KAWERAU GENERATION EXPORT ENHANCEMENT INVESTMENT PROPOSAL December GRID UPGRADE PLAN 2009 Instalment 9 Part XII

Size: px
Start display at page:

Download "KAWERAU GENERATION EXPORT ENHANCEMENT INVESTMENT PROPOSAL December GRID UPGRADE PLAN 2009 Instalment 9 Part XII"

Transcription

1 KAWERAU GENERATION EXPORT ENHANCEMENT INVESTMENT PROPOSAL December 2011 GRID UPGRADE PLAN 2009 Instalment 9 Part XII

2 Executive Summary A new geothermal power station (installed capacity of 25 MW) is being built at Kawerau with commissioning expected in December The amount of electricity that can be injected into the 110 kv bus at Kawerau is already limited from time to time. With more generation at Kawerau, these constraints on generation are likely to occur more often. We estimate that by removing these constraints and allowing all the existing geothermal and hydro generation at Kawerau (including the new power station) to be exported to the wider grid, the total cost of producing electricity could reduce by between $20-27 million. By providing some spare interconnection capacity into the 220 kv network we should enable the future development of low cost geothermal generation in the Eastern Bay of Plenty. The information we have received through our consultation has highlighted the potential for significant geothermal development in the area. Our analysis has shown this could result in reduced future generation costs, due to geothermal generation being one of the most cost effective methods of producing electricity. A number of transmission and non-transmission options to remove the constraint have been assessed. The short listed options included: replace a 220/110 kv transformer at Kawerau (T12 or T13) with a higher rated unit; reconfigure the grid to connect part or all Matahina and Aniwhenua power station generation to Edgecumbe. We will not be able to replace a transformer before 2014 due to the lead time to procure and install it. Therefore, we have identified an interim, low-cost measure which will relieve constraints between the time the new Kawerau power station is commissioned and when we commission a new transformer. The interim measure is to connect one of the Matahina to Kawerau circuits directly to one of the Edgecumbe to Kawerau, bypassing Kawerau, to create a single circuit between Matahina and Edgecumbe. One Matahina generating unit will be connected to this new circuit, moving up to 40 MW of generation off the Kawerau 110 kv bus. Special protection schemes are required for this reconfiguration, and for all permanent options.. Typically these options cost between $5-7 million and are significantly less than the benefits investment will provide. In our Grid Investment Test analysis we considered these options across five different market development scenarios, each with different assumptions about generation development at Kawerau. The results show that replacing the Kawerau T12 transformer with a new unit rated at 250 MVA is the best option on average across the five market development scenarios, although the difference between options is very small. After further considering unquantified costs and benefits associated with each option it is our view that replacing Kawerau T12 with a 250 MVA transformer is the best option. In addition to being the most economic option from our Grid Investment Test analysis, it also provides the greatest number of unquantified benefits. It will provide additional capacity to encourage geothermal generation development and will capture some of the large benefits identified in our analysis in enabling geothermal development. It also provides a number of operational benefits, such as the capacity to perform some maintenance work without iii

3 disruption. The incremental cost of installing a 250 MVA transformer rather than a smaller 150 MVA transformer is also low (less than $1 million). As such the extra capacity is good value for money and may avoid the need to install another new transformer in the near future. Proposal at a Glance What: 1. Install a special protection scheme to manage loading on the Edgecumbe Owhata circuit and loading on the Kawerau interconnecting transformers as soon as practical 2. Reconfigure Kawerau Matahina circuit 2 and Edgecumbe Kawerau circuit 2 to bypass Kawerau substation as an interim measure as soon as practical 3. Procure and install a new 250 MVA transformer by 2014 to replace the Kawerau T12 transformer, install a special protection scheme to manage loading on the Edgecumbe Kawerau 1 and 2 circuits and undo the reconfiguration. When: Commence work in 2012 and complete in How much: Transpower is seeking approval for up to $ million This document is our formal submission to the Commerce Commission for approval to reconfigure circuits at Kawerau and then replace the Kawerau T12 transformer with a 250 MVA unit. 1 Our Maximum Approval Cost (MAC) is higher than the expected cost of the project as it includes an allowance for price uncertainties, project unknowns, is expressed in 2014 dollars and includes the financing costs associated with the proposed project. iv

4 Table of Contents 1 The need for investment The issue Options The options Analysis Benefits from investment Existing generation dispatch benefits Generation enabling benefits The cost of investment Investment Proposal Grid Investment Test Results Sensitivity of the results Unquantified costs and benefits Stakeholder engagement and submissions Approval Amount Appendices Glossary

5 1 The proposal This section describes our proposal. Components of the Proposal Installation of a special protection scheme to manage loading on the Edgecumbe Owhata circuit and loading on the Kawerau interconnecting transformers Reconfiguration of the Kawerau Matahina circuit 2 and Edgecumbe Kawerau circuit 2 to bypass Kawerau substation Procuring, installing and commissioning a new 250 MVA transformer to replace the Kawerau T12 transformer Installation of a special protection scheme to manage loading on the Edgecumbe Kawerau 1 and 2 circuits Decommisioning of the reconfiguration We propose starting this work in 2013 and completing it in We expect the project to cost $8.5 million once commissioned. However, we are seeking Commerce Commission approval to recover the full costs associated with the Proposal, upon commissioning, up to a total amount of $9.5 million. This amount includes a contingency to allow for uncertainties in the project costs and is the estimated Maximum Approval Cost to implement the Proposal. Please note that whilst we conducted the GIT analysis on an expected cost of $6.8 million, a subsequent cost review led to an increase to $7.2 million. This cost increase does not impact the GIT analysis since it is common to all options, nor does it affect the approval amount on which we consulted. 6

6 2 The need for investment A new geothermal power station (installed capacity of 25 MW) is being built at Kawerau and will be commissioned in December The amount of electricity that can be injected into the 110 kv bus at Kawerau is already constrained from time to time. The presence of the new generation will materially increase the amount of time that existing low fuel cost generation (hydro and geothermal) is constrained off at Kawerau and replaced with more expensive generation from elsewhere. We have identified a number of economic investments to relieve the generation constraint and enable further generation development. In this section we explain the need for investment. 2.1 The issue This investigation relates to our Kawerau substation. The current system is shown in Figure 2-1. Figure 2-1 System diagram Te Kaha Tarukenga 110 kv Okere Edgecumbe 110 kv 33 kv Waiotahi 110 kv 50 kv 11 kv Edgecumbe-Kawerau 110kV circuits Kawerau interconnecting transformers Owhata 110 kv 11 kv Kawerau 110 kv 220 kv 220 kv 11 kv 11 kv 11 kv (TASMAN) KAG Ohakuri 11 kv KEY 220kV CIRCUIT 110kV CIRCUIT 50kV CIRCUIT SUBSTATION BUS TRANSFORMER TEE POINT LOAD CAPACITOR GENERATOR Matahina 110 kv Aniwhenua There are a number of power stations that inject electricity into Kawerau substation: Mighty River Power s 105 MW geothermal power station Trustpower s 80 MW Matahina hydro station Todd Energy s 25 MW Aniwhenua hydro station. 7

7 Norske Skog Tasman Ltd plans to connect a further 25 MW of geothermal generation in December This will result in a total of 235 MW of generation being connected to our substation. Our grid does not have capacity to accept all this generation at times of low load at Kawerau. As a result, if additional capacity is not provided generation will need to be constrained off to manage loading on our equipment. Several industrial consumers are supplied via the Kawerau s 110 kv bus including Norske Skog Tasman Ltd, Carter Holt Harvey and SCA Hygiene. Figure 2-2 shows the 2010 load duration curve. In 2010 demand peaked at around 90 MW and averaged approximately 50 MW. Figure 2-2 Demand at Kawerau 110 kv bus MW Demand on Kawerau 110kV bus 2010 Halfhourly demand (sorted from top to bottom) Figure 2-3 shows the generation exported from the Kawerau 110 kv substation in Electricity is exported via the two 220/110 kv interconnecting transformers at Kawerau (T12 and T13) and the Edgecumbe Kawerau 110 kv circuits. With the commissioning of new generation the generation export line will move up, as shown in green. Figure 2-3 Generation export at Kawerau Generation Export at Kawerau 110kV Constrained generation MW With new Norkse Skog generation Halfhourly export (sorted from top to bottom) 8

8 The maximum amount of generation that could be exported from the Kawerau 110 kv bus by 2014 is around 148 MW. The area above the transmission limit, shown in red, represents constrained off generation. The quantum and duration of constrained off generation is highly dependent on hydrology. Aniwhenua and Matahina generation are likely to be constrained off more often in years where there are high inflows into the hydro catchments for the power stations. 9

