Lower Mornington Peninsula Supply Area

Size: px
Start display at page:

Download "Lower Mornington Peninsula Supply Area"

Transcription

1 Non Network Options Report RIT-D Report This report presents the sub-transmission network limitations in the lower Mornington Peninsula including options and technical characteristics of non-network options to alleviate those limitations.

2 This page has been intentionally left blank Page 1 of 33

3 Table of Contents 1 Approval and Document Control 3 2 Executive summary 4 3 Introduction 5 4 Identified Need Network overview Description of the identified need Voltage collapse limitation Insufficient thermal capacity in sub-transmission network Bushfire exposure Closing comments on the need for investment Quantification of the identified need 14 5 Key assumptions in relation to the Identified Need Method for quantifying the identified need Expected unserved energy due to voltage collapse limitation Expected unserved energy due to insufficient thermal capacity Forecast maximum demand Characteristic of load profile Plant failure rates Sub-transmission network losses under N-1 condition Plant ratings Value of customer reliability Discount rates 23 6 Potential credible options to address the identified need 24 7 Technical characteristics of non-network options Size and location Time of year Reliability Operation 29 8 Submission Request for submission Next steps 30 9 Abbreviations and Glossary 31 Page 2 of 33

4 1 Approval and Document Control VERSION DATE AUTHOR 1 18 December 2014 UE Network Planning Amendment overview New document Page 3 of 33

5 2 Executive summary The lower Mornington Peninsula is supplied by a 66kV sub-transmission network supplying Dromana (DMA), Rosebud (RBD) and Sorrento (STO) 66/22 kv zone substations. These three zone substations together with other zone substations in the region including Frankston South (FSH), Hastings (HGS) and Mornington (MTN) are supplied from the 220/66 kv transmission connection point known as Tyabb Terminal Station (TBTS), the sole source of electricity supply to the Mornington Peninsula from the Victorian shared transmission network. The 66 kv sub-transmission network which supplies this region is relatively long with the transmission connection point located on the eastern side of the Mornington Peninsula and most of the load centres located on the west side. This sub-transmission network is also highly utilised at maximum demand. On the present forecast, it is estimated that the following sub-transmission lines, which provide electricity supply to the region, will have maximum demands that exceed their N-1 thermal ratings: DMA-RBD No. 1 66kV line; DMA-RBD No kv line; MTN-DMA 66 kv line; TBTS-DMA 66 kv line; and TBTS-MTN No.1 66 kv line. The other more pressing issue is the inability of the network to maintain voltage levels within regulatory limits in the event of an outage of either the MTN-DMA 66 kv line or the TBTS-DMA 66 kv line at maximum demand conditions, with the former being the more severe condition. Given the relatively long distance of existing zone substations and the load centres from the transmission connection point in this region, all credible network options are relatively expensive to implement. United Energy (UE) has identified two potential credible network options that are technically comparable to address the identified need: 1. Install a new HGS-RBD 66 kv line for service by December The estimated capital cost of this option is $25.3 million (±30%). 2. Install a new TBTS-RBD 66 kv line for service by December The estimated capital cost of this option is $26.9 million (±30%). Alternatively, demand reduction or embedded generation up to 30 MVA in summer would be required to address both the thermal and voltage limitations. UE has already received a proposal from one non-network service provider to reduce demand in the lower Mornington Peninsula. Details of this proposal are currently being confirmed. UE welcomes written submissions from other registered participants and interested parties to address the issues described in this consultation report on or before 29 May All Submissions and enquiries should be directed to the United Energy Manager Network Planning at planning@ue.com.au. Page 4 of 33

6 3 Introduction This Non Network Options Report has been prepared by United Energy (UE) in accordance with the requirements of clause (e) of the National Electricity Rules (NER). This report represents the first stage of the consultation process in relation to the application of the Regulatory Investment Test for Distribution (RIT-D) on potential credible options to address the sub-transmission network limitations in the lower Mornington Peninsula. The need for investment and the possible options for addressing limitations have been foreshadowed in UE s 2013 Distribution Annual Planning Report (DAPR). 1 This report: Provides background information on the sub-transmission network limitations in the lower Mornington Peninsula. Identifies the need which UE is seeking to address, together with the assumption used in identifying that need. Describes the credible options that UE currently considers may address the identified need, including for each: o o o Its technical definitions; The estimated commissioning date; and The total indicative cost (including capital and operating costs). Sets out the technical characteristics that a non-network option would be required to deliver in order to address the identified need. An invitation to registered participants and interested parties to make submission on credible options to address the identified need. 1 UE: Distribution Annual Planning Report. Available at: Page 5 of 33

7 4 Identified Need 4.1 Network overview The geographic area that comprises the lower Mornington Peninsula include Cape Schanck, Dromana, Flinders, Main Ridge, McCrae, Portsea, Red Hill, Rosebud, Rye, Shoreham and Sorrento. The electricity demand in this region is made up of predominantly residential sector demand with the majority of the population load centres based along the coastline of Port Phillip Bay. Pockets of commercial and light industrial sectors are also based in the major population centres. The lower (south-western) Mornington Peninsula is currently supplied by Dromana (DMA), Rosebud (RBD) and Sorrento (STO) 66/22kV zone substations as illustrated in Figure 1. Figure 1 Geographical regions of the lower Mornington Peninsula STO RBD DMA Recent trends have shown a large growth in electricity demand in the residential sector on the Mornington Peninsula. The number of permanent residents is increasing as holiday homes are being converted into permanent dwellings, residential developments and retirement villages. 2 The Mornington Peninsula remains one of Melbourne s premier holiday destinations. The population being serviced rises from approximately 150,000 in early December to a peak of nearly 195,000 during the summer months. 3 2 The Mornington Peninsula is predicted to have the strongest population growth in the UE service area over the next 10 years. The predicted annual average population growth in the Mornington Peninsula is about 1.6% over the 2015 to 2025 period compared to an average of 1.1% for the total UE service area. 3 Mornington Peninsula Shire: Shire Strategic Plan Available at: Page 6 of 33

8 Figure 2 below illustrates the existing sub-transmission network arrangements in the lower Mornington Peninsula. Figure 2 Existing sub-transmission configuration in the Mornington Peninsula (schematic view) TBTS-MTN No.1 66kV Line MTN-DMA 66kV Line DMA-RBD No. 1 & No. 2 66kV Lines TBTS-DMA 66kV Line The existing sub-transmission network to DMA, RBD and STO zone substations consist of: One 66 kv line from Tyabb Terminal Station (TBTS) to DMA zone substation; One 66 kv line from Mornington (MTN) zone substation to DMA zone substation; Two 66 kv lines from DMA to RBD zone substation; and Two 66 kv radial lines from RBD to STO zone substations. This network is currently supporting more than 120 MVA of electrical load at times of maximum demand. The lengths of the 66 kv line segments from TBTS to DMA, to RBD and finally to STO are 29 km, 12 km and 18 km respectively, indicating that the supply route extends for 59 km. Given the relatively long length of the sub-transmission network and high demand, capacitor banks are installed at STO and RBD zone substations to provide reactive power compensation for the load, with one bank at STO used to slightly over-compensate the power factor to minimise reactive power losses in the 66 kv lines. Both these stations are currently operating near unity power factor. Although DMA zone substation is not equipped with any capacitor banks, the zone substation also operates near unity power factor due to the use of pole-mounted capacitor banks within the 22 kv distribution network. The effectiveness of these devices together with the on-load Page 7 of 33

9 tap changers (of zone substation transformers) to maintain voltage levels within acceptable levels is diminishing rapidly in the event of loss of one of the sub-transmission lines to DMA zone substation during maximum demand conditions because of the magnitude of the losses along the 66 kv lines, particularly for loss of the MTN-DMA 66kV line. The distribution network in the lower Mornington Peninsula is characterised by relatively long distribution feeders with below average reliability performance compared to the overall UE network. As a result, the transfer capability in this region is limited during summer maximum demand conditions. The extent of the distribution network in this region is illustrated in Figure 3. Figure 3 Existing distribution network in the Mornington Peninsula FSH MTN HGS DMA STO RBD Page 8 of 33

10 4.2 Description of the identified need Voltage collapse limitation The lower Mornington Peninsula is currently supplied by DMA, RBD and STO zone substations. An unplanned outage either of the incoming 66 kv sub-transmission lines to DMA (i.e. MTN-DMA or TBTS-DMA) during summer maximum demand conditions could cause voltage in the lower Mornington Peninsula to drop uncontrollably, leading to voltage collapse and ultimately supply interruption to the entire region. In order to avoid voltage collapse, pre-emptive load reductions would be required during summer maximum demand periods. The figure below depicts the historical actual maximum demand in the lower Mornington Peninsula, 10% 4 and 50% 5 PoE summer maximum demand forecasts together with the voltage collapse limits. Figure 4 Forecast maximum demand against voltage limits for lower Mornington Peninsula 6 As illustrated above: An unplanned outage of the MTN-DMA 66 kv line at 10% and 50% PoE summer maximum demand conditions is expected to lead to voltage collapse in the lower Mornington Peninsula from summer Therefore, pre-contingent load curtailment may be required from this time to maintain regulatory compliance with respect to voltage. 4 This forecast is also referred to as having a 10% probability of exceedance. It represents a forecast that is expected, on average, to be exceeded once in ten years. 5 This forecast is also referred to as having a 50% probability of exceedance. It represents a forecast that is expected, on average, to be exceeded once in two years. 6 The voltage limits under each credible contingency were calculated using a series of PSS/E (power system simulation software) simulations by considering various loading scenarios. Page 9 of 33

