THE PERFORMANCE OF DISBURSEMENT PROCEDURES IN HIGHWAY PUBLIC WORKS IN THAILAND

Size: px
Start display at page:

Download "THE PERFORMANCE OF DISBURSEMENT PROCEDURES IN HIGHWAY PUBLIC WORKS IN THAILAND"

Transcription

1 THE PERFORMANCE OF DISBURSEMENT PROCEDURES IN HIGHWAY PUBLIC WORKS IN THAILAND Dr. B. Israngkura Na Ayudhya, Prof. M. Kunishima Senior lecturer of Civil Engineering Department, Rajamangala University of Technology Krungthep, Bangkok, Thailand, Professor of Civil Engineering and International Studies Department, University of Tokyo, Kashiwa-shi, Chiba, JAPAN, ABSTRACT This paper analyzed performance of disbursement procedure of highway public works projects in Thailand. The results of research were summarized and compared which based on contracts, submitted invoice, inspection dated, copies of payment dated between client and their main contractor and interviewed with persons involved in government project during The data collection was to investigate the reasons related to delaying in payment during construction project (Actual duration of exercise the payment in each month were compared with contract agreement). Literature review, interview and a questionnaire survey targeted at government and local government agencies had been used as the tools to carry out this study. A graphical presentation of a duration analysis of the projects illustrated significant disbursement formation in each project. It was established that the source of fund, the financial stability of clients, method of disbursement and economics situation has play major role on efficiency of disbursement to main contractors in highway public works projects. Key words: Construction delay, Highway construction, Disbursement process, Public works 1. INTRODUCTION Organizational weakness can be observed from several factors. One of significant factors is prolonging debts. Owner tended to stick to a play safe policy in a chronically uncertain environment by keeping the minimum number of permanent employees on their payrolls, elongated their payment due if it is possible without any penalty from employees or suppliers [1-3]. Construction projects can be delayed for several numbers of reasons. The delaying in construction projects are almost accompanied by cost and time overruns. Projects delays are difficult to predict with any accuracy and each delay causes certain risk factors. Delay factors may be prioritized based on the importance of the activity being delayed and the amount of risk involved in each activity. The degree of seriousness of delaying in construction projects varies considerably from projects which were only a few days behind the schedule to projects which delayed over a year [4-5].The successful execution of construction projects within estimated margin cost and planned schedules depend on chosen method that requires good in both engineering and economic judgments [6-7]. Assaf and Al-kahali [8] identified the main causes of delay factors in large building projects and their relative importance. They found 56 causes of delay exist in Saudi construction projects. The main delay factors were preparation and approval of shop drawings, delays in contractor s progress, payment by owners and design changes. The architects and engineers point of view were cash problems during construction period, the relationship between subcontractors and the slow decision making process of the owner. The owners agree architects and engineers on the design errors, labour shortage and inadequate labour skills were important delay factors. Al-Hammed A [9] describes the various elements of cost upon individual public projects but does not deal specifically with construction delays. The government or in another words, the efficiency in making payment to those main contractor, nominated subcontractors and materials suppliers has not been accordingly to agreement contract. Kaming et al [10] studied factors influencing time and cost performance on high-rise projects in Indonesia and conclude that cost and time overruns were very frequent. Therefore, poor cost performance of construction projects seems to be the norm rather the exception particularly in most developing countries where the problem is more acute. ISSN:

2 2. LITERATURE REVIEWS The nature of delays encountered on international construction projects is different from the types of delays experienced on domestic projects. Various factors needed to be taken into consideration. Each country has their rule and regulations for exercise the payment. Government restrictions are imposed in contract agreement. Governmental regulations exasperates banking can cause disbursement delays manifested themselves in the form of delays in the release of foreign currency required for importing materials and equipments, delays in customs clearance and bureaucratic procedures [11]. Furthermore, traditional construction contract has also play a momentum impact on delaying disbursement process as it governs both procedure and duration of each activity is needed in order to assessing the structures or making payment after quantity surveyor has verified the work [12]. The work is paid after the work has been done, usually by installments as agreed amount of progress, rather than in advance. Consequence, the whole industry is economically affected by any drying up of the cascade of payments downward from the top of the pyramid. Elazouni and Metwally (2000) suggest that subcontracting is a practice that contractors reply on to partially finance projects. The funds generated from operations are potentially far greater than the value of the organization managing them [13]. This gives the contracting organization significant opportunities, but leads also to significant risk for the system. Several investigations of the reasons behinds construction delay in construction projects have been carried out in the last two decades. Some of these studies concentrate on specific construction project or types of construction [14]. Others identify the general problems crated by delays and cost overruns, on macro level in aspect of economy [15]. Some delay may occur in the preconstruction stage which is defined as the period between the initial conception of the project and the signing of the construction contract between the public owner and the main contractor. On the other hand, may occur in the construction phase that is basically the period when actual construction is under way. The findings reported in this paper are confined to the reasons for delays in the construction stage. The objective of this research is to determine the performance of actual disbursement against schedule payment of highway public projects and to aid construction managers in establishing adequate evaluation prior to the contract award using quantitative data. The key task was to design research so that the information obtained permits the assessment of their impact. Therefore, the best approach to assessing these potentials was to adopt randomly selected samples. The sampling population was established by selecting 113 public projects. The data was found in contract agreement between central, local government agencies and main contractor. This research projects upon results obtained from a pilot study undertaken on investigating key elements that contribute to the level of success or failure payment system in linkage between client and main contractor for those domestic and international construction companies engaged with the provision of construction infrastructure projects in Thailand. Therefore, this paper aims to add to the body of knowledge of efficiency in disbursement through providing valuable insights from very senior level executives in these organizations. It is often very difficult to gain access for in-depth discussion with such individuals. 3. RESEARCH METHODOLOGY This approach mainly concerns with the examination of statistical data of domestic construction markets from both domestic and international main contractors in Thailand. There were two main data sources in this approach namely: original and residual. The original data consists of original documents or official files and records, such as government book keeping record for disbursement and construction company s record books. The original data consisted mainly of the calculated or justified data which was derived personally. ISSN:

3 Methodology of collective data and analysis data Quantitative data Interview data - Collecting Invoices papers etc. - Reviews published papers Interviews involved persons in disbursement procedure Type of agencies -Central government - Local government Source of funds -Central government - Local government - Oversea funds Calculate the duration of each stage of disbursement and tabulated into graphical data Confirmed the results of quantitative data with interview Analyze the performance of projects Conclusions Fig.1 Methodology of collecting and analysis data The original data was used in order to find the number of days used in disbursement procedure. The disbursement procedure is divided into three stages. It is based on FIDIC recommendation for disbursement procedure [16-17]. The designed method was divided into three stages. The first stage was the submission of invoice from main contractor to client or client s representative when fully requested invoices from main contractor has been approved and verified according to client requirement. Second stage was inspection and issued the certificate of inspection. It was counted as quantity surveyor/engineers inspection has approved on amount of work which has been done and the certificate has been issued to main contractor. Third stage was payment. It was counted as the actual date of transferring the payment from client to the date of receiving the payment from main contractor account. Therefore, the duration of days used in each stage was defined as number of days used in exercise subtracted with the number of day allowed in contract agreement and subtracted with sum of the unforeseen events (days) which ceased work progress and holidays. These were three stages which had been implemented in this research. The residual data consisted mainly of interview with person involved in each activity of each stage of disbursement procedure. The target group for questionnaire and interview were head of engineer division, law and land acquisition, procurement, accounting, budget administration, project managers, engineers, accountants, consultants and quantity surveyors. The interview consisted of a series of closed questions related to the reasons for delays in the disbursement procedures. The interviewees were asked to interpret the reasons for delays which they had indicated. The residual data would be conducted after the original data had been completed and tabulated into graphical data. The residual data provided factors and reasons which the performance of each activity in the disbursement procedure is performed. The archival research method was mostly applied approach in this research, as it enabled to access to a vast quantity of data from the already widely accepted publications. If there was a difficulty in collecting original data, the residual method was used in the analysis. However, the collection of such types of data suffers from the biases existing in the original data. The greatest difficulty in this research is the possibility acquires the contract agreement as well as the actual dated of each activity in payment procedure. ISSN:

