Palo Verde Generating Station NEI Lessons Learned. Michael Wittas September 28, 2017

Size: px
Start display at page:

Download "Palo Verde Generating Station NEI Lessons Learned. Michael Wittas September 28, 2017"

Transcription

1 Palo Verde Generating Station NEI Lessons Learned Michael Wittas September 28, 2017

2 Overview Background & History Pre-FLEX Temporary Equipment Fukushima Daiichi Response NRC RIS Palo Verde Generating Station FLEX Plus Strategies 4160 Volt Alternating Current Power Steam Generator Makeup Application of NEI at Palo Verde Lessons Learned NRC Presentation and Input Staging of FLEX Plus Equipment Deployment Strategy Performance Monitoring Implementation for 10 CFR (a)(4) FLEX Plus Engineering Bases

3 3 Background & History

4 Pre-FLEX: Temporary Equipment for Configuration Risk Management PVGS Shutdown Risk Reduction Site-wide effort beginning in early 2009 Multidisciplinary effort including leadership and frontline from PRA, Operations, Work Management, and Engineering Purpose was to assess existing defense in depth shutdown risk assessment process and identify means to reduce risk Updates implemented include programmatic changes, procedure revisions, and use of temporary equipment Project was subsequently expanded to include at-power, probabilistic configuration risk management These efforts primed the pump for eventually considering FLEX for configuration risk management at PVGS

5 Fukushima Daiichi Response March 2011 Fukushima Daiichi Disaster March 2012 Nuclear Regulatory Commission Order EA Leadership behind the risk reduction initiatives were chosen to lead the PVGS response to NRC Flexible and Diverse Coping Strategies (i.e. FLEX) requirements Carried forward the risk management mindset when deciding how PVGS would implement NRC FLEX requirements 5

6 FLEX Plus at PVGS PVGS FLEX responses that go beyond base FLEX requirements are colloquially known as FLEX Plus FLEX Plus was planned and implemented as part of the PVGS FLEX response, with the explicit intent of use in configuration risk management Examples include: Robust exterior connection points (electrical and mechanical) On-site 4160 volt AC generation N+1 FLEX success paths 6

7 NRC Regulatory Issue Summary Prior to issuance of NEI 16-06, no specific industry guidance on crediting temporary equipment for configuration risk management Pieces of information available across various industry documents, but none specifically for this purpose PVGS identified NRC RIS as providing guidance that could be applied to configuration risk management NRC RIS was originally written to provide guidance crediting mitigating strategies for B.5.b NEI lists NRC RIS as a developmental reference 7

8 PVGS FLEX Plus Strategies implemented in the PVGS probabilistic configuration risk management program 8

9 4160V AC Electrical Power PVGS on-site generator skids 2MW capacity per skid (4160V AC output) Minimum of 2 deployed to a given unit when credited for configuration risk management Meets same PRA mission as PVGS Station Blackout Generator Provides 4160V AC power to a single safety bus Locally operated Operation driven by plant procedures, hard card instructions, and once-per-shift Operator briefings Staged and connected to the unit in order to receive credit in the configuration risk management program

10 2MW 4160V AC Generator Skids 10

11 Permanent 4160V Bus Connection Box 11

12 4160V Manual Transfer Switch 12

13 Palo Verde AC Power System 13

14 Steam Generator Makeup Single diesel-driven portable pump skid Takes suction from Condensate Storage Tank Capable of feeding either Steam Generator, but not both The Palo Verde Combustion Engineering System 80 plant is a 2-loop design Same PRA success criteria as a single permanent Auxiliary Feedwater pump Flow to one Steam Generator with one Atmospheric Dump Valve provides adequate secondary cooling Locally operated Operation driven by plant procedures, hard card instructions, and once-per-shift Operator briefings Staged (but not connected) at the unit in order to receive credit in the configuration risk management program 14

15 FLEX Steam Generator Makeup Pump Skid 15

16 Permanent Exterior Connection Points Discharge Connections Alternate Suction Primary Suction 16

17 Application of NEI at PVGS Overview of methodology and lessons learned 17

18 NEI Overview History of NRC Orders and industry guidance that have driven use of temporary equipment Examples include NRC Order EA (FLEX), NRC Order EA (B.5.b), NUMARC Three-tiered assessment approach Tier 1 Qualitative Assessment Tier 2 Semi-Quantitative Streamlined Assessment Tier 3 Full Probabilistic Risk Assessment Example evaluations for each Tier Example human failure event analysis 18

19 PVGS Assessments Palo Verde performed Tier 1 and 3 assessments Tier 1 approach (NEI section 5) Each subsection treated as its own specific criterion requiring assessment and documentation Criterion focused on general feasibility and availability assessments (as opposed to true PRA assessment) Served as foundation for further tiers of assessment Tier 2 assessment (NEI section 6) Not performed by PVGS Deemed of minimal benefit given the nature of FLEX Plus deployment at PVGS and performance of Tier 3 PRA assessment 19

20 PVGS Assessments Tier 3 assessment (NEI section 7) Full PRA analysis, under the presumption of attempting to meet Regulatory Guide criteria Guidance structured to follow ASME/ANS PRA Standard high-level requirements common to all Level 1 hazards PVGS assessment did not attempt to meet RG criteria for modeling of FLEX Plus, given the limited use of the modeling for 10 CFR (a)(4) configuration risk management 20

21 Lessons Learned NRC Interaction NRC performed a site visit to assess PVGS use of NEI 16-06, specifically for the FLEX Plus 4160V AC power success path Regional and national NRC staff toured PVGS, had briefings with subject matter experts, and participated in a full-day meeting with PVGS leadership to discuss the implementation of NEI PVGS fulfillment of each criteria for Tier 1 and 3 assessments (per NEI sections 5 and 7) were clearly itemized in table format for the NRC This was an effective communications tool that received positive feedback after its presentation Simple items were addressed directly in the table, but others required reference to supporting documents and engineering evaluations 21

22 Example Tier 1 Assessment Table Entry Criterion Description of how each criterion is met Criterion Met (YES/NO) NEI , Scenario Assessment Engineering Evaluation (EE) (Ref. 5) evaluated the PRA mission for the 2MW 4160V portable generators and determined that they could fulfill the same mission as a single SBOG. Hence they may be credited in any scenario where a single SBOG successfully supplies power to a Class 1E 4160V bus. YES See Attachment A for the evaluation detailing the adequacy of the scenario timeline. The human reliability analysis (HRA) assessment performed in Attachment A demonstrates that the available time is adequate to support employing the 2MW 4160V portable generators. Equipment necessary to employ the 2MW 4160V portable generators includes the generators themselves (AEBDNG04A*FLEX*GENERA and AEBDNG04B*FLEX*GENERA), the cables connecting the generators to the plant, permanently installed transfer switches NBN-U10 (connection to PBA-S03) and NBN-U12 (connection to NBN-U12), and supply breakers PBA- S03L and PBB-S04K. Operators are cued to employ the 2MW 4160V portable generators by alarm response procedure 40AL-9RK1A (Ref. 7), response section 1A06A or alarm response procedure 40AL- 9RK1C (Ref. 8), response section 1C10B. Both alarm response procedures direct the operator to enter procedure 40MT-9ZZ01 (Ref. 4), which contains instructions on how to restore power to the appropriate Class 1E bus. 22 Deployment and installation of the 2MW 4160V portable generators has been demonstrated. Successful deployment and installation was demonstrated in Unit 1 in support of an emergent emergency diesel generator outage starting 8/1/16.

