu deposit a large, low cost, long life, block cave mining operation. Updated Golpu Probable Ore Reserve estimate containing 12.4 million ounces of gold, 5.4 million tonnes of copper and 19.7 million ounces of silver. First production forecast by 2019, subject to approvals and Feasibility Study. 1

2 The PFS estimates mine life of 26 years with annual production up to approximately 550 thousand ounces of gold and 330 thousand tonnes of copper. Projected annual production in the PFS averages approximately 400 thousand ounces of gold and 250 thousand tonnes of copper during the initial 15 years of full production (2025 to 2040). First quartile cash costs (whether measured by gold or copper unit cost). Estimated capital cost to first production of US$4.8 billion. This estimate is at PFS level and, with current weaker economic conditions, capital costs are being re-assessed. Only the study and drilling costs for the 2013 financial year (US$120m for Newcrest s share) are committed to date. Total capital expenditure to first production occurs over a six year period. Newcrest expects to be able to fund its share of the capital expenditure from operating cash flow and existing available funds. Highest grade drill intercepts occur at depth indicating good potential for a third mining lift. Further metallurgical test work is expected to optimise the metal recoveries assumed in the PFS. Wafi deposit is in Concept Study, with progress to PFS likely to occur later this calendar year. Based on sensitivity analysis in the PFS, Newcrest has also defined an Enhanced Production Case with a mine life of 28 years and annual production up to approximately 720 thousand ounces of gold and 380 thousand tonnes of copper. Projected annual production in the Enhanced Production Case averages approximately 580 thousand ounces of gold and 300 thousand tonnes of copper during the initial 15 years of full production (2025 to 2040). Mineral Resource Estimate for the Golpu Deposit Tonnes (%) Indicated Resource Inferred Resource Total Resource 1 1, Rounding may cause some computational discrepancies in totals. Tonnes Ore Reserve Estimate for the Golpu Deposit (%) Probable Reserve Newcrest reports its resource and reserve estimates in compliance with the 2004 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (the JORC Code). 2 The Golpu Indicated Mineral Resource estimate, as set out above, is inclusive of the Golpu Probable Ore Reserve estimate as set out above. For the purpose of this release, Mineral Resources and Ore Reserves are reported in 100% terms. Newcrest has a beneficial interest of 50% in these resources and reserves. 2

3 Overview The Wafi-Golpu property, which comprises exploration licences EL1105 and EL440, is located in the Morobe Province of PNG, approximately 65 km west of Lae and is owned by the WGJV. The WGJV is one of three 50/50 unincorporated joint ventures in the Morobe Province of PNG between Newcrest and Harmony. The Wafi-Golpu project, which is located within EL440, comprises multiple porphyry and epithermal gold-copper-silver deposits located on the western flanks of the Timini Range. The Wafi-Golpu project area is hosted within the Wafi Transfer Zone which can be traced for some 25km. Two porphyry copper-gold deposits (Golpu and Nambonga) and one high sulphidation gold-silver epithermal deposit (Wafi) have so far been identified in the Wafi- Golpu project area. The approximate relative locations of Wafi, Golpu and Nambonga are as follows. Plan View of Wafi-Golpu Project Area EL km Zimake Bavaga village EL1105 Nambonga EL440 Golpu Wafi EL1103 Miapilli Porphyry Target Mt Tonn EL1316 EL1612 Northern Zone Nambonga Porphyry Au-Cu Western Zone Golpu Porphyry Cu-Au 721,000mN Diatreme PLAN VIEW 500 m Wafi Epithermal Au 20,000mE 720,000mN local mine grid 3

4 In addition, there are a number of early stage exploration porphyry targets located along the entire length of the Wafi Transfer Zone, including Mt Tonn, Pekumbe, Kesiago and Miapilli. Limited drilling conducted to date has confirmed the presence of porphyry related mineralisation. In the years ahead, exploration will continue in the Wafi Transfer Zone on these and other targets. A plan view of the Wafi Transfer Zone showing the location of the Wafi-Golpu project and principal deposits and targets is as follows: Plan View of Wafi-Golpu Property Showing the Wafi Transfer Zone Bavaga /gold target area Wafi-Golpu property area EL1105 Zenapu EL440 Nambonga Miapilli Wafi Golpu WAFI GOLPU Hekeng Kesiago Pekumbe EL1103 PLAN VIEW Mt Tonn EL km The PFS concluded that the block caving mining method is optimal for extracting ore from the Golpu deposit. Block caving enables the orebody to be mined in two blocks, known as Lifts 1 and Lift 2. As part of the PFS outcomes, revised Indicated Mineral Resource and Probable Ore Reserve estimates are being reported in respect of the Golpu deposit. Initial drilling results for the mineralisation beneath Lift 2 (referred to as Lift 3) have also supported an initial Inferred Mineral Resource estimate for that zone. The PFS does not take into account these Inferred Mineral Resources at Golpu of 190 million tonnes, grading 0.61g/t gold and 0.8% copper and containing 3.7 million ounces of gold and 1.5 million tonnes of copper. Exploration drilling of the Lift 3 area is ongoing and will continue in the medium term. The deposit remains open at depth. A revised resource estimate is also being reported for the Wafi deposit. The Golpu orebody is shown in section on the following page. The Golpu deposit comprises a vertical porphyry intrusion with a thrust fault slightly displacing the upper and lower sections of the deposit. The fault is an important structural feature that influences the location of the boundary between Lifts 1 and 2. 4

5 Schematic Cross Section of the Golpu Porphyry Deposit Section 721,000mN Looking North West East 5,000 mrl Lift 1 Lift mrl Indicated Resource Probable Reserve Conversion 4,500 mrl Indicated 16.6 Moz Au 12.4 Moz Au 7.46 Mt Cu 5.44 Mt Cu 75% 73% 4100 mrl 4,000 mrl Lift 3 Inferred 3850 mrl Inferred Resource Exploration 3.7 Moz Au 250 mrl OPEN 1.52 Mt Cu 20,000 me 20,500 me Licences The WGJV holds two exploration licences, covering a total area of approximately 129 km 2, registered in the name of the WGJV participants Newcrest PNG2 Limited (50%) (a wholly owned Newcrest subsidiary) and Wafi Mining Limited (50%) (a wholly owned Harmony subsidiary). The Wafi-Golpu project is located in Exploration Licence EL440. Under the terms of the Wafi-Golpu exploration licences, the PNG Government has also reserved the right to acquire up to a 30% equity interest in any mineral discovery at Wafi- Golpu. In January 2011, the PNG Government nominated a subsidiary of State-owned Petromin as the entity that would purchase the interest and indicated that it would be likely to exercise that option. The option is able to be exercised at any time up to the commencement of mining but has not been exercised to date. Subject to the project being developed, a royalty of 2% of net smelter revenue would be payable to the PNG Government. Mineral Resource and Ore Reserve Estimates Mineral Resources have been reported for: Golpu (porphyry-related copper and gold) deposit this comprises stockwork vein arrays and disseminated sulphides hosted in altered diorite porphyry intrusions and surrounding metasedimentary rocks. and gold mineralisation is both disseminated and fracture controlled with and without quartz fill. The highest grades are associated with abundant biotite and potassium feldspar alteration, typically rich 5