9 3 Options In May we consulted on a long-list of options for relieving the generation constraint. A further two options were suggested by submitters during consultation and added to the long-list. The long list has been refined to a short list of five credible options to which we have applied the Grid Investment Test (GIT). Further details of the short listing process can be found in Attachment B The options The short list of options is shown in Table 3-1 below. Table 3-1 Credible Option List No. Option Description Cost ($000s) 0 Base Case Do Nothing 0 1 T12 150MVA Half reconfiguration the KAW T12 transformer with a 150MVA transformer 5,917 2 T12 250MVA Half reconfiguration the KAW T12 transformer with a 250MVA transformer 6,840 3 T13 150MVA 4 T MVA 5 Full reconfiguration Half reconfiguration the KAW T13 transformer with a 150MVA transformer Half reconfiguration the KAW T13 transformer with a 250MVA transformer Reconfigure the Edgecumbe-Kawerau 1&2 and Kawerau-Matahina 1&2 circuits EDG T4 transformer 100MVA 5,979 6,896 6,826 All new transformer options assume an interim half reconfiguration solution from The half reconfiguration will join the Edgecumbe Kawerau 2 and Kawerau Matahina 2 circuits together to bypass Kawerau substation. The output of one of the Matahina generating units flows directly on this new circuit to Edgecumbe. The Edgecumbe-Kawerau 1 circuit will be de-energised, The half-reconfiguration system configuration is shown in Figure 3-1. This solution is undone once a new transformer is commissioned at Kawerau in Our analysis has shown that with the constraint in 2013 the total cost of producing electricity would be approximately $0.7 million higher than if the half reconfiguration was in effect, based on an average hydro inflow year. The cost to install and then undo the half reconfiguration is estimated to be less than $0.6 million. Hence, it is economic to invest in the half reconfiguration, given it also manages the risk 10

10 associated with project delays and reduces production costs during sustained periods of high hydro inflows. The half reconfiguration has not been considered as a long-term solution by itself as it will not completely remove constraints, provides no additional capacity to enable future generation, and would necessitate the return to service of the Edgecumbe transformers. The full reconfiguration (Option 5) also requires that the Edgecumbe 220/110 kv interconnecting transformers be permanently returned to service 2. The Edgecumbe transformers are 59 years old and, if returned to service, the existing transformers would need to be replaced under the fleet strategy for older transformers around As such, this cost is associated with this option. For each option a number of special protection schemes are also required. These are protection schemes that monitor events on the system and automatically take action to ensure our assets are not overloaded. The accompanying Technical, Options and Costing report further describes these special protection schemes. It should be noted that the short list options represent the first stage of investment. As more generation is connected at Kawerau further investment will be required. This is discussed in more detail in Section 4.2. Figure 3-1 half-reconfiguration system configuration T4 Edgecumbe 110 kv 26 MW 10 MW EDG-WAI 2 Owhata Tarukenga 110 kv 110 kv OKE-TRK 1 Okere 110 kv EDG-OWH 1 OKE-OWH 1 OKE-TMI 1 Te Matai 110 kv EDG-KAW 2 KAW-MAT 2 KAW-MAT 1 Kawerau 220 kv EDG-KAW 3 36 MW 60 MW Matahina 110 kv 36 MW 36 MW MAT- G2 EDG-KAW 1 ANI- G1 T5 MAT-ANI 1 Edgecumbe 220 kv 24 MW 12 MW 12 MW ANI- G2 T MW KAG MAT- G1 139 MW 48 MW Aniwhenua 110 kv 25 MW NSK 100 MW T13 slack 8 MW Constraint KAW-OHK 1 Kawerau 110 kv 2 The Edgecumbe transformers are currently out of service (i.e. opened) to help maximise the amount of generation that can be exported from Kawerau. 11

11 4 Analysis 4.1 Benefits from investment The GIT requires us to determine the market benefits and costs of the base case and each of the upgrade options over five market development scenarios. We have assessed two key benefits of investing in the grid to enable unconstrained renewable generation: 1. Existing Generation Dispatch Benefits The existing generation dispatch benefits assume that no further generation connects to Kawerau after Norske Skog s new 25 MW plant. With no investment the existing renewable generation will at times be constrained off and more expensive generation elsewhere (e.g. gas turbines) will be dispatched in its place. The benefit is the difference in the production cost of electricity between doing nothing (base case) and investing to unconstrained dispatch. The first stage of all five development options provides sufficient capacity to remove the constraint. 2. Generation enabling benefits Generation enabling benefits arise from the reduction in the total capital cost of building and operating new generation across New Zealand by providing greater capacity for new generation to connect at Kawerau. If the total cost of building and operating new generation at Kawerau with no transmission constraint is lower than the total cost of building and operating new generation elsewhere, then there is benefit from investment in the Grid to relieve the transmission constraint at Kawerau. As new geothermal power stations currently represent one of the lowest cost means of generating electricity, this benefit is likely to be high. Our analysis includes an assessment of both the dispatch and enabling benefits arising from the short list options Existing generation dispatch benefits Without any transmission upgrade the existing generation at Kawerau (including Norske Skog Tasman s new 25 MW power station) will be constrained off at times resulting in more expensive generation being dispatched in its place. We have built a model utilising historical generation profiles, forecast demand profiles and the appropriate transmission capacity parameters to value this dispatch benefit by half-hour. The model calculates the amount of generation that is constrained for each year over the period from 2013 to It then multiplies the amount of generation constrained by the Short Run Marginal Cost (SRMC) of generation. A range of assumptions have been made in this calculation: 12

12 Matahina and Aniwhenua generation is based on the actual output in the 2005 year as this is considered an average inflow year, while Mighty River Power s geothermal generation is based on the 2009 year. New generation is assumed to have a similar half hourly relationship as Mighty River Power s geothermal generation. Local demand supplied via Horizon s distribution network is assumed to grow at 2% per annum. Forecast demand at Norske Skog Tasman is based on Norske Skog Tasman s advice regarding future projections of load at Kawerau. Norske Skog Tasman s peak demand tends to be in non-peak periods when wholesale market prices are lower. The existing generation at Kawerau comes from geothermal and hydro fuel sources. These forms of generation have a low marginal operating cost. With a constraint at Kawerau this low cost generation is likely to be replaced by more expensive thermal generation that requires burning gas and coal. Hence the constraint will result in higher production costs. To determine the additional production costs we have multiplied the amount of constrained off generation by the Short Run Marginal Cost (SRMC) of generation. The SRMC represents the cost of producing the last unit of electricity. It is our view that this approach is conservative, and using alternative methods, such as using Huntly s cost of production, would likely result in a higher benefit associated with removing the present constraint. We have calculated the SRMC for each of the five Market Development Scenarios (MDS) in the Electricity Commission s 2010 Statement of Opportunities 3 (SoO). Figure 4-1 illustrates the average annual SRMC that we have used to value constrained off generation by MDS. On average, values vary between $60/MWh to $180/MWh. 3 SRMCs were derived from modelling the SoO Scenarios using our modelling tool, SDDP. SDDP simulates the operation of the electricity market, over all historical inflow sequences. 13

13 Figure 4-1 Average short run cost of generation used to value constrained generation Average short run marginal cost of generation $/MWh MDS1 Sustainable path MDS3 Medium renewables MDS5 High gas discovery MDS2 South Island wind MDS4 Coal Under average hydro inflow conditions, around 20 GWh of generation would be constrained off each year with a value of $2 million per annum. Table 4-1 shows the net present value of the existing generation dispatch benefit arising from using the SRMCs from each MDS over the period. Table 4-1 Existing Generation Dispatch Benefit, NPV $ million MDS1 MDS2 MDS3 MDS4 MDS5 Average Benefit (in 2011 $) Generation enabling benefits The presence of generation constraints at Kawerau will provide a disincentive for new generation to locate behind the constraint. New generation in the area connecting behind the constraint would have to be prepared to either have output constrained some of the time or have to invest in transmission assets to enable connection to an unconstrained part of the network. There is a considerable benefit in investment to enable low-cost generation to connect at the Kawerau 110 kv bus given the potential for such low-cost renewable generation in the nearby area. To quantify this benefit, we have used five Market Development Scenarios (MDS) which are based on the MDS contained in the 2010 SoO but have been modified to: 14

