Positive Train Control Quarterly Report

Size: px
Start display at page:

Download "Positive Train Control Quarterly Report"

Transcription

1 ATTACHMENT 13A Positive Train Control Quarterly Report For the Period April 1, 2017 June 30, 2017 (Q2 of FY 2017)

2 Contents 1. EXECUTIVE SUMMARY Project Overview PTC Inter-Agency Coordination PTC Operations and Maintenance Scope of Work Overview Key Issues Wabtec Railway Electronics (WRE) Documentation Schedule Testing PROGRAM MANAGEMENT Integration Management Program Governance Program Control Change Management Program/Project Management Information Systems Scope Management Configuration Control Management Quality Management Quality Plans Deficiency Notices (DN), Nonconformance Reports (NCR), Corrective Action Reports (CAR) PTC Quality Audits and Surveillances Corrective Action Reports (CAR) Quality Tasks Risk Management Stakeholder and Communications Management PROGRAM SAFETY PROGRAM PROGRESS POSITIVE TRAIN CONTROL CONTRACTS AND STATUS EXPENDITURES / FUNDING SOURCES Expenditures Funding Sources PROJECT PHOTOS... 24

3 APPENDIX A: ABBREVIATIONS... 25

4 1. EXECUTIVE SUMMARY 1.1. Project Overview The North County Transit District (NCTD) is implementing an interoperable Positive Train Control (PTC) System on the San Diego Subdivision where passenger and freight operations are conducted (as set forth in the Rail Safety Improvement Act of 2008 (RSIA08) and 49 CFR 236 Subpart I). The purpose of a PTC System is to prevent the following: Train-to-train collisions Over speed accidents Incursion into work zones Movements through a misaligned switch by requiring automatic control systems to override mistakes by human operators This PTC System will be designed and implemented to follow the standard and guidelines established by the Interoperable Train Control (ITC) Committee. The ITC Committee is comprised of the four largest US freight railroads: BNSF Railway, CSX, Norfolk Southern Railway (NS), and Union Pacific Railroad (UPRR). The NCTD goal for PTC implementation is the extended December 31, 2018 completion date as stipulated in the Surface Transportation Extension Act of In August 2011, NCTD procured a Vendor/Integrator contractor, Herzog Technologies Inc. (HTI), to design, install, commission, and maintain the PTC System. In addition to, and in advance of, the implementation of the PTC System, NCTD has assumed the management control of the San Diego Subdivision by installing a new computer-aided dispatch system, Train Management and Dispatching System (TMDS), and assumes responsibility for railroad dispatching. Previously, NCTD s dispatching was managed by Southern California Regional Rail Authority (SCRRA) using the DIGICON CTC system. NCTD awarded a contract to HTSI for CTC installation and dispatch services. The San Diego Subdivision dispatch cutover was April 2012, and the Escondido Subdivision dispatch cutover was December The new PTC system will be located at the Rail Operations Center (ROC) within the Sprinter Operations Facility (SOF) in Escondido, CA. NCTD s General Administration Office (GAO) has been identified as a second location to provide geographic redundancy for both the command and control functions as well as the PTC back office functions. Once the Operations Control Center at GAO is fully built out, GAO will be transitioned to the primary location, with the ROC becoming the backup center PTC Inter-Agency Coordination Inter-Agency Coordination is one of the keys for successful implementation of the project. The PTC system must be fully and mutually compatible with host and tenant railroads. Interoperability will enable safe operation of mixed freight and passenger services to allow seamless uninterrupted movement among different host railroads. Interoperability shall be based on the ITC Committee standard and guidelines, and member governance currently in development by the UPRR, BNSF Railway, CSX, and NS. Host and tenant railroads may also execute Interoperability Agreements, which are envisioned as being similar to Shared Use Agreements. NCTD has executed Interoperability Agreements with BNSF Railway (April 2010), SCRRA (April 2010), Amtrak (March 2010) and Pacific Sun Railroad (August 2010). Page 3 of 26

5 The San Diego Subdivision rail corridor is 60.3 miles in length from the Orange County/San Diego County line (MP 207.4) to 200 feet south of Broadway Street in San Diego (MP 267.7). The entire line is signaled CTC territory with 50% of the territory having segments of multiple main track and passing sidings. Passenger train operations on the corridor are COASTER (22 trains/weekday), Amtrak Pacific Surfliner intercity service (22-24 trains/day), and SCRRA Metrolink commuter rail services (up to 14 trains/day). Freight service on the Subdivision is BNSF Railway (4-6 trains/day) and Pacific Sun Railroad (5-10 trains/week). NCTD's COASTER service operates between the Oceanside Transit Center in Oceanside (MP 226.4) and Santa Fe Depot in San Diego (MP 267.5). NCTD s Maintenance facility is located at Stuart Mesa (MP 221.9), north of Oceanside on Camp Pendleton. This yard is also used by SCRRA Metrolink. A layover facility is located at the San Diego Trolley Yard (MP 268.4) at 12th and Imperial in Centre City San Diego where COASTER train sets are stored during midday. In addition to the NCTD COASTER service area, the tenant railroads use the corridor as follows: Amtrak's Pacific Surfliner Service - Entire subdivision; BNSF Railway - Entire subdivision; SCRRA's Metrolink Orange County Line - From Oceanside to the Orange County Line; BNSF Railway s contracted operator Pacific Sun Railroad, a Watco Company - Local freight service operating between Stuart Mesa Maintenance Facility and Miramar freight spur, and Escondido Subdivision with occasional trips to San Onofre near the Orange County Line. NCTD has organized monthly interoperability calls that include the Federal Railroad Administration (FRA), Caltrans Division of Rail, Pacific Sun, Southern California Regional Rail Authority (SCRRA), BNSF Railway, and Amtrak. NCTD also attends the LA Regional PTC Conference quarterly meeting hosted by SCRRA and attended by BNSF Railway, UPRR and Amtrak PTC Operations and Maintenance The project is still under development. Once the project is complete, PTC Operations and Maintenance will be handed over to Bombardier Scope of Work Overview HTI and its subcontractors are solely responsible for designing and implementing a PTC system that meets FRA and other applicable requirements and is FRA approved for NCTD rail operations. HTI is required to follow the Positive Train Control Development Plan (PTCDP) submitted by the NS, CSX, and UPRR railroads and utilize it as the basis for the NCTD PTC system. This PTCDP, revised on June 1, 2011 and subsequently approved by the FRA on August 26, 2011, is known as Interoperable Electronic Train Management System (I-ETMS). HTI and its subcontractors are scoped to be following the I-ETMS Rung 1 model, which fully adheres to AAR/ITC standards and specifications, while designing the NCTD PTC system. This is in an effort to ensure FRA required "type approval" as well as streamlining the final FRA acceptance process. Page 4 of 26

6 Any deviations from I-ETMS functionalities will require Request(s) for Amendment (RFA) to the FRA and may extend the timeline for FRA acceptance. The Contract has been awarded as a single Contract to be executed in two phases (based on available funding). Phase I includes the initial surveys, studies, and all design work necessary to amend the PTCDP submitted by NS, CSX, and UP to the FRA. Phase 2 includes all other work necessary for the design, installation and implementation of the PTC system. The PTC System is scoped to be completed by December 31, 2018 in accordance with the Surface Transportation Extension Act of 2015, and must be compliant with standards and specifications developed by the ITC Committee for forthcoming publication by the Association of American Railroads (AAR). Safety is paramount. Consideration must also be given during the PTC System design to the NCTD level of service. The throughput (capacity) of the commuter railroad system must be maintained after PTC deployment, and the PTC System needs to support future capacity improvements and ridership growth. a. Phase 1 HTI is scoped to: i. Perform the necessary studies and surveys, attend meetings, and perform the engineering analysis, design and systems engineering necessary to amend the PTCDP per the RFA procedural requirements of 49 CFR HTI is scoped to provide all documentation, research, validation and verification services to ensure a "Type- Approved" system is provided to NCTD prior to commissioning. ii. iii. Provide for the development and submittal of a project schedule and planning for each task of the overall PTC program. HTI is scoped to develop a design, procurement and installation milestone schedule and plan construction, testing, and certification of the specified NCTD PTC System for full deployment in accordance with the milestones and deadlines established by NCTD. As part of HTI's coordination with tenant railroads, HTI shall prepare and submit an Interoperability Coordination Plan (ICP). Provide services necessary to perform detailed onboard surveys: a. Perform data collection subtasks for onboard systems. The data shall be used in designing the removal, relocation, and installation of on board systems (both existing and new systems). b. Develop and submit a Locomotive Survey Report and a Cab Car Survey Report. The survey report is intended to identify probable equipment mounting locations for all Interoperable-Electronic Train Management System (IETMS) system components, create the preliminary BOM, measure probable cable lengths required, and identify probable relocations of existing equipment. c. Develop and submit a preliminary Bill of Materials (BOM) and a baseline installation and relocation manual and schematics for each locomotive, cab car, and Hy-Rail vehicle type. Page 5 of 26

7 b. Phase 2 Upon issuance of the second NTP for Phase 2 by NCTD, HTI is scoped to: i. Continue with the development, procurement, and installation of the PTC System for NCTD's PTC program. ii. iii. iv. Prepare all required documents for submittal to, and approval by, the FRA, including the PTC Safety Plan (PTCSP). Provide a complete functional PTC System in accordance with the Contract Documents in compliance with the NCTD approved milestone schedule. The system is scoped to include wayside, onboard, radio communications network, and back office server segments. Develop an installation milestone schedule. v. Plan construction, testing, and certification of the specified NCTD PTC System, including full deployment. vi. vii. viii. Complete an initial design incorporating all PTC System components, including pre-ptc equipment. The PTC System proposed shall be based on NCTD's PTCIP deferred track area of the San Diego Subdivision. Be responsible for ensuring proper systems engineering processes, systems integration, system function, and correct sub-systems interaction for all aspects of the NCTD PTC System and its inter-relationships, inter-dependencies, and interfaces with other equipment and systems. The furnished PTC System shall be interoperable with the PTC Systems that are being deployed in Southern California by SCRRA and BNSF. Interoperability refers to the ability of trains to cross property boundaries under PTC at territory speed without stopping to acquire authorities. The PTC System shall also require direct or throughput communications among the PTC offices of NCTD, SCRRA, and BNSF. Coordinate all PTC activities with the FRA and the California Public Utilities Commission (CPUC), as necessary. ix. Establish a safety program that conforms with the requirements of 49 CFR 236 Parts 214, 218, 219, CPUC General Orders, and NCTD Operating Rules; and obtain roadway worker safety training certification for all HTI and supplier, subcontractor and subconsultant personnel who may enter the NCTD San Diego Subdivision and project right-of way. Figure 1.1 provides an overview of the NCTD PTC System Architecture. Page 6 of 26

