High Energy Arcing Faults (HEAF) and Their Impact on PRA for a Nuclear Power Plant Latest International Operating Experience and Research Activities
|
|
- Marybeth Martin
- 6 years ago
- Views:
Transcription
1 High Energy Arcing Faults (HEAF) and Their Impact on PRA for a Nuclear Power Plant Latest International Operating Experience and Research Activities Marina Roewekamp GRS ggmbh, Germany Nicholas Melly, Mark Henry Salley US NRC Office of Nuclear Regulatory Research PSA 2017 International Topical Meeting on Probabilistic Safety Assessment and Analysis Pittsburgh, PA, USA, September 24-28, 2017
2 Presentation Overview Background Current HEAF PRA guidance OECD/NEA HEAF test program Methodology Test results Influence of Aluminum Test 23 Aluminum influence Test 26 Aluminum influence Aluminum Testing Conclusions HEAF operating experience Maanshan HEAF event Onagawa HEAF Event Fort Calhoun HEAF Event Conclusions 2
3 Background (1) International NPP OPEX data clearly show occurrence of a significant number of high energy arcing faults (HEAF) events worldwide 48 out of 415 fire events collected in the international NPP database up to mid-2012 represent HEAF induced fire events (over 10 %), see Clearly identified the need for imporoved methods to analyze the broad spectrum of hazards 3
4 Background (2) HEAF events often create complications impairing the plant s ability to safely shutdown the reactor and maintain it in a safe condition Electrical disturbance initiating HEAF often causes loss of essential electrical power and physical damage Large amounts of smoke provide significant challenges to the operators and fire brigade members handling the emergency In many U.S. plants, internal fire risk is can be a dominant hazard contributor HEAF-initiated scenarios are significant contributors to the overall fire risk based on a preliminary assessment of ten U.S. NFPA 805 NPPs risk assessment Fire risk contributed by HEAF initiated fire scenarios ranged from 1 % to 27 % on a unit basis Average per unit risk contribution was approximately 15 % 4
5 Current HEAF PRA Guidance There are currently 2 methods available for modeling HEAF events Electrical enclosure guidance (NUREG/CR-6850, Vol. 2, Appendix M: very limited model, largely derived from empirical evidence based one single well-documented HEAF event at SONGS, Unit 3, in February 2001 Bus duct HEAF events (NUREG/CR-6850, Supplement 1, Section 7) Both methods employ a one size fits all zone of influence (ZOI) methodology prescribing a damage zone around an initiating component ZOIs prescribe damage to potentially vulnerable electrical or electromechanical components nearby (cables, transformers, etc.) International OECD/NEA experimental HEAF Project was initiated to take an exploratory, scientific approach in an attempt to better understand HEAF phenomena and produce data to better inform fire modeling techniques 5
6 OECD/NEA HEAF Test Program (1) Purpose and objectives Perform experiments to obtain scientific data on HEAF phenomena Test methodology 26 full scale experiments HEAF events exhibit two major damage phases: 1. Short, rapid release of electrical energy o o Catastrophic failure of the electrical enclosure Ejection of hot projectiles and/or fire(s) o Damage to overhead cable trays or nearby panels 2. Ensuing fire o Ignition of combustible material within the HEAF zone of influence (ZOI) 6
7 OECD/NEA HEAF Test Program (2) Experimentally controlled parameters Arc location Nominal arc current Nominal arc voltage Arc duration Measurements Heat release rate (HRR) Temperature Heat flux Pressure Damage zone o Blast damage vs. enduring fire damage Extent of damage o o Thermal (i.e. ensuing fire / smoke damage) Physical ( i.e. thrown cabinet door, shrapnel) 7
8 Arc Initiation/Location Arcs generated at KEMA were initiated by means of a copper shorting wire 2.6 mm in diameter (10 AWG) as described in IEEE C HEAF events can quickly progress to three phase faults. This is evident from a number of LERs: The Kewaunee HEAF event (LER ) involved a phase-toground fault, which progressed to a phase-to-phase fault which accounted for the extensive bus damage The Prairie Island HEAF event (LER ) involved a C-phase ground arcing event, which quickly involved all phases The Zion HEAF event (LER ) states that the failure started as a single phase to ground fault which rapidly evolved into a three phase to ground fault 8
9 Arc Current /Voltage Testing was informed by OPEX and NPP configurations: Actual NPP plant equipment was used in testing Voltage, current, arc duration within the bounds observed in licensee event reports (LERs) and within ratings of the actual NPP equipment tested LERs describe numerous three-phase arc faults with failure of an upstream breaker Damage observed comports with LERs H. B. Robinson Steam Electric Plant, Unit 2; March 28, 2010 OECD HEAF, Test 20 October 13,2015 9
10 Duration OPEX indications Protective devices have not always worked as designed Incorrect breaker settings and fuse sizing due to design errors can increase the likelihood of a HEAF to occur and allow for extended HEAF duration Fault can be initiated in a location not protected by fault clearance devices, which allows for extended fault exposure times Properly implemented protection coordination, would limit arc fault duration to just a few cycles Many of HEAF events contributing to HEAF frequency involve one or more breaker malfunctions that fail to clear the fault Usually little information available on HEAF durations from OPEX KEMA s largest short-circuit generator can deliver instantaneous 2200 MVA Arc durations from 1 s to 8 s, mean value ~ 3 s, medium voltage components only 4 s All tests performed in excess of 4 s conducted at 480 V 10