6 in chalcopyrite, bornite and gold. The epithermal overprint that caps the porphyry system hosts mineralisation that is disseminated and contains abundant pyrite with lesser covellite, enargite and electrum. Wafi (gold-silver epithermal) deposit this comprises disseminated sulphides and quartz vein stockworks in advanced argillic to intermediate argillic altered conglomerate, siltstone and sandstone units. Alteration and mineralisation is hosted in and around diatreme breccia. Nambonga (porphyry-related copper and gold) deposit this comprises stockwork vein arrays and dissemination hosted in altered diorite porphyry intrusions and surrounding metasedimentary rocks. Structurally-controlled quartz-carbonate veins also occur in the Nambonga deposit. The Wafi gold deposit comprises: Oxide and transition mineralisation suitable for conventional milling and cyanidation processing; and Primary mineralisation that requires sulphide oxidation prior to cyanidation to achieve satisfactory gold recoveries. As noted, a Concept Study is presently underway to assess Wafi development options leveraging infrastructure planned for the nearby Golpu deposit. For Wafi, Golpu and Nambonga, Indicated Mineral Resources totalling 22.9 million ounces of contained gold, 7.46 million tonnes of copper and 42.4 million ounces of silver have been defined. A further 5.7 million ounces of contained gold, 1.6 million tonnes of copper and 8.1 million ounces of silver have been defined in Inferred Mineral Resources 3. Mineral Resources estimated for the deposits which comprise the Wafi-Golpu property as at the date of this release are tabulated below. Mineral Resources Estimated for the Wafi, Golpu and Nambonga Deposits Indicated Resource Tonnes (%) Golpu (Porphyry Au/Cu) Wafi (Epithermal Au/Ag) Nambonga (Porphyry Au/Cu) Total Indicated Resource Inferred Resource Golpu (Porphyry Au/Cu) Wafi (Epithermal Au/Ag) Nambonga (Porphyry Au/Cu) Total Inferred Resource Total Mineral Resources 4 1, Rounding may cause some computational discrepancies in totals. 3 Newcrest reports its resource and reserve estimates in compliance with the JORC Code, along with reconciliation of any material differences between the JORC Code and the applicable definitions adopted by the Canadian Institute of Mining, Metallurgy and Petroleum. There are no material differences between the definitions of Measured, Indicated and Inferred Mineral Resources or Proved and Probable Ore Reserves under the JORC Code and the equivalent or corresponding definitions in the CIM Definition Standards. 4 Newcrest reports its resource and reserve estimates in compliance with the JORC Code. 6

7 The Golpu Mineral Resource is reported within a 0.2% Cu shell which reflects the proposed bulk underground mining method of block caving with ore processing by sulphide flotation as proposed by the Golpu PFS. The Wafi Mineral Resource is reported at a cut-off grade of 0.4g/t Au for non-refractory, predominantly oxide material and a cut-off grade of 0.9g/t Au for low recovery, refractory sulphide material. The Mineral Resource estimates were developed using prices of US$1,400/oz gold and US$3.50/lb copper respectively. The Ore Reserve estimate for Golpu as at the date of this release is tabulated below. Ore Reserve Estimate for the Golpu Deposit Tonnes (%) Probable Reserve The Golpu Ore Reserve estimate was developed using prices of US$1,250/oz gold and US$3.10/lb copper. Ore has been classified using a net value, rather than a cut-off grade, to take into account the contributions of both gold and copper. The cut-off value used in this estimate is US$18/t. The Qualified Person commissioned AMC Consultants Pty Ltd (AMC) to conduct a review of the drilling, sampling and analytical processes and associated Quality Assurance / Quality Control procedures that were relied upon to support the new estimates. The Golpu Mineral Resource and Ore Reserve estimates have also been the subject of independent external review by AMC. No material issues have been identified in these reviews and AMC concluded that the estimates have been prepared using accepted industry practice and have been classified and reported in accordance with the JORC Code. Metallurgical Testing and Mineral Processing Metallurgical test work was conducted as part of the PFS. The Golpu deposit consists predominantly of two major mineralisation types, porphyry and metasediments. Within the porphyry, the majority of gold (in excess of 80%) is typically hosted in copper mineralisation and pyrite. associated with copper mineralisation is recoverable however the proportion associated with pyrite is not recovered. Metasediments are characterised by finer grain sizes and clay alteration that deleteriously affects flotation performance and gold recovery. PFS laboratory test work indicates copper recovery from porphyry ores is typically +95%. Metallurgical test work completed during the PFS indicates process recoveries for gold in the range 51% to 66%. Based on this data, metallurgical recoveries were separately estimated for Lift 1 and Lift 2. The PFS assumes an average gold recovery of 61% and an average copper recovery of 93%. 5 The Golpu Indicated Mineral Resource estimate, as set out above, is inclusive of the Golpu Probable Ore Reserve estimate as set out above. For the purpose of this release, Mineral Resources and Ore Reserves are reported in 100% terms. Newcrest has a beneficial interest of 50% in these resources and reserves. 7

8 Metallurgical recoveries are yet to be optimised and future test work programs are planned to be conducted during the Feasibility Study phase of the project. The purpose of this work will be to assess alternative flow sheets and reagent options with the objective of improving gold recovery. In the PFS, mine start-up and development is based on a gradual ramp-up in production. The process plant would be constructed in two stages: initially a 15Mtpa module would be constructed with a second 7Mtpa module added to match the mine ramp-up to achieve a total treatment rate of 22Mtpa of ore. The flow sheet for each concentrator module would comprise: a primary crusher, SAG mill, ball mill and pebble crushing circuit; bulk rougher flotation followed by regrinding and three stages of concentrate cleaning; and concentrate thickening and storage facilities. It is proposed that concentrate would be transferred by slurry pipeline to dewatering, storage and ship loading facilities near Lae. Mining Operations The PFS has proposed the block caving mining method for the Golpu deposit with initial production commencing from Lift 1 whilst ramp development continues down to Lift 2. Lift 1 has an extraction horizon located at 4850mRL 6 (approximately 700m below surface) and a 250m column height. The extraction horizon for Lift 2 is located at 4100mRL (approximately 1.45km below surface) with a 750m column height. In the PFS, production from Lift 1 is scheduled to ramp up to 15Mtpa over a four year period commencing in 2019 with development of Lift 2 undercut and initial production scheduled to commence in Production from Lift 2 would progressively ramp up to reach 22Mtpa in Mining from Lift 1 would be suspended in 2028 with remaining ore from Lift 1 recovered through overdraw of Lift 2. The mineralisation continues below Lift 2, indicating good potential for a third mining lift (Lift 3). The mine development for Golpu Lifts 1 and 2 (and potentially Lift 3) is depicted on the following page. The PFS expressly includes a Lift 3 development scenario as part of its sensitivity analysis of the PFS Base Case. 6 5,000m has been added to the national height datum to establish the local height datum. 8

9 Process Plant Ventilation Shafts Surface Conveyor Portal Surface profile above section Twin Declines Main Access + Conveyor Lift mrl Lift 2 Access + Conveyor Declines Indicated Inferred Exploration OPEN Lift mrl Lift mrl 500 mrl Underground infrastructure is planned to comprise twin declines for access of mobile equipment and ore handling via an inclined conveyor system. Other significant underground infrastructure would include a dewatering system, electrical reticulation and ventilation systems, crushers and conveyor transfer stations. Preconditioning has been included in the mine plan to reduce the impact of the coarse fragmentation on cave propagation and production rate. Infrastructure and Waste Management The Wafi-Golpu project is located in a greenfields location and there is currently minimal effective local infrastructure with respect to power, water and roads trafficable by vehicles larger than small trucks. The main infrastructure requirements for the Wafi-Golpu project are therefore access roads, tailings storage, water management, port facilities and power supply and transmission. A new road access corridor is proposed to be developed to facilitate safe and efficient transport of labour and materials to the site. A number of viable terrestrial tailings storage sites have been identified. These would be assessed during the Feasibility Study. A port facility for the export of concentrates is proposed for the project. A number of alternative port options have been identified in the Lae area which will be further assessed during the Feasibility Study. Effective management of the water generated, collected and used by the project is recognised as being important. The PFS contemplates that the project would re-use water where possible, with water treatment facilities being established and erosion and sediment control structures put in place. The project scope envisages the establishment of a power supply capable of delivering up to 150MW of electrical power to meet the expected peak demand for mining and processing operations, as well as supporting infrastructure. A range of power generation options have been considered including coal steam, gas and hydropower. The power case adopted for the PFS involves establishing 150MW generating capacity for project start-up based on a combination of heavy fuel oil and gas-generated power supply. 9

