Lessons Learned from Fukushima-Daiichi Accident (Safety Measures and PSA Utilization)

Size: px
Start display at page:

Download "Lessons Learned from Fukushima-Daiichi Accident (Safety Measures and PSA Utilization)"

Transcription

1 PSAM Tokyo Lessons Learned from Fukushima-Daiichi Accident (Safety Measures and PSA Utilization) April 15, 2013 Akio Komori (Takafumi Anegewa) Tokyo Electric Power Company All Rights Reserved 2013The Tokyo Electric Power Company, Inc. 0

2 1. PRA application before Fukushima-daiich accident 2. Key findings of Fukushima-daiich accident regarding earthquake and tsunami 3. The change of design philosophy in TEPCO after Fukushima-daiichi accident 4. Practical and effective PRA utilization for external events All Rights Reserved 2013The Tokyo Electric Power Company, Inc. 1

3 1.1 Risk assessment before 1F accident - Internal events Chronology 1979 TMI accident 1986 Chernobyl accident 1992 Regulatory request of Accident Management (AM) development 1994 AM review report 1997 Implementation of PRA to PSR 2002 Effectiveness evaluation report of AM measures Activities in TEPCO 1Deterministic approach Safety measures based on deterministic safety assessment 2PRA introduction Preparations for internal events PRA approach Development of AM measures 3PRA application PRA for Periodic Safety Review (PSR) Effectiveness evaluation report of AM measures Risk monitor All Rights Reserved 2013The Tokyo Electric Power Company, Inc. 2

4 1.2 Accident Management Measures applied in 90 s Basic concept: Utilize existing systems and components as much as possible. Function Shutdown Water injection Heat removal Electric power supply AM measures Alternate reactivity control (Recirculation Pump Trip and Alternate Rod Insertion) Alternate water injection to RPV and PCV (through Make Up Water Condensation System and Fire Protection System) Automatic Depressurization System Alternate Heat Removal PCV Hardened Vent Addition EDG Alternate power source(480v) cross-tied from adjacent units All Rights Reserved 2013The Tokyo Electric Power Company, Inc. 3

5 1.3 PRA evaluation of AM effectiveness Reduction Core Damage Frequency is around 70 %. reference:effectiveness evaluation report of AM measures(2002) 1.00E % % 1.00E+01 10% % Enhancement of depressurization function Before the development of AM measures After the development of AM measures Enhancement of power supply Enhancement of shutdown function 1% 1.00E+00 % 1.00E % % 0.01% 1.00E-02 % TQUX LOCA TQUV TB TW TC Total Enhancement of water injection function Enhancement of heat removal function example of 1F Unit 2 All Rights Reserved 2013The Tokyo Electric Power Company, Inc. 4

6 1.4 Risk assessment before the 1F accident - External events Chronology 1978 Establishment of Reg. Guide for Reviewing Seismic Design 2002 Establishment of JSCE method 2006 Revision of Reg. Guide 2007 Niigata-Chuetsu-Oki Earthquake 2007 Establishment of Standard for Seismic PRA Procedures 1 2 Activities in TEPCO 1Deterministic approach Design based on historical record 180gal seismic acceleration 3.1m Tsunami height based on 1960 Chili tsunami Seismic back-check based on the guide ( gal) Tsunami re-assessment based on JSCE (Japan Society of Civil Engineers) method Seismic back-check based on the revised Reg. Guide( gal) Reflection of lessons learned 2PRA introduction Start of residual risk assessment All Rights Reserved 2013The Tokyo Electric Power Company, Inc. 5

7 1.5 Revision of seismic evaluation and safety measures Continuous enhancement of seismic durability of SSCs. the Regulatory Guide for Reviewing Seismic Design of Nuclear Power Reactor Facilities has revised in 2006: Upgrade of evaluation method of seismic acceleration (Introduction of Ss) Quantification of residual risk of FP release and exposure to the public Start of back-check of seismic resistance Submittal of the Interim report between 2008 and 2009 (Increase seismic resistant margin) Evaluation of seismic PRA was started as residual risk evaluation since seismic PRA standard was issued by AESJ (2007) Niigata- Chuetsu-Oki Earthquake happened, and seismic acceleration exceeded previous assumption (2007) Implemented additional countermeasures Seismic isolated building for on site emergency response center Fire engines Inlets for alternate water injection line All Rights Reserved 2013The Tokyo Electric Power Company, Inc. 6

8 1.6 Tsunami height evaluation Tsunami height evaluation based on JSCE methods. Unit Tsunami Height m Design Basis (Chile tsunami) 2002 Tsunami source located off the coast of Miyagi Pref Tsunami source located off the coast of Fukushima Pref. Record of March 11th, F Maximum run up height: Maximum run up height: F Spent too much time to evaluate possibility of tsunami source existence. Limited effort had been done for tsunami measures. All Rights Reserved 2013The Tokyo Electric Power Company, Inc. 7

9 1.7 Seismic PRA procedure Seismic Hazard Analysis Probability of exceedance Seismic acceleration Reasonable hazard according to record Sequence analysis 1Frequency of earthquake based on hazard analysis 2Plant level fragility Seimic Fragility Analysis Accumulate damage frequency Sequence analysis Seismic acceleration Frequency 1 2 CDF Seismic acceleration All Rights Reserved 2013The Tokyo Electric Power Company, Inc. 8

10 1.8 Tsunami PRA procedure Probability of exceedance Accumulate damage frequency Hazard curve Tsunami Height (m) Sequence analysis Fragility Analysis Tsunami height Point :Hazard curve is correct? Different tsunami height due to location and scale of tsunami source Different tsunami height due to landform Different tsunami height in case of same scale of earthquake and tsunami Frequency Sequence analysis 1Frequency of Tsunami based on hazard analysis 2Plant level fragility All Rights Reserved 2013The Tokyo Electric Power Company, Inc CDF Tsunami height 1

11 1. PRA application before Fukushima-daiich accident 2. Key findings of Fukushima-daiich accident regarding earthquake and tsunami 3. The change of design philosophy in TEPCO after Fukushima-daiichi accident 4. Practical and effective PRA utilization for external events All Rights Reserved 2013The Tokyo Electric Power Company, Inc. 10

12 2.1 Deficiency in DID protection against external events Facts: Underestimate tsunami height for design base. Site level was not high enough to prevent inundation of tsunami as the 1 st layer of DID. Equipments as 3 rd,4 th barriers of DID layer were disabled by tsunami. (common cause failure mode) Lessons Learned: Necessary to enhance DID for external events Basic policy of safety enhancement: Define Design Extended Condition (DEC) for each DID functions physical barriers (1), shutdown (2), cooling (3), confinement (4) All Rights Reserved 2013The Tokyo Electric Power Company, Inc. 11

