High Energy Arcing Faults (HEAF) and Their Impact on PRA for a Nuclear Power Plant Latest International Operating Experience and Research Activities

Size: px
Start display at page:

Download "High Energy Arcing Faults (HEAF) and Their Impact on PRA for a Nuclear Power Plant Latest International Operating Experience and Research Activities"

Transcription

1 High Energy Arcing Faults (HEAF) and Their Impact on PRA for a Nuclear Power Plant Latest International Operating Experience and Research Activities Marina Roewekamp GRS ggmbh, Germany Nicholas Melly, Mark Henry Salley US NRC Office of Nuclear Regulatory Research PSA 2017 International Topical Meeting on Probabilistic Safety Assessment and Analysis Pittsburgh, PA, USA, September 24-28, 2017

2 Presentation Overview Background Current HEAF PRA guidance OECD/NEA HEAF test program Methodology Test results Influence of Aluminum Test 23 Aluminum influence Test 26 Aluminum influence Aluminum Testing Conclusions HEAF operating experience Maanshan HEAF event Onagawa HEAF Event Fort Calhoun HEAF Event Conclusions 2

3 Background (1) International NPP OPEX data clearly show occurrence of a significant number of high energy arcing faults (HEAF) events worldwide 48 out of 415 fire events collected in the international NPP database up to mid-2012 represent HEAF induced fire events (over 10 %), see Clearly identified the need for imporoved methods to analyze the broad spectrum of hazards 3

4 Background (2) HEAF events often create complications impairing the plant s ability to safely shutdown the reactor and maintain it in a safe condition Electrical disturbance initiating HEAF often causes loss of essential electrical power and physical damage Large amounts of smoke provide significant challenges to the operators and fire brigade members handling the emergency In many U.S. plants, internal fire risk is can be a dominant hazard contributor HEAF-initiated scenarios are significant contributors to the overall fire risk based on a preliminary assessment of ten U.S. NFPA 805 NPPs risk assessment Fire risk contributed by HEAF initiated fire scenarios ranged from 1 % to 27 % on a unit basis Average per unit risk contribution was approximately 15 % 4

5 Current HEAF PRA Guidance There are currently 2 methods available for modeling HEAF events Electrical enclosure guidance (NUREG/CR-6850, Vol. 2, Appendix M: very limited model, largely derived from empirical evidence based one single well-documented HEAF event at SONGS, Unit 3, in February 2001 Bus duct HEAF events (NUREG/CR-6850, Supplement 1, Section 7) Both methods employ a one size fits all zone of influence (ZOI) methodology prescribing a damage zone around an initiating component ZOIs prescribe damage to potentially vulnerable electrical or electromechanical components nearby (cables, transformers, etc.) International OECD/NEA experimental HEAF Project was initiated to take an exploratory, scientific approach in an attempt to better understand HEAF phenomena and produce data to better inform fire modeling techniques 5

6 OECD/NEA HEAF Test Program (1) Purpose and objectives Perform experiments to obtain scientific data on HEAF phenomena Test methodology 26 full scale experiments HEAF events exhibit two major damage phases: 1. Short, rapid release of electrical energy o o Catastrophic failure of the electrical enclosure Ejection of hot projectiles and/or fire(s) o Damage to overhead cable trays or nearby panels 2. Ensuing fire o Ignition of combustible material within the HEAF zone of influence (ZOI) 6

7 OECD/NEA HEAF Test Program (2) Experimentally controlled parameters Arc location Nominal arc current Nominal arc voltage Arc duration Measurements Heat release rate (HRR) Temperature Heat flux Pressure Damage zone o Blast damage vs. enduring fire damage Extent of damage o o Thermal (i.e. ensuing fire / smoke damage) Physical ( i.e. thrown cabinet door, shrapnel) 7

