Front End Engineering Design (FEED) Challenges in EPC Projects: Design, LLI Strategy & Fast Track
|
|
- Arabella Chambers
- 6 years ago
- Views:
Transcription
1 progetti Front End Engineering Design (FEED) Challenges in EPC Projects: Design, LLI Strategy & Fast Track By Armando Bianco, Engineering Manager, Eniprogetti Global Conference on EPC Contract & Project Management 9th-10th November 2017 Lisbon, Portugal
2 Index Eni Design Basis, Key Deliverables & Battery Limits: how to approach a Front End Engineering Design Balance between engineering freezing and early procurement: Long Lead Items strategy Fast Track: Basic, FEED & Detail Design phases in overlap aiming at Project goals Conclusions 2
3 Eni 3
4 Design Basis, Key Deliverables & Battery Limits: how to approach a Front End Engineering Design 4
5 Oil and Gas Project Development Phases Pre-feasibily 1-3 MM (typical ref.) Feasibility 2-4 MM (typical ref.) Basic - FEED 3-9 MM (typical ref.) G1 G2 G3 Detail Design & Procurement 9-18 MM (typical ref.) Construction Commissioning 12+ MM (typical ref.) Execution: detailed development and physical realizatio of the scope of the project s ork Definition: finalization of the development concept Selection: choice of optimal development configuration Appraisal / Evaluation: assess e t of the opportu it s eco o ic alue Project expenditure Capital Risk Difficulty to implement changes Personnel involved Stakeholders e pectatio s Time 5
6 Project Development Phases Key Activities -> Key Deliverables (es. for process and piping and layout engineering) Pre-feasibily 1-3 MM (typical ref.) Feasibility 2-4 MM (typical ref.) Basic - FEED 3-9 MM (typical ref.) Detail Design & Procurement 9-18 MM (typical ref.) Construction Commissioning 12+ MM (typical ref.) Support to Construction and commissioning Feasibility Red-marked and as-built Finalization of all processes, utilities and transportation systems. Design of all engineering systems Constructability reviews finalization 3D model Detail Engineering Design Procurement and Construction P&ID (with vendor information) Equipment DS (for all items) Details MTO (2 nd and 3 rd ) Isometrics Construction drawings Stress Reports Finalization of Heat & Material balance, P&ID & Equipment and packages DS Plot Plan, Equipment layouts, Underground layouts Finalization of Technical Specifications (Stress analysis Criteria) Single lines for steel structures Preli i ar MTO s Pipi g ( st MTO) 6 Identification and analysis of the main process and utilities for each generated concept alternative Preparation of process specifications, design criteria, for all processes, utilities and transportation systems. Preliminary engineering, safety and constructability. Technology selection report Preliminary Heat & Material balance Block Flow Diagram Preliminary Site Plan Process Flow Diagrams Battery Limits Table Preliminary P&I Ds Equipment Data Sheets Design Criteria Preliminary Plot Plan
7 How Design Basis, Key Delivery and B.L. can affect a Project What if Desig Bases are not finalized Example: the pressure of the Sea Water Make-up (rely upon information) was significantly different from the reality. Technical resolution: lower the pumps with an additional basin (groundwater level very high). Impact: additional costs and delay in schedule Key Deliverables are not ready as needed Example: the supply of a critical reactor was assigned to a vendor in the Far East and a shipping to North Africa was fixed in advance. Due to the delay in the 3D model, the nozzle orientation was not ready as per original plan agreed with the vendor resulting in late finalization of the vendor engineering and eventually of the supply. Recovery plan: an acceleration plan was agreed with the vendor to meet shipping window. Impact: additional costs 7 Battery Li its are not aligned (process-wise) Example: two different mechanical contractors were assigned to install the cooling water circuits in the relevant area and a battery limits was established. During the commissioning phase after the battery limits were connected it was noticed that one contractor inverted the connection from a process point of view. Technical resolution: the connections were modified during commissioning and with acceleration in procurement for the unforeseen additional material during commissioning Impact: delay during commissioning phase Note: Lesson Learnt not related with ENI projects
8 Why Basic-FEED is the most important part of a Project? Pre-feas. Feasibility 1-3 MM 3-6 MM (typical ref.) Basic - FEED 3-9 MM (typical ref.) Detail Design & Procurement 9-18 MM (typical ref.) Construction MM (typical ref.) Construction Commissioning 12+ MM (typical ref.) $ value BOQ & Construction strategy Material Selection & Take-off Peak Construction Cost Project Cost Curvet Peak Material Cost Availability of Information time 8 During Basic FEED project costs can be properly evaluated by finalization of material selectio a d MTOs, owi g to that this phase is the ost i porta t for the go/ o go final assessment
9 Design approach Key points The Basic - FEED engineering shall be tailor fit to allow the correct definition of the i vest e t cost a d to support the go / o go decisio gate 3 (key deliverables fit for purpose to the activities and not vice-versa); In Basic FEED phase, the key deliverables allow to fix the material selection and estimate material take-offs which are the input for the procurement and construction strategy based on the project drivers; 9
