PROBABILISTIC SAFETY ANALYSIS (PSA) LEVEL 2. Kaliopa Mancheva

Size: px
Start display at page:

Download "PROBABILISTIC SAFETY ANALYSIS (PSA) LEVEL 2. Kaliopa Mancheva"

Transcription

1 PROBABILISTIC SAFETY ANALYSIS (PSA) LEVEL 2 Kaliopa Mancheva March 16, 2017

2 WHY PSA LEVEL 2? o The safety bases are established on the principles of safety, thereby ensuring protection of those working at a nuclear facility, as well as of the population and the environment against harmful ionizing radiation at this moment and in future. These principles determine the need for risk assessment and management of nuclear facilities. The PSA is one of the basic means for risk assessment of possible releases of radioactive products into the environment and the consequences thereof o More specifically, the PSA Level 2 deals basically with the investigation and assessment of possible paths of radioactive products release after nuclear fuel damage and the possibility not to release them into the environment o Nuclear fuel damage is associated with the term severe accident March 16, 2017

3 o The implementation of such type of projects has the following objectives: A systematic analysis to achieve certainty in the nuclear facility project compliance with the main safety objectives - overall level of safety Risk assessment of releases of radioactive products into the environment after fuel damage in the reactor, spent fuel pool, storage facilities and other facilities containing radioactive material Verification of project balancing, i.e. to ascertain that there are no expressed deficiencies in terms of specific impacts Use of the source terms and frequencies to determine off-site consequences (Level 3 PSA input) Evaluation of plant design To identify potential vulnerabilities in the mitigation of severe accidents To compare design options Support and verification of SAMG Use of a range of other PSA applications in combination with the Level 1 PSA results

4 o Objectives of the specific task: Assessment of Large Early Release Frequency (LERF): it considers only the sequences, for which the releases occur in the early phase of the accident. It is used for early risk release assessments A full-scope PSA Level 2: it considers all sequences, which lead to releases into the environment, both at the early and late phase of the accident

5 SCOPE OF PSA LEVEL 2 o PSA Level 2 can have a different scope, depending on the following: The type of initiating events that are to be analyzed: Internal initiating events (which include facility-internal failures, fires and flooding) External hazards (which include seismic, tornado, strong winds, high temperatures, external fires and floodings and etc.) The facility operational modes Full power modes Low power and shutdown modes The fuel location: Reactor vessel Spent fuel pool Spent fuel storage facility

6 General Steps of Level 2 PSA Input from the Level 1 PSA core damage minimal cut-sets/accident sequences Plant familiarisation for Level 2 PSA Plant damage states definition Severe accident modelling Containment performance analysis Source term analysis Quantification Results Sensitivities, uncertainties Use of the results Information collection and familiarization with plant features that influence severe accident progression Grouping of core damage MCSs into PDSs Phenomena/ Containment Event Tree (CET) analysis Response to severe accidents Fission product transport/ release categorization CET probabilities/ quantification Frequencies of large (early) release / release categories Sources of uncertainty Identifications of severe accident vulnerabilities and other applications

7 Design aspects identification o Identify and highlight plant SSC and operating procedures that can influence: severe accidents progression containment response transport of radioactive material o o The task includes also Reactor Building, Auxiliary Building, Secondary containment and etc. Examples: core materials and geometry of the reactor internals area under the reactor pressure vessel flow paths from the area under the reactor pressure vessel to the main containment volume chemical content of the concrete features that could lead to containment bypass sequences

8 [kg-zr per MW] PWR BWR WWER ANF 10x10 GNF 10x10 Fuel Channel Control Rods Fuel Channel Box 0.5 [--] 0.78 [--] 5.6 [--] Grids and other [--] [--] x9 8x8 Total (kg) 3000 MW reactor 20,000 51,000 28,800 Channel box

9 General Steps of Level 2 PSA Input from the Level 1 PSA core damage minimal cut-sets/accident sequences Plant damage states definition Grouping of core damage MCSs into PDSs

10 Initiating Events (< 100) Initial plant Accident damage sequences states (millions) (50 to 100) Consolidated plant damage states (< 20) Accident progression / containment event tree end states (10 4 to 10 6 ) Release categories (< 20) Conditional consequence bins (< 20) Frequency * Consequence Accident sequence event trees (event probabilities from fault trees) Binning Process Combine Similar PDS Accident progression / containment event trees (branch probabilities with uncertainties) Risk Integration Stop Iterative truncation to convergence Screen on low frequency Sensitivity analysis & reconsideration of low-frequency PDS with high consequences LEVEL 1 LEVEL 1-2 Interface LEVEL 2 LEVEL 3

11 o o Plant Damage State (PDS) core melt sequences identified in the Level-1 PSA grouped based on similarities in accident progression and availability of containment safeguards and other systems that might have impact on accident progression after core melt Binning process is intended to establish an interface between The plant systems analysis (Level-1 PSA) and The containment response analysis (Level-2 PSA) o Software: SAPHIRE RiskSpectrum 1.2 last version

12 General Steps of Level 2 PSA Input from the Level 1 PSA core damage minimal cut-sets/accident sequences Severe accident modelling Phenomena/ Containment Event Tree (CET) analysis

13 o Main purposes and outcomes from the deterministic analysis Time chronology of the accident physical parameters of accident progression dependencies between phenomena o Used for expert judgment assessment of probabilities for different phenomena o Software: MELCOR, MAAP, ASTEC CV070 CV092 CV091 CV050 CV060 CV012 CV013 CV014 CV015 CV016 CV017 CV022 CV023 CV024 CV025 CV026 CV027 CV032 CV033 CV034 CV035 CV036 CV037 CV042 CV043 CV044 CV045 CV046 CV047 CV052 CV053 CV054 CV055 CV056 CV057 CV040 CV010 CV020 WWER-1000 Reactor Model

14 First Phase of Accident Progression IE TBO and DC power available Covers the period from CD to vessel breach - CD = 1200 C of claddings Chronology: Time [h:m] Event Comment 0.0 IE TBO with DC available Reactor Scram, MSIV* closure Diesel generators fail to start 0:03 MCP coast down 0:58 PORV opens Pressure is >180 MPa 3:03 H 2 generation starts H 2 O-Zr 3:08 Gap release Core damage 3:36 Tcl >1200 C Core damage 4:23 Core degradation Loss of mass of CL 6:55 Vessel failure Start to eject to cavity

15 Pressure and Temperatures Primary Side pressure is controlled by PORV Temperature increase rapidly after water depletion Secondary Side pressure is controlled by SG SV SDA assumed failed (no DC power)

16 Level [m] Level [m] Levels Primary Side - Levels TAF BAF Time [hours] 2.5 Pressurizer level is maintained up to vessel failure RPV level start to decrease after SG depletion SG levels 2 Major insights: PRZ level not indicative for mass inventory in the system Time [hours]

17 Area Fraction [-] Mass [kg] Hydrogen generation Core blocking Time [hours] Hydrogen generated in in-vessel phase Time [hours] Upper FL Lowest FL Last Upper FL Lower FL Total H 2 production Simplified nodalization 5 volumes in core region H 2 production from Zr H 2 production from Steel H 2 production from B 4 C

