Figure 3-1. Potable Water Preliminary Replacement Project
|
|
- Samuel Rich
- 5 years ago
- Views:
Transcription
1 Utility Asset Summary L_ "-"""" for San Juan Capistrano r,/ ~ Figure 3-1. Potable Water Preliminary Replacement Project _, No Repli11:~m~nl Recommended ~._, 1 \ - z - z POTABLE WATER SYSTEM PRELIMINARY REPLACEMENT PROJECTS OVERVIEW FIGURE J-1 March 29,
2 Utility Asset Summary ~-~~ for San Juan Capistrano ',.1 ~ Appendix A contains a map for each potential replacement project based on this break data. These project extents will change after the City conducts a more detailed assessment and incorporates break data collected after The project extents shown are only meant to provide a basis to determine planning level replacement needs. The 15 miles identified constitutes approximately 7% of the system that should be replaced as of Additionally, based on the system characteristics and the performance of similar utilities, it is estimated that an additional 0.25% to 0.5% of the system will need to be replaced annually. Assuming the 10 year renewal period ends in 2025, this yields an additional 4% - 8% of the system requiring renewal from the baseline year when data was available (2012). Therefore, we forecast that approximately 11% to 15% of the distribution system, as well as the associated services, meters and appurtenances should be replaced by With respect to reservoirs and pump stations, we assumed that infrastructure older than 35 years would need to be replaced or renewed over the next 10 years. Improvements for the GWRP are not included in these forecasted projections. Based on these assumptions the forecasted capital cost for the water system ranges between $33,000,000 and $56,000,000. Table 3-2 summarizes the range of estimated costs for the linear and vertical potable water assets. Table 3-2. Potable Water 10-Year CIP Forecast POTABLE WATER CIP FORECAST (LOW RANGE) CIP FORECAST (HIGH RANGE) Linear Assets Reservoirs Pump Stations Total $28,000,000 $4,000,000 $1,000,000 $33,000,000 $39,000,000 $9,000,000 $8,000,000 $56,000, Recycled Water System Limited data is available regarding the condition of the recycled water system. The recycled water system is relatively new, has experienced low levels of breaks, and generally has a lower consequence of failure than the Potable Water System. Therefore, the renewal needs of the recycled water system are considered negligible. This 10 year investment forecast assumes 1% of the infrastructure will need to be replaced over the next 10 years, approximately $1,000,000. A high and low range is not provided since they are relatively the same estimate. Table 3-3 summarizes the range of estimated costs for the linear and vertical recycled water assets. Table 3-3.Recycled Water 10-Year CIP Forecast RECYCLED WATER CIP FORECAST Linear Assets $200,000 Water Storage Facility- Reservoir $800,000 Total $1,000,000 March 29,
3 Utility Asset Summary 1-)"" for San Juan Capistrano ~ 3.4 Wastewater System In the City's 2004 Sanitary Sewer System Master Plan, the City inspected 58,000 linear feet of gravity sewer pipe and 140 manholes. Approximately 9,800 linear feet (about 17% of pipes inspected) were identified for renewal. Twenty three manholes (about16% of all manholes inspected) were identified for minor renewal work ranging from installing new rungs, raising manholes, and applying epoxy coatings. We evaluated the decision making criteria used by City staff to develop capital projects; we determined that the City is relatively risk adverse and focuses on extending the useful life of pipes using trenchless technologies before the pipe deteriorates to a state where more costly renewal techniques (i.e. excavation) is required. Based on the City's Sanitary Sewer Management Plan, updated in August 2014, the entire system has been inspected and is re-inspected and re-evaluated for structural deficiencies once every four years. Now that the City has applied this approach to its entire system, it is assumed that acute structural defects will rarely be discovered. The 1 0-year wastewater capital forecast will provide a range of investment levels depending upon various risk management and infrastructure condition assumptions. The high end of the range assumes that the risk tolerance and current condition of the system is similar to that found in the 2004 Sanitary Sewer System Master Plan. It also assumes that minor levels of deterioration that typically occur in collection systems is counter balanced by the City's four year inspection and renewal program and the renewal that has already been conducted as part of the 2004 Sanitary Sewer System Master Plan. Therefore, about 17% of all pipes will require renewal and about 16% of all manholes will require minor renewal over the 10 year investment forecast. In general, the 2004 Sanitary Sewer System Master Plan decision criteria is relatively risk adverse when compared to the rest of