THE CONTRACTORS' GUIDE TO OPERATIONS AND PROCEDURES

Size: px
Start display at page:

Download "THE CONTRACTORS' GUIDE TO OPERATIONS AND PROCEDURES"

Transcription

1 THE CONTRACTORS' GUIDE TO OPERATIONS AND PROCEDURES

2 INTRODUCTION The purpose of this guide is to document general procedures a contractor might implement for the (1) Bidding, Planning and Scheduling Functions, (2) Contract Administration Activities, and (3) The Accounting Duties. Each contractor has their own procedures, written or unwritten, for the above mentioned activities. It is my intent to provide the users of this guide a means to compare their company procedures with those on the following pages in order to determine the completeness of the readers' operation procedures. BIDDING The first question the contractor should ask is whether or not he or she should bid a specific job. Some of the issues that should be addressed are Timing, Company Resources, Type of Work, and Location of Work. TIMING * Is the company already operating at capacity or is there a need for additional work? * Are other jobs, perhaps better suited to the type of work the contractor normally performs, on the horizon? * Does the company have sufficient bonding capacity? * Is the company's cash flow adequate? How much cash will be needed to handle the job? What is the anticipated collection date on existing retention (Monthly cash flow

3 projections should always be performed)? * Is there, or will there be, adequate staff available to do the work in an effective and efficient manner? RESOURCES * How long will the job last? * What are the payment and retention provisions? * Are there any liquidated damage provisions? * Does the job lend itself toward unusual or high risk? * Does the profit potential offset the risk factors? * Will known subcontractors be available? * Cash availability? What is the available amount on the company's credit lines and other borrowing sources? TYPE OF WORK * Has the contractor operated primarily in the public sector and the work is in the private sector (or vice-versa)? * What is the size of the project? Is the project much larger or smaller than the contractor is use to building? * Project complexity. Perhaps the project is a clean room for an electronics manufacturer. Does the contractor have experience in this type of construction? LOCATION OF WORK

4 * Is the job in the geographic area where the contractor operates? If not, then: * Can the contractor manage and control the project? * Is there an experienced project superintendent or manager available and is willing to relocate for the duration of the project? * If so, do you have an adequate replacement for the local jobs which no longer have the relocated staff(s)? * Is the contractor familiar with the foreign location's price structures for materials, labor, payroll overhead items, subcontractors, equipment rentals, etc. * What are the location's regulatory practices? * What is the areas labor resources? ESTIMATING PRE-BID PROCEDURES * Plans and specs should be acquired as soon as they are available in order to eliminate errors due to time restraints. * The plans and specs should first be read to get an overview of the project. They should then be read in detail paying special attention to potential problems and risks. The estimator should note all unusual or unfamiliar items as well as familiar and unfamiliar

5 construction processes. * The estimator should review the plans and specs for: * Minority requirements. * Warranty obligations. * Liquidated damage provisions. * Incentive provisions. * Substitute materials and/or processes where the job could save costs and still meet the plans and spec requirements. * Payment provisions such as paid when paid. * The estimator should visit the job site and attend pre-bid meetings. BIDDING THE JOB * The estimator should obtain historical data for similar projects done by the company. * What work items were profitable? What work items were unprofitable? * A cover sheet should accompany the bid (for internal use only). The following cost components should be summarized on the cover sheet: * Labor

6 * Labor overhead * Materials * Equipment, company owned * Rental equipment * Subcontractors * General conditions * Indirect costs * General and administrative allocation * Interest expense * Profit * The bid should be defined by work items (phases). The criteria for defining the work items are: * The work items should be defined compatible with the concept that if a unique set of resources are required to perform the work, a work item is defined for the work. (For example, if carpenters are needed to form job built wall forms, and laborers are needed to place a steel ply forming system for wall forms, then the fact that two different types of crews perform the work, even if they are both wall forms, should result in the definition of two work items). * The work items should be defined such that any work that results in a substantially different productivity, even if the same resources are required, should be defined as a separate work item.

7 (For example, if a substantially different productivity results when a specific crew of masons place brickwork for a straight wall versus walls with many blockouts, then masonry straight walls and masonry wall with blockouts should be defined as two separate work items). * The work items should be defined compatible with industry terminology. (For example, walls, beams, slabs, columns, etc.). * The work items should be defined such that accurate data can be collected at the job site for the specified work items. (For example, it may be feasible to require a foreman to record the amount of time a craftsman works on footings versus slabs in a given day. However, it may not be realistic to require the foreman to record the number of hours a craftsman works on 2 by 4 concrete footing forming versus 2 by 6 concrete footing forming. As such, 2 by 4 concrete footing forming and 2 by 6 footings should not be defined as separate work items. Instead, consideration should be given to defining one work item called concrete isolated footing forming). * The work items should be defined compatible with the construction industry's movement towards standardization. (For example, the Construction Specifications Institute (CSI) has defined work items or categories. While such a list may be too detailed for estimating, the definition or work items or codes compatible with such a criteria is useful). * The work items should be defined compatible with a defined project billing system as set out by the

8 project owner. (For example, the state highway department may set out 30 or 40 billing items that are used for paying the contractor. If such is the case, the contractor should consider defining the work items/codes compatible with the billing items). * The work items should be defined compatible with the concept that whatever is a work item for estimating, is an activity on the project schedule (bar chart or CPM diagram, and a cost object in the control system). (This is important in light of the movement towards computer software that attempts to integrate the entire information system for the contractor. The estimate, schedule and cost system should all tie together; they should not be viewed as independent functions). * The work items should be defined compatible with the fact that the quantities for the defined work items must be able to be determined from the project drawings. (For example, it is not possible to quantify the amount of grout to be needed from the project drawings. As such "grout" should not be defined as a separate work item. Instead, the grout should be determined as a function of another work item; for example, the number of bricks). * The work items should be defined compatible with the concept that if a certain percentage (for example 50%) of the work is in place then if no problems exist, 50% of the labor effort should be expended. Such a criteria is necessary if the firm is to be able to monitor and control the work process via comparing percent complete versus percentage of effort expended. (For example, if concrete wall forming and the placement of the concrete in the