13 2.1 Inadequate high-pressure injection in SBO Facts: Isolation condenser in 1F1 didn t work well after Tsunami hit. Core melted down in 5 hours after scram High-pressure injection systems worked 3 days for 1F2 and one day for 1F3. Couldn t depressurize RPV and lined up alternative injection systems while RCIC & HPCI were operating. Lessons Learned: Necessary to enhance high pressure injection function which is very important after SBO. Basic policy of safety enhancement: Extend DB-SBO duration to 12hours and enhance high pressure injection functions All Rights Reserved 2013The Tokyo Electric Power Company, Inc. 12

14 2.3 Revision of design requirements for PCV Facts: 1F Unit 1,2,3 containment were breached by high temperature and pressure resulted from core damage, and radioactive materials were released. Design requirements of PCV as the 4 th barrier were not clearly defined. Original design requirements for PCV as a 3 rd layer were based on LOCA Lessons Learned: PCV designed based LOCA cannot withstand core meltdown condition. Basic policy of safety enhancement: Enhance the design requirements for PCV and related equipments as a 4th barrier of DID in melt through condition. All Rights Reserved 2013The Tokyo Electric Power Company, Inc. 13

15 2.4 Impact of the earthquake on isolation condenser in 1F1 PCV pressure after the earthquake was stable. Record of charts indicated pressure boundary integrity. RPV pressure after the earthquake responded properly following IC operation. Isolation Condenser worked well. No damage due to the earthquake were found on safety features of R/B of 1F5 and 1F6 by walk down inspection. No damage due to the earthquake were found on any equipments in T/B of 1F1, 1F2 and 1F3. All Rights Reserved 2013The Tokyo Electric Power Company, Inc. 14

16 2.5 Recorded charts of 1F1 * (Mpa) RPV Pressure 1 Scram by the earthquake at 14:46 2 Pressure increase due to MSIV closed 3 Depressuring due to IC operation at 14:52 4 Pressure increase due to IC shut down 5 Pressure change due to IC operation (assumed) * The recorder may have stopped due to the tsunami PCV Pressure 8 10 (kpa) All Rights Reserved 2013The Tokyo Electric Power Company, Inc. 15

17 2.6 Field investigation around Isolation Condenser in 1F1 No damage on main tanks, piping, flange, valve of 1F1 IC. 1 Hydrogen recombiner of FCS device and tube 2 Ventilation duct and flooding protection chamber: connect with SFP wall 3 IC vent line:small diameter tube(3/4inch) included high temperature steam 4 Conduit All Rights Reserved 2013The Tokyo Electric Power Company, Inc. 16

18 1. PRA application before Fukushima-daiich accident 2. Key findings of Fukushima-daiich accident regarding earthquake and tsunami 3. The change of design philosophy in TEPCO after Fukushima-daiichi accident 4. Practical and effective PRA utilization for external events All Rights Reserved 2013The Tokyo Electric Power Company, Inc. 17

19 3.1 DID enhancement policy Tsunami destroyed 1 st & 3 rd barriers of DID completely. necessary to enhance each layers of DID Necessary to use Design Extended Condition (DEC) for each DID layer in order to consider safety enhancement measures. To cope with tangled and complex Beyond DBE condition, DEC design requirements should promote diversity and flexible measures. In order to enhance the reliability of high pressure injection and RPV depressurization function, SBO should be treated as design base, then single failure criteria should be applied. All Rights Reserved 2013The Tokyo Electric Power Company, Inc. 18

20 3.2 Measures in each DID layer for Tsunami Levels of DID Purpose (Important Function) 1 st Prevention of occurrence of anomaly (Physical barrier) 2 nd Prevention of escalation of anomaly (Shutdown) Prevention of core 3 rd damage (Cooling) Mitigation of accident 4 th after core damage (Confinement) Design Base Site elevation, Embankment, Tidal wall, Tidal board No additional system [Cooling] - additional high pressure water injection system besides RCIC - increase DC battery capacity for RCIC [Depressurization] No additional system Design Requirement DEC(promote diversity & flexibility) - Water tight doors to limit water inundation to significant areas - Water discharge pump at safety significant areas No additional system [Cooling] - portable DC battery for RCIC -CUW and MUWC enable by power supply vehicle -fire engine, Diesel Driven pump, Movable heat exchanger, hardened w/w vent, filter vent (before core damage) [Depressurization] - dedicated DC battery for SRVs - increase N2 capacity and pressure - compressor - additional diverse depressurization method - substitute spray, pedestal water injection, top head flange cooling - filter vent (after core damage) Originally defined as DEC - passive hydrogen recombine system in reactor building Newly added as DEC All Rights Reserved 2013The Tokyo Electric Power Company, Inc. 19

21 3.3 Phased Approach for DID enhancement Design requirements for safety measures should be determined according to required time and available alternative equipments. Early phase: limited human resource and difficulty in the field access Later phase: difficulty in cope with only installed equipments due to complex situation Accident occurrence 12hrs 72hrs Support from off-site Response by portable equipments and AM Responses by installed equipments Complexity of accident progression [time] [Time margin: Small] - Installed equipments - Shift team [Time margin: Medium] - Portable equipments - On-site team [Time margin: Large] - Support from off-site - Off-site team All Rights Reserved 2013The Tokyo Electric Power Company, Inc. 20

22 3.4 1 st layer of defense in depth The flood by tsunami is prevented and the measure which protects power sources and other important apparatus is implemented. Tidal board Water-tight door Tidal wall Embankment : Preventing inundation of site Tidal wall : Preventing inundation of building Water-tight door : Preventing flooding of critical areas (~60 places) Spent Fuel Pool Start up Transformer (Low Voltage) Tidal board (under consideration) Emergency D/G, Power Supply panel Waterproof treatment at Cable trays Waterproof treatment at Pipes Waterproof treatment : Preventing flooding of critical areas (~ 300 places) All Rights Reserved 2013The Tokyo Electric Power Company, Inc. 21

23 3.5 3rd layer of defense in depth HP water injection Depressurization spare gas cylinder LP water infection and SFP cooling Fire engine Various power supply means GTG Turbine Water Lubricant pump Assure means of heat removal Power supply vehicle Charge DC power supply Emergency HV power supply panel Assure water sources Critical are a Alternative sea water heat ex. (deployed on high ground) Emergency HV power supply panel Water reservoir All Rights Reserved 2013The Tokyo Electric Power Company, Inc. 22

24 3.6 4th layer of defense in depth Preventing primary containment vessel damage Controlling hydrogen ~ 原子炉ウェル Reactor well Preventing release of radioactive materials Fire 消防車 engine R/B top vent Passive autocatalytic recombiner Top head flange cooling Hydrogen detector Filter venting All Rights Reserved 2013The Tokyo Electric Power Company, Inc. 23

25 1. PRA application before Fukushima-daiich accident 2. Key findings of Fukushima-daiich accident regarding earthquake and tsunami 3. The change of design philosophy in TEPCO after Fukushima-daiichi accident 4. Practical and effective PRA utilization for external events All Rights Reserved 2013The Tokyo Electric Power Company, Inc. 24

