Gas Networks Ireland Renewable Natural Gas Connections Policy Proposals

Size: px
Start display at page:

Download "Gas Networks Ireland Renewable Natural Gas Connections Policy Proposals"

Transcription

1 An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities Gas Networks Ireland Renewable Natural Gas Connections Policy Proposals Commission for Regulation of Utilities Consultation Decision Paper Reference: CRU18089 Date Published: 16/05/2018 Closing Date: N/A 0

2 Executive Summary The Commission for Regulation of Utilities (CRU) is Ireland s independent energy and water regulator. The CRU was established in 1999 and now has a wide range of economic, customer protection and safety responsibilities in energy. The CRU is also the regulator of Ireland s public water and wastewater system. The CRU is today, 16 May 2018, publishing a decision on proposals submitted by Gas Networks Ireland (GNI) to the CRU to amend the current GNI Connections Policy. The amendments proposed to allow for the following: (i) the connection of renewable natural gas facilities to the natural gas network; and (ii) the appraisal of group sites as part of the GNI Connections Policy. The CRU published a consultation (CRU/17/297) 1 on the above proposals which had been submitted by GNI to the CRU in September The consultation closed on 21 November The CRU received 10 responses to CRU/17/297. The consultation on the above proposals from GNI follows the CRU paper Renewable Natural Gas Bridging Paper 2, published in The paper requested that GNI prepare proposals to allow for the inclusion of renewable natural gas 3 facilities into the existing GNI Connections Policy. In response, in 2017 GNI prepared proposals for the connection of renewable natural gas facilities to the natural gas network, which are now the subject of this decision. In addition, GNI also requested that the appraisal of group sites for connection to the gas network also be reviewed, currently sites for connection are appraised individually. Grouping sites belonging to the same entity is a potential method of assessing the 1 CRU/17/297-Connections-Policy Consultation Sustainably produced or purified Renewable Natural Gas (RNG) includes gas types such as; Biomethane, Synthetic Methane, Methanised Hydrogen, Natural Gas blended Hydrogen, egas/p2g, Green Gas, etc. 1

3 connection of a number of different sites as a whole instead of separately. The CRU previously rejected the proposal to connect group sites in 2015, stating that it was not convinced that the absence of such a policy would result in lost opportunities. However, the CRU committed to keeping the proposal under review. In CRU/17/297, the CRU sought the views of respondents relating to the proposals submitted by GNI. These were: 1. If a 15 year assessment period proposed by GNI is appropriate. 2. If seven years of financial security is appropriate. 3. If GNI s view that the appraisal is based on 100% of costs associated with transmission and distribution entry revenue and 50% of transmission exit revenue and 50% of distribution exit revenue associated with the connection is appropriate If the upfront customer contribution of 30% is appropriate. 5. Whether the proposal regarding group sites is appropriate and should be included in the GNI Connections Policy. Taking account of the responses received, the CRU has decided that the following rules will apply regarding the connection of renewable natural gas facilities. The economic viability of renewable natural gas connections will be assessed and recovered over a ten year period. Financial security will be required for seven years. The CRU has decided that the existing connection charges as outlined in the GNI Connections Policy will apply for renewable natural gas facilities. Renewable natural gas facilities will pay a 30% upfront connection cost with the remainder recouped over ten years 5. 4 In this context it is worth recalling that entry is at the point where renewable natural gas/natural gas is injected into the system and exit is where renewable natural gas/natural gas is taken off the system by customers. 5 GNI will perform an economic test to determine whether such connections are economically viable. Where the economic test shows the proposed connection will not meet the requirements set out above, the connecting party will pay a supplemental charge to connect to the natural gas network.. 2

4 The CRU has not approved the appraisal of group sites. 3

5 Public/ Customer Impact Statement Renewable gas has the potential to decrease the carbon intensity of the gas network and can also assist in the security of supply of gas. In recognition of this, the CRU requested that GNI prepare a connections policy for the connection of renewable gas facilities to the natural gas network. The availability of renewable gas will allow users of the natural gas network to decrease their carbon intensity and assist Ireland as it moves to a low carbon economy. Renewable gas is a sustainable source that could assist in the continued utilisation of the natural gas network which in turn could help maintain tariffs, so that gas remains a competitive fuel source for all gas customers. The CRU regulates the activities of GNI and gas undertakings with respect to safety under the Gas Safety Framework (GSF). The connection of renewable gas facilities to the natural gas network is not covered under the current version of the GSF Safety Case Guidelines. The CRU is currently updating the guidelines to reflect this change in order to ensure that the associated risks are properly managed. 4

6 Table of Contents Table of Contents... 5 Glossary of Terms and Abbreviations Rationale for consultation Background... 7 Renewable Gas... 7 Legislative Basis... 8 Structure of Paper GNI Proposals Proposal for consideration... 9 Group Sites Consultation responses Respondent comments Assessment and recovery period proposed Financial Security Proposal Connection costs Upfront payment Group sites CRU decisions and next steps

7 Glossary of Terms and Abbreviations Abbreviation or Term Definition or Meaning BGE CRU GNI GSF I&C NPV Bord Gáis Energy Commission for Regulation of Utilities Gas Networks Ireland Gas Safety Framework Industrial and Commercial Net Present Value PC5 Price Control 5 WDC Western Development Commission 6

8 1. Rationale for consultation 1.1 Background Renewable Gas In 2013, the CRU published a consultation paper on Biogas injection into the Natural Gas Grid (CER/13/209) 6, which sought the views of the public and industry as to the facilitation of the injection of renewable gas into the natural gas network in Ireland. In October 2016, the CRU published the Renewable Natural Gas Bridging Paper 7. In this bridging paper, the CRU requested that GNI prepare proposals to allow for the inclusion of renewable gas facilities into the existing GNI Connections Policy. In response, GNI submitted proposals for the connection of renewable gas facilities to the natural gas network in September In October 2017, the CRU published a consultation on the proposals submitted by GNI. Within the proposals submitted by GNI, GNI also proposed that the appraisal of group sites for connection to the natural gas network is reviewed, currently sites are appraised individually. Grouping sites is a potential method of assessing the connection of a number of different sites belonging to the same entity as a whole instead of separately. GNI contend that such a method of appraisal could result in a decrease in administration and potentially increase gas throughput and hence place downward pressure on gas tariffs. The CRU previously rejected the connection of group sites in 2015, stating that it was not convinced that the absence of such a policy would result in lost opportunities. However, the CRU committed to keeping the proposal under review. The consultation sought comments on the GNI proposals regarding the appraisal of group sites. In October 2017, the CRU published CRU/17/297 which sought responses from the public on the GNI proposals regarding the connection of renewable natural gas Paper.pdf 7

9 facilities to the natural gas network. CRU/17/297 closed on 22 November 2017, the CRU received 10 responses. Legislative Basis Under Section 9 of the Electricity Regulation Act 1999 (as amended), the CRU is to have regard to the need to ensure that grid connection policy takes account of renewable energy policy, including any such policy in relation to community energy projects. Information on the CRU s role and relevant legislation can be found on the CRU s website at Structure of Paper The structure of this paper is set out as follows: Section 1: Introduction. Section 2: Gas Networks Ireland connections policy proposals. Section 3: Consultation responses. Section 4: CRU decision and next steps. 8

