SCA Environmental Management Report September Report to IPART

Size: px
Start display at page:

Download "SCA Environmental Management Report September Report to IPART"

Transcription

1 SCA Environmental Management Report September Report to IPART WaterNSW was formed on 1 January 2015 under the Water NSW Act 2014, effecting a merger of the Sydney Catchment Authority (SCA) and State Water Corporation. Reference to the SCA in this report is taken to mean that part of WaterNSW s business that relates to the former SCA. In accordance with clause of the Sydney Catchment Authority (SCA) Operating Licence , the SCA must maintain programs to manage the risks to the environment from carrying out its activities and must ensure all activities are carried out in accordance with those programs until the Environmental Management System (EMS) has been developed and implemented. The SCA s Environmental Management Program provides a summary of the activities that are undertaken by the SCA to manage risks to the environment and to meet the requirements of the Water NSW Act 2014 and the SCA Operating Licence It outlines the SCA s environmental objectives and targets, and the environmental management programs being implemented to achieve these. This Environmental Management Report outlines the environmental management programs implemented in , in accordance with clause of the Reporting Manual. Objective One - minimise the environmental impacts of the SCA s activities, projects and infrastructure The SCA s Annual Environmental Audit aims to assess the effectiveness of actions to minimise environmental impacts. The findings are used to improve environmental management for future activities. In , three SCA projects were subject to independent audit consisting of both desktop and on-site components. While the audit process identified some business improvement opportunities, the auditor noted that all relevant environmental safeguards appeared to be implemented effectively for all projects. 1.1 Comply with SCA s Environmental Impact Assessment Policy Target: 100% of audited projects meet the SCA s environmental impact assessment policy each year 100% met. All audited projects met the EIA policy. Target: 100% audited projects comply with the environmental assessment conditions imposed For the projects audited, documentation could not be provided as evidence that contractors notified SCA of the commencement date of on ground works. 1.2 Increase environmental performance of contractors Target: 100% of audited projects have environmental performance provisions included in the relevant contracts. 100% met. All projects assessed had environmental performance provisions included in contract documentation. Target: 100% of audited projects meet contract conditions in relation to environmental management. Not applicable. For all three projects, individual environmental management conditions were not required.

2 1.3 Findings of the annual environmental audit report addressed Target: 100% of approved recommendations addressed before 30 June the following year Ten of the twelve recommendations (83%) from the previous audit were addressed before 30 June. The two remaining recommendations relating to inclusion of relevant environmental safeguards and conditions of approval, and review of the Site Inspection Procedure are being addressed. 1.4 Findings of the environmental inspection program addressed Target: 100% of non-compliances addressed within six months of inspection being completed 100% met. The SCA implemented its Environmental Inspection Procedure in to improve environmental practice and reduce the impact of its activities on the environment. Six environmental inspections were undertaken in , with the projects selected on the basis of the type of works, nature of the risk and the duration of the works. One inspection identified four non compliances requiring corrective action, and these were addressed within six months of being identified. 1.5 SCA staff made aware of environmental responsibilities Target: 100% new staff inductions include environmental requirements 100% met. Environmental requirements are included in staff inductions and inductions are routinely held for all new staff. Some exceptions were found whereby some staff had not attended inductions; however, arrangements were made for these staff to be inducted at future induction sessions. Target: Relevant SCA staff undertake environmental assessment training as required On an as needs basis, project managers were advised of the SCA s environmental assessment requirements and procedures. An online environmental awareness training module for project and contract managers was developed. 47 staff completed the module during Continued release of environmental flows from SCA storages Target: 100% of Water Management Licence requirements for environmental flow releases met WaterNSW maintained 100% compliance with requirements of the Water Sharing Plan for the Greater Metropolitan Region Unregulated River Water Sources over the FY. There were a number of daily shortfalls over the period which were managed in accordance with agreed operating protocols and therefore did not constitute any non-compliances. Objective Two - manage and minimise resource use and waste generation 2.1 Conduct biennial waste audit Target: Waste audits conducted by 30 June 2013 and 30 June 2015 The SCA engaged an independent auditor to undertake a waste audit of its offices in February 2013 to help meet its obligations under the NSW Government s Waste Reduction and Purchasing Policy (WRAPP). The audit covered the Penrith, Warragamba, Campbelltown and Burrawang offices, and focused on general waste streams and recycling generation. The next waste audit was due to be conducted in February However, the Office of Environment and Heritage advised that WRAPP reporting obligations were being replaced by the Government Resource Efficiency Policy reporting requirements and agencies were no longer required to provide a WRAPP Report as at June 2015.

3 2.2 Waste audit recommendations addressed Target: 100% of recommendations considered and addressed as appropriate by 30 June the following year. All (100%) of the recommendations from the 2013 waste audit were considered and those considered appropriate were approved by management and implemented. 2.3 Implement waste reduction and minimisation actions as outlined in the SCA WRAPP Plan Target: 100% compliance with timeframes specified in the SCA WRAPP Plan All key reporting requirements have been considered and the majority of actions commenced in accordance with the timeframes of the WRAPP plan. Priority had been given to key actions under the WRAPP plan to address the 2013 waste audit recommendations. Key actions implemented since that audit was undertaken include: actions to reduce waste to landfill a communications / waste education plan has been drafted waste education in public spaces and liaising with building managers and cleaning staff to ensure correct recycling for office waste development of a waste process table for effective waste data collection and reporting communicating actions such as providing a summary of waste audit findings to staff, publishing articles on waste management initiatives on the intranet and development of WRAPP fact sheets development and implementation of integrated waste management contracts for the Penrith Office building to help reduce contamination levels in waste streams and improve resource recovery. implementation of a new office recycling system for the Penrith office building establishment of a green lease office working group for the Penrith building, comprised of the building manager and tenants implementation of waste management initiatives under the Penrith building s green lease plan (in line with NSW Government best practice) The WRAPP plan was not revised during given the changes to the WRAPP reporting requirements and the introduction of the Government Resource Efficiency Policy (GREP). It is intended to develop a Sustainability Management Plan for WaterNSW by the end of Report to the NSW Government on progress of the SCA WRAPP Plan biennially Target: WRAPP Plan progress report prepared by 31 August 2013 and June 2015 The biennial WRAPP progress report was submitted to the Office of Environment and Heritage (OEH) by 31 st August OEH has advised that the WRAPP reporting requirements have now been replaced by the GREP reporting requirements, and agencies are no longer required to provide a WRAPP Report as at June Objective three - minimise the environmental impact of the SCA s use of energy 3.1 Determine SCA carbon footprint Target: Report on SCA carbon footprint in Annual Report

