Results for 2001 indicate achievement year-to-date and/or projected levels.

Size: px
Start display at page:

Download "Results for 2001 indicate achievement year-to-date and/or projected levels."

Transcription

1 What the Program Has Achieved: Since its inception, the NYISO incentive compensation program has proven highly effective at motivating employees toward achieving high priority objectives for the organization. A primary reason the program has been so successful results from its being developed and implemented at the employee level rather than being directed top-down from senior management. This has achieved high-level commitment and buy-in from the employees. In 2000, the first year of the program, there was one Reliability Gateway goal and nine individual goals. The gateway goal was fully achieved and of the individual goals, seven were achieved at superior level and two at target level. This resulted in an achievement of 139 % of the 2000 incentive goal program. A summary of the 2000 goals is provided as an attachment. For 2001, a second gateway goal, the Market Gateway, was added to the Reliability Gateway and there were ten individual goals. Year-to-date the gateway goals are being fully met, five individual goals are tracking at superior level, four at target level, and one failed to meet the threshold objective. The program is tracking toward an achievement of 105 %. The following table summarizes the incentive program results during the first two years: Incentive Goals Gateway goals achieved 1 of 1 2 of 2 Goals achieved at Superior level 7 5 Goals achieved at Target level 2 3 Goals achieved at Threshold level 0 1 Failed to achieve goals 0 1 Total achievement 139 % 110 % Results for 2001 indicate achievement year-to-date and/or projected levels. Approach for the 2002 Program: For the 2002 program, the planning process was expanded to include not only the incentive goals, but also, development and tracking of the Business Plan. This change was intended to drive the business planning process further down into the organization, thereby providing more visibility to and involvement of all employees. 1

2 Work on the 2002 program began in June 2001 with the formation of the Business Plan and Incentive Goals team. The team includes thirteen individuals - two representatives each from Market Services, Operations & Reliability, Information Technology, Finance & Compliance and Strategic Initiatives; one representative each from Government Affairs & Communication and General Counsel & Regulatory Affairs; and the team leader who is the Manager of Strategic Planning. The team comprises a balance of managers/supervisors and individual contributors a mix that was intended to broaden knowledge and understanding of the process and to provide for orderly succession. The Budget, Standards and Performance Subcommittee (BS&PS), which reports to the Management Committee, submitted a list of suggested 2002 goals in May The BS&PS participated in the incentive goals process in prior years as one of their charter roles. The Business Plan and Incentive Goals team accepted the BS&PS suggestions as a primary input for developing the incentive goals and the 2002 Business Plan. Most of the BS&PS suggestions were incorporated into the incentive goals or in some cases included as Group or Department-level goals. Some were deemed impossible to implement at the present time. The following pages present a summary of the proposed 2002 incentive goals, the existing 2001 incentive goals, and a detailed explanation of each of the proposed incentive goals for Incentive Goals Alignment with Strategic Objectives The NYISO strategic plan identified four key strategic objectives for the organization. The incentive goals have been aligned with the four strategic objectives as indicated in the descriptions below. This relationship will be highlighted when the incentive goals are introduced to employees and it will be emphasized as the goals are tracked and reported on during the year. 2

3 Detailed Explanation of Incentive Goals for 2002: 1. Reliability Gateway Goal - Maintain Service to New York Control Area Achieving No Interruption of Load (> 300 MW for > 15 minutes) Because of Improper Implementation of NYISO Operating Procedures. Definition: The Reliability Gateway is a go/no-go goal, which emphasizes the importance of maintaining system reliability. Both Gateway goals must be achieved for there to be any payment earned under the NYISO Organizational Incentive Plan even if all of the other goals are achieved. The successful achievement of this Gateway is based upon the NYISO staff operating the bulk power system in compliance with all internal operating procedures, as well as those of NPCC, NERC and the DOE. Should there be a loss of load or deliberate load shedding, successful achievement of this goal is predicated upon the NYISO staff demonstrating, to the satisfaction of the CEO and the NYISO Board of Directors that the appropriate procedures were followed (i.e., the loss of load or deliberate load shedding did not result from inappropriate actions of the NYISO staff). Appropriately documenting the circumstances associated with a loss of load or deliberate load shedding event is the responsibility of the NYISO staff. In the event of a loss of load, the Operating Committee will review the events and provide their comments to the NYISO. The CEO and Board of Directors will exercise their discretion in determining whether or not this goal was achieved, to establish that the NYISO is responsible (to the extent of its bonus pool) if NYISO procedures are not followed and, as a result, service to NYCA load is not maintained. Why this is a challenge: A Gateway Goal should send the proper signal to employees about mission-critical activities. At the same time, because achieving the Gateway is a minimal threshold, there should be a very high likelihood of attainment (99+ %) with the appropriate level of commitment and support from staff. How it is tracked: System Operators actions are logged, and in the event that a load shed order is given analysis of the recorded data would provide the amount of load shed and the duration. BS&PS input: The BS&PS suggested using this goal as it is stated. 3

4 Comparison to 2001: This Reliability Gateway is identical to the goals used in 2001 and Since the NYISO began operations in 1999, there have been no instances of load shedding. Alternatives: The target levels for this goal are chosen to coincide with a NERC reportable event (>300 MW for >15 minutes). Alignment with strategic objectives: This Gateway Goal is aligned with the NYISO strategic objective to be the Leader in Reliable Service and Environmental Quality. Responsibility: The Operations Department is responsible for achieving this goal with substantial support from the Information Technology Group. 4

5 2. Market Gateway Goal Successfully Post DAM Schedules/ Forward Contracts 99 % of the Time. Definition: The Market Gateway is a go/no-go goal, which emphasizes the importance of ensuring that the marketplace is operational. As a go/no-go goal, unless it is achieved, a bonus payment will not be earned under the Corporate Goals and Objectives Bonus Program even if all of the other goals are achieved. The successful achievement of this goal is based upon the NYISO staff ensuring that the DAM is posted successfully. The goal will be successfully achieved if no more than five times during the year the DAM schedules/ forward contracts are unable to be posted. Should there be an occasion where the DAM schedules/ forward contracts are not posted due to a Force Majeure or by uncontrollable actions of the marketplace, that instance will not be counted as one of the five allowed occurrences. As long as the posting occurs prior to the end of the day, it will considered to be successful. Why this is a challenge: A Gateway should send the proper signal to employees about mission critical activities. At the same time, because achieving the Gateway is a minimal threshold, there should be a very high likelihood of attainment (99+ %) with the appropriate level of commitment and support from staff. How it is tracked: The OASIS MIS web site displays the date and time of actual posting of each day s DAM LBMP prices. The posting time will be used to assess achievement of this goal. BS&PS input: The BS&PS suggested a goal of 100 % successful posting (based on the 11 AM tariff requirement) with an allowance for late postings provided it was # 10 cumulative hours during the year. NYISO has proposed to retain the Market Gateway Goal as previously stated, but also, to add a new individual incentive goal (see # 5) to address the 11 AM posting time. Comparison to 2001: This Gateway Goal is identical to that used for 2001 when it was first introduced. Since the NYISO began operations in 1999, the DAM schedules / forward contracts have been posted successfully every day, never being more than two hours after the scheduled posting time. Year-to-date through September 2001, DAM postings have occurred after the 11 AM requirement on 11 days for a cumulative total of 298 minutes. 5

6 Alternatives: There was considerable discussion and debate about the definition of this goal both among the NYISO staff and at the BS&PS meetings. NYISO staff are concerned that there are many uncertainties regarding the performance of the SCUC with the anticipated changes such as virtual transactions, fixed-block transactions, etc., that may impact our ability to post prices on time. This situation is further complicated by the fixed period of time from the market closing at 5:00 AM until the 11:00 AM posting time. Alignment with strategic objectives: This Gateway Goal is aligned with the NYISO strategic objective to be the Competitive Market Champion. Responsibility: The Market Operations Department is responsible for achieving this goal with substantial support from the Information Technology Group. 6