11 An unplanned outage of the TBTS-DMA 66 kv line at 10% PoE summer maximum demand conditions is expected to lead to voltage collapse in the lower Mornington Peninsula from summer Therefore, pre-contingent load curtailment may be required from this time to maintain regulatory compliance with respect to voltage. The table below summarises the forecast impact of the voltage collapse limitation, in particular: Load at risk, which is the MVA load shedding required to address the voltage collapse limitation at 10% PoE maximum demand forecast. This represents the pre-emptive load reduction. Hours at risk, which is the duration of load shedding required to address the voltage collapse limitation. Expected unserved energy at risk 7, which is portion of the energy at risk after taking into account the probability of the demand conditions occurring. Expected value of unserved energy is obtained by multiplying the expected unserved energy by the Value of Customer Reliability (VCR). Table 1 Forecast voltage limitation Year Load at Risk 8 adadffadfda (MVA) Hours at Risk afdafdadfad (Hours) Expected Energy at Risk (kwh) Expected value of unserved energy ($,000) , , , ,903 1, ,537 2, ,189 3, ,337 5, ,974 7, ,160 11, ,186 15,663 7 The expected unserved energy is the portion of the energy at risk taking into account the probability of an outage, combined with a 30% weighting of the 10% PoE demand and 70% weighting of the 50% PoE demand, as described in Section The maximum load reduction required to address the voltage limitation (assumes no diversity between the three zone stations). Page 10 of 33

12 4.2.2 Insufficient thermal capacity in sub-transmission network On the present forecast, it is estimated that the following sub-transmission lines 9, which provide electricity supply to the lower Mornington Peninsula, will have maximum demands that exceed their N-1 thermal ratings: DMA-RBD No.1 66 kv line for loss of the DMA-RBD No.2 66 kv line. DMA-RBD No.2 66 kv line for loss of the DMA-RBD No.1 66 kv line. MTN-DMA 66 kv line for loss of the TBTS-DMA 66 kv line. TBTS-DMA 66 kv line for loss of the MTN-DMA 66 kv line. TBTS-MTN No.1 66 kv line for loss of TBTS-DMA 66 kv line. 10 Unlike other parts of the UE network where load can be transferred to adjacent sub-transmission systems, the load transfer capability away from abovementioned network is significantly limited. This is because: For the DMA-RBD lines which supply RBD and STO zone substations, only RBD has offloading capability to neighbouring DMA zone substation. For the TBTS-DMA and MTN-DMA lines which supply DMA, RBD and STO zone substations, only DMA has off-loading capability to neighbouring MTN zone substation. For the TBTS-MTN No.1 line which supplies the DMA, FSH, MTN, RBD and STO zone substations, a limited amount of load can be transferred from MTN to neighbouring FSH and HGS zone substations. It has a highly utilised distribution feeder network with below average reliability performance. The table below summarises the forecast impact of thermal limitations, in particular: Load at risk, which is the MVA load shedding required to address the abovementioned thermal limitations at 10% PoE maximum demand forecast (i.e. the worst case scenario). This represents a post-contingent load reduction after considering the impact of load transfer capability. Hours at risk, which is the duration of load shedding required addressing the abovementioned thermal limitations. Expected unserved energy at risk 11, which is portion of the energy at risk after taking into account the probability of the demand conditions occurring and plant unavailability. 9 Only the outages that lead to overload and results in the highest loading levels of the remaining sub-transmission network is listed. 10 The TBTS-MTN No.1 66 kv line also becomes overloaded following the loss of the TBTS-MTN No.2 66 kv line. 11 The expected unserved energy is the portion of the energy at risk taking into account the probability of an outage, combined with a 30% weighting of the 10% PoE demand and 70% weighting of the 50% PoE demand, as described in Section 5.3. Page 11 of 33

13 Expected value of unserved energy is obtained by multiplying the expected unserved energy by the Value of Customer Reliability (VCR). Table 2 Forecast thermal limitations Year Load at Risk adadffadfda (MVA) Hours at Risk afdafdadfad (Hours) Expected Energy at Risk (kwh) Expected value of unserved energy ($,000) , , , , , , Page 12 of 33

14 4.3 Bushfire exposure Large areas of natural bush, state parks or local reserves, rural fields and other vegetation co-exist along populated areas of the Mornington Peninsula. Therefore, there exists a higher threat of bushfire in many parts of this region compared to other parts of UE s service area. In recent years, UE has observed four separate incidents of sub-transmission line forced outages as a result of bushfire-related incidents in the area. Two of these incidents related to outage of both the DMA-RBD 66 kv lines (i.e. N-2 outage). This resulted in total loss of supply to a majority of the lower Mornington Peninsula (i.e. all of RBD and STO zone substations). The prospect of bushfire-related factors leading to outage of both the DMA-RBD 66 kv lines is greater in the area of Arthurs Seat Park where both lines traverse in close proximity in difficult to access terrain with thick vegetation. In light of recent events, UE considers the loss of both the DMA-RBD 66 kv lines, due to bushfirerelated incidents, to be a credible contingency event. UE has not quantified this risk as part of this report. Instead, UE discusses qualitatively whether each potential credible option discussed in Section 6 addresses the risk of loss-of-supply under an N-2 contingent event. 4.4 Closing comments on the need for investment The following limitations are to be addressed by this RIT-D: From summer , an unplanned outage of one of the incoming sub-transmission lines to DMA zone substation during summer maximum demand conditions is expected to lead to voltage collapse in the lower Mornington Peninsula. From summer , an unplanned outage of a critical sub-transmission line during summer maximum demand conditions is expected to lead to supply interruptions in the lower Mornington Peninsula due to thermal overload of remaining in-service subtransmission lines. Outage of both the DMA-RBD 66 kv lines due to bushfire incidents are expected to lead to total loss of supply to a majority of the lower Mornington Peninsula until one or both lines are fully restored. In light of the growing demand and the forecast increase in load-at-risk, UE has examined a number of options to alleviate the identified need. These options are outlined in Section 6. Page 13 of 33

15 4.5 Quantification of the identified need The table below summarises the forecast impact of the identified need discussed in Section 4.2. The table shows: Load at risk, which is the MVA load shedding required to address the sub-transmission network limitations at 10% PoE maximum demand forecast. This represents both the precontingent load reductions and post-contingent load reductions. Hours at risk, which is the duration of load shedding required to address the subtransmission limitations. Expected unserved energy at risk 12, which is portion of the energy at risk after taking into account the probability of the limitation occurring, including the probability of the demand conditions occurring. Expected value of unserved energy is obtained by multiplying the expected unserved energy by the Value of Customer Reliability (VCR). Table 3 Forecast sub-transmission network limitations in the lower Mornington Peninsula Voltage Limitation (Pre-contingent) Thermal Limitation (Post-contingent) Total Limitation Year Load at Risk fffffffff Hours at Risk Load at Risk fffffffff Hours at Risk Expected Energy at Risk Expected value of unserved energy (MVA) (Hours) (MVA) (Hours) (kwh) ($,000) , , , ,812 1, ,665 3, ,615 4, ,968 5, ,057 7, ,519 11, ,120 15, The expected unserved energy is the portion of the energy at risk taking into account the probability of an outage, combined with a 30% weighting of the 10% PoE demand and 70% weighting of the 50% PoE demand, as described in Section 5.3. Page 14 of 33

16 5 Key assumptions in relation to the Identified Need 5.1 Method for quantifying the identified need The identified need that is to be addressed by this RIT-D, presented in Section 4.5, is comprised of the following components: Expected unserved energy due to voltage collapse limitation in the lower Mornington Peninsula; and Expected unserved energy due to insufficient thermal capacity in the sub-transmission network. The section below summarises the method adopted to quantify the abovementioned risks Expected unserved energy due to voltage collapse limitation In order to avoid the voltage collapse limitation and maintain voltage stability, load must be reduced during system normal conditions (i.e. prior to an outage) at times when the total load in the lower Mornington Peninsula reaches the voltage collapse limit to maintain regulatory compliance. The expected unserved energy due to voltage collapse limitation was estimated as follows: Identify the expected unserved energy under system normal conditions by comparing the total demand in the lower Mornington Peninsula (i.e. combined demand at DMA, RBD and STO zone substations) against the voltage collapse limit Expected unserved energy due to insufficient thermal capacity The expected unserved energy due to insufficient thermal capacity in the sub-transmission network was calculated as follows: 1. Identify the expected unserved energy in the following sub-transmission network under system normal conditions (i.e. N condition) and following loss of a critical sub-transmission line (i.e. N-1 condition): a. DMA-RBD lines which supplies RBD and STO zone substations. b. TBTS-DMA line which supplies DMA, RBD and STO zone substations. c. MTN-DMA line which supplies DMA, RBD and STO zone substations. d. TBTS-MTN No.1 line which supplies DMA, FSH, MTN, RBD and STO zone substations. The combined expected unserved energy from (a) to (d) represents the expected unserved energy that is to be addressed due insufficient thermal capacity in the sub-transmission network. This assessment excludes the impact of load transfer capability. Analysis indicated that the total risks to be addressed due to insufficient thermal capacity in the sub-transmission network is greater under the scenario that considers the impact of load transfers compared to the scenario Page 15 of 33

17 Maximum demand (MVA) RIT-D Non Network Options Report that excludes such transfers. 13 This is due to significant incremental risks in the distribution feeder network, particularly during N-1 conditions where the distribution feeders are exposed to greater level of risk given increased utilisation. In order to realise market benefits arising from load transfers to neighbouring network during emergency conditions, the available load transfer capability must be optimised such that the incremental risks in the distribution feeder network is reduced (particularly under N-1 conditions). This requires significant iterative modelling assessment which would be disproportionate to any additional benefits that may be identified given: High proportion of the identified need relates to the voltage collapse limitation. Any additional benefits realised from load transfers during emergency conditions would not alter the timing of proposed augmentation nor alter the outcome of this RIT-D. The available load transfer is already limited and expected to deteriorate. Further reduction is unlikely to yield significant market benefits. 5.2 Forecast maximum demand Forecasts of the 10% PoE and 50% PoE summer maximum demand for the relevant zone substations and sub-transmission systems in the lower Mornington Peninsula are presented in figures below. These forecasts are based on the base (expected) economic growth scenario. Figure 5 10% PoE summer maximum demand forecasts at DMA, RBD and STO zone substations Forecast 10% PoE summer maximum demand DMA RBD STO 13 Load transfer capability away from sub-transmission systems on the UE network was calculated for summer as part of contingency planning studies. Page 16 of 33

