Regulatory Review PHMSA Regulatory Update. Tom Finch Western Region CATS Manager

Size: px
Start display at page:

Download "Regulatory Review PHMSA Regulatory Update. Tom Finch Western Region CATS Manager"

Transcription

1 Regulatory Review PHMSA Regulatory Update Tom Finch Western Region CATS Manager

2 Rulemaking Process ANPRM Advance Notice of Proposed Rulemaking Used to gather information (non-mandatory) NPRM Notice of Proposed Rulemaking Almost always required Defines intent and scope SNPRM Supplemental Notice of Proposed Rulemaking

3 Rulemaking Process FR Final Rule Implementation date, days depending on significance of regulation DFR Direct Final Rule Used for non-controversial issues

4 Final Rule Amendment , August 11, 2010 Updates to Referenced Technical Standards and Miscellaneous Edits Updated some incorporated by reference documents Moved and added definitions Changes to Subpart F Joining by other than Welding Transmission repair procedures IM clarifications

5 Final Rule Amendment , November 25, 2010 Updates to Pipeline and LNG Reporting Requirements Incident definition IM reporting requirements Operator ID numbers

6 ANPRM August 25, 2011 Safety of Gas Transmission Pipelines Requested comments regarding some changes to Integrity Management (IM) requirements, including: HCA definitions ILI requirements Modifying repair criteria Proscriptive requirements for data integration

7 ANPRM November 25, 2011 Expanding the Use of Excess Flow Valves in Gas Distribution Systems to Applications Other Than Single- Family Residences Practicable to implement? Cost factors Use of technical standards and guidance for EFVs

8 NPRM November 29, 2011 Miscellaneous Changes to Pipeline Safety Regulations National Pipeline Mapping System Welding and Welding Operator Definitions Welding and welding operator procedures, qualifications and weld inspection and testing Plastic pipe qualifications (15 months) Construction inspection by person not involved in construction

9 NPRM November 29, 2011 Miscellaneous Changes to Pipeline Safety Regulations Changes to Subpart J, testing requirements Clarification of lateral definition for odorization requirements Alternate MAOP changes

10 NPRM April 2, 2012 Pipeline Damage Prevention Programs Establish criteria and procedures for determining the adequacy of state pipeline excavation damage prevention law enforcement programs Comments due by 7/9/12 Comments under review NPRM being developed

11 NPRM August 13, 2012 Proposed Changes to 190 Pipeline Safety Programs Changes include increases in both civil and criminal penalties, investigations, response options, hearings, addresses and contact information, and other administrative procedures.

12 December 5, 2012 Letter Director, Office of Secretary of Transportation, Office of Drug and Alcohol Policy and Compliance Department of Transportation State initiatives have no bearing on the Department of Transportation s regulated drug testing program. The Department of Transportation s Drug and Alcohol Testing Regulation 49 CFR Part 40 does not authorize the use of Schedule I drugs, including marijuana, for any reason

13 Notice January 28, 2013 Annual Reports, OpID Validation, and Supplemental Reports Changes to gas, hazardous liquid and LNG Annual Report Forms approved 12/5/12 Extending filing deadline to June 15, 2013 Online data entry enabled no later than March 1, 2013

14 Notice January 28, 2013 Annual Reports, OpID Validation, and Supplemental Reports 49 CFR and required operators to validate data on file with PHMSA by September 30, 2013

15 Notice, February 6, 2013 Revision to Annual Report for Hazardous Liquid Pipeline Systems Part 195 Comments submitted by April 6, 2013 Notice, February 13, 2013 Revision to Gas Distribution Annual Report Part 191 Comments submitted by April 15, 2013

16 Notice of Proposed Rulemaking August 1, 2013 Public comment on applying Class locations and IMP requirements beyond HCAs Add class locations Eliminate class locations and design factors Testing of transmission pipelines Repairs of transmission pipeline Comments under review

17 Final Rule issued January 5,2015 Periodic Updates of Regulatory References to Technical Standards and Miscellaneous Amendments Updated 21 editions of currently referenced standards in Parts 192, 193, and 195 Changing IBR from table to list Miscellaneous edits to address changes

18 Notice of Proposed Rulemaking August 16, 2013 Periodic Updates of Regulatory References to Technical Standards and Miscellaneous Amendments New standard API RP 5LT Recommended Practice for Truck Transportation of Line Pipe (first edition) New Standard ASTM D a except for Section 4.2 which addresses reworked material

19 Notice of Proposed Rulemaking August 16, 2013 Periodic Updates of Regulatory References to Technical Standards and Miscellaneous Amendments Not incorporating by reference: API RP 1162 Public Awareness (2nd edition), but leaving as 1 st edition API Standard Tank Inspection (4th edition), but leaving as 3rd edition

20 Notice of Proposed Rulemaking August 16, 2013 Periodic Updates of Regulatory References to Technical Standards and Miscellaneous Amendments Removing (a)(1)(i) referring to Paragraph 8.9 of ASTM D

21 Notice of Proposed Rulemaking August 16, 2013 Periodic Updates of Regulatory References to Technical Standards and Miscellaneous Amendments Clarify (l) to specify records for IM compliance must be maintained for the useful life of the pipe

22 Final Rule January 5, 2015 Periodic Updates of Regulatory References to Technical Standards and Miscellaneous Amendments Removing because of conflict between Part 199 and 49 CFR Part 40 Adequately covered by 49 CFR Part 40

23 Notice September 12, 2013 Extension of comment period for integrity verification process (IVP) (gas transmission)

24 Notice September 18, 2013 Request for comments National Pipeline Mapping System (NPMS) submittals required by all operators (except distribution) Comments by October 18, 2013

25 Final Rule September 25, 2013 Changes to 49 CFR 190 Pipeline Safety Programs Increases in both civil and criminal penalties ($200,000) Investigations, response options, hearings, addresses and contact information, Other administrative procedures

26 Notice November 27, 2013 Random drug rate to remain at 25% for calendar year 2014 and now positive drug test rate was <1% Reminder to submit information through PHMSA portal

27 Notice March 25, 2014 Public Workshop on Class Location Methodology Present perspectives and seek comment on whether applying the gas pipeline integrity management (IM) requirements beyond high consequence areas would mitigate the need for class location requirements Working on report to Congress

28 Notice April 1, 2014 Revision to Operator Registry Comments on proposed revision of two forms, PHMSA F OPID Assignment Request and PHMSA F Operator Registry Notification

29 Notice April 1, 2014 Revision to Operator Registry PHMSA F OPID Assignment Request Align information on all gas distribution and transmission forms(annual, incident) Miles of pipeline by state Clarify ownership relationships Cell number

30 Notice April 1, 2014 Revision to Operator Registry PHMSA F Operator Registry Notification Revise instruction for clarity Align commodity choices Adding construction notification choices

31 Notice April 28, 2014 Revision to Distribution Annual Report Minor changes to the report Commodity transported i.e. landfill, hydrogen, propane, natural gas, other (chlorine) Operator type i.e. investor, municipally, privately owned, other Additional material types Revision of leak causes and adding categories to excavation damage Comments were due June 27, 2014

32 The Pipeline Safety, Regulatory Certainty, and Job Creation Act of 2011 Signed January 3, 2012 Funds programs of the Pipeline and Hazardous Materials Safety Administration (PHMSA) through fiscal year Addressed National Transportation Safety Board recommendations resulting from recent pipeline incidents

33 Reauthorization Fines Maximums increased to $200,000 and $2,000,000. (Amdt , Oct 25, 2013) HCA Emergency Response Time Comptroller General report was due in 2013.