4 The SCA has determined its carbon footprint during the period July 2008 to December 2014 and reported results in its Annual Reports. The carbon footprint has been calculated and was reported as part of the 2014 SCA Annual Report (July to December 2014), but will not be included in the WaterNSW Annual Report (January to June 2015). Note: Carbon footprint has been calculated for the first six months but not for the second six months. Scope one and two emissions data is not available until October 2015 to enable the carbon footprint to be calculated. Also note that the carbon footprint has not been included in the six-monthly WaterNSW Annual Report for Minimise energy consumption Target: Implement and report on agreed initiatives annually The focus for continued to be the maintenance and sustainability of implemented initiatives. The Energy Coordinator continued to monitor energy consumption in office buildings and worked closely with water supply operators to ensure that the lowest possible amount of electricity was used in the SCA s day-to-day supply operations. Where possible, the SCA has incorporated energy saving measures in its capital upgrade projects. For example, the upgrade of the Burrawang Pumping Station electrical systems incorporates the installation of a variable speed drive (VSD) motor that has the potential for significant energy savings. Other energy management initiatives undertaken include: Subscribing vehicles to the Greenfleet program Continuing to monitor industry development in mini-hydropower generation through the attendance of industry seminars and workshops Investigating external proposals to generate hydroelectricity using the water supply assets. Table 1: Electricity consumption for the past four years in kilowatt hours Electricity consumption for the past four years in kilowatt hours Office buildings 466, , , ,760 Public buildings 104,231 92, , ,849 Other facilities 73,249 70,131 85,402 67,466 Water supply infrastructure 6,555,977 9,669,613 9,381,519 27,191,895 Shoalhaven drought transfers Infrastructure roadways 21,878 21, ,905 Total electricity 7,222,120 10,332,620 10,105,670 27,904,875

5 Table 2: Energy comparisons for the past two financial years in Gigajoules Energy comparisons for the past two financial years in Gigajoules Total energy (GJ) Change in GJ% Costs of energy ($) Electricity 26,000 37, % 2.25% 1,039,336 1,548,509 Petrol 1,315 1, % % 47,786 55,485 Auto distillate 6,684 6, % 3.56% 230, ,565 (diesel) Bio fuel (B20) Wood Gas Total 33,999 45, % 1.76% 1,317,964 1,840,559 Table 3: Greenhouse gas emissions comparisons (carbon dioxide tonnes equivalent) Energy type Greenhouse gas emissions comparisons (CO 2 tonnes equivalent) Greenhouse gas emissions Greenhouse gas emissions % % change Electricity 5,441 8, Petrol Auto distillate (diesel) Bio fuel (B20) Wood Gas Total 6,001 8, Report to the Commonwealth Government on NGERS indicators annually NGERS report will be submitted to the Commonwealth Government on 31 October This information can be collated only in August/September 2015 after final quarterly bills are received. 3.4 Report energy consumption to Department of Trade and Investment, Regional Infrastructure and Services The report on energy consumption to the Department of Trade and Investment, Regional Infrastructure and Services will be submitted through the OSCAR reporting system on 31 October This information can only be collated in August/September 2015 after final quarterly bills are received.

6 3.5 Report energy consumption to Water Services Association of Australia (WSAA) The report on energy consumption will be sent to WSAA by in October This information will be collated in August/September 2015 after final quarterly bills are received. 3.6 Report to IPART on the National Water Initiative (NWI) Environmental Indicators annually The SCA will report to IPART on the three NWI Environmental Indicators in October 2015, as per the Reporting Manual. The indicators are listed below. Table 4: NWI Environmental Indicators Item No NWI Indicator Tonnes of CO2-e Tonnes of CO2-e/ML E9.1 GHG Emissions -Water E11.1 Net GHG Emissions -Other E12.1 Total Net ML Supplied 520,958

Water NSW Reporting Manual

Water NSW Reporting Manual Water NSW Reporting Manual Operating Licence 2017-2022 Reporting Manual Water July 2017 Independent Pricing and Regulatory Tribunal of New South Wales 2017 This work is copyright. The Copyright Act 1968

More information

Compliance and Performance Report

Compliance and Performance Report Compliance and Performance Report Environmental Management System 2017-2018 This page is intentionally blank. D2018/73234 Review Date: September_2018 2 Contents 1. Introduction... 4 2. Purpose of the Report...

More information

To reduce the consumption of energy and the emission of greenhouse gases associated with Transit Systems NSW s activities.

To reduce the consumption of energy and the emission of greenhouse gases associated with Transit Systems NSW s activities. Transit Systems NSW Environmental Management Plan GOAL 1: REDUCE THE GREENHOUSE IMPACT OF ENERGY USE To reduce the consumption of energy and the emission of greenhouse gases associated with Transit Systems

More information

Compliance & Performance Report. Under the State Water Operating Licence

Compliance & Performance Report. Under the State Water Operating Licence Compliance & Performance Report Under the State Water Operating Licence 2013-2018 Contents 1 Introduction.........4 2 Assets....5 2.1 Compliance and performance reporting (before certification of Asset

More information

Environment Plan Sydney Water s objectives, targets and actions to protect the environment and enhance the liveability of our communities.