11 Test Results Key observations Experiments involving Aluminum as a component of the electrical device resulted in more severe physical damage to equipment than those containing only copper and steel o Reactions were so violent that measurement devices were damaged r maximum measuring range was exceeded One of the most severe electrical enclosure damage was observed as result of low voltage (480 V) HEAF in enclosure with aluminum bus bars Increased duration arcing events were more likely to create an ensuing fire HEAF events involving Aluminum were seen to produce conductive product of combustion in the smoke coating test facility causing short circuits and unintended current paths in electrical systems All medium voltage enclosures, > 4.16 kv, maintained arc for > 2 s Large variability in 480 V enclosures for creating sustained arcing event; variables important to sustaining an arc at low voltages were enclosure configuration and design, and bus bar material (e.g., Aluminum vs. Copper) Experiments with arc durations less than 2 s did not result in ensuing fires 11
12 Influence of Aluminum Aluminium material impact Potentially much larger ZOI Potentially greater likelihood of maintaining arcing at low voltage levels Higher risk of fire propagation Testing indications: Introducing Aluminum into arcing fault events significantly larger energy release than expected Sources of Aluminum can include components that form parts o of the normal current carrying pathway or o of the current pathway as a result of a ground fault 12
13 Test 23 Aluminum Influence Low voltage 480 V AC switchgear cabinet utilizing Aluminum bus bar Failure of cabinet walls such that the plasma wave front created by the arcing fault was expelled out of the cabinet a significant distance of several feet Melting and destruction of the Inconel temperature sensors located 1m (3 ft.) from enclosure Conductive Aluminum byproducts coating facility after testing o Shorting out equipment and causing damage to electrical circuits All other low voltage tests (without Aluminum): Temperature sensors not damaged Minimal electrical enclosure breach 13
14 Test 26 Aluminum Influence Bus duct section removed from the 4.16 kv switchgear room of a decommissioned US NPP consisting of segmented (non-segregated) copper bus bars enclosed within aluminum bus duct housing Arc initiated on the copper conductors and progressed to the grounded aluminum bus duct housing as it became involved in the arc path Hot gas mixture and arc jetted out of the bus duct, distributing hot gas/molten metal linearly from the bus duct opening 1.50 in. copper bus bar material and 7 in. aluminum enclosure material were vaporized OPEX shows this same phenomena (e.g., Diablo Canyon NPP bus duct fire in May 2000) 14
15 Aluminum Testing Conclusions Physical damage to test specimens, measurement devices, and testing facility in Test 23 and Test 26 was attributed to presence of Aluminum Presence of Aluminum caused a more energetic plasma development when consumed during the arcing process HEAFs can produce temperatures of 19,426 C (35,000 F) It appears that Aluminum is igniting and contributing to the energy released Test results significantly exceeded expected ZOI postulated in current Fire PRA guidance New, previously unidentified failure mechanism: Conductive Aluminum byproduct coating enclosure environment caused short circuits and unintended current paths in electrical systems Scale of that impact was unexpected and is an area that warrants further investigation 15
16 HEAF Operating Experience - Maanshan HEAF Event HEAF event and subsequent loss of external and internal power supply at Taiwanese 2 unit PWR plant on March 18, 2001 Salt deposit on insulators due to foggy weather caused instability of 345 kv high voltage grid leading to HEAF Breaker opened the connection to the 161 kv external supply During switch to the 345 kv grid, short circuit and HEAF occurred in 4 kv power switch of one redundancy emergency power lines causing a cable fire 2 emergency diesels of Unit 1 were unable to provide power to both essential buses After > 2 h, the so-called swing emergency diesel generator, which can provide power to either one of the units, was successfully connected to Unit 1 16
17 HEAF Operating Experience - Onagawa HEAF Event Tohoku district earthquake caused arcing fault in 2 (No. 7 and No. 8) of 10 enclosures of the non-emergency M/C switchgear cabinets of the Onagawa NPP in Japan on March 11, 2011 Affected cabinet was installed in the underground floor of the turbine building Arcing started at high voltage electric component (6.9 kv M/C) initiated by short to ground Heat due to arcing resulted in ensuing fire inside cabinet affecting all 10 sections of enclosure lineup Control cables for non-emergency components directly above cabinet were affected by heat generated by the fire Fire caused trip of over-current relay start-up transformer causing loss of offsite power in combination with switching over of power supply system and loss of auxiliary transformer 17