4 4. FINDINGS AND DISCUSSION 4.1 The performance of disbursement Highway agencies data related to the 113 public projects were shown in Table 1, 2, 3 and 4. Information on the type of clients, financial sources and the performance of each construction works were categorized into Tables 1, 2 and 3 respectively. Table 3 represents the summary of client s performance. The number indicates an average number of days used in each stage of disbursement procedure. In each stages of activity, the performance was calculated by following the designed method. It had been found from Table 3 that the number of days used in submission of invoice stage of central, local government and oversea funded projects were varied between -1 and +2 days. Whereas, the number of days used in the inspected and issued the certificate of inspection stage and the payment stage were fluctuated. Classification Number of projects Government 96 Local-government 17 Total 113 Table 1. Summary of public projects information Classification Number of projects ADB 22 IBRD 18 JBIC 24 Central 32 Local 17 Total 113 Table 2. Profiles of financial projects Performance of disbursement Submit (days) Inspect (days) Payment (days) Sum (days) ADB IBRD JBIC Local Central Average mean Note: (-) = under due date, (+) = overdue date Table 3. Performance of disbursement procedure (Days) It had further been found from Table 3 that the disbursement procedure of oversea funding agency (IBRDfunded projects) used lesser time than the other disbursement procedure of oversea funding agencies. IBRD disbursement procedure consumed thirteen days lesser than contract agreed While domestic disbursment procedures, the disbursement procedure of central government agencies used lesser time than disbursement of ISSN:

5 local government agencies. The disbursement procedure of central govenment funded projects took an extra one day than contract agreed. 4.2 Pattern of disbursement The disbursement of each project was calculated and plotted into graphical data. It had been found from result (figure 2-7) that the overall performance of disbursement in highways construction works can be generalized in 3 major patterns. First pattern was a moderate straight line with few jumping points. Each month of these first pattern projects obtain indicents which caused the number of delayed days in disbursement process lesser 30 days than contract agreement. It had seen as general patterns of construction work with few obstructions. Second pattern was gradually increasing with time and have few jumping points. The projects obtain incidents which caused the number of delayed days in disbursement process in each month greater 30 days but lesser 60 days when it was compared with contract agreement. This pattern had similarity to pattern one but the degree of seriousness was higher than the first pattern. It can be noticed from graphical results that pattern two have few higher in amplitude points and more often to occur. Third pattern was frustrated line. The project obtained the incidents which caused the number of delayed days in disbursement process in each month greater than 60 days but lesser 120 days than contract agreement. This pattern represents the highest sensitivities of factors. The degree of seriousness was the most severe in all three patterns which brings the point to a sudden high amplitude level. The summary of patterns of disbursement in highway construction works were shown in Table 4. The patterns of disbursement of highway public works were caused by these factors. It had been found from interview and questionnaire with persons involved in each stage of disbursement procedure. The factors which caused submission, inspection and issue the certificate and the payment stage delay were showed in Table 5-7. Type of funds Pattern one Pattern two Pattern three JBIC IBRD ADB Local Central TABLE 4. Summary of patterns in highway construction works Fig. 2 Summary of duration in disbursement process of highway works Fig. 3 Characteristic of highways works with central government fund projects ISSN:

6 Fig. 4 Characteristic of highways works with local government fund projects Fig. 5 Characteristic of highways works with ADB fund projects Fig. 6 Characteristic of highways works with JBIC fund projects Fig. 7 Characteristic of highways works with IBRD fund projects 4.3 Influenced factors in disbursement process Further study was conducted in order to find factors which reflect its performance. Interview and questionnaire had been implemented with persons involved in each stage of disbursement process in each project. The scale of degree of seriousness was The most seriousness was scored as 10 and the least degree of seriousness which affected to disbursement performance was 1. The influenced factors of each stage were shown in Table 5-7. The first finding was financial conditions of main contractor. It caused a decrease in their disbursement performance. The financial of main contractor played an important effect on the number of days delay [18-19]. In order words, the financial of main contractor had affect on their performance as completed works could not be claimed. Unless, all completion of each work of each stage had been fully completed and submitted to client or client s representative. Therefore, main contractors faced cash flow problem and might not able to purchase for construction materials and pay for labour fee. These factors caused the performance of work ISSN:

7 decreased. Interviewees agreed further on the size of construction firm had influence on the performance of progress work. Especially, a larger construction companies had advantage on rise the capital to alleviate the cash flow problem in shorter time than small-medium construction companies [20-21]. The second finding was source of fund. It was found that the performance of disbursement of each fund faced both delay and advance in payment schedule. It had been found during interveiw that main contractors found difficulties in receiving monthly payments from agencies. According to respondents with administrative position, explicitly define the timing of montly installment. The reason for these delays lied in the timing of the cash flow from the comptroller agency to the agencies s budegets. The payment were not made on time. This was due to agencies did not have the necessary funds in thier budget. Or because they are not able to organize the flow of expenditures in their budget properly. It was difficult to maintain such a level of high performance. This might be a close link between disbursement procedure of each fund and working culture of each country during communications. Nonetheless, there was no evident to analyze and conclude. The third finding was shortage of staff. This factor has been mentioned in each stage of disbursement process. Interviewers admitted the shortage of staff factor caused an overload to their staffs which affected to their performance. Source of fund Factors Degree of seriousness Government/Overseas Main contractor s financial diffculties 10 Shortage of experienced staffs 9 Unfamiliar with overseas required 8 documents Communication between main contractor 7 and engineers and government agencies Deficiencies in main contractors company 6 Bureaucratic 5 Change in works 4 Long holiday break 3 Traveling allowance 2 Government acts 1 TABLE 5. Summary of delayed factors in submission stage Source of fund Factors Degree of seriousness Government/Overseas Delayed dispute resolution 10 Defective design 9 Unclear drawings 8 Frequent change orders 7 Adverse weather 6 Shortage of technical personnel 5 Unexpected natural events (flood) 4 Contractor competence 3 Third party delays 2 The relationship between overseas and local staffs 1 TABLE 6. Summary of delayed factors in inspection and issued the certificate stage ISSN:

8 Source of fund Factors Degree of seriousness Government/Overseas Fiscal budget 10 Bank procedure 9 Deficiencies in public agenies organization 8 Shortage of staff 7 Change in works 6 Unfamiliar with overseas required 5 documents Traveling allowance 4 Communication with overseas agencies 3 Long holiday break 2 Financial crisis Further Finding TABLE 7. Summary of delayed factors in payment stage Main contractors expressed their point of view on an extra work ordered by public agencies. The main contractors have an obligation to execute extra works in accordance with the term of conditions stipulated in the contract and specifications. It acquired extra time to settle new agreement, legal formalities and procedures which caused significant delays. Furthermore, the disbursement of procedure in Thailand has to comply with Bank of Thailand (BOT) rules and regulations which might not suitable and workable with oversea rules and regulations. Therefore, there might be difficulties in bringing the performance of disbursement as it was stated in contract agreement. Experiencing in disbursement procedure was also one of the important factors which has influenced on improving the performance of disbursement procedures. Nonetheless, the performance of disbursement of project should be kept as contract agreement was written. Therefore, this thought was a result of prevention in fearing of conspiracy and generosity theory from public thought and awareness. 5. CONCLUSIONS 5.1 Performance of disbursement The overseas funded projects had lesser time consumed in disbursement process than government and local government funded projects The performance of central government had better performance than local government funded projects IBRD fund agency had lesser time consumed in disbursement practice than other overseas fund agencies Payment stage caused in the delay in total performance of disbursement process than inspection and issue the certificate and submission stage. 5.2 Pattern of disbursement Pattern of disbursement in highway public works could be categorized into 3 patterns: First pattern was a moderate straight line with few jumping points. The projects obtain the incidents which caused the number of delayed days in disbursement process lesser 30 days than contract agreement in each month Second pattern was gradually increasing with time and have few jumping points. The projects obtain incidents which cause the number of delayed days in disbursement process greater 30 days but lesser 60 days than contract agreement in each month. ISSN:

9 5.2.3 Third pattern was frustrated line. The projects obtain incidents which caused the number of delayed days in disbursement process greater 60 days but lesser 120 days than contract agreement in each month. 5.3 Influenced factors in disbursement performance It had been found and concluded that: Main contractor s financial difficulties, shortage of staff and unfamiliar with overseas required documents were among highest factors concerned from practitioners in submission stage Delayed dispute resolution, defective design and unclear drawings were among highest factors which are concerned from persons involved in inspection and issued the certificate stage Fiscal budget, Bank procedure and deficiencies in public agenies organization were among highest factors which are to be concerned from accountants in payment stage. ACKNOWLEDGEMENT This study was partly financially supported by Grant-in-Aid for Scientific Research No from Ministry of Education, Culture, Sports, Science and Technology. 6. REFERENCES [1] Greenwood, D. Subcontract procurement: Are relationship changing? Construction Management and Economics, 19,2000, pp.5-7. [2] Gray, C. and Flanagan, R. The changing role of specialist and trade contractor, Chartered Institute of Building, Ascot.(1989). [3] Mansfeild, N.F. Ugwu O.O. and Doran, T. Causes of delay and cost of overruns in Nigerian construction projects, International Journal of Project Management, 12(4), 1994, pp [4] Odeyinka, H.A. and Yusif, A. The causes and effects of construction delays on completion cost of housing projects in Nigeria, Journal of Financial Management of Property and Construction., 2(3), 1997, pp [5] Ayudhya Israngkura. B, Kunishima M, Study of Payment Procedures of Public Works in Thailand, Proceeding of Annual Forum on Construction Management, 23, 2005, pp [6] Love, S. Subcontractor partnering: I ll believe it when I see it, Journal of Management in Engineering, 13(5), 1997, pp [7] Bordoli, D.A and Balwin, A.N. A methodology for assessing construction project delays, Construction Management and Economics, 16, 1998, pp [8] Chan, D.W.M and Kumaraswamy, M.M. A comparative study of causes of time overrun in Hong Kong construction projects, International Journal of Project Management, 15(1), 1997, pp [9] Elazouni, A.M and Metwally, F.G. Factor-based path analysis to support subcontractor management, International Journal of Project Management, 23(2), 2000 pp [10] Arditi D, Akan G.T. and Gurdamar S. Reasons for delays in public projects in Turkey. Construction Management and Economics, 3, 1985, pp [11] Assaf S.A., Alkhalil M. and Al-Hazmi M. Cause of delay in large building construction projects, Journal of Management in Engineer, ASCE., 11(2), 1995, pp [12] Hancher, D.E and Rowing, J.E. Setting highway construction contract duration Journal of the Construction Division, ASCE., 107(2), 1981, pp [13] Chalabi, F.A and Camp, D. Causes of delay and overruns of construction projects in developing countries, CIB Proc, W-65; 2, 1984, pp [14] Kabatepe, E. Deficiencies observed in the omplementation of project completion deadlines, Tuskish Prime Ministry Sate Planning Organization, Ankara, [15] Hacaloglu, A. The construction Sector: Problems, Developments, measures. Turkish Prime Ministry state Planning Organization, Ankara [16] International Federation of Consulting Engineers (FIDIC)., Conditions of contract (contract agreement) [17] International Federation of Consulting Engineers (FIDIC)., Conditions of contract (construction) [18] Perry, J.G. and Hayes, R.W. Risk and its management in construction projects, Proceedings of Institution of Civil Engineers, 78, 1985, pp [19] Khalil, I.A. and Ghafly, A.A. Delay in public utility projects in Saudi Arabia, International Journal of Project Management., 17(2), 1999, pp ISSN:

10 [20] Aibinu, A.A. and Jagboro, G. O. The effects of construction delays on project delivery in Nigerian, International Journal of Project Management, 20, (2002) pp [21] Ayudhya Israngkura, B.Ph.D Study of Payment Procedures of Public Works in Thailand, thesis, University of Tokyo BIOGRAPHICAL NOTES Dr. Borvorn Israngkura Na Ayudhya is senior lecturer at Department of Civil Engineering at Rajamangala University of Technology Krungthep. He holds B.Eng in Civil Engineering from University of London, a Master in Structuring Engineering from University of Surrey and a Ph. D. in Construction management and infrastructure system from University of Tokyo. His current research interests included international disbursement procedures, project administration, construction delays and claims. Dr. Kunishima Masahiko is a professor at Civil Engineering Department and International studies Department at University of Tokyo. He holds a B.Eng. and a Master in Civil Engineering, and a Ph.D in Construction management and infrastructure. His current research interests include Bidding and contracting systems, public works bidding system and safety control on construction sites. CONTACTS Dr. Borvorn Israngkura Na Ayudhya Rajamangala University of Technology Krungthep Address 2 Nanglinchi rd. Tungmahamek Sathorn Bangkok City Bangkok Country THAILAND Tel Fax ayudhya2003@yahoo.com Dr. Kunishima Masahiko. Professor of Civil Engineering and International studies Department, University of Tokyo Address Kashiwanoha, Kashiwa-shi, Chiba, City Chiba Country JAPAN kuni@civil.t.u-tokyo.ac.jp, kuni@k.u-tokyo.ac.jp ISSN:

CAUSE OF DELAY IN CONSTRUCTION PROJECTS IN

CAUSE OF DELAY IN CONSTRUCTION PROJECTS IN International Journal of Civil Engineeringg and Technology (IJCIET) Volume 8, Issue 7, July 2017, pp. 30 36, Article ID: IJCIET_08_07_004 Available online at http://www.ia aeme.com/ijc CIET/issues.a asp?jtype=ijciet&vtyp

More information

Study of Delay Factors in Construction Projects

Study of Delay Factors in Construction Projects Study of Delay Factors in Construction Projects Shabbab Al Hammadi 1, M. Sadique Nawab 2 Assistant Professor, Civil Engineering Department, Shaqra University, Al Dawadmi, KSA 1 Lecturer, Civil Engineering

More information

Factors Causing Delay in Payment of Residential Building Projects in Thailand

Factors Causing Delay in Payment of Residential Building Projects in Thailand Factors Causing Delay in Payment of Residential Building Projects in Thailand Borvorn Israngkura Na Ayudhya, Thailand Key words: Construction delay; Residential building; Delay in payment. SUMMARY The

More information

Analysis and Identification of Critical Factors of Delay in Construction Projects

Analysis and Identification of Critical Factors of Delay in Construction Projects Analysis and Identification of Critical Factors of Delay in Construction Projects 83 Analysis and Identification of Critical Factors of Delay in Construction Projects M.P.Venkatesh*, C.Umarani**, S. M.

