For personal use only

Size: px
Start display at page:

Download "For personal use only"

Transcription

1 Positive Scoping Study: Aphrodite Gold Project 9 February 2012 Company Announcements Office Australian Securities Exchange Limited Positive Scoping Study for Aphrodite Gold Project Potential to Become a Significant Cost Competitive Producer Independent Consultants Recommend Commencement of PFS Aphrodite Gold Ltd s (ASX:AQQ) market capitalisation was around $8M prior to the release of this Scoping Study. In my opinion, the results of the Study demonstrate significant potential for growth said Aphrodite s Technical Director, Leon Reisgys. HIGHLIGHTS Positive Scoping Study completed by independent consultants Potential to become a significant cost competitive producer Technical and economic assessments justify proceeding with pre feasibility study (PFS) A combined open pit and underground mining operation over a project life of 9 years Gold production over life of project estimated at 550,000 oz 1Mtpa processing plant on site to treat all ore types to produce gold doré Nominal plant throughput of 750,000 tpa at an average grade of 3.8g/t gold

2 Peak gold production of 84,000 oz per annum for Years 2 to 6 Pressure oxidation method preferred for treatment of refractory ore Anticipated + 90% gold recoveries for all ore types Potential to increase gold production and project life with expansion in resources - a revised resource estimate expected end Q incorporating all 2011 drill results with further drilling planned Estimated average cash cost of $756/oz gold Significant reduction in costs possible should the plant be run at a higher throughput NPV (8%DF) estimated at $129M with IRR 25% at current gold price of around $1650/oz. NPV (8%DF) estimated at $51M with IRR 15% at $1450/oz gold price Significant upside if gold price continues its long term upward trajectory Project close to key infrastructure including road, rail, power and housing Possibility for toll treating other local deposits Introduction In September 2011 Aphrodite Gold commissioned a Scoping Study to determine a preferred mining and processing scenario for economically exploiting the Aphrodite Gold Deposit located 65 km north of Kalgoorlie, Western Australia. Two internationally recognised consultancy firms were selected to complete the Study. The mining related part of the Study, including estimates for capital and operating costs, and the overall economic analysis for the Project was completed by Tetra Tech Australia Pty Ltd (Tetra Tech). Tetra Tech is a leading engineering group with offices worldwide (including Perth, Western Australia) servicing mining, environmental and energy projects. Mineral Engineering Technical Services Pty Ltd (METS) was engaged to determine the preferred method for processing the Aphrodite ore including associated capital and operating costs. METS is an independent consulting group based in Perth, Western Australia, providing specialist processing services to the global mining industry. The preferred mining scenario selected by Tetra Tech is a contractor operated, selective open pit and underground mine providing feed to an onsite process plant at a nominal rate of 750,000tpa. The total project life is estimated at nine (9) years, with the open pit operating from Year 0 to Year 5 and the underground operating from Year 2 to Year 8. METS has developed a process flow sheet incorporating a pressure oxidation plant for processing the refractory component of the deposit. The proposed processing plant is designed to treat 1 Mtpa of ore to producing gold doré onsite. A more detailed description of the project follows. All cost/revenue estimates, and gold prices, are reported in Australian dollars.

3 Resources Current JORC compliant resource estimates prepared by independent resources consultants McDonald Speijers (MS) in March 2011 were used for the Scoping Study. These are summarised in Table 1 with further details contained in the Company s previous ASX announcements. Ore Type Table1: Aphrodite JORC Resource Tonnes (t) Indicated Gold (g/t) Gold (oz) Tonnes (t) Inferred Surface Accessible Mineralisation, 0-150m Depth (cutoff = 0.5 g/t gold) Gold (g/t) Oxidised 180, ,700 Gold (oz) Transition 200, ,900 3,200, ,500 Primary 1,720, ,000 1,760, ,600 Total Surface 1,920, ,900 5,140, ,800 Underground Accessible Mineralisation, Below 150 m Depth (cutoff = 3.0 g/t gold) Primary 1,750, ,900 1,250, ,200 Total Underground 1,750, ,900 1,250, ,200 Resource Block Models were developed by MS for the Scoping Study based on the resource estimate. The models contained attributes representing the amount of potential ore and gold above 0.8 g/t and 2.8g/t cut-off grades, for open pit and underground mining respectively, after allowing for dilution and ore loss. Pit optimisation software was then applied to evaluate the deposit for potential open pit and underground mining inventories. Mining A number of mining scenarios were analysed to identify a preferred mining option that maximises resource recovery and project Net Present Value (NPV). Pit optimisation was performed using $1,350/oz gold price to determine potential open pit and underground mining inventories and select a target plant throughput. 90% process recovery was assumed for all material types during the pit optimisation process. Tetra Tech has selected a combined open pit and underground approach as the preferred mine plan, which aims to recover near surface ore via an open pit while recovering the deeper high grade resource via an underground extension. This option provides the following advantages: Reduced pre-strip and therefore initial capital cost Access to the underground mine via an in-pit portal, reducing decline development and sustaining capital cost Increased extraction of known resources resulting from lower total cash costs.

4 An open pit versus underground trade off optimisation was conducted using pit optimisation software to identify a conceptual open pit below which ore may be mined more economically by underground methods. Figure1: Illustration of Proposed Mine Design Open Pit Mining Open pit movement will be evenly distributed between two pushbacks to create two near symmetrical linked pits, on the Alpha and Phi lodes with an adjoining saddle from which a portal will be developed to access higher grade underground ore. Mineralised linking structures (referred to as Epsilon) between the lodes may reduce the size of the saddle between Alpha and Phi pits in the future. The combined pit will be around 670 metres in diameter with a maximum depth of 195 metres on the Alpha lode and 190 metres on Phi. The average waste-to-ore ratio is estimated at 12:1. Approximately 60 metres of sand, clay and weathered rock overburden will be removed from the deposit and used for tailings dam construction or placed in the waste storage facility. Conventional, contractor operated, truck and shovel and drill and blast methods have been assumed for open pit mining.