10 2. GNI Proposals 2.1 Proposal for consideration GNI made a number of key proposals regarding the connection of renewable natural gas facilities to the natural gas network, these are: 1. That connection costs are recovered over a 15 year period i.e. the costs of connecting to the gas network are assessed and recovered over a 15 year period from the date of connection. 2. That the appraisal is based on 100% of the connection costs associated with transmission and distribution. GNI proposed that exit transmission and distribution revenues associated with the renewable natural gas connection are included as revenue in the appraisal. GNI also proposed that 50% of transmission exit revenue and 50% of distribution exit revenue will be associated with the connection. 8 GNI s rationale for using 50% of the transmission and distribution exit revenue is that it is a conservative estimate of the increased demand in the long term. This is because GNI consider that the introduction of renewable gas will be linked in increased gas consumption. 3. That 30% of the total connection cost is to be paid upfront by the producer with the remaining 70% recovered over a 15 year period. 4. That financial security 9 is provided for the initial seven years by the producer to cover the costs of the network connection. Financial security will limit the risk to the general gas customer in the event that a renewable gas facility ceases injecting renewable gas into the natural gas network before year seven. GNI did not propose seeking financial security for the period thereafter. 8 Entry is at the point where renewable natural gas/natural gas is injected into the system and exit is where renewable natural gas/natural gas is taken off the system by customers. 9 operations/related-documents/financial-security-policy-(amendments-for-legal-go-live)_version-3-1.pdf 9

11 Group Sites GNI is of the view that it would be advantageous for new customers with multiple sites to have those sites appraised as a group so that the portfolio benefit of connecting a group of sites could be recognised. GNI proposed that group sites which are owned by the same entity but are situated in different locations should be appraised together and that the economic test 10 would be appraised over seven years. If the treatment of group sites (same entity, different locations/sites) was formalised via a connections policy change, this would result in the sites being appraised together so that the overall Net Present Value (NPV) is taken into account rather than the individual NPVs for each site, which is the approach taken in the current connections policy. In addition, under the one appraisal one total contribution from the customer(s) would be sought to cover the connection of all of the sites within the group. 10 The economic test would evaluate the present value of the total cost of the group connection (as defined above plus operating costs, but less the standard 30% contribution) against the present value of the tariff revenue attributable to the facility. The present value in both cases will be evaluated over a 7-year time horizon and using GNI s regulated rate of return as the discount rate. 10

12 3. Consultation responses Following closure of the consultation, the CRU received 10 responses. The CRU received responses from the following: Alchemy Utilities. Bord Gáis Energy. Composting and Anaerobic Digestion Association of Ireland. Diageo. Dr Pau Farràs Costa, NUI Galway. Energia. Fingleton White. GenComm. Renewable Gas Forum. Western Development Commission. 11

13 The CRU sought specific comment from interested parties regarding the following: 1. The assessment period of 15 years proposed by GNI. 2. The level of financial security proposed by GNI. 3. The GNI view regarding the appraisal being based on 100% of costs associated with transmission and distribution entry revenues and 50% of transmission and distribution exit revenues. 4. The upfront customer contribution proposed by GNI. 5. Whether the proposal regarding group sites is appropriate and should be included in the GNI Connections Policy. 3.1 Respondent comments The CRU received 10 responses to the consultation. In general, respondents were supportive of a renewable natural gas connections policy proposal and the group sites proposal from GNI. The Western Development Commission (WDC) outlined concerns that reviews of the GNI Connections Policy only take place on an ad hoc basis based on submissions from the network operator. WDC is of the view that the CRU, in consultation with the Department of Communication, Climate Action and Environment (DCCAE) and the public should hold regular reviews of the connections policy. The CRU notes that the both the DCCAE and the public can provide written responses to any CRU consultation. The CRU further notes that this decision paper focuses on the connection of renewable natural as facilities and not a review of the GNI Connections Policy as a whole. 12

14 Assessment and recovery period proposed GNI proposed to assess the economic viability of renewable natural gas connections over 15 years. GNI is of the view that a 15 year time horizon is appropriate given the assumed lifespan for a renewable gas facility. GNI carried out analysis on the components of the injection facility to ascertain the technical lives of the equipment. The technical lives of the components of the renewable gas injection facility range from 8 years to 25 years with an average of 18.5 years. Given this, GNI is of the view that 15 years is an appropriate lifespan for a renewable gas facility. As an alternative, GNI proposed that the assessment and recovery period could be linked to the length of time of any support scheme in place. GNI in their proposal outlined that DCCAE was developing a Renewable Heat Incentive (RHI) 11 support scheme. GNI stated in their submission it was not known how long the scheme would run for but suggested that the evaluation period could be linked to the duration of support provided by the RHI when it is in place. Consultation Responses The majority of respondents are of the view that a 15 year assessment period is appropriate for the connections of renewable natural gas facilities. Two respondents, in recognition of the CRU s concerns outlined that they could support an assessment period of years or a ranging assessment period from 7-15 years with a larger upfront payment in instances where the project is assessed over a 15 year period. One respondent suggested that the CRU consider the potential of increasing the % contribution to enable a 15 year assessment and recovery period. CRU Response While noting the environmental benefits e.g. decreasing emissions in energy, transport and waste sectors that renewable gas may bring, the CRU is of the view that the assessment period proposed by GNI is too long. The CRU views a 15 year assessment period as too great a risk (when financial security ceases at year seven) 11 Now referred to as the Support Scheme for Renewable Heat: ew.pdf 13

15 for the general gas customer who will underwrite any shortfall if a renewable gas facility ceases production prior to year 15. In addition, the CRU notes that the existing GNI Connections Policy 12 assesses small Industrial and Commercial (I&C) connections over a seven year period. However, the CRU notes the text in the Recast Renewable Energy Directive 13 which states that the costs of connecting new producers of gas from renewable energy sources to the gas grids should be based on objective, transparent and nondiscriminatory criteria and due account should be taken of the benefit that local producers of gas from renewable sources bring to the gas grids. In addition, the CRU notes the reference to natural gas vehicles in the DCCAE paper Ireland s Transition to a Low Carbon Energy Future 14 and the use of renewable natural gases in the transport sector. The CRU also notes the commitment of the Department of Tourism, Transport, and Sport (DTTAS) with regard to Compressed Natural Gas (CNG) 15 and the potential of renewable natural gas to be used in CNG vehicles. Given the wider benefits outlined above and noting both the DCCAE White Paper and the DTTAS Alternative Fuel National Framework Policy, the CRU is of the view that a ten year assessment period is appropriate to ensure that Ireland is in a position to transition to a low carbon economy by Financial Security Proposal 12 Policy-v4.1-effective-01-October-2015-reflecting-CER-approved-changes.pdf