the industry. Additionally, the areas that were inspected were believed to be areas of the system in the worst condition based on age, material, and infiltration rates. Therefore, the low end of the 10 year investment forecast assumes that yield rates will be approximately 5% lower based on increased risk tolerances and the remaining portion of the system being in better condition. Therefore, we forecast that about 12% of all pipes will require renewal and about 11% of all manholes will require minor renewal over a 10 year investment. Based on these assumptions the forecasted capital cost for the wastewater system ranges between $9,000,000 and $14,000,000. Table 3-4 summarizes the range of estimated costs for the linear and vertical wastewater assets. Table 3-4. Wastewater 10-Year CIP Forecast WASTEWATER CIP FORECAST CIP FORECAST (LOW RANGE) (HIGH RANGE) Linear Assets Pump Station Total $9,000,000 $9,000,000 $12,500,000 $1,500,000 $14,000,000 March 29, 2016 I 23
4 Utility Asset Summary 1-'~ for San Juan Capistrano J ~ 3.5 Gravity Stormwater System Limited data is available regarding the condition of the stormwater system. In general, stormwater pipes are exposed to similar deterioration mechanisms as gravity sewer pipe and in the City's wastewater system, are of similar age. In general, the City's stormwater pipes have a lower consequence of failure but far less condition assessment and renewal has historically been conducted relative to the sewer system. For the purposes of this 10 year investment forecast, it is assumed that the renewal rate in the stormwater system will be similar to that of the wastewater system. Forecasting a range of 12% renewal to 17% renewal for the stormwater system, the CIP forecasted cost will range between $11,000,000 and $16,000, Summary of Forecasted Capital Improvements Based on our review of the asset registry and available condition data, we developed forecasted costs of improvements that a utility operator may consider in developing a valuation of each utility. We present a range of costs because these values represent possible capital improvements which must be reviewed and evaluated prior to commencing any project. Table 3-5. Preliminary 1 0-year Projected Capital Improvement Project Summary UTILITY Potable Water Recycles Wa.ter Wastewater ll\liw.atew Total CIP FORECAST (LOW RANGE) $33,000,000 $1,0130,000 $9,000,000 $11, $54,000,000 CIP FORECAST (HIGH RANGE) $56,00.0,000 $'1l,tm0,000. $14,000,000 $1p,001il,OOO $87,000,000 March 29,
5 Utility Asset Summary L)~ for San Juan Capistrano ~ ~ 4 References The following references were used in the development of this Utility Summary: California Regional Water Quality Control Board, San Diego Region, Letter dated July 31, 2013, subject San Diego Water Board Comments on Revised South Orange County Hydromodification Management Plan (HMP) dated October 25, 2012 required by MS4 Permit Order No. R , NPDES No. CAS City of San Juan Capistrano, California Comprehensive Annual Financial Report for the Fiscal Year Ended June 30, City of San Juan Capistrano, Cost-Est_AWT-Pipe-Pump_Resv_Exp Microsoft Excel file. City of San Juan Capistrano, Microsoft Excel Files: lnframap _DBO_sForce_Mains, lnframap _DBO_sline, lnframap_dbo_dwwatermain, lnframap _DBO_rwMain, Infra MAP _DBO _sdlines. City of San Juan Capistrano, Non-Domestic I Recycled Water Master Plan Update, March 2008, AKM Consulting Engineers. City of San Juan Capistrano, Utility Asset Database, ESRI geographic information system {GIS) files. City of San Juan Capistrano, Water Master Plan Update. March 2004, AKM Consulting Engineers. City of San Juan Capistrano 2010 Urban Water Management Plan, March 2012, Malcom Pirnie, Inc. Ed Almanza & Associates San Juan Creek Road Recycled Water Pipeline Capital Improvement Project (CIP) 13603, Public Review Draft Initial Study, August. G3Soi1Works, Wildermuth Environmental, Black & Veatch San Juan Basin Authority Groundwater and Desalination Optimization Program Foundational Actions Fund Final Report, March. Tetra Tech, Inc Final Report Sanitary Sewer System Master Plan and Rehabilitation Program, January 21. March 29,
6 Utility Asset Summary 1-)~ for San Juan Capistrano ~ This page intentionally left blank March 29,
7 Utility Asset Summary for San Juan Capistrano 1-)~ APPENDIX A Preliminary Potable Water CIP Maps March 29, 2016
8 Utility Asset Summary l...:)~ for San Juan Capistrano ~ ~ This page intentionally left blank. March 29, 2016
9 N A Miles PRELIMINARY REPLACEMENT LIMITS- PROJECT 1 FIGURE A-1 CITY OF SAN JUAN CAPISTRANO
10 Miles PRELIMINARY REPLACEMENT LIMITS- PROJECT 2 FIGURE A-2 CITY OF SAN JUAN CAPISTRANO
11 Miles PRELIMINARY REPLACEMENT LIMITS- PROJECT 3 FIGURE A-3 CITY OF SAN JUAN CAPISTRANO
12 N A Miles PRELIMINARY REPLACEMENT LIMITS- PROJECT 4 FIGURE A-4 CITY OF SAN JUAN CAPISTRANO
13 N A PRELIMINARY REPLACEMENT LIMITS- PROJECT Miles FIGURE A-5 CITY OF SAN JUAN CAPISTRANO
