Verification Report Oldman River Hydroelectric Power Plant (January 1, 2016 May 31, 2016)

Size: px
Start display at page:

Download "Verification Report Oldman River Hydroelectric Power Plant (January 1, 2016 May 31, 2016)"

Transcription

1 Verification Report Oldman River Hydroelectric Power Plant (January 1, 2016 May 31, 2016) PRESENTED TO ATCO Power Canada Ltd. SEPTEMBER 28, 2016 ISSUED FOR USE FILE: ENV.CENV Tetra Tech EBA Inc. Riverbend Atrium One, 115, 200 Rivercrest Drive SE Calgary, AB T2C 2X5 CANADA Tel Fax

2 This page intentionally left blank. Verification Report ATCO Oldman_IFU.docx

3 SUMMARY Project Title Project Description Project Location Oldman River Hydroelectric Power Plant The project reduces greenhouse gas (GHG) emissions from a theoretical baseline of the emissions that would have been emitted with the generation of an equivalent quantity of electricity based on an established electricity displacement factor. Located 9 km northeast of Pincher Creek, Alberta at the Oldman River Dam; LSD W4M Project Start Date June 1, 2003 Credit Start Date June 1, 2003 Credit Duration Period Expected Lifetime of the Project Actual Emissions Reductions /Removals Achieved Other Environmental Attributes Project Registration Ownership Quantification Protocol Initial Credit Duration: June 1, 2003 to May 31, 2011 Approved Credit Duration Extension: June 1, 2011 to May 31, 2016 The project is expected to last 50 years. 21,697 tonne CO2e for the period of January 1, 2016 May 31, 2016 None This project is only registered once and in one offset system the Alberta Offset Registry. The Project is owned by ATCO Power Canada Ltd. and the Piikani Oldman Hydro Limited Partnership. Quantification Protocol for Quantification Protocol for Low-retention, Water-powered Electricity Generation as Run-of-river or on an Existing Reservoir (Version 1, May 2008) Verification Period This verification covers the period from January 1, 2016 May 31, i Verification Report ATCO Oldman_IFU.docx

4 Project Title Oldman River Hydroelectric Power Plant Project Activity The Oldman River Hydroelectric Power Plant (the Project) meets the requirements for offset eligibility as outlined in Section 3.1 of the Technical Guidance for Offset Project Developers (Version 4.0, February 2013). In particular: 1. The Project occurs in Alberta as outlined above. 2. The Project results from actions not otherwise required by law and beyond business as usual and sector common practices. 3. The Project results from actions taken on or after January 1, 2002, as outlined above. 4. The Project reductions/removals are real, demonstrable, quantifiable and verifiable: The Project is creating real reductions that are not a result of shutdown, cessation of activity or drop in production levels. The emission reductions are demonstrable, quantifiable and verifiable as outlined in the Project Developer s Project plan. 5. The Project has clearly established ownership. 6. The Project will be counted once for compliance purposes: The Project credits will be registered with the Alberta Emissions Offset Registry which tracks the creation, sale and retirement of credits. Credits created from the specified reduction activity have not been, and will not be, created, recorded or registered in more than one trading registry for the same time period. 7. The Project was implemented according to a government approved protocol. 8. The Project is verified by a qualified third party, Tetra Tech EBA Inc. Project Proponent Anne Vigneau Environment Advisor ATCO Power Canada Ltd. 400, th Avenue SW, Calgary, Alberta T2R 1P3 Phone: anne.vigneau@atco.com ii Verification Report ATCO Oldman_IFU.docx

5 VERIFICATION SUMMARY Project Title Objective Summary Lead Verifier Verification Team Subject Matter Expert Independent Peer Reviewer Designated Signing Authority Oldman River Hydroelectric Power Plant Reasonable assurance on Emission Reductions contained in the GHG Assertion. Based on our review, it is our opinion to a reasonable level of assurance that the GHG emission reductions contained in the GHG Assertion are materially correct and presented fairly in accordance with the related criteria. Min Si, M.N.R.M, GHG-V Tetra Tech EBA Inc. 115, 200 Rivercrest Drive SE, Calgary, AB T2C 2X5 Phone: Min.Si@tetratech.com Min Si, M.N.R.M., GHG-V Nelson Lee, M.A.Sc., P.Eng., GHG-V Nancy Wellhausen Kathleen Dunnett, P. Eng. N/A Nancy Wellhausen Nelson Lee, M.A.Sc., P.Eng., GHG-V Verification Date July 15, 2016 September 19, 2016 Site Visit Date August 10, 2016 Report Date September 28, 2016 iii Verification Report ATCO Oldman_IFU.docx

6 TABLE OF CONTENTS SUMMARY... I VERIFICATION SUMMARY... III 1.0 INTRODUCTION Objective Scope Level of Assurance Verification Criteria Materiality METHODOLOGY Verification Strategy Procedure Verification Procedures Verification Steps and Site Visit Risk Assessment Verification / Sampling Plan Team Schedule RESULTS Assessment of Internal Data Management and Controls Assessment of GHG Data and Information B1 Electricity Generation P1 Facility Operation and P2 Fuel Extraction and Processing Assessment Against Criteria Evaluation of GHG Assertion Summary of Findings VERIFICATION STATEMENT CONFIRMATIONS LIMITATIONS OF LIABILITY CLOSURE iv Verification Report ATCO Oldman_IFU.docx

7 LIST OF TABLES IN TEXT Table 1: Verification Scope... 2 Table 2: Verification Procedures... 4 Table 3: Rating Matrix for Inherent Risk and Control Risk... 6 Table 4: Scoring Definition... 7 Table 5: Risk Assessment for Applicable Emission Sources... 7 Table 6: Verification Team... 8 Table 7: Schedule of Verification Activities... 8 Table 8: Summary of Internal Controls Table 9: Eligibility Criteria Assessment LIST OF FIGURES IN TEXT Figure 1: Verification Steps... 5 Figure 2: Summary of Internal Data Management and Data Flow... 9 Figure 3: Verification Procedures for B1 Electricity Generation APPENDIX SECTIONS APPENDICES Appendix A Appendix B Appendix C Appendix D Appendix E Appendix F Verification Plan Statement Of Qualification Finding Log Statement of Verification Conflict of Interest Checklist Tetra Tech s General Conditions v Verification Report ATCO Oldman_IFU.docx

8 LIMITATIONS OF REPORT This report and its contents are intended for the sole use of ATCO Power Canada Ltd. and their agents. Tetra Tech EBA Inc. (Tetra Tech EBA) does not accept any responsibility for the accuracy of any of the data, the analysis, or the recommendations contained or referenced in the report when the report is used or relied upon by any Party other than ATCO Power Canada Ltd., or for any Project other than the proposed development at the subject site. Any such unauthorized use of this report is at the sole risk of the user. Use of this report is subject to the terms and conditions stated in Tetra Tech EBA s Services Agreement. Tetra Tech EBA s General Conditions are provided in Appendix F of this report. Verification Report ATCO Oldman_IFU.docx vi

9 1.0 INTRODUCTION Tetra Tech EBA Inc. (Tetra Tech) was contracted by ATCO Power Canada Ltd. (ATCO Power) to conduct verification of greenhouse gas (GHG) emission reductions from the Oldman River Hydroelectric Power Plant (the Project) for the period of January 1, 2016 May 31, The Oldman plant was implemented on an existing reservoir at the Oldman River Dam. The Project is a water powered electricity generation project located at LSD W4M, 9 km northeast of Pincher Creek, Alberta, at the Oldman River Dam. The Project is owned by ATCO Power and the Piikani Oldman Hydro Limited Partnership (POHLP). The Project is operated by ATCO Power (Facility Operator). The project is comprised of two 16 MW turbines for a total capacity of approximately 32 MW. Electricity is generated year round, with higher generation loads occurring between May to September when the water level is highest in the reservoir. Summary of Offset Project Baseline The baseline condition for the Project is that an equivalent quantity of electricity would have been generated from either grid-connected or off-grid facilities Summary of Changes to Baseline or at the Project Condition There are no changes to the Project operation since baseline. Since October 2010, the 15-minute data for electricity generation provided to the Alberta Electric System Operator (AESO) has been used, instead of hourly data prior to October OBJECTIVE The objective of the verification is to provide an independent assessment of the offset project to identify any material and immaterial errors, omission or misrepresentations and to provide our opinion on the GHG Assertion in the Offset Project Report. 1.2 SCOPE The scope of this project level emission reduction verification includes the project boundaries, physical infrastructure, activities, technologies, and processes of the project, GHG sources, sinks, and/or reservoirs (SSRs), types of GHGs, and time periods covered. The scope of the verification is listed in Table 1. \Verification Report ATCO Oldman_IFU.docx 1

10 Table 1: Verification Scope Project Oldman River Hydroelectric Power Plant Geography Organization Activities and Processes SSRs * GHG GHG Assertion Located 9km northeast of Pincher Creek, Alberta at the Oldman River Dam; LSD W4M ATCO Power Canada Ltd. Hydroelectricity Generation Baseline: B1 Electricity Generation Project: P1 Facility Operation and P2 Fuel Extraction and Processing Carbon dioxide (CO2), Methane (CH4), Nitrous oxide (N2O) 21,697 t CO2 Time Period January 1, 2016 to May 31, 2016 * Emission sources are specified in the Quantification Protocol for Low-retention, Water-powered Electricity Generation as Run-of-river or on an Existing Reservoir (Version 1, May 2008). Alphanumerics refer to specific sources in the Protocol. 1.3 LEVEL OF ASSURANCE The scope and level of effort of this verification is planned to achieve a reasonable level of assurance as required to satisfy requirements of the Specified Gas Emitter Regulation (SGER). The level of assurance is used to determine the depth of detail that a verifier designs into their verification plan to determine if there are any material errors, omissions, or misrepresentations. Reasonable level of assurance is to evaluate whether the GHG assertion is deemed to be presented fairly and substantiated by sufficient and appropriate evidence. As such, the verification is to provide positive, but not absolute assurance regarding the GHG assertions. 1.4 VERIFICATION CRITERIA The verification assesses the Project against Alberta Offset program eligibility criteria, including: Occur in Alberta; Result from actions not otherwise required by laws and be beyond business as usual and sector common practices; Result from actions taken on or after January 1, 2002; Be real, demonstrable, quantifiable, and verifiable; Have clearly established ownership; and Be counted once for compliance purpose. \Verification Report ATCO Oldman_IFU.docx 2