34 Reauthorization Automatic / Remote Shut Off Valve Regulations to require these valves for new (or replaced) transmission lines by Study completed October, 2012 Available at: oadablefiles/files/press%20release%20files/fin al%20valve_study.pdf or primis.phmsa.dot.gov/meetings/dochome.mtg? Mtg=80

35 Reauthorization Integrity Management (ANPRM and NPRM Expanding IMP requirements outside HCA s Report due 2014 to include evaluation of public safety enhancement, risk reduction and incremental cost factors. Findings / future rulemaking?

36 Reauthorization Leak Detection (Liquids) Study Completed 77C7A89CAA18E E3DB9C /filenam e/leak%20detection%20study.pdf Evaluation of limitations of current technology. Establish standards for capabilities of leak detection systems? Findings / future rulemaking?

37 Reauthorization Accident and Incident Notification Post discovery, one hour maximum time to notify NRC. (ADB ) Study of Transportation of Diluted Bitumen - Report completed Excess Flow Valves NTSB recommendation. Regulations for multi-family dwellings?

38 Reauthorization Cover Over Buried Pipelines (Liquids) Study of accidents at inland water body crossings. Report submitted 2013 to include evaluation of depth of cover as a contributing factor. Findings / legislative recommendations? ADB

39 Reauthorization MAOP Records Verification (ADB and ADB ) Complete by mid 2012 for Class 3 & 4 locations and Class 1 & 2 HCA s. Identify all pipelines with insufficient records by mid Regulations for confirmation of material strength of transmission lines located in HCA s

40 Reauthorization MAOP exceedances Section 23 For gas transmission pipelines, if the MAOP exceeds the build-up allowed for operation of pressure-limiting or control devices, the owner or operator shall report the exceedance to the Secretary and appropriate State authorities on or before the 5th day following the date on which the exceedance occurs. (ADB )

41 IBR Documents Incorporated by Reference (IBR) Section 24 of Reauthorization addresses issue of incorporated by reference documents Public Meeting Incorporating by Reference consensus standards unless available free of charge to the public on the Internet Modified to available for free

42 Access to safety standards PHMSA negotiated agreements with: American Petroleum Institute (API) American Gas Association (AGA) American society for Testing and Materials (ASTM) Gas Technology Institute (GTI) Manufacturers Standardization Society of Valves and Fittings Industry, Inc. (MSS) NACE National Fire Protection Association (NFPA)

43 Should or May Shall or Must Incorporated by Reference documents, should is must unless written justification why not practicable/necessary for safety

44 Enforcement Guidance Various enforcement guidance is available at: /e-reading-room Includes O&M, OQ, Corrosion, IM, Public Awareness

45

46 Example Includes terms defined in code and interpretations Technical documents and other IBR sources

47 PHMSA Information Websites PHMSA Training and Qualification PHMSA Pipeline Safety Regulations PHMSA Rulemaking making

48 PHMSA Rule Update

49 Advisory Bulletin No. ADB Issued May 6, 2014 Pipeline Safety: Natural Gas and HL Pipeline Operators Lessons Learned From the Release at Marshall, Michigan To inform all pipeline owners and operators of the deficiencies identified in Enbridge's integrity management (IM) program that contributed to the release of hazardous liquid near Marshall, Michigan, on July 25, 2010.

50 Advisory Bulletin No. ADB Issued May 6, 2014 Continued Pipeline owners and operators are encouraged to review their IM programs for similar deficiencies and take corrective action. Operators should also consider training their control room staff as teams to recognize and respond to emergencies or unexpected conditions. The advisory encourages operators to evaluate their leak detection capabilities to ensure adequate leak detection coverage during transient operations and assess the performance of their leak detection systems following a product release to identify and implement improvements as appropriate.

51 Advisory Bulletin No. ADB Issued May 6, 2014 Continued Additionally, operators are encouraged to review the effectiveness of their public awareness programs and whether local emergency response teams are adequately prepared to identify and respond to early indications of ruptures. Finally, this advisory reminds all pipeline owners and operators to review NTSB recommendations following accident investigations. Owners and operators should evaluate and implement recommendations that are applicable to their programs.

52 Advisory Bulletin No. ADB Issued September 12, 2014 Pipeline Safety: Natural Gas and HL Pipeline Operators Notification(s) Required Prior to Certain Construction-Related Events PHMSA needs to be aware of certain construction-related events to have sufficient time to schedule reviews of pipeline construction plans and inspections. Timely construction plan reviews and inspections could help operators avoid costly modifications, repairs and/or additions to achieve compliance with the regulations. PHMSA strongly encourages operators to provide constructionrelated notification(s) not later than 60 days prior to whichever occurs first: Material purchasing and manufacturing; right-of-way acquisition; construction equipment move-in activities; onsite or offsite fabrications; or right-of-way clearing, grading and ditching.

53 Advisory Bulletin No. ADB Issued September 12, 2014 Pipeline Safety: Natural Gas and HL Pipeline Operators Notification(s) Required Prior to Certain Construction-Related Events PHMSA also strongly encourages operators to provide notification(s) for the construction of 10 or more miles of a new pipeline for a pipeline that: (1) Did not previously exist; and (2) for the replacement of 10 or more contiguous miles of line pipe in an existing pipeline. Construction or any planned rehabilitation, replacement, modification, upgrade, uprate, or update of a facility, other than a section of line pipe, that costs $10 million or more.

54 Advisory Bulletin No. ADB Issued September 18, 2014 Pipeline Safety: Natural Gas and HL Pipeline Operators Guidance for Pipeline Flow Reversals, Product Changes and Conversion to Service PHMSA is alerting operators of the potential significant impact flow reversals, product changes and conversion to service may have on the integrity of a pipeline. Failures on natural gas transmission and hazardous liquid pipelines have occurred after these operational changes. Describes specific notification requirements and general operating and maintenance (O&M) and integrity management actions regarding flow reversals, product changes and conversion to service. Recommends additional actions operators should take when these operational changes are made including the submission of a comprehensive written plan to the appropriate PHMSA regional office regarding these changes prior to implementation.

55 Advisory Bulletin No. ADB Issued October 15, 2014 Pipeline Safety: Natural Gas and HL Pipeline Operators Guidance for Strengthening Pipeline Safety Through Rigorous Program Evaluation and Meaningful Metrics. PHMSA is informing operators that they have developed guidance on the elements and characteristics of a mature IM program evaluation process using meaningful metrics. The guidance document titled Guidance for Strengthening Pipeline Safety Through Rigorous Program Evaluation and Meaningful Metrics, is available on PHMSA's public Web site at e/regulations/impeg.pdf and should be used when operators develop and perform IM program evaluations. The guidance document provides additional specificity to several of the topics detailed in a previously issued Advisory Bulletin, ADB , Using Meaningful Metrics in Conducting Integrity Management Program Evaluations.

56 Advisory Bulletin No. ADB Issued October 15, 2014 Pipeline Safety: Natural Gas and HL Pipeline Operators Guidance for Strengthening Pipeline Safety Through Rigorous Program Evaluation and Meaningful Metrics Operators are required to perform program evaluations and use meaningful metrics. The guidance builds on existing standards and regulations to provide a more detailed and comprehensive description of the steps involved in program evaluations as well as the selection of meaningful performance metrics to support these evaluations and clarifies PHMSA's expectations for operator processes when measuring IM program effectiveness. PHMSA inspectors will use the program evaluation guidance within the guidance document as criteria when evaluating the effectiveness of operator IM program evaluations to assure operators are developing sound program evaluation processes and are developing and applying a robust and meaningful set of performance metrics in their program evaluations.

