MARITIME ELECTRIC Environmental Assessment

Size: px
Start display at page:

Download "MARITIME ELECTRIC Environmental Assessment"

Transcription

1 Project No.: ADDENDUM MARITIME ELECTRIC Environmental Assessment O Leary to Sherbooke Transmission Line ISO 9001 Registered Company

2

3 Changes or Additions The following information is provided as an addendum to, or clarification of, the environmental assessment of the O Leary to Sherbrooke Transmission Line. The proposed transmission line is designed to conduct 200 MW and will therefore have the capacity to accommodate additional wind power that is generated in Prince County. Section 1.2 now reads: To reflect the above fact the following clarifications and additions in bold should be read into the environmental assessment. 1.2 Project Overview Maritime Electric Company, Limited (MECL) is proposing to construct and operate a 138 kv transmission line from its substation in St. Anthony near O Leary to the Sherbrooke Substation near Summerside, a distance of approximately 60 km (see Figure 1.1) in Prince County in western PEI. The proposed transmission line will connect to the recently constructed 138 kv 3 phase transmission line that extends from the West Cape Wind Energy Inc. wind farm to the O Leary Substation; it will also have the capacity to accommodate another 100 MW from other wind farms that may be constructed in the future. From the O Leary Substation the new line would be routed to the Sherbrooke Substation; there is no need for new substations, switching stations or other interconnections between these locations at this time. Construction at the Sherbrooke Substation will involve the installation of additional equipment inside the existing fenced area. At the O Leary Substation construction will be limited to the removal of some of the existing equipment inside the fenced area. Section 1.3 now reads: 1.3 Project Need and Justification Phase I of the West Cape Wind Farm, which is owned and operated by Suez Renewable Energy North America, was completed in 2007; the wind farm is located some 19 km from the O Leary Substation. This first phase consisted of 11 x 1.8 megawatt (MW) wind turbines with the capacity of generating up to 20 MW. Phase II of this development is designed to increase the total generation capacity to 100 MW; the in-service target date is the fall of To accommodate this increased transmission load, a transmission line to enable later use at 138 kv was constructed from the wind farm along the highway right-of-way to the O Leary Substation. With Phase II of the West Cape Wind Farm coming on line, there is a need to increase the capacity of the transmission system between the O Leary Substation and the Sherbrooke Substation. It is therefore proposed to construct a new transmission line to connect the existing 138 kv line to the O Leary Substation to the Sherbrooke Substation. To facilitate future wind development in the area, the 138 kv transmission line will be constructed with an additional circuit capable of transmitting up to an additional 100 MW of electricity. Section now reads: Electric and Magnetic Fields As indicated in Section , the issue that is raised about EMF from overhead transmission lines is the perception that EMF exposure can increase the occurrence of certain chronic health issues. Nearly two

4 decades of study on this topic, however, have shown that the evidence suggesting that EMF exposures pose any health risk is weak. According to the National Institute of Environmental Health Sciences, the strongest evidence for health effects has been in epidemiological studies for childhood leukaemia and chronic lymphocytic leukaemia in occupationally exposed adults. While epidemiological studies are limited in their ability to demonstrate a cause and effect relationship, cause and effect relationships can be inferred from laboratory studies. The laboratory studies in this case fail to demonstrate any consistent pattern across studies, and no indication of increased leukaemia in experimental animals has been observed. Based on previous measurements and calculations undertaken by MECL, it is estimated that the EMF values associated with an energized 138 kv line will range from 37 mg (3.7 x 10-6 T) directly underneath the fully loaded (100MW) line, 14.0 mg (14.0 x 10-7 T) at 15 m. from the line and 4.6 mg (4.6 x 10-7 T) at 30.5 m. from the line. The predicted EMF values versus distance curve is shown in Figure 6.1. When the additional 138 kv circuit is put in to service future wind development, an EMF cancellation effect due to individual line configuration will reduce the EMF values. With both circuits fully loaded (200 MW), the EMF levels will range from 23.3 Mg (2.3 X 10-6 T) directly under the transmission line, 4.5 mg (0.45 X 10-6 T) at 15 meters from the line and 0.9 mg (0.1 X 10-6 T) at 30.5 meters from the line. The predicted EMF values verses the distance curves are shown on Figure 6.2. To determine the background EMF values at various residences prior to energizing a 138 kv transmission line, MECL measured EMF values at several private residences before and after the construction of a 138 kv transmission line in western Prince Edward Island. During the background testing, the technician noted that in most of the homes, residents had unplugged their appliances, computers, televisions and turned off their lights; therefore the actual background EMF exposure in these homes is most likely higher than that measured. The results of the background testing indicated that EMF readings were highest at the point where the electrical service enter the house with readings as high as 403 mg. Inside the homes readings ranged from 0.1 mg in those areas where no appliances or lights were on, to 59.6 mg next to a fish tank that was on in one of the residences. This is in keeping with the literature which shows typical EMF values for electrical devices used in the homes and workplace to be fairly high (see Table 6.2). Many of these readings, along with the background readings obtained by MECL are higher that the anticipated EMF field measurements directly below a fully energized 138 kv line. Table 6.2: EMF Data Readings for Common Appliances (mg) Appliance EMF (10 cm from source) EMF reading (30 cm from source) EMF reading (1 m from source) Blender Clothes Dryer Clothes washers <0.1 Coffee Makers <0.1 Fluorescent Desk Lamp Hair Dryers < < Television < Source: and is based on data obtained from Gauger, J.R.