18 HEAF Operating Experience Fort Calhoun HEAF Event Switchgear fire occurred at Fort Calhoun NPP on June 7, 2011, while the plant was shut down for planned refueling outage Fire was caused by the catastrophic failure of the feeder breaker for 480 V AC load center with aluminum present Fire resulted in loss of power to 6 of 9 safety related 480 V AC electrical distribution buses and 2 of 4 safety related 4160 V AC buses Event resulted in the loss of the spent fuel pool cooling Combustion products caused fault across open bus-tie breaker on an island bus Feeder breaker tripped unexpectedly resulting in loss of power to opposite train bus resulting in grounds on both trains of safety related direct current power used for breaker operation and electrical protection Large quantity of soot and smoke migrated into non-segregated bus duct connecting island buses causing arcing Maximum conditional CDP: 3.4 x 10-4 at the time of the fire 18
19 Conclusions HEAF-initiated scenarios contribute significantly to fire risk OPEX shows: HEAFs continue to occur, despite the extensive electrical protection against such fire-initiated scenarios built into the plant design Significant complications to shutting down the plant can occur during and after a HEAF HEAF events generate large quantities of dense smoke, cause significant equipment damage, and challenge operators with scenarios unlikely to have been trained on OECD HEAF testing program identified a potential issue where existing regulations, guidance, and analytical models used for PRA applications may not bound the hazard if aluminum is present Severity and risk impact of these events and consequences highlight need for greater understanding of the underlying phenomena and treatment of HEAF events 19
20 Information Notice (IN) 2017-XX High Energy Arc Faults in Electrical Equipment Containing Aluminum Components OECD/NEA international test program insights 6 U.S. operating experience events involving aluminum components Plant Date Fort Calhoun June 7, 2011 Columbia August 5, 2009 Diablo Canyon May 15, 2000 Zion April 3, 1994 Shearon Harris October 9, 1989 Kewaunee July 10, 1987 Issued August 21,
21 PIRT & HEAF Phase 2 Testing HEAF Phase 2 testing to be conducted as an OECD/NEA International Project with more focused objectives International Phenomena Identification and Ranking Table (PIRT) exercise held in February 2017 Early PIRT Insights: Aluminum oxidation and byproducts Pressure effects Target characterization and sensitivity Mitigating factors ( HEAF shields ) PIRT NUREG to be issued in Summer 2017 OECD/NEA HEAF Phase 2 Test Program currently under development 21
22 Thank you for your attention! 22
POTOMAC ELECTRIC POWER COMPANY
POTOMAC ELECTRIC POWER COMPANY FERC Form 715 (Part 4) - Transmission Planning Study Guidelines Transmission Reliability Guidelines 1. General Overview The reliability guidelines used to plan the transmission
More informationPower Generation. Ronaldo Jenkins Electrical Engineering Branch Chief Office of New Reactors (NRO)
Power Generation Ronaldo Jenkins Electrical Engineering Branch Chief Office of New Reactors (NRO) Agenda Overview Design Considerations 10 Code of Federal Regulations (CFR) 50 10 CFR 50, General Design
More informationDOWNTOWN UNDERGROUND NETWORK SECONDARY SERVICES GUIDELINES
Guidelines effective March 5, 2007 NES is committed to providing safe, reliable electric service at a reasonable price for all of our customers. These guidelines offer direction for activities relating
More informationTitle: YALE OFFICE OF FACILITIES PROCEDURE MANUAL Chapter: 01 - Yale Design Standard Division: Electrical Standards
Date Description of Change Pages / Sections Modified ID 6/15/16 Updated format, division title, and removed references to other sections. - mgl44 A. Summary This section contains design criteria for the
More informationELECTRICAL BULLETIN
PO Box 697 Halifax, Nova Scotia B3J 2T8 ELECTRICAL BULLETIN 2015-01 From: David MacLeod, C.E.I., P.Eng. Pg. 1 of 7 Provincial Chief Electrical Inspector Date: March 10, 2015 Subject: Adoption of the 2015
More informationGUIDELINES FOR REGULATORY REVIEW OF EOPs AND SAMGs
GUIDELINES FOR REGULATORY REVIEW OF EOPs AND SAMGs CNCAN, ROMANIA 2016 1 TABLE OF CONTENTS 1. INTRODUCTION 1.1. Background 1.2. Purpose and scope of the guidelines 1.3. Structure of the guidelines 1.4.
More informationCONSOLIDATED EDISON COMPANY OF NEW YORK, INC Van Dam Street Long Island City, NY ELECTRIC METER SHOP DEPARTMENT
CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 48-05 Van Dam Street Long Island City, NY 11101 ELECTRIC METER SHOP DEPARTMENT METER ENGINEERING SPECIFICATION MES-350 REVISION 3 June 2016 EFFECTIVE DATE
More informationTelecommunication Spaces
Telecommunication Spaces October 19, 2016 Page 1 Revision History Telecommunication Spaces Standard Effective Date Email Version Contact Phone OIT-TS strevena@csustan.edu 1.0 Stan Trevena 209.667.3137
More informationSAFETY GUIDES. Deterministic Safety Assessment РР - 5/2010 ÀÃÅÍÖÈß ÇÀ ßÄÐÅÍÎ ÐÅÃÓËÈÐÀÍÅ BULGARIAN NUCLEAR REGULATORY AGENCY
S ON IMPLEMENTATION OF THE LEGAL REQUIREMENTS Deterministic Safety Assessment РР - 5/2010 ÀÃÅÍÖÈß ÇÀ ßÄÐÅÍÎ ÐÅÃÓËÈÐÀÍÅ BULGARIAN NUCLEAR REGULATORY AGENCY TABLE OF CONTENTS 1. GENERAL PROVISIONS...2 LEGAL
More informationAP1000 European 19. Probabilistic Risk Assessment Design Control Document
19.39 In-Vessel Retention of Molten Core Debris 19.39.1 Introduction In-vessel retention of molten core debris through water cooling of the external surface of the reactor vessel is a severe accident management
More informationRisks Associated with Shutdown in PWRs
International Conference Nuclear Option in Countries with Small and Mi Opatija, Croatia, 1996 Risks Associated with Shutdown in PWRs Igor Grlicarev Slovenian Nuclear Safety Administration Vojkova 59, 1113