Environment Plan Sydney Water s objectives, targets and actions to protect the environment and enhance the liveability of our communities. Environment Plan 18 Sydney Water s objectives, targets and actions to protect the environment and enhance the liveability of our communities. Environment Plan 18 Introduction Sydney Water s vision is to

More information

Dendrobium Mine. Waste Management Plan

Dendrobium Mine. Waste Management Plan Dendrobium Mine Waste Management Plan DOCUMENT SIGN OFF SHEET AND REVISION LOG Document Owner: Authorised by: Peter McMillan 25/06/2018 (Name) (Date) Peter McMillan 25/06/2018 (Name) (Date) VERSION HISTORY

More information

CLIMATE CHANGE IMPACTS ON SYDNEY S WATER SUPPLY

CLIMATE CHANGE IMPACTS ON SYDNEY S WATER SUPPLY CLIMATE CHANGE IMPACTS ON SYDNEY S WATER SUPPLY Selvaratnam Maheswaran 1, Jason Martin 1, Golam Kibria 1 1. Sydney Catchment Authority, Penrith, NSW, Australia INTRODUCTION The drinking water for Sydney

More information

ENVIRONMENTAL MANAGEMENT PLAN

ENVIRONMENTAL MANAGEMENT PLAN ENVIRONMENTAL MANAGEMENT PLAN 2018-2020 DOCUMENT CONTROL Document Controller: Manager Adopted: 22 February 2018 Document number: EP0128 Rev Date Description Prepared Approved 1.0 Feb 2018 Initial issue

More information

Submission to the Environmental future funding package. February 2017

Submission to the Environmental future funding package. February 2017 Submission to the February 2017 Table of contents Opening 3 Climate Change Fund Draft Strategic Plan 3 Accelerating Advanced Energy 3 National Leadership in Energy Efficiency 4 Preparing for a Changing

More information

Sydney Water Operating Licence Environment Report. Environment Plan Annual Report Environmental Indicators Report

Sydney Water Operating Licence Environment Report. Environment Plan Annual Report Environmental Indicators Report Sydney Water Operating Licence Environment Report Environment Plan 2011 16 Annual Report Environmental Indicators Report 2011 12 Introduction Sydney Water is governed by the Sydney Water Act 1994 (the

More information

GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08

GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08 CS ENERGY PROCEDURE FOR GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08 Responsible Officer: Manager Environment Approved: Executive General Manager Asset Strategy DOCUMENT HISTORY Date

More information

Memorandum of Understanding

Memorandum of Understanding Memorandum of Understanding between the NSW Ministry of Health and Sydney Water Corporation July 2016 MoU between Sydney Water and NSW Ministry of Health - July 2016 Page 1 of 11 1. Introduction and purpose

More information

Greater Sydney customer drought update

Greater Sydney customer drought update Greater Sydney customer drought update 14 January 2019 Weekly Greater Sydney customer drought update 1 Key messages As of 13 January, Sydney s dam levels are at 60.9%, a decrease of 0.1% since last Sunday.

More information

Greater Sydney customer drought update

Greater Sydney customer drought update Greater Sydney customer drought update 22 January 2019 Weekly Greater Sydney customer drought update 1 Key messages As of 21 January, Sydney s dam levels are at 60.3%, a decrease of 0.5% since last Sunday.

More information

ENVIRONMENTAL SUSTAINABILITY POLICY 2015

ENVIRONMENTAL SUSTAINABILITY POLICY 2015 ENVIRONMENTAL SUSTAINABILITY POLICY 2015 The Vice-Chancellor and Principal, as delegate of the Senate of the University of Sydney, adopts the following policy. Dated: 9 June 2015 Last amended: 19 June

More information

Pollution Incident Response Management Plan (Addendum to Emergency Response Plan)

Pollution Incident Response Management Plan (Addendum to Emergency Response Plan) Pollution Incident Response Management Plan (Addendum to Emergency Response Plan) 3.3.1 Description and likelihood of hazards (clause 98c (1) (a) and (b) St George Motor Boat Club operates a 242 berth

More information

How to set up a sewer mining scheme

How to set up a sewer mining scheme Sewer Mining How to set up a sewer mining scheme With a growing population and highly variable rainfall over the catchments, water recycling is making an increasingly important contribution to our water

More information

Greater Sydney Customer Advisory Group Minutes of Meeting Friday 8 September 2017 WaterNSW, 169 Macquarie Street, Parramatta

Greater Sydney Customer Advisory Group Minutes of Meeting Friday 8 September 2017 WaterNSW, 169 Macquarie Street, Parramatta Greater Sydney Customer Advisory Group Minutes of Meeting Friday 8 September 2017 WaterNSW, 169 Macquarie Street, Parramatta Present: Peter Gray, Paul Elias, Grant Moller, Chris Schumacher, Rhys Brownlow,

More information

REPORT TO THE IPART UNDER THE OPERATING LICENCE

REPORT TO THE IPART UNDER THE OPERATING LICENCE WATERNSW REPORT TO THE IPART UNDER THE OPERATING LICENCE 2013-2018 for STATE WATER 1 SEPTEMBER 2015 i Table of Contents Note: a reference to Part corresponds with the relevant part of the Operating Licence

More information

Monitoring Program Energy Use and Greenhouse Gas Emissions

Monitoring Program Energy Use and Greenhouse Gas Emissions Information Document Document No. 67616 Document Title Monitoring Program Energy Use and Greenhouse Gas Emissions Area HSEC Issue Date 7 June 2013 Major Process Environment Sub Process Authoriser Darryl

More information

ALBANY PORT AUTHORITY ENVIRONMENTAL MANAGEMENT SYSTEM

ALBANY PORT AUTHORITY ENVIRONMENTAL MANAGEMENT SYSTEM ALBANY PORT AUTHORITY ENVIRONMENTAL MANAGEMENT SYSTEM May 2006 Document Status Rev Author Reviewer/s Date Approved for Issue No. Name Distributed To Date 1 J. Prout V. Ee 26/05/06 V. Ee Albany Port Authority

More information

Greater Sydney customer drought update

Greater Sydney customer drought update Greater Sydney customer drought update 12 February 2019 Weekly Greater Sydney customer drought update 1 Key messages As of 11 February, Sydney s dam levels are at 59.2%, a decrease of 0.3% since last Sunday.