5 Underground Mining A conceptual mine design was created to illustrate access, ventilation, decline and level development requirements. The in-pit portal, for development of the decline, would be located on the saddle between pits Alpha and Phi, approximately 75 m below the surface. The central decline extends from the portal down to approximately 450 metres below the surface, spiralling down between the Alpha and Phi lodes (see Figure 1). Level access would be via horizontal drives branching from the central decline to the stoping panels every 25 m vertically. For the purpose of the Study, a longitudinal up-hole retreat stoping method was selected as the preferred mining method. This method relies mainly on gravity to carry the broken ore from the stoping panel to the lower level development where it is recovered by a Load-Haul-Dump (LHD) unit before being trucked to the surface. Two independent ventilation raises are proposed. These raises will also act as the second means of egress. Mine Scheduling A total of 5.0Mt will be scheduled for processing at an average grade of 3.8g/t containing 610,000 oz of gold over a project life of 9 years. The estimated average (diluted) gold grade of open pit and underground ore is 2.3 g/t and 5.5 g/t respectively. Open pit and underground development will run in parallel to prioritise the extraction of high grade ore from underground. An initial pre-strip will be required to ensure a sustainable mill feed of 750,000tpa is achieved early in the mine life. This will be done while the processing plant is being constructed. Pre-strip will be prioritised to the Alpha pit to speed up exposure of fresh rock for development of the portal. Underground pre-production development commences in Year 1, after the portal position is exposed. Full underground production starts in Year 2 and is maintained until Year 8, targeting an average of 365,000tpa of high grade ore. Gold production over life of project is estimated at 550,000 ounces with peak production of around 85,000 ounces per annum in Years 2 to 6. An estimated mining and production summary is presented in Table 2.

6 Table 2: Mining and Production Summary Description Values Open pit : Ore Mined (Mt) 2.8 Open pit: Ore Mined Grade (g/t) 2.3 Open pit: Metal Mined (000 s oz) 207 Underground : Ore Mined (Mt) 2.3 Underground: Ore Mined Grade (g/t) 5.5 Underground: Metal Mined (000 s oz) 403 Total Ore Mined (Mt) 5.0 Total Ore Grade (g/t) 3.8 Total Metal Mined (000 s oz) 610 Total Metal Produced* (000 s oz) 550 Note: * Assumes 90% metallurgical recovery Metallurgical Testwork To provide a basis for the Scoping Study a metallurgical testwork program was undertaken immediately prior to the commencement of the Scoping Study to determine the metallurgical properties of the mineralisation. The testwork showed that the deposit contains both free milling and refractory ore. Significantly, the refractory material performed very well during the flotation tests where a high gold grade, sulphide concentrate was produced at a very low mass pull. Gold recoveries of 91.3% were achieved in 2.9% of the mass at a grade of g/t gold. Further testwork has been recommended by METS. Process Selection and Plant Design As the Aphrodite deposit contains both free milling and refractory ore, a processing plant has been designed to treat both ore types to the final stage of producing gold doré on site. The majority of feed to the mill will be primary refractory ore and therefore this processing option was the primary focus for the Study. However, consideration has also been given to the free milling circuit to treat oxide and transition ore types. An oxidation process options study was completed to assess the various oxidation processes used in industry and their suitability to treat the refractory Aphrodite ore. From this study it was determined that Pressure Oxidation (POX) was the most appropriate treatment method for use in the proposed processing plant.

7 The proposed processing plant developed by METS is designed to treat 1 Mtpa of ore to producing gold dorè onsite. The process plant contains: A crushing circuit consisting of a primary jaw and secondary cone crusher. A grinding circuit containing a grate discharge ball mill, Falcon concentrator and intensive leach, gravity gold recovery circuit, flash float cell, pebble crusher and cyclone cluster. A flotation circuit consisting of rougher flotation cells, scavenger flotation cells, cleaner flotation cells and a concentrate thickener. A POX circuit consisting of an Isamill, autoclave, flash vessel and wash thickeners. A CIL circuit containing leach and adsorption tanks. An elution and metals recovery circuit containing an acid wash column, elution column, electrowinning cells and carbon regeneration kiln. A tailing detox and thickener to destroy any residual cyanide before the thickened slurry is pumped to the tailings storage facility. Further to the design of this POX plant, a refractory circuit bypass was integrated into the process so that free milling oxide and transition ore could be treated through the same plant with minimal modification or additional equipment required. Infrastructure The Aphrodite Project is located 65km north of Kalgoorlie, placing the project conveniently close to key infrastructure and utilities. Key infrastructure within the area includes: The Goldfields highway located immediately west of the project which can be used for consumable and employee transport. The Kalgoorlie Township which can be used to house employees, thus eliminating the requirement for onsite accommodation. The Goldfields Gas Pipeline which, can be used for site power generation, is located approximately 10 km east of the project. The Kalgoorlie to Esperance rail line which can be used if concentrate sale overseas is considered. Water resources will need to be identified and developed as there is no known large water source in the immediate vicinity. Environment, Permitting and Community Flora, fauna, ethnographic and archaeological baseline surveys have been completed over the project area. No significant adverse impacts are expected to occur as a result of the Project. Additional baseline data may be required in order for the regulators to assess the potential impacts of the Project before permitting can be finalised. Aphrodite Gold has undertaken preliminary stakeholder engagement activities with local landowners, Traditional Owners and government regulators.

8 Capital and Operating Cost Estimates Capital and operating cost estimates have been developed by METS for the proposed process plant with a capacity of 1 Mtpa with an accuracy of ±35%. The capital cost estimate for a new processing plant is $108M. The estimate is calculated through the addition of direct and indirect costs and a contingency allowance to cover the level of risk associated with a project of this level and scope. Other initial capital items include infrastructure ($10M) and pre-stripping ($37M). An additional sustaining capital cost over the life of the project is estimated at $89M, including underground development. The operating cost estimates are summarised below. The total operating cost is $83/t ore (see Table 3). This equates to an average $756/oz gold produced. Table 3: Operating Cost Estimates Operating Cost $/t ore Mining* 46 Processing 27 General and Administrative 5 Offsite 1 State Government Royalties 4 Total 83 * weighted for open pit and underground. $26/t ore for open pit at a stripping ratio of approx. 12:1, and $78/t ore for underground mining. Significant saving in processing costs could be achieved by running the plant at a higher throughput. The processing plant is designed for 1 Mtpa, however the mine plan used in the Study has a nominal mill throughput of 750,000 tpa. Increased throughput could result from the availability of more ore as a result of exploration and/or the mining and treatment of lower grade material as a result of higher gold prices. Project Economic Analysis An economic evaluation for the project was prepared by Tetra Tech based on a pre-tax financial model. Financial parameters at gold prices of $1,450 and $1,650 per oz (the approximate current gold price) are summarised in Table 4. The project NPV is most sensitive to the metal price and metallurgical recovery, and in decreasing order: operating costs, plant capital costs, sustaining capital costs and underground development costs. Similarly, the IRR is most sensitive to metal price and metallurgical recovery.