23 Example Tier 3 Assessment Table Entry Criterion Description of how each criterion is met Criterion Met (YES/NO) NEI , System Analysis Equipment necessary to employ the 2MW 4160V portable generators includes the generators themselves (AEBDNG04A*FLEX*GENERA and AEBDNG04B*FLEX*GENERA), the cables connecting the generators to the plant, transfer switches NBN-U10 (connection to PBA-S03) and NBN-U12 (connection to NBN-U12), and supply breakers PBA-S03L and PBB-S04K. Existing data and system modeling for supply breakers PBA-S03L and PBB-S04K was incorporated into the FLEX+ 4160V generator modeling, which includes random faults, DC control power faults, and logic circuit faults. Per study 13-NS-B063 (Ref. 12), PVNGS At-Power PRA Study for Generic and Bayesian Updated Reliability Data Analysis, the failure rate for a manual switch to fail to remain closed (MS-RC) is 1.7E-7/hour. Per Attachment B, the random failure likelihoods used for the 2MW 4160V portable generators are 2.94E-2/demand (fail to start) and 1.44E-3/hour (fail to run). The HRA to start and align the 2MW 4160V portable generators has a value of as derived in Attachment A. As the random failure rates are dominated by the magnitude of the HRA, it was decided for modeling simplicity to group the generators, transfer switches, and human action in a single undeveloped event with a value of 0.5. The 0.5 value includes margin to account for the uncertainty associated with both the random failures and the HRA. YES 23 Status flags were used to ensure 1) that the 2MW 4160V portable generators would only be turned on in the model when they were staged and 2) to ensure that only one Class 1E bus could be powered by the portable generators at a time.

24 Staging of FLEX Equipment FLEX strategies are designed for extended losses of offsite power, which have long system time windows This challenges typical PRA success criteria and human reliability analysis methods The apparent answer to this is to stage equipment However, this comes with its own challenges and considerations Environment, security, industrial safety are all factors that determine feasibility of staging equipment PVGS considered all of these both during FLEX response planning and subsequently when deploying FLEX Plus for configuration risk management 24

25 PVGS FLEX Plus Deployment Strategy PVGS does not permanently stage FLEX Plus equipment No FLEX Plus success paths are credited in the baseline zero maintenance PRA model FLEX Plus equipment is deployed in response to specific evolutions, such as: Staging a FLEX Plus steam generator makeup pump during maintenance on an Auxiliary Feedwater pump Staging FLEX 4160V AC generators during an emergency diesel generator super outage 25

26 FLEX Equipment Performance Monitoring Responses as dictated in FLEX response procedures do not fall under the scope of Maintenance Rule performance monitoring However, use of FLEX equipment in roles beyond FLEX raises the potential of inclusion in Maintenance Rule performance monitoring via inclusion in emergency operating procedures This would result in more resource intensive monitoring for FLEX equipment than originally intended by most stations PVGS addressed this concern by using a combination of Alarm Response procedures and an Operations Maintenance Activities procedure Alarm response allows operator flexibility in response to an event Operations Maintenance Activities procedure houses all FLEX Plus actions Neither are Emergency Operating Procedures NRC reviewed the procedures as implemented by PVGS No negative feedback, but NRC is expected to offer guidance in the future 26

27 RG and 10 CFR (a)(4) NEI Tier 3 assessments follow the ASME/ANS PRA Standard with the intent of allowing users to credit temporary equipment in RG applications PVGS performed PRA analysis per Tier 3, but explicitly chose not to meet ASME/ANS PRA Standard requirements 27 The only intended application for FLEX Plus was 10 CFR (a)(4) configuration risk management, which does not require meeting RG criteria Further effort beyond demonstrating compliance with NEI is necessary is necessary to credit temporary equipment in risk-informed applications per RG and RG 1.174

28 Review of Engineering Bases Review of existing FLEX engineering basis information is necessary to support NEI assessments PVGS found instances where evaluations performed in support of FLEX configurations were not applicable to FLEX Plus, requiring further evaluation to justify physical performance of equipment 28

29 Conclusions PVGS has seen tangible benefit to safety, operational flexibility, and cost from implementing temporary equipment for configuration risk management NEI provides a robust framework for both qualitative and quantitative assessment of temporary equipment used for risk reduction The use of FLEX equipment for risk reduction is still in its nascent phase There are still open items in question or under development, such as data for temporary equipment, HRA methodology, and performance monitoring requirements 29

30 30 Questions?

Efficiency Bulletin: Maximizing the Benefit of Portable Equipment

Efficiency Bulletin: Maximizing the Benefit of Portable Equipment March 23, 2017 Color Code: Green Efficiency Bulletin: 17-10 Maximizing the Benefit of Portable Equipment Utilize portable equipment, including equipment procured as a part of the B.5.b and FLEX programs,

More information

United States Industry Perspectives on Implementation of Post-Fukushima Actions

United States Industry Perspectives on Implementation of Post-Fukushima Actions United States Industry Perspectives on Implementation of Post-Fukushima Actions Andrew Mauer Senior Project Manager, Risk Assessment, Nuclear Energy Institute Michael Powell Director, Fukushima Initiatives,

More information

Regulatory Guide Monitoring the Effectiveness of Maintenance at Nuclear Power Plants

Regulatory Guide Monitoring the Effectiveness of Maintenance at Nuclear Power Plants Regulatory Guide 1.160 Revision 2 Page 1 of 14 Revision 2 March 1997 Regulatory Guide 1.160 Monitoring the Effectiveness of Maintenance at Nuclear Power Plants Publication Information (Draft issued as

More information

NUCLEAR POWER PLANT RISK-INFORMED SURVEILLANCE FREQUENCY CONTROL PROGRAM IMPLEMENTATION WITH A FOCUS ON INSTRUMENTATION AND CONTROL SYSTEMS