8 Arc Initiation/Location Arcs generated at KEMA were initiated by means of a copper shorting wire 2.6 mm in diameter (10 AWG) as described in IEEE C HEAF events can quickly progress to three phase faults. This is evident from a number of LERs: The Kewaunee HEAF event (LER ) involved a phase-toground fault, which progressed to a phase-to-phase fault which accounted for the extensive bus damage The Prairie Island HEAF event (LER ) involved a C-phase ground arcing event, which quickly involved all phases The Zion HEAF event (LER ) states that the failure started as a single phase to ground fault which rapidly evolved into a three phase to ground fault 8

9 Arc Current /Voltage Testing was informed by OPEX and NPP configurations: Actual NPP plant equipment was used in testing Voltage, current, arc duration within the bounds observed in licensee event reports (LERs) and within ratings of the actual NPP equipment tested LERs describe numerous three-phase arc faults with failure of an upstream breaker Damage observed comports with LERs H. B. Robinson Steam Electric Plant, Unit 2; March 28, 2010 OECD HEAF, Test 20 October 13,2015 9

10 Duration OPEX indications Protective devices have not always worked as designed Incorrect breaker settings and fuse sizing due to design errors can increase the likelihood of a HEAF to occur and allow for extended HEAF duration Fault can be initiated in a location not protected by fault clearance devices, which allows for extended fault exposure times Properly implemented protection coordination, would limit arc fault duration to just a few cycles Many of HEAF events contributing to HEAF frequency involve one or more breaker malfunctions that fail to clear the fault Usually little information available on HEAF durations from OPEX KEMA s largest short-circuit generator can deliver instantaneous 2200 MVA Arc durations from 1 s to 8 s, mean value ~ 3 s, medium voltage components only 4 s All tests performed in excess of 4 s conducted at 480 V 10

11 Test Results Key observations Experiments involving Aluminum as a component of the electrical device resulted in more severe physical damage to equipment than those containing only copper and steel o Reactions were so violent that measurement devices were damaged r maximum measuring range was exceeded One of the most severe electrical enclosure damage was observed as result of low voltage (480 V) HEAF in enclosure with aluminum bus bars Increased duration arcing events were more likely to create an ensuing fire HEAF events involving Aluminum were seen to produce conductive product of combustion in the smoke coating test facility causing short circuits and unintended current paths in electrical systems All medium voltage enclosures, > 4.16 kv, maintained arc for > 2 s Large variability in 480 V enclosures for creating sustained arcing event; variables important to sustaining an arc at low voltages were enclosure configuration and design, and bus bar material (e.g., Aluminum vs. Copper) Experiments with arc durations less than 2 s did not result in ensuing fires 11

12 Influence of Aluminum Aluminium material impact Potentially much larger ZOI Potentially greater likelihood of maintaining arcing at low voltage levels Higher risk of fire propagation Testing indications: Introducing Aluminum into arcing fault events significantly larger energy release than expected Sources of Aluminum can include components that form parts o of the normal current carrying pathway or o of the current pathway as a result of a ground fault 12

13 Test 23 Aluminum Influence Low voltage 480 V AC switchgear cabinet utilizing Aluminum bus bar Failure of cabinet walls such that the plasma wave front created by the arcing fault was expelled out of the cabinet a significant distance of several feet Melting and destruction of the Inconel temperature sensors located 1m (3 ft.) from enclosure Conductive Aluminum byproducts coating facility after testing o Shorting out equipment and causing damage to electrical circuits All other low voltage tests (without Aluminum): Temperature sensors not damaged Minimal electrical enclosure breach 13

14 Test 26 Aluminum Influence Bus duct section removed from the 4.16 kv switchgear room of a decommissioned US NPP consisting of segmented (non-segregated) copper bus bars enclosed within aluminum bus duct housing Arc initiated on the copper conductors and progressed to the grounded aluminum bus duct housing as it became involved in the arc path Hot gas mixture and arc jetted out of the bus duct, distributing hot gas/molten metal linearly from the bus duct opening 1.50 in. copper bus bar material and 7 in. aluminum enclosure material were vaporized OPEX shows this same phenomena (e.g., Diablo Canyon NPP bus duct fire in May 2000) 14