10 There is a strong possibility of hydro power later in the mine life; this would be expected to be considered in conjunction with the PNG Government and communities during the Feasibility Study. Environmental and Sustainable Development The future development and delivery of the Wafi-Golpu project would be underpinned by a sustainable development approach. As identified in the PFS, the four areas of sustainable development focus comprise people, environment, social environment, and health and safety. A key objective of the people strategy is to maximise local employment. This would be supported by early education, training and development initiatives to maximise local involvement at all levels of the organisation as quickly as possible. Benefits would also flow to communities in the region through local business opportunities and community development programs. The Wafi-Golpu environmental plans and operations would be guided by the WGJV s policy and standards, which are in line with international benchmarks. Environmental baseline studies and risk and impact assessments have been undertaken as part of the PFS and are ongoing. The Wafi-Golpu project has the potential to provide significant benefits to local and regional communities, to PNG s economy and to the various levels and departments of government in PNG. These benefits would include training and employment opportunities, business and community development programs, health and education investments, taxes and royalty payments. There will also be a range of social programs and studies delivered in partnership with local communities. The health, safety and welfare of WGJV employees, contractors, visitors and local communities are of primary importance. The project will continue to develop and sustain appropriate occupational health and safety management systems. Capital Cost and Operating Cost Estimates The estimated initial capital cost to first production for the Golpu development as per the PFS is set out below. Capital Cost Estimate Area PFS Estimate (US$M) Direct Costs Mine 965 Process Plant 650 Infrastructure 560 Power Supply 475 Total Direct Costs 2,650 Indirect Costs Project Management 680 Owners Costs 635 Drilling and Studies 445 Total Indirect Costs 1,760 Contingency 435 Total Capital Cost 4,845 10

11 Newcrest sees potential for capital costs to be optimised from the PFS estimates and capital costs are undergoing further evaluation so as to take account of weaker economic conditions. No major contracts are being committed until this review has been completed. Pre Execution Phase expenditure for the period 1 July 2012 to 31 December 2014 is estimated to represent approximately US$800 million (100% terms). The majority of this spend comprises resource definition drilling and studies (approximately US$250 million), access decline and advanced exploration works (approximately US$200 million) and EPCM and owners costs (approximately US$250 million). In addition to the contingency shown in the capital cost estimate table, growth allowances have been made in each sub-element of Direct and Indirect Costs. After first production, there will be ongoing capital expenditure for the remainder of the mine life, including ongoing mine development to deliver the projected production. The PFS estimates total capital expenditure (including the US$4.8 billion referred to above) for the life of the project to be US$9.8 billion over 32 years. The operating costs per tonne of ore processed for Lift 1 and Lift 2 estimated in the PFS are as follows: Operating Cost Estimate Area PFS Estimate (US$/t processed) (Life-of-Project) Mining 8.64 Processing 7.39 Infrastructure 1.61 G&A (US$100m p.a.) 5.01 Total Operating Cost Project Cases The base case for analysis is the PFS Base Case. Enhanced Production Case Several factors have been identified with the potential to impact production, grade and metal recoveries for a Golpu development beyond that assumed and modelled for the PFS Base Case. Each of these factors is expressly addressed in the PFS as part of its sensitivity analysis of the PFS Base Case. These factors are assessed in an Enhanced Production Case and are summarised as follows: Higher Grade and Recovery in Lift 1: A further three holes recently drilled into the upper section of the Golpu deposit returned high grade intercepts within the Lift 1 envelope. This drilling has revealed that the volume of high grade porphyry has the potential to be greater than that currently modelled in the PFS in the upper section (Lift 1) of the Golpu deposit, supporting higher grades and higher metal recoveries in Lift 1. The Enhanced Production Case assesses the potential impact of these recent results on grade and recovery from Lift 1. 11

12 Optimised Metallurgical Recovery for : Metallurgical recoveries are yet to be optimised. Future test work programs are planned during the Feasibility Study phase of the project with the objective of improving gold recovery and enhancing the metallurgical performance of the concentrator. The Enhanced Production Case assesses the impact of a 10% increase in gold recovery, which is considered to be a conservative target having regard to recovery rates typically achievable. Ramp up and Production Rate: The PFS Base Case adopts moderate assumptions regarding ramp up and sustainable production rates. The Enhanced Production Case assesses the impact of accelerating the ramp up in production and sustaining a 25 million tonne per annum mining and processing rate. Additional Mining Lift: Holes drilled at depth beneath Lift 2 (lower horizon of the current Probable Ore Reserves) have returned the highest grade drill intercepts so far recorded at Golpu. These indicate good potential for a third mining lift (Lift 3) beneath the current base of the Golpu Probable Ore Reserves. The Enhanced Production Case assesses the impact of a third mining lift at Golpu on the basis that development of this zone of mineralisation could have a significant positive effect on the overall production schedule for a Golpu development. In the Enhanced Production Case, grades applied for this potential further production are based on the mean value of the grade of drill intercepts achieved so far in the relevant zone. Project Cases and Outcomes The two cases considered in this release are as follows: Case Description PFS Base Case Enhanced Production Case Lift 1 Probable Ore Reserve Modified Grade Lift 2 Probable Ore Reserve Probable Ore Reserve Lift 3 N/A Depth Extension Mill Throughput 22Mtpa 25Mtpa Ramp Up Standard Accelerated Metallurgical Recovery Un-optimised Optimised (+10% Au) The key outcomes for the PFS Base Case and Enhanced Production Case are as follows: Description Units PFS Base Case Enhanced Production Case Peak Au Production koz pa Peak Cu Production kt pa Annual Au Production 7 koz pa Annual Cu Production 7 kt pa Production Life Yrs Unit Cash Cost 8 US$/oz -2,150-1,900 Unit Production Cost 8 US$/oz -1,200-1,200 Total Initial Capital US$B Total Life of Project Capital (including Initial) US$B For the period Net of by-product credits, copper US$3.10 per pound. 12

13 The forecast gold and copper production profile and mill feed schedule developed for the PFS Base Case is presented as follows: Metal Production and Mill Feed Schedule PFS Base Case The forecast gold and copper production profile and mill feed schedule developed for the Enhanced Production Case is presented below. Metal Production and Mill Feed Schedule Enhanced Production Case 9 1 Note that the Lift 3 Tonnes production profile component in this graph comprises a projected tonnage from the zone beneath Lifts 1 and 2, as well as overdrawn volumes from Lifts 1 and 2. To the extent that the production profile relates to the former, it is noted that this quantity is conceptual only, and there is no certainty that Ore Reserves to support this production will be defined in the future. Accordingly there is no demonstrated economic viability for tonnages other than those produced from Lift 1 and 2. However, based on results and studies to date, Newcrest considers that the projected production from this zone is appropriate and justified as a component of the sensitivity analysis undertaken in relation to the PFS Base Case. 13