16 GNI proposed that financial security should be in place for seven years with the economic viability of the connection assessed over 15 years. Consultation Responses The majority of respondents are of the view that GNI s proposal regarding financial security being in place for seven years is appropriate. Respondents outlined that extending the financial security period will likely create a barrier to such projects. Bord Gáis Energy stated that financial security should be linked to the assessment period. CRU Response The CRU recognises the benefit that renewable gas will have to large users of natural gas who aim to reduce their carbon emissions by switching from natural gas to renewable natural gas. The CRU does not view an eight year gap in financial security as an appropriate risk for the general gas customer to bear. This is due to the CRU s view that in the short term renewable gas is likely to be consumed by large users of heat only and not the general gas customer. Given this, the CRU views the financial exposure of all gas customers as inequitable, particularly when they are unlikely to be in a position to gain a direct benefit (in this case, the consumption of renewable natural gas). The CRU is cognisant that this could change, as the percentage of renewable natural gas increases in the natural gas network. With this in mind, the CRU will monitor the demand and consumption of renewable natural gas by various customer groups. Given the concerns outlined above, the CRU has decided that financial security will be required for seven years. The CRU recognises that this places a potential risk to the general gas customer of an increase in gas tariffs if a renewable natural gas facility ceases production before year ten. However, the CRU views this risk as acceptable to ensure that renewable gas facilities are facilitated in their attempts to connect to the natural gas network which will assist in the continued utilisation of the gas network. In addition, the CRU recognises the potential security of supply benefit that such connections may bring. In their 2017 Network Development Plan, GNI outline that renewable natural gas has the potential to satisfy over 20% of Ireland s gas demand 15

17 by Given the low level of renewable natural gas facilities connecting to the gas network in the next number of years, the CRU understands that a total of three will connect to the natural gas network by 2020, any potential risk to the general gas customer will be relatively small (approx. 200,000 per plant). The CRU will keep this under review as the number of renewable natural gas facilities increase and may decide to link the assessment period to the level of financial security required. The CRU commits to reviewing this during the next Price Control (PC5) which will take place in Any decision to link the assessment period to the level of financial security will be based on the performance of renewable natural gas facilities. Connection costs GNI proposed that it would be appropriate for the appraisal to be based on 100% of the connection costs associated with transmission and distribution, 100% of the entry revenue from the connection, 50% of transmission exit revenue and 50% of distribution exit revenue associated with the connection. GNI s rationale for using 50% of the transmission and distribution exit revenue is that GNI deem that this is a conservative estimate of the increased demand in the long term. 17 GNI considers it likely that renewable gas will be supplied to new sources of gas demand initially. However, as the percentage of renewable gas in the gas network grows it is likely that renewable gas will start to be consumed by customers that had been consuming natural gas i.e. renewable gas will result in a reduction in natural gas consumption. It is GNI s view that the NPV calculation takes account of 50% of transmission and distribution exit revenues to strike a balance between the new demand being created now and the existing demand that will transition to renewable gas in the future Entry is at the point where renewable natural gas/natural gas is injected into the system and exit is where renewable natural gas/natural gas is taken off the system by customers. 16

18 Consultation responses In general, respondents agreed with GNI s proposal. Bord Gáis Energy (BGE) outlined that it was not clear what the expected demand growth for renewable natural gas is and what it is based on. Analysis conducted by the ESRI suggests that gas demand will grow by circa. 20% out to 2050, albeit at a lesser rate than would be expected if Ireland did not decarbonize. Given this, BGE is if the view that it is appropriate to assume some growth in demand as part of the economic test. CRU response The CRU is not convinced that any incremental demand growth should be considered to result from renewable natural gas injection to the extent that it should be included as an assumption in an economic test. The CRU is of the view that if total gas demand remains static then renewable gas will not result in increased gas throughput, renewable gas may simply displace imported/indigenous natural gas. The CRU agrees with GNI that this policy will need to be developed as the renewable natural gas industry continues to grow. Given that the renewable gas industry is in its infancy in Ireland, the CRU has decided that existing connection charging arrangements as outlined in the GNI Connections Policy 18 will remain in place. Upfront payment GNI proposed that a 30% upfront payment should be made by the connecting party with the remainder of the costs recovered over a 15 year period. Consultation responses In general, respondents were in favour of GNI s proposal that a 30% upfront payment is provided by the party wanting to connect to the natural gas grid. Some respondents cited general European practice where a 25/75 split is in place and emphasised a 18 Policy-v4.1-effective-01-October-2015-reflecting-CER-approved-changes.pdf 17

19 preference for such a model with economic assessments conducted over a 15 year period. CRU response The CRU notes the varying upfront payments that are currently in place in different jurisdictions. The CRU notes that the proposed upfront payment is in line with existing upfront payment arrangements for connections in the GNI Connections Policy. The CRU is cognisant that a higher upfront payment may result in some renewable gas facilities not connecting to the natural gas network. The CRU is also cognisant that a higher upfront payment will result in a reduced risk of tariff variation for all gas customers. The CRU examined the potential of varying the assessment and recovery periods (7, 10, and 15 years) with upfront payment rates of 30%, 50%, and 70% respectively. As outlined earlier, the CRU is of the view that a 15 year assessment and recovery period is too long. Hence, the CRU has rejected the GNI proposal for a 15 year assessment and recovery period. In addition, the CRU is of the view that a 70% upfront payment could be a significant barrier for renewable natural gas facilities and as such is not appropriate. The CRU has decided that a 30% of the connection cost will be paid upfront by parties wishing to inject renewable natural gas into the natural gas network. The remaining 70% will be recovered through network tariffs over the following ten years 19. The CRU views this as an appropriate balance between protecting existing gas customers and facilitating renewable natural gas producers in connecting to the gas network. Group sites GNI submitted a proposal regarding the grouping of sites when seeking connection to the natural gas grid. GNI is of the view that it would be advantageous for new customers with multiple sites to have those sites appraised as a group so that the portfolio benefit of connecting a group of sites could be recognised. GNI proposed that group sites which are owned by the same entity but are situated in different locations 19 GNI will perform an economic test to determine whether such connections are economically viable. Where the economic test shows the proposed connection is not economically viable, the connecting party will have the option to pay an upfront supplemental charge. 18

20 should be appraised together and that the economic test would be appraised over seven years. If the treatment of group sites was formalised via a connections policy change, this would result in the sites being appraised together so that the overall Net Present Value (NPV) is taken into account rather than the individual NPVs for each site, which is the approach taken in the current connections policy. In addition, under the one appraisal one total contribution from the customer(s) would be sought to cover the connection of all of the sites within the group. Consultation responses Respondents who specifically referenced the group site proposal were in favour of the GNI proposal stating that measures to improve efficiency should be encouraged. BGE recognised the CRU s concerns which were outlined in CRU/17/297 and stated that to alleviate such concerns that ensuring that both and upfront payment and financial security are required. CRU response In CRU/17/297, the CRU outlined that it was not convinced that the absence of this proposal will result in significant missed opportunities. From information provided by GNI, the CRU notes that GNI assumes that it will connect approximately 60% of proposed group sites located near the natural gas network 20. The CRU is not convinced that the uptake levels assumed by GNI will be achieved. The total potential increase in gas demand estimated by GNI was 95.03GWh per annum 21. GNI did not provide any additional information to convince the CRU that such a policy will result in an increase in gas throughput. The CRU notes that the category of business used by GNI in this proposal (in this case supermarkets) did not submit a response outlining their support for such a policy. The CRU is of the view that this is not insignificant. 20 GNI did not provide specific details on the distance sites would be located from the natural gas network. 21 Approximately 0.13% of total annual gas demand based on 16/17 gas demand. 19