26 4.1 Effectiveness evaluation of countermeasures in 2F4 Core Damage Frequency (/y) 1.00E E E E E E E E-11 Before Tsunami measures Less then 1.0E-11 After Tsunami measures Around 10-3 /y decrease LOCA TB TQUV TQUX TW Total Water tight measures in Hx/B and R/B Enhancement of functions using alternative facility All Rights Reserved 2013The Tokyo Electric Power Company, Inc. 25

27 Conclusion Estimation of natural hazard has large uncertainty. Deficiency in DID protection caused Fukushima-daiichi accident. Elimination of cliff-edge effect is essential for external events. Each DID layer should have measures based on DEC. Diversity and flexibility are important for these measures. Effectiveness of safety measures can be evaluated using PRA. As 4 th layer DID measures, TEPCO adopts following measures even if PRA doesn t indicate reasonable cost vs. benefit results. Filtered venting system Passive Autocatalytic Recombiner All Rights Reserved 2013The Tokyo Electric Power Company, Inc. 26

28 Thank you for your attention All Rights Reserved 2013The Tokyo Electric Power Company, Inc. 27

Development of SAMG Verification and Validation for Kashiwazaki-Kariwa(KK) Nuclear Power Station

Development of SAMG Verification and Validation for Kashiwazaki-Kariwa(KK) Nuclear Power Station Development of SAMG Verification and Validation for Kashiwazaki-Kariwa(KK) Nuclear Power Station December 12-14, 2016 Toshinobu KITA TEPCO Holdings, Inc. Japan BWRs SAMG Development History 1 Original

More information

Lessons Learned from Fukushima Daiichi Nuclear Power Station Accident and Consequent Safety Improvements

Lessons Learned from Fukushima Daiichi Nuclear Power Station Accident and Consequent Safety Improvements Hitachi Review Vol. 62 (2013), No. 1 75 Lessons Learned from Fukushima Daiichi Nuclear Power Station Accident and Consequent Safety Improvements Masayoshi Matsuura Kohei Hisamochi Shinichiro Sato Kumiaki

More information

Overview of Fukushima accident. Nov. 9, 2011 Orland, Florida

Overview of Fukushima accident. Nov. 9, 2011 Orland, Florida Overview of Fukushima accident Nov. 9, 2011 Orland, Florida Nuclear Power Plants in Japan Japan Nuclear Japan Energy Nuclear Energy Safety Safety Organization Japan Atomic Industrial Forum, Inc. -Tohoku

More information

The Fukushima Daiichi Nuclear Power Station Accident

The Fukushima Daiichi Nuclear Power Station Accident The Fukushima Daiichi Nuclear Power Station Accident Tomomi Matsunaga Kansai Electric Power Company Cooperation with JEPIC (Japan an Electric Power Information Center) Nuclear Power Plants in Japan 2 1

More information

Fukushima Daiichi NPP Accident

Fukushima Daiichi NPP Accident Fukushima Daiichi NPP Accident Plant Design and Preliminary Observations K. Moriya and K. Sato Hitachi GE Nuclear Energy, Ltd. May 3, 2011 [Note] 1. The view expressed herein are not the official view

More information

Safety Enhancement of Nuclear Power Plant Post Fukushima. Kumiaki Moriya

Safety Enhancement of Nuclear Power Plant Post Fukushima. Kumiaki Moriya International Conference on Nuclear Governance Post-Fukushima Marina Bay Sands, Singapore, 31 October 2013 Safety Enhancement of Nuclear Power Plant Post Fukushima October 31,2013 Kumiaki Moriya Hitachi-GE

More information

TEPCO s Nuclear Power Plants suffered from big earthquake of March 11,2011

TEPCO s Nuclear Power Plants suffered from big earthquake of March 11,2011 TEPCO s Nuclear Power Plants suffered from big earthquake of March 11,2011 Follow up prepared at 4pm of March 23, revised 1pm of March 31 Yoshiaki Oka Waseda university Recovery action is in progress.

More information

Isolation Condenser; water evaporation in the tank and steam into the air. Atmosphere (in Severe Accident Management, both P/S and M/S)

Isolation Condenser; water evaporation in the tank and steam into the air. Atmosphere (in Severe Accident Management, both P/S and M/S) Loss of Ultimate Heat Sink ANS AESJ AESJ Fukushima Symposium, March h4, 2012 Hisashi Ninokata, Tokyo Institute of Technology Available ultimate heat sinks at 1F1~3 1F1 (Fukushima Dai ichi Unit 1) Sea water

More information

Regulatory Actions and Follow up Measures against Fukushima Accident in Korea

Regulatory Actions and Follow up Measures against Fukushima Accident in Korea Int Conference on Effective Nuclear Regulatory Systems, April 9, 2013, Canada Regulatory Actions and Follow up Measures against Fukushima Accident in Korea Seon Ho SONG* Korea Institute of Nuclear Safety

More information

TEPCO s Nuclear Power Plants suffered from big earthquake of March 11,2011

TEPCO s Nuclear Power Plants suffered from big earthquake of March 11,2011 TEPCO s Nuclear Power Plants suffered from big earthquake of March 11,2011 Follow up prepared at 4pm of March 23 in Japan Yoshiaki Oka Waseda university Recovery action is in progress. The presentation

More information

Overview of the Disaster Situation and the Restoration Condition at Fukushima Daini Nuclear Power Station

Overview of the Disaster Situation and the Restoration Condition at Fukushima Daini Nuclear Power Station Overview of the Disaster Situation and the Restoration Condition at Fukushima Daini Nuclear Power Station June 7, 2013 Fukushima Daini Nuclear Power Station 目的外使用 複製 開示禁止東京電力株式会社 0 The 2011 off the Pacific

More information

Fukushima Event PCTRAN Analysis. Dr. LI-Chi Cliff Po. Dr. LI-Chi Cliff Po. March 25, 2011

Fukushima Event PCTRAN Analysis. Dr. LI-Chi Cliff Po. Dr. LI-Chi Cliff Po. March 25, 2011 Fukushima Event PCTRAN Analysis Dr. LI-Chi Cliff Po Fukushima Event PCTRAN Analysis Dr. LI-Chi Cliff Po 1. Description of Event March 25, 2011 The earthquake caused instant loss of offsite power. The scale-9

More information

Comprehensive Safety Assessment for Kashiwazaki Kariwa NPS

Comprehensive Safety Assessment for Kashiwazaki Kariwa NPS Comprehensive Safety Assessment for Kashiwazaki Kariwa NPS International Experts Meeting on Reactor and Spent Fuel Safety in the Light of the Accident at the Fukushima Daiichi Nuclear Power Plant IAEA,

More information

New Safety Standards (SA) Outline (Draft) For Public Comment

New Safety Standards (SA) Outline (Draft) For Public Comment Provisional Translation (Feb.7,2013 Rev.0) February 6, 2013 New Safety Standards (SA) Outline (Draft) For Public Comment 0 February 6, 2013 New Safety Standards (SA) Outline (Draft) Table of Contents Foreword

More information

Preliminary Lessons Learned from the Fukushima Daiichi Accident for Advanced Nuclear Power Plant Technology Development