11 The verification assesses the Project against the following program criteria and relevant supporting documentation: Alberta s Climate Change and Emissions Management Act, S.A. 2003, c. C-16.7; Alberta Specified Gas Emitters Regulation (SGER), 2007; Alberta SGER, Technical Guidance Document for Offset Project Developers (Version 4.0, February 2013); Alberta SGER, Technical Guidance for Greenhouse Gas Verification at Reasonable Level Assurance (Version 1.0, January 2013); Quantification Protocol for Quantification Protocol for Low-retention, Water-powered Electricity Generation as Run-of-river or on an Existing Reservoir (Version 1, May 2008); Offset Project Plan for Oldman River Hydroelectric Power Plant; and Offset Project Report for Oldman River Hydroelectric Power Plant. 1.5 MATERIALITY A 5% materiality threshold is set to assess errors, omissions, and misrepresentations in the GHG assertion as required by the SGER. Quantitative discrepancies are aggregated and assessed on the basis of net and absolute values. Qualitative discrepancies are evaluated by professional judgement of the verification body, and determined if the discrepancies could be deemed to be material errors. 2.0 METHODOLOGY The verification is performed according to ISO : Specification with Guidance for the Validation and Verification of GHG Assertions. 2.1 VERIFICATION STRATEGY The approach used in this verification includes a combination of substantive procedures and test of controls. Tetra Tech uses predominantly substantive procedures during the verification process, with a focus on source data and evidence gathered during site visits and sampling procedures. Tetra Tech has developed the following steps to substantiate the GHG assertion: Conducted a site visit to confirm the boundary, physical sources and sinks within the Project boundary. Observed, interviewed personnel, and verified various processes, instrumentation and data management procedures during the site visit. Conducted sampling on primary documentation to confirm the processes resulting in the GHG assertions. Reviewed original data sources and calculations. Controls reliance was used in supporting the substantive approach as described above. Procedures used in this verification include inspection, observation, inquiry, confirmation, recalculation, and analytics test. The detailed verification procedures are provided in Section 2.2. Verification Report ATCO Oldman_IFU.docx 3

12 2.2 PROCEDURE Verification Procedures Verification procedures for the key components are provided in Table 2. Table 2: Verification Procedures Verification Component Description of the nature, scale and complexity of the verification activity Procedures The verification is conducted for the Oldman River Hydroelectric Power Plant (Oldman plant) for the period of January 1, 2016 May 31, Emission reductions are calculated from a theoretical baseline of the emissions that would have been emitted with the generation of an equivalent quantity of electricity based on an established electricity displacement factor. The baseline is dynamic as the quantity of electricity produced will change each year. As specified in the Protocol, the GHG sources include: Baseline: B1 Electricity Generation Project: P1 Facility Operation and P2 Fuel Extraction and Processing Comparability with the baseline Confidence and completeness of the responsible party s GHG information and assertion Assessment of GHG information system and its controls Assessment of GHG data and information Assessment against criteria Evaluation of the GHG Assertion ISO Principle Relevance ISO Principle Completeness The Project has a dynamic baseline Conduct a site tour to determine GHG sources and compare with the Protocol and calculation tool for completeness. Check the quantification against the Protocol. Interview personnel for completing GHG quantification. Review data collection and transfer processes. Interview personnel for internal control procedures. Inquiry of data verification procedures for double entries. Examine diesel fuel inspection. Examine the electricity generation. Compare SSRs inspected through site visit to the GHG identified in the Project Report and calculator. Review raw data, including metering data and third party records. Review emission factors used. Review and check against related criteria. Conduct site visit for physical boundary. Recalculate GHG assertions. Evaluate supporting documents. Review the supporting documents to determine if the appropriate data sources are used to quantify, monitor, or estimate emission sources. Review the justification of exclusion or aggregation of minor GHG sources or the number of data points monitored. Conduct a site tour to determine GHG sources and compare with the Protocol and calculator for completeness. Review the process diagram for facility boundary. 4 \Verification Report ATCO Oldman_IFU.docx

13 Verification Component ISO Principle Consistency ISO Principle Accuracy ISO Principle Transparency ISO Principle Conservativeness Procedures Confirm the uniform calculations are employed to enable meaningful comparisons. Review the justification for changes made for the reporting period. Review the measurements and estimates used to support the GHG assertion. Review the procedures and estimates for missing data. Review the calculations and supporting documents. Confirm assumptions, calculations, and supporting materials are clearly stated and referenced. Inspect highly uncertain data sources. Confirm the uncertain data sources utilized result in an underestimation of the GHG assertion Verification Steps and Site Visit The verification follows the steps outlined in the following diagram (Figure 1). Planning Gain understanding of technical operations and processes Gain understanding of data management Assessment Risk assessment and planning analytics Contribution analysis and Materiality analysis Verification plan and Sampling plan Verification Conduct verification procedures Conduct site visit Discuss findings log Report Senior review and independent peer review Issued for Review verification report Issued for Use report Figure 1: Verification Steps 5 Verification Report ATCO Oldman_IFU.docx

14 Site Visit Mr. Min Si conducted the site visit on August 10, The purpose of the site visit was to gain understanding of the offset project s operation, equipment, and control processes for assessment of the Project s conformance with the criteria. During the site visit, Mr. Si was accompanied by Ms. Anne Vigneau of ATCO. The emission sources, various processes, data acquisition, on-site records handling process, and meter location were observed. The control devices that are used to collect and monitor activity data for emission calculations were observed. Electricity meter serial numbers were crosschecked against the numbers in the OPP. On-site operator was interviewed for data transfer process, diesel dip procedures, data transfer processes Risk Assessment As part of the verification process, a risked-based verification and sampling plan must be developed that outlines: The amount and type of evidence necessary to achieve the agreed level of assurances; Methodologies for determining representative samples; and Risks of potential errors, omissions, or misrepresentation. Tetra Tech s verification team utilizes the risk assessment process to develop a compliant verification and sampling plan. The risk assessment includes considerations associated with regulatory requirements, GHG program requirements, industry/sector specific factors, and other non-technical risks. The risk assessment considers inherent risk, control risk and detection risk. Inherent risk is the Responsible Party s risk of material error, omission, or discrepancy due to the complexity of the facility or lack of capacity by staff at the facility. Control risk is the risk that the Responsible Party s control system will not detect and rectify a material error, omission or discrepancy. Detection risk is the risk that the Tetra Tech verification team will not identify a material discrepancy. The inherent risk and control risk are rated by likelihood multiplied by consequence in accordance with the matrix provided in Table 3. The detection risk is to balance out the combination of the inherent and control risks. Table 3: Rating Matrix for Inherent Risk and Control Risk Consequence Likelihood Risk Matrix Immaterial Minor Moderate Major Material Almost Certain Likely Possible Unlikely The definition for the scoring is provided in Table 4, adapted from IPCC \Verification Report ATCO Oldman_IFU.docx 6

15 Table 4: Scoring Definition Score Likelihood Consequence 5 Possibility of Misstatement >95% Misstated GHG Assertion (threshold) >5% 4 66% < Possibility of Misstatement <95% 4% < Misstated GHG Assertion <5% 3 33% < Possibility of Misstatement <66% 3% < Misstated GHG Assertion <4% 2 5% < Possibility of Misstatement <33% 1% < Misstated GHG Assertion<3% 1 Possibility of Misstatement <5% <1% Misstated GHG Assertion Inherent risk is determined to be low based on the following: Quantification methodology is established by the Protocol; Limited emission sources; and Major source is metered Control risk is determined to be low based on the following: ATCO has completed several years of offset project reporting; and ATCO completes an internal senior review in order to check both calculations and reports for transcription errors and omissions, correctly functioning links and formulas as part of their quality assurance/quality control (low risk). Detection risk is the risk that Tetra Tech s procedures do not detect a misstatement in the GHG Assertion. The overall verification risk must be low to achieve a reasonable level of assurance. As specified in the Verification Technical Guidance, the design of Tetra Tech s detection risk procedures will as a minimum, satisfy a medium risk level as both the inherent risk and control risk are low. The application of Tetra Tech s procedures are designed to achieve an overall low verification risk. The risk assessment for the applicable emission sources is provided in Table 5. Table 5: Risk Assessment for Applicable Emission Sources Applicable Emission Sources Inherent Control B1 Electricity Generation Low Low P1 Facility Operation and P2 Fuel Extraction and Processing Low Low Verification Report ATCO Oldman_IFU.docx 7

16 2.2.4 Verification / Sampling Plan Verifier sampled 100% of evidence. The type and amount of evidence reviewed for each emission source is provided in the final Verification Plan (Appendix A). 2.3 TEAM The verification team is included in Table 6 and the Statement of Qualification is provided in Appendix B. Table 6: Verification Team Name Min Si, M.N.R.M., GHG-V Nelson Lee, M.A.Sc., P.Eng. Nancy Wellhausen Kathleen Dunnett, P.Eng. Role Lead Verifier Designated Signing Authority Independent Peer Reviewer Verifier 2.4 SCHEDULE The schedule for the verification is presented in Table 7. Table 7: Schedule of Verification Activities Task Completion Date Kick-off Meeting July 15, 2016 Site Visit August 10, 2016 Submit Issued for Review Report September 16, 2016 Issued for Use Report Delivered September 28, 2016 \Verification Report ATCO Oldman_IFU.docx 8

17 3.0 RESULTS The included GHG emissions identified in the Protocol were observed, assessed, and evaluated. 3.1 ASSESSMENT OF INTERNAL DATA MANAGEMENT AND CONTROLS A summary of ATCO s internal data management and data flow is provided in Figure 2. ATCO Electric Meter Monthly diesel fuel dips Diesel supplier's invoice 15 minute generation Fuel dips and invoice reconciliation data SAS Information Delivery Portal 2016 OMRH Fuel Dip Records Hourly net generation spreadsheet GHG Calculation Tool Offset Project Report Manual Automatic Figure 2: Summary of Internal Data Management and Data Flow The GHG data management system and its controls are assessed through a combination of verifier site visit activities, interviews with staff involved in the data flow and review of the data itself. These activities verify the data flow process and information management system. A summary of ATCO s internal controls are provided in Table 8. Verification Report ATCO Oldman_IFU.docx 9

18 Table 8: Summary of Internal Controls Reporting Element Data Source Controls Electricity Diesel GHG Calculator ATCO Electric meter (3 rd party) SAS information delivery portal 2016 Hourly Net Generation OMRH Monthly inspection Custom Excel based calculator SAS data downloaded monthly by commercial analyst Data manually entered into GHG quantification tool Data input and calculation reviewed by ATCO environmental staff Weekly and monthly inspection reports were reviewed and signed off by Supervisor, and then transferred to environmental personnel Environment personnel reviewed the electronic record against the hard copy records Quantification completed by Environment Advisor and reviewed by another personnel of ATCO Offset report Reviewed by Environmental Team at ATCO The internal data management and controls are assessed based on the review of the Offset Project Plan, observations during the site visits, and interviews with key project personnel. Based on the controls procedures established and performed by ATCO, the internal data management and controls for the offset project are deemed to be adequate. 3.2 ASSESSMENT OF GHG DATA AND INFORMATION B1 Electricity Generation The emissions from electricity generation is calculated from the metered electricity data multiplied by electricity grid displacement factor. The verification procedures along the data flow are provided in Figure 3. \Verification Report ATCO Oldman_IFU.docx 10

19 ACTO Data flow Verifier Procedures ATCO Electric Meter Observe meter location Review calibration 15 minute generation data Review the raw data SAS Information Delivery Portal Review the data transfer process Hourly net generation spreadsheet Compare hourly data with 15 minute data GHG Calculator Review calculation Check data use Offset project report Check for consistency Manual Automatic Figure 3: Verification Procedures for B1 Electricity Generation Small discrepancies of MWH in some months were noted between hourly electricity generation data and 15 minutes generation data file. The discrepancy is considered as a rounding issue. The GHG data and information provided to support the GHG assertion is deemed to be appropriate and sufficient P1 Facility Operation and P2 Fuel Extraction and Processing Diesel is used by an on-site backup generator that is tested monthly. The on-site operator produces monthly inspection reports. The inspection reports were reviewed and signed off by the supervisor and manually entered into the spreadsheet. The hard copy inspection reports are stored on site. The diesel consumption is based on the dip measurement before and after the generator test. The emission factors for diesel combustion and production are taken from the Alberta Environment and Parks (AEP) Emission Factor handbook. The GHG data and supporting information are deemed to be appropriate and sufficient. Verification Report ATCO Oldman_IFU.docx 11