21 The CRU is not convinced of the benefit to all gas customers. The CRU previously rejected the proposal to connect of group sites in 2015, stating that it was not convinced that the absence of such a policy would result in lost opportunities. Given the information provided above, the CRU is of the view that the rejection of the group site proposal will not result in a significant opportunities being missed. For example, an entity with five sites (four of which are NPV positive, one of which is not), under the GNI proposal, the addition of the fifth site would make the combined effect less positive for the general gas customer. The CRU s decision in 2015 was that it was uncertain that an entity would forego the benefit of connecting the four positive sites if the fifth uneconomic site could not be connected. In any event, there is nothing to stop the entity from considering the five sites as a single group in its own evaluation of conversion to natural gas. GNI s 2017 submission did not materially address these issues, therefore the CRU sees no reason to change the policy. Given the above, the CRU has again decided to not approve the group sites proposal from GNI. The CRU commits to keeping this decision under review should robust rational data become available. 20

22 4. CRU decisions and next steps As outlined earlier, the CRU has taken account of the responses received to CRU/17/297and has decided that the following: Renewable natural gas facilities that seek connection to the natural gas network will be assessed over a ten year period. Financial security will be required for seven years. The CRU has decided that existing connection charging arrangements as outlined in the GNI Connections Policy will remain in place for renewable natural gas facilities. Renewable natural gas facilities will pay a 30% upfront cost with the remainder recouped over ten years 22. The CRU has not approved the appraisal of group sites. The CRU now requests that GNI prepare an updated connections policy to allow for the connection of renewable gas facilities to the natural gas grid. GNI will submit this updated connections policy for the CRU s acceptance. Following the CRU s acceptance of the updated GNI connections policy, GNI will publish the updated Connections Policy on the GNI website. The CRU will make a decision on a further review of the GNI Connections Policy at a later date. It is envisaged that this review will take place post GNI will perform an economic test to determine whether such connections are economically viable. Where the economic test shows the proposed connection is not economically viable, the connecting party will have the option to pay an upfront supplemental charge. 21

Gas Networks Ireland Connections Policy Proposals

Gas Networks Ireland Connections Policy Proposals An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities Gas Networks Ireland Connections Policy Proposals Commission for Regulation of Utilities Consultation Consultation Paper Reference:

More information

Renewable Natural Gas Bridging Paper. Bridging Paper

Renewable Natural Gas Bridging Paper. Bridging Paper Renewable Natural Gas Bridging Paper Bridging Paper Reference: CER/16/307 Date Published: 28/10/2016 Executive Summary In 2013, the Commission for Energy Regulation (CER) published a consultation paper

More information

Regulatory Approach to Maintaining Local Security of Supply in Electricity

Regulatory Approach to Maintaining Local Security of Supply in Electricity An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities Regulatory Approach to Maintaining Local Security of Supply in Electricity Information Paper Reference: CRU17346 Date Published: 18/12/2017

More information

Energy Supply Costs Information Paper

Energy Supply Costs Information Paper An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities Energy Supply Costs Information Paper 0 Information Paper Reference: CRU17291 Date Published: 11 th October 2017 www.cru.ie Public/

More information

RE: Renewable Gas Forum Ireland Opening Statement & Executive Summary

RE: Renewable Gas Forum Ireland Opening Statement & Executive Summary Joint Committee on Communications, Climate Action & Environment The House of the Oireachtas Service Kildare Street Dublin 2 20 th February 2018 RE: Renewable Gas Forum Ireland Opening Statement & Executive

More information

Explaining the Renewable Heat Incentive in Ireland. Frank Groome Energy in Agriculture 22 August 2017

Explaining the Renewable Heat Incentive in Ireland. Frank Groome Energy in Agriculture 22 August 2017 Explaining the Renewable Heat Incentive in Ireland Frank Groome Energy in Agriculture 22 August 2017 Why a Renewable Heat Incentive (RHI)? Meeting the 2020 Renewable Energy Target. Renewable Heat Target:

More information

Electricity and Gas Retail Markets Report Q3 2017

Electricity and Gas Retail Markets Report Q3 2017 An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities Electricity and Gas Retail Markets Report Q3 2017 Information Paper Reference: CRU 17354 Date Published: 20/12/2017 Public/ Customer

More information

ESB GWM Response to Consultation on Gas Networks Ireland s 2016 Ten Year Network Development Plan (CER/16/235)

ESB GWM Response to Consultation on Gas Networks Ireland s 2016 Ten Year Network Development Plan (CER/16/235) ESB GWM Response to Consultation on Gas Networks Ireland s 2016 Ten Year Network Development Plan (CER/16/235) Introduction ESB GWM welcomes the opportunity to respond to GNIs draft Network Development

More information

Green Source Product Verification Report 2017

Green Source Product Verification Report 2017 An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities Green Source Product Verification Report 2017 Information Paper Reference: CRU18204 Date Published: 14/09/2018 Closing Date: N/A www.cru.ie

More information

Supplier of Last Resort in Prepayment Electricity. Consultation Paper. An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities

Supplier of Last Resort in Prepayment Electricity. Consultation Paper. An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities Supplier of Last Resort in Prepayment Electricity Consultation Paper Consultation Paper Reference: CRU17333 Date Published: 07/12/2017

More information

Derogation Criteria for the High Voltage Direct Current Network Code

Derogation Criteria for the High Voltage Direct Current Network Code An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities Derogation Criteria for the High Voltage Direct Current Network Code (Commission Regulation (EU) 2016/1447) Decision Paper Reference:

More information

Interface analysis and report for incorporation and alignment of data from biomethane study into RHI workstream. Final Report. for

Interface analysis and report for incorporation and alignment of data from biomethane study into RHI workstream. Final Report. for Project Name Document Name Interface analysis and report for incorporation and alignment of data from biomethane study into RHI workstream Final Report for Sustainable Energy Authority of Ireland January

More information

Water Services Innovation Fund

Water Services Innovation Fund An Coimisiún um Rialáil Fóntais Commission for Regulation of Utilities Water Services Innovation Fund Report 2017 Information Paper Reference: CRU/17/345 Date Published: 20/12/2017 Closing Date: N/A 0

More information

Support Scheme for Renewable Heat. Scheme Overview

Support Scheme for Renewable Heat. Scheme Overview Support Scheme for Renewable Heat Scheme Overview Table of Contents Introduction... 3 Support Types... 4 Operational Support... 4 Installation Grant... 8 Page 2 Introduction 1. This document is intended

More information

Gas Networks Ireland Customer Performance Indicators Consultation Paper

Gas Networks Ireland Customer Performance Indicators Consultation Paper Gas Networks Ireland Customer Performance Indicators Consultation Paper Reference: CER/16243 Date Published: 22/08/2016 Closing Date: 19/09/2016 0 Executive Summary The Commission for Energy Regulation

More information

Review of the Suppliers Handbook

Review of the Suppliers Handbook Review of the Suppliers Handbook Decision Paper Reference: CER/17/059 Date Published: 13 April 2017 Closing Date: N/A Executive Summary Promoting Competition and Strengthening Consumer Protection The liberalisation

More information

Distribution Capital Contribution Policy

Distribution Capital Contribution Policy Distribution Capital Contribution Policy October 2017 to September 2018 First Gas Limited December 2017 First Gas Limited 1 Introduction First Gas operates 2,500km of gas transmission pipelines (including