18 o STRUCTURAL ANALYSIS OF THE PRIMARY SIDE ELEMENTS In case of a severe accident, the primary side elements operate in beyond design conditions. Therefore, an analysis is required of their operability and probability of failure, respectively. Tube bundle of the steam generator part o o The conditions of their operation are determined by deterministic analyses results with MELCOR or other integral code. The analysis of Primary Side components response is based on the following: WWER-1000 models with the ALGOR product MCP/ SG header/ pressurizer surge Steam Generator line Deterministic part: determining the ultimate capacity by using the finite elements method Probabilistic part: assessment of the probability of failure (e.g. Larson-Miller approach)

19 o A CET is a logical framework for estimating the range of consequences associated with a given accident sequence Initiating Event System failures Human actions Level 1 Level 2 Core Damage Challenges to Containment Integrity Fission Product Release to the Environment o A CET is a time-line of accident progression It represents the sequence of events that could lead to failure of the containment pressure boundary and fission product release to the environment

20 o It is a Probabilistic model It represents uncertainties in ability to predict accident progression Particular assumptions regarding each o uncertainty lead to different conclusions regarding plant response to the sequence Branch point probabilities typically NOT based on statistical analysis of data Reflect confidence that one outcome is more likely to be correct than its alternative Accident Sequence xxx Containment Response Intact Fails Late Fails Early Fission Product Release None Large Small Large Small

21 o Unlike the Level 1 event tree, branch points in a CET often have more than two possible outcomes: Branch may not simply represent success or failure of an event Often represent alternative conditions or physical process Hydrogen Concentration in Containment? 4 < Conc < 8% No burn Hydrogen Burn? Weak Deflagration None Accident Sequence xxx 8 < Conc < 14% Weak Deflagration Strong Deflagation o All branches represent sequences of interest Conc > 14% Strong Deflagation Detonation Quantification does not exclude success paths

22 RV at Low Pressure at Onset of Core Damage Injection Recovered No Vessel Breach No Early Containment Failure No MCCI No Late Containment Failure Sprays Containment Fails Early Containment Fails at VB with RCS at High Pressure Containment Fails at VB with RCS at Low Pressure Containment Bypass or Isolation Failure Containment Fails Prior to Vessel Breach RCS Not Depressurized Before Vessel Breach Containment Fails Given RCS at High Pressure RCS Depressurized at Vessel Breach Containment Fails Given RCS at Low Pressure In-vessel Steam Explosion Fails Containment Containment Fails by Overpressure During Core Degradation RCS Depressurized Before Vessel Breach High- Temperature Failure of Cavity Penetration Hydrogen Burn at Vessel Breach Fails Containment

23

24 KOZLODUY NPP EVENT TREE SARRP 59 NQ = NUMBER OF QUESTIONS (SEE LINE 2) TB-OPT 1 WHAT IS THE INITIATING EVENT? 8 VB LL MBL SML ISL SGTR TR TBO DOES THE OPERATOR DEPRESSURIZE THE RCS AFTER CD? 2 DEPR_Y DEPR_N CASES SGTR TR TBO OTHERWISE

25 General Steps of Level 2 PSA Input from the Level 1 PSA core damage minimal cut-sets/accident sequences Containment performance analysis Response to severe accidents

26 o o The analysis of containment structures response is based on the following: Deterministic part: determining the ultimate capacity by using the finite elements method Probabilistic part: assessment of the probability of failure under static and dynamic loads by creating the so-called fragility curves Software: Risk Engineering uses the SOLVIA and LSDYNA, which allows the development of 3D models of the studied objects Shell elements Models of containment and WWER-1000/В320 Reactor Building Solid elements

27 General Steps of Level 2 PSA Input from the Level 1 PSA core damage minimal cut-sets/accident sequences Source term analysis Fission product transport/ release categorization

28 o o The purpose of the analysis is to determine the following: time, location, energy and amount of the fission products released Analysis of the fractions by groups of elements of fission products released (MELCOR results) Assessment of fission products retention Using this analysis, both the full release activity, and the activities of individual nuclides, which have different consequences on the human body and soil, water, etc., are obtained. Vessel at Low Pressure No Early Contain. Failure Early F.P. Release to Pool No Core- Concrete Interaction No Late Contain. Failure Late Release to Pool Sprays Operate Auxiliary Building Retention RELEASE CATEGORY PDS LP CFE POOL DF CCI CFL POOL SPRYS AB RC Release category Release frequency, [y -1 ] Aerosol release activity, [Bq] Risk of aerosol release, [Bq/y] Contribution to the risk of aerosol release, [%] Full release [Bq] TRAR [Bq/y] Contribution to the TRAR [%] RC1 1.0E E14 1.3E E E

29 General Steps of Level 2 PSA Input from the Level 1 PSA core damage minimal cut-sets/accident sequences Quantification Results Sensitivities, uncertainties CET probabilities/ quantification Frequencies of large (early) release / release categories Sources of uncertainty

30 o Two interpretations of the concept of Probability Classical statistics: Statistical analysis of set of random data generates confidence intervals, not (strictly speaking) probability probability of frequency Bayesian: a quantity that we assign theoretically, for the purpose of representing a state of knowledge probability of probability Bayesian: Informed judgment that a particular outcome will occur reflects degree of belief of the observer. Only Bayesian interpretation is appropriate for PSA (particularly Level 2)

31 o Uncertainty : epistemic uncertainty reflects our lack of knowledge of the state of a system Can be reduced by further analysis (realistic approach) Can be reduced by changing our domain of experience (constructivist approach) aleatory variability randomness, observable measure of correspondence of our system model with the real world system Cannot be reduced by any means (for given system boundaries or for same model of a system) Very important statement aleatory variability is a property of our model and not a property of the real world system

32 100% 80% 60% 40% 20% 0% <12 18% 82% <24 20% 80% 21% <48 79% LERF 100% 80% 60% LRF 40% 20% 0% <12 93% 7% 11% 0% 7% <24 82% 83% 7% <48 10% SFP Closed Reactor Open Reactor Insights NO big impact of releases between hours Dominant releases starts after 48 hours Dominant risk comes from POS s with closed reactor 40% 30% 20% 10% 0% 38% 38% 36% 29% 13% 4% 13% 9% 2% 9% RC01 RC02 RC03 RC04 RC05 All Phenomena Isolation Failure Insights Low risk of hydrogen burning Low risk steam explosions and HPME Almost 100% of the risk for Open reactor comes from isolation failure (RC4, 5) March 16,

33 General Steps of Level 2 PSA Input from the Level 1 PSA core damage minimal cut-sets/accident sequences Use of the results Identifications of severe accident vulnerabilities and other applications

34 o Successful examples of applications of Level 2 PSA Comparison of results of the Level 2 PSA with probabilistic criteria To determine if the overall level of safety of the plant is adequate Evaluation of plant design To identify potential vulnerabilities in the mitigation of severe accidents To compare design options Development of severe accident management guidelines Use of the source terms to provide an input into emergency planning Use of the source terms and frequencies to determine off-site consequences (Level 3 PSA) Prioritization of research relating to severe accident issues Use of a range of other PSA applications in combination with the Level 1 PSA results