7 3. Prepare Accurate Day-ahead, Non-weather-adjusted Load Forecasts Definition: This goal is based upon the cumulative 365-day accuracy rate of the daily peak load, nonweather-adjusted, day-ahead forecast (i.e., the average accuracy of the forecast over the 365 day period). The 2002 load forecast goal will not be adjusted for weather conditions. The concept for this change is to provide incentive to the NYISO staff to continually evaluate and select the most accurate weather forecast services upon which to base the zonal load forecasts. Zones that will be tracked are: West, East, J and K Threshold Target Superior NYISO proposed goal 2.8 % 2.5 % 2.3% BS&PS suggested goal 3.0 % 2.5 % 1.5 % Why this is a challenge: The non-weather-adjusted average error YTD through September 2001 was 2.87 %. The proposed Threshold for next year is a lower error percentage than that currently being achieved. The Target level, represents a 13 % improvement in accuracy compared to the current year s experience. The Superior level represents a level of accuracy that was achieved in only three of the last twelve months and is more accurate than the level being achieved on a weather-adjusted basis so far this year. How it is tracked: The error, expressed as the percentage difference between the actual and predicted daily peak load divided by the actual peak load, is tracked individually for each of the four zones every day. The average error is the sum of the four individual zonal errors divided by four. (Each individual zonal error is expressed as an absolute value, so negative errors do not cancel positive errors.) For 2002, there will be 365 observations of the average zonal error. The annual average zonal error is the sum of these observation divided by 365. This is the figure that will be evaluated against the goal attainment levels. BS&PS input: The BS&PS suggested the goal be based on the non-weather adjusted forecast for the dayahead zonal load forecasts with values as shown above. 7

8 Comparison to 2001: The 2001 goal is based on weather-adjusted forecast data with the following targets: Threshold Target Superior 2001 weather-adjusted goal 3.2 % 3.0 % 2.75 % Additional model refinements have resulted in improved forecasting for both zonal and statewide load. Through September 2001 achievement for weather-adjusted forecasts is 2.59 %. By comparison, the 2000 year-end weather-adjusted load forecast accuracy was 3.26 % The non-weather adjusted forecast accuracy is 2.87 % through September 2001 and by comparison the 2000 year-end figure was 3.5 % Alternatives: This is deemed to be the most appropriate goal regarding day-ahead load forecasting and its impact on the NYISO markets. The move toward use of the non-weather-adjusted accuracy has placed even greater burden upon the NYISO staff, while correspondingly reducing market risk faced by the Market Participants. Alignment with strategic objectives: This incentive goal is aligned with the NYISO strategic objective to be the Competitive Market Champion. Responsibility: The Analysis and Planning Dept s Load Forecasting Unit is responsible for performing the load forecast calculations, obtaining weather service data, and for maintaining the monitoring records. 8

9 4. Comply with NERC Standards CPS-1 and CPS-2 Definition: Control Performance Standards (CPS) are criteria defined by NERC to monitor and compare power system operation across North America. The two CPS parameters are derived from the theory that system reliability is impacted by the effectiveness of frequency control. CPS-1 measures the Area Control Error (ACE) impact on frequency over a 12-month horizon, while CPS-2 measures the magnitude of short-term ACE values. The NERC compliance threshold for CPS-1 is 100% (typical values range from %) and for CPS-2 is 90 % (with a maximum of 100%). The NYISO proposed goals are as follows: Threshold Target Superior a) CPS-1 100% 12 of of of 12 b) CPS-2 90 % 10 of of of 12 (number of months achieved) Why this is a challenge: CPS-1 and CPS-2 values are not monitored in real-time as they are normally calculated on the following day. The CPS values are a function of the Area Control Error (ACE) that is influenced by generators not following their base point signals and by deviations in schedules with adjacent control areas. System Operators do not have direct control over the generating units or the control areas with which we schedule transactions, however they do act to avoid or resolve high ACE values thereby helping to maintain acceptable CPS values. A further complication results from changes that have been recently implemented, such as the elimination of accumulating base points and uninstructed overgeneration, which may affect the CPS quantities in ways that cannot be fully anticipated. How it is tracked: The data required to calculate CPS-1 and CPS-2 are collected continuously, and a daily summary is issued the following day. Compliance with the two standards is determined on a monthly basis. BS&PS input: The BS&PS suggested goals were as follows: Threshold Target Superior a) CPS-1 100% 12 of of of 12 mo. b) CPS % % % 9

10 For CPS-2, the BS&PS proposed a different approach than exceeding the minimum compliance threshold. In their view, it would be preferable not to incent operators toward overcompliance (approaching 100%), on the theory that there is a cost to regulating more than is required. Therefore, the BS&PS suggested the target and superior level goals should have narrower ranges, % and % respectively. Comparison to 2001: Below is a graph that shows CPS-1 and CPS-2 performance over the past twelve months. CPS1 CPS2 NERC Control Performance NYISO Compliance Year 2000/ Sep-00 Oct-00 Nov-00 Dec-00 Jan-01 Feb-01 Mar-01 Apr-01 May-01 Jun-01 Jul-01 Aug-01 Sep-01 Month Alternatives: There are no known studies substantiating that a savings would result from restricting control to a narrower band, although it is likely that there are regulation costs associated with achieving higher percentages. However, changes being planned for BME and SCD software (such as uninstructed overgeneration, virtual bidding, etc.) may have deleterious effects on CPS-2 that cannot presently be quantified. Also, the dispatchers are not able to observe CPS-2 performance in real time since the index is not calculated until the following day. 10

11 The reserve sharing agreement that was reached with ISO-NE will allow NYISO to reduce the in-state reserve requirement and may at times have a negative impact on CPS- 2. As a result, some of the envisioned cost savings that the BS&PS was hoping to achieve may be accomplished through the new reserve sharing practices. The NYISO does have the option of not using reserve sharing if it causes a perceived impact on reliability and/or CPS-2. The NYISO has an existing defined task to study the value of reliability within the planned Center for Market Excellence (CME) initiative. To address the issue raised by the BS&PS regarding CPS-2, this scope of this task will be expanded to specifically include research that attempts to quantify the economics of lower values of CPS-2 compliance. Alignment with strategic objectives: This incentive goal is aligned with the NYISO strategic objective to be the Leader in Reliable Service and Environmental Quality. Responsibility: The Operations Department is responsible for monitoring and achieving this goal with substantial support from the Information Technology Group. 11

12 5. Timely Posting of DAM Schedules/Forward Contracts Definition: This is a new goal, created to complement the Market Gateway goal, which provides an incentive to achieve the 11 AM posting time for the Day-ahead Market a high percentage of the time. The NYISO proposed goal is as follows: Threshold Target Superior Achieve DAM posting 85 % 90 % 95 % by 11 AM this percentage of days in the year Why this is a challenge: This goal is a challenge due to the increased computational complexity and the finite period of time that is available to accomplish the Security-Constrained Unit Commitment (SCUC) process. This process requires the use of a complex software package, a number of manual actions, and at times, prompt decisions based on unusual circumstances that may be encountered. There are many uncertainties that could impact the SCUC process as a result of future changes being planned for the day-ahead market, for example, virtual transactions, and fixed-block transactions. These changes, even when thoroughly tested before implementation, may have unanticipated consequences that impact timely posting of the SCUC results. The situation is further complicated by the fixed period of time from the market closing at 5:00 AM until the required 11:00 AM posting time. The collective amount of contingency time in this period continues to shrink as the process becomes more complex. How it is tracked: Performance toward this goal will be determined based upon the DAM LBMP posting time on the OASIS portion of the NYISO web site. If the posting time is later than 11:00 AM, by as little as one minute, it will be counted as one day missed for this goal. BS&PS input: The BS&PS suggested a Market Gateway goal of 100 % successful posting (based on the 11 AM tariff requirement) of the day-ahead schedules/forward contracts with an allowance for late postings provided it was # 10 cumulative hours during the year. Comparison to 2001: This is a new goal for YTD through September the DAM postings have been late on 11 days. 12

13 Alternatives: This goal was added to demonstrate responsiveness to the MP s concerns and as an alternative to changing the Market Gateway Goal. Alignment with strategic objectives: This incentive goal is aligned with the NYISO strategic objective to be the Competitive Market Champion. Responsibility: Market Operations is responsible for achieving this goal with substantial support from the Information Technology Group. 13

14 6. Real-time Price Certainty and Accuracy Definition: There are two issues regarding prices in the real-time market: 1) the number of hours that are reserved for review thereby causing price uncertainty and 2) the number of prices that are actually corrected after review thus resulting in inaccuracy. A goal focusing only on corrections might encourage making fewer price reservations. The reservation and correction process is conducted primarily by LECG, an outside consulting firm. The NYISO proposes a two-part goal to properly address each issue: Threshold Target Superior a) Hours Reserved: 22 % 20 % 18 % b) Intervals Corrected: 0.6 % 0.5 % 0.4 % It should be noted that price reservations are tracked based on hours whereas the realtime market produces prices at five-minute intervals. The reservation of a single price for any one of the five-minute intervals results in that entire hour being counted as reserved. Corrections, on the other hand, are tracked based on the individual five-minute interval prices. During a calendar month the number of interval prices will typically exceed 14,000. Thus, a 1 % level of intervals corrected would mean that 140 of the five-minute prices were corrected during the month. Why this is a challenge: The number of price interval corrections has been reduced from nearly 7 % at the beginning of 2000 to the present level of 0.48 % on a cumulative year-to-date basis. The potential to further reduce the number of corrections is limited. The challenge now will be to maintain the current level of accuracy as changes are made to the real-time market and the BME/SCD process. It could be argued that since little further improvement is expected this should not be an incentive goal. However, it is important that MPs see that NYISO remains focused on real-time price accuracy by way of this incentive goal. Price reservations have also been drastically reduced from more than 35 % early in 2000 to the current level of % on a cumulative year-to-date basis. The level of price reservations can be improved further, although not at the same rate of decline already achieved. Improving price reservations is the primary focus of this two-part incentive goal. 14