More information

21 st November 2016 Our Ref: SCP

21 st November 2016 Our Ref: SCP National Policy Framework for Alternative Fuels Infrastructure for Transport in Ireland Climate Change Unit Department of Transport, Tourism and Sport Leeson Lane Dublin 2 21 st November 2016 Our Ref:

More information

Annex 21. Methodological tool. Tool for the demonstration and assessment of additionality. (Version )

Annex 21. Methodological tool. Tool for the demonstration and assessment of additionality. (Version ) Page 1 Methodological tool Tool for the demonstration and assessment of additionality (Version 06.0.0) 1. The use of the Tool for the demonstration and assessment of additionality is not mandatory for

More information

Update on the Smart Meter Upgrade

Update on the Smart Meter Upgrade Update on the Smart Meter Upgrade Information Paper Reference: CER/17/279 Date Published: 21 September 2017 Closing Date: N/A Smart meters are the next generation of electricity and gas meter and are being

More information

ELECTRICITY DISTRIBUTION NETWORK PLANNING AND CONNECTION

ELECTRICITY DISTRIBUTION NETWORK PLANNING AND CONNECTION ELECTRICITY DISTRIBUTION NETWORK PLANNING AND CONNECTION A National Framework for Electricity Distribution Networks MCE Standing Committee of Officials Policy Response 15 December 2008 Stakeholder consultation

More information

Electricity and Gas Retail Markets Report Q3 2018

Electricity and Gas Retail Markets Report Q3 2018 An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities Electricity and Gas Retail Markets Report Q3 2018 Information Paper Reference: CRU19014 Date Published: 14/02/2019 An Coimisiún um

More information

An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities. Decision Paper.

An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities. Decision Paper. An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities REQUEST FOR AMENDMENT (RfA) BY THE CRU OF EirGrid TSO and TSO Proposal for the Determination of LFC Blocks on the Synchronous System

More information

Sustainable Energy in Ireland. 4 th EU Biomethane Conference, Clontarf Castle, Dublin 20 th September 2018

Sustainable Energy in Ireland. 4 th EU Biomethane Conference, Clontarf Castle, Dublin 20 th September 2018 Sustainable Energy in Ireland 4 th EU Biomethane Conference, Clontarf Castle, Dublin 20 th September 2018 Overview Targets Results from economic assessment Preliminary findings for sustainability assessment

More information

Pass Through Costs for Business Electricity Customers from 1st October 2017

Pass Through Costs for Business Electricity Customers from 1st October 2017 An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities Pass Through Costs for Business Electricity Customers from 1st October 2017 Information Paper Reference: CRU 18083 Date Published:

More information

Small-Scale CDM & Bundling: Criteria, Advantages & Status

Small-Scale CDM & Bundling: Criteria, Advantages & Status Small-Scale CDM & Bundling: Criteria, Advantages & Status Need for Small-Scale CDM introduced by CDM EB to encourage the development of smaller CDM projects typically would have been less attractive in

More information

Ireland s renewable gas potential

Ireland s renewable gas potential Ireland s renewable gas potential James Browne (B.E., Ph.D.) Innovation Engineer 3 rd October 2017, AgriForValor Gas Networks Ireland Gas Networks Ireland owns, operates, develops and maintains the natural

More information

Compressed Natural Gas for transport Licensing arrangements

Compressed Natural Gas for transport Licensing arrangements Compressed Natural Gas for transport Licensing arrangements DOCUMENT TYPE: REFERENCE: DATE PUBLISHED: CLOSING DATE: RESPONSES TO: Consultation Paper D/15/051 March 25 th 2015 May 8 th 2015 bhussey@cer.ie

More information

Irish Water Capital Investments

Irish Water Capital Investments An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities Irish Water Capital Investments Monitoring Report January to June 2017 Information Paper Reference: CRU/18/057 Date Published: 04/04/2018

More information

Submission to the Electricity Authority

Submission to the Electricity Authority pwc.co.nz Submission to the Electricity Authority on Transmission Pricing Methodology: Avoided cost of transmission (ACOT) payments for distribution generation Made on behalf of 22 Electricity Distribution

More information

Eurogas Response to the CEER Public Consultation on Incentives Schemes for regulating DSOs, including for Innovation.

Eurogas Response to the CEER Public Consultation on Incentives Schemes for regulating DSOs, including for Innovation. Eurogas Response to the CEER Public Consultation on Incentives Schemes for regulating DSOs, including for Innovation. (A) Current principles and regulatory approaches 1. Is there any regulatory aim that

More information

Annual Audit of Compliance for Electricity & Gas Suppliers 2017

Annual Audit of Compliance for Electricity & Gas Suppliers 2017 An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities Annual Audit of Compliance for Electricity & Gas Suppliers 2017 Information Paper Reference: CRU17355 Date Published: 20/12/2017 0

More information

Retail and Reducing Energy Costs: a Working Group of the Retail Consultation Forum Submission in response to CER Consultation CER/16/031

Retail and Reducing Energy Costs: a Working Group of the Retail Consultation Forum Submission in response to CER Consultation CER/16/031 Retail and Reducing Energy Costs: a Working Group of the Retail Consultation Forum Submission in response to CER Consultation CER/16/031 Review of the Electricity and Gas Supplier s Handbook 25 April 2016

More information

Energy Projections

Energy Projections www.seai.ie Energy Projections 2017 2030 Overview SEAI National Energy Projections Process Modelling Framework Scenarios 2020 insights 2030 insights Summary and next steps 3 www.seai.ie National Energy

More information

Future Energy Scenarios: Call for Evidence initial summary of results

Future Energy Scenarios: Call for Evidence initial summary of results Future Energy Scenarios: Call for Evidence initial summary of results October 2018 Error! No text of specified style in document. 0 Initial summary of our Call for Evidence findings In September this year

More information

Reporting and Incentives under Price Review 4

Reporting and Incentives under Price Review 4 An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities Reporting and Incentives under Price Review 4 Decision PR4 Reporting & Incentives Decision Reference: CER/18/087 Date Published: 10/05/2018

More information

By 22 nd June 2018

By  22 nd June 2018 By Email 22 nd June 2018 Joint Office of Gas Transporters Radcliffe House Blenheim Court Warwick Road Solihull B91 2AA Sent by email to: enquires@gasgovernance.co.uk Representation - UNC Modification 0621,

More information

Market development of biomethane in the UK

Market development of biomethane in the UK Market development of biomethane in the UK Berlin, 22nd March 2017 Gaynor Hartnell Renewable Energy Association REA Biogas Overview of talk Putting Biomethane in context: as a form of biogas Evolution

More information

Recommendations for incentivising innovation in the gas DSO sector

Recommendations for incentivising innovation in the gas DSO sector October 2016 Position Paper Recommendations for incentivising innovation in the gas DSO sector This paper sets out the status and challenges facing gas DSOs when investing in innovation. It describes a

More information

Initial Modification Report No.39. Transfer of Exit Capacity between Northern Ireland Exit Points to permit Secondary Trading of Exit Capacity

Initial Modification Report No.39. Transfer of Exit Capacity between Northern Ireland Exit Points to permit Secondary Trading of Exit Capacity Initial Modification Report No.39 Transfer of Exit Capacity between Northern Ireland Exit Points to permit Secondary Trading of Exit Capacity 30 th September 2016 Please find below Initial Modification

More information

Electricity and Gas Retail Markets Report Q1 2018

Electricity and Gas Retail Markets Report Q1 2018 An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities Electricity and Gas Retail Markets Report Q1 2018 Information Paper Reference: CRU18210 Date Published: 26/09/2018 An Coimisiún um

More information

Cush RNG Injection Project. Prepared by: James Browne (B.E., Ph.D.)