8 Figure 1.1: NCTD PTC System Architecture 1.3. Key Issues This section describes the key issues that are contributing to, or have the potential to contribute to, schedule slippage Wabtec Railway Electronics (WRE) WRE is a key supplier of PTC equipment. While the performance of their onboard equipment has been favorable, their BOS and CAD software has been a consistent source of project delay Individual Composite CRC (Cyclic Redundancy Check) Calculator (IC3) IC3 requirements are in development by the ITC, and the functionality will be required by the FRA for PTC Certification. NCTD s approach will be to apply for Safety Certification as a vital system, accepting a conditional acceptance as a non-vital from the FRA, and meeting the federally mandated requirements. Once vitality is defined within the industry, NCTD will implement the solution Back Office Server (BOS) and Computer Aided Dispatch (CAD) WRE has fixed the BOS and CAD software issues that were hindering entering Revenue Service Demonstration last quarter Documentation Documentation is a continued focus Schedule Page 7 of 26

9 The schedule updates submitted by the Contractor in 2015 and 2016 continue to raise concerns for the NCTD team. NCTD continues to work with the Contractor on the schedule. This has improved with the development of the PTC Project Burn Down List but is a continued area of focus. NCTD expects to enter the FRA Revenue Service Demonstration early in the 3 rd Quarter of Testing Software version changes and related regression testing may impact the schedule. 2. PROGRAM MANAGEMENT 2.1. Integration Management This section describes the status of integration management, program governance, program controls, change management process, and program/project management information systems Program Governance The governance for the PTC program is organized as follows: NCTD Organization: Deputy Chief Operating Officer Rail Systems: Eric Roe Chief Technology Officer: Ryan Cashin Chief Financial Officer: Luz Cofresí-Howe Chief Operations Officer - Rail: Don Filippi Senior Network Engineer: Roy Gilbert Rail Systems Project Manager: Robert Paladino Right of Way Manager: Tim Morehead HNTB Organization: PTC Program/Construction Manager: Mike Steffen II Document Control Coordinator: Cara Smith Business Manager/Scheduler: Robert Hartley PTC Quality Manager: Mike Phillips PTC Quality Inspector: Patrick Malley Program Control The PTC program has had over 21 active vendor-implemented projects. The status of selected projects is described in Section 5 of this report. Page 8 of 26

10 Change Management The changes that are currently in process for the active vendor-implemented projects include: PTC for the LOSSAN Corridor (PO # OS) Herzog Technologies, Inc. A potential change order is in process that includes the addition of scope associated with the implementation of IC3. A potential change order is in process that includes the addition of scope associated with the Disaster Recover Center A potential change order is in process that includes the dynamic braking in the event recorder download. A potential change order is in process that includes the ElectroLogIXS/EC5 in the PTC documentation. ElectroLogIXS/EC5 is being installed at intermediate wayside locations in the SANDAG contracts. A potential change order is in process that includes Class D High Availability licenses for NCTD PTC WIUs. This General Electric (GE) functionality is necessary to interface between the WSRS and Wayside Interface Units (WIUs) on the network Program/Project Management Information Systems The current document control software was assessed for adequacy and will be maintained at this time Scope Management The Contract Document Requirements List (CDRL) for the PTC project is being crosschecked against the scope to ensure that contract requirements are met. This occurs once per quarter so that adjustments can be made, where applicable Configuration Control Management The Configuration Control Management Plan (CCMP) and the Field Control Management Plan (FCMP) were formally submitted to the FRA in November 2014 and were found to be acceptable. The Configuration Control Board (CCB) continues to meet to organize the PTC configuration management structure. The CCB has been meeting regularly and is establishing configuration control processes Quality Management Quality Plans The quality plans being used for the PTC program include: NCTD Quality Plan, Rev. A, January 1, 2012 HTI PTC Project: FTA Quality Management System Guidelines (FTA-PA ), December 2012 HTI PTC System Quality Plan, Rev. 1, April 30, 2012 Wabtec Quality Assurance Plan for NCTD Onboard Installation, Rev. 2, August 13, 2013 Page 9 of 26

11 Wabtec I-ETMS - Locomotive Segment, Software Quality Assurance Plan, Rev. 1.2, August 19, 2013 Wabtec Quality Management System Manual, Rev. 14, December 15, 2012 Convergent Communications, Inc. Quality Policy, Rev. A, May 17, 2013 JLP Quality Control / Quality Assurance Manual, Last Revised, February 28, 2007 Innovative Solutions In Signaling, LLC, Supplier Quality Survey, March 18, 2016 Experior Systems Ltd, Supplier Quality Survey, April 15, 2016 NCTD Program Support and Design: HNTB Northern California Office, Best Practices, Quality Assurance/Quality Control Manual, Rev. 1, October 29, 2004 Pacific Railway Enterprises, Inc. Design Quality Process, November 2, 2010 NCTD Fiber Construction Projects: HTI Quality Assurance Manual, Rev. G, July Deficiency Notices (DN), Nonconformance Reports (NCR), Corrective Action Reports (CAR) The PTC Quality Manager and the HTI System Quality Manager meet on an as needed basis to review the status of the project DNs, NCRs, and CARs. These items are defined as follows: DNs are items that have been identified as being deficient but not in nonconformance. These items can remain installed and in operation until they are either repaired or otherwise brought out of deficient standing. NCRs are items that have been identified where there is a discrepancy in characteristic, documentation, or procedure affecting form, fit, or function and renders the quality of an item unacceptable or indeterminate in regard to meeting relevant project requirements. CARs are measures taken to rectify conditions adverse to quality and to avoid repetition. Table 2.1 summarizes the total number of DNs, NCRs, and CARs that the PTC Quality Manager is tracking for the PTC project: Table 2.1: Quality Tracking Item Total Open Items Closed items Number Remaining Deficiency Notices Nonconformance Reports Corrective and Preventative Actions The work needed to resolve deficiency notices are scheduled to coincide with other work taking place at the same locations in order to be as efficient and productive as possible. The deficiency notices are closed through final inspections. Page 10 of 26

12 Nonconformance Reports are closed when the contractor has provided evidence that the nonconforming item has been properly repaired and/or corrected and meets the requirements of the project. Corrective and Preventative Actions are described in Section below. These are closed when the root cause analysis has been performed and when the adverse condition has been corrected to meet the requirements of the project based on an inspection of the HTI Quality Manager. In addition to the corrective action, a preventative action may be put in place to prevent recurrence of similar situations PTC Quality Audits and Surveillances The PTC Quality Manager is working with the HTI System Quality Manager on the following: Quality Records - HTI uses Fogbugz, a project management software program, to conduct quality checks and to maintain quality records. Although this program is proprietary and only accessible by HTI employees, the HTI System Quality Manager will be coordinating efforts with the PTC Quality Manager to provide quality documents in a timely fashion when requested. HTI is developing a plan to transfer all quality records over to NCTD per the contract requirements for the project. Once developed, the plan will be submitted for review. Audits The following is a summary of audits that were conducted during this quarter and the audits planned for next quarter: o Conducted: o Planned Wayside/Network Walk Downs: Resolution of Punch List Items is currently In Progress. PTC System Audit (Part of the Change Control Board Function) This Audit is In Progress. All future System Audits will be based off of the process and procedure and results discovered from this Audit. PTC System Audit (to be performed quarterly) PTC Back Office (2 nd Audit) Corrective Action Reports (CAR) The PTC Quality Manager is monitoring the progress of the following Corrective Action Reports for the PTC project: CAR 012 (Wayside Audit Actions) Issue Date of 04/13/15 This is a follow-up on the action items resulting from the Wayside audit. The purpose of this CAR is to resolve the outstanding findings and observations resulting from the Audit. Update: Item was closed by the contractor. NCTD is leaving this item open until the Wayside locations have been inspected and signed off as completed. Estimated Closure Date: 09/30/2017 DN Log No. None Quality Tasks Page 11 of 26

13 The Wayside and Network installations have been completed along the corridor under continuous NCTD Quality Inspection Representatives oversight. The PTC Quality Manager, along with NCTD representatives, have developed a final punch list of items to be resolved at each Wayside location by the Contractor. The Contractor is addressing all punch list items identified by the inspection team; completion of the punch list will be verified by NCTD. Staffed personnel for various PTC tests and engineer training that required NCTD witness verification. In the process of completing the first System Audit as per the Configuration Control Management Plan with NCTD. Reviewing the completion of the As-built drawings by HTI to be inclusive of all PTC construction items at all of the Wayside / Network locations for NCTD Risk Management Monitoring of project risk is ongoing by the NCTD and HTI project teams. A Risk Management Plan (RMP) has been developed and is reviewed on a monthly basis Stakeholder and Communications Management NCTD communicated to stakeholders about the broader PTC project. This included communications with City Staff, SANDAG, neighbors, written notices, communications, and website updates. 3. PROGRAM SAFETY Per the National Transportation Safety Board (NTSB) s Safety Recommendations dated June 18, 2013, Tables 3.1 and 3.2 reflect the progress being made on the required components and training for the NCTD PTC program. All wayside units have been installed. The base station radio installations are complete. The locomotive / on-board radios were completed in April Table 3.1: Components Component Locomotives / On-board Wayside Units Switches Description F40 (x5); F59 (x2); BCC (x10) VHLC; EC4; EL-1A Total Components Completed Remaining Percent Complete Estimated Completion Date % Mar % Dec-2014 Not Applicable Base Station Radios Meteorcomm % Feb-2015 Locomotive Radios Meteorcomm % Apr-2016 Wayside Radios New/novel technologies (if applicable) Not Applicable % TBD Training activities, shown in Table 3.2, are in progress. The number in the column titled Employees Trained represent the number of employees that have completed training. The Roadway Worker Protection System remains under development in the industry; training will be provided when the Roadway Worker Protection System becomes available. Future completion dates are estimated. Page 12 of 26

14 Table 3.2: Training Classification / Craft Total Employees Employees Trained Employees Remaining Percent Trained Completion Date Train Operator % December 2016 Vehicle Maintainer % December 2016 Signal Maintainer % December 2016 Communications Maintainer % April 2016 Dispatcher % December 2016 IT & Administration % May 2016 Track Maintainer % December 2016 Configuration Control Board % March 2016 GIS Technician % September 2015 Hy-Rail Maintainer - Onboard % December 2016 Hy-Rail Maintainer - Communications % April PROGRAM PROGRESS The schedule updates submitted by the Contractor in 2015,2016, and 2017 have raised some concerns for the NCTD team. NCTD is working with Contractor to resolve the issues in the schedule updates. However, NCTD has made significant progress on the PTC project this quarter. All of the FRA s prerequisites to enter Revenue Service Demonstration have been met and NCTD is currently running revenue service trains with PTC enabled. Key milestones expected to complete next quarter: - Meet Criteria to Enter Extended Revenue Service Demonstration - Submit PTCSP to the FRA FRA Certification and Acceptance is anticipated to be received by July Page 13 of 26