Preliminary Lessons Learned from the Fukushima Daiichi Accident for Advanced Nuclear Power Plant Technology Development Preliminary Lessons Learned from the Fukushima Daiichi Accident for Advanced Nuclear Power Plant Technology Development A. Introduction The IAEA Report on Reactor and Spent Fuel Safety in the Light of

More information

The 2011 Tohoku Pacific Earthquake and Current Status of Nuclear Power Stations

The 2011 Tohoku Pacific Earthquake and Current Status of Nuclear Power Stations The 2011 Tohoku Pacific Earthquake and Current Status of Nuclear Power Stations March 31, 2011 Tokyo Electric Power Company Tohoku Pacific Ocean Earthquake Time: 2:46 pm on Fri, March 11, 2011. Place:

More information

TEPCO s Nuclear Power Plants suffered from big earthquake of March 11,2011

TEPCO s Nuclear Power Plants suffered from big earthquake of March 11,2011 TEPCO s Nuclear Power Plants suffered from big earthquake of March 11,2011 Follow up prepared at 4pm of March 23, revised April 13 Yoshiaki Oka Waseda university Recovery action is in progress. The presentation

More information

A Study of Fukushima Nuclear Power Plant Accidents by the Viewpoint of PSA

A Study of Fukushima Nuclear Power Plant Accidents by the Viewpoint of PSA A Study of Fukushima Nuclear Power Plant Accidents by the Viewpoint of PSA Takeshi MATSUOKA (*) Utsunomiya University, 7-1-2 Yoto, Utsunomiya city, Tochigi pref. Japan 321-8585 mats@cc.utsunomiya-u.ac.jp

More information

Flow of Assessment. (1) Select events. (2) Select facilities. (3) Evaluate margins. (4) Identify cliff edge

Flow of Assessment. (1) Select events. (2) Select facilities. (3) Evaluate margins. (4) Identify cliff edge Mar. 2, 202 Comprehensive Assessment for the Safety of Units and 7 at Kashiwazaki-Kariwa Nuclear Station (Stress Tests) - Results of Primary Assessment and Safety Ensuring Measures Tokyo Electric Company

More information

Improvements Needed in Nuclear Power Plant Probabilistic Risk Assessments: Lessons Learned from Fukushima

Improvements Needed in Nuclear Power Plant Probabilistic Risk Assessments: Lessons Learned from Fukushima Improvements Needed in Nuclear Power Plant Probabilistic Risk Assessments: Lessons Learned from Fukushima Mohammad Modarres Professor of Nuclear Engineering Department of Mechanical Engineering University

More information

Recent Developments in Risk Assessment: Future Perspectives

Recent Developments in Risk Assessment: Future Perspectives Recent Developments in Risk Assessment: Future Perspectives Mohammad Modarres Minta Martin Professor of Engineering Director, Reliability Engineering Program Department of Mechanical Engineering University

More information

Severe Accident in Fukushima Dai ichi Nuclear Power Plant and Lessons Learned. October 14 th, 2015

Severe Accident in Fukushima Dai ichi Nuclear Power Plant and Lessons Learned. October 14 th, 2015 Severe Accident in Fukushima Dai ichi Nuclear Power Plant and Lessons Learned October 14 th, 2015 Akira Yamaguchi University of Tokyo, JAPAN E mail: yamaguchi@n.t.u tokyo.ac.jp 1 The Beginning The first

More information

Study on Severe Accident Progression and Source Terms in Fukushima Dai-ichi NPPs

Study on Severe Accident Progression and Source Terms in Fukushima Dai-ichi NPPs Study on Severe Accident Progression and Source Terms in Fukushima Dai-ichi NPPs October 27, 2014 H. Hoshi, R. Kojo, A. Hotta, M. Hirano Regulatory Standard and Research Department, Secretariat of Nuclear

More information

Post-Fukushima Actions in Korea

Post-Fukushima Actions in Korea Post-Fukushima Actions in Korea IAEA TWG-LWR Vienna, June 18-20, 2013 Presented by Jong-Tae Seo 1. Impacts on National Energy Policy and NPP Plan 2. Actions Taken after Fukushima Accident 3. Findings and

More information

Lessons Learned from the Fukushima Dai-ichi Accident and Responses in New Regulatory Requirements

Lessons Learned from the Fukushima Dai-ichi Accident and Responses in New Regulatory Requirements International Experts Meeting on Severe Accident Management in the Light of the Accident at the Fukushima Daiichi Nuclear Power Plant, Vienna, Austria March 17, 2014 Lessons Learned from the Fukushima

More information

IV. Occurrence and Development of the Accident at the Fukushima Nuclear Power Stations

IV. Occurrence and Development of the Accident at the Fukushima Nuclear Power Stations IV. Occurrence and Development of the Accident at the Fukushima Nuclear Power Stations 1. Outline of Fukushima Nuclear Power Stations (1) Fukushima Daiichi Nuclear Power Station Fukushima Daiichi Nuclear

More information

Wolsong-1 Stress Test

Wolsong-1 Stress Test PHWR Safety 2014/CANSAS-2014 Wolsong-1 Stress Test June 23, 2014 Geun-Sun Auh Korea Institute of Nuclear Safety Table of Contents 1. Stress Test Definition 2. EU Stress Test 3. Stress Test of Korea 4.

More information

Efforts for the restoration at Fukushima Daiichi Nuclear Power Plants

Efforts for the restoration at Fukushima Daiichi Nuclear Power Plants PF3-2013-000001 PSN-2013-0069 Efforts for the restoration at Fukushima Daiichi Nuclear Power Plants January 31, 2013 Executive Officer, Corporate Senior Vice president Chief Technology Executive, Power

More information

Stress tests specifications Proposal by the WENRA Task Force 21 April 2011

Stress tests specifications Proposal by the WENRA Task Force 21 April 2011 Stress tests specifications Proposal by the WENRA Task Force 21 April 2011 Introduction Considering the accident at the Fukushima nuclear power plant in Japan, the Council of the European Union declared

More information

Safety Implication for Gen-IV SFR based on the Lesson Learned from the Fukushima Dai-ichi NPPs Accident. Ryodai NAKAI Japan Atomic Energy Agency

Safety Implication for Gen-IV SFR based on the Lesson Learned from the Fukushima Dai-ichi NPPs Accident. Ryodai NAKAI Japan Atomic Energy Agency Safety Implication for Gen-IV SFR based on the Lesson Learned from the Fukushima Dai-ichi NPPs Accident Ryodai NAKAI Japan Atomic Energy Agency Contents Introduction Japanese Government Report to the IAEA

More information

Deconstructing the Nuclear Accident at the Fukushima-Daiichi Plant: What Went Wrong and What are the Prospects of Recovery?