14 Forward Looking Statements This release includes forward looking statements. Often, but not always, forward looking statements can generally be identified by the use of forward looking words such as may, will, expect, intend, plan, estimate, anticipate, continue, and guidance, or other similar words and may include, without limitation statements regarding plans, strategies and objectives of management, anticipated production or construction commencement dates and expected costs or production outputs. Forward looking statements in this release include, but are not limited to, the capital and operating cost estimates and economic analyses from the PFS. Forward looking statements inherently involve known and unknown risks, uncertainties and other factors that may cause the company s actual results, performance and achievements to differ materially from any future results, performance or achievements. Relevant factors may include, but are not limited to, changes in commodity prices, foreign exchange fluctuations and general economic conditions, increased costs and demand for production inputs, the speculative nature of exploration and project development, including the risks of obtaining necessary licences and permits and diminishing quantities or grades of reserves, political and social risks, changes to the regulatory framework within which the company operates or may in the future operate, environmental conditions including extreme weather conditions, recruitment and retention of personnel, industrial relations issues and litigation. Forward looking statements are based on the company and its management s good faith assumptions relating to the financial, market, regulatory and other relevant environments that will exist and affect the company s business and operations in the future. The company does not give any assurance that the assumptions on which forward looking statements are based will prove to be correct, or that the company s business or operations will not be affected in any material manner by these or other factors not foreseen or foreseeable by the company or management or beyond the company s control. Although the company attempts and has attempted to identify factors that would cause actual actions, events or results to differ materially from those disclosed in forward looking statements, there may be other factors that could cause actual results, performance, achievements or events not to be anticipated, estimated or intended, and many events are beyond the reasonable control of the company. Accordingly, readers are cautioned not to place undue reliance on forward looking statements. Forward looking statements in this release are given as at the date of issue only. Subject to any continuing obligations under applicable law or any relevant stock exchange listing rules, in providing this information the company does not undertake any obligation to publicly update or revise any of the forward looking statements or to advise of any change in events, conditions or circumstances on which any such statement is based. Ore Reserves and Mineral Resources Reporting Requirements As an Australian company with securities listed on the Australian Securities Exchange (ASX), Newcrest is subject to Australian disclosure requirements and standards, including the requirements of the Corporations Act and the ASX. Investors should note that it is a requirement of the ASX listing rules that the reporting of ore reserves and mineral resources in Australia comply with the 2004 Edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves (the JORC Code) and that Newcrest s ore reserve and mineral resource estimates comply with the JORC Code. As a company listed on the Toronto Stock Exchange (TSX), Newcrest is subject to certain Canadian disclosure requirements and standards, including the requirements of National Instrument Standards of Disclosure for Mineral Projects of the Canadian Securities Administrators (NI ). In accordance with NI , Newcrest reports its ore reserve and mineral resource estimates in compliance with the JORC Code, along with a reconciliation for any material differences between the JORC Code and the applicable definitions adopted by the Canadian Institute of Mining, Metallurgy and Petroleum (CIM Definition Standards). There are no material differences between the definitions of Measured, Indicated and Inferred Mineral Resources, and Proven and Probable Reserves, under the CIM Definition Standards and the equivalent or corresponding definitions in the JORC Code. Competent Persons Information contained in this release that relates to Mineral Resources and Ore Reserves is based upon and accurately reflects reports prepared by the respective Competent Persons as follows: Golpu Mineral Resource, Wafi Mineral Resource and Nambonga Mineral Resource James Francis; Golpu Ore Reserve German Flores. These persons are full-time employees of Newcrest Mining Limited. Each Competent Person consents to the inclusion of the material in the form and context in which it appears. All Competent Persons named are members of The Australasian Institute of Mining and Metallurgy and/or The Australian Institute of Geoscientists and possess relevant experience in relation to the mineralisation being reported on or by them to qualify as Competent Persons as defined by the JORC Code. Qualified Person The information in this release that relates to Mineral Resources, Ore Reserves, Exploration Results and other scientific and technical information is based on information compiled by or under the direction of Colin Moorhead, EGM Minerals for Newcrest Mining Limited, who is a Fellow of The Australasian Institute of Mining and Metallurgy and a full-time employee of Newcrest Mining Limited. Mr Moorhead has sufficient experience which is relevant to the styles of mineralisation and types of deposits under consideration, and to the activity which he is undertaking, to qualify as a Competent Person as defined in the JORC Code and a Qualified Person within the meaning of NI Mr Moorhead consents to and has approved the inclusion in this release of the matters based on this information in the form and context in which it appears, including sampling, analytical and test data underlying the results. For details of exploration reports refer to the Newcrest website at 14

Harmony is positioned to measure, measure up and deliver against its stated strategy

Harmony is positioned to measure, measure up and deliver against its stated strategy Harmony is positioned to measure, measure up and deliver against its stated strategy Johannesburg. Wednesday, 29 August 2012. Harmony Mining Company Limited ( Harmony or the Company ) has positioned itself

More information

Brett Fletcher Executive General Manager PNG & Indonesian Operations

Brett Fletcher Executive General Manager PNG & Indonesian Operations Hidden Valley Brett Fletcher Executive General Manager PNG & Indonesian Operations Disclaimer Forward Looking Statement These materials include forward looking statements. Often, but not always, forward

More information

Hidden Valley PNG s Newest Mine Briefing for Analysts

Hidden Valley PNG s Newest Mine Briefing for Analysts Hidden Valley PNG s Newest Mine Briefing for Analysts 30 March 2011 Harmony Gold Disclosure Statement This presentation contains "forward-looking statements" within the meaning of Section 27A of the Securities

More information

DALGARANGA GOLD PROJECT OPERATIONAL UPDATE: MILL PERFORMANCE TEST COMPLETED AS RAMP UP CONTINUES

DALGARANGA GOLD PROJECT OPERATIONAL UPDATE: MILL PERFORMANCE TEST COMPLETED AS RAMP UP CONTINUES July 25 th 2018 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 DALGARANGA GOLD PROJECT OPERATIONAL UPDATE: MILL PERFORMANCE TEST COMPLETED AS RAMP UP CONTINUES The Process

More information

DALGARANGA GOLD PROJECT - CONSTRUCTION UPDATE 8 MONTHS TO FIRST GOLD

DALGARANGA GOLD PROJECT - CONSTRUCTION UPDATE 8 MONTHS TO FIRST GOLD November 3 rd 2017 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 DALGARANGA GOLD PROJECT - CONSTRUCTION UPDATE 8 MONTHS TO FIRST GOLD Construction work at Gascoyne s 100%

More information

CAPITAL DOWN AT TALA HAMZA

CAPITAL DOWN AT TALA HAMZA CAPITAL DOWN AT TALA HAMZA ASX Shareholder Report 8 April 2009 Enquiries on this Report or the Company Business may be directed to: Dr Kevin Moriarty Executive Chairman + 61 8 8213 1415 + 61 408 173 157

More information

Confidence in Carrapateena project grows

Confidence in Carrapateena project grows 7 NOVEMBER 2016 Confidence in Carrapateena project grows Carrapateena Pre-Feasibility Study released - project competitive with, or better than comparable long-life copper assets globally Project metrics

More information

Market Release Newcrest Mining 15 February 2016

Market Release Newcrest Mining 15 February 2016 Market Release Newcrest Mining 15 February 2016 Lihir Pit Optimisation Project to progress to Feasibility Study stage As previously advised, a project is being undertaken to optimise the integrated life

More information

ASX Release ASX Code: YTC

ASX Release ASX Code: YTC HERA DEFINITIVE FEASIBILITY STUDY TO BE EXPANDED Hera DFS scope to be expanded to include the assessment of mining and treatment of high grade copper ores from the Nymagee Copper Mine together with additional

More information

Aeon Metals Limited HIGHLIGHTS

Aeon Metals Limited HIGHLIGHTS ASX Announcement 15 February 2017 WALFORD CREEK PRELIMINARY ECONOMIC ASSESSMENT Early start up Copper-Zinc-Cobalt project indicated for Vardy Zone 2017 drill program focused on significant mine life extension

More information

Molybdenum- The New Battery Metal 2018

Molybdenum- The New Battery Metal 2018 Molybdenum- The New Battery Metal 2018 Why Hammer Why Molybdenum? 2018 Molybdenum has been one of the best price performing metals traded on the London Metals Exchange (LME) up 62.5% in the first 4 months

More information

DALGARANGA GOLD PROJECT CONSTRUCTION UPDATE LESS THAN 5 MONTHS TO FIRST GOLD

DALGARANGA GOLD PROJECT CONSTRUCTION UPDATE LESS THAN 5 MONTHS TO FIRST GOLD December 8 th 2017 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 DALGARANGA GOLD PROJECT CONSTRUCTION UPDATE LESS THAN 5 MONTHS TO FIRST GOLD Construction at Gascoyne s

More information

Thalanga Project Ore Reserve and Mineral Resource Statement (as at 1 December 2017)

Thalanga Project Ore Reserve and Mineral Resource Statement (as at 1 December 2017) Thalanga Project Ore Reserve and Mineral Resource Statement (as at 1 December 2017) Thalanga Project Ore Reserves Ore Reserves Classification Tonnage (Kt) Cu (%) Pb (%) Zn (%) Au (g/t) Ag (g/t) Zn Eq.

