Audit Report Rio Tinto 2012 Network Quality and Reliability of Supply Performance Audit - Operation of Compliance Monitoring Systems

Size: px
Start display at page:

Download "Audit Report Rio Tinto 2012 Network Quality and Reliability of Supply Performance Audit - Operation of Compliance Monitoring Systems"

Transcription

1 ABN Rio Tinto 2012 Network Quality and Reliability of Supply Performance Audit - Operation of Compliance Monitoring Systems Telephone: Fax: projects@qualeng.net Web: Postal Address: PO Box Z5261, St George s Terrace, PERTH WA 6831 Office: Level 2, 231 Adelaide Terrace, Perth, Western Australia, 6000

2 executive summary Under the Electricity Industry (Network Quality and Reliability of Supply) Code 2005 (the Code), Division 3, Section 26, Rio Tinto is required to arrange for an independent audit of the operation of the systems that are in place to monitor its compliance with Part 2 of the Code or an instrument made under Section 14(3). In August 2012 Rio Tinto commissioned to carry out the audit in respect of the operation of such systems to cover the period 1 July 2011 to 30 June The audit was conducted between August and September 2012 and included:! review of actions resulting from previous audit recommendations,! access and review of supporting documentation,! interviews of key personnel,! review of evidence, data, reports and processes demonstrating the operation and performance of the systems. The audit found that five actions arising from the previous audit have been completed; one action, regarding the creation of maps to demonstrate the process work flows is still in progress. Rio Tinto has a system in place to monitor the quality of supply at its five town sites. Rio Tinto work management system creates monthly jobs to initiate the power quality measurements required by the Act. Measurements at one site had not commenced at the start of the audit. Some of the flicker peaks were higher than limits. Harmonics measurements were confined to THD (Total Harmonic Distortion). No complaints were received from customers on power quality. Interruptions are managed using forms and an Outage Database which records all data relevant to the interruption. Alternative supplies are arranged at all sites to mitigate the effect of interruptions.

3 There is a system for managing planned outages and customers' notifications, however at this point there is no documented notification procedure. Extensive preparation and advance notification was noted on planned outages that were due to affect several customers. The number and duration of interruptions are reported. The system identifies customer numbers, however it does not identify the individual customers affected by interruptions at present. Actions are in place to review the customer information system and address the limitations of the present system. Statistics for duration of interruptions have been readjusted to cover the required four years rather than five as reported previously. Overall the audit found that the system had been substantially improved since the last audit. Some actions are still required to further improve the system, however the processes show maturity in implementation. There was awareness of the Code requirements in all interviews and the attitude displayed by staff throughout the audit was very positive and commendable. Based on the scope of the audit defined in section 26 of the Code has found that the system and processes within Rio Tinto are in compliance with the requirements of Part 2 of the Code, "Quality and Reliability Standards".

4 This report is an accurate representation of the findings and opinions of the auditors following the assessment of the client's conformance to nominated Licence conditions. The review is reliant on evidence provided by other parties and is subject to limitations due to the nature of the evidence available to the auditor, the sampling process inherent in the audit process, the limitations of internal controls and the need to use judgement in the assessment of evidence. On this basis shall not be liable for loss or damage to other parties due to their reliance on the information contained in this report or in its supporting documentation. Approvals Representation Name Signature Position Date Auditor: M Zammit Lead Auditor / Engineering Manager, 20/09/2012 Audit Team M Zammit Description Audit Team Project Director and Lead Auditor Issue No Issue Status Date Description Approved 1 19/09/2012 First issue MZ 2 20/09/2012 Final issue MZ AUDITREPORT-63-1-RIO TINTO QUAL&RELIAB-02 Page 4 of

5 TABLE OF CONTENTS 1 OBJECTIVES AND SCOPE OF AUDIT Introduction Audit Objectives Audit Scope Audit Methodology Limitations and Qualifications Acronyms and Abbreviations LICENSEE'S RESPONSE TO PREVIOUS AUDIT RECOMMENDATIONS Background Progress of actions from 2011 Audit KEY FINDINGS System to manage compliance with Part 2, Division 1, Quality Standards (sec. 5 to 8) Quality of Supply - System/Process Evidence of power quality issues and reports System to manage compliance with Part 2, Division 2, Standards for Interruption of Supply Maintain the supply with a minimum number and duration of interruptions (Sec. 9) Reduction of effects of interruptions and provision for alternative supplies for proposed interruptions (Sec. 10) Planned interruptions (Sec. 11) Significant interruptions to small use customers (Sec.12) System to manage compliance with Part 2, Division 3, Standards for the duration of interruption of supply in particular areas (Sec. 13) AUDIT SUMMARY AND RECOMMENDATIONS...21 AUDITREPORT-63-1-RIO TINTO QUAL&RELIAB-02 Page 5 of

6 1 Objectives and Scope of Audit 1.1 INTRODUCTION Rio Tinto supplies electricity services to five town sites in Western Australia, including Dampier, Pannawonica, Wickham, Tom Price and Paraburdoo. Rio Tinto has an exemption from the licensing regime under the Electricity Industry Act 2004, however it still has to comply with the Electricity Industry (Network Quality and Reliability of Supply) Code 2005 (the Code). In accordance with Division 3 "Performance reporting", Section 26 "Annual report on monitoring systems" of the Code, Rio Tinto is required to arrange for an independent audit of the operation of the systems that are in place to monitor its compliance with Part 2 of the Code or an instrument under Section 14(3). In August 2012 Rio Tinto commissioned to carry out the annual audit to cover the period 1 July 2011 to 30 June The audit has been conducted and this report prepared in accordance with the Code. 1.2 AUDIT OBJECTIVES The purpose of the Network Quality and Reliability of Supply (NQRS) audit is to assess and report on the operation of the systems implemented by the licensee to monitor its compliance with Part 2 of the Code or an instrument under section 14(3). 1.3 AUDIT SCOPE Part 2 of the Code includes 4 Divisions: 1. Division 1, "Quality Standards" for compliance with requirements for quality of supply at the point of connection to the customer, in regard to voltage fluctuations and harmonic distortion. 2. Division 2, "Standards for the interruption of supply to individual customers" provides for the maintenance of supply and management of interruptions to customers, both in terms of the duration and number of interruptions. It includes for: 2.1. Provision of supply with the minimum number and duration of interruptions Consideration of providing alternative supply if the interruption is expected to be significant, its effect substantial or if the customer has special health needs that require continuous supply Allowing planned interruptions if the customer is notified within a suitable time and where AUDITREPORT-63-1-RIO TINTO QUAL&RELIAB-02 Page 6 of

7 the duration is under 6 hours, or under 4 hours for temperatures over 30 C or north of the 26th parallel Provides for the distributor to remedy the causes of interruptions or enter into alternative arrangements if the supply has been interrupted more than 12 hours continuously or more than 16 times in the prescribed 12 months and it is considered that the prescribed standard is unlikely to be met for the customer. 3. Division 3, "Standards for the duration of interruptions of supply in particular areas" provides that the average length of interruptions be less than 290 minutes in any area of the State, other than the Perth CBD and urban areas and 160 minutes for urban areas other than the Perth CBD (calculated as average of the yearly averages over 4 years). 4. Division 4, "Variations of obligations under this Part" provides for: 4.1. review and approval by the Minister of alternative requirements and 4.2. agreement between the transmitter/distributor and the customer of extensions and modifications to the standards. The audit was carried out between August and September On Rio Tinto's behalf various representatives participated in the audit, contributed to sourcing the documentation and providing evidence to the audit. Staff interviewed were: Operations & Services:! Noel Michelson, Network Control Superintendent;! Teagan Penny, Compliance advisor; Asset Management: Dampier:! John Taylor, Long Term Planner;! Russell Turner, Superintendent Maintenance Dampier;! Michael Sillick, Supervisor, Dampier;! Russell Balch, Planner & Scheduler; Pannawonica! Andrew Pezzali, Superintendent Maintenance, Pannawonica Robe River Wickham! Darrol Parsonage, Superintendent Maintenance, Wickham;! Simon Millward, Reliability Engineer;! Matt McDermott, Planner & Scheduler; Paraburdoo: AUDITREPORT-63-1-RIO TINTO QUAL&RELIAB-02 Page 7 of