10 Balance between engineering freezing and early procurement: Long Lead Items strategy 10
11 Long Lead Items definitions Those components of a system or piece of equipment for which the times to design and fabricate are the longest and for which an early commitment of funds may be desirable or necessary in order to meet the earliest possible date of system completion. 11
12 Critical Path The critical path is the sequence of activities that represents the longest path through a project, which determines the shortest possible project duration [PMBOK Critical Path Method] Appling Critical Path method for all the systems of a project, even material with a rather short delivery can result to be critical, owing to that we can split LLI in two categories: Typical LLI such as: High pressure equipment High temperature equipment Special Material equipment 12 Not Typical LLI such as: Tie-ins: integration with existing Facilities Bulk material for early commissioning system
13 Tie-ins: integration with existing Facilities REFERENCE GREEN-FIELD PROJECT SCHEDULE Pre-feas. 1-3 MM (typ.ref.) Feasibility 3-6 MM (typ.ref.) FEED 3-9 MM (typical ref.) Detail Design & Procurement 9-18 MM (typical ref.) PROCUREMENT PROCUREMENT FOR TRADITIONAL FOR LLI LLI Construction MM (typical ref.) Commissioning 3-12 MM (typical ref.) EARLY ENGINEERING EARLY CONSTRUCTION EARLY PROCUREMENT TIE-INS PRODUCTION PLAN of EXISTING FACILITIES EARLY COMMISSIONING UNIT 10 UNIT 20 UNIT 30 Plant to be disinvested Shutdown Shutdown Production Dismantelling Dismantling Production Shutdown OVERALL SCHEDULE INTEGRATED WITH PRODUCTION PLAN Feasibility Study TIE-INS FEED TIE-INS INSTAL. Shutdown Detail Design & Procurement TIE-INS INSTAL. Dismantling Construction Commissioning 13 Tie-ins shall be planed in an early stage of the project, with a dedicated engineering, construction and commissioning team. The project schedule incorporates the production plan in terms of turn-around or critical milestones.
14 Bulk Material for Early Commissioning System Engineering design for bulk material is aimed to produce MTOs with increased levels of definition Procurement generally follows the MTO by engineering based on master agreements or project agreements Construction strategy is divided into: 1 st phase by area 2 nd phase by system 14 During the engineering phase it is important to verify that the delivery of bulk material fits the Mechanical Completion dates (additional specific MTOs can be envisaged).
15 Long Lead Items strategy Key points The critical path developed for all the project systems allows us to recognize critical delivery items which do not have the longest delivery such as tie-ins or bulk material for early commissioning system, which shall be focused since the start of the project with a dedicated integrated team (engineering, construction and commissioning); For a revamping project, the integration of the production plan in the project baseline allows to execute tie-ins during turn-around, minimizing the number of shut-downs and avoiding unnecessary loss of production; 15
16 Fast Track: Basic, FEED & Detail Design phases in overlap aiming at Project goals If you're not confused, you're not paying attention. Tom Peters 16
17 Project objectives and Fast-Track Projects Pre-feas. 1-3 MM (typ.ref.) Feasibility 3-6 MM (typ.ref.) Basic - FEED 3-9 MM (typical ref.) Detail Design & Procurement 9-18 MM (typical ref.) Construction MM (typical ref.) Commissioning 3-12 MM (typical ref.) Opt.1) Compress the activity lengths Pre-F. Feasibil. FEED Detail Design & Procurement Opt.2) Fast-Track by parallelization of phases Feasibility Study FEED Detail Design & Procurement 17
18 Possible outcomes when implementing a Fast-Track in a project Relying upon preliminary information Overdesign material Design based on assumptions Increased interface management Not linear approach in decision making Higher Cost More Engineering Man-hours More Reworks More difficult engagement of personnel Increased possibility of inconsistencies Higher Risk Which it the greatest objective? 18
19 How to mitigate risks in fast-track projects Feasibility Study FEED Re-cycling Design inputs/outputs Detail Design & Procurement ENGINEERING Preliminary information evaluated from Basic (used for detail design) are always re-checked when more information are available ENGINEERING Final alignment mitigates risk of further phases for critical aspects D MATERIAL Material check/re-rated is re-consolidated both in Basic and Detail Design to avoid reworks during construction and commissioning MATERIAL When procurement cycle is long, procurement can be start with preliminary data, updating more consolidated information during the vendor alignment before PO Final alignment TEAM If the approach is aligned since the beginning with a common goal, all the team is aimed to support unavoidable project changes and reworks activities 19
20 Case Study Feasibility Study FEED Detail Design & Procurement D Project Organization Engineering Approach: Re-cycling Design 1. Process and Layout for critical circuit 2. 3D Model Review 30% and 60% 3. Material Selection 4. Vendor design 5. Design Philosophy Operating manual 20