57 Final Rule Issued January 5, CFR Part 192, 193, 195, and 199 Docket ID: PHMSA Pipeline Safety: Periodic Updates of Regulatory References to Technical Standards and Miscellaneous Amendments PHMSA is amending the pipeline safety regulations to incorporate by reference (IBR) all or parts of new, updated, or reaffirmed editions of voluntary consensus standards that are available on the Internet, free-of-charge, to the public. PHMSA is also making non-substantive edits and to clarify regulatory language in certain provisions. These proposed changes are relatively minor, and will not require pipeline operators to undertake any significant new pipeline safety initiatives. (Removal of which conflicts with CFR Part 40, changing title of welder to welder operator, etc.)

58 Final Rule Issued January 5, CFR Part 192, 193, 195, and 199 Docket ID: PHMSA Pipeline Safety: Periodic Updates of Regulatory References to Technical Standards and Miscellaneous Amendments New Standards Incorporated by Reference (Fully or Partially) API RP 5LT, Recommended Practice for Truck Transportation of Line Pipe (First edition) (March 1, 2012). (API RP 5LT) - Referenced in and ASTM D a, Standard Specification for Polyethylene (PE) Gas Pressure Pipe, Tubing, and Fittings, (December 1, 2009), (except section 4.2 pertaining to rework material) (ASTM D2513) - Referenced in (d); (a); (e); (b); (b); (a); Item 1, Appendix B to Part 192. Changes include a new requirement for outdoor storage of PE pipe, three years for yellow pipe and 10 years for black pipe; new high performance PE pipe material designation codes, with increased long-term performance requirements; and more stringent requirements for use of rework material in PE gas pipe.

59 Final Rule Issued January 5, CFR Part 192, 193, 195, and 199 Docket ID: PHMSA Pipeline Safety: Periodic Updates of Regulatory References to Technical Standards and Miscellaneous Amendments New Standards Incorporated by Reference (Fully or Partially) PHMSA proposes for other non-pe plastic materials to continue to reference the ASTM D (for only, marking of materials) and ASTM D (except section 4.2 pertaining to rework material) for (d); (b); (b)(2); (a)(1)(i); and Item 1, Appendix B to Part 192).

60 Final Rule Issued January 5, CFR Part 192, 193, 195, and 199 Docket ID: PHMSA Pipeline Safety: Periodic Updates of Regulatory References to Technical Standards and Miscellaneous Amendments Updated Editions Not To Be Incorporated by Reference API Recommended Practice 1162, Public Awareness Programs for Pipeline Operators, (2 nd edition) API Standard 653, Tank Inspection, Repair, Alteration, and Reconstruction (4 th edition) and Addendum (2010)

61 Final Rule Issued March 26, CFR Part 191, 192, 195, 198 Docket ID: PHMSA Pipeline Safety: Miscellaneous Changes to Pipeline Safety Regulations PHMSA is making miscellaneous changes to the pipeline safety regulations that are relatively minor, will impose minimal (if any) burden, and will clarify the existing regulations. Issues addressed: Responsibility to Conduct Construction Inspections Leak Surveys for Type B Gathering Lines Qualifying Plastic Pipe Joiners Mill Hydrostatic Tests for Pipe to Operate at Alternative MAOP

62 Final Rule Issued March 26, CFR Part 191, 192, 195, 198 Docket ID: PHMSA Pipeline Safety: Miscellaneous Changes to Pipeline Safety Regulations Issues addressed: Regulating the Transportation of Ethanol by Pipeline Limitation of Indirect Costs in State Grants, Transportation of Pipe, Threading Copper Pipe Offshore Pipeline Condition Reports, Calculating Pressure Reductions for Hazardous Liquid Pipeline Integrity Anomalies Testing Components other than Pipe Installed in Low- Pressure Gas Pipelines Alternative MAOP Notifications

63 Final Rule Issued March 21, CFR Part 191, 192, 195, 198 Docket ID: PHMSA Pipeline Safety: Miscellaneous Changes to Pipeline Safety Regulations Issues addressed: National Pipeline Mapping System Welders vs. Welding Operators Components Fabricated by Welding Odorization of Gas Editorial Amendments (Effective Date: October 1, 2015)

64 Current Rulemakings in Process Excavation Damage Prevention Final Rule moved past PHMSA Adv. Committee approval vote December 2012 NPRM published 4/2/2012 Major Topic Enforce damage protection laws in States that have inadequate enforcement to protect safety. Complies with PIPE s Act 60114(f).

65 Current Rulemakings in Process EFV Expansion beyond Single Family Residences NPRM moved past DOT ANPRM published 11/25/2011 Major Topics under consideration: Rule will propose to require EFVs for: branched service lines serving more than one single family residence multi-family residential dwellings commercial buildings

66 Current Rulemakings in Process Operator Qualification, Cost Recovery and Other Pipeline Safety Proposed Changes NPRM moved past PHMSA This rule will address issues related to: Operator Qualification for new construction Incident Reporting Cost Recovery Renewal process for special permits Other issues to be determined

67 Current Rulemakings in Process Rupture Detection and Valve Rule (NPRM stage) Will establish and define rupture detection and response time metrics including the integration of Automatic Shutoff Valves (ASV) and Remote Control Valve (RCV) placement, with the objective of improving overall incident response. This rule responds to: Requirements of the Pipeline Safety, Regulatory Certainty, and Job Creation Act of 2011 (The Act): Section 4: Auto Safety Valve/Remote Control Valve or equivalent technology be installed on newly constructed or entirely replaced natural gas and hazardous liquid transmission pipelines 2 years after the act was issued

68 Current Rulemakings in Process Rupture Detection and Valve Rule (NPRM stage) Section 8: Require operators of hazardous liquid pipeline facilities to use leak detection systems and establish standards for their use. NTSB Recommendation P (gas) which requires transmission and distribution operators to equip SCADA systems with tools to assist with recognizing and pinpointing leaks.

69 Notice Concerning Required Reporting to the National Response Center (NRC) The National Response Center (operated by the US Coast Guard) has taken down it s online reporting webpages. All required reports must be reported to the NRC by phone until further notice. NRC Phone Number: In Washington, DC: (202)

70 Information Websites PHMSA Inspector Training and Qualifications PHMSA Pipeline Safety Regulations PHMSA Rulemaking PHMSA Inspector Enforcement Guidance

71 PHMSA is Hiring! PHMSA s FY15 budget appropriated 100+ new positions. Typical jobs include professional, engineering, or scientific occupations like General Engineers, Accident/ Incident Investigators, and Transportation Specialists; Human Resources Specialists, Budget Analysts, and other administrative or management-related occupations; and technical support, including GIS Specialists, Data Analysts, and IT Specialists Work at our Washington, D.C., headquarters or one of five regional offices across the country Sign up for job alerts, view current job openings, and find out how to apply at: LinkedIn: Pipeline-and-Hazardous-Materials-Safety-Administration Twitter: PHMSA_DOT YouTube: PHMSADOT

72

73 PHMSA Western Region CATS Contact Information Tom Finch: Phone: (720) Dave Mulligan: Phone: (720)

74 Questions? Thank You!

Regulatory Update - 1 -

Regulatory Update - 1 - Regulatory Update - 1 - Leticia Santos Hernández Pipeline Safety Specialist PHMSA Training & Qualifications Leticia.santos@dot.gov - 2 - ANPRM Advance Notice of Proposed Rulemaking Used to gather information

More information

U.S. DOT Pipeline and Hazardous Materials Safety Administration

U.S. DOT Pipeline and Hazardous Materials Safety Administration U.S. DOT Pipeline and Hazardous Materials Safety Administration Priority Issues for 2017+ - -2 2 - - Organizational Updates Leveraging Lessons from Prior Years Congressional Mandates and Recommendations