Cush RNG Injection Project. Prepared by: James Browne (B.E., Ph.D.) Cush RNG Injection Project Prepared by: James Browne (B.E., Ph.D.) Gas Networks Ireland Gas Networks Ireland owns and operates the transmission and distribution gas network in Ireland. Over 13,954km; 2,427km

More information

Transmission Prices Roles and Responsibilities

Transmission Prices Roles and Responsibilities Transmission Prices Roles and Responsibilities August 2016 Introduction Gas Industry Co has had a programme of work over several years aimed at improvements to gas transmission code arrangements; the Maui

More information

Facilitating Renewable Gas

Facilitating Renewable Gas Facilitating Renewable Gas How to incorporate small scale AD in gas to grid systems in Ireland James Browne Innovation Engineer James.Browne@gasnetworks.ie +353-21-4534121 14 th April 2016 Contents Introduction

More information

From the Electricity Networks Association. Comment on the Electricity Authority s Sunk Costs Working Paper

From the Electricity Networks Association. Comment on the Electricity Authority s Sunk Costs Working Paper From the Electricity Networks Association Comment on the Electricity Authority s Sunk Costs Working Paper 15 November 2013 The Electricity Networks Association makes this submission along with the explicit

More information

Bioenergy New Zealand

Bioenergy New Zealand Bioenergy New Zealand Biogass Renewables Economic Viability of Commercial Anaerobic Digestion Jandakot Bioenergy Facility in focus September 2017 Joseph Oliver, General Manager About Biogass Renewables

More information

I-SEM Testing Tariff High Level Options Consultation

I-SEM Testing Tariff High Level Options Consultation I-SEM Testing Tariff High Level Options Consultation 02 June 2017 Version 1.0 EXECUTIVE SUMMARY Testing Tariffs are currently applied to Units Under Test (UUT) in the Single Electricity Market (SEM) on

More information

Decision Paper on DSO Proposals on LCTA, Rebates and Fees

Decision Paper on DSO Proposals on LCTA, Rebates and Fees Decision Paper on DSO Proposals on LCTA, Rebates and Fees CER/08/077 9 th May 2008 May 2008 1/10 CER/08/077 1.0 Introduction This paper will be of interest to any commercial or industrial developer wishing

More information

Hydrogen and other routes to decarbonization of the gas network

Hydrogen and other routes to decarbonization of the gas network Hydrogen and other routes to decarbonization of the gas network FCH2 Conference, Birmingham, 14 th March 2018 14 th March 2018 1 DNV GL 2018 14 th March 2018 SAFER, SMARTER, GREENER DNV GL - A global classification,

More information

National Farmers Union 28 February Connecting to the electricity and gas networks

National Farmers Union 28 February Connecting to the electricity and gas networks National Farmers Union 28 February 2013 Connecting to the electricity and gas networks Olivia Powis Senior Manager Smarter Grids and Governance, Ofgem 2 Content Connecting to the electricity and gas network

More information

Long Term Resilience Study

Long Term Resilience Study Long Term Resilience Study 2018 Long Term Resilience Study 2018 Table of Contents 1. Executive Summary 2 2 The Current Position 6 3 A Changing Landscape 8 3.1 Policy 8 3.2 Infrastructure 9 3.3 Economy

More information

Eastland Network Limited. Pricing Methodology Disclosure

Eastland Network Limited. Pricing Methodology Disclosure Eastland Network Limited Pricing Methodology Disclosure Pursuant to: Requirements 22 and 23 of the Electricity Information Disclosure Requirements 2004 For Line Charges introduced on 31 March 2011 April

More information

COMMISSION STAFF WORKING PAPER

COMMISSION STAFF WORKING PAPER EN EN EN EUROPEAN COMMISSION Brussels, 22 January 2010 COMMISSION STAFF WORKING PAPER INTERPRETATIVE NOTE ON DIRECTIVE 2009/72/EC CONCERNING COMMON RULES FOR THE INTERNAL MARKET IN ELECTRICITY AND DIRECTIVE

More information

1 The Modification Proposal

1 The Modification Proposal Workstream Report Update of the default System Marginal Buy Price and System Marginal Sell Price Modification Reference Number 0333 Version 1.0 This Workstream Report is presented for the UNC Modification

More information

STATE OF VERMONT PUBLIC SERVICE BOARD JULY 7, 2016

STATE OF VERMONT PUBLIC SERVICE BOARD JULY 7, 2016 STATE OF VERMONT PUBLIC SERVICE BOARD Docket No. Petition of Vermont Gas Systems, Inc. for ) Renewable Natural Gas Program ) DIRECT TESTIMONY OF DAVID G. HILL, PH.D. ON BEHALF OF CONSERVATION LAW FOUNDATION

More information

Establishing Irish Water s Non-Domestic Tariff Framework

Establishing Irish Water s Non-Domestic Tariff Framework An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities Establishing Irish Water s Non-Domestic Tariff Framework Information Note Information Note Reference: /17/287 Date Published: 06/10/2017

More information

Improving the way we price our network services. Consultation paper

Improving the way we price our network services. Consultation paper Improving the way we price our network services Consultation paper October 2015 Table of Contents 1 Overview... 4 2 Background... 6 3 Purpose... 7 4 Network tariff strategy... 7 4.1 Network tariff reform

More information

Renewable Gas Forum Ireland

Renewable Gas Forum Ireland Renewable Gas Forum Ireland Meeting Ireland s targets under the 2020 Climate & Energy Package An Opportunity for Ireland. PJ McCarthy Chair 27th February 2018 Renewable Gas Forum Ireland Industry Forum

More information

WP 3.3: Policy Roadmap for large-scale biogas implementation in Latvia

WP 3.3: Policy Roadmap for large-scale biogas implementation in Latvia Project: (EIE/07/214) WP 3.3: Policy Roadmap for large-scale biogas implementation in Latvia Deliverable 3.3 M.Sc.ing Ilze Dzene EKODOMA Ltd. Noliktavas street 3-3, Riga LV-1010, Latvia February September,

More information

Proposal for a Renewable Future

Proposal for a Renewable Future Proposal for a Renewable Future Contents Energy Efficiency Green Gas Renewable Transport Security of Supply Renewable Heat Job Security The Strategic Energy Framework was developed in 2010, with a 10 year

More information

Bord Gáis Éireann. Response to CER Strategic Plan

Bord Gáis Éireann. Response to CER Strategic Plan Bord Gáis Éireann Response to CER Strategic Plan 2014 2018 1 Response to CER Strategic Plan Introduction Bord Gáis Éireann (BGE) welcomes the opportunity to respond to the consultation paper issued by

More information

Attachment 10.8 Transmission price path Access Arrangement Information

Attachment 10.8 Transmission price path Access Arrangement Information Attachment 10.8 Transmission price path Access Arrangement Information 2 October 2017 Access Arrangement Information (AAI) for the period 1 July 2017 to 30 June 2022 Transmission price path Access arrangement