9 walls is defined as one work item that is subsequently measured in cubic yards, it follows that a significant number of labor hours will be expended before a corresponding percentage of concrete is placed. The end result is that the firm would not have a good means of monitoring or controlling the work via a comparison of work in place versus effort. The end result is that the two types of work should be defined as two different work items). * The bid should be reviewed and checked for accuracy and completeness, then approved by management. * The contractor should establish bid withdrawal criteria, and know the last day he can safely withdrawal his bid. CONTRACT AWARD * The estimator should review the contract documents to determine if there are any discrepancies with the plans and specs. * Management should review the contract documents to ascertain if contract provisions comply with company contract criteria. If there are questions, the contractor should consult with legal counsel. * The bonding agent should be notified in order to obtain payment and performance bonds. * Purchase orders should be faxed to confirm material and subcontractor commitments in order to allocate risk. * A project budget should be prepared, prior to any work commencing. As previously mentioned, the estimate,

10 scheduling and cost system should tie together. * Following are examples of job cost controls. The contractor should strive to obtain example 3. THREE LEVELS OF CONTROL: THE NEED FOR INTEGRATION 1. Monitoring After The Affect Work Description Budget Labor Hours Actual Labor Hours to Date Status Place wall concrete In Process Place beam concrete Complete Place column concrete In Process Note: Can only tell you have a problem when budget is exceeded. 2. Monitoring Effort Versus Work Performed Work Description Budgeted Budgeted labor Actual quanity Actual labor Projected labor quanity (cy) hours (cy) hours hour overrun Place wall concrete Place beam concrete Place column concrete Note: Problem is detected whenever percentage of labor hours expended is greater than percentage of work in place. 3. Monitoring Schedule and Cost Control Work Budget Budget Budget Calc. Actual Actual Actual Project- Variance Variance Descrip- quanity labor Crew duration quanity labor Crew ed hours duration tion (qy) hours size (qy) hours size duration Place

11 Wall days days days conc Place beam days days days conc Place column days days days conc Note: The integration allows for monitoring duration as well as costs. It is possible for a work activity to be under budget in regard to duration but over budget in regard to cost or under budget in regard to cost but over budget in regard to duration. PRE-PLANNING * The contractor should meet with the owner, construction manager or general contractor. This meeting should address: * Planning and scheduling. Problems such as right of way should be resolved. This is a time to ask for additional money. * A review of the construction methods should determine if any reengineering is necessary. This is a time to ask for additional money. * Change orders and change order dispute procedures must be established. THIS IS ESSENTIAL!!! PRE-CONSTRUCTION

12 * The estimator hands the baton off to the project manager. The following activities are addressed at this phase: * Staffing the project * Equipment requirements * Budgets, report types and frequency * Record keeping requirements and frequency. What forms will be used to record the project activities, e.g. time cards, foreman reports, equipment logs, work authorizations, change orders, claims, etc. It must be established when these records are turned in for processing and when the output will be received. CONTRACT ADMINISTRATION * A job file should be assembled. The file should contain: * Contract and purchase order copies * Insurance certificates -expiration dates should be noted in a tickler file * License confirmations with expiration dates -a tickler file should be used to note expiration dates * Change order and extra work authorization procedures -determines time of billing these items * Preliminary liens * Billing and lien release procedures

13 * Reports and other requirements by owners, general contractors or others * Job cost accumulation data * Time cards * Material receivers and invoice copies * Equipment use -a company policy should be established re: costing of company equipment, e.g. idle equipment on a job site should be charged to that job. The superintendent and project manager are then motivated to eliminate equipment charges to their jobs due to idle equipment. * Rental equipment -daily reports * Subcontractors -daily reports if invoices aren't timely * Allocation of indirect costs * A reconciliation of quantities to cost and billings should be performed. The contractor should sit down with the owner or general contractor if the billing is in dispute. This reconciliation is a valuable aid when billing disputes arise. * A job completion reconciliation which should consider: * Quantities

14 * Scope changes, i.e. work authorizations for extra work * Unapproved change orders and claims * Back charges * Unpaid invoices * Notice of completion * Completeness procedures ensuring all notices and reports have been filed and copies of the notices and reports * Copy of the owners acceptance * Retention releases * A post job review should be performed. Significant variances, both favorable and unfavorable, should be analyzed. Any comments from the owner or general contractor, suppliers, subs, superintendents, foreman, crews, and other interested parties should be evaluated. If there are no comments, the contractor should solicit them through open ended questions. ACCOUNTING * Job Reporting * The cost reporting should interface with contract administration. Many contractors have their accounting departments perform the contract

15 administration function. * Preparation of payroll reports including certified or minority * Reconcile purchase orders, receivers, and invoices * Calculate percent complete. This function should interface with the company's operations. Work item estimates of cost to complete should be determined by field personnel not assigned to the job in question. * Review job and work item coding * Generate management reports * Input and pay invoices * Billings and collections * Record billings and cash receipts in the proper period. Establish cut-off procedures. * Reconcile payments and cash receipts * Establish and/or adhere to work authorizations, change orders, claims, and back charge accounting procedures. * Retention tracking * Cash flows and financial reports * Prepare monthly cash flow report -must be compared with the budget and revised monthly.

16 * Prepare monthly balance sheet and income statement and compare with the budget. * Prepare and/or review monthly billings and compare with the budget. * Prepare monthly open job report. Prepare monthly under and over billings report.