5 There are no standards or regulations in Canada associated with EMF, nor are there any regulations which dictate a minimum distance between residences and transmission lines. The International Commission on Non Ionizing Radiation Protection (ICNIRP) has developed voluntary guidelines for occupational exposure to EMF, but also exposure to EMF by the general public. It is assumed that these numbers are based upon a timed exposure of an eight-hour day for the occupational exposure and a 24 hour a day exposure for the general public. These guidelines are intended to prevent effects, such as induced currents in cells or nerve stimulation, which are known to occur at high magnitudes, much higher (more than 1,000 times higher) than EMF levels found typically in occupational and residential environments. These guidelines are summarized in Table 6.3. Table 6.3: ICNIRP Guideline Summary for Exposure to EMFs ICNIRP Guidelines for EMF Exposure Exposure (60 Hz) Electric field Magnetic field Occupational 8.3 kv/m 4.2 G (4,200 mg) General Public 4.2 kv/m G (833 mg) International Commission on Non-Ionizing Radiation Protection (ICNIRP) is an organization of 15,000 scientists from 40 nations who specialize in radiation protection. Source: ICNIRP, All of the anticipated EMF values for a 138 kv line are below these guidelines. i) Boundaries Given the linear nature of the Project footprint, the physical boundaries can be defined as a linear corridor 30 m either side of the transmission line. The temporal boundaries relate to the anticipated life of the Project. ii) Pathway Analysis As discussed above and in Section , a 138 kv power line emits low frequency, long wave length nonionizing electromagnetic energy. At a frequency of 60 Hz, it is well below the levels emitted by the microwave, or the RF radiation emitted by cellular phones and radio broadcast transmitters. Epidemiological studies have failed to establish a cause and effect relationship between electromagnetic energy and health concerns. Based on the evidence there is no obvious pathway between the proposed Project and the articulated public concern with respect to EMFA. iii) Mitigative Measures No pathway has been identified. There are no federal or provincial regulations in place; Health Canada does not consider guidelines necessary because the scientific evidence is not strong enough to conclude that typical exposures cause health exposures. No mitigative measures are proposed. iv) Residual Effects In the absence of a defined pathway and scientific verification of cause and effect, there is no impact. There can therefore be no residual effects.

6 Figure 6.2: EMF Levels 138kV Double Circuit Vertical Orientation

4.8 ENVIRONMENTAL HEALTH - ELECTRIC AND MAGNETIC FIELDS

4.8 ENVIRONMENTAL HEALTH - ELECTRIC AND MAGNETIC FIELDS 4.8 ENVIRONMENTAL HEALTH - ELECTRIC AND MAGNETIC FIELDS This section provides project-level discussion and analysis of potential health and safety impacts related to power frequency electric and magnetic

More information

Scaling Public Concerns of Electromagnetic Fields Produced by Solar Photovoltaic Arrays

Scaling Public Concerns of Electromagnetic Fields Produced by Solar Photovoltaic Arrays Scaling Public Concerns of Electromagnetic Fields Produced by Solar Photovoltaic Arrays Introduction In our modern society electricity is vital to our health, safety, comfort and well-being. While our

More information

UNDERSTANDING ELECTRIC AND MAGNETIC FIELDS

UNDERSTANDING ELECTRIC AND MAGNETIC FIELDS UNDERSTANDING ELECTRIC AND MAGNETIC FIELDS CONTENTS 3 BC Hydro & EMF 4 What are Electric & Magnetic Fields? 5 A Comparison of Electric & Magnetic Fields 6 Electric Fields 7 Magnetic Field Strength 9 Magnetic

More information

RP01/ An Overview on Governments Positions and Policies Regarding Electromagnetic Fields

RP01/ An Overview on Governments Positions and Policies Regarding Electromagnetic Fields RP01/95-96 An Overview on Governments Positions and Policies Regarding Electromagnetic Fields Research and Library Services Division Legislative Council Secretariat October 1995 An Overview on Governments

More information

Understanding Electric and Magnetic Fields

Understanding Electric and Magnetic Fields Understanding Electric and Magnetic Fields Contents What we do about EMF.... 3 What are electric & magnetic fields?.... 5 Comparing electric & magnetic fields... 6 Electric field strength... 7 Magnetic

More information

X:\Transbay\ADEIR 3\Appendices\Appendix K\App K cvrsht.doc K-1 4/29/ :09:58 AM

X:\Transbay\ADEIR 3\Appendices\Appendix K\App K cvrsht.doc K-1 4/29/ :09:58 AM Information pertaining to electric and magnetic fields (EMF) associated with transmission lines is discussed in this appendix. The discussion provides overview of the physical parameters of EMF and also

More information

Galloper Wind Farm Project Environmental Statement Chapter 28: Electric and Magnetic Fields October 2011 Document Reference

Galloper Wind Farm Project Environmental Statement Chapter 28: Electric and Magnetic Fields October 2011 Document Reference Galloper Wind Farm Project Environmental Statement Chapter 28: Electric and Magnetic Fields October 2011 Document Reference 5.2.28 Galloper Wind Farm Limited Document title Galloper Wind Farm Project Environmental

More information

EMF & YOU. Information about Electric & Magnetic Fields and the electricity network in Ireland. April 2017 EMF & YOU 1

EMF & YOU. Information about Electric & Magnetic Fields and the electricity network in Ireland. April 2017 EMF & YOU 1 EMF & YOU Information about Electric & Magnetic Fields and the electricity network in Ireland April 2017 EMF & YOU 1 ABOUT ESB WELCOME ESB was established in 1927, as a corporate body in the Republic of

More information

I. ELECTRIC AND MAGNETIC FIELDS

I. ELECTRIC AND MAGNETIC FIELDS I. ELECTRIC AND MAGNETIC FIELDS This section provides EMF information for the Project, presenting projections for future EMF levels associated with the proposed transmission line in each segment of the

More information

Electromagnetic fields (EMF) What are electromagnetic fields?