14 account for 25 MW of new generation being built by Norske Skog which is not in any of the SoO scenarios. take into account the feedback from our May consultation that highlighted a number of potential new generators in the area over the coming 20 years. provide a greater range in the timing and size of new generation and hence make an assessment over a greater range of scenarios. The total amount of generation injecting into the 110 kv bus at Kawerau by MDS is shown in Figure 4-2 below. The majority of the new generation is assumed to be geothermal, and we have assumed that this generation has the generic capital cost of geothermal generation used in the SoO of $5,200/kW. Further detail on these MDS can be found in the Attachment B.. Figure 4-2 Total installed generation capacity at Kawerau by MDS Total Generation at Kawerau, MW MW MDS1 Sustainable path MDS3 Medium renewables MDS5 High gas discovery MDS2 South Island wind MDS4 Coal We have used the Electricity Authority s Generation Expansion Model (GEM), which is a least cost capacity expansion model of the New Zealand electricity sector, to calculate the benefit of enabling the generation. To calculate the benefit we have run the model twice for each MDS as follows: 1. assuming that generation expansion at Kawerau is unconstrained and is built as shown in Figure assuming generation expansion is constrained and only Norske Skog s new 25 MW generation plant is built. 15

15 The difference between the costs of generation expansion under these conditions gives us the benefit of enabling the generation shown in Figure 4-2. Table 4-2 presents the results. The results show the significant benefit that can arise from enabling lower cost renewable generation. Table 4-2 Generation enabling benefits, $ million 2011 MDS1 MDS2 MDS3 MDS4 MDS5 Average Enabling Generation Benefit MDS1 and MDS4 have the highest benefit due to the timing and size of the amount of generation that is enabled. In MDS5 only Norske Skog Tasman s new generation is built in both the constrained and unconstrained cases, hence there is no benefit. Intuitively, one would expect the benefit from MDS4 to be higher than MDS1 given there is more generation enabled under MDS4. However this is not the case since MDS4 assumes lower costs of thermal generation than MDS1 lessening the advantage of geothermal generation. 4.2 The cost of investment The cost of investment required to relieve constraints over an analysis period to 2034 will differ for each of the MDS. For example, to enable the generation in MDS4 both Kawerau T12 and T13 will eventually be replaced with larger units. Our analysis has focused on our 110 kv network as the constraints on this network arise first. Some additional investment may be required in our 220 kv network if a large power station is connected at Kawerau. Investigating these issues would significantly increase the scope of this investigation and is unlikely to alter our conclusions for investment at Kawerau as whatever is needed is likely to be common to all options over the analysis period. As noted in Section 2, the short list options represent the first stage of investment required to enable the generation in all of the MDS. In order to apply the GIT over the analysis period for each MDS, we have created a number of development plans, illustrated in Figure 4-3 below. 16

16 Figure 4-3 Development Plans The need and timing of the stages subsequent to stage 1 depends on the timing and amounts of future generation in each MDS. The development plans allow for sufficient transmission investment to be built to enable the generation in each MDS to be built without constraint 4. More information about the development plans are provided in the Attachment B. In some cases, if the incidence of constraint is minor, it may be economic to defer investment and incur a small constraint cost. Further, the full reconfiguration option results in reduced security and some small additional constraints associated with Matahina and Aniwhenua generation. Hence, for all options there is a minor constraint cost. We have also accounted for the need to replace assets due to age and condition. In particular, the full reconfiguration option would require the replacment of the Edgecumbe interconnecting transformers. With the other options this is deferred until significant amounts of additional generation appear at Kawerau. In the analysis it is assumed that if T12 (the younger transformer at Kawerau) is replaced then it could be moved to Edgecumbe to replace the existing interconnecting transformers saving the need to spend money on a new transformer. A 60 year replacement age has been assumed for the existing transformers at Kawerau. Table 4-3 and Table 4-4 show the total capital and constraint costs associated with the optimal development plan (including the cost of replacement of assets) for each option, by MDS. The figures shown in the table are present values and account for the timing of each subsequent investment that may be required. 4 Details of the optimal development plans for each scenario are contained in the accompanying Technical, Options and Costing document. 17

17 Table 4-3 Capital cost of optimal development plan, present value, $ million No. Option MDS1 MDS2 MDS3 MDS4 MDS5 Average Base Case Kawerau T MVA Kawerau T MVA Kawerau T MVA Kawerau T MVA Full reconfiguration Table 4-4 shows the value of constraints associated with each of the options. These values are low. MDS1 has more constraints as the generation that is commissioned in the scenario is smaller and at some times it is more cost effective to delay investment and incur a small cost of constraint. Table 4-4 Constraint costs of optimal development plan, present value, $ million No. Option MDS1 MDS2 MDS3 MDS4 MDS5 Average Kawerau T MVA Kawerau T MVA Kawerau T MVA Kawerau T MVA Full reconfiguration

18 5 Selecting the Investment Proposal Our investment proposal is option 2, the replacement of the T12 interconnecting transformer at Kawerau with a 250 MVA transformer. The benefits and costs for the options are very similar and it is not easy to differentiate between the options to identify the one that provides the best net benefit purely from the economic analysis. The replacement of Kawerau T12 with a new unit rated at 150 MVA (Option 1) is sufficient to reduce the level of constraint at Kawerau to an acceptable level following the commissioning of the new power station and is the lowest capital cost option. Our GIT analysis identified additional benefits from replacing T12 with a unit rated at 250 MVA (Option 2). The incremental cost of a larger unit is low (around $0.9 million). The benefits to New Zealand from investing to enable new low cost generation to connect at Kawerau ranges from $46-$193 million. If investing in additional capacity enabled only 5% of the lower bound of this benefit to be realised then a larger transformer may be associated with $2.3 million in additional benefits. This section details how Option 2 satisfies the Grid Investment Test and is also supported by our qualitative assessment of unquantified benefits. 5.1 Grid Investment Test Results Table 5-1 shows the expected net market benefit of each option relative to the base case averaged over all the MDS. The expected net market benefit is calculated as: the benefits from investment identified in Table 4-1 and Table 4-2 minus the capital cost of investment set out in Table 4-3, minus the constraint costs associated with investment shown in Table 4-4. Table 5-1: Expected Net Market Benefit (NPV $ million) No. Option Existing generation Dispatch Benefits (A) Enabling generation benefits (B) Transmission costs (C) Constraint Cost (D) Expected Net Market Benefit (A+B-C-D) Rank Kawerau T MVA Kawerau T MVA Kawerau T MVA Kawerau T MVA Full

19 No. Option Existing generation Dispatch Benefits (A) Enabling generation benefits (B) Transmission costs (C) Constraint Cost (D) Expected Net Market Benefit (A+B-C-D) Rank reconfiguration The results show that replacing our T12 transformer at Kawerau with a 250 MVA transformer (Option 2) has the highest net market benefit. However, there is very little difference between options. The expected net market benefit of Option 2 is only $0.4 million higher than the lowest ranked option (full reconfiguration). 5.2 Results by Market Development Scenarios (MDS) Table 5-2 shows the expected net market benefit of each option for each MDS. Our proposal, Option 2 has the highest net market benefit in three of the five MDS. Only in the two scenarios with limited new generation, is it not the best option. The results also show that all options continue to give similar levels of benefit to each other across MDS. Table 5-2: Expected Net Market Benefit (NPV $ million) No. Option MDS1 MDS2 MDS3 MDS4 MDS5 Average Kawerau T MVA Kawerau T MVA Kawerau T MVA Kawerau T MVA Full reconfiguration Sensitivity of the results We have re-run the analysis 5 to test the proposal s sensitivity to: capital costs demand growth discount rates Table 5-3 shows the expected net market benefit under this range of sensitivities. 5 In a commensurate manner, the years associated with each stage of the development plan for each option has not been reassessed for each sensitivity. 20

20 Our proposal, Option 2, returns the highest expected net market benefit in three of the six sensitivities. However, the table shows that all options retain a similar net market benefit to one another across the range of sensitivities. Table 5-3: Sensitivity results, Net market benefits, $ million No. Option -20% capital cost +20% capital cost Low demand High demand 4% discount rate 10% discount rate Kawerau T MVA Kawerau T MVA Kawerau T MVA Kawerau T MVA Full reconfiguration It is our view that these results support our proposal and show it is robust. 5.4 Unquantified costs and benefits In order to further assist our decision making we have assessed the unquantified benefits for all options. Table 5-4 shows our qualitative assessment of the unquantified benefits of the different options. The benefit of each option has been qualitatively ranked between - and, with more ticks indicating a more favourable option. The following benefits have been considered: Operational benefits to what extent does the option provide operational benefits not reflected in the economic analysis? Installing a larger transformer is likely to provide operational benefits in that we will be able to perform some maintenance at the Kawerau substation without any need to constrain generation export. Option benefits does the option include flexibility to be amended in the future if there are significant changes and will it help enable further favourable benefits? All options allow a staged approach to future investments. In general, the full reconfiguration option may limit future options, either by way of using the Edgecumbe Kawerau circuits to supply new load in the region or by using the Edgecumbe interconnectors to connect other new generation in the wider region. Consumer benefits through enhanced competition to what extent will the option enhance competition in the New Zealand electricity market? 21