21 Case Study Organization Chart OWNER FEASIBILI TY PRE- FEAS. LICENSOR FEASIBIL. CNT DETAILED ENG. BASIC - FEED FAST-TRACK BASIC FEED VENDOR VENDOR DETAIL ENG. VENDOR CONSTRUCTION SUB. CONSTRUCTION SUB. SUB. CONSTRUCTION SUB. Interface Management
22 #1: Process and Layout for critical circuit 2) PROCESS SCENARIOS (DESIGN CASES AND TRANSIENTS) 1) PRELIMINARY SIZE CALCULATION & PLOT PLAN PUMP FV s Valves Flow PSVs Valves Flow DISCHARGE File by FVA FVB FVC PSVA PSVB PSVC A B C IN OUT IN OUT IN OUT IN OUT IN OUT IN OUT Case EST9 4 SA EST9 4 SA EST9 4 SA EST9 4 SA EST9 4 SA EST9 4 SA EST9 4 SA x x x x x x x x x x x x x x x CEER 4 CEER CEER 4 CEER CEER 4 CEER CEER 4 CEER CEER 4 CEER CEER 4 CEER CEER 4 CEER CEER 4 CEER CEER 4 CEER In Process: Pump Nozzle Alignment for installation case, Pumps ABC at ambient CEER 4 CEER temperature, piping not anchored to the pumps. CEER 4 CEER In Process: Pump Nozzle Alignment for maintenaince case, Pump A, B or C as spare. CEER 4 CEER In Process: Tracing Failure Scenario analysis 3) STRESS CRITERIA WITH PRELIMINARY CRITICAL VERIFICATION AND TYPICAL DETAILS 4) 3D LAYOUT 6) UPDATING PROCESS LINE CALCULATION & PLOT PLAN 5) STRESS CALCULATION BASIC-FEED DETAIL ENGINEERING 22
23 #2: 3D Model Review 30% AND 60% DETAIL ENGINEERING BASIC-FEED BASIC-FEED DETAIL ENGINEERING 23
24 #3: Material Selection (Piping) Fluid list Piping Classes Process Fluid List Material Requirements Vendor Follow-up Material requisition & Purchase Order BASIC-FEED DETAIL ENGINEERING 24
25 #4: Vendor design Process DataSheet Material Requisition Mechanical and Material Check Vendor Follow-up BASIC-FEED DETAIL ENGINEERING 25
26 #5: Design Philosophy Operating manual Updated Control Philosophy Updating Process Design Design Scenarios Operating Scenarios Process Philosophy Operating Manual BASIC-FEED DETAIL ENGINEERING 26
27 Fast Track Key points The Fast Track with parallelization of phases which traditionally are developed sequentially is a possible strategy to meet Project Objectives when the schedule is challenging; To mitigate the risk associated to fast track (more interfaces, reworks, designing by conservative assumptions rather that consolidated data etc.) project team needs to be integrated with an interface management plan and dedicated engineering methods such as re-cycling and final alignment need to be set-up in the engineering execution plan. 27
28 Conclusions - Key Factors for Basic-FEED Projects Tailor fit Design by Project Objectives Advanced monitor of costs with correct Basic-FEED data System-wise approach since the beginning of the project For revamping, integration of project schedule with production plan Interface management, re-cycling and final alignment for fast-track project 28
Identification Selection Definition Execution. Schedule.
SCHEDULE DEVELOPMENT Schedule development is the identification, definition and sequencing of activities that are required to be performed for successful completion of the project scope. Identification
More informationInternational Construction Consulting, LLC. Modularization Overview.
International Construction Consulting, LLC Modularization Overview Presentation Overview 1 Modularization Overview 2 An Alternative Construction Method to Deliver Projects 3 Quick Selection Criteria for
More informationHSE Design Reviews and Action Close-out
HSE Design Reviews and Action Close-out Simon Round, Manager Design HSE, Amec Foster Wheeler, Shinfield Park, Reading, Berkshire RG2 9FW, UK HSE design reviews and the management and close-out of resulting
More informationLeading Indicators and Dashboarding for Advanced Work Packaging. Lloyd Rankin
Leading Indicators and Dashboarding for Advanced Work Packaging Lloyd Rankin Slide # AWP KPIs EWP RFI POC PWP CWP IWP 2017-10-24 Slide # 2 POC Defined Path of Construction (POC) Path of Construction is
More informationECC ENGINEERING MANAGEMENT STRATEGY WORKSHOP
TEAM: A ISSUE ADDRESSED: Issue 1 The cost and time required to complete engineering often exceeds the estimate. Describe the issue in specific terms, using realistic project scenarios as appropriate. Quality
More informationEngineering & Schematics
SmartPlant Enterprise Engineering & Schematics 2 Industry Challenges Engineering, Procurement, and Construction Companies (EPCs) During engineering, there is increasing pressure on margins and intense
More informationDoseo Pipeline Project Modularization Overview Advantages/Disadvantages & Drivers
PURPOSE Modularization will be evaluated herein as a cold eyes look into the potential construction technique to be applied to the Doseo Pipeline Project. This analysis will include a review of the drivers
More informationAdvanced Work Packaging IMPLEMENTATION
Advanced Work Packaging IMPLEMENTATION 5 October 2016 Antonio Romero-Monteiro Lionel Jagnanan Advanced Work Packaging AWP Definition AWP is the back-to-front project planning and execution process for
More informationTaking AWP to the Next Level
Taking AWP to the Next Level 10 May 2017 Antonio Romero-Monteiro Advanced Work Packaging AWP Definition Taking AWP to the Next Level AWP is the back-to-front project planning and execution process for
More informationTHE MISSING LINK - OBJECT ORIENTED ESTIMATING
71 THE MISSING LINK - OBJECT ORIENTED ESTIMATING A PAPER BY AAFJE JANSEN-ROMIJN During the decision making process of investment projects, it is often not possible to wait for the final cost estimate,