15 A further complexity results because both hours reserved and intervals corrected are determined by LECG, an outside consulting firm. In order to achieve the two-part goal, the NYISO Market Monitoring and Performance (MMP) unit will need to ensure the goals are conveyed to LECG and that their work is effectively managed. MMP will also work with LECG to develop more precise screens to reduce the need for reservations. LECG reviews real-time prices on a continual basis seven days per week. The process involves scanning the prices with software algorithms as well as inspection by a qualified analyst. Hours are reserved when anomalies are identified through this initial screening. Price reservations are announced to Market Participants within 24 hours of the day s realtime price posting which completes shortly after midnight. Reserved hours are then studied in a more detail primarily through a manual process. Corrections, if required, are announced to Market Participants within five calendar days of the reservation announcement. This five-day period evolved based on ECAs that were issued under the TEPs during NYISO s early days and was intended to allow sufficient time for weekends, holidays, and staffing requirements. Efforts are on-going to reduce the elapsed time till corrections are posted and the process is being reviewed as part of the SAS70 audit. A review of price correction data from two recent months follows: August 2001 October 2001 Average # of calendar days till correction Average # of business days till correction The higher numbers in August result primarily from mitigation due to thunderstorm alerts requiring a more extensive and detailed review by the analysts. How it is tracked: LECG provides a daily report that includes the number of hours reserved. A separate report details the intervals corrected. The MMP data services section maintains an archive file with data from all the reports and it tracks both the hours reserved and intervals corrected. The monthly figures as well as the cumulative percentages are provided in the NYISO monthly reports. BS&PS input: The BS&PS suggested a goal only for interval price corrections which was similar to last year but with smaller percentages as shown below. NYISO believes the suggested Target and Superior levels to presently be unachievable. 15

16 Threshold Target Superior Intervals Corrected: 0.5 % 0.25 % 0.1 % Comparison to 2001: The 2001 goal is based on intervals corrected as follows: Threshold Target Superior Intervals Corrected: 3.0 % 2.0 % 1.5 % Through September 19, the actual percentage of intervals corrected is 0.48 %, which exceeds the superior level of performance. The actual percentage of hours reserved is %. The graphs below show the 2001 year-to-date cumulative values for real-time price reservations and corrections as well as the proposed 2002 goals. 30% 28% 26% 24% 22% 20% 18% 16% Real-time Hours Reserved Jan Feb Mar Apr May Jun Jul Aug Sep YTD 2001 Cum Threshold 2002 Target 2002 Superior % 0.7% 0.6% 0.5% 0.4% 0.3% 0.2% 0.1% 0.0% Real-time Intervals Corrected Jan Feb Mar Apr May Jun Jul Aug Sep YTD 2001 Cum Threshold 2002 Target 2002 Superior

17 Alternatives: An alternative to the current NYISO proposal is to measure only the intervals corrected, as was recommended by the BS&PS and is the format of the existing 2001 goal. However, to balance reservations/certainty with corrections/accuracy, it is necessary to have both of the countering goals. Alignment with strategic objectives: This incentive goal is aligned with the NYISO strategic objective to be the Premiere Business Model. Responsibility: The Market Monitoring and Performance unit is responsible for tracking and reporting on this goal. LECG is responsible for the day-to-day execution of the price review process. 17

18 7. Improve the Billing and True-up Process How it is tracked: The Customer Settlements department maintains a schedule of invoices to be issued each month and it tracks achievement relative to this schedule. BS&PS input: The BS&PS suggested a goal to issue the true-up bills within three months of original invoices. On-going discussions between Customer Settlements and the Transmission Owners, however, have concluded that a 3-month true-up period cannot be achieved given the existing metering limitations. As an alternative, the true-up intervals were agreed to be 4, 8, 12 and 24 months. Alternatives: The issuance of timely and accurate bills is a high priority issue for the NYISO and its Customers. This incentive goal is deemed to be the most appropriate way to incent the necessary action. Alignment with strategic objectives: This incentive goal is aligned with the NYISO strategic objective to be the Premiere Business Model. Responsibility: The Customer Settlements department is responsible for tracking and reporting on this goal. 18

19 8. Improve Customer Responsiveness with Timely Resolution of Customer Inquiries Definition: The NYISO proposes a goal that will track the timeliness of responses via a Customer response program. Each answer sent to a Customer will include a message asking if the response was provided in a timely manner. The Customer will be able to reply immediately to express an unsatisfactory turn-around time and to identify the time that would have been acceptable. For purposes of tracking this goal, receiving no response from a Customer will be counted as a satisfied result. The proposed incentive goal is as follows: Threshold Target Superior Customer-identified 80 % 85 % 95 % responses that are timely Why this is a challenge: The NYISO operates some of the most complex electricity markets and one of the most congested transmission systems in the country. Many Customer inquiries require extensive review and evaluation of data and on-line systems to explain the mechanisms that affect markets and settlements. For example, during the first nine months of 2001, almost 50 percent of the inquiries tracked were transaction scheduling or billing questions. The Security Constrained Unit Commitment and Billing and Accounting system experts, whose primary responsibilities are running these systems, are often the ones called upon to explain the systems operations in response to these types of Customer inquiries. The time-consuming investigations that are required to address these questions have to be prioritized with dayto-day responsibilities and other special projects. Improving timeliness of responses to Customer inquiries will require a combination of internal process improvements for sharing information, continued improvements in the operation of our markets and transmission system, and further development of expertise across the organization. How it is tracked: Measurement of this goal will be done monthly and reported cumulatively for the year. This goal will be measured on an exception basis, through a modification to the existing Customer Relations Issue Tracking and Resolution system. With every response sent to Customers, a reply button will allow Customers to indicate if they feel their response was not timely. 19

20 This goal will be conservatively calculated, because measurement will only include responses to Customers. Many inquiries are addressed immediately on the telephone by Customer Account Representatives. The Threshold, Target and Superior values currently shown are preliminary values. Benchmarking data will be collected during the remainder of 2001 and as a result these values may need to be adjusted. BS&PS input: The BS&PS suggested there be three defined categories for inquiries and that there be four timing intervals to track responses: <4 hours, <24 hours, <10 days and <20 days. The suggested categories and goals were as follows: Threshold Target Superior Oper./real time In-day 75% <4 hrs 80%<4hrs 90%<4hrs Oper./real time Next day 85% <24 hrs 90%<24hrs 95%<24hrs Billing/analysis 10% <24 hrs 15%<24hrs 20%<24hrs All inquiries 65% <10 days 70%<10days 75%<10days All inquiries 80% <20 days 85%<20days 100%<20days During subsequent discussion with the BS&PS, it was agreed that multiple categories described above would be difficult to implement. The proposed NYISO alternative was considered to be acceptable. Comparison to 2001: The goal for 2001 is as follows: Threshold Target Superior Respond within 10 days 65 % 70 % 75 % Respond within 20 days 80 % 85 % 90 % Through September we have closed 78% of Customer inquiries within ten days and 88% within 20 days. Alternatives: The approach suggested by the BS&PS is complicated and would require development and implementation of an intricate tracking and reporting system. In addition, each inquiry received from Market Participants would require a judgment by Customer Relations to determine which category it should be assigned to. The proposed method of measuring timeliness asking the Market Participants if responses are timely requires that judgment determination to be made by Market Participants. 20

21 Alignment with strategic objectives: This incentive goal is aligned with the NYISO strategic objective to be the Best-in-Class Customer Service. Responsibility: The Customer Relations Department is primarily responsible for tracking and reporting on this goal. Support and commitment is required from the entire organization, however, to prepare the responses that are sent back to Customers. 21