More information

Melbourne Health Environmental Report

Melbourne Health Environmental Report Melbourne Health Environmental Report 2015-16 Melbourne Health Environmental Report 2015-16 Introduction Melbourne Health continues to promote environmental sustainability among staff, visitors, patients

More information

Regulatory Compliance and Enforcement Framework

Regulatory Compliance and Enforcement Framework Contents 1. About us... 3 1.1 Our Mission and Values... 3 2. Relevant Legislation and Obligations... 4 3. Approach to Regulatory Compliance and Enforcement... 4 3.1 Our Approach... 4 3.2 Working with Stakeholders...

More information

Environmental Officer

Environmental Officer POSITION DESCRIPTION Officer 1 POSITION DETAILS Position Title: Reports to: Department: Location: Officer Environment and Sustainability Coordinator Environment / Operations Traralgon Date: November 2018

More information

GREENHOUSE GAS EMISSIONS AND ENERGY USE ANNUAL REPORT

GREENHOUSE GAS EMISSIONS AND ENERGY USE ANNUAL REPORT GREENHOUSE GAS EMISSIONS AND ENERGY USE ANNUAL REPORT 2015 16 TABLE OF CONTENTS 1. SUMMARY 4 2. INTRODUCTION 6 3. BACKGROUND 8 4. GREENHOUSE GAS EMISSION IN 2014/2015 10 5. ENERGY CONSUMPTION IN 2014/2015

More information

HSEQ. Energy. Version 2

HSEQ. Energy. Version 2 2013 HSEQ Management System Energy Management Action Sub Plan SICTL Version 2 Telephone 02 8268 8000 Fax 022 9269 0717 Document Control: Document control shall be in accordance with the HPA Document Control

More information

/ 1 2 ANNUAL REPORT BALANCE RECRUITMENT E N V I R O N M E N T A L

/ 1 2 ANNUAL REPORT BALANCE RECRUITMENT E N V I R O N M E N T A L BALANCE RECRUITMENT E N V I R O N M E N T A L ANNUAL REPORT 2 0 1 1 / 1 2 Balance Recruitment provides recruitment consultancy services for the placement of professionals in office environments, on both

More information

ENERGY EFFICIENCY OPPORTUNITIES REPORT July June 2012

ENERGY EFFICIENCY OPPORTUNITIES REPORT July June 2012 ENERGY EFFICIENCY OPPORTUNITIES REPORT 2012 1 July 2009 30 June 2012 CONTENTS 1 IntroductIon... 2 1.1 About the WestpAc Group... 2 1.2 the WestpAc Group energy use...4 2 energy Assessments And opportunities...5

More information

Stands for purpose. Draft Environmental Management Plan

Stands for purpose. Draft Environmental Management Plan Stands for purpose Draft Environmental Management Plan 2017-2020 Prepared by: Environment Unit May 2017 Approved: Chief Administrative Officer Distributed to: Environmental Advisory Committee BIA-BA-TEM-015

More information

Greenhouse Gas Assessment

Greenhouse Gas Assessment Sustainability, Energy & Carbon Management Greenhouse Gas Assessment for Pangolin Associates Pty Ltd FY 213/14 Authored by Serena Li Reviewed by Chris Wilson* Approved by Iain Smale Document Number: v1

More information

Environmental Sustainability

Environmental Sustainability Guidelines for Implementing Total Management Planning Environmental Sustainability IMPLEMENTATION GUIDE 2 Environmental Sustainability: Implementation Guide TABLE OF CONTENTS Page No. LIST OF ACRONYMS

More information

Waste FY Introduction. 2. Waste. 3. Management Approach

Waste FY Introduction. 2. Waste. 3. Management Approach 1. Introduction This document forms part of our Disclosures on Management Approach (DMA) series, prepared in accordance with the Global Reporting Initiative s G4 Guidelines. The DMA series is designed

More information

SA Power Networks Environmental Management

SA Power Networks Environmental Management SA Power Networks Environmental Management Contents Climate Change and Environmental Sustainability Initiatives 2 Aboriginal Cultural Heritage Management 3 A Green approach to Substation Audits 4 In-house

More information

Appendix B6 Construction Heritage Management Plan

Appendix B6 Construction Heritage Management Plan Appendix B6 Project: Keepit Dam Work Package 2 - Post Tensioning Works Location: Keepit Dam, Namoi River, Northern NSW Client: WaterNSW Contract: 04532F31 Page 2 of 21 Document Acceptance and Release Notice

More information

GRANGE RESOURCES LIMITED

GRANGE RESOURCES LIMITED July 2006 GRANGE RESOURCES LIMITED DRAFT ENVIRONMENTAL MANAGEMENT SYSTEM 1025 Wellington Street WEST PERTH WA 6005 phone: 9322 1944 fax: 9322 1599 ACN 088 821 425 ABN 63 088 821 425 Document Status Rev

More information

Emission Inventory Report. For the period 1 July 2006 to 30 June 2007

Emission Inventory Report. For the period 1 July 2006 to 30 June 2007 Emission Inventory Report For the period 1 July 2006 to 30 June 2007 Published in April 2008 by the Ministry for the Environment Manatū Mō Te Taiao PO Box 10362, Wellington, New Zealand ISBN: 978-0-478-30209-7