9 Table 4: Financial Summary Financial Parameter Base Case Gold $1450/oz Alternative Case Gold $1650/oz NPV at 8% discount rate ($M) IRR (%) 15 25% Gross Revenue ($M) Total Capital ($M) Total Operating Costs ($M) Cash Cost ($/oz) Undiscounted Cash Flow ($M) Payback (years) 4 3 Mine Life (years) 8 8 Project Life (years) 9 9 Opportunities Various opportunities exist to further optimise the Project and economic returns, including: Resource drilling completed post the March 2011 resource estimate (used in the Scoping Study) has the potential to increase the mining inventory together with the discovery of additional resources below the currently planned mine and from numerous gold prospects (such as Chameleon) located within the Aphrodite area. An increased resource inventory has the potential of increasing plant throughput, reducing operating costs, increasing annual gold production and project life. Drilling has identified gold bearing linking structures between Alpha and Phi lodes. The linking structures may reduce the size of the saddle between the Alpha and Phi pits. Pit optimisation to determine potential open pit and underground mining inventories was performed using $1,350/oz gold price. There may be significant upside if the gold price increases. 90% process recovery was assumed for all material types during the pit optimisation process. Actual recoveries may yield an extra 5% depending on material type. Investigation of these opportunities should form part of future studies by way of a further drilling, metallurgical testwork and comprehensive review of existing data. Risks There are risks associated with the project (as with all mining ventures), the most important of which include: Higher than estimated capital costs reflecting the impact of the current mining boom.

10 Sustained increases in costs during the life of the project. Lower than forecast resource grades and/or metallurgical recovery. Lower than forecast gold prices. Higher than anticipated ore dilution and waste recovery. Recommendations Both Tetra Tech and METS recommend that the project should move to Pre-Feasibility Study (PFS). Tetra Tech state that there is strong justification for additional expenditures and efforts to develop the Aphrodite deposit. They recommend that both the fully integrated process plant option (outlined in this report) and processing of ore to produce a high gold grade concentrate for toll treatment or outright sale, be examined in the next stage of project development. The latter option would result in significant savings in plant costs; however reduced gold receipts would be expected. METS assessed the Aphrodite Gold Project and considered the project positive for a number of reasons including: Reasonable capital and operating costs for a standalone refractory processing plant. Possibility of becoming a toll treatment plant for local ore bodies once Aphrodite Gold deposits have been depleted. A flotation plant on site followed by toll treatment or sale of the high grade product could also yield favourable economics. Proximity of the site to Kalgoorlie, the Goldfields Gas Pipeline and the Goldfields Highway reduces the need for excessive spending on project infrastructure. METS state that a pre-feasibility study should be performed to confirm parameters for processing and to provide further design data for the plant. Yours Sincerely, Leon Reisgys Exploration and Development Director Notes Information in this report that relates to Mineral Resources is based on information compiled by Diederik Speijers who is a Fellow of the Australasian Institute of Mining and Metallurgy. Diederik Speijers is employed by independent consultants McDonald Speijers and has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the 2004 edition of the Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves. Diederik Speijers consents to the inclusion in the report of the matters based on his information in the context in which it appears. Information in this report that relates to technical information reflects information compiled by Leon Reisgys FAusIMM and Exploration and Development Director of Aphrodite Gold Ltd who has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is reporting on as a competent person as defined in the 2004 Edition of The Australian Code for Reporting Exploration Results, Mineral Resources and Ore Reserves. Mr. Reisgys consents to the inclusion in this report of the matters based on the information compiled by him, in the form and context in which it appears. The scoping study has been prepared based on a delineated inferred and indicated mineral resource estimate and any investment decision should be considered based on this information.

For personal use only

For personal use only 7 August 2012 ASX: PAN Gidgee Gold Project Scoping Study Key Highlights Gold Production estimated at 606,000oz of gold over an initial seven years, average annual production of 87,000oz Operating Cash

More information

Koka Project Stands to be a Highly Profitable Gold Mine: Scoping Study

Koka Project Stands to be a Highly Profitable Gold Mine: Scoping Study Koka Project Stands to be a Highly Profitable Gold Mine: Scoping Study Chalice Gold Mines Limited ABN 47 116 648 956 30 October 2009 Highlights Scoping Study finds Koka deposit at the Zara Project in Eritrea

More information

Malachite Resources AGM. November For personal use only. Malachite Resources Limited

Malachite Resources AGM. November For personal use only. Malachite Resources Limited Malachite Resources AGM November 2013 1 Malachite Resources Limited Disclaimer and Competent Person Statement Disclaimer This presentation may contain forward looking statements that are subject to risk

More information

Great Western Scoping Study Update & Onsite Gold Processing

Great Western Scoping Study Update & Onsite Gold Processing ASX RELEASE 10 August 2017 ABN: 45 116 153 514 ASX: TMX Great Western Scoping Study Update & Onsite Gold Processing Terrain Minerals Limited (ASX: TMX) is pleased to provide the following update on its

More information

DALGARANGA GOLD PROJECT CONSTRUCTION UPDATE LESS THAN 5 MONTHS TO FIRST GOLD

DALGARANGA GOLD PROJECT CONSTRUCTION UPDATE LESS THAN 5 MONTHS TO FIRST GOLD December 8 th 2017 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 DALGARANGA GOLD PROJECT CONSTRUCTION UPDATE LESS THAN 5 MONTHS TO FIRST GOLD Construction at Gascoyne s

More information

For personal use only

For personal use only Pre-Feasibility Study Highlights World Class Potential of Mt Lindsay Tin/Tungsten Project ASX Announcement Tuesday, 1 March 2011 Ref: /VMS/606/VMS/0249 Highlights: Project generates substantial revenue

More information

For personal use only

For personal use only 2 May 2018 ASX Announcement METALLURGICAL TESTWORK CONFIRMS WILUNA TRANSITIONAL RESERVES AMENABLE TO PROCESSING THROUGH THE EXISTING WILUNA CIL PLANT Highlights Expansion PFS published in Aug 17 includes

More information

For personal use only

For personal use only ACN 097 088 689 01 DEFINITIVE FEASIBILITY STUDY SUPPORTS A MAJOR EXPANSION OF THE SYAMA GOLD MINE Definitive Feasibility Study completed for multifaceted expansion of Syama operation confirms its technical

More information

For personal use only

For personal use only Mutiny makes substantial metallurgical performance gains Forecast copper recoveries increased from 58.5% to 64% in the oxide zone and copper concentrate grade increased from 21.5% Cu to 35% Cu Forecast

More information

For personal use only

For personal use only ABN 79 106 879 690 30 August 2016 The Manager Companies ASX Limited 20 Bridge Street Sydney NSW 2000 (11 pages by email) Updated Internal Scoping Study Delivers Positive Results (ASX: AUK) The Directors

More information

Garden Well Gold Deposit. Reserve Increases to 1.66 Million Ounces

Garden Well Gold Deposit. Reserve Increases to 1.66 Million Ounces ABN 28 009 174 761 31 March 2011 Manager Announcements Company Announcements Office Australian Securities Exchange Limited Level 4, 20 Bridge Street Sydney NSW 2000 www.regisresources.com Level 1 1 Alvan