More information

FIRST GOLD FROM DALGARANGA GOLD PROJECT: AHEAD OF SCHEDULE AND UNDER BUDGET

FIRST GOLD FROM DALGARANGA GOLD PROJECT: AHEAD OF SCHEDULE AND UNDER BUDGET May 30 th 2018 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 FIRST GOLD FROM DALGARANGA GOLD PROJECT: AHEAD OF SCHEDULE AND UNDER BUDGET First Gold poured from Dalgaranga

More information

Great Western Scoping Study Update & Onsite Gold Processing

Great Western Scoping Study Update & Onsite Gold Processing ASX RELEASE 10 August 2017 ABN: 45 116 153 514 ASX: TMX Great Western Scoping Study Update & Onsite Gold Processing Terrain Minerals Limited (ASX: TMX) is pleased to provide the following update on its

More information

For personal use only

For personal use only Mutiny makes substantial metallurgical performance gains Forecast copper recoveries increased from 58.5% to 64% in the oxide zone and copper concentrate grade increased from 21.5% Cu to 35% Cu Forecast

More information

Ban Houayxai Project Approved operation to produce over 100,000 ounces of gold and 700,000 ounces of silver per annum

Ban Houayxai Project Approved operation to produce over 100,000 ounces of gold and 700,000 ounces of silver per annum ASX ANNOUNCEMENT 29 March 2010 Ban Houayxai Project Approved operation to produce over 100,000 ounces of gold and 700,000 ounces of silver per annum PanAust is pleased to announce that the Board of Directors

More information

For personal use only

For personal use only Positive Scoping Study: Aphrodite Gold Project 9 February 2012 Company Announcements Office Australian Securities Exchange Limited Positive Scoping Study for Aphrodite Gold Project Potential to Become

More information

Azure Minerals Ltd ASX Code:

Azure Minerals Ltd ASX Code: Azure Minerals Ltd ASX Code: AZS @AzureMinerals www.azureminerals.com.au Tony Rovira Managing Director Azure Minerals Ltd Objective To be a low cost, high margin copper producer Strategy Developing our

More information

Thalanga Operations Ore Reserve and Mineral Resource Statement

Thalanga Operations Ore Reserve and Mineral Resource Statement Thalanga Operations Ore Reserve and Mineral Resource Statement Ore Reserves Classification Tonnage (Kt) Cu (%) Pb (%) Zn (%) Au (g/t) Ag (g/t) Zn Eq. (%) West 45 (1) Proved 101 0.3 2.0 4.6 0.3 38 8.4 Probable

More information

Hot Chili and CMP sign Non-Binding Letter of Intent on Second Copper Project

Hot Chili and CMP sign Non-Binding Letter of Intent on Second Copper Project ASX ANNOUNCEMENT 16th October 2015 Hot Chili and CMP sign Non-Binding Letter of Intent on Second Copper Project Hot Chili and its partner in the Productora Project, Compañía Minera del Pacífico S.A. (CMP)

More information

Financial results for the 6 months to 30 June 2008

Financial results for the 6 months to 30 June 2008 28 August 2008 Financial results for the 6 months to 30 June 2008 During the June half 2008, PanAust emerged as a significant producer of copper gold concentrate in Southeast Asia. Activities during the

More information

For personal use only

For personal use only 7 August 2012 ASX: PAN Gidgee Gold Project Scoping Study Key Highlights Gold Production estimated at 606,000oz of gold over an initial seven years, average annual production of 87,000oz Operating Cash

More information

UPDATE TO BROKEN HILL MINERAL RESOURCES AND ORE RESERVES

UPDATE TO BROKEN HILL MINERAL RESOURCES AND ORE RESERVES 7 November 2008 UPDATE TO BROKEN HILL MINERAL RESOURCES AND ORE RESERVES Highlights Broken Hill Ore Reserves increase life of mine to 9 years at conservative price assumptions Substantial Resource base

More information

For personal use only

For personal use only RDM ASX Announcement 23 October 2013 ACN 103 367 684 ASX ANNOUNCEMENT 8 MARCH 2016 ASX Code: RDM Red Metal Limited is a minerals exploration company focused on the exploration, evaluation and development

More information

For personal use only

For personal use only ACN 097 088 689 01 DEFINITIVE FEASIBILITY STUDY SUPPORTS A MAJOR EXPANSION OF THE SYAMA GOLD MINE Definitive Feasibility Study completed for multifaceted expansion of Syama operation confirms its technical

More information

ASX ANNOUNCEMENT 12 MAY 2016

ASX ANNOUNCEMENT 12 MAY 2016 ASX ANNOUNCEMENT 12 MAY 2016 FÄBOLIDEN METALLURGICAL TEST WORK IMPROVES RECOVERY LEVELS Dragon Mining Limited (ASX:DRA) ( Dragon Mining or the Company ) is pleased to announce that the second phase of

More information

Drilling, metallurgical test work and a new resource model add 21% to oxide gold reserves

Drilling, metallurgical test work and a new resource model add 21% to oxide gold reserves LA ARENA GOLD OXIDE RESERVES INCREASED TO 1.28MM OZ AT AU PRICE OF $1,200 COMPLETION OF THE PRE-FEASIBILITY STUDY FOR THE PHASE II SULPHIDE Cu-Au PROJECT Drilling, metallurgical test work and a new resource

More information

T S X : R M X N Y S E. M K T : R B Y. Rubicon Begins Stockpiling Mill Feed for Projected Production Commencing Mid-2015

T S X : R M X N Y S E. M K T : R B Y. Rubicon Begins Stockpiling Mill Feed for Projected Production Commencing Mid-2015 T S X : R M X N Y S E. M K T : R B Y News Release D e c e m b e r 1 8, 2014 Rubicon Begins Stockpiling Mill Feed for Projected Production Commencing Mid-2015 TORONTO, Ontario Rubicon Minerals Corporation

More information

Underground Ore Reserve growth at Prominent Hill extends mine life to 2030

Underground Ore Reserve growth at Prominent Hill extends mine life to 2030 12 NOVEMBER 2018 Underground Ore Reserve growth at Prominent Hill extends mine life to 2030 Prominent Hill underground Ore Reserve increased to 40Mt @ 1.7% copper equivalent i with a 50% increase in Proved

More information

For personal use only

For personal use only ASX Announcement 19 December 2014 BOARD OF DIRECTORS Paul Murphy (Non-Executive Chairman) Bryan Dixon (Managing Director) Alan Thom (Executive Director) Greg Miles (Non-Executive Director) ASX CODE BLK

More information

OPERATIONAL UPDATE AND 2019 PRODUCTION GUIDANCE

OPERATIONAL UPDATE AND 2019 PRODUCTION GUIDANCE December 24 th 2018 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 OPERATIONAL UPDATE AND 2019 PRODUCTION GUIDANCE Dalgaranga Operational Update: The project remains Lost

More information

For personal use only

For personal use only December 24 th 2018 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 OPERATIONAL UPDATE AND 2019 PRODUCTION GUIDANCE Dalgaranga Operational Update: The project remains Lost

More information

Investor Update. June 2016

Investor Update. June 2016 Investor Update June 2016 Next Steps: 2015 Work Programme Is this the time?! 500%? Introducing Impact Minerals (ASX:IPT) Capital Structure Listed on ASX November 2006 Shares on Issue Options/Warrants Convertible

More information

For personal use only

For personal use only ABN 79 106 879 690 30 August 2016 The Manager Companies ASX Limited 20 Bridge Street Sydney NSW 2000 (11 pages by email) Updated Internal Scoping Study Delivers Positive Results (ASX: AUK) The Directors

More information

ASX ANNOUNCEMENT. CMP to Purchase Additional Stake in Productora for US$1.5 Million. Sprott Loan to be Reduced and Extended by 12 Months

ASX ANNOUNCEMENT. CMP to Purchase Additional Stake in Productora for US$1.5 Million. Sprott Loan to be Reduced and Extended by 12 Months ASX ANNOUNCEMENT Wednesday 18 th May 2016 CMP to Purchase Additional Stake in Productora for US$1.5 Million Sprott Loan to be Reduced and Extended by 12 Months Hot Chili Limited (ASX Code: HCH) is pleased

More information

DALGARANGA PRE-FEASIBILITY UPDATE

DALGARANGA PRE-FEASIBILITY UPDATE January 19th, 2016 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 DALGARANGA PRE-FEASIBILITY UPDATE PFS Pit optimisations indicate a production target far larger than anticipated

More information

For personal use only

For personal use only January 19th, 2016 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 DALGARANGA PRE-FEASIBILITY UPDATE PFS Pit optimisations indicate a production target far larger than anticipated

