1 Importance of Adequate Interface Management and Systems Integration Navin, Sagar, PE, MBA, MEE Vice President, HDR Inc., USA

2 Content Discuss: Interface Management & Systems Integration as encountered in typ. rail projects Why it is Needed Typical Approach Plan and Basis Process and Associated Tasks Documents Typical Interfaces Organization Lessons Learned Goal: Enhance the importance of Interface Management & Systems Integration 2

3 Interface Management & Systems Integration Why It Is Needed? Projects getting more Complex & Demanding Contract delivery options: PPP, D-B, DBO&M, etc. keen on meeting bottom line, performance, efficiency and schedule New Starts or Improvement Projects: Focused approach for Infrastructure development Integration and testing Seamless operation Railroad Agencies Concerns Fading funding streams, overruns and delays Need to increase local participation and distribute work increases the interfaces and entities to interface Lack of Staffing 3

4 Interface Management & Systems Integration Approach IM & SI Plan shall be Integral to Eng Mgt Plan: Focused and Logical, Structured and Documentable Built-in tools for managing, controlling, tracking and verifying interfaces Plan ensures that Civil facilities are compatible within the facility Civil and Infrastructure elements are fully integrated with all Systems elements Civil and Systems elements function as Planned, designed and Constructed Basis of IM & SI Client/Railroad Agency defined Project Objectives, O&M Parameters+ RAMS Design Criteria, Standards and Directive Drawings Requirements specific to the Project Stakeholders Project Participants and Third- Parties having jurisdiction Existing Systems, External & Internal Interfaces Test & Commissioning Requirements 4

5 Interface Management & Systems Integration Approach Interface Management Process Capable to Identify - Define - Describe - Coordinate - Clarify - Resolve - Document Achieve desired functionality of integrated systems Prevent unnecessary rework, cost overruns and schedule delays Structured to Continue throughout the Project Life Cycle Tasks within Interface Management Process Identify and define all interfaces for all phases of the scope Ensure that interfacing systems are designed to the same requirements All participants are identified and committed Schedule, hold regular meetings and document to coordinate and track interfaces Ensure that all interfaces are resolved and verified before prerevenue testing 5

6 Typical Framework of Interface Management Functional Analysis Matrix Block Diagrams Interface Matrix Interface Register Interface Design Procedures Define Interfaces Integration Documents Identify Interfaces Interface Management Framework New Design Existing System User Requirements Functional Requirements Change Management and Traceability Interface Database Compliance Requirements Configuration Management & Control/Reports Design Procurement Installation Testing Implementation Process Testing & Validation FAT Test Sequence Field Test Test Organization Validation / Verification Requirements 6

7 Typical Interface Management Process Through Project Life Cycle Operation Requirements Concept of Operations Plan, Basis of design Systems Acceptance Plan & RAMS Validation & Acceptance Performance Demonstration Planning Phase Functional Analysis Certified Test Reports, Deliverables & Verification System Safety Certification Verification & Safety Certification Verification & Certification Design Phase & Integration during Design & Procurement Infrastructure Facilities Systems Vehicles Power OCS Signal Communication Control Center Vehicles Existing Systems Interfaces Overall Systems Design Long Lead Equip Material Equipment FAT QA/QC Test & Commissioning Plan Interface Management Plan Procurement Doc.Control Document & Configuration Control Manufacturing Construction Installation Integration Testing & Commissioning System Integration during Const. Field Testing Local Remote Power OCS Signaling & Communications Control Center Vehicles Delivery Testing Phase Installation Phase & Integration during Mfg. + Construction 7

8 Interface Management & Systems Integration Typical List of Documents U.S. Clients or Railroads Require: Interface Responsibility Matrix Project Integration Implementation Plan Interface Tasks and Phasing Matrix Interface Block Diagrams Composite Drawings Interface Coordination and Systems Integration Checklists Test Plan Equipment Matrix Interface Control Documents Systems Integration Database 3-D Models/Drawings 8

9 Interface Management & Systems Integration Typical List of Interfaces Interfaces during Design, Procurement & Construction Stakeholders and other participants Third Parties having jurisdiction Adjacent Contract related Civil/Infra, Tracks, Alignment Facilities, Vehicles and Systems Vendors and Suppliers Interfaces with Client or Agency for Force Account Supports As-Built Drawings and deviations there from O&M Requirements including RAMS Interfaces with existing operating segment Test & Commissioning Requirements Training 9

10 Typical Interface Management Organization Project Manager Technical Resolution Committee QA/QC Design Mgr Design Coordination Mgr Construction Mgr System Safety Civil/Infra, Track & Structural Design Architectural and Facilities Design Interface & Systems Integration Mgr Civil/Infra, Track & Structural Construction Architectural and Facilities Construction Systems Design Vehicles and Existing Systems Coordination Force Account Coordination Tests and Commissioning Vendors and Systems Construction Traction Power OCS Signaling & TC Communications Coordination with Other Contracts Traction Power OCS Signaling & TC Communications 10

11 Lessons Learned Plan for a meaningful Interface Management and Systems Integration Set reasonable IM & SI goals and requirements in proportion to the size and complexity of the Project Assign Systems Integration Manager from the inception of the Project. Provide support staff in proportion to the responsibilities Empower him with authority to make timely decisions Hold him responsible and accountable for Interface Management and Systems Integration Provide IM & SI throughout the Project Life-Cycle Do not Expect Miracles If Adequate Resources are not provided to perform Effective and Efficient Interface Management & Systems Integration 11