8 ! Ross George, Maintenance Superintendent;! Peter Linde, Maintenance Supervisor; Tom Price:! John Spence, Maintainer Superintendent;! John Brockman, Planner & Scheduler;! Daniel Abetz, Reliability Engineer; Customer Services:! Gary Boylan, Customer Services Superintendent;! Michelle Jeffery, Customer Services Supervisor. Mr Noel Michelson coordinated the audit on behalf of Rio Tinto. The main auditor representatives were Mr M Zammit, Lead Auditor and Mr S Campbell, Reviewer. 1.4 AUDIT METHODOLOGY The audit followed in part the methodology defined in the Authority's Audit Guidelines: Electricity, Gas and Water Licences, August 2010 including:! preparation of an audit plan and risk assessment for internal control,! fieldwork,! reporting. The audit proceeded through a documentation review, meetings, interviews and checks of processes. These were supported by additional queries to clarify aspects of Rio Tinto policies and procedures. 1.5 LIMITATIONS AND QUALIFICATIONS An audit provides a reasonable level of assurance on the effectiveness of control procedures, however there are limitations due to the nature of the evidence available to the auditor, the sampling process inherent in checking the evidence, the limitations of internal controls and the need to use judgement in the assessment of evidence. 1.6 ACRONYMS AND ABBREVIATIONS AUDITREPORT-63-1-RIO TINTO QUAL&RELIAB-02 Page 8 of

9 Abbreviation CAIDI SAIDI SAIFI THD Description CustomerAverage Interruption Duration Index System Average Interruption Duration Index System Average Frequency Duration Index Total Harmonic Distortion AUDITREPORT-63-1-RIO TINTO QUAL&RELIAB-02 Page 9 of

10 2 Licensee's Response to Previous Audit Recommendations 2.1 BACKGROUND The previous quality and reliability of supply audit was completed in October This section reviews Rio Tinto's progress on that audit recommendations as well as Rio Tinto's planned actions to address any outstanding issues. The recommendations arising from the previous report and the confirmation and status of actions determined in this audit have been summarised in the following table. AUDITREPORT-63-1-RIO TINTO QUAL&RELIAB-02 Page 10 of

11 PERFORMANCE AUDIT - OPERATION OF COMPLIANCE REF 63/1 2.2 PROGRESS OF ACTIONS FROM 2011 AUDIT Item No Requirement Findings Process / Procedure / Evidence Status 11/ Induction of new staff on process requirement now man-to-man, simple checklist will be adequate. Training department was going to be established and will formalise induction.! New training department has been established and has started to develop New Starter Packs (Paraburdoo). Action has been implemented. Completed Process effectiveness, create process roadmap to link processes, show interactions (inputs & outputs) and responsibilities:! Action is still in progress. 1. In progress. e.g. outage reporting exists but as unclear responsibilities and lack of controls Responsibilities: Service level agreement between asset owner and service provider not seen. Expected inputs e.g. inspection/ maintenance records/ load changes to influence capital plan. Annual Capital Plan & Maintenance Plan directed by Asset Manager. Documenting process can enhance Outage Management, outages identified by field staff,! Utilities now are responsible for the assets. Recommendation is not applicable any longer.! Second paragraph of the recommendation is not applicable to this Code.! A system is now in place to address outages. It includes: Outage recording in Outage Database 2012 Action closed Action closed. New recommendations are included in the report. AUDITREPORT-63-1-RIO TINTO QUAL&RELIAB-02 Page11 of

12 PERFORMANCE AUDIT - OPERATION OF COMPLIANCE REF 63/1 Item No Requirement Findings Process / Procedure / Evidence Status reports are not accurate or consistent to call centre, need responsibilities, KPIs, manage responsibilities Responsibilities are not clear to staff Stronger supervision, review, sign off, managing staff performance Customer DB (and special needs customers) not always consulted in outage planning. Use a check and sign-off on Outage Registration Form to assign responsibility to outage supervisor Power quality monitoring: need regular PQ monitoring, at least 1/y at one of the extremities of LV network (on rotating basis) /y monitoring measurements for each town distribution network. Recording of all required data in database Identification of responsibilities Notifications to customers Trail of follow-up actions is recorded in the database Closure of actions is recorded in database.! Customer management needs improvement, this finding is noted in the new recommendations.! Power quality monitoring has been implemented, details are noted in the report. Except for one site that has not started the monitoring regime, all other sites have implemented the process. Action closed. new observations are included in the report Need accurate recording of number and duration of significant interruptions to Small Use Customers (SUC). Insufficient details in DB for each individual customer.! The Outage Database 2012 includes records of interruptions. The outage system includes a "Network Control - System Disturbance Data Power" form which records the duration, location and the number of customers affected by outages. Through identification of network location there is identification of customers affected. Action closed. New recommendations on customer information system are included in the report. AUDITREPORT-63-1-RIO TINTO QUAL&RELIAB-02 Page12 of

13 3 Key Findings 3.1 SYSTEM TO MANAGE COMPLIANCE WITH PART 2, DIVISION 1, QUALITY STANDARDS (SEC. 5 TO 8) The Licensee is required to comply with requirements for quality of supply at the point of connection to the customer, both in terms of voltage fluctuations and harmonic distortion and to disconnect the customer where there is a possibility of damage to the customer installation Quality of Supply - System/Process Quality of supply monitoring takes place monthly in accordance with automatically initiated PM01 jobs created by the enterprise work management system in SAP. The test is performed in accordance with procedures Network Routine Quality of Supply Monitoring and Procedure for Quality of Supply Testing which include instructions for the measurement of power quality through harmonic and flicker testing. Currently the testing procedure includes testing of both short term and long term flicker and reporting to the superintendent of regulatory compliance if a "Quality of Supply" test fails. In practice it was found that field staff carried out both measurements however the process is still in the early stages of implementation and at this point no action had been taken to review any flicker spikes. In regard to harmonics measurements, Total Harmonic Distortion (THD) is measured, however there are no measurements of individual harmonics. It is noted that the THD measurements sighted were well below the Code limits. Site Flicker (Pst! 1.0; Plt! 0.8) Dampier Pst 0.2 with peak at 0.7, viewed Plt peak at 0.3 tested between 11/6 and 18/6/2012 Pannawonica Pst < 0.4 with one peak at 1.3 Wickham Plt < 0.4 with peak at 0.7 Pst < 0.2 with single spikes at 1.1 and 1.6 Plt < 0.2 with spikes at 0.5 and 0.7 Harmonics (THD! 8%) Measured on three phases with peak at 1.3% THD Measured on three phases, minimal values. Measured on three phases, minimal values. Customer Complaints Related to PQ No No No AUDITREPORT-63-1-RIO TINTO QUAL&RELIAB-02 Page 13 of

14 Tom Price Paraburdoo Site Flicker (Pst! 1.0; Plt! 0.8) Not doing tests but has the capability (equipment now available) Pst under 0.5 with excursion to 4 (28/3 to 4/4/12) - only on 1 phase [27.9] Harmonics (THD! 8%) Not doing tests but has the capability (equipment now available) Under 1.6% with 1 spike at 2% (8/1 to 15/1/12) Customer Complaints Related to PQ No No Pst under 0.5 with many spikes to 1.8 with 2 peaks at 4 Plt Under 0.8 with 2 excursions to (1/1/12 to 4/1/12) Disconnection if Quality of Supply may Lead to Damage The field crews can disconnect the customer if they determines that the customer installation may be damaged due to supply quality Evidence of power quality issues and reports Review of the systems, processes and practices dealing with quality of supply has shown the following gaps: 2. The program of power quality measurements had not yet started at Tom Price. The equipment is now available and the field staff are aware of procedure and requirements. 3. Flicker average measurements were below limits; however at some sites there were spikes above the limits: 3.1. Pannawonica with peak at 1.3; 3.2. Paraburdoo, excursions to 4; 3.3. Wickham. 4. Harmonics measurements: Total Harmonic Distortion (THD) is measured, however there are no measurements of individual harmonics. There were no "quality" events reported during the audit period and no complaints on power quality. AUDITREPORT-63-1-RIO TINTO QUAL&RELIAB-02 Page 14 of