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District

REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE. St. Charles County Ambulance District REQUEST FOR PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES NOT AT RISK FOR THE St. Charles County Ambulance District Base 3 & Training Facility Construction 4169 Old Mill Parkway St. Peters, MO 63376 September

More information

Document B252TM 2007

Document B252TM 2007 Document B252TM 2007 Standard Form of Architect s Services: Architectural Interior Design for the following PROJECT: (Name and location or address) This document has important legal consequences. Consultation

More information

Owner s Representative SCOPE OF SERVICES

Owner s Representative SCOPE OF SERVICES Owner s Representative SCOPE OF SERVICES Scope of Services DeMaria s steady growth has enabled the construction of more sophisticated buildings through various methods and services. As your Owners Representative,

More information

SAN FRANCISCO PUBLIC UTILITIES COMMISSION WATER SYSTEM IMPROVEMENT PROGRAM CONSTRUCTION MANAGEMENT PROCEDURES

SAN FRANCISCO PUBLIC UTILITIES COMMISSION WATER SYSTEM IMPROVEMENT PROGRAM CONSTRUCTION MANAGEMENT PROCEDURES SAN FRANCISCO PUBLIC UTILITIES COMMISSION WATER SYSTEM IMPROVEMENT PROGRAM CONSTRUCTION MANAGEMENT PROCEDURES SECTION: WSIP CONSTRUCTION MANAGEMENT PROCEDURE NO.: 010 TITLE: APPLICATIONS FOR PAYMENT APPROVED:

More information

Your School District Procurement Card. Staff Guide Staff Agreement & Board Policy

Your School District Procurement Card. Staff Guide Staff Agreement & Board Policy Your School District Procurement Card Staff Guide Staff Agreement & Board Policy OVERVIEW The Procurement Card Program is intended to streamline and simplify the Procurement and Accounts Payable functions.

More information

JTT Project Manager Standard Guidelines

JTT Project Manager Standard Guidelines ESTIMATING THE PROJECT The guidelines below are for all bid requests. However, many of the subjects will only apply to larger, more complex projects. Always keep in mind that a thorough and well organized

More information

ARRA Monthly Employment Report Guidance Page 1 of 5 December 21, 2009

ARRA Monthly Employment Report Guidance Page 1 of 5 December 21, 2009 ARRA Monthly Employment Report Guidance Page 1 of 5 The following guidance for ARRA Monthly Employment Reporting will be in effect beginning January 1, 2010. Sections 1201 and 1512 of the American Recovery

More information

CHAPTER 1 INTRODUCTION

CHAPTER 1 INTRODUCTION CHAPTER 1 INTRODUCTION Cost is a major factor in most decisions regarding construction, and cost estimates are prepared throughout the planning, design, and construction phases of a construction project,

More information

707 Minnesota Ave., Suite 506 Kansas City, Kansas Tel Fax

707 Minnesota Ave., Suite 506 Kansas City, Kansas Tel Fax ADDENDUM 707 Minnesota Ave., Suite 506 Kansas City, Kansas 66101 Tel. 913.287.1900 Fax. 816.300.4102 www.wskfarch.com A r c h i t e c t u r e I n t e r i o r D e s i g n I l l u s t r a t I o n P l a n

More information

ATTACHMENT D SCOPE OF SERVICES

ATTACHMENT D SCOPE OF SERVICES ATTACHMENT D SCOPE OF SERVICES OBJECTIVE Owner s Capital Improvement Program (major capital, minor construction, repair, and rehabilitation projects) includes numerous construction and renovation projects.

More information

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk REQUEST FOR PROPOSAL Construction Management Services Not at Risk The St. Charles County Ambulance District proposes to retain a qualified firm/team for the Construction Management Services Not at Risk

More information

4 Secrets to Pain-Free Payment Management

4 Secrets to Pain-Free Payment Management 4 Secrets to Pain-Free Payment Management Textura is the leading provider of collaboration and productivity tools for the construction industry. Our solutions serve all construction industry professionals

More information

APPENDIX D CONSTRUCTION PHASE CRITERIA

APPENDIX D CONSTRUCTION PHASE CRITERIA A. GENERAL REQUIREMENTS CONSTRUCTION PHASE CRITERIA For the Construction Phase of the Project, the Architect/Engineer (A/E) is responsible for providing project administration for the Owner in accordance

More information

QUALIFICATION MATRIX ADDENDUM:

QUALIFICATION MATRIX ADDENDUM: QUALIFICATION MATRIX ADDENDUM: The following are just some examples of typical Responsible-in-Charge (RIC) functions for each of the fifteen specific areas identified in the experience matrix, Section

More information

What You Should Know For Auditing Capital Projects Presented by: Robert S. Bright, President

What You Should Know For Auditing Capital Projects Presented by: Robert S. Bright, President What You Should Know For Auditing Capital Projects Presented by: Robert S. Bright, President September 1, 2009 1 Part One Agenda Why the Session? Audit Themes Increasing Your Value Establishing Objectives

More information

Construction Auditing: UTILIZING INDUSTRY STANDARDS, BEST PRACTICES AND CHANGE ORDER AUDITING APRIL 4, 2017

Construction Auditing: UTILIZING INDUSTRY STANDARDS, BEST PRACTICES AND CHANGE ORDER AUDITING APRIL 4, 2017 Construction Auditing: UTILIZING INDUSTRY STANDARDS, BEST PRACTICES AND CHANGE ORDER AUDITING APRIL 4, 2017 OPENING REMARKS Kinney Poynter Moderator Executive Director NASACT Alan Pennington Speaker Vice

More information

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES

1997 Part 2. Document B141. Standard Form of Architect's Services: Design and Contract Administration TABLE OF ARTICLES TM Document B141 Standard Form of Architect's Services: Design and Contract Administration 1997 Part 2 TABLE OF ARTICLES 2.1 PROJECT ADMINISTRATION SERVICES 2.2 SUPPORTING SERVICES 2.3 EVALUATION AND PLANNING

More information

TRUMAN STATE UNIVERSITY SITE IMPROVEMENTS, KIRK BLDG, MISSOURI HALL & STUDENT REC CENTER LTD RENOVATIONS

TRUMAN STATE UNIVERSITY SITE IMPROVEMENTS, KIRK BLDG, MISSOURI HALL & STUDENT REC CENTER LTD RENOVATIONS SECTION 011000 - SUMMARY PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections,

More information

Both envelopes must have the following information in the lower left hand corner:

Both envelopes must have the following information in the lower left hand corner: SECTION 001116 INVITATION TO BID The City of Morgantown is requesting a bid for masonry restoration for the City Hall Building in Morgantown, WV. The Project is for building envelope rehabilitation including

More information

DIVISION 1 GENERAL REQUIREMENTS SECTION PROJECT SCHEDULE

DIVISION 1 GENERAL REQUIREMENTS SECTION PROJECT SCHEDULE DIVISION 1 GENERAL REQUIREMENTS SECTION 01 32 16 PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. All drawings and technical specifications, Notice to Bidders, Instructions and Information to Bidders, Bid Proposal

More information

The construction phase, of course, is the execution of the work as required by the contract documents when the building is finally built.