12 ...Thank you...thank you for your kind attention

MANUAL QUALITY CONTROL & QUALITY ASSURANCE

MANUAL QUALITY CONTROL & QUALITY ASSURANCE MANUAL QUALITY CONTROL & QUALITY ASSURANCE METROTEC ENGINEERING LLC P.O. BOX: 26045, DUBAI U.A.E TEL : 043889771 FAX:043889772 E Mail: metrotecengg@yahoo.com info@metrotec.ae Web: www.metrotec.ae 2 TABLE

More information

SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES

SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES SECTION: SFPUC INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURE NO: 018 TITLE: SYSTEM TESTING AND START-UP APPROVED:

More information

DORNERWORKS QUALITY SYSTEM

DORNERWORKS QUALITY SYSTEM DORNERWORKS QUALITY SYSTEM ALIGNMENT WITH CMMI INTRODUCTION Since its beginning, DornerWorks has had quality as one of our main goals. We have delivered solutions for over a dozen aircraft, including several

More information

This guide is applicable to River Protection Project - Waste Treatment Plant (RPP-WTP) project suppliers and is intended for supplier use only.

This guide is applicable to River Protection Project - Waste Treatment Plant (RPP-WTP) project suppliers and is intended for supplier use only. 1.0 Objective 2.0 Scope Provide guidance to those suppliers preparing and submitting quality verification documents to Bechtel National Inc. (BNI), when required by a Bechtel National Inc. (BNI) Purchase

More information

Engineering Management Manual

Engineering Management Manual Engineering Management Manual Configuration Management ED0014 Document Category: DMS: Document Control: Procedure CRN-EPR-ENG-014 Version Date Author/discipline Reviewer Approver Remarks 1.0 13/12/2011

More information

Quality Manual. Specification No.: Q Revision 07 Page 1 of 14

Quality Manual. Specification No.: Q Revision 07 Page 1 of 14 Page 1 of 14 Quality Manual This Quality Manual provides the overall quality strategy and objectives of Pyramid Semiconductor s quality system. It is based on the requirements of ISO 9000. This manual

More information

RISSB Product Proposal (and Prioritisation)

RISSB Product Proposal (and Prioritisation) RISSB Product Proposal (and Prioritisation) Primary information Type of product being suggested: Title of product being suggested: Guideline Rail System Description Models Date of suggestion: 12/02/2019

More information

PART THREE: Work Plan and IV&V Methodology (RFP 5.3.3)

PART THREE: Work Plan and IV&V Methodology (RFP 5.3.3) PART THREE: Work Plan and IV&V Methodology (RFP 5.3.3) 3.1 IV&V Methodology and Work Plan 3.1.1 NTT DATA IV&V Framework We believe that successful IV&V is more than just verification that the processes

More information

Engineering Process Transformation driven by Use Cases.

Engineering Process Transformation driven by Use Cases. Engineering Process Transformation driven by Use Cases juergen.schmied@methodpark.com 1 From Process Models to Projects Corporate Initiatives Six Sigma 16949 PMI CMMI 26262 Automotive SPICE One group,

More information

Quality Assurance Policy and Procedures

Quality Assurance Policy and Procedures 650 Montana Ave, Suite A Las Cruces, NM 88001 (575) 522-0430 www.rmgovernmentservices.com Quality Assurance Policy and Procedures PURPOSE. The purpose of this policy is to outline the quality assurance

More information

Project Procedures 1.0 PURPOSE 2.0 SCOPE 3.0 REFERENCES. No.: P /21/2012 PAGE 1 OF 13 BASIS OF OPERATION

Project Procedures 1.0 PURPOSE 2.0 SCOPE 3.0 REFERENCES. No.: P /21/2012 PAGE 1 OF 13 BASIS OF OPERATION Project Procedures BASIS OF OPERATION 09/21/2012 PAGE 1 OF 13 1.0 PURPOSE The purpose of this procedure is to establish the basis of operations that ensures that Project activities, including engineering,

More information

QUALITY ASSURANCE PLAN OKLAHOMA DEPARTMENT OF HUMAN SERVICES ENTERPRISE SYSTEM (MOSAIC PROJECT)

QUALITY ASSURANCE PLAN OKLAHOMA DEPARTMENT OF HUMAN SERVICES ENTERPRISE SYSTEM (MOSAIC PROJECT) QUALITY ASSURANCE PLAN OKLAHOMA DEPARTMENT OF HUMAN SERVICES ENTERPRISE SYSTEM (MOSAIC PROJECT) MOSAIC Quality Assurance Plan v04.02 Prepared by: Approved by: QUALITY ASSURANCE PLAN APPROVALS QA/QC Program

More information

Title: Project Director Location: Tallahassee, FL Clearance: none required

Title: Project Director Location: Tallahassee, FL Clearance: none required Title: Project Director Location: Tallahassee, FL Clearance: none required Position Overview: The Project Director (PD) shall define, establish, and direct the planning and operations of the Project Management

More information

A. Title: Systems Integration on a Light Rail Project: A Tale of Two Agencies

A. Title: Systems Integration on a Light Rail Project: A Tale of Two Agencies A. Title: Systems Integration on a Light Rail Project: A Tale of Two Agencies B. Authors: Jennifer Ryan, PE, Primary Author East Link Systems Integration Lead For H-J-H JV Final Design Team Hatch Mott