More information

Koka Project Stands to be a Highly Profitable Gold Mine: Scoping Study

Koka Project Stands to be a Highly Profitable Gold Mine: Scoping Study Koka Project Stands to be a Highly Profitable Gold Mine: Scoping Study Chalice Gold Mines Limited ABN 47 116 648 956 30 October 2009 Highlights Scoping Study finds Koka deposit at the Zara Project in Eritrea

More information

Brett Fletcher Executive General Manager PNG & Indonesian Operations

Brett Fletcher Executive General Manager PNG & Indonesian Operations Lihir Brett Fletcher Executive General Manager PNG & Indonesian Operations Disclaimer Forward Looking Statement These materials include forward looking statements. Often, but not always, forward looking

More information

For personal use only

For personal use only ASX ANNOUNCEMENT / MEDIA RELEASE ASX: ABU 30th September, 2014 ABM s Development Plan & Production Guidance for Old Pirate High-Grade Gold Deposit Highlights: 50,000 to 60,000 ounces of gold production

More information

For personal use only

For personal use only ASX Release 20 March 2012 PANTON REVIEW STUDY RESULTS (ASX:PLA) is pleased to advise that the results from the recently completed Panton Review Study ( PRS ) showed that the Project could achieve and Internal

More information

TEMBANG PRE-FEASIBILITY STUDY DELIVERS POSITIVE OUTCOME

TEMBANG PRE-FEASIBILITY STUDY DELIVERS POSITIVE OUTCOME ASX ANNOUNCEMENT 23 February 2012 (8 pages by email) TEMBANG PRE-FEASIBILITY STUDY DELIVERS POSITIVE OUTCOME Sumatra Copper & Gold plc ( Sumatra or the Company ) is pleased to announce that the Prefeasibility

More information

For personal use only

For personal use only ASX ANNOUNCEMENT / MEDIA RELEASE ASX: ABU 5th September, 2012 Old Pirate Metallurgical Test-Work delivers Exceptional Gold Recovery (up to 97.3%) from Two Different Gravity Methods ABM Resources NL ( ABM

More information

ASX and Media Release: 20 September 2016 ASX Code: WRM Initial mining review demonstrates potential upside at Mt Carrington

ASX and Media Release: 20 September 2016 ASX Code: WRM Initial mining review demonstrates potential upside at Mt Carrington ASX and Media Release: 20 September 2016 ASX Code: WRM Initial mining review demonstrates potential upside at Mt Carrington ASX Code: WRM Issued Securities Shares: 441.3 million Options: 100.5 million

More information

For personal use only

For personal use only 4 AUGUST 2017 TROPICANA GOLD MINE UPDATE Independence Group NL ( IGO or the Company ) (ASX: IGO) is pleased to provide a progress report on initiatives to further maximise and optimise the Tropicana Gold

More information

INV METALS ANNOUNCES ROBUST PRELIMINARY FEASIBILITY STUDY AT LOMA LARGA

INV METALS ANNOUNCES ROBUST PRELIMINARY FEASIBILITY STUDY AT LOMA LARGA INV METALS ANNOUNCES ROBUST PRELIMINARY FEASIBILITY STUDY AT LOMA LARGA TORONTO, ON July 14, 2016 INV Metals Inc. ( INV Metals or the Company ) (TSX:INV) is pleased to announce the positive results of

More information

Second drill rig to accelerate major drilling program at Productora

Second drill rig to accelerate major drilling program at Productora DRAFT ASX ANNOUNCEMENT Thursday 11th September 2014 Second drill rig to accelerate major drilling program at Productora Expanded resource-reserve base will underpin completion of Productora Pre-feasibility

More information

Forward Looking Statement

Forward Looking Statement Olympias Forward Looking Statement Certain of the statements made in this Presentation may contain forward-looking statements or information within the meaning of the United States Private Securities Litigation

More information

MEDIA RELEASE OCEANAGOLD ANNOUNCES COMMENCEMENT OF CONSTRUCTION AT THE DIDIPIO PROJECT IN THE PHILIPPINES

MEDIA RELEASE OCEANAGOLD ANNOUNCES COMMENCEMENT OF CONSTRUCTION AT THE DIDIPIO PROJECT IN THE PHILIPPINES 15 June 2011 MEDIA RELEASE OCEANAGOLD ANNOUNCES COMMENCEMENT OF CONSTRUCTION AT THE DIDIPIO PROJECT IN THE PHILIPPINES (MELBOURNE) OceanaGold Corporation (ASX: OGC, TSX: OGC, NZX: OGC) ( the Company )

More information

Garden Well Gold Deposit. Reserve Increases to 1.66 Million Ounces

Garden Well Gold Deposit. Reserve Increases to 1.66 Million Ounces ABN 28 009 174 761 31 March 2011 Manager Announcements Company Announcements Office Australian Securities Exchange Limited Level 4, 20 Bridge Street Sydney NSW 2000 www.regisresources.com Level 1 1 Alvan

More information

DALGARANGA GOLD PROJECT CONSTRUCTION & OPERATIONAL UPDATE 2 MONTHS TO FIRST GOLD

DALGARANGA GOLD PROJECT CONSTRUCTION & OPERATIONAL UPDATE 2 MONTHS TO FIRST GOLD March 19 th 2018 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 DALGARANGA GOLD PROJECT CONSTRUCTION & OPERATIONAL UPDATE 2 MONTHS TO FIRST GOLD Process plant construction

More information

HORSESHOE LIGHTS PROJECT ASX/MEDIA ANNOUNCEMENT

HORSESHOE LIGHTS PROJECT ASX/MEDIA ANNOUNCEMENT OXIDE COPPER STUDY UNDERWAY AT 8 HORSESHOE LIGHTS PROJECT ASX/MEDIA ANNOUNCEMENT 20 AUGUST 2015 ASX Code: HOR Management Mr Neil Marston Managing Director/Company Secretary Mr Michael Fotios Non-Executive

More information

FIRST GOLD ORE DISPATCHED FROM ULYSSES

FIRST GOLD ORE DISPATCHED FROM ULYSSES Genesis Minerals Limited (ASX: GMD) ASX Announcement 14 November 2016 FIRST GOLD ORE DISPATCHED FROM ULYSSES Genesis poised for first cash-flow as first parcel of ore departs for Paddington gold plant

More information

Papua New Guinea Mineral resources and ore reserves

Papua New Guinea Mineral resources and ore reserves Harmony Annual Report 2009 139 Papua New Guinea and ore reserves Geology: Papua New Guinea (PNG) lies at the northern end of the Australian Plate and has three major components: a continental cratonic

More information

PRELIMINARY OXIDE HEAP LEACH TESTWORK DELIVERS EXCELLENT RESULTS AT THE SOUTH HOUNDÉ PROJECT

PRELIMINARY OXIDE HEAP LEACH TESTWORK DELIVERS EXCELLENT RESULTS AT THE SOUTH HOUNDÉ PROJECT NEWS RELEASE APRIL 7, 2014 PRELIMINARY OXIDE HEAP LEACH TESTWORK DELIVERS EXCELLENT RESULTS AT THE SOUTH HOUNDÉ PROJECT VANCOUVER, CANADA. Sarama Resources Ltd. ( Sarama or the Company ) is pleased to

More information

Market Release 19 March 2018

Market Release 19 March 2018 Market Release 19 March 2018 Updated Wafi-Golpu Feasibility Study Newcrest Mining Limited (Newcrest) has today released an updated Wafi-Golpu Feasibility Study prepared by the Wafi-Golpu Joint Venture

More information

STUDIES CONFIRM COMBINED WILUNA URANIUM PROJECT IMPROVEMENTS

STUDIES CONFIRM COMBINED WILUNA URANIUM PROJECT IMPROVEMENTS ASX RELEASE 30th January 2014 STUDIES CONFIRM COMBINED WILUNA URANIUM PROJECT IMPROVEMENTS Uranium developer Toro Energy Limited (ASX: TOE) (Toro) today announced the completion of an independent Mining

More information

Australia s leading explorer in Mexico

Australia s leading explorer in Mexico Australia s leading explorer in Mexico ASX: AZS @AzureMinerals www.azureminerals.com.au Tony Rovira Managing Director & CEO VRIC January 2017 Corporate Overview KEY STATISTICS ASX Code Share Price AZS