More informationPost-Fukushima Assessment of the AP1000 Plant
ABSTRACT Post-Fukushima Assessment of the AP1000 Plant Ernesto Boronat de Ferrater Westinghouse Electric Company, LLC Padilla 17-3 Planta 28006, Madrid, Spain boronae@westinghouse.com Bryan N. Friedman,
More informationELECTRICAL BULLETIN
PO Box 697 Halifax, Nova Scotia B3J 2T8 Labour and Advanced Education ELECTRICAL BULLETIN 2012-01 From: David MacLeod,C.E.I.,P.Eng. Pg 1 of 8 Provincial Chief Electrical Inspector Date : March 1, 2012
More informationFEMA P-1019 Emergency Power Systems for Critical Facilities. ASFPM May 4, 2017 David K Low, PE DK Low & Associates
FEMA P-1019 Emergency Power Systems for Critical Facilities ASFPM May 4, 2017 David K Low, PE DK Low & Associates FEMA P-1019 FEMA P-1019 A critical facility that is fully compliant with the minimum building
More informationThe Westinghouse Advanced Passive Pressurized Water Reactor, AP1000 TM. Roger Schène Director,Engineering Services
The Westinghouse Advanced Passive Pressurized Water Reactor, AP1000 TM Roger Schène Director,Engineering Services 1 Background Late 80: USA Utilities under direction of EPRI and endorsed by NRC : Advanced
More informationCLASSIFICATION OF SYSTEMS, STRUCTURES AND COMPONENTS OF A NUCLEAR FACILITY
CLASSIFICATION OF SYSTEMS, STRUCTURES AND COMPONENTS OF A NUCLEAR FACILITY 1 Introduction 3 2 Scope of application 3 3 Classification requirements 3 3.1 Principles of safety classification 3 3.2 Classification
More informationReactor Technology: Materials, Fuel and Safety. Dr. Tony Williams
Reactor Technology: Materials, Fuel and Safety Dr. Tony Williams Course Structure Unit 1: Reactor materials Unit 2. Reactor types Unit 3: Health physics, Dosimetry Unit 4: Reactor safety Unit 5: Nuclear
More informationRegulatory Guide Monitoring the Effectiveness of Maintenance at Nuclear Power Plants
Regulatory Guide 1.160 Revision 2 Page 1 of 14 Revision 2 March 1997 Regulatory Guide 1.160 Monitoring the Effectiveness of Maintenance at Nuclear Power Plants Publication Information (Draft issued as
More informationLow Voltage Switchgear Construction Checklist (under 500 kva)
Low Voltage Switchgear Checklist (under 500 kva) Project: Building: Location: Submittal / Approvals Submittal. The above equipment and systems integral to them are complete and ready for functional testing.
More information2008 NEC Guide Lines for Home Owner Doing Electrical Work on their Property
2008 NEC Guide Lines for Home Owner Doing Electrical Work on their Property A brief summary of the most used code references for residential wiring State of Idaho Division of Building Safety Electrical
More informationWGRISK Site-Level Project: Status update and Preliminary insights for the Risk Aggregation focus area
WGRISK Site-Level Project: Status update and Preliminary insights for the Risk Aggregation focus area S. Yalaoui, Y. Akl (CNSC, Canada), D. Hudson (US NRC), and M. Roewekamp (GRS, Germany) PSA 2017 Pittsburgh,
More informationCHAPTER 5 METERING REQUIREMENTS
CHAPTER 5 METERING REQUIREMENTS CHAPTER 5 METERING REQUIREMENTS 5.1 General 1. All installations connected to, or intended to be connected to HK Electric s supply of electricity must comply with HK Electric
More informationAnalysis of distribution system reliability and outage rates
Reclosers Technical Data TD280026EN Supersedes pril 2003 (R280-90-7) COOPER POWER SERIES nalysis of distribution system reliability and outage rates Recloser Technical Data TD280026EN nalysis of distribution
More informationMarch 16, Mr. William M. Dean Director, Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, DC
ANTHONY R. PIETRANGELO Senior Vice President and Chief Nuclear Officer 1201 F Street, NW, Suite 1100 Washington, DC 20004 P: 202.739.8081 arp@nei.org nei.org March 16, 2015 Mr. William M. Dean Director,
More informationZion Project Overview S. Chris Baker VP EH&S
Zion Project Overview S. Chris Baker VP EH&S 1 Agenda Asset Sale Agreement Organization Nuclear Decommissioning Process Overview of Zion Station Decommissioning Schedule Near Term Activities Spent Fuel
More informationEnvironmental Qualification of
Environmental Qualification of Safety Related Electrical Equipment for Nuclear Power Plants Gary W Castleberry PE PMP Gary W. Castleberry 1 of 63 Learning Modules 1. What is Environmental Qualification
More informationStandard TPL Transmission System Planning Performance Requirements
A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon
More informationB. Accept materials on site in original factory packaging, labeled with manufacturer s identification.
SECTION 26 05 02 - BASIC ELECTRICAL REQUIREMENTS PART 1 - GENERAL 1.1 SUMMARY A. Work Included: Furnish all labor, material, services and skilled supervision necessary for the construction, erection, installation,
More informationEnhancement of Nuclear Safety
Enhancement of Nuclear Safety Soon Heung Chang Handong Global University May 6, 2015 Contents 1 2 3 4 Importance of Energy Fundamentals of Nuclear Safety How to Enhance Nuclear Safety Closing Remarks 2
More informationELECTRIC METERING GENERAL
1.0 INDEX 1.0 INDEX 2.0 SCOPE 3.0 GENERAL REQUIREMENTS 4.0 EQUIPMENT 5.0 METER REQUIREMENTS 6.0 METER FACILITIES 7.0 ELECTRICAL CONNECTIONS 2.0 SCOPE This guide covers general requirements and codes for
More informationFor the 2008 Code, the minimum clear distances were revised to reflect an accurate metric conversion (also known as a soft conversion).