Deconstructing the Nuclear Accident at the Fukushima-Daiichi Plant: What Went Wrong and What are the Prospects of Recovery? Deconstructing the Nuclear Accident at the Fukushima-Daiichi Plant: What Went Wrong and What are the Prospects of Recovery? Goldschmidt Conference 2011 Fukushima Review Session Prague, Czech Republic Edward

More information

The cause of RCIC shutdown in Unit 3

The cause of RCIC shutdown in Unit 3 Attachment 3-5 The cause of RCIC shutdown in Unit 3 1. Outline of the incident and issues to be examined Unit 3 experienced a station blackout when it was hit by tsunami on March 11 th, 2011, following

More information

Fukushima Daiichi Disaster. Facts and lessons learned. July Takashi Shoji Programme Director of WANO

Fukushima Daiichi Disaster. Facts and lessons learned. July Takashi Shoji Programme Director of WANO Fukushima Daiichi Disaster Facts and lessons learned July 13 2011 Takashi Shoji Programme Director of WANO 7/12/2011 1 Earthquake occurrence and automatic shut-down of nuclear reactors The Tohoku Pacific

More information

UK ABWR - NEW NPP DESIGN FOR UK

UK ABWR - NEW NPP DESIGN FOR UK IAEA PLiM2017 [IAEA-CN-246-085] UK ABWR - NEW NPP DESIGN FOR UK 25-October-2017 Kazuhiro YOSHIKAWA Masaaki HAYASHI Yasuhiro MABUCHI Daisuke TANIGUCHI Hitachi-GE Nuclear Energy, Ltd. Contents 1. Introduction

More information

STRESS TEST METHODOLOGY FOR NUCLEAR POWER PLANTS IN THE WAKE OF THE FUKUSHIMA ACCIDENT

STRESS TEST METHODOLOGY FOR NUCLEAR POWER PLANTS IN THE WAKE OF THE FUKUSHIMA ACCIDENT STRESS TEST METHODOLOGY FOR NUCLEAR POWER PLANTS IN THE WAKE OF THE FUKUSHIMA ACCIDENT Frank Nuzzo IAEA Nuclear Power Engineering f.nuzzo@iaea.org ENSREG High Level Requirements Following the extreme events

More information

Accident at Fukushima Dai-ichi Nuclear Power Station and Lessons Learned from the Accident

Accident at Fukushima Dai-ichi Nuclear Power Station and Lessons Learned from the Accident Accident at Fukushima Dai-ichi Nuclear Power Station and Lessons Learned from the Accident For IAEA TWG LMNPP Meeting 20 February 2013 Takeyuki INAGAKI Safety Enhancement Project Management Group Nuclear

More information

An overview of what happened at Fukushima NPPs

An overview of what happened at Fukushima NPPs An overview of what happened at Fukushima NPPs Per F. Peterson Professor and Chair Department of Nuclear Engineering University of California, Berkeley 2011 PEER Annual Meeting Hotel Shattuck Berkeley

More information

IAEA International Conference on Topical Issues in Nuclear Installation Safety

IAEA International Conference on Topical Issues in Nuclear Installation Safety IAEA International Conference on Topical Issues in Nuclear Installation Safety Guidance on the Implementation of Modifications to Mitigate Beyond Design Basis Accidents Fred Dermarkar Vice President Engineering

More information

EPR Safety in the post-fukushima context

EPR Safety in the post-fukushima context EPR Safety in the post-fukushima context October 19 th 2011 Jürgen Wirkner, Peter Volkholz EPR safety approach An accident is a complex series of events: NEED THE MEANS TO REMAIN IN CONTROL OF THE SITUATION,

More information

The 4th Progress Report

The 4th Progress Report The 4th Progress Report on the Investigation and Examination of Unconfirmed and Unresolved Issues on the Development Mechanism of the Fukushima Daiichi Nuclear Accident December 17, 2015 Tokyo Electric

More information

Regulatory Review Aspects of Post-Fukushima Safety Enhancements in Indian NPPs

Regulatory Review Aspects of Post-Fukushima Safety Enhancements in Indian NPPs Regulatory Review Aspects of Post-Fukushima Safety Enhancements in Indian NPPs RAHUL PORWAL Atomic Energy Regulatory Board Mumbai, INDIA Outline Introduction AERB Safety Review Methodology Safety Observations

More information

Development and use of SAMGs in the Krško NPP

Development and use of SAMGs in the Krško NPP REPUBLIC OF SLOVENIA Development and use of SAMGs in the Krško NPP Tomaž Nemec Slovenian Nuclear Safety Administration tomaz.nemec@gov.si IAEA TM on the Verification and Validation of SAMGs, Vienna, 12

More information

Compilation of recommendations and suggestions

Compilation of recommendations and suggestions Post- Fukushima accident Compilation of recommendations and suggestions Peer review of stress tests performed on European nuclear power plants 26/07/2012 Compilation of Recommendations and Suggestions

More information

Post-Fukushima Action Plan in Korea. WNU-SI 2011, August 11 Christ Church, Oxford

Post-Fukushima Action Plan in Korea. WNU-SI 2011, August 11 Christ Church, Oxford Post-Fukushima Action Plan in Korea WNU-SI 2011, August 11 Christ Church, Oxford Contents Korean nuclear overview BK Kim Government action plan BS Jeong Post-Fukushima action plan MK Jo Nuclear Power Plants

More information

ESSENCE AND CHARACTERISTICS OF THE ATMEA TECHNOLOGY: THE ATMEA1 REACTOR

ESSENCE AND CHARACTERISTICS OF THE ATMEA TECHNOLOGY: THE ATMEA1 REACTOR ESSENCE AND CHARACTERISTICS OF THE ATMEA TECHNOLOGY: THE ATMEA1 REACTOR Antoine VERDIER Business Development Manager BULATOM Varna / June 4 th, 2014 An AREVA and MHI Company Introduction ATMEA Company

More information

Improvements in defense in depth on French NPPs following Fukushima Accidents

Improvements in defense in depth on French NPPs following Fukushima Accidents Improvements in defense in depth on French NPPs following Fukushima Accidents Xavier Pouget-Abadie Jean BARBAUD IAEA, October 2013 1 Copyright EDF 2013 1 Context -Timeline 6 fields assessed : Earthquake

More information

Improvements on French Nuclear Power Plants Taking Into Account the Fukushima Accidents

Improvements on French Nuclear Power Plants Taking Into Account the Fukushima Accidents Improvements on French Nuclear Power Plants Taking Into Account the Fukushima Accidents Jean BARBAUD IAEA, August 2013 1 1 Context - Timeline 6 fields assessed : Earthquake Flooding Loss of heat sink LHS

More information

in China Nuclear and Radiation Safety Center, Ministry i of Environmental Protection, ti P. R. China August , Vienna

in China Nuclear and Radiation Safety Center, Ministry i of Environmental Protection, ti P. R. China August , Vienna Post-Fukushima Safety Improvement Measures for NPPs in China ZHENG Lixin Nuclear and Radiation Safety Center, Ministry i of Environmental Protection, ti P. R. China August 26-2929 2013, Vienna 1 Background