22 9. Improve Customer Satisfaction with NYISO Services Definition: Customer satisfaction will be measured twice in 2002, once each in the Spring and Fall, via web-based surveys that will include all Customers. In 2000 and 2001 only one survey was conducted each year in the Fall. The targeted levels for improvement in overall Customer satisfaction will be as follows: Threshold Target Superior Average score This goal will be evaluated based on the average score achieved on thirty-four individuals survey questions. The improvement in average score will be based on the Fall 2002 survey compared to the Fall 2001 survey. The questions, which are included in the appendices, will be identical in both surveys to ensure consistency. Why achieving a high Customer satisfaction level is a challenge: NYISO Customers have divergent objectives for their participation in the markets and their interactions with the NYISO. On any given issue, the NYISO s responsibility to maintain the viable markets may very likely conflict with one or more of our Customers objectives. Across multiple issues, the NYISO s independent intent and actions to establish a workable competitive marketplace for electricity is likely to dissatisfy many Customers who actively seek to achieve advantages in the marketplace. Also, even with a level playing field, many contracts between parties in the marketplace result in financial winners and losers especially when Locational Based Marginal Prices vary from average levels. Customers who are successful in the marketplace will tend to be satisfied, while those who are not successful will tend to be unsatisfied. Thus, Customer satisfaction levels will always be lower than in industries where Customers do not have opposing interests. In addition, dissatisfaction with determinations made by committees and general unease with frequent changes in the industry is often projected onto the NYISO. How it is tracked: The incentive goal will measure the average score improvement, based on a scale of 1-5, in Customer Satisfaction between the Fall 2002 survey and the 2001 survey. The Spring 2002 survey results will be used to identify areas needing improvement, so that action plans can be developed and implemented to improve Customer Satisfaction and the Fall survey results. 22

23 BS&PS input: The BS&PS suggested that a percentage improvement over the 2001 survey, similar to the previous year, be established once the results of the 2001 survey are known. Comparison to 2001: The first Customer survey conducted in 2000 resulted in an average satisfaction score of 2.82 on a scale of 1-5. The average score achieved on the 2001 survey completed in October was 3.29, which represents a 16.7 % improvement over the 2000 survey. The individual category scores used to determine the average are shown below. Category: 2000 score 2001 score Training Customer Support Web Site Billing Tariffs Communications Average % Increase % Although a 16.7 % improvement was considered by NYISO staff to be a notable accomplishment, this achieves only the threshold level for 2001 goal based on the defined percentage improvement levels as shown below. Threshold Target Superior Average score Percent improvement 10 % 20 % 30 % Alternatives: A number of alternatives were considered in lieu of the approach described above. One option was to develop a Customer Satisfaction Index that would be based on a number of parameters that could be tracked internally by the NYISO. Although this approach has merit, it was not selected for an incentive goal primarily because it is based on an internal NYISO perspective. The Customer Satisfaction Index will, however, be developed in 2002 as a department-level goal. Depending on its effectiveness, it may be considered as an incentive goal for Alignment with strategic objectives: This incentive goal is aligned with the NYISO strategic objective to be the Best-in-Class Customer Service. 23

24 Responsibility: The Market Services Group is responsible for achieving this goal with substantial support from the entire NYISO organization. 24

25 10. Improve Project Management Deliverables with On-time Completion of High Priority Projects Definition: At least monthly, beginning December 2001 and through at least June 2002, the Senior Management Steering Group (SMSG), comprised of the leaders of Market Services, Strategic Planning, Operations, Information Technology, Regulatory Affairs, Finance, and chaired by the Manager of Projects, will meet to select projects that are meaningful to enhance the markets and/or NYISO operations. After June 2002 meetings may be held at a less frequent rate because resources for the year will have been mostly committed. At each meeting, the SMSG will select projects from the NYISO Program Plan that have their detailed functional specifications completed (including the project s description, objectives, deliverable, and resource requirements), and that are scheduled to be completed by December 31, In addition, the SMSG will take into account the priority assigned by the Project Prioritization Team (PPT) on which Market Participants play a key role. Should a selected project no longer be of high priority to the Market or NYISO operations, the SMSG might remove that project from the list. The NYISO s CEO will review the selections for appropriateness. At the first meeting, the SMSG will establish criteria for selecting projects from the Program Plan. Subsequent to that first meeting, every month (i.e., during January, February, March, etc.), the SMSG will again meet to select additional projects that meet the established criteria. Projects may not be selected that are well into their life cycle (and as a result, their successful implementation would be a given ). The incentive goal will be to achieve timely completion of a certain percentage of the high priority projects: Threshold Target Superior Percentage of on-time 80 % 85 % 95 % completion of projects designated by the PPT Why this is a challenge: Achievement of this goal is a challenge first and foremost because of the finite nature of NYISO resources available to accomplish projects and the nearly inexhaustible list of competing needs. This goal recognizes that dichotomy and seeks to reward performance that successfully and predictably applies finite resources to the satisfaction of high priority needs. 25

26 How it is tracked: Progress on this goal will be tracked in accordance with project schedules developed by the respective Project Managers, approved by the Project Sponsor in most cases a NYISO VP or Director, and maintained by the Project Services department. Based on the completion of activities and the achievement of milestones, Project Services will provide reports to the SMSG on the progress of the selected projects in accordance with the projects schedules. The SMSG will be the arbiter to determine whether a project has achieved its stated objective in accordance with its planned schedule. The SMSG may authorize deviations from original deliverables and/or schedules based on overriding circumstances (regulatory, scope expansion, or priority redirection for example). BS&PS input: The BS&PS suggested that the 2001 project management goal be used with the same values for percent completion. They also suggested that a 30 % weighting be applied to this particular goal. The NYISO proposes to weight each of the eight individual incentive goals equally (i.e %). Comparison to 2001: The incentive goal for 2001 is the same as that proposed for Through October 2001 there have been 40 projects identified and 24 have been completed on time. One project has missed its target, and the remaining 15 projects appear on target for successful accomplishment. Alternatives: There were no other alternatives considered. Alignment with strategic objectives: This incentive goal is aligned with the NYISO strategic objective to be the Premiere Business Model. Responsibility: Responsibility for achieving this goal is spread across the entire NYISO as are all of the various projects that make up the NYISO Program Plan. Responsibility for monitoring the success of this goal rests with the Senior Management Steering Group. This concludes the description of individual incentive goals. 26

27 27

Operations Highlights

Operations Highlights Operations Highlights Description Highlights of Operations System Performance. A high-level summary of notable events and update of important operation information not otherwise covered in other Board

More information

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION California Independent System ) Docket Nos. ER12-1630 Operator Corporation ) ER14-971 Informational Report of the California Independent System

More information

Operations Report. Hong Chen Senior Lead Engineer, Markets Coordination Members Committee October 22, PJM 2018

Operations Report. Hong Chen Senior Lead Engineer, Markets Coordination Members Committee October 22, PJM 2018 Operations Report Hong Chen Senior Lead Engineer, Markets Coordination Members Committee October 22, 2018 Forecast Error (Absolute %) Load Forecasting Error (Achieved 80% of the Time) 4.0 3.5 On-Peak Average

More information

Operations Report. Stephanie Monzon Manager, Markets Coordination Operating Committee July 10, PJM 2018

Operations Report. Stephanie Monzon Manager, Markets Coordination Operating Committee July 10, PJM 2018 Operations Report Stephanie Monzon Manager, Markets Coordination Operating Committee July 10, 2018 Forecast Error (Absolute %) Load Forecasting Error (Achieved 80% of the Time) 5.0 4.5 4.0 On-Peak Average

More information

Business Practice Manual for The Transmission Planning Process

Business Practice Manual for The Transmission Planning Process Business Practice Manual for The Transmission Planning Process Posted: June 2, 2015 Intentionally left blank TABLE OF CONTENTS 1. Introduction... 9 1.1. Purpose of California ISO Business Practice Manuals...