Electromagnetic fields (EMF) What are electromagnetic fields? Electromagnetic fields (EMF) What are electromagnetic fields? Current standards Standards are set to protect our health and are well known for many food additives, for concentrations of chemicals in water

More information

Walk through the associated design considerations associated with transmission line design

Walk through the associated design considerations associated with transmission line design Walk through the associated design considerations associated with transmission line design Follow-up to Transmission Design 101 (2012) & Transmission Design 102 (2013) Additional design considerations

More information

ELF EMF AND SLOVENIAN LEGISLATION. Elektroinštitut Milan Vidmar (EIMV)

ELF EMF AND SLOVENIAN LEGISLATION. Elektroinštitut Milan Vidmar (EIMV) ELF EMF AND SLOVENIAN LEGISLATION Elektroinštitut Milan Vidmar (EIMV) 1 EIMV activities in the field of ELF EMF 1. Measurements and calculation of electric and magnetic fields (E and B) 2. Conformity assessment

More information

Quick guide to living and working near electric transmission lines

Quick guide to living and working near electric transmission lines Quick guide to living and working near electric transmission lines October 2015 about atc American Transmission Co. has approximately 50,000 easement agreements with property owners in our service area.

More information

EMF: Electric and Magnetic Fields

EMF: Electric and Magnetic Fields EMF: Electric and Your trusted source for energy information EMF and Scientific Studies For over 40 years, there has been a great deal of scientific research devoted to finding out more about electric

More information

Electric and Magnetic Fields due to Rooftop Photovoltaic Units

Electric and Magnetic Fields due to Rooftop Photovoltaic Units Electric and Magnetic Fields due to Rooftop Photovoltaic Units Anastasia S. Safigianni *1, Aristotle M. Tsimtsios 2 Electrical and Computer Engineering Department, Democritus University of Thrace University

More information

D-1. SOUTH PEACE EAST AND WEST SOP PROJECTS PATRICK HENN, DEVELOPMENT MANAGER PRRD Board of Directors Meeting, April

D-1. SOUTH PEACE EAST AND WEST SOP PROJECTS PATRICK HENN, DEVELOPMENT MANAGER PRRD Board of Directors Meeting, April SOUTH PEACE EAST AND WEST SOP PROJECTS PATRICK HENN, DEVELOPMENT MANAGER PRRD Board of Directors Meeting, April 28 2016 Renewable Energy Systems (RES) In Canada for more than 12 years Family-owned company

More information

Company Directive. Relating to Occupational Exposure to Electromagnetic Fields

Company Directive. Relating to Occupational Exposure to Electromagnetic Fields Company Directive STANDARD TECHNIQUE: HS12R Relating to Occupational Exposure to Electromagnetic Fields Summary This document details the requirements to ensure the health and safety of staff and contractors

More information

Up to 9.5MW AC solar project located near Burdett, Alberta

Up to 9.5MW AC solar project located near Burdett, Alberta PROJECT OVERVIEW Up to 9.5MW AC solar project located near Burdett, Alberta Located on agricultural land within the quarter section NE-21-010-12-W4M near the intersection of Range Road 123 and Township

More information

14 INFRASTRUCTURE, TELECOMMUNICATIONS & SHADOW FLICKER

14 INFRASTRUCTURE, TELECOMMUNICATIONS & SHADOW FLICKER Knockskae Wind Farm Environmental Statement Volume 2 Main Report 14-1 14 INFRASTRUCTURE, TELECOMMUNICATIONS & SHADOW FLICKER 14.1 Introduction 14.1.1 This Chapter has been prepared by. It identifies and

More information

Guidelines for Best Practice in relation to Electric and Magnetic Fields (EMFs) in the Design and Management of Low Voltage Distribution Networks

Guidelines for Best Practice in relation to Electric and Magnetic Fields (EMFs) in the Design and Management of Low Voltage Distribution Networks PRODUCED BY THE OPERATIONS DIRECTORATE OF ENERGY NETWORKS ASSOCIATION Engineering Recommendation G92 Guidelines for Best Practice in relation to Electric and Magnetic Fields (EMFs) in the Design and Management

More information

4.5 ELECTROMAGNETIC FIELDS

4.5 ELECTROMAGNETIC FIELDS 4.5 ELECTROMAGNETIC FIELDS This section presents information on electromagnetic fields and interference related to the BEP and SVRTP alternatives. Information in this section is based on the Electromagnetic

More information

ORION NEW ZEALAND LIMITED NOTICE OF REQUIREMENT BROMLEY ZONE SUBSTATION, CHRISTCHURCH

ORION NEW ZEALAND LIMITED NOTICE OF REQUIREMENT BROMLEY ZONE SUBSTATION, CHRISTCHURCH ORION NEW ZEALAND LIMITED NOTICE OF REQUIREMENT BROMLEY ZONE SUBSTATION, CHRISTCHURCH Date of Issue: 15 July 2014 ORION NEW ZEALAND LIMITED NOTICE OF REQUIREMENT BROMLEY ZONE SUBSTATION, CHRISTCHURCH Prepared

More information

LETTER OF NOTIFICATION FOR THE DON MARQUIS-BIXBY 345 KV TRANSMISSION LINE PROP STRUCTURE PROJECT

LETTER OF NOTIFICATION FOR THE DON MARQUIS-BIXBY 345 KV TRANSMISSION LINE PROP STRUCTURE PROJECT LETTER OF NOTIFICATION FOR THE DON MARQUIS-BIXBY 345 KV TRANSMISSION LINE PROP STRUCTURE PROJECT PUCO Case No. 14-1397-EL-BLN Submitted pursuant to OAC 4906-11-01 AEP Ohio Transmission Company (AEP Ohio

More information

Information Document Protection System Information ID# R

Information Document Protection System Information ID# R Information Documents are for information purposes only and are intended to provide guidance. In the event of any discrepancy between the Information Document and the related authoritative document(s)