More informationProject and Program Management in ehealth
Project and Program Management in ehealth Foundational Curricula: Cluster 10: Leadership & Management Module 19: Project and Resource Management Unit 1: Project and Program Management in ehealth 53/60
More informationPROCESS & PRODUCTION ENGINEERING DIRECTORY
PROCESS & PRODUCTION ENGINEERING DIRECTORY INDEX 1.0 INTRODUCTION 4 2.0 PROCESS & PRODUCTION ENGINEERING SERVICES 5 2.1 Operating manuals and SOP/POG 5 2.2 Commissioning & start-up procedures 8 2.3 Simulation
More informationPath of Construction Enhancing the Best Practice for Engineering & Supply Chain to Support AWP Implementation
Path of Construction Enhancing the Best Practice for Engineering & Supply Chain to Support AWP Implementation Presenters Glen Warren COAA Co-Chair, Industry Expert Emeritus Yogesh Srivastava Intergraph,
More informationEST Accuracy of FEL 2 Estimates in Process Plants
EST.2215 Accuracy of FEL 2 Estimates in Process Plants Melissa C. Matthews Abstract Estimators use a variety of practices to determine the cost of capital projects at the end of the select stage when only
More informationDeliverables list for Projects in the fertilizer industry
Deliverables list for s in the fertilizer industry Document Development Guidance Department: s / Engineering Revision 1 August 2018 Doc. No: AKH01-GUI-ENG-LST-001 Contents 1. Synopsis... 2 2. Why develop
More informationGuten Tag. (good day)
Guten Tag (good day) Project Management Process Groups Project 4. Integration Management Knowledge Areas 13. Stakeholder Initiating Planning Executing 5. Scope 6. Time 7. Cost 8. Quality 9. Human Resources
More informationEstimating and Scheduling
Estimating and Scheduling Practical Tips and Techniques for Construction Scott Feeney, CPE, LEED AP Q1stCM Ram Ramdass, PMP, PSP Turner Construction April 2018 Today s Discussion: Scheduling techniques
More informationENGINEERING MANAGEMENT
ENGINEERING MANAGEMENT Identification Selection Definition Execution Develop engineering to sufficient detail to enable a Class 4 or 5 capital estimate to be prepared for the alternative. Use benchmarking,
More informationOil & Gas Project demands on Engineering
Hervé Baron SPE, Paris June 11 th, 2015 The Engineering of a Process Plant The role of Engineering The work process The Engineering of a Process Plant The role of Engineering The work process Process
More informationFeasibility Consulting & Successful Study Completion
Feasibility Consulting & Successful Study Completion Philippines Mineral Exploration Association Manila ~ 04 July 2011 Hugh Thompson Principal Mining Consultant Brisbane The views and opinions expressed
More information2.0 SCHEDULE DEVELOPMENT
Filed: 0-0- Exhibit D Tab Page of 0 0 0 PROGRAM SCHEDULE.0 OVERVIEW The ability to validate, integrate, oversee and ultimately to retain control over the program schedule is one of the key factors that
More informationThe execution of a Complex Project A guided tour
The execution of a Complex Project A guided tour The COMPANY Client The actors The EPC Contractor The suppliers The sub-contractors The phases Sanction Sanction Conceptual evaluation + Pre-Project By COMPANY
More informationChapter 3 Managing the Information Systems Project
Princess Noura University Computer Science and Information Faculty Information Systems Department IS321 Chapter 3 Managing the Information Systems Project Learning Objectives Discuss skills required to
More informationPMP Exam Preparation Course Project Time Management
Project Time Management 1 Project Time Management Processes Define Activities Sequence Activities Estimate Activity Resources Estimate Activity duration Develop Schedule Control Schedule In some projects,
More informationGlobal Project Management, LLC
Global Project Management, LLC 2250 Gause Boulevard, Suite 310 Slidell, Louisiana 70461 Tel: 985-781-9190 A Projectis a temporary endeavor undertaken to create a unique product, service, or result. Initiation
More informationChapter 4 Project Management
Chapter 4 Project Management For internal use of BSNL only Page 1 Project Management 1.0 Introduction Project management is concerned with the overall planning and co-ordination of a project from conception
More informationImportance of Adequate Interface Management and Systems Integration
Importance of Adequate Interface Management and Systems Integration Navin, Sagar, PE, MBA, MEE Vice President, HDR Inc., USA Content Discuss: Interface Management & Systems Integration as encountered in
More informationGLOBAL ENERGY FORUM. Managing Large EPC Projects with Data at Your Fingertips. Maurice Tayeh. February 20 th, 2014 Houston, Texas
GLOBAL ENERGY FORUM Managing Large EPC Projects with Data at Your Fingertips Maurice Tayeh February 20 th, 2014 Houston, Texas Global Capabilities and Expertise McDermott is a leading engineering, procurement,
More informationEffective Control of Instrumentation and Control (I&C) Modernization, Methods and Tools
Effective Control of Instrumentation and Control (I&C) Modernization, Methods and Tools Presented by: Zakia Rabbani Deputy Chief Engineer, Karachi Nuclear Power Plant, Pakistan Presented at 2 nd International
More informationFULLY INTEGRATED SCHEDULE FOR A REACTOR DECOMMISSIONING PROJECT. G. Cross, BNFL Inc.