More information

Internal NYISO HVDC Controllable Line Scheduling. Concept of Operation. LECG Staff

Internal NYISO HVDC Controllable Line Scheduling. Concept of Operation. LECG Staff ConOp Internal NYISO HVDC Controllable Line Scheduling Concept of Operation Author: Scott Harvey, LECG Reviewers: ISO Staff LECG Staff Project Sponsor: Point of Contact: C. King B. Kranz Document Locator:

More information

2015 Annual Incentive Goals

2015 Annual Incentive Goals 2015 Annual Incentive Goals Budget & Priorities Working Group November 21, 2014 Jennifer Chatt Vice President - Human Resources 2014 New York Independent System Operator, Inc. All Rights DRAFT FOR DISCUSSION

More information

ConOp. Internal NYISO Controllable Lines. Concept of Operation. Scott Harvey, LECG. Document Locator:

ConOp. Internal NYISO Controllable Lines. Concept of Operation. Scott Harvey, LECG. Document Locator: ConOp Internal NYISO Controllable Lines Concept of Operation Author: Reviewers: Scott Harvey, LECG Project Sponsor: Point of Contact: Document Locator: Revision History Date Additions, deletions, modifications

More information

Energy Marketplace. Nicolé K. Grottoli. Market Overview Course. Senior Market Trainer, Market Training, NYISO. March 8, 2018 Rensselaer, NY 12144

Energy Marketplace. Nicolé K. Grottoli. Market Overview Course. Senior Market Trainer, Market Training, NYISO. March 8, 2018 Rensselaer, NY 12144 Energy Marketplace Nicolé K. Grottoli Senior Market Trainer, Market Training, NYISO Market Overview Course March 8, 2018 Rensselaer, NY 12144 1 NYISO Energy Marketplace Benefits to Understanding How is

More information

Wind Update. Renewable Energy Integration Lessons Learned. March 28, 2012

Wind Update. Renewable Energy Integration Lessons Learned. March 28, 2012 Wind Update Renewable Energy Integration Lessons Learned March 28, 212 Contents Summary Review of Historical Wind Growth and Output Impact of Wind on Operations Wind Curtailments Dispatchable Intermittent

More information

Operations Report. Stephanie Monzon Manager, Markets Coordination MC Webinar January 22, PJM 2018

Operations Report. Stephanie Monzon Manager, Markets Coordination MC Webinar January 22, PJM 2018 Operations Report Stephanie Monzon Manager, Markets Coordination MC Webinar January 22, 2019 Forecast Error (Absolute %) Load Forecasting Error (Achieved 80% of the Time) 4.0 3.5 On-Peak Average Off-Peak

More information

REAL-TIME SCHEDULING PRIMER

REAL-TIME SCHEDULING PRIMER REAL-TIME SCHEDULING PRIMER Introduction System Market Design 2 (SMD2) is name given to a New York Independent System Operator (NYISO) program that replaces the NYISO s legacy control and computing platforms

More information

Pay for Performance Regulation Year 1 Design Changes. Draft Final Proposal

Pay for Performance Regulation Year 1 Design Changes. Draft Final Proposal Pay for Performance Regulation Year 1 Design Changes Draft Final Proposal September 26, 2014 Pay for Performance Regulation Year 1 Design Changes Draft Final Proposal Table of Contents 1 Introduction...

More information

Delivery From Off Dispatch Units Into the Real-Time Market

Delivery From Off Dispatch Units Into the Real-Time Market FERC Directive on Off-Dispatch Generation Issue Delivery From Off Dispatch Units Into the Real-Time Market ISSUE: Current NYISO rules prohibit offdispatch units from being paid for making deliveries into

More information

California ISO. Q Report on Market Issues and Performance. February 10, Prepared by: Department of Market Monitoring

California ISO. Q Report on Market Issues and Performance. February 10, Prepared by: Department of Market Monitoring California Independent System Operator Corporation California ISO Q4 2013 Report on Market Issues and Performance February 10, 2014 Prepared by: Department of Market Monitoring Department of Market Monitoring

More information

Virtual Workshop on PJM ARR and FTR Market 2017/2018

Virtual Workshop on PJM ARR and FTR Market 2017/2018 Virtual Workshop on PJM ARR and FTR Market 2017/2018 PJM State & Member Training Dept. Webex February 10, 2017 PJM 2017 Disclaimer: PJM has made all efforts possible to accurately document all information

More information

Section 3 Characteristics of Credits Types of units. Economic Noneconomic Generation.

Section 3 Characteristics of Credits Types of units. Economic Noneconomic Generation. Section 3 Operating Reserve Operating Reserve Day-ahead and real-time operating reserve credits are paid to market participants under specified conditions in order to ensure that resources are not required

More information

Energy Uplift (Operating Reserves)

Energy Uplift (Operating Reserves) Section 4 Energy Uplift Energy Uplift (Operating Reserves) Energy uplift is paid to market participants under specified conditions in order to ensure that resources are not required to operate for the

More information

3.2 Market Settlements.

3.2 Market Settlements. 3.2 Market Settlements. If a dollar-per-mw-hour value is applied in a calculation under this section 3.2 where the interval of the value produced in that calculation is less than an hour, then for purposes

More information

2001 Annual Report on the New York Electricity Markets

2001 Annual Report on the New York Electricity Markets 2001 Annual Report on the New York Electricity Markets Presented to: New York ISO Management Committee David B. Patton, Ph.D. Independent Market Advisor April 16, 2002 Conclusions and Recommendations The

More information

Resource Adequacy Enhancements Straw Proposal - Part 1. Stakeholder Call January 23, 2019

Resource Adequacy Enhancements Straw Proposal - Part 1. Stakeholder Call January 23, 2019 Resource Adequacy Enhancements Straw Proposal - Part 1 Stakeholder Call January 23, 2019 Agenda Time Topic Presenter 1:00 1:10PM Welcome and introduction Jody Cross 1:10 1:40PM Rules for Import RA Chris

More information

California ISO 2009 Annual Report on Market Issues and Performance

California ISO 2009 Annual Report on Market Issues and Performance California Independent System Operator Corporation California ISO 2009 Annual Report on Market Issues and Performance Special Revised Executive Summary June 30, 2010 Prepared by: Department of Market Monitoring

More information

the Real-Time Market will be based on the system marginal costs produced by the Real-Time

the Real-Time Market will be based on the system marginal costs produced by the Real-Time 17.1 LBMP Calculation The Locational Based Marginal Prices ( LBMPs or prices ) for Suppliers and Loads in the Real-Time Market will be based on the system marginal costs produced by the Real-Time Dispatch

More information

California Independent System Operator Corporation. California ISO. Import resource adequacy. Department of Market Monitoring

California Independent System Operator Corporation. California ISO. Import resource adequacy. Department of Market Monitoring k California Independent System Operator Corporation California ISO Import resource adequacy September 10, 2018 Department of Market Monitoring Summary This report provides an update of analysis and trends

More information

Ancillary Service Markets

Ancillary Service Markets Section 9 Ancillary Services Ancillary Service Markets The United States Federal Energy Regulatory Commission (FERC) defined six ancillary services in Order No. 888: 1) scheduling, system control and dispatch;

More information

Flexible Resource Adequacy Criteria and Must Offer Obligation Phase 2. Second Revised Flexible Capacity Framework

Flexible Resource Adequacy Criteria and Must Offer Obligation Phase 2. Second Revised Flexible Capacity Framework Flexible Resource Adequacy Criteria and Must Offer Obligation Phase 2 April 27, 2018 Table of Contents 1. Executive Summary... 3 2. Stakeholder Comments on Draft Flexible Capacity Framework... 5 3. Stakeholder

More information

the Real-Time Market will be based on the system marginal costs produced by the Real-Time

the Real-Time Market will be based on the system marginal costs produced by the Real-Time 17.1 LBMP Calculation The Locational Based Marginal Prices ( LBMPs or prices ) for Suppliers and Loads in the Real-Time Market will be based on the system marginal costs produced by the Real-Time Dispatch

More information

Capacity Performance FAQ Response

Capacity Performance FAQ Response PJM Interconnection September 15, 2014 This page is intentionally left blank. PJM 2014 www.pjm.com 2 P age Contents FAQ Response Introduction... 4 Capacity Products... 4 Methodology for Establishing Maximum

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination of Ancillary Service Standards... 4 8.2.2 Time-Frame for Revising Ancillary Service

More information

Compliance Analysis Report FAC Facilities Ratings Methodology FAC Establish and Communicate Facility Ratings

Compliance Analysis Report FAC Facilities Ratings Methodology FAC Establish and Communicate Facility Ratings Compliance Analysis Report FAC-008-1 Facilities Ratings Methodology FAC-009-1 Establish and Communicate Facility Ratings February 19, 20 Background The NERC Board of Trustees Compliance Committee (BOTCC)

More information

ERCOT Public LTRA Probabilistic Reliability Assessment. Final Report

ERCOT Public LTRA Probabilistic Reliability Assessment. Final Report ERCOT Public 2016 LTRA Probabilistic Reliability Assessment Final Report November 21, 2016 Contents Summary... 1 Software Model Description... 3 Demand Modeling... 3 Controllable Capacity Demand Response

More information

California ISO. Structural competitiveness of the energy imbalance market: Arizona Public Service Balancing Area. April 10, 2018

California ISO. Structural competitiveness of the energy imbalance market: Arizona Public Service Balancing Area. April 10, 2018 California Independent System Operator Corporation California ISO Structural competitiveness of the energy imbalance market: Arizona Public Service Balancing Area April 10, 2018 Department of Market Monitoring

More information

Ancillary Service Markets

Ancillary Service Markets Section 9 Ancillary Services Ancillary Service Markets The United States Federal Energy Regulatory Commission (FERC) defined six ancillary services in Order No. 888: 1) scheduling, system control and dispatch;

More information

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

California Independent System Operator Corporation Fifth Replacement Electronic Tariff Table of Contents California Independent System Operator Corporation 8. Ancillary Services... 3 8.1 Scope... 3 8.2 Ancillary Services Standards... 4 8.2.1 Determination Of Ancillary Service Standards...