18 Maximum demand (MVA) Maximum demand (Amps) RIT-D Non Network Options Report Figure 6 10% PoE summer maximum demand forecasts of relevant sub-transmission systems Forecast 10% PoE summer maximum demand TBTS-DMA-FSH-MTN-TBTS TBTS-DMA-MTN DMA-RBD-DMA Figure 7 50% PoE summer maximum demand forecasts at DMA, RBD and STO zone substations Forecast 50% PoE summer maximum demand DMA RBD STO Page 17 of 33

19 Maximum demand (Amps) RIT-D Non Network Options Report Figure 8 50% PoE summer maximum demand forecasts of relevant sub-transmission systems Forecast 50% PoE summer maximum demand TBTS-DMA-FSH-MTN-TBTS TBTS-DMA-MTN DMA-RBD-DMA The amount of expected unserved energy is estimated in this report by taking 30% weighting of the unserved energy at 10% PoE demand forecast and 70% weighting of the unserved energy at 50% PoE demand forecast. Page 18 of 33

20 Normalised Load (%) RIT-D Non Network Options Report 5.3 Characteristic of load profile The Mornington Peninsula remains one of Melbourne s premier seasonal holiday destinations. As such, the maximum demand occurs during summer holiday periods as illustrated in Figure 9. Figure 9 Load profile for lower Mornington Peninsula ( ) Lower Mornington Peninsula Load Profile 110% 100% Winter Spring Summer Autumn 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% Hours A typical load profile on the day of summer maximum demand is presented in Figure 10. Normally, the electricity demand in the lower Mornington Peninsula remains relatively low during the early hours of the day, with a large increase in demand during the afternoon to early evening hours. Page 19 of 33

21 Proporation of maximum demand 0:00 1:00 2:00 3:00 4:00 5:00 6:00 7:00 8:00 9:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00 21:00 22:00 23:00 Normalised Load (%) RIT-D Non Network Options Report Figure 10 Typical load profile on day of summer maximum demand for lower Mornington Peninsula Lower Mornington Peninsula Daily peak load profile 110% 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% Time of day Figure 11 shows the normalised load duration curves of the lower Mornington Peninsula for the last five summers. Figure 11 Historical load duration curves for lower Mornington Peninsula Load duration curve for lower Mornington Peninsula 100% 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Proportion of time Page 20 of 33

22 The figure above shows that that the load characteristics can vary from year to year. It also shows that around 45-60% of the maximum demand lasts less than five per-cent of the period. This implies that although the probability of reaching high demand levels is reasonably low, the impact of not having sufficient capacity can result in significant amount of load-at-risk. To account for variability in load characteristics, UE has prepared load traces based on historical load traces that characterised: 10% and 50% PoE demand profiles (or close to) for the lower Mornington Peninsula 14 ; Maximum demand occurring during summer holiday periods; and Excludes load transfer from / to neighbouring network. Based on this approach, the expected unserved energy due to both thermal and voltage limitations were estimated using the and historical traces. 5.4 Plant failure rates The base (average) outage data adopted in this RIT-D are presented below. Table 4 Summary of sub-transmission line outage rates Major plant item: Sub-transmission lines Interpretation Sub-transmission line failure rate per km Duration of outage (major fault) 5.1 faults per 100 km per annum 10 hours The average sustained failure rate of UE s subtransmission network is 5.1 faults per 100 km per year. A total of 10 hours is required to repair / replace the sub-transmission line (or sections of the line), during which time the sub-transmission line (or sections of the line) is not available. 5.5 Sub-transmission network losses under N-1 condition As discussed earlier, the lower Mornington Peninsula is supplied by an extended sub-transmission network. The network losses following the loss of a critical sub-transmission line in the region is significant, particularly in the case where the total supply is via the radial TBTS-DMA-RBD-STO sub-transmission network. To account for the network losses under N-1 conditions, UE has adopted 3.0 per-cent of the total load in this assessment. 14 The total demand in the lower Mornington Peninsula was estimated by summing the individual station demands at DMA, RBD and STO zone substations. This method considers diversity exhibited in the historical base trace. 15 The historic load traces characterised (or close to) a 10% PoE maximum demand profile in the lower Mornington Peninsula. 16 The historic load trace characterised (or close to) a 50% PoE maximum demand profile in the lower Mornington Peninsula. Page 21 of 33

23 5.6 Plant ratings The voltage collapse ratings under each credible sub-transmission line outage were calculated using a series of PSSE simulations by considering various loading scenarios. The critical voltage collapse rating is for the loss of the MTN-DMA 66 kv line, where the total supply to the lower Mornington Peninsula is from the radial TBTS-DMA-RBD-STO sub-transmission network. The sub-transmission line thermal ratings were calculated based on ambient temperature of 40 C. In addition to temperature, overhead line ratings are based on solar radiation of 1000 W/m 2 and a wind speed of 3 m/s at an angle to the conductor of 15 (i.e. an effective transverse wind speed of 0.78 m/s), while the underground cable ratings are based on soil thermal resistivity of 0.9 Cm/W or 1.2 Cm/W at specific sites. For underground cables, a typical load profile has been considered to accommodate the variability in demand over time. Summer ratings adopted in this assessment are summarised in the table below. Table 5 Summary of sub-transmission line cyclic ratings (MVA) Description Summer cyclic rating at 40 C N N-1 Voltage rating N/A Thermal rating: DMA-RBD 66 kv lines Thermal rating: TBTS-DMA 66 kv line Thermal rating: MTN-DMA 66 kv line Thermal rating: TBTS-FSH-MTN-DMA-TBTS system Value of customer reliability Location specific Value of Customer Reliability (VCR) is used to calculate the customer value of lost load. Where a limitation impacts multiple zone substations, an average VCR of the affected zone substations is used to calculate the customer value of lost load. The location VCR was derived from the sector VCR estimates provided by AEMO, weighted in accordance with the composition of the load, by sector, at the relevant zone substations. 17 The voltage rating following the loss of the MTN-DMA 66 kv line. 18 The thermal rating following the loss of one of the DMA-RBD 66 kv lines. 19 The thermal rating following loss of the MTN-DMA 66 kv line. 20 The thermal rating following loss of the TBTS-DMA 66 kv line. 21 The thermal rating following loss of the TBTS-DMA 66 kv line. Page 22 of 33

24 Table 6 Summary of location specific VCRs (based on 2013 estimates) Zone substation VCR ($ per MWh) DMA 54,130 FSH 57,255 MTN 65,221 RBD 68,280 STO 54,140 While AEMO s recent VCR review in 2014 concludes a reduction in its baseline VCR, the timebased VCRs in Appendix B of AEMO s Final Report conclude that the revised VCRs are comparable in magnitude to those presented above. Given the AEMO consultation on the VCR Application Guidelines is still in progress at the time of developing this report, the VCRs above may be updated for the Draft Project Assessment Report (DPAR). 5.8 Discount rates To compare cash flows of options with different time profiles, it is necessary to use a discount rate to express future costs and benefits in present value terms. The choice of discount rate will impact on the estimated present value of net market benefits, and may affect the ranking of alternative options. A real, pre-tax discount rate of 9.5 per-cent is adopted in this RIT-D. Page 23 of 33

25 6 Potential credible options to address the identified need The table below provides a summary of potential credible options to address the identified need. Table 7 Credible options under consideration Option Description 1 Install a new HGS-RBD 66 kv line This option includes: This option will: Installing approximately 53 km of new 66 kv line from Hastings (HGS) zone substation to Rosebud (RBD) zone substation. The new line would be constructed along the south-eastern coast (along the road reserve) of the Mornington Peninsula, clear of high bushfire zones. Most of the route would involve the reconstruction of existing overhead pole lines. Installing three 66 kv circuit breakers, one at RBD and two at HGS zone substations. Upgrade the TBTS-HGS No.1 and No.2 feeder exits at Tyabb Terminal Station (TBTS). Addresses the thermal limitations by reducing utilisation of the constrained sub-transmission network. Addresses the voltage limitation by improving voltage regulation in the lower Mornington Peninsula. Addresses the risk of bushfire-related incidents leading to outage of both the DMA-RBD 66 kv lines. Facilitates the sub-transmission connection of a future zone substation in the Flinders / Shoreham area. Based on the current forecasts, this new zone substation is not required within the next 20 year planning period. The estimated capital cost of this option is $25.3 million (± 30%), in $AUD. Annual operating and maintenance costs are anticipated to be around 0.5% of the capital cost. 22 The above-estimate includes the cost of the TBTS-HGS No.1 and No.2 feeder exit upgrade works which would be undertaken by AusNet Transmission Group. The estimated commissioning date is before summer The estimated total annual cost of this option is $2,403,500. This cost provides a broad upper bound indication of the maximum contribution from UE which may be available to non-network service providers to avoid this augmentation. 2 Install new TBTS-RBD 66 kv line This option includes: Installing 3.4 km of additional 66 kv line from TBTS to HGS zone substation. Installing approximately 53 km of new 66 kv line from Hastings (HGS) zone substation to Rosebud (RBD) zone substation. The new line would be constructed along the south-eastern coast of the Mornington Peninsula, clear of high bushfire zones. Most of the route would involve the reconstruction of existing overhead pole lines. Installing two 66 kv circuit breakers, one at RBD and one at TBTS (Bus 3). This option: Addresses the thermal limitations by reducing utilisation of the constrained sub-transmission network. 22 Based on the average maintenance cost of overhead lines per km for Page 24 of 33

