NYISO COMPREHENSIVE PLANNING PROCESS for RELIABILITY NEEDS
|
|
- Bernice Bell
- 5 years ago
- Views:
Transcription
1 NYISO COMPREHENSIVE PLANNING PROCESS for RELIABILITY NEEDS By Garry Brown Vice President Strategic Development New York Independent System Operator September 29, 2004 Montreal, Quebec
2 Background NYISO has historically performed short-term planning analyses (1-3 year) in conformance with NERC, NPCC and NYSRC requirements Since Order 888 FERC has deemed that a broad regional planning process is an essential function for ISO/RTOs NYISO s Board supports a strong planning role In Early 2003, as part of its Strategic Planning efforts, NYISO approached its Stakeholders to begin the development of a comprehensive planning process for New York Wide stakeholder support for moving ahead 2
3 Stakeholder Response In June 2003, the Electric System Planning Working Group ( ESPWG ) was formed Reports to both the Business Issues Committee and Operating Committee of the NYISO ESWPG s initial function was to work with NYISO Staff to develop a comprehensive planning process for the NYISO Role was later expanded by the OC to include an ongoing responsibility to provide input and review of the planning process itself Consensus to employ a phased process which would address reliability needs first 3
4 NYISO Planning Process Phase I: Initial Planning Process Approved by OC on Sept 10, 2003 Identifies reliability needs only: 10-year planning horizon Reports on historic congestion First draft report issued June 2004: under committee review Phase II: Comprehensive Planning Process Builds on Initial Planning Process Establishes a formal planning process for the NYISO which initially addresses reliability needs NYISO Objective: To ensure that upgrades will be built when needed for reliability Approved by the NYISO Management Committee on July 7, 2004 with a 68% vote 4
5 Stakeholder Process Electric System Planning Working Group (ESPWG) brings together business and technical interests NYISO Comprehensive Reliability Planning Process is the result of more than a year s intensive efforts A compromise was forged to meet the interests of many diverse groups Generators and Marketers, LSE s & consumers, TO s, Public Power and Environmental, regulatory authorities & NYISO Resulting in the establishment of a comprehensive planning process for New York that ensures reliability needs will be met 5
6 Annual Needs Assessment NYISO Staff will perform a needs assessment over a 10-year planning horizon based upon existing reliability criteria Scenario analysis will be employed to test the robustness of the base case assumptions Needs Assessment will identify violations of reliability criteria, but will not identify specific facilities to meet the identified needs Provision for MP input & review of Needs Assessment Provision for coordination with adjacent regions The final approved Needs Assessment will be widely distributed 6
7 Request for Solutions Following issuance of its Needs Assessment, the NYISO will provide an appropriate time period for the development of market-based & regulated responses Process is open to all resources NOT a formal RFP process When a reliability need is first identified by the NYISO: TOs have obligation to prepare a regulated backstop proposal Such proposals are not limited to transmission Development time for the regulated backstop provides the benchmark for the lead time for non-to alternate proposals 7
8 Request For Solutions (Cont d) Market-based proposals are prepared in parallel with regulated backstop proposals All resources eligible: generation, merchant transmission, demand response Non-TO s may submit alternative regulated proposals to the NYDPS for consideration Such proposals which satisfy the DPS may be submitted to the NYISO for evaluation 8
9 NYISO Evaluation Process NYISO to evaluate proposals to determine if they will meet the identified reliability needs Regulated backstop proposals by TOs will establish the lead time for non-to proposals If Market based proposals are judged sufficient to meet the identified needs in a timely manner, the Comprehensive Reliability Plan ( CRP ) will so state NYISO will not select from among the market-based responses NYISO will monitor status of market projects to ensure needs will be met as part of its annual update process 9
10 NYISO Evaluation Process (Cont d) If Market proposals are judged insufficient, NYISO will indicate that a regulated solution is needed in the CRP NYISO will evaluate non-to regulated alternatives to determine whether they will meet the identified need, and will report its evaluation in the CRP If market-based proposals are not forthcoming NYISO and its Independent Market Advisor will investigate whether that is due to market failure in one of its markets If so, NYISO and its IMA will examine appropriate modifications to its market rules with MPs. 10