More information

Causes and Effects of Construction Project Delays in Nigerian Construction Industry

Causes and Effects of Construction Project Delays in Nigerian Construction Industry IJISET - International Journal of Innovative Science, Engineering & Technology, Vol. 3 Issue 5, May 016. ISSN 348 7968 Causes and Effects of Construction Project Delays in Nigerian Construction Industry

More information

Assessment of Extension of Time Claims in Hydropower Projects of Pakistan

Assessment of Extension of Time Claims in Hydropower Projects of Pakistan International Journal of Engineering and Advanced Technology (IJEAT) Assessment of Extension of Time Claims in Hydropower Projects of Pakistan Hashim Hanif, Yasar Saleem, Zuhaib Aslam Shahid, Abdullah

More information

Ranking of Delay Factors for Makkah s Construction Industry

Ranking of Delay Factors for Makkah s Construction Industry Ranking of Delay Factors for Makkah s Construction Industry Nashwan Al-Emad 1,*, Ismail Abdul Rahman 2, Sasitharan Nagapan 1, and Yaser Gamil 1 1 Faculty of Civil and Environmental Engineering, Universiti

More information

EVALUATION OF CONSTRUCTION COST AND TIME ATTRIBUTES

EVALUATION OF CONSTRUCTION COST AND TIME ATTRIBUTES EVALUATION OF CONSTRUCTION COST AND TIME ATTRIBUTES T.M.S. Elhag and A.H. Boussabaine School of Architecture and Building Engineering, The University of Liverpool, Liverpool L69 3BX, UK Understanding the

More information

CONSTRUCTION PROFESSIONALS PERCEPTION ON THE CAUSES AND EFFECTS OF PROJECT DELAY IN LUSAKA, ZAMBIA

CONSTRUCTION PROFESSIONALS PERCEPTION ON THE CAUSES AND EFFECTS OF PROJECT DELAY IN LUSAKA, ZAMBIA CONSTRUCTION PROFESSIONALS PERCEPTION ON THE CAUSES AND EFFECTS OF PROJECT DELAY IN LUSAKA, ZAMBIA MJ Mukuka 1, CO Aigbavboa 2, and WD Thwala 3 Department of Construction Management & Quantity Surveying,

More information

Architecture Information in Construction Environment in Malaysia

Architecture Information in Construction Environment in Malaysia Available online at www.sciencedirect.com ScienceDirect Procedia - Social and Behavioral Sciences 153 ( 2014 ) 36 43 AicQoL2014Kota Kinabalu AMER International Conference on Quality of Life The Pacific

More information

International Journal of Modern Trends in Engineering and Research e-issn No.: , Date: 2-4 July, 2015

International Journal of Modern Trends in Engineering and Research   e-issn No.: , Date: 2-4 July, 2015 International Journal of Modern Trends in Engineering and Research www.ijmter.com e-issn No.:2349-9745, Date: 2-4 July, 2015 Study of Pros and Cons of Subcontracting System Adopted in Executing Indian

More information

Study and Assessment of Causes and Effects of Delay in Large Public Construction Projects in Jordan

Study and Assessment of Causes and Effects of Delay in Large Public Construction Projects in Jordan Study and Assessment of Causes and Effects of Delay in Large Public Construction Projects in Jordan Ghanim A. Bekr Associate Professor, Civil Engineering Dept., Zarqa University, Jordan. Abstract In Jordan,

More information

Causes and Effects of Delays in Construction of Medium Scale Drinking Water Supply Projects in Sri Lanka

Causes and Effects of Delays in Construction of Medium Scale Drinking Water Supply Projects in Sri Lanka Annual Transactions of IESL, pp. [ 151-159], 2012 The Institution of Engineers, Sri Lanka Causes and Effects of Delays in Construction of Medium Scale Drinking Water Supply Projects in Sri Lanka W.D.A.

More information

AFRICAN JOURNAL OF APPLIED RESEARCH (AJAR) Vol.1, No.1 ISSN January 2015

AFRICAN JOURNAL OF APPLIED RESEARCH (AJAR)   Vol.1, No.1 ISSN January 2015 DELAY AND ITS EFFECT ON THE DELIVERY OF CONSTRUCTION PROJECTS IN GHANA Addo J.N.T. Department of Building Technology, Cape Coast Polytechnic, Cape Coast- Ghana ABSTRACT It is common knowledge that our

More information

Causes of Delay in Public Building Construction Projects: A Case of Addis Abeba Administration, Ethiopia

Causes of Delay in Public Building Construction Projects: A Case of Addis Abeba Administration, Ethiopia Asian Journal of Managerial Science ISSN: 2249-6300 Vol.8 No.2, 2019, pp. 4-9 The Research Publication, www.trp.org.in Causes of Delay in Public Building Construction Projects: A Case of Addis Abeba Administration,

More information

Assessment of Factors Causing Delay on Building Construction Projects in Enugu, Nigeria

Assessment of Factors Causing Delay on Building Construction Projects in Enugu, Nigeria Assessment of Factors Causing Delay on Building Construction Projects in Enugu, Nigeria Agu. N. N1 and Ibe, B. O. Department of Quantity Survey, Nnamdi, Azikiwe University, Awka, Anambra State, Nigeria

More information

Construction Experts Perception on the Causes and Effects of Cost Overruns in Johannesburg, Gauteng Province, South Africa

Construction Experts Perception on the Causes and Effects of Cost Overruns in Johannesburg, Gauteng Province, South Africa Construction Experts Perception on the Causes and Effects of Cost Overruns in Johannesburg, Gauteng Province, South Africa Abstract Mukuka MJ 1, Clinton Aigbavboa 2, and Wellington Thwala 3 The construction

More information

RISK FACTORS INFLUENCING INTERNATIONALLY FUNDED PUBLIC INFRASTRUCTURE PROJECTS IN THAILAND

RISK FACTORS INFLUENCING INTERNATIONALLY FUNDED PUBLIC INFRASTRUCTURE PROJECTS IN THAILAND Suranaree J. Sci. Technol. Vol. 19 No. 3; July - September 2013 189 RISK FACTORS INFLUENCING INTERNATIONALLY FUNDED PUBLIC INFRASTRUCTURE PROJECTS IN THAILAND Borvorn Israngkura Na Ayudhya Received: June

More information

ANALYSIS OF THE RELATIONSHIPS BETWEEN CAUSES OF DELAY IN CONSTRUCTION PROJECTS IN BANGLADESH

ANALYSIS OF THE RELATIONSHIPS BETWEEN CAUSES OF DELAY IN CONSTRUCTION PROJECTS IN BANGLADESH ANALYSIS OF THE RELATIONSHIPS BETWEEN CAUSES OF DELAY IN CONSTRUCTION PROJECTS IN BANGLADESH M. A. Salam 1, H. J. Staines 2, D. J. Blackwood 1 and S. Sarkar 1 1 School of Science and Engineering, and 2

More information

PUBLIC SECTOR PROCUREMENT METHODS USED IN THE CONSTRUCTION INDUSTRY IN TURKEY

PUBLIC SECTOR PROCUREMENT METHODS USED IN THE CONSTRUCTION INDUSTRY IN TURKEY PUBLIC SECTOR PROCUREMENT METHODS USED IN THE CONSTRUCTION INDUSTRY IN TURKEY F.H.Mustapha, Department of Civil Eng. and Building, University of Glamorgan S.G.Naoum, Tarik Aygun, School of Construction

More information

Analysis Of Critical Causes Of Delays In Indian Infrastructure Projects

Analysis Of Critical Causes Of Delays In Indian Infrastructure Projects ISSN: 2278 0211 (Online) Analysis Of Causes Of Delays In Indian Infrastructure Projects Prof: Siddesh K Pai DME, DBM, BE Mech, PGP PEM,MIM Assistant professor, National Institute of construction Management