26 Option Description 2 Addresses the voltage limitation by improving voltage regulation in the lower Mornington Peninsula. Addresses the risk of bushfire related incidents leading to outage of both the DMA-RBD 66 kv lines. Facilitates the sub-transmission connection of a future zone substation in the Flinders / Shoreham area. Based on the current forecasts, this new zone substation is not required within the next 20 year planning period. The estimated capital cost of this option is $26.9 million (± 30%), in $AUD. Annual operating and maintenance costs are anticipated to be around 0.5% of the capital cost 21. The estimated commissioning date is before summer The estimated total annual cost of this option is $2,555,500. This cost provides a broad upper bound indication of the maximum contribution from UE which may be available to non-network service providers to avoid this augmentation. 3 Non-network solutions Embedded generation or demand reduction may defer network investments to address the identified need. UE has been working with a number of non-network service providers under the Memorandum of Understanding (MoU). At the time of publication of this report, UE has received a proposal from one proponent providing an option for demand reduction within the lower regions of the Mornington Peninsula. Likely costs and operating parameters are currently being confirmed. Once confirmed, UE intends to evaluate this proposal to determine whether it is an alternative or complementary measure to network augmentation. The outcome of this assessment will be published in the Draft Project Assessment Report (i.e. the second consultation paper in relation to this RIT-D). UE welcomes proposals, including cost estimates from other non-network service providers to address the issues described in Section 4. Section 7 provides information to assist non-network service providers in responding to this consultation report. The table below describes the options that have been considered by UE, and are currently regarded as being not credible for the reasons set out: Table 8 Options regarded as being not credible Option Description 4 Upgrading existing sub-transmission systems This option includes: Reconductoring approximately 18 km of the DMA-RBD 66 kv lines. Reconductoring approximately 7 km of the TBTS-MTN No.1 66 kv line. The estimated capital cost of this option is $8.3 million (± 30%), in $AUD. This option does not fully address the thermal limitation nor does it address the voltage collapse limitation in the lower Mornington Peninsula. Given a majority of the identified need is associated with the voltage collapse limitation, the expected net market benefits of this option is likely to be considerably lower than the credible options discussed earlier. Under the RIT-D, the preferred option is the credible option that maximise the network market benefits. For this reason, UE does not consider this option to be a credible option. Page 25 of 33

27 Option Description 5 Reactive power compensation Reactive power compensation by means of installing capacitor banks at various zone substations in the lower Mornington Peninsula is not a technically viable option. This is because all zone substations in the region are operating near unity power factor. Currently, STO has already been overcompensated to minimise the risk of the voltage collapse limitation. For this reason, UE does not consider this option to be a credible option. 6 Install new HGS-STO 66 kv line This option includes: This option: Installing approximately 53 km of new 66 kv line from Hastings (HGS) zone substation to Rosebud (RBD) zone substation. The new line would be constructed along the south-eastern coast of the Mornington Peninsula, clear of high bushfire zones. Installing new 66 kv line from RBD to STO zone substation. Upgrade the TBTS-HGS No.1 and No.2 feeder exits at Tyabb Terminal Station (TBTS). Addresses the thermal limitations by reducing utilisation of the constrained sub-transmission network. Addresses the voltage limitation by improving voltage regulation in the lower Mornington Peninsula. Addresses the risk of bushfire related incidents leading to outage of both the DMA-RBD 66 kv lines. Facilitates the sub-transmission connection of future zone substation in the Flinders / Shoreham area. Based on the current forecasts, this new zone substation is not required within the next 20 year planning period. The estimated capital cost of this option is $33.1 million (± 30%), in $AUD. The above-estimate includes the cost of the TBTS-HGS No.1 and No.2 feeder exit upgrade works which would be undertaken by AusNet Transmission Group. Under this option, the new sub-transmission line is extended to STO zone substation. This relieves loading on the existing RBD-STO-RBD system under system normal and N-1 conditions. However, additional market benefits would not be realised given there is no immediate thermal limitation on this system. Therefore, the net market benefit associated with this option would be lower than the credible network options described earlier due to its higher costs. Under the RIT-D, the preferred option maximises the net market benefits. Therefore, this option would not satisfy the RIT-D. For this reason, UE does not consider this option to be a credible option. Page 26 of 33

28 Option Description 7 Install new HGS-DMA 66 kv line with DMA-RBD 66 kv line reconductoring This option includes: This option: Installing approximately 22 km of new 66 kv line from Hastings (HGS) zone substation to Dromana (DMA) zone substation. Reconductor approximately 18 km of the existing DMA-RBD 66 kv lines. Convert the existing 66 kv outdoor switchyard to Gas Insulated Switchgear (GIS) due to space constraints at DMA zone substation. Upgrade the TBTS-HGS No.1 and No.2 feeder exits at Tyabb Terminal Station (TBTS). Addresses the thermal limitations by reducing utilisation of the constrained sub-transmission network. Addresses the voltage limitation by improving voltage regulation in the lower Mornington Peninsula. The estimated capital cost of this option is $26.2 million (± 30%), in $AUD. The above-estimate includes the cost of the TBTS-HGS No.1 and No.2 feeder exit upgrade works which would be undertaken by AusNet Transmission Group. Although this option is similar to Option 1 in terms of both costs and the expected market benefits, UE has identified a number of issues associated with this options: The feasibility of constructing a sub-transmission line along the Mornington Peninsula Freeway is yet to be established. However, approval is likely to be difficult given UE s recent previous experience in the Keysborough area. The project cost is likely to increase if a route along the freeway cannot be achieved. The feasibility of reconstructing the sub-transmission lines between DMA and RBD is yet to be established. Easement renegotiations are likely to be expensive given UE s experience with land-holders for the previous upgrade of the TBTS-DMA 66 kv lines in this area. The project cost is significantly dependant on easement renegotiation costs for this option. This option does not facilitate the sub-transmission connection of a future zone substation in the Flinders / Shoreham area. This option does not address the risk of bushfire related incidents leading to outage of both the DMA-RBD 66 kv lines. Significant disruption / outages during conversion of existing 66 kv outdoor switchgear to 66 kv GIS switchgear at DMA zone substation. This is likely to increase the cost of this project. Given these practical limitations, reduced market benefits and potential increased costs compared to the potential credible options discussed earlier, UE does not consider this option to be a credible option. Page 27 of 33

29 7 Technical characteristics of non-network options This section describes the technical characteristics of the identified need that a non-network option would be required to deliver. A credible non-network option must satisfy timing, operational and technical requirements stipulated below. 7.1 Size and location Non-network service providers would need to be able to reduce load (demand-side or generation solutions) in the lower Mornington Peninsula to avoid network limitations discussed in this paper. This could be achieved by: 1. Pre-contingent load reductions. This arrangement would involve measures to reduce the load at times when an outage of the MTN-DMA 66 kv line results in voltage collapse in the lower Mornington Peninsula. 2. Post contingent load reductions. This arrangement would involve measures to reduce the load should a critical outage occur and the sub-transmission network be overloaded. Such reductions would need to occur within a few minutes of the critical outage occurring. Table 9 outlines the maximum amount of load reduction, or additional generation required to address the network limitations discussed in this paper. Non-network solutions must be provided in the Sorrento, Rosebud and/or Dromana supply areas. Table 9 Peak Demand offsets required from non-network solutions to address the identified need Pre-contingent requirements Post-contingent requirements Year Load at Risk Hours at Risk Load at Risk Hours at Risk (MVA) (hours) (MVA) (hours) Page 28 of 33

30 7.2 Time of year Proposed non-network options, at a minimum, must be capable of reducing demand in the lower Mornington Peninsula during summer holiday periods (typically from December to January inclusive). 7.3 Reliability Proposed non-network options must be capable of reliably meeting electricity demand under a range of conditions. If the non-network option is a generator operating in parallel with UE s network, the generator must comply with the requirements set out in UE s Embedded Generation Network Access Standard (Document No. UE ST 2008) Operation The market benefits associated with the identified need relate to: Reducing the expected amount of unserved energy due to voltage collapse limitation; and Reducing the expected amount unserved energy due to insufficient thermal capacity in a number of sub-transmission systems under N-1 condition. The load curve in Figure 10 shows that the demand in the lower Mornington Peninsula remains high over the hours from 3:00 pm to 8:00 pm. Any pre-contingent non-network solution will therefore need to be capable of operating continuously over this period, until the demand declines. Any post-contingent non-network solution will need to be capable of operating continuously, during high demand periods where there is insufficient spare capacity in neighbouring distribution feeders, until the faulted asset is repaired or replaced, or the demand declines. A high proportion of the total risk to be addressed by this RIT-D is associated with the voltage limitation. Therefore, any non-network solutions that address this limitation would be associated with significant market benefits Page 29 of 33

31 8 Submission 8.1 Request for submission UE invites written submissions on this report from registered participants and interested parties. All submissions should completely and comprehensively address the technical characteristics of non-network options provided in Section 7 and include information listed in listed in Section 5 of UE s Demand Side Engagement Document (DSED). 24 All Submissions and enquiries should be directed to the United Energy Manager Network Planning at planning@ue.com.au. Submissions are due on or before 29 May All submissions will be published on UE website Next steps Following UE s consideration of the submissions, a detailed option assessment including the preferred option to address the identified need, and a summary of, and commentary on, the submissions to this report will be included as part of the Draft Project Assessment Report. This report represents the second stage of the consultation process in relation to the application of the RIT-D. UE intends to publish the Draft Project Assessment Report in July UE: Demand Side Engagement Document. Available at: 25 If you do not want your submission to be publically available, please clearly stipulate this at the time of lodgement. Page 30 of 33

32 9 Abbreviations and Glossary Abbreviations AEMO Australian Energy Market Operator DAPR Distribution Annual Planning Report DMA Dromana zone substation DPAR Draft Project Assessment Report DSED Demand Side Engagement Document FPAR Final Project Assessment Report HGS Hastings zone substation MTN Mornington zone substation NEM National Electricity Market NER National Electricity Rules NNOR Non Network Options Report PoE Probability of Exceedance PSSE Power System Simulator for Engineers RBD Rosebud zone substation RIT-D Regulatory Investment Test for Distribution STO Sorrento zone substation TBTS Tyabb Terminal Station UE United Energy Distribution Pty Ltd VCR Value of Customer Reliability Page 31 of 33