FULLY INTEGRATED SCHEDULE FOR A REACTOR DECOMMISSIONING PROJECT G. Cross, BNFL Inc. ABSTRACT The paper discusses the process of generating a fully integrated schedule for a Reactor Decommissioning Project
More informationCMMI V2.0 MODEL AT-A-GLANCE. Including the following views: Development Services Supplier Management. CMMI V2.0 outline BOOKLET FOR print.
CMMI V.0 MODEL AT-A-GLANCE Including the following views: Development Services Supplier Management CMMI V.0 outline BOOKLET FOR print.indd CMMI V.0 An Integrated Product Suite Designed to meet the challenges
More informationWM2014 Conference, March 2 6, 2014, Phoenix, Arizona, USA
Reactor D&D: AREVA French and German Latest Experiences - 14458 (1) Stephan Krüger, AREVA GmbH, Kaiserleistr. 29, 63067 Offenbach, Germany; stephan.krueger@areva.com (2) Xavier de Brimont, AREVA NC, 1
More informationBuilding an ERP Project Work Breakdown Structure - a few common scenarios
Building an ERP Project Work Breakdown Structure - a few common scenarios One of the keys to success in and ERP project is to have a solid understanding of what activities that needs to be included for
More informationE2-E3: MANAGEMENT. CHAPTER-3 PROJECT MANAGEMENT (Date of creation: )
E2-E3: MANAGEMENT CHAPTER-3 PROJECT MANAGEMENT (Date of creation: 01-04-2011) Page: 1 Project Management Introduction: Project management is concerned with the overall planning and co-ordination of a project
More informationProject Management Consultancy Services. Ensuring safe and successful execution of your projects
Project Management Consultancy Services Ensuring safe and successful execution of your projects Deep expertise in Project Management Consultancy TechnipFMC s Project Management Consultancy business unit
More informationCity of San Mateo Clean Water Program Programmable Logic Controller (PLC) and Human Machine Interface (HMI) Programming Services
ATTACHMENT A SAMPLE SCOPE OF SERVICES PLC & HMI PROGRAMMING City of San Mateo Clean Water Program Programmable Logic Controller (PLC) and Human Machine Interface (HMI) Programming Services December, 2017
More informationProject Execution Plan For
Project Execution Plan For [Insert Name Here] Project Document Revision History Revision Date Project Manager Project Sponsor Page 1 of 24 About This Project Execution Plan Template: This template is intended
More informationTenStep Project Management Process Summary
TenStep Project Management Process Summary Project management refers to the definition and planning, and then the subsequent management, control, and conclusion of a project. It is important to recognize
More informationREPRINTED FROM MAGAZINE JANUARY/FEBRUARY 2017
REPRINTED FROM MAGAZINE JANUARY/FEBRUARY 2017 G. MANENTI, V. PESCUMA AND S. SARTI, ALFA LAVAL OLMI SPA, ITALY, PROVIDE AN OVERVIEW OF THE DELIVERY SCHEDULE FOR A KEY PIECE OF HEAT TRANSFER EQUIPMENT, PROCESS
More informationValue improving practices for revamp and greenfield projects in fertilizer industry
Value improving practices for revamp and greenfield projects in fertilizer industry Document Development Guidance Department: Engineering / Projects Revision 1 September 2018 Doc. No: AKH01-GUI-ENG-PHY-003
More informationProject Production Institute Challenges and Myths of Offsite Fabrication for Mega Projects
Project Production Institute Challenges and Myths of Offsite Fabrication for Mega Projects Alan Richard Director Capital Projects Deloitte Transactions and Business Analytics LLP December 3, 2014 How did
More informationSoftware Global Customer Conference
Intergraph Process, Power & Marine Smart Engineering from Concept to Operations Software Global Customer Conference Presenter: Paras Trivedi - Frank Joop Product Owner SPP&ID/SPPE Executive Director Global
More informationSGM Engineering, Inc.
SGM Engineering, Inc. 1. What is a typical Central Energy Plant consists of? BAS controls, chillers, pumps, cooling towers, electrical distribution, piping, chemicals, heating systems, and generators.