11 Review and Approval Process NYISO staff issues draft plan including recommended transmission upgrades, or other regulatory solution, if needed for reliability NYISO Staff draft plan circulated for stakeholder review and comment NYISO staff makes revisions as appropriate Final draft plan sent to the appropriate stakeholder committees for review and vote NYISO staff makes revisions as appropriate Final draft plan sent to Board for approval Provision for remand to Management Committee NYISO Board to have final approval of CRP CRP provided to regulatory agencies for their consideration 11
12 Gap Solutions for Reliability Needs If neither market proposals nor regulated proposals can satisfy the need in a timely manner, the NYISO may seek a Gap solution Provision for NYISO to seek a gap solution outside of the normal Planning Process if there is an imminent threat to reliability TOs assume the obligation to immediately propose a gap solution for consideration by the NYISO and DPS To the extent possible, the gap solution should be temporary and strive to ensure that market based solutions will not be economically harmed A permanent regulated solution, if appropriate, may proceed in parallel with gap measures 12
13 Cost Allocation and Cost Recovery Cost Allocation for Regulated Projects Based upon a beneficiaries pay principle Specific methodology to be developed by NYISO/ESPWG Near-term reliability needs are not anticipated based upon Phase I needs assessment Cost Recovery for Regulated Projects Transmission solutions TOs to file for recovery with FERC Recovery through a separate rate schedule under the NYISO Tariff Non-transmission solutions In accordance with NYS Public Service Law 13
14 NYISO-TO Agreement Defines TO rights and obligations with respect to the Comprehensive Reliability Planning Process Similar provisions to those recently approved for RTO-NE TOs assume obligation to provide backstop regulated solutions If NYISO determines that there are no viable market-based solutions which will meet identified Reliability Needs Subject to cost recovery, permitting and other conditions Supplements existing NYISO/TO Agreement Not subject to OC/MC approval Will be filed for FERC approval Filed concurrently with NYISO Tariff Filing 14
15 Role of the NYS PSC Reviews and screens regulated alternatives proposed by non-tos Reviews and screens gap solutions Adjudicates disputes relating to reliability determinations in final Needs Assessment and in CRP Reviews TOs backstop solution when NYISO determines action is necessary to ensure reliability PSC has final authority with respect to solution ultimately implemented 15
16 NYISO Reliability Planning Process INITIAL PHASE NYISO Performs Needs Assessment for Reliability Publicize Needs Assessment NYISO Issues Request for Solutions Market Responses Generation DSM Merchant Transmission Regulated Responses Transmission May consider alternatives TO & non-to proposals NYISO Evaluates Market Responses and Regulated Responses To Ensure They Will Meet the Identified Reliability Needs NYISO Formulates Comprehensive Reliability Plan Board Approval of Plan No viable/timely mkt or reg solution to an identified need Gap Solutions by TOs COMPREHENSIVE PHASE Board Approval of Plan
DRAFT FOR DISCUSSION PURPOSES PROPOSED STRAWMAN PROPOSAL IN RESPONSE TO ORDER 890
DRAFT FOR DISCUSSION PURPOSES PROPOSED STRAWMAN PROPOSAL IN RESPONSE TO ORDER 890 OVERVIEW AND PURPOSE This strawman proposes enhancements to NYISO s existing reliability and economic planning processes
More informationPublic Policy Transmission Planning Process Manual
MANUAL 36 Public Policy Transmission Planning Process Manual July 2015 Version: 1.0 Effective Date: 07/31/2015 Committee Acceptance: 07/15/2015 BIC 07/16/2015 OC This document was prepared by: System &
More informationWritten Statement of Thomas Rumsey Vice President External Affairs New York Independent System Operator
Written Statement of Thomas Rumsey Vice President External Affairs New York Independent System Operator Senate Energy and Telecommunications Committee Senator George D. Maziarz, Chairman Public Hearing
More informationDefining Outage States to Include a Mothball Outage
Defining Outage States to Include a Mothball Outage Emilie Nelson Director, Operations Josh Boles Manager ICAP Market Market Issues Working Group November 7, 2013 2013 New York Independent System Operator,
More informationAddressing Affected System Impacts of Generator Interconnection: Processes and Principles
Addressing Affected System Impacts of Generator Interconnection: Processes and Principles August 5, 2013 Table of Contents 1 Executive Summary... 2 2 Introduction... 2 3 Stakeholder Process and Schedule...