14 Cast Iron Cast Iron N A Miles PRELIMINARY REPLACEMENT LIMITS - PROJECT 6 FIGURE A-6 OF SAN JUAN CAPISTRANO
15 N A Miles PRELIMINARY REPLACEMENT LIMITS- PROJECT 7 FIGURE A-7 CITY OF SAN JUAN CAPISTRANO
16 8 Asbestos Cement 4 Ductile Iron N A Miles POTABLE "' WATER SYSTEM PRELIMINARY REPLACEMENT LIMITS - PROJECT 8 FIGURE A-8
17 Asbestos Cement ~ 6 Cast Iron Miles PRELIMINARY REPLACEMENT LIMITS- PROJECT 9 CITY OF SAN JUAN FIGURE A-9
18 N A PRELIMINARY REPLACEMENT LIMITS- PROJECT Miles FIGURE A-10 CllY OF SAN JUAN CAPISTRANO
19 _...::...:_ 10 Asbestos Cement 12 Asbestos Cement Unknown Unknown N A 0 O,Q Mlle.s PRELIMINARY REPLACEMENT LIMITS- PROJECT 11 FIGURE A-11 CITY OF SAN JUAN CAPISTRANO
20 Ductile Iron Ductile Iron Unknown N A Miles PRELIMINARY REPLACEMENT LIMITS- PROJECT 12
21 Ductile Iron 8 Ductile Iron --~ 12 Ductile Iron ---~--- N A PRELIMINARY REPLACEMENT LIMITS- PROJECT Miles FIGURE A-13 CITY OF SAN JUAN CAPISTRANO
Section 8 System Evaluation and Capacity Assurance Plan (SECAP)
System Evaluation and Capacity Assurance Plan (SECAP) The WDR requires owners and operators of sewer collection systems to have a (SECAP). This component involves preparing and implementing a Capital Improvement
More informationVALLECITOS WATER DISTRICT
VALLECITOS WATER DISTRICT WATER, WASTEWATER, AND RECYCLED WATER MASTER PLAN Draft Program Environmental Impact Report SCH No. 2010071073 VALLECITOS WATER DISTRICT 2008 Water, Wastewater and Recycled Water
More informationIMPLEMENTING AN ADAPTIVE CAPITAL IMPROVEMENT PLAN
IMPLEMENTING AN ADAPTIVE CAPITAL IMPROVEMENT PLAN MATTHEW WHITMAN IT TECH SUPPORT ANALYST CITY/COUNTY UTILITIES, WINSTON-SALEM NC BRIAN LENDT GISP B&V SR, GIS SPECIALIST ESRI INTERNATIONAL USER CONFERENCE
More informationMichigan Department of Environmental Quality (MDEQ) Revolving Loan Section, Attn: Jonathan Berman
MEMORANDUM To: Michigan Department of Environmental Quality (MDEQ) Revolving Loan Section, Attn: Jonathan Berman From: OHM Advisors CC: City of Novi Oakland County Water Resources Commissioner Date: November
More informationNotice of Public Hearing. Notice of Public Hearing
2015 URBAN WATER MANAGEMENT PLAN Table 8-2: Notification to Cities and Counties Retail: Notification to Cities and Counties City Name 60 Day Notice Notice of Public Hearing Dana Point Mission Viejo County
More informationTexas Commission on Environmental Quality Sanitary Sewer Overflow Initiative Plan
Texas Commission on Environmental Quality Sanitary Sewer Overflow Initiative Plan For the City of University Park Customer Number CN600292122 Regulated Entity Number RN101451243 3800 University Boulevard
More informationTown of New Castle, New Hampshire Sewer Infrastructure Evaluation
Town of New Castle, New Hampshire Sewer Infrastructure Evaluation March 2016 EXECUTIVE SUMMARY The Town of New Castle (Town) is working collaboratively with the City of Portsmouth (City) to consider options
More informationRequest for Proposals
Request for Proposals The Marina Coast Water District wishes to contract for an individual or firm to prepare Master Plans and Capacity Fees for Sewer, Water and Recycled Water Proposals due 4:00 PM October
More informationGood to Great: A More Dynamic and Robust Linear Asset Management Program. Presented By: Jonathan Okafor, P.E. Fairfax County Paul Longo Dewberry
Good to Great: A More Dynamic and Robust Linear Asset Management Program Presented By: Jonathan Okafor, P.E. Fairfax County Paul Longo Dewberry Outline What is Asset Management? Fairfax County Overview
More informationInfiltration and Inflow. Michael Sassaman Phone
Infiltration and Inflow Michael Sassaman msassaman@entecheng.com Phone 610-373-3345 Inflow and Infiltration PA DEP Learning Objectives Do you have Excessive I/I? Sources of Inflow and Infiltration I/I
More informationVALLECITOS WATER DISTRICT WATER, WASTEWATER, AND RECYCLED WATER MASTER PLAN. November 2010
VALLECITOS WATER DISTRICT WATER, WASTEWATER, AND RECYCLED WATER MASTER PLAN VALLECITOS WATER DISTRICT WATER, WASTEWATER, AND RECYCLED WATER MASTER PLAN Prepared For: Vallecitos Water District 201 Vallecitos
More informationCHAPTER 8 CAPITAL IMPROVEMENT PLAN
INTRODUCTION CHAPTER 8 CAPITAL IMPROVEMENT PLAN This chapter presents 6-, 10-, and 20-year Capital Improvement Plans (CIPs) in accordance with the requirements of WAC 26-290. Water system capital improvements
More informationCHAPTER 6 COLLECTION SYSTEM HYDRAULIC MODEL
CHAPTER 6 COLLECTION SYSTEM HYDRAULIC MODEL INTRODUCTION The District developed a hydraulic model of the sanitary sewer system as part the 2000 Wastewater Comprehensive Plan. The output from this model
More informationThe City of Tacoma s GIS-Centric Wastewater Asset Performance Modeling Approach
The City of Tacoma s GIS-Centric Wastewater Asset Performance Modeling Approach Tacoma s Sanitary Sewer Upfront Information Tacoma is located within Puget Sound on Commencement Bay Over 90,000 Customers
More informationCHAPTER 12: SANITARY SEWER SYSTEM