NUCLEAR POWER PLANT RISK-INFORMED SURVEILLANCE FREQUENCY CONTROL PROGRAM IMPLEMENTATION WITH A FOCUS ON INSTRUMENTATION AND CONTROL SYSTEMS NUCLEAR POWER PLANT RISK-INFORMED SURVEILLANCE FREQUENCY CONTROL PROGRAM IMPLEMENTATION WITH A FOCUS ON INSTRUMENTATION AND CONTROL SYSTEMS James K. (Jim) Liming ABSG Consulting Inc. (ABS Consulting) 300

More information

Post-Fukushima Assessment of the AP1000 Plant

Post-Fukushima Assessment of the AP1000 Plant ABSTRACT Post-Fukushima Assessment of the AP1000 Plant Ernesto Boronat de Ferrater Westinghouse Electric Company, LLC Padilla 17-3 Planta 28006, Madrid, Spain boronae@westinghouse.com Bryan N. Friedman,

More information

Introduction to the 2015 Darlington NGS Probabilistic Safety Assessment. Carlos Lorencez and Robin Manley Ontario Power Generation August 2015

Introduction to the 2015 Darlington NGS Probabilistic Safety Assessment. Carlos Lorencez and Robin Manley Ontario Power Generation August 2015 Introduction to the 2015 Darlington NGS Probabilistic Safety Assessment Carlos Lorencez and Robin Manley Ontario Power Generation August 2015 Introduction to the 2015 Darlington NGS Probabilistic Safety

More information

Regulatory Actions and Follow up Measures against Fukushima Accident in Korea

Regulatory Actions and Follow up Measures against Fukushima Accident in Korea Int Conference on Effective Nuclear Regulatory Systems, April 9, 2013, Canada Regulatory Actions and Follow up Measures against Fukushima Accident in Korea Seon Ho SONG* Korea Institute of Nuclear Safety

More information

Seismic PRA Insights and Lessons Learned

Seismic PRA Insights and Lessons Learned PSA 2015 International Topical Meeting On Probabilistic Safety Assessment and Analysis April 26-30, Sun Valley, ID Session 20-2: Seismic II, Paper 12324 Seismic PRA Insights and Lessons Learned Presentation:

More information

Risks Associated with Shutdown in PWRs

Risks Associated with Shutdown in PWRs International Conference Nuclear Option in Countries with Small and Mi Opatija, Croatia, 1996 Risks Associated with Shutdown in PWRs Igor Grlicarev Slovenian Nuclear Safety Administration Vojkova 59, 1113

More information

Improvements Needed in Nuclear Power Plant Probabilistic Risk Assessments: Lessons Learned from Fukushima

Improvements Needed in Nuclear Power Plant Probabilistic Risk Assessments: Lessons Learned from Fukushima Improvements Needed in Nuclear Power Plant Probabilistic Risk Assessments: Lessons Learned from Fukushima Mohammad Modarres Professor of Nuclear Engineering Department of Mechanical Engineering University

More information

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C December

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C December UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 December 17. 2013 Mr. Michael J. Pacilio Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555 SUBJECT: THREE MILE ISLAND NUCLEAR

More information

Risk-Informed Design Changes of an Advanced Reactor in Low Power and Shutdown Operation

Risk-Informed Design Changes of an Advanced Reactor in Low Power and Shutdown Operation Risk-Informed Design Changes of an Advanced Reactor in Low Power and Shutdown Operation Ji-Yong Oh* a, Ho-Rim Moon a, Han-Gon Kim a and Myung-Ki Kim a a Korea Hydro and Nuclear Power Co. Ltd, Central Research

More information

Industry Guidance for Compliance with NRC Order EA , To Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation

Industry Guidance for Compliance with NRC Order EA , To Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation NEI 12-02 [Revision B] Industry Guidance for Compliance with NRC Order EA-12-051, To Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation ACKNOWLEDGEMENTS The Nuclear Energy Institute

More information

REGULATORY GUIDE An Approach for Using Probabilistic Risk Assessment In Risk-Informed Decisions On Plant-Specific Changes to the Licensing Basis

REGULATORY GUIDE An Approach for Using Probabilistic Risk Assessment In Risk-Informed Decisions On Plant-Specific Changes to the Licensing Basis REGULATORY GUIDE 1.174 An Approach for Using... Page 1 of 38 July 1998 REGULATORY GUIDE 1.174 An Approach for Using Probabilistic Risk Assessment In Risk-Informed Decisions On Plant-Specific Changes to

More information

Safety Implication for Gen-IV SFR based on the Lesson Learned from the Fukushima Dai-ichi NPPs Accident. Ryodai NAKAI Japan Atomic Energy Agency

Safety Implication for Gen-IV SFR based on the Lesson Learned from the Fukushima Dai-ichi NPPs Accident. Ryodai NAKAI Japan Atomic Energy Agency Safety Implication for Gen-IV SFR based on the Lesson Learned from the Fukushima Dai-ichi NPPs Accident Ryodai NAKAI Japan Atomic Energy Agency Contents Introduction Japanese Government Report to the IAEA

More information

Westinghouse Small Modular Reactor. Passive Safety System Response to Postulated Events

Westinghouse Small Modular Reactor. Passive Safety System Response to Postulated Events Westinghouse Small Modular Reactor Passive Safety System Response to Postulated Events Matthew C. Smith Dr. Richard F. Wright Westinghouse Electric Company Westinghouse Electric Company 600 Cranberry Woods

More information

Safety Challenges for New Nuclear Power Plants

Safety Challenges for New Nuclear Power Plants Implementing Design Extension Conditions and Fukushima Changes in the Context of SSR-2/1 Michael Case Office of Nuclear Regulatory Research United States Nuclear Regulatory Commission Outline of Presentation

More information

12-051, To Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, August 2012

12-051, To Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, August 2012 Steven P. Kraft SENIOR DIRECTOR FUKUSHIMA RESPONSE COORDINATION & STRATEGY August 24, 2012 Ms. Cindy K. Bladey Chief, Rules, Announcements and Directives Branch Office of Administration U.S. Nuclear Regulatory

More information

International Atomic Energy Agency. Impact of Extreme Events on Nuclear Facilities following Fukushima. Dr C H Shepherd Nuclear Safety Consultant, UK

International Atomic Energy Agency. Impact of Extreme Events on Nuclear Facilities following Fukushima. Dr C H Shepherd Nuclear Safety Consultant, UK Impact of Extreme Events on Nuclear Facilities following Fukushima by Dr C H Shepherd Nuclear Safety Consultant, UK CRA PSA/HFA Forum 8-9 September 2011, Warrington Contents of the Presentation IAEA views

More information

HPR1000: ADVANCED PWR WITH ACTIVE AND PASSIVE SAFETY FEATURES

HPR1000: ADVANCED PWR WITH ACTIVE AND PASSIVE SAFETY FEATURES HPR1000: ADVANCED PWR WITH ACTIVE AND PASSIVE SAFETY FEATURES D. SONG China Nuclear Power Engineering Co., Ltd. Beijing, China Email: songdy@cnpe.cc J. XING China Nuclear Power Engineering Co., Ltd. Beijing,

More information

OPG Proprietary Report

OPG Proprietary Report N/A R001 2 of 114 Table of Contents Page List of Tables and Figures... 5 Revision Summary... 6 Executive Summary... 7 1.0 INTRODUCTION... 9 1.1 Objectives... 10 1.2 Scope... 10 1.3 Organization of Summary...