II. 600 Volts, Nominal, or Less 110.26 Spaces About Electrical Equipment. Sufficient access and working space shall be provided and maintained about all electrical equipment to permit ready and safe operation
More informationSECTION 16496A MTS MANUAL TRANSFER SWITCH (MANUAL CONTROL ONLY) Note to Spec Writer: { } Denotes EATON Feature reference number
MTS MANUAL TRANSFER SWITCH (MANUAL CONTROL ONLY) Note to Spec Writer: { } Denotes EATON Feature reference number PART 1 GENERAL 01 02 03 04 SCOPE Furnish and install Manual Transfer Switches (MTS) and
More informationS. A. Eide (INEEL) M. B. Calley (INEEL) C. D. Gentillon (INEEL) T. Wierman (INEEL) D. Rasmuson (USNRC) D. Marksberry (USNRC) PSA 99
INEEL/CON-99-00374 PREPRINT Westinghouse Reactor Protection System Unavailability, 1984 1995 S. A. Eide (INEEL) M. B. Calley (INEEL) C. D. Gentillon (INEEL) T. Wierman (INEEL) D. Rasmuson (USNRC) D. Marksberry
More informationPROBABILISTIC RELIABILITY ASSESSMENT OF TRANSMISSION SYSTEMS
PROBABILISTIC RELIABILITY ASSESSMENT OF TRANSMISSION SYSTEMS DAWOOD ALALI Thesis submitted to Cardiff University in candidature for the degree of Doctor of Philosophy. School of Engineering Cardiff University
More informationIV. Occurrence and Development of the Accident at the Fukushima Nuclear Power Stations
IV. Occurrence and Development of the Accident at the Fukushima Nuclear Power Stations 1. Outline of Fukushima Nuclear Power Stations (1) Fukushima Daiichi Nuclear Power Station Fukushima Daiichi Nuclear
More informationDESIGN AND SAFETY PRINCIPLES LEONTI CHALOYAN DEPUTY CHIEF ENGINEER ON MODERNIZATION
DESIGN AND SAFETY PRINCIPLES LEONTI CHALOYAN DEPUTY CHIEF ENGINEER ON MODERNIZATION VIENNA OKTOBER 3-6, 2016 1 ANPP * ANPP is located in the western part of Ararat valley 30 km west of Yerevan close to
More informationGILA RIVER FIRE DEPARTMENT REQUIREMENTS
GILA RIVER FIRE DEPARTMENT REQUIREMENTS Case Number: Date: 09/07/2016 Reviewer: G. Lindenmier #0305 Project Name: Portable Generators Special Events & Use Location: WHPDA Property Applicant: Applicant
More informationProbabilistic Safety Analysis (PSA): Quality and Scope. Guideline for Swiss Nuclear Installations. ENSI-A05/e
Guideline for Swiss Nuclear Installations ENSI-A05/e Edition March 2009 Edition March 2009 Guideline for Swiss Nuclear Installations ENSI-A05/e English is not an official language of the Swiss Confederation.
More informationRESIDENTIAL BUILDING REQUIREMENTS
RESIDENTIAL BUILDING REQUIREMENTS Residential Building Requirements This is an informational booklet with some of the general residential construction requirements taken from the codes adopted by Campbell
More informationMedium Voltage UPS Solutions - When and Why? Frank Herbener, Piller Group GmbH, Germany
Medium Voltage UPS Solutions - When and Why? Frank Herbener, Piller Group GmbH, Frank.Herbener@Piller.com, Germany 1 Contents 1 Scope 3 2 Power Demand and Distribution in today s Mission Critical Applications
More informationELECTRICAL SAFETY INSPECTION REPORT
ELECTRICAL SAFETY INSPECTION REPORT ADVANCE WORLD LIMITED Lalkha Shair Char, Fatullah, Narayanganj, Dhaka, Bangladesh Factory List: 1.. Inspected by: Sherub Tenzin & Md. Moin Hasan Report Generated by:
More informationRevisions for the 2011 National Electrical Code - Part 2
PDHonline Course E356 (3 PDH) Revisions for the 2011 National Electrical Code - Part 2 Instructor: Patrick Ouillette 2012 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA 22030-6658 Phone &
More informationUFL Micro Biogas CHPs
UFL Micro Biogas CHPs The UFL Micro Biogas CHPs are based on the highly durable Petter industrial diesel engine. Low cost replacement parts are available worldwide. This range of micro biogas CHPs has
More informationFacility Interconnection Requirements
Facility Interconnection Effective 1/1/2016 1. Purpose Facility Interconnection Facility Interconnection (FAC-001-2) To avoid adverse impacts on the reliability of the Bulk Electric System (BES), RPU documents
More informationInstallation, Inspection and Maintenance of Dry Type Transformers
Dry Type TX 1 of 8 Installation, Inspection and Maintenance of Dry Type Page 1 of 8 Dry Type TX 2 of 8 Table Of Contents Page Number 1. General... 3 2. Installation... 3 3. Safety Inspections... 4 4. Safety
More informationNuclear power: OECD/NEA perspective
R&D activities underway and priority gaps and opportunities for climate resilience and preparedness Nuclear power: OECD/NEA perspective Dr. Henri PAILLERE, OECD Nuclear Energy Agency henri.paillere@oecd.org
More informationFactors Affecting Current Ratings for Underground and Air Cables
Factors Affecting Current Ratings for Underground and Air Cables S. H. Alwan, J. Jasni, M. Z. A. Ab Kadir, N. Aziz Abstract The aim of this paper is to present a parametric study to determine the major
More informationThe Canadian Electrical Code (Saskatchewan Amendments) Regulations, 1999
CANADIAN ELECTRICAL CODE 1 The Canadian Electrical Code (Saskatchewan Amendments) Regulations, 1999 Repealed by Chapter E-6.3 Reg 8 (effective June 24, 2003). Formerly Chapter E-6.3 Reg 6 (effective March
More informationEnsuring Spent Fuel Pool Safety
Ensuring Spent Fuel Pool Safety Michael Weber Deputy Executive Director for Operations U.S. Nuclear Regulatory Commission American Nuclear Society Meeting June 28, 2011 1 Insights from Fukushima Nuclear
More informationB. Provide liquid-filled secondary substation transformers as indicated on drawings.