15 5. POSITIVE TRAIN CONTROL CONTRACTS AND STATUS The PTC Program, extending from the Orange County Line to the Santa Fe Depot, has had over 21 active vendor-implemented projects. The detail for these projects can be found in previous progress reports. Table 5.1 provides at-a-glance information for the five significant remaining open contracts. Additional detail on the progress and financial status is provided in Tables 5.2 through 5.6. Table 5.1: PTC Program Projects Summary Table 5.1 NCTD Tracking Number Project Name Contractor PTC Vendor-Integrator Project Contract Amount Status Table # on report PTC for the LOSSAN Corridor Herzog Technologies, Inc. $37,637,515 On-Going 5.2 Other PTC Program Implemented Projects Design Support During Construction Pacific Railway Enterprises, Inc. $2,742,430 On-Going Engineering Support Services HNTB $2,001,014 On-Going Environmental Support Services BRG Consulting $65,647 On-Going 5.6 Page 14 of 26

16 Table 5.2: Positive Train Control System for the LOSSAN Corridor; NCTD PO#11046 NCTD PURCHASE ORDER PROJECT NAME CONTRACTOR/CONSULTANT PTC for the LOSSAN Corridor Herzog Technologies, Inc. BRIEF PROJECT DESCRIPTION The PTC System for the LOSSAN Corridor is the primary contract for implementation of the PTC system. PROJECT STATUS On-Going Stakeholder and interoperability meetings continue to be held. The Caltrans quarterly meeting was held in August An LA Regional PTC meeting was held in July 2016 focusing on tenant interoperability; the next meeting is scheduled for August COMMUNICATIONS: Regarding the ATCS Antenna Install Proposal, HTI is working on the disposal quote. Wi-Fi site testing and base radio startup test results were accepted by NCTD in The microwave installation test results and cellular test results were accepted by NCTD in March System level integration testing is in process. Completion of the Level 2 and Level 3 Backhaul Network Verification and Validation Plan is anticipated next quarter. ONBOARD: Onboard installation was completed in March with installations complete on all 17 vehicles. All onboard radio startup tests were accepted in April The onboard installation binders containing all test results and as-builts have been accepted. Brake testing began and completed in June 2016, and test results were submitted to the SIR site on 7/8/2016. WAYSIDE: Critical Feature V&V testing with the FRA began in January 2016 with test results uploaded to the SIR site in May Wayside V&V Regression Test 1 Submitted to the FRA SIR site on 10/28/2016 NETWORK: NMS witness training occurred in March 2016 with testing started in April 2016 and expected to conclude next quarter. BACK OFFICE: Federated MPLS test results with Metrolink and BNSF and back office network connection test results were accepted in March BOS-CAD testing occurred in April 2016 with test results accepted in April TMDS testing occurred in March 2016 with approval of test results occurring May TMDS and BOS to ITCM Test Results were approved in June INTEGRATION: Field Integration and Functional Test (FI&FT) Book 1 testing completed in July 2016 with one failed test that will be captured in a regression test book. FI&FT Book 2 testing completed in August 2016 with two failed tests that will be captured in a regression test book. FI&FT Book 3 testing is ongoing and is expected to complete in October FI&FT Book 4 testing completed in August 2016 with all tests passing. Brake regression testing was required in order to complete the FI&FT Book 3 enforcement test cases; brake regression testing completed in September All testing required prior to entering RSD has been completed. TRAINING: Training has been completed for 80 of 91 staff. The trainings for the Train Operators, Signal Maintainers, Configuration Control Board, Speedtrax, GIS Technician, Communications/Network, and Back Office have been completed. DOCUMENTATION: The Test Waiver was conditionally approved by the FRA in August Test waiver conditions continue under review by HTI. The Configuration Control Management Plan (CCMP) and Field Configuration Management Plan (FCMP) have been formally submitted to the FRA and were found to be acceptable by the FRA (December 2014). Critical Feature V&V were found to be acceptable for formal submittal by the FRA (November 2015). The new PTCIP was submitted to the SIR site on 1/22/2016. The Wayside V&V and Route V&V Test Reports were accepted by NCTD in March and submitted to the SIR site on 3/10/2016. The Brake Test Cases and Procedures and Brake Test Book were submitted to the SIR site on 3/29/2016. The PTC Annual Report was submitted to the SIR site on 3/29/2016. The Critical Feature V&V Test Reports were approved in May 2016 and submitted to the SIR site on 5/4/16. The Field Integration and Functional Test Book (FI&FT) Book 1 was submitted to the SIR site on 6/20/2016 and was found to be acceptable by the FRA (June 2016). The FI&FT Book 2 was submitted to the SIR site on 6/30/2016 and was found to be acceptable by the FRA (July 2016). The FI&FT Book 3 was submitted to the SIR site on 8/5/2016 and was found to be acceptable by the FRA (August 2016). The FI&FT Book 4 was submitted to the SIR site on 7/26/2016 and was found to be acceptable by the FRA (July 2016). Conditional Approval to enter RSD was given by the FRA in March PTCSP submittal is anticipated in Q OTHER ISSUES: None. Page 15 of 26

17 CONTRACT DATES NTP 08/19/2011 Phase 1: Development Completed 07/31/2012 Phase 2: Procurement/Installation/Testing 10/14/2016 System Safety Certification 03/13/2017 System Commissioned into Revenue Service 03/14/2018 Phase 1 includes the initial surveys, studies, and all design work necessary to amend the Positive Train Control Development Plan (PTCDP) submitted by NS, CSX, and UPRR to the FRA. This Phase has been completed. An amended PTCDP was not needed at the time this phase was completed. Once lab testing is underway, the PTCDP may be revisited. Phase 2 includes all other work necessary for the design, installation and implementation of the PTC system. COMPLETION UPDATE COST UPDATE Phase 1: Development Completed 100% Contract Amount $37,637,515 Phase 2: Procurement/Installation/Testing 81% Spent to Date $33,953,206 System Safety Certification Not Started Encumbered $3,684,310 System Commissioning into Revenue Service Not Started CONTRACT & BUDGET INFORMATION Description Contract Amount Date Executed Original Contract Value $33,044,670 5-Aug-11 Change order 001 $237,000 5-Oct-12 Change order 002 $809, Jan-13 Change order 003 $2,456, Jun-13 Change order 004 $1,089, Jun-14 CONTRACTOR/CONSULTANT SUBMITTALS DURING THIS PERIOD Hy-Rail Vehicle Field Survey Report c.2 Rev Hy-Rail Vehicle Bill of Materials Rev Operating Rule Modifications-DRAFT e Rev Onboard Physical and Functional ICD F59 Survey Report c.1 Rev F40 F59 BCC Antenna Base Connection Sealant e.7 Rev F40 F59 BCC Antenna Base Connection Sealant e.7 Revised Rev Onboard Antenna Base Connection Sealant Alternate e.8 Rev GE MDS 220MHz PTC Radio g.iii.2 Rev Lilee PTC Radios g.iii.3 Rev MHz In-Line Filter g.iii.5 Rev MHz In-Line Filter g.iii.6 Rev Dixie Helical Tower Base Extension g.iii.10 Rev Polyphaser Transmission Line Static Arrestor g.iii.11 Rev Trebuchet Tower Systems g.iii.21 Rev PTC Dual Track Antenna System g.iii.27 Rev Trebuchet Tower Bases Part 2 - Pier Extensions g.iii.42 Rev Back Office Connections "Draft" Rev % Design - Typical PTC Comm Site Rev Wi-Fi System c Rev Level 2 Network V and V Plan i.x Rev TMDS BOS Equipment Bill of Materials i.iii.1.1 Rev Back Office ITCM, WSRS, and NMS BOM with Product Data i.iii.4 Rev Field Integration and Functional Regression Test Book m.vi.16.b Rev As-Built Drawings Back Office e.iii.58 Rev Typical PTC Communication Site "Draft" Rev PTCSP Appendix V Post Implementation Safety Testing and Monitoring Plan Final Acceptance Test Program a.i.7 Rev WSRS Test Cases and Procedures d.8 Rev Regression Test 1 Wayside V & V Test Report m.vi.1.d Rev 1 Page 16 of 26

18 System Integration Test Book m.vi.10 Rev WRE Onboard Software Quality Assurance Plan a.3 Rev PTCSP Appendix L O&M Manuals e.ii Rev Wheel Size Calibration d Rev 0 and sent reply to NCTD ICD for PTC Communications Design i.vii.b Rev Level 3 Communication Network Architecture Layout j.ii.1 Rev ITCM Guide to Federation Between Organizations c.i.2 Rev PTC Safety Plan 90% b.1.a Rev OSCAR Training Validation Report b.24 Rev Availability and Reliability Demo Report c.iii Rev System Integration Test Cases and Procedures d.15 Rev Regression Test 2 Wayside V&V Test Report m.vi.1.g Rev Regression Test 4 Critical Feature V&V Test Book m.vi.11.h Rev Regression Test 4 Critical Feature V&V Test Report m.vi.11.j Rev System Training Manual e.1 Rev System Hardware Manual e.3 Rev System Software Manual e.4 Rev System Communication Network/Administration Manual e.5 Rev Communications, Network, and Wayside Spare Parts List Rev 3 Page 17 of 26

19 Jul-11 Oct-11 Jan-12 Apr-12 Jul-12 Oct-12 Jan-13 Apr-13 Jul-13 Oct-13 Jan-14 Apr-14 Jul-14 Oct-14 Jan-15 Apr-15 Jul-15 Oct-15 Jan-16 Apr-16 Jul-16 Oct-16 Jan-17 Apr-17 Jul-17 Oct-17 Jan-18 Apr-18 Jul-18 Oct-18 Figure 5.1 shows the S-curve for the PTC project (PO 11046) dollars expended and projected, versus dollars contracted. The equation used to formulate the S-Curve is a logistic differential formula, which creates a graphic display of cumulative estimated costs plotted against time. S-Curve forecasting assumes slow initial growth, subsequent rapid growth, followed by declining growth as saturation levels are achieved. The essential concept of this function illustrates that the rate of growth is proportional to both the amount of growth already accomplished and the amount of growth remaining to be accomplished. The expended amount shows the total amount that NCTD has paid to HTI as of December 31, Figure 5.1: PTC Project (PO 11046) Budgeted versus Expended $40,000,000 $35,000,000 $30,000, HTI Contract $31,891,426 $37,637, $37,581,26 $25,000,000 $20,000,000 $15,000,000 $10,000,000 $5,000,000 $- Budgeted Expended (Cumulative) Future Spending San Diego Subdivision Fiber Installation The San Diego Subdivision fiber installation is comprised of three geographically based contracts as listed below: North COASTER Orange County Line to Oceanside Transit Center South COASTER Oceanside Transit Center to Old Town Transit Center San Diego Old Town Transit Center to Santa Fe Depot All three contracts include the installation of fiber conduit and cable along the San Diego Subdivision right-of-way to provide fiber for the PTC communication system. Status and financial information on the individual contracts is provided on Tables 5.3, 5.4 and 5.5. Page 18 of 26