More information

EAST-WEST TIE TRANSMISSION PROJECT

EAST-WEST TIE TRANSMISSION PROJECT EAST-WEST TIE TRANSMISSION PROJECT Connecting Ontario s Northwest THANK YOU for attending this Open House We want to hear from you www.nextbridge.ca Purpose of the Open House We are here to provide you

More information

National Policy Statement on Electricity Transmission. Implementation Guidance for Local Authorities

National Policy Statement on Electricity Transmission. Implementation Guidance for Local Authorities National Policy Statement on Electricity Transmission Implementation Guidance for Local Authorities Acknowledgements Thank you to Local Government New Zealand, Transpower New Zealand Ltd, Boffa Miskell,

More information

Your guide to the. SOUTHERN ALBERTA Transmission Reinforcement

Your guide to the. SOUTHERN ALBERTA Transmission Reinforcement Your guide to the SOUTHERN ALBERTA Transmission Reinforcement OUR TRANSMISSION LINES TRANSPORT THE POWER YOU USE EVERY DAY. Edmonton Red Deer Calgary Lethbridge 85% AltaLink s transmission system efficiently

More information

Impact of innovation on renewables Integration on renewables

Impact of innovation on renewables Integration on renewables 16 TH ERRA ENERGY INVESTMENT AND REGULATION CONFERENCE, SEPTEMBER 25-26, 2017, ASTANA, KAZAKHSTAN Impact of innovation on renewables Integration on renewables DR. ALEXANDRE OUDALOV, MARKET INNOVATION,

More information

Amherst Island Wind Energy Project - Renewable Energy Approval Amendment Modification Report #4

Amherst Island Wind Energy Project - Renewable Energy Approval Amendment Modification Report #4 Amherst Island Wind Energy Project - Renewable Energy Approval Amendment Modification Report #4 Prepared for: Windlectric Inc. 2845 Bristol Circle Oakville ON L9H 7H7 Prepared by: Stantec Consulting Ltd.

More information

1 The International Space Station (ISS) has several solar panels called wings. The wings convert energy from the Sun into a form useful in the ISS.

1 The International Space Station (ISS) has several solar panels called wings. The wings convert energy from the Sun into a form useful in the ISS. 1 The International Space Station (ISS) has several solar panels called wings. The wings convert energy from the Sun into a form useful in the ISS. (a) The energy reaching the ISS from the Sun is carried

More information

Ellerslie Substation Expansion

Ellerslie Substation Expansion Ellerslie Substation Expansion Volume 2 UV 2 North Saskatchewan River EDMONTON UV 216 UV 14 ") ELLERSLIE 89S Bretona!! Trevithick March 2010 Why are you receiving this newsletter? You are receiving this

More information

Sudbury to Hudson Transmission Reliability Project Frequently Asked Questions (FAQs)

Sudbury to Hudson Transmission Reliability Project Frequently Asked Questions (FAQs) Sudbury to Hudson Transmission Reliability Project Frequently Asked Questions (FAQs) June 2, 2016 revised Project Overview Eversource is proposing to construct a new 115-kilovolt (kv) transmission line

More information

Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017

Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017 Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA March 21, 2017 Contents 1 Background...3 2 National and Regional Criteria and Guides...4 2.1 2.1 NERC Transmission Planning Standards...4 2.2

More information

October 20, International Commission on Non-Ionizing Radioprotection Protection. Madam, sir,

October 20, International Commission on Non-Ionizing Radioprotection Protection. Madam, sir, October 20, 2009 International Commission on Non-Ionizing Radioprotection Protection Danielle Laurier Directrice Santé et sécurité Hydro-Québec 75, boul. René-Lévesque Ouest 7e étage Montréal (Québec)

More information

Reducing Electromagnetic Field Exposure from Hydro Corridors

Reducing Electromagnetic Field Exposure from Hydro Corridors STAFF REPORT ACTION REQUIRED Reducing Electromagnetic Field Exposure from Hydro Corridors Date: June 18, 2008 To: From: Wards: Board of Health Medical Officer of Health All Reference Number: SUMMARY The

More information

Preferential Subjects for the 2010 Session

Preferential Subjects for the 2010 Session Preferential Subjects for the 2010 Session Study Committee A1 PS1: Developments in Electrical Machine Design and Experience in Service New trends in design, materials, insulation, cooling and bearings

More information

EAST-WEST TIE TRANSMISSION PROJECT

EAST-WEST TIE TRANSMISSION PROJECT Connecting Ontario s Northwest What s Inside? Answers to On: NextBridge Infrastructure and the East-West Tie Project Electricity in Northern Ontario Land issues Routing Project approval process Health

More information

An electric motor is designed to transform electrical energy into. Some of the electrical energy supplied to the motor is wasted as

An electric motor is designed to transform electrical energy into. Some of the electrical energy supplied to the motor is wasted as (a) Complete the following sentences. (i) An electric motor is designed to transform electrical energy into... energy. (ii) Some of the electrical energy supplied to the motor is wasted as... energy and...