More informationInformation Technology Audit & Cyber Security
Information Technology Audit & Cyber Security Managing Information System Projects Systems & Infrastructure Lifecycle Management Introduction Definitions INTRODUCTION Governance Roles and Responsibilities
More informationManaging Schedule Change
Managing Schedule Change Ted Douglas, CCP, PSP, FAACE CPM Construction Conference Orlando, Florida January 11, 2017 Managing Schedule Change Outline Change Drivers Contract Changes Clause Schedule Change
More informationDIRECTIVE 15H-9 Issue date: October 2018 COMMISSIONING
DIRECTIVE 15H-9 Issue date: October 2018 COMMISSIONING Purpose: The purpose of this Directive is to describe, in outline, the requirements of Commissioning on SUCF Projects. 1. Applicability a. New York
More informationStatement of Work. 1.0 Executive Summary. InfraStruXure Site Coordination - 1 InfraStruXure - Site Coordination. Installation Services
Installation Services Statement of Work InfraStruXure Site Coordination - 1 InfraStruXure - Site Coordination Service 1.0 Executive Summary Table of Contents 1.0 Executive Summary 2.0 Features & Benefits
More informationLecture- 10. Project Scheduling. Dronacharya College of Engineering
Lecture- 10 Project Scheduling Dronacharya College of Engineering Scheduling and Planning The majority of projects are 'completed' late, if at all. A project schedule is required to ensure that required
More informationFluid Catalytic Cracking (FCC) delivering Predictable Results
Fluid Catalytic Cracking (FCC) delivering Predictable Results Wood Group Mustang brings vast process plants experience to your project. Our process engineers and project managers average more than 20 years
More informationProject Management Consultancy Services. Ensuring safe and successful execution of your projects
Project Management Consultancy Services Ensuring safe and successful execution of your projects Deep expertise in Project Managem TechnipFMC s Project Management Consultancy business unit supports contract
More informationTVU CCS Pre FEED Study Outline Execution Strategy for delivery of SSI Anchor Project including CO 2 Transportation & Storage Infrastructure
TVU CCS Pre FEED Study Outline Execution Strategy for delivery of SSI Anchor Project including CO 2 Transportation & Storage Infrastructure Additional Information Regarding The Implementation Programme
More informationProject Management Auditing Guide
Project Management Auditing Guide Index Page 1.0 Objective 4 2.0 Risks 4 3.0 Safeguards and Controls 3.1.Project Characteristics 4 3.2.Quality in Project Management Process 4 3.3.Strategic Processes 5
More informationWhy end users are selecting Foundation Fieldbus
Why end users are selecting Foundation Fieldbus Business Climate Contractor s Role Process Design FEED Project Management Owner s Engineer Detailed Engineering Construction and Startup Maintenance 2 Range
More informationA COMPLICATED PROJECT FOR POWER AND WATER CO- GENERATION: THE RAF SITE
A COMPLICATED PROJECT FOR POWER AND WATER CO- GENERATION: THE RAF SITE Authors: Presenter: M. Garzoglio, L. Riccardo M. Garzoglio [Process Senior Eng. Fisia Italimpianti Italy] Abstract The Ras Abu Fontas
More informationTime has the least. amount of flexibility; Schedule issues are the main reason for
PMBOK 5 Ed. DEI- Time has the least amount of flexibility; Schedule issues are the main reason for conflicts on projects, especially during the second half of projects The process required to manage timely
More informationCurrent State of PSM
Current State of PSM Hydrocarbon Process Industry has exacting PSM audit requirements Current state of art tends more to manual or antiquated data processing systems Issues of data migration, operations
More informationThis guide is applicable to River Protection Project - Waste Treatment Plant (RPP-WTP) project suppliers and is intended for supplier use only.