More information

Compliance & Validation Validation of Software-as-a-Service (SaaS Solutions)

Compliance & Validation Validation of Software-as-a-Service (SaaS Solutions) www.arisglobal.com A White Paper Presented By ArisGlobal Compliance & Validation Validation of Software-as-a-Service (SaaS Solutions) ARIS GLOBAL CORPORATE HEADQUARTERS ArisGlobal, 1266 East Main Street,

More information

Project Management Auditing Guide

Project Management Auditing Guide Project Management Auditing Guide Index Page 1.0 Objective 4 2.0 Risks 4 3.0 Safeguards and Controls 3.1.Project Characteristics 4 3.2.Quality in Project Management Process 4 3.3.Strategic Processes 5

More information

ADVANCED INTERNAL AUDIT WORKSHOP

ADVANCED INTERNAL AUDIT WORKSHOP ADVANCED INTERNAL AUDIT WORKSHOP By Paul J. Kunder RABQSA QMS Lead Auditor/Aerospace Industry Experienced Auditor RABQSA Approved Aerospace Auditor Transition Training (AATT) Trainer Vice Chair U.S. Z1A

More information

GENERAL REQUIREMENTS FOR ENGINEERING AND DESIGN

GENERAL REQUIREMENTS FOR ENGINEERING AND DESIGN Project Procedures GENERAL REQUIREMENTS FOR ENGINEERING AND DESIGN 07/28/2011 PAGE 1 OF 7 1.0 PURPOSE 1.1 PURPOSE OF ENGINEERING PROJECT PROCEDURES This P-4 series of Engineering Project Procedures provides

More information

7. Model based software architecture

7. Model based software architecture UNIT - III Model based software architectures: A Management perspective and technical perspective. Work Flows of the process: Software process workflows, Iteration workflows. Check Points of The process

More information

Job Family Matrix. Core Duties Core Duties Core Duties

Job Family Matrix. Core Duties Core Duties Core Duties Job Function: Information Technology Job Family Matrix Job Family: IT Project Management - Professional Job Family Summary: Perform or manage a range of activities related to the design, planning, execution,

More information

9110 Correlation matrices

9110 Correlation matrices 9110 Correlation matrices 9110:2016 to 9110:2012 9110:2012 to 9110:2016 This document provides correlation matrices from 9110:2016 to 9110:2012 and 9110:2012 to 9110:2016. This document can be used to

More information

Applying Systems Engineering to ITS Projects: Advancing Beyond Federal Rule 940. INCOSE IW Transportation Working Group January 27, 2015

Applying Systems Engineering to ITS Projects: Advancing Beyond Federal Rule 940. INCOSE IW Transportation Working Group January 27, 2015 Applying Systems Engineering to ITS Projects: Advancing Beyond Federal Rule 940 William Gleckler Deputy Systems Engineering Officer, NYCT Capital Program Management Vincent Cavataio, CCM Deputy Systems

More information

For. Planning and Research Related to Procurement of a Systems Integration, Enhancements to a MMIS, New Fiscal Agent, and a Replacement DSS

For. Planning and Research Related to Procurement of a Systems Integration, Enhancements to a MMIS, New Fiscal Agent, and a Replacement DSS IMPLEMENTATION ADVANCE PLANNING DOCUMENT - UPDATE For Systems Integrator/ Florida Medicaid Management Information System/ Fiscal Agent Operations/ Decision Support System For Planning and Research Related

More information

S2 IT GROUP IT AND CLOUD CONSULTING CORPORATE TRAINING QUALITY ASSURANCE & PRODUCTION SUPPORT SOFTWARE DEVELOPMENT YOUR ON-SHORE IT PARTNER

S2 IT GROUP IT AND CLOUD CONSULTING CORPORATE TRAINING QUALITY ASSURANCE & PRODUCTION SUPPORT SOFTWARE DEVELOPMENT YOUR ON-SHORE IT PARTNER INFORMATION BY YOU, TECHNOLOGY BY US YOUR ON-SHORE IT PARTNER IT AND CLOUD CONSULTING SOFTWARE DEVELOPMENT QUALITY ASSURANCE & PRODUCTION SUPPORT CORPORATE TRAINING ARE THESE VALID CONCERNS Not having

More information

BABOK v3 Task to Technique Mapping

BABOK v3 Task to Technique Mapping BABOKv3 Task Technique # Technique Name Knowledge Area Business Planning and Monitoring Plan Business Approach 10.18 Document 10.20 Financial Plan Stakeholder Engagement 10.9 Business Rules 10.18 Document

More information

Executive Steering Committee Medicaid Eligibility System

Executive Steering Committee Medicaid Eligibility System Medicaid Eligibility System Project Project Governance April 26, 2013 Medicaid Eligibility System External Stakeholders DCF Project Team Medicaid Eligibility System 2 (ESC) Critical success factor for

More information

Quality Manual TABLE OF CONTENTS APPROVAL SIGNATURE PAGE AMENDMENT RECORD SCOPE EXCLUSIONS 2.1 3

Quality Manual TABLE OF CONTENTS APPROVAL SIGNATURE PAGE AMENDMENT RECORD SCOPE EXCLUSIONS 2.1 3 TABLE OF CONTENTS DESCRIPTION SECTION PAGE INTRODUCTION 1.0 1 APPROVAL SIGNATURE PAGE 1.1 1 AMENDMENT RECORD 1.2 2 SCOPE 2.0 3 EXCLUSIONS 2.1 3 CORPORATE POLICY 3.0 3 QUALITY MANAGEMENT SYSTEM 4.0 4 GENERAL