35 Headquarters: 10, Vihren str. Sofia 1618 Bulgaria Tel Fax: riskeng@riskeng.bg March 16, 2017

36 March 16, 2017 THANK YOU!

Introduction to Level 2 PSA

Introduction to Level 2 PSA Introduction to Level 2 PSA Dr Charles Shepherd Chief Consultant, Corporate Risk Associates CRA PSA/HFA FORUM 13-14 September 2012, Bristol Accident sequences modelled by the PSA INITIATING EVENTS SAFETY

More information

Main Aspects And Results Of Level 2 PSA For KNPP WWER-1000/B320

Main Aspects And Results Of Level 2 PSA For KNPP WWER-1000/B320 Proceedings of the 0 th International Conference on Nuclear Option in Countries with Small and Medium Electricity Grids Zadar, Croatia, -4 June 04 Paper No. 46 Main Aspects And Results Of Level PSA For

More information

Accident Progression & Source Term Analysis

Accident Progression & Source Term Analysis IAEA Training in Level 2 PSA MODULE 4: Accident Progression & Source Term Analysis Outline of Discussion Overview of severe accident progression and source term analysis Type of calculations typically

More information

Evaluation of a Containment Failure Frequency Considering Mitigation Accident Managements for a Japanese PWR Plant *

Evaluation of a Containment Failure Frequency Considering Mitigation Accident Managements for a Japanese PWR Plant * Evaluation of a Containment Failure Frequency Considering Mitigation Accident Managements for a Japanese PWR Plant * Osamu KAWABATA, Mitsuhiro KAJIMOTO, and buo TANAKA NUPEC/Institute of Nuclear Safety

More information

Insights and lessons learned from Level 2 PSA for Bohunice V2 plant

Insights and lessons learned from Level 2 PSA for Bohunice V2 plant Insights and lessons learned from Level 2 PSA for Bohunice V2 plant MACIEJ KULIG, ENCONET Consulting, Ges. m. b. H., Auhofstrasse 58, 1130 Vienna, Austria Abstract The paper provides a brief overview of

More information

Application of MELCOR at GRS Regarding Spent Fuel Pool Analyses and Assessment of SAMG Procedures

Application of MELCOR at GRS Regarding Spent Fuel Pool Analyses and Assessment of SAMG Procedures Application of MELCOR at GRS Regarding Spent Fuel Pool Analyses and Assessment of SAMG Procedures 7 th Meeting of the European MELCOR User Group March 17, 2015 TRACTEBEL Engineering, Brussels, Belgium

More information

THE IAEA SAFETY ASSESSMENT EDUCATION AND TRAINING PROGRAMME (SAET)

THE IAEA SAFETY ASSESSMENT EDUCATION AND TRAINING PROGRAMME (SAET) THE IAEA SAFETY ASSESSMENT EDUCATION AND TRAINING PROGRAMME (SAET) The Safety Assessment Education and Training (SAET) Programme has been designed to support the Member States with development of required

More information

Dr. Martin Sonnenkalb & Dr. Manfred Mertins GRS Cologne. Severe Accident Mitigation in German NPP - Status and Future Activities -

Dr. Martin Sonnenkalb & Dr. Manfred Mertins GRS Cologne. Severe Accident Mitigation in German NPP - Status and Future Activities - Dr. Martin Sonnenkalb & Dr. Manfred Mertins GRS Cologne Severe Accident Mitigation in German NPP - Status and Future Activities - Content History and status of implementation of Severe Accident Management

More information

Instrumentation and Control to Prevent and Mitigate Severe Accident Conditions

Instrumentation and Control to Prevent and Mitigate Severe Accident Conditions Instrumentation and Control to Prevent and Mitigate Severe Accident Conditions SAMG-D Toolkit, Module 3, Chapter 3 Martin Gajdoš Nuclear Engineering, Slovenské elektrárne IAEA Workshop on the Development

More information

Accident Sequence Analysis. Workshop Information IAEA Workshop

Accident Sequence Analysis. Workshop Information IAEA Workshop IAEA Training Course on Safety Assessment of NPPs to Assist Decision Making Accident Sequence Analysis Lecturer Lesson Lesson IV IV 3_2.2 3_2.2 Workshop Information IAEA Workshop City, XX XX - City -XX,

More information

EXAMPLE OF SEVERE ACCIDENT MANAGEMENT GUIDELINES VALIDATION AND VERIFICATION USING FULL SCOPE SIMULATOR

EXAMPLE OF SEVERE ACCIDENT MANAGEMENT GUIDELINES VALIDATION AND VERIFICATION USING FULL SCOPE SIMULATOR International Conference Nuclear Energy in Central Europe 2001 Hoteli Bernardin, Portorož, Slovenia, September 10-13, 2001 www: http://www.drustvo-js.si/port2001/ e-mail: PORT2001@ijs.si tel.:+ 386 1 588

More information

Assessment of Phenomenological Uncertainties in Level 2 PRAs 1

Assessment of Phenomenological Uncertainties in Level 2 PRAs 1 Assessment of Phenomenological Uncertainties in Level 2 PRAs 1 Hossein P. Nourbakhsh and Thomas S. Kress Advisory Committee on Reactor Safeguards U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

More information

ANALYSES OF AN UNMITIGATED STATION BLACKOUT TRANSIENT WITH ASTEC, MAAP AND MELCOR CODE

ANALYSES OF AN UNMITIGATED STATION BLACKOUT TRANSIENT WITH ASTEC, MAAP AND MELCOR CODE ANALYSES OF AN UNMITIGATED STATION BLACKOUT TRANSIENT WITH ASTEC, MAAP AND MELCOR CODE Technical Meeting on the Status and Evaluation of Severe Accident Simulation Codes for Water F. Mascari 1, J. C. De

More information

Assessing and Managing Severe Accidents in Nuclear Power Plant

Assessing and Managing Severe Accidents in Nuclear Power Plant Assessing and Managing Severe Accidents in Nuclear Power Plant Harri Tuomisto Fortum, Finland IAEA Technical Meeting on Managing the Unexpected - From the Perspective of the Interaction between Individuals,

More information

RISK ENGINEERING EXPERIENCE IN PROBABILISTIC SAFETY ANALYSES (PSA)

RISK ENGINEERING EXPERIENCE IN PROBABILISTIC SAFETY ANALYSES (PSA) RISK ENGINEERING EXPERIENCE IN PROBABILISTIC SAFETY ANALYSES (PSA) May 14, 2013 PSA OVERVIEW o o PSA is a methodical, logical tool for deriving numerical estimates of risk from nuclear power plant (or

More information

The Spanish Involvement

The Spanish Involvement The OECD-BSAF Project: The Spanish Involvement Luis E. Herranz Unit of Nuclear Safety Research Division of Nuclear Fission Department of Energy CIEMAT BACKGROUND CIEMAT and CSN closely collaborate on severe

More information

IAEA-TECDOC-1229 Regulatory review of probabilistic safety assessment (PSA) Level 2