More information

Nymagee Scoping Study

Nymagee Scoping Study 2 May 2017 Nymagee Scoping Study Aurelia Metals Limited ( AMI or the Company ) is pleased to announce the results of the Nymagee Scoping Study ( Study ) were positive and justify the Company committing

More information

Gruyere Project - Updated Mine Plan

Gruyere Project - Updated Mine Plan ASX Announcement 6 December 2018 Gruyere Project - Updated Mine Plan CONTACT DETAILS Highlights Gruyere confirmed as a global Tier 1 gold mine 1 with a long life and forecast high margins Life of mine

More information

2018 Resources and Reserves

2018 Resources and Reserves 2018 Resources and Reserves Aeris Resources Limited has updated its Mineral Resource and Ore Reserves estimates for its Tritton Copper Operations as at 30 June 2018. reported Measured and Indicated Mineral

More information

SARACEN MINERAL HOLDINGS LTD

SARACEN MINERAL HOLDINGS LTD Saracen Mineral Holdings Limited Australian Gold Producer ASX:SAR SARACEN MINERAL HOLDINGS LTD Guido Staltari, Executive Chairman Raleigh Finlayson, Chief Operating Officer Diggers n Dealers Conference

More information

Bald Hill Delivers Excellent Metallurgical Test Work Results

Bald Hill Delivers Excellent Metallurgical Test Work Results 6 September 2017 Bald Hill Delivers Excellent Metallurgical Test Work Results Tawana Resources NL (TAW:ASX) (Tawana) and Alliance Mineral Assets Limited (SGX:AMA) (AMAL) are pleased to announce encouraging

More information

BROKEN HILL MINERAL RESOURCES AND ORE RESERVES UPDATE

BROKEN HILL MINERAL RESOURCES AND ORE RESERVES UPDATE 28 December 2011 BROKEN HILL MINERAL RESOURCES AND ORE RESERVES UPDATE Highlights The Ore Reserve has been established and a new Life of Mine plan for Southern Operations has been developed with economic

More information

Q Preliminary Production Results, 2018 Production Guidance and Mineral Reserve and Resource Update

Q Preliminary Production Results, 2018 Production Guidance and Mineral Reserve and Resource Update For immediate release 10 January 2018 Centamin plc ("Centamin" or "the Company") (LSE:CEY, TSX:CEE) Q4 2017 Preliminary Production Results, 2018 Production Guidance and Mineral Reserve and Resource Update

More information

METATES UPDATED PEA INDICATES EXCELLENT PROJECT ECONOMICS 26,000 METRE DRILL PROGRAM UNDERWAY

METATES UPDATED PEA INDICATES EXCELLENT PROJECT ECONOMICS 26,000 METRE DRILL PROGRAM UNDERWAY March 7, 2011 Symbol: TSX V-CKG NR1-2011 METATES UPDATED PEA INDICATES EXCELLENT PROJECT ECONOMICS 26,000 METRE DRILL PROGRAM UNDERWAY Chesapeake Gold Corp. ( Chesapeake ) is pleased to announce the results

More information

For personal use only

For personal use only 9 December 2011 Bass Metals Confirms Commercial Robustness of Hellyer Gold Project (HGP) HIGHLIGHTS: A study on tailings treatment options confirms HGP as a robust project utilising the Albion Process

More information

For personal use only

For personal use only ASX RELEASE Sorby Hills Silver Lead Project Major Milestone Achieved with Environmental Approval As announced on 3 April, the WA Minister for Environment has approved the development of the Sorby Hills

More information

T S X : R M X N Y S E. M K T : R B Y

T S X : R M X N Y S E. M K T : R B Y T S X : R M X N Y S E. M K T : R B Y News Release A p r i l 1 4, 2015 Rubicon s Phoenix Gold Project Commences Mill Commissioning and Remains on Schedule for Mid-2015 Projected Initial Production TORONTO,

More information

CHINA MINING Conference Tianjin October 2014

CHINA MINING Conference Tianjin October 2014 CHINA MINING Conference Tianjin October 2014 Forward Looking Statements These materials include forward looking statements. Often, but not always, forward looking statements can generally be identified

More information

SIGNIFICANT INCREASE IN KANMANTOO LIFE OF MINE AND TARGETED PROCESSING THROUGHPUT INCREASE

SIGNIFICANT INCREASE IN KANMANTOO LIFE OF MINE AND TARGETED PROCESSING THROUGHPUT INCREASE Wednesday, 20 February 2013 SIGNIFICANT INCREASE IN KANMANTOO LIFE OF MINE AND TARGETED PROCESSING THROUGHPUT INCREASE The Kanmantoo Copper Mine s Indicative Life of Mine (LOM) anticipated to extend to

More information

DALGARANGA GOLD PROJECT DEVELOPMENT UPDATE

DALGARANGA GOLD PROJECT DEVELOPMENT UPDATE August 7 th 2017 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 DALGARANGA GOLD PROJECT DEVELOPMENT UPDATE Credit approved commitment letters received from a number of tier

More information

(TSX: AUQ) (NYSE: AUQ)

(TSX: AUQ) (NYSE: AUQ) AuRico Gold Announces a New Gold-Copper Porphyry Discovery at the Kemess Project; Initial Resource Estimate Expected in Early 2015 Hole KH-14-04 intersects 768 metres of 0.442 g/t Au and 0.392% Cu Toronto:

More information

6 June 2017 Georgian Mining Corporation Further Drill Results from Kvemo Bolnisi East s Gold Zone 2 Target

6 June 2017 Georgian Mining Corporation Further Drill Results from Kvemo Bolnisi East s Gold Zone 2 Target 6 June 2017 Georgian Mining Corporation Further Drill Results from Kvemo Bolnisi East s Gold Zone 2 Target Georgian Mining Corporation ('GEO') is pleased to announce the final set of drill results from

More information

PILOT TEST WORK TRIGGERS FINAL TRANCHE OF TREMONT FINANCING

PILOT TEST WORK TRIGGERS FINAL TRANCHE OF TREMONT FINANCING 8 October 2015 ASX Release ASX Code: CXX Highlights PILOT TEST WORK TRIGGERS FINAL TRANCHE OF TREMONT FINANCING Tremont has paid the final tranche of US$5 million Integrated pilot plant testing confirms

More information

Kingsgate 2012 Mineral Resources & Ore Reserves

Kingsgate 2012 Mineral Resources & Ore Reserves 16 October 2012 Via ASX Online Manager Company Announcements Office Australian Securities Exchange Kingsgate 2012 Mineral Resources & Ore Reserves Kingsgate Consolidated Limited (ASX: KCN) increased its

More information

Gold Producer and Developer Corporate Presentation September 2015

Gold Producer and Developer Corporate Presentation September 2015 Kingsgate Consolidated Limited Gold Producer and Developer Corporate Presentation September 2015 Disclaimer Forward Looking Statements: These materials include forward looking statements. Forward looking

More information

TINKA RESOURCES LIMITED

TINKA RESOURCES LIMITED TINKA RESOURCES LIMITED #1305 1090 WEST GEORGIA STREET VANCOUVER, B.C. V6E 3V7 Tel: (604) 685 9316 Fax (604) 683 1585 Website: www.tinkaresources.com TSXV & BVL: TK OTCPK: TKRFF NEWS RELEASE November 8,

More information

NEWS RELEASE Trading Symbol: TSX: SVM

NEWS RELEASE Trading Symbol: TSX: SVM NEWS RELEASE Trading Symbol: TSX: SVM SILVERCORP REPORTS Q3 FISCAL 2016 FINANCIAL AND OPERATING RESULTS AND FISCAL 2017 GUIDANCE ISSUED VANCOUVER, British Columbia February 5, 2016 Silvercorp Metals Inc.

More information

SILVERCORP REPORTS Q3 FISCAL 2016 FINANCIAL AND OPERATING RESULTS AND FISCAL 2017 GUIDANCE ISSUED

SILVERCORP REPORTS Q3 FISCAL 2016 FINANCIAL AND OPERATING RESULTS AND FISCAL 2017 GUIDANCE ISSUED NEWS RELEASE Trading Symbol: TSX: SVM SILVERCORP REPORTS Q3 FISCAL 2016 FINANCIAL AND OPERATING RESULTS AND FISCAL 2017 GUIDANCE ISSUED VANCOUVER, British Columbia February 5, 2016 Silvercorp Metals Inc.