More information

RENEWABLE ENERGY SERVICES GRID SOLUTIONS

RENEWABLE ENERGY SERVICES GRID SOLUTIONS RENEWABLE ENERGY SERVICES GRID SOLUTIONS 1 ABOUT US Leaders in Global Services for Renewable Energy UL works to help renewable energy manufacturers, developers, owners, investors, lenders, utilities and

More information

Eastside Needs Assessment Report Transmission System King County Executive Summary December 2013

Eastside Needs Assessment Report Transmission System King County Executive Summary December 2013 Attachment 4 - Needs Assessment Eastside Needs Assessment Report Transmission System King County Executive Summary December 2013 PO BOX 97034, EST06W Bellevue, WA 98004 1-800-548-2614 Attachment 4 - Needs

More information

AMERICAN RENEWABLES GAINESVILLE REGIONAL UTILITIES GAINESVILLE RENEWABLE ENERGY CENTER

AMERICAN RENEWABLES GAINESVILLE REGIONAL UTILITIES GAINESVILLE RENEWABLE ENERGY CENTER AMERICAN RENEWABLES GAINESVILLE REGIONAL UTILITIES --------------------------------------------- GAINESVILLE RENEWABLE ENERGY CENTER OPERATING PROCEDURES Revision 0; September 1, 2012 Revision 1; November

More information

ENERGY AND TELECOMMUNICATIONS

ENERGY AND TELECOMMUNICATIONS ENERGY AND 13 13 ENERGY AND Vision To accord with the principles of sustainable development and to be at the forefront of new technology, it is the vision of this Plan to encourage and support energy efficiency,

More information

Most Severe Single Contingency (MSSC) Impacts on Alberta Balancing Authority Area Operation. Observations and Information Sharing

Most Severe Single Contingency (MSSC) Impacts on Alberta Balancing Authority Area Operation. Observations and Information Sharing Most Severe Single Contingency (MSSC) Impacts on Alberta Balancing Authority Area Operation Observations and Information Sharing Date: June, 2015 Prepared by: AESO Table of Contents Executive Summary...

More information

Preliminary Environmental Information Report

Preliminary Environmental Information Report Riverside Energy Park Preliminary Environmental Information Report CHAPTER: 02 PLANNING INSPECTORATE REFERENCE NUMBER: EN010093 REGULATORY AND POLICY BACKGROUND June 2018 Revision 0 Planning Act 2008 Infrastructure

More information

ORDINANCE NO. Commercial WECS: A WECS of equal to or greater than 15 kw in total name plate generating capacity.

ORDINANCE NO. Commercial WECS: A WECS of equal to or greater than 15 kw in total name plate generating capacity. ORDINANCE NO. AN ORDINANCE AMENDING ORDINANCE NO. 1060 KNOWN AS THE WILLMAR ZONING ORDINANCE BY ADDING SECTION 11 RELATING TO WIND ENERGY CONVERSION SYSTEMS (WECS) The City of Willmar does ordain as follows:

More information

Electric and Magnetic Forces

Electric and Magnetic Forces Imagine that you had two superpowers. Both powers allow you to move things without touching them. You can even move things located on the other side of a wall! One power is the ability to pull something

More information

DISTRIBUTED ENERGY RESOURCE INTERCONNECTION PROCESS REQUIREMENTS

DISTRIBUTED ENERGY RESOURCE INTERCONNECTION PROCESS REQUIREMENTS DISTRIBUTED ENERGY RESOURCE INTERCONNECTION PROCESS REQUIREMENTS FOR DISTRIBUTED GENERATION AND LARGE MICRO-GENERATION FortisAlberta s Distributed Energy Resource (DER) Process explains what is required

More information

Lakeshore Looks to the Future with Renewable Energy

Lakeshore Looks to the Future with Renewable Energy Lakeshore Looks to the Future with Renewable Energy Wind Energy Farm Projects are Renewable Energy Systems. They are large scale generating systems comprised of one or more generating units (wind turbines)

More information

6. CONCLUSIONS AND RECOMMENDATIONS

6. CONCLUSIONS AND RECOMMENDATIONS Environmental Impact Assessment Report: Proposed third 400 kv Transmission line between Poseidon and Grassridge, Eastern Cape and Extension to Grassridge 6. CONCLUSIONS AND RECOMMENDATIONS This Environmental

More information

SOCIAL IMPACT ASSESSMENT FOR

SOCIAL IMPACT ASSESSMENT FOR SOCIAL IMPACT ASSESSMENT FOR BOITSHOKO SOLAR (RF) (PTY) LTD ENERGY FACILITY NORTHERN CAPE PROVINCE April 2016 Prepared for Boitshoko Solar (RF) (Pty) Ltd By Leandri Kruger EXECUTIVE SUMMARY INTRODUCTION

More information

Strong Breeze Wind Project

Strong Breeze Wind Project IESO LRP 1 RFP Date: July 2, 2015 Qualified Applicant: Invenergy LLC 120 Front Street East, Suite 201 Toronto, ON M5A 4L9 Registered Proponent: Strong Breeze Wind Power Partnership Email: strongbreezeinfo@invenergyllc.com

More information

AMERICAN RENEWABLES GAINESVILLE REGIONAL UTILITIES GAINESVILLE RENEWABLE ENERGY CENTER

AMERICAN RENEWABLES GAINESVILLE REGIONAL UTILITIES GAINESVILLE RENEWABLE ENERGY CENTER AMERICAN RENEWABLES GAINESVILLE REGIONAL UTILITIES --------------------------------------------- GAINESVILLE RENEWABLE ENERGY CENTER OPERATING PROCEDURES Revision 0; September 1, 2012 Revision 1; November

More information

3. Introducing Narda Workers Directive preliminary approach

3. Introducing Narda Workers Directive preliminary approach 1. EU Legislation 1. Introducing Narda 2. Introducing Legislations / General Public and Workers 3. Introducing Narda Workers Directive preliminary approach Johann Saustingl j.saustingl@willtron.at +43

More information

Decision GTE Solar Inc. Brooks Solar Power Plant. January 31, 2013

Decision GTE Solar Inc. Brooks Solar Power Plant. January 31, 2013 Decision 2013-027 Brooks Solar Power Plant January 31, 2013 The Alberta Utilities Commission Decision 2013-027: Brooks Solar Power Plant Application No. 1608532 Proceeding ID No. 1938 January 31, 2013

More information

Exposure to the magnetic fields generated by waterbeds can be reduced by the following precautions:

Exposure to the magnetic fields generated by waterbeds can be reduced by the following precautions: Waterbeds Date: 19 October 2016 Unlike conventional beds, which have mattresses made of foam, latex or natural products, waterbeds feature a mattress with a water-filled core. To prevent the loss of body

More information

BTEC Unit 1 Physics Revision. Learning Aim E: Energy Stores, Energy Transfers and Energy Transformations

BTEC Unit 1 Physics Revision. Learning Aim E: Energy Stores, Energy Transfers and Energy Transformations BTEC Unit 1 Physics Revision Learning Aim E: Energy Stores, Energy Transfers and Energy Transformations Forms of Energy and Their Uses Kinetic (Mechanical) Description and Use The energy in moving objects.