21 The more competitive a market is, the more efficient it will be at delivering the advantages that markets can provide to consumers. Consumer benefits are likely to be highest when installing a larger transformer which enables more renewable generation to be built. Minimises disruption to what extent will the local community be disrupted by the implementation of an alternative? All options are equal in this respect since the vast majority of the work will be carried out within the Kawerau substation. Some additional disruption may occur with the transformer options as outages will be required for the installation of the new transformer. Diversity benefits to what extent will the option provide diversity of supply? The full reconfiguration splits the system and improves system diversity by shifting generation to Edgecumbe. Table 5-4: Unquantified benefits No. Option ENMB Operational Option benefits Consumer Benefits Minimises Disruption Diversity benefits Overall Kawerau T MVA Kawerau T MVA Kawerau T MVA Kawerau T MVA Full reconfiguration T12 with a 250 MVA transformer outweighs other options as it allows minimum generation constraints for outages on the Edgecumbe Kawerau circuits and T13 transformer. Replacing T12 with a 250 MVA transformer allows for minimum generation constraints when T13 is to be replaced with a 250 MVA transformer as more generation connects onto Kawerau. This option provides Transpower the flexibility in the future to either increase the interconnection capacity at Kawerau or shift some generation to Edgecumbe as more generation development appears. Our qualitative assessment of the non quantified benefit supports the option which passes the GIT, namely Option 2 the interim half reconfiguration as soon as possible followed by a new 250 MVA to replace Kawerau T12 transformer in

22 6 Stakeholder engagement and submissions We have engaged with stakeholders on two occasions. The overall theme of all the submissions was supportive and positive. 6.1 Request for Information In May 2011 we released an Options, Assumptions, Approach and Request for Information document. In response, we received eight submissions: Eastland Generation Limited Bay of Plenty Energy/TrustPower (joint submission) Horizon Energy Bay of Plenty Regional Governance Group Norske Skog Tasman Limited Mighty River Power Kawerau District Council Ngati Tuwharetoa Holdings Ltd In general the submissions stressed the need to remove the constraint on generation for commercial, economic and regional development reasons. The submissions highlighted the number of new generation opportunities being considered in the Kawerau area. This feedback was incorporated into our analysis through amendments to the market development scenarios. Further a number of alternative options were raised during this consultation and this feedback helped us to develop the full and half reconfiguration short listed options. 6.2 Consultation on our application of the Grid Investment Test In November 2011 we released the results from our application of the Grid Investment Test which showed that our preferred upgrade option was to half reconfigure the grid at Kawerau as soon as possible and then replace the T12 transformer at Kawerau with a 250 MVA transformer in 2014 (with associated Special Protection Schemes). During the consultation. we ran a forum at Tauranga that was attended by 10 stakeholders. At the forum we presented the results from our analysis and clarified any matters arising from the consultation material. During the consultation we requested feedback on our application of the Grid Investment Test. Overall industry stakeholders believe that we have reasonably applied the GIT. and we do not consider any of the issues that were raised impact on the conclusions presented in the consultation material. 23

23 Full details of the consultation can be found in Attachment C.. 24

24 7 Approval Amount If a project is approved by the Commerce Commission, we can recover the costs of the project through the regulated charges for the transmission grid. The Commerce Commission also approves an amount that we can spend. If we spend under this amount, we only recover actual costs. Our investment proposal is to Install a special protection scheme to manage loading on the Edgecumbe Owhata circuit and loading on the Kawerau interconnecting transformers as soon as practical; Reconfigure Kawerau Matahina circuit 2 and Edgecumbe Kawerau circuit 2 to bypass Kawerau substation as soon as practical; Procure and install a new transformer rated at 250 MVA by 2014 to replace Kawerau T12, install a special protection scheme to manage loading on the Edgecumbe Kawerau 1&2 circuits and undo the reconfiguration. We determine an approval amount by accounting for the uncertainties in the project cost to calculate a Maximum Approval Amount (MAC). The Expected Cost of the investment proposal is estimated to be $7.2 6 million and the MAC is estimated to be $9.5 million. As we recover the costs once the project is commissioned (completed), the approved amount from the Commerce Commission is expressed in commissioning year dollars. Also included in the expected cost is an amount for our Community Care funding. Transpower acknowledges that while there are clear benefits from electricity transmission, our work will impact on local communities. In summary, the MAC is higher than the Expected Cost because it: includes an allowance for price uncertainties, and project unknowns. is expressed as 2014 dollars not 2011 covers all the financing costs associated with the proposed project. This is shown in Table Please note that whilst we conducted the GIT analysis on an expected cost of $6.8 million, a subsequent cost review led to an increase to $ million. This cost increase does not impact the GIT analysis since it is common to all options, nor does it affect the approval amount on which we consulted. 25

25 Table Approval Amount Expected Cost ($ million, 2011) Including Price Uncertainty ($ million, 2011) Including Inflation to 2014 ($ million, 2014) Including Financing Costs - MAC ($ million, 2014)

26 8 Attachments Further information is contained in the following attachments: Attachment A Meeting the requirements of the Rules Attachment B Technical, options and costing report Attachment C Summary of submissions and response to submissions 27

27 Glossary Term Alternative Project Economic Investment GEM Grid Investment Test (GIT) Grid Modelled project Description Limited to those appropriate in number and technology given the cost magnitude of the proposed investment, the complexity of the modelling and the urgency of the proposed investment. Likely to proceed if neither the proposed investment nor any other alternative project proceeds and unlikely to proceed if the proposed investment does proceed. Reasonably expected to provide similar benefits in type but not necessarily magnitude to relevant nodes as the proposed investment (Schedule F4 clauses 11 and relevant part of clause 19). Investments in the grid that can be justified on the basis of the Grid Investment Test set out at Schedule F4. Generation Expansion Model is a capacity expansion model of the New Zealand electricity sector developed by the Electricity Commission and Electricity Authority. A test for reliability investments and economic investments in the grid The system of transmission lines, substations and other works used to connect grid injection points and grid exit points to convey electricity throughout the North and South Islands of New Zealand A modelled project is a project which is not part of the proposal, but is likely to occur in one or more scenarios within the time horizon of the analysis. Schedule F4 (Grid Investment Test) SDDP Statement of Opportunities (SoO) Transmission Alternatives Authorised under the Commerce Act section 54R. Stochastic Dual Dynamic Programme developed by Power Systems Research in Brazil. It is used to assess national generation costs based on a distribution of hydro inflows into storage lakes across various generation scenarios. Statement of Opportunities developed by the Electricity Commission (EC). The EC has been disestablished and the 2010 SoO is the last. Alternatives to investment in the grid, including investment in local generation, energy efficiency, demand-side management and distribution network augmentation 28

IS Kawerau Electricity Resource Background Study

IS Kawerau Electricity Resource Background Study 1. Background IS Kawerau Electricity Resource Background Study New Zealand s electricity sector is broken down into four main parts: Generation: Various entities generate electricity at plants throughout

More information

Wairakei Ring Investment Proposal

Wairakei Ring Investment Proposal Wairakei Ring Investment Proposal Project Reference: CTNI_TRAN-DEV-01 Attachment B Analysis assumptions and methodology December 2008 Document Revision Control Document Number/Version Description Date

More information

TEMPORARY GRID RECONFIGURATIONS NET BENEFIT TEST METHODOLOGY

TEMPORARY GRID RECONFIGURATIONS NET BENEFIT TEST METHODOLOGY TEMPORARY GRID RECONFIGURATIONS NET BENEFIT TEST METHODOLOGY 1 1. Summary When one part of the grid is facing security of supply risk where local generation in one region of the grid is not enough for

More information

Request for Market Performance Review.

Request for Market Performance Review. 1 st August 2013 Attn: Bruce Smith General Manager Market Performance Electricity Authority Level 7 ASB Bank Tower 2 Hunter Street PO Box 10041 Wellington From: Christopher Brown Site Energy Coordinator

More information

BELLS POND-WAITAKI TRANSMISSION CONSTRAINT - PROPOSED APPROACH INFORMATION DOCUMENT

BELLS POND-WAITAKI TRANSMISSION CONSTRAINT - PROPOSED APPROACH INFORMATION DOCUMENT BELLS POND-WAITAKI TRANSMISSION CONSTRAINT - PROPOSED APPROACH INFORMATION DOCUMENT CONTINGENCY PLANS NET BENEFIT ANALYSIS Transpower New Zealand Limited October 2016 i Table of Contents Proposal Summary...