More information

Environmental Sustainability Destination Action Plan

Environmental Sustainability Destination Action Plan Sustainability Destination Action Plan . T (02)64594100 F (02) 64594101 W www.thredbo.com.au PO Box 92 Thredbo NSW 2625 Australia ABN 95000139015 (incorporated in NSW) Document version: Final Author: Bryce

More information

GREENHOUSE GAS EMISSIONS AND ENERGY USE ANNUAL REPORT

GREENHOUSE GAS EMISSIONS AND ENERGY USE ANNUAL REPORT GREENHOUSE GAS EMISSIONS AND ENERGY USE ANNUAL REPORT 2014 2015 TABLE OF CONTENTS 1. SUMMARY 4 2. INTRODUCTION 6 3. BACKGROUND 8 4. GREENHOUSE GAS EMISSION IN 2014/2015 10 5. ENERGY CONSUMPTION IN 2014/2015

More information

Environmental Management Policy Statement

Environmental Management Policy Statement Environmental Management Policy Statement 1. Commitment Busways Group, as a major public transport provider, seeks to make a considerable effort to minimise its impact on the environment through the efficient

More information

POLICY ON ENVIRONMENTAL MANAGEMENT

POLICY ON ENVIRONMENTAL MANAGEMENT POLICY ON ENVIRONMENTAL MANAGEMENT 1 Title Summary Purpose Environmental Management Policy Policy formalises the BSO s commitment to supporting the principles of environmental sustainability and the need

More information

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP)

POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP) Established 1907 POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN (PIRMP) DATE: JULY 2018 Version Date Section Modified 1 July 2018 All Reason for Modification Original Management Plan Review Team MCC Environmental,

More information

Rosehill Recycled Water Scheme. Fairfield Recycled Water Plant

Rosehill Recycled Water Scheme. Fairfield Recycled Water Plant Rosehill Recycled Water Scheme Fairfield Recycled Water Plant Front cover Aerial view of foundation customer sites at Rosehill and Camellia The project The Rosehill Recycled Water Scheme is a private sector

More information

12. STATUTORY REQUIREMENTS

12. STATUTORY REQUIREMENTS 12. STATUTORY REQUIREMENTS (SMP GUIDELINES SECTION 6.9) This section identifies the statutory requirements that apply to the SMP Area and the proposed mining operation in relation to any potential subsidence

More information

Master Plan. Volume 3: Sustainability Plan (AIRPORT ENVIRONMENT STRATEGY) November

Master Plan. Volume 3: Sustainability Plan (AIRPORT ENVIRONMENT STRATEGY) November Master Plan Parafield Airport Volume 3: Sustainability Plan (AIRPORT ENVIRONMENT STRATEGY) November 2012 www.parafieldairport.com.au Parafield Airport Master Plan TABLE OF CONTENTS 9 INTRODUCTION 105

More information

CONSTRUCTION ENVIRONMENTAL MANAGEMENT FRAMEWORK

CONSTRUCTION ENVIRONMENTAL MANAGEMENT FRAMEWORK CONSTRUCTION ENVIRONMENTAL MANAGEMENT FRAMEWORK APPENDIX D Contents 1 Introduction... 1 1.1 Purpose and Scope... 1 1.2 Status... 1 1.3 Environment and Sustainability Policy... 1 1.4 Project Description...

More information

draft Environment Strategy

draft Environment Strategy draft Environment Strategy Our Commitment Our vision is to be the lifestream of Sydney for generations to come. We want to be world-class, delivering essential services that our customers love, in our

More information

The Neutral or Beneficial Effect on Water Quality Assessment Tool

The Neutral or Beneficial Effect on Water Quality Assessment Tool The Neutral or Beneficial Effect on Water Quality Assessment Tool Author(s): Alison Kniha, Greg Greene Organisation: WaterNSW Country: Australia Email: alison.kniha@waternsw.com.au Paper: INTRODUCTION

More information

GREATER SYDNEY S WATER SUPPLY SYSTEM YIELD. August 2015

GREATER SYDNEY S WATER SUPPLY SYSTEM YIELD. August 2015 1 GREATER SYDNEY S WATER SUPPLY SYSTEM YIELD August 2015 2 Greater Sydney s water supply system yield is currently 615 GL/a WaterNSW supplies raw water for treatment and distribution by its Greater Sydney

More information

Section 75J of the Environmental Planning and Assessment Act 1979

Section 75J of the Environmental Planning and Assessment Act 1979 Project Approval Section 75J of the Environmental Planning and Assessment Act 1979 I approve the project application referred to in Schedule 1, subject to the conditions in Schedules 2 to 4. These conditions

More information

Engineering Compliance East London Regional Waste Disposal Site A Case Study

Engineering Compliance East London Regional Waste Disposal Site A Case Study Engineering Compliance East London Regional Waste Disposal Site A Case Study A.S Dookhi, Envitech Solutions (Pty) Ltd, South Africa, nash@envitech.co.za ABSTRACT The East London Regional Waste Disposal

More information

Stage 2: WestConnex M5 King Georges Road Interchange Upgrade. Appendix B7 Construction Waste Management Plan

Stage 2: WestConnex M5 King Georges Road Interchange Upgrade. Appendix B7 Construction Waste Management Plan Stage 2: WestConnex M5 King Georges Road Interchange Upgrade Appendix B7 Construction Waste Management Plan JULY 2016 DOCUMENT CONTROL File name Report name CEMP App B7 CWMP Rev D Construction Waste Management

More information

Conditions of Approval for the MDP for the brickworks at Perth Airport

Conditions of Approval for the MDP for the brickworks at Perth Airport Conditions of Approval for the MDP for the brickworks at Perth Airport Definitions In this document, unless a contrary intention appears, the terms below have the meanings given to them: AES means Airport

More information

EDO NSW Key Issues Summary Biodiversity Certification: Upfront planning for conservation & future impacts 1 November 2017

EDO NSW Key Issues Summary Biodiversity Certification: Upfront planning for conservation & future impacts 1 November 2017 EDO NSW Key Issues Summary Biodiversity Certification: Upfront planning for conservation & future impacts 1 November 2017 1. Biocertification: Quick guide and EDO NSW analysis What is Biocertification?