15 Aluminum Testing Conclusions Physical damage to test specimens, measurement devices, and testing facility in Test 23 and Test 26 was attributed to presence of Aluminum Presence of Aluminum caused a more energetic plasma development when consumed during the arcing process HEAFs can produce temperatures of 19,426 C (35,000 F) It appears that Aluminum is igniting and contributing to the energy released Test results significantly exceeded expected ZOI postulated in current Fire PRA guidance New, previously unidentified failure mechanism: Conductive Aluminum byproduct coating enclosure environment caused short circuits and unintended current paths in electrical systems Scale of that impact was unexpected and is an area that warrants further investigation 15

16 HEAF Operating Experience - Maanshan HEAF Event HEAF event and subsequent loss of external and internal power supply at Taiwanese 2 unit PWR plant on March 18, 2001 Salt deposit on insulators due to foggy weather caused instability of 345 kv high voltage grid leading to HEAF Breaker opened the connection to the 161 kv external supply During switch to the 345 kv grid, short circuit and HEAF occurred in 4 kv power switch of one redundancy emergency power lines causing a cable fire 2 emergency diesels of Unit 1 were unable to provide power to both essential buses After > 2 h, the so-called swing emergency diesel generator, which can provide power to either one of the units, was successfully connected to Unit 1 16

17 HEAF Operating Experience - Onagawa HEAF Event Tohoku district earthquake caused arcing fault in 2 (No. 7 and No. 8) of 10 enclosures of the non-emergency M/C switchgear cabinets of the Onagawa NPP in Japan on March 11, 2011 Affected cabinet was installed in the underground floor of the turbine building Arcing started at high voltage electric component (6.9 kv M/C) initiated by short to ground Heat due to arcing resulted in ensuing fire inside cabinet affecting all 10 sections of enclosure lineup Control cables for non-emergency components directly above cabinet were affected by heat generated by the fire Fire caused trip of over-current relay start-up transformer causing loss of offsite power in combination with switching over of power supply system and loss of auxiliary transformer 17

18 HEAF Operating Experience Fort Calhoun HEAF Event Switchgear fire occurred at Fort Calhoun NPP on June 7, 2011, while the plant was shut down for planned refueling outage Fire was caused by the catastrophic failure of the feeder breaker for 480 V AC load center with aluminum present Fire resulted in loss of power to 6 of 9 safety related 480 V AC electrical distribution buses and 2 of 4 safety related 4160 V AC buses Event resulted in the loss of the spent fuel pool cooling Combustion products caused fault across open bus-tie breaker on an island bus Feeder breaker tripped unexpectedly resulting in loss of power to opposite train bus resulting in grounds on both trains of safety related direct current power used for breaker operation and electrical protection Large quantity of soot and smoke migrated into non-segregated bus duct connecting island buses causing arcing Maximum conditional CDP: 3.4 x 10-4 at the time of the fire 18

19 Conclusions HEAF-initiated scenarios contribute significantly to fire risk OPEX shows: HEAFs continue to occur, despite the extensive electrical protection against such fire-initiated scenarios built into the plant design Significant complications to shutting down the plant can occur during and after a HEAF HEAF events generate large quantities of dense smoke, cause significant equipment damage, and challenge operators with scenarios unlikely to have been trained on OECD HEAF testing program identified a potential issue where existing regulations, guidance, and analytical models used for PRA applications may not bound the hazard if aluminum is present Severity and risk impact of these events and consequences highlight need for greater understanding of the underlying phenomena and treatment of HEAF events 19

20 Information Notice (IN) 2017-XX High Energy Arc Faults in Electrical Equipment Containing Aluminum Components OECD/NEA international test program insights 6 U.S. operating experience events involving aluminum components Plant Date Fort Calhoun June 7, 2011 Columbia August 5, 2009 Diablo Canyon May 15, 2000 Zion April 3, 1994 Shearon Harris October 9, 1989 Kewaunee July 10, 1987 Issued August 21,

21 PIRT & HEAF Phase 2 Testing HEAF Phase 2 testing to be conducted as an OECD/NEA International Project with more focused objectives International Phenomena Identification and Ranking Table (PIRT) exercise held in February 2017 Early PIRT Insights: Aluminum oxidation and byproducts Pressure effects Target characterization and sensitivity Mitigating factors ( HEAF shields ) PIRT NUREG to be issued in Summer 2017 OECD/NEA HEAF Phase 2 Test Program currently under development 21