20 Table 5.4: Design Support During Construction; NCTD PO#29895 NCTD PURCHASE ORDER PROJECT NAME CONTRACTOR/CONSULTANT Design Support During Construction Pacific Railway Enterprises, Inc. BRIEF PROJECT DESCRIPTION This contract provides signal and communication systems support for the PTC project as well as inspection services. PROJECT STATUS On-Going The consultant is providing ongoing design reviews and inspection services for the PTC project. CONTRACT DATES COMPLETION UPDATE NTP 11/08/2011 Contract Completion 12/31/2015 Amendment 3 Contract Completion 4/30/2016 COST UPDATE Overall Contract 98% Contract Amount $2,742,430 Spent to Date $2,741,500 Encumbered $900 CONTRACT & BUDGET INFORMATION Description Contract Amount Date Executed Contract Value $2,000,000 8-Nov-11 Amendment 1 $160, Jun-12 Amendment 3 $581,908 1-Oct-15 CONTRACTOR/CONSULTANT SUBMITTALS DURING THIS PERIOD Various project documentation. Page 19 of 26

21 Table 5.5: Engineering Support Services; NCTD PO#17021 NCTD PURCHASE ORDER PROJECT NAME CONTRACTOR/CONSULTANT Engineering Support Services HNTB BRIEF PROJECT DESCRIPTION Scope includes design submittal review, as needed design work, scheduling services, and general project management. PROJECT STATUS On-Going HNTB Program Management efforts are ongoing. Primary activity is submittal review for the PTC project. CONTRACT DATES COMPLETION UPDATE NTP 12/1/2016 Contract Completion 12/31/2018 COST UPDATE Overall Contract 0% Contract Amount $2,001,014 Spent to Date $0 Encumbered $2,001,014 CONTRACT & BUDGET INFORMATION Description Contract Amount Date Executed Contract Value $2,001,014 11/1/2016 CONTRACTOR/CONSULTANT SUBMITTALS DURING THIS PERIOD Various project documentation. Page 20 of 26

22 Table 5.6: Environmental Support Services; NCTD PO#16011 NCTD PURCHASE ORDER PROJECT NAME CONTRACTOR/CONSULTANT Environmental Support Services BRG Consulting BRIEF PROJECT DESCRIPTION This contract provides as needed environmental support for PTC project. PROJECT STATUS On-Going Efforts are provided on an as-needed basis for environmental and archeological monitoring support for the PTC Program. CONTRACT DATES NTP 10/1/2016 Contract Completion 12/31/2018 COMPLETION UPDATE COST UPDATE Overall Contract 8% Contract Amount $65,647 Spent to Date $5,190 Encumbered $60,457 CONTRACT & BUDGET INFORMATION Description Contract Amount Date Executed Original Contract Value $65,647 10/1/2016 CONTRACTOR/CONSULTANT SUBMITTALS DURING THIS PERIOD None. Page 21 of 26

23 6. EXPENDITURES / FUNDING SOURCES 6.1. Expenditures Through March 31, 2017, expenditures to date on the PTC Program total $67,165,190 or 75 percent of the project budget. The period expenditures total $620,846 and were primarily composed of contractor charges, followed by engineering and consultant charges. Overall, expenditures are in line with the current $87,292,969 estimate at completion. Without contingency, the project value is currently $85,515,711. NCTD is closely monitoring the budget and the impact of pending contractor change orders and schedule changes. Figure 6.1 represents the budgeted funding versus the expenditures to-date for the overall PTC Program. Figure 6.1: PTC Program Budgeted versus Expended Page 22 of 26

24 6.2. Funding Sources The FRA and Prop 1A Discretionary funds comprise just over 55 percent of the overall PTC budget. Prop 1A Formula funds total 20 percent of the PTC program budget and Federal Section 5307 Formula Funds total comprise roughly 9 percent. A variety of sources makes up the remaining 16 percent, with the largest component being Proposition 1B TSGP funds. Table 6.2 summarizes the PTC Program Funding. Table 6.2: PTC Program Funding Description Total Planned and Programmed Funding Federal Section 5307 Formula Funds $7,658, FRA $24,900, Prop 1A Discretionary $24,010, Prop 1A Formula $17,833, Prop 1B - PTMISEA $1,302, Prop 1B TSGP $5,757, Other State / Local Funding $3,641, TDA Article 4.0 $1,190, TransNet Major Corridor $1,000, Total $87,292, Page 23 of 26

25 7. PROJECT PHOTOS NCTD Purchase Order 11046: PTC for the LOSSAN Corridor The following photos were taken during construction: Reviewing brake test results Back office server Network nodes Network management system Page 24 of 26

26 APPENDIX A: ABBREVIATIONS AAR Association of American Railroads FHWA Federal Highway Administration ABS Automatic Block Signal System FIT Field Integration Test AFR Audit Finding Report FIT-I Field Integration Test Interoperable ALI Application Layer Interface FMEA Failure Modes and Effects Analysis AMQP Advanced Message Queuing Protocol FMECA Failure Modes, Effects and Criticality Analysis AMTRAK National Railroad Passenger Corporation FQT Field Qualification Test ANSI American National Standards Institute FQT-I Field Qualification Test Interoperable APTA American Public Transportation Association FRA Federal Railroad Administration AREMA American Railway Engineering and FRACAS Failure Reporting Analysis and Corrective Action AREMA C&S Maintenance-of Way Association American Railroad Engineering and Maintenance of Way Association Signal and Communications Manual of Recommended Practices FST FTA Page 25 of 26 System Fire Safety Test Fault Tree Analysis ASCE American Society of Civil Engineers GCOR General Code of Operating Rules ASQ American Society For Quality GIS Geographic Information System ASTM American Society for Testing and Materials GPS Global Positioning System ATCS Automatic Train Control System HFA Human Factors Analysis ATS Automatic Train Stop HL Hazard Log BCP Base Communications Package HMI Human Machine Interface BER Bit Error Rate HTI Herzog Technologies, Inc. BMP Best Management Practices HVAC High Volume Air Conditioning BNSF BNSF Railway HW Hardware BOS Back Office Server HwDD Hardware Design Document BPRA Baseline Pre-Release Audit I Interface C Carrier IA Impact Analysis CA California IC3 Individual Composite CRC (Cyclic Redundancy Check) Calculator CAD Computer Aided Dispatch ICD Interface Control Document CADD Computer Aided Drafting and Design ICM Interface Control Module CAR Corrective Action Request ICWG Interface Control Working Group CBTC Communications Based Train Control ID Identifier CCB Change Control Board IEEE Institute of Electrical and Electronic Engineers CCMP Configuration Control Management Plan IETF Internet Engineering Task Force CDR Critical Design Review I-ETMS Interoperable Electronic Train Management System CDRL Contract Deliverable Requirements List IM Inter-Modulation CDU Computer Display Unit (onboard) IMM Interface Management Matrix CFR Code of Federal Regulation IO Input / Output CHM Crash Hardened Memory IOC Input Output Concentrator (module) CI Configuration Item IP Ingress Protection / Implementation Plan CIL Configuration Item Library ISO International Organization for Standardization CIPAA Configuration Item Pre-Acceptance Audit IT Information Technology CM Configuration Management ITC Interoperable Train Control CMU Communication Management Unit ITCM ITC Messaging COM Communications Network (PTC Subsystem) ITP Interoperable Transport Protocol CONOPS Concept of Operations JRST Joint Railroad Safety Team COT Current Of Traffic LAN Local Area Network COTS Commercial Off the Shelf LCD Liquid Crystal Display CP Control Point LIEE Laboratory Integration End to End CPM Critical Path Method LIEE-I Laboratory Integration End to End Interoperable CPU Central Processor Unit LINN Laboratory Integration Nearest Neighbor CPUC California Public Utilities Commission LOB Locomotive On-Board (PTC Subsystem) CRC Cyclic Redundancy Check LQEE Laboratory Qualification End to End CSA Configuration Status Accounting LQS Laboratory Qualification Segment CTC Centralized Traffic Control LRU Lowest Replaceable Unit DIO Digital Input / Output (module) MA Message Agent DIP Design Integration Plan MAH Model-Approved Hardware DOD Department of Defense MAS Maximum Authorized Speed DT Double Track MCC Meteorcomm LLC DVCS Distributed Version Control System MCP Mobile Communications Package ecil Electronic Configuration Item Library MDT Maintainability Demonstration Test EIA Electronic Industries Alliance ME Message Exchange EIC Employee in Charge (Work Crew) MGT Million Gross Tons EMC Electromagnetic Compatibility MHz Megahertz EMD Electro Motive Diesel MIS Management Information System EMI Electromagnetic Interference ML Mainline ETL Electrical Testing Laboratories MO Message Originator ETMS Electronic Train Management System MOC Metrolink Operations Center FAT Factory Acceptance Testing MOE Maintenance of Equipment FCC Federal Communications Commission MOW Maintenance of Way FCMP Field Configuration Management Plan MP Mile Post FFT Functional Fault Tree MPH Miles per Hour