20 3.3 ASSESSMENT AGAINST CRITERIA The result of the assessment against program eligibility criteria is provided in Table 9. Table 9: Eligibility Criteria Assessment Offset Eligibility Criteria Assessment of Eligibility Criteria Occur in Alberta Result from actions not required by law Result from actions taken on or after January 1, 2002 and occur on or after January 1, 2002 Real and demonstrable Quantifiable and measurable Have clearly established ownership Counted once for compliance purposes Implemented according to a government approved protocol (for offset projects) Verified by a qualified person meeting the requirements under Section 18 of SGER. Registered on the Alberta Emission Offset Registry Site visit confirmed the project physical location. No regulations required for the project implementation. Project was implemented in June Site visit confirmed the existence of the project. Activity data is measured and emissions are quantified using approved protocol. Ownership of emissions credits is clearly established in the Joint Venture Agreement between the Project owners. The Facility Operator has a written agreement from the Project owners to register all available carbon dioxide equivalent emission reduction credits associated with the Project on behalf of the owners. The offset credits will be serialized on the CSA Carbon Registry. Approved Protocol is used. Verifier meets the requirement under Section 18 of SGER. Project registered under CSA Carbon Registry Alberta Emission Offset Registry. 3.4 EVALUATION OF GHG ASSERTION The verification opinion is that the GHG Assertion meets the requirements of the SGER. The GHG data and supporting documents are deemed to be sufficient and appropriate. The GHG Assertion is calculated in accordance with the approved quantification protocol. It is our opinion that 21,697 t CO2e of the emission reductions meet the materiality requirements and the reasonable level assurance. 3.5 SUMMARY OF FINDINGS There are unresolved discrepancies in the GHG Assertion. A findings log is provided in Appendix C. \Verification Report ATCO Oldman_IFU.docx 12

21 4.0 VERIFICATION STATEMENT Based on our review, it is our opinion that the Emission Reductions of 21,697 t CO2e contained in the GHG Assertion generated from the Oldman River Hydroelectric Power Plant for the period of January 1, 2016 May 31, 2016 are materially correct and presented fairly in accordance with the relevant criteria. The Statement of Verification is provided in Appendix D. 5.0 CONFIRMATIONS As required by AEP, the verifier has confirmed the following information: Consistency of offset project information across offset project documentation; Offset project location; Methodology document/project Report exists; Offset project contact and the amount of GHG emission reductions; and Completeness and accuracy of process and data flow diagram. 6.0 LIMITATIONS OF LIABILITY Tetra Tech has undertaken the verification of the asserted emission reductions associated with the ATCO Power Canada Ltd. (ATCO) s Oldman River Hydroelectric Power Plant for the period of January 1, 2016 May 31, 2016 in accordance with Technical Guidance for Offset Project Developers (Version 4.0, February 2013). Tetra Tech has assessed the offset project GHG assertions using reasonably ascertainable information as defined by ISO The assessment represents the condition in the subject area at the time of the assessment. Tetra Tech did not conduct direct GHG emissions monitoring or other actual environmental data sampling or analysis as part of this verification. The purpose of this report is to identify noted exceptions and observations, in the quantification of emission reductions. This report is not intended to imply exhaustive compliance or non-compliance by the verification team. The verification team has made diligent effort to sample applicable information available regarding emission reductions during the verification. It should be noted that the inherent limitation in verification sampling and review practices may result in the verifier not identifying all potential aspects of the project. Observations, exceptions and conclusions are based on the judgement of the verifier. The Conflict of Interest Checklist is provided in Appendix E. Verification Report ATCO Oldman_IFU.docx 13

22

23 APPENDIX A VERIFICATION PLAN 1 Verification Report ATCO Oldman_IFU.docx

24 September 28, 2016 ATCO Power Canada Ltd. 400, th Avenue SW Calgary, AB T2R 1P3 ISSUED FOR USE FILE: ENV.CENV Via Attention: Subject: Anne Vigneau Environment Advisor Verification Plan Oldman River Hydroelectric Power Plant Project (January 1, 2016 May 31, 2016) 1.0 INTRODUCTION Tetra Tech EBA Inc. (Tetra Tech) was contracted by ATCO Power Canada Ltd. (ATCO) to verify Greenhouse Gas (GHG) emission reductions from the Oldman River Hydroelectric Power Plant (Oldman plant) for the period of January 1, 2016 May 31, The Oldman plant was installed in June 2003 on an existing reservoir at the Oldman River Dam. 1.1 OBJECTIVE The objective of the verification is to provide an independent assessment of the offset project to identify any material and immaterial errors, omissions or misrepresentations and to provide our opinion that the GHG assertion in the Offset Project Report is reliable, and of sufficient quality, and that it meets applicable eligibility and performance criteria. 1.2 ASSURANCE The scope and level of effort of this verification is planned to achieve a reasonable level of assurance as required by the Specified Gas Emitter Regulation (SGER). The level of assurance is used to determine the depth of detail that a verifier designs into their verification plan to identify if there are any material errors, omissions, or misrepresentations. A reasonable level of assurance is to evaluate whether the GHG assertion is deemed to be presented fairly and substantiated by sufficient and appropriate evidence. As such, the verification is to provide positive, but not absolute assurance regarding the GHG assertions 1.3 SCOPE The scope of this project level emission reduction verification includes the project boundaries, physical infrastructure, activities, technologies, and processes of the project, GHG sources, sinks, and/or reservoirs (SSRs), types of GHGs, and time periods covered. The scope of the verification is listed in Table 1. Tetra Tech EBA Inc. Riverbend Atrium One, 115, 200 Rivercrest Drive SE Calgary, AB T2C 2X5 CANADA Tel Fax

25 VERIFICATION PLAN FOR 2016 ATCO OLDMAN RIVER PROJECT Table 1: Verification Scope Project Geography Organization Activities and Processes SSRs * GHG GHG Assertion Oldman River Hydroelectric Power Plant Located 9km northeast of Pincher Creek, Alberta at the Oldman River Dam; LSD W4M ATCO Power Canada Ltd. Power Generation Baseline: B1 Electricity Generation Project: P1 Facility Operation and P2 Fuel Extraction and Processing Carbon dioxide (CO2), Methane (CH4), Nitrous oxide (N2O) 21,697 tonne CO2e Time Period January 1, 2016 May 31, 2016 * Emission sources are specified in the Quantification Protocol for Low-retention, Water-powered Electricity Generation as Run-of-river or on an Existing Reservoir (Version 1, May 2008). Alphanumerics refer to specific sources in the Protocol. 1.4 VERIFICATION STANDARDS The verification is performed according to ISO : Specification with Guidance for the Validation and Verification of GHG Assertions. 1.5 VERIFICATION CRITERIA The verification assesses the project against Alberta Offset program eligibility criteria, including: Occur in Alberta; Result from actions not otherwise required by laws and be beyond business as usual and sector common practices; Result from actions taken on or after January 1, 2002; Occur on or after January, 2002; Be real, demonstrable, quantifiable, and verifiable; Have clearly established ownership; and Be counted once for compliance purpose. The verification assesses the project against the following program criteria and relevant supporting documentation: Alberta s Climate Change and Emissions Management Act, S.A. 2003, c. C-16.7; Alberta Specified Gas Emitter Regulation (SGER), 2007; Alberta SGER, Technical Guidance Document for Offset Project Developers (Version 4.0, February 2013); Alberta SGER, Technical Guidance for Greenhouse Gas Verification at Reasonable Level Assurance (Version 1.0, January 2013); \Verification Plan ATCO Oldman.docx 2

26 VERIFICATION PLAN FOR 2016 ATCO OLDMAN RIVER PROJECT Quantification Protocol for Quantification Protocol for Low-retention, Water-powered Electricity Generation as Run-of-river or on an Existing Reservoir (Version 1, May 2008); Offset Project Plan for Oldman River Hydroelectric Power Plant; and Offset Project Report for Oldman River Hydroelectric Power Plant. 1.6 MATERIALITY A 5% materiality threshold is set to assess errors, omissions, and misrepresentations in the GHG assertion as required by the SGER for offset projects. Quantitative discrepancies are aggregated and assessed on the basis of net and absolute values. Qualitative discrepancies are evaluated by the verification body using professional judgement to determine if the discrepancies could be deemed to be material errors. 2.0 DATA MANAGEMENT AND CONTROLS A summary of ATCO s internal data management and data flow is provided in Figure 1. ATCO Electric Meter Monthly diesel fuel dips Diesel supplier's invoice 15 minute generation Fuel dips and invoice reconciliation data SAS Information Delivery Portal 2016 OMRH Fuel Dip Records Hourly net generation spreadsheet GHG Calculation Tool Offset Project Report Manual Automatic Figure 1: Data Management and Data Flow 3 Verification Plan ATCO Oldman.docx

27 VERIFICATION PLAN FOR 2016 ATCO OLDMAN RIVER PROJECT The GHG data management system and its controls are assessed through a combination of verifier site visit activities, interviews with staff involved in the data flow, and review of the data itself. These activities verify the data flow process and information management system. A summary of ATCO s control is provided in Table 2. Table 2: Summary of Internal Controls Reporting Element Data Source Controls Electricity Diesel GHG Calculator ATCO electric meter SAS information delivery portal 2016 Hourly Net Generation OMRH Monthly fuel dip records Third party invoices Custom Excel based calculator SAS data downloaded monthly by commercial analyst Data manually entered into GHG quantification tool Data input and calculation reviewed by ATCO environmental staff. Reviewed by accounting and reconciled with fuel dip records Quantification completed by Environment Advisor and reviewed by other ATCO personnel Offset report Reviewed by Environmental Team at ATCO 3.0 TEAM The verification team is presented in Table 3. Table 3: Verification Team Name Min Si, M.N.R.M., GHG-V Nelson Lee, M.A.Sc., P.Eng., GHG-V Nancy Wellhausen Kathleen Dunnett, P.Eng. Role Lead Verifier Designated Signing Authority Independent Peer Reviewer Verifier 4.0 SCHEDULE The schedule for the verification is presented in Table 4. Table 4: Schedule of Verification Activities Task Completion Date Kick-off Meeting July 15, 2016 Site Visit August 10, 2016 Submit Issued for Review Report September 16, 2016 Issued for Use Report Delivered September 28, 2016 \Verification Plan ATCO Oldman.docx 4