The construction phase, of course, is the execution of the work as required by the contract documents when the building is finally built. L1C4: Commercial Building Fundamentals Lesson 7 Study Guide Construction The construction phase, of course, is the execution of the work as required by the contract documents when the building is finally

More information

Florida Institute of Technology

Florida Institute of Technology Florida Institute of Technology Procurement Policy POLICY SOURCE: Procurement Services POLICY NO.: 5383 SUPERCEDES: 5382 TITLE: Procurement Policy SUBMITTED BY: Purchasing REVISED DATE: May 1, 2017 APPROVED

More information

Document B Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition

Document B Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition Document B132 2009 Standard Form of Agreement Between Owner and Architect, Construction Manager as Adviser Edition AGREEMENT made as of the in the year (In words, indicate day, month and year.) BETWEEN

More information

APPENDIX 2H UNDISCLOSED ROTTING STRUCTURAL COMPONENTS AND BRICK REPOINTING AND RENDER REPAIRS

APPENDIX 2H UNDISCLOSED ROTTING STRUCTURAL COMPONENTS AND BRICK REPOINTING AND RENDER REPAIRS APPENDIX 2H UNDISCLOSED ROTTING STRUCTURAL COMPONENTS AND BRICK REPOINTING AND RENDER REPAIRS 1. DEFINITIONS In this Appendix, in addition to the definitions set out in Schedule 1 of this Agreement: Approved

More information

EXHIBIT 6 Preconstruction Work

EXHIBIT 6 Preconstruction Work EXHIBIT 6 Preconstruction Work The following tasks shall be accomplished by the CM/GC as part of its obligations during the preconstruction phase. The work is to be coordinated with the services requirements

More information

REQUEST FOR PROPOSAL: Construction Management at Risk Services Hamilton International Air Cargo Logistics Facility. RFP Components

REQUEST FOR PROPOSAL: Construction Management at Risk Services Hamilton International Air Cargo Logistics Facility. RFP Components REQUEST FOR PROPOSAL: Construction Management at Risk Services Hamilton International Air Cargo Logistics Facility RFP Components CLIENT: TradePort International Corporation, Operators of John C. Munro

More information

Purchase Card Program

Purchase Card Program Purchase Card Program POLICIES AND PROCEDURES South Puget South Community College has established a Purchase Card Program in accordance with the Office of Financial Management and the Department of Enterprise

More information

Managing Fraud Risks. Procurement & Contacting. John J. Hall, CPA (970)

Managing Fraud Risks. Procurement & Contacting. John J. Hall, CPA (970) Managing Fraud Risks in Procurement & Contacting The IIA Los Angeles Chapter October 2, 2017 John J. Hall, CPA (970) 926-0355 John@JohnHallSpeaker.com 1 Four Categories 1. Theft 2. Results Manipulation

More information

FORENSIC INVESTIGATION FI (4) 1 98

FORENSIC INVESTIGATION FI (4) 1 98 FORENSIC INVESTIGATION FI (4) 1 98 FI (4) Work Step Work Step: Construction expert to: 219 - Conduct industry benchmarking (A) - Assess if the SGI contract is reasonable and within industry standards (B)

More information

CONSERVATION DISTRICT OPERATIONS REVIEW: A conservation district s self-guide to better operations CDB CD REVIEW VERSION. District Operations

CONSERVATION DISTRICT OPERATIONS REVIEW: A conservation district s self-guide to better operations CDB CD REVIEW VERSION. District Operations CONSERVATION DISTRICT OPERATIONS REVIEW: A conservation district s self-guide to better operations CDB CD REVIEW VERSION Montana conservation district (CD) law (76-15-101 through 810, MCA) as well as laws

More information

REQUEST FOR PROPOSALS 7530 Roofing Services 2013

REQUEST FOR PROPOSALS 7530 Roofing Services 2013 REQUEST FOR PROPOSALS 7530 Roofing Services 2013 General Description The City of Fort Collins is soliciting proposals for an experienced roofing contractor to perform needed repair, maintenance and repair-by-replacement

More information

San Francisco State University San Francisco, California Seismic Rehabilitation - Administration Building SF-454

San Francisco State University San Francisco, California Seismic Rehabilitation - Administration Building SF-454 San Francisco State University San Francisco, California Seismic Rehabilitation - Administration Building SF-454 GOAL The goal of KPMG, Peat Marwick, LLP s review of the San Francisco State University

More information

Town of Bennington, Vermont Pleasant Street and School Street Sidewalk Installation STP EH08(11)

Town of Bennington, Vermont Pleasant Street and School Street Sidewalk Installation STP EH08(11) , Vermont Pleasant Street and School Street Sidewalk Installation STP EH08(11) Request for Qualifications Construction Inspection and Testing Services Issued: January 3, 2017 Due: January 24, 2017 I. INTRODUCTION

More information

INVITATION FOR BID (IFB):

INVITATION FOR BID (IFB): DATE: May 8, 2018 ADDENDUM NO. 1 INVITATION FOR BID (IFB): B180022132 RPD Furnish & Install Ballistic Glass Lobby Counters IFB #B180022132 WAS ISSUED: Wednesday April 25, 2018 RECEIPT DATE: May 23, 2018

More information

***************************************************************************************************************

*************************************************************************************************************** 03365 POST-TENSIONED CONCRETE *************************************************************************************************************** SPECIFIER: CSI MasterFormat 2004 number 03 38 00. ***************************************************************************************************************

More information

a. An ability to apply knowledge of mathematics, science, and applied sciences.

a. An ability to apply knowledge of mathematics, science, and applied sciences. The ABET Criteria: a. An ability to apply knowledge of mathematics, science, and applied sciences. b. An ability to design and conduct experiments, as well as analyze and interpret data. c. An ability