More information

Evaluation of AP1000 Containment Hydrogen Control Strategies for Post- Fukushima Lessons Learned

Evaluation of AP1000 Containment Hydrogen Control Strategies for Post- Fukushima Lessons Learned Evaluation of AP1000 Containment Hydrogen Control Strategies for Post- Fukushima Lessons Learned James H. Scobel and Hong Xu Westinghouse Electric Company, EEC 1000 Westinghouse Dr. Cranberry Township,

More information

DEVELOPMENT AND APPLICATION OF PROBABILISTIC SAFETY ASSESSMENT PSA IN DAYA BAY NUCLEAR POWER STATION

DEVELOPMENT AND APPLICATION OF PROBABILISTIC SAFETY ASSESSMENT PSA IN DAYA BAY NUCLEAR POWER STATION 18th International Conference on Structural Mechanics in Reactor Technology (SMiRT 18) Beijing, China, August 7-12, 2005 SMiRT18-A01-2 DEVELOPMENT AND APPLICATION OF PROBABILISTIC SAFETY ASSESSMENT PSA

More information

Isolation Condenser; water evaporation in the tank and steam into the air. Atmosphere (in Severe Accident Management, both P/S and M/S)

Isolation Condenser; water evaporation in the tank and steam into the air. Atmosphere (in Severe Accident Management, both P/S and M/S) Loss of Ultimate Heat Sink ANS AESJ AESJ Fukushima Symposium, March h4, 2012 Hisashi Ninokata, Tokyo Institute of Technology Available ultimate heat sinks at 1F1~3 1F1 (Fukushima Dai ichi Unit 1) Sea water

More information

Enhancement of Nuclear Safety

Enhancement of Nuclear Safety Enhancement of Nuclear Safety Soon Heung Chang Handong Global University May 6, 2015 Contents 1 2 3 4 Importance of Energy Fundamentals of Nuclear Safety How to Enhance Nuclear Safety Closing Remarks 2

More information

Lessons Learned from Fukushima Daiichi Nuclear Power Station Accident and Consequent Safety Improvements

Lessons Learned from Fukushima Daiichi Nuclear Power Station Accident and Consequent Safety Improvements Hitachi Review Vol. 62 (2013), No. 1 75 Lessons Learned from Fukushima Daiichi Nuclear Power Station Accident and Consequent Safety Improvements Masayoshi Matsuura Kohei Hisamochi Shinichiro Sato Kumiaki

More information

March 16, Mr. William M. Dean Director, Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, DC

March 16, Mr. William M. Dean Director, Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, DC ANTHONY R. PIETRANGELO Senior Vice President and Chief Nuclear Officer 1201 F Street, NW, Suite 1100 Washington, DC 20004 P: 202.739.8081 arp@nei.org nei.org March 16, 2015 Mr. William M. Dean Director,

More information

APR1400 Safe, Reliable Technology

APR1400 Safe, Reliable Technology APR1400 Safe, Reliable Technology OECD/NEA Workshop on Innovations in Water-cooled Reactor Technology Paris, Feb 11 12, 2015 Presented by Shin Whan Kim Contents 1. Introduction 2. Major Safety Design Characteristics

More information

DRAFT REGULATORY GUIDE

DRAFT REGULATORY GUIDE U.S. NUCLEAR REGULATORY COMMISSION April 2015 OFFICE OF NUCLEAR REGULATORY RESEARCH Division 1 DRAFT REGULATORY GUIDE DRAFT REGULATORY GUIDE DG-1322 (Proposed New Regulatory Guide) Technical Lead Steven

More information

European level recommendations Sect. in NAcP 2 Generic recommendation for WENRA, Finland participates and follows the work.

European level recommendations Sect. in NAcP 2 Generic recommendation for WENRA, Finland participates and follows the work. Cross reference table of ENSREG and Extraordinary CNS recommendations and national actions 1(16) 2.1 European guidance on assessment of natural hazards and margins The peer review Board recommends that

More information

Westinghouse 10 CFR Program

Westinghouse 10 CFR Program Consistent with the tenets of the Delivering the Nuclear Promise initiative, Westinghouse has developed a streamlined approach to promote cost-effective, standardized implementation of the 10CFR50.69 regulation

More information

Power Generation. Ronaldo Jenkins Electrical Engineering Branch Chief Office of New Reactors (NRO)

Power Generation. Ronaldo Jenkins Electrical Engineering Branch Chief Office of New Reactors (NRO) Power Generation Ronaldo Jenkins Electrical Engineering Branch Chief Office of New Reactors (NRO) Agenda Overview Design Considerations 10 Code of Federal Regulations (CFR) 50 10 CFR 50, General Design

More information

Main Steam & T/G Systems, Safety

Main Steam & T/G Systems, Safety Main Steam & T/G Systems, Safety Page 1 This steam generator, built for the Wolsong station in Korea, was manufactured in Canada by the Babcock and Wilcox company. In Wolsong 2,3, and 4 a joint venture

More information

September 19, Mr. Biff Bradley, Director Risk Assessment Nuclear Energy Institute Suite I Street, NW Washington, DC

September 19, Mr. Biff Bradley, Director Risk Assessment Nuclear Energy Institute Suite I Street, NW Washington, DC September 19, 2007 Mr. Biff Bradley, Director Risk Assessment Suite 400 1776 I Street, NW SUBJECT: FINAL SAFETY EVALUATION FOR NUCLEAR ENERGY INSTITUTE (NEI) TOPICAL REPORT (TR) 04-10, REVISION 1, RISK-INFORMED

More information

AP1000 European 19. Probabilistic Risk Assessment Design Control Document

AP1000 European 19. Probabilistic Risk Assessment Design Control Document 19.39 In-Vessel Retention of Molten Core Debris 19.39.1 Introduction In-vessel retention of molten core debris through water cooling of the external surface of the reactor vessel is a severe accident management