More information

CONSTRUCTION DELAY FACTORS IN GENERAL AND ESPECIALLY IN DEVELOPED COUNTRIES

CONSTRUCTION DELAY FACTORS IN GENERAL AND ESPECIALLY IN DEVELOPED COUNTRIES Int. J. Struct. & Civil Engg. Res. 2014 Basim Khadier Khadim and Pramila Adavi, 2014 Research Paper ISSN 2319 6009 www.ijscer.com Vol. 3, No. 4, November 2014 2014 IJSCER. All Rights Reserved CONSTRUCTION

More information

A METHODOLOGY TO IDENTIFY THE DELAYS AND RANK ITS CAUSATIVE FACTORS IN INDIAN CONSTRUCTION INDUSTRY

A METHODOLOGY TO IDENTIFY THE DELAYS AND RANK ITS CAUSATIVE FACTORS IN INDIAN CONSTRUCTION INDUSTRY A METHODOLOGY TO IDENTIFY THE DELAYS AND RANK ITS CAUSATIVE FACTORS IN INDIAN CONSTRUCTION INDUSTRY Anup Wilfred 1, Muhamad Sharafudeen 2 1 Associate Professor, Civil Engineering Department, MIT, Karnataka,

More information

NATURE OF THE CRITICAL RISK FACTORS AFFECTING PROJECT PERFORMANCE IN INDONESIAN BUILDING CONTRACTS

NATURE OF THE CRITICAL RISK FACTORS AFFECTING PROJECT PERFORMANCE IN INDONESIAN BUILDING CONTRACTS NATURE OF THE CRITICAL RISK FACTORS AFFECTING PROJECT PERFORMANCE IN INDONESIAN BUILDING CONTRACTS I Putu Artama Wiguna and Stephen Scott 1 School of Civil Engineering and Geosciences, University of Newcastle

More information

Critical Factors Influencing Construction Productivity in Thailand

Critical Factors Influencing Construction Productivity in Thailand Critical Factors Influencing Construction Productivity in Thailand Arun Makulsawatudom,* Margaret Emsley* and Kuldej Sinthawanarong** Abstract Factors affecting construction in Thailand were disclosed

More information

INVESTIGATING THE CAUSES OF DELAY WITHIN OIL AND GAS PROJECTS IN THE U.A.E.

INVESTIGATING THE CAUSES OF DELAY WITHIN OIL AND GAS PROJECTS IN THE U.A.E. INVESTIGATING THE CAUSES OF DELAY WITHIN OIL AND GAS PROJECTS IN THE U.A.E. Mohamed Salama 1, Moustafa Abd El Hamid and Bill Keogh School of Management and Languages, Heriot-Watt University, Riccarton,

More information

CAUSES OF DELAYS IN CONSTRUCTION PROJECTS IN TURKEY

CAUSES OF DELAYS IN CONSTRUCTION PROJECTS IN TURKEY JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT ISSN 1392-3730 print/issn 1822-3605 online 2012 Volume 18(3): 426 435 doi:10.3846/13923730.2012.698913 CAUSES OF DELAYS IN CONSTRUCTION PROJECTS IN TURKEY Aynur

More information

Major Mitigation Measures for Delays in Construction Projects

Major Mitigation Measures for Delays in Construction Projects 1Major Mitigation Measures Major Mitigation Measures for Delays in Construction Projects Mohammad Abedi, PhD Candidate, Department of Civil Engineering, RAZAK School of Engineering & Advanced Technology,

More information

Blue List. Green List. Civil Engineering Commercial Training Courses

Blue List. Green List. Civil Engineering Commercial Training Courses Blue List Green List Civil Engineering Commercial Training Courses From SURCO, the information business of the Chartered Institution of CIVIL ENGINEERING SURVEYORS SURCO Limited Chartered Institution of

More information

International Journal of Advance Engineering and Research Development

International Journal of Advance Engineering and Research Development Scientific Journal of Impact Factor (SJIF): 5.71 International Journal of Advance Engineering and Research Development Volume 5, Issue 04, April -2018 e-issn (O): 2348-4470 p-issn (P): 2348-6406 A COMPARATIVE

More information

Causes of Contractors Failure: Contractors View

Causes of Contractors Failure: Contractors View 2011 2 nd International Conference on Construction and Project Management IPEDR vol.15 (2011) (2011) IACSIT Press, Singapore Causes of Contractors Failure: Contractors View Ibrahim Mahamid 1+ 1 PhD, Norwegian

More information

AFGHANISTAN RING ROAD PROJECT Financed under Grant 0081: Road Network Development - Project 1, and Grant 0012: Qaisar-Bala Murghab Road Project

AFGHANISTAN RING ROAD PROJECT Financed under Grant 0081: Road Network Development - Project 1, and Grant 0012: Qaisar-Bala Murghab Road Project A. Introduction AFGHANISTAN RING ROAD PROJECT Financed under Grant 0081: Road Network Development - Project 1, and Grant 0012: Qaisar-Bala Murghab Road Project TERMS OF REFERENCE FOR PROJECT MANAGEMENT

More information

Development Fund for Iraq. Agreed-Upon Procedures Report

Development Fund for Iraq. Agreed-Upon Procedures Report Agreed-Upon Procedures Report KPMG Bahrain June 2004 This report contains 16 pages Agreed-Upon Procedures Report 1 Key internal controls at the CPA over disbursements to, and on behalf of, Iraqi Ministries

More information

A Brief Study on Residential Construction Projects from View of Delay Causes Ranking

A Brief Study on Residential Construction Projects from View of Delay Causes Ranking International Journal of Humanities and Management Sciences (IJHMS) Volume 4, Issue 4 () ISSN 44 (Online) A Brief Study on Residential Construction Projects from View of Delay Causes ing Siamak Hajiyakhchali,

More information

Contributions of Construction Project Team to Cost Overruns: The Contractors Perspective. Nigeria; PH (234) ;

Contributions of Construction Project Team to Cost Overruns: The Contractors Perspective. Nigeria; PH (234) ; 1528 Contributions of Construction Project Team to Cost Overruns: The Contractors Perspective Olusegun AKINSIKU 1, Adeyemi AKINTOLA 1, Oko AMEH 1 and Ayokunle IGE 1 1 Department of Building, Faculty of

More information

The Effects of Economic Development on Project Management in Developing Countries

The Effects of Economic Development on Project Management in Developing Countries The Effects of Economic Development on Project Management in Developing Countries M KURUOGLU and E ERGEN Department of Construction Management, Faculty of Civil Engineering,VWDQEXO7HFKQLFDO8QLYHUVLW\0DVODNøVWDQEXO7XUNH\

More information

Effects of construction projects schedule overruns: A case of the Gauteng Province, South Africa

Effects of construction projects schedule overruns: A case of the Gauteng Province, South Africa Available online at www.sciencedirect.com ScienceDirect Procedia Manufacturing 00 (2015) 000 000 www.elsevier.com/locate/procedia 6th International Conference on Applied Human Factors and Ergonomics (AHFE

More information

Course List 2008 Civil Engineering Commercial Training

Course List 2008 Civil Engineering Commercial Training Course List 2008 Civil Engineering Commercial Training From SURCO, the trading company of the Institution of CIVIL ENGINEERING SURVEYORS SURCO Limited Institution of CIVIL ENGINEERING SURVEYORS Dominion

More information

CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS

CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS CHAPTER 2 DEVELOPMENT AND ORGANIZATION OF PROJECTS 1) THE LIFE CYCLE OF A CONSTR. PROJECT: 1.1:CONCEPT AND FEASIBILITY STUDIES: THE START Recognition of a need for a new facility conceptual analyses Technical

More information

REQUEST FOR OFFER RFO: For: Business Continuity Program Development Consultant Services. For: Covered California