15 3.2 SYSTEM TO MANAGE COMPLIANCE WITH PART 2, DIVISION 2, STANDARDS FOR INTERRUPTION OF SUPPLY The Licensee has to comply with requirements for the management of interruptions to customers, both in term of the duration and number of interruptions. The requirements are for the Licensee to:! Maintain the supply with the minimum number and duration of interruptions.! Reduce the effects of interruptions; provide alternative supply if the proposed interruption is expected to be significant, its effect substantial or if the customer has special health needs that require continuous supply.! Ensure that where interruptions are planned, where practicable the customer is notified within a suitable time and the duration is kept under 6 hours, or under 4 hours for temperatures over 30 C or north of the 26th parallel.! Remedy the causes of interruptions or enter into alternative arrangements if the supply has been interrupted more than 12 hours continuously or more than 16 times in the prescribed 12 months and it is considered that the prescribed standard is unlikely to be met for the customer Maintain the supply with a minimum number and duration of interruptions (Sec. 9) Rio Tinto has procedures for dealing with outages and maintaining the supply with a minimum number and duration of interruptions. The policy is provided by the "Network Control Guiding Principles" which addresses the directions for managing interruptions and remedial actions. Instruction CRI 1.07 "Outage Management" covers outages for planned, unplanned and emergency outages. A form is in use Network Control - System Disturbance Data/Power, which is used to record the conditions of the interruption:! location and time;! cause of incident;! description of incident;! duration;! number of customers affected. The form is ed to the Operation Centre Network Advisor and the information is entered in the "Outage Database 2012". A separate SMS System generates pre-formatted messages to pre-set lists of stakeholders. The database stores:! all documents linked to the outage, such as: screenshots of system operation at the time of the incident and reports;! identifies whether the Authority needs to be informed; AUDITREPORT-63-1-RIO TINTO QUAL&RELIAB-02 Page 15 of

16 ! when towns and residential customers are affected, the number of customers affected and the duration of the outage. Some of the town sites had flexibility due to design of the network, so that loss of power from one feeder could be mitigated by the availability of a second feeder The number of outages is monitored through reports, if the number increases investigation on reasons for increase are carried out. Forced outages are subject to investigations:! Network Control Outage Report, System Wide 220kV Outage 2 November 2011 reports on an analysis into the events causing a system wide 220kV outage at 2:17am, on Wednesday the 2nd of November. Dampier Site Procedures dealing with outages Procedures monitoring performance Pannawonica Wickham Tom Price Paraburdoo Yes Yes, records in central database, causes recorded, reports available. Selected outages are investigated Reduction of effects of interruptions and provision for alternative supplies for proposed interruptions (Sec. 10) All sites had arrangements to provide alternative supply for extended outages and all staff interviewed on sites were aware of the requirement. Discussion with Customer Services indicated that the customer information system is in need of an overhaul and is under review:! the current system OVSD (Open View Service Desk) records customer calls, the calls entered are classified as complaints, queries, fault or feedback. Sites do not have access to OVSD. If the call is critical s are initiated;! linkage of customers to the network are managed manually;! the UMS (Utilities Management System) stores customer connection and account data;! the enterprise management system stores customer accounts. Overall the system for handling customers and identifying special needs (SN) customers is still informal. It relies on customers advising Rio TInto of their special needs. At this point there is no corporate function managing customers' information. The sites are left with the task of managing SN customers and being responsible for communicating with them in regard to forthcoming outages. AUDITREPORT-63-1-RIO TINTO QUAL&RELIAB-02 Page 16 of

17 Site Alternative Supply Special Needs Customers Dampier Yes No Pannawonica Yes No Wickham Yes; ability to switch to other lines 2 Tom Price Yes Not known Paraburdoo Yes No 5. There is no formal system for managing special needs (SN) customers. Sites are left with the task of managing SN customers and being responsible for advising them of outages Planned interruptions (Sec. 11) There is no documented procedure on handling of notification, however the process is mature and in operation. Notices are dropped by field staff to customers that will be affected by planned outages, the audit sighted forms issued by individual sites. As noted above, outages are entered into the "Outage Database 2012". The database shows the number of customers affected, date and length of interruptions. Reports can be adapted to requirements. Sighted a report for interruptions greater than 12 hours. Site Dampier Pannawonica Wickham Tom Price Paraburdoo Yes Yes Yes Yes Notification 72 hours prior and Duration < 4h Yes; Usually two notifications for planned outages, at 2 weeks and 48 hours. Most sites were found to be aware of the correct requirements for providing notices to customers. Outages of duration longer that 4 hours receive special treatment. If the interruption is due to be longer that 4 hours sites deal directly with customers. Paraburdoo has offered alternative accommodation to customers if required. Eight hour outages at Pannawonica due to the project "Pannawonica Town high voltage conductor replacement" were preceded by presentations to the public advising of the program of outages and of available facilities during the outages. One site notification timing was not as per Code requirements. Paraburdoo site identified that a procedure / flowchart should be available to address notification to AUDITREPORT-63-1-RIO TINTO QUAL&RELIAB-02 Page 17 of

18 customers [27.9]. 6. There is no formal system for notification of outages to customers. In practice sites are responsible for advising customers of outages and were found to provide that function consistently. A procedure (or a simple flowchart) will be of assistance to sites in managing notifications Significant interruptions to small use customers (Sec.12) Requirement: For significant interruption (duration over 12 hours or more than 16 interruptions in the preceding year) where the licensee considers that the standard is unlikely to be met the licensee is required to remedy the causes of interruptions or make alternative arrangements. The Outage Database 2012 provides reports for significant interruptions with duration over 12 hours. The reports sighted showed that there were interruptions greater than 12 hours at four of the five sites and that for each interruption the causes had been identified. Data was available to show the performance over the past years, records sighted showed that the causes of the interruptions had been identified and actions taken to remedy the causes. There were no sites where customers experienced more that 16 interruptions in the year over the audit period. There is not sufficient capability in the present system to clearly identify the individual customers affected by outages. The assessment the annual number of interruptions is made based on local information and knowledge of the network configuration. There are actions in progress to review the customer information system and address the limitations of the present system. Site 2012 > 12 hours 9 Years out of 10 (< 12 hours) 2012 > 16# 9 Years out of 10 (<16#) Causes of Interruption Remedied / Alternative Arrangements Compliance Compliance 2012 Dampier 1 No (2006) No 1 Note 2) Yes Pannawonica 1 No (2008) No Note 2) Yes Wickham 1 No (2011) No Note 2)) Yes Investigation Tom Price 1 No (2009) Note 2 Note 2 Yes AUDITREPORT-63-1-RIO TINTO QUAL&RELIAB-02 Page 18 of

19 Site 2012 > 12 hours 9 Years out of 10 (< 12 hours) 2012 > 16# 9 Years out of 10 (<16#) Causes of Interruption Remedied / Alternative Arrangements Paraburdoo - No (2006, 7, 8, 9, 10) Note 2 Note 2 - Note 1: Of the 12 interruptions in Dampier, four were related to single customers at different addresses, so that no customer was subject to 12 interruptions. Note 2: There were 16 interruptions in Tom Price and 21 in Paraburdoo in the period, however there is no automatic capability in the system to identify if the same customers were subjected to any or all of the outages, traceability is manual. 7. There is not sufficient capability in the present system to clearly identify the actual customers affected by outages. Current actions to review the customer information system and address the limitations of the present system should be continued. 3.3 SYSTEM TO MANAGE COMPLIANCE WITH PART 2, DIVISION 3, STANDARDS FOR THE DURATION OF INTERRUPTION OF SUPPLY IN PARTICULAR AREAS (SEC. 13) The Code provides that the average length of interruptions for the four years up to the current year for areas other than the Perth CBD to be less than 160 minutes in urban areas and less than 290 minutes in any other area of the State. Overall figures for the system comply with requirements. Of the townsites:! Tom Price is high in 2012 due to its earlier connection to an old and problematic 220/33 kv substation, now removed.! Pannawonica figures for the year are within limits, the four year average is high due historically high past interruptions. Site 2012 ( < 290 m) 4 Year Average (Avg over 4 years! 290 min) (For information only) Figures have been calculated over 5 years up to All sites Dampier Pannawonica Wickham AUDITREPORT-63-1-RIO TINTO QUAL&RELIAB-02 Page 19 of