More information

Dalrymple Substation Upgrade

Dalrymple Substation Upgrade Dalrymple Substation Upgrade RIT-T: Project Assessment Conclusions Report Version 1 ElectraNet Corporate Headquarters 52-55 East Terrace, Adelaide, South Australia 5000 PO Box, 7096, Hutt Street Post Office,

More information

Draft Project Assessment Report. Dromana Supply Area. Project UE-DZA-S RIT-D Report

Draft Project Assessment Report. Dromana Supply Area. Project UE-DZA-S RIT-D Report Draft Project Assessment Report RIT-D Report This report presents the network limitations at Dromana zone substation and the distribution feeder network within the Dromana / Mornington supply areas, including

More information

Ergon Energy Corporation Limited

Ergon Energy Corporation Limited Ergon Energy Corporation Limited Final Report Emerging Distribution Network Limitations in the Central Toowoomba Area 16 May 2013 Disclaimer While care was taken in preparation of the information in this

More information

PART A - The Proposal...IV PART B Justification Introduction...1

PART A - The Proposal...IV PART B Justification Introduction...1 Contents TABLE OF CONTENTS PART A - The Proposal...IV PART B Justification...1 1 Introduction...1 1.1 Purpose...1 1.2 Background to the Proposals...1 1.3 Document structure...1 1.4 Glossary/terminology...2

More information

Lower Mornington Peninsula Supply Area

Lower Mornington Peninsula Supply Area Final Project Assessment Report RIT-D Report This report presents the sub-transmission network limitations in the lower Mornington Peninsula including the preferred option to address those limitations.

More information

ALL ISLAND GRID STUDY STUDY OVERVIEW. January 2008

ALL ISLAND GRID STUDY STUDY OVERVIEW. January 2008 ALL ISLAND GRID STUDY STUDY OVERVIEW January 2008 1 Study Overview The All Island Grid Study is the first comprehensive assessment of the ability of the electrical power system and, as part of that, the

More information

Ergon Energy Corporation Limited 4 June 2010

Ergon Energy Corporation Limited 4 June 2010 Ergon Energy Corporation Limited 4 June 2010 Disclaimer While care was taken in preparation of the information in this discussion paper, and it is provided in good faith, Ergon Energy Corporation Limited

More information

Connecting New Generation in New Zealand. Len Gould Customer Services Manager Transpower New Zealand Ltd

Connecting New Generation in New Zealand. Len Gould Customer Services Manager Transpower New Zealand Ltd Connecting New Generation in New Zealand Len Gould Customer Services Manager Transpower New Zealand Ltd Outline New Zealand s power system & Transpower s roles The planning process for new generation The

More information

contents executive summary introduction Future requirements scenarios electricity demand Generation impact on the Grid scenario outcomes

contents executive summary introduction Future requirements scenarios electricity demand Generation impact on the Grid scenario outcomes THE ENDURING GRID contents 01 Executive Summary 02 1 Introduction 03 2 Future requirements 03 3 Scenarios 06 3.1 Electricity demand 09 3.2 Generation 12 3.3 Impact on the Grid 12 3.4 Scenario Outcomes

More information

Dalrymple substation upgrade

Dalrymple substation upgrade Dalrymple substation upgrade RIT-T: Project Specification Consultation Report ElectraNet Corporate Headquarters 52-55 East Terrace, Adelaide, South Australia 5000 PO Box, 7096, Hutt Street Post Office,

More information

Amendments to input methodologies for electricity distribution services and Transpower New Zealand

Amendments to input methodologies for electricity distribution services and Transpower New Zealand ISBN 978-1-869454-11-1 14.09/12685:14.11/12685 Public version Amendments to input methodologies for electricity distribution services and Transpower New Zealand Incremental Rolling Incentive Scheme Date

More information

LOWER SOUTH ISLAND RELIABILITY INVESTMENT PROPOSAL. Attachment F Summary of Stakeholder Engagement

LOWER SOUTH ISLAND RELIABILITY INVESTMENT PROPOSAL. Attachment F Summary of Stakeholder Engagement LOWER SOUTH ISLAND RELIABILITY INVESTMENT PROPOSAL Attachment F Summary of Stakeholder Engagement May 2010 Document Revision Control Document Number/Version Description Date 001/Rev A Lower South Island

More information

Section 3 Firm Access Quantities and Associated Transmission Reinforcements

Section 3 Firm Access Quantities and Associated Transmission Reinforcements GATE 3 FREQUENTLY ASKED QUESTIONS Latest Update May 2013 Section 3 Firm Access Quantities and Associated Transmission Reinforcements 1. What does the term Firm Access Quantity or FAQ mean? 2. I own or

More information

RCP2 Project Overview Document

RCP2 Project Overview Document RCP2 Project Overview Document Project: Expenditure Class: Base Capex Expenditure Category: Grid - Enhancement & Development As at date: 15 November 2013 Expenditure Forecast Real 2012/13 NZ$ (m) 2015-2016

More information

Ergon Energy Corporation Limited 12 November 2009

Ergon Energy Corporation Limited 12 November 2009 Ergon Energy Corporation Limited 12 November 2009 Disclaimer While care was taken in preparation of the information in this discussion paper, and it is provided in good faith, Ergon Energy Corporation

More information

Generation Technology Assessment & Production Cost Analysis

Generation Technology Assessment & Production Cost Analysis SPO Planning Analysis Generation Technology Assessment & Production Cost Analysis EAI Stakeholder Meeting July 31, 212 Technology Life Cycle Technology Deployment Over Time Conceptual Research & Development

More information

PERFORMANCE MEASURES SUMMARY OF CUSTOMER FEEDBACK ON JULY 2013 CONSULTATION. Transpower New Zealand Limited September 2013

PERFORMANCE MEASURES SUMMARY OF CUSTOMER FEEDBACK ON JULY 2013 CONSULTATION. Transpower New Zealand Limited September 2013 PERFORMANCE MEASURES SUMMARY OF CUSTOMER FEEDBACK ON JULY 2013 CONSULTATION Transpower New Zealand Limited September 2013 Performance Measures Transpower New Zealand Limited 2007. All rights reserved.

More information

APPENDIX 9.2 Description of SPLASH Model

APPENDIX 9.2 Description of SPLASH Model APPENDIX 9.2 Description of SPLASH Model This page is intentionally left blank. Description of SPLASH Model Overview of SPLASH Model The Simulation Program for Long-term Analysis of System Hydraulics (SPLASH)

More information

Submission to the Economic Regulation Authority

Submission to the Economic Regulation Authority Submission to the Economic Regulation Authority APPROVAL OF NEW FACILITIES INVESTMENT Installation of a second 330/132 kv transformer at Kemerton Terminal and construction of a 132 kv transmission line

More information

From: Keith Casey, Vice President, Market and Infrastructure Development

From: Keith Casey, Vice President, Market and Infrastructure Development California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market and Infrastructure Development Date: August 18, 2011 Re: Briefing on Renewable

More information

MAINTAINING RELIABLE ELECTRICITY SUPPLY TO PORT LINCOLN

MAINTAINING RELIABLE ELECTRICITY SUPPLY TO PORT LINCOLN MAINTAINING RELIABLE ELECTRICITY SUPPLY TO PORT LINCOLN APPLICATION NOTICE (ABN 41 094 482 416) December 2007 COPYRIGHT ElectraNet - All Rights Reserved This document is protected by copyright vested in

More information

REVIEW OF POWER SYSTEM EXPANSION PLANNING IN VIETNAM

REVIEW OF POWER SYSTEM EXPANSION PLANNING IN VIETNAM Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized REVIEW OF POWER SYSTEM EXPANSION PLANNING IN VIETNAM Tasks 1 and 2 Report Prepared for

More information

4 Calculation of Demand Curve Parameters

4 Calculation of Demand Curve Parameters 4 Calculation of Demand Curve Parameters This section addresses the demand curve for the Alberta capacity market, including the calculations for the components of the demand curve. 4.1 Resource adequacy

More information

Electricity Market Modelling of Network Investments: Comparison of Zonal and Nodal Approaches

Electricity Market Modelling of Network Investments: Comparison of Zonal and Nodal Approaches Electricity Market Modelling of Network Investments: Comparison of Zonal and Nodal Approaches Sadhvi Ganga 1,3 Iain Ferguson MacGill 1,2 School of Electrical Engineering and Telecommunications, University

More information

Appendix 3.1: The Need for a Second North South Electricity Interconnector. A4 appendix.indd 4 25/05/ :59

Appendix 3.1: The Need for a Second North South Electricity Interconnector. A4 appendix.indd 4 25/05/ :59 Appendix 3.1: The Need for a Second North South Electricity Interconnector A4 appendix.indd 4 25/05/2015 13:59 North-South 400kV Interconnection Development The Need for a second North-South Electricity