22 Thank you for your attention! 22

POTOMAC ELECTRIC POWER COMPANY

POTOMAC ELECTRIC POWER COMPANY POTOMAC ELECTRIC POWER COMPANY FERC Form 715 (Part 4) - Transmission Planning Study Guidelines Transmission Reliability Guidelines 1. General Overview The reliability guidelines used to plan the transmission

More information

Power Generation. Ronaldo Jenkins Electrical Engineering Branch Chief Office of New Reactors (NRO)

Power Generation. Ronaldo Jenkins Electrical Engineering Branch Chief Office of New Reactors (NRO) Power Generation Ronaldo Jenkins Electrical Engineering Branch Chief Office of New Reactors (NRO) Agenda Overview Design Considerations 10 Code of Federal Regulations (CFR) 50 10 CFR 50, General Design

More information

DOWNTOWN UNDERGROUND NETWORK SECONDARY SERVICES GUIDELINES

DOWNTOWN UNDERGROUND NETWORK SECONDARY SERVICES GUIDELINES Guidelines effective March 5, 2007 NES is committed to providing safe, reliable electric service at a reasonable price for all of our customers. These guidelines offer direction for activities relating

More information

Title: YALE OFFICE OF FACILITIES PROCEDURE MANUAL Chapter: 01 - Yale Design Standard Division: Electrical Standards

Title: YALE OFFICE OF FACILITIES PROCEDURE MANUAL Chapter: 01 - Yale Design Standard Division: Electrical Standards Date Description of Change Pages / Sections Modified ID 6/15/16 Updated format, division title, and removed references to other sections. - mgl44 A. Summary This section contains design criteria for the

More information

ELECTRICAL BULLETIN

ELECTRICAL BULLETIN PO Box 697 Halifax, Nova Scotia B3J 2T8 ELECTRICAL BULLETIN 2015-01 From: David MacLeod, C.E.I., P.Eng. Pg. 1 of 7 Provincial Chief Electrical Inspector Date: March 10, 2015 Subject: Adoption of the 2015

More information

GUIDELINES FOR REGULATORY REVIEW OF EOPs AND SAMGs

GUIDELINES FOR REGULATORY REVIEW OF EOPs AND SAMGs GUIDELINES FOR REGULATORY REVIEW OF EOPs AND SAMGs CNCAN, ROMANIA 2016 1 TABLE OF CONTENTS 1. INTRODUCTION 1.1. Background 1.2. Purpose and scope of the guidelines 1.3. Structure of the guidelines 1.4.

More information

CONSOLIDATED EDISON COMPANY OF NEW YORK, INC Van Dam Street Long Island City, NY ELECTRIC METER SHOP DEPARTMENT

CONSOLIDATED EDISON COMPANY OF NEW YORK, INC Van Dam Street Long Island City, NY ELECTRIC METER SHOP DEPARTMENT CONSOLIDATED EDISON COMPANY OF NEW YORK, INC. 48-05 Van Dam Street Long Island City, NY 11101 ELECTRIC METER SHOP DEPARTMENT METER ENGINEERING SPECIFICATION MES-350 REVISION 3 June 2016 EFFECTIVE DATE

More information

Telecommunication Spaces

Telecommunication Spaces Telecommunication Spaces October 19, 2016 Page 1 Revision History Telecommunication Spaces Standard Effective Date Email Version Contact Phone OIT-TS strevena@csustan.edu 1.0 Stan Trevena 209.667.3137

More information

SAFETY GUIDES. Deterministic Safety Assessment РР - 5/2010 ÀÃÅÍÖÈß ÇÀ ßÄÐÅÍÎ ÐÅÃÓËÈÐÀÍÅ BULGARIAN NUCLEAR REGULATORY AGENCY