SECTION 26 12 13 PART 1 - GENERAL 1.01 WORK INCLUDED A. Comply with the provisions of Sections 26 05 00. B. Provide liquid-filled secondary substation transformers as indicated on drawings. 1.02 RELATED
More informationWestinghouse Small Modular Reactor. Passive Safety System Response to Postulated Events
Westinghouse Small Modular Reactor Passive Safety System Response to Postulated Events Matthew C. Smith Dr. Richard F. Wright Westinghouse Electric Company Westinghouse Electric Company 600 Cranberry Woods
More informationSECTION GROUNDING AND BONDING
SECTION 16060 PART 1 GENERAL 1.01 DESCRIPTION A. Section includes requirements for an electrical grounding system, including electrodes, grounding rods, connectors, insulators, equipment grounding and
More informationControlled management of a severe accident
July 2015 Considerations concerning the strategy of corium retention in the reactor vessel Foreword Third-generation nuclear reactors are characterised by consideration during design of core meltdown accidents.
More informationSteam Power Station (Thermal Station)
Steam Power Station (Thermal Station) A generating station which converts heat energy into electrical energy through turning water into heated steam is known as a steam power station. A steam power station
More informationCommunications Page 1 of 9
Page 1 of 9 Last Update: April 23 rd, 2014 Introduction Design In the design of Telecommunications systems in Purdue facilities, the overall consideration should be to understand and treat telecom as a
More informationElectrical Protection Methods and Devices SAMPLE. Learner Workbook Version 1. Training and Education Support Industry Skills Unit Meadowbank
Electrical Protection Methods and Devices Learner Workbook Version 1 Training and Education Support Industry Skills Unit Meadowbank Product Code: 5635 Table of Contents Introduction... 5 1. Protection
More informationOperatiOn and safety report Of MOchOvce and BOhunice v2 nuclear power plants
2016 OperatiOn and safety report Of MOchOvce and BOhunice v2 nuclear power plants The company is certified according to three management systems: Certificate stn en iso 9001:2008 Quality management system
More informationPHYSICAL FACILITIES Consultant s Handbook Division 27 COMMUNICATIONS 0000 COMMUNICATIONS
1 Introduction 1.1 In the design of Telecommunications systems in Purdue facilities, the overall consideration should be to understand and treat telecom as a utility. It should be assumed that all new
More informationResearch and Application Study on Accident-Based 3D Power Station Simulation Technology
International Conference on Electromechanical Control Technology and Transportation (ICECTT 2015) Research and Application Study on Accident-Based 3D Power Station Simulation Technology Tie Li, Xiaoming
More informationHazards. Hazards. Hazards. Effects on the Body. GA Tech Electrical Safety Presentation
Hazards The direct result can be electrocution. SHOCK. Electric shock occurs when the human body becomes part of the path through which current flows. The indirect result can be injury resulting from a
More informationHPR1000: ADVANCED PWR WITH ACTIVE AND PASSIVE SAFETY FEATURES
HPR1000: ADVANCED PWR WITH ACTIVE AND PASSIVE SAFETY FEATURES D. SONG China Nuclear Power Engineering Co., Ltd. Beijing, China Email: songdy@cnpe.cc J. XING China Nuclear Power Engineering Co., Ltd. Beijing,
More informationNational Status on Life Management of NPPs in Finland Meeting of the IAEA TWG-LMNPP February th 2017 Vienna, Jyrki Kohopää
National Status on Life Management of NPPs in Finland 2017 Meeting of the IAEA TWG-LMNPP February 22-24 th 2017 Vienna, Jyrki Kohopää NUCLEAR POWER IN FINLAND Teollisuuden Voima Oyj, Olkiluoto: OL1/2:
More informationUNDERGROUND SERVICES SECONDARY
Reference UNDERGROUND SERVICES SECONDARY Underground services secondary... U- 1 General requirements for underground service... U- 2 Name of parts for underground service... U- 3 Conduit layouts... U-
More informationTHOMAS JEFFERSON UNIVERSITY HOSPITAL STANDARD OPERATING PROCEDURE FOR THE BUILD OUT OF TELECOMMUNICATIONS ROOMS AND ASSOCIATED SPACES
THOMAS JEFFERSON UNIVERSITY HOSPITAL STANDARD OPERATING PROCEDURE FOR THE BUILD OUT OF TELECOMMUNICATIONS ROOMS AND ASSOCIATED SPACES PREPARED BYBALA CONSULTING ENGINEERS, INC FOR THOMAS JEFFERSON UNIVERSITY
More informationIntroduction to Level 2 PSA
Introduction to Level 2 PSA Dr Charles Shepherd Chief Consultant, Corporate Risk Associates CRA PSA/HFA FORUM 13-14 September 2012, Bristol Accident sequences modelled by the PSA INITIATING EVENTS SAFETY
More informationSECTION CHAIN-LINK FENCES AND GATES 02821/1
SECTION 02821 - CHAIN-LINK FENCES AND GATES 02821/1 PART 1 - GENERAL 1.1 SUMMARY A. This Section includes the following: 1. Chain-Link Fences: 2. Gates: horizontal slide or swing. 3. Fences installed where
More informationBasic Requirements for Residential Electrical Installations
Basic Requirements for Residential Electrical Installations Wayne County Building Department 428 West Liberty Street Wooster, Ohio 44691 Phone: 330-287-5525 Fax: 330-287-5649 This brochure is intended
More informationPublic Utility District Number 1 of Snohomish County