More information

The Westinghouse Advanced Passive Pressurized Water Reactor, AP1000 TM. Roger Schène Director,Engineering Services

The Westinghouse Advanced Passive Pressurized Water Reactor, AP1000 TM. Roger Schène Director,Engineering Services The Westinghouse Advanced Passive Pressurized Water Reactor, AP1000 TM Roger Schène Director,Engineering Services 1 Background Late 80: USA Utilities under direction of EPRI and endorsed by NRC : Advanced

More information

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C August25, 2016

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C August25, 2016 UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 August25, 2016 Mr. Jon A. Franke Site Vice President Susquehanna Nuclear, LLC 769 Salem Boulevard NUCSB3 Berwick, PA 18603-0467 SUBJECT:

More information

NuScale SMR Technology

NuScale SMR Technology NuScale SMR Technology UK IN SMR; SMR IN UK Conference - Manchester, UK Tom Mundy, EVP Program Development September 25, 2014 Acknowledgement & Disclaimer This material is based upon work supported by

More information

Generator Assessment & Roles During A Restoration

Generator Assessment & Roles During A Restoration Generator Assessment & Roles During A Restoration PJM State & Member Training Dept. PJM 2015 Objectives Students will be able to: Identify the process and requirements for operating during system restoration

More information

Ageing Management and Long Term Operation of Nuclear Power Plants

Ageing Management and Long Term Operation of Nuclear Power Plants Ageing Management and Long Term Operation of Nuclear Power Plants Senior Regulators Meeting 17 September 2015 Jan BENS AGENDA Belgian Nuclear Reactor Sites LTO Legal Framework LTO Regulatory Framework

More information

Implementation of Lessons Learned from Fukushima Accident in CANDU Technology

Implementation of Lessons Learned from Fukushima Accident in CANDU Technology e-doc 4395709 Implementation of Lessons Learned from Fukushima Accident in CANDU Technology Greg Rzentkowski Director General, Power Reactor Regulation Canadian Nuclear Safety Commission on behalf of CANDU

More information

Preliminary Lessons Learned from the Fukushima Daiichi Accident for Advanced Nuclear Power Plant Technology Development

Preliminary Lessons Learned from the Fukushima Daiichi Accident for Advanced Nuclear Power Plant Technology Development Preliminary Lessons Learned from the Fukushima Daiichi Accident for Advanced Nuclear Power Plant Technology Development A. Introduction The IAEA Report on Reactor and Spent Fuel Safety in the Light of

More information

NUCLEAR POWER NEW NUCLEAR POWER PLANTS IN 2012

NUCLEAR POWER NEW NUCLEAR POWER PLANTS IN 2012 NUCLEAR POWER NEW NUCLEAR POWER PLANTS IN 2012 AP1000 IN FEBRUARY 2012, THE FIRST NUCLEAR POWER PLANTS IN THE US IN 35 YEARS WERE LICENSCED TO BEGIN CONSTRUCTION. TWO WESTINGHOUSE AP1000 NUCEAR REACTOR

More information

Safety enhancement of NPPs in China after Fukushima Accident

Safety enhancement of NPPs in China after Fukushima Accident Safety enhancement of NPPs in China after Fukushima Accident CHAI Guohan 29 June 2015, Brussels National Nuclear Safety Administration, P. R. China Current Development of Nuclear Power Mid of year 2015

More information

Accident Management under Extreme Events

Accident Management under Extreme Events International Journal of Performability Engineering Vol. 10, No. 7, November 2014, pp. 669-680. RAMS Consultants Printed in India Accident Management under Extreme Events GEORGE VAYSSIER * NSC Netherlands,

More information

Stress tests specifications Proposal by the WENRA Task Force 21 April 2011

Stress tests specifications Proposal by the WENRA Task Force 21 April 2011 Stress tests specifications Proposal by the WENRA Task Force 21 April 2011 Introduction Considering the accident at the Fukushima nuclear power plant in Japan, the Council of the European Union declared

More information

Regulation of existing and new nuclear power stations in South Africa in the light of the Fukushima Accident

Regulation of existing and new nuclear power stations in South Africa in the light of the Fukushima Accident Regulation of existing and new nuclear power stations in South Africa in the light of the Fukushima Accident O Phillips: Senior Executive Manager - National Nuclear Regulator The Fukushima Ministerial

More information

Curtiss-Wright/Scientech Seismic HRA Insights and Lessons Learned from the Application of EPRI Report TR

Curtiss-Wright/Scientech Seismic HRA Insights and Lessons Learned from the Application of EPRI Report TR Curtiss-Wright/Scientech Seismic HRA Insights and Lessons Learned from the Application of EPRI Report TR- 1025294 Michael Hirt 1, Kaydee Kohlhepp-Gunter 2, Jan Grobbelaar 3, Jeff Julius 4, Steve Eide 5

More information

Brazilian Operator s Response to Fukushima Daiichi Accident Luiz Soares Technical Director

Brazilian Operator s Response to Fukushima Daiichi Accident Luiz Soares Technical Director Simposyum Siting of New Nuclear Power Plants and Irradiated Fuel Facilities Buenos Aires Argentina 24-28 June 2013 Panel Fukushima Daiichi s Impact in Nuclear Power Programs Worldwide Brazilian Operator

More information

OPG Proprietary Report

OPG Proprietary Report N/A R001 2 of 121 Table of Contents Page List of Tables and Figures... 5 Revision Summary... 6 Executive Summary... 7 1.0 INTRODUCTION... 9 1.1 Objectives... 10 1.2 Scope... 10 1.3 Organization of Summary...

More information

CNE Cernavoda Response to Fukushima Event/EU Stress Test Requirements

CNE Cernavoda Response to Fukushima Event/EU Stress Test Requirements CNE Cernavoda Response to Fukushima Event/EU Stress Test Requirements Sorin Holostencu IAEA Technical Meeting on Operational Experience with Implementation of Post-Fukushima Actions in Nuclear Power Plants,

More information

Joint ICTP-IAEA Essential Knowledge Workshop on Deterministic Safety Analysis and Engineering Aspects Important to Safety. Trieste,12-23 October 2015

Joint ICTP-IAEA Essential Knowledge Workshop on Deterministic Safety Analysis and Engineering Aspects Important to Safety. Trieste,12-23 October 2015 Joint ICTP- Essential Knowledge Workshop on Deterministic Safety Analysis and Engineering Aspects Important to Safety Trieste,12-23 October 2015 Safety classification of structures, systems and components