28 VERIFICATION PLAN FOR 2016 ATCO OLDMAN RIVER PROJECT 5.0 RISK ASSESSMENT A summary of potential risks identified and the procedure to check these during the verification is provided in Table 5. Table 5: Summary of Risk Identified Category/ Line Item Verification Objective Risk/Concern Identified Procedure Accuracy Inaccuracy Conduct a site visit to determine meter locations and meter ID Review calculations Occurrence and responsibility Non-existence Conduct a site visit GHG Assertion Completeness Cut-off Incomplete emission sources disclosed Improper metering and recording Conduct a site visit Conduct a site visit Review records Consistency Inconsistent quantification Review calculations Review Project Plan and Project Report Classification Inappropriate emissions types, presentation, and description Review calculations Review Project Plan and Project Report Electricity Generation Completeness Improper measurement of electricity import and export Conduct a site visit to determine meter locations and identification numbers Reconcile meter identification numbers with meters identified in Project Plan and Report Trace meter records to emissions calculations Accuracy Inaccurate calculations and measurement for the electricity export Check calculations Inspect calibration records Review QA/QC procedures Diesel Accuracy Inaccurate measurement Inspect raw data Diesel dip records Review QA/QC procedures SF6 Accuracy Leaks and top-ups Interview staff Check reports/records 5 Verification Plan ATCO Oldman.docx

29 VERIFICATION PLAN FOR 2016 ATCO OLDMAN RIVER PROJECT 6.0 SAMPLING PLAN The type and amount of evidence reviewed during the verification are summarized in Table 6. Table 6. Type of Evidence Reporting Element Type of Evidence Amount of Evidence Reviewed Electricity Diesel consumption SF6 Metering data Dip record Inspection Records Records/invoices/reports 12 month hourly records 12 month 15 minute metering data records One fuel Fuel dip record Six monthly inspection reports Leak or top-up record invoices 7.0 CLOSURE We trust this report meets your present requirements. If you have any questions or comments, please contact Min Si ( , Respectfully submitted, Tetra Tech EBA Inc. Prepared by: Min Si, M.N.R.M., GHG-V Lead Verifier Reviewed by: Nelson Lee, M.A.Sc., P.Eng, GHG-V Designated Signing Verifier 6 \Verification Plan ATCO Oldman.docx

30 APPENDIX B STATEMENT OF QUALIFICATION 1 Verification Report ATCO Oldman_IFU.docx

31 September 28, 2016 ATCO Power Canada Ltd. 400, th Avenue SW Calgary, Alberta T2R 1P3 ISSUED FOR USE FILE: ENV.CENV Via Attention: Subject: Anne Vigneau Environment Advisor Statement of Qualification Oldman River Hydroelectric Power Plant Offset Project (January 1, 2016 May 31, 2016) 1.0 INTRODUCTION Tetra Tech EBA Inc. (Tetra Tech) has completed the verification for emission reductions for ATCO Power Canada Ltd. (ATCO) Oldman River Hydroelectric Power Plant (Oldman plant) for the period of January 1, 2016 May 31, Table 1 lists the verification team members and their roles. Table 1: Verification Team Name Min Si, M.N.R.M., GHG-V Nelson Lee, M.A.Sc., P.Eng., GHG-V Nancy Wellhausen Kathleen Dunnett, P.Eng. Role Lead Verifier Designated Signing Authority Independent Peer Reviewer Verifier Mr. Nelson Lee is a professional engineer registered by the Association of Professional Engineers and Geoscientists of Alberta. Mr. Lee is the Designated Signing Authority for the report and satisfies the Section 18 (1)(ii)(A) of the Specified Gas Emitter Regulation (SGER). Each team member has the required technical knowledge of greenhouse gas (GHG) emission quantification methodologies and has experience in completing third-party GHG verifications. The team members satisfy the requirement of technical knowledge under Section 18(b)(i-iii) under the SGER. Tetra Tech EBA Inc. Riverbend Atrium One, 115, 200 Rivercrest Drive SE Calgary, AB T2C 2X5 CANADA Tel Fax

32 STATEMENT OF QUALIFICAITON FOR 2016 ATCO OLDMAN RIVER PROJECT 2.0 VERIFICATION TEAM QUALIFICATIONS The verification team meets the requirements under SGER and contains the required knowledge of GHG emission quantification methodologies. They have experience in completing third party reviews and audits related to emission inventories, including verifications in Alberta. The verification member received training under CSA Part 3 from the CSA group. Mr. Min Si, M.N.R.M., GHG-V, was the Lead Verifier for this verification. Mr. Si is an Environmental Scientist with Tetra Tech in Calgary. He has worked on GHG verification and quantification projects for a wide range of sectors, including oil and gas, pulp and paper, agriculture, manufacturing, etc. His emission experience includes GHG life cycle assessment, GHG quantification and verification for carbon offset projects, compliance report verification, National Pollution Registry Inventory (NPRI) and corporate GHG reporting. Mr. Si has completed CSA ISO Part 3 training. Mr. Nelson Lee, M.A.Sc., P.Eng., GHG-V, was the Designated Signing Authority for this verification. Mr. Lee has a B.Sc. in Chemical Engineering from the University of Alberta, and a M.A.Sc. in Environmental Engineering from the University of British Columbia. He has eight years of experience in Alberta SGER system, and has completed over 10 GHG verifications in Alberta and British Columbia. Mr. Lee completed ISO training, and is a CSA certified GHG verifier, and a California Air Resources Board (ARB) registered offset project verifier. Mr. Lee is a member of the CSA Technical Committee on Climate Change which is also a harmonized mirror committee that represents Canada s interest in the development of international standards through the ISO Technical Committee 207 / Subcommittee 7 on GHG Management and Related Activities. This harmonized committee represents Canada s interest in the development of international standards through the ISO (TC 207 / Subcommittee 7: Greenhouse gas management and related activities). The committee also develops new standards and adopts existing international standards at the Canadian national level. Ms. Nancy Wellhausen was the Peer Reviewer for this verification. Ms. Wellhausen is a senior GHG Lead Verifier and air quality and inventory specialist with over 20 years of experience. She has served in the role of Independent Peer Reviewer for over 30 GHG report verifications in British Columbia and Alberta. She is registered with the California Air Resources Board as a GHG Lead Verifier. Ms. Kathleen Dunnett, P.Eng., was a Verifier for this verification. Ms. Dunnett is a Professional Engineer in the Province of Alberta with a degree in Chemical and Petroleum Engineering. Ms. Dunnett is an Environmental Manager and Auditor with over 20 years of regulatory compliance and environmental management systems experience. Ms. Dunnett has been a verifier for nine GHG projects in Alberta in the forest products, agricultural, pulp & paper, and oil & gas sectors. \Statement of Qualifications ATCO Oldman.docx 2

33 STATEMENT OF QUALIFICAITON FOR 2016 ATCO OLDMAN RIVER PROJECT 3.0 CLOSURE If there are any questions or clarifications regarding the team s qualifications or roles, please contact Min Si ( , Min.Si@tetratech.com) Respectfully submitted, Tetra Tech EBA Inc. Prepared by: Min Si, M.N.R.M., GHG-V Environmental Scientist Reviewed by: Nelson Lee, M.A.Sc., P.Eng, GHG-V Designated Signing Authority 3 Statement of Qualifications ATCO Oldman.docx

34 APPENDIX C FINDING LOG 1 Verification Report ATCO Oldman_IFU.docx

35 FILE: ENV.CENV SEPTEMBER 16, 2016 ISSUED FOR REVIEW Item Description Responses Resolution Conclusion B1 Electricity Generation, January hour 24 hour, there are no data ATCO Electric submits 15 minute generation data to ATCO Power to be consistent with available in the 15 minutes recording, please clarify the data source in the the 15 minute data they provide to the Alberta Electric System Operator (AESO). The 15 minute generation data pulled from AESO is provided. hourly data file, and provide clarification why the 15 minutes data is missing data submitted to ATCO Power is through a secure login SAS Information Delivery Portal, which automatically tabulates the data into an hourly format. The Commercial Analyst downloads the hourly data and tabulates it on a monthly basis, and is provided in the file '2016 Hourly Net Generation OMRH'. This is the file that is used to for the generation data for the offset quantification, the source data. At the verifier's request we pull data in the 15 minute increments, this data was not used in the quantification of the offsets. No further issues B1 Electricity Generation, there is no March 13 3:00 hour ending data in the 15 minutes file, please clarify the data source in the hourly data and provide clarification why the 15 min data is missing See response to minute generation data pulled from AESO is provided. No further issues the calculator is taken data from the dip record spreadsheet, column P average liters/hours. Please explain why column M data is not used? The on site operator reported that approx. 600 liter/re fuel for appro.10 months. So approx. 300 liter for 5 months. The diesel consumed seems off a bit according to the Operator's knowledge. Please explain Column M should have been used rather than column P. This has been update in the quantification file saved as v1 and attached for your review. This did not change the net emission reduction total which still is 21,697. In a normal annual operating period or 10 month period there are usually times when it is not possible to take energy from the grid. During that time the emergency generator runs to support site services, therefore consuming more fuel. During the period of January to May 2016 the emergency generator was not used for more than 3.3 hours in a single month therefore there were not extended periods of time when the generator was used therefore diesel consumption was much below the estimated 300 L usage for a 5 moth period. Error corrected the justification is deemed to appropriate No further issues No further issues the dip record Cell A10 show 2015 Jan 4, but cell Q11 explain it is average of Dec and Feb readings. Please explain what data is used to estimate missing data Column M is the 'Fuel Consumption (adjusted)' values where Monthly consumption = the justification is deemed to fuel consumption during the current month's inspection + fuel consumption occurring appropriate between the current and following month's inspections, as inspections are typically conducted near the beginning of the calendar month. December's fuel consumption (adjusted) was calculated in the previous year and provided in cell M10 which is grey and February's consumption is provide in cell M12. To calculate fuel usage in January due to an erroneous dip the average of December and February was used (M10+M12/2). No further issues

36 APPENDIX D STATEMENT OF VERIFICATION 1 Verification Report ATCO Oldman_IFU.docx

37 September 28, 2016 Alberta Environment and Parks 12th Floor, Baker Centre Street Edmonton, AB T5J 1G4 ISSUED FOR USE FILE: ENV.CENV Attention: Subject: Executive Director Statement of Verification Oldman River Hydroelectric Power Plant Offset Project (January 1, 2016 May 31, 2016) 1.0 INTRODUCTION Tetra Tech EBA Inc. (Tetra Tech) has reviewed the greenhouse green (GHG) emission reduction presented by ATCO Power Canada Ltd. (ATCO) for Oldman River Hydroelectric Power Plant for the period of January 1, 2016 May 31, Emission reductions are calculated from a theoretical baseline of the emissions that would have been emitted with the generation of an equivalent quantity of electricity based on an established electricity displacement factor. The baseline is dynamic as the quantity of electricity produced will change each year. 1.1 OBJECTIVE The objective of the verification is to provide an independent assessment of the offset project to identify any material and immaterial errors, omission or misrepresentations and to provide our opinion that the GHG Assertion in the Offset Project Report is reliable, and of sufficient quality. 1.2 GHG ASSERTION Tetra Tech reviewed the GHG Assertion presented by ATCO for the Oldman River Hydroelectric Power Plant. Total Project Emissions: Total Baseline Emissions: Net Reductions: Materiality: 5% 0.5 t CO2e 21,698 t CO2e 21,697 t CO2e Period: January 1, 2016 May 31, 2016 Tetra Tech EBA Inc. Riverbend Atrium One, 115, 200 Rivercrest Drive SE Calgary, AB T2C 2X5 CANADA Tel Fax