20 Site 2012 ( < 290 m) 4 Year Average (Avg over 4 years! 290 min) Tom Price Paraburdoo Previous reports had calculated the performance over 5 years rather than 4 years. The 2012 Report calculates figures over 4 years, starting from 2008/09. AUDITREPORT-63-1-RIO TINTO QUAL&RELIAB-02 Page 20 of

21 4 Audit Summary and Recommendations Under Section 26 "Annual report on monitoring systems" of the Code, Rio Tinto is required to arrange for an independent audit of the operation of the systems that are in place to monitor its compliance with Part 2 of the Code. or an instrument under Section 14(3). The audit has found that systems are in operation and are in general compliance with the requirements of the Code except as noted below in the summary. Actions resulting from the previous audit have been completed except for one action, regarding the creation of maps to demonstrate the process work flows, which is still in progress.. Table 1 below provides a summary of the findings and recommendations of the report in regard to the system operation. The table rates the various element as satisfactory (!), unsatisfactory ("), or as actions in progress, observations or opportunities for improvement. Throughout the audit it was noted that staff were committed to implementing and improving the systems for managing the quality and reliability of the networks. The response to queries was prompt and staff attitude was commendable. AUDITREPORT-63-1-RIO TINTO QUAL&RELIAB-02 Page 21 of

22 PERFORMANCE AUDIT - OPERATION OF COMPLIANCE REF 63/1 Table 1: Systems Compliance Code Division, Section Div 1, Sec. 5-7 Code Requirement General system Quality and Reliability standards: voltage fluctuations, harmonics. Evidence of System Evidence of Process!! Findings / Comments Recommended Corrective Actions / Measurements are systematic, generated from SAP system and occur monthly. There were no complaints from customers on quality of supply. The program of power quality measurements had not yet started at Tom Price. The equipment is now available and the field staff are aware of procedure and requirements. Some flicker readings higher than requirement. No system action taken to check high readings. THD is measured. Opportunities for Improvement (OFI) 1. Continue with the creation of process maps to link processes, show interactions (inputs & outputs) and responsibilities. 2. Improve scaling of traces of power quality measurement. [OFI] 3. Start and monitor program of power quality measurements at Tom Price. 4. Implement recognition and review of flicker measurements in excess of Code limits. 5. Assess measurements of individual harmonics. No measurements carried out on each harmonic. Div 1, Sec. 8 Duty to disconnect if damage may result due to power quality.!! Responsibility to disconnect customers remains with the service crew. Div 2, Sec. 9 Maintain the supply with a minimum number and duration of interruptions.!! A response system is in place to attend to faults and interruptions and to address loss of supply. Complies. AUDITREPORT-63-1-RIO TINTO QUAL&RELIAB-02 Page22 of

23 PERFORMANCE AUDIT - OPERATION OF COMPLIANCE REF 63/1 Code Division, Section Div 2, Sec. 10 Div 2, Sec. 11 Div 2, Sec. 12 Div 3, Sec. 13 Part 4, Div. 3, Sec. 27 Code Requirement Reduction of effects of interruptions or provision for alternative supplies for proposed interruptions. Planned interruptions. Significant interruptions to small use customers (> 16 times or > 12 Hours). Standards for the duration of interruption of supply in particular areas (30, 160, 290 min) Publication of information about performance. Evidence of System Evidence of Process!!!!!!!!!! Findings / Comments Recommended Corrective Actions / There is no formal system for managing special needs (SN) customers. Sites are left with the task of managing SN customers and being responsible for advising them of outages. A review of Customer Service systems is in place to address limitations of present system. There is no formal system for notification of outages to customers. In practice sites are responsible for advising customers of outages and were found to provide that function consistently. A procedure (or a simple flowchart) will be of assistance to sites in managing notifications. There were interruptions greater than 12 hours at four of the five sites. For each interruption the causes had been identified and rectified. Sites showed that extended planned outages had been preceded by notifications and the special arrangements had been put in place. There were no sites where customers experienced more that 16 interruptions in the year over the audit period Previous report covered 5 years rather than 4. New report statistic will be improved by removing high impact events from 2008/08. Complies with direction from Authority. Opportunities for Improvement (OFI) 6. Continue with the review and development of improved Customer Service systems to enable better traceability of customers within the network, clearly identify the actual customers affected by outages and identification of customers with special health needs. 7. Create a procedure (or a simple flowchart) to guide sites in managing notifications. Recommendation included in 6. above. AUDITREPORT-63-1-RIO TINTO QUAL&RELIAB-02 Page23 of

Qualeng. Audit Report Horizon Power 2017 Network Quality and Reliability of Supply Performance Audit - Operation of Compliance Monitoring Systems

Qualeng. Audit Report Horizon Power 2017 Network Quality and Reliability of Supply Performance Audit - Operation of Compliance Monitoring Systems ABN 20 009 454 111 Horizon Power 2017 Network Quality and Reliability of Supply Performance Audit - Operation of Compliance Monitoring Systems August 2017 Level 2, 231 Adelaide Terrace, Perth, Western

More information

Bluewaters Power 1 Pty Ltd

Bluewaters Power 1 Pty Ltd Bluewaters Power 1 Pty Ltd Electricity Generation Licence (EGL 4) 2014 Performance Audit (Independent Assurance) Report June 2014 Deloitte Touche Tohmatsu ABN 74 490 121 060 Woodside Plaza Level 14 240

More information

Regulatory Audit Of Compliance Reporting For The Ord Hydro Transmission Network

Regulatory Audit Of Compliance Reporting For The Ord Hydro Transmission Network Regulatory Audit Of Compliance Reporting For The Ord Hydro Transmission Network Final 26 March 2007 Regulatory Audit Of Compliance Reporting For The Ord Hydro Transmission Network Final 26 March 2007 Sinclair

More information

Distribution Information Exchange Code

Distribution Information Exchange Code Distribution Information Exchange Code Version 5.1 Approved September 2007 Comments to this document can be forwarded to: The RSA Grid Code Secretariat Attention: Mr. Bernard Magoro Eskom, Transmission

More information

Technical Requirements for Distributed Generation Connection

Technical Requirements for Distributed Generation Connection Technical Requirements for Distributed Generation Connection Distributed Generation Connection Requirements SECTION 1: INTRODUCTION 1.1 General Purpose This document defines the requirements for connecting

More information

Standard connections for water, sewerage and electricity supply

Standard connections for water, sewerage and electricity supply Pilbara electricity and water services Standard connections for water, sewerage and electricity supply Introduction Rio Tinto is committed to providing safe, reliable electricity, water and sewerage services,

More information

CHECKLIST FOR PART 145 APPROVAL

CHECKLIST FOR PART 145 APPROVAL Section/division AIRWORTHINESS: AIRCRAFT MAINTENANCE ORGANISATION Form Number: CA 145-03 CHECKLIST FOR PART 145 APPROVAL AMO Number Name of organization Physical address Postal address Postal code Telephone

More information

2017 Archaeology Audit Program Procedure Manual. April 2017

2017 Archaeology Audit Program Procedure Manual. April 2017 2017 Archaeology Audit Program Procedure Manual April 2017 Table of Contents Contents Table of Contents... 2 1.0 Introduction and Scope... 3 2.0 Audit Objectives... 3 3.0 Audit Procedures... 4 3.1 Audit

More information

Security Operations. BS EN ISO 9001: 2008 Issue 1.2: 21/10/2016. Quality Manual. Managing Director. Controlled / Uncontrolled when printed

Security Operations. BS EN ISO 9001: 2008 Issue 1.2: 21/10/2016. Quality Manual. Managing Director. Controlled / Uncontrolled when printed of Security Operations BS EN ISO 9001: 2008 : 21/10/2016 Manual No. 1 Issued to Managing Director Authorised By Date Issued 21/10/2016 Controlled / Uncontrolled when printed SECTION: 0 Index Page 2 Note