More information

WORK PLAN AND IV&V METHODOLOGY Information Technology - Independent Verification and Validation RFP No IVV-B

WORK PLAN AND IV&V METHODOLOGY Information Technology - Independent Verification and Validation RFP No IVV-B 1. Work Plan & IV&V Methodology 1.1 Compass Solutions IV&V Approach The Compass Solutions Independent Verification and Validation approach is based on the Enterprise Performance Life Cycle (EPLC) framework

More information

CAPITAL AVIONICS, INC. Quality Manual

CAPITAL AVIONICS, INC. Quality Manual CAPITAL AVIONICS, INC. Issued 31 July 2018 Conforms to ISO 9001:2015 2018 ; all rights reserved. This document may contain proprietary information and may only be released to third parties with approval

More information

ECC ENGINEERING MANAGEMENT STRATEGY WORKSHOP

ECC ENGINEERING MANAGEMENT STRATEGY WORKSHOP TEAM: A ISSUE ADDRESSED: Issue 1 The cost and time required to complete engineering often exceeds the estimate. Describe the issue in specific terms, using realistic project scenarios as appropriate. Quality

More information

CMMI Project Management Refresher Training

CMMI Project Management Refresher Training CMMI Project Management Refresher Training Classifica(on 2: Foxhole Technology Employees Only RMD 032 Project Management Refresher Training Course September 21, 2017 Version 1.0 The Process Approach The

More information

NEW HORIZONS ONLINE LIVE

NEW HORIZONS ONLINE LIVE NEW HORIZONS ONLINE LIVE WELCOME TO Certified Associate of Project Management (CAPM ) Fifth Edition PMBOK Guide - Please configure your audio: Meeting Audio Setup Wizard The Project Life Cycle Overview

More information

QUALITY ASSURANCE / QUALITY CONTROL POLICY

QUALITY ASSURANCE / QUALITY CONTROL POLICY QUALITY ASSURANCE / QUALITY CONTROL POLICY TABLE OF CONTENTS SI. NO. DETAILS 1. Introduction 2. Quality Policy and Objectives 3. Organization 4. Contract Review 5. Document and Data Control 6. Purchasing

More information

Guidance for Managing Product Change

Guidance for Managing Product Change Guidance for Managing Product Change Most organizations with product development or manufacturing responsibilities must manage product change. Typically this is handled as a Change Order, Change Request,

More information

Design & Development of a Schedule Management Plan. Session #PRJ10

Design & Development of a Schedule Management Plan. Session #PRJ10 Design & Development of a Schedule Management Plan Session #PRJ10 Chris Carson, PMP, PSP, CCM Alpha Corporation 2010 Permission is granted to PMI for PMI Marketplace use only Chris Carson, PSP, CCM, PMP

More information

Information Technology Independent Verification and Validation

Information Technology Independent Verification and Validation Florida Department of Management Services Information Technology Independent Verification and Validation RFP No. Work Plan and Methodology ; 2:30 PM EST 2150 River Plaza Drive Suite 380 Sacramento California

More information

Work Plan and IV&V Methodology

Work Plan and IV&V Methodology Work Plan and IV&V Methodology Technology initiatives and programs should engage with an IV&V process at the project planning phase in order to receive an unbiased, impartial view into the project planning,

More information

Program/Project Management

Program/Project Management PROCEDURE OVERVIEW PROGRAM/PROJECT MANAGEMENT PROCEDURE defines the project management infrastructure, reporting relationships and project management activities within SDLC.com. Project Managers, Program

More information

ISO 9001: 2000 (December 13, 2000) QUALITY MANAGEMENT SYSTEM DOCUMENTATION OVERVIEW MATRIX

ISO 9001: 2000 (December 13, 2000) QUALITY MANAGEMENT SYSTEM DOCUMENTATION OVERVIEW MATRIX In completing your Documented Quality Management System Review, it is important that the following matrix be completed and returned to us as soon as possible. This will save time during the review and

More information

Quality Management Plan

Quality Management Plan Document # 01-13283-GG-0000-RPT-CM-0002 Rev No. Prepared by/ Date Reviewed by/ Date Approved by/ Date Accepted by/ Date Pages Revised Remarks 0 B C T.Rath 2017-1-27 P. Poos D. Safari Issued for Use Page

More information

M3 Playbook Guidance. 1.1 Establish Initial Customer PMO and Processes. Human Resources (HR)/Staffing Plan

M3 Playbook Guidance. 1.1 Establish Initial Customer PMO and Processes. Human Resources (HR)/Staffing Plan M3 Playbook Guidance Phase 1: Readiness This guidance is intended for use by organizations to confirm and validate that their plans are comprehensive and have adequate level of detail for proper migration

More information

City of McKinney Texas Commissioning Process Requirements International Energy Conservation Code (IECC 2015 Section C408).