CHAPTER 12: SANITARY SEWER SYSTEM Chapter 12 includes the following information: 1. System Overview 2. On Site Sewage Treatment 3. Inter Community Services 4. Future Demand Forecast 5. Infiltration and
More informationCHAPTER 12: SANITARY SEWER SYSTEM
CHAPTER 12: SANITARY SEWER SYSTEM Chapter 12 includes the following information: 1. System Overview 2. On-Site Sewage Treatment 3. Inter-Community Services 4. Future Demand Forecast 5. Infiltration and
More informationAGENDA ITEM C8. COST/FUNDING SOURCE: $215,348.48/Uniform Rate (Total project costs $520, includes $304,952 previously committed to Phase II)
AGENDA ITEM C8 DATE: February 6, 2017 TO: Matt Jordan, General Manager FROM: Charles H. Carden, Chief Operating Officer SUBJECT: South Pasco Transmission Main Phase III Condition Assessment Services with
More informationWASTEWATER ASSET MANAGEMENT PLAN
Must be kept on file and available upon request until 2032 (per 2014 MDEQ/SAW grant requirements) WASTEWATER ASSET MANAGEMENT PLAN CITY OF NORTON SHORES, MI May 2017 Where we re going: System Goals INTRODUCTION
More informationsewers ANd storm drains Storm Drain Under Construction, 1916
sewers ANd storm drains Storm Drain Under Construction, 1916 A d o p t e d C A p I t A L I M p R o V e M e N t p R o G R A M F I s C A L Y e A R 2 1 9 FY 219-223 Capital Improvement Program FY 218 FY 219
More informationCalendar Year capital improvement. Program
Calendar Year 2010 capital improvement Program Important Notice: The information found in this file concerning the 2010 Capital Improvements Program, has been extracted from the San Antonio Water System
More informationA. Introduction 7 1. Purpose 7 2. Authority 7 3. Contact 8 4. Plan Submittal Process 8 B. Design Standards General 11 a. Future Extensions 11
A. Introduction 7 1. Purpose 7 2. Authority 7 3. Contact 8 4. Plan Submittal Process 8 B. Design Standards 11 1. General 11 a. Future Extensions 11 b. Design Calculations 11 c. Easements and Property 12
More informationTABLE OF CONTENTS 4.17 UTILITIES AND SERVICE SYSTEMS...
TABLE OF CONTENTS 4.17 UTILITIES AND SERVICE SYSTEMS... 4.17-1 4.17.0 Introduction... 4.17-1 4.17.1 Methodology... 4.17-2 4.17.2 Existing Conditions... 4.17-2 4.17.3 Impacts... 4.17-4 4.17.4 Applicant-Proposed
More informationData-driven Analysis of Pipeline System Performance and Service Life Estimates
Making a Critical Investment: Data-driven Analysis of Pipeline System Performance and Service Life Estimates PNWS AWWA Conference May 10, 2013 Presentation Outline Purpose of Study EWEB capital planning
More informationMay 15, 2017 Joseph C. Schiebel Director of Public Utilities Caroline County 12613 Mill Creek Road Ruther Glen, VA 22546 P.O. Box 424 Bowling Green, Virginia 22427 RE: Proposal for Professional Engineering
More informationUSDA RURAL UTILITIES SERVICE, WATER AND ENVIRONMENTAL PROGRAMS PROJECT EXAMPLES FOR RURAL WATER AND WASTE PROJECTS
Obligation Strategy This strategy was developed to summarize types of projects that can be expeditiously reviewed and, therefore, more efficiently obligated with respect to engineering and environmental
More informationLong Beach Water Department Fiscal Year 2018 Annual Budget Summary
Long Beach Water Department Fiscal Year 2018 Annual Summary I. Overview For over 100 years, the Long Beach Water Department has provided Long Beach residents and businesses with a reliable, cost-effective
More informationSouth Watershed Management Area Executive Committee
South Watershed Management Area Executive Committee May 12, 2016 Item 1: Self Introductions Item 2: Public Comments, Non-Agenda Topics Item 3: Approval of Minutes for February 2, 2016 Recommended Action:
More informationCity of Lawrence, Kansas
Table of Contents 1 EXECUTIVE SUMMARY... 1-1 1.1 General Overview... 1-1 1.2 Phase 1 Field Investigation Findings... 1-3 1.2.1 Public Sector Inflow/Infiltration Sources... 1-3 1.2.2 Private Sector Inflow/Infiltration
More informationClean Water 2020 Program
Clean Water 2020 Program INFRASTRUCTURE REHABILITATION PROGRAM (IR Program) November 2016 Updated March 2017 Table of Contents Infrastructure Rehabilitation Program 2016 List of Tables... 2 List of Figures...
More informationFINAL ASSET MANAGEMENT PROGRAM March 2016
FINAL ASSET MANAGEMENT PROGRAM March 2016 Orange Water and Sewer Authority Carrboro, North Carolina A public, non-profit agency providing water, sewer and reclaimed water services to the Carrboro-Chapel
More informationVolume 1 Executive Summary
2013 Cheyenne Water and Wastewater Master Plans Final November 27, 2013 Prepared for: City of Cheyenne Board of Public Utilities 2416 Snyder Ave. Cheyenne, WY 82001 Prepared by: HDR Engineering AMEC Earth
More informationFOCUSED MUNICIPAL SERVICE REVIEW
10/10/2018 FOCUSED MUNICIPAL SERVICE REVIEW City of San Juan Capistrano Water and Wastewater Utilities ORANGE COUNTY LOCAL AGENCY FORMATION COMMISSION ATTACHMENT 1 - Page 1 of 230 TABLE OF CONTENTS I.