SAFETY GUIDES. Deterministic Safety Assessment РР - 5/2010 ÀÃÅÍÖÈß ÇÀ ßÄÐÅÍÎ ÐÅÃÓËÈÐÀÍÅ BULGARIAN NUCLEAR REGULATORY AGENCY S ON IMPLEMENTATION OF THE LEGAL REQUIREMENTS Deterministic Safety Assessment РР - 5/2010 ÀÃÅÍÖÈß ÇÀ ßÄÐÅÍÎ ÐÅÃÓËÈÐÀÍÅ BULGARIAN NUCLEAR REGULATORY AGENCY TABLE OF CONTENTS 1. GENERAL PROVISIONS...2 LEGAL

More information

AP1000 European 19. Probabilistic Risk Assessment Design Control Document

AP1000 European 19. Probabilistic Risk Assessment Design Control Document 19.39 In-Vessel Retention of Molten Core Debris 19.39.1 Introduction In-vessel retention of molten core debris through water cooling of the external surface of the reactor vessel is a severe accident management

More information

Risks Associated with Shutdown in PWRs

Risks Associated with Shutdown in PWRs International Conference Nuclear Option in Countries with Small and Mi Opatija, Croatia, 1996 Risks Associated with Shutdown in PWRs Igor Grlicarev Slovenian Nuclear Safety Administration Vojkova 59, 1113

More information

Post-Fukushima Assessment of the AP1000 Plant

Post-Fukushima Assessment of the AP1000 Plant ABSTRACT Post-Fukushima Assessment of the AP1000 Plant Ernesto Boronat de Ferrater Westinghouse Electric Company, LLC Padilla 17-3 Planta 28006, Madrid, Spain boronae@westinghouse.com Bryan N. Friedman,

More information

ELECTRICAL BULLETIN

ELECTRICAL BULLETIN PO Box 697 Halifax, Nova Scotia B3J 2T8 Labour and Advanced Education ELECTRICAL BULLETIN 2012-01 From: David MacLeod,C.E.I.,P.Eng. Pg 1 of 8 Provincial Chief Electrical Inspector Date : March 1, 2012

More information

FEMA P-1019 Emergency Power Systems for Critical Facilities. ASFPM May 4, 2017 David K Low, PE DK Low & Associates

FEMA P-1019 Emergency Power Systems for Critical Facilities. ASFPM May 4, 2017 David K Low, PE DK Low & Associates FEMA P-1019 Emergency Power Systems for Critical Facilities ASFPM May 4, 2017 David K Low, PE DK Low & Associates FEMA P-1019 FEMA P-1019 A critical facility that is fully compliant with the minimum building

More information

The Westinghouse Advanced Passive Pressurized Water Reactor, AP1000 TM. Roger Schène Director,Engineering Services

The Westinghouse Advanced Passive Pressurized Water Reactor, AP1000 TM. Roger Schène Director,Engineering Services The Westinghouse Advanced Passive Pressurized Water Reactor, AP1000 TM Roger Schène Director,Engineering Services 1 Background Late 80: USA Utilities under direction of EPRI and endorsed by NRC : Advanced

More information

CLASSIFICATION OF SYSTEMS, STRUCTURES AND COMPONENTS OF A NUCLEAR FACILITY

CLASSIFICATION OF SYSTEMS, STRUCTURES AND COMPONENTS OF A NUCLEAR FACILITY CLASSIFICATION OF SYSTEMS, STRUCTURES AND COMPONENTS OF A NUCLEAR FACILITY 1 Introduction 3 2 Scope of application 3 3 Classification requirements 3 3.1 Principles of safety classification 3 3.2 Classification

More information

Reactor Technology: Materials, Fuel and Safety. Dr. Tony Williams

Reactor Technology: Materials, Fuel and Safety. Dr. Tony Williams Reactor Technology: Materials, Fuel and Safety Dr. Tony Williams Course Structure Unit 1: Reactor materials Unit 2. Reactor types Unit 3: Health physics, Dosimetry Unit 4: Reactor safety Unit 5: Nuclear

More information

Regulatory Guide Monitoring the Effectiveness of Maintenance at Nuclear Power Plants

Regulatory Guide Monitoring the Effectiveness of Maintenance at Nuclear Power Plants Regulatory Guide 1.160 Revision 2 Page 1 of 14 Revision 2 March 1997 Regulatory Guide 1.160 Monitoring the Effectiveness of Maintenance at Nuclear Power Plants Publication Information (Draft issued as

More information

Low Voltage Switchgear Construction Checklist (under 500 kva)

Low Voltage Switchgear Construction Checklist (under 500 kva) Low Voltage Switchgear Checklist (under 500 kva) Project: Building: Location: Submittal / Approvals Submittal. The above equipment and systems integral to them are complete and ready for functional testing.