38 STATEMENT OF VERIFICATION FOR 2016 ATCO OLDMAN RIVER PROJECT 1.3 ROLE AND RESPONSIBILITIES ATCO was responsible for the preparation and presentation of information within the Project Report and GHG Assertion. Tetra Tech was responsible for determining whether anything has come to our attention to suggest that the GHG emission reduction is not presented fairly in accordance with Alberta Environment and Parks (AEP) approved quantification methodology, Quantification Protocol for Low-retention, Water-powered Electricity Generation as Run-of-river or on an Existing Reservoir (Version 1, May 2008), the Specified Gas Emitters Regulation (SGER), and associated guidance documents. The Tetra Tech verification team, including roles and responsibilities are listed in Table 1. Table 1: Verification Team Name Role Responsibilities Min Si, M.N.R.M., GHG-V Lead Verifier Lead verification, including site visit and desktop review. Review verification deliverables, adherence to ISO , regulatory compliance, and technical soundness. Nelson Lee, M.A.S., P.Eng. Designated Signing Authority Review the verification procedures Nancy Wellhausen Kathleen Dunnett P.Eng. Independent Peer Reviewer Verifier Independently review verification deliverables for adherence to ISO and regulatory compliance Assist with verification activities, including verification planning, desktop review, and verification report. 2.0 SCOPE 2.1 PROGRAM CRITERIA The verification assesses the Project against Alberta Offset program eligibility criteria, including: Occur in Alberta; Result from actions not otherwise required by laws and be beyond business as usual and sector common practices; Result from actions taken on or after January 1, 2002; Occur on or after January, 2002; Be real, demonstrable, quantifiable, and verifiable; Have clearly established ownership; and Be counted once for compliance purpose. \Statement of Verification ATCO Oldman.docx 2

39 STATEMENT OF VERIFICATION FOR 2016 ATCO OLDMAN RIVER PROJECT The verification assesses the Project against the following program criteria and relevant supporting documentation: Alberta s Climate Change and Emissions Management Act, S.A. 2003, c. C-16.7; Alberta Specified Gas Emitters Regulation (SGER), 2007; Alberta SGER, Technical Guidance Document for Offset Project Developers (Version 4.0, February 2013); Alberta SGER, Technical Guidance for Greenhouse Gas Verification at Reasonable Level Assurance (Version 1.0, January 2013); Quantification Protocol for Quantification Protocol for Low-retention, Water-powered Electricity Generation as Run-of-river or on an Existing Reservoir (Version 1, May 2008); Offset Project Plan for Oldman River Hydroelectric Power Plant; and Offset Project Report for Oldman River Hydroelectric Power Plant. 2.2 STANDARD The scope and level of effort of this verification were conducted to a reasonable level of assurance in accordance with ISO : Specification with Guidance for the Validation and Verification of GHG Assertions. 2.3 PROCEDURES The verification procedures were developed based on the results of our risk assessment for the GHG data and information as well as Responsibility s control procedures. Tetra Tech verification team reviewed, recalculated, vouched, retraced, and confirmed GHG data and information provided by the Responsibility Party. The site visit assessed the Responsibility Party s data management system, examined quality assurance/quality control (QA/QC) procedures, and tested controls in the data management system. The Responsibility Party s data flow process, and risks, controls and processes documents were reviewed. The effectiveness of the data management system s QA/QC procedures and controls was assessed. The detailed verification procedures are provided in the Verification Report and Verification Plan. Statement of Verification ATCO Oldman.docx 3

40

Verification Report Canfor Grande Prairie Sawmill Biomass Energy Project (2016)

Verification Report Canfor Grande Prairie Sawmill Biomass Energy Project (2016) Verification Report Canfor Grande Prairie Sawmill Biomass Energy Project (2016) PRESENTED TO Canadian Forest Products Ltd. FEBRUARY 8, 2017 ISSUED FOR USE FILE: 704-ENW.EENW03030-01 Tetra Tech Canada Inc.

More information

Canfor Grande Prairie Sawmill Biomass Energy Project (January 1, 2017 December 31, 2017)

Canfor Grande Prairie Sawmill Biomass Energy Project (January 1, 2017 December 31, 2017) Verification Report for Offset Project Canfor Grande Prairie Sawmill Biomass Energy Project (January 1, 2017 December 31, 2017) PROPONENT Canfor Green Energy Grande Prairie PREPARED BY Tetra Tech Canada

More information

Green Sky Sustainability Consulting Inc.

Green Sky Sustainability Consulting Inc. Green Sky Sustainability Consulting Inc. Verification Report: GrowTEC Biogas Offset Project August 1, 2015 December 31, 2016 Prepared by: Green Sky Sustainability Consulting Inc. File Number: 2016-Nov

More information

Offset Project Report

Offset Project Report CHICKADEE CREEK GENERATING STATION Greenhouse Gas Emissions Reduction Offset Project Report For the Period December 8, 2014 November 30, 2016 FINAL REPORT, version 1.0 21 February 2017 Suite 700, 717-7

More information

Verification Report for the TransAlta Corporation Wintering Hills Wind Farm Offset Project

Verification Report for the TransAlta Corporation Wintering Hills Wind Farm Offset Project KPMG Performance Registrar Inc. Box 10426, 777 Dunsmuir Street Vancouver BC V7Y 1K3 Canada Telephone (604) 691-3000 (604) 691-3401 Telefax (604) 691-3031 www.kpmg.ca Matthew Toohey TransAlta Corporation

More information

AltaGas Turin Acid Gas Injection Project Verification Report

AltaGas Turin Acid Gas Injection Project Verification Report AltaGas Processing Partnership AltaGas Turin Acid Gas Injection Project Verification Report March 9, 2017 +1 (604) 353-0264 www.brightspot.co info@brightspot.co This page intentionally blank Statement

More information

Verification Report for TransAlta Corporation Macleod Flats Wind Turbine Offset Project

Verification Report for TransAlta Corporation Macleod Flats Wind Turbine Offset Project KPMG Performance Registrar Inc. Box 10426, 777 Dunsmuir Street Vancouver BC V7Y 1K3 Canada Telephone (604) 691-3000 (604) 691-3401 Telefax (604) 691-3031 www.kpmg.ca Martina Damm Emissions Specialist,

More information

Verification Report for Kruger Products LP New Westminster Biomass Gasification Project January 1, 2010 December 31, 2010 Reporting Period

Verification Report for Kruger Products LP New Westminster Biomass Gasification Project January 1, 2010 December 31, 2010 Reporting Period Verification Report for Kruger Products LP New Westminster Biomass Gasification Project January 1, 2010 December 31, 2010 Reporting Period Prepared for: Kruger Products LP May 13, 2011 Ruby Canyon Engineering

More information

Verification Report for Permolex Ltd. Red Deer Ethanol Production Expansion Offset Project ( )

Verification Report for Permolex Ltd. Red Deer Ethanol Production Expansion Offset Project ( ) Verification Report for Permolex Ltd. Red Deer Ethanol Production Expansion Offset Project (2011 2014) Prepared for: Permolex Ltd. 8010 Edgar Industrial Crescent Red Deer, AB T4P 3R3 Prepared by: Stantec

More information

Greenhouse Gas Verification Report

Greenhouse Gas Verification Report Greenhouse Gas Verification Report University of Ottawa: 2016 GHG Inventory Prepared for: University of Ottawa ( uottawa ) 75 Laurier Ave E, Ottawa, ON K1N 6N5 Prepared by: Internat Energy Solutions Canada

More information

Verification Report for: Chickadee Creek Generation Station Offset Project Proponent: NRGreen Power Limited Partnership

Verification Report for: Chickadee Creek Generation Station Offset Project Proponent: NRGreen Power Limited Partnership Verification Report for: Proponent: NRGreen Power Limited Partnership Prepared by: ICF Consulting Canada, Inc. Prepared for: Alberta Environment and Parks Version: Final Date: February 27, 2018 Table of

More information

Orica Canada Inc. Nitrous Oxide Abatement from Nitric Acid Production Project NAP2

Orica Canada Inc. Nitrous Oxide Abatement from Nitric Acid Production Project NAP2 Nitrous Oxide Abatement from Nitric Acid Production Project NAP2 Verification Report March 7, 2017 ICF Consulting Canada, Inc. 400 University Avenue, 17 th Floor Toronto, Ontario M5G 1S5 This page intentionally

More information

Verification Report for the TransAlta Renewables Inc. Ardenville Wind Farm Offset Project

Verification Report for the TransAlta Renewables Inc. Ardenville Wind Farm Offset Project KPMG Performance Registrar Inc. Box 10426, 777 Dunsmuir Street Vancouver BC V7Y 1K3 Canada Telephone (604) 691-3000 (604) 691-3401 Telefax (604) 691-3031 www.kpmg.ca Matthew Toohey TransAlta Corporation

More information

Standard for Validation, Verification and Audit

Standard for Validation, Verification and Audit Standard for Validation, Verification and Audit Carbon Competitiveness Incentive Regulation Version 2.0 June 2018 Title: Standard for Validation, Verification and Audit Number: 2.0 Program Name: Carbon

More information

Validation Report, Cover Letter and Statement of Assurance

Validation Report, Cover Letter and Statement of Assurance B.C. Ministry of Environment Climate Investment Branch Validation Report, Cover Letter and Statement of Assurance Page 1 of 19 KPMG Performance Registrar Inc. Box 10426, 777 Dunsmuir Street Vancouver BC

More information

Millar Western Forest Products Ltd. Pulp Mill Refiner Plate Energy Savings Project

Millar Western Forest Products Ltd. Pulp Mill Refiner Plate Energy Savings Project Millar Western Forest Products Ltd. Pulp Mill Refiner Plate Energy Savings Project Project #6796-8882 Verification Report ICF 400 University Avenue, 17 th Floor Toronto, Ontario M5G 1S5 March 9, 2017 This

More information

Validation Report, Cover Letter and Statement of Assurance

Validation Report, Cover Letter and Statement of Assurance B.C. Ministry of Environment Climate Investment Branch Validation Report, Cover Letter and Statement of Assurance Page 1 of 20 7220 Financial Way, Suite 100 Jacksonville, Florida 32256 Phone: 904-470-2200

More information

VERIFICATION REPORT FOR THE COAL MINE METHANE CAPTURE AND USE PROJECT AT THE NORTH ANTELOPE ROCHELLE COAL MINE COMPLEX

VERIFICATION REPORT FOR THE COAL MINE METHANE CAPTURE AND USE PROJECT AT THE NORTH ANTELOPE ROCHELLE COAL MINE COMPLEX VERIFICATION REPORT FOR THE COAL MINE METHANE CAPTURE AND USE PROJECT AT THE NORTH ANTELOPE ROCHELLE COAL MINE COMPLEX Document Prepared By First Environment, Inc. Project Title Coal Mine Methane Capture

More information

VERIFICATION REPORT FOR CAMBRIA 33 ABANDONED MINE METHANE CAPTURE & USE PROJECT

VERIFICATION REPORT FOR CAMBRIA 33 ABANDONED MINE METHANE CAPTURE & USE PROJECT VERIFICATION REPORT FOR CAMBRIA 33 ABANDONED MINE METHANE CAPTURE & USE PROJECT Document Prepared by First Environment, Inc. Project Title Cambria 33 Abandoned Mine Methane Capture & Use Project Version

More information

2016 NAP2 OFFSET PROJECT REPORT FOR ORICA NITRIC ACID PLANT 2 - NITROUS OXIDE ABATEMENT FROM NITRIC ACID PRODUCTION FOR 1 JANUARY TO 31 DECEMBER 2016