More informationUpdate on Northeast Seams Issues. February 20, 2008 NYISO Business Issues Committee Meeting
Update on Northeast Seams Issues February 20, 2008 NYISO Business Issues Committee Meeting Status of Seams Projects Current Deliverables Project 1. Intra-Hour Transaction Scheduling NYISO and ISO-NE have
More informationRamapo Phase Angle Regulator Cost Recovery Discussion
Ramapo Phase Angle Regulator Cost Recovery Discussion Wes Yeomans Vice President Operations MIWG April 10, 2017 Background The NYISO and PJM have commenced a joint stakeholder initiative to consider modifying
More informationNew York Independent System Operator System Reliability Impact Study Criteria and Procedures
New York Independent System Operator System Reliability Impact Study Criteria and Procedures Note: Project Developers are advised that these documents do not address cost allocation Approved by the Operating
More information2015 Annual Incentive Goals
2015 Annual Incentive Goals Budget & Priorities Working Group November 21, 2014 Jennifer Chatt Vice President - Human Resources 2014 New York Independent System Operator, Inc. All Rights DRAFT FOR DISCUSSION
More informationTransmission Expansion and Interconnection Manual. June 2017
MANUAL 23 Transmission Expansion and Interconnection Manual June 2017 Version: 3.0 Effective Date: 06/30/2017 Committee Acceptance: BIC 06/14/2017 OC 06/15/2017 This document was prepared by: NYISO Interconnection
More informationNotice of Attachment H Transmission Owners Stakeholder Process for Order No Interregional Cost Allocation Proposals (June 10, 2013)
Notice of Attachment H Transmission Owners Stakeholder Process for Order No. 1000 Interregional Cost Allocation Proposals (June 10, 2013) Described on the following pages are the proposals of the Attachment
More informationISO New England - ISO New England Inc. Transmission, Markets and Services Tariff
ATTACHMENT K REGIONAL SYSTEM PLANNING PROCESS TABLE OF CONTENTS 1. Overview 2. Planning Advisory Committee 2.1 Establishment 2.2 Role of Planning Advisory Committee 2.3 Membership 2.4 Procedures (a) Notice
More informationLoad Forecasting Manual
Load Forecasting Manual 1. OVERVIEW 1.1 PURPOSE AND SCOPE This manual has two purposes. The first is to explain the load forecasting methodology and load data submission requirements that are contained
More informationBroader Regional Markets Report
Broader Regional Markets Report Rana Mukerji SENIOR VICE PRESIDENT MARKET STRUCTURES, NYISO Business Issues Committee Meeting June 20, 2018, Rensselear, NY 1 Market-to-Market Coordination-PJM Implement
More information/s/ Henry Chao Henry Chao Vice President, System Resource Planning. December 9, 2013
December 9, 2013 10 Krey Boulevard Rensselaer, NY 12144 Re: NYISO 2013 Congestion Assessment and Resource Integration Studies Report Dear NYISO Economic Planning Interested Parties: On November 19, 2013
More informationBroader Regional Markets Report
Broader Regional Markets Report Rana Mukerji SENIOR VICE PRESIDENT MARKET STRUCTURES, NYISO Business Issues Committee Meeting February 14, 2018, Rensselear, NY 1 Market-to-Market Coordination-PJM Implement
More informationNERC Organization Standards: What are they????
NERC Organization Standards: What are they???? Northeast Power Coordinating Council General Meeting September 19, 2002 Stanley E. Kopman Director, Planning and Compliance Northeast Power Coordinating Council
More informationCongestion Assessment and Resource Integration Studies. A Report by the New York Independent System Operator
Congestion Assessment and Resource Integration Studies A Report by the New York Independent System Operator April 2018 2017 Congestion Assessment and Resource Integration Study Comprehensive System Planning
More informationISO-NE and NYISO Inter-Regional Interchange Scheduling (IRIS)
Joint Stakeholder Meeting ISO-NE and NYISO Inter-Regional Interchange Scheduling (IRIS) May 20, 2011 / Springfield, MA Agenda Today: Voting Process and Principles - Discussion Q&A on Proposals DBD and
More informationMinutes of RRS Meeting No Introduction
Joint Meeting of the New York State Reliability Council, L.L.C. (NYSRC) Reliability Rules Subcommittee (RRS) / Reliability Compliance Monitoring Subcommittee (RCMS) Thursday, August 3, 2017 Minutes of
More informationBusiness Practice Manual for The Transmission Planning Process
Business Practice Manual for The Transmission Planning Process Posted: June 2, 2015 Intentionally left blank TABLE OF CONTENTS 1. Introduction... 9 1.1. Purpose of California ISO Business Practice Manuals...