More information

NCSL Natural Gas Policy Institute

NCSL Natural Gas Policy Institute - 1 - Pipeline Infrastructure: Replacement and Expansion Needs NCSL Natural Gas Policy Institute PHMSA Pipeline Safety Program Updates September 9, 2015 - 2 - Topics for Today Introductions Who We are

More information

Notice of Proposed Rulemaking (NPRM) Huy Nguyen Western Region

Notice of Proposed Rulemaking (NPRM) Huy Nguyen Western Region Notice of Proposed Rulemaking (NPRM) Huy Nguyen Western Region Rulemaking Process Topics Safety of Hazardous Liquid Pipelines (PHMSA- 2010-0229) Safety of Gas Transmission Pipelines (PHMSA- 2011-0023)

More information

U.S. DOT Pipeline and Hazardous Materials Safety Administration

U.S. DOT Pipeline and Hazardous Materials Safety Administration U.S. DOT Pipeline and Hazardous Materials Safety Administration Today s Agenda PHMSA Update PHMSA Rulemaking PHMSA Advisory Bulletins 2017: What is happening Rulemaking action continues Covering all Congressional

More information

Regulatory Agenda and Notices RSPA / OPS

Regulatory Agenda and Notices RSPA / OPS Regulatory Agenda and Notices RSPA / OPS Download the Regulations http://www.tsi.dot.gov Click on Pipeline Safety (Valve Setting), Publications & Follow Links Advisory Bulletins Advisory Bulletins http://ops.dot.gov

More information

U.S. Department of Transportation Pipeline and Hazardous Materials Safety Administration

U.S. Department of Transportation Pipeline and Hazardous Materials Safety Administration Organization and Regulatory Overview Contact Information John West Transportation Specialist U.S. Department of Transportation PHMSA Office of Training and Qualifications Main: (405) 954-7219 My Office:

More information

API Pipeline Conference San Antonio, Texas

API Pipeline Conference San Antonio, Texas Page 1 of 15 API Pipeline Conference San Antonio, Texas The Best Regulations Don t Happen By Accident April 8, 2014 Alan Mayberry -1- Page 2 of 15 External Drivers Current PHMSA major rulemaking activity

More information

PHMSA = Pipelines and Hazardous. RITA = Research and Innovative Technologies Administration

PHMSA = Pipelines and Hazardous. RITA = Research and Innovative Technologies Administration Arkansas Gas Pipeline Safety Seminar June 20-21, 21, 2007 Arkansas Public Service Commission PHMSA T&Q Wayne St. Germain Pipeline Safety Specialist Phone (405) 954-7219 Live Person (405) 954-8575 Direct

More information

June 2009 Portland, Oregon Wayne St. Germain U.S. DOT/PHMSA T&Q

June 2009 Portland, Oregon Wayne St. Germain U.S. DOT/PHMSA T&Q Oregon Pipeline Safety Seminar June 2009 Portland, Oregon Wayne St. Germain U.S. DOT/PHMSA T&Q Wayne F. St. Germain YOUR INSTRUCTOR WELCOME WELCOME PHMSA Training & Qualifications 6500 South MacArthur

More information

Pipeline Safety Update

Pipeline Safety Update Jul y 2012 Pipeline Safety Update B r i e f S u m m a r y o f 2 0 1 1 It was a blur! San Bruno facts were still unknown NTSB immediate safety recommendations Cast iron failures in Pennsylvania US DOT Secretary

More information

TQ Presentation Intro Slide

TQ Presentation Intro Slide TQ Presentation Intro Slide 2014 Oklahoma Seminar Tulsa, Oklahoma November 2014 Contact Information Wayne St. Germain Pipeline Safety Specialist U.S. Department of Transportation PHMSA Inspector Training

More information

INGAA Foundation, Inc. Construction Safety and Construction QA/QC Workshop Houston, Texas. PHMSA Update on Construction and Inspection March 21, 2012

INGAA Foundation, Inc. Construction Safety and Construction QA/QC Workshop Houston, Texas. PHMSA Update on Construction and Inspection March 21, 2012 INGAA Foundation, Inc. Construction Safety and Construction QA/QC Workshop Houston, Texas PHMSA Update on Construction and Inspection March 21, 2012 Alan Mayberry - 1 - Today s Agenda Updates on the past

More information

This Part prescribes requirements for the REPORTING of:

This Part prescribes requirements for the REPORTING of: This Part prescribes requirements for the REPORTING of: Incidents Safety Related Conditions Annual Pipeline Summary Data Other Reporting Requirements 191.1 (b) Offshore Gathering of Gas Upstream from the

More information

PHMSA rule update. David Johnson November 1, 2017

PHMSA rule update. David Johnson November 1, 2017 PHMSA rule update David Johnson November 1, 2017 No, it s not still Halloween. These are all real. 2 PHMSA Active Rulemakings Safety of Hazardous Liquid Pipelines Gas Transmission (Mega Rule) Underground

More information

National Academy of Sciences. PHMSA s Evolving Approach to Oversight

National Academy of Sciences. PHMSA s Evolving Approach to Oversight National Academy of Sciences Transportation Research Board Study of Pipeline Transportation of Diluted Bitumen PHMSA s Evolving Approach to Oversight Associate Administrator Jeff Wiese Senior Engineer

More information

Recent & Proposed Rulemakings

Recent & Proposed Rulemakings U.S. Department of Transportation Pipeline and Hazardous Materials Safety Administration PHMSA'S S Recent & Proposed Rulemakings and Initiatives Byron Coy Region Director, Eastern USDOT/PHMSA PENNSYLVANIA

More information

Initiated by PHMSA, NTSB accident report, Congress, petition for rulemaking, inspector general, etc. Advance notice of proposed rulemaking (ANPRM)

Initiated by PHMSA, NTSB accident report, Congress, petition for rulemaking, inspector general, etc. Advance notice of proposed rulemaking (ANPRM) How a regulation is made Initiated by PHMSA, NTSB accident report, Congress, petition for rulemaking, inspector general, etc. Advance notice of proposed rulemaking (ANPRM) Public comments and possible

More information

Underground Natural Gas Storage Safety Regulation. Mary L. McDaniel, P.E. Baker Engineering and Risk Consultants, Inc Oakwell Court Suite 100

Underground Natural Gas Storage Safety Regulation. Mary L. McDaniel, P.E. Baker Engineering and Risk Consultants, Inc Oakwell Court Suite 100 Underground Natural Gas Storage Underground Natural Gas Storage Safety Regulation Mary L. McDaniel, P.E. Baker Engineering and Risk Consultants, Inc. 3330 Oakwell Court Suite 100 San Antonio, Texas 78218

More information

Pipeline Safety: Plastic Pipe

Pipeline Safety: Plastic Pipe U.S. Department of Transportation Pipeline and Hazardous Materials Safety Administration Pipeline Safety: Plastic Pipe Draft Environmental Assessment Docket No. PHMSA-2014-0098 May 1, 2015 Prepared for:

More information

American Petroleum Institute th St, NW Suite L St, NW Washington, DC Washington, DC December 1, 2017

American Petroleum Institute th St, NW Suite L St, NW Washington, DC Washington, DC December 1, 2017 David Murk Andrew Black Pipeline Manager, President & CEO Midstream & Industry Operations Association of Oil Pipe Lines American Petroleum Institute 900 17 th St, NW Suite 600 1220 L St, NW Washington,

More information

Pipeline Safety Regulatory Update - 1 -

Pipeline Safety Regulatory Update - 1 - Pipeline Safety Regulatory Update - 1 - The Protecting our Infrastructure of Pipelines and Enhancing Safety (PIPES) Act of 2016, was passed by Congress and signed into law on June 22, 2016 It authorizes

More information

What s Happening to Make Pipelines Safer?