2016 NAP2 OFFSET PROJECT REPORT FOR ORICA NITRIC ACID PLANT 2 - NITROUS OXIDE ABATEMENT FROM NITRIC ACID PRODUCTION FOR 1 JANUARY TO 31 DECEMBER 2016 2016 NAP2 OFFSET PROJECT REPORT FOR ORICA NITRIC ACID PLANT 2 - NITROUS OXIDE ABATEMENT FROM NITRIC ACID PRODUCTION FOR 1 JANUARY TO 31 DECEMBER 2016 JANUARY 18, 2017 Project Document Information Project

More information

AQUATERA LANDFILL GAS TO ENERGY OFFSET PROJECT THIRD-PARTY VERIFICATION REPORT

AQUATERA LANDFILL GAS TO ENERGY OFFSET PROJECT THIRD-PARTY VERIFICATION REPORT AQUATERA LANDFILL GAS TO ENERGY OFFSET PROJECT THIRD-PARTY VERIFICATION REPORT REPORTING PERIOD: SEPTEMBER 18, 2016 DECEMBER 31, 2016 Submitted to: Aquatera Utilities Inc. 11101 104 Avenue Grande Prairie,

More information

OFFSET PROJECT REPORT for

OFFSET PROJECT REPORT for OFFSET PROJECT REPORT for CARBON CREDIT SOLUTIONS INC. WIND PROJECT #1 REPORTING PERIOD: JANUARY 1, 2014 DECEMBER 31, 2015 May 2016 Carbon Credit Solutions Inc. 2016 OFFSET PROJECT REPORT for CARBON CREDIT

More information

Waste Heat Recovery Protocol SPECIFIED GAS EMITTERS REGULATION. Withdrawn. SEPTEMBER 2007 Version 1. Page i

Waste Heat Recovery Protocol SPECIFIED GAS EMITTERS REGULATION. Withdrawn. SEPTEMBER 2007 Version 1. Page i SPECIFIED GAS EMITTERS REGULATION QUANTIFICATION PROTOCOL FOR WASTE HEAT RECOVERY PROJECTS SEPTEMBER 2007 Version 1 Page i Disclaimer: The information provided in this document is intended as guidance

More information

FIRST ASSESSMENT REPORT FOR THE REVISIONS TO AMS-III.BC TO INCLUDE MOBILE MACHINERY

FIRST ASSESSMENT REPORT FOR THE REVISIONS TO AMS-III.BC TO INCLUDE MOBILE MACHINERY FIRST ASSESSMENT REPORT FOR THE REVISIONS TO AMS-III.BC TO INCLUDE MOBILE MACHINERY Document Prepared By Stantec Consulting Ltd. Methodology Element Title Revisions to AMS-III.BC to Include Mobile Machinery

More information

Validation Report for Blue Source Canada ULC Noel Electrification Offset Project

Validation Report for Blue Source Canada ULC Noel Electrification Offset Project Validation Report for Blue Source Canada ULC Noel Electrification Offset Project Prepared for: Blue Source Canada ULC Suite 700, 717 7th Ave. SW Calgary, AB, T2P 0Z3 Intended User: Pacific Carbon Trust

More information

Validation Report for Blue Source Canada ULC CNRL Septimus Offset Project

Validation Report for Blue Source Canada ULC CNRL Septimus Offset Project Validation Report for Blue Source Canada ULC CNRL Septimus Offset Project Prepared for: Blue Source Canada ULC Suite 700, 717 7th Ave. SW Calgary, AB, T2P 0Z3 Intended User: Pacific Carbon Trust 976 Meares

More information

Qualifying Explanatory Statement for PAS 2060 Declaration of Achievement to Carbon Neutrality

Qualifying Explanatory Statement for PAS 2060 Declaration of Achievement to Carbon Neutrality SCS Global Services PAS 2060 Qualifying Explanatory Statement Qualifying Explanatory Statement for PAS 2060 Declaration of Achievement to Carbon Neutrality Prepared for: Planet Labs Date Completed: August

More information

Urban Forest Project Verification Protocol. Version 1.0

Urban Forest Project Verification Protocol. Version 1.0 Urban Forest Project Verification Protocol Version 1.0 August 2008 The TABLE OF CONTENTS I. Introduction...1 II. Standard of Verification...2 III. Core Verification Activities...2 Step 1: Identifying Emission

More information

VERIFICATION REPORT ADAMS LAKE BIOENERGY-FIRED ENERGY SYSTEM

VERIFICATION REPORT ADAMS LAKE BIOENERGY-FIRED ENERGY SYSTEM VERIFICATION REPORT ADAMS LAKE BIOENERGY-FIRED ENERGY SYSTEM Prepared For: International Forest Products Limited Adams Lake, British Columbia Prepared by: Conestoga-Rovers & Associates 110-3851 Shell Road

More information

CARGILL HIGH RIVER METHANE CAPTURE OFFSET PROJECT THIRD-PARTY VERIFICATION REPORT

CARGILL HIGH RIVER METHANE CAPTURE OFFSET PROJECT THIRD-PARTY VERIFICATION REPORT CARGILL HIGH RIVER METHANE CAPTURE OFFSET PROJECT THIRD-PARTY VERIFICATION REPORT REPORTING PERIOD: JANUARY 1, 2016 DECEMBER 31, 2016 Submitted to: Blue Source Canada ULC Suite 700, 717 th Avenue SW Calgary,

More information

Reducing GHG Emissions from Fed Cattle Aggregation Project

Reducing GHG Emissions from Fed Cattle Aggregation Project Trimble Canada Corporation and Feedlot Health Management Services Reducing GHG Emissions from Fed Cattle Aggregation Project Verification Report +1 (604) 353-0264 www.brightspot.co info@brightspot.co November

More information

Landfill Bioreactor Protocol May 2008 SPECIFIED GAS EMITTERS REGULATION. Withdrawn. MAY 2008 Version 1. Page 1

Landfill Bioreactor Protocol May 2008 SPECIFIED GAS EMITTERS REGULATION. Withdrawn. MAY 2008 Version 1. Page 1 SPECIFIED GAS EMITTERS REGULATION QUANTIFICATION PROTOCOL FOR AEROBIC LANDFILL BIOREACTOR PROJECTS MAY 2008 Version 1 Page 1 Disclaimer: The information provided in this document is intended as guidance

More information

Landfill Bioreactor Protocol May 2008 SPECIFIED GAS EMITTERS REGULATION. MAY 2008 Version 1. Page 1

Landfill Bioreactor Protocol May 2008 SPECIFIED GAS EMITTERS REGULATION. MAY 2008 Version 1. Page 1 SPECIFIED GAS EMITTERS REGULATION QUANTIFICATION PROTOCOL FOR AEROBIC LANDFILL BIOREACTOR PROJECTS MAY 2008 Version 1 Page 1 Disclaimer: The information provided in this document is intended as guidance

More information

Offset Verification Report for Carbon Credit Solutions Inc. Tillage Project #21

Offset Verification Report for Carbon Credit Solutions Inc. Tillage Project #21 Offset Verification Report for Carbon Credit Solutions Inc. Tillage Project #21 Reporting Period: January 1, 2015 December 1, 2017 Prepared for: Carbon Credit Solutions Inc. For Submission to: Alberta

More information

Point-of-contact name Point-of-contact Point-of-contact phone Lori Cmar (313)

Point-of-contact name Point-of-contact  Point-of-contact phone Lori Cmar (313) VERIFICATION REPORT ORGANIZATION Company name Address Ford Motor Company 290 Town Center Dr. Dearborn MI 48126 Point-of-contact name Point-of-contact email Point-of-contact phone Lori Cmar lcmar@ford.com

More information

GrowTEC Biogas Offset Project. Grow the Energy Circle Ltd.

GrowTEC Biogas Offset Project. Grow the Energy Circle Ltd. Offset Project Report for: GrowTEC Biogas Offset Project Project Developer: Grow the Energy Circle Ltd. 1 st Reporting Period: August 1, 2015 December 31, 2016 Blue Source Canada ULC June 5, 2017 Version

More information

Livestock Project Verification Protocol. Capturing and combusting methane from manure management systems

Livestock Project Verification Protocol. Capturing and combusting methane from manure management systems Livestock Project Verification Protocol Capturing and combusting methane from manure management systems Version 1.0 June, 2007 The Capturing and combusting methane from manure management systems TABLE

More information

Quantification Protocol for Aerobic Composting

Quantification Protocol for Aerobic Composting Quantification Protocol for Aerobic Composting Specified Gas Emitters Regulation Version 2.0 January 2017 Title: Quantification Protocol for Aerobic Composting Number: 2.0 Program Name: Alberta Carbon

More information

Framework Convention on Climate Change. Materiality standard under the clean development mechanism

Framework Convention on Climate Change. Materiality standard under the clean development mechanism United Nations Framework Convention on Climate Change Distr.: General 31 May 2011 English only FCCC/TP/2011/4 Materiality standard under the clean development mechanism Technical paper Summary This document

More information

Corporate Emissions Assessment Protocol

Corporate Emissions Assessment Protocol Corporate Emissions Assessment Protocol For the measurement, management, and reduction of organisations greenhouse gas emissions 1 1 Version 1_4 2 Part 1: Requirements The Carbon Trust About the Carbon

More information

YAPRAK WEIR AND HEPP

YAPRAK WEIR AND HEPP YAPRAK WEIR AND HEPP Document Prepared By: KBS Certification Services Pvt. Ltd. Project Title Yaprak Weir and HEPP Version 01.1 Report ID VCS.15.VER.005 Report Title Client Pages 19 Date of Issue Prepared

More information

REVISION TO AMS-II.M. METHODOLOGY ELEMENT ASSESSMENT REPORT

REVISION TO AMS-II.M. METHODOLOGY ELEMENT ASSESSMENT REPORT REVISION TO AMS-II.M. METHODOLOGY ELEMENT ASSESSMENT REPORT Document Prepared by First Environment, Inc. Methodology Title Revision to AMS-II.M. Energy Efficiency from installation of low-flow water devices

More information

Product Carbon Footprint Protocol

Product Carbon Footprint Protocol Product Carbon Footprint Protocol Required data and documentation to achieve product carbon footprint certification in preparation for communication and labelling. Part 1: Requirements for Certification

More information

Technical Guidance for Offset Protocol Development and Revision

Technical Guidance for Offset Protocol Development and Revision 1 1 1 1 1 1 1 1 0 1 0 1 Technical Guidance for Offset Protocol Development and Revision Draft Version.0 May 01 Title: Number: Program Name: Effective Date: Technical Guidance for Offset Protocol Development

More information

Offset Project Plan for the Aggregated Small-Scale Waste Heat Recovery Project

Offset Project Plan for the Aggregated Small-Scale Waste Heat Recovery Project Offset Project Plan for the Aggregated Small-Scale Waste Heat Recovery 2017-2024 Project Project Developer: Blue Source Canada ULC Crediting Period: January 1, 2017 December 31, 2024 Blue Source Canada