More informationMBARI Sanitary Sewer Analysis Report
Revised 9-10-08 MBARI Sanitary Sewer Analysis Report Executive Summary: This Sanitary Sewer Analysis Report has been prepared for the Monterey Bay Aquarium Research Institute (MBARI) located on Moss Landing
More informationSSO- WDR Compliance Workshop Electronic Reporting: Reporting Requirements & Tips. Sewer System Management Plan Chapter
Chapter Contents Introduction SSMP Requirements and Suggested Content SSMP Preparation Deadlines Introduction This chapter provides a brief overview of the GWDR requirements for an SSMP and provides some
More informationBrisbane Water s. Sewer Trunk Trunk Main Rehabilitation Program A Practical Overview
Brisbane Water s Sewer Trunk Trunk Main Rehabilitation Program A Practical Overview Overview of Presentation Trunk Sewer System Overview; Maintenance Planning - Condition Monitoring : Fail Modes; Risk
More informationINFRASTRUCTURE CANADA PHASE 1 PROJECT REQUESTS CLEAN WATER AND WASTEWATER FUND RECOMMENDATION
TO: FROM: SUBJECT: CHAIR AND MEMBERS CIVIC WORKS COMMITTEE MEETING ON OCTOBER 4, 2016 JOHN BRAAM, P. ENG. MANAGING DIRECTOR, ENVIRONMENTAL & ENGINEERING SERVICES AND CITY ENGINEER INFRASTRUCTURE CANADA
More informationWastewater Collection System Infrastructure Condition Update
Wastewater Collection System Infrastructure Condition Update Planning Committee May 12, 2015 Agenda Background Condition Assessment Findings Gravity Interceptors Force Mains Pump Stations Phased Capital
More informationINFLOW & INFILTRATION CORRECTION VIA LATERAL LINE DITCH LEAK REPAIRS
1 of 5 8/1/2013 2:10 PM INFLOW & INFILTRATION CORRECTION VIA LATERAL LINE DITCH LEAK REPAIRS Project Location and Description Glen Mayberry, Project Manager Roy F. Weston, Houston, TX The project is in
More informationMassachusetts Water Resources Authority Update on 2018 Water and Wastewater Master Plan
Massachusetts Water Resources Authority Update on 2018 Water and Wastewater Master Plan February 12, 2019 Background 33 Years of MWRA Capital Investment FY86 18 $8.3 Billion Capital Spending 70% on Wastewater
More informationOC LAFCO RFPs on San Juan Capistrano Utility System Municipal Services Review Pre-proposal Conference Questions and Answers
OC LAFCO RFPs on San Juan Capistrano Utility System Municipal Services Review Pre-proposal Conference Questions and Answers On August 24, 2017, the Orange County Local Agency Formation Commission (LAFCO)
More informationSection 3 - Land Use, Population, and Water Demands. Section 3
Section 3 - Land Use, Population, and Water Demands Section 3 SECTION 3 DEMANDS LAND USE, POPULATION, AND WATER This section describes the existing water demands, the population projections, and the projected
More informationCITY OF TOPPENISH General Sewer Plan DRAFT FOR AGENCY REVIEW
CITY OF TOPPENISH General Sewer Plan DRAFT FOR AGENCY REVIEW G&O #15039 JUNE 2017 CITY OF TOPPENISH YAKIMA COUNTY WASHINGTON GENERAL SEWER PLAN G&O#l5039 JUNE 2017 Gray & Oshor.n.e~ l.n.c. CONSUL TING
More informationNewberg Inflow and Infiltration Study WES 2017 PETER OLSEN, PE EMILY FLOCK, EI 1
Newberg Inflow and Infiltration Study WES 2017 PETER OLSEN, PE EMILY FLOCK, EI 1 What is Infiltration and Inflow? Infiltration and inflow (I/I) represent extraneous groundwater and storm water runoff that
More informationSewer Modeling of Near- Term Development Technical Memorandum
Sewer Modeling of Near- Term Development City of Reedley, CA March 8, 2018 Page Intentionally Blank The City of Reedley (City) is anticipating near-term developments to the north of the City s currently
More informationWATER AND WASTEWATER RATE STUDY
WATER AND WASTEWATER RATE STUDY B&V PROJECT NO. 176244.0100 PREPARED FOR Camrosa Water District MARCH 20, 2013 Black & Veatch Holding Company 2011. All rights reserved. Camrosa Water District WATER AND
More informationASSET MANAGEMENT PROGRAM
ASSET MANAGEMENT PROGRAM July 2017 Orange Water and Sewer Authority Carrboro, North Carolina A public, non-profit agency providing water, sewer and reclaimed water services to the Carrboro-Chapel Hill
More informationAPPENDIX I. Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer
APPENDIX I Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer THE CITY OF BARRIE PROJECT NO. 15M-00594-01 CONCEPTUAL DESIGN SALEM ROAD AND MCKAY ROAD TRUNK WATERMAIN AND SANITARY
More informationMemorandum Karen Nickols, Project Manager Michigan Department of Environmental Quality (MDEQ) Revolving Loan Section
Memorandum To: Karen Nickols, Project Manager Michigan Department of Environmental Quality (MDEQ) Revolving Loan Section From: CC: John Michalski, P.E.; Eric Wahrman, E.I.T Oakland County Water Resource
More informationFOCUSED MUNICIPAL SERVICE REVIEW
10/10/2018 FOCUSED MUNICIPAL SERVICE REVIEW City of San Juan Capistrano Water and Wastewater Utilities ORANGE COUNTY LOCAL AGENCY FORMATION COMMISSION TABLE OF CONTENTS I. INTRODUCTION... 1 MSR Background