IAEA-TECDOC-1229 Regulatory review of probabilistic safety assessment (PSA) Level 2 IAEA-TECDOC-1229 Regulatory review of probabilistic safety assessment (PSA) Level 2 Prepared jointly by the International Atomic Energy Agency and the OECD Nuclear Energy Agency July 2001 The originating

More information

Energie braucht Impulse. Dr. Andreas Strohm Kernkraftwerk Neckarwestheim PSAM9, Hong Kong /

Energie braucht Impulse. Dr. Andreas Strohm Kernkraftwerk Neckarwestheim PSAM9, Hong Kong / Approach to Quantification of Uncertainties in the Risk of Severe Accidents at NPP Neckarwestheim Unit 1 (GKN I) and the Risk Impact of Severe Accident Management Measures A. Strohm, L. Ehlkes, W. Schwarz

More information

METHODOLOGY USING MELCOR2.1/SNAP TO ESTABLISH AN SBO MODEL OF CHINSHAN BWR/4 NUCLEAR POWER PLANT

METHODOLOGY USING MELCOR2.1/SNAP TO ESTABLISH AN SBO MODEL OF CHINSHAN BWR/4 NUCLEAR POWER PLANT METHODOLOGY USING MELCOR2.1/SNAP TO ESTABLISH AN SBO MODEL OF CHINSHAN BWR/4 NUCLEAR POWER PLANT Yu Chiang 1, Jong-Rong Wang 1,3, Hao-Tzu Lin 2, Shao-Wen Chen 1 and Chunkuan Shih 1,3 1 : Institute of Nuclear

More information

IAEA-TECDOC Probabilistic safety assessments of nuclear power plants for low power and shutdown modes

IAEA-TECDOC Probabilistic safety assessments of nuclear power plants for low power and shutdown modes IAEA-TECDOC-1144 Probabilistic safety assessments of nuclear power plants for low power and shutdown modes March 2000 The originating Section of this publication in the IAEA was: Safety Assessment Section

More information

Accident Diagnostic, Analysis and Management (ADAM) System Applications to Severe Accident Management *

Accident Diagnostic, Analysis and Management (ADAM) System Applications to Severe Accident Management * Reprint of Paper Presented at the OECD/NEA Severe Accident Management (SAM) Workshop on Operator Training and Instrumentation Capabilities, Lyon, France, 12-14 March 2001 Accident Diagnostic, Analysis

More information

Development and use of SAMGs in the Krško NPP

Development and use of SAMGs in the Krško NPP REPUBLIC OF SLOVENIA Development and use of SAMGs in the Krško NPP Tomaž Nemec Slovenian Nuclear Safety Administration tomaz.nemec@gov.si IAEA TM on the Verification and Validation of SAMGs, Vienna, 12

More information

Use of PSA to Support the Safety Management of Nuclear Power Plants

Use of PSA to Support the Safety Management of Nuclear Power Plants S ON IMPLEMENTATION OF THE LEGAL REQUIREMENTS Use of PSA to Support the Safety Management of Nuclear Power Plants РР - 6/2010 ÀÃÅÍÖÈß ÇÀ ßÄÐÅÍÎ ÐÅÃÓËÈÐÀÍÅ BULGARIAN NUCLEAR REGULATORY AGENCY TABLE OF CONTENTS

More information

DECOMMISSIONING LEVEL 2 PROBABILISTIC RISK ASSESSMENT METHODOLOGY FOR BOILING WATER REACTORS

DECOMMISSIONING LEVEL 2 PROBABILISTIC RISK ASSESSMENT METHODOLOGY FOR BOILING WATER REACTORS DECOMMISSIONING LEVEL PROBABILISTIC RISK ASSESSMENT METHODOLOGY FOR BOILING WATER REACTORS Davide Mercurio 1, Vincent Andersen, KC Wagner 3 1 JENSEN HUGHES: 111 Rockville Pike, Suite 550, Rockville, MD

More information

SAM strategy&modifications and SA simulator at Paks NPP

SAM strategy&modifications and SA simulator at Paks NPP Technical Meeting on Verification and Validation of SAMGs for Nuclear Power Plants 12-14 December 2016, Vienna, Austria SAM strategy&modifications and SA simulator at Paks NPP Éva Tóth Group Leader Safety

More information

Nuclear Safety Standards Committee

Nuclear Safety Standards Committee Nuclear Safety Standards Committee 41 st Meeting, IAEA 21 23 Topical June, Issues 2016 Conference in Nuclear Installation Safety Agenda item Safety Demonstration of Advanced Water Cooled NPPs Title Workshop

More information

Verification of the MELCOR Code Against SCDAP/RELAP5 for Severe Accident Analysis

Verification of the MELCOR Code Against SCDAP/RELAP5 for Severe Accident Analysis Verification of the Code Against SCDAP/RELAP5 for Severe Accident Analysis Jennifer Johnson COLBERT 1* and Karen VIEROW 2 1 School of Nuclear Engineering, Purdue University, West Lafayette, Indiana 47907-2017,

More information

Meetings for Sharing International Knowledge and Experience on Stress Tests

Meetings for Sharing International Knowledge and Experience on Stress Tests Meetings for Sharing International Knowledge and Experience on Stress Tests Presented by: Peter Hughes, Ovidiu Coman, Javier Yllera Department of Nuclear Safety and Security Division of Nuclear Installation

More information

Improvements Needed in Nuclear Power Plant Probabilistic Risk Assessments: Lessons Learned from Fukushima

Improvements Needed in Nuclear Power Plant Probabilistic Risk Assessments: Lessons Learned from Fukushima Improvements Needed in Nuclear Power Plant Probabilistic Risk Assessments: Lessons Learned from Fukushima Mohammad Modarres Professor of Nuclear Engineering Department of Mechanical Engineering University

More information

LABGENE CONTAINMENT FAILURE MODES AND EFFECTS ANALYSIS

LABGENE CONTAINMENT FAILURE MODES AND EFFECTS ANALYSIS LABGENE CONTAINMENT FAILURE S AND ANALYSIS F. B. NATACCI Centro Tecnológico da Marinha em São Paulo São Paulo, Brasil Abstract Nuclear power plant containment performance is an important issue to be focused

More information

Activities on Safety Improvement of Czech NPPs in Solution of Severe Accident Issues

Activities on Safety Improvement of Czech NPPs in Solution of Severe Accident Issues Activities on Safety Improvement of Czech NPPs in Solution of Severe Accident Issues Jiří Duspiva ÚJV Řež, a. s. Division of Nuclear Safety and Reliability Dept. of Severe Accidents and Thermomechanics

More information

Severe accidents management in PWRs

Severe accidents management in PWRs Severe accidents management in PWRs J. Rajzrová, J.Jiřičková Abstract According to a new trend in safety upgrades in PWRs, the nuclear power plants have started to adopt strategs to mitigate events beyond

More information

Source Terms Issues and Implications on the Nuclear Reactor Safety

Source Terms Issues and Implications on the Nuclear Reactor Safety Source Terms Issues and Implications on the Nuclear Reactor Safety Jin Ho Song Korea Atomic Energy Research Institute t Technical Meeting on Source Term Evaluation for Severe Accidents, Vienna International