More information

VERIFICATION/CERTIFICATION REPORT PERIODIC VERIFICATION OF THE TROJES HYDROELECTRIC PROJECT IN MEXICO

VERIFICATION/CERTIFICATION REPORT PERIODIC VERIFICATION OF THE TROJES HYDROELECTRIC PROJECT IN MEXICO VERIFICATION/CERTIFICATION REPORT PERIODIC VERIFICATION OF THE TROJES HYDROELECTRIC PROJECT IN MEXICO (Registration Ref No. 0649) Monitoring period: 01 April 2003-30 November 2006. REPORT NO. 2006-2174

More information

Emission Reduction Protocol. Ontario Power Generation - Lennox GS Units 1 to 4 Fuel Switch

Emission Reduction Protocol. Ontario Power Generation - Lennox GS Units 1 to 4 Fuel Switch Emission Reduction Protocol Ontario Power Generation - Lennox GS Units 1 to 4 Fuel Switch 1.0 Introduction In 2000 Lennox completed the conversion at all four units to dual fuel capability (oil and/or

More information

Third Party Auditor s Report Summary of Verification

Third Party Auditor s Report Summary of Verification www.pwc.com/ca Third Party Auditor s Report Summary of Verification Project Report Title: Pragmatic Conferencing GHG Inventory Report 2012 Project Report Date: May 2012 Contents Introduction 1 Project

More information

SBTi Target Submission Form Guidance. TWG-INF-003 Version August 2017

SBTi Target Submission Form Guidance. TWG-INF-003 Version August 2017 SBTi Target Submission Form Guidance TWG-INF-003 Version 1.1 14 August 2017 SBTi Target Submission Form Guidance General guidance Use of this guidance Please read this document carefully before completing

More information

Draft Quantification Protocol for Landfill Gas Capture and Combustion Carbon Competitiveness Incentive Regulation

Draft Quantification Protocol for Landfill Gas Capture and Combustion Carbon Competitiveness Incentive Regulation Draft Quantification Protocol for Landfill Gas Capture and Combustion Carbon Competitiveness Incentive Regulation Draft Version 3.0 January 2018 Title: Draft Quantification Protocol for Landfill Gas Capture

More information

Offset Project Plan Form: Modern Resources Pneumatic Device Electrification Project. Project Developer: Modern Resources Inc.

Offset Project Plan Form: Modern Resources Pneumatic Device Electrification Project. Project Developer: Modern Resources Inc. Offset Project Plan Form: Modern Resources Pneumatic Device Electrification Project Project Developer: Modern Resources Inc. Prepared by: Modern West Advisory Inc. Date: March 29, 2018 Table of Contents

More information

INTERNATIONAL STANDARD

INTERNATIONAL STANDARD INTERNATIONAL STANDARD ISO 14064-2 First edition 2006-03-01 Greenhouse gases Part 2: Specification with guidance at the project level for quantification, monitoring and reporting of greenhouse gas emission

More information

VERIFICATION REPORT OF INNER MONGOLIA HANGJIN YIHEWUSU WIND POWER PROJECT

VERIFICATION REPORT OF INNER MONGOLIA HANGJIN YIHEWUSU WIND POWER PROJECT VERIFICATION REPORT OF INNER MONGOLIA HANGJIN YIHEWUSU WIND POWER PROJECT Document Prepared By China Environmental United Certification Centre Co., Ltd. Project Title Inner Mongolia Hangjin Yihewusu Wind

More information

VERIFICATION REPORT YUNNAN MANGLI HYDROPOWER PROJECT

VERIFICATION REPORT YUNNAN MANGLI HYDROPOWER PROJECT VERIFICATION REPORT YUNNAN MANGLI HYDROPOWER PROJECT Document Prepared By: Bureau Veritas Certification Holding SAS Report No.BVC/China-VR/7066/2012 Project Title Version Report ID Yunnan Mangli Hydropower

More information

Report of Independent Accountants

Report of Independent Accountants Report of Independent Accountants To the Board of Directors and Management of VMware, Inc. We have reviewed VMware Inc. s management assertion, included in the accompanying Appendix A, that the metrics

More information

Towards Sustainable Mining Energy and Greenhouse Gas Emissions Management Protocol

Towards Sustainable Mining Energy and Greenhouse Gas Emissions Management Protocol Towards Sustainable Mining Energy and Greenhouse Gas Emissions Management Protocol TSM ASSESSMENT PROTOCOL A Tool for Assessing Energy Use and Greenhouse Gas Emissions Management Performance Purpose The

More information

Report of Independent Accountants

Report of Independent Accountants To the Board of Directors of Ball Corporation, Report of Independent Accountants We have reviewed management s assertion, included in the accompanying Appendix A, Management Assertion, that the selected

More information

Quantification Protocol for Landfill Gas Capture and Combustion Carbon Competitiveness Incentive Regulation

Quantification Protocol for Landfill Gas Capture and Combustion Carbon Competitiveness Incentive Regulation Quantification Protocol for Landfill Gas Capture and Combustion Carbon Competitiveness Incentive Regulation Version 3.0 November 2018 Title: Quantification Protocol for Landfill Gas Capture and Combustion

More information

Lithuania s Initial Report under the Kyoto Protocol. Calculation of Assigned Amount under Article 7, paragraph 4, of the Kyoto Protocol

Lithuania s Initial Report under the Kyoto Protocol. Calculation of Assigned Amount under Article 7, paragraph 4, of the Kyoto Protocol Lithuania s Initial Report under the Kyoto Protocol Calculation of Assigned Amount under Article 7, paragraph 4, of the Kyoto Protocol Ministry of Environment of the Republic of Lithuania Vilnius, July

More information

Identifying General and Specific Risks Inherent in Project Development and Credit Generation from N 2 O Reduction Methodologies

Identifying General and Specific Risks Inherent in Project Development and Credit Generation from N 2 O Reduction Methodologies Identifying General and Specific Risks Inherent in Project Development and Credit Generation from N 2 O Reduction Methodologies Introduction December 2015 C-AGG Project Implementation Working Group The

More information

Final Proposal for Technical Working Group on Scope 2 Accounting and Reporting October I. Summary of Scope 2 Accounting and Reporting Steps

Final Proposal for Technical Working Group on Scope 2 Accounting and Reporting October I. Summary of Scope 2 Accounting and Reporting Steps Final Proposal for Technical Working Group on Scope 2 Accounting and Reporting October 2013 Proposal Purpose and Outline This Proposal outlines the key accounting and reporting approaches that will be

More information

Greenhouse Gas Inventory Verification for:

Greenhouse Gas Inventory Verification for: Greenhouse Gas Inventory Verification for: Tiger Brands Limited 24 April 2015 Terra Firma Solutions (Pty) Ltd Reg: 2011/134156/07 Suite 1B Madison Place Alphen Office Park Constantia Main Road 7806 Cape

More information

International Auditing and Assurance Standards Board ISA 500. April International Standard on Auditing. Audit Evidence

International Auditing and Assurance Standards Board ISA 500. April International Standard on Auditing. Audit Evidence International Auditing and Assurance Standards Board ISA 500 April 2009 International Standard on Auditing Audit Evidence International Auditing and Assurance Standards Board International Federation of

More information

GREENHOUSE GAS PROJECT REPORT PRISM FARMS BIOMASS HEATING PROJECT

GREENHOUSE GAS PROJECT REPORT PRISM FARMS BIOMASS HEATING PROJECT 11 June 2012 GREENHOUSE GAS PROJECT REPORT PRISM FARMS BIOMASS HEATING PROJECT Prepared By: Blue Source Canada ULC (Authorized Project Contact) Suite 700, 717-7 th Avenue SW Calgary, Alberta T2P 0Z3 T:

More information

Lead or be Led: GHG Reporting and Verification

Lead or be Led: GHG Reporting and Verification Lead or be Led: GHG Reporting and Verification John Fraser Product Manager Environment May 2, 2011 Energy Matters 2011 Peel Region Agenda QMI SAI Overview ISO History GHG Programs Reporting and Verification

More information

STATEMENT OF AUDITING STANDARDS 500 AUDIT EVIDENCE

STATEMENT OF AUDITING STANDARDS 500 AUDIT EVIDENCE STATEMENT OF AUDITING STANDARDS 500 AUDIT EVIDENCE (Issued January 2004) Contents Paragraphs Introduction 1-2 Concept of Audit Evidence 3-6 Sufficient Appropriate Audit Evidence 7-14 The Use of Assertions

More information

Guidance Document HOME ENERGY CALCULATOR

Guidance Document HOME ENERGY CALCULATOR Guidance Document HOMEENERGYCALCULATOR Preparedbythegreenregistry.org 2008 Guidance Document for Green Registry: Home Energy Calculator IMPORTANCE OF THIS CALCULATOR... 2 SCOPE OF ACTIVITY AND EMISSIONS...

More information

Offset Project Plan Pulp Mill Refiner-Plate Energy Savings Project Version 1, October 2009, Amended January 2013 and March 2017

Offset Project Plan Pulp Mill Refiner-Plate Energy Savings Project Version 1, October 2009, Amended January 2013 and March 2017 Millar Western Forest Products Ltd. Offset Project Plan Pulp Mill Refiner-Plate Energy Savings Project Version 1, October 2009, Amended January 2013 and March 2017 Table of Contents Introduction 3 1 Project

More information

Independent Accountants Report

Independent Accountants Report KPMG LLP Suite 2100 1003 Bishop Street Honolulu, HI 96813-6400 Independent Accountants Report The Board of Directors CA Inc.: We have reviewed the accompanying Statement of Greenhouse Gas Emissions for

More information

Report of Independent Accountants

Report of Independent Accountants Report of Independent Accountants To the Board of Directors of VMware, Inc. We have reviewed the accompanying management s assertion, included in Appendix A, that the Metrics identified below 2016 are

More information

HTSUS U.S. ARTICLES ASSEMBLED ABROAD TECHNICAL INFORMATION FOR PRE-ASSESSMENT SURVEY (TIPS)

HTSUS U.S. ARTICLES ASSEMBLED ABROAD TECHNICAL INFORMATION FOR PRE-ASSESSMENT SURVEY (TIPS) HTSUS 9802.00.80 U.S. ARTICLES ASSEMBLED ABROAD TECHNICAL INFORMATION FOR PRE-ASSESSMENT SURVEY (TIPS) TABLE OF CONTENTS PART 1 BACKGROUND...2 PART 2 HTSUS 9802.00.80 GUIDANCE...2 2.1 EXAMPLES OF RED FLAGS...2

More information

Santangou First and Second Grade Hydropower Stations Project MONITORING REPORT

Santangou First and Second Grade Hydropower Stations Project MONITORING REPORT Santangou First and Second Grade Hydropower Stations Project MONITORING REPORT Document Prepared By (Zhijie Duan, South Pole Carbon Asset Management Ltd.) Contact Information (j.duan@southpolecarbon.com)

More information

Guidelines for Quantifying GHG emission. reductions of goods or services through Global. Value Chain

Guidelines for Quantifying GHG emission. reductions of goods or services through Global. Value Chain Guidelines for Quantifying GHG emission reductions of goods or services through Global Value Chain March 2018 Ministry of Economy, Trade and Industry Table of Contents Introduction... 2 1. Use of the Guidelines...