More information

MARKET OPENING PROGRAMME

MARKET OPENING PROGRAMME CER/03/285 Proposal for co-ordination of ongoing reform programmes in the Irish gas market Version 1.0 27 November 2003 Market Opening Programme Interim market opening options - Version 1.0 Document Control

More information

22 February 2017 Cork

22 February 2017 Cork VRF Workshop 22 February 2017 Cork 1 Agenda 1. Introduction and EU Context 2. Review of Existing VRF Product Processes Usage to date 3. Industry Views on VRF Tariffing Structure 4. Discussion 5. Next Steps

More information

RENEWABLE NATURAL GAS

RENEWABLE NATURAL GAS RENEWABLE NATURAL GAS FULLY INTEGRATED SOLUTIONS FOR BIOGAS UPGRADING FUELLING OUR FUTURE BIOGAS PRODUCTION Various feedstocks can be used to produce the raw biogas used to make Biomethane. Biogas (the

More information

Higher Education Procurement Association. Procurement Benefits Reporting Guidance 2016/17 Onwards

Higher Education Procurement Association. Procurement Benefits Reporting Guidance 2016/17 Onwards Higher Education Procurement Association Procurement Benefits Reporting Guidance 2016/17 Onwards January 2017 1 Contents Section Subject Page Section 1 Background & Introduction 3 Section 2 Reporting 4

More information

Is Biomethane Your Best Option? Energy Now Expo 8th February 2017 Mike McLaughlin

Is Biomethane Your Best Option? Energy Now Expo 8th February 2017 Mike McLaughlin Is Biomethane Your Best Option? Energy Now Expo 8th February 2017 Mike McLaughlin Opportunity Grid capacity? Feedstock? Permits? Risk/Price Payment method? Feedstock? 2 Agenda 1 2 3 4 Renewable Heat Incentive

More information

Pricing Methodology for Gas Distribution Services. From 1 October 2018

Pricing Methodology for Gas Distribution Services. From 1 October 2018 Pricing Methodology for Gas Distribution Services From 1 October 2018 Pursuant to: The Gas Distribution Information Disclosure Determination 2012 - Consolidated in 2015 1 INTRODUCTION Vector owns and operates

More information

Future of Gas Entry Tariff Regime Draft Decision (CER/15/057)

Future of Gas Entry Tariff Regime Draft Decision (CER/15/057) 19 th May 2015 Mr Colm Ó Gormáin Commission for Energy Regulation The Exchange Belgard Square North Tallaght Dublin 24 Dear Colm Re: Future of Gas Entry Tariff Regime Draft Decision (CER/15/057) I am writing

More information

Brent Gloy, April

Brent Gloy, April Digester Economics and Financing Cornell Manure Nutrient Management and Renewable Energy Workshop Brent Gloy Cornell University April 1-2, 2008 Agenda Economic keys and evaluation Incentives Evaluation

More information

CER s Decision. ESB Networks. Updated PSO Levy Cost Allocation. Methodology

CER s Decision. ESB Networks. Updated PSO Levy Cost Allocation. Methodology CER s Decision on ESB Networks Updated PSO Levy Cost Allocation Methodology Decision Paper Reference: CER/17/073 Date Published: 31/03/2017 Executive Summary This paper presents the CER s decision following

More information

Draft Modification Report Revision of the Gas Balancing Alert (GBA) Trigger/Safety Monitor Modification Reference Number 0257 Version 1.

Draft Modification Report Revision of the Gas Balancing Alert (GBA) Trigger/Safety Monitor Modification Reference Number 0257 Version 1. Draft Modification Report Revision of the Gas Balancing Alert (GBA) Trigger/Safety Monitor Modification Reference Number 0257 Version 1.0 This Draft Modification Report is made pursuant to Rule 9.1 of

More information

Securing Income Biomethane Sales. Peter Rayson UK Biomethane Day 26th June 2012

Securing Income Biomethane Sales. Peter Rayson UK Biomethane Day 26th June 2012 Securing Income Biomethane Sales Peter Rayson UK Biomethane Day 26th June 2012 Biomethane Sales Market Overview Engineering Solution Commercial Arrangements RHI Application Process Green Gas Certificate

More information

Representation - Draft Modification Report UNC 0621; 0621A; 0621B; 0621C; 0621D; 0621E; 0621F; 0621H; 0621J; 0621K*; 0621L

Representation - Draft Modification Report UNC 0621; 0621A; 0621B; 0621C; 0621D; 0621E; 0621F; 0621H; 0621J; 0621K*; 0621L Representation - Draft Modification Report UNC 0621; 0621A; 0621B; 0621C; 0621D; 0621E; 0621F; 0621H; 0621J; 0621K*; 0621L Amendments to Gas Transmission Charging Regime * Amendments to Gas Transmission

More information

Future of Gas Entry Tariff Regime Initial Modelling Evidence. Consultation Paper CER/14/ nd September th October 2014

Future of Gas Entry Tariff Regime Initial Modelling Evidence. Consultation Paper CER/14/ nd September th October 2014 Future of Gas Entry Tariff Regime Initial Modelling Evidence DOCUMENT TYPE: REFERENCE: Consultation Paper CER/14/455 DATE PUBLISHED: 02 nd September 2014 CLOSING DATE: 14 th October 2014 RESPONSES TO:

More information

Renewable Heat Incentive Schemes. Neil Witney Renewable Heat Premium Payment

Renewable Heat Incentive Schemes. Neil Witney Renewable Heat Premium Payment Renewable Heat Incentive Schemes Neil Witney Renewable Heat Premium Payment Background Public consultation on Renewable Heat Incentive (RHI) proposals published February 2010 Change of Government before

More information

14 May 2015

14 May 2015 Highlands and Islands Enterprise Fraser House, Friar's Lane, Inverness IV1 1BA olivia.powis@ofgem.gov.uk 14 May 2015 Dear Olivia, Introduction Thank you for providing the opportunity to respond to this

More information

IWEA response to the DCENR Renewable Electricity Support Scheme Technology Review Deadline: 11 September 2015

IWEA response to the DCENR Renewable Electricity Support Scheme Technology Review Deadline: 11 September 2015 IWEA response to the DCENR Renewable Electricity Support Scheme Technology Review Deadline: 11 September 2015 By e-mail to: ress@dcenr.gov.ie Introduction IWEA welcomes the opportunity to respond to the

More information

- Position Paper - Europex reactions to the CEER study on the Future Role of Gas

- Position Paper - Europex reactions to the CEER study on the Future Role of Gas - Position Paper - Europex reactions to the CEER study on the Future Role of Gas Brussels, 25 June 2018 Europex welcomes the initiative from the Council of European Energy Regulators (CEER) to explore

More information

American Municipal Power Proposal to the Capacity Construct/Public Power Senior Task Force Executive Summary

American Municipal Power Proposal to the Capacity Construct/Public Power Senior Task Force Executive Summary American Municipal Power Proposal to the Capacity Construct/Public Power Senior Task Force Executive Summary I. Introduction The genesis of the AMP proposal was in part due to AMP s strong belief that

More information

Joint TSO/DSO Group Processing Approach Pricing Principles Guidelines

Joint TSO/DSO Group Processing Approach Pricing Principles Guidelines Joint TSO/DSO Group Processing Approach Pricing Principles Guidelines Published: 27/02/2007 Table of Contents 1 Introduction...3 2 Connection Method Principles...5 3 Connection Charging Principles...8

More information

Consultation Response

Consultation Response Consultation Response Review of Support for Anaerobic Digestion and micro CHP under the FiT scheme Date: 13 Introduction The CLA is the membership organisation for owners of land, property and businesse

More information

Consultation on an EU strategy for liquefied natural gas and gas storage

Consultation on an EU strategy for liquefied natural gas and gas storage Consultation on an EU strategy for liquefied natural gas and gas storage (EBA) Rue d Arlon 63-65 1040 Brussels BELGIUM Identification number in the transparency register: 18191445640-83 QUESTIONS & s responses

More information

Entergy New Orleans, Inc.