REQUEST FOR OFFER RFO: For: Business Continuity Program Development Consultant Services. For: Covered California REQUEST FOR OFFER RFO: 2017-04 For: Business Continuity Program Development Consultant Services For: Covered California Date: Tuesday, September 19, 2017 You are invited to review and respond to this Request

More information

Analysis of Improper Material Management Affecting Cost in Construction Projects

Analysis of Improper Material Management Affecting Cost in Construction Projects Analysis of Improper Material Management Affecting Cost in Construction Projects P.Lenin *, L.Krishnaraj *, D.Narendra Prasad *, V.R Prasath Kumar *, Assistant Professor, Civil Engineering Department,

More information

Schedule Delay in Saudi Arabia Road Construction Projects: Size, Estimate, Determinants and Effects

Schedule Delay in Saudi Arabia Road Construction Projects: Size, Estimate, Determinants and Effects International Journal of Architecture, Engineering and Construction Vol 6, No 3, September 2017, 51-58 Schedule Delay in Saudi Arabia Road Construction : Size, Estimate, Determinants and Effects Ibrahim

More information

Analysis of Delay due to Material Supply by Tower Crane at different Height of High Rise Buildings in Mumbai

Analysis of Delay due to Material Supply by Tower Crane at different Height of High Rise Buildings in Mumbai IOSR Journal of Engineering (IOSRJEN) e-issn: 2250-3021, p-issn: 2278-8719 Vol. 3, Issue 11 (November. 2013), V2 PP 19-26 Analysis of Delay due to Material Supply by Tower Crane at different Height of

More information

ASIAN JOURNAL OF MANAGEMENT RESEARCH Online Open Access publishing platform for Management Research

ASIAN JOURNAL OF MANAGEMENT RESEARCH Online Open Access publishing platform for Management Research Online Open Access publishing platform for Management Research Copyright by the authors - Licensee IPA- Under Creative Commons license 3.0 Research Article ISSN 2229 3795 Stakeholders perspective on cost

More information

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE St. Charles County Ambulance District Base 3 & Training Facility Construction 4169 Old Mill Parkway St. Peters, MO 63376 September

More information

East Central College

East Central College SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

This is EXHIBIT A, consisting of [ ] pages, referred to in and part of the Task Order dated [ ]. Engineer's Services for Task Order

This is EXHIBIT A, consisting of [ ] pages, referred to in and part of the Task Order dated [ ]. Engineer's Services for Task Order This is EXHIBIT A, consisting of [ ] pages, referred to in and part of the Task Order dated [ ]. Engineer's Services for Task Order [Introductory Note to User: The following text as published describes

More information

Available online at ScienceDirect. Procedia Manufacturing 3 (2015 )

Available online at  ScienceDirect. Procedia Manufacturing 3 (2015 ) Available online at www.sciencedirect.com ScienceDirect Procedia Manufacturing 3 (2015 ) 1690 1695 6th International Conference on Applied Human Factors and Ergonomics (AHFE 2015) and the Affiliated Conferences,

More information

Project Management Techniques

Project Management Techniques ALUMASA QATAR Project Management Techniques A project is usually one time effort. Although similar work may have been done previously, every project has its own features and therefore is of non-repetitive

More information

WHY IT PROJECTS FAIL BY ZIMBABWE

WHY IT PROJECTS FAIL BY ZIMBABWE WHY IT PROJECTS FAIL BY ZIMBABWE INTOSAI EDP COMMITTEE PERFOMANCE AUDIT SEMINAR, SLOVENIA 14-16 MAY 2001 WHY IT PROJECTS FAIL The Zimbabwean Government is computerised in almost all areas of its operation

More information

Reference No. RAMP/C/03-10/CQ

Reference No. RAMP/C/03-10/CQ REPUBLIC OF CROATIA MINISTRY OF FINANCE TAX ADMINISTRATION REVENUE ADMINISTRATION MODERNIZATION PROJECT Reference No. RAMP/C/03-10/CQ Terms of Reference Technical Supervision of reconstruction and construction

More information

b u i l d i n g a b r o a d

b u i l d i n g a b r o a d b u i l d i n g a b r o a d procurement of construction and reconstruction projects in the international context FACTORS CAUSING CONSTRUCTION COMPANY FAILURE Serkan Kivrak, Anadolu University email: serkankivrak@anadolu.edu.tr

More information

CHAPTER 2 LITERATURE REVIEW

CHAPTER 2 LITERATURE REVIEW 10 CHAPTER 2 LITERATURE REVIEW 2.1 GENERAL One of the most important problems in the construction industry is Time overrun. Time overrun occur in every construction project and the magnitude of these delays

More information

Investigation of Factors Influencing Cost Overrun in High-Rise Building Constructions

Investigation of Factors Influencing Cost Overrun in High-Rise Building Constructions Investigation of Factors Influencing Cost Overrun in High-Rise Building Constructions Prof. Yogini K. Patil Professor, G. C.O.E.Jalgaon, Maharashtra, India. Prof. Pankaj P. Bhangale Head of Civil Dept,

More information

THE CONTRACTORS' GUIDE TO OPERATIONS AND PROCEDURES

THE CONTRACTORS' GUIDE TO OPERATIONS AND PROCEDURES THE CONTRACTORS' GUIDE TO OPERATIONS AND PROCEDURES INTRODUCTION The purpose of this guide is to document general procedures a contractor might implement for the (1) Bidding, Planning and Scheduling Functions,

More information

FACTORS AFFECTING LABOUR PRODUCTIVITY IN ROAD CONSTRUCTION

FACTORS AFFECTING LABOUR PRODUCTIVITY IN ROAD CONSTRUCTION FACTORS AFFECTING LABOUR PRODUCTIVITY IN ROAD CONSTRUCTION Mr. D.Sukumar1, Mr. S.Saravanan2 Assistant Prof, Dept of Civil Engineering, Erode Sengunthar Engineering College, Thudupathi-6807, India1 Assistant

More information

Development of a Delay Analysis System for a railway construction Project

Development of a Delay Analysis System for a railway construction Project ISSN (Online) : 2319-8753 ISSN (Print) : 2347-6710 International Journal of Innovative Research in Science, Engineering and Technology An ISO 3297: 2007 Certified Organization, Volume 2, Special Issue

More information

Kong, China however, there has been some successful results from the informal process (see the Hong Kong, China local study) Consideration of wo

Kong, China however, there has been some successful results from the informal process (see the Hong Kong, China local study) Consideration of wo INFORMAL WORKOUTS IN THE RETA ECONOMIES 10.1 Introduction As mentioned earlier in this report, the commercial culture of many of the RETA economies appears to be more conditioned toward non-confrontational

More information

EYNSFORD PARISH COUNCIL

EYNSFORD PARISH COUNCIL EYNSFORD PARISH COUNCIL FINANCIAL REGULATIONS These Financial Regulations were adopted by the Council at its Meeting held on 20 September 2007, last amended on 20 th July 2017. 1. GENERAL 1.1 These financial

More information

Understanding construction projects schedule overruns in South Africa

Understanding construction projects schedule overruns in South Africa Understanding construction projects schedule overruns in South Africa Mulenga MUKUKA 1, Clinton AIGBAVBOA 2 and Wellington THWALA 3 1 MTECH, Department of Construction Management and Quantity Surveying,

More information

ASSESSMENT OF PROCUREMENT METHODS USED FOR EXECUTING MAINTENANCE WORKS IN LAGOS STATE. ADENUGA, O.A. 1 and DOSUMU, O.S. 2