City of McKinney Texas Commissioning Process Requirements International Energy Conservation Code (IECC 2015 Section C408). City of McKinney Texas Commissioning Process Requirements International Energy Conservation Code (IECC 2015 Section C408). The application of the Commissioning Process starts at the beginning of the project

More information

ISO 9001:2008 Quality Management System QMS Manual

ISO 9001:2008 Quality Management System QMS Manual 2501 Kutztown Road Reading, PA, 19605 Tel. 610-929-3330 Fax 610-921-6861 ISO 9001:2008 Quality Management System QMS Manual The information contained in this document is Fidelity Technologies Corporation

More information

Design Compliance Matrix

Design Compliance Matrix Waste Treatment Plant Project Design Compliance Matrix Tracy Hawkins WTP Responsible Engineering Specialist 06-August-2015 Design Compliance Matrix (DCM) Overview AGENDA What is the Purpose of a DCM? What

More information

Expert Design & Support Engineer to work within Diagnostics Division. Technical Specifications

Expert Design & Support Engineer to work within Diagnostics Division. Technical Specifications Expert Design & Support Engineer to work within Diagnostics Division Technical Specifications Version 1.0 Date: 17/07/2012 Name Affiliation Author V UDINTSEV CHD / DIAGNOSTICS Reviewers M WALSH CHD/ DIAGNOSTICS

More information

Timothy Stokes. PE, MBA Delcan Corp, Senior Principal Denver, CO

Timothy Stokes. PE, MBA Delcan Corp, Senior Principal Denver, CO Improving Project Management to Realize Successful Outcomes by Focusing on Requirements Management Timothy Stokes. PE, MBA Delcan Corp, Senior Principal Denver, CO Introduction Begin at the beginning,

More information

Copyright 2013 Pearson Education, Inc. Publishing as Prentice Hall 5-1

Copyright 2013 Pearson Education, Inc. Publishing as Prentice Hall 5-1 Copyright 2013 Pearson Education, Inc. Publishing as Prentice Hall -1 Learning objectives Manage the planning process of a project Understand the work breakdown structure of a project Understand different

More information

Introduction. Scope Management Approach. Roles and Responsibilities. Processes included in Scope Management are:

Introduction. Scope Management Approach. Roles and Responsibilities. Processes included in Scope Management are: Introduction Scope Management involves the management of techniques that make sure that the project comprises a Processes included in Scope Management are: 1. Collect Requirements In this process, project

More information

Attachment J-4 Milestone Acceptance Criteria and Payment Schedule

Attachment J-4 Milestone Acceptance Criteria and Payment Schedule Attachment J-4 Milestone Acceptance Criteria and Payment Schedule Page 1 of 7 For Base, CLIN 001: Milestone Payment Event Integrated System Baseline Review (ISBR) Milestone Objective: At a NASA and Contractor

More information

Sample Delivery Schedule

Sample Delivery Schedule Sample Delivery Schedule The following model delivery schedule will provide the list of expected s with their proposed due date, and an illustration of a possible financial consequence. The milestones

More information

Executive Steering Committee Medicaid Eligibility System

Executive Steering Committee Medicaid Eligibility System Project July 19, 2013-1- Minutes and Action Items from June 21 Meeting -2- Federal Partner Update -3- Rulemaking Received Advanced Copy of Final Eligibility Rules on July 5 th Project Team Analysis Complete

More information

Desk Audit of. Based on Federal Transit Administration (FTA) Quality Assurance and Quality Control Guidelines FTA-IT

Desk Audit of. Based on Federal Transit Administration (FTA) Quality Assurance and Quality Control Guidelines FTA-IT Desk Audit of Based on Federal Transit Administration (FTA) Quality Assurance and Quality Control Guidelines FTA-IT-90-5001-02.1 Reviewed by: Element Requirements Applicable 1. Is a quality policy defined

More information

CMMI-DEV V1.3 CMMI for Development Version 1.3 Quick Reference Guide

CMMI-DEV V1.3 CMMI for Development Version 1.3 Quick Reference Guide processlabs CMMI-DEV V1.3 CMMI for Development Version 1.3 Quick Reference Guide CMMI-DEV V1.3 Process Areas Alphabetically by Process Area Acronym processlabs CAR - Causal Analysis and Resolution...

More information

Front End Engineering Design (FEED) Challenges in EPC Projects: Design, LLI Strategy & Fast Track

Front End Engineering Design (FEED) Challenges in EPC Projects: Design, LLI Strategy & Fast Track progetti Front End Engineering Design (FEED) Challenges in EPC Projects: Design, LLI Strategy & Fast Track By Armando Bianco, Engineering Manager, Eniprogetti Global Conference on EPC Contract & Project

More information

Citi Institutional Clients Group - Business Continuity Management

Citi Institutional Clients Group - Business Continuity Management Citi Institutional Clients Group - Business Continuity Management Enterprise Risk Management Establishing a Risk Control-based Continuity Program, CBCP, CBCP Senior Vice President, Citi Institutional Clients

More information

TAMING COMPLEXITY ON MAJOR RAIL PROJECTS WITH A COLLABORATIVE SYSTEMS ENGINEERING APPROACH

TAMING COMPLEXITY ON MAJOR RAIL PROJECTS WITH A COLLABORATIVE SYSTEMS ENGINEERING APPROACH TAMING COMPLEXITY ON MAJOR RAIL PROJECTS WITH A COLLABORATIVE SYSTEMS ENGINEERING APPROACH Chris Rolison CEO, Comply Serve Limited The Collaborative Systems Engineering Approach Collaboration A system