More information

Lower Mornington Peninsula Supply Area

Lower Mornington Peninsula Supply Area Non Network Options Report RIT-D Report This report presents the sub-transmission network limitations in the lower Mornington Peninsula including options and technical characteristics of non-network options

More information

South Australia Energy Transformation

South Australia Energy Transformation South Australia Energy Transformation RIT-T Project Assessment Draft Report Summary ElectraNet has investigated interconnector and network support options aimed at reducing the cost of providing secure

More information

1.3 Planning Assumptions and Model Development

1.3 Planning Assumptions and Model Development Section 1: Process Overview In addition, projects that originate through local Transmission Owner planning will be posted on the PJM web site. This site will include all currently planned transmission

More information

Submission to the Electricity Authority

Submission to the Electricity Authority pwc.co.nz Submission to the Electricity Authority on Transmission Pricing Methodology: Avoided cost of transmission (ACOT) payments for distribution generation Made on behalf of 22 Electricity Distribution

More information

A SUPPORTING DOCUMENT TO OUR 2015 INTEGRATED TRANSMISSION PLAN SERVICES REPORT 2015

A SUPPORTING DOCUMENT TO OUR 2015 INTEGRATED TRANSMISSION PLAN SERVICES REPORT 2015 A SUPPORTING DOCUMENT TO OUR 2015 INTEGRATED TRANSMISSION PLAN SERVICES REPORT 2015 Services Report September 2015 ii TABLE OF CONTENTS 1. INTRODUCTION... 1 1.1. Purpose... 1 1.2. Services covered by this

More information

Addressing reliability requirements in the Flemington substation load area

Addressing reliability requirements in the Flemington substation load area Addressing reliability requirements in the Flemington substation load area Notice on screening for non-network options May 2018 Title of Contents DISCLAIMER... 1 1 INTRODUCTION... 2 2 FORECAST LOAD AND

More information

Roadmaps for Demand Response & Storage

Roadmaps for Demand Response & Storage 1 Roadmaps for Demand Response & Storage Jim Price, California ISO Senior Advisor, Market Development & Analysis jprice@caiso.com PSERC Summer Planning Workshop Market Stem July 15, 2015 CAISO markets

More information

INTEGRATION OF RENEWABLE BASED GENERATION INTO SRI LANKAN GRID

INTEGRATION OF RENEWABLE BASED GENERATION INTO SRI LANKAN GRID CEYLON ELECTRICITY BOARD INTEGRATION OF RENEWABLE BASED GENERATION INTO SRI LANKAN GRID 2018-2028 Dr. H.M Wijekoon Chief Engineer (Transmission Planning) Randika Wijekoon Electrical Engineer (Generation

More information

PJM White Paper. Transource Independence Energy Connection Market Efficiency Project

PJM White Paper. Transource Independence Energy Connection Market Efficiency Project PJM White Paper PJM Interconnection November 15, 2018 This page is intentionally left blank. PJM 2018 www.pjm.com i P a g e Contents Highlights... 1 Executive Summary... 1 I. Introduction... 2 Reliability

More information

PRELIMINARY REVENUE PROPOSAL

PRELIMINARY REVENUE PROPOSAL PRELIMINARY REVENUE PROPOSAL 2019-2023 ElectraNet // September 2016 Preliminary Revenue Proposal 2019-2023 // Page 2 This Preliminary Revenue Proposal is intended to promote effective early engagement

More information

Appendix 1 PRELIMINARY DELIVERABILITY BASELINE ANALYSIS STUDY REPORT

Appendix 1 PRELIMINARY DELIVERABILITY BASELINE ANALYSIS STUDY REPORT Generation and Import Deliverability to the Aggregate of Load (Baseline) Study Methodology Executive Summary Deliverability is an essential element of any resource adequacy requirement. Specifically, Load

More information

Emergency Management Policy

Emergency Management Policy Emergency Management Policy Effective from 19 June 2016 1. Background 1.1 This Policy is the emergency management policy, which the system operator is required to prepare and publish under clause 7.3(3)

More information

ASSOCIATED NERC STANDARD(S): TPL (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved.

ASSOCIATED NERC STANDARD(S): TPL (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved. ASSOCIATED NERC STANDARD(S): TPL-001-4 (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved. Phase in of individual TPL-001 requirements will be based on the effective dates

More information

Transmission Pricing Methodology: CBA

Transmission Pricing Methodology: CBA pwc.co.nz on Transmission Pricing Methodology: CBA Made on behalf of 22 Electricity Distribution Businesses PwC Submission on behalf of 22 EDBs 15 October 2013 Glossary i Submission on Transmission Pricing

More information

Commerce Committee additional questions /12 financial review of Mighty River Power

Commerce Committee additional questions /12 financial review of Mighty River Power Commerce Committee additional questions 1-18 2011/12 financial review of Mighty River Power 1. Has Mighty River Power increased or reduced its power prices due to the Emissions Trading Scheme or changes

More information

recent Input Methodologies (IM's) Review Forum held on July 2015 and present a major user perspective on our experience of the current DPP.

recent Input Methodologies (IM's) Review Forum held on July 2015 and present a major user perspective on our experience of the current DPP. 21 August 2015 Commerce Commission (via email to Keston.ruxton@comcom.govt.nz)) Dear Keston, Re: Input Methodologies Review 1. This submission is made on behalf of the Major Gas Users Group (MGUG): a.

More information

ECONOMIC ANALYSIS. B. Calculation of Economic Internal Rate of Return, Risk Assessment, and Sensitivity Analysis

ECONOMIC ANALYSIS. B. Calculation of Economic Internal Rate of Return, Risk Assessment, and Sensitivity Analysis Sustainable Power Sector Support Project (RRP SRI 39415) ECONOMIC ANALYSIS A. Background and Approach 1. The analysis was undertaken to determine the economic viability of the project components. The analysis

More information

EVALUATION REPORT RFP-ER 005/06

EVALUATION REPORT RFP-ER 005/06 EVALUATION REPORT RFP-ER 005/06 On reinforcement options to address projected network constraints described in RFP 005/06 Projected Distribution Network constraints: Electricity Supply to the Wudinna to

More information

Kintyre Hunterston Link. The upgrade of grid access in Kintyre

Kintyre Hunterston Link. The upgrade of grid access in Kintyre The upgrade of grid access in Kintyre About us Scottish Hydro Electric Transmission plc (SHE Transmission), part of Scottish and Southern Energy Power Distribution (SSEPD), is the licensed electricity

More information

JULY 2015 INITIATIVES PLAN FOR REGULATED TRANSMISSION SERVICES

JULY 2015 INITIATIVES PLAN FOR REGULATED TRANSMISSION SERVICES JULY 2015 INITIATIVES PLAN FOR REGULATED TRANSMISSION SERVICES TABLE OF CONTENTS 1. INTRODUCTION... 3 1.1 Services Covered by the Initiatives Plan... 3 1.2 Activities Covered by the Initiatives Plan...

More information

Flexibility in the Swiss Electricity Markets. Jan Abrell Energieforschungsgespräche Disentis 2019,

Flexibility in the Swiss Electricity Markets. Jan Abrell Energieforschungsgespräche Disentis 2019, Flexibility in the Swiss Electricity Markets Jan Abrell Energieforschungsgespräche Disentis 2019, 24.01.2019 Motivation Share of renewable energy sources in electricity supply is increasing Wind and solar

More information

PROPOSED FCAS CALCULATION CHANGES IN TASMANIA

PROPOSED FCAS CALCULATION CHANGES IN TASMANIA PROPOSED FCAS CALCULATION CHANGES IN TASMANIA FOR THE NATIONAL ELECTRICITY MARKET PUBLISHED JUNE 2014 IMPORTANT NOTICE IMPORTANT NOTICE Purpose AEMO has prepared this document to provide information to

More information

AESO System Operating Limits Methodology for the Planning Horizon (R1 FAC-010-AB-2.1)

AESO System Operating Limits Methodology for the Planning Horizon (R1 FAC-010-AB-2.1) (R1 FAC-010-AB-2.1) 1 Purpose This document sets out the System Operating Limits Methodology the Alberta Electric System Operator ( AESO ) uses for any studies conducted on the interconnected electric

More information

18/05/2018. Mr John Pierce Chair Australian Energy Market Commission PO Box A2449 Sydney NSW Lodged online via:

18/05/2018. Mr John Pierce Chair Australian Energy Market Commission PO Box A2449 Sydney NSW Lodged online via: ABN 70 250 995 390 180 Thomas Street, Sydney PO Box A1000 Sydney South NSW 1235 Australia T (02) 9284 3000 F (02) 9284 3456 18/05/2018 Mr John Pierce Chair Australian Energy Market Commission PO Box A2449