More information

A Firm s System of Quality Control

A Firm s System of Quality Control A Firm s System of Quality Control 2759 QC Section 10 A Firm s System of Quality Control (Supersedes SQCS No. 7.) Source: SQCS No. 8; SAS No. 122; SAS No. 128. Effective date: Applicable to a CPA firm's

More information

OPTUS SUPPLIER WORK HEALTH & SAFETY POLICY

OPTUS SUPPLIER WORK HEALTH & SAFETY POLICY OPTUS SUPPLIER WORK HEALTH & SAFETY POLICY 1. Introduction 1.1 SCOPE & PURPOSE This policy (which includes this document and the work health and safety standards, policies, procedures and safety control

More information

AGREEMENT FOR CONNECTION TO [EASTERN /LONDON / SOUTH EASTERN] POWER NETWORKS PLC S DISTRIBUTION SYSTEM

AGREEMENT FOR CONNECTION TO [EASTERN /LONDON / SOUTH EASTERN] POWER NETWORKS PLC S DISTRIBUTION SYSTEM AGREEMENT FOR CONNECTION TO [EASTERN /LONDON / SOUTH EASTERN] POWER NETWORKS PLC S DISTRIBUTION SYSTEM BETWEEN AND (1) [Eastern / London / South Eastern] Power Networks plc Company Number [02366906 / 03929195

More information

Health and Safety Management Standards

Health and Safety Management Standards Management Standards Curtin University Sept 2011 PAGE LEFT INTENTIONALLY BLANK Management Standards Page 2 of 15 CONTENTS 1. Introduction... 4 1.1 Hierarchy of Documents... 4 2. Management System Model...

More information

Internal Audit Quality Analysis Evaluation against the Standards International Standards for the Professional Practice of Internal Auditing (2017)

Internal Audit Quality Analysis Evaluation against the Standards International Standards for the Professional Practice of Internal Auditing (2017) Internal Audit Quality Analysis Evaluation against the Standards International Standards for the Professional Practice of Internal Auditing (2017) Assessor 1: Assessor 2: Date: Date: Legend: Generally

More information

Electricity Supply Agreement

Electricity Supply Agreement Electricity Supply Agreement 1. General 1.1 Mazoon Electricity Company SAOC (the Supplier) shall on or from the Start Date, subject to the satisfactory completion of a Supply Application Form, provide

More information

SCHEDULE SS STANDBY SERVICE

SCHEDULE SS STANDBY SERVICE SCHEDULE SS STANDBY SERVICE SHEET NO. 69 A. APPLICABILITY: Applicable to customers with alternate regular source(s) of energy other than electricity from the Company when such sources are connected to

More information

Social Sector Accreditation Standards Level 4

Social Sector Accreditation Standards Level 4 Social Sector Accreditation Standards Level 4 Introduction These standards for accreditation are produced by the New Zealand Government for the accreditation of providers funded to deliver social services.

More information

Management of Fatigue in Tram Operations Limited - TOL (IA )

Management of Fatigue in Tram Operations Limited - TOL (IA ) INTERNAL AUDIT REPORT HSE & Technical Management of Fatigue in Tram Operations Limited - TOL (IA 17 780) Rory O Neill, Director London Trams, Transport for London 15 September 2017 CONTENTS INTRODUCTION

More information

Rail Safety Management Procedure General Engineering and Operational Systems - Asset Management of Rolling Stock

Rail Safety Management Procedure General Engineering and Operational Systems - Asset Management of Rolling Stock 1/16 Management of Rolling Stock Revision Date Comments 1 January 2011 Procedure developed to support SMS and legislative requirements. 2 February 2012 Reviewed with RISSB Standards and change of titles

More information

LC 16 SITE PLANS, DESIGNS AND SPECIFICATIONS

LC 16 SITE PLANS, DESIGNS AND SPECIFICATIONS Title of document ONR GUIDE LC 16 SITE PLANS, DESIGNS AND SPECIFICATIONS Document Type: Unique Document ID and Revision No: Nuclear Safety Technical Inspection Guide Date Issued: September 2015 Review

More information

Work Health and Safety Management Systems and Auditing Guidelines

Work Health and Safety Management Systems and Auditing Guidelines Work Health and Safety Management Systems and Auditing Guidelines 5th edition, September 2013 (Updated May 2014) Work Health and Safety Management Systems and Auditing Guidelines These Guidelines are a

More information

Facilities Planning and Construction (FP&C)

Facilities Planning and Construction (FP&C) Appendix 8.4a Facilities Planning and Construction (FP&C) UAA FP&C Quality Assessment Checklist (A) Project: PM: Project ID: Updated:

More information

Intermaritime Certification Services (ICS) QUALITY MANAGEMENT SYSTEM INSTRUCTIVE FOR ISM-CODE

Intermaritime Certification Services (ICS) QUALITY MANAGEMENT SYSTEM INSTRUCTIVE FOR ISM-CODE 1.0 TITLE: 2.0 OBJECTIVES This Instructive reflect, as applicable, the IMO Resolution A.1022 (26) "Guidelines on the Implementation of the ISM-Code by Administrations" and the IMO Resolution A.741 (18)

More information

3.2 Direction, Management, Implementation and Review

3.2 Direction, Management, Implementation and Review STF Safety Management Standards 3 Safety Management Standards The Standards in this section identify the minimum health and safety provision that STF members shall implement. It is recommended that appropriate

More information

ISO 9001:2015 ISO 14001:2015 OHSAS

ISO 9001:2015 ISO 14001:2015 OHSAS JSM Group Management System Manual January 2017 ISO 9001:2015 ISO 14001:2015 OHSAS 18001:2004 National Electricity Registration Scheme (NERS) Fleet Operators Recognition Scheme (FORS) Issue & Amendment

More information

AICPA Peer Review Program Compliance: Responding to Latest Developments

AICPA Peer Review Program Compliance: Responding to Latest Developments AICPA Peer Review Program Compliance: Responding to Latest Developments TUESDAY, JUNE 24, 2014 1:00-2:50 pm Eastern IMPORTANT INFORMATION This program is approved for 2 CPE credit hours. To earn credit

More information

YOUR CERTIFICATION PROCESS EXPLAINED

YOUR CERTIFICATION PROCESS EXPLAINED ISO 22000 FOOD SAFETY MANAGEMENT SYSTEMS FSSC 22000 FOOD SAFETY SYSTEM CERTIFICATION This document outlines the audit process for the above referenced standard. It outlines the stages to audit and gives

More information

SUSTAINABLE GREEN ELECTRICITY FOR RURAL DEVELOPEMNT IN TANZANIA

SUSTAINABLE GREEN ELECTRICITY FOR RURAL DEVELOPEMNT IN TANZANIA RIFT VALLEY ENERGY CUSTOMER SERVICE CHARTER Page 1 of 7 RIFT VALLEY ENERGY TANZANIA 1. SERVICE DELIVERY STANDARDS Rift Valley Energy (RVE) forms the energy division of Rift Valley Corporation (RVC), and

More information

P&O MARITIME Limassol, Cyprus Position Description

P&O MARITIME Limassol, Cyprus Position Description POSITION TITLE Marine Manager DIVISION P&O Maritime Limassol REPORTS TO Reports to the Board with dotted lines reporting to Head of Group Marine P&OM Direct Reports 5+ PRIMARY LOCATION Limassol Port -

More information

Guidance Document. RMP Template for Farm Dairies Export Eligible Milk. 11 December 2015

Guidance Document. RMP Template for Farm Dairies Export Eligible Milk. 11 December 2015 Guidance Document RMP Template for Farm Dairies Export Eligible Milk 11 December 2015 A guidance document issued by the Ministry for Primary Industries Title Guidance Document: RMP Template for Farm Dairies

More information

WHS Management Plans

WHS Management Plans WHS Management Plans Disclaimer This Guide provides general information about the obligations of persons conducting a business or undertaking and/or persons in control of premises and workers under the