Public Utility District Number 1 of Snohomish County Facility Connection Requirements September 29, 2011 1 Revision History: Number Date Description Original Sept. 29, 2011 Document Origination Compilation
More informationAssessment of Electric and Magnetic Field Exposure from Power Generation for Energy UK
CRCE/NIR/5/639 Assessment of Electric and Magnetic Field Exposure from Power Generation for Energy UK N A Cridland, A J Lowe, F M Petty, N Northrop and S Jakes Commercial-in-confidence Contract Report
More informationTechnical Specification for LV ABC Fuse Switch Disconnectors
Ergon Energy Corporation Limited Technical Specification for LV ABC Fuse ETS-06-02-02 Check this is the latest Process Zone version before use. Specification ETS 06-02-02 Ver 3 Contents 1. Purpose and
More informationChapter 2 Energy Produced and Carbon Released from Fossil Fuels and the Amount of Alternative Energy Required as a Replacement
Chapter 2 Energy Produced and Carbon Released from Fossil Fuels and the Amount of Alternative Energy Required as a Replacement 2.1 Use and Production of Power and Energy from Fossil Fuels Before we embark
More informationSummary on Fukushima Related Activities in Japan
0 Keynote Presentation Summary on Fukushima Related Activities in Japan Masashi HIRANO Director-General for Regulatory Standard and Research Nuclear Regulation Authority (NRA) International Conference
More informationLong Beach July 2015 Secondary Network Outages RCE. Summary and Report
Long Beach July 2015 Secondary Network Outages RCE Summary and Report 1 P age Table of Contents Background... 3 Root Cause... 5 Chronology... 7 Immediate, Interim, and Corrective Actions... 12 Exhibit
More informationPower Zone Center. Your solution for power distribution and control systems
Power Zone Center Your solution for power distribution and control systems The Strength of One Powerful When you need to install a new power distribution center in your facility, you need it done in fastest
More informationEvaluation of CSST Gas Piping Subjected to Electrical Insult
Evaluation of CSST Gas Piping Subjected to Electrical Insult Rising Tide Consulting, LLC Brian Kraft, PE and Cutting Edge Solutions, LLC Robert Torbin, PE October 2009 The research data presented within
More informationMeetings for Sharing International Knowledge and Experience on Stress Tests
Meetings for Sharing International Knowledge and Experience on Stress Tests Presented by: Peter Hughes, Ovidiu Coman, Javier Yllera Department of Nuclear Safety and Security Division of Nuclear Installation
More informationThe Value of Customer Reliability to the Utility
The Value of Customer Reliability to the Utility Interviewing Lee Taylor, Consulting Engineer Presentation to IEEE Working Group on Distribution Reliability June 20, 2006 Montreal Canada Overview Service
More informationGalvanic and Stray Current Corrosion
Chapter 5 Galvanic and Stray Current Corrosion MElec-Ch5-1 Overview Galvanic Corrosion Understanding Galvanic Corrosion Controlling Galvanic Corrosion Stray Current Corrosion Understanding Stray Current
More informationBUSWAY LOW VOLTAGE (POW-R-WAY III) SECTION SECTION 16466
BUSWAY LOW VOLTAGE (POW-R-WAY III) PART 1 GENERAL 1.01 1.02 SCOPE The Contractor shall furnish and install the busway system including all necessary fittings, hangers and accessories as specified herein
More informationLightning Protection Practice for Large-Extended Photovoltaic Installations
202 International Conference on ightning Protection (ICP), Vienna, Austria ightning Protection Practice for arge-extended Photovoltaic Installations Dr. Nikolaos Kokkinos Research and Development Department
More informationSection ARMORED MEDIUM VOLTAGE CABLES SHIELDED 3 CONDUCTOR POWER CABLE - INTERLOCKED ARMOR
PART 1 - GENERAL Section 26 05 15 SHIELDED 3 CONDUCTOR POWER CABLE - INTERLOCKED ARMOR 1.1 Cable shall be 15 kv, shielded, three conductor with ground, stranded copper, with continuously welded and corrugated
More informationGenerator Assessment & Roles During A Restoration
Generator Assessment & Roles During A Restoration PJM State & Member Training Dept. PJM 2015 Objectives Students will be able to: Identify the process and requirements for operating during system restoration
More informationCompact Substation Design. Kobus Coetzer TGOOD Africa
Compact Substation Design Kobus Coetzer TGOOD Africa 1. 2. 3. 4. TGOOD Electric Compact Substation Design Considerations Project Reference Agenda 1. TGOOD Electric Key Facts Sino German Joint Venture Leading
More informationTop Five Reasons to Implement Distributed Bus Protection
GE Grid Solutions Top Five Reasons to Implement Distributed Bus Protection White Paper Author: JC Theron g imagination at work 1. Abstract Power systems have evolved in the past few decades due to factors
More informationUNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C SAFETY EVALUATION REPORT
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 SAFETY EVALUATION REPORT Docket No. 72-1040 HI-STORM UMAX Canister Storage System Holtec International, Inc. Certificate of Compliance
More informationEuropean level recommendations Sect. in NAcP 2 Generic recommendation for WENRA, Finland participates and follows the work.