ASSESSMENT OF PROCUREMENT METHODS USED FOR EXECUTING MAINTENANCE WORKS IN LAGOS STATE. ADENUGA, O.A. 1 and DOSUMU, O.S. 2 ASSESSMENT OF PROCUREMENT METHODS USED FOR EXECUTING MAINTENANCE WORKS IN LAGOS STATE ADENUGA, O.A. 1 and DOSUMU, O.S. 2 http://dx.doi.org/10.4314/ejesm.v5i4.s6 Received 16th August 2012; accepted 8th

More information

Construction Financial Management

Construction Financial Management Unit 8: Construction Financial Management Unit code: K/504/4352 QCF level: 6 Credit value: 15 Aim This unit gives learners an understanding of the methods used to determine the price of a proposed. Learners

More information

PART 2.10 DEPARTMENT OF HUMAN RESOURCES, LABOUR AND EMPLOYMENT NEWFOUNDLAND AND LABRADOR LABOUR RELATIONS AGENCY

PART 2.10 DEPARTMENT OF HUMAN RESOURCES, LABOUR AND EMPLOYMENT NEWFOUNDLAND AND LABRADOR LABOUR RELATIONS AGENCY PART 2.10 DEPARTMENT OF HUMAN RESOURCES, LABOUR AND EMPLOYMENT NEWFOUNDLAND AND LABRADOR LABOUR RELATIONS AGENCY Executive Summary The Labour Standards Division (the Division) of the Newfoundland and Labrador

More information

International Journal of Engineering Research and General Science Volume 4, Issue 4, July-August, 2016 ISSN

International Journal of Engineering Research and General Science Volume 4, Issue 4, July-August, 2016 ISSN Causes of Variation Orders on Public Building Projects in Addis Ababa Andualem Endris Yadeta 1 1 School of Civil and Environmental Engineering, Addis Ababa Institute of Technology, Addis Ababa University,

More information

TERMS OF REFERENCE FOR CONSULTING SERVICES FOR ENGINEERING AND CONSTRUCTION SUPERVISION CONSULTANT

TERMS OF REFERENCE FOR CONSULTING SERVICES FOR ENGINEERING AND CONSTRUCTION SUPERVISION CONSULTANT TERMS OF REFERENCE FOR CONSULTING SERVICES FOR ENGINEERING AND CONSTRUCTION SUPERVISION CONSULTANT 1. Background The Asian Development Bank (ADB) has assisted the Kyrgyz Republic in the rehabilitation

More information

Audio Sessions. Session 4 PROCUREMENT. Construction Contract Administration Education Program

Audio Sessions. Session 4 PROCUREMENT. Construction Contract Administration Education Program Audio Sessions Session 4 PROCUREMENT Construction Contract Administration Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course 2011 The Construction Specifications

More information

SECTION CONSTRUCTION PROGRESS DOCUMENTATION

SECTION CONSTRUCTION PROGRESS DOCUMENTATION SECTION 01 32 00 CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

REQUEST FOR PROPOSAL

REQUEST FOR PROPOSAL THE URBAN DEVELOPMENT CORPORATION OF TRINIDAD AND TOBAGO LIMITED (UDeCOTT) REQUEST FOR PROPOSAL FIDIC ENGINEER SERVICES FOR THE ROXBOROUGH FIRE STATION The Ministry of National Security ( MNS ), on behalf

More information

Evaluating the factors affecting Quality of Residential projects in Construction Industry

Evaluating the factors affecting Quality of Residential projects in Construction Industry Evaluating the factors affecting Quality of Residential projects in Construction Industry Ashish Mutha Sardar Patel college of Engineering, Mumbai Dr. Anil Ghadge Sardar Patel college of Engineering, Mumbai

More information

Subcontractor's Selection Practice in the Gaza Strip

Subcontractor's Selection Practice in the Gaza Strip Subcontractor's Selection Practice in the Gaza Strip Adnan Enshassi School of Civil Engineering, IUG, Palestine aenshassi@gmail.com Younis Shoman Ministry of Public Works and Housing, Palestine Abstract

More information

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY - PHASE II SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other

More information

List of Financial Regulations

List of Financial Regulations HEPTONSTALL PARISH COUNCIL FINANCIAL REGULATIONS List of Financial Regulations 1. General 25 2. Annual Estimates 25 3. Budgetary Controls 25 4. Accounting and Audit 26 5. Banking Arrangements and Cheques

More information

CHAPTER 1 INTRODUCTION

CHAPTER 1 INTRODUCTION 1 CHAPTER 1 INTRODUCTION 1.1 BACKGROUND In India, Construction Industry plays a key role in both economic growth and poverty reduction. The industry consumes about 40 to 50% of the national five year plan

More information

Evaluation on the Application of Quality Management System in Tanzania Building Construction Projects

Evaluation on the Application of Quality Management System in Tanzania Building Construction Projects American Journal of Management Science and Engineering 2017; 2(6): 170-175 http://www.sciencepublishinggroup.com/j/ajmse doi: 10.11648/j.ajmse.20170206.12 ISSN: 2575-193X (Print); ISSN: 2575-1379 (Online)

More information

COUNTYWIDE RISK ASSESSMENT AND AUDIT PLAN SUMMIT COUNTY, OHIO

COUNTYWIDE RISK ASSESSMENT AND AUDIT PLAN SUMMIT COUNTY, OHIO COUNTYWIDE RISK ASSESSMENT AND AUDIT PLAN CONTENTS Page Independent Accountants Report on Applying Agreed-Upon Procedures 1 I. Introduction 2 II. Principles for the Risk Assessment and Audit Plan Development

More information

Simulating The Impact Of The Material Flow In The Jordanian Construction Supply Chain And Its Impact On Project Performance

Simulating The Impact Of The Material Flow In The Jordanian Construction Supply Chain And Its Impact On Project Performance Simulating The Impact Of The Material Flow In The Jordanian Construction Supply Chain And Its Impact On Project Performance Dr. Ghaith Al-Werikat Abstract: With the new developments and challenges within

More information

COSCSMO15 SQA Unit Code H99L 04 Control projects in construction management

COSCSMO15 SQA Unit Code H99L 04 Control projects in construction management Overview This unit is about controlling projects. You will identify quality standards and pass them to the project team. You will set up systems for recording the quality of work against these standards,

More information

Follow-Up on VFM Section 3.13, 2016 Annual Report RECOMMENDATION STATUS OVERVIEW

Follow-Up on VFM Section 3.13, 2016 Annual Report RECOMMENDATION STATUS OVERVIEW Chapter 1 Section 1.13 Supply Chain Ontario and Procurement Practices Follow-Up on VFM Section 3.13, 2016 Annual Report RECOMMENDATION STATUS OVERVIEW # of Status of Actions Recommended Actions Fully In

More information

Identification of Critical Construction Delay Factors

Identification of Critical Construction Delay Factors Identification of Critical Construction Delay Factors Ashwini Arun Salunkhe Post Graduate Student, Department of Civil Engineering, Padmashree Dr. D.Y.Patil Institute of Engineering & Technology. Pimpri,

More information

FIDIC PROCUREMENT OPTIONS, Clause 3 and Clause 20

FIDIC PROCUREMENT OPTIONS, Clause 3 and Clause 20 FIDIC PROCUREMENT OPTIONS, Clause 3 and Clause 20 PATRIZIA PALMITESSA-SAVRIC BSc Arch Eng MArch Arch.BW RIBA MAAB FCIArb FAArb FBIArb Head Contracts & Dispute Resolution GINDER PALMITESSA PTY LTD T: +267

More information

Chapter 2 Parties to the Contract

Chapter 2 Parties to the Contract Chapter 2 Parties to the Contract 2.1 Introduction Construction work may include building of a new structure, additions, alterations, expansion, replacement, dismantling, erection, commissioning, rehabilitation,

More information

MINUTES OF PRE-BID CONFERENCE. INVITATION TO BID INTERIOR FITTING-OUT WORKS FOR NEW UNDP CAMBODIA COUNTRY OFFICE Process No:

MINUTES OF PRE-BID CONFERENCE. INVITATION TO BID INTERIOR FITTING-OUT WORKS FOR NEW UNDP CAMBODIA COUNTRY OFFICE Process No: I. Background MINUTES OF PRE-BID CONFERENCE INVITATION TO BID INTERIOR FITTING-OUT WORKS FOR NEW UNDP CAMBODIA COUNTRY OFFICE Process No: 35-46214 The United Nations Development Programme (UNDP) would

More information

CLAIMS AND DISBURSEMENTS

CLAIMS AND DISBURSEMENTS CLAIMS AND DISBURSEMENTS LEGAL COMPLIANCE MANUAL CLAIMS AND DISBURSEMENTS Introduction Municipal transactions involving an account, claim, or demand made for any property or service which can be itemized

More information

Conception Design Construction Operation.