More information

Tariffs January 1, 2017

Tariffs January 1, 2017 Tariffs January 1, 2017 Nova Scotia Power Inc. Tariffs & Regulations Approved by the Nova Scotia Utility and Review Board pursuant to The Public Utilities Act, R.S.N.S., 189,c.380 as amended Tariffs For

More information

POWER QUALITY IN REGULATION OF DISTRIBUTION COMPANIES A FINNISH CASE

POWER QUALITY IN REGULATION OF DISTRIBUTION COMPANIES A FINNISH CASE POWER QUALITY IN REGULATION OF DISTRIBUTION COMPANIES A FINNISH CASE Markku KINNUNEN Energy Market Authority Finland markku.kinnunen@emvi.fi Ritva HIRVONEN Energy Market Authority - Finland ritva.hirvonen@emvi.fi

More information

WUNGENING ABORIGINAL CORPORATION

WUNGENING ABORIGINAL CORPORATION WUNGENING ABORIGINAL CORPORATION Employment Information Pack Date: August 2017 Version: 3 Page 1 of 2 Congratulations on taking the first step towards working for Wungening Aboriginal Corporation (Wungening),

More information

WHO Prequalification of In Vitro Diagnostics Programme

WHO Prequalification of In Vitro Diagnostics Programme P r e q u a l i f i c a t i o n T e a m - D i a g n o s t i c s Information for Manufacturers on the Manufacturing Site(s) Inspection (Assessment of the Quality Management System) WHO Prequalification

More information

Audit report VET Quality Framework

Audit report VET Quality Framework Audit report VET Quality Framework Standards for Registered Training Organisations 2015 ORGANISATION DETAILS Organisation s legal name: Train Assess Australia Pty Ltd Trading name/s: Train Assess Australia

More information

BRC Storage and Distribution Quality and Safety Management System Implementation Workbook

BRC Storage and Distribution Quality and Safety Management System Implementation Workbook We have written this workbook to assist in the implementation of your BRC quality & safety management system. The workbook is divided into 8 steps that are designed to assist you in implementing your quality

More information

Bowmer. & Kirkland. Kirkland. & Accommodation. Health & Safety Policy.

Bowmer. & Kirkland. Kirkland. & Accommodation. Health & Safety Policy. Bowmer Kirkland & Kirkland & Accommodation Health & Safety Policy December 2013 www.bandk.co.uk Index Policy Statement Page 3 Interaction of Health and Safety Responsibilities Page 5 Organisation Page

More information

Critical 0 Major 0 Minor 0. Certification Body name and address

Critical 0 Major 0 Minor 0. Certification Body name and address Audit Report Global Standard for Agents and Brokers Issue 1: January 2014 1.Audit Summary Company name BRC Site Code BRC Site code 2.Scope Operation Services Scope of audit Product categories Select Operation

More information

SAI Global Full Service Team

SAI Global Full Service Team General information regarding elements of the certification process is described below. A degree of flexibility and options in the certification process are available so please feel free to contact us

More information

Service Suppliers Engaged in Condition Monitoring of Machinery Onboard Ships and Mobile Offshore Units

Service Suppliers Engaged in Condition Monitoring of Machinery Onboard Ships and Mobile Offshore Units pproval of rvc upplrsno. 2.9 STANDARD FOR CERTIFICATION Approval Programmes Approval of Service Suppliers No. 416 Service Suppliers Engaged in Condition Monitoring of Machinery Onboard Ships and Mobile

More information

ARD OPERATIONAL PROCEDURE 6.- Audit Reporting

ARD OPERATIONAL PROCEDURE 6.- Audit Reporting 1. Purpose The purpose of this procedure is to provide guidance and authority to internal auditors in the reporting of their work and to ensure consistency and completeness of the reporting function. 2.

More information

Quality and Environmental Business Process Manual

Quality and Environmental Business Process Manual PMC SOIL SOLUTIONS 2 Fountain Court Victoria Square St Albans Hertfordshire AL1 3TF T: 01727 822500 F: 01727 821600 E: headoffice@pmcsoilsolutions.com W: www.pmcsoilsolutions.com Quality and Environmental

More information

Facility Interconnection Requirements

Facility Interconnection Requirements Facility Interconnection Effective 1/1/2016 1. Purpose Facility Interconnection Facility Interconnection (FAC-001-2) To avoid adverse impacts on the reliability of the Bulk Electric System (BES), RPU documents

More information

Railway Interface Planning Scheme Rules (RIPS Rules)

Railway Interface Planning Scheme Rules (RIPS Rules) Contents 1. Purpose.. 1 2. Scope... 2 3. Scheme Rules.... 3 4. Roles and Responsibilities... 4 5. Management System Requirements... 7 6. Investigating Breaches of the Railway Interface Planning Scheme

More information

EQUASS 2018 ASSURANCE PROCEDURES

EQUASS 2018 ASSURANCE PROCEDURES EQUASS 2018 ASSURANCE PROCEDURES Table of Contents Introduction... 2 1. Application and self-assessment... 5 2. Selection of the auditor... 6 3. The audit... 7 4. Certification... 10 Progress reports...

More information

SECTION QUALITY REQUIREMENTS

SECTION QUALITY REQUIREMENTS SECTION 014000 - PART 1 - GENERAL 1.1 SUMMARY A. Defines SRP requirements for Contractor Quality Control and Owner Quality Assurance. As an Electric and Water Utility, SRP has many critical facilities.

More information

Revision. Quality Manual. Multilayer Prototypes. Compliant to ISO / AS9100 Rev C

Revision. Quality Manual. Multilayer Prototypes. Compliant to ISO / AS9100 Rev C 1 of 29 Quality Manual Multilayer Prototypes Compliant to ISO 9001-2008 / AS9100 Rev C This Quality Manual sets forth the quality system policies and Defines compliance with the ISO 9001-2008 SAE AS 9100

More information

Productivity improvements in a changing world

Productivity improvements in a changing world Productivity improvements in a changing world Michael Gollschewski Managing director Pilbara Mines 13 July 2015 Cautionary statement General This presentation has been prepared by Rio Tinto plc and Rio

More information

INTERNATIONAL STANDARD

INTERNATIONAL STANDARD INTERNATIONAL STANDARD ISO 19011 Second edition 2011-11-15 Guidelines for auditing management systems Lignes directrices pour l audit des systèmes de management Reference number ISO 19011:2011(E) ISO 2011

More information

HSE statement on radiation protection advisers

HSE statement on radiation protection advisers HSE statement on radiation protection advisers The requirements of this Statement came into effect on 31 March 2007 Purpose Introduction Criteria of core competence Assessing bodies Suitable RPA's Annex

More information

Review of agreed-upon procedures engagements questionnaire

Review of agreed-upon procedures engagements questionnaire Review of agreed-upon procedures engagements questionnaire Review code Reviewer Review date Introduction Standards on Related Services (ASRSs) detail the responsibilities of an assurance practitioner,

More information

Area Services Manager Lifeskills (North Metropolitan Area - Balcatta)

Area Services Manager Lifeskills (North Metropolitan Area - Balcatta) Area Services Manager Lifeskills (North Metropolitan Area - Balcatta) Full time Permanent Thank you for your interest in this position. A current position description and selection criteria follows. If

More information

NUCLEAR SAFETY REQUIREMENTS BSR

NUCLEAR SAFETY REQUIREMENTS BSR NUCLEAR SAFETY REQUIREMENTS BSR-1.8.2-2015 APPROVED BY Order No. 22.3-99 of The Head of State Nuclear Power Safety Inspectorate, of 7 October 2011 (as amended by Order No. 22.3-57 of the Head of State

More information

Hazardous. Scheme. the power behind your business

Hazardous. Scheme. the power behind your business Hazardous Areas Scheme YOUR GUIDE TO REGISTRATION the power behind your business GUIDE TO REGISTRATION REQUIREMENTS Electrical work in potentially explosive atmospheres (hazardous areas) is not included

More information

FSC36 SAFE FEED/SAFE FOOD GUIDANCE DOCUMENT

FSC36 SAFE FEED/SAFE FOOD GUIDANCE DOCUMENT FSC36 SAFE FEED/SAFE FOOD GUIDANCE DOCUMENT FSC36 Safe Feed/Safe Food (www.safefeedsafefood.org) is a facility certification program for the American Feed Industry Association (www.afia.org) Version 7.0

More information

Title: How to assess a PQS testing laboratory Table of Content

Title: How to assess a PQS testing laboratory Table of Content Version: 01.05 Effective date: 08/07/2004 Page: 2 of 22 Table of Content 1.0 Purpose... 3 2.0 Scope... 3 3.0 Responsibility... 3 4.0 Documentation required... 4 5.0 Procedure... 4 5.1 Assessment Register...