More information9.0 General Infrastructure Element
9.0 Element The purpose of this element is to ensure adequate provision of public facilities and services required to meet the future needs of the University, including the following: 1. Provision of adequate
More informationFOCUSED MUNICIPAL SERVICE REVIEW
8/29/2018 FOCUSED MUNICIPAL SERVICE REVIEW City of San Juan Capistrano Water and Wastewater Utilities ORANGE COUNTY LOCAL AGENCY FORMATION COMMISSION TABLE OF CONTENTS I. INTRODUCTION... 1 MSR Background
More informationCity of Tacoma Stormwater Management Program Assessment. Attachment B3
City of Tacoma Stormwater Management Program Assessment Attachment B3 Attachment B3. City of Tacoma Stormwater Management Program Assessment The following discussion includes an assessment of the appropriateness
More informationSEWER SYSTEM MANAGEMENT PLAN (SSMP) DEVELOPMENT GUIDE
SEWER SYSTEM MANAGEMENT PLAN (SSMP) DEVELOPMENT GUIDE MISSION SPRINGS WATER DISTRICT Sewer System Management Plan Goals Mission Springs Water District's mission statement is to ''provide, protect, and
More informationCost Estimating Framework
Cost Estimating Framework Water and Wastewater Master Study Prepared by: GM BluePlan Engineering for: Project No. 717022 TABLE OF CONTENTS 1 Introduction... 1 2 Cost Estimation Framework... 2 2.1 Approach
More informationSouth Interceptor 3 rd Street Rehabilitation Phase 2
South Interceptor 3 rd Street Rehabilitation Phase 2 Planning Committee September 11, 2018 Agenda Background Project Scope Rehabilitation Method Schedule Potential Impacts and Mitigation Community Outreach
More informationGIS UTILITY MAPPING. Akhilesh Pal, P.E. Public Works Department, City of Oskaloosa June 19, 2017
GIS UTILITY MAPPING Akhilesh Pal, P.E. Public Works Department, City of Oskaloosa June 19, 2017 GEOGRAPHIC INFORMATION SYSTEM (GIS) Objective: Prepare a comprehensive Geographic Information Systems for
More informationTown of Petrolia PRELIMINARY ASSET MANAGEMENT PLAN. Prepared by: Julie Fortier, ing. Marie-Élaine Desbiens, ing.
PRELIMINARY ASSET MANAGEMENT PLAN Prepared by: Julie Fortier, ing. Marie-Élaine Desbiens, ing. Verified by: Stuart Winchester, P.Eng. 236 Victoria Street North, Suite 301 Kitchener, Ontario N2H 5C8 Canada
More informationSection 9 Monitoring, Measurement, and Program Modifications
Monitoring, Measurement, and Program Modifications One of the critical components of a comprehensive SSMP program is the development and tracking of performance indicators. Performance indicators describe
More informationThe Township of Bonnechere Valley Asset Management Plan for Water and Sewer Infrastructure and Arena/Community Hall
arena is approximately 20,000 ft 2 in area with a 5,000 ft², two-storey community centre (Eagles Nest) addition constructed in the 1980s. Since then, there has been regular maintenance, numerous upgrades
More informationMunicipal Service Review
Willow Creek Community Services District Municipal Service Review May 2008 Prepared by: For the District Sphere of Influence Report TABLE OF CONTENTS Page Local Agency Formation Commission Authority...
More informationImpact Fees: Existing Capacity Valuation
Impact Fees: Existing Capacity Valuation Capital Improvements Advisory Committee Louis Lendman Senior Financial Analyst Existing Infrastructure Value Categories Water Flow (Distribution Lines) Water System
More informationPipeline Condition Assessment. The Essential Engineering Step in the Asset Management Process
Pipeline Condition Assessment. The Essential Engineering Step in the Asset Management Process Tom Sangster. Principal, Jason Consultants Group, Geneva, Switzerland Synopsis Condition assessment is a critical
More informationMarina Coast Water District: A California Special District STATE OF THE DISTRICT
Marina Coast Water District: A California Special District STATE OF THE DISTRICT DIRECTORS Dr. THOMAS P. MOORE President JAN SHRINER Vice President HOWARD GUSTAFSON WILLIAM Y. LEE PETER LE Interim General
More informationAPPENDIX Y. Audit Closeout Memo. Revision History
APPENDIX Y Audit Closeout Memo Revision History Revision Date Approval Reason 0 12/19/11 Original 1 05/19/16 M. Esquer Addressed 2013 Audit Findings 2 06/30/16 M. Esquer Addressed 2015 Audit Findings ORANGE
More informationSection 5 - Inflow and Infiltration Analysis
Section 5 - Inflow and Infiltration Analysis 5.1 Introduction The section presents a comprehensive review of the historical flow metering data collected for the sewer collection system in the Towns of
More informationWastewater Collection System Condition Assessment. Putting it all Together
Wastewater Collection System Condition Assessment Putting it all Together Drivers for CAP CMOM and SSOI Commitment 10-year Program to inspect the entire Collection System Asset Management Approach to Identify