More information

For personal use only

For personal use only ASX Release 20 March 2012 PANTON REVIEW STUDY RESULTS (ASX:PLA) is pleased to advise that the results from the recently completed Panton Review Study ( PRS ) showed that the Project could achieve and Internal

More information

Ban Houayxai Project Approved operation to produce over 100,000 ounces of gold and 700,000 ounces of silver per annum

Ban Houayxai Project Approved operation to produce over 100,000 ounces of gold and 700,000 ounces of silver per annum ASX ANNOUNCEMENT 29 March 2010 Ban Houayxai Project Approved operation to produce over 100,000 ounces of gold and 700,000 ounces of silver per annum PanAust is pleased to announce that the Board of Directors

More information

For personal use only

For personal use only 11 June 2015 ASX Limited Marked Announcements Platform Exchange Centre 20 Bridge Street Sydney NSW 2000 Preliminary Economic Assessment Delivers Excellent Results at the Fair Bride Deposit Study confirms

More information

DALGARANGA GOLD PROJECT - CONSTRUCTION UPDATE 8 MONTHS TO FIRST GOLD

DALGARANGA GOLD PROJECT - CONSTRUCTION UPDATE 8 MONTHS TO FIRST GOLD November 3 rd 2017 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 DALGARANGA GOLD PROJECT - CONSTRUCTION UPDATE 8 MONTHS TO FIRST GOLD Construction work at Gascoyne s 100%

More information

ASX and Media Release: 20 September 2016 ASX Code: WRM Initial mining review demonstrates potential upside at Mt Carrington

ASX and Media Release: 20 September 2016 ASX Code: WRM Initial mining review demonstrates potential upside at Mt Carrington ASX and Media Release: 20 September 2016 ASX Code: WRM Initial mining review demonstrates potential upside at Mt Carrington ASX Code: WRM Issued Securities Shares: 441.3 million Options: 100.5 million

More information

ASX Release ASX Code: YTC

ASX Release ASX Code: YTC HERA DEFINITIVE FEASIBILITY STUDY TO BE EXPANDED Hera DFS scope to be expanded to include the assessment of mining and treatment of high grade copper ores from the Nymagee Copper Mine together with additional

More information

For personal use only

For personal use only ASX Announcement 19 December 2014 BOARD OF DIRECTORS Paul Murphy (Non-Executive Chairman) Bryan Dixon (Managing Director) Alan Thom (Executive Director) Greg Miles (Non-Executive Director) ASX CODE BLK

More information

DALGARANGA GOLD PROJECT OPERATIONAL UPDATE: MILL PERFORMANCE TEST COMPLETED AS RAMP UP CONTINUES

DALGARANGA GOLD PROJECT OPERATIONAL UPDATE: MILL PERFORMANCE TEST COMPLETED AS RAMP UP CONTINUES July 25 th 2018 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 DALGARANGA GOLD PROJECT OPERATIONAL UPDATE: MILL PERFORMANCE TEST COMPLETED AS RAMP UP CONTINUES The Process

More information

For personal use only

For personal use only ASX ANNOUNCEMENT / MEDIA RELEASE ASX: ABU 30th September, 2014 ABM s Development Plan & Production Guidance for Old Pirate High-Grade Gold Deposit Highlights: 50,000 to 60,000 ounces of gold production

More information

For personal use only

For personal use only 9 December 2011 Bass Metals Confirms Commercial Robustness of Hellyer Gold Project (HGP) HIGHLIGHTS: A study on tailings treatment options confirms HGP as a robust project utilising the Albion Process

More information

Highlights. Wa Project. Akoko Project. Scoping studies on the Julie West gold vein were completed with the following outcomes;

Highlights. Wa Project. Akoko Project. Scoping studies on the Julie West gold vein were completed with the following outcomes; 24 th July 2009 June December 2009 Quarterly Report Report 2008 Highlights Wa Project Scoping studies on the Julie West gold vein were completed with the following outcomes; 250,000 tonnes @ 4.9g/t gold

More information

For personal use only

For personal use only 29 February 2016 The Company Announcements Office Australian Securities Exchange Limited SCOPING STUDY ON APHRODITE OXIDE / SUPERGENE / TRANSITION ORES Key Points Aphrodite has commissioned independent

More information

Gum Creek Gold Project Free Milling Scoping Study

Gum Creek Gold Project Free Milling Scoping Study 18 March 2016 ASX: PAN Highlights Gum Creek Gold Project Free Milling Scoping Study Mining Inventory of 4.9Mt at 1.94g/t Au for 309koz gold based on material from Swan, Swift and Howards Resources Average

More information

For personal use only

For personal use only ASX RELEASE Sorby Hills Silver Lead Project Major Milestone Achieved with Environmental Approval As announced on 3 April, the WA Minister for Environment has approved the development of the Sorby Hills

More information

WA s MT THIRSTY COBALT-NICKEL PROJECT POTENTIALLY WORLD S FOURTH LARGEST COBALT PRODUCER

WA s MT THIRSTY COBALT-NICKEL PROJECT POTENTIALLY WORLD S FOURTH LARGEST COBALT PRODUCER WA s MT THIRSTY COBALT-NICKEL PROJECT POTENTIALLY WORLD S FOURTH LARGEST COBALT PRODUCER Highlights Project has potential to deliver 3,700 tonnes of cobalt, 10,300 tonnes of nickel and 27,000 tonnes of

More information

DALGARANGA PRE-FEASIBILITY UPDATE

DALGARANGA PRE-FEASIBILITY UPDATE January 19th, 2016 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 DALGARANGA PRE-FEASIBILITY UPDATE PFS Pit optimisations indicate a production target far larger than anticipated

More information

For personal use only

For personal use only January 19th, 2016 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 DALGARANGA PRE-FEASIBILITY UPDATE PFS Pit optimisations indicate a production target far larger than anticipated

More information

Mt Thirsty Cobalt-Nickel Joint Venture Infill Drilling Results

Mt Thirsty Cobalt-Nickel Joint Venture Infill Drilling Results 31 January 2007 ASX ANNOUNCEMENT. Mt Thirsty Cobalt-Nickel Joint Venture Infill Drilling Results The Company is pleased to announce results of infill drilling at the Mt Thirsty Cobalt Nickel Project, strategically

More information

RENISON TAILINGS RETREATMENT PROJECT ( RENTAILS ) UPDATED DFS CONFIRMS HIGH MARGIN PROJECT

RENISON TAILINGS RETREATMENT PROJECT ( RENTAILS ) UPDATED DFS CONFIRMS HIGH MARGIN PROJECT 4 JULY 2017 RENISON TAILINGS RETREATMENT PROJECT ( RENTAILS ) UPDATED DFS CONFIRMS HIGH MARGIN PROJECT HIGHLIGHTS Robust economics: NPV 8% of A$260M (pre-tax) and IRR of 37% 1 ; Cash operating cost of