More information

Seattle Public Schools The Office of Internal Audit

Seattle Public Schools The Office of Internal Audit only Seattle Public Schools The Office of Internal Audit Internal Audit Report September 1, 2011 through April 30 2013 Issue Date: June 18, 2013 Executive Summary Background Information The District s

More information

MANATEE COUNTY CLERK OF THE CIRCUIT COURT INTERNAL AUDIT DIVISION PUBLIC WORKS WATER DIVISION A U D I T R E P O R T

MANATEE COUNTY CLERK OF THE CIRCUIT COURT INTERNAL AUDIT DIVISION PUBLIC WORKS WATER DIVISION A U D I T R E P O R T MANATEE COUNTY CLERK OF THE CIRCUIT COURT INTERNAL AUDIT DIVISION PUBLIC WORKS WATER DIVISION A U D I T R E P O R T TABLE OF CONTENTS I. INTERNAL AUDIT REPORT C. Irregularities, Abuse, or Illegal Acts,

More information

A62 PRE-CONSTRUCTION MEETING AGENDA

A62 PRE-CONSTRUCTION MEETING AGENDA Provided below are the agenda items typically required by the Owner for the Pre-Construction Meeting. Guidance provided in agenda items does not revise the requirements of the Agreement. Instructions:

More information

ADDENDUM #1 Construction Support Services for the Water Treatment Plant Project PW

ADDENDUM #1 Construction Support Services for the Water Treatment Plant Project PW January 31, 2018 To Whom It May Concern: I. INSTRUCTIONS ADDENDUM #1 Construction Support Services for the Water Treatment Plant Project 18-0018PW A. The following additions, deletions, revisions, and/or

More information

ADDENDUM 1. Repair and Maintenance of Landfill Gas Chiller System. Return date: Bid must be received no later than 2:00 PM, Monday, June 25, 2018

ADDENDUM 1. Repair and Maintenance of Landfill Gas Chiller System. Return date: Bid must be received no later than 2:00 PM, Monday, June 25, 2018 ADDENDUM 1 Date: June 13, 2018 Bid No.: Title: 18-11/AL Repair and Maintenance of Landfill Gas Chiller System Return date: Bid must be received no later than 2:00 PM, Monday, June 25, 2018 This Addendum

More information

EGYPTIAN AREA AGENCY ON AGING Fiscal Monitoring Program

EGYPTIAN AREA AGENCY ON AGING Fiscal Monitoring Program EGYPTIAN AREA AGENCY ON AGING Fiscal Monitoring Program Fiscal Year: Name of Project/Site: (TIN #) Address: (city) (state) (zip code) Project Director/Site Manager: Geographic Area Served: (county) Project/Site

More information

CONTRACT SERVICES PHASE 1: PRE-CONSTRUCTION

CONTRACT SERVICES PHASE 1: PRE-CONSTRUCTION PHASE 1: PRE-CONSTRUCTION Schematics Phase Based upon program requirements and design parameters, D&J will establish conceptual budget and preliminary schedule for the project, which will highlight specific

More information

Pre-Construction Conference Discussion Guide

Pre-Construction Conference Discussion Guide Pre-Construction Conference Discussion Guide This guide is a summary of the topics normally required at the Pre-Construction Conference based upon the Tennessee Board of Regents Designers Manual standard

More information

SMALL CONTRACTORS INITIATIVE ASSESSMENT TOOL USER S GUIDE

SMALL CONTRACTORS INITIATIVE ASSESSMENT TOOL USER S GUIDE SMALL CONTRACTORS INITIATIVE ASSESSMENT TOOL USER S GUIDE SMALL CONTRACTORS INITIATIVE Assessment Tool User s Guide OVERVIEW OF THE INITIATIVE Federally funded construction projects represent substantial

More information

UNIVERSITY OF KENTUCKY Memorial Hall/College of Law Expansion and Renovation UK Project No

UNIVERSITY OF KENTUCKY Memorial Hall/College of Law Expansion and Renovation UK Project No PART 1 GENERAL 1.1 RELATED DOCUMENTS REQUIREMENTS COMMON TO ALL WORK CATEGORIES 1. Drawings and general provisions of the Contract, including General Special Conditions and other Division 1 Specification

More information

COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL

COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL SECTION 01310 COST LOADED CONSTRUCTION SCHEDULES PART 1 - GENERAL 1.01 SCOPE: A. COST LOADED CONSTRUCTION SCHEDULE (Construction Schedule): The WORK under this Contract shall be planned, scheduled, executed,

More information

A62 UT PRE-CONSTRUCTION MEETING AGENDA

A62 UT PRE-CONSTRUCTION MEETING AGENDA Provided below are the agenda items typically required by the Owner for the Pre-Construction Meeting. Guidance provided in agenda items does not revise the requirements of the Agreement. Instructions:

More information

A TECHNICAL SPECIFICATIONS LOCK BOX PAYMENTS

A TECHNICAL SPECIFICATIONS LOCK BOX PAYMENTS JEA Solicitation #146-18 Customer Payment Processing Services - Bank to Bank Payments and Lockbox Payments APPENDIX A TECHNICAL SPECIFICATIONS LOCK BOX PAYMENTS The scope of Work is for lockbox payment

More information

Table of Contents. Project Agreement Schedule 14

Table of Contents. Project Agreement Schedule 14 Table of Contents PART 1 DEFINITIONS... 3 PART 2 INTEGRATED MANAGEMENT SYSTEM REQUIREMENTS... 6 2.1. Introduction... 6 2.2. Overview... 6 2.2.1 Management System Requirements... 7 2.2.2 Certification...