More information

EMF Exposure from Selected Laboratory and Office Equipment

EMF Exposure from Selected Laboratory and Office Equipment EMF Exposure from Selected Laboratory and Office H. Aniolczyk, P. Politanski, P. Mamrot Nofer s Institute of Occupational Medicine, 90-950 Lodz, Poland. E-mail: h_aniol@imp.lodz.pl Abstract. EMF of different

More information

Canadian Natural Resources Limited

Canadian Natural Resources Limited Decision 23468-D01-2018 Margie 1034S Substation May 28, 2018 Alberta Utilities Commission Decision 23468-D01-2018 Margie 1034S Substation Proceeding 23468 Application 23468-A001 May 28, 2018 Published

More information

BIOMASS POWER PLANT NEAR MKUZE, KWAZULU-NATAL

BIOMASS POWER PLANT NEAR MKUZE, KWAZULU-NATAL BIOMASS POWER PLANT NEAR MKUZE, KWAZULU-NATAL DEA ref: 14/12/16/3/3/1/619 MOTIVATION FOR AMENDMENT OF ENVIRONMENTAL AUTHORISATION March 2014 Prepared for: Navosync (Pty) Ltd Suite 103 Dixon Street, Cape

More information

Stakeholder Communication. Inputs, Assumptions, and Preliminary Assessment. Base Model. Needs, Solutions, Sensitivity: Yr 5

Stakeholder Communication. Inputs, Assumptions, and Preliminary Assessment. Base Model. Needs, Solutions, Sensitivity: Yr 5 Methodology and Assumptions 1.1 Overview These sections describe the process we used to perform a network assessment of the ATC transmission system. The description includes study assumptions, methods

More information

PRECAUTIONARY LIMITS OF EXPOSURE TO ELECTROMAGNETIC FIELDS: CAN THEY BE PRACTICALLY ENFORCED? P. Vecchia

PRECAUTIONARY LIMITS OF EXPOSURE TO ELECTROMAGNETIC FIELDS: CAN THEY BE PRACTICALLY ENFORCED? P. Vecchia PRECAUTIONARY LIMITS OF EXPOSURE TO ELECTROMAGNETIC FIELDS: CAN THEY BE PRACTICALLY ENFORCED? P. Vecchia Physics Laboratory, National Institute of Health Viale Regina Elena, 299 00161 Rome, Italy INTRODUCTION

More information

The Future of Power? Power is the Future!

The Future of Power? Power is the Future! The Future of Power? Power is the Future! University of Minnesota Electric Energy Systems Group Seminar 21 Yakout Mansour President & CEO California ISO September 18, 2009 Who is the California ISO? Began

More information

Grid Interconnection Issues for Wind Generation

Grid Interconnection Issues for Wind Generation Grid Interconnection Issues for Wind Generation NRECA APPA - DOE Teleconference December 8, 2005 By Thomas A. Wind, PE Wind Utility Consulting Jefferson, Iowa Topics I Will Cover What are the key technical

More information

electricity future REPORT TO COMMUNITIES

electricity future REPORT TO COMMUNITIES renewing our electricity future REPORT TO COMMUNITIES ReNEWing OUR RESPONSIBILITY As I listen to customers across Alberta, your expectations of our province s electricity system are clear. You want to

More information

2018 Oakland Clean Energy Initiative Request for Offers Q&A

2018 Oakland Clean Energy Initiative Request for Offers Q&A PG&E may modify the information provided below at any time for any reason. No advance notice is necessary for such modifications to take effect. In the case of differences between this information and

More information

Grid-Scale Energy Storage

Grid-Scale Energy Storage Grid-Scale Energy Storage Saurav Mohapatra smohapa2@illinois.edu Department of Electrical and Computer Engineering University of Illinois at Urbana-Champaign NPRE 498: Energy Storage Systems 30 November

More information

Inveraray to Crossaig Overhead Line Reinforcement

Inveraray to Crossaig Overhead Line Reinforcement About Scottish Hydro Electric (SHE) Transmission plc Scottish and Southern Energy Power Distribution is part of the SSE plc group of companies. We own, maintain and invest in the electricity networks in

More information

QGIS Calculation Method for Evaluation of ELF Electromagnetic Field Exposure of General Public due to Overhead Power Lines

QGIS Calculation Method for Evaluation of ELF Electromagnetic Field Exposure of General Public due to Overhead Power Lines QGIS Calculation Method for Evaluation of ELF Electromagnetic Field Exposure of General Public due to Overhead Power Lines Wout Joseph 1*, Kris Vanhecke 1, C. Geuzaine 2, Leen Verloock 1, Matthias Van

More information

South Fork RFP LIPA Board of Trustees REV Committee Briefing. September 21, 2016

South Fork RFP LIPA Board of Trustees REV Committee Briefing. September 21, 2016 South Fork RFP LIPA Board of Trustees REV Committee Briefing September 21, 2016 Latest Developments A portfolio of projects is recommended to meet the needs of the South Fork, which includes the South