More information

For personal use only

For personal use only ASX ANNOUNCEMENT / MEDIA RELEASE ASX: ABU 5th September, 2012 Old Pirate Metallurgical Test-Work delivers Exceptional Gold Recovery (up to 97.3%) from Two Different Gravity Methods ABM Resources NL ( ABM

More information

For personal use only

For personal use only Bulletin Resources is the 100% owner of the Nicolson s Gold Project located near Halls Creek in the Kimberley region of Western Australia. The project has a combined open pit and underground Mineral Resource

More information

For personal use only

For personal use only ASX Announcement Arafura Extends Nolans Mine Life To Beyond Thirty Years 2 September 217 Two-thirds of Measured and Indicated Resources inventory identified as NdPr-bearing phosphate-rich material types

More information

Bald Hill Delivers Excellent Metallurgical Test Work Results

Bald Hill Delivers Excellent Metallurgical Test Work Results 6 September 2017 Bald Hill Delivers Excellent Metallurgical Test Work Results Tawana Resources NL (TAW:ASX) (Tawana) and Alliance Mineral Assets Limited (SGX:AMA) (AMAL) are pleased to announce encouraging

More information

TEMBANG PRE-FEASIBILITY STUDY DELIVERS POSITIVE OUTCOME

TEMBANG PRE-FEASIBILITY STUDY DELIVERS POSITIVE OUTCOME ASX ANNOUNCEMENT 23 February 2012 (8 pages by email) TEMBANG PRE-FEASIBILITY STUDY DELIVERS POSITIVE OUTCOME Sumatra Copper & Gold plc ( Sumatra or the Company ) is pleased to announce that the Prefeasibility

More information

CAPITAL DOWN AT TALA HAMZA

CAPITAL DOWN AT TALA HAMZA CAPITAL DOWN AT TALA HAMZA ASX Shareholder Report 8 April 2009 Enquiries on this Report or the Company Business may be directed to: Dr Kevin Moriarty Executive Chairman + 61 8 8213 1415 + 61 408 173 157

More information

Maiden Ore Reserve for Camel Creek JV

Maiden Ore Reserve for Camel Creek JV 10 September 2013 Manager Company Announcements Company Announcements Office Australian Securities Exchange Limited Level 4, 20 Bridge Street SYDNEY NSW 2000 ABN 85 003 257 556 Maiden Ore Reserve for Camel

More information

ABM Hits 3000 Ounce Target from Trial Mining

ABM Hits 3000 Ounce Target from Trial Mining ASX ANNOUNCEMENT / MEDIA RELEASE ASX:ABU 12 th December 2013 ABM Hits 3000 Ounce Target from Trial Mining ABM Resources NL ( ABM or The Company ) presents an update on the Trial Mining and Processing at

More information

OPERATIONAL UPDATE AND 2019 PRODUCTION GUIDANCE

OPERATIONAL UPDATE AND 2019 PRODUCTION GUIDANCE December 24 th 2018 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 OPERATIONAL UPDATE AND 2019 PRODUCTION GUIDANCE Dalgaranga Operational Update: The project remains Lost

More information

For personal use only

For personal use only December 24 th 2018 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 OPERATIONAL UPDATE AND 2019 PRODUCTION GUIDANCE Dalgaranga Operational Update: The project remains Lost

More information

Awak Mas DFS Optimisation - Metallurgical Breakthrough

Awak Mas DFS Optimisation - Metallurgical Breakthrough 10 October 2017 Awak Mas DFS Optimisation - Metallurgical Breakthrough Whole of Ore leach testwork delivers improved metallurgical recoveries. Gold recoveries range from 92% - 98% vs previous flotation-leach

More information

FIRST GOLD FROM DALGARANGA GOLD PROJECT: AHEAD OF SCHEDULE AND UNDER BUDGET

FIRST GOLD FROM DALGARANGA GOLD PROJECT: AHEAD OF SCHEDULE AND UNDER BUDGET May 30 th 2018 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 FIRST GOLD FROM DALGARANGA GOLD PROJECT: AHEAD OF SCHEDULE AND UNDER BUDGET First Gold poured from Dalgaranga

More information

Study on Gonka Deposit and Taurus Extension

Study on Gonka Deposit and Taurus Extension Study on Gonka Deposit and Taurus Extension RNS Number : 7037N Hummingbird Resources PLC 02 February 2016 Hummingbird Resources plc ('Hummingbird' or 'the Company') Study on Gonka Deposit and Taurus Extension

More information

JORC RESOURCE FOR OLD KONONGO TAILINGS DAM

JORC RESOURCE FOR OLD KONONGO TAILINGS DAM ASX Release Friday 5 March 2010 SIGNATURE METALS LIMITED Level 1 / 33 Richardson Street WEST PERTH Australia Tel: +61 8 9481 0101 Fax: +61 8 9200 4469 JORC RESOURCE FOR OLD KONONGO TAILINGS DAM The Company

More information

ASX ANNOUNCEMENT 12 MAY 2016

ASX ANNOUNCEMENT 12 MAY 2016 ASX ANNOUNCEMENT 12 MAY 2016 FÄBOLIDEN METALLURGICAL TEST WORK IMPROVES RECOVERY LEVELS Dragon Mining Limited (ASX:DRA) ( Dragon Mining or the Company ) is pleased to announce that the second phase of

More information

MINING COMMENCES AT KONONGO GOLD PROJECT

MINING COMMENCES AT KONONGO GOLD PROJECT ASX Release Monday 28 th March 2011 MINING COMMENCES AT KONONGO GOLD PROJECT Signature Metals Limited is pleased to announce that it has commenced mining at the Konongo Gold Project. SIGNATURE METALS LIMITED

More information

Pre Feasibility Study Advances the Taronga Tin Project

Pre Feasibility Study Advances the Taronga Tin Project Pre Feasibility Study Advances the Taronga Tin Project 7 th April 2014 Disclaimer Forward Looking Statement This presentation may contain certain statements and projections provided by or on behalf of

More information

UPDATE TO BROKEN HILL MINERAL RESOURCES AND ORE RESERVES

UPDATE TO BROKEN HILL MINERAL RESOURCES AND ORE RESERVES 7 November 2008 UPDATE TO BROKEN HILL MINERAL RESOURCES AND ORE RESERVES Highlights Broken Hill Ore Reserves increase life of mine to 9 years at conservative price assumptions Substantial Resource base