27 MPP Maintainability Program Plan SCM Software Configuration Management MQ Message Queue SHA System Hazard Analysis MR Message Recipient SHA-1 Secure Hash Algorithm 1 MRB Message Routing and Binding SMCP Software Management Control Plan MTBF Mean Time Between Failures SME Subject Matter Expert MTBSDF Mean Time Between Service-Disrupting Failure SOF Sprinter Operations Facility MTEA Mainline Track Exclusion Addendum SRS Systems Requirements Specification MTS Master Test Strategy SSHA Subsystem Hazard Analysis MTTHE Mean Time to Hazardous Event SSID System Safety Integration Document MTTRS Mean Time to Restore Service SSIP System Safety Integration Packet MUTCD Manual on Uniform Traffic Control Devices Subpart H 49 CFR Part 236 Subpart H N Noise Subpart I 49 CFR Part 236 Subpart I NAD North American Datum SW Software NAVD North American Vertical Datum SwDD Software Design Document NCTD North County Transit District SyDS System Design Specification NDGPS Nationwide Differential Global Positioning SyRS System Requirements Specification System NEC National Electrical Code TASI TransitAmerica Services, Inc. NEMA National Electrical Manufacturers Association TBD To Be Determined NESC National Electrical Safety Code TCNS Tower Construction Notification System NETA National Electrical Testing Association, Inc. TCP / IP Transmission Control Protocol / Internet Protocol NPI Notice of Product Intent TEC Test Environment Configuration NS Norfolk Southern Railroad TIA Telecommunications Industry Association NTP Notice to Proceed TIH Toxic Inhalation Hazard O&SHA Operation and Support Hazard Analysis TMC Train Management Computer OBC Onboard Segment Hardware Chassis TMDS Train Management and Dispatching System OCC Operations Control Center TSR Temporary Speed Restrictions OEM Original Equipment Manufacturer TWC Track Warrant Control OS Office Segment UBC Uniform Building Code OSHA Occupational Safety and Health Administration UHF Ultra High Frequency OSI Open Systems Interconnection UI User Interface OTA Over The Air UL Underwriters Laboratories, Inc. OTE On-Track Equipment UPRR Union Pacific Railroad PC Printed Circuit UPS Uninterruptible Power Supply PCBA Production Current Baseline Audit USB Universal Serial Bus PCIL Physical Configuration Item Library USC United States Code PHA Preliminary Hazard Analysis V&V Verification & Validation PIH Poison by Inhalation Hazard VCS Version Control System PMP Project Management Plan VHF Very High Frequency PRE Pacific Railway Enterprises WAAS Wide Area Application System PSP PSR Product Safety Plan (per FRA Subpart H) Permanent Speed Restrictions Wabtec PTC Positive Train Control WAN Wide Area Network PTCDP PTC Development Plan WIU Wayside Interface Unit Westinghouse Air Brake Technologies Corporation PTCIP PTC Implementation Plan WLAN Wireless Local Area Network PTCPVL PTC Product Vendors List WMS Wayside Message Server PTCSP PTC Safety Plan WRE Wabtec Railway Electronics PTCSPDD PTC Safety Plan Definition Document WSWS Wayside Status Message PTCSYS PTC System WS Wayside Segment PTS Positive Train Stop WSRS Wayside Status Relay Service QA Quality Assurance QC Quality Control QM Quality Management RA Risk Assessment RAM Reliability, Availability, Maintainability RF Radio Frequency RFA Request for Amendment RFC Request for Comment RFI Request for Information RFP Request for Proposal ROW Right of Way RPP Reliability Program Plan RSAC Railway Safety Advisory Committee RSD Revenue Service Demonstration RSIA08 Rail Safety Improvement Act of 2008 RSPP Railroad Safety Program Plan RTM Requirements Traceability Matrix SAC Safety Assurance Concept SANDAG San Diego Area Governments SAT Site Acceptance Test SBD Safe Breaking Distance SCIL Safety-Critical Items List (same as Hazard Log) Page 26 of 26

Positive Train Control Quarterly Report

Positive Train Control Quarterly Report ATTACHMENT 12A Positive Train Control Quarterly Report For the Period October 1, 2017 December 31, 2017 (Q2 of FY 2018) Contents 1. EXECUTIVE SUMMARY... 3 1.1. Project Overview... 3 1.1.1. PTC Inter-Agency

More information

POSITIVE TRAIN CONTROL

POSITIVE TRAIN CONTROL POSITIVE TRAIN CONTROL Quarterly Report Quarter Ending September 30, 2016 CONTENTS 1. EXECUTIVE SUMMARY... 1 1.1. Project Overview... 1 1.1.1. PTC Inter-Agency Coordination... 1 1.1.2. PTC Operations and

More information

Positive Train Control Quarterly Report

Positive Train Control Quarterly Report ATTACHMENT 3A Positive Train Control Quarterly Report For the Period July 1, 2018 September 30, 2018 (Q1 of FY 2019) Contents 1. EXECUTIVE SUMMARY... 3 1.1. Project Overview... 3 1.1.1. PTC Inter-Agency

More information

POSITIVE TRAIN CONTROL

POSITIVE TRAIN CONTROL POSITIVE TRAIN CONTROL Quarterly Report Quarter Ending September 30, 2014 CONTENTS 1. EXECUTIVE SUMMARY... 1 1.1. Project Overview... 1 1.1.1. PTC Inter-Agency Coordination... 1 1.1.2. PTC Operations and

More information

POSITIVE TRAIN CONTROL

POSITIVE TRAIN CONTROL POSITIVE TRAIN CONTROL Quarterly Report Quarter Ending June 30, 2014 CONTENTS 1. EXECUTIVE SUMMARY... 1 1.1. Project Overview... 1 1.1.1. PTC Inter-Agency Coordination... 1 1.1.2. PTC Operations and Maintenance...

More information

ARINC PROPRIETARY. Overview of PTC. Gary Pruitt Senior Director Advanced Technology Programs ARINC

ARINC PROPRIETARY. Overview of PTC. Gary Pruitt Senior Director Advanced Technology Programs ARINC ARINC PROPRIETARY Overview of PTC Gary Pruitt Senior Director Advanced Technology Programs ARINC Topics PTC History and Mandate PTC Functions ITC versus ACSES ITC PTC Architecture ACSES Architecture Interoperability

More information

Deploying I-ETMS: What do I need to know???

Deploying I-ETMS: What do I need to know??? Deploying I-ETMS: What do I need to know??? 1 Agenda Why should I care? I-ETMS Overview How hard can it be? 2 Why should I care? Do you have to deploy PTC? Are you a Class 1 railroad? Required to deploy

More information

PART II SCHEDULE. Scope of Services. Special Terms and Conditions. Virginia Railway Express

PART II SCHEDULE. Scope of Services. Special Terms and Conditions. Virginia Railway Express PART II SCHEDULE SECTION TITLE D E Scope of Services Special Terms and Conditions 10 SECTION D SCOPE OF SERVICES D.1 OVERVIEW A. PTC was mandated by Congress in the RSIA of 2008 for all railroads that

More information

The Use of E-ATC as a PTC System By

The Use of E-ATC as a PTC System By The Use of E-ATC as a PTC System By Dale Hein, P.Eng. Hatch Mott MacDonald 840 7 th Avenue SW, Suite 1250 Calgary, AB, Canada T2P-3G2 (587) 293-6224 dale.hein@hatchmott.com And Richard Morris Hatch Mott

More information

Interoperable Positive Train Control (PTC) William A Petit AREMA 2009 Annual Conference Communications and Signals Track

Interoperable Positive Train Control (PTC) William A Petit  AREMA 2009 Annual Conference Communications and Signals Track Interoperable Positive Train Control (PTC) William A Petit www.billpetit.com AREMA 2009 Annual Conference Communications and Signals Track Abstract: This paper discusses architecture, interoperability

More information

FLORIDA DEPARTMENT OF TRANSPORTATION

FLORIDA DEPARTMENT OF TRANSPORTATION FLORIDA DEPARTMENT OF TRANSPORTATION ADDENDUM NO. 5 DATE: 3/31/17 RE: RFP-DOT-16/17-9010-GH POSITIVE TRAIN CONTROL SYSTEM FOR THE (CFRC) Notice is hereby given of the following changes to the above-referenced

More information

ANTF September 7th, 2013

ANTF September 7th, 2013 Transportation Technology Center, Inc., a subsidiary of the Association of American Railroads Positive Train Control Overview Ruben D. Peña Paulo Vieira IV Encontro de Ferrovias ANTF September 7th, 2013

More information

ABCs of Positive Train Control (PTC)

ABCs of Positive Train Control (PTC) ABCs of Positive Train Control (PTC) ASLRRA PTC Symposium April 27th, 2013 Why PTC? Over the last four decades, the National Transportation Safety Board (NTSB) has investigated a long list of accidents

More information

Frequently Asked Questions (FAQs) For Communications Based Overlay Signal System (CBOSS) Positive Train Control (PTC)

Frequently Asked Questions (FAQs) For Communications Based Overlay Signal System (CBOSS) Positive Train Control (PTC) (FAQs) For Communications Based Overlay Signal System (CBOSS) Positive Train Control (PTC) 1. What is CBOSS PTC? CBOSS PTC stands for Communications Based Overlay Signal System (CBOSS) Positive Train Control

More information

CALTRAIN S PTC SOLUTION FOR 2015 CBOSS

CALTRAIN S PTC SOLUTION FOR 2015 CBOSS CALTRAIN S PTC SOLUTION FOR 2015 CBOSS (COMMUNICATIONS BASED OVERLAY SIGNAL SYSTEM) SYSTEM DESCRIPTION 1. INTRODUCTION This document provides the system level description of the Communications Based Overlay

More information

INTELLIGENT TRANSPORTATION SYSTEMS APPENDIX

INTELLIGENT TRANSPORTATION SYSTEMS APPENDIX INTELLIGENT TRANSPORTATION SYSTEMS APPENDIX Southern California Association of Governments ADOPTED APRIL 2012 INTELLIGENT TRANSPORTATION SYSTEMS Introduction 1 Existing System Description 1 Existing System

More information

Modeling Risk for Positive Train Control (PTC) Systems

Modeling Risk for Positive Train Control (PTC) Systems Modeling Risk for Positive Train Control (PTC) Systems Craig W. Shier craig.shier@lmco.com Lockheed Martin Risk Modeling on IDOT PTC The IDOT Positive Train Control (PTC) System prevents Train-to to-train

More information

Train Control, Communications and Operations Committee Update for APTA

Train Control, Communications and Operations Committee Update for APTA Train Control, Communications and Operations Committee Update for APTA Michael R Newcomb (AAR - TCCO Chair) AVP Transportation Systems Development Union Pacific Railroad June 2017 - APTA Conference Agenda

More information

Positive Train Control (PTC) Amtrak s Northeast Corridor

Positive Train Control (PTC) Amtrak s Northeast Corridor Positive Train Control (PTC) on Amtrak s Northeast Corridor 12 July 2012, Session: Infrastructure 3 - Power Supply & Signaling Requirement for PTC The Rail Safety Improvement Act of 2008 requires that

More information

Third Party Contracts Quality Management Plan (TPCQMP) Revision 00 Issue Date: August 6, 2018

Third Party Contracts Quality Management Plan (TPCQMP) Revision 00 Issue Date: August 6, 2018 Third Party Contracts Quality Management Plan (TPCQMP) Revision 00 Issue Date: August 6, 2018 Northeast Illinois Regional Commuter Railroad Corporation 547 West Jackson Boulevard Chicago, Illinois 60661

More information

Board of Directors Meeting Monday May 22, :30 p.m.