More information

Quality Assurance / Quality Control Plan

Quality Assurance / Quality Control Plan Quality Assurance / Quality Control Plan Table of Contents MANAGEMENT APPROACH... 3 SUBCONTRACT MANAGEMENT... 3 QUALITY MANAGEMENT APPROACH... 3 METHODOLOGY... 4 CONCEPT OF OPERATIONS... 5 QUALITY MANAGEMENT

More information

Systems Assurance within the Systems Engineering Lifecycle

Systems Assurance within the Systems Engineering Lifecycle Systems Assurance within the Systems Engineering Lifecycle Key Lessons & Benefits Rob Scarbro 12 th February 2013 1 Introduction Overview of Systems Assurance across a Project Life- Cycle Key objectives,

More information

Page 1 (5) KBE EP (E) (E) EXAMINATION PROCEDURE

Page 1 (5) KBE EP (E) (E) EXAMINATION PROCEDURE Page 1 (5) EXAMINATION PROCEDURE Type Inspection Certificate Quality and Identity Certificate Inspection Documentation Document Issue Date Supersedes KBE EP-180 2 (E) 2013-08-20 1 (E) 1 SCOPE This Examination

More information

1.0 PART THREE: Work Plan and IV&V Methodology

1.0 PART THREE: Work Plan and IV&V Methodology 1.0 PART THREE: Work Plan and IV&V Methodology 1.1 Multi-Faceted IV&V Methodology Large, complex projects demand attentive and experienced IV&V and project management support to meet expectations. Monitoring

More information

MBA BADM559 Enterprise IT Governance 12/15/2008. Enterprise Architecture is a holistic view of an enterprise s processes, information and

MBA BADM559 Enterprise IT Governance 12/15/2008. Enterprise Architecture is a holistic view of an enterprise s processes, information and Enterprise Architecture is a holistic view of an enterprise s processes, information and information technology assets as a vehicle for aligning business and IT in a structured, more efficient and sustainable

More information

VMware Network Virtualization Deploy Service

VMware Network Virtualization Deploy Service DATA SHEET VMware Network Virtualization Deploy Service AT-A-GLANCE The primary objective of this service is a rapid installation, configuration, and high-level validation (deployment) of a reference design

More information

M. Health Provider Management. Addressing enhanced requirements for provider networks. Health and Human Services

M. Health Provider Management. Addressing enhanced requirements for provider networks. Health and Human Services Health Provider Management Addressing enhanced requirements for provider networks Health and Human Services Enroll, Screen and Manage Networks Healthcare regulations mandate significant changes to state

More information

QUALITY ASSURANCE AND QUALITY CONTROL MANUAL

QUALITY ASSURANCE AND QUALITY CONTROL MANUAL 1 QUALITY ASSURANCE AND QUALITY CONTROL 2 TABLE OF CONTENTS SECTION 1 SECTION 2 SECTION 3 SECTION 4 SECTION 5 SECTION 6 SECTION 7 SECTION 8 SECTION 9 SECTION 10 QUALITY POLICY & AUTHORITY MANAGEMENT RESPONSIBILITY

More information

Technical Specifications. For. ITER Specialist Diagnostics Engineering Support

Technical Specifications. For. ITER Specialist Diagnostics Engineering Support Technical Specifications For ITER Specialist Diagnostics Engineering Support Version 1.0 Date: 19/02/2014 Name Affiliation Author V UDINTSEV CHD / DIAGNOSTICS Reviewers M WALSH CHD/ DIAGNOSTICS Approver

More information

I. Development, Submittal, and Acceptance of a Quality Management System

I. Development, Submittal, and Acceptance of a Quality Management System I. Development, Submittal, and Acceptance of a Quality Management System 1. Scope Under the Contract, quality assurance and quality control management are the responsibility of the Contractor. The Contractor

More information

Commissioning. National Training for Commissioning, Presented By Paul Sra and Mike Cavan

Commissioning. National Training for Commissioning, Presented By Paul Sra and Mike Cavan Commissioning National Training for Commissioning, 2006 Presented By Paul Sra and Mike Cavan 1 Scope of Presentation Commissioning overview Commissioning requirements for LEED Standard Roles and responsibilities

More information

Instrument Control System Project Management

Instrument Control System Project Management Project Documentation Document PMCS-0021 Revision A Instrument Control System Project Management Bret Goodrich Software September 2015 Advanced Technology Solar Telescope 950 N. Cherry Avenue Tucson, AZ

More information

WOODS CONTRACTING QUALITY ASSURANCE QUALITY CONTROL QA/QC MANUAL VERSION: REV.2

WOODS CONTRACTING QUALITY ASSURANCE QUALITY CONTROL QA/QC MANUAL VERSION: REV.2 WOODS CONTRACTING QUALITY ASSURANCE QUALITY CONTROL QA/QC MANUAL VERSION: 2.011218 REV.2 CONTENTS SECTION 1: QUALITY POLICY & AUTHORITY SECTION 2: MANAGEMENT RESPONSIBILITY SECTION 3: QUALITY SYSTEMS SECTION

More information

WESTERN ELECTRICITY COORDINATING COUNCIL GENERATING UNIT MODEL VALIDATION POLICY

WESTERN ELECTRICITY COORDINATING COUNCIL GENERATING UNIT MODEL VALIDATION POLICY WESTERN ELECTRICITY COORDINATING COUNCIL GENERATING UNIT MODEL VALIDATION POLICY A. Introduction A.1. Title: Generating Unit Model Validation Policy A.2. Purpose: Accurate models of generators and associated