More information

Safety Challenges for New Nuclear Power Plants

Safety Challenges for New Nuclear Power Plants Implementing Design Extension Conditions and Fukushima Changes in the Context of SSR-2/1 Michael Case Office of Nuclear Regulatory Research United States Nuclear Regulatory Commission Outline of Presentation

More information

Safety Aspects of SMRs: A PRA Perspective

Safety Aspects of SMRs: A PRA Perspective Safety Aspects of SMRs: A PRA Perspective Mohammad Modarres Minta Martin Professor of Engineering Director, Reliability Engineering Program Department of Mechanical Engineering University of Maryland,

More information

Olkiluoto 3 EPR PSA Main results and conclusions fulfillment of the regulatory requirements for operating license

Olkiluoto 3 EPR PSA Main results and conclusions fulfillment of the regulatory requirements for operating license Olkiluoto 3 EPR PSA Main results and conclusions fulfillment of the regulatory requirements for operating license Presented by: Heiko Kollasko Framatome Co-Authors: Roman Grygoruk AREVA Gerben Dirksen

More information

Westinghouse UK AP1000 GENERIC DESIGN ASSESSMENT. Resolution Plan for GI-AP1000-PSA-01. Success Criteria for the Probabilistic Risk Assessment (PSA)

Westinghouse UK AP1000 GENERIC DESIGN ASSESSMENT. Resolution Plan for GI-AP1000-PSA-01. Success Criteria for the Probabilistic Risk Assessment (PSA) Westinghouse UK AP1000 GENERIC DESIGN ASSESSMENT Success Criteria for the Probabilistic Risk Assessment (PSA) MAIN ASSESSMENT AREA RELATED ASSESSMENT AREA(S) RESOLUTION PLAN REVISION GDA ISSUE REVISION

More information

Answers to Questions on the National Report

Answers to Questions on the National Report Status of the National Action Plan at the Paks NPP in Hungary on the implementation actions decided upon lessons learned from Fukushima Daiichi accident Answers to Questions on the National Report András

More information

Joint ICTP-IAEA Essential Knowledge Workshop on Deterministic Safety Analysis and Engineering Aspects Important to Safety. Trieste,12-23 October 2015

Joint ICTP-IAEA Essential Knowledge Workshop on Deterministic Safety Analysis and Engineering Aspects Important to Safety. Trieste,12-23 October 2015 Joint ICTP- Essential Knowledge Workshop on Deterministic Safety Analysis and Engineering Aspects Important to Safety Trieste,12-23 October 2015 Safety classification of structures, systems and components

More information

Safety Research Activities on Severe Accident Management in S/NRA/R after Fukushima Daiichi Nuclear Power Plant Accident

Safety Research Activities on Severe Accident Management in S/NRA/R after Fukushima Daiichi Nuclear Power Plant Accident Safety Research Activities on Severe Accident Management in S/NRA/R after Fukushima Daiichi Nuclear Power Plant Accident K. AONO, H. HOSHI, A. HOTTA, M. FUKASAWA Regulatory Standard and Research Department,

More information

FRAMEWORK FOR ASSESSING INTEGRATED SITE RISK OF SMALL MODULAR REACTORS USING DYNAMIC PROBABILISTIC RISK ASSESSMENT SIMULATION

FRAMEWORK FOR ASSESSING INTEGRATED SITE RISK OF SMALL MODULAR REACTORS USING DYNAMIC PROBABILISTIC RISK ASSESSMENT SIMULATION FRAMEWORK FOR ASSESSING INTEGRATED SITE RISK OF SMALL MODULAR REACTORS USING DYNAMIC PROBABILISTIC RISK ASSESSMENT SIMULATION Mohammad Modarres Nicole Y. Kim Eminent Professor April 28, 2015 PSA 2015 Sun

More information

Research Article Assessment of Severe Accident Depressurization Valve Activation Strategy for Chinese Improved 1000 MWe PWR

Research Article Assessment of Severe Accident Depressurization Valve Activation Strategy for Chinese Improved 1000 MWe PWR Science and Technology of Nuclear Installations Volume 3, Article ID 79437, pages http://dx.doi.org/.55/3/79437 Research Article Assessment of Severe Accident Depressurization Valve Activation Strategy

More information

Working together for a safer world. Nuclear Academy. Courses in Nuclear Probabilistic Safety Assessment

Working together for a safer world. Nuclear Academy. Courses in Nuclear Probabilistic Safety Assessment Working together for a safer world Nuclear Academy Courses in Nuclear Probabilistic Safety Assessment Lloyd s Register Nuclear Academy offers a comprehensive training programme in Probabilistic Safety

More information

PSA ANALYSIS FOCUSED ON MOCHOVCE NPP SAFETY MEASURES EVALUATION FROM OPERATIONAL SAFETY POINT OF VIEW

PSA ANALYSIS FOCUSED ON MOCHOVCE NPP SAFETY MEASURES EVALUATION FROM OPERATIONAL SAFETY POINT OF VIEW International Conference Nuclear Energy in Central Europe 2001 Hoteli Bernardin, Portorož, Slovenia, September 10-13, 2001 www: http://www.drustvo-js.si/port2001/ e-mail: PORT2001@ijs.si tel.:+ 386 1 588

More information

Compilation of recommendations and suggestions

Compilation of recommendations and suggestions Post- Fukushima accident Compilation of recommendations and suggestions Peer review of stress tests performed on European nuclear power plants 26/07/2012 Compilation of Recommendations and Suggestions

More information

HPR1000: ADVANCED PWR WITH ACTIVE AND PASSIVE SAFETY FEATURES

HPR1000: ADVANCED PWR WITH ACTIVE AND PASSIVE SAFETY FEATURES HPR1000: ADVANCED PWR WITH ACTIVE AND PASSIVE SAFETY FEATURES D. SONG China Nuclear Power Engineering Co., Ltd. Beijing, China Email: songdy@cnpe.cc J. XING China Nuclear Power Engineering Co., Ltd. Beijing,

More information

RELAP 5 ANALYSIS OF PACTEL PRIMARY-TO-SECONDARY LEAKAGE EXPERIMENT PSL-07

RELAP 5 ANALYSIS OF PACTEL PRIMARY-TO-SECONDARY LEAKAGE EXPERIMENT PSL-07 Fifth International Seminar on Horizontal Steam Generators 22 March 21, Lappeenranta, Finland. 5 ANALYSIS OF PACTEL PRIMARY-TO-SECONDARY LEAKAGE EXPERIMENT PSL-7 József Bánáti Lappeenranta University of

More information

RELAP5/MOD3.2 INVESTIGATION OF A VVER-440 STEAM GENERATOR HEADER COVER LIFTING

RELAP5/MOD3.2 INVESTIGATION OF A VVER-440 STEAM GENERATOR HEADER COVER LIFTING Science and Technology Journal of BgNS, Vol. 8, 1, September 2003, ISSN 1310-8727 RELAP5/MOD3.2 INVESTIGATION OF A VVER-440 STEAM GENERATOR HEADER COVER LIFTING Pavlin P. Groudev, Rositsa V. Gencheva,