More information

IAEA-J4-TM TM for Evaluation of Design Safety

IAEA-J4-TM TM for Evaluation of Design Safety Canadian Nuclear Utility Principles for Beyond Design Basis Accidents IAEA-J4-TM-46463 TM for Evaluation of Design Safety Mark R Knutson P Eng. Director of Fukushima Projects Ontario Power Generation Overview

More information

Findings from the latest analyses using MAAP5

Findings from the latest analyses using MAAP5 Attachment 3 Findings from the latest analyses using MAAP5 1. Latest analysis of Unit-1 by MAAP5.01 1.1. Plant conditions and event chronology Table 1-1 summarizes key plant conditions, while Table 1-2

More information

Copyright 2016 ThinkReliability. How a Reactor Works

Copyright 2016 ThinkReliability. How a Reactor Works Cause Mapping Problem Solving Incident Investigation Root Cause Analysis Risk Mitigation Root Cause Analysis Case Study Angela Griffith, P.E. webinars@thinkreliability.com www.thinkreliability.com Office

More information

Enhancement of Nuclear Safety

Enhancement of Nuclear Safety Enhancement of Nuclear Safety Soon Heung Chang Handong Global University May 6, 2015 Contents 1 2 3 4 Importance of Energy Fundamentals of Nuclear Safety How to Enhance Nuclear Safety Closing Remarks 2

More information

1) Order of accident progress and provisional expedient (chronological sequence)

1) Order of accident progress and provisional expedient (chronological sequence) (3)Fukushima Daiichi NPS, Unit 3 1) Order of accident progress and provisional expedient (chronological sequence) a From the earthquake until the arrival of the tsunami As described in Chapter 3, the plant

More information

KHNP s strategies for Multi-unit Extreme Hazards Response

KHNP s strategies for Multi-unit Extreme Hazards Response KHNP s strategies for Multi-unit Extreme Hazards Response Jang Hwan Na 2018. 5. 8 Safety Technology Center Central Research Institute, KHNP Contents 1 Post Fukushima Safety Measures 2 Stress Tests 3 Integrated

More information

Post Fukushima actions in India. Mukesh Singhal, Chief Engineer, Reactor Safety & Analysis Directorate NPCIL

Post Fukushima actions in India. Mukesh Singhal, Chief Engineer, Reactor Safety & Analysis Directorate NPCIL Post Fukushima actions in India Mukesh Singhal, Chief Engineer, Reactor Safety & Analysis Directorate NPCIL 14 th Meeting of IAEA-TWG on advance technologies, IAEA, Vienna, June 18-20, 2013 Presentation

More information

Lessons learned from the Fukushima Daiichi Nuclear Power Plant Accident

Lessons learned from the Fukushima Daiichi Nuclear Power Plant Accident 2012 Begell House, Inc. Lessons learned from the Fukushima Daiichi Nuclear Power Plant Accident T. Narabayashi 1 1 Division of Energy and Environmental Systems, Hokkaido University, Kita 13, Nishi 8, Kita-ku,

More information

Meetings for Sharing International Knowledge and Experience on Stress Tests

Meetings for Sharing International Knowledge and Experience on Stress Tests Meetings for Sharing International Knowledge and Experience on Stress Tests Presented by: Peter Hughes, Ovidiu Coman, Javier Yllera Department of Nuclear Safety and Security Division of Nuclear Installation

More information

The Risk of Nuclear Power

The Risk of Nuclear Power 13 th International Conference on Probabilistic Safety Assessment and Management [PSAM13] The Risk of Nuclear Power Soon Heung Chang Handong Global University Oct 4, 2016 Contents 1 2 3 4 Introduction:

More information

BWR3 Mark I. Dr. John H. Bickel

BWR3 Mark I. Dr. John H. Bickel Beyond the Design Bases BWR3 Mark I Dr. John H. Bickel BWR3, Mark I DBA Features: Electric di driven Mi Main Feedwater, Condensate Pumps 2 Diesels supply: 4kV power, 480V, 250VDC, 125VDC 2 Trains Electric

More information

Safety Measures taken at Kashiwazaki Kariwa NPS based on the Fukushima Daiichi Accident

Safety Measures taken at Kashiwazaki Kariwa NPS based on the Fukushima Daiichi Accident Safety Measures taken at Kashiwazaki Kariwa NPS based on the Fukushima Daiichi Accident February 17, 2015 Toshihiro Matsuo Tokyo Electric Power Company Overview of the 10-Unit Simultaneous Accidents Date

More information

Fukushima Accident Summary(3) 2011-July-17, Ritsuo Yoshioka (Text in blue are Yoshioka s comments) 1) Earthquake and Tsunami

Fukushima Accident Summary(3) 2011-July-17, Ritsuo Yoshioka (Text in blue are Yoshioka s comments) 1) Earthquake and Tsunami Fukushima Accident Summary(3) 2011-July-17, Ritsuo Yoshioka (Text in blue are Yoshioka s comments) 1) Earthquake and Tsunami 14:46 March 11th 2011 (Please see Summary-1 report for detail.) Tohoku Pacific

More information

Safety enhancement of NPPs in China after Fukushima Accident

Safety enhancement of NPPs in China after Fukushima Accident Safety enhancement of NPPs in China after Fukushima Accident CHAI Guohan 29 June 2015, Brussels National Nuclear Safety Administration, P. R. China Current Development of Nuclear Power Mid of year 2015

More information

FUKUSHIMA DAI-ICHI ACCIDENT: LESSONS LEARNED AND FUTURE ACTIONS FROM THE RISK PERSPECTIVES

FUKUSHIMA DAI-ICHI ACCIDENT: LESSONS LEARNED AND FUTURE ACTIONS FROM THE RISK PERSPECTIVES FUKUSHIMA DAI-ICHI ACCIDENT: LESSONS LEARNED AND FUTURE ACTIONS FROM THE RISK PERSPECTIVES JOON-EON YANG Integrated Safety Assessment Division, Korea Atomic Energy Research Institute, Daedeok-daero 989-111,

More information

Safety and Standardization Issues of Nuclear Power Plants in Design and Operation on ISO12100 of Safety Design Principle

Safety and Standardization Issues of Nuclear Power Plants in Design and Operation on ISO12100 of Safety Design Principle E-Journal of Advanced Maintenance Vol.9-2 (2017) 112-117 Japan Society of Maintenology Safety and Standardization Issues of Nuclear Power Plants in Design and Operation on ISO12100 of Safety Design Principle

More information

Side Event of IAEA General Conference. Severe Accident Analyses of Fukushima-Daiich Units 1 to 3. Harutaka Hoshi and Masashi Hirano

Side Event of IAEA General Conference. Severe Accident Analyses of Fukushima-Daiich Units 1 to 3. Harutaka Hoshi and Masashi Hirano Side Event of IAEA General Conference Severe Accident Analyses of Fukushima-Daiich Units 1 to 3 Harutaka Hoshi and Masashi Hirano Japan Nuclear Energy Safety Organization (JNES) September 17, 2012 Side