33 Glossary Term Definition 1-in-2 peak day The 1-in-2 peak day demand projection has a 50% probability of exceedance (PoE). This projected level of demand is expected, on average, to be exceeded once in two years. 1-in-10 peak day The 1-in-10 peak day demand projection has a 10% probability of exceedance (PoE). This projected level of demand is expected, on average, to be exceeded once in ten years. Credible option An option that: Addresses the identified need ; Is commercially and technically feasible; and Can be implemented in sufficient time to meet the identified need. Expected Energy at Risk The expected amount of energy that cannot be supplied each year because there is insufficient capacity to meet demand, taking into account equipment unavailability and load-at-risk. Identified need Any capacity or voltage limitation on the distribution system that will give rise to Expected Energy at Risk. Limitation Any limitations on the operation of the distribution system that will give rise to expected energy at risk. Network option A means by which an identified need can be fully or partly addressed by expenditure on the distribution asset. Non-network option A means by which an identified need can be fully or partially addressed other than by a network option. Non-network service provider A party who provides a non-network option Potential credible option An option has the potential to be a credible option based on an initial assessment of the identified need. Preferred option A credible option that maximise the present value of net economic benefit to all those who produce, consume and transport electricity in the market. The preferred option can be a network option, non-network option, or do nothing (i.e. status quo). Page 32 of 33

Dalrymple substation upgrade

Dalrymple substation upgrade Dalrymple substation upgrade RIT-T: Project Specification Consultation Report ElectraNet Corporate Headquarters 52-55 East Terrace, Adelaide, South Australia 5000 PO Box, 7096, Hutt Street Post Office,

More information

RIT-T: Project Specification Consultation Report. Powering Sydney s Future

RIT-T: Project Specification Consultation Report. Powering Sydney s Future RIT-T: Project Specification Consultation Report Powering Sydney s Future 11 October 2016 1. Executive Summary Powering Sydney - now and into the future A reliable, affordable and sustainable electricity

More information

TEMPORARY GRID RECONFIGURATIONS NET BENEFIT TEST METHODOLOGY

TEMPORARY GRID RECONFIGURATIONS NET BENEFIT TEST METHODOLOGY TEMPORARY GRID RECONFIGURATIONS NET BENEFIT TEST METHODOLOGY 1 1. Summary When one part of the grid is facing security of supply risk where local generation in one region of the grid is not enough for

More information

DUQUESNE LIGHT COMPANY TRANSMISSION PLANNING CRITERIA

DUQUESNE LIGHT COMPANY TRANSMISSION PLANNING CRITERIA DUQUESNE LIGHT COMPANY TRANSMISSION PLANNING CRITERIA Transmission Planning Criteria Updated: March Compiled: September 2007 Compiled from: s Comprehensive Transmission Reliability Plan, July 2005 s Strategic

More information

POTOMAC ELECTRIC POWER COMPANY

POTOMAC ELECTRIC POWER COMPANY POTOMAC ELECTRIC POWER COMPANY FERC Form 715 (Part 4) - Transmission Planning Study Guidelines Transmission Reliability Guidelines 1. General Overview The reliability guidelines used to plan the transmission

More information

Ergon Energy Corporation Limited

Ergon Energy Corporation Limited Ergon Energy Corporation Limited Request for Information Emerging Distribution Network Limitations in the Palm Island Area 1 May 2012 Disclaimer While care was taken in preparation of the information in

More information

WESTERN VICTORIA RENEWABLE INTEGRATION PROJECT SPECIFICATION CONSULTATION REPORT

WESTERN VICTORIA RENEWABLE INTEGRATION PROJECT SPECIFICATION CONSULTATION REPORT WESTERN VICTORIA RENEWABLE INTEGRATION PROJECT SPECIFICATION CONSULTATION REPORT Published: April 2017 IMPORTANT NOTICE Purpose AEMO has prepared this document to provide information about potential network

More information

COST ALLOCATION POLICY FOR VICTORIAN TERMINAL STATIONS NEGOTIATED TRANSMISSION SERVICES

COST ALLOCATION POLICY FOR VICTORIAN TERMINAL STATIONS NEGOTIATED TRANSMISSION SERVICES COST ALLOCATION POLICY FOR VICTORIAN TERMINAL STATIONS NEGOTIATED PREPARED BY: Network Development VERSION: 2.0 RELEASE DATE: 30 May 2012 Version Release History Version Date By Changes 1.0 6 Oct 11 Transmission

More information

POWER SYSTEM STABILITY GUIDELINES

POWER SYSTEM STABILITY GUIDELINES PREPARED BY: DOCUMENT REF: Planning PSSG-02 VERSION: 1.0 DATE: 25 May 2012 FINAL Final Matt Zema CEO Date 25/ 5 /2012 Version Release History VERSION DATE AUTHOR PEER REVIEW APPROVED COMMENTS 1.0 25/5/12

More information

Methodology & Learning Report. Work package 2.1: Dynamic thermal rating of assets Primary Transformers

Methodology & Learning Report. Work package 2.1: Dynamic thermal rating of assets Primary Transformers Flexible Networks for a Low Carbon Future Methodology & Learning Report Work package 2.1: Dynamic thermal rating of assets Primary Transformers May 2015 Contents 1 Executive Summary 2 2 Background 3 3

More information

Standard TPL Transmission System Planning Performance Requirements

Standard TPL Transmission System Planning Performance Requirements A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon

More information

Standard Development Timeline

Standard Development Timeline Standard Development Timeline This section is maintained by the drafting team during the development of the standard and will be removed when the standard is adopted by the NERC Board of Trustees (Board).

More information

Distribution Information Exchange Code

Distribution Information Exchange Code Distribution Information Exchange Code Version 5.1 Approved September 2007 Comments to this document can be forwarded to: The RSA Grid Code Secretariat Attention: Mr. Bernard Magoro Eskom, Transmission

More information

ENABLING EMBEDDED GENERATION

ENABLING EMBEDDED GENERATION APRIL 2014 ENABLING EMBEDDED GENERATION Turning Australian electricity on its head WHAT IS EMBEDDED GENERATION? Energy supply systems around the world are being transformed by embedded (or distributed)

More information

October 6, Submitted to: CAISO

October 6, Submitted to: CAISO October 6, 2017 Submitted to: CAISO (regionaltransmission@caiso.com) COMMENTS OF NEXTERA ENERGY TRANSMISSION WEST, LLC ON THE CALIFORNIA INDEPENDENT SYSTEM OPERATOR CORPORATION S 2017-2018 TRANSMISSION

More information

Methodology for deriving delivery prices

Methodology for deriving delivery prices Methodology for deriving delivery prices For prices applying from 1 April 2018 Issued xx February 2018 DRAFT Please note that this document has not yet been certified by Orion s directors A certified version

More information

Electrical Networks Principles and Performance

Electrical Networks Principles and Performance Engineering Standard Electrical Networks Electrical Networks Principles and Performance Version: 1 Issued: January 2015 Owner: Chief Engineer Approved By: Paul O Halloran Chief Engineer PRINTOUT MAY NOT

More information

HPC-9DJ

HPC-9DJ Manual Distribution Design Manual Volume 2: Low Voltage Aerial Bundle Cable Standard Number: HPC-5DC-07-0002-2014 Document Control Author Name: Anthony Seneviratne Position: Standards Engineer Document

More information

WIND TURBINES IN WEAK GRIDS CONSTRAINTS AND SOLUTIONS. J O G Tande and K Uhlen. SINTEF Energy Research, Norway SUMMARY

WIND TURBINES IN WEAK GRIDS CONSTRAINTS AND SOLUTIONS. J O G Tande and K Uhlen. SINTEF Energy Research, Norway SUMMARY WIND TURBINES IN WEAK GRIDS CONSTRAINTS AND SOLUTIONS J O G Tande and K Uhlen SINTEF Energy Research, Norway SUMMARY Cost efficient utilisation of the wind energy resource requires wind farms to be located

More information

Energex. Tariff Structure Statement. 1 July 2017 to 30 June Energex s Tariff Structure Statement

Energex. Tariff Structure Statement. 1 July 2017 to 30 June Energex s Tariff Structure Statement Energex Tariff Structure Statement 1 July 2017 to 30 June 2020-1- Energex s 2017-20 Tariff Structure Statement Version control Version Date Description V.1 27 November 2015 TSS proposal submitted to the

More information

TABLE OF CONTENTS. LIST OF FIGURES Figure 4-1: Alternative 1 System Overview Figure 4-2: Alternative 3 System Overview...