More information

Adopted by Naytahwaush Community Charter School Board: November 13, 2012

Adopted by Naytahwaush Community Charter School Board: November 13, 2012 INTERNAL CONTROLS (MSBA/MASA Model Policy 703) Adopted by Naytahwaush Community Charter School Board: November 13, 2012 This policy is designed to be used in conjunction with current procedures, and to

More information

Discovery Children s Museum Document Retention and Destruction Policy

Discovery Children s Museum Document Retention and Destruction Policy Discovery Children s Museum Document Retention and Destruction Policy The Document Retention and Destruction Policy identifies the record retention responsibilities of employees, volunteers, members of

More information

UNIVERSITY OF TOLEDO INTERNAL AUDIT DEPARTMENT PURCHASE CAPITAL GOODS

UNIVERSITY OF TOLEDO INTERNAL AUDIT DEPARTMENT PURCHASE CAPITAL GOODS The following control objectives provide a basis for strengthening your control environment for the process of purchasing capital goods. When you select an objective, you will access a list of the associated

More information

Division of Student Affairs Internal Control Questionnaire FY 2011

Division of Student Affairs Internal Control Questionnaire FY 2011 Control Environment Yes No N/A Notations Are the roles and responsibilities of financial and administrative staff (including the establishment of the unit Director as the appropriate signature authority)

More information

Nutrition & Food Services AHIA 2012

Nutrition & Food Services AHIA 2012 Internal Control Questionnaire (2) page 1 of 5 7/17/2012 General Information Control Questionnaire Objective: To gather departmental information and documentation as a part of the preliminary survey phase

More information

Schedule 3 Services Schedule Equipment and Equipment-Related Supplies

Schedule 3 Services Schedule Equipment and Equipment-Related Supplies Equipment and Equipment-Related Supplies Services Schedule Equipment and Supplies Template LHIN Version June 2017 Schedule 3 Services Schedule Equipment and Equipment-Related Supplies TABLE OF CONTENTS

More information

Construction Administration Updates

Construction Administration Updates Ohio Department of Transportation John R. Kasich, Governor Jerry Wray, Director Construction Administration Updates Clint Bishop Construction Administration Updates Construction Administration Updates

More information

Spring Lake Public Schools. Spring Lake, MI. March RE: High School Storage Buildings

Spring Lake Public Schools. Spring Lake, MI. March RE: High School Storage Buildings Spring Lake Public Schools Spring Lake, MI March 2018 RE: High School Storage Buildings Advertisement for bids Bid Proposal Sealed bids for Spring Lake Public Schools-High School Storage Buildings will

More information

SECTION QUALITY CONTROL

SECTION QUALITY CONTROL SECTION 01 45 00 QUALITY CONTROL PART 1 - GENERAL 1.1 DESCRIPTION This section specifies requirements for Contractor Quality Control (CQC) for Design-Bid-Build (DBB) or Design-Build (DB) construction projects.

More information

HFTP Hospitality Financial and Technology Professionals

HFTP Hospitality Financial and Technology Professionals About our Sample Accounting Jobs Descriptions for Clubs: The HFTP Americas Research Center, with guidance from members of the HFTP Club Advisory Council, has developed example job descriptions for accounting

More information

BIDDING AND ESTIMATING

BIDDING AND ESTIMATING BIDDING AND ESTIMATING Chapter Survey ð Bid Documents ð Ethics in Bidding ð Estimate Planning ð Estimating Framework ð Determining Estimated Costs ð Other Methods of Estimating ð Estimating Pitfalls ð

More information

Candy Training Courses 2016

Candy Training Courses 2016 Candy Training Courses 2016 ESSENTIAL CORE COURSES Construction Estimating & Valuations (C201) - 2 days A two-day course suitable for Estimators and Quantity Surveyors new to Candy. The course covers all

More information

Candy Training Courses 2016

Candy Training Courses 2016 Candy Training Courses 2016 ESSENTIAL CORE COURSES Construction Estimating & Valuations (C201) - 2 days A two-day course suitable for Estimators and Quantity Surveyors new to Candy. The course covers all

More information

SPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S

SPECIFICATIONS - DETAILED PROVISIONS Section Project Control Schedule C O N T E N T S SPECIFICATIONS - DETAILED PROVISIONS Section 01310 - Project Control Schedule C O N T E N T S PART 1 - SCHEDULE REQUIREMENTS PROGRESS SCHEDULE... 1 PART 2 - SUBMITTAL PROCEDURES... 2 PART 3 - DEFINITIONS...

More information

CONSTRUCTION MANAGEMENT. By GREEN PLANET SERVICES Lesley Padayachee Cell:

CONSTRUCTION MANAGEMENT. By GREEN PLANET SERVICES Lesley Padayachee Cell: CONSTRUCTION MANAGEMENT By GREEN PLANET SERVICES Lesley Padayachee Cell: 084 525 4720 Lesley.gpes@gmail.com 5 th FEBRUARY 2013 CONSTRUCTION MANAGEMENT - DEFINED Act of managing the construction process

More information

ROLES AND RESPONSIBILITIES

ROLES AND RESPONSIBILITIES Audio Sessions Session 2 ROLES AND RESPONSIBILITIES Education Program Certified Construction Contract Administrator (CCCA) Preparatory Course 2011 The Construction Specifications Institute www.csinet.org

More information

Developer s Packet. For Developments Requiring Large Meters

Developer s Packet. For Developments Requiring Large Meters Developer s Packet For Developments Requiring Large Meters We at White House Utility District understand the importance of helping you to meet your project deadlines. This WHUD developer s packet has been

More information

Ensemble Business Software ClientFirst Product Support. November 4, 2008

Ensemble Business Software ClientFirst Product Support. November 4, 2008 November 4, 2008 The ClientFirst Product Support Program includes Telephone Support Services covering the day-to-day issues associated with the use of Ensemble and MAS 90 modules. A one-year subscription

More information

ATTACHMENT A. Bid # 6793

ATTACHMENT A. Bid # 6793 ATTACHMENT A SCOPE OF WORK TECHNICAL SPECIFICATIONS AND CONTRACT DRAWINGS STORAGE SHED INSTALLATION AT THE SAN JOAQUIN COUNTY HOUSEHOLD HAZARDOUS WASTE FACILITY Bid # 6793 Department of Public Works Solid

More information

APPENDIX A - TECHNICAL SPECIFICATIONS. JEA Fleet Services Light Duty Equipment Maintenance and Repair