More information

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments

Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments Rule 007 Applications for Power Plants, Substations, Transmission Lines, Industrial System Designations and Hydro Developments This rule as amended was approved by the Alberta Utilities Commission on December

More information

Large-scale Integration of Distributed Energy Resources within Electric Power Systems. Danish Cell Controller Project Brief

Large-scale Integration of Distributed Energy Resources within Electric Power Systems. Danish Cell Controller Project Brief Large-scale Integration of Distributed Energy Resources within Electric Power Systems Danish Cell Controller Project Brief Project Introduction Energinet.dk Owns/Operates High Voltage Electric Power System

More information

Windpower: Can MISO Get Too Much of a Good Thing? VITO Perspective Karl Kohlrus P.E. City Water, Light & Power (CWLP) Springfield, IL 4 th Annual

Windpower: Can MISO Get Too Much of a Good Thing? VITO Perspective Karl Kohlrus P.E. City Water, Light & Power (CWLP) Springfield, IL 4 th Annual Windpower: Can MISO Get Too Much of a Good Thing? VITO Perspective Karl Kohlrus P.E. City Water, Light & Power (CWLP) Springfield, IL 4 th Annual MISO Stakeholders Meeting Renewable Resources Integration

More information

EMF Health Assessment and Radio-Frequency Safety - Program 60

EMF Health Assessment and Radio-Frequency Safety - Program 60 EMF Health Assessment and Radio-Frequency Safety - Program 60 Program Description Program Overview The safe and reliable operation of the power delivery system will take on heightened importance as the

More information

Exposure Assessment of Electromagnetic Fields in Malaysian Public Schools Environment

Exposure Assessment of Electromagnetic Fields in Malaysian Public Schools Environment Electromagnetic ields and Our Health Exposure Assessment of Electromagnetic ields in Malaysian Public Schools Environment A.S. arag, T. Juhana Hashim, H. Hussain, I. Said, N. Abdul Rahman University Tenaga

More information

Primary access to the site is proposed from two locations along the B3420 Andover Road, and a secondary access from Well House Lane.

Primary access to the site is proposed from two locations along the B3420 Andover Road, and a secondary access from Well House Lane. 17. SERVICES 17.1 Introduction 17.1.1 WSP Development Limited has been appointed by CALA Homes to investigate and appraise the availability of services to serve a proposed mix-use development of approximately

More information

Electromagnetic Interference

Electromagnetic Interference 4.6 4.6.1 Introduction This section describes the affected environment and environmental consequences related to electromagnetic fields (EMF) and electromagnetic interference (EMI) from operations of the

More information

Corporate Standard Electric and Magnetic Fields (EMF) HB#

Corporate Standard Electric and Magnetic Fields (EMF) HB# Contents Contents... 1 Functional Flowchart... 1 Objective... 1 Scope... 1 Definitions... 2 Responsibilities... 2 OH&S Systems Manager... 2 Station / Site Manager... 2 Workers... 2 Hazards... 2 Identification

More information

NPCC 2018 MARITIMES AREA INTERIM REVIEW OF RESOURCE ADEQUACY. Approved by RCC December 4, 2018

NPCC 2018 MARITIMES AREA INTERIM REVIEW OF RESOURCE ADEQUACY. Approved by RCC December 4, 2018 NPCC 2018 MARITIMES AREA INTERIM REVIEW OF RESOURCE ADEQUACY Approved by RCC December 4, 2018 NEW BRUNSWICK POWER CORP. NOVA SCOTIA POWER INC. MARITIME ELECTRIC COMPANY, LIMITED NORTHERN MAINE ISA, INC.

More information

2 3 4 Distance from centre of reactor (m)

2 3 4 Distance from centre of reactor (m) ONE OPTIMISED NETWORK EQUIPMENT 12 January 2016 c 0MPRMF-4 Magnetic fields and air core reactors 1 Introduction Air core reactors are commonly used as shunt reactors, fault current limiting reactors, tuning

More information

Klixbüll-Endrup Interconnection

Klixbüll-Endrup Interconnection Klixbüll-Endrup Interconnection The essential power connection between Germany and Denmark Information Leaflet for Public Participation under the TEN-E regulation Manual of procedures for TEN-E projects

More information

Carbon Pricing Plan. Prince Edward Island submission to Environment and Climate Change Canada on Carbon Pricing

Carbon Pricing Plan. Prince Edward Island submission to Environment and Climate Change Canada on Carbon Pricing Carbon Pricing Plan Prince Edward Island submission to Environment and Climate Change Canada on Carbon Pricing September 2018 A large part of our efforts will be to engage Islanders directly in reducing

More information

Lower Churchill Project

Lower Churchill Project Lower Churchill Project Prepared by: Nalcor Energy Muskrat Falls: building for the future in Newfoundland and Labrador The lower Churchill River is one of the most attractive undeveloped hydroelectric

More information

4 Responding to Climate Change Guiding Question: How can we respond to climate change?

4 Responding to Climate Change Guiding Question: How can we respond to climate change? LESSON 4 Responding to Climate Change Guiding Question: How can we respond to climate change? List ways to reduce greenhouse gases related to the use and generation of electricity. Describe some of the

More information

Final Project: Putting Building Biology Principles in Practice

Final Project: Putting Building Biology Principles in Practice IBE 321 v1.4 Final Project: Putting Building Biology Principles in Practice This final project is the home stretch for your certification as a Building Biology Electromagnetic Radiation Specialist. You

More information

Comprehensive Study Scoping Document. for Lower Mattagami Hydroelectric Complex Redevelopment CEAR Reference Number:

Comprehensive Study Scoping Document. for Lower Mattagami Hydroelectric Complex Redevelopment CEAR Reference Number: Comprehensive Study Scoping Document for Lower Mattagami Hydroelectric Complex Redevelopment CEAR Reference Number: 07-03-26302 Prepared pursuant to Subsection 21(1) of the Canadian Environmental Assessment