TABLE OF CONTENTS. LIST OF FIGURES Figure 4-1: Alternative 1 System Overview Figure 4-2: Alternative 3 System Overview... TABLE OF CONTENTS 4 DESCRIPTION AND EVALUATION OF ALTERNATIVES... 4-1 4.1 INTRODUCTION... 4-1 4.2 METHODOLOGY... 4-1 4.3 DESCRIPTION OF ALTERNATIVES... 4-2 4.3.1 No Project Alternative... 4-2 4.3.2 Alternative

More information

United Energy 2016 Pricing Proposal

United Energy 2016 Pricing Proposal United Energy 2016 Pricing Proposal Stephen Harrison Revenue Manager United Energy November 2015 United Energy 2016 Pricing Proposal United Energy 2016 Pricing Proposal Table of contents Executive Summary..5

More information

DISTRIBUTION LOSS ADJUSTMENT FACTORS ESB SUBMISSION THE COMMISSION FOR ELECTRICITY REGULATION

DISTRIBUTION LOSS ADJUSTMENT FACTORS ESB SUBMISSION THE COMMISSION FOR ELECTRICITY REGULATION DISTRIBUTION LOSS ADJUSTMENT FACTORS ESB SUBMISSION TO THE COMMISSION FOR ELECTRICITY REGULATION Document No: DOC-140105-AIL 7/02/2000 Introduction: The Commission for Electricity Regulation (CER) have

More information

The effectiveness of oil analysis for failure prediction of power transformers

The effectiveness of oil analysis for failure prediction of power transformers The effectiveness of oil analysis for failure prediction of power transformers by Krige Visser and Yashin Brihmohan, University of Pretoria The availability of an electricity network is of utmost importance

More information

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Delaney to Colorado River 2014

Transmission Competitive Solicitation Questions Log Question / Answer Matrix Delaney to Colorado River 2014 No. Comment Submitted ISO Response Date Q&A Posted 1 Can the CAISO provide a line rating methodology (similar to a NERC FAC-008 standard) or include a requirement of using any The ISO does not provide

More information

Improving the way we price our network services. Consultation paper

Improving the way we price our network services. Consultation paper Improving the way we price our network services Consultation paper October 2015 Table of Contents 1 Overview... 4 2 Background... 6 3 Purpose... 7 4 Network tariff strategy... 7 4.1 Network tariff reform

More information

IMP/001/914 Code of Practice for the Economic Development of the 132kV System

IMP/001/914 Code of Practice for the Economic Development of the 132kV System Version:- 3.0 Date of Issue:- September 2015 Page 1 of 36 IMP/001/914 Code of Practice for the Economic Development of the 132kV System 1 Purpose The purpose of this document is to state Northern Powergrid

More information

TPL Transmission System Planned Performance for Geomagnetic Disturbance Events

TPL Transmission System Planned Performance for Geomagnetic Disturbance Events A. Introduction 1. Title: Transmission System Planned Performance for Geomagnetic Disturbance Events 2. Number: TPL-007-1 3. Purpose: Establish requirements for Transmission system planned performance

More information

Energex 2017 DAPR 2017/ /22. Energex Limited 2017 DAPR 2017/ /22

Energex 2017 DAPR 2017/ /22. Energex Limited 2017 DAPR 2017/ /22 Energex 2017 DAPR 2017/18-2021/22 Energex Limited 2017 DAPR 2017/18-2021/22 Version Control Version Date Description 1.0 27/09/2017 Initial Issue 2.0 01/11/2017 Amendment 1 Disclaimer Energex s Distribution

More information

1. Introduction Background Purpose Scope of the Tariff Structure Statement... 3

1. Introduction Background Purpose Scope of the Tariff Structure Statement... 3 Contents 1. Introduction... 3 1.1 Background... 3 1.2 Purpose... 3 1.3 Scope of the Tariff Structure Statement... 3 1.4 Application of the Tariff Structure Statement... 4 2. Compliance matrix... 7 3. Understanding

More information

NEEDS ASSESSMENT REPORT

NEEDS ASSESSMENT REPORT Hydro One Networks Inc. 483 Bay Street Toronto, Ontario M5G 2P5 NEEDS ASSESSMENT REPORT Toronto Region Date: October 18, 2017 Prepared by: Toronto Region Study Team Disclaimer This Needs Assessment Report

More information

SQUEEZING MARGINS: REDUCING COSTS WHILE BALANCING RISKS. G.A. Bloemhof, J. Knijp. KEMA T&D Power, the Netherlands

SQUEEZING MARGINS: REDUCING COSTS WHILE BALANCING RISKS. G.A. Bloemhof, J. Knijp. KEMA T&D Power, the Netherlands SQUEEZING MARGINS: REDUCING COSTS WHILE BALANCING RISKS G.A. Bloemhof, J. Knijp KEMA T&D Power, the Netherlands Liberalising the energy market increased the awareness of transmission and distribution companies

More information

Withlacoochee River Electric Cooperative, Inc. P.O. Box 278 Dade City, FL Billy E. Brown, Executive V.P.

Withlacoochee River Electric Cooperative, Inc. P.O. Box 278 Dade City, FL Billy E. Brown, Executive V.P. Wednesday, February 25, 2015 PSC 25 6.0343 Municipal Electric Utility and Rural Electric Cooperative Reporting Requirements Withlacoochee River Electric Cooperative, Inc. P.O. Box 278 Dade City, FL 33526-0278

More information

Optimum Return Period of an Overhead Line Considering Reliability, Security and Availability with Respect to Extreme Icing Events

Optimum Return Period of an Overhead Line Considering Reliability, Security and Availability with Respect to Extreme Icing Events IWAIS XIV, China, May 0 Optimum Return Period of an Overhead Line Considering Reliability, Security and Availability with Respect to Extreme Icing Events Asim Haldar, Ph.D, P.Eng. ahaldar@nalcorenergy.com

More information

ENGINEERING & ECONOMIC PLANNING FOR ELECTRIC POWER GENERATION, TRANSMISSION AND DISTRIBUTION

ENGINEERING & ECONOMIC PLANNING FOR ELECTRIC POWER GENERATION, TRANSMISSION AND DISTRIBUTION ENGINEERING & ECONOMIC PLANNING FOR ELECTRIC POWER GENERATION, TRANSMISSION AND DISTRIBUTION BY Engr. Otis Anyaeji B.Sc.MechE, FNSE, F. Val, FCostE., AEcon @ the 2011 NATIONAL CONFERENCE OF INSTITUTE OF

More information

Regulatory Audit Of Compliance Reporting For The Ord Hydro Transmission Network

Regulatory Audit Of Compliance Reporting For The Ord Hydro Transmission Network Regulatory Audit Of Compliance Reporting For The Ord Hydro Transmission Network Final 26 March 2007 Regulatory Audit Of Compliance Reporting For The Ord Hydro Transmission Network Final 26 March 2007 Sinclair

More information

NEM EVENT - DIRECTION TO SOUTH AUSTRALIA GENERATOR - 9 FEBRUARY 2017

NEM EVENT - DIRECTION TO SOUTH AUSTRALIA GENERATOR - 9 FEBRUARY 2017 NEM EVENT - DIRECTION TO SOUTH AUSTRALIA GENERATOR - 9 FEBRUARY 2017 Published: July 2017 IMPORTANT NOTICE Purpose AEMO has prepared this report in accordance with clause 3.13.6A(a) of the National Electricity

More information

Economic assessment of distribution network planning: a practical approach

Economic assessment of distribution network planning: a practical approach Economic assessment of distribution network planning: a practical approach Seminar@University of Liège Yannick PHULPIN EDF R&D - EFESE February 8, 2013 1 EDF R&D 08/02/2013 Outline of the talk! Context

More information

Asset Risk Management Journey Plan

Asset Risk Management Journey Plan Asset Risk Management Journey Plan STRATEGIC PLAN 2010-2013 Transpower New Zealand Limited April 2011 TABLE OF CONTENTS EXECUTIVE SUMMARY... 3 1. PURPOSE... 4 2. OVERVIEW OF TRANSPOWER S RISK MANAGEMENT

More information

LOCAL PLANNING REPORT

LOCAL PLANNING REPORT Hydro One Networks Inc. 483 Bay Street Toronto, Ontario M5G 2P5 LOCAL PLANNING REPORT Kent TS Transformation Capacity Region: Chatham-Kent/Lambton/Sarnia Date: June 28 th, 2017 Revision: Final Prepared

More information

DISTRIBUTION SYSTEM PLANNING TUTORIAL. MN Power Systems Conference November 6, 2014

DISTRIBUTION SYSTEM PLANNING TUTORIAL. MN Power Systems Conference November 6, 2014 DISTRIBUTION SYSTEM PLANNING TUTORIAL MN Power Systems Conference November 6, 2014 CONNEXUS ENERGY 128,000 customers 1,000 sq. miles territory 44 substations 8,800 miles distribution 12.47 kv Wholesale

More information

Jemena Electricity Networks (Vic) Ltd

Jemena Electricity Networks (Vic) Ltd Jemena Electricity Networks (Vic) Ltd 2016-20 Electricity Distribution Price Review Regulatory Proposal User-requested services explanatory statement Public 30 April 2015 TABLE OF CONTENTS TABLE OF CONTENTS

More information

Customer charter for electricity networks.

Customer charter for electricity networks. Customer charter for electricity networks. MAINTAINING OUR ELECTRICITY NETWORK IN SUMMER. Who does this Customer Charter cover? This ActewAGL Customer Charter covers customers who are connected to the

More information

Distribution System Design General Requirements

Distribution System Design General Requirements Electricity Policy Document 279 Issue 7 September 2017 Distribution System Design General Requirements Contents 1 Introduction 2 Scope 3 Definitions 4 General Requirements 5 Documents Referenced 6 Keywords

More information

South Fork RFP LIPA Board of Trustees REV Committee Briefing. September 21, 2016

South Fork RFP LIPA Board of Trustees REV Committee Briefing. September 21, 2016 South Fork RFP LIPA Board of Trustees REV Committee Briefing September 21, 2016 Latest Developments A portfolio of projects is recommended to meet the needs of the South Fork, which includes the South

More information

Uncontrolled Document when printed. Refer to internet for latest version. Disclaimer refer

Uncontrolled Document when printed. Refer to internet for latest version. Disclaimer refer Issue June 2013 Page 83 of 91 SA Power Networks 2013 Network Tariff & Negotiated Services Manual No. 18 Issue June 2013 Page 84 of 91 SA Power Networks 2013 Network Tariff & Negotiated Services Manual

More information

WIND AND SOLAR ENERGY CONVERSION MODEL GUIDELINES CONSULTATION DRAFT REPORT AND DETERMINATION

WIND AND SOLAR ENERGY CONVERSION MODEL GUIDELINES CONSULTATION DRAFT REPORT AND DETERMINATION WIND AND SOLAR ENERGY CONVERSION MODEL GUIDELINES CONSULTATION DRAFT REPORT AND DETERMINATION Published: AUGUST 2016 DRAFT REPORT CONSULTATION ON AMENDMENTS TO THE WIND ENERGY CONVERSION MODEL (ECM) GUIDELINES

More information

QUALITY CONTROL Prepared: V. van Gastel / team TenneT Reviewed: M. Müller Approved: F. Wester BACKGROUND MATERIAL...