More information

Nuclear Safety Standards Committee

Nuclear Safety Standards Committee Nuclear Safety Standards Committee 41 st Meeting, IAEA 21 23 Topical June, Issues 2016 Conference in Nuclear Installation Safety Agenda item Safety Demonstration of Advanced Water Cooled NPPs Title Workshop

More information

Fundamental Policy for the Reform of TEPCO Nuclear Power Organization. October 12, 2012 Nuclear Reform Special Task Force

Fundamental Policy for the Reform of TEPCO Nuclear Power Organization. October 12, 2012 Nuclear Reform Special Task Force Fundamental Policy for the Reform of TEPCO Nuclear Power Organization October 12, 2012 Nuclear Reform Special Task Force How to Proceed with the Development of the Reform Plan (1) Measures Measures Adopted

More information

INPRO Criterion Robustness of Design Position of the EPR TM reactor Part 3. Franck Lignini Reactor & Services / Safety & Licensing

INPRO Criterion Robustness of Design Position of the EPR TM reactor Part 3. Franck Lignini Reactor & Services / Safety & Licensing INPRO Criterion 1.1.1 Robustness of Design Position of the EPR TM reactor Part 3 Franck Lignini Reactor & Services / Safety & Licensing 0 E.P?.?.?.? Robustness against External Hazards 1 External Hazards

More information

STRESS TESTS ACTION PLAN LEONTI CHALOYAN DEPUTY CHIEF ENGINEER ON MODERNIZATION

STRESS TESTS ACTION PLAN LEONTI CHALOYAN DEPUTY CHIEF ENGINEER ON MODERNIZATION STRESS TESTS ACTION PLAN LEONTI CHALOYAN DEPUTY CHIEF ENGINEER ON MODERNIZATION VIENNA MARCH 27-29, 2017 1 ANPP * The ANPP is located in the western part of Ararat valley, 30 km west of Yerevan, close

More information

The Spanish Involvement

The Spanish Involvement The OECD-BSAF Project: The Spanish Involvement Luis E. Herranz Unit of Nuclear Safety Research Division of Nuclear Fission Department of Energy CIEMAT BACKGROUND CIEMAT and CSN closely collaborate on severe

More information

European level recommendations Sect. in NAcP 2 Generic recommendation for WENRA, Finland participates and follows the work.

European level recommendations Sect. in NAcP 2 Generic recommendation for WENRA, Finland participates and follows the work. Cross reference table of ENSREG and Extraordinary CNS recommendations and national actions 1(16) 2.1 European guidance on assessment of natural hazards and margins The peer review Board recommends that

More information

Severe Accident Countermeasures of SFR (on Monju)

Severe Accident Countermeasures of SFR (on Monju) Severe Accident Countermeasures of SFR (on Monju) Mamoru Konomura FBR Plant Engineering Center Japan Atomic Energy Agency 1. Safety Approach of Monju Safety Approaches in early LMFBR There were several

More information

Chapter 3 Accident of Fukushima Daiichi Nuclear Power Plant: Sequences, Fission Products Released, Lessons Learned

Chapter 3 Accident of Fukushima Daiichi Nuclear Power Plant: Sequences, Fission Products Released, Lessons Learned Chapter 3 Accident of Fukushima Daiichi Nuclear Power Plant: Sequences, Fission Products Released, Lessons Learned Jun Sugimoto Abstract The nuclear accident that occurred at the Fukushima Daiichi Nuclear

More information

OVERVIEW ON FINAL STRESS TEST REPORT CERNAVODA NPP Dumitru DINA CEO Nuclearelectrica. 16 th of May 2012 Nuclear 2012 Pitesti, Romania

OVERVIEW ON FINAL STRESS TEST REPORT CERNAVODA NPP Dumitru DINA CEO Nuclearelectrica. 16 th of May 2012 Nuclear 2012 Pitesti, Romania OVERVIEW ON FINAL STRESS TEST REPORT CERNAVODA NPP Dumitru DINA CEO Nuclearelectrica 16 th of May 2012 Nuclear 2012 Pitesti, Romania 1 PREAMBLE On 25 March, 2011, European Council decided that nuclear

More information

Information on Status of Nuclear Power Plants in Fukushima

Information on Status of Nuclear Power Plants in Fukushima Information on Status of Nuclear Power Plants in Fukushima Japan Atomic Industrial Forum, Inc. Policy on information and compilation This JAIF-compiled information chart represents the situation, phenomena,

More information

Accident Management Programme for Indian Pressurized Heavy Water Reactors Chander Mohan Bhatia Nuclear Power Corporation of India Limited

Accident Management Programme for Indian Pressurized Heavy Water Reactors Chander Mohan Bhatia Nuclear Power Corporation of India Limited Accident Management Programme for Indian Pressurized Heavy Water Reactors Chander Mohan Bhatia Nuclear Power Corporation of India Limited cmbhatia@npcil.co.in Presentation Contents Indian nuclear power

More information

Information on Status of Nuclear Power Plants in Fukushima

Information on Status of Nuclear Power Plants in Fukushima Information on Status of Nuclear Power Plants in Fukushima Japan Atomic Industrial Forum, Inc. Policy on information and compilation This JAIF-compiled information chart represents the situation, phenomena,

More information

Contents of summary. 1. Introduction

Contents of summary. 1. Introduction Contents of summary 1. Introduction 2. Situation regarding Nuclear Safety Regulations and Other Regulatory Frameworks in Japan before the Accident 3. Disaster Damage in Japan from the Tohoku District -

More information

Information on Status of Nuclear Power Plants in Fukushima

Information on Status of Nuclear Power Plants in Fukushima Information on Status of Nuclear Power Plants in Fukushima Japan Atomic Industrial Forum, Inc. Policy on information and compilation This JAIF-compiled information chart represents the situation, phenomena,

More information

Information on Status of Nuclear Power Plants in Fukushima

Information on Status of Nuclear Power Plants in Fukushima Information on Status of Nuclear Power Plants in Fukushima Japan Atomic Industrial Forum, Inc. Policy on information and compilation This JAIF-compiled information chart represents the situation, phenomena,

More information

Lessons Learned from the Fukushima Daiichi Nuclear Power Plant Accident

Lessons Learned from the Fukushima Daiichi Nuclear Power Plant Accident Lessons Learned from the Fukushima Daiichi Nuclear Power Plant Accident Nuclear Energy Safety Symposium Academy of Science of South Africa October 13, 2011 Hideki Nariai Professor Emeritus of the University

More information

Tsunami Countermeasures at Hamaoka Nuclear Power Station

Tsunami Countermeasures at Hamaoka Nuclear Power Station Tsunami Countermeasures at Hamaoka Nuclear Power Station Reference Reactor No. 5 Reactor No. 4 Reactor No. 3 Reactor No. 2 Reactor No. 1 March 16, 2012 2011 Chubu Electric Power Co., Inc. All rights reserved.

More information

Fukushima-Daiichi - a radiochemical view of the evolving situation in Summer 2011.