What s Happening to Make Pipelines Safer? What s Happening to Make Pipelines Safer? Pipeline Safety Trust Salt Lake City, Utah March 15, 2012 Chris Hoidal - OPS - 1 - Today s Agenda Some Basics on Pipeline Safety Where are These Pipeline and Why

More information

PHMSA Rule Update. David Johnson November 14, 2018

PHMSA Rule Update. David Johnson November 14, 2018 PHMSA Rule Update David Johnson November 14, 2018 PHMSA Active Rulemakings Gas Transmission (Mega Rule) now 3 parts o o o MAOP, Assessment requirements Repair criteria, IM improvements, CP, MOC Gas gathering

More information

National Academy of Sciences

National Academy of Sciences National Academy of Sciences Transportation Research Board Study of Pipeline Transportation of Diluted Bitumen PHMSA Regulatory Authority and Keystone XL Pipeline October 23, 2012-1 - Topics for Briefing

More information

Pipeline Safety Management Systems API RP 1173

Pipeline Safety Management Systems API RP 1173 Pipeline Safety Management Systems API RP 1173 August 12, 2015 John A. Jacobi, P.E., J.D. Vice President Today s Agenda PHMSA Update PHMSA Safety Posture Initiative Importance of Management Systems Safety

More information

Proposed Changes to the Annual Gas Transmission DOT Report Concerning MAOP Verification. NGA Fall Operations Conference October 4, 2012 Mary Holzmann

Proposed Changes to the Annual Gas Transmission DOT Report Concerning MAOP Verification. NGA Fall Operations Conference October 4, 2012 Mary Holzmann Proposed Changes to the Annual Gas Transmission DOT Report Concerning MAOP Verification NGA Fall Operations Conference October 4, 2012 Mary Holzmann National Grid In the US, we serve 3.4 million customers

More information

FLORIDA PUBLIC SERVICE COMMISSION

FLORIDA PUBLIC SERVICE COMMISSION FLORIDA PUBLIC SERVICE COMMISSION NATURAL GAS PIPELINE ANNUAL SAFETY REPORT 2012 DIVISION OF ENGINEERING TABLE OF CONTENTS TABLE OF FIGURES... II ABBREVIATIONS... III GAS SAFETY BACKGROUND... 1 GAS SAFETY

More information

Integrity Program Evaluation Using Meaningful Performance Metrics

Integrity Program Evaluation Using Meaningful Performance Metrics Integrity Program Evaluation Using Meaningful Performance Metrics 1 Objective Pipeline Safety Management Systems (API 1173), the recent PHMSA guidance presented in ADB 14-05 and Asset Management (ISO 55001),

More information

Pipeline Safety Trust Annual Conference New Orleans, Louisiana October 20, 2016

Pipeline Safety Trust Annual Conference New Orleans, Louisiana October 20, 2016 Pipeline Safety Trust Annual Conference New Orleans, Louisiana October 20, 2016 PHMSA Pipeline Safety Program Updates Alan Mayberry Acting Associate Administrator Who is PHMSA - DOT/PHMSA? Pipeline and

More information

NAS Study on Propane Gas Pipeline Facilities

NAS Study on Propane Gas Pipeline Facilities NAS Study on Propane Gas Pipeline Facilities - 2 - Project Scope Subpart P Gas Distribution Pipeline Integrity Management (IM) 192.1001 What definitions apply to this subpart? Small LPG Operator means

More information

Gas Pipeline Safety Under Heightened State and Federal Scrutiny

Gas Pipeline Safety Under Heightened State and Federal Scrutiny Presenting a live 90-minute webinar with interactive Q&A Gas Pipeline Safety Under Heightened State and Federal Scrutiny Navigating the New Regulatory Landscape and Preparing for Increased Testing and

More information

Spire STL Pipeline Project

Spire STL Pipeline Project Spire STL Pipeline Project Resource Report 11 Reliability and Safety FERC Docket No. CP17- - FERC Application January 2017 Public RESOURCE REPORT 11 - RELIABILITY AND SAFETY SUMMARY OF FILING INFORMATION

More information

ILI: An Improvement Over Pressure Testing for Pipeline Integrity Management

ILI: An Improvement Over Pressure Testing for Pipeline Integrity Management Bruce L. Paskett, PE Dr. Pete Riccardella June, 2018 ILI: An Improvement Over Pressure Testing for Pipeline Integrity Management Gas MegaRule MAOP Verification Requirements - Advantages from Using ILI

More information

NATURAL GAS SYSTEM OPERATOR SAFETY PLAN

NATURAL GAS SYSTEM OPERATOR SAFETY PLAN TABLE OF CONTENTS SOCALGAS SAFETY- PLAN.0 SECTION DESCRIPTION REQUIRED ELEMENTS FROM CA Public Utilities Code 956.5, 961, and 963 1 INTRODUCTION 961(b)(1-3) 2 EXECUTIVE OFFICER S SAFETY PERFORMANCE 961(b)(4)

More information

A~h. COpy. American Gas Association. September 9, 2009

A~h. COpy. American Gas Association. September 9, 2009 A~h. American Gas Association COpy September 9, 2009 Mr. Jeffrey D. Wiese Associate Administrator for Pipeline Safety U.S. Department of Transportation Pipeline and Hazardous Materials Safety Administration

More information

Gas Transmission MAOP Verification Integrity Verification Process Oklahoma CC Pipeline Safety Conference

Gas Transmission MAOP Verification Integrity Verification Process Oklahoma CC Pipeline Safety Conference Gas Transmission MAOP Verification Integrity Verification Process Oklahoma CC Pipeline Safety Conference U.S. DOT / PHMSA Steve Nanney November 19, 2014 1 Integrity Verification Process Drivers Overview

More information

DOT Proposes Tougher Safety Regulations For Hazardous Liquids Pipelines

DOT Proposes Tougher Safety Regulations For Hazardous Liquids Pipelines RESEARCH North America Fossil Fuels Oil DOT Proposes Tougher Safety Regulations For Hazardous Liquids Pipelines New Rule Would Expand Reach Of DOT Reporting Requirements; Cost Operators Upwards Of $22.4

More information

U.S. DOT Pipeline and Hazardous Materials Safety Administration. William (Bill) Lowry, PE Community Liaison

U.S. DOT Pipeline and Hazardous Materials Safety Administration. William (Bill) Lowry, PE Community Liaison U.S. DOT Pipeline and Hazardous Materials Safety Administration William (Bill) Lowry, PE Community Liaison Community Assistance & Technical Services (CATS) Name Change Effective: January 1, 2017 Community

More information

Excavation Damage Prevention

Excavation Damage Prevention PHMSA OFFICE OF PIPELINE SAFETY SOUTHERN REGION Excavation Damage Prevention Georgia Municipal Association Gas Section & Georgia Public Service Commission Arthur O. Buff, P.E. CATS Program Manager PHMSA,

More information

Annual Natural Gas Pipeline Safety Report

Annual Natural Gas Pipeline Safety Report Annual Natural Gas Pipeline Safety Report 2009 Florida Public Service Commission Division of Service, Safety and Consumer Assistance Annual Natural Gas Pipeline Safety Report 2009 At the March 5, 1984,

More information

Preliminary Regulatory Impact Assessment. Notice of Proposed Rulemaking - Pipeline Safety: Safety of Gas Transmission and Gathering Pipelines