More information

Developed by: Steven Jacobs, Eck Doerry

Developed by: Steven Jacobs, Eck Doerry Developed by: Steven Jacobs, Eck Doerry 1 Consequences of Bad Requirements Engineering http://www.knovelblogs.com/2012/08/30/the-importance-of-requirements-engineering/ 2 Building an efficient organization

More information

STATEMENT OF WORK SMALL SPACECRAFT PROTOTYPING ENGINEERING DEVELOPMENT & INTEGRATION (SSPEDI) Space Solutions (SpS)

STATEMENT OF WORK SMALL SPACECRAFT PROTOTYPING ENGINEERING DEVELOPMENT & INTEGRATION (SSPEDI) Space Solutions (SpS) SSPEDI SpS J.1(a), Attachment 1 80ARC018R0007 National Aeronautics and Space Administration Ames Research Center Moffett Field, CA 94035-0001 STATEMENT OF WORK SMALL SPACECRAFT PROTOTYPING ENGINEERING

More information

Enabling the Nuclear Renaissance The Importance of Quality Assurance

Enabling the Nuclear Renaissance The Importance of Quality Assurance Enabling the Nuclear Renaissance The Importance of Quality Assurance Bill Borchardt Executive Director for Operations US Nuclear Regulatory Commission 35th Annual Energy and Environmental Training and

More information

DOCUMENT CONTROL INFORMATION

DOCUMENT CONTROL INFORMATION DOCUMENT CONTROL INFORMATION System: Document Title: Document Status: Quality Manual Approved 5 11/5/2014 Current Document Revision Details Formal review. Added section 2, 3. Revised section 5.5.2, 6.2,

More information

COMMISSIONING PROCESS FOR BUILDINGS AND SYSTEMS ASHRAE STANDARD 202

COMMISSIONING PROCESS FOR BUILDINGS AND SYSTEMS ASHRAE STANDARD 202 COMMISSIONING PROCESS FOR BUILDINGS AND SYSTEMS ASHRAE STANDARD 202 Gerald J. Kettler, PE, CCP, CPMP 21 st National Conference on Building Commissioning AIA Quality Assurance The Building Commissioning

More information

PART THREE - WORK PLAN AND IV&V METHODOLOGY WORK PLAN. FL IT IV&V Work Plan

PART THREE - WORK PLAN AND IV&V METHODOLOGY WORK PLAN. FL IT IV&V Work Plan WORK PLAN FL IT IV&V Work Plan PART THREE - WORK PLAN AND IV&V METHODOLOGY ID Task Name Duration 1 FL IT IV&V Project Work Plan 261 days 2 DDI / SI Contract Award 0 days 3 Project Initiation and Planning

More information

Project ASSIST. Software Development Framework

Project ASSIST. Software Development Framework Project ASSIST Software Development Framework November 7, 1995 Table of Contents Introduction...1 Terminology - Software Maintenance and Software Development...1 Framework Objectives...2 Framework Scope...2

More information

International Diploma in Project Management. (Level 4) Course Structure & Contents

International Diploma in Project Management. (Level 4) Course Structure & Contents Brentwood Open Learning College (Level 4) Page 1 Unit 1 Overview of Project Management The unit 1 covers the following topics: What is A Project? What is Project Management? Project Constraints Tools and

More information

Construction Auditing: UTILIZING INDUSTRY STANDARDS, BEST PRACTICES AND CHANGE ORDER AUDITING APRIL 4, 2017

Construction Auditing: UTILIZING INDUSTRY STANDARDS, BEST PRACTICES AND CHANGE ORDER AUDITING APRIL 4, 2017 Construction Auditing: UTILIZING INDUSTRY STANDARDS, BEST PRACTICES AND CHANGE ORDER AUDITING APRIL 4, 2017 OPENING REMARKS Kinney Poynter Moderator Executive Director NASACT Alan Pennington Speaker Vice

More information

Adaptive Signal Control Lessons Learned in Systems Engineering and Procurement

Adaptive Signal Control Lessons Learned in Systems Engineering and Procurement 2014 HDR Architecture, 2014 2014 HDR, HDR, Inc., all all rights reserved. Adaptive Signal Control Lessons Learned in Systems Engineering and Procurement ACHD Three Cities River Crossing Boise, Idaho Iowa

More information

REQUIREMENTS DOCUMENTATION

REQUIREMENTS DOCUMENTATION REQUIREMENTS DOCUMENTATION Project Title: Date Prepared: Stakeholder Requirement Category Priority Acceptance Criteria REQUIREMENTS DOCUMENTATION Project Title: Date Prepared: Stakeholder Requirement Category

More information

André Thibault Head of Mass Transit Platforms Bombardier Transportation St-Bruno, Québec, Canada

André Thibault Head of Mass Transit Platforms Bombardier Transportation St-Bruno, Québec, Canada Managing and Standardization in Passenger trains The Platform Approach André Thibault Head of Mass Transit Platforms Bombardier Transportation St-Bruno, Québec, Canada Agenda 1 INTRODUCTION AND CONTEXT

More information

APPENDIX O CONTRACTOR ROLES, RESPONSIBILITIES AND MINIMUM QUALIFICATIONS

APPENDIX O CONTRACTOR ROLES, RESPONSIBILITIES AND MINIMUM QUALIFICATIONS APPENDIX O CONTRACTOR ROLES, RESPONSIBILITIES AND MINIMUM QUALIFICATIONS Shared denotes whether a Contractor Resource may be responsible for that in addition to another identified. Contractor Required