More informationELECTRIC TRANSMISSION 201: Markets, ISO/RTOs and Grid Planning/Operations
ELECTRIC TRANSMISSION 201: Markets, ISO/RTOs and Grid Planning/Operations Kevin Reeves Managing Director, Transmission Strategy American Electric Power Organized Markets Organized markets are managed by
More informationCraig Glazer Vice President Federal Government Policy PJM Interconnection
On behalf of the RTOs that submitted comments in this proceeding, we wanted to express again our appreciation for your reaching out to us to discuss the Reliability Safety Valve proposal embodied in our
More informationWes Yeomans Vice President Operations Management Committee May 31, 2017 COPYRIGHT NYISO ALL RIGHTS RESERVED
Ramapo Phase Angle Regulator Cost Recovery Wes Yeomans Vice President Operations Management Committee May 31, 2017 Agenda Background Benefits of Two Ramapo Phase Angle Regulators Annual Cost Projections
More informationOpen Access Transmission Tariff ATTACHMENT K
ATTACHMENT K PART I Introduction The Transmission Provider s (herein referred to as Tacoma Power) local transmission planning process will include open planning meetings that Tacoma Power will conduct
More informationATTACHMENT K TRANSMISSION PLANNING PROCESS
ATTACHMENT K TRANSMISSION PLANNING PROCESS 1.0 Introduction This Attachment K addresses the rights and obligations of Transmission Customers, relevant stakeholders and the Transmission Provider related
More informationBroader Regional Markets Report
Broader Regional Markets Report Rana Mukerji SENIOR VICE PRESIDENT MARKET STRUCTURES, NYISO Business Issues Committee Meeting February 13, 2019, Rensselaer, NY 1 Market-to-Market Coordination-PJM Implement
More informationDave LaPlante Vice President, Markets Development September 18, 2002
Northeast Power Coordinating Council 2002 General Meeting ISO New England Perspectives on the FERC SMD NOPR Dave LaPlante Vice President, Markets Development September 18, 2002 Restructuring in the Northeast:
More informationBroader Regional Markets Report
Broader Regional Markets Report Rana Mukerji SENIOR VICE PRESIDENT MARKET STRUCTURES, NYISO Business Issues Committee Meeting December 12, 2018, Rensselaer, NY 1 Market-to-Market Coordination-PJM Implement
More informationBroader Regional Markets Report
Broader Regional Markets Report Rana Mukerji SENIOR VICE PRESIDENT MARKET STRUCTURES, NYISO Business Issues Committee Meeting January 16, 2019, Rensselaer, NY 1 Market-to-Market Coordination-PJM Implement
More informationBroader Regional Markets Report
Broader Regional Markets Report Rana Mukerji SENIOR VICE PRESIDENT MARKET STRUCTURES, NYISO Business Issues Committee Meeting November 14, 2018, Rensselaer, NY 1 Market-to-Market Coordination-PJM Implement
More informationBroader Regional Markets Report
Broader Regional Markets Report Rana Mukerji SENIOR VICE PRESIDENT MARKET STRUCTURES, NYISO Business Issues Committee Meeting April 11, 2018, Rensselear, NY 1 Market-to-Market Coordination-PJM Implement
More informationA separate notification will be provided to NPCC Members announcing the start of the formal 10 day ballot period.
October 3, 2011 NPCC Full and General Members; Please find attached a draft of the NPCC Regional Standard PRC-006-NPCC-1 Automatic Underfrequency Load Shedding which has been posted to the NPCC Website
More informationNorth American Energy Standards Board
North American Energy Standards Board 1301 Fannin, Suite 2350, Houston, Texas 77002 Phone: (713) 356-0060, Fax: (713) 356-0067, E-mail: naesb@naesb.org Home Page: www.naesb.org NERC NAESB Template Prepared
More information2013 Congestion Assessment and Resource Integration Study
Style Definition: Footnote: Font: (Default) Arial 2013 Congestion Assessment and Resource Integration Study Comprehensive System Planning Process CARIS Phase 1 DRAFT August 27September 9, 2013 NYISO System
More informationNYSRC RELIABILITY RULE/NERC STANDARD CROSS-REFERENCE
7/1/05 NYSRC RELIABILITY RULE/NERC STANDARD CROSS-REFERENCE NYSRC Reliability A. RESOURCE ADEQUACY A-R1. Statewide Installed Reserve Margin Requirements A-R2. Load Serving Entity ICAP Requirements None