Preliminary Regulatory Impact Assessment. Notice of Proposed Rulemaking - Pipeline Safety: Safety of Gas Transmission and Gathering Pipelines Preliminary Regulatory Impact Assessment Notice of Proposed Rulemaking - Pipeline Safety: Safety of Gas Transmission and Gathering Pipelines Office of Pipeline Safety Pipeline and Hazardous Materials Safety

More information

NATURAL GAS SYSTEM OPERATOR SAFETY PLAN

NATURAL GAS SYSTEM OPERATOR SAFETY PLAN TABLE OF CONTENTS SOCALGAS SAFETY- PLAN.0 SECTION DESCRIPTION REQUIRED ELEMENTS FROM CA Public Utilities Code 956.5, 961, and 963 1 INTRODUCTION 961(b)(1-3) 2 EXECUTIVE OFFICER S SAFETY PERFORMANCE 961(b)(4)

More information

Gas Pipeline Safety March 2012

Gas Pipeline Safety March 2012 Gas Pipeline Safety March 2012 Contact: edbaker@scottmadden.com jgdavis@scottmadden.com Introduction Pipeline safety has become a top priority for the gas industry. Several drivers have increased scrutiny

More information

DOT s Federal Pipeline Safety Program: Background and Key Issues for Congress

DOT s Federal Pipeline Safety Program: Background and Key Issues for Congress DOT s Federal Pipeline Safety Program: Background and Key Issues for Congress Paul W. Parfomak Specialist in Energy and Infrastructure Policy May 20, 2016 Congressional Research Service 7-5700 www.crs.gov

More information

Notice of Proposed Rule Making

Notice of Proposed Rule Making Notice of Proposed Rule Making Oregon, Washington and Idaho Natural Gas Pipeline Safety Seminar June 17 18, 2009 Bruce L. Paskett, P.E. Pipeline Safety Improvement Act of 2002 D.O.T. Inspector General

More information

Integrity Management for Gas Distribution Pipelines. Report of Phase 1 Investigations

Integrity Management for Gas Distribution Pipelines. Report of Phase 1 Investigations Integrity Management for Gas Distribution Pipelines Report of Phase 1 Investigations December 2005 Prepared by Joint Work/study Groups including Representatives of: Stakeholder Public Gas Distribution

More information

Pipeline Status Document. API Document AUGUST 2017

Pipeline Status Document. API Document AUGUST 2017 Pipeline Status Document API Document AUGUST 2017 Special Notes Classified areas may vary depending on the location, conditions, equipment, and substances involved in any given situation. Users of this

More information

Ohio s One-Stop Utility Resource. Gas Pipeline Safety. Ed Steele, Section Chief Gas Pipeline Safety Section

Ohio s One-Stop Utility Resource. Gas Pipeline Safety. Ed Steele, Section Chief Gas Pipeline Safety Section Gas Pipeline Safety Ed Steele, Section Chief Gas Pipeline Safety Section Program Structure The Gas Pipeline Safety Program is a Federally certified program (Intrastate and Interstate agent) In order to

More information

BSR GPTC Z TR x GM Referenced Standards Page 1 of 12

BSR GPTC Z TR x GM Referenced Standards Page 1 of 12 Page 1 of 12 PURPOSE: Review existing GM and modify as appropriate in light of Amendment 192 119. Regulations Section 192.620 To address increased risk of a maximum allowable operating pressure based on

More information

Plastic Pipe Timeline

Plastic Pipe Timeline Copyright Plastic Pipe Data Collection Committee 2015All Rights Reserved Administered by American Gas Association 400 North Capitol Street, N.W., 4 th Floor Washington, DC 20001 U.S.A. NOTICE AND COPYRIGHT

More information

VALLEY LATERAL PROJECT. RESOURCE REPORT 11 Reliability and Safety. FERC Docket No. CP

VALLEY LATERAL PROJECT. RESOURCE REPORT 11 Reliability and Safety. FERC Docket No. CP VALLEY LATERAL PROJECT RESOURCE REPORT 11 Reliability and Safety FERC Docket No. CP16- -000 November 2015 Section TABLE OF CONTENTS Page 11.0 RELIABILITY AND SAFETY... 11-1 11.1 NATURAL GAS PIPELINE INDUSTRY

More information

FLORIDA PUBLIC SERVICE COMMISSION

FLORIDA PUBLIC SERVICE COMMISSION FLORIDA PUBLIC SERVICE COMMISSION NATURAL GAS PIPELINE ANNUAL SAFETY REPORT 2017 DIVISION OF ENGINEERING Table of Contents Figures and Tables... iii Gas Safety Background... 1 Transmission Integrity Management

More information

ASSET INTEGRITY Project Case Studies

ASSET INTEGRITY Project Case Studies Project Case Studies Development of Corrosion Under Insulation (CUI) Protocol and Inspection Procedure Multi-National Natural Gas Pipeline Operator Texas Contacts Background A large multi-national energy

More information

API Recommended Practice for Rural Onshore Gas Gathering Lines Forward

API Recommended Practice for Rural Onshore Gas Gathering Lines Forward API Recommended Practice for Rural Onshore Gas Gathering Lines Forward [INSERT API LANGUAGE] Introduction This recommended practice contains safety standards for the design, construction, testing, corrosion

More information

Pipeline Safety Update

Pipeline Safety Update Pipeline Safety Update NAPCA Workshop August 16, 2012 Houston, Texas Safety Administration (PHMSA) Steve Nanney - 1 - PHMSA Safety Update - Topics PHMSA Overview Perspective on Past Performance Agency

More information

PHMSA Update: Aging Infrastructure and Integrity Verification Process

PHMSA Update: Aging Infrastructure and Integrity Verification Process PHMSA Update: Aging Infrastructure and Integrity Verification Process NAPCA Workshop August 15, 2013 Houston, Texas Safety Administration (PHMSA) Steve Nanney 1 PHMSA Safety Update - Topics Performance

More information

Natural Gas Infrastructure Replacement and Expansion Efforts

Natural Gas Infrastructure Replacement and Expansion Efforts Natural Gas Infrastructure Replacement and Expansion Efforts National Association of State Energy Officials 2014 Energy Outlook Conference February 5, 2014 Washington, D.C. 2 Trillion cubic Feet Future

More information

GAS. Gas Distribution Systems Safety and Loss Management System Guidelines. Prepared by: Brad Wyatt, Provincial Safety Manager - Gas

GAS. Gas Distribution Systems Safety and Loss Management System Guidelines. Prepared by: Brad Wyatt, Provincial Safety Manager - Gas GAS Gas Distribution Systems Safety and Loss Management System Guidelines Prepared by: Brad Wyatt, Provincial Safety Manager - Gas Date: November - 2017 Controlled Document: MAN-4057-00 Contents 1. Introduction...

More information

U.S. DOT Pipeline and Hazardous Materials Safety Administration. William (Bill) Lowry, PE Community Liaison

U.S. DOT Pipeline and Hazardous Materials Safety Administration. William (Bill) Lowry, PE Community Liaison U.S. DOT Pipeline and Hazardous Materials Safety Administration William (Bill) Lowry, PE Community Liaison Community Assistance & Technical Services (CATS) Name Change Effective: January 1, 2017 Community

More information

Pipeline Safety. RRT IV Fall 2015 Meeting. August 18, Arthur O. Buff, P.E CATS Program Manager PHMSA, Southern Region

Pipeline Safety. RRT IV Fall 2015 Meeting. August 18, Arthur O. Buff, P.E CATS Program Manager PHMSA, Southern Region - 1 - Pipeline Safety RRT IV Fall 2015 Meeting August 18, 2015 Arthur O. Buff, P.E. CATS Program Manager PHMSA, Southern Region Overview - 2 - Explosion de Gas en Reynosa U. S. Department of Transportation

More information

Before the Pipeline and Hazardous Materials Safety Administration United States Department of Transportation Washington, D.C.