Fukushima-Daiichi - a radiochemical view of the evolving situation in Summer 2011. Fukushima-Daiichi - a radiochemical view of the evolving situation in Summer 2011. Kath Morris. Research Centre for Radwaste and Decommissioning The University of Manchester With thanks to Dr Edward Blandford,

More information

CNSC Fukushima Task Force Nuclear Power Plant Safety Review Criteria

CNSC Fukushima Task Force Nuclear Power Plant Safety Review Criteria CNSC Fukushima Task Force E-doc 3743877 July 2011 Executive Summary In response to the March 11, 2011 accident at the Fukushima Daiichi Nuclear Power Plant (NPP), the CNSC convened a Task Force to evaluate

More information

Joint ICTP-IAEA Essential Knowledge Workshop on Deterministic Safety Analysis and Engineering Aspects Important to Safety. Trieste,12-23 October 2015

Joint ICTP-IAEA Essential Knowledge Workshop on Deterministic Safety Analysis and Engineering Aspects Important to Safety. Trieste,12-23 October 2015 Joint ICTP- Essential Knowledge Workshop on Deterministic Safety Analysis and Engineering Aspects Important to Safety Trieste,12-23 October 2015 Safety classification of structures, systems and components

More information

Phenomena Identification in Severe Accident Sequence and Safety Issues for Severe Accident Management of Light Water Reactors

Phenomena Identification in Severe Accident Sequence and Safety Issues for Severe Accident Management of Light Water Reactors Japan-U.S. Seminar on Two-Phase Flow Dynamics June 7-12, 2012 @ Tokyo, Japan Identification in Severe Accident Sequence and Safety Issues for Severe Accident Management of Light Water Reactors University

More information

ACR Safety Systems Safety Support Systems Safety Assessment

ACR Safety Systems Safety Support Systems Safety Assessment ACR Safety Systems Safety Support Systems Safety Assessment By Massimo Bonechi, Safety & Licensing Manager ACR Development Project Presented to US Nuclear Regulatory Commission Office of Nuclear Reactor

More information

Contents of Summary. 1. Introduction

Contents of Summary. 1. Introduction Contents of Summary 1. Introduction 2. Situation of Nuclear Safety Regulations and Other Regulatory Frameworks in Japan before the Accident 3. Disaster Damage by Tohoku District - off the Pacific Ocean

More information

Conditions of Fukushima Dai-ichi Nuclear Power Station Unit 1 (As of 18:00 March 25th, 2011)

Conditions of Fukushima Dai-ichi Nuclear Power Station Unit 1 (As of 18:00 March 25th, 2011) 機密性 2 Conditions of Fukushima Dai-ichi Nuclear Station Unit 1 (As of 18:00 March 25th, 2011) Pool Water Temperature - EDG* 2 Reactor Pressure A 0.453MPa* Reactor Pressure B 0.453MPa* Condition :Tend to

More information

Brazilian Operator s Response to Fukushima Daiichi Accident Luiz Soares Technical Director

Brazilian Operator s Response to Fukushima Daiichi Accident Luiz Soares Technical Director Simposyum Siting of New Nuclear Power Plants and Irradiated Fuel Facilities Buenos Aires Argentina 24-28 June 2013 Panel Fukushima Daiichi s Impact in Nuclear Power Programs Worldwide Brazilian Operator

More information

Fukushima Accident : An overview

Fukushima Accident : An overview Fukushima Accident : An overview 5 July 2011, Akira OMOTO, Commissioner of AECJ OUTLINE Part I 3.11 Earthquake and Tsunami Part II Response of the nuclear reactors Part III Recovery actions Part IV Offsite

More information

Fukushima Dai-ichi. Short overview of 11 March 2011 accidents and considerations. 3 rd EMUG Meeting ENEA Bologna April 2011

Fukushima Dai-ichi. Short overview of 11 March 2011 accidents and considerations. 3 rd EMUG Meeting ENEA Bologna April 2011 Fukushima Dai-ichi Short overview of 11 March 2011 accidents and considerations Marco Sangiorgi - ENEA 3 rd EMUG Meeting ENEA Bologna 11-12 April 2011 NPPs affected by Earthquake NPPs affected by Earthquake

More information

Activities on Safety Improvement of Czech NPPs in Solution of Severe Accident Issues

Activities on Safety Improvement of Czech NPPs in Solution of Severe Accident Issues Activities on Safety Improvement of Czech NPPs in Solution of Severe Accident Issues Jiří Duspiva ÚJV Řež, a. s. Division of Nuclear Safety and Reliability Dept. of Severe Accidents and Thermomechanics

More information

SMART Standard Design Approval inspection result July. 4 th

SMART Standard Design Approval inspection result July. 4 th SMART Standard Design Approval inspection result 2012. July. 4 th Content Ⅰ. Inspection outline. 1 Ⅱ. Inspection proceedings 2 Ⅲ. SMART Standard Design features. 3 Ⅳ. Standard Design inspection result

More information

India s HWR Activities S.G.Ghadge Executive Director (Reactor Safety & Analysis) Nuclear Power Corporation of India Limited

India s HWR Activities S.G.Ghadge Executive Director (Reactor Safety & Analysis) Nuclear Power Corporation of India Limited India s HWR Activities S.G.Ghadge Executive Director (Reactor Safety & Analysis) Nuclear Power Corporation of India Limited 13 th Meeting of the Technical Working Group on Advanced Technologies for HWRs

More information

PHWR Group of Countries Implementation of Lessons Learned from Fukushima Accident in CANDU Technology

PHWR Group of Countries Implementation of Lessons Learned from Fukushima Accident in CANDU Technology Implementation of Lessons Learned from Fukushima Accident in CANDU Technology Greg Rzentkowski Director General Directorate of Power Reactor Regulation Canadian Nuclear Safety Commission on behalf of CANDU

More information

Safety Provisions for the KLT-40S Reactor Plant

Safety Provisions for the KLT-40S Reactor Plant 6th INPRO Dialogue Forum on Global Nuclear Energy Sustainability: Licensing and Safety Issues for Small and Medium-sized Nuclear Power Reactors (SMRs) 29 July - 2 August 2013 IAEA Headquarters, Vienna,

More information

Measures against Earthquakes and Tsunamis in View of the Accident at Fukushima Daiichi Nuclear Power Station

Measures against Earthquakes and Tsunamis in View of the Accident at Fukushima Daiichi Nuclear Power Station Nuclear and Industrial Safety Agency Ministry of Economy, Trade and Industry IEM 3: International Expert s Meeting (Earthquakes / Tsunamis) 4-7 September, 2012 Vienna Measures against Earthquakes and Tsunamis

More information

Expanding Capabilities of PSA To Address Multi-Unit Sites

Expanding Capabilities of PSA To Address Multi-Unit Sites Expanding Capabilities of PSA To Address Multi-Unit Sites By: Karl N. Fleming, President KNF Consulting Services LLC KarlFleming@comcast.net Presented to: CRA s 6 th Risk Forum Warwick UK September 16

More information