More information

Development of the Methodologies for Evaluating Severe Accident Management

Development of the Methodologies for Evaluating Severe Accident Management IAEA Technical Meeting on the Verification and Validation of Severe Accident Management Guidelines December 12-14, 2016 IAEA Headquarters, Vienna, Austria Development of the Methodologies for Evaluating

More information

Westinghouse UK AP1000 GENERIC DESIGN ASSESSMENT. Resolution Plan for GI-AP1000-PSA-01. Success Criteria for the Probabilistic Risk Assessment (PSA)

Westinghouse UK AP1000 GENERIC DESIGN ASSESSMENT. Resolution Plan for GI-AP1000-PSA-01. Success Criteria for the Probabilistic Risk Assessment (PSA) Westinghouse UK AP1000 GENERIC DESIGN ASSESSMENT Success Criteria for the Probabilistic Risk Assessment (PSA) MAIN ASSESSMENT AREA RELATED ASSESSMENT AREA(S) RESOLUTION PLAN REVISION GDA ISSUE REVISION

More information

Technical Challenges Associated with Shutdown Risk when Licensing Advanced Light Water Reactors

Technical Challenges Associated with Shutdown Risk when Licensing Advanced Light Water Reactors Technical Challenges Associated with Shutdown Risk when Licensing Advanced Light Water Reactors Marie Pohida a1, Jeffrey Mitman a a United States Nuclear Regulatory Commission, Washington, DC, USA Abstract:

More information

Lessons Learned from Fukushima-Daiichi Accident (Safety Measures and PSA Utilization)

Lessons Learned from Fukushima-Daiichi Accident (Safety Measures and PSA Utilization) PSAM12 2013 Tokyo Lessons Learned from Fukushima-Daiichi Accident (Safety Measures and PSA Utilization) April 15, 2013 Akio Komori (Takafumi Anegewa) Tokyo Electric Power Company All Rights Reserved 2013The

More information

The Nuclear Crisis in Japan

The Nuclear Crisis in Japan The Nuclear Crisis in Japan March 21, 2011 Daniel Okimoto Alan Hanson Kate Marvel The Fukushima Daiichi Incident 1. Plant Design 2. Accident Progression 3. Radiological releases 4. Spent fuel pools " Fukushima

More information

The Fukushima Daiichi Incident

The Fukushima Daiichi Incident The data and information contained herein are provided solely for informational purposes. None of the information or data is intended by AREVA to be a representation or a warranty of any kind, expressed

More information

Critical Issues Concerned with the Assessment of Passive System Reliability

Critical Issues Concerned with the Assessment of Passive System Reliability IAEA Technical Meeting on Probabilistic Safety Assessment for New Nuclear Power Plants Design Vienna, October 1-5 2012 Critical Issues Concerned with the Assessment of Passive System Reliability Luciano

More information

PWR and BWR plant analyses by Severe Accident Analysis Code SAMPSON for IMPACT Project

PWR and BWR plant analyses by Severe Accident Analysis Code SAMPSON for IMPACT Project GENES4/ANP2003, Sep. 15-19, 2003, Kyoto, JAPAN Paper 1074 PWR and BWR plant analyses by Severe Accident Analysis Code SAMPSON for IMPACT Project Hiroshi Ujita 1*, Yoshinori Nakadai 2, Takashi Ikeda 3,

More information

Effects of Source Term on Off-site Consequence in LOCA Sequence in a Typical PWR

Effects of Source Term on Off-site Consequence in LOCA Sequence in a Typical PWR Effects of Source Term on Off-site Consequence in LOCA Sequence in a Typical PWR Seok-Jung HAN a, Tae-Woon KIM, and Kwang-Il AHN a Korea Atomic Energy Research Institute, P.O. Box 105, Yuseong, Daejeon,

More information

ÚJV Řež, a. s. Research Needs for. Improvement of Severe. Accident Management. Strategies at Czech NPPs. Jiří Duspiva

ÚJV Řež, a. s. Research Needs for. Improvement of Severe. Accident Management. Strategies at Czech NPPs. Jiří Duspiva ÚJV Řež, a. s. Research Needs for Improvement of Severe Accident Management Strategies at Czech NPPs Jiří Duspiva International Experts Meeting on Strengthening Research and Development Effectiveness in

More information

The Risk of Nuclear Power

The Risk of Nuclear Power 13 th International Conference on Probabilistic Safety Assessment and Management [PSAM13] The Risk of Nuclear Power Soon Heung Chang Handong Global University Oct 4, 2016 Contents 1 2 3 4 Introduction:

More information

Nuclear Safety. Lecture 3. Beyond Design Basis Accidents Severe Accidents

Nuclear Safety. Lecture 3. Beyond Design Basis Accidents Severe Accidents Nuclear safety Lecture 3. Beyond Design Basis Accidents Severe Accidents Ildikó Boros Prof. Dr. Attila Aszódi Budapest University of Technology and Economics Institute of Nuclear Techniques (BME NTI) 1

More information

Modeling and Analysis of In-Vessel Melt Retention and Ex-Vessel Corium Cooling in the U. S.

Modeling and Analysis of In-Vessel Melt Retention and Ex-Vessel Corium Cooling in the U. S. Modeling and Analysis of In-Vessel Melt Retention and Ex-Vessel Corium Cooling in the U. S. E. L. Fuller, S. Basu, and H. Esmaili Office of Nuclear Regulatory Research United States Nuclear Regulatory

More information

Plant-Specific Uncertainty Analysis for a Severe Accident Pressure Load Leading to a Late Containment Failure

Plant-Specific Uncertainty Analysis for a Severe Accident Pressure Load Leading to a Late Containment Failure Plant-Specific Uncertainty Analysis for a Severe Accident Pressure Load Leading to a Late Containment Failure S.Y.Park a* and K.I.Ahn a a Korea Atomic Energy Research Institute, Daeduk-Daero 989-111, Yusong,

More information

Supporting Deterministic T-H Analyses for Level 1 PSA

Supporting Deterministic T-H Analyses for Level 1 PSA Supporting Deterministic T-H Analyses for Level 1 PSA ABSTRACT SLAVOMÍR BEBJAK VUJE, a.s. Okružná 5 918 64 Trnava, Slovakia slavomir.bebjak@vuje.sk TOMÁŠ KLIMENT VUJE, a.s. Okružná 5 918 64 Trnava, Slovakia

More information

Deterministic Safety Analyses for Human Reliability Analysis

Deterministic Safety Analyses for Human Reliability Analysis Deterministic Safety Analyses for Human Reliability Analysis Andrej Prošek Reactor Engineering Division Jožef Stefan Institute, Slovenia Marko Čepin Faculty of Electrical Engineering University of Ljubljana,

More information

Enhancement of Nuclear Safety

Enhancement of Nuclear Safety Enhancement of Nuclear Safety Soon Heung Chang Handong Global University May 6, 2015 Contents 1 2 3 4 Importance of Energy Fundamentals of Nuclear Safety How to Enhance Nuclear Safety Closing Remarks 2