More informationB-R1 TRANSMISSION SYSTEM PLANNING PERFORMANCE REQUIREMENTS
Draft 7/15/14 rev7 1 B-R1 TRANSMISSION SYSTEM PLANNING PERFORMANCE REQUIREMENTS A. Reliability Rule NYCA transmission facilities in the NYS Bulk Power System shall be planned to operate reliably over a
More informationEastern Interconnection Planning Project Status John P Buechler NYISO Executive Regulatory Policy Advisor
Eastern Interconnection Planning Project Status John P Buechler NYISO Executive Regulatory Policy Advisor NPCC Governmental/Regulatory Affairs Advisory Group Meeting November 27, 2012 Montreal, Quebec
More informationSustaining & Enhancing Reliability in NY
Sustaining & Enhancing Reliability in NY Stephen G. Whitley President & CEO New York Independent System Operator Northeast Power Coordinating Council General Meeting December 1, 2010 Albany, NY Topics
More informationIntroduction to RRG Drafting Team Proposal
November 17, 2003 Introduction to RRG Drafting Team Proposal SUMMARY This introduction will review the overall task the RRG drafting team took on, set out the overall guiding principles it used, and describe
More information2011 Congestion Assessment and Resource Integration Study
2011 Congestion Assessment and Resource Integration Study Comprehensive System Planning Process CARIS Phase 1 Final Report March 20, 2012 NYISO System Resources and Planning staff can be reached at 518-356-6000
More informationAppendix 5B. Statement of Compliance Registry Criteria
Appendix 5B Statement of Compliance Registry Criteria Revision 5.1 Effective: July 1, 2014 (as noted below) The highlighted terms Bulk Electric System and Load in this document will become effective as
More informationBroader Regional Markets Report
Broader Regional Markets Report Rana Mukerji SENIOR VICE PRESIDENT MARKET STRUCTURES, NYISO Business Issues Committee Meeting August 13, 2018, Rensselear, NY 1 Market-to-Market Coordination-PJM Implement
More informationEastern Interconnection Planning Collaborative
Eastern Interconnection Planning Collaborative Challenge to the Industry New energy policies are driving the need to create a framework to analyze transmission scenarios on a broad multi-regional and interconnection-wide
More informationRevised Transmission Planning Process. Complete Final Proposal
Revised Transmission Planning Process Complete Final Proposal May 7, 2010 Complete Final Proposal 1. Introduction and Summary In this document the ISO provides a complete description of its revised transmission
More informationNERC Analysis of NERC Standard Process Results Second Quarter 2011 in Docket Nos. RR , RR
July 29, 2011 VIA ELECTRONIC FILING Ms. Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, NE Washington, D.C. 20426 Re: NERC Analysis of NERC Standard Process Results Second
More informationSPP RE Regional Reliability Standards Development Process Manual
SPP RE Regional Reliability Standards Development Process Manual FERC Approved January 31, 2014 Table of Contents I. Introduction...2 II. Background...3 III. Regional Reliability Standard Definition, Characteristics,
More informationAdvancing Renewable Alternatives
Advancing Renewable Alternatives FERC/RTO Training Session Institute for Policy Integrity New York University School of Law June 15, 2011 Abigail Krich President, Boreas Renewables About Boreas Renewables
More informationApproved by Standing Committees Approved by Board of Trustees
Reliability Functional Model Function Definitions and Responsible Entities Prepared by the Functional Model Working Group Version 4 Approved by Standing Committees Approved by Board of Trustees August
More informationContents. DRAFT Capacity Deliverability Fact Finding Summary Report
DRAFT Capacity Deliverability Fact Finding Summary Report Contents 1 Background... 3 2 Overview of findings... 5 2.1 Implement methods for setting limits that respect the physical topology of the system
More informationReliability Cost Allocation
Reliability Cost Allocation Zach Smith Director, Transmission Planning New York Independent System Operator ESPWG May 16, 2016 NYISO 2014 New York Independent System Operator, Inc. All Rights Reserved.