More information

Frequently Asked Questions: Japanese Nuclear Energy Situation

Frequently Asked Questions: Japanese Nuclear Energy Situation NUCLEAR ENERGY INSTITUTE Frequently Asked Questions: Japanese Nuclear Energy Situation 1. What will be the impact of the Fukushima Daiichi accident on the U.S. nuclear program? It is premature to draw

More information

Regulatory Guide An Approach For Plant-Specific Risk-informed Decisionmaking Inservice Inspection of Piping

Regulatory Guide An Approach For Plant-Specific Risk-informed Decisionmaking Inservice Inspection of Piping Regulatory Guide 1.178An Approach For Plant-S... Page 1 of 32 July 1998 Regulatory Guide 1.178 An Approach For Plant-Specific Risk-informed Decisionmaking Inservice Inspection of Piping Publication Information

More information

NRC INSPECTION MANUAL INSPECTION PROCEDURE 35065

NRC INSPECTION MANUAL INSPECTION PROCEDURE 35065 NRC INSPECTION MANUAL INSPECTION PROCEDURE 35065 DQASIP PROCUREMENT, RECEIVING, AND STORAGE PROGRAM APPLICABILITY: 2512 35065-01 INSPECTION OBJECTIVES To determine whether equipment procurement specifications

More information

PJM Black Start Replacement Process RTO Wide Black Start RFP Review Plan

PJM Black Start Replacement Process RTO Wide Black Start RFP Review Plan PJM Black Start Replacement Process RTO Wide Black Start RFP Review Plan David Schweizer Manager, Generation OC Meeting June 6, 2017 Overview PJM target for issuing next 5-Year RTO Wide Black Start RFP

More information

CRFA System B BASES

CRFA System B BASES CRFA System B 3.7.2 APPLICABLE SAFETY ANALYSES LCO and 15 ( Refs. 3 and 4, respectively). The isolation mode of the CRFA System is assumed to operate following a DBA. The radiological doses to CRE occupants

More information

High Energy Arcing Faults (HEAF) and Their Impact on PRA for a Nuclear Power Plant Latest International Operating Experience and Research Activities

High Energy Arcing Faults (HEAF) and Their Impact on PRA for a Nuclear Power Plant Latest International Operating Experience and Research Activities High Energy Arcing Faults (HEAF) and Their Impact on PRA for a Nuclear Power Plant Latest International Operating Experience and Research Activities Marina Roewekamp GRS ggmbh, Germany Nicholas Melly,

More information

Meetings for Sharing International Knowledge and Experience on Stress Tests

Meetings for Sharing International Knowledge and Experience on Stress Tests Meetings for Sharing International Knowledge and Experience on Stress Tests Presented by: Peter Hughes, Ovidiu Coman, Javier Yllera Department of Nuclear Safety and Security Division of Nuclear Installation

More information

BWR MODERNIZATION PROJECT: INSTALLATION OF A NEW DIGITAL FEEDWATER CONTROL SYSTEM

BWR MODERNIZATION PROJECT: INSTALLATION OF A NEW DIGITAL FEEDWATER CONTROL SYSTEM BWR MODERNIZATION PROJECT: INSTALLATION OF A NEW DIGITAL FEEDWATER CONTROL SYSTEM Javier Lasierra; Cristina Corrales; Mateo Ramos Control Rooms and Simulation Tecnatom Avda. Montes de Oca 1, 28703 San

More information

Risk monitor during shutdown of CANDU NPPs

Risk monitor during shutdown of CANDU NPPs Risk monitor during shutdown of CANDU NPPs Korea Electric Power Research Institute Daejon, Korea Myung-Ki Kim PSAM 9, Hong Kong, 2008.05.18-23 1 Contents Introduction Defense-In-Depth Safety Function Assessment

More information

Steam Power Station (Thermal Station)

Steam Power Station (Thermal Station) Steam Power Station (Thermal Station) A generating station which converts heat energy into electrical energy through turning water into heated steam is known as a steam power station. A steam power station

More information

Lessons learned from the accident at the Fukushima Daiichi Nuclear Power Plant

Lessons learned from the accident at the Fukushima Daiichi Nuclear Power Plant May 9, 2011 Lessons learned from the accident at the Fukushima Daiichi Nuclear Power Plant Technical Analysis Subcommittee Committee for Investigation of Nuclear Safety Atomic Energy Society of Japan We

More information

CNSC Evaluation of Plant-Specific SAMG

CNSC Evaluation of Plant-Specific SAMG CNSC Evaluation of Plant-Specific SAMG Quanmin Lei IAEA Technical Meeting on Verification and Validation of SAMG Vienna, Austria December 12-14, 2016 e-docs # 5104918 nuclearsafety.gc.ca Outline Summarize

More information

A/E Design Deliverable Checklist

A/E Design Deliverable Checklist A/E Design Deliverable Checklist Design deliverables for the Design Development phase shall include all items listed in the Design Development column as well as those all items listed in the Schematic

More information

LOLE Fundamentals Loss of Load Expectation (LOLE) Fundamentals

LOLE Fundamentals Loss of Load Expectation (LOLE) Fundamentals Loss of Load Expectation (LOLE) Fundamentals March 13, 2014 Last material update: 03/12/2014 LOLE Agenda 2 Loss of Load Expectation (LOLE) Fundamentals Sections LOLE Background LOLE Study Connections to

More information

OPG Proprietary Report

OPG Proprietary Report N/A R000 2 of 101 Table of Contents Page List of Tables and Figures... 5 Revision Summary... 6 Executive Summary... 7 1.0 INTRODUCTION... 9 1.1 Objectives... 10 1.2 Scope... 10 1.3 Organization of Summary...

More information

BWR Safety Improvement as a Lesson Learned from Fukushima Accident

BWR Safety Improvement as a Lesson Learned from Fukushima Accident BWR Safety Improvement as a Lesson Learned from Fukushima Accident M. M. Zaky and S. A. Kotb ETRR-2, Atomic Energy Authority, Cairo, Egypt Received: 20/5/2016 Accepted: 15/7/2016 ABSTRACT The serious accident

More information

ANTICIPATED ANALYSIS OF FLAMANVILLE 3 EPR OPERATING LICENSE - STATUS AND INSIGHTS FROM LEVEL 1 PSA REVIEW

ANTICIPATED ANALYSIS OF FLAMANVILLE 3 EPR OPERATING LICENSE - STATUS AND INSIGHTS FROM LEVEL 1 PSA REVIEW ANTICIPATED ANALYSIS OF FLAMANVILLE 3 EPR OPERATING LICENSE - STATUS AND INSIGHTS FROM LEVEL 1 PSA REVIEW Gabriel Georgescu, Patricia Dupuy and Francois Corenwinder Institute for Radiological Protection