Board of Directors Meeting Monday May 22, :30 p.m. Board of Directors Meeting Monday May 22, 2017 3:30 p.m. Intermodal Transportation Center (ITC) 1001 Jones Street, 2nd Floor Community Room Fort Worth, TX 76102 BOARD OF DIRECTORS MEETING AGENDA 3:30

More information

SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES

SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES SECTION: SFPUC INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURE NO: 018 TITLE: SYSTEM TESTING AND START-UP APPROVED:

More information

TESTIMONY OF PAUL P. SKOUTELAS PRESIDENT AND CEO AMERICAN PUBLIC TRANSPORTATION ASSOCIATION BEFORE THE

TESTIMONY OF PAUL P. SKOUTELAS PRESIDENT AND CEO AMERICAN PUBLIC TRANSPORTATION ASSOCIATION BEFORE THE TESTIMONY OF PAUL P. SKOUTELAS PRESIDENT AND CEO AMERICAN PUBLIC TRANSPORTATION ASSOCIATION BEFORE THE SUBCOMMITTEE ON RAILROADS, PIPELINES AND HAZARDOUS MATERIALS OF THE HOUSE COMMITTEE ON TRANSPORTATION

More information

Safety Analysis of Electronically Controlled Pneumatic Brake Equipment for Passenger Trains

Safety Analysis of Electronically Controlled Pneumatic Brake Equipment for Passenger Trains Request for Proposals (RFP) Safety Analysis of Electronically Controlled Pneumatic Brake Equipment for Passenger Trains Issued by: The North American Transit Services Association, a subsidiary of The American

More information

A Balancing Act: Positive Train Control

A Balancing Act: Positive Train Control A Balancing Act: Positive Train Control Rickey Green Stantec Consulting Services Inc. Dallas, TX In August 1999, the Federal Railroad Administration's Safety Advisory Committee issued a report stating

More information

SCRRA RIGHT-OF-WAY ENCROACHMENT PROCESS

SCRRA RIGHT-OF-WAY ENCROACHMENT PROCESS SCRRA RIGHT-OF-WAY ENCROACHMENT PROCESS MARCH 2017 SCRRA RIGHT-OF-WAY ENCROACHMENT PROCESS 1.0 General A. All work activities within the SCRRA operating corridor and right-of-way, or work activities that

More information

Christy Wegener, Director of Planning and Operations

Christy Wegener, Director of Planning and Operations SUBJECT: FROM: Transit Signal Priority Upgrade Project Scope of Work for Design and Project Management Christy Wegener, Director of Planning and Operations DATE: October 2, 2017 Action Requested Authorize

More information

Commuter Rail Positive Train Control (PTC)

Commuter Rail Positive Train Control (PTC) Commuter Rail Positive Train Control (PTC) Program Update March 6, 2017 Overview To provide an update to the Fiscal and Management Control Board on the status of the MBTA s Commuter Rail Positive Train

More information

10-PCJPB-T Design/Procure/Install A Positive Train Control System For Caltrain Questions Received and Answers No. 6

10-PCJPB-T Design/Procure/Install A Positive Train Control System For Caltrain Questions Received and Answers No. 6 10-PCJPB-T-021 - Design/Procure/Install A Positive Train Control System For Caltrain Questions Received and Answers No. 6 # Question Response 1 Sample Agreement, Part 1 Section 3, Insurance, 20.2.1 requires

More information

ECP Brake Standardization Passenger and Commuter Equipment

ECP Brake Standardization Passenger and Commuter Equipment ECP Brake Standardization Passenger and Commuter Equipment Paul E. Jamieson, PE Interfleet Technology Principal Consultant Philadelphia, PA Andrew F. Pressley Wabtec Passenger Transit Lead Engineer Mechanical

More information

Regulatory Update. Southwest Association of Rail Shippers Dallas, Texas October 8, 2015

Regulatory Update. Southwest Association of Rail Shippers Dallas, Texas October 8, 2015 Regulatory Update Southwest Association of Rail Shippers Dallas, Texas October 8, 2015 Hottest Regulatory Issues Surface Transportation Board: Senate reauthorization bill, Revenue Adequacy / Cost of Capital,

More information

Transbay Transit Center Program

Transbay Transit Center Program Transbay Transit Center Program Quality Management System Manual Revision 1 September 2013 Quality Management System Manual Revision 1 September 2013 Prepared for the Transbay Joint Powers Authority

More information

An Approach to Predicting Passenger Operation Performance from Commuter System Performance

An Approach to Predicting Passenger Operation Performance from Commuter System Performance An Approach to Predicting Passenger Operation Performance from Commuter System Performance Bo Chang, Ph. D SYSTRA New York, NY ABSTRACT In passenger operation, one often is concerned with on-time performance.

More information

TESTIMONY OF JEFFREY D. KNUEPPEL, P.E. GENERAL MANAGER SOUTHEASTERN PENNSYLVANIA TRANSPORTATION AUTHORITY (SEPTA) ON BEHALF OF THE

TESTIMONY OF JEFFREY D. KNUEPPEL, P.E. GENERAL MANAGER SOUTHEASTERN PENNSYLVANIA TRANSPORTATION AUTHORITY (SEPTA) ON BEHALF OF THE TESTIMONY OF JEFFREY D. KNUEPPEL, P.E. GENERAL MANAGER SOUTHEASTERN PENNSYLVANIA TRANSPORTATION AUTHORITY (SEPTA) ON BEHALF OF THE AMERICAN PUBLIC TRANSPORTATION ASSOCIATION (APTA) BEFORE THE SUBCOMMITTEE

More information

TESTIMONY OF JEFFREY D. KNUEPPEL, P.E. GENERAL MANAGER SOUTHEASTERN PENNSYLVANIA TRANSPORTATION AUTHORITY (SEPTA) ON BEHALF OF THE

TESTIMONY OF JEFFREY D. KNUEPPEL, P.E. GENERAL MANAGER SOUTHEASTERN PENNSYLVANIA TRANSPORTATION AUTHORITY (SEPTA) ON BEHALF OF THE TESTIMONY OF JEFFREY D. KNUEPPEL, P.E. GENERAL MANAGER SOUTHEASTERN PENNSYLVANIA TRANSPORTATION AUTHORITY (SEPTA) ON BEHALF OF THE AMERICAN PUBLIC TRANSPORTATION ASSOCIATION (APTA) BEFORE THE SUBCOMMITTEE

More information

Federal Railroad Administration Report to Congress. Railroads Progress Toward Implementation of Positive Train Control Systems

Federal Railroad Administration Report to Congress. Railroads Progress Toward Implementation of Positive Train Control Systems Federal Railroad Administration Report to Congress Railroads Progress Toward Implementation of Positive Train Control Systems July 1, 2018 I. Introduction Pursuant to Title 49 United States Code (U.S.C.)

More information

Rail Division. Riding the Rails

Rail Division. Riding the Rails Rail Division Riding the Rails Amtrak Ridership within Texas Remains Strong The annual ridership within Texas on all three services (Heartland Flyer, Texas Eagle and Sunset Limited) continues to soar.

More information

FACILITIES BUILDING STANDARDS

FACILITIES BUILDING STANDARDS FACILITIES BUILDING STANDARDS Section 25 0000 Integrated Automation Revised date: 09/18/18 PART 1 - GENERAL 1.1 SUMMARY A. Section includes the general requirements for the Integrated Automation systems.

More information

TECHNICAL MEMORANDUM

TECHNICAL MEMORANDUM TECHNICAL MEMORANDUM Concept Level Operational Feasibility Study TM 4.1 Prepared by: Signed document on file Paul Mosier _21 July 08 _ Date Checked by: Signed document on file 21 July 08 Ken Jong, PE Date

More information

EXHIBIT C OPERATING SYSTEM INTERFACE (OSI)

EXHIBIT C OPERATING SYSTEM INTERFACE (OSI) EXHIBIT C OPERATING SYSTEM INTERFACE (OSI) PART 1 - GENERAL 1.01 DESCRIPTION Outline for Contractor s interface with Caltrain s operating system, including track work, train control, and communications.

More information

LILEE Systems Office 365 Experience Sharing

LILEE Systems Office 365 Experience Sharing LILEE Systems Office 365 Experience Sharing Ken Yu Ken.Yu@lileesystems.com Dec 20, 2015 Agenda About LILEE Systems Total Addressable Market Products & Solutions Current Customers IT Cloud Services 2 About

More information

City of San Mateo Clean Water Program Programmable Logic Controller (PLC) and Human Machine Interface (HMI) Programming Services

City of San Mateo Clean Water Program Programmable Logic Controller (PLC) and Human Machine Interface (HMI) Programming Services ATTACHMENT A SAMPLE SCOPE OF SERVICES PLC & HMI PROGRAMMING City of San Mateo Clean Water Program Programmable Logic Controller (PLC) and Human Machine Interface (HMI) Programming Services December, 2017

More information

SECTION BASIC REQUIREMENTS FOR SYSTEMS

SECTION BASIC REQUIREMENTS FOR SYSTEMS SECTION 13570 BASIC REQUIREMENTS FOR SYSTEMS PART 1 GENERAL 1.01 SUMMARY A. This Section describes the basic requirements and functionality for designing, furnishing, and installing the SEPTA Wayside System

More information

SIXTH STREET VIADUCT REPLACEMENT PROJECT MONTHLY EXECUTIVE MEETING REPORT JULY 2013

SIXTH STREET VIADUCT REPLACEMENT PROJECT MONTHLY EXECUTIVE MEETING REPORT JULY 2013 SIXTH STREET VIADUCT REPLACEMENT PROJECT MONTHLY EXECUTIVE MEETING REPORT JULY 2013 Sixth Street Viaduct Replacement Project Monthly Executive Meeting Report July 2013 TABLE OF CONTENTS Project Manager

More information

I. Development, Submittal, and Acceptance of a Quality Management System

I. Development, Submittal, and Acceptance of a Quality Management System I. Development, Submittal, and Acceptance of a Quality Management System 1. Scope Under the Contract, quality assurance and quality control management are the responsibility of the Contractor. The Contractor

More information

City of Dubuque: Smart Traffic Routing with Efficient & Effective Traffic System (STREETS) Final Report version 1.1

City of Dubuque: Smart Traffic Routing with Efficient & Effective Traffic System (STREETS) Final Report version 1.1 City of Dubuque: Smart Traffic Routing with Efficient Final Report version 1.1 June 22, 2018 Submitted to: 17J18 0640 Prepared by Iteris, Inc. Iteris, Inc. i DOCUMENT VERSION CONTROL DOCUMENT NAME SUBMITTAL

More information

Testimony of. Scot Naparstek. Chief Operating Officer. National Railroad Passenger Corporation. Before the. United States Senate

Testimony of. Scot Naparstek. Chief Operating Officer. National Railroad Passenger Corporation. Before the. United States Senate Testimony of Scot Naparstek Chief Operating Officer National Railroad Passenger Corporation Before the United States Senate Committee on Commerce, Science, and Transportation Implementation of Positive

More information

YOUR TRANSPORTATION CO.