More information

PROBABILISTIC SAFETY ANALYSIS IN SAFETY MANAGEMENT OF NUCLEAR POWER PLANTS

PROBABILISTIC SAFETY ANALYSIS IN SAFETY MANAGEMENT OF NUCLEAR POWER PLANTS PROBABILISTIC SAFETY ANALYSIS IN SAFETY MANAGEMENT OF NUCLEAR POWER PLANTS 1 GENERAL 3 2 PSA DURING THE DESIGN AND CONSTRUCTION OF A NPP 3 2.1 Probabilistic design objectives 3 2.2 Design phase 4 2.3 Construction

More information

The Fukushima Daiichi Incident Dr. Matthias Braun - 16 November p.1

The Fukushima Daiichi Incident Dr. Matthias Braun - 16 November p.1 Dr. Matthias Braun - 16 November 2012 - p.1 The Fukushima Daiichi Incident 1. Plant Design 2. Accident Progression 3. Radiological releases 4. Spent fuel pools 5. Sources of Information Matthias Braun

More information

Corium Retention Strategy on VVER under Severe Accident Conditions

Corium Retention Strategy on VVER under Severe Accident Conditions NATIONAL RESEARCH CENTRE «KURCHATOV INSTITUTE» Corium Retention Strategy on VVER under Severe Accident Conditions Yu. Zvonarev, I. Melnikov National Research Center «Kurchatov Institute», Russia, Moscow

More information

Seismic Margin Assessment for Nuclear Facilities of Kozloduy NPP

Seismic Margin Assessment for Nuclear Facilities of Kozloduy NPP Proceedings of the 10 th International Conference on Nuclear Option in Countries with Small and Medium Electricity Grids Zadar, Croatia, 1-4 June 2014 Paper No. 121 Seismic Margin Assessment for Nuclear

More information

Fukushima Event PCTRAN Analysis. Dr. LI-Chi Cliff Po. Dr. LI-Chi Cliff Po. March 25, 2011

Fukushima Event PCTRAN Analysis. Dr. LI-Chi Cliff Po. Dr. LI-Chi Cliff Po. March 25, 2011 Fukushima Event PCTRAN Analysis Dr. LI-Chi Cliff Po Fukushima Event PCTRAN Analysis Dr. LI-Chi Cliff Po 1. Description of Event March 25, 2011 The earthquake caused instant loss of offsite power. The scale-9

More information

A Methodology for Spent Fuel Pool Internal Events Level 1 and Level 2 PRA for APR1400

A Methodology for Spent Fuel Pool Internal Events Level 1 and Level 2 PRA for APR1400 A Methodology for Spent Fuel Pool Internal Events Level 1 and Level 2 PRA for APR1400 Taehee Hwang 1, Inn Seock Kim 2, Jaegap Kim 3 1 KEPCO E&C, Integrated Safety Assessment Department, Gyeongsangbuk-do,

More information

THE ASSESSMENT OF LOW PROBABILITY CONTAINMENT FAILURE MODES USING DYNAMIC PRA DISSERTATION

THE ASSESSMENT OF LOW PROBABILITY CONTAINMENT FAILURE MODES USING DYNAMIC PRA DISSERTATION THE ASSESSMENT OF LOW PROBABILITY CONTAINMENT FAILURE MODES USING DYNAMIC PRA DISSERTATION Presented in Partial Fulfillment of the Requirements for the Degree Doctor of Philosophy in the Graduate School

More information

THE ROLE OF PASSIVE SYSTEMS IN ENHANCING SAFETY AND PREVENTING ACCIDENTS IN ADVANCED REACTORS

THE ROLE OF PASSIVE SYSTEMS IN ENHANCING SAFETY AND PREVENTING ACCIDENTS IN ADVANCED REACTORS THE ROLE OF PASSIVE SYSTEMS IN ENHANCING SAFETY AND PREVENTING ACCIDENTS IN ADVANCED REACTORS M. Aziz Nuclear and radiological regulatory authority Cairo, Egypt moustafaaaai@yahoo.com Abstract Most of

More information

ACCIDENT SEQUENCE PRECURSOR PROGRAM LARGE EARLY RELEASE FREQUENCY MODEL DEVELOPMENT*

ACCIDENT SEQUENCE PRECURSOR PROGRAM LARGE EARLY RELEASE FREQUENCY MODEL DEVELOPMENT* ACCIDENT SEQUENCE PRECURSOR PROGRAM LARGE EARLY RELEASE FREQUENCY MODEL DEVELOPMENT* Douglas A. Brownson Idaho National Engineering and Environmental Laboratory P.O. Box 1625, MS 3850 Idaho Falls, ID 83415-3850

More information

Nuclear Engineering and Technology

Nuclear Engineering and Technology Nuclear Engineering and Technology 48 (2016) 1174e1183 Available online at ScienceDirect Nuclear Engineering and Technology journal homepage: www.elsevier.com/locate/net Original Article Investigation

More information

NURETH Progress on Severe Accident Code Benchmarking in the Current OECD TMI-2 Exercise

NURETH Progress on Severe Accident Code Benchmarking in the Current OECD TMI-2 Exercise NURETH-15 544 Progress on Severe Accident Code Benchmarking in the Current OECD TMI-2 Exercise G. Bandini (ENEA), S. Weber, H. Austregesilo (GRS), P. Drai (IRSN), M. Buck (IKE), M. Barnak, P. Matejovic

More information

Licensing of New Build Reactors in the UK Part 2

Licensing of New Build Reactors in the UK Part 2 Licensing of New Build Reactors in the UK Part 2 Keith Ardron UK Licensing Manager, UK Imperial College Nuclear Thermalhydraulics Course: February 2014 Contents Role of Safety Authorities & Technical Support

More information

IAEA Training in level 1 PSA and PSA applications. Other PSA s. Low power and shutdown PSA

IAEA Training in level 1 PSA and PSA applications. Other PSA s. Low power and shutdown PSA IAEA Training in level 1 PSA and PSA applications Other PSA s Low power and shutdown PSA Content Why shutdown PSA? Definitions Plat damage states and Plant operational states Specific modelling tasks of

More information

Source terms designate typical environmental releases of radioactive substances,

Source terms designate typical environmental releases of radioactive substances, 1 2 Source term evaluation studies for PWRs J. FLEUROT (IRSN) J.-M. EVRARD (IRSN) B. CHAUMONT (IRSN) Source terms designate typical environmental releases of radioactive substances, which are also the

More information

IAEA, Vienna, October

IAEA, Vienna, October IAEA, Vienna, 21-23 October 2013 1 SEVERE ACCIDENT ACTIVITIES IN BELGIUM Use of Source Term for Regulatory and Design Applications Technical Meeting on Source Term Evaluation for Severe Accidents 21-23

More information

Experiences from Application of MELCOR for Plant Analyses. Th. Steinrötter, M. Sonnenkalb, GRS Cologne March 2nd, 2010

Experiences from Application of MELCOR for Plant Analyses. Th. Steinrötter, M. Sonnenkalb, GRS Cologne March 2nd, 2010 Experiences from Application of MELCOR 1.8.6 for Plant Analyses Th. Steinrötter, M. Sonnenkalb, GRS Cologne March 2nd, 2010 Content Introduction MELCOR 1.8.6 Analyses for the Atucha II Power Plant Modeling

More information

NSSS Design (Ex: PWR) Reactor Coolant System (RCS)