More information

Unleashing the Enormous Power of Call Center KPI s. Call Center Best Practices Series

Unleashing the Enormous Power of Call Center KPI s. Call Center Best Practices Series Unleashing the Enormous Power of Call Center KPI s Call Center Best Practices Series 27 Years of Call Center Benchmarking Data Global Database More than 3,700 Call Center Benchmarks 30 Key Performance

More information

Wastewater Audit Follow-up

Wastewater Audit Follow-up Wastewater Audit Follow-up Jed Johnson, CGAP City Auditor Prepared by Pamela Asbell, CIA Sr. Auditor June 23, 2014 Report 201475 Table of Contents Page Authorization... 1 Objective... 1 Scope and Methodology...

More information

3.2 Market Buyers Spot Market Energy Charges.

3.2 Market Buyers Spot Market Energy Charges. 3.2 Market Buyers. 3.2.1 Spot Market Energy Charges. (a) The Office of the Interconnection shall calculate System Energy Prices in the form of Day-ahead System Energy Prices and Real-time System Energy

More information

Pricing Logic Under Flexible Modeling of Constrained Output Generating Units

Pricing Logic Under Flexible Modeling of Constrained Output Generating Units Draft Final Proposal Pricing Logic Under Flexible Modeling of Constrained Output Generating Units April 14, 2008 This is the third CAISO paper on this issue. An Issue Paper was posted on February 1, 2008

More information

Congestion and Marginal Losses

Congestion and Marginal Losses Section 10 Congestion and Marginal Losses Congestion and Marginal Losses The Locational Marginal Price (LMP) is the incremental price of energy at a bus. The LMP at any bus is made up of three components:

More information

2018 DRAFT Annual Incentive Goals

2018 DRAFT Annual Incentive Goals 2018 DRAFT Annual Incentive Goals Emilie Nelson VP MARKET OPERATIONS, NYISO Budget & Priorities Working Group November 2, 2017. Krey Corporate Center, Rensselaer, NY. Agenda Background Objectives Structural

More information

The Texas Experience: Implications of 8,000+ MW Wind Generation Resources In ERCOT. David Campbell CEO, Luminant 2009 Summer Seminar August 3, 2009

The Texas Experience: Implications of 8,000+ MW Wind Generation Resources In ERCOT. David Campbell CEO, Luminant 2009 Summer Seminar August 3, 2009 The Texas Experience: Implications of 8,000+ MW Wind Generation Resources In ERCOT David Campbell CEO, Luminant 2009 Summer Seminar August 3, 2009 Growth of Wind Generation in ERCOT MW 12,000 10,000 8,000

More information

Flexible Resource Adequacy Criteria and Must Offer Obligation Working Group Meeting

Flexible Resource Adequacy Criteria and Must Offer Obligation Working Group Meeting Flexible Resource Adequacy Criteria and Must Offer Obligation Working Group Meeting Karl Meeusen, Ph.D. September 26, 2017 2017 CAISO - Public Page 1 FRACMOO 2 Working Group Meeting Agenda 9/26/2017 Time

More information

FINAL REPORT PHASE IV MARKET TRIALS

FINAL REPORT PHASE IV MARKET TRIALS October 26, 1999 FINAL REPORT PHASE IV MARKET TRIALS Scott M. Harvey, William W. Hogan, Susan L. Pope, Andrew Hartshorn and Kurt Zala EXECUTIVE SUMMARY On behalf of the Member Systems of the New York Power

More information

Storage as a Transmission Asset:

Storage as a Transmission Asset: Storage as a Transmission Asset: Enabling storage assets providing regulated cost-ofservice-based transmission service to access market revenues Straw Proposal Karl Meeusen, Ph.D. Stakeholder Meeting May

More information

CHAPTER 6 - Load Forecast & Resource Plan

CHAPTER 6 - Load Forecast & Resource Plan CHAPTER 6 - Load Forecast & Resource Plan Introduction This Chapter describes the electric resource portfolio that may be acquired to meet the energy requirements of MBCP customers. The following overarching

More information

2017 Project Prioritization & Budgeting Process

2017 Project Prioritization & Budgeting Process 2017 Project Prioritization & Budgeting Process Ryan Smith Senior Manager Budget & Priorities Working Group June 24, 2016 Krey Corporate Center 2000-2016 New York Independent System Operator, Inc. All

More information

SETTLEMENT ESTIMATION AND REVISIONS POLICY CONSULTATION PAPER. AeN 94 on Oh) 327 Wv'IW.oemo.oo m.ou infofffoemo.corr.ou VERSION: 1. DATE: 4 April 2012

SETTLEMENT ESTIMATION AND REVISIONS POLICY CONSULTATION PAPER. AeN 94 on Oh) 327 Wv'IW.oemo.oo m.ou infofffoemo.corr.ou VERSION: 1. DATE: 4 April 2012 SETTLEMENT ESTIMATION AND REVISIONS POLICY CONSULTATION PAPER PREPARED BY: Market Performance VERSION: 1 DATE: 4 April 2012 FINAL Am,ttolion l:nergy 1\_.n,ketOpe rctor Ltd AeN 94 on Oh) 327 Wv'IW.oemo.oo

More information

Future Market Implementation

Future Market Implementation SPP.org 1 Future Market Implementation Requirements - way forward MWG June 29 th, 2009 SPP.org WebEx Instructions Please submit questions to host. If it is a long question you can type a summary until

More information

Energy Uplift (Operating Reserves)

Energy Uplift (Operating Reserves) Section 4 Energy Uplift Energy Uplift (Operating Reserves) Energy uplift is paid to market participants under specified conditions in order to ensure that resources are not required to operate for the

More information

Broader Regional Markets

Broader Regional Markets Attachment B Broader Regional Markets, Long-Term Solutions to Lake Erie Loop Flow Slide Presentation from the December 15, 2009 Technical Conference Held in Carmel, Indiana LAKE SUPERIOR LAKE SUPERIOR

More information

Wholesale Electricity Markets. New England Independent System Operator. Commissioner Mark Vannoy Maine Public Utilities Commission

Wholesale Electricity Markets. New England Independent System Operator. Commissioner Mark Vannoy Maine Public Utilities Commission Wholesale Electricity Markets and New England Independent System Operator Commissioner Mark Vannoy Maine Public Utilities Commission March 26, 2014 Overview and Background 2 Wholesale Electricity Markets

More information

Reliability Pricing Model (RPM) DRAFT Business Rules

Reliability Pricing Model (RPM) DRAFT Business Rules Definition and Purpose of Reliability Pricing Model (RPM) 1. The purpose of the RPM is to develop a long term pricing signal for capacity resources and LSE obligations that is consistent with the PJM Regional

More information

A REPORT FROM THE OFFICE OF INTERNAL AUDIT

A REPORT FROM THE OFFICE OF INTERNAL AUDIT A REPORT FROM THE OFFICE OF INTERNAL AUDIT PRESENTED TO THE CITY COUNCIL CITY OF BOISE, IDAHO AUDIT / TASK: #11-09 S2, P-Card Purchasing Review AUDIT CLIENT: DFA / Cross-Functional REPORT DATE: December

More information

Design Services Assessment Report, 2013

Design Services Assessment Report, 2013 Design Services Assessment Report, 2013 1. Expected Outcome: Improve Communication Clients and stakeholders will be satisfied with communication efforts and therefore will be better informed about project

More information

New York Independent System Operator, Inc. NYISO Tariffs. OATT Schedules

New York Independent System Operator, Inc. NYISO Tariffs. OATT Schedules New York Independent System Operator, Inc. NYISO Tariffs OATT Schedules Document Generated On: 6/30/2010 Page 1 Contents 6 Schedules... 7 6.1 Schedule 1 Scheduling, System Control and Dispatch Service...