More information

UoD IT Job Description

UoD IT Job Description UoD IT Job Description Role: Service Delivery Manager (People HERA Grade: 8 Management Systems) Responsible to: Assistant Director (Business Services) Accountable for: Day to day leadership of team members

More information

Florida Cleanroom Systems

Florida Cleanroom Systems Florida Cleanroom Systems Design Build Projects / Project Quality Control Plan (PQCP) Quality Control / Quality Assurance Manual May 2010 1 TABLE OF CONTENTS Section 1: Introduction 3 1.1 Defining Plan

More information

PROJECT MANAGEMENT PLAN

PROJECT MANAGEMENT PLAN PROJECT MANAGEMENT PLAN AS A TOOL TO DEVELOP EFFECTIVE COMMUNICATION TO MANAGE STAKEHOLDERS AND THE DESIGN TEAM Adelaide Airport plaza Event: Design and Development of Stations and Terminals Conference

More information

Sargent & Lundy LLC April 8, 2014

Sargent & Lundy LLC April 8, 2014 Farid M. Berry Vice President & Project Director Sargent & Lundy LLC April 8, 2014 Role of the OWNER S ENGINEER Technical Meeting on Becoming a Knowledgeable Customer Obninsk and Novovoronezh, Russian

More information

PaintCare Inc. Request for Proposal Salesforce Implementation

PaintCare Inc. Request for Proposal Salesforce Implementation PaintCare Inc. Request for Proposal Salesforce Implementation RFP Issued: December 15, 2017 Responses Due: January 15, 2018 Staff Contacts: Shaun Murray Senior Director, Information Technology, Business

More information

Virtual Foundation Business Analyst Course Outline

Virtual Foundation Business Analyst Course Outline Virtual Foundation Business Analyst Course Outline General Description We all know that the validity and accuracy of the requirements can make or break a project, yet often insufficient time and effort

More information

Validation Documentation. Presented by John Montalto 27 March, 2013

Validation Documentation. Presented by John Montalto 27 March, 2013 Validation Documentation Presented by John Montalto 27 March, 2013 Validation planning Validation policies define management intent and commitment Validation Master Plans (VMPs) Individual Validation Plans

More information

Railroad Friction Products Corporation

Railroad Friction Products Corporation Railroad Friction Products Corporation Our Quality Philosophy: "At Railroad Friction Products Corporation we will consistently provide products that meet and exceed customer and regulatory requirements

More information

Awareness to ISO 9001:2000

Awareness to ISO 9001:2000 Awareness to ISO 9001:2000 Tutor s Introduction Course Objectives Be able to understand and interpret the requirements of the standard Planning to implement the requirements of the standard Course Structure

More information

California Independent System Operator Corporation Fifth Replacement Tariff

California Independent System Operator Corporation Fifth Replacement Tariff Table of Contents Station Power Protocol... 2 1 General Conditions... 2 1.1 Procurement... 2 1.2 Eligibility... 2 1.3 Limitations... 2 2 Station Power Requirements and Review... 3 2.1 Applications to Self-Supply

More information

version NDIA CMMI Conf 3.5 SE Tutorial RE - 1

version NDIA CMMI Conf 3.5 SE Tutorial RE - 1 Requirements Engineering SE Tutorial RE - 1 What Are Requirements? Customer s needs, expectations, and measures of effectiveness Items that are necessary, needed, or demanded Implicit or explicit criteria

More information

Quality Management_100_Quality Checklist Procedure

Quality Management_100_Quality Checklist Procedure Quality Management_100_Quality Checklist Procedure Last updated 05/15/2017 Audience: Project Team, Process Owners, Project Management Office Frequency: As Required This procedure provides detailed information

More information

Quality Manual Revision: C Effective: 03/01/10

Quality Manual Revision: C Effective: 03/01/10 TABLE OF CONTENTS DESCRIPTION SECTION PAGE INTRODUCTION 1.0 1 APPROVAL SIGNATURE PAGE 1.1 1 AMENDMENT RECORD 1.2 2 SCOPE 2.0 3 EXCLUSIONS 2.1 3 CORPORATE POLICY 3.0 3 QUALITY MANAGEMENT SYSTEM 4.0 4 GENERAL

More information

Modern Service Management Solutions for Defense Agencies

Modern Service Management Solutions for Defense Agencies Modern Service Management Solutions for Defense Agencies White paper John M. Clark (joclark@microsoft.com ) Cross-Domain Solution Architect WW Modern Service Management Community Lead June 2018 Contents

More information

Policy and Procedure Examples

Policy and Procedure Examples Appendix 1 Policy and Procedure Examples Four sample documents are shown in this appendix to illustrate the type of administrative guidelines that should be developed in support of project operations within

More information

COMPUTERIZED SYSTEM VALIDATION (CSV) IMPLEMENTATION, DEMARCATION AND STRUCTURATION

COMPUTERIZED SYSTEM VALIDATION (CSV) IMPLEMENTATION, DEMARCATION AND STRUCTURATION COMPUTERIZED SYSTEM VALIDATION (CSV) IMPLEMENTATION, DEMARCATION AND STRUCTURATION Audit Security is the high priority for pharmaceutical companies, especially when computerized Systems are used. The everchanging

More information