More informationNorth American Energy Standards Board
Principles & Assumptions: The joint standards should be readily and easily available to all industry participants required to follow them. The jointly developed standard(s) should clearly distinguish components
More informationNYISO Management Response to FTI Consulting Report Evaluation of the New York Capacity Market
NYISO Management Response to FTI Consulting Report Evaluation of the New York Capacity Market March 2013 Evaluation of the New York Capacity Market Introduction In an effort to evaluate and, where appropriate,
More informationConcepts for Aggregation Participation In Demand Side Ancillary Service Program (DSASP)
Concepts for Aggregation Participation In Demand Side Ancillary Service Program (DSASP) Donna Pratt Manager, Demand Response Products Demand Response Products New York Independent System Operator Market
More information2014 Project Schedule Milestone Update
2014 Project Schedule Milestone Update Ryan Smith Senior Manager, Enterprise Product & Project Management New York Independent System Operator Budget and Priorities Working Group May 05, 2013 Krey Corporate
More information2007 NYSRC RELIABILITY COMPLIANCE PROGRAM
2007 RELIABILITY PROGRAM MEASUREMENT DESCRIPTION DOC. OF Resource Adequacy A-M2 A-R2,3 Establishing LSE ICAP requirements A 4/1/07 3/8/07 3/8/07 FC A-M3 A-R2,3 Certifying LSE ICAP obligations are met*
More informationShared Governance at the New York Independent System Operator
Shared Governance at the New York Independent System Operator Robert E. Fernandez General Counsel Presentation to Consumer Advisory Council October 6, 2011 Governing Documents Transmission Owners (TO)
More informationMemorandum. This memorandum requires Board action. EXECUTIVE SUMMARY
California Independent System Operator Corporation Memorandum To: ISO Board of Governors From: Keith Casey, Vice President, Market & Infrastructure Development Date: December 6, 2017 Re: Decision on contingency
More information2014 Project Schedule Milestone Update
2014 Project Schedule Milestone Update Ryan Smith Senior Manager, Enterprise Product & Project Management New York Independent System Operator Budget and Priorities Working Group November 21, 2014 Krey
More informationMEMORANDUM OF UNDERSTANDING BETWEEN THE ONTARIO ENERGY BOARD AND THE NORTH AMERICAN ELECTRIC RELIABILITY CORPORATION
MEMORANDUM OF UNDERSTANDING BETWEEN THE ONTARIO ENERGY BOARD AND THE NORTH AMERICAN ELECTRIC RELIABILITY CORPORATION This Memorandum of Understanding ( MOU ) between the Ontario Energy Board (the Board
More informationPJM Manual 14A: New Services Request Process Revision: 20 Effective Date: October 1, Prepared by Interconnection Planning Department
PJM Manual 14A: New Services Request Process Revision: 20 Effective Date: October 1, 2017 Prepared by Interconnection Planning Department PJM 2017 Table of Contents Table of Contents Table of Exhibits...7
More informationCalifornia Independent System Operator Corporation Fifth Replacement Electronic Tariff
Table of Contents 40. Resource Adequacy Demonstration for all SCs in the CAISO BAA... 3 40.1 Applicability... 3 40.1.1 [Not Used]... 3 40.2 Information Requirements for Resource Adequacy Programs... 3
More informationElectric Storage as a Transmission Solution in the MTEP Reliability Planning Process. Planning Advisory Committee September 26, 2018
Electric Storage as a Transmission Solution in the MTEP Reliability Planning Process Planning Advisory Committee September 26, 2018 Discussion Today Discuss Stakeholder response to MISO proposed process
More informationParticipation in the monthly auction and the capability period auction shall consist of:
New York Capacity Market (NYISO Installed Capacity Market) The term Installed Capacity in the ICAP Manual and the NYISO Services Tariff Manual describes the market as opposed to the product. For example,
More informationINDEPENDENT SYSTEM OPERATORS (VI + Access Rules vs. ISO vs. ITSO)
INDEPENDENT SYSTEM OPERATORS (VI + Access Rules vs. ISO vs. ITSO) Paul L. Joskow September 28, 2007 ALTERNATIVE SYSTEM OPERATOR MODELS System operator (SO) is vertically integrated utility (G+T) Functional
More informationISO/RTO Metrics Initiative
ISO/RTO Metrics Initiative Mary McGarvey Vice President & Chief Financial Officer New York Independent System Operator Management Committee NYISO Krey Corporate Center January 20, 2010 Government Accountability
More informationBusiness Practice Manual for Reliability Requirements. Version 34