More information

2008 NEC Guide Lines for Home Owner Doing Electrical Work on their Property

2008 NEC Guide Lines for Home Owner Doing Electrical Work on their Property 2008 NEC Guide Lines for Home Owner Doing Electrical Work on their Property A brief summary of the most used code references for residential wiring State of Idaho Division of Building Safety Electrical

More information

WGRISK Site-Level Project: Status update and Preliminary insights for the Risk Aggregation focus area

WGRISK Site-Level Project: Status update and Preliminary insights for the Risk Aggregation focus area WGRISK Site-Level Project: Status update and Preliminary insights for the Risk Aggregation focus area S. Yalaoui, Y. Akl (CNSC, Canada), D. Hudson (US NRC), and M. Roewekamp (GRS, Germany) PSA 2017 Pittsburgh,

More information

CHAPTER 5 METERING REQUIREMENTS

CHAPTER 5 METERING REQUIREMENTS CHAPTER 5 METERING REQUIREMENTS CHAPTER 5 METERING REQUIREMENTS 5.1 General 1. All installations connected to, or intended to be connected to HK Electric s supply of electricity must comply with HK Electric

More information

Analysis of distribution system reliability and outage rates

Analysis of distribution system reliability and outage rates Reclosers Technical Data TD280026EN Supersedes pril 2003 (R280-90-7) COOPER POWER SERIES nalysis of distribution system reliability and outage rates Recloser Technical Data TD280026EN nalysis of distribution

More information

March 16, Mr. William M. Dean Director, Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, DC

March 16, Mr. William M. Dean Director, Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, DC ANTHONY R. PIETRANGELO Senior Vice President and Chief Nuclear Officer 1201 F Street, NW, Suite 1100 Washington, DC 20004 P: 202.739.8081 arp@nei.org nei.org March 16, 2015 Mr. William M. Dean Director,

More information

Zion Project Overview S. Chris Baker VP EH&S

Zion Project Overview S. Chris Baker VP EH&S Zion Project Overview S. Chris Baker VP EH&S 1 Agenda Asset Sale Agreement Organization Nuclear Decommissioning Process Overview of Zion Station Decommissioning Schedule Near Term Activities Spent Fuel

More information

Environmental Qualification of

Environmental Qualification of Environmental Qualification of Safety Related Electrical Equipment for Nuclear Power Plants Gary W Castleberry PE PMP Gary W. Castleberry 1 of 63 Learning Modules 1. What is Environmental Qualification

More information

Standard TPL Transmission System Planning Performance Requirements

Standard TPL Transmission System Planning Performance Requirements A. Introduction 1. Title: Transmission System Planning Performance Requirements 2. Number: TPL-001-4 3. Purpose: Establish Transmission system planning performance requirements within the planning horizon

More information

B. Accept materials on site in original factory packaging, labeled with manufacturer s identification.

B. Accept materials on site in original factory packaging, labeled with manufacturer s identification. SECTION 26 05 02 - BASIC ELECTRICAL REQUIREMENTS PART 1 - GENERAL 1.1 SUMMARY A. Work Included: Furnish all labor, material, services and skilled supervision necessary for the construction, erection, installation,

More information

Enhancement of Nuclear Safety

Enhancement of Nuclear Safety Enhancement of Nuclear Safety Soon Heung Chang Handong Global University May 6, 2015 Contents 1 2 3 4 Importance of Energy Fundamentals of Nuclear Safety How to Enhance Nuclear Safety Closing Remarks 2

More information

ELECTRIC METERING GENERAL

ELECTRIC METERING GENERAL 1.0 INDEX 1.0 INDEX 2.0 SCOPE 3.0 GENERAL REQUIREMENTS 4.0 EQUIPMENT 5.0 METER REQUIREMENTS 6.0 METER FACILITIES 7.0 ELECTRICAL CONNECTIONS 2.0 SCOPE This guide covers general requirements and codes for

More information

For the 2008 Code, the minimum clear distances were revised to reflect an accurate metric conversion (also known as a soft conversion).