APPENDIX A - TECHNICAL SPECIFICATIONS. JEA Fleet Services Light Duty Equipment Maintenance and Repair APPENDIX A - TECHNICAL SPECIFICATIONS JEA Fleet Services Light Duty Equipment Maintenance and Repair 1. GENERAL SCOPE OF WORK This scope of work is looking for a Respondent(s) to provide JEA Fleet Services

More information

INSTRUCTIONS TO BIDDERS

INSTRUCTIONS TO BIDDERS INSTRUCTIONS TO BIDDERS CONTENTS I. Bid Documents II. Ethical Business Practices III. Contractor Qualifications IV. Performance and Quality Standards V. Bid Evaluation VI. Contract Award VII. Work Operations

More information

ACADEMY OF NATURAL SCIENCES PURCHASING AND PROCUREMENT POLICY

ACADEMY OF NATURAL SCIENCES PURCHASING AND PROCUREMENT POLICY ACADEMY OF NATURAL SCIENCES PURCHASING AND PROCUREMENT POLICY Academy of Natural Sciences Purchasing Policy Overview This policy framework is intended to provide for the procurement of goods and services

More information

HOUSING OPPORTUNITIES COMMISSION OF MONTGOMERY COUNTY DAVIS BACON ACT GUIDELINES

HOUSING OPPORTUNITIES COMMISSION OF MONTGOMERY COUNTY DAVIS BACON ACT GUIDELINES HOUSING OPPORTUNITIES COMMISSION OF MONTGOMERY COUNTY DAVIS BACON ACT GUIDELINES The purpose of this Davis Bacon Act Guideline ( Guideline ) is to implement the applicable provisions of the Davis Bacon

More information

Construction Project Management: A Complete Introduction

Construction Project Management: A Complete Introduction Construction Project Management: A Complete Introduction by Alison Dykstra, AIA, CSI Slides are available for instructors who assign this book. They were developed using PowerPoint to assist instructors

More information

DeFoe Corp. 800 South Columbus Ave. Mount Vernon, NY QUALITY ASSURANCE MEASUREMENT ANALYSIS AND IMPROVEMENT

DeFoe Corp. 800 South Columbus Ave. Mount Vernon, NY QUALITY ASSURANCE MEASUREMENT ANALYSIS AND IMPROVEMENT DeFoe Corp. 800 South Columbus Ave. Mount Vernon, NY 10550 QUALITY ASSURANCE TABLE OF CONTENTS SECTION I SECTION 2 SECTION 3 SECTION 4 SECTION 5 QUALITY MANAGEMENT SYSTEM MANAGEMENT RESPONSIBILITY RESOURCE

More information

45. Feedlot construction delivery

45. Feedlot construction delivery Client Des i gn/ Builder Design Consultant Construction Sub-contractors and suppliers FEEDLOT DESIGN AND CONSTRUCTION 45. Feedlot construction delivery AUTHORS: Rod Davis and Ross Stafford Introduction

More information

CAS -18 COST ACCOUNTING STANDARD ON RESEARCH AND DEVELOPMENT COSTS

CAS -18 COST ACCOUNTING STANDARD ON RESEARCH AND DEVELOPMENT COSTS CAS -18 COST ACCOUNTING STANDARD ON RESEARCH AND DEVELOPMENT COSTS The following is the Cost Accounting Standard-18 (CAS-18) issued by the Council of The Institute of Cost Accountants of India for determination

More information

Request for Proposal For: 2018 American Bar Association Temporary Services

Request for Proposal For: 2018 American Bar Association Temporary Services Table of Contents Bid Timetable [2] 1.0 General Bid Information [3] 2.0 Proposal Requirements [5] 3.0 Criteria for Selection [7] 4.0 Specifications and Work Statement [7] Appendix A: Bidder Response Sheet

More information

DETAILED WORK BREAKDOWN STRUCTURE (WBS) FOR CONSTRUCTION PROJECTS

DETAILED WORK BREAKDOWN STRUCTURE (WBS) FOR CONSTRUCTION PROJECTS DETAILED WORK BREAKDOWN STRUCTURE (WBS) FOR CONSTRUCTION PROJECTS DESCRIPITION (TASK) 1.0 PRE-CONSTRUCTION PHASE 1.1 - Bid Process 1.1.1 - Get plans from Architect Estimator Estimator PM 1.1.2 - Assign

More information

TRUMAN STATE UNIVERSITY BALDWIN HALL, PERSHING BLDG AND VIOLETTE HALL ROOFING & EXT. RENOV.

TRUMAN STATE UNIVERSITY BALDWIN HALL, PERSHING BLDG AND VIOLETTE HALL ROOFING & EXT. RENOV. SECTION 011000 - SUMMARY PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections,

More information

REQUEST FOR PROPOSALS

REQUEST FOR PROPOSALS REQUEST FOR PROPOSALS CONSTRUCTION MANAGEMENT SERVICES OCTOBER 09, 2014 EAST BAY REGIONAL PARK DISTRICT Atlas Road Extension Improvements POINT PINOLE REGIONAL SHORELINE PROPOSALS DUE: 2:00PM, NOVEMBER

More information

Section IV. Bidding Forms

Section IV. Bidding Forms Section IV. Bidding Forms 1-1 Section IV. Bidding Forms Table of Forms Letter of Bid... 3 Form of Bid Security (Bank Guarantee)... 6 Form of Bid Security (Bid Bond)... 7 Form of Bid-Securing Declaration...