More information

Corporate. 32 Melbourne Water Annual Report

Corporate. 32 Melbourne Water Annual Report Corporate 32 Melbourne Water Annual Report 2011 12 34 Environmental stewardship Protect the natural environment and ensure resource availability for future generations 42 Relationships To be valued by

More information

UNDERGROUND OPERATION

UNDERGROUND OPERATION UNDERGROUND OPERATION Approved Mine Manager Date: Environmental Adviser Date: Integra Coal Underground ENVIRONMENTAL MANAGEMENT STRATEGY TABLE OF CONTENTS 1 GENERAL 5 C:\Users\oshan\AppData\Local\Microsoft\Windows\Temporary

More information

CATEGORY Policy SUBJECT Work Health & Safety ISSUED BY Human Resources APPROVAL DATE 05/08/2015

CATEGORY Policy SUBJECT Work Health & Safety ISSUED BY Human Resources APPROVAL DATE 05/08/2015 POLICY NUMBER P15/2 VERSION 1.0 CATEGORY Policy SUBJECT Work Health & Safety ISSUED BY Human Resources APPROVAL DATE 05/08/2015 AUTHORISED BY Trust ISSUED DATE 10/08/2015 DISTRIBUTION External REVIEW DATE

More information

Traffic Management Plan. Environmental Management and Monitoring Program. Appendix VI

Traffic Management Plan. Environmental Management and Monitoring Program. Appendix VI Traffic Management Plan Environmental Management and Monitoring Program Appendix VI Gunlake Quarries December 2009 Olsen Consulting Group Pty Ltd 6/25 Victoria Street WOLLONGONG 2500 PO Box 353 FIGTREE

More information

GLOBAL SUSTAINABILITY FRAMEWORK FY16 ENVIRONMENTAL DATA (ENERGY, EMISSIONS, WATER, WASTE & NORMALISATION DATA) AND SUMMARY BASIS OF PREPARATION

GLOBAL SUSTAINABILITY FRAMEWORK FY16 ENVIRONMENTAL DATA (ENERGY, EMISSIONS, WATER, WASTE & NORMALISATION DATA) AND SUMMARY BASIS OF PREPARATION GLOBAL SUSTAINABILITY FRAMEWORK FY16 ENVIRONMENTAL DATA (ENERGY, EMISSIONS, WATER, WASTE & NORMALISATION DATA) AND SUMMARY BASIS OF PREPARATION FY16 Environmental Data The FY16 Environmental Data (detailed

More information

Environmental Impact Assessment of Lake Menindee Shallow Aquifer Test Bores

Environmental Impact Assessment of Lake Menindee Shallow Aquifer Test Bores Environmental Impact Assessment of Lake Menindee Shallow Aquifer Test Bores October 2015 Environmental Impact Assessment of Lake Menindee Shallow Aquifer Test Bores WaterNSW on behalf of the NSW Government

More information

Investigating the Low Carbon Readiness of Built Environment Supply Chain

Investigating the Low Carbon Readiness of Built Environment Supply Chain Investigating the Low Carbon Readiness of Built Environment Supply Chain A CRC for Low Carbon Living and Sustainable Built Environment National Research Centre (SBEnrc) initiative by Curtin University

More information

ENVIRONMENT STRATEGY

ENVIRONMENT STRATEGY 10 ENVIRONMENT STRATEGY 183 ENVIRONMENT STRATEGY 10.1 Introduction Adelaide Airport Limited s (AAL) vision and ongoing success is founded on building and maintaining the three pillars of responsible business

More information

Submission to the Inquiry into the Product Stewardship Bill 2011

Submission to the Inquiry into the Product Stewardship Bill 2011 Submission to the Inquiry into the Product Stewardship Bill 2011 Status of this Submission This Submission has been prepared through the Municipal Waste Advisory Council (MWAC) for the Western Australian

More information

Derbyshire Constabulary ENVIRONMENTAL MANAGEMENT PLAN NOVEMBER POLICY REFERENCE 07/190. This plan is suitable for Public Disclosure

Derbyshire Constabulary ENVIRONMENTAL MANAGEMENT PLAN NOVEMBER POLICY REFERENCE 07/190. This plan is suitable for Public Disclosure Derbyshire Constabulary ENVIRONMENTAL MANAGEMENT PLAN NOVEMBER 2015-2018 POLICY REFERENCE 07/190 This plan is suitable for Public Disclosure Owner of Doc: Head of Department, Finance & Business Services

More information

Clogrennane Lime Ltd. Toonagh Lime Works AER Licence # P

Clogrennane Lime Ltd. Toonagh Lime Works AER Licence # P Clogrennane Lime Ltd Toonagh Lime Works AER 2010 Licence # P0 771-01 Section 1 Overview. 3 1.0 Introduction 1.1 Description of Activities 1.2 Responsibility for Environmental Management 1.3 Environmental

More information

Network Operator s Licence Operational Audit

Network Operator s Licence Operational Audit Cooranbong Water Pty Ltd Network Operator s Licence Operational Audit Flow Systems Date: February 2018 Version: 3.00 Final report Document Status: Version: 3.00 Final report Document History: Status Review

More information

Management Plan. Environmental Management Strategy

Management Plan. Environmental Management Strategy 3-3544 No. 9 31 Oct 18 PSE Manager Management Plan Environmental Management Strategy Risk Statement: High This document will be reviewed on a yearly basis, unless a process change occurs earlier than this

More information

BEVERAGE CANS REVESBY

BEVERAGE CANS REVESBY BEVERAGE CANS REVESBY POLLUTION INCIDENT RESPONSE MANAGEMENT PLAN Environment Protection Authority License 643 Item ID: 8409 Version: 1.2 Page 1 of 16 1.0 OVERVIEW AND LEGAL REQUIREMENTS This Pollution

More information

Contractor Training Courses & Pre-requisites. October 2017

Contractor Training Courses & Pre-requisites. October 2017 Contractor Training Courses & Pre-requisites October 2017 Available courses and pre-requisites It is very important that all participants have completed the course pre-requisites before attending our training.