More information

Southern Cross Goldfields Ltd

Southern Cross Goldfields Ltd Southern Cross Goldfields Ltd ASX Announcement - 20 December 2013 Marda Gold Project: Feasibility Study Review Additional Information On 10 December 2013, Southern Cross Goldfields (ASX: SXG SXG or the

More information

JORC RESOURCE AT KONONGO INCREASED TO 1.47 MILLION OUNCES OF CONTAINED GOLD

JORC RESOURCE AT KONONGO INCREASED TO 1.47 MILLION OUNCES OF CONTAINED GOLD ASX Release Wednesday 10 November 2010 SIGNATURE METALS LIMITED Level 1 / 33 Richardson Street WEST PERTH Australia Tel: +61 8 9481 0101 Fax: +61 8 9200 4469 Contact: Bill Oliver (Managing Director) E-mail:

More information

DALGARANGA GOLD PROJECT CONSTRUCTION & OPERATIONAL UPDATE 2 MONTHS TO FIRST GOLD

DALGARANGA GOLD PROJECT CONSTRUCTION & OPERATIONAL UPDATE 2 MONTHS TO FIRST GOLD March 19 th 2018 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 DALGARANGA GOLD PROJECT CONSTRUCTION & OPERATIONAL UPDATE 2 MONTHS TO FIRST GOLD Process plant construction

More information

ASX ANNOUNCEMENT 26 February 2013 ASX Code: BDR. MAIDEN DUCKHEAD HANGINGWALL LODE RESOURCE 584, g/t for 71,000 oz gold

ASX ANNOUNCEMENT 26 February 2013 ASX Code: BDR. MAIDEN DUCKHEAD HANGINGWALL LODE RESOURCE 584, g/t for 71,000 oz gold ASX ANNOUNCEMENT 2 February 2013 ASX Code: BDR MAIDEN DUCKHEAD HANGINGWALL LODE RESOURCE 58,000 tonnes @ 3.8 g/t for 71,000 oz gold MAIDEN DUCKHEAD HANGINGWALL STARTER PIT RESERVE 272,000 tonnes @ 3.2

More information

AGM - Lorena Gold Project

AGM - Lorena Gold Project AGM - Lorena Gold Project For personal use onlynovember 2015 Disclaimer and Competent Person Statement Disclaimer This presentation may contain forward looking statements that are subject to risk factors

More information

Ravenswood Expansion Project Update

Ravenswood Expansion Project Update 11 July 2018 Ravenswood Expansion Project Update Highlights AISC down, mine life extended, all required approvals received Significant enhancements have been made to Ravenswood Expansion Project All required

More information

HORSESHOE LIGHTS PROJECT ASX/MEDIA ANNOUNCEMENT

HORSESHOE LIGHTS PROJECT ASX/MEDIA ANNOUNCEMENT OXIDE COPPER STUDY UNDERWAY AT 8 HORSESHOE LIGHTS PROJECT ASX/MEDIA ANNOUNCEMENT 20 AUGUST 2015 ASX Code: HOR Management Mr Neil Marston Managing Director/Company Secretary Mr Michael Fotios Non-Executive

More information

For personal use only

For personal use only 1 SCOPING STUDY CONFIRMS PROFITABLE POTENTIAL OF HASTINGS HEAVY RARE EARTH PROJECT The Manager Company Announcements Office Australian Securities Exchange 4th Floor, 20 Bridge Street SYDNEY NSW 2000 Hastings

More information

For personal use only

For personal use only 25 January 2013 EXCELLENT RECOVERIES IN HEAP LEACH TESTS AT MELROSE PROJECT HIGHLIGHTS Excellent gold recoveries in column leach tests with 94%+ Au extracted after 32 days of leaching from Bungarra deposit

More information

FEASIBILITY STUDY COMPLETED CONFIRMING ROBUST CASH MARGINS FOR JOGJAKARTA IRON PROJECT

FEASIBILITY STUDY COMPLETED CONFIRMING ROBUST CASH MARGINS FOR JOGJAKARTA IRON PROJECT ANNOUNCEMENT TO THE AUSTRALIAN SECURITIES EXCHANGE: 29 AUGUST 2011 FEASIBILITY STUDY COMPLETED CONFIRMING ROBUST CASH MARGINS FOR JOGJAKARTA IRON PROJECT Highlights: Feasibility Study completed on a 2

More information

Pilbara Gold Project, Western Australia Open Pit Development Opportunity Scoping Study nearing completion. ASX Code : DEG May 2017 Andy Beckwith

Pilbara Gold Project, Western Australia Open Pit Development Opportunity Scoping Study nearing completion. ASX Code : DEG May 2017 Andy Beckwith Pilbara Gold Project, Western Australia Open Pit Development Opportunity Scoping Study nearing completion ASX Code : DEG May 2017 Andy Beckwith De Grey Corporate Snapshot ASX: DEG De Grey Ordinary Shares

More information

Drilling, metallurgical test work and a new resource model add 21% to oxide gold reserves

Drilling, metallurgical test work and a new resource model add 21% to oxide gold reserves LA ARENA GOLD OXIDE RESERVES INCREASED TO 1.28MM OZ AT AU PRICE OF $1,200 COMPLETION OF THE PRE-FEASIBILITY STUDY FOR THE PHASE II SULPHIDE Cu-Au PROJECT Drilling, metallurgical test work and a new resource

More information

For personal use only

For personal use only RDM ASX Announcement 23 October 2013 ACN 103 367 684 ASX ANNOUNCEMENT 8 MARCH 2016 ASX Code: RDM Red Metal Limited is a minerals exploration company focused on the exploration, evaluation and development

More information

FIRST GOLD ORE DISPATCHED FROM ULYSSES

FIRST GOLD ORE DISPATCHED FROM ULYSSES Genesis Minerals Limited (ASX: GMD) ASX Announcement 14 November 2016 FIRST GOLD ORE DISPATCHED FROM ULYSSES Genesis poised for first cash-flow as first parcel of ore departs for Paddington gold plant

More information

For personal use only

For personal use only ACN 092 471 513 QUARTERLY REPORT FOR THE PERIOD ENDING 31 DECEMBER 2017 HIGHLIGHTS PENNY S FIND GOLD MINE KALGOORLIE (WA) 84,367 tonnes of ore processed at an average head grade of 3.09g/t Au 7,837 ounces

More information

TEMBANG PROJECT OPTIMISATION

TEMBANG PROJECT OPTIMISATION ASX ANNOUNCEMENT 16 April 2012 (13 pages by email) TEMBANG PROJECT OPTIMISATION Sumatra Copper & Gold plc ('Sumatra' or 'the Company') is pleased to confirm Optimisation Studies for its wholly-owned Tembang