YOUR TRANSPORTATION CO. For fast dependable Transportation Services YOUR TRANSPORTATION CO. Compliments of Marc T. Smith CAYMAN SYSTEMS INTERNATIONAL Specializing in Small & Medium Business Compliance Help e-mail to:cayman@qs9000.com

More information

NRC INSPECTION MANUAL

NRC INSPECTION MANUAL NRC INSPECTION MANUAL QVIB INSPECTION PROCEDURE 70702 PART 52, INSPECTION OF PREOPERATIONAL TEST PERFORMANCE PROGRAM APPLICABILITY: 2504 70702-01 INSPECTION OBJECTIVES 01.01 To provide guidance for inspection

More information

Development Services Department Anchorage: Performance. Value. Results.

Development Services Department Anchorage: Performance. Value. Results. Anchorage: Performance. Value. Results. Purpose Development Services works to facilitate development in accordance with municipal codes, municipal design criteria, and municipal construction standards.

More information

Agency Request for Regular Processing of Collection of Information by the Office of Management and Budget

Agency Request for Regular Processing of Collection of Information by the Office of Management and Budget This document is scheduled to be published in the Federal Register on 05/09/2016 and available online at http://federalregister.gov/a/2016-10831, and on FDsys.gov 4910-06-P DEPARTMENT OF TRANSPORTATION

More information

Technology Integration Project

Technology Integration Project Project Progress Report #3 As of January 31, 2003 Sam M. McCall, CPA, CIA, CGFM City Auditor Technology Integration Project Report #0311 February 20, 2003 Summary The City is currently in the process of

More information

Development Services Department Anchorage: Performance. Value. Results.

Development Services Department Anchorage: Performance. Value. Results. Anchorage: Performance. Value. Results. Purpose Development Services works to facilitate development in accordance with municipal codes, municipal design criteria, and municipal construction standards.

More information

PRIIA Section 305 Executive Committee 10/20/2010. Version 3

PRIIA Section 305 Executive Committee 10/20/2010. Version 3 Requirements Document Diesel Locomotive Version 3 Introduction The Next-Generation Equipment Committee (NGEC) was established under the provisions of section 305 of the Passenger Rail Investment and Improvement

More information

Progress Report Sounder Program

Progress Report Sounder Program Progress Report Sounder Program Tacoma Trestle - Flatiron workers installing forms for the south platform grade beam. September 2017 Prepared by Project Control l Design, Engineering & Construction Management

More information

Table of Contents. Project Agreement Schedule 14

Table of Contents. Project Agreement Schedule 14 Table of Contents PART 1 DEFINITIONS... 3 PART 2 INTEGRATED MANAGEMENT SYSTEM REQUIREMENTS... 6 2.1. Introduction... 6 2.2. Overview... 6 2.2.1 Management System Requirements... 7 2.2.2 Certification...

More information

Development Services Department Anchorage: Performance. Value. Results.

Development Services Department Anchorage: Performance. Value. Results. Development Services Department Anchorage: Performance. Value. Results. Purpose Development Services works to facilitate development in accordance with municipal codes, municipal design criteria, and municipal

More information

ASSOCIATION 0 OF AMERICAN RAILROADS

ASSOCIATION 0 OF AMERICAN RAILROADS ASSOCIATION 0 OF AMERICAN RAILROADS 6/25/2013 Overview of the AAR for The 2013 DP&FC Conference Jim Grady Assistant Vice President Technical Services AAR IS A Trade Association Based in Washington, DC

More information

CODE: FD10 Rev: A Date: 9/24/2008 CONFIGURATION MANAGEMENT

CODE: FD10 Rev: A Date: 9/24/2008 CONFIGURATION MANAGEMENT 1.0 Definition of terms: CONFIGURATION MANAGEMENT 1.01 The term shall, will and may are used with specific intent thought-out these documents and will observe the following rules: 1.1 Requirements defined

More information

ATTACHMENT D SCOPE OF SERVICES

ATTACHMENT D SCOPE OF SERVICES ATTACHMENT D SCOPE OF SERVICES OBJECTIVE Owner s Capital Improvement Program (major capital, minor construction, repair, and rehabilitation projects) includes numerous construction and renovation projects.

More information

CHAPTER 11 SIGNALLING SYSTEM

CHAPTER 11 SIGNALLING SYSTEM CHAPTER 11 SIGNALLING SYSTEM 11.1 SIGNALLING 11.2 SIGNALLING AND TRAIN CONTROL 11.3 SPACE REQUIREMENT FOR SIGNALLING INSTALLATIONS 11.4 MAINTENANCE PHILOSOPHY FOR SIGNALLING SYSTEMS TABLES TABLE 11.1 SIGNALLING

More information

A. The purpose of this section is to specify Division 23 responsibilities in the commissioning process.

A. The purpose of this section is to specify Division 23 responsibilities in the commissioning process. SECTION 23 99 50 - (ADD#4) PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections,

More information

Communications Contractor QA/QC Plan Sample

Communications Contractor QA/QC Plan Sample Communications Contractor QA/QC Plan Sample Selected pages (not a complete plan) QA/QC Plan Sample Project-Specific Quality Plan Quality Manual Communications Standards & Inspection Forms Contact: Ed Caldeira

More information

METRO MANAGEMENT RESPONSES TO FISCAL 2005 FISCAL 2008 STATE REQUIRED PERFORMANCE AUDIT OF THE METROPOLITAN TRANSIT AUTHORITY OF HARRIS COUNTY, TEXAS

METRO MANAGEMENT RESPONSES TO FISCAL 2005 FISCAL 2008 STATE REQUIRED PERFORMANCE AUDIT OF THE METROPOLITAN TRANSIT AUTHORITY OF HARRIS COUNTY, TEXAS I. INTRODUCTION Pursuant to Chapter 451, Section 451.454 of the Texas Transportation Code, METRO must have an independent auditor perform a management audit every four years. The audit must include three

More information

SCHEDULE [NUMBER NAME OF WORK UNIT/WORK PACKAGE] TO THE IN-KIND CONTRIBUTION AGREEMENT SIGNED BETWEEN ESS AND PARTNER ON DATE

SCHEDULE [NUMBER NAME OF WORK UNIT/WORK PACKAGE] TO THE IN-KIND CONTRIBUTION AGREEMENT SIGNED BETWEEN ESS AND PARTNER ON DATE 1 (11) TA Template V3.0 SCHEDULE [NUMBER NAME OF WORK UNIT/WORK PACKAGE] TO THE IN-KIND CONTRIBUTION AGREEMENT SIGNED BETWEEN ESS AND PARTNER ON DATE 1. SCOPE This document describes the Scope of Work

More information

Progress Report Sounder Program

Progress Report Sounder Program Progress Report Sounder Program Sound Transit added a mid-day Sounder train to its popular south line service beginning Monday, September 12th September 2016 Prepared by Project Control l Design, Engineering

More information

1. Evaluation of route and service alternatives; 2. Tier 1 Environmental Impact Analysis; and 3. Service Development Plan.

1. Evaluation of route and service alternatives; 2. Tier 1 Environmental Impact Analysis; and 3. Service Development Plan. Rail Rail plays a significant role in transportation planning, especially when considering economic development, safety, freight, and intermodal connectivity. Jackson has two rail lines serving the area,

More information

2004 FEASIBILITY STUDY UPDATE

2004 FEASIBILITY STUDY UPDATE Austin-San Antonio Intermunicipal Commuter Rail District 2004 FEASIBILITY STUDY UPDATE December 2004 EXECUTIVE SUMMARY INTRODUCTION Almost 3 million people in Central Texas, living and working between

More information

Progress Report Sounder Program

Progress Report Sounder Program Progress Report Sounder Program Continued construction work for the Tacoma Trestle at East 26th and East G Streets. March 2017 Prepared by Project Control l Design, Engineering & Construction Management

More information

REQUIREMENTS DOCUMENTATION

REQUIREMENTS DOCUMENTATION REQUIREMENTS DOCUMENTATION Project Title: Date Prepared: Stakeholder Requirement Category Priority Acceptance Criteria REQUIREMENTS DOCUMENTATION Project Title: Date Prepared: Stakeholder Requirement Category

More information

UNIFIED FACILITIES GUIDE SPECIFICATIONS

UNIFIED FACILITIES GUIDE SPECIFICATIONS USACE / NAVFAC / AFCEC / NASA UFGS-01 45 00.10 20 (February 2010) Changed 1-08/17 ----------------------------------- Preparing Activity: NAVFAC Superseding UFGS-01 45 02.10 (November 2008) UNIFIED FACILITIES

More information

Instrument Control System Project Management

Instrument Control System Project Management Project Documentation Document PMCS-0021 Revision A Instrument Control System Project Management Bret Goodrich Software September 2015 Advanced Technology Solar Telescope 950 N. Cherry Avenue Tucson, AZ

More information

The Design-Builder shall provide Project preconstruction conference minutes within seven Days after the preconstruction conference.