For the 2008 Code, the minimum clear distances were revised to reflect an accurate metric conversion (also known as a soft conversion). II. 600 Volts, Nominal, or Less 110.26 Spaces About Electrical Equipment. Sufficient access and working space shall be provided and maintained about all electrical equipment to permit ready and safe operation

More information

SECTION 16496A MTS MANUAL TRANSFER SWITCH (MANUAL CONTROL ONLY) Note to Spec Writer: { } Denotes EATON Feature reference number

SECTION 16496A MTS MANUAL TRANSFER SWITCH (MANUAL CONTROL ONLY) Note to Spec Writer: { } Denotes EATON Feature reference number MTS MANUAL TRANSFER SWITCH (MANUAL CONTROL ONLY) Note to Spec Writer: { } Denotes EATON Feature reference number PART 1 GENERAL 01 02 03 04 SCOPE Furnish and install Manual Transfer Switches (MTS) and

More information

S. A. Eide (INEEL) M. B. Calley (INEEL) C. D. Gentillon (INEEL) T. Wierman (INEEL) D. Rasmuson (USNRC) D. Marksberry (USNRC) PSA 99

S. A. Eide (INEEL) M. B. Calley (INEEL) C. D. Gentillon (INEEL) T. Wierman (INEEL) D. Rasmuson (USNRC) D. Marksberry (USNRC) PSA 99 INEEL/CON-99-00374 PREPRINT Westinghouse Reactor Protection System Unavailability, 1984 1995 S. A. Eide (INEEL) M. B. Calley (INEEL) C. D. Gentillon (INEEL) T. Wierman (INEEL) D. Rasmuson (USNRC) D. Marksberry

More information

PROBABILISTIC RELIABILITY ASSESSMENT OF TRANSMISSION SYSTEMS

PROBABILISTIC RELIABILITY ASSESSMENT OF TRANSMISSION SYSTEMS PROBABILISTIC RELIABILITY ASSESSMENT OF TRANSMISSION SYSTEMS DAWOOD ALALI Thesis submitted to Cardiff University in candidature for the degree of Doctor of Philosophy. School of Engineering Cardiff University

More information

IV. Occurrence and Development of the Accident at the Fukushima Nuclear Power Stations

IV. Occurrence and Development of the Accident at the Fukushima Nuclear Power Stations IV. Occurrence and Development of the Accident at the Fukushima Nuclear Power Stations 1. Outline of Fukushima Nuclear Power Stations (1) Fukushima Daiichi Nuclear Power Station Fukushima Daiichi Nuclear

More information

DESIGN AND SAFETY PRINCIPLES LEONTI CHALOYAN DEPUTY CHIEF ENGINEER ON MODERNIZATION

DESIGN AND SAFETY PRINCIPLES LEONTI CHALOYAN DEPUTY CHIEF ENGINEER ON MODERNIZATION DESIGN AND SAFETY PRINCIPLES LEONTI CHALOYAN DEPUTY CHIEF ENGINEER ON MODERNIZATION VIENNA OKTOBER 3-6, 2016 1 ANPP * ANPP is located in the western part of Ararat valley 30 km west of Yerevan close to

More information

GILA RIVER FIRE DEPARTMENT REQUIREMENTS

GILA RIVER FIRE DEPARTMENT REQUIREMENTS GILA RIVER FIRE DEPARTMENT REQUIREMENTS Case Number: Date: 09/07/2016 Reviewer: G. Lindenmier #0305 Project Name: Portable Generators Special Events & Use Location: WHPDA Property Applicant: Applicant

More information

Probabilistic Safety Analysis (PSA): Quality and Scope. Guideline for Swiss Nuclear Installations. ENSI-A05/e

Probabilistic Safety Analysis (PSA): Quality and Scope. Guideline for Swiss Nuclear Installations. ENSI-A05/e Guideline for Swiss Nuclear Installations ENSI-A05/e Edition March 2009 Edition March 2009 Guideline for Swiss Nuclear Installations ENSI-A05/e English is not an official language of the Swiss Confederation.