Business Practice Manual for Reliability Requirements Version 34 Last Revised: January 1, 2009July 28, 2010 Approval History Approval Date: 3/27/09 Effective Date: 3/31/09 BPM Owner: Chetty Mamandur BPM
More informationRegional Planning at Midwest ISO. Mr. Clair Moeller Vice President, Transmission Asset Management
Regional Planning at Midwest ISO Mr. Clair Moeller Vice President, Transmission Asset Management Midwest ISO Planning Objectives Fundamental Goal The development of a comprehensive expansion plan that
More informationNV Energy Job Titles and Descriptions [18 CFR Section 358.7(f)(1)] 9/12/2013
NV Energy Job Titles and Descriptions [18 CFR Section 358.7(f)(1)] 9/12/2013 Transmission Function Employees: Vice President, Transmission Responsible for management of transmission operations, including
More informationBusiness Practice Manual for the Transmission Planning Process
Business Practice Manual for the Transmission Planning Process Order 890 Compliance Version 76.0 September 15,February 11, 2010 TABLE OF CONTENTS Order 890 Compliance... i 1. Introduction... 6 1.1 Purpose
More informationCoordination with PJM
Market-to-Market Coordination with PJM Mike DeSocio Market Product Specialist New York Independent System Operator MIWG October 27, 2011 Rensselaer, New York Agenda M2M and NYISO Markets Examples Tariff
More informationNew England States Committee on Electricity
New England Electricity Outlook Environmental & Energy Technology Council of Maine October 20, 2016 New England States Committee on Electricity NESCOE is New England s Regional State Committee, governed
More information2015 Northeastern Coordinated System Plan. ISO New England, New York ISO, and PJM
ISO New England, New York ISO, and PJM April 11, 2016 Contents Preface... iv 1. Executive Summary...1 2. FERC Order No. 1000: Transmission Planning and Cost Allocation...2 2.1 Interregional Coordination
More informationLONG-RANGE TRANSMISSION PLAN
LONG-RANGE TRANSMISSION PLAN 2018-2027 Transmission and Substation Engineering Department October 31, 2017 LONG-RANGE TRANSMISSION PLAN 2018-2027 Prepared by: Roleto Mangonon, Senior Engineer Transmission
More informationCompetitive Entry Exemption: New Proposal
Competitive Entry Exemption: New Proposal Dr. Nicole Bouchez Principal Economist, Market Design New York Independent System Operator Installed Capacity Working Group December 10, 2013 KCC 2013 New York
More information2017 CARIS Phase 1 Report
2017 CARIS Phase 1 Report Timothy Duffy Manager, Economic Planning Business Issues Committee Mar.15, 2018, KCC Topics Background and Objectives of NYISO s Economic Planning Process ( Congestion Asesssment
More informationDistributed Energy Resources Roadmap
Distributed Energy Resources Roadmap Updates Overview James Pigeon Senior Market Design Specialist Distributed Resources Integration MIWG December 19, 2016 Krey Corporate Center - Rensselaer, NY 2000-2016
More informationFlywheel Based Energy Storage for Grid Services
Flywheel Based Energy Storage for Grid Services Matthew Lazarewicz VP and Chief Technical Officer Beacon Power Corporation Buffalo, NY 2011 Advanced Energy Conference October 12-13, 2011 1 Safe Harbor
More informationELECTRIC TRANSMISSION 101: Regulation. Jeff Dennis Office of Energy Policy and Innovation Federal Energy Regulatory Commission
ELECTRIC TRANSMISSION 101: Regulation Jeff Dennis Office of Energy Policy and Innovation Federal Energy Regulatory Commission Obligatory Disclaimer Any views expressed in this presentation are my own,
More informationPJM s Implementation of Order 845
PJM s Implementation of Order 845 Susan McGill Manager, Interconnection Analysis Michelle Harhai PJM Legal Compliance Filing Update On September 24, 2018, the Edison Electric Institute on behalf of its
More informationISO-NE and NYISO Inter-Regional Interchange Scheduling (IRIS)
Joint Stakeholder Meeting ISO-NE and NYISO Inter-Regional Interchange Scheduling (IRIS) April 28, 2011 / Rensselaer, NY Agenda Today: Review of Latency Impacts Congestion Revenue and Uplift Charges Real-Time
More informationConOp. Internal NYISO Controllable Lines. Concept of Operation. Scott Harvey, LECG. Document Locator:
ConOp Internal NYISO Controllable Lines Concept of Operation Author: Reviewers: Scott Harvey, LECG Project Sponsor: Point of Contact: Document Locator: Revision History Date Additions, deletions, modifications
More informationin the NYISO s Market Administration and Control Area Services Tariff ( Services Tariff ).