Entergy New Orleans, Inc. . Entergy New Orleans, Inc. An Integrated Resource Plan (2009 2028) Scope and Structure This document describes Entergy New Orleans, Inc. s ( ENOI ) long-term integrated resource plan ( IRP ) 1 for the

More information

Transmission Pricing Methodology: CBA

Transmission Pricing Methodology: CBA pwc.co.nz on Transmission Pricing Methodology: CBA Made on behalf of 22 Electricity Distribution Businesses PwC Submission on behalf of 22 EDBs 15 October 2013 Glossary i Submission on Transmission Pricing

More information

A GUIDE TO THE GB RENEWABLE HEAT INCENTIVE SCHEME.

A GUIDE TO THE GB RENEWABLE HEAT INCENTIVE SCHEME. A GUIDE TO THE GB RENEWABLE HEAT INCENTIVE SCHEME 1. What is the Renewable Heat Incentive Scheme ("RHI")? The RHI is a scheme to encourage the take up of renewable heat technologies such as biomass boilers,

More information

MARITIME OPERATOR SAFETY SYSTEM FEES

MARITIME OPERATOR SAFETY SYSTEM FEES Chair Cabinet Economic Growth and Infrastructure Committee Office of the Minister of Transport MARITIME OPERATOR SAFETY SYSTEM FEES Proposal 1. This paper proposes that the Economic Growth and Infrastructure

More information

RENEWABLE HEAT INCENTIVE FOR NORTHERN IRELAND

RENEWABLE HEAT INCENTIVE FOR NORTHERN IRELAND 髂髂獒獒 RENEWABLE HEAT INCENTIVE FOR NORTHERN IRELAND A REPORT FOR THE DEPARTMENT OF ENTERPRISE, TRADE AND INVESTMENT (DETI) 28 June 2011 Final Report Submitted by: Cambridge Economic Policy Associates Ltd

More information

A look at the Irish Gas Market

A look at the Irish Gas Market A look at the Irish Gas 1 Natural gas plays a vital role in Ireland s energy mix and economic progress. Gas Networks Ireland provides safe, reliable and efficient transportation of natural gas through

More information

ORR consultation on on-rail competition: Options for change in open access Network Rail s response

ORR consultation on on-rail competition: Options for change in open access Network Rail s response Peter Swattridge Head of Regulatory Economics Network Rail Kings Place, 90 York Way London, N1 9AG To: Philip Wilcox Office of Rail Regulation One Kemble Street London, WC2B 4AN 13 August 2013 Dear Philip,

More information

REVIEW OF THE IRISH GOVERNMENT S STRATEGY FOR COMPLIANCE WITH THE EUROPEAN DIRECTIVE 2009/28

REVIEW OF THE IRISH GOVERNMENT S STRATEGY FOR COMPLIANCE WITH THE EUROPEAN DIRECTIVE 2009/28 REVIEW OF THE IRISH GOVERNMENT S STRATEGY FOR COMPLIANCE WITH THE EUROPEAN DIRECTIVE 2009/28 By BW Energy Limited March 2014 SUMMARY 1 2 3 4 5 6 Executive Summary Introduction 2011 IAE perspective on alternative

More information

Water Supply Project Eastern and Midlands Region. Appendix C Cost-Benefit Analysis of Water Supply Projects for the Eastern and Midlands Region

Water Supply Project Eastern and Midlands Region. Appendix C Cost-Benefit Analysis of Water Supply Projects for the Eastern and Midlands Region Water Supply Project Eastern and Midlands Region Appendix C Cost-Benefit Analysis of Water Supply Projects for the Eastern and Midlands Region Cost-Benefit Analysis of Water Supply Projects for the Eastern

More information

The Non-Domestic Renewable Heat Incentive (RHI)

The Non-Domestic Renewable Heat Incentive (RHI) The Pinnacle Power View The Non-Domestic Renewable Heat Incentive (RHI) BEIS RHI Consultation Results - December 2016 Following on from the first stage reform that was implemented at the end of March 2016

More information

Manifesto of the European Gas Industry

Manifesto of the European Gas Industry Manifesto of the European Gas Industry Brussels October 2018 www.gasnaturally.eu 1 GasNaturally Policy Recommendations Fully implement a well-integrated and interconnected internal gas market across Europe

More information

Biogas Policy Recommendations

Biogas Policy Recommendations Biogas Policy Recommendations Jennifer Green November 27, 2013 at Queen s Park, Ontario Overview Introduction to Biogas Association FIT Program Feedstock Supply Innovation RNG and Transportation Summary

More information

Counties Power Limited

Counties Power Limited Counties Power Limited Electricity Distribution Business Pricing Methodology Disclosure 1 April 2018 to 31 March 2019 Pursuant to Electricity Information Disclosure Information for compliance with Part

More information

Carbon Cost Issue ADBA DECC Fundamental basis Subsidy cost-effectiveness Societal cost-effectiveness

Carbon Cost Issue ADBA DECC Fundamental basis Subsidy cost-effectiveness Societal cost-effectiveness Anaerobic Digestion and Bioresources Association Renewable Energy Association Department of Energy & Climate Change 3 Whitehall Place, London SW1A 2AW T: +44 (0)300 068 5700 E: Katie.Halter@decc.gsi.gov.uk

More information

Ontario Energy Board Business Plan

Ontario Energy Board Business Plan Ontario Energy Board 2009-12 Business Plan Ontario Energy Board P.O. Box 2319 2300 Yonge Street 27th Floor Toronto ON M4P 1E4 Telephone: (416) 481-1967 Facsimile: (416) 440-7656 Toll-free: 1 888 632-6273

More information

IMPACT OF HIGH PENETRATIONS OF MICRO-GENERATION ON LOW VOLTAGE DISTRIBUTION NETWORKS

IMPACT OF HIGH PENETRATIONS OF MICRO-GENERATION ON LOW VOLTAGE DISTRIBUTION NETWORKS IMPACT OF HIGH PENETRATIONS OF MICRO-GENERATION ON LOW VOLTAGE DISTRIBUTION NETWORKS Peter RICHARDSON University College Dublin Ireland peter.richardson@ee.ucd.ie Andrew KEANE University College Dublin

More information

Review of the Regulatory Framework for the Retail Electricity Market Roadmap to Deregulation

Review of the Regulatory Framework for the Retail Electricity Market Roadmap to Deregulation Review of the Regulatory Framework for the Retail Electricity Market Roadmap to Deregulation DOCUMENT TYPE: REFERENCE: DATE PUBLISHED: QUERIES TO: Decision Paper CER/10/058 21 April 2010 pfuller@cer.ie

More information