QUALITY CONTROL Prepared: V. van Gastel / team TenneT Reviewed: M. Müller Approved: F. Wester BACKGROUND MATERIAL... POSITION PAPER STAKE HOLDER CONSULTATION PROCESS OFFSHORE GRID NL Type: Position paper Work stream Technical Topic: T.1 Voltage level Filename ONL15-058-T1_Voltage level_pp_v1 Version 1 - release for Expert

More information

NEEDS SCREENING REPORT

NEEDS SCREENING REPORT Hydro One Networks Inc. 483 Bay Street Toronto, Ontario M5G 2P5 NEEDS SCREENING REPORT Region: GTA East Revision: Final Date: August 11, 2014 Prepared by: GTA East Region Study Team GTA East Region Study

More information

Performance Reporting Criteria

Performance Reporting Criteria Revision Date: February 2012 Revision No.: 2 Document No.: DOC-131102-ADV Status: Approved by CER Date: 01/03/2012 ESB Networks Ltd. Contents 1. Background... 3 2. Report Headings... 4 3. Criteria... 5

More information

CONTENTS 2. PROJECT DESCRIPTION NEED FOR THE PROJECT ABOUT THE PROPONENT SITE SELECTION OVERVIEW OF THE PROJECT 2 5

CONTENTS 2. PROJECT DESCRIPTION NEED FOR THE PROJECT ABOUT THE PROPONENT SITE SELECTION OVERVIEW OF THE PROJECT 2 5 CONTENTS 2. PROJECT DESCRIPTION 2-2 2.1 NEED FOR THE PROJECT 2 2 2.2 ABOUT THE PROPONENT 2 4 2.3 SITE SELECTION 2 4 2.4 OVERVIEW OF THE PROJECT 2 5 Figure 2.1: Provisional wind profile for the Jeffrey

More information

System Impact Study E001 Moon Lake 230 kv 200 MW Plant

System Impact Study E001 Moon Lake 230 kv 200 MW Plant System Impact Study E001 Moon Lake 230 kv 200 MW Plant Prepared by: Midcontinent Independent System Operator Independent Coordinator of Transmission 720 City Center Drive Carmel, IN 46032 Rev Issue Date

More information

PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES

PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES Prepared by: NIB/EOB PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES 05503 Department: Electric T&D Section: T&D Engineering and Technical Support Approved by: G.O. Duru (GOD)

More information

Analysis of distribution system reliability and outage rates

Analysis of distribution system reliability and outage rates Reclosers Technical Data TD280026EN Supersedes pril 2003 (R280-90-7) COOPER POWER SERIES nalysis of distribution system reliability and outage rates Recloser Technical Data TD280026EN nalysis of distribution

More information

Community and Stakeholder Consultation Report. Powering Sydney s Future

Community and Stakeholder Consultation Report. Powering Sydney s Future Community and Stakeholder Consultation Report Powering Sydney s Future Early Engagement July 2017 1. Executive Summary Powering Sydney s Future (the Project) aims to secure a reliable, safe and economical

More information

Distribution Network Planning for Mumbai

Distribution Network Planning for Mumbai Newsletter Issue 98 January 2006 Distribution Network Planning for Mumbai Carsten Böse Project Manager Siemens AG, PTD SE PT carsten.boese@siemens.com Introduction The Indian utility Reliance Energy Ltd.

More information

ASSET MANAGEMENT PLAN NETWORK TASMAN LIMITED

ASSET MANAGEMENT PLAN NETWORK TASMAN LIMITED ASSET MANAGEMENT PLAN 2012-2022 NETWORK TASMAN LIMITED CONTENTS 1 EXECUTIVE SUMMARY... 1 1.1 OVERVIEW AND PLAN PURPOSE... 1 1.2 CORPORATE OBJECTIVES AND ASSET MANAGEMENT DRIVERS... 1 1.3 STATUS OF PROGRAMMES

More information

TABLE OF CONTENTS LIST OF FIGURES LIST OF ATTACHMENTS

TABLE OF CONTENTS LIST OF FIGURES LIST OF ATTACHMENTS TABLE OF CONTENTS 2.0 TRANSMISSION SYSTEM OVERVIEW... 2-1 2.1 PROPOSED PROJECT OBJECTIVES... 2-2 2.2 SAFETY, RELIABILITY AND RESILIENCY, AND OPERATIONAL FLEXIBILITY AND CAPACITY... 2-5 2.2.0 Pipeline Safety...

More information

Investigation of Impacts of Solar PV on Transmission System Voltage Stability Considering Load Characteristics and Protection

Investigation of Impacts of Solar PV on Transmission System Voltage Stability Considering Load Characteristics and Protection 7th Solar Integration Workshop, 24-25 October 2017, Berlin, Germany Investigation of Impacts of Solar PV on Transmission System Voltage Stability Considering Load Characteristics and Protection Baheej

More information

4»IEEE POWER SYSTEMS .*ISK ASSESSMENT OF. Models, Methods, and Applications. Wiley. Ph.D., Fellow, IfE, CAE, EIC SECOND EDITION

4»IEEE POWER SYSTEMS .*ISK ASSESSMENT OF. Models, Methods, and Applications. Wiley. Ph.D., Fellow, IfE, CAE, EIC SECOND EDITION .*ISK ASSESSMENT OF POWER SYSTEMS Models, Methods, and Applications SECOND EDITION Wenyuan Li, Ph.D., Fellow, IfE, CAE, EIC Chongqing University, China BC H> Canada, n IEEE PRESS SERIES ON POWER ENGINEERING

More information

California Independent System Operator Corporation Fifth Replacement Tariff

California Independent System Operator Corporation Fifth Replacement Tariff Table of Contents Method to Assess Available Transfer Capability... 2 L.1 Description of Terms... 2 L.1.1 Available Transfer Capability (ATC)... 2 L.1.2 Total Transfer Capability (TTC)... 2 L.1.3 Existing

More information

Tariffs January 1, 2017

Tariffs January 1, 2017 Tariffs January 1, 2017 Nova Scotia Power Inc. Tariffs & Regulations Approved by the Nova Scotia Utility and Review Board pursuant to The Public Utilities Act, R.S.N.S., 189,c.380 as amended Tariffs For

More information

Index January 23, 2015 MANITOBA HYDRO 2015/16 & 2016/17 GENERAL RATE APPLICATION

Index January 23, 2015 MANITOBA HYDRO 2015/16 & 2016/17 GENERAL RATE APPLICATION 0 0 Tab Index MANITOBA HYDRO 0/ & 0/ GENERAL RATE APPLICATION CAPITAL EXPENDITURE FORECAST INDEX.0 Overview.... Capital Expenditure Forecast.... Electric Operations Capital Expenditure Forecast (CEF)....

More information

Information Document Protection System Information ID# R

Information Document Protection System Information ID# R Information Documents are for information purposes only and are intended to provide guidance. In the event of any discrepancy between the Information Document and the related authoritative document(s)

More information

Methodology for Determining and Communicating System Operating Limits for the Planning Horizon (FAC-010 & -014) Revision Log

Methodology for Determining and Communicating System Operating Limits for the Planning Horizon (FAC-010 & -014) Revision Log Revision Log Page 2 of 13 Revision or Change Number Effective Date Affected Page Numbers Description of Revision/Change 0000 03-26-2011 All Converted TPD document to SPP format 0001 03-26-2012 All Annual

More information

SOUTH AUSTRALIAN RENEWABLE ENERGY REPORT SOUTH AUSTRALIAN ADVISORY FUNCTIONS

SOUTH AUSTRALIAN RENEWABLE ENERGY REPORT SOUTH AUSTRALIAN ADVISORY FUNCTIONS SOUTH AUSTRALIAN RENEWABLE ENERGY REPORT SOUTH AUSTRALIAN ADVISORY FUNCTIONS Published: December 2016 IMPORTANT NOTICE Purpose The purpose of this publication is to provide information about renewable

More information

Transmission Owner Asset Management

Transmission Owner Asset Management Transmission Owner Asset Management Pieces of Asset Management New customers, load growth, repairs, maintenance, operational issues, etc. All the pieces make up the asset management plan for repair or

More information

AURORA ENERGY LTD. Use-of-System Pricing Methodology

AURORA ENERGY LTD. Use-of-System Pricing Methodology AURORA ENERGY LTD Methodology Applicable from 1 April 2009 Prices Applicable from 1 April 2009 1 INTRODUCTION 2 PRICING OBJECTIVES 3 COST STRUCTURE 4 REVENUE STRUCTURE 5 PRICING COMPONENTS 5.1 Distribution

More information

BR04 SERVICE PERFORMANCE MEASURES

BR04 SERVICE PERFORMANCE MEASURES SERVICE PERFORMANCE MEASURES 1 October 2013 C O P Y R I G H T 2013 T R A N S P O W E R N E W Z E A L A N D L I M I T E D. A L L R I G H T S R E S E R V E D This document is protected by copyright vested

More information

Customer Connection Guide. Document number SOP Issue number 9 Status Approver

Customer Connection Guide. Document number SOP Issue number 9 Status Approver Customer Connection Guide Document number SOP 11-4013 Issue number 9 Status Approver Approved T Hallam Date of approval 4/8/2014 Table of Contents 1 SUMMARY OF RESPONSIBILITIES... 4 1.1 OUR RESPONSIBILITIES...