Cross reference table of ENSREG and Extraordinary CNS recommendations and national actions 1(16) 2.1 European guidance on assessment of natural hazards and margins The peer review Board recommends that
More information(Condensed from National Electric Code)
WIRING, SPECIFICATIONS, INSPECTION, AND METER INSTALLATION PROCEDURES FOR RESIDENTIAL CUSTOMERS SERVED BY SOUTHWEST ARKANSAS ELECTRIC COOPERATIVE CORPORATION Effective April 1, 1974 Revised February 3,
More informationPressurized Thermal Shock Potential at Palisades
Pressurized Thermal Shock Potential at Palisades Prepared by Michael J. Keegan Coalition for a Nuclear Free Great Lakes (July 8, 1993, Rekeyed August 3, 2005) History of Embrittlement of Reactor Pressure
More informationRESULTS OF THE GRADUAL UPGRADING AT BOHUNICE WWER - 440/230 NPP
RESULTS OF THE GRADUAL UPGRADING AT BOHUNICE WWER - 440/230 NPP P. Krupa Ingeneer, e-mail: Krupa_Peter@ebo.seas.sk Bohunice NPPs Introduction The centre of upgrading activities in VVER NPP is clearly in
More informationACS OTHER PRIMARY EQUIPMENT
ACS OTHER PRIMARY EQUIPMENT Fleet Strategy Document 31/10/2013 Transpower New Zealand Limited 2013. All rights reserved. Page 1 of 70 C O P Y R I G H T 2013 T R A N S P O W E R N E W Z E A L A N D L I
More informationDEVELOPMENT AND APPLICATION OF PROBABILISTIC SAFETY ASSESSMENT PSA IN DAYA BAY NUCLEAR POWER STATION
18th International Conference on Structural Mechanics in Reactor Technology (SMiRT 18) Beijing, China, August 7-12, 2005 SMiRT18-A01-2 DEVELOPMENT AND APPLICATION OF PROBABILISTIC SAFETY ASSESSMENT PSA
More informationCITY OF GRANDE PRAIRIE
Inspection Services CITY OF GRANDE PRAIRIE HOMEOWNER S PERMIITS AND WIRING GUIDE FOR ELECTRICAL INSTALLATIONS 2016 INDEX Page Applying for an Electrical Permit 3 Permit Application Requirements 3 Permit
More informationAn assessment by the Radiation and Nuclear Safety Authority on the periodic safety review of Loviisa NPP
Safety assessment 1 (107) An assessment by the Radiation and Nuclear Safety Authority on the periodic safety review of Loviisa NPP Table of Contents Table of Contents... 1 1 Introduction... 4 1.1 Documents
More informationJune 7, 2012 PARTIES INTERESTED IN HVAC DUCT ENCLOSURE ASSEMBLIES
June 7, 2012 TO: PARTIES INTERESTED IN HVAC DUCT ENCLOSURE ASSEMBLIES SUBJECT: Revisions to the Acceptance Criteria for Metallic HVAC Duct Enclosure Assemblies, Subject AC179-0612-R1 (MB/CA) Dear Colleague:
More informationSubstation Bus Design: Current Methods Compared with Field Results
Electrical Transmission and Substation Structures Conference 2009 ASCE 143 Substation Bus Design: Current Methods Compared with Field Results Keith Malmedal Ph.D. P.E. P.Eng. 1 and John Wendelburg P.E.
More informationUnit Substation Transformer Construction Checklist (under 500 kva)
Unit Substation Transformer Checklist (under 500 kva) Building: Location: Submittal / Approvals Submittal. The above equipment and systems integral to them are complete and ready for functional testing.
More informationRevision 1 RAM ELEVATORS. Elevator Electrical Planning Guide. RAM Manufacturing Ltd
RAM ELEVATORS Elevator Electrical Planning Guide This guide is intended for people with an understanding of electricity. If you are not, please consult a licensed electrician as errors in application of
More information7. Electrical Facility Ratings
7. Electrical Facility Ratings 7.1 Accredited Net Generating Capacity This Section shall be used to determine the annual and seasonal accredited net generating capacity of generators in calculating the
More informationWhat Are the Qualifications to Conduct Arc Flash Studies? Where Do You Begin?
What Are the Qualifications to Conduct Arc Flash Studies? Where Do You Begin? How to compare apples-to-apples bids. By R. Dee Jones, P.E., AVO Training Institute Electrical Engineering Division Manager/Principal
More information