More information

7. Electrical Facility Ratings

7. Electrical Facility Ratings 7. Electrical Facility Ratings 7.1 Accredited Net Generating Capacity This Section shall be used to determine the annual and seasonal accredited net generating capacity of generators in calculating the

More information

The Westinghouse AP1000 Advanced Nuclear Plant Plant description

The Westinghouse AP1000 Advanced Nuclear Plant Plant description The Westinghouse AP1000 Advanced Nuclear Plant Plant description Copyright 2003, Westinghouse Electric Co., LLC. All rights reserved. Table of Contents 1 Introduction 1 2 Description of the nuclear systems

More information

SODIUM HYPOCHLORITE PORTABLE DOSING UNIT. Max Hadzidimitriou. Yarra Valley Water

SODIUM HYPOCHLORITE PORTABLE DOSING UNIT. Max Hadzidimitriou. Yarra Valley Water SODIUM HYPOCHLORITE PORTABLE DOSING UNIT Paper Presented by: Max Hadzidimitriou Authors: Max Hadzidimitriou, Project Manager, David Younger, Water Quality Engineer, Yarra Valley Water 73 rd Annual Water

More information

Aircraft Lockout/Tagout (LOTO)

Aircraft Lockout/Tagout (LOTO) Aircraft Lockout/Tagout Program (LOTO) for All EMPLOYEES Rules codified in 29 CFR 1910.147 and 1910.146. There are many areas on an aircraft that require positive control of Hazardous Energy: E & E Bays,

More information

Combined Cycle Power Plants. Combined Cycle Power Plant Overview (Single- and Multi-Shaft) Training Module. ALSTOM (Switzerland) Ltd )*+,

Combined Cycle Power Plants. Combined Cycle Power Plant Overview (Single- and Multi-Shaft) Training Module. ALSTOM (Switzerland) Ltd )*+, Power Plant Overview Training Module ALSTOM (Switzerland) Ltd )*+, We reserve all rights in this document and in the information contained therein. Reproduction, use or disclosure to third parties without

More information

IAEA SAFETY STANDARDS Seismic Hazards in Site Evaluation of Nuclear Installations

IAEA SAFETY STANDARDS Seismic Hazards in Site Evaluation of Nuclear Installations IAEA SAFETY STANDARDS Seismic Hazards in Site Evaluation of Nuclear Installations Regional Workshop on Volcanic, Seismic, and Tsunami Hazard Assessment Related to NPP Siting Activities and Requirements

More information

Nuclear Power A Journey of Continuous Improvement

Nuclear Power A Journey of Continuous Improvement Nuclear Power A Journey of Continuous Improvement Westinghouse Non Proprietary Class 3 Our Place in Nuclear History Innovation 1886 and forever Implementation & Improvement 1957 through Today Renaissance

More information

Introduction to Level 2 PSA

Introduction to Level 2 PSA Introduction to Level 2 PSA Dr Charles Shepherd Chief Consultant, Corporate Risk Associates CRA PSA/HFA FORUM 13-14 September 2012, Bristol Accident sequences modelled by the PSA INITIATING EVENTS SAFETY

More information

Long-Term Nucle ar O p erations

Long-Term Nucle ar O p erations Long-Term Nucle ar O p erations E x e c u t i v e S u m m a r y Long-Term Nuclear Operations What is a feasible life span for a nuclear plant? I would say 80 years, without question. And I think if we

More information

Development and use of SAMGs in the Krško NPP

Development and use of SAMGs in the Krško NPP REPUBLIC OF SLOVENIA Development and use of SAMGs in the Krško NPP Tomaž Nemec Slovenian Nuclear Safety Administration tomaz.nemec@gov.si IAEA TM on the Verification and Validation of SAMGs, Vienna, 12

More information

during Normal Operations

during Normal Operations Hitachi-GE Nuclear Energy, Ltd. UK ABWR GENERIC DESIGN ASSESSMENT Resolution Plan for RI-ABWR-0001 Definition and Justification for the Radioactive Source Terms in UK ABWR during Normal Operations Definition

More information

SYSTEMATIC AND DESIGN SAFETY IMPROVEMENTS OF NPPS IN CZECH REPUBLIC

SYSTEMATIC AND DESIGN SAFETY IMPROVEMENTS OF NPPS IN CZECH REPUBLIC SYSTEMATIC AND DESIGN SAFETY IMPROVEMENTS OF NPPS IN CZECH REPUBLIC 3.10.2016 ČEZ, a. s. Meeting at IAEA Vienna Overview of topics ČEZ nuclear fleet (basic features) Systematic measures targeted to improve

More information

Safety Enhancement of Nuclear Power Plant Post Fukushima. Kumiaki Moriya

Safety Enhancement of Nuclear Power Plant Post Fukushima. Kumiaki Moriya International Conference on Nuclear Governance Post-Fukushima Marina Bay Sands, Singapore, 31 October 2013 Safety Enhancement of Nuclear Power Plant Post Fukushima October 31,2013 Kumiaki Moriya Hitachi-GE

More information

FOSH Forsmark Safety Enhancement Project Post-Fukushima actions at Forsmark NPP

FOSH Forsmark Safety Enhancement Project Post-Fukushima actions at Forsmark NPP FOSH Forsmark Safety Enhancement Project Post-Fukushima actions at Forsmark NPP NKS January 12-13, 2016 Ove Nilsson Sekretessklass: Open (S1) 1 2015-12-23 FOSH Forsmark Safety Enhancement Project F-0003165

More information

DOE Small Modular Reactor Licensing Technical Support Program Overview for National Conference of State Legislatures June 19, 2014

DOE Small Modular Reactor Licensing Technical Support Program Overview for National Conference of State Legislatures June 19, 2014 DOE Small Modular Reactor Licensing Technical Support Program Overview for National Conference of State Legislatures June 19, 2014 Tim Beville Office of Nuclear Energy U.S. Department of Energy Administration

More information

Applicability of PSA Level 2 in the Design of Nuclear Power Plants

Applicability of PSA Level 2 in the Design of Nuclear Power Plants Applicability of PSA Level 2 in the Design of Nuclear Power Plants Estelle C. SAUVAGE a, Gerben DIRKSEN b, and Thierry COYE de BRUNELLIS c a AREVA-NP SAS, Paris, France b AREVA-NP Gmbh, Erlangen, Germany

More information

FlexEfficiency* 60 Portfolio

FlexEfficiency* 60 Portfolio FlexEfficiency* 60 Portfolio A new standard of high efficiency and operational flexibility * Trademark of General Electric Company All Rights Reserved. No part of this document may be reproduced, transmitted,

More information

Development of an Update to ISA S67.04 and RP 67.04: Setpoints for Nuclear Safety-Related Instrumentation for Nuclear Power Plants

Development of an Update to ISA S67.04 and RP 67.04: Setpoints for Nuclear Safety-Related Instrumentation for Nuclear Power Plants Development of an Update to ISA S67.04 and RP 67.04: Setpoints for Nuclear Safety-Related Instrumentation for Nuclear Power Plants Wayne Marquino Chairman, ISA S67.04 Committee Team Leader, ESBWR System

More information

Appendix B. Aging Management Programs and Activities

Appendix B. Aging Management Programs and Activities Appendix B Aging Management Programs and Activities This page is intentionally blank. TABLE OF CONTENTS Table of Contents...i Appendix B: Aging Management Programs and Activities... B.1-1 B.1 INTRODUCTION...