More information

1.818J/2.65J/3.564J/10.391J/11.371J/22.811J/ESD166J SUSTAINABLE ENERGY

1.818J/2.65J/3.564J/10.391J/11.371J/22.811J/ESD166J SUSTAINABLE ENERGY 1.818J/2.65J/3.564J/10.391J/11.371J/22.811J/ESD166J SUSTAINABLE ENERGY Prof. Michael W. Golay Nuclear Engineering Dept. 1 Energy Supply, Demand, and Storage Planning The Example of Electricity PRESENTATION

More information

PLANNING FOR TODAY, TOMORROW, AND THE FUTURE. P. 1

PLANNING FOR TODAY, TOMORROW, AND THE FUTURE. P. 1 PLANNING FOR TODAY, TOMORROW, AND THE FUTURE. P. 1 P. 2 RELIABILITY AND RESOURCE PLANNING Hydro s 2018 Reliability and Resource Adequacy Study addresses our long-term approach to providing continued least-cost,

More information

Rule Change Notice: Removal of constrained off compensation for Outages of network equipment (RC_2018_07)

Rule Change Notice: Removal of constrained off compensation for Outages of network equipment (RC_2018_07) Rule Change Notice: Removal of constrained off compensation for Outages of network equipment (RC_2018_07) This notice is given under clause 2.5.7 of the Wholesale Electricity Market Rules (Market Rules).

More information

The Future of Electricity Generation in New Zealand

The Future of Electricity Generation in New Zealand The Future of Electricity Generation in New Zealand Phil Bishop New Zealand Electricity Commission, PO Box 141 Wellington 6143 Ph (4) 46 886, e-mail: phil.bishop@electricitycommission.govt.nz Brian Bull

More information

Dispatch Signal & Locational Marginal Pricing (LMP)

Dispatch Signal & Locational Marginal Pricing (LMP) Dispatch Signal & Locational Marginal Pricing (LMP) PJM State & Member Training Dept. PJM 2017 Objectives Students will be able to: Identify how PJM dispatches & utilizes LMP PJM 2017 2 Dispatch Rate Definition:

More information

Response to I-SEM DS3 System Services Auction Design Consultation Paper SEM

Response to I-SEM DS3 System Services Auction Design Consultation Paper SEM Response to I-SEM DS3 System Services Auction Design Consultation Paper SEM-15-105 22 nd December 2015 On behalf of AES Kilroot Power Ltd and AES Ballylumford Ltd 12 th February 2016 DS3 Auction Design

More information

Capacity reserves until 2025: declining, but sufficient

Capacity reserves until 2025: declining, but sufficient 1 Capacity reserves until 2025: declining, but sufficient Trends from ENTSO-E s Scenario Outlook & Adequacy Forecast 2015 Once a year, ENTSO-E 1 publishes a Scenario Outlook & Adequacy Forecast (SO&AF).

More information

Carbon abatement effects of electricity demand reductions

Carbon abatement effects of electricity demand reductions Carbon abatement effects of electricity demand reductions Ted Jamieson Ministry for the Environment November 2007 728966 1 Foreword If we reduce the demand for electricity in New Zealand, how much of a

More information

CAISO Generator Deliverability Assessment Methodology. On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes)

CAISO Generator Deliverability Assessment Methodology. On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes) Background On-Peak Deliverability Assessment Methodology (for Resource Adequacy Purposes) The CAISO s deliverability study methodology for resource adequacy purposes was discussed extensively in the CPUC

More information

System Management Standard. System Restart Services. (System Restart Standard)

System Management Standard. System Restart Services. (System Restart Standard) System Management System Management Standard System Restart Services (System Restart Standard) This Standard is a guide to the acquisition of System Restart Services. 1 October 2014 Table of contents 1.

More information

REPORT ON CONSULTATION ON DRAFT TRANSMISSION DEVELOPMENT PLAN

REPORT ON CONSULTATION ON DRAFT TRANSMISSION DEVELOPMENT PLAN REPORT ON CONSULTATION ON DRAFT TRANSMISSION DEVELOPMENT PLAN 2016-2026 Table of Contents Abbreviations... 3 Glossary... 4 Introduction... 5 Description of Consultation Process... 5 Purpose of the Transmission

More information

Support continued transparency for policy and design choices

Support continued transparency for policy and design choices Transpower House 96 The Terrace PO Box 1021, Wellington New Zealand www.transpower.co.nz Catherine.jones@transpower.co.nz 04 590 8624 / 027 5646976 10 October 2017 John Rampton General Manager Market Design

More information

MODELLING THE MARKET IMPACT OF BATTERY STORAGE IN ASIA-PACIFIC ELECTRICITY MARKETS

MODELLING THE MARKET IMPACT OF BATTERY STORAGE IN ASIA-PACIFIC ELECTRICITY MARKETS MODELLING THE MARKET IMPACT OF BATTERY STORAGE IN ASIA-PACIFIC ELECTRICITY MARKETS DISCLAIMER THIS PAPER HAS BEEN PREPARED BASED ON OUR PROFESSIONAL EXPERIENCE AND INFORMATION WHICH IS AVAILABLE IN THE

More information

Electronic Dispatch Facility Enhancement Project. Service Enhancement Consultation Information. October 2016

Electronic Dispatch Facility Enhancement Project. Service Enhancement Consultation Information. October 2016 Electronic Dispatch Facility Enhancement Project Service Enhancement Consultation Information October 2016 IMPORTANT Disclaimer The information in this document is provided in good-faith and represents

More information

Platte River Power Authority. Ten-Year Transmission Plan ( )

Platte River Power Authority. Ten-Year Transmission Plan ( ) Platte River Power Authority Ten-Year Transmission Plan (2015-2024) Prepared by PRPA System Planning December 31, 2014 Table of Contents I. Executive Summary II. III. IV. Scope Assumptions Criteria V.

More information

Busbar Classification Review

Busbar Classification Review Busbar Classification Review Updated Credible Methodology and Trial Results Transpower New Zealand Limited February 2017 Version Date Change 1 01/02/2017 Pubilshed for feedback IMPORTANT Disclaimer The

More information

Assessment of the Impact of Flow Alterations on Electricity Generation

Assessment of the Impact of Flow Alterations on Electricity Generation Assessment of the Impact of Flow Alterations on Electricity Generation For The Ministry for the Environment and Ministry for Primary Industries 13 th March 2015 Energy Modeling Consultants Ltd Tom Halliburton

More information

The Marginal Effects of the Price for Carbon Dioxide: Quantifying the Effects on the Market for Electric Generation in Florida

The Marginal Effects of the Price for Carbon Dioxide: Quantifying the Effects on the Market for Electric Generation in Florida The Marginal Effects of the Price for Carbon Dioxide: Quantifying the Effects on the Market for Electric Generation in Florida Theodore J. Kury Director of Energy Studies Public Utility Research Center

More information

Sharing. Andy Wainwright National Grid

Sharing. Andy Wainwright National Grid Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. Andy Wainwright National Grid Sharing under

More information

EVALUATION OF MIDWEST ISO INJECTION/WITHDRAWAL TRANSMISSION COST ALLOCATION DESIGN. Prepared by Scott Harvey and Susan Pope

EVALUATION OF MIDWEST ISO INJECTION/WITHDRAWAL TRANSMISSION COST ALLOCATION DESIGN. Prepared by Scott Harvey and Susan Pope EVALUATION OF MIDWEST ISO INJECTION/WITHDRAWAL TRANSMISSION COST ALLOCATION DESIGN Prepared by Scott Harvey and Susan Pope March 5, 2010 (Updated April 15, 2010) 1 TABLE OF CONTENTS I. Introduction...