More information

Project siting. Lanfine. Wind resource assessment. Wind Power Project

Project siting. Lanfine. Wind resource assessment. Wind Power Project Project siting Wind resource assessment This assessment determines how much electrical energy can be extracted from the wind Meteorological towers are installed on site to measure wind speed and direction

More information

Interconnection System Feasibility Study

Interconnection System Feasibility Study Interconnection System Feasibility Study Zonnebeke Wind Project Report No: T&S Planning 2015-053 November 2015 FINAL British Columbia Hydro and Power Authority British Columbia Hydro and Power Authority

More information

EDP Renewables North America

EDP Renewables North America Response to New York Energy Highway RFI May 30, 2012 EDP Renewables North America Additional shunt stations and substations from Marcy to New Scotland Respondent Information EDP Renewables North America

More information

TA10 Non Ionizing Radiations EVALUATION OF EMF EXPOSURE FROM MEDICAL ELECTRICAL EQUIPMENT. Halina Aniołczyk, Paweł Mamrot, Piotr Politański

TA10 Non Ionizing Radiations EVALUATION OF EMF EXPOSURE FROM MEDICAL ELECTRICAL EQUIPMENT. Halina Aniołczyk, Paweł Mamrot, Piotr Politański TA10 Non Ionizing Radiations EVALUATION OF EMF EXPOSURE FROM MEDICAL ELECTRICAL EQUIPMENT Halina Aniołczyk, Paweł Mamrot, Piotr Politański Nofer Institute of Occupational Medicine, Lodz, Poland Abstract

More information

BOLAND ENVIRONMENTAL CONSULTANTS CC

BOLAND ENVIRONMENTAL CONSULTANTS CC BOLAND ENVIRONMENTAL CONSULTANTS CC y ENVIRONMENTAL IMPACT ASSESSMENT PROCESS Proposed Photo-Voltaic Solar Power Plant On Farm Nuwerus, No. 450 Portion 6, Worcester DEA REF. NO: 12/12/20/2019 BACKGROUND

More information

22.1 ISSUES OBJECTIVES POLICIES RULES PERFORMANCE STANDARDS 10

22.1 ISSUES OBJECTIVES POLICIES RULES PERFORMANCE STANDARDS 10 22 NETWORK UTILITIES 22.1 ISSUES 3 22.2 OBJECTIVES 4 22.3 POLICIES 4 22.4 RULES 6 22.5 PERFORMANCE STANDARDS 10 Whanganui District Plan (15 January 2018) Chapter 22 Network Utilities 22-1 22 NETWORK UTILITIES

More information

Welcome to our Information Centre

Welcome to our Information Centre Welcome to our Information Centre Overbrook to Riverview Transmission Line Upgrade September 21 and 22, 2016 Purpose of the Information Centre Meet our project team and learn more about: The proposed project

More information

Additional Information on Project Components

Additional Information on Project Components Additional Information on Project Components A. Part A: Ashuganj 450 MW Combine Cycle Power Plant 1. Description 1. The proposed project involves retirement of the existing combined cycle power plant (CCPP)

More information

Forthcoming smart DC nano-grid for green buildings A reflective vision

Forthcoming smart DC nano-grid for green buildings A reflective vision International Journal of Smart Grid and Clean Energy Forthcoming smart DC nano-grid for green buildings A reflective vision M. H. Shwehdi, M. A. Al Aqil * a College of Engineering, King Faisal University,

More information

SUMMARY OF TRANSMISSION BUSINESS

SUMMARY OF TRANSMISSION BUSINESS Filed: September, 0 EB-0-00 Schedule Page of SUMMARY OF TRANSMISSION BUSINESS.0 INTRODUCTION 0 Hydro One Networks Inc. is licensed by the Ontario Energy Board (the OEB or the Board ) to own, operate and

More information

Karen, Best regards, *National Environmental Policy Act

Karen, Best regards, *National Environmental Policy Act From: Pell, Jerry To: 'karen_goebel@fws.gov' Cc: 'Tim Murphy' ; 'Richard Williams' ; Como, Anthony ;

More information

SMUD S COMMENTS ON THE DRAFT 2030 PUBLIC FACILITIES ELEMENT SACRAMENTO COUNTY GENERAL PLAN PUBLIC FACILITIES ELEMENT SECTION VIII ENERGY FACILITIES

SMUD S COMMENTS ON THE DRAFT 2030 PUBLIC FACILITIES ELEMENT SACRAMENTO COUNTY GENERAL PLAN PUBLIC FACILITIES ELEMENT SECTION VIII ENERGY FACILITIES SMUD S COMMENTS ON THE DRAFT 2030 PUBLIC FACILITIES ELEMENT SACRAMENTO COUNTY GENERAL PLAN PUBLIC FACILITIES ELEMENT SECTION VIII ENERGY FACILITIES GOAL: Appropriately sited energy facilities that efficiently

More information

Network Utilities. Amendment 3: New Chapter. 1 Introduction

Network Utilities. Amendment 3: New Chapter. 1 Introduction Amendment 3: New Chapter NU Network Utilities 1 Introduction 1.1 This chapter outlines the provisions of the District Plan that relate to network utilities within Porirua City. Network utilities provide

More information

Steps in Building a Wind Farm

Steps in Building a Wind Farm Steps in Building a Wind Farm Andre Otto Project Manager South Africa Wind Energy Programme Dept of Energy South Africa Outline Outline SA Energy Overview GHG Emissions Water situation Practical RE potential

More information

1.0 Introduction and background

1.0 Introduction and background .0 Introduction and background. Purpose of the document This (EA Report) for the proposed Poplar Bluff Transmission Project (the Project ) is in support of an application to obtain a license for a Class

More information