More information

EDUCATION SUPPORT OFFICER. GRADE FIVE Position Information Document

EDUCATION SUPPORT OFFICER. GRADE FIVE Position Information Document J:\office\Advertising new positions\bursar\finanaceofficer2015.docx EDUCATION SUPPORT OFFICER GRADE FIVE Position Information Document Name Position Title School Finance Officer Stream Resources Admin

More information

2015 Corporate Energy Consumption Report. london.ca. City of London. August 2016

2015 Corporate Energy Consumption Report. london.ca. City of London. August 2016 2015 Corporate Energy Consumption Report City of London August 2016 london.ca Contents 1. Background... 3 2. Corporate Energy Consumption Overview... 3 2.1 Methods of Measurement... 4 2.2 Limitations of

More information

Kurnell Refinery Conversion Project

Kurnell Refinery Conversion Project Kurnell Refinery Conversion Project Waste Management Plan CALTEX REFINERIES (NSW) PTY LTD January 2014 Page 1 1 INTRODUCTION Caltex propose to convert the petroleum refinery in Kurnell (the Site ) to a

More information

PUBLIC REPORT TEMPLATE 2011

PUBLIC REPORT TEMPLATE 2011 PUBLIC REPORT TEMPLATE 2011 Please note that this template has been updated based on feedback from a number of Corporations during the recent review of regulations. It is not compulsory for you to use

More information

ENERGY PERFORMANCE CONTRACTING IN AUSTRALIA Thailand ESCO Fair By: Tony Dorotic National Sales & Marketing Manager Energy Conservation Systems

ENERGY PERFORMANCE CONTRACTING IN AUSTRALIA Thailand ESCO Fair By: Tony Dorotic National Sales & Marketing Manager Energy Conservation Systems ENERGY PERFORMANCE CONTRACTING IN AUSTRALIA Thailand ESCO Fair 2009 By: Tony Dorotic National Sales & Marketing Manager Energy Conservation Systems Commonwealth of Australia 7,617,930 square kilometres

More information

Environmental Management System 2015

Environmental Management System 2015 Environmental Management System 2015 Table of Contents 1 Scope of EMS... 3 2 Environmental policy... 5 3 Planning... 5 3.1 Environmental aspects... 5 3.2 Legal and other requirements... 7 3.3 Objectives,

More information

AUDIT GUIDELINES: ELECTRICITY, GAS AND WATER LICENSING: AUDIT TEMPLATE FOR SMALLER ORGANISATIONS

AUDIT GUIDELINES: ELECTRICITY, GAS AND WATER LICENSING: AUDIT TEMPLATE FOR SMALLER ORGANISATIONS AUDIT GUIDELINES: ELECTRICITY, GAS AND WATER LICENSING: AUDIT TEMPLATE FOR SMALLER ORGANISATIONS This document is available from the Economic Regulation Authority website www.era.wa.gov.au. For further

More information

Waste Coordination Officer. (Closes Tuesday 7th February 2017)

Waste Coordination Officer. (Closes Tuesday 7th February 2017) Hilltops Council INFORMATION PACKAGE for the position of Waste Coordination Officer (Closes Tuesday 7th February 2017) PACKAGE CONTENTS ADVERTISEMENT... 2 GENERAL INFORMATION... 3 CONDITIONS OF EMPLOYMENT...

More information

Rail Safety Management Procedure General Engineering and Operational Systems - Asset Management of Rolling Stock

Rail Safety Management Procedure General Engineering and Operational Systems - Asset Management of Rolling Stock 1/16 Management of Rolling Stock Revision Date Comments 1 January 2011 Procedure developed to support SMS and legislative requirements. 2 February 2012 Reviewed with RISSB Standards and change of titles

More information

CARBON NEUTRAL PROGRAM PUBLIC DISCLOSURE SUMMARY Carbon Neutral Program

CARBON NEUTRAL PROGRAM PUBLIC DISCLOSURE SUMMARY Carbon Neutral Program 2014- Carbon Neutral Program PUBLIC DISCLOSURE SUMMARY 1 JULY 2014 30 JUNE Declaration FOR WESTPAC GROUP, SUSTAINABILITY IS NOT A STATIC AGENDA. WE KNOW THAT THE ISSUES THAT IMPACT OUR CUSTOMERS, EMPLOYEES

More information

The White Certificate Scheme in New South Wales, Australia

The White Certificate Scheme in New South Wales, Australia The White Certificate Scheme in New South Wales, Australia Dr David Crossley Managing Director Energy Futures Australia Pty Ltd IEA Demand Side Management Programme Task 14 Workshop on White Certificates

More information

Control Centre Operator. Permanent, Part-time. Intelligent Networks. Service Delivery for Customers. Team Leader System Monitoring

Control Centre Operator. Permanent, Part-time. Intelligent Networks. Service Delivery for Customers. Team Leader System Monitoring Position Description Position Title: Employment Type: Section: Division: Control Centre Operator Permanent, Part-time Intelligent Networks Service Delivery for Customers Salary Band: Band 2 Agreement:

More information

Health and Safety Policy Standard

Health and Safety Policy Standard Health and Safety Policy Standard Issue Date: 1 st July 2010 Authority: Directors, AES Group Applicability: AES Group covering all business divisions, operating companies and business units throughout

More information

OHS Management of Contractors in Capital Works and Maintenance

OHS Management of Contractors in Capital Works and Maintenance OHS Management of Contractors in Capital Works and Maintenance Physical Resources/Risk, Health and Safety Prepared by: Physical Resources/Risk, Health and Safety Version: 08/04/2008 Contents Page 1. INTRODUCTION...