More information

Electricity trading and transmission arrangements. Towards better electricity trading and transmission arrangements

Electricity trading and transmission arrangements. Towards better electricity trading and transmission arrangements Agenda Advancing economics in business Electricity trading and transmission arrangements Towards better electricity trading and transmission arrangements The UK is facing the significant challenge of integrating

More information

Eastland Network Limited. Pricing Methodology Disclosure

Eastland Network Limited. Pricing Methodology Disclosure Eastland Network Limited Pricing Methodology Disclosure Pursuant to: Requirements 22 and 23 of the Electricity Information Disclosure Requirements 2004 For Line Charges introduced on 31 March 2011 April

More information

SOUTH AUSTRALIA VICTORIA (HEYWOOD) INTERCONNECTOR UPGRADE

SOUTH AUSTRALIA VICTORIA (HEYWOOD) INTERCONNECTOR UPGRADE 26 October 2012 Hugo Klingenberg Senior Manager Network Development Electranet Pty Ltd consultation@electranet.com.au Ashley Lloyd Senior Manager Victorian Planning Australian Energy Market Operator planning@aemo.com.au

More information

Paper for TRANSPORT WORKING GROUP. Part F: Plain English Guide and Examples DRAFT. July 2002

Paper for TRANSPORT WORKING GROUP. Part F: Plain English Guide and Examples DRAFT. July 2002 Paper for TRANSPORT WORKING GROUP Part F: Plain English Guide and Examples DRAFT July 2002 Prepared by Transpower 1 PART F: PLAIN ENGLISH GUIDE INTRODUCTION On 7 December 2000, the Government announced

More information

STATE OF ILLINOIS ILLINOIS COMMERCE COMMISSION

STATE OF ILLINOIS ILLINOIS COMMERCE COMMISSION STATE OF ILLINOIS ILLINOIS COMMERCE COMMISSION Rock Island Clean Line LLC ) ) Petition for an Order granting Rock Island ) Clean Line a Certificate of Public Convenience ) and Necessity pursuant to Section

More information

Joanne Flynn David Cormie NFAT Technical Conference July 15, 2013

Joanne Flynn David Cormie NFAT Technical Conference July 15, 2013 Joanne Flynn David Cormie NFAT Technical Conference July 15, 2013 1 Who is MISO? Midwest Independent Transmission System Operator, Inc. Changing name to the Midcontinent t Independent d tsystem Operator,

More information

CONSULTATION PAPER: TRANSMISSION PRICING. November 2013

CONSULTATION PAPER: TRANSMISSION PRICING. November 2013 CONSULTATION PAPER: TRANSMISSION PRICING November 2013 Table of Contents Overview and Introduction... 3 1. Background and Purpose... 4 2. Transmission Pricing Objectives and Principles... 6 2.1 Introduction

More information

Re: RIT-T Market Modelling, high level review. Introduction & background. June Mr R Korte, Executive Manager Asset Management

Re: RIT-T Market Modelling, high level review. Introduction & background. June Mr R Korte, Executive Manager Asset Management Oakley Greenwood Pty Ltd 2/20 Baynes Street Margate Beach QLD 4019 PO Box 125 Margate Beach QLD 4019 Phone +617 3283 3249 Fax +617 3112 5068 June 2018 Mr R Korte, Executive Manager Asset Management ElectraNet

More information

APPENDIX I PLANNING RESERVE MARGIN STUDY

APPENDIX I PLANNING RESERVE MARGIN STUDY APPENDIX I PLANNING RESERVE MARGIN STUDY Introduction The planning reserve margin (), measured as a percentage of coincident system peak load, is a parameter used in resource planning to ensure there are

More information

Approaches to Generation Dispatch in Transmission Planning

Approaches to Generation Dispatch in Transmission Planning 21, rue d Artois, F-75008 PARIS Paper 135 GUILIN 2009 Approaches to Generation Dispatch in Transmission Planning P. J. PALERMO KEMA, Inc. USA SUMMARY A critical factor affecting transmission system development

More information

South Australia Energy Transformation (Riverlink) RIT-T Total Environment Centre Submission

South Australia Energy Transformation (Riverlink) RIT-T Total Environment Centre Submission South Australia Energy Transformation (Riverlink) RIT-T Total Environment Centre Submission 31 August 2018 1/99 Devonshire Street, Surry Hills, NSW 2010 Ph: 02 9211 5022 Fax: 02 9211 5033 www.tec.org.au

More information

MARKET EFFICIENCY STUDY PROCESS AND PROJECT EVALUATION TRAINING

MARKET EFFICIENCY STUDY PROCESS AND PROJECT EVALUATION TRAINING MARKET EFFICIENCY STUDY PROCESS AND PROJECT EVALUATION TRAINING December 22, 2014 Training Objectives To Provide an Overview of: The Market Efficiency proposal window process The critical modeling inputs

More information

Transmission System Capability and the Decision to Abolish the Snowy Region

Transmission System Capability and the Decision to Abolish the Snowy Region 9 October 2007 Issue 008 Transmission System Capability and the Decision to Abolish the Snowy Region By Andrew Campbell, Stephen Wallace and Stuart Thorncraft Preamble With the recent decision to abolish

More information

Recommended Values for I-SEM Scheduling and Dispatch Parameters

Recommended Values for I-SEM Scheduling and Dispatch Parameters Recommended Values for I-SEM Scheduling and Dispatch Parameters Report to the Regulatory Authorities Version 1.0 10/05/2017 2017 EirGrid plc. Contents 1. SEM Committee Policy and Trading & Settlement Code

More information

PJM Analysis of the EPA Clean Power Plan

PJM Analysis of the EPA Clean Power Plan PJM Analysis of the EPA Clean Power Plan PJM Interconnection October 6, 2016 PJM CPP Study Objectives Evaluate potential impacts to: Resource adequacy Transmission system operations PJM energy and capacity

More information

NETWORK CONTROL ANCILLARY SERVICE QUANTITY PROCEDURE

NETWORK CONTROL ANCILLARY SERVICE QUANTITY PROCEDURE NETWORK CONTROL ANCILLARY SERVICE QUANTITY PROCEDURE PREPARED BY: Electricity System Operations Planning and Performance DOCUMENT NO: 1.0 VERSION NO: 1.0 FINAL (Updated in July 2009 to reflect NEMMCO s

More information

NYISO s Integrating Public Policy Project

NYISO s Integrating Public Policy Project NYISO s Integrating Public Policy Project Phase 2: Study Description and Assumption Review Dr. Nicole Bouchez & Mike Swider MIWG Krey Blvd, Rensselaer February 16, 2017 2000-2017 New York Independent System

More information

AEMO RIT-T on Western Victoria Renewable Integration Network options study

AEMO RIT-T on Western Victoria Renewable Integration Network options study AEMO RIT-T on Western Victoria Renewable Integration Network options study Network Planning Group This issue Revision 0 Pages this issue 66 Author Reviewed Approved Joseph Leung, Senior Electrical Engineer

More information

The PRISM model. Simulating the future. of the New Zealand electricity sector. Dr. Geoffrey Pritchard. University of Auckland

The PRISM model. Simulating the future. of the New Zealand electricity sector. Dr. Geoffrey Pritchard. University of Auckland The PRISM model Simulating the future of the New Zealand electricity sector Dr. Geoffrey Pritchard University of Auckland 0 Aims Produce some self-consistent snapshots of the NZ electricity sector, representing

More information

Demand Side Engagement Strategy. Version 2.0 Effective Date: 08/02/18

Demand Side Engagement Strategy. Version 2.0 Effective Date: 08/02/18 Demand Side Engagement Strategy Version 2.0 Effective Date: 08/02/18 Document management Version control Date Version Description Author 16/07/2013 0.1 Initial Draft. Y. Jayathilaka 23/07/2013 0.2 Revised

More information

Alberta Capacity Market

Alberta Capacity Market Alberta Capacity Market Comprehensive Market Design (CMD 1) Design Proposal Document Section 3: Calculation of Capacity Market Demand Parameters Prepared by: Alberta Electric System Operator Date: January

More information

GSR016: Small and Medium Embedded Generation Assumptions

GSR016: Small and Medium Embedded Generation Assumptions Stage 01: Workgroup National Electricity Transmission System Security and Quality of Supply Standards (NETS SQSS) GSR016: Small and Medium Embedded Generation Assumptions 01 02 03 Workgroup Industry Consultation

More information

Chapter 3: The Scheduling & Chapter 4: The Scheduling and Dispatch Process

Chapter 3: The Scheduling & Chapter 4: The Scheduling and Dispatch Process Chapter 3: The Scheduling & Chapter 4: The Scheduling and Dispatch Process 1 Foreword Our scheduling and dispatch process incorporates a range of activities associated with managing the close to real-time

More information

Nova Scotia Power System Operator (NSPSO)

Nova Scotia Power System Operator (NSPSO) Nova Scotia Power System Operator (NSPSO) Market Procedure MP-09 Outage Planning and Approval Effective Date: 2008 12 31 Wholesale Market Procedure MP-09 Table of Contents Page 1 Document Control and General

More information

Embedded generation and gross demand analysis. July 2016

Embedded generation and gross demand analysis. July 2016 Embedded generation and gross demand analysis July 2016 2 Outline Transpower requested us to: Analyse half-hourly generation data provided by the Reconciliation Manager (RM) to provide an indication on

More information

National Transmission Network Development Plan AEMO Consultation Paper

National Transmission Network Development Plan AEMO Consultation Paper 16 March 2011 Ms Natalie Bakas Project Manager AEMO Level 22, 530 Collins St MELBOURNE VIC 3000 Email: planning@aemo.com.au Dear Ms Bakas National Transmission Network Development Plan AEMO Consultation

More information