More information

Regulus Announces that Preliminary Metallurgical Results Indicate Good Gold Recovery is Achievable at the Rio Grande Cu-Au-Ag Project, Argentina

Regulus Announces that Preliminary Metallurgical Results Indicate Good Gold Recovery is Achievable at the Rio Grande Cu-Au-Ag Project, Argentina Regulus Announces that Preliminary Metallurgical Results Indicate Good Gold Recovery is Achievable at the Rio Grande Cu-Au-Ag Project, Argentina December 6, 2011, (Waterdown, Ontario) Regulus Resources

More information

930 West 1 st Street, Suite 202, North Vancouver, BC V7P 3N4. Tel: (604) Tel:

930 West 1 st Street, Suite 202, North Vancouver, BC V7P 3N4. Tel: (604) Tel: 930 West 1 st Street, Suite 202, North Vancouver, BC V7P 3N4 Tel: (604) 998-4175 Tel: 1888 648-4218 www.sabinagoldsilver.com April 22, 2014 SBB NR 14-05 SBB TSX SABINA GOLD & SILVER REPORTS SIGNIFICANT

More information

Orezone Announces Updated Feasibility Study to Incorporate a Phase II High-Grade Sulphide Expansion

Orezone Announces Updated Feasibility Study to Incorporate a Phase II High-Grade Sulphide Expansion Orezone Announces Updated Feasibility Study to Incorporate a Phase II High-Grade Sulphide Expansion November 19, 2018, Orezone Gold Corporation (TSXV: ORE) ( Orezone or the Company ) is pleased to provide

More information

Nevada Copper Hits with 19 Mineralized Holes: Enhances Potential of Open Pit Economics

Nevada Copper Hits with 19 Mineralized Holes: Enhances Potential of Open Pit Economics NEWS RELEASE TSX: NCU Nevada Copper Hits with 19 Mineralized Holes: Enhances Potential of Open Pit Economics September 24, 2018 - Nevada Copper Corp. (TSX: NCU) ("Nevada Copper" or the Company ) is pleased

More information

For personal use only

For personal use only 2 May 2018 ASX Announcement METALLURGICAL TESTWORK CONFIRMS WILUNA TRANSITIONAL RESERVES AMENABLE TO PROCESSING THROUGH THE EXISTING WILUNA CIL PLANT Highlights Expansion PFS published in Aug 17 includes

More information

EXCO S PROJECT PIPELINE

EXCO S PROJECT PIPELINE EXCO S PROJECT PIPELINE INVESTOR UPDATE EXCO RESOURCES N.L. MAY 2010 Presented by Michael Anderson Managing Director DISCLAIMER This presentation contains forward looking statements that are subject to

More information

QUARTERLY REPORT 30 September 2008 Twin Hills Silver Mine

QUARTERLY REPORT 30 September 2008 Twin Hills Silver Mine MACMIN SILVER LTD (A.B.N. 53 056 776 160) QUARTERLY REPORT 30 September Twin Hills Silver Mine SUMMARY Mining Silver leaching and powder production decreased slightly with approximately 109,000oz of silver

More information

N E W S R E L E A S E

N E W S R E L E A S E ASM: TSX/NYSE American Avino Silver & Gold Mines Ltd. T (604) 682 3701 Suite 900-570 Granville Street F (604) 682 3600 Vancouver, BC V6C 3P1 www.avino.com February 21, 2018 N E W S R E L E A S E AVINO

More information

TEMBANG PROJECT OPTIMISATION

TEMBANG PROJECT OPTIMISATION ASX ANNOUNCEMENT 16 April 2012 (13 pages by email) TEMBANG PROJECT OPTIMISATION Sumatra Copper & Gold plc ('Sumatra' or 'the Company') is pleased to confirm Optimisation Studies for its wholly-owned Tembang

More information

September 2018 Quarterly Report Presentation and Webcast 25 October 2018

September 2018 Quarterly Report Presentation and Webcast 25 October 2018 September 2018 Quarterly Report Presentation and Webcast 25 October 2018 Access this presentation at: http://webcasting.brrmedia.com/broadcast/5bb2ad1abfd72969440cb5a0 or http://www.sandfire.com.au 1 Important

More information

Sierra Metals Exploration Update Call

Sierra Metals Exploration Update Call Sierra Metals Exploration Update Call October 5, 2017 TSX SMT NYSE AMERICAN: SMTS BVL SMT Forward Looking Statements Disclaimer Certain statements in this presentation constitute forward-looking information

More information

STRONG PRE-FEASABILITY STUDY SUPPORTS 1.5 MTPA URQUHART BAUXITE DEVELOPMENT

STRONG PRE-FEASABILITY STUDY SUPPORTS 1.5 MTPA URQUHART BAUXITE DEVELOPMENT ASX RELEASE 30 DECEMBER 2016 STRONG PRE-FEASABILITY STUDY SUPPORTS 1.5 MTPA URQUHART BAUXITE DEVELOPMENT HIGHLIGHTS Independent Pre-Feasibility Study (PFS) supports development of the Urquhart Bauxite

More information

AVALON SIGNS HOA WITH HANNANS TO ACQUIRE DISCOVERY ZONE COPPER-IRON DEPOSIT FOR A$4M

AVALON SIGNS HOA WITH HANNANS TO ACQUIRE DISCOVERY ZONE COPPER-IRON DEPOSIT FOR A$4M 6 May 2013 AVALON SIGNS HOA WITH HANNANS TO ACQUIRE DISCOVERY ZONE COPPER-IRON DEPOSIT FOR A$4M Highlights Following continued negotiations Avalon and Hannans have signed a Heads of Agreement for Avalon

More information

For personal use only

For personal use only 28 November 2017 Corporate Details Ordinary Shares: 780,917,069 Market Capitalisation: ~$156 million Cash and bullion at 30 September 2017: ~$20.1 million Debt: NIL ASX Code: MOY Board of Directors Greg

More information

AVINO ANNOUNCES FOURTH QUARTER AND FULL YEAR 2017 PRODUCTION RESULTS FROM ITS AVINO PROPERTY

AVINO ANNOUNCES FOURTH QUARTER AND FULL YEAR 2017 PRODUCTION RESULTS FROM ITS AVINO PROPERTY ASM: TSX/NYSE American Avino Silver & Gold Mines Ltd. T (604 682 3701 Suite 900-570 Granville Street F (604) 682 3600 Vancouver, BC V6C 3P1 avino.com January 16, 2018 AVINO ANNOUNCES FOURTH QUARTER AND

More information

Frieda River Copper-Gold Project feasibility study completed

Frieda River Copper-Gold Project feasibility study completed PANAUST LIMITED ABN 17 011 065 160 Level 1, 15 James Street, Fortitude Valley, Brisbane QLD 4006 Australia PO Box 2297, Fortitude Valley Business Centre QLD 4006 T: +61 7 3117 2000 F: +61 7 3846 4899 E:

More information

AGM - Lorena Gold Project

AGM - Lorena Gold Project AGM - Lorena Gold Project For personal use onlynovember 2015 Disclaimer and Competent Person Statement Disclaimer This presentation may contain forward looking statements that are subject to risk factors

More information

ACTIVITIES REPORT FOR THE QUARTER ENDED 31 DECEMBER 2018

ACTIVITIES REPORT FOR THE QUARTER ENDED 31 DECEMBER 2018 ASX ANNOUNCEMENT 31 JANUARY 2019 ACTIVITIES REPORT FOR THE QUARTER ENDED 31 DECEMBER 2018 OVERVIEW Horseshoe Metals Limited (ASX: HOR) ( Horseshoe or the Company ), through its wholly owned subsidiary,

More information

5 th Asian Bauxite & Alumina Conference

5 th Asian Bauxite & Alumina Conference 5 th Asian Bauxite & Alumina Conference October 2015 Bauxite Hills Project Deliberate Focus ASX : MMI CORPORATE SNAPSHOT Shareholders 0.140 0.120 MMI Share Price (A$) Other 47% NetWealth Investments 5%

More information