More information

Professional Services Contract (PSC) for Consultants Selection Process for NHS Clients

Professional Services Contract (PSC) for Consultants Selection Process for NHS Clients Professional Services Contract (PSC) for Consultants Selection Process for NHS Clients December 2008 Contents Page Contents...2 Introduction...3 The Process Flowchart...4 Project Registration: Step 1...5

More information

Procedures: QP 4 through QP 8, QP 16, QP 17, and QP 19

Procedures: QP 4 through QP 8, QP 16, QP 17, and QP 19 SRI Quality System Registrar Procedures: QP 4 through QP 8, QP 16, QP 17, and QP 19 Booklet Version 171122 Revision Date QP 4.0 Pre-Audit Registration Procedures 15 11/07/15 QP 5.0 On-Site Audit Procedure

More information

Audit report VET Quality Framework

Audit report VET Quality Framework Audit report VET Quality Framework Standards for Registered Training Organisations 2015 ORGANISATION DETAILS Organisation s legal name: Boomerang Training Solutions Pty Ltd Trading name/s: Boomerang Training

More information

LEARNING OBJECTIVES FOR SECTION 4. Inspection and Enforcement by the Regulatory Body

LEARNING OBJECTIVES FOR SECTION 4. Inspection and Enforcement by the Regulatory Body LEARNING OBJECTIVES FOR SECTION 4 Inspection and Enforcement by the Regulatory Body After following the lectures, studying the printed material, performing the exercises, studying the given IAEA references

More information

The Idaho Power Company

The Idaho Power Company Preventing Electrical Pollution Working with Customers to Control Electrical Pollution Idaho Power s Approach By Jon D Roholt For the IEEE PES T&D Conference & Exposition Chicago IL, April 23, 2008 The

More information

Statements of Membership Obligations 1 7

Statements of Membership Obligations 1 7 IFAC Board Statements of Membership Obligations Issued April 2004 Statements of Membership Obligations 1 7 The mission of the International Federation of Accountants (IFAC) is to serve the public interest,

More information

DRIFFIELD GOLF CLUB - ADMINISTRATIVE ASSISTANT

DRIFFIELD GOLF CLUB - ADMINISTRATIVE ASSISTANT DRIFFIELD GOLF CLUB - ADMINISTRATIVE ASSISTANT Driffield Golf Club (DGC) requires an Administrative Assistant to support the Club and its Management Committee. The post will be part time, working on Tuesday,

More information

Statement of Methodology and Charges for Connection to the Electricity Distribution Systems of: The Electricity Network Company Limited.

Statement of Methodology and Charges for Connection to the Electricity Distribution Systems of: The Electricity Network Company Limited. Statement of Methodology and Charges for Connection to the Electricity Distribution Systems of: The Electricity Network Company Limited and Independent Power Networks Limited. Important Note This document

More information

CHOPTANK ELECTRIC COOPERATIVE, INC. P.S.C. Md. No. 3 Fifth Revised Page No. 59 COGENERATION AND SMALL POWER PRODUCTION RATE SCHEDULE X

CHOPTANK ELECTRIC COOPERATIVE, INC. P.S.C. Md. No. 3 Fifth Revised Page No. 59 COGENERATION AND SMALL POWER PRODUCTION RATE SCHEDULE X Fifth Revised Page No. 59 908 COGENERATION AND SMALL POWER PRODUCTION RATE SCHEDULE X A. AVAILABILITY Available to members of the Cooperative for purchases of electricity by the Cooperative from qualified

More information

Standard TPL Transmission System Planning Performance Requirements

Standard TPL Transmission System Planning Performance Requirements A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon

More information

safe reliable affordable GENERATOR COMPLIANCE MONITORING PROGRAM REQUIREMENTS 1 21 September 2015 TITLE: PREPARED BY: SYSTEM ANALYSIS & SOLUTIONS

safe reliable affordable GENERATOR COMPLIANCE MONITORING PROGRAM REQUIREMENTS 1 21 September 2015 TITLE: PREPARED BY: SYSTEM ANALYSIS & SOLUTIONS TITLE: GENERATOR COMPLIANCE MONITORING PROGRAM REQUIREMENTS PREPARED BY: SYSTEM ANALYSIS & SOLUTIONS DOCUMENT STATUS: FINAL REVISION: DATE: 1 21 September 2015 2015 Electricity Networks Corporation trading

More information

STATEMENT OF METHODOLOGY AND CHARGES FOR CONNECTION TO SP DISTRIBUTION LTD AND SP MANWEB PLC S ELECTRICITY DISTRIBUTION SYSTEMS

STATEMENT OF METHODOLOGY AND CHARGES FOR CONNECTION TO SP DISTRIBUTION LTD AND SP MANWEB PLC S ELECTRICITY DISTRIBUTION SYSTEMS STATEMENT OF METHODOLOGY AND CHARGES FOR CONNECTION TO SP DISTRIBUTION LTD AND SP MANWEB PLC S ELECTRICITY DISTRIBUTION SYSTEMS Contents Important Note... 5 Section 1 General Information... 6 Competition

More information

9 ENVIRONMENTAL MANAGEMENT PLAN 9.1 OVERVIEW AND SCOPE Introduction

9 ENVIRONMENTAL MANAGEMENT PLAN 9.1 OVERVIEW AND SCOPE Introduction 9 ENVIRONMENTAL MANAGEMENT PLAN 9.1 OVERVIEW AND SCOPE 9.1.1 Introduction This chapter is the provisional Environmental Management Plan (EMP) for the Jubilee Phase 1 Development project. The elements of

More information

Customer outcome 2. Warn me, inform me. What our customers say. Our five-year approach. What we do now

Customer outcome 2. Warn me, inform me. What our customers say. Our five-year approach. What we do now Page 24 Customer outcome 2 Customer outcome 2 Warn me, inform me Keeping customers informed and in control Rectifying interruptions to minimise disruption Reducing disruption in peak times Understanding

More information

Achieve. Performance objectives

Achieve. Performance objectives Achieve Performance objectives Performance objectives are benchmarks of effective performance that describe the types of work activities students and affiliates will be involved in as trainee accountants.

More information

Electrical Safety Management Plan (ESMP)

Electrical Safety Management Plan (ESMP) Electrical Safety Management Plan (ESMP) CONTENTS 1 INTRODUCTION 4 1.1 Purpose 4 1.2 Background 4 2 OBJECTIVES OF THE ESMP 2.1 Electrical Safety Policy 2.2 Electrical Safety Goals 2.3 Objectives 5 5 5

More information

Mobile Device Management (MDM)

Mobile Device Management (MDM) Mobile Device Management (MDM) Service Level Agreement www.eisit.uk info@eisit.uk Tel: 0300 065 8800 Fax: 01622 663591 EIS The Shepway Centre, Oxford Road, Maidstone, Kent, ME15 8AW Contents 1. Service

More information

The Advantage of Implementing a Safety Management System. Integrating Occupational Safety Management into Other Management Functions

The Advantage of Implementing a Safety Management System. Integrating Occupational Safety Management into Other Management Functions Contents Introduction, Objectives The Advantage of Implementing a Safety Management System Occupational Safety Charter Integrating Occupational Safety Management into Other Management Functions Establishing

More information

Loch Lomond & The Trossachs National Park Authority. Annual internal audit report Year ended 31 March 2015

Loch Lomond & The Trossachs National Park Authority. Annual internal audit report Year ended 31 March 2015 Loch Lomond & The Trossachs National Park Authority Annual internal audit report Year ended 31 March 2015 Contents This report is for: Information Chief executive Audit committee Jaki Carnegie, director