Conception Design Construction Operation. 4 Development Process and Procurement 4.1 The development process by which the project moves from the earliest ideas to the final completion of the facilities and their use can be considered as having

More information

Assessing the impact of main contractor's site co-ordination on sub-contractors' performance in Hong Kong

Assessing the impact of main contractor's site co-ordination on sub-contractors' performance in Hong Kong Loughborough University Institutional Repository Assessing the impact of main contractor's site co-ordination on sub-contractors' performance in Hong Kong This item was submitted to Loughborough University's

More information

Causes and Effects of Cost Overrun On Construction Projects in Madhya Pradesh

Causes and Effects of Cost Overrun On Construction Projects in Madhya Pradesh Causes and Effects of Cost Overrun On Construction Projects in Madhya Pradesh Santosh kumar prajapati, Rakesh Gupta, Mukesh Pandey M. Tech Student, Assistant Professor, Head of civil Engineering department

More information

JFMPC 14,2. Jomah Al-Najjar Islamic University of Gaza, Gaza Strip, Palestinian Authority, and

JFMPC 14,2. Jomah Al-Najjar Islamic University of Gaza, Gaza Strip, Palestinian Authority, and The current issue and full text archive of this journal is available at www.emeraldinsight.com/1366-4387.htm JFMPC 14,2 126 Delays and cost overruns in the construction projects in the Gaza Strip Adnan

More information

What You Should Know For Auditing Capital Projects Presented by: Robert S. Bright, President

What You Should Know For Auditing Capital Projects Presented by: Robert S. Bright, President What You Should Know For Auditing Capital Projects Presented by: Robert S. Bright, President September 1, 2009 1 Part One Agenda Why the Session? Audit Themes Increasing Your Value Establishing Objectives

More information

FIDIC Contracts. Training Course in English language. May, 25-26, Two days course on:

FIDIC Contracts. Training Course in English language. May, 25-26, Two days course on: FIDIC Contracts Training Course in English language May, 25-26, 2018 Two days course on: FIDIC Module 4 - FIDIC Contracts Management and Administration FIDIC 99 EDITIONS ESSENTIALS FOR WORKING IN INTERNATIONAL

More information

Cashflow. Total price. Total cost. Contract completion. Predicted revenue (2) Total price. Total price. Total cost. Total cost. Contract completion

Cashflow. Total price. Total cost. Contract completion. Predicted revenue (2) Total price. Total price. Total cost. Total cost. Contract completion Cashflow The significance to the contractor s cashflow of different patterns of payment from the client and of delays is illustrated in the next figure showing a hypothetical contract of 2 years duration.

More information

[Sharafadeen, 2(10): October, 2015] ISSN Impact Factor (PIF): 2.243

[Sharafadeen, 2(10): October, 2015] ISSN Impact Factor (PIF): 2.243 DELAY OF BUILDING CONSTRUCTION PROJECTS IN NIGERIA-A REVIEW OF CAUSES, EFFECTS AND SOLUTIONS Olanrewaju Sharafadeen, Babatunde Owolabi and Ajetomobi Oludare Olayinka Department of Building Technology,

More information

Partnering In Construction: Improvementthrough. Integration And Collaboration

Partnering In Construction: Improvementthrough. Integration And Collaboration Partnering In Construction: Improvementthrough Downloaded from ascelibraryorg by 3744193189 on 01/24/18 Copyright ASCE For personal use only; all rights reserved Integration And Collaboration SEVDA BAYRAMOGLU

More information

Analysis of Time Slippage for Construction Projects in Public Sector: Owner s Perspective

Analysis of Time Slippage for Construction Projects in Public Sector: Owner s Perspective Analysis of Time Slippage for Construction Projects in Public Sector: Owner s Perspective MISBAH JAMIL*, NADEEM A. MUFTI**, AND WASEEM SAIF DAR*** RECEIVED ON 21.12.2009 ACCEPTED ON 08.06.2010 ABSTRACT

More information

To Study Effects of Cost Overrun on High-Rise Building Projects - A Case Study

To Study Effects of Cost Overrun on High-Rise Building Projects - A Case Study International Journal of Research and Scientific Innovation (IJRSI) Volume III, Issue VII, July 21 ISSN 2321 275 To Study Effects of Cost Overrun on High-Rise Building Projects - A Case Study Prof. Yogini

More information

Federal Education Programs Financial Management Practices

Federal Education Programs Financial Management Practices Federal Education Programs Financial Management Practices Legal Structures for Federal Programs Statutes / Legislation Program Statues (NCLB, IDEA, Perkins) General Education Provisions Act (GEPA) Regulations

More information

VILLAGE OF VERNON HILLS REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER AT RISK SERVICES. Part I: Proposal Information

VILLAGE OF VERNON HILLS REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER AT RISK SERVICES. Part I: Proposal Information VILLAGE OF VERNON HILLS REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGER AT RISK SERVICES Part I: Proposal Information A General Information The Village of Vernon Hills is soliciting proposals for construction

More information

CONTRACT ADMINISTRATION STANDARD OPERATING PROCEDURES

CONTRACT ADMINISTRATION STANDARD OPERATING PROCEDURES CONTRACT ADMINISTRATION STANDARD OPERATING PROCEDURES SOP #.004 Title: MONITORING OF CONTRACT PERFOMANCE AND DELIVERABLES Version: 1 Approval Date: May 10, 2018 1. Purpose. The purpose of a contract monitoring

More information

The letter of expression of interest (EOI) should provide information of the company s technical qualifications and experience in the Annex B.

The letter of expression of interest (EOI) should provide information of the company s technical qualifications and experience in the Annex B. Request for Expression of Interest of Initial, Intermediate and Final Technical Review Support Missions/ Technical Audit for the Project of Gujarat Rural Roads Funding source: Sector: Asian Infrastructure

More information

This document describes how Austin implements projects using The Austin Method. Step 1 Preliminary Design and Engineering

This document describes how Austin implements projects using The Austin Method. Step 1 Preliminary Design and Engineering The Austin Company offers multiple approaches in implementing a project. These generally can be classified into either a design-bid-construct or design-build project approach. In addition, Austin offers

More information

IMPROVING SUBCONTRACT CONDITIONS TOWARDS SUCCESSFUL INFRASTRUCTURE PROJECTS IN GAZA

IMPROVING SUBCONTRACT CONDITIONS TOWARDS SUCCESSFUL INFRASTRUCTURE PROJECTS IN GAZA MPROVNG SUBCONTRACT CONDTONS TOWARDS SUCCESSFUL NFRASTRUCTURE PROJECTS N GAZA Rebhy El Sheikh Palestinian Water Authority, Gaza Technical Director, MSc Mechanical Engineering ABSTRACT: Amongst the so many

More information