More information

Review of Interconnection Assistance Reliability Benefits. May 12, NPCC CP-5 Working Group

Review of Interconnection Assistance Reliability Benefits. May 12, NPCC CP-5 Working Group Review of Interconnection Assistance Reliability Benefits May 12, 1999 NPCC CP-5 Working Group NORTHEAST POWER COORDINATING COUNCIL WORKING GROUP CP-5 REVIEW OF INTERCONNECTION ASSISTANCE RELIABILITY BENEFITS

More information

Day Ahead Market Enhancements: Issue Paper/Straw Proposal

Day Ahead Market Enhancements: Issue Paper/Straw Proposal Day Ahead Market Enhancements: Issue Paper/Straw Proposal Don Tretheway Senior Advisor, Market Design Policy Megan Poage Senior Market Design & Regulatory Policy Developer March 7, 2018 Agenda Time Topic

More information

MARKET MATTERS HVDC UTILISATION REPORT OCTOBER 2018

MARKET MATTERS HVDC UTILISATION REPORT OCTOBER 2018 HVDC Utilisation In late 2016 we published a report covering what restricts HVDC north transfer 1. We are now publishing monthly updates on the market aspects that restricted HVDC north transfer, and some

More information

Demand Response. Mathangi Srinivasan. New York Market Orientation Course (NYMOC) Senior Market Trainer, NYISO. March 20-23, 2018 Rensselaer, NY 12144

Demand Response. Mathangi Srinivasan. New York Market Orientation Course (NYMOC) Senior Market Trainer, NYISO. March 20-23, 2018 Rensselaer, NY 12144 Demand Response Mathangi Srinivasan Senior Market Trainer, NYISO New York Market Orientation Course (NYMOC) March 20-23, 2018 Rensselaer, NY 12144 1 Demand Response Module Objectives Upon completion of

More information

NSPM Rate Design Pilot

NSPM Rate Design Pilot NSPM Rate Design Pilot Stakeholder Meeting May 5, 2017 Agenda and Purpose Agenda Introduction of MN Pilot Development A. Liberkowski Concept and Goals Pilot Development Timeline MN Time of Use Rate Option

More information

Impact of Convergence Bidding on Interties. Draft Final Proposal

Impact of Convergence Bidding on Interties. Draft Final Proposal Impact of Convergence Bidding on Interties Draft Final Proposal July 29, 2011 Impact of Convergence Bidding on Interties Table of Contents 1 Introduction... 3 2 Plan for Stakeholder Engagement... 3 3 Issue

More information

Traffic Division Public Works Department Anchorage: Performance. Value. Results.

Traffic Division Public Works Department Anchorage: Performance. Value. Results. Mission Promote safe and efficient area-wide transportation that meets the needs of the community and the Anchorage Municipal Traffic Code requirements. Direct Services Design, operate and maintain the

More information

PJM ARR and FTR Market

PJM ARR and FTR Market PJM ARR and FTR Market PJM State & Member Training Dept. PJM 2017 Objectives At the completion of this training, you should be able to describe the concepts and principles of Auction Revenue Rights and

More information

Final Flexible Capacity Needs Assessment for 2018

Final Flexible Capacity Needs Assessment for 2018 Final Flexible Capacity Needs Assessment for 2018 April 28, 2017 1 Table of Contents 1. Introduction... 3 2. Summary... 3 3. Defining the ISO System-Wide Flexible Capacity Need... 5 4. Forecasting Minute-by-Minute

More information

Flexible Resource Adequacy Criteria and Must-Offer Obligation

Flexible Resource Adequacy Criteria and Must-Offer Obligation Flexible Resource Adequacy Criteria and Must-Offer Obligation February 13, 2014 Karl Meeusen, Ph.D. Market Design and Regulatory Policy Lead Stakeholder Meeting Agenda 2/13/14 Time Topic Presenter 12:30

More information

Wheaton Precious Metals Corp. Board Manual Tab B-2 TERMS OF REFERENCE FOR THE HUMAN RESOURCES COMMITTEE

Wheaton Precious Metals Corp. Board Manual Tab B-2 TERMS OF REFERENCE FOR THE HUMAN RESOURCES COMMITTEE I. PURPOSE The Human Resources Committee (the Committee ) is established by the Board of Directors (the Board ) of Wheaton Precious Metals Corp. (the Company ) to assist the Board in fulfilling its responsibilities

More information

Business Practice Energy Imbalance Market (EIM BP) Revision Number: Revision Date: November 30July 29, 2015

Business Practice Energy Imbalance Market (EIM BP) Revision Number: Revision Date: November 30July 29, 2015 Revision Number: 3.02.1 Revision Date: November 30July 29, 2015 Revision Log 0.0 3/31/15 Pre-market initial draft 1.0 5/15/15 Email and phone contacts, Sections 3, 7, 8, 9, 11 and Appendix A for participating

More information

Overview Of PJM Demand Response and Energy Efficiency. Issues September 22, Susan Covino, Senior Consultant Market Strategy

Overview Of PJM Demand Response and Energy Efficiency. Issues September 22, Susan Covino, Senior Consultant Market Strategy Overview Of PJM Demand Response and Energy Efficiency MARAMA Workshop on Energy and Air Quality Issues September 22, 2008 Susan Covino, Senior Consultant Market Strategy Energy price incentive changes

More information

Limited Energy Storage Resource (LESR) Market Integration Update

Limited Energy Storage Resource (LESR) Market Integration Update Limited Energy Storage Resource (LESR) Market Integration Update John Hickey Product Business Analyst Energy Markets New York Independent System Operator Market Issues working Group November 3, 2008 1

More information

Business Practice Manual for Reliability Requirements. Version 34

Business Practice Manual for Reliability Requirements. Version 34 Business Practice Manual for Reliability Requirements Version 34 Last Revised: January 1, 2009July 28, 2010 Approval History Approval Date: 3/27/09 Effective Date: 3/31/09 BPM Owner: Chetty Mamandur BPM

More information

Congestion and Marginal Losses

Congestion and Marginal Losses Section 11 Congestion and Marginal Losses Congestion and Marginal Losses The locational marginal price (LMP) is the incremental price of energy at a bus. The LMP at a bus is made up of three components:

More information

FINAL SETTLEMENT CHALLENGES POLICY AND PROCEDURE

FINAL SETTLEMENT CHALLENGES POLICY AND PROCEDURE May 8, 2002 BAWG Conference Call FINAL SETTLEMENT CHALLENGES POLICY AND PROCEDURE The NYISO tariffs provide Market Participants with a twelve-month time frame after the issuance of final billing invoices

More information

Portland General Electric Company First Revision of Sheet No P.U.C. Oregon No. E-18 Canceling Original Sheet No. 26-1

Portland General Electric Company First Revision of Sheet No P.U.C. Oregon No. E-18 Canceling Original Sheet No. 26-1 First Revision of Sheet No. 26-1 P.U.C. Oregon No. E-18 Canceling Original Sheet No. 26-1 PURPOSE SCHEDULE 26 NONRESIDENTIAL DEMAND RESPONSE PILOT PROGRAM This schedule is an optional supplemental service

More information

Design Services Assessment Report, 2012

Design Services Assessment Report, 2012 Design Services Assessment Report, 2012 1. Expected Outcome: Improve Communication Clients and stakeholders will be satisfied with communication efforts and therefore will be better informed about project

More information

2018 Draft Policy Initiatives Roadmap. Market and Infrastructure Policy December 7, 2017

2018 Draft Policy Initiatives Roadmap. Market and Infrastructure Policy December 7, 2017 2018 Draft Policy Initiatives Roadmap Market and Infrastructure Policy December 7, 2017 Primary drivers of proposed three-year roadmap Recent grid operations challenges pointing to need for day-ahead market

More information

ConOp. Real-Time Scheduling Concept of Operation 1 MSWG. Document Locator: Revision History. Additions, deletions, modifications

ConOp. Real-Time Scheduling Concept of Operation 1 MSWG. Document Locator: Revision History. Additions, deletions, modifications ConOp Real-Time Scheduling Concept of Operation 1 Author: NYISO Staff Reviewers: NYISO Staff MSWG Project Sponsor: Point of Contact: Document Locator: Revision History Date Additions, deletions, modifications

More information

Load Shift Working Group. https://gridworks.org/initiatives/load-shift-working-group/

Load Shift Working Group. https://gridworks.org/initiatives/load-shift-working-group/ Load Shift Working Group APRIL 18 10AM 2PM PST CPUC GOLDEN GATE ROOM https://gridworks.org/initiatives/load-shift-working-group/ Agenda 10:00 10:20am: Intro and Purpose (Gridworks) 10:20 12:00pm: Grid