More informationWASHINGTON SUBURBAN SANITARY COMMISSION BUSINESS OPPORTUNITIES ASSOCIATED WITH WSSC S CONSENT DECREE FOR SANITARY SEWER OVERFLOW
WASHINGTON SUBURBAN SANITARY COMMISSION BUSINESS OPPORTUNITIES ASSOCIATED WITH WSSC S CONSENT DECREE FOR SANITARY SEWER OVERFLOW By: Marcia Tucker, MBA Group Leader Infrastructure Systems Group WSSC FACTS
More informationCapital Investment Plan (CIP) Quarterly report for period ending September 2015
Report Group Capital Investment Plan (CIP) Quarterly report for period ending September 2015 Summary This report provides a summary of fiscal year accomplishments, capital expenditures to date, and updates
More informationAGENDA ITEM C2. COST/FUNDING SOURCE: $304,952.00/ Uniform Rate
AGENDA ITEM C2 DATE: April 4, 2016 TO: Matt Jordan, General Manager FROM: Charles H. Carden, Chief Operating Officer SUBJECT: South Pasco Transmission Main Condition Assessment Services with Pure Technologies
More informationBellevue s Approach to Stormwater Management
Bellevue s Approach to Stormwater Management By Don McQuilliams Operations Manager-Regulatory Compliance and Surface Water Bellevue Utilities Department City of Bellevue, Washington Bellevue, Washington
More informationMassachusetts Water Resources Authority. Water and Wastewater System. Briefing to WSCAC and WAC
Massachusetts Water Resources Authority 2013 MWRA Master Plan Water and Wastewater System Briefing to WSCAC and WAC November 19, 2013 Presentation Outline Introduction Water System Wastewater System 2
More informationSUPPLEMENTAL SPECIFICATIONS AND DRAWINGS TO THE IDAHO STANDARDS FOR PUBLIC WORKS CONSTRUCTION TABLE OF CONTENTS
PREFACE AND CITY ENGINEER S LETTER INDEX OF STANDARD DRAWINGS DIVISION 100 GENERAL CONDITIONS ARTICLE 1 DEFINITIONS AND TERMINOLOGY 1.01 Defined Terms ARTICLE 2 PRELIMINARY MATTERS 2.01 Delivery of Bonds
More informationSection 9 Design Criteria Non-Potable Water Facilities
Section 9 Design Criteria Non-Potable Water Facilities 9.1 Background For the purposes of this section, non-potable water means reclaimed wastewater (recycled water), Colorado River water (canal water)
More information2015 Comprehensive Facilities MASTER PLAN SMART INFRASTRUCTURE FOR A SUSTAINABLE FUTURE
2015 Comprehensive Facilities MASTER PLAN SMART INFRASTRUCTURE FOR A SUSTAINABLE FUTURE TABLE OF CONTENTS SECTION I SECTION 2 SECTION 3 SECTION 4 Who We Are Preparing Now for a Sustainable Future Evaluating
More informationMay Preliminary Condition Assessment Report
May 2010 Preliminary Condition Assessment Report PRELIMINARY CONDITION ASSESSMENT REPORT Prepared for Hampton Roads Sanitation District September 2009 Updated May 2010 Table of Contents Hampton Roads Sanitation
More informationSECTION 7 SEPARATION OF WATER MAINS AND SANITARY SEWERS
SECTION 7 SEPARATION OF WATER MAINS AND SANITARY SEWERS To prevent the contamination of the public water supplies from nearby sanitary sewers, the following State Water Resources Control Board Division
More informationCity of Crosby, ND Municipal Infrastructure Needs Assessment September 2012
City of Crosby, ND Municipal Infrastructure Needs Assessment September 2012 Project made possible by US Dept. of HUD Regional Substantiality Planning Grant and ND Energy Development Infrastructure and
More information3.0 DESIGN CRITERIA FOR SANITARY SEWER FACILITIES
3.0 DESIGN CRITERIA FOR SANITARY SEWER FACILITIES All sanitary sewers shall be designed in accordance with these Design Standards, LBWD Rules and Regulations, and to accepted engineering principles. In
More informationMWRD Infiltration and Inflow Control Program Compliance Update. Committee of the Whole Meeting April 3, 2018
MWRD Infiltration and Inflow Control Program Compliance Update Committee of the Whole Meeting April 3, 2018 Presentation Outline Background on MWRD s Watershed Management Ordinance Wastewater, Infiltration
More informationOC Water Reliability Study
OC Water Reliability Study South Orange County (SOC) Update June 2016 Municipal Water District of Orange County 1 Where South Orange County (SOC) Gets Its Water = 90% Import & 10% Local Bay Delta Area
More informationASSET MANAGEMENT PROGRAM
ASSET MANAGEMENT PROGRAM MAKING IT PRACTICAL & USEFUL NORTHERN MICHIGAN OPERATORS SEMINAR Sam Bender Fleis & VandenBrink September 29, 2016 What is asset management and why should I care about it? Asset
More informationCity of San Juan Capistrano Focused MSR Comment Log
City of San Juan Capistrano Focused MSR On July 11, 2018, OC LAFCO held a study session on the Public Review Draft of the Focused Municipal Service Review (MSR) for the City of San Juan Capistrano Water
More information2.3.3 Defining Metrics Refining Survey Questions Arranging Data in a Matrix Reviewing Performance Indicators 18
Table of Contents Chapter 1 Understanding Wastewater Collection System Problems and Needs 1.1 Purpose of a Wastewater Collection System 2 1.2 Problems 2 1.3 O&M Programs 4 1.3.1 Types of Maintenance 5