More information

SECTION 1 Audit Statement and Audit Findings

SECTION 1 Audit Statement and Audit Findings Independent Audit Report SECTION 1 Audit Statement and Audit Findings Organisation Being Audited Organisation Name Zoos Victoria Contact person Kiam Yoong Position title Senior Manager, Environmental Sustainability

More information

NISOURCE INC KEY PERFORMANCE INDICATORS INDEPENDENT VERIFICATION STATEMENT

NISOURCE INC KEY PERFORMANCE INDICATORS INDEPENDENT VERIFICATION STATEMENT NISOURCE INC. 2017 KEY PERFORMANCE INDICATORS INDEPENDENT VERIFICATION STATEMENT Introduction Trinity Consultants, Inc. ( Trinity ) was contracted by NiSource Inc. ( NiSource ) to verify its environmental

More information

POLYTECHNIC OF NAMIBIA SCHOOL OF MANAGEMENT SCIENCES

POLYTECHNIC OF NAMIBIA SCHOOL OF MANAGEMENT SCIENCES POLYTECHNIC OF NAMIBIA SCHOOL OF MANAGEMENT SCIENCES DEPARTMENT ACCOUNTING, ECONOMICS & FINANCE 23BACF BACHELOR OF ACCOUNTING COURSE: AUDITING 38 COURSE CODE: AUD312S SECOND OPPORTUNITY EXAMINATION QUESTION

More information

INTERNATIONAL STANDARD ON AUDITING 530 AUDIT SAMPLING AND OTHER MEANS OF TESTING CONTENTS

INTERNATIONAL STANDARD ON AUDITING 530 AUDIT SAMPLING AND OTHER MEANS OF TESTING CONTENTS INTERNATIONAL STANDARD ON AUDITING 530 AUDIT SAMPLING AND OTHER MEANS OF TESTING (Effective for audits of financial statements for periods beginning on or after December 15, 2004) CONTENTS Paragraph Introduction...

More information

Report on Inspection of K. R. Margetson Ltd. (Headquartered in Vancouver, Canada) Public Company Accounting Oversight Board

Report on Inspection of K. R. Margetson Ltd. (Headquartered in Vancouver, Canada) Public Company Accounting Oversight Board 1666 K Street, N.W. Washington, DC 20006 Telephone: (202) 207-9100 Facsimile: (202) 862-8433 www.pcaobus.org Report on 2016 (Headquartered in Vancouver, Canada) Issued by the Public Company Accounting

More information

Sole and Single Source Audit

Sole and Single Source Audit Office of the City Auditor 1200, Scotia Place, Tower 1 10060 Jasper Avenue Edmonton, Alberta T5J 3R8 edmonton.ca/auditor Sole and Single Source Audit September 19, 2016 The Office of the City Auditor conducted

More information

SSE s criteria used for GHG emissions reporting

SSE s criteria used for GHG emissions reporting SSE s criteria used for reporting 1 Introduction This document details the annual greenhouse gas emissions reporting approach used by SSE Plc to report the tonnes of carbon dioxide equivalent (CO2e) during

More information

CPA REVIEW SCHOOL OF THE PHILIPPINES M a n i l a AUDITING THEORY AUDIT PLANNING

CPA REVIEW SCHOOL OF THE PHILIPPINES M a n i l a AUDITING THEORY AUDIT PLANNING CPA REVIEW SCHOOL OF THE PHILIPPINES M a n i l a Related PSAs: PSA 300, 310, 320, 520 and 570 Appointment of the Independent Auditor AUDITING THEORY AUDIT PLANNING Page 1 of 9 Early appointment of the

More information

VERIFICATION REPORT OF THE LUGOUHE HYDROPOWER PROJECT IN SICHUAN PROVINCE, CHINA

VERIFICATION REPORT OF THE LUGOUHE HYDROPOWER PROJECT IN SICHUAN PROVINCE, CHINA VCS Verification Report VERIFICATION REPORT OF THE LUGOUHE HYDROPOWER PROJECT IN SICHUAN PROVINCE, CHINA Voluntary Carbon Standard 2007.1 Report No: VCS 009-06, rev. 03 Germanischer Lloyd Certification

More information

Karen Haugen-Kozyra, M.Sc. P.Ag. Principal, KHK Consulting. May 6, 2010 AFGO Forest Offsets Workshop #2 Ramada Inn, Edmonton

Karen Haugen-Kozyra, M.Sc. P.Ag. Principal, KHK Consulting. May 6, 2010 AFGO Forest Offsets Workshop #2 Ramada Inn, Edmonton Karen Haugen-Kozyra, M.Sc. P.Ag. Principal, KHK Consulting May 6, 2010 AFGO Forest Offsets Workshop #2 Ramada Inn, Edmonton Alberta US Fed Voluntary Carbon Standard *Point Carbon 2010 Western Climate Initiative

More information

Net Zero Waste Abbotsford Composting Facility Offset Project

Net Zero Waste Abbotsford Composting Facility Offset Project Page 1 Net Zero Waste Abbotsford Composting Facility Offset Project Greenhouse Gas Emissions Reduction Report For The Period 1 January, 2015 30 April, 2016 Draft Report, version 1.0 July 29, 2016 (Authorized

More information

ACR VALIDATION AND VERIFICATION STANDARD

ACR VALIDATION AND VERIFICATION STANDARD ACR VALIDATION AND VERIFICATION STANDARD VERSION 1.1 May 2018 VERSION 1.1 May 2018 American Carbon Registry WASHINGTON DC OFFICE c/o Winrock International 2121 Crystal Drive, Suite 500 Arlington, Virginia

More information

10. GREENHOUSE GASES EAST-WEST TIE TRANSMISSION PROJECT AMENDED ENVIRONMENTAL ASSESSMENT REPORT

10. GREENHOUSE GASES EAST-WEST TIE TRANSMISSION PROJECT AMENDED ENVIRONMENTAL ASSESSMENT REPORT 10. GREENHOUSE GASES This section describes and summarizes an assessment of the effects of the East-West Tie Transmission Project (the Project) on gases. Greenhouse gases (GHGs) have the potential to affect

More information

VERIFICATION REPORT PA KHOANG HYDROPOWER PROJECT REPORT NO. GHGCC(E) REVISION NO. 03 GHG CERTIFICATION OFFICE

VERIFICATION REPORT PA KHOANG HYDROPOWER PROJECT REPORT NO. GHGCC(E) REVISION NO. 03 GHG CERTIFICATION OFFICE VERIFICATION REPORT PA KHOANG HYDROPOWER PROJECT REPORT NO. GHGCC(E)12-004 REVISION NO. 03 GHG CERTIFICATION OFFICE KOREA ENERGY MANAGEMENT CORPORATION Date of first issue: Project No.: 19/06/2012 GHGCC(E)12-004

More information

Audit Sampling and Other Means of Testing

Audit Sampling and Other Means of Testing Issued December 2007 International Standard on Auditing Audit Sampling and Other Means of Testing The Malaysian Institute Of Certified Public Accountants (Institut Akauntan Awam Bertauliah Malaysia) INTERNATIONAL

More information

MRR Guidance on Risk assessment and control activities Examples

MRR Guidance on Risk assessment and control activities Examples EUROPEAN COMMISSION DIRECTORATE-GENERAL CLIMATE ACTION Directorate A International and Climate Strategy CLIMA.A.3 - Monitoring, Reporting, Verification Guidance Document MRR Guidance on Risk assessment

More information

Farming 4R Land 4R Toolkit

Farming 4R Land 4R Toolkit Farming 4R Land 4R Toolkit Supporting farmers and communities with practical tools to implement Beneficial Management Practices that protect soil quality and grow agriculture. Contents 1. Introduction...

More information

Green Building Offsets in Alberta Challenges and Opportunities. Chelsea Thomson Capital Power Corporation October 25, 2012

Green Building Offsets in Alberta Challenges and Opportunities. Chelsea Thomson Capital Power Corporation October 25, 2012 Green Building Offsets in Alberta Challenges and Opportunities Chelsea Thomson Capital Power Corporation cthomson@capitalpower.com October 25, 2012 1 Capital Power Capital Power (CPX:TSX) is a growth-oriented

More information

Monitoring and Verification Plan Graneros Plant Fuel Switching Project June Prepared by

Monitoring and Verification Plan Graneros Plant Fuel Switching Project June Prepared by Monitoring and Verification Plan Graneros Plant Fuel Switching Project June 2003 Prepared by MGM International, Inc. Ayacucho 1435, 9 B C1111AAM Buenos Aires Argentina Table of Contents 1. Introduction

More information

TORONTO DISTRICT SCHOOL BOARD ENERGY EFFICIENCY PROJECT GHG REPORT

TORONTO DISTRICT SCHOOL BOARD ENERGY EFFICIENCY PROJECT GHG REPORT TORONTO DISTRICT SCHOOL BOARD ENERGY EFFICIENCY PROJECT GHG REPORT For the Period January 1, 2014 June 30, December 6 th, FINAL REPORT, v3.0 Prepared by: Blue Source Canada ULC (Authorized Project Contact)

More information

Auditing Standards and Practices Council

Auditing Standards and Practices Council Auditing Standards and Practices Council PHILIPPINE STANDARD ON AUDITING 330 THE AUDITOR S PROCEDURES IN RESPONSE TO ASSESSED RISKS PHILIPPINE STANDARD ON AUDITING 330 THE AUDITOR S PROCEDURES IN RESPONSE

More information

GHG Emission Offset Protocols. Or how to turn a biological phenomenon into a financial instrument.

GHG Emission Offset Protocols. Or how to turn a biological phenomenon into a financial instrument. GHG Emission Offset Protocols Or how to turn a biological phenomenon into a financial instrument. Introduction Define offsets Place offsets in context of climate change Review implication of offsets and

More information

Cargill High River Fluidized Bed Boiler Offset Project

Cargill High River Fluidized Bed Boiler Offset Project Cargill High River Fluidized Bed Boiler Offset Project Greenhouse Gas Emissions Reduction Offset Project Report For the Period January 1, 2016 December 31, 2016 FINAL REPORT, version 3.0 May 3, 2017 (Authorized

More information

FIRST METHODOLOGY ASSESSMENT REPORT FOR SULPHUR CONCRETE IN PRECAST APPLICATIONS

FIRST METHODOLOGY ASSESSMENT REPORT FOR SULPHUR CONCRETE IN PRECAST APPLICATIONS FIRST METHODOLOGY ASSESSMENT REPORT FOR SULPHUR CONCRETE IN PRECAST APPLICATIONS Document Prepared By Stantec Consulting Ltd. Methodology Element Title: Quantification Methodology for Use of Sulphur Concrete

More information

VER + Verification Report

VER + Verification Report VER + Verification Report Enecore Carbon Initial Verification and Verification of the First Monitoring Period of the Beijing No.3 Thermal Power Plant Gas-Steam Combined Cycle Project Using Natural Gas

More information

Corporate Responsibility Reporting Criteria 2018 Annual Report

Corporate Responsibility Reporting Criteria 2018 Annual Report Corporate Responsibility Reporting Criteria 2018 Annual Report This document ( the CR Reporting Criteria ) sets out the scope, principles and methodologies used in reporting certain Corporate Responsibility

More information

TOLKO SLAVE LAKE BIOMASS OFFSET PROJECT

TOLKO SLAVE LAKE BIOMASS OFFSET PROJECT TOLKO SLAVE LAKE BIOMASS OFFSET PROJECT Greenhouse Gas Emissions Reduction Offset Project Report For the 2 nd Reporting Period of January 1, 2016 December 31, 2016 FINAL REPORT, version 2.2 September 8,

More information