Before the Pipeline and Hazardous Materials Safety Administration United States Department of Transportation Washington, D.C. Before the Pipeline and Hazardous Materials Safety Administration United States Department of Transportation Washington, D.C. Pipeline Safety: Safety of Gas Transmission and Gathering Pipelines; Proposed

More information

Regulation Of Oil And Natural Gas Pipelines: A Legal Primer For The Layman

Regulation Of Oil And Natural Gas Pipelines: A Legal Primer For The Layman Pipeline & Gas Journal March 2008 Copyright 2008 ProQuest Information and Learning All Rights Reserved Copyright 2008 Oildom Publishing Company of Texas, Inc. Section: Pg. 124; Vol. 235; No. 3; ISSN: 0032-0188

More information

Pennsylvania Energy Association Pipeline Safety. Paul Metro Manager Pipeline Safety PAPUC

Pennsylvania Energy Association Pipeline Safety. Paul Metro Manager Pipeline Safety PAPUC Pennsylvania Energy Association 2017 Pipeline Safety Paul Metro Manager Pipeline Safety PAPUC 1 Intrastate Pipeline Facilities Intrastate Gas: Transmission mileage: 1,127 miles Distribution mileage: 47,499

More information

OPERATOR REGISTRY NOTIFICATION

OPERATOR REGISTRY NOTIFICATION Notice: This report is required by 49 CFR Parts 191 and 195. Failure to report may result in a civil penalty not to exceed $100,000 for each violation for each day the violation continues up to a maximum

More information

Control Information: (copy and fill-in for each Operator)

Control Information: (copy and fill-in for each Operator) PUBLIC AWARENESS PROGRAM EFFECTIVE INSPECTION SPECIFIC INFORMATION Control Information: (copy and fill-in for each Operator) Inspection Date(s): Operator ID: OpID: State/Other ID: Unit ID No. Activity

More information

Liquid Petroleum Pipelines Safe, Efficient and Improving

Liquid Petroleum Pipelines Safe, Efficient and Improving Liquid Petroleum Pipelines Safe, Efficient and Improving Peter Lidiak Pipeline Director March 15, 2012 U.S. Oil Pipelines & Refineries Pipelines: Safe and Getting Safer Safest and most efficient mode for

More information

David Spangler CATS Coordinator Office of Pipeline Safety (202)

David Spangler CATS Coordinator Office of Pipeline Safety (202) Damage Prevention PHMSA s Perspective David Spangler CATS Coordinator Office of Pipeline Safety (202) 366-5064 David.spangler@dot.gov Presentation Overview PHMSA s perspective on damage prevention Variability

More information

Applicability of OQ for new construction activities Addressing abnormal operating conditions during evaluations and at job site Span of Control

Applicability of OQ for new construction activities Addressing abnormal operating conditions during evaluations and at job site Span of Control Applicability of OQ for new construction activities Addressing abnormal operating conditions during evaluations and at job site Span of Control limitations Tracking OQ during O&M activities & projects

More information

Testimony of Ronald W. Jibson Vice President of Operations Questar Gas Company

Testimony of Ronald W. Jibson Vice President of Operations Questar Gas Company Testimony of Ronald W. Jibson Vice President of Operations Questar Gas Company On Behalf of the American Gas Association and The American Public Gas Association Before the U.S. House Energy and Commerce

More information

BEFORE THE PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION UNITED STATES DEPARTMENT OF TRANSPORTATION WASHINGTON, D.C.

BEFORE THE PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION UNITED STATES DEPARTMENT OF TRANSPORTATION WASHINGTON, D.C. BEFORE THE PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION UNITED STATES DEPARTMENT OF TRANSPORTATION WASHINGTON, D.C. Pipeline Safety: Public Workshop on the Integrity Verification Process Docket

More information

March 6, Docket No. PHMSA : Pipeline Safety: Miscellaneous Changes to Pipeline Safety Regulations

March 6, Docket No. PHMSA : Pipeline Safety: Miscellaneous Changes to Pipeline Safety Regulations DOT Docket Management System U.S. Department of Transportation Docket Operations, M-30 Room W12-140 1200 New Jersey Avenue, S.E. Washington, D.C. 20590-0001 VIA E-GOV WEB SITE (http://www.regulations.gov)

More information

Company Name: Click here to enter text. Contractor Contact (Name & Ph #): Click here to enter text. OpQual & DER USE ONLY

Company Name: Click here to enter text. Contractor Contact (Name & Ph #): Click here to enter text. OpQual & DER USE ONLY Company Name: Click here to enter text. Contractor Contact (Name & Ph #): Click here to enter text. OQ Tasks? Y N CMV Guidelines for Completion of the DOT Covered Function Checklist OpQual & DER USE ONLY

More information

Pipeline Records - - Lessons Learned. The Changing Industry Landscape and Transmission Records Implications NGA Operations Conference April 3, 2012

Pipeline Records - - Lessons Learned. The Changing Industry Landscape and Transmission Records Implications NGA Operations Conference April 3, 2012 Pipeline Records - - Lessons Learned The Changing Industry Landscape and Transmission Records Implications NGA Operations Conference April 3, 2012 Who Are We? CHA Consulting, Inc. CHA is a highly diversified,

More information

Part 192 Corrosion Enforcement Guidance

Part 192 Corrosion Enforcement Guidance Part 192 Corrosion Enforcement Introduction The materials contained in this document consist of guidance, techniques, procedures and other information for internal use by the PHMSA pipeline safety enforcement

More information

Integrity Management Program for

Integrity Management Program for Compliance Assurance Protocol Integrity Management Program for Pipelines April 2018 Version 1.9 Table of Contents BACKGROUND... 4 SAFETY CULTURE... 4 COMPLIANCE ASSURANCE PROCESS... 5 PHASE ONE... 5 PHASE

More information

December 30, Christopher A. Hart National Transportation Safety Board Washington, DC 20954

December 30, Christopher A. Hart National Transportation Safety Board Washington, DC 20954 December 30, 2016 Christopher A. Hart National Transportation Safety Board Washington, DC 20954 Re: Joint INGAA and AGA Response to Safety Recommendations P-15-23 and P-15-25 Chairman Hart, The Interstate

More information

PIPELINES 102: PART 192 REGULATORY REQUIREMENTS FOR NATURAL GAS PIPELINES

PIPELINES 102: PART 192 REGULATORY REQUIREMENTS FOR NATURAL GAS PIPELINES COURSE PIPELINES 102: PART 192 REGULATORY REQUIREMENTS FOR NATURAL GAS PIPELINES January 16-17, 2019 Doubletree Houston Galleria Houston, TX RELATED EVENT: PIPELINES 101 BASIC PRINCIPLES OF ONSHORE PIPELINES

More information

Distribution Integrity Management. Record Requirements

Distribution Integrity Management. Record Requirements Distribution Integrity Management Record Requirements CONTACT INFORMATION John West Transportation Specialist U.S. Department of Transportation PHMSA Office of Training and Qualifications Main: (405) 954-7219

More information

4. "Commission" means the Arizona Corporation Commission.