1.0 Objective 2.0 Scope Provide guidance to those suppliers preparing and submitting quality verification documents to Bechtel National Inc. (BNI), when required by a Bechtel National Inc. (BNI) Purchase
More informationDefinition. Name of the tool or technique Project mission statement
Tools and Techniques Definitions (or by alphabetic order ; see below) A definition of each of the tools and techniques is provided below. The primary sources of definitions were the PMBOK Guide and Max
More informationAgeing Management and Development of a Programme for Long Term Operation of Nuclear Power Plants
DS485 17 July 2017 IAEA SAFETY STANDARDS for protecting people and the environment STEP 13: Establishment by the Publications Committee Reviewed in NSOC (Asfaw) Ageing Management and Development of a Programme
More informationTop 10 Areas for Productivity Improvement on Alberta Mega Oil Sands Construction Projects
Top 10 Areas for Productivity Improvement on Alberta Mega Oil Sands Construction Projects George F. Jergeas PhD, PEng Professor of Project Management, University of Calgary October 24, 2012: BREAKOUT:
More informationRisk Mitigation in a Core Banking Conversion
Risk Mitigation in a Core Banking Conversion Greg Meidt, chief information officer Chemical Bank Dick Smies, vice president IBS Conversion Services 1 800 822 6758 Introduction A core banking migration
More informationAttachment J-4 Milestone Acceptance Criteria and Payment Schedule
Attachment J-4 Milestone Acceptance Criteria and Payment Schedule Page 1 of 7 For Base, CLIN 001: Milestone Payment Event Integrated System Baseline Review (ISBR) Milestone Objective: At a NASA and Contractor
More informationModern Systems Analysis and Design Seventh Edition
Modern Systems Analysis and Design Seventh Edition Jeffrey A. Hoffer Joey F. George Joseph S. Valacich Managing the Information Systems Project Learning Objectives ü Explain the process of managing an
More informationSMARTPLANT ENTERPRISE
SOLUTION SMARTPLANT ENTERPRISE Engineering & Schematics Industry Challenges ENGINEERING, PROCUREMENT, AND CONSTRUCTION COMPANIES (EPCs) Projects are growing more complex. They are larger, workshared with
More informationServiceNow Integration Services
Overview Service Description July 2013 address integrations between ServiceNow and Customer or third party systems to ensure that Customer s configurations align with ServiceNow best practices for manageability,
More informationQUALITY INTEGRATED ENGINEERING SERVICES to the energy sector
QUALITY INTEGRATED ENGINEERING SERVICES to the energy sector COMPANY PROFILE offers a complete service including Project Management, Engineering, Procurement, Construction Management, Training and related
More informationA White Paper February System for piping global management
A White Paper February 2004 System for piping global management Page blank Table of contents Summary... 4 Modules... 5 Piping Classes... 6 Data Dictionaries 6 Tables 6 Piping Classes 7 Branch Tables 7
More informationNinth Edition. Rita Mulcahy, PMP, etai. Rita Mulcahy s. Inside this book:
Rita s Course in a Book for Passing the Project Management Professional (PMP) Exam Rita Mulcahy s Ninth Edition Inside this book: Tricks of the Trade What you really need to know to pass the exam Straightforward
More informationPilot Plant Cost Factors Guide
Pilot Plant Cost Factors Guide Factors That Raise the Cost of a Pilot Plant Process systems typically have two types of cost. The first category of costs: upfront capital required to design and build the
More informationCanada. Iron and Steel Sector - PI Specifics
How can process integration help me? Process integration (PI) is a very efficient approach to improving the energy efficiency of large and complex industrial facilities. PI refers to the application of
More information3 PART THREE: WORK PLAN AND IV&V METHODOLOGY (SECTION 5.3.3)
3 PART THREE: WORK PLAN AND IV&V METHODOLOGY (SECTION 5.3.3) Emagine IT s approach to Independent Verification and Validation (IV&V) has been shaped over the years by hands-on experience and contributions
More informationEmerson Digital Twin: A Key Technology for Digital Transformation
Emerson Digital Twin: A Key Technology for Digital Transformation Introduction As decision-makers in the process industry embrace Digital Transformation to improve visibility over their businesses, to
More information4. Which of the following statements are true regarding The Project Scope Statement based on the PMBOK 5h Edition?
1. Which of the following is true regarding the project charter? A. The project charter is a document that formally authorize a project or phase.. B. The project charter represent a high level planning
More information7. Model based software architecture
UNIT - III Model based software architectures: A Management perspective and technical perspective. Work Flows of the process: Software process workflows, Iteration workflows. Check Points of The process
More informationDo not open this paper until instructed by the invigilator. Please note: This question paper must not be removed from the examination room.
APM Project Fundamentals Qualification Examination paper Candidate Number Date Location Examination Paper Sample Paper v1.4 General Notes Time allowed 1 hour. Answer all 60 multiple choice questions Use
More informationNetwork Diagram 11/10/2016 WORK BREAKDOWN STRUCTURE (WBS)
/11/16 Network Diagram 11//16 1 WORK BREAKDOWN STRUCTURE (WBS) A work breakdown structure is a key project deliverable that organizes the team's work into manageable sections. The Project Management Body
More informationSmartSPEND. KBR SmartSPEND SM. The Economic Approach to Project Development and Execution that Delivers Maximum Project Returns
SM Your Capital Optimized : Project Delivery Execution Strategy Capacity Operations KBR SM The Economic Approach to Project Development and Execution that Delivers Maximum Project Returns KBR SM Approach
More informationWelcome to lecture 4 of Topic 2.9. In this lecture we focus on Phase 2 of the Project Management Lifecycle the planning phase