NSSS Design (Ex: PWR) Reactor Coolant System (RCS) NSSS Design (Ex: PWR) Reactor Coolant System (RCS) Purpose: Remove energy from core Transport energy to S/G to convert to steam of desired pressure (and temperature if superheated) and moisture content

More information

ICONE ADAM: AN ACCIDENT DIAGNOSTIC, ANALYSIS AND MANAGEMENT SYSTEM APPLICATIONS TO SEVERE ACCIDENT SIMULATION AND MANAGEMENT

ICONE ADAM: AN ACCIDENT DIAGNOSTIC, ANALYSIS AND MANAGEMENT SYSTEM APPLICATIONS TO SEVERE ACCIDENT SIMULATION AND MANAGEMENT Proceedings of ICONE 10: 10TH International Conference on Nuclear Engineering Arlington, VA, USA, April 14-18, 2002 ICONE10-22195 ADAM: AN ACCIDENT DIAGNOSTIC, ANALYSIS AND MANAGEMENT SYSTEM APPLICATIONS

More information

Source Term modeling for CANDU reactors

Source Term modeling for CANDU reactors Source Term modeling for CANDU reactors IAEA Technical Meeting on Source term Evaluation for Severe Accidents October 21-23, 2013 Objectives of presentation To provide overview of the current state in

More information

In Vessel Retention Strategy VVER 1000/320 VVER 2013 Conference

In Vessel Retention Strategy VVER 1000/320 VVER 2013 Conference ÚJV Řež, a. s. In Vessel Retention Strategy VVER 1000/320 VVER 2013 Conference J. Zdarek Presentation content Background of SA issues VVER 1000/320 Containment and RPV Cavity Configuration IVR Strategy

More information

Recent progress in source term research and evaluations with the ASTEC code

Recent progress in source term research and evaluations with the ASTEC code Enhancing nuclear safety Recent progress in source term research and evaluations with the ASTEC code Jacquemain D., Vola D., Cantrel L., Chevalier-Jabet K., Mun C. IRSN Nuclear Safety Division 8 th International

More information

Verification and Validation of SAMGs

Verification and Validation of SAMGs Verification and Validation of SAMGs SAMG-D Toolkit, Module 3, Chapter 7 Martin Gajdoš Nuclear Engineering, Slovenské elektrárne IAEA Workshop on the Development of Severe Accident Mitigation Guidelines

More information

Ensuring Spent Fuel Pool Safety

Ensuring Spent Fuel Pool Safety Ensuring Spent Fuel Pool Safety Michael Weber Deputy Executive Director for Operations U.S. Nuclear Regulatory Commission American Nuclear Society Meeting June 28, 2011 1 Insights from Fukushima Nuclear

More information

Study on Severe Accident Progression and Source Terms in Fukushima Dai-ichi NPPs

Study on Severe Accident Progression and Source Terms in Fukushima Dai-ichi NPPs Study on Severe Accident Progression and Source Terms in Fukushima Dai-ichi NPPs October 27, 2014 H. Hoshi, R. Kojo, A. Hotta, M. Hirano Regulatory Standard and Research Department, Secretariat of Nuclear

More information

Guidance on the Use of Deterministic and Probabilistic Criteria in Decision-making for Class I Nuclear Facilities

Guidance on the Use of Deterministic and Probabilistic Criteria in Decision-making for Class I Nuclear Facilities DRAFT Regulatory Document RD-152 Guidance on the Use of Deterministic and Probabilistic Criteria in Decision-making for Class I Nuclear Facilities Issued for Public Consultation May 2009 CNSC REGULATORY

More information

Simulation of thermal hydraulics accidental transients: evaluation of MAAP5.02 versus CATHAREv2.5

Simulation of thermal hydraulics accidental transients: evaluation of MAAP5.02 versus CATHAREv2.5 1/12 Simulation of thermal hydraulics accidental transients: evaluation of MAAP5.02 versus CATHAREv2.5 J. Bittan¹ 1) EDF R&D, Clamart (F) Summary MAAP is a deterministic code developed by EPRI that can

More information

The NRC s SPAR Models: Current Status, Future Development, and Modeling Issues

The NRC s SPAR Models: Current Status, Future Development, and Modeling Issues INL/CON-08-14484 PREPRINT The NRC s SPAR Models: Current Status, Future Development, and Modeling Issues ANS PSA 2008 Topical Meeting Richard R. Sherry Peter L. Appignani Robert F. Buell September 2008

More information

State of the Art and Challenges in Level-2 Probabilistic Safety Assessment for New and Channel Type Reactors in India Abstract

State of the Art and Challenges in Level-2 Probabilistic Safety Assessment for New and Channel Type Reactors in India Abstract State of the Art and Challenges in Level-2 Probabilistic Safety Assessment for New and Channel Type Reactors in India R.S. Rao, Avinash J Gaikwad, S. P. Lakshmanan Nuclear Safety Analysis Division, Atomic

More information

The Fukushima Daiichi Incident Dr. Matthias Braun - 19 May p.1

The Fukushima Daiichi Incident Dr. Matthias Braun - 19 May p.1 Dr. Matthias Braun - 19 May 2011 - p.1 The Fukushima Daiichi Incident 1. Plant Design 2. Accident Progression 3. Radiological releases 4. Spent fuel pools 5. Sources of Information Matthias Braun PEPA4-G,

More information

Chemical Engineering 693R

Chemical Engineering 693R Chemical Engineering 693R Reactor Design and Analysis Lecture 11 Nuclear Safety Spiritual Thought 2 2 Kings 6:16 And he answered, Fear not: for they that be with us are more than they that be with them.

More information

Safety Principles and Defence-in-Depth concept implemented in German Regulations

Safety Principles and Defence-in-Depth concept implemented in German Regulations Safety Principles and Defence-in-Depth concept implemented in German Regulations Shanna Eismar, GRS 04 October 2016 IAEA Technical Meeting on Novel Design and Safety Principles of Nuclear Power Plants

More information

SYSTEMATIC AND DESIGN SAFETY IMPROVEMENTS OF NPPS IN CZECH REPUBLIC

SYSTEMATIC AND DESIGN SAFETY IMPROVEMENTS OF NPPS IN CZECH REPUBLIC SYSTEMATIC AND DESIGN SAFETY IMPROVEMENTS OF NPPS IN CZECH REPUBLIC 3.10.2016 ČEZ, a. s. Meeting at IAEA Vienna Overview of topics ČEZ nuclear fleet (basic features) Systematic measures targeted to improve

More information

LFW-SG ACCIDENT SEQUENCE IN A PWR 900: CONSIDERATIONS CONCERNING RECENT MELCOR / CALCULATIONS

LFW-SG ACCIDENT SEQUENCE IN A PWR 900: CONSIDERATIONS CONCERNING RECENT MELCOR / CALCULATIONS LFW-SG ACCIDENT SEQUENCE IN A PWR 900: CONSIDERATIONS CONCERNING RECENT MELCOR 1.8.5 / 1.8.6 CALCULATIONS F. DE ROSA ENEA FIS NUC - Bologna 1 st EUROPEAN MELCOR USERS GROUP Villigen, Switzerland 15-16

More information