4. Commission means the Arizona Corporation Commission. ARTICLE 2. PIPELINE SAFETY Editor's Note: The Arizona Corporation Commission has determined that the following Section is exempt from the Attorney General certification provisions of the Arizona Administrative

More information

Industry Guidance on Records Review for Re-affirming Transmission Pipeline MAOPs

Industry Guidance on Records Review for Re-affirming Transmission Pipeline MAOPs October 2011 Industry Guidance on Records Review for Re-affirming Transmission Pipeline MAOPs The intent of this document is to provide general guidance to pipeline operators who are undertaking a process

More information

INSTRUCTIONS FOR FORM PHMSA F (Rev ) ANNUAL REPORT FOR CALENDAR YEAR 20 LIQUEFIED NATURAL GAS (LNG) FACILITIES

INSTRUCTIONS FOR FORM PHMSA F (Rev ) ANNUAL REPORT FOR CALENDAR YEAR 20 LIQUEFIED NATURAL GAS (LNG) FACILITIES GENERAL INSTRUCTIONS All section references are to Title 49 of the Code of Federal Regulations (49 CFR). The Liquefied Natural Gas (LNG) Facilities Annual Report has been revised as of calendar year 2010

More information

PHMSA Pipeline Safety Program Update

PHMSA Pipeline Safety Program Update PHMSA Pipeline Safety Program Update NACE Central Area Conference August 28, 2013 William Lowry, PE Community Assistance and Technical Services Mgr, Southwest Region USDOT/PHMSA 1 Today s Agenda Underlying

More information

PHMSA Update on Public Awareness

PHMSA Update on Public Awareness PHMSA Update on Public Awareness 2010 Western Regional Gas Conference August 24, 2010 Tom Finch PHMSA - Western Region CATS Manager Overview PHMSA Mission and Scope Why Public Awareness Public Awareness

More information

PHMSA's Proposed Rules for Natural Gas: Breaking Down the Regulations and Their Impact Across Gathering and Transmission Systems

PHMSA's Proposed Rules for Natural Gas: Breaking Down the Regulations and Their Impact Across Gathering and Transmission Systems PHMSA's Proposed Rules for Natural Gas: Breaking Down the Regulations and Their Impact Across Gathering and Transmission Systems Texas Gas Association November 11, 2016 Disclaimer Discussion and information

More information

PIPELINE INSPECTOR TRAINING PROGRAMS

PIPELINE INSPECTOR TRAINING PROGRAMS ABSTRACT As our pipeline industry grows and changes, regulations and standards are developed to help facilitate and drive these changes. New amendments concerning pipeline inspectors will require both

More information

Pipeline Safety: Clarification of Terms Relating to Pipeline Operational Status.

Pipeline Safety: Clarification of Terms Relating to Pipeline Operational Status. This document is scheduled to be published in the Federal Register on 08/16/2016 and available online at http://federalregister.gov/a/2016-19494, and on FDsys.gov Billing Code: 4910-60-W DEPARTMENT OF

More information

Natural Gas Gathering Lines. John Williams Director Service Monitoring and Enforcement Department

Natural Gas Gathering Lines. John Williams Director Service Monitoring and Enforcement Department Natural Gas Gathering Lines John Williams Director Service Monitoring and Enforcement Department Gas Pipeline Safety Staff Program Manager Office Support Staff 11 Inspectors The Federal/State Partnership

More information

Stephanie Weidman PHMSA Program Director

Stephanie Weidman PHMSA Program Director RAILROAD COMMISSION OF TEXAS Stephanie Weidman PHMSA Program Director Oversight and Safety Division Pipeline Safety February 2016 RRC Mission Our mission is to serve Texas by our stewardship of natural

More information

Public Workshop on Integrity Verification Process (IVP)

Public Workshop on Integrity Verification Process (IVP) Public Workshop on Integrity Verification Process (IVP) Arlington, Virginia 8/7/2013 Presenting on behalf of INGAA Dwayne Burton Kinder Morgan INGAA s Integrity Management Continuous Improvement (IMCI)

More information

PHMSA Update Safety Management Systems

PHMSA Update Safety Management Systems PHMSA Update Safety Management Systems Oklahoma Pipeline Safety Seminar Tulsa, Ok Wednesday November 19, 2014 9:30-10:30 AM Chris McLaren - 1 - Today s Agenda Importance of Management Systems Safety Culture

More information

Kevin C. Connors Pipeline Program Supervisor

Kevin C. Connors Pipeline Program Supervisor Underground Gathering Pipelines: Building a Regulatory Program Kevin C. Connors Pipeline Program Supervisor kcconnors@nd.gov 600 East Boulevard Ave. Dept 405 Bismarck, ND 58505-0840 (701)328-8020 Focused

More information

PHMSA 2011 reporting requirements March 2012

PHMSA 2011 reporting requirements March 2012 PHMSA 2011 reporting requirements March 2012 Agenda 2011 Hazardous Liquid Annual Report Improvements Operator Validation Operator Notifications PHMSA Portal Improvements Questions - 2 - 2011 Hazardous

More information

1220 L St., NW Washington, DC Washington, DC January 8, 2016

1220 L St., NW Washington, DC Washington, DC January 8, 2016 Robin Rorick Andrew J. Black Group Director, Midstream President & CEO & Industry Operations Association of Oil Pipe Lines American Petroleum Institute 1808 Eye St., NW 1220 L St., NW Washington, DC 20006

More information

Federal Railroad Administration s Action Plan For Hazardous Materials Safety

Federal Railroad Administration s Action Plan For Hazardous Materials Safety Federal Railroad Administration s Action Plan For Hazardous Materials Safety In response to train accidents in the United States and Canada involving tank cars carrying crude oil, the U.S. Department of

More information

Smart Modernization: Infrastructure Replacement & Expansion Update. NARUC Staff Subcommittee on Accounting and Finance, 2016 Fall Conference

Smart Modernization: Infrastructure Replacement & Expansion Update. NARUC Staff Subcommittee on Accounting and Finance, 2016 Fall Conference Smart Modernization: Infrastructure Replacement & Expansion Update NARUC Staff Subcommittee on Accounting and Finance, 2016 Fall Conference Natural Gas Records in 2015 Domestic Annual Production 27.1 Tcf

More information

Company Name: Property Name:

Company Name: Property Name: Distribution Integrity Management: Guidance for Master Meter and Small Liquefied Petroleum Gas Pipeline Operators Pipeline Safety: Integrity Management Program for Gas Distribution Pipelines Company Name:

More information

SUMMARY OF TRANSMISSION INTEGRITY MANAGEMENT PROGRAM

SUMMARY OF TRANSMISSION INTEGRITY MANAGEMENT PROGRAM Page 1 of 6 SUMMARY OF TRANSMISSION INTEGRITY MANAGEMENT PROGRAM Program Overview: The Company s Transmission Integrity Management Program ( TIMP ) was established to comply with federal TIMP regulations

More information

2012 Northeast Corrosion Conference Springfield, Massachusetts San Bruno, CA Lessons Learned & Recent Legislation

2012 Northeast Corrosion Conference Springfield, Massachusetts San Bruno, CA Lessons Learned & Recent Legislation 2012 Northeast Corrosion Conference Springfield, Massachusetts San Bruno, CA Lessons Learned & Recent Legislation Randy Knepper Director of Safety New Hampshire Public Utilities Commission 1Jan 18th, 2012

More information

PIPELINE SAFETY REGULATIONS

PIPELINE SAFETY REGULATIONS U.S. DEPARTMENT OF TRANSPORTATION PIPELINE AND HAZARDOUS MATERIALS SAFETY ADMINISTRATION OFFICE OF PIPELINE SAFETY PIPELINE SAFETY REGULATIONS 49 CFR PART 191 ANNUAL REPORTS, INCIDENT REPORTS AND SAFETY-RELATED

More information