More information

Information Technology Services Project Management Office Operations Guide

Information Technology Services Project Management Office Operations Guide Information Technology Services Project Management Office Operations Guide Revised 3/31/2015 Table of Contents ABOUT US... 4 WORKFLOW... 5 PROJECT LIFECYCLE... 6 PROJECT INITIATION... 6 PROJECT PLANNING...

More information

Improvements of Safety and Reliability by PRA

Improvements of Safety and Reliability by PRA Document 2, The 3rd Meeting, Working Group on Voluntary Efforts and Continuous Improvement of Nuclear Safety, Advisory Committee for Natural Resources and Energy Improvements of Safety and Reliability

More information

Use of PSA to Support the Safety Management of Nuclear Power Plants

Use of PSA to Support the Safety Management of Nuclear Power Plants S ON IMPLEMENTATION OF THE LEGAL REQUIREMENTS Use of PSA to Support the Safety Management of Nuclear Power Plants РР - 6/2010 ÀÃÅÍÖÈß ÇÀ ßÄÐÅÍÎ ÐÅÃÓËÈÐÀÍÅ BULGARIAN NUCLEAR REGULATORY AGENCY TABLE OF CONTENTS

More information

Westinghouse AP1000. Reactor

Westinghouse AP1000. Reactor Westinghouse AP1000 A Third Generation Nuclear Reactor International Council on Systems Engineering (INCOSE) September 18, 2013 Andrew Drake, PMP Director, AP1000 Engineering Completion Engineering, Equipment

More information

SAFETY GUIDES. Deterministic Safety Assessment РР - 5/2010 ÀÃÅÍÖÈß ÇÀ ßÄÐÅÍÎ ÐÅÃÓËÈÐÀÍÅ BULGARIAN NUCLEAR REGULATORY AGENCY

SAFETY GUIDES. Deterministic Safety Assessment РР - 5/2010 ÀÃÅÍÖÈß ÇÀ ßÄÐÅÍÎ ÐÅÃÓËÈÐÀÍÅ BULGARIAN NUCLEAR REGULATORY AGENCY S ON IMPLEMENTATION OF THE LEGAL REQUIREMENTS Deterministic Safety Assessment РР - 5/2010 ÀÃÅÍÖÈß ÇÀ ßÄÐÅÍÎ ÐÅÃÓËÈÐÀÍÅ BULGARIAN NUCLEAR REGULATORY AGENCY TABLE OF CONTENTS 1. GENERAL PROVISIONS...2 LEGAL

More information

REGULATORY DIRECTORATE OF REGULATORY STANDARDS

REGULATORY DIRECTORATE OF REGULATORY STANDARDS U.S. ATOMIC ENERGY COMMISSION REGULATORY DIRECTORATE OF REGULATORY STANDARDS December 1974 GUIDE REGULATORY GUIDE 1.93 AVAILABILITY OF ELECTRIC POWER SOURCES A. INTRODUCTION Section 50.36(cX2), "Limiting

More information

IHRDC s Competency-Based e-learning Pathways for Refinery Personnel

IHRDC s Competency-Based e-learning Pathways for Refinery Personnel International Human Resources Development Corporation V.2.0 IHRDC s Competency-Based e-learning Pathways for Refinery Personnel COMPETENCY-BASED TRAINING PATHWAYS FOR REFINERY TECHNICIANS Our highly regarded

More information

EVALUATION OF SAFETY CULTURE IN WANO PRE-STARTUP REVIEWS

EVALUATION OF SAFETY CULTURE IN WANO PRE-STARTUP REVIEWS EVALUATION OF SAFETY CULTURE IN WANO PRE-STARTUP REVIEWS Todd Brumfield World Association of Nuclear Operators (WANO) Atlanta, Georgia, USA ABSTRACT: The requirements for performance of pre-startup reviews

More information

INVESTIGATION OF CRITICAL SAFETY FUNCTION INTEGRITY IN CASE OF STEAM LINE BREAK ACCIDENT FOR VVER 1000/V320

INVESTIGATION OF CRITICAL SAFETY FUNCTION INTEGRITY IN CASE OF STEAM LINE BREAK ACCIDENT FOR VVER 1000/V320 International Conference 12th Symposium of AER, Sunny Beach, pp.99-105, 22-28 September, 2002. INVESTIGATION OF CRITICAL SAFETY FUNCTION INTEGRITY IN CASE OF STEAM LINE BREAK ACCIDENT FOR VVER 1000/V320

More information

Randy Lockwood, Senior Vice President CMD 18-H6.1A. PICKERING NUCLEAR GENERATING STATION Part I Hearing Licence Renewal April 4, 2018

Randy Lockwood, Senior Vice President CMD 18-H6.1A. PICKERING NUCLEAR GENERATING STATION Part I Hearing Licence Renewal April 4, 2018 Randy Lockwood, Senior Vice President CMD 18-H6.1A PICKERING NUCLEAR GENERATING STATION Part I Hearing Licence Renewal April 4, 2018 Presentation Outline Opening Remarks Performance Highlights Our Request

More information

Guidance on the Use of Deterministic and Probabilistic Criteria in Decision-making for Class I Nuclear Facilities

Guidance on the Use of Deterministic and Probabilistic Criteria in Decision-making for Class I Nuclear Facilities DRAFT Regulatory Document RD-152 Guidance on the Use of Deterministic and Probabilistic Criteria in Decision-making for Class I Nuclear Facilities Issued for Public Consultation May 2009 CNSC REGULATORY

More information

2017 NEC Changes for Renewable Energy Systems Session one by Christopher LaForge

2017 NEC Changes for Renewable Energy Systems Session one by Christopher LaForge 2017 NEC Changes for Renewable Energy Systems Session one 2017 by Christopher LaForge Christopher LaForge IREC Certified Master Trainer NABCEP Certified Photovoltaic Installation Professional 30 years

More information