More information

PILOT TEST WORK TRIGGERS FINAL TRANCHE OF TREMONT FINANCING

PILOT TEST WORK TRIGGERS FINAL TRANCHE OF TREMONT FINANCING 8 October 2015 ASX Release ASX Code: CXX Highlights PILOT TEST WORK TRIGGERS FINAL TRANCHE OF TREMONT FINANCING Tremont has paid the final tranche of US$5 million Integrated pilot plant testing confirms

More information

For personal use only

For personal use only 21 November 2011 Kentor Gold (ASX: KGL) is an Australian-based, emerging midadvanced tier gold company with projects in Australia and the Kyrgyz Republic. Formed in 1998 and listed on the ASX in 2005,

More information

For personal use only

For personal use only ACN 092 471 513 QUARTERLY REPORT FOR THE PERIOD ENDING 31 MARCH 2018 HIGHLIGHTS PENNY S FIND GOLD MINE KALGOORLIE (WA) 25,771 dry tonnes of ore processed at an average head grade of 6.55g/t Au 5,061 ounces

More information

Updated Epanko Scoping Study

Updated Epanko Scoping Study ASX ANNOUNCEMENT 18 August 2014 Updated Epanko Scoping Study Kibaran Resources Limited (ASX: KNL) is pleased to announce the upgraded Scoping Study ( Study ) completed for its Epanko graphite deposit.

More information

STRONG PRE-FEASABILITY STUDY SUPPORTS 1.5 MTPA URQUHART BAUXITE DEVELOPMENT

STRONG PRE-FEASABILITY STUDY SUPPORTS 1.5 MTPA URQUHART BAUXITE DEVELOPMENT ASX RELEASE 30 DECEMBER 2016 STRONG PRE-FEASABILITY STUDY SUPPORTS 1.5 MTPA URQUHART BAUXITE DEVELOPMENT HIGHLIGHTS Independent Pre-Feasibility Study (PFS) supports development of the Urquhart Bauxite

More information

For personal use only

For personal use only 28 November 2017 Corporate Details Ordinary Shares: 780,917,069 Market Capitalisation: ~$156 million Cash and bullion at 30 September 2017: ~$20.1 million Debt: NIL ASX Code: MOY Board of Directors Greg

More information

SALT LAKE POTASH PLANS SOP PILOT PLANT AT GOLDFIELDS SALT LAKES PROJECT. ONGOING DISCUSSIONS WITH PROSPECTIVE GLOBAL INDUSTRY PARTNERS.

SALT LAKE POTASH PLANS SOP PILOT PLANT AT GOLDFIELDS SALT LAKES PROJECT. ONGOING DISCUSSIONS WITH PROSPECTIVE GLOBAL INDUSTRY PARTNERS. ASX ANNOUNCEMENT 21 April 2017 SALT LAKE POTASH PLANS SOP PILOT PLANT AT GOLDFIELDS SALT LAKES PROJECT. ONGOING DISCUSSIONS WITH PROSPECTIVE GLOBAL INDUSTRY PARTNERS. The Directors of Salt Lake Potash

More information

EXCO S PROJECT PIPELINE

EXCO S PROJECT PIPELINE EXCO S PROJECT PIPELINE INVESTOR UPDATE EXCO RESOURCES N.L. MAY 2010 Presented by Michael Anderson Managing Director DISCLAIMER This presentation contains forward looking statements that are subject to

More information

MCINTOSH STAGE 1 PRE-FEASIBILITY STUDY UPDATE

MCINTOSH STAGE 1 PRE-FEASIBILITY STUDY UPDATE ASX ANNOUNCEMENT 8 June 2016 MCINTOSH STAGE 1 PRE-FEASIBILITY STUDY UPDATE Open pit mining optimisation results demonstrate the potential for multiple low strip ratio, open pit operations across a range

More information

STUDIES CONFIRM COMBINED WILUNA URANIUM PROJECT IMPROVEMENTS

STUDIES CONFIRM COMBINED WILUNA URANIUM PROJECT IMPROVEMENTS ASX RELEASE 30th January 2014 STUDIES CONFIRM COMBINED WILUNA URANIUM PROJECT IMPROVEMENTS Uranium developer Toro Energy Limited (ASX: TOE) (Toro) today announced the completion of an independent Mining

More information

For personal use only

For personal use only ABN 64 123 993 233 ASX Announcement 21 March ABN 2016 64 123 993 233 Leigh Creek Magnesite - Project Study Highlights The Study examines possible open pit mining and processing options and provides a strong

More information

For personal use only

For personal use only Malachite Resources Limited ABN 86 075 613 268 ASX Announcement ASX Code: MAR 12 March 2012 LORENA GOLD PROJECT - UPDATE Summary Malachite s commitment to establish a gold mining and production plant at

More information

For personal use only

For personal use only ASX Market Update/Media release Monday 22 August 2016 Metals of Africa Reports Further Exceptional Metallurgical Results High grade chemical-free Flotation Testwork at Montepuez Project delivers >98% TGC

More information

SIGNIFICANT INCREASE IN KANMANTOO LIFE OF MINE AND TARGETED PROCESSING THROUGHPUT INCREASE

SIGNIFICANT INCREASE IN KANMANTOO LIFE OF MINE AND TARGETED PROCESSING THROUGHPUT INCREASE Wednesday, 20 February 2013 SIGNIFICANT INCREASE IN KANMANTOO LIFE OF MINE AND TARGETED PROCESSING THROUGHPUT INCREASE The Kanmantoo Copper Mine s Indicative Life of Mine (LOM) anticipated to extend to

More information

2014 MINERAL RESOURCES AND ORE RESERVES

2014 MINERAL RESOURCES AND ORE RESERVES 9 October 2014 ASX & MEDIA RELEASE 2014 MINERAL RESOURCES AND ORE RESERVES The Directors of Saracen Mineral Holdings Limited (ASX: SAR) ( Saracen or the Company ), are pleased to advise the updated Mineral

More information

ASX ANNOUNCEMENT. MacPhersons Nimbus Silver Target up to 6 Million Ounces. Highlights. ASX Code: MRP. Contact Details

ASX ANNOUNCEMENT. MacPhersons Nimbus Silver Target up to 6 Million Ounces. Highlights. ASX Code: MRP. Contact Details ASX Code: MRP Contact Details PO Box 10977 109 Maritana Street Kalgoorlie WA 6430 T +61 (0) 8 9091 7515 F +61 (0) 8 9091 7610 E info@macphersonsreward.com.au ABN 98 139 357 967 ASX ANNOUNCEMENT 28 July

More information

Saracen Mineral Holdings Limited ACN

Saracen Mineral Holdings Limited ACN Saracen Mineral Holdings Limited ACN 009 215 347 ASX Release 25 September 2012 2012 Mineral Resources and Ore Reserves Corporate Details: As at 30 June 2012 ASX codes: Ordinary shares: SAR 30 June 2013

More information

RESOURCE GOLD PTY. LTD.