More informationTri-Cities North Regional. Wastewater Authority Friday, March 22, Tri-Cities North Regional
Tri-Cities North Regional Wastewater Authority Friday, March 22, 2013 Tri-Cities North Regional Wastewater Authority (TCA) 3777 Old Needmore Road Dayton, OH 45424 Tel: 937-236-6558 Veolia Environmental
More informationINFRASTRUCTURE ELEMENT SANITARY SEWER SUB-ELEMENT
INFRASTRUCTURE ELEMENT SANITARY SEWER SUB-ELEMENT GOALS, OBJECTIVES & POLICIES GOAL, OBJECTIVES & POLICIES GOAL SS. SANITARY SEWER PUBLIC SERVICE. It is the goal of the City of Casselberry to provide,
More informationWASTEWATER & STORM WATER COLLECTION AND REMOVAL
CVE 471 WATER RESOURCES ENGINEERING WASTEWATER & STORM WATER COLLECTION AND REMOVAL Assist. Prof. Dr. Bertuğ Akıntuğ Civil Engineering Program Middle East Technical University Northern Cyprus Campus CVE
More information10.1 Local Water Planning
10 COORDINATION WITH EXISTING LOCAL/REGIONAL PLANS Each of the IRWM agencies plan and execute both short-term capital improvement programs and long-term plans and management programs. It is their plans,
More informationBOROUGH OF ALBURTIS SEWER DEPARTMENT
BOROUGH OF ALBURTIS SEWER DEPARTMENT Capacity, Management, Operations, and Maintenance Program for Sewers Borough of Alburtis Lehigh Co., Pennsylvania February 2018 Prepared for: BOROUGH OF ALBURTIS 260
More informationCasselberry Asbestos Cement Pipe Bursting Project
Casselberry Asbestos Cement Pipe Bursting Project Edward Alan Ambler, P.E., LEED AP TRENCHLESS TECHNOLOGY ROADSHOW May 28-29, 2014 Scotiabank Convention Centre, Niagara Falls, ON Agenda Introduction Asbestos
More informationCITY OF TAMPA ADDENDUM NO. 1. DATE: September 15, Contract 11-C-00001; Wastewater Sewer Rehabilitation by Cured-in-Place Pipe (C.I.P.P.
CITY OF TAMPA Pam Iorio, Mayor CONTRACT ADMINISTRATION DEPARTMENT David L. Vaughn, AIA, Director ADDENDUM NO. 1 DATE: September 15, 2010 Contract 11-C-00001; Wastewater Sewer Rehabilitation by Cured-in-Place
More informationAPPENDIX 1: CITY OF SAN JUAN CAPISTRANO FOCUSED MSR INFRASTRUCTURE ASSESSMENT
APPENDIX 1: CITY OF SAN JUAN CAPISTRANO FOCUSED MSR INFRASTRUCTURE ASSESSMENT October 10, 2018 Prepared for the Orange County Local Agency Formation Commission by Policy Consulting Associates, LLC. & QK
More informationEnvironmental Task Force SSSMP Summary, September 18, 2011 Scheduled for City Council Approval September 26, 2017
Attachment 1 Environmental Task Force SSSMP Summary, September 18, 2011 Scheduled for City Council Approval September 26, 2017 Sanitary Sewer System Master Plan Summary Points - City s sanitary system
More informationCAPITAL IMPROVEMENT PROGRAM J - 1
CITY OF SACRAMENTO CITY UTILITIES PROGRAM OVERVIEW INTRODUCTION Funded primarily by enterprise funds, the City Utilities Program consists of four subprograms: Water, Wastewater, Solid Waste, and Storm
More informationDescription of Water Systems
Description of Water Systems 1 WATER SYSTEM OWNERSHIP AND MANAGEMENT The City is a Washington State municipal corporation that owns and operates a Group A community water system within the boundaries of
More informationBUILDING A WORLD OF DIFFERENCE. Madison Water Utility Infrastructure Management Plan
Madison Water Utility Infrastructure Management Plan February 17, 2009 BUILDING A WORLD OF DIFFERENCE Infrastructure Failure Can Have Serious Consequences! B&V - 2 MADISON WATER UTILITY WATER MASTER PLAN
More informationProposition 1 Funding Opportunities for Los Angeles
Proposition 1 Funding Opportunities for Presentation to the CMAA SC Chapter October 30, 2014 EVELYN CORTEZ DAVIS, P.E. MANAGER OF WATER RECYCLING POLICY & WATER RIGHTS Department of Water and Power Proposition
More informationIn general, the City will not approve a development which cannot be served by extensions to the City s wastewater collection system.
6. WASTEWATER SYSTEM 6.1 General: The design and construction of the wastewater collection system to serve the development shall be in accordance with good engineering principles, these Standards of Design,
More informationBecause of its coastal location on the Gulf
CMOM: Does it Work? Clearwater s Program Performance History Robert Fahey, Tracy Mercer, Janice Nan Bennett, Donald McCullers, Dorean Modjeski, and Kelly Wehner Because of its coastal location on the Gulf
More informationAppendix J. Existing Efforts for Identifying Multi-Benefit Projects
Appendix J Existing Efforts for Identifying Multi-Benefit Projects Water Purveyor Projects Existing Efforts for Identifying Multi Benefits Projects In-lieu groundwater recharge under RWA planning efforts
More informationOTHER CEQA CONSIDERATIONS
Chapter 5 OTHER CEQA CONSIDERATIONS CEQA Guidelines Section 15128 requires that an EIR disclose the reasons why various possible environmental effects of a proposed project are found not to be significant
More information