More information

Greenhouse Gas Assessment

Greenhouse Gas Assessment Sustainability, Energy & Carbon Management Greenhouse Gas Assessment for Impact Digital Pty Ltd FY 216/17 Authored by Susan Kitchener Reviewed by Chris Wilson* Approved by Iain Smale Document Number: v1

More information

RING FENCING GUIDELINE

RING FENCING GUIDELINE RING FENCING GUIDELINE PLAN AER Submission - July 2017 Purpose of this document > This document outlines Essential Energy s strategy to achieve compliance with the AER s Ring Fencing Guideline > This strategic

More information

Chapter 6 Objective: Protect and Enhance the Environment

Chapter 6 Objective: Protect and Enhance the Environment Chapter 6 Objective: Protect and Enhance the Environment 49 Irish Water Water Services Strategic Plan Our Strategic Aims Ensure that Irish Water services are delivered in a sustainable manner which contributes

More information

Sydney Port Botany Terminal 3 Project Out of Hours Works Protocol

Sydney Port Botany Terminal 3 Project Out of Hours Works Protocol 1/11 Terms and Definitions The following terms, abbreviations and definitions are used in this plan: Terms Explanation SPBT3 Sydney Port Botany Terminal 3 CEMP EM EPA ERAP OEH PAH OOHWP EIS MCoA Distribution

More information

Outage Protocol: Explanatory note

Outage Protocol: Explanatory note Outage Protocol: Explanatory note This is the version of the outage protocol (previously in section VII of part F of the Electricity Governance Rules 2003) that the Authority is required to publish by

More information

Carbon Neutrality Action Plan

Carbon Neutrality Action Plan Carbon Neutrality Action Plan 2018-2020 Contents Executive Summary...3 Action Plan...5 1. Glossary... 16 2. Purpose... 16 3. Council s Better Place Strategic Planning Framework... 16 4. Scope... 18 5.

More information

Environment and Sustainability Coordinator

Environment and Sustainability Coordinator POSITION DESCRIPTION Environment and Sustainability Coordinator 1 POSITION DETAILS Position Title: Reports to: Department: Location: Environment and Sustainability Coordinator Manager Wastewater and Environment

More information

ANNUAL ENVIRONMENTAL MANAGEMENT REPORT

ANNUAL ENVIRONMENTAL MANAGEMENT REPORT ORICA KURRI KURRI ANE PLANT ANNUAL ENVIRONMENTAL MANAGEMENT REPORT JULY 2018 Revision Date Description Author Approver 0 2018 Annual Environmental Report D Horne Kurri ANE Plant Senior Supervisor Richard

More information

Kurnell Refinery Conversion Project

Kurnell Refinery Conversion Project Kurnell Refinery Conversion Project Contamination Management Plan CALTEX REFINERIES (NSW) PTY LTD January 2014 Page 1 1 INTRODUCTION Caltex propose to convert the petroleum refinery in Kurnell (the Site

More information

Sustainability Report

Sustainability Report Sustainability Report 1 Our Environmental Responsibility 1. Environmental Risk 2. Energy 3. Greenhouse Gases (GHG) Emissions 4. Water 5. Waste Management (1031), (1032), (1033) Because we operate in an

More information

EO & GSA S STRATEGIC SUSTAINABILITY PERFORMANCE PLAN

EO & GSA S STRATEGIC SUSTAINABILITY PERFORMANCE PLAN EO 13514 & GSA S STRATEGIC SUSTAINABILITY PERFORMANCE PLAN MAUREEN ROSKOSKI, REPA, LEED AP O+M FACILITY ENGINEERING ASSOCIATES, PC December 1, 2010 GSA Heartland Sustainability Forum Today s Agenda Why:

More information

Greenhouse Gas Assessment

Greenhouse Gas Assessment Sustainability, Energy & Carbon Management Greenhouse Gas Assessment for Clayton Utz FY 217/18 Authored by Natalie Saunders Reviewed by Chris Wilson* Approved by Iain Smale Document Number: v1 Date: 24

More information

NSW MINING Health, Safety, Environment & Community

NSW MINING Health, Safety, Environment & Community NSW MINING Health, Safety, Environment & Community Oliver Holm Executive Director Resource Assessments and Compliance NSW Department of Planning and Environment An Update on Assessment Reforms Our Objectives

More information

Water Management Act Amendment Bill 2018 EDO NSW Briefing Note and Key Issues Summary 19 June 2018

Water Management Act Amendment Bill 2018 EDO NSW Briefing Note and Key Issues Summary 19 June 2018 Water Management Act Amendment Bill 2018 EDO NSW Briefing Note and Key Issues Summary 19 June 2018 This briefing note is divided into the following 12 Parts: Part 1: Introduction Part 2: Executive Summary

More information

Process Definition: Sustainability

Process Definition: Sustainability Facilities and Services Division 1. SUMMARY Process Definition: 1.1. This document defines the processes provided by the team in detail. 1.2. The relationship between this Business Unit process and the

More information

ANNUAL ENVIRONMENTAL MANAGEMENT REPORT

ANNUAL ENVIRONMENTAL MANAGEMENT REPORT ORICA KURRI KURRI ANE PLANT ANNUAL ENVIRONMENTAL MANAGEMENT REPORT JULY 2014 Revision Date Description Author Approver 0 2014 Annual Environmental Report D Horne Manufacturing Superintendent Kurri R Powell

More information

Supply Chain Sustainability School Self Assessment

Supply Chain Sustainability School Self Assessment Supply Chain Sustainability School Self Assessment Question Tally Question No: Sustainability issues and topic No knowledge Understand the basic principles but would like to know more Have a good working

More information