NYISO 15-25 2015/2016 ICAP Demand Curve Reset RFP 1.3 RFP Objectives, Scope, and Deliverables The objective of this Request for Proposal is to select a consultant to conduct a study of the parameters,
More informationNew England States Committee on Electricity
New England States Committee on Electricity NARUC Energy Regulatory Partnership Program The Energy Regulatory Commission of the Republic of Macedonia and The Vermont Public Service Board by David O Brien,
More informationPJM Black Start Replacement Process RTO Wide Black Start RFP Review Plan
PJM Black Start Replacement Process RTO Wide Black Start RFP Review Plan David Schweizer Manager, Generation OC Meeting June 6, 2017 Overview PJM target for issuing next 5-Year RTO Wide Black Start RFP
More informationCRIS for External-to-ROS Transmission Investment External-to-ROS Deliverability Rights (EDR)
CRIS for External-to-ROS Transmission Investment External-to-ROS Deliverability Rights (EDR) Ethan D. Avallone Senior Market Design Specialist, Energy Market Design Management Committee March 28, 2018
More informationDevelop PJM Criteria/Guidelines for Assessing End of Life Transmission Facilities
Develop PJM Criteria/Guidelines for Assessing End of Life Transmission Facilities AMP, ODEC, DVP, PJM ICC, PJM PPC, LS Power, ITC Mid-Atlantic Development February 25, 2016 Changes from First Read Problem
More information2018/2019 NYSRC RELIABILITY RULE A.2 REQUIREMENTS R1, R2, R3 COMPLIANCE SUBMITTAL
2018/2019 NYSRC RELIABILITY RULE A.2 REQUIREMENTS R1, R2, R3 COMPLIANCE SUBMITTAL COVERING THE NEW YORK CONTROL AREA For the 2018 2019 Capability Year Presented to the Reliability Compliance Monitoring
More informationNew York Independent System Operator, Inc. NYISO Tariffs. OATT Schedules
New York Independent System Operator, Inc. NYISO Tariffs OATT Schedules Document Generated On: 6/30/2010 Page 1 Contents 6 Schedules... 7 6.1 Schedule 1 Scheduling, System Control and Dispatch Service...
More informationRequest to Develop Reliability Rules for Implementation of Rules Enhancement Plan (REP)
Request to Develop Reliability Rules for Implementation of Rules Enhancement Plan (REP) Item 1.Rules Enhancement Plan (REP) Description Response On April 11, 2013, the NYSRC Executive Committee adopted
More informationPage 1 of 1. NPCC Methodology and Guidelines for Forecasting TTC and ATC
Page 1 of 1 NPCC Methodology and Guidelines for Forecasting TTC and ATC Page 3 of 3 Table of Contents TABLE OF CONTENTS... 3 1. SUMMARY... 5 2. STATUS OF OPEN ACCESS IN NPCC... 6 3. OBJECTIVE OF THE NPCC
More informationStatement of Compliance Registry Criteria (Revision 3.1)
Statement of Compliance Registry Criteria (Revision 3.1) Summary Since becoming the Electric Reliability Organization (ERO), NERC has initiated a program to identify candidate organizations for its compliance
More informationNBP (ATG) IR 01 March 5, Reference: NBP 18.01
NBP (ATG) IR 01 March 5, 2015 Reference: NBP 18.01 a. Who does NB Power intend to have testify with respect to the evidence? b. In preparing the evidence, who has reviewed or prepared portions of the evidence
More informationBTM:NG Initiative Energy Market Design Concepts
BTM:NG Initiative Energy Market Design Concepts Pradip Ganesan Market Product Specialist, Energy Market Design New York Independent System Operator MIWG January 29, 2015 Rensselaer, NY 2014 New York Independent
More informationPlease contact the undersigned if you have any questions concerning this filing.
!! February 27, 2018 VIA ELECTRONIC FILING Kirsten Walli, Board Secretary Ontario Energy Board P.O Box 2319 2300 Yonge Street Toronto, Ontario, Canada M4P 1E4 Re: North American Electric Reliability Corporation
More informationA New Role For States In The Administration of Regional Electricity Markets
A New Role For States In The Administration of Regional Electricity Markets David O Connor Commissioner Massachusetts Division of Energy Resources Harvard Electricity Policy Group June 2, 2006 Major Points
More informationDemand Response and Scarcity Pricing
Item #/ Check When Complete Demand and Scarcity Pricing Begin End Category Sub-Category Order 719 Summary Draft Status SPP Notes References Assignment 41 47 63 Demand Allow DR to provide ancillary services
More informationInter-regional Planning Update
Inter-regional Planning Update Transmission Expansion Advisory Committee October 12, 2017 EIPC Production Cost Database Assembly Trial 4 results under review Database renewal and potential next steps under
More informationPJM Transmission Replacement Processes Senior Task Force COST ALLOCATION & COST RECOVERY Educational Session. June 3, 2016
PJM Transmission Replacement Processes Senior Task Force COST ALLOCATION & COST RECOVERY Educational Session June 3, 2016 By Vilna Gaston Associate General Regulatory Counsel PSEG Services Corporation
More informationCongestion Revenue Rights (CRRs) Associated with Integrated Balancing Authority Areas (IBAAs)
Issue Paper and Straw Proposal Congestion Revenue Rights (CRRs) Associated with Integrated Balancing Authority Areas (IBAAs) February 20, 2008 CAISO 2/21/08, page 1 Congestion Revenue Rights (CRRs) Associated
More information