RESOURCE GOLD PTY. LTD. Copyright RESOURCE GOLD PTY. LTD. Gold Recovery From Processing Of - Mill Site Materials - Alluvial Gold Deposits - Hard Rock Resources NOVEMBER, 2009 REVISION 3 1 Disclaimer! This presentation contains

More information

For personal use only

For personal use only 4 March 2014 ASX Market Announcements ASX Limited Exchange Centre 20 Bridge Street Sydney NSW 2000 ASX Code: EXG KALGOORLIE NORTH GOLD PROJECT POSITIVE PRE-FEASIBILITY STUDY RESULTS PFS Ore Reserves (optimised

More information

MARILLANA MAIDEN HEMATITE ORE RESERVE OF 1.05 BILLION TONNES

MARILLANA MAIDEN HEMATITE ORE RESERVE OF 1.05 BILLION TONNES ASX Release: 9 September 2010 MARILLANA MAIDEN HEMATITE ORE RESERVE OF 1.05 BILLION TONNES Definitive Mining Studies confirm continuity, quality and quantum of Ore body at MARILLANA Detrital Ore Reserves

More information

5 th Asian Bauxite & Alumina Conference

5 th Asian Bauxite & Alumina Conference 5 th Asian Bauxite & Alumina Conference October 2015 Bauxite Hills Project Deliberate Focus ASX : MMI CORPORATE SNAPSHOT Shareholders 0.140 0.120 MMI Share Price (A$) Other 47% NetWealth Investments 5%

More information

Panda Hill Niobium Project. January 2014

Panda Hill Niobium Project. January 2014 Panda Hill Niobium Project January 2014 ASX Capital Structure Issued Shares* 128,675,017 Unlisted options (May 2016 at 26.7c) 7,687,500 Listed options (January 2015 at 26.7c) 17,962,506 Total Options 25,650,006

More information

Gruyere Project - Updated Mine Plan

Gruyere Project - Updated Mine Plan ASX Announcement 6 December 2018 Gruyere Project - Updated Mine Plan CONTACT DETAILS Highlights Gruyere confirmed as a global Tier 1 gold mine 1 with a long life and forecast high margins Life of mine

More information

ASX : BLK. Australian gold producer with exceptional growth opportunity

ASX : BLK. Australian gold producer with exceptional growth opportunity ASX : BLK Australian gold producer with exceptional growth opportunity AMEC Conference Perth June 2017 The information contained in the report that relates to ore reserves at the Matilda Gold Project is

More information

Excellent Results from Conceptual Mine Study Ondjou Prospect, Namibia

Excellent Results from Conceptual Mine Study Ondjou Prospect, Namibia ASX Announcement & Media Release 3 February 2012 Excellent Results from Conceptual Mine Study Ondjou Prospect, Namibia Mine study completed by Mining Plus based on recently upgraded inferred JORC resource

More information

Aeon Metals Limited HIGHLIGHTS

Aeon Metals Limited HIGHLIGHTS ASX Announcement 15 February 2017 WALFORD CREEK PRELIMINARY ECONOMIC ASSESSMENT Early start up Copper-Zinc-Cobalt project indicated for Vardy Zone 2017 drill program focused on significant mine life extension

More information

QUARTERLY REPORT March 2011

QUARTERLY REPORT March 2011 QUARTERLY REPORT March 2011 Australian energy company, Blackham Resources Ltd (Blackham) ( ASX: BLK ) continues to advance the development of the Scaddan and Zanthus Coal to Liquids ( CTL ) projects. The

More information

OMITIOMIRE OXIDE COPPER FEASIBILITY STUDY

OMITIOMIRE OXIDE COPPER FEASIBILITY STUDY INTERNATIONAL BASE METALS LIMITED OMITIOMIRE OXIDE COPPER FEASIBILITY STUDY 21 NOVEMBER 2013 Frank Bethune Ken Maiden Andre Genis Karl Hartmann PRESENTED BY FRANK BETHUNE AND KEN MAIDEN Disclaimer 2 This

More information

Confidence in Carrapateena project grows

Confidence in Carrapateena project grows 7 NOVEMBER 2016 Confidence in Carrapateena project grows Carrapateena Pre-Feasibility Study released - project competitive with, or better than comparable long-life copper assets globally Project metrics

More information

QUARTERLY ACTIVITIES REPORT

QUARTERLY ACTIVITIES REPORT QUARTERLY ACTIVITIES REPORT For the quarter ended 31 March 2011 ABN: 38 108 779 782 Silver Lake Resources Ltd ( Silver Lake or the Company ) is pleased to present this Quarterly Activities Report. Les

More information

Second drill rig to accelerate major drilling program at Productora

Second drill rig to accelerate major drilling program at Productora DRAFT ASX ANNOUNCEMENT Thursday 11th September 2014 Second drill rig to accelerate major drilling program at Productora Expanded resource-reserve base will underpin completion of Productora Pre-feasibility

More information

BROKEN HILL MINERAL RESOURCES AND ORE RESERVES UPDATE

BROKEN HILL MINERAL RESOURCES AND ORE RESERVES UPDATE 28 December 2011 BROKEN HILL MINERAL RESOURCES AND ORE RESERVES UPDATE Highlights The Ore Reserve has been established and a new Life of Mine plan for Southern Operations has been developed with economic

More information

Nullagine Gold Project Life of Mine Update

Nullagine Gold Project Life of Mine Update 19 March 2014 Manager Company Announcements Company Announcements Office Australian Securities Exchange Limited Level 4, 20 Bridge Street SYDNEY NSW 2000 ABN 85 003 257 556 Dear Sir/Madam Via Electronic

More information

DALGARANGA GOLD PROJECT DEVELOPMENT UPDATE

DALGARANGA GOLD PROJECT DEVELOPMENT UPDATE August 7 th 2017 Australian Securities Exchange Limited Via Electronic Lodgement 57 139 522 900 DALGARANGA GOLD PROJECT DEVELOPMENT UPDATE Credit approved commitment letters received from a number of tier

More information

Kibali Mine Development

Kibali Mine Development Kibali Mine Development The Kibali mine development in the Democratic Republic of Congo is the largest project undertaken to date by Randgold. With a reserve base at plus 10 million ounces and still growing,

More information

NOLANS RARE EARTHS PROJECT: MAIDEN JORC ORE RESERVE

NOLANS RARE EARTHS PROJECT: MAIDEN JORC ORE RESERVE ASX RELEASE 11 December 2012 NOLANS RARE EARTHS PROJECT: MAIDEN JORC ORE RESERVE Independently prepared JORC Ore Reserve for Nolans Bore to support a 22 year mine life; 95% of Measured and Indicated Resources

More information