More information

The New Procurement Review for School Nutrition Programs

The New Procurement Review for School Nutrition Programs New Jersey Department of Agriculture 1 The New Procurement Review for School Nutrition Programs What New Jersey schools need to know August 2017 WEBINAR LEARNING OBJECTIVES Participants should be able

More information

NEW MEXICO HIGHLANDS UNIVERSITY INDEPENDENT ACCOUNTANTS REPORT ON APPLYING AGREED-UPON PROCEDURES

NEW MEXICO HIGHLANDS UNIVERSITY INDEPENDENT ACCOUNTANTS REPORT ON APPLYING AGREED-UPON PROCEDURES NEW MEXICO HIGHLANDS UNIVERSITY INDEPENDENT ACCOUNTANTS REPORT ON APPLYING AGREED-UPON PROCEDURES June 30, 2015 CERTIFIED PUBLIC CERTIFIED ACCOUNTANTS PUBLIC ACCOUN CONSULTANTS CERTIFIED PUBLIC ACCOUNTANTS

More information

CALLEGUAS MUNICIPAL WATER DISTRICT THOUSAND OAKS, CALIFORNIA NOTICE INVITING BIDS

CALLEGUAS MUNICIPAL WATER DISTRICT THOUSAND OAKS, CALIFORNIA NOTICE INVITING BIDS CALLEGUAS MUNICIPAL WATER DISTRICT THOUSAND OAKS, CALIFORNIA NOTICE INVITING BIDS For the construction of the CCNB Broken Back Rehabilitation, Phase 3 located at 8 sites in the City of Simi Valley in the

More information

Highway / Utility Guide

Highway / Utility Guide Oregon Department of Transportation Highway Division Right of Way Section Highway / Utility Guide Railroad & Utilities Unit Right of Way Section STATEMENT OF PURPOSE It is important to understand that

More information

CONSTRUCTION PROCEDURES MANUAL PROJECT

CONSTRUCTION PROCEDURES MANUAL PROJECT CONSTRUCTION PROCEDURES MANUAL ADMINISTRATIVE SCHOOL DISTRICT #1 BEND LaPINE PUBLIC SCHOOLS (DATE) Page 1 ADMINISTRATIVE SCHOOL DISTRICT #1 BEND LaPINE PUBLIC SCHOOLS TABLE OF CONTENTS CONTENTS PAGE: 1.0

More information

Minnesota State University Moorhead Construction Management CM 496 CM Capstone Project Semester Project Description Fall 2004

Minnesota State University Moorhead Construction Management CM 496 CM Capstone Project Semester Project Description Fall 2004 Minnesota State University Moorhead Construction Management CM 496 CM Capstone Project Semester Project Description Fall 2004 A group of investors has approached your construction company with a simple

More information

Audit Department Report for June 2014

Audit Department Report for June 2014 Report Report Office of the General Auditor Audit Department Report for June 2014 Summary Three reports were issued during the month: Gas Card Program Audit Report and Management Response ABSG Consulting,

More information

G , Request for Proposal Land Survey

G , Request for Proposal Land Survey G601 1994, Request for Proposal Land Survey AIA Document G601 1994 allows owners to request proposals from a number of surveyors based on information deemed necessary by the owner and architect. G601 1994

More information

The Superintendent is appointed by the Area Manager and must have the following qualifications:

The Superintendent is appointed by the Area Manager and must have the following qualifications: SUPERINTENDENT Introduction The Superintendent s primary function for Superior Gunite is one of the most important activities in our operations. The Superintendent is the company's representative with

More information

Chapter 4 State Requirements for Educational Facilities Section 4.1

Chapter 4 State Requirements for Educational Facilities Section 4.1 providential cause, other impending danger to life safety, or pursuant to Section 1013.46(1)(b), F.S., the board can declare an emergency, can negotiate a contract with a design-build firm, design professional,

More information

CONSTRUCTION MANAGEMENT CORE COMPETENCIES

CONSTRUCTION MANAGEMENT CORE COMPETENCIES CONSTRUCTION MANAGEMENT CORE COMPETENCIES A Guide to the Construction Management Core Competencies and their Body of Knowledge CM PROFESSIONAL PRACTICE... 1 CM PROJECT MANAGEMENT... 4 COST MANAGEMENT...

More information

All subcontractor bidders are responsible for assuring that their subcontractors and vendors are properly apprised of the contents of this Addendum.

All subcontractor bidders are responsible for assuring that their subcontractors and vendors are properly apprised of the contents of this Addendum. ADDENDUM NUMBER: 2 PROJECT: UNC Charlotte Residence Hall Phase XIV - Elevator Bid Package DATE: May 28, 2015 OWNER: UNC Charlotte ARCHITECT: FWA Group NOTICE TO BIDDERS: This addendum is issued prior to

More information

A. General Information

A. General Information Management Systems Questionnaire for Standard Cost Reimbursement Grants (Jan 2016) 1. Legal name of applicant organization: 2. Name and title of individual completing this questionnaire: 3. Signature of

More information

CONSTRUCTION DOCUMENTS Part 1

CONSTRUCTION DOCUMENTS Part 1 Audio Presentation Session 4 CONSTRUCTION DOCUMENTS Part 1 Project Delivery Education Program Construction Document Technology (CDT) Preparatory Course 2011 The Construction Specifications Institute www.csinet.org

More information

TEXAS TECH UNIVERSITY HEALTH SCIENCES CENTER MEDICAL SCIENCE BUILDING II EARLY GMP SUB SELECTION REQUEST FOR PROPOSAL

TEXAS TECH UNIVERSITY HEALTH SCIENCES CENTER MEDICAL SCIENCE BUILDING II EARLY GMP SUB SELECTION REQUEST FOR PROPOSAL TEXAS TECH UNIVERSITY HEALTH SCIENCES CENTER MEDICAL SCIENCE BUILDING II El Paso, Texas EARLY GMP SUB SELECTION REQUEST FOR PROPOSAL for the BUILDING CONCRETE GLASS AND GLAZING FIRE SPRINKLER MECHANICAL

More information

CHAPTER 5.0: RECORD-KEEPING AND REPORTING REQUIREMENTS

CHAPTER 5.0: RECORD-KEEPING AND REPORTING REQUIREMENTS CHAPTER 5.0: RECORD-KEEPING AND REPORTING REQUIREMENTS Accurate record keeping and reporting are crucial to the successful management of your CDBGfunded activities. The failure to maintain adequate documentation

More information

Bidding & Estimating Course Syllabus

Bidding & Estimating Course Syllabus Bidding & Estimating Course Syllabus 2 Hours (Interactive) Introduction & Overview to Bidding & Estimating Review Sundt/Walsh Abstracting Process Estimating Templates Introduction to Estimating Bid Documents

More information