Welcome to lecture 4 of Topic 2.9. In this lecture we focus on Phase 2 of the Project Management Lifecycle the planning phase 1 The main aim of the planning phase of the project management lifecycle is
More informationVI International Forum ATOMEXPO 2014
VI International Forum ATOMEXPO 2014 Moscow, 9 th to 11 th June, 2014 Gostiny Dvor Round Table: Planning and Optimization of the NPP Generated Power Cost at the Design and Construction Stages NPP Capital
More informationProject Time Management
Project Time Management Project Time Management Project Time Management includes the processes required to manage timely completion of the project. Plan schedule management The process of establishing
More informationFlorida PALM Quarterly Project Oversight Report: Comprehensive Review For April - June 2015
Department of Financial Services Florida Planning, Accounting, and Ledger Management (PALM) For Period: April June 2015 Project Description Quarter Ending: 6/30/2015 Agency Name: Department of Financial
More informationProject Management Process Groups. PMP Study Group Based on the PMBOK Guide 4 th Edition
Project Management Process Groups PMP Study Group Based on the PMBOK Guide 4 th Edition Introduction PM Process Groups In order for a project to be successful, the project team must: Select appropriate
More informationENGINEERING SERVICES
ICONS... ICONS ENGINEERING SERVICES Contact us at: Ph: (+91) 9704 038 648 E-mail: contactus@iconsengg.com Web: http:// ABOUT US A group of professionals imbibed with the power of knowledge thru many years
More informationApplying Dynamic Process Simulations Toward Flaring Reduction
Applying Dynamic Process Simulations Toward Flaring Reduction White Paper Siemens AG 2018, All rights reserved 1 Dynamic process simulation has traditionally been a tool of process engineers and process
More informationThe 9 knowledge Areas and the 42 Processes Based on the PMBoK 4th
The 9 knowledge Areas and the 42 Processes Based on the PMBoK 4th www.pmlead.net PMI, PMP, CAPM and PMBOK Guide are trademarks of the Project Management Institute, Inc. PMI has not endorsed and did not
More informationDefine and Initiate SubPhase
Project Management Methodology Project Management Methodology Training Define and Initiate SubPhase Course Purpose Familiarize team members with the Start Project Sub-Phase processes. Understand process
More information1. Project Definition
Project System Audit Electrical Group Note: Not all items of the checklist shall be checked. It depends on the status of the work and whether it is the first, second or third audit. = EH&S related question
More informationEngineering Management Manual
Engineering Management Manual Configuration Management ED0014 Document Category: DMS: Document Control: Procedure CRN-EPR-ENG-014 Version Date Author/discipline Reviewer Approver Remarks 1.0 13/12/2011
More informationProject Management Professional (PMP) Exam Prep Course 4 - Project Integration Management
Project Management Professional (PMP) Exam Prep Course 4 - Project Integration Management Slide 1 Project Integration Management Looking Glass Development, LLC (303) 663-5402 / (888) 338-7447 4610 S. Ulster
More informationDesign of Instrumentation and Control Systems for Nuclear Power Plants
Date: 2014 March 21 IAEA SAFETY STANDARDS for protecting people and the environment Draft M Step 10 Addressing Member States for comments. Design of Instrumentation and Control Systems for Nuclear Power
More informationIn general, a model is used to understand a system. It is only a representation of a more complicated original system based on mutual
In general, a model is used to understand a system. It is only a representation of a more complicated original system based on mutual characteristics, that is used for a specific exercise by a third system.
More informationA DESIGN PROCESS MODELING APPROACH INCORPORATING NONLINEAR ELEMENTS
Proceedings of 1998 DETC: ASME Design Theory and Methodology Conference September 13-16, 1998, Atlanta DETC98-5663 A DESIGN PROCESS MODELING APPROACH INCORPORATING NONLINEAR ELEMENTS Johan Andersson Department
More informationXXX Development. Facility Feasibility & Option Selection Plan
Facility Feasibility & Option Selection Plan C For Information Jan 3 2015 MR JM / SC DL Rev Status Date Author Checker Lead EM PM Document Title: XXX Facility Feasibility & Option Selection Plan DRL Document
More informationWell Delivery Process A Proven Method to Improve Value and Performance While Reducing Costs. IADC/SPE
Well Delivery Process A Proven Method to Improve Value and Performance While Reducing Costs. IADC/SPE 128716 John P de Wardt DE WARDT AND COMPANY INC. www.dewardt.com To day I will cover the following
More informationAbsolute Energy Raters Commissioning Plan Outline Template
IMPORTANT NOTICE: This sample document is provided for instructional purposes only. Absolute Energy Raters is not rendering advice concerning any commission project or practices. This document is neither
More informationProject Management. Risk Management
Brandt s History of IV&V Success Using over 30 years of experience supporting local, state, and federal agencies, Brandt provides IV&V services using proven, strategic methodologies to ensure project success
More informationOrganization and Responsibilities of Internal/External TSO
Organization and Responsibilities of Internal/External TSO International Conference on Challenges Faced by TSOs in Enhancing Nuclear Safety and Security Beijing, 29 October, 2014 N. Kilic IAEA-NE Content
More informationProject Engineering Support for the Site Construction Preparation and Coordination Activities. Technical Specification
Project Engineering Support for the Site Construction Preparation and Coordination Activities Technical Specification Page 1 of 8 Table of Contents 1. SCOPE OF WORK...3 2. ESTIMATED DURATION...3 3. WORK
More informationCONSIDERATIONS AND MILESTONES INFRASTRUCTURE FOR A RESEARCH REACTOR PROJECT
Invited Paper C1 CONSIDERATIONS AND MILESTONES INFRASTRUCTURE FOR A RESEARCH REACTOR PROJECT A.M. SHOKR, H. ABOU YEHIA Department of Nuclear Safety and Security, International Atomic Energy Agency (IAEA),
More information