The Design-Builder shall provide Project preconstruction conference minutes within seven Days after the preconstruction conference. 2 PROJECT MANAGEMENT 2.1 Scope Management 2.1.1 General The Design-Builder shall conduct all Work necessary to meet the requirements of scope management, including preparing, documenting, revising, and

More information

MEETING DATE: July 28, 2017 ITEM 20. Update on Coordination with the California High Speed Rail, Link US Projects, and Freight Railroads

MEETING DATE: July 28, 2017 ITEM 20. Update on Coordination with the California High Speed Rail, Link US Projects, and Freight Railroads REVISED July 25, 2017 Page 4 TRANSMITTAL DATE: July 21, 2017 MEETING DATE: July 28, 2017 ITEM 20 TO: FROM: SUBJECT: Board of Directors Arthur T. Leahy Update on Coordination with the California High Speed

More information

Railroad Industry Opportunity: Railway Signal & Systems Engineer

Railroad Industry Opportunity: Railway Signal & Systems Engineer Railroad Industry Opportunity: Railway Signal & Systems Engineer Description: The Northern Indiana Commuter Transportation District (NICTD) owns, operates and maintains the South Shore Line passenger rail

More information

Summary of TL 9000 R4.0 Requirements Beyond ISO 9001:2000

Summary of TL 9000 R4.0 Requirements Beyond ISO 9001:2000 This summary identifies the additional TL 9000 Release 4.0 requirements beyond those stated in ISO 9001:2000. See the TL 9000 R4.0 Handbook for the actual TL 9000 R4.0 requirements. ISO 9001:2000 section

More information

Using Hybrid LiDAR for Positive Train Control (PTC) Systems

Using Hybrid LiDAR for Positive Train Control (PTC) Systems Merrick s High Density Mapping System mounted on a helicopter collecting PTC information Using Hybrid LiDAR for Positive Train Control (PTC) Systems On May 12, 2015 an Amtrak Train from Washington D.C

More information

Quality Assurance Program for CDA / Design-Build Projects with a Capital Maintenance Agreement with Three Optional 5-Year Terms.

Quality Assurance Program for CDA / Design-Build Projects with a Capital Maintenance Agreement with Three Optional 5-Year Terms. Quality Assurance Program for CDA / Design-Build Projects with a Capital Maintenance Agreement with Three Optional 5-Year Terms August 29, 2017 2017 by Texas Department of Transportation 512/506-5808 All

More information

Enterprise Technology Projects Fiscal Year 2012/2013 Fourth Quarter Report

Enterprise Technology Projects Fiscal Year 2012/2013 Fourth Quarter Report Enterprise Technology Projects Fiscal Year 2012/2013 Fourth Quarter Report Enterprise Projects Fiscal Year 2012/2013 Fourth Quarter The Enterprise Program Investment Council (EPIC) is responsible for governance

More information

Patrick Malloy Communities Quality Assurance System

Patrick Malloy Communities Quality Assurance System Patrick Malloy Communities Quality Assurance System Page 1 of 83 Log of Quality Manual Revisions Version Number Revision Date Type of Revision 1 April 9, 2007 1 st release 1 April 13, 2007 Sec 1.10 removed

More information

Progress Report Sounder Program

Progress Report Sounder Program Progress Report Sounder Program Completing downspouts and other final touches on the Mukilteo Sounder Program new platform. September 2015 Prepared by Project Control September 2015 l Design, Engineering

More information

EXHIBIT A. TRANSIT AND MULTIMODAL DEVELOPMENT SUPPORT CONTINUING SERVICES SCOPE OF SERVICES FM No

EXHIBIT A. TRANSIT AND MULTIMODAL DEVELOPMENT SUPPORT CONTINUING SERVICES SCOPE OF SERVICES FM No EXHIBIT A TRANSIT AND MULTIMODAL DEVELOPMENT SUPPORT CONTINUING SERVICES SCOPE OF SERVICES FM No. 429768-4-12-01 This Exhibit forms an integral part of the Agreement between the DEPARTMENT and, the CONSULTANT,

More information

Supplier Quality Manual

Supplier Quality Manual ALLIANCE ELECTRONICS DISTRIBUTOR Supplier Quality Manual 22412 Gilberto Rd. Rancho Santa Margarita, CA 92688 INTRODUCTION Welcome to Alliance Electronics Distributor (AED) Alliance Electronics Distributor

More information

PROPOSAL EVALUATION WORKSHEET (CONSENSUS) EVALUATION FACTOR: TRANSPORTATION SERVICES PLAN (RATED) Selection Committee -#1, #12 and #25

PROPOSAL EVALUATION WORKSHEET (CONSENSUS) EVALUATION FACTOR: TRANSPORTATION SERVICES PLAN (RATED) Selection Committee -#1, #12 and #25 Selection Committee -#1, #12 and #25 PROPOSER: Keolis DATE: 09/25/2013 CONSENSUS RATING: Acceptable NARRATIVE SUMMARY: The Proposer has submitted an acceptable. The plan focuses on improving employee and

More information

10-PCJPB-T Design/Procure/Install A Positive Train Control System For Caltrain Questions Received and Answers No. 4

10-PCJPB-T Design/Procure/Install A Positive Train Control System For Caltrain Questions Received and Answers No. 4 10-PCJPB-T-021 - Design/Procure/Install A Positive Train Control System For Caltrain Questions Received and Answers No. 4 # Question Response 1 Will sales tax be applicable to materials ordered for this

More information

Notice of Preparation For Link Union Station (Link US) Project. Joint Environmental Impact Statement and Environmental Impact Report

Notice of Preparation For Link Union Station (Link US) Project. Joint Environmental Impact Statement and Environmental Impact Report Notice of Preparation For Link Union Station (Link US) Project Joint Environmental Impact Statement and Environmental Impact Report Date: May 27, 2016 To: Subject: Project Title: From: All Interested Agencies,

More information

Schedule Guidance Document

Schedule Guidance Document Schedule Guidance Document Version: 1.2 Effective Date: August 20, 2013 Contents 1. Purpose... 1 2. Applicability and Basic Requirements... 2 3. Baseline Schedule... 3 3.1. General... 3 3.2. Schedule Work

More information

Implementation of the NSW Government s response

Implementation of the NSW Government s response Implementation of the NSW Government s response to the Final Report of the Special Commission of Inquiry into the Waterfall Rail Accident Reporting period: April 2014 March 2015 REPORT 35 Implementation

More information

Final Quiet Zone Work Plan

Final Quiet Zone Work Plan Executive Summary Recognizing the impacts of commuter train horns on the communities they serve, RTD will assist and facilitate the local jurisdictions Quiet Zone applications along the Gold Line, Northwest

More information

EXHIBIT A SCOPE OF SERVICES FOR MODAL DEVELOPMENT (MD) SUPPORT - CONTINUING. Financial Project Nos

EXHIBIT A SCOPE OF SERVICES FOR MODAL DEVELOPMENT (MD) SUPPORT - CONTINUING. Financial Project Nos EXHIBIT A SCOPE OF SERVICES FOR MODAL DEVELOPMENT (MD) SUPPORT - CONTINUING Financial Project Nos. 411461-1-12-10 422799-2-12-12 FLORIDA DEPARTMENT OF TRANSPORTATION DISTRICT SEVEN Revised: 07/16/18 07/10/18

More information

Iowa Department of Transportation Intelligent Work Zone Deployments

Iowa Department of Transportation Intelligent Work Zone Deployments Iowa Department of Transportation Intelligent Work Zone Deployments SMARTER WORK ZONES TECHNOLOGY APPLICATIONS CASE STUDY The Every Day Counts Initiative (EDC-3) aims to accelerate the deployment of identified,

More information

DeFoe Corp. 800 South Columbus Ave. Mount Vernon, NY QUALITY ASSURANCE MEASUREMENT ANALYSIS AND IMPROVEMENT

DeFoe Corp. 800 South Columbus Ave. Mount Vernon, NY QUALITY ASSURANCE MEASUREMENT ANALYSIS AND IMPROVEMENT DeFoe Corp. 800 South Columbus Ave. Mount Vernon, NY 10550 QUALITY ASSURANCE TABLE OF CONTENTS SECTION I SECTION 2 SECTION 3 SECTION 4 SECTION 5 QUALITY MANAGEMENT SYSTEM MANAGEMENT RESPONSIBILITY RESOURCE

More information

SUPPLY AND INSTALLATION OF TURBINES AND GENERATORS CONTRACT SCHEDULE 8 QUALITY MANAGEMENT TABLE OF CONTENTS

SUPPLY AND INSTALLATION OF TURBINES AND GENERATORS CONTRACT SCHEDULE 8 QUALITY MANAGEMENT TABLE OF CONTENTS SUPPLY AND INSTALLATION OF TURBINES AND GENERATORS CONTRACT SCHEDULE 8 QUALITY MANAGEMENT TABLE OF CONTENTS 1 INTERPRETATION... 1 1.1 Definitions... 1 2 QUALITY MANAGEMENT SYSTEM... 2 2.1 Quality Management

More information

NAPA SANITATION DISTRICT

NAPA SANITATION DISTRICT NAPA SANITATION DISTRICT PSOMAS COMPANY - TASK ORDER No. 25 HEADWORKS EQUIPMENT REHAB-REPLACE PROJECT (CIP 17726) Date: July 25, 2018 Issued under Professional Services Agreement dated ---------, 2018.

More information

MetroLink Operations 700 South Ewing Street Saint Louis, Missouri

MetroLink Operations 700 South Ewing Street Saint Louis, Missouri Operating Procedure SOP # Date: Page 1 of 10 Classifications: OCC Rail Dispatchers Maintenance of Way - Contractors Other Departments: Real Estate Operation Safety - Risk Management - Engineering & New

More information

Technology Improvement Plan. Department of Information Technology Thomas A. McQuillan CIO February 28, 2015

Technology Improvement Plan. Department of Information Technology Thomas A. McQuillan CIO February 28, 2015 Technology Improvement Plan Department of Information Technology Thomas A. McQuillan CIO February 28, 2015 Technology Improvement Plan The Technology Improvement Plan (TIP) was adopted in April as part

More information

Quality Assurance Program for the Carolina Crossroads Project

Quality Assurance Program for the Carolina Crossroads Project Quality Assurance Program for the Carolina Crossroads Project 08/31/18 (Draft QAP) Contents Scope... 1 1.1 General... 1 1.2 Program Components... 1 1.3 Construction Quality Management Plan... 2 1.4 Owner

More information

CQR-1. CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES Revision Date: 6/8/2015

CQR-1. CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES Revision Date: 6/8/2015 CQR-1 CONTRACTOR QUALITY REQUIREMENTS for CONSTRUCTION SERVICES Revision Date: 6/8/2015 SCOPE This document establishes the minimum quality program requirements for a contractor providing equipment, material,

More information

QRS-108 Supplier Quality Plans

QRS-108 Supplier Quality Plans QRS-108 Issue 02 Page 1/14 QRS-108 Supplier Quality Plans QRS-108 Issue 01 Page 1/13 QRS-108 Supplier Quality Plans Issue Date: Issue: 01 CHANGES LOG Issue Approval Date Main changes 00 April 2015 First

More information

Connected Corridors: I-210 Pilot Integrated Corridor Management System

Connected Corridors: I-210 Pilot Integrated Corridor Management System PARTNERS FOR ADVANCED TRANSPORTATION TECHNOLOGY INSTITUTE OF TRANSPORTATION STUDIES UNIVERSITY OF CALIFORNIA, BERKELEY Connected Corridors: I-210 Pilot Integrated Corridor Management System System Integration

More information