More information

Information Document Service Proposals and Cost Estimating ID # R

Information Document Service Proposals and Cost Estimating ID # R Information Documents are not authoritative. Information Documents are for information purposes only and are intended to provide guidance. In the event of any discrepancy between an Information Document

More information

International ejournals

International ejournals ISSN 2249 5460 Available online at www.internationalejournals.com International ejournals International Journal of Mathematical Sciences, Technology and Humanities 21 (2011) 205 212 ENERGY CONTROL CENTER

More information

Transmission Expansion Advisory Committee. Reliability Analysis Update

Transmission Expansion Advisory Committee. Reliability Analysis Update Transmission Expansion Advisory Committee Reliability Analysis Update June 11, 2015 Deactivation Update Generation Deactivations 3 Deactivation Status Unit(s) FPL MH50 (50.8MWs) - UPDATED AES Beaver Valley

More information

VALUE OF CUSTOMER RELIABILITY REVIEW FINAL REPORT

VALUE OF CUSTOMER RELIABILITY REVIEW FINAL REPORT VALUE OF CUSTOMER RELIABILITY REVIEW FINAL REPORT Published: September 2014 IMPORTANT NOTICE Purpose The purpose of this publication is to provide information about the outcomes of AEMO s 2013 14 Value

More information

Technical considerations for integration of distributed renewables on the grid

Technical considerations for integration of distributed renewables on the grid Technical considerations for integration of distributed renewables on the grid A paper by Dr Charlotte Higgins, Dr Bunmi Adefajo & Kumbuyani Chisoro Kumbuyani Chisoro Manager Southern Africa TNEI Services

More information

Electric Rate Schedule GS-TOU General Service Commercial, Time-of-Use

Electric Rate Schedule GS-TOU General Service Commercial, Time-of-Use Page 1 of 5 Applicability This Schedule is offered as an option to commercial customers having demands from 500 kilowatts up to 1,000 kilowatts in any month during the previous twelve (12) months. Character

More information

Consultation on Connecting Further Generation in Northern Ireland. Call for Evidence

Consultation on Connecting Further Generation in Northern Ireland. Call for Evidence Consultation on Connecting Further Generation in Northern Ireland Call for Evidence 12 Table of Contents 1 Executive Summary... 3 2 Introduction... 6 2.1 Purpose of this Paper... 6 3 Alternative Connection

More information

Initial Plant Assessment Report

Initial Plant Assessment Report Initial Plant Assessment Report Modelling and Optimisation Report (Public Release Version) RATCH-Australia Collinsville Solar Thermal Power Station www.ratchaustralia.com 1 P a g e Contents Introduction...

More information

Annual Electricity Network Performance Results 2015/16. TransGrid

Annual Electricity Network Performance Results 2015/16. TransGrid T Annual Electricity Network Performance Results 2015/16 TransGrid Contents Introduction... 3 1. Profile... 4 1.1 Overview... 4 1.2 Capital Works Program... 7 2. Network Management... 9 2.1 Overview...

More information

2750 Monroe Blvd Audubon, PA

2750 Monroe Blvd Audubon, PA 2750 Monroe Blvd Audubon, PA 19403-2497 October 21, 2014 Mr. Jonathan Feipel Executive Director Illinois Commerce Commission 527 East Capitol Avenue Springfield, Illinois 62701 Dear Mr. Feipel: This report

More information

Factors Affecting Current Ratings for Underground and Air Cables

Factors Affecting Current Ratings for Underground and Air Cables Factors Affecting Current Ratings for Underground and Air Cables S. H. Alwan, J. Jasni, M. Z. A. Ab Kadir, N. Aziz Abstract The aim of this paper is to present a parametric study to determine the major

More information

ANTICIPATING AND ADDRESSING SECURITY CHALLENGES IN AN EVOLVING POWER SYSTEM

ANTICIPATING AND ADDRESSING SECURITY CHALLENGES IN AN EVOLVING POWER SYSTEM ANTICIPATING AND ADDRESSING SECURITY CHALLENGES IN AN EVOLVING POWER SYSTEM January 2017 PRESENTED BY JENNY RIESZ SLIDE 1 AGENDA 1. Introduction to the NEM 2. Future Power System Security Program 3. Identifying

More information

Five Minute Settlement. Submission to AEMC Directions Paper May 2017

Five Minute Settlement. Submission to AEMC Directions Paper May 2017 Contents Introduction...3 Assessment framework and materiality...4 Impact on operation and investment...6 Design issues...6 Costs and transition...7 Conclusion...8 2 Introduction Energy Consumers Australia

More information

TRANSPOWER S ASSET MANAGEMENT STRATEGIES AND PLANS

TRANSPOWER S ASSET MANAGEMENT STRATEGIES AND PLANS TRANSPOWER S ASSET MANAGEMENT STRATEGIES AND PLANS AN INDEPENDENT REVIEW BY BW CONSULTING Transpower New Zealand Limited December 2010 Transpower s asset management strategies and plans Transpower New

More information

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments Rule 007 Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments This rule as amended was approved by the Alberta Utilities Commission on December

More information

Southwest Power Pool CRITERIA

Southwest Power Pool CRITERIA Southwest Power Pool CRITERIA LATEST REVISION: April 28, 2015 FOREWORD... i INTRODUCTION... ii 1.0 LOAD AND ENERGY FORECASTS...1-1 2.0 CAPACITY MARGIN...2-1 2.1 Definitions...2-1 2.1.1 Load Serving Member...2-1

More information

Total Transmission Cost Estimate for the Maximum Reserve Capacity Price for 2018/19

Total Transmission Cost Estimate for the Maximum Reserve Capacity Price for 2018/19 Total Transmission Cost Estimate for the Maximum Reserve Capacity Price for 2018/19 Date: 19 October 2015 Prepared by: Regulation and Investment Management DM 12392512 Contents Introduction... 2 1.1 Revised

More information

Revision to ISO Transmission Planning Standards

Revision to ISO Transmission Planning Standards Revision to ISO Transmission Planning Standards Market and Infrastructure Policy Straw Proposal REVISED DRAFT May 28, 2014 Revision to ISO Transmission Planning Standards May 28, 2014 Straw Proposal Table

More information

First Stage Rules Consultation Congestion Information Resource (CIR) Guidelines

First Stage Rules Consultation Congestion Information Resource (CIR) Guidelines Mr Ben Blake Manager Electricity Constraints Australian Energy Market Operator PO Box 7326 Baulkham Hills BC NSW 2153 Submitted via email: ben.blake@aemo.com.au 23 March 2012 Dear Mr Blake First Stage

More information

Benefit-Cost Analysis Summary Report

Benefit-Cost Analysis Summary Report Benefit-Cost Analysis Summary Report Site 74 City of Syracuse PROJECT OVERVIEW As part of NYSERDA s NY Prize community microgrid competition, the CNY RPDB has proposed development of a microgrid that would

More information

NATIONAL ELECTRICITY FORECASTING REPORT FOR THE NATIONAL ELECTRICITY MARKET

NATIONAL ELECTRICITY FORECASTING REPORT FOR THE NATIONAL ELECTRICITY MARKET NATIONAL ELECTRICITY FORECASTING REPORT FOR THE NATIONAL ELECTRICITY MARKET Published: June 2016 IMPORTANT NOTICE Purpose AEMO has prepared this document in connection with its national transmission planning

More information

Jan Strack and Huang Lin March 14, 2017

Jan Strack and Huang Lin March 14, 2017 SDG&E Request for Economic Planning Study of the Renewable Energy Express Transmission Project as part of CAISO s 2017-2018 Transmission Planning Process (TPP) Jan Strack (jstrack@semprautilities.com)

More information

Patrick McHugh. Vice President Con Edison

Patrick McHugh. Vice President Con Edison Patrick McHugh Vice President Con Edison Agenda BQDM overview Utility-sided storage project Customer-sided storage project Marcus Garvey Clean virtual power plant Storage demonstration portfolio DR Auction

More information

MOD-001-1a Available Transfer Capability Implementation Document

MOD-001-1a Available Transfer Capability Implementation Document Available Transfer Capability Implementation Document For NERC MOD-001-2a Page 1 of 18 1.0 Purpose The California Independent System Operator Corporation (ISO), as a Transmission Service Provider 1 and

More information

Business Practice Manual for The Transmission Planning Process

Business Practice Manual for The Transmission Planning Process Business Practice Manual for The Transmission Planning Process Posted: June 2, 2015 Intentionally left blank TABLE OF CONTENTS 1. Introduction... 9 1.1. Purpose of California ISO Business Practice Manuals...

More information

Demand based network tariffs offering a new choice

Demand based network tariffs offering a new choice Version 1.1 30 September 2015 Demand based network tariffs offering a new choice Consultation paper September 2015 Table of Contents 1 Overview... 5 2 Background... 7 3 Purpose... 8 4 Network tariff strategy...

More information

Attachment B. [Note: The following new definitions inserted after the definition of Regulations ]

Attachment B. [Note: The following new definitions inserted after the definition of Regulations ] Attachment B Comparison Version of the Final Amendments to the Distribution System Code Relative to the Distribution System Code Prior to the Adoption of the Final Amendments (for information purposes

More information

INITIAL ASSESSMENT OF REACTIVE POWER EXCHANGES AT UK GRID SUPPLY POINTS

INITIAL ASSESSMENT OF REACTIVE POWER EXCHANGES AT UK GRID SUPPLY POINTS INITIAL ASSESSMENT OF REACTIVE POWER EXCHANGES AT UK GRID SUPPLY POINTS Christos KALOUDAS The University of Manchester UK christos.kaloudas@manchester.ac.uk Ben MARSHALL National Grid UK ben.marshall@nationalgrid.com

More information

Schedule 2 TECHNICAL INFORMATION

Schedule 2 TECHNICAL INFORMATION Schedule 2 TECHNICAL INFORMATION This document is intended to provide context to the Haida Gwaii Request for Expressions of Interest (RFEOI) for the potential electricity supply opportunity for clean electricity

More information

System Management Standard. System Restart Services. (System Restart Standard)

System Management Standard. System Restart Services. (System Restart Standard) System Management System Management Standard System Restart Services (System Restart Standard) This Standard is a guide to the acquisition of System Restart Services. 1 October 2014 Table of contents 1.

More information