More information

Internal Audit Report. IT Change Management Review March 2016

Internal Audit Report. IT Change Management Review March 2016 Internal Audit Report IT Change Management Review March 2016 To: Chief Operating Officer Head of Information Management IT Director (CSG) Programme Director (CSG) Copied to: Enterprise Architect (CSG)

More information

PACIFIC MARINE SERVICES

PACIFIC MARINE SERVICES APPR No : PMS/D.A.RSP/ Date : Pages : One (7) /UAE Data Sheet for Approval of Firms Issued within the scope of the Pacific Marine Services General Conditions - Radio Service Supplier for Inspection Services

More information

Quality Manual DRAFT. Quality Management Plan Version A1 Date: <22/01/11> Page 1 of 17

Quality Manual DRAFT. Quality Management Plan Version A1 Date: <22/01/11> Page 1 of 17 Quality Manual DRAFT Page 1 of 17 Document Acceptance and Release Notice This is Revision A1 of the East Coast Designer Builders Quality Manual. The Manual is a managed document. For identification of

More information

OPAC EN Operating Procedure for the Attestation of Conformity of Structural Bearings in compliance with Annex ZA of EN 1337/3/4/5/6/7

OPAC EN Operating Procedure for the Attestation of Conformity of Structural Bearings in compliance with Annex ZA of EN 1337/3/4/5/6/7 OPAC EN1337-00 Operating Procedure for the Attestation of Conformity to EN1337 Revision 00 Approved by BT3 on 20050525, by Board of directors on 20050610 Operating Procedure for the Attestation of Conformity

More information

Building up an IT Service Management System through the ISO Certification

Building up an IT Service Management System through the ISO Certification International Journal of Knowledge Content Development & Technology Vol.2, No.2, 31-44 (December, 2012) 31 Building up an IT Service Management System through the ISO 20000 Certification Jung-Hoon Park*,

More information

Audit report VET Quality Framework

Audit report VET Quality Framework The QCAA uses an exceptions-based model of reporting. This means that the QCAA will only record a comprehensive description of evidence gathered and compliance findings if noncompliance is identified at

More information

(Adopted by the Board of Directors on 13 May 2009 and amended on 24 September 2009, 13 September 2012 and 27 November 2013)

(Adopted by the Board of Directors on 13 May 2009 and amended on 24 September 2009, 13 September 2012 and 27 November 2013) Thomas Cook Group plc THE AUDIT COMMITTEE TERMS OF REFERENCE (Adopted by the Board of Directors on 13 May 2009 and amended on 24 September 2009, 13 September 2012 and 27 November 2013) Chairman and members

More information

Desk Audit of. Based on Federal Transit Administration (FTA) Quality Assurance and Quality Control Guidelines FTA-IT

Desk Audit of. Based on Federal Transit Administration (FTA) Quality Assurance and Quality Control Guidelines FTA-IT Desk Audit of Based on Federal Transit Administration (FTA) Quality Assurance and Quality Control Guidelines FTA-IT-90-5001-02.1 Reviewed by: Element Requirements Applicable 1. Is a quality policy defined

More information

Irish Water Business Customer Codes of Practice

Irish Water Business Customer Codes of Practice Irish Water Business Customer Codes of Practice 1 P a g e 02 October 2017 Introduction As Ireland s national water utility, Irish Water aims to meet our customers expectations through the provision of

More information

Seven-Year Electric Service Reliability Statistics Summary

Seven-Year Electric Service Reliability Statistics Summary Oregon Investor-owned Utilities Seven-Year Electric Service Reliability Statistics Summary 2010-2016 June 2017 Report available at http://www.puc.state.or.us (Click on Safety, then click on Reports ) Information

More information

Work Health and Safety

Work Health and Safety Policy Health and Safety Endorsed: 23 August 2016 Brief description The GPC Health and Safety Policy and its supporting standards and procedures provide a framework to protect the health and safety of

More information

Quality Assurance Manual

Quality Assurance Manual Quality Assurance Manual Current Electrical is committed to leading the market in satisfying customer needs by providing versatile and innovative electrical and control solutions We take pride in the ability

More information

B H P B I L L I T O N W O R S L E Y A L U M I N A P T Y L T D G E N E R A T I O N L I C E N C E E G L 1 2

B H P B I L L I T O N W O R S L E Y A L U M I N A P T Y L T D G E N E R A T I O N L I C E N C E E G L 1 2 McGill Engineering Services Pty Ltd Engineering, Adjudication & Arbitration Services ABN 45 106 691 169 B H P B I L L I T O N W O R S L E Y A L U M I N A P T Y L T D G E N E R A T I O N L I C E N C E E

More information

Academy FTO Program Effective June 30, 2008

Academy FTO Program Effective June 30, 2008 DEFINITIONS Correctional Officer Trainee: A newly-hired Correctional Officer enrolled in both the residential and field training components of the Vermont Correctional Academy. Community Service Team Leader

More information

Jemena Electricity Networks (Vic) Ltd

Jemena Electricity Networks (Vic) Ltd Jemena Electricity Networks (Vic) Ltd 2016-20 Electricity Distribution Price Review Regulatory Proposal User-requested services explanatory statement Public 30 April 2015 TABLE OF CONTENTS TABLE OF CONTENTS

More information

Permit to Work Manual

Permit to Work Manual Permit to Work Manual Release Date March 2016 CS-PTW-01 Version 3.1 Originator PTW Committee For further information, contact your supervisor or the site safety department. THIS DOCUMENT IS UNCONTROLLED

More information

BRC Packaging Management System Implementation Workbook

BRC Packaging Management System Implementation Workbook We have written this workbook to assist in the implementation of your BRC Packaging Safety and Quality Management System. The workbook is divided into 8 steps that are designed to assist you in implementing

More information

JAA Administrative & Guidance Material Section Six: Synthetic Training Devices (STD/FSTD), Part Three: Temporary Guidance Leaflet

JAA Administrative & Guidance Material Section Six: Synthetic Training Devices (STD/FSTD), Part Three: Temporary Guidance Leaflet LEAFLET NO. 9 (rev. 1): ADDITIONAL GUIDANCE ON QUALITY SYSTEMS FOR OPERATORS OF SYNTHETIC TRAINING DEVICES NOTE: The material contained in this Leaflet has been issued in accordance with Chapter 9 of Administrative

More information

Member Service Electric Wiring Guidelines

Member Service Electric Wiring Guidelines Member Service Electric Wiring Guidelines Table of Contents A. Definitions... 2 B. Member Service Wiring Guidelines... 2 C: Meter located on the house from an underground source - pad transformer or j-box....

More information

Distribution Code Definitions

Distribution Code Definitions Distribution Code Definitions Version 5 Approved September 2007 Comments to this document can be forwarded to: RSA Grid Code Secretariat Attention: Mr. Bernard Magoro Eskom, Transmission System Operator

More information

Paragon Software Group

Paragon Software Group Group Technical Support Policy Table of Contents TABLE OF CONTENTS 2 PARAGON TECHNICAL SUPPORT - MISSION STATEMENT 3 INTRODUCTION 4 Purpose of this document 4 Disclaimer 4 SUPPORT SERVICES OVERVIEW 5 Support

More information

Distribution System Design General Requirements

Distribution System Design General Requirements Electricity Policy Document 279 Issue 7 September 2017 Distribution System Design General Requirements Contents 1 Introduction 2 Scope 3 Definitions 4 General Requirements 5 Documents Referenced 6 Keywords

More information

Gulfstream Flight Test Safety Management System. Evaluation Tool Guidance

Gulfstream Flight Test Safety Management System. Evaluation Tool Guidance Gulfstream Flight Test Safety Management System Evaluation Tool Guidance Flight test presents unique hazards and elevated risk levels during the development and certification of aircraft and new systems.

More information

Exit Procedure. Date: September Version number: 2. Emilie Gray, Senior HR Advisor. Review Date: September 2020

Exit Procedure. Date: September Version number: 2. Emilie Gray, Senior HR Advisor. Review Date: September 2020 Exit Procedure Date: September 2017 Version number: 2 Authors: Emilie Gray, Senior HR Advisor Review Date: September 2020 If you would like this document in an alternative language or format, please contact

More information