More information

People will support that which they help to create. -- Mary Kay Ash --

People will support that which they help to create. -- Mary Kay Ash -- 1 People will support that which they help to create -- Mary Kay Ash -- 2 Team Committee-Based Safety System EnPro Learning System is powered by individuals throughout EnPro Industries. Our safety system

More information

Resource Adequacy Enhancements. Straw Proposal Part 1

Resource Adequacy Enhancements. Straw Proposal Part 1 Resource Adequacy Enhancements Straw Proposal Part 1 December 20, 2018 Table of Contents 1. Executive Summary... 3 2. Introduction and Background... 4 3. Stakeholder Engagement Plan... 6 4. Straw Proposal

More information

A REPORT FROM THE OFFICE OF INTERNAL AUDIT

A REPORT FROM THE OFFICE OF INTERNAL AUDIT A REPORT FROM THE OFFICE OF INTERNAL AUDIT PRESENTED TO THE CITY COUNCIL CITY OF BOISE, IDAHO AUDIT / TASK: #18-06, P-Card Program Review AUDIT CLIENT: Purchasing / Cross-Functional REPORT DATE: September

More information

Demand Response. Overview. Recommendations

Demand Response. Overview. Recommendations Section 6 Demand Response Demand Response Markets require both a supply side and a demand side to function effectively. The demand side of wholesale electricity markets is underdeveloped. Wholesale power

More information

Self-Schedules Bid Cost Recovery Allocation and Lower Bid Floor

Self-Schedules Bid Cost Recovery Allocation and Lower Bid Floor Summary Self-Schedules Bid Cost Recovery Allocation and Lower Bid Floor Draft Final Proposal Comments by Department of Market Monitoring August 23, 2016 The ISO proposal to lower the energy bid floor from

More information

Accelerating the Whiteshell Laboratories Decommissioning Through the Implementation of a Projectized and Delivery-Focused Organization 13074

Accelerating the Whiteshell Laboratories Decommissioning Through the Implementation of a Projectized and Delivery-Focused Organization 13074 Accelerating the Whiteshell Laboratories Decommissioning Through the Implementation of a Projectized and Delivery-Focused Organization 13074 Brian Wilcox, Russ Mellor and Craig Michaluk Atomic Energy of

More information

HOUSE OF REPRESENTATIVES KNOTT COMMITTEE ROOM 116 OCTOBER 24, 2018

HOUSE OF REPRESENTATIVES KNOTT COMMITTEE ROOM 116 OCTOBER 24, 2018 HOUSE OF REPRESENTATIVES KNOTT COMMITTEE ROOM 116 OCTOBER 24, 2018 3 FACILITATOR: MELISSA TURNER 4 FACILITATOR: MELISSA TURNER 5 FACILITATORS: DAYMON JENSEN, RACHAEL LIEBLICK, MELISSA TURNER Budget FY

More information

Fundamentals of Transmission Operations

Fundamentals of Transmission Operations Fundamentals of Transmission Operations Equipment Outages PJM State & Member Training Dept. Objectives At the end of this presentation the Learner will be able to: Identify how weather may influence outage

More information

Price Validation of Energy and Ancillary Markets

Price Validation of Energy and Ancillary Markets Price Validation of Energy and Ancillary Markets Mathangi Srinivasan Senior Market Trainer, NYISO New York Market Orientation Course (NYMOC) October 16-19, 2018 Rensselaer, NY 1 Session Objectives Upon

More information

ENERGY IMBALANCE MARKET BUSINESS PRACTICE ( EIM BP ) TABLE OF CONTENTS 1. Introduction 2. Communication with the PSEI EIM Entity 3.

ENERGY IMBALANCE MARKET BUSINESS PRACTICE ( EIM BP ) TABLE OF CONTENTS 1. Introduction 2. Communication with the PSEI EIM Entity 3. ENERGY IMBALANCE MARKET BUSINESS PRACTICE ( EIM BP ) TABLE OF CONTENTS 1. Introduction 2. Communication with the PSEI EIM Entity 3. PSEI EIM Participating Resource Application and Processing 3.1 Application

More information

Reliability Assurance Initiative. Sonia Mendonca, Associate General Counsel and Senior Director of Enforcement

Reliability Assurance Initiative. Sonia Mendonca, Associate General Counsel and Senior Director of Enforcement Reliability Assurance Initiative Sonia Mendonca, Associate General Counsel and Senior Director of Enforcement Agenda Reliability Assurance Initiative (RAI) Overview 2015 ERO CMEP Implementation Plan Inherent

More information

Generation Desk Logging

Generation Desk Logging 1. Provides guidelines for the different logging scenarios used by the Generation Dispatcher. Caution: Since Settlements reconciles and/or is supported by data from these entries, accurate and detailed

More information

Electric Forward Market Report

Electric Forward Market Report Mar-01 Mar-02 Jun-02 Sep-02 Dec-02 Mar-03 Jun-03 Sep-03 Dec-03 Mar-04 Jun-04 Sep-04 Dec-04 Mar-05 May-05 Aug-05 Nov-05 Feb-06 Jun-06 Sep-06 Dec-06 Mar-07 Jun-07 Sep-07 Dec-07 Apr-08 Jun-08 Sep-08 Dec-08

More information

Residual imbalance energy settlement and ramp rate changes for self-scheduled variable energy resources

Residual imbalance energy settlement and ramp rate changes for self-scheduled variable energy resources Market Issues Bulletin Residual imbalance energy settlement and ramp rate changes for self-scheduled variable energy resources March 10, 2015 www.caiso.com 250 Outcropping Way, Folsom, CA 95630 916.351.4400

More information

STANDARDS OF CONDUCT IMPLEMENTATION AND COMPLIANCE. Standards of Conduct for Transmission Providers Pursuant to FERC Order No. 717

STANDARDS OF CONDUCT IMPLEMENTATION AND COMPLIANCE. Standards of Conduct for Transmission Providers Pursuant to FERC Order No. 717 STANDARDS OF CONDUCT IMPLEMENTATION AND COMPLIANCE Standards of Conduct for Transmission Providers Pursuant to FERC Order No. 717 In compliance with Chapter I, Title 18, Part 358 of the Code of Federal

More information

CO2, SO2 and NOX Emission Rates. March 15, 2018

CO2, SO2 and NOX Emission Rates. March 15, 2018 March 15, 2018 This page is intentionally left blank. PJM 2018 www.pjm.com 1 P age Introduction To support the efforts of regulators, stakeholders, and other interested parties as they work towards achieving

More information

Capital project planning, design, delivery and operation process review City of Nanaimo November 20, 2017

Capital project planning, design, delivery and operation process review City of Nanaimo November 20, 2017 Capital project planning, design, delivery and operation process review City of Nanaimo November 20, 2017 Background Deloitte s Scope Conduct a review of the City s project planning, design, delivery and

More information

Influence of Natural Gas Price and Other Factors on ISO-NE Electricity Price

Influence of Natural Gas Price and Other Factors on ISO-NE Electricity Price Influence of Natural Gas Price and Other Factors on ISO-NE Electricity Price Final Report for Undergraduate Research Opportunities Program Prepared by: Christiane Adcock, Milos Cvetkovic, Anuradha Annaswamy

More information

Locational Based Marginal Pricing

Locational Based Marginal Pricing Locational Based Marginal Pricing Gina Craan Manager, Market Training, NYISO Market Overview Course March 8, 2018 Rensselaer, NY 12144 1 Locational Based Marginal Pricing Attendees will be able to Explain

More information

PJM ENERGY PRICES 2005 Response to Howard M. Spinner Paper

PJM ENERGY PRICES 2005 Response to Howard M. Spinner Paper PJM ENERGY PRICES 2005 Response to Howard M. Spinner Paper Joseph Bowring PJM Market Monitor Response to Howard M. Spinner Paper Re: PJM Energy Prices 2005 A March 13, 2006 paper ( Spinner paper ) by Howard

More information

SECTION 6 - ANCILLARY SERVICE MARKETS

SECTION 6 - ANCILLARY SERVICE MARKETS 2010 Quarterly State of the Market Report for PJM: January through March ANCILLARY SERVICES 6 SECTION SECTION 6 - ANCILLARY SERVICE MARKETS The United States Federal Energy Regulatory Commission (FERC)

More information

Congestion and Marginal Losses

Congestion and Marginal Losses Section 10 Congestion and Marginal Losses Congestion and Marginal Losses The Locational Marginal Price (LMP) is the incremental price of energy at a bus. The LMP at a bus is made up of three components:

More information