More information

RESIDENTIAL BUILDING REQUIREMENTS

RESIDENTIAL BUILDING REQUIREMENTS RESIDENTIAL BUILDING REQUIREMENTS Residential Building Requirements This is an informational booklet with some of the general residential construction requirements taken from the codes adopted by Campbell

More information

Medium Voltage UPS Solutions - When and Why? Frank Herbener, Piller Group GmbH, Germany

Medium Voltage UPS Solutions - When and Why? Frank Herbener, Piller Group GmbH, Germany Medium Voltage UPS Solutions - When and Why? Frank Herbener, Piller Group GmbH, Frank.Herbener@Piller.com, Germany 1 Contents 1 Scope 3 2 Power Demand and Distribution in today s Mission Critical Applications

More information

ELECTRICAL SAFETY INSPECTION REPORT

ELECTRICAL SAFETY INSPECTION REPORT ELECTRICAL SAFETY INSPECTION REPORT ADVANCE WORLD LIMITED Lalkha Shair Char, Fatullah, Narayanganj, Dhaka, Bangladesh Factory List: 1.. Inspected by: Sherub Tenzin & Md. Moin Hasan Report Generated by:

More information

Revisions for the 2011 National Electrical Code - Part 2

Revisions for the 2011 National Electrical Code - Part 2 PDHonline Course E356 (3 PDH) Revisions for the 2011 National Electrical Code - Part 2 Instructor: Patrick Ouillette 2012 PDH Online PDH Center 5272 Meadow Estates Drive Fairfax, VA 22030-6658 Phone &

More information

UFL Micro Biogas CHPs

UFL Micro Biogas CHPs UFL Micro Biogas CHPs The UFL Micro Biogas CHPs are based on the highly durable Petter industrial diesel engine. Low cost replacement parts are available worldwide. This range of micro biogas CHPs has

More information

Facility Interconnection Requirements

Facility Interconnection Requirements Facility Interconnection Effective 1/1/2016 1. Purpose Facility Interconnection Facility Interconnection (FAC-001-2) To avoid adverse impacts on the reliability of the Bulk Electric System (BES), RPU documents

More information

Installation, Inspection and Maintenance of Dry Type Transformers

Installation, Inspection and Maintenance of Dry Type Transformers Dry Type TX 1 of 8 Installation, Inspection and Maintenance of Dry Type Page 1 of 8 Dry Type TX 2 of 8 Table Of Contents Page Number 1. General... 3 2. Installation... 3 3. Safety Inspections... 4 4. Safety

More information

Nuclear power: OECD/NEA perspective

Nuclear power: OECD/NEA perspective R&D activities underway and priority gaps and opportunities for climate resilience and preparedness Nuclear power: OECD/NEA perspective Dr. Henri PAILLERE, OECD Nuclear Energy Agency henri.paillere@oecd.org

More information

Factors Affecting Current Ratings for Underground and Air Cables

Factors Affecting Current Ratings for Underground and Air Cables Factors Affecting Current Ratings for Underground and Air Cables S. H. Alwan, J. Jasni, M. Z. A. Ab Kadir, N. Aziz Abstract The aim of this paper is to present a parametric study to determine the major

More information

The Canadian Electrical Code (Saskatchewan Amendments) Regulations, 1999

The Canadian Electrical Code (Saskatchewan Amendments) Regulations, 1999 CANADIAN ELECTRICAL CODE 1 The Canadian Electrical Code (Saskatchewan Amendments) Regulations, 1999 Repealed by Chapter E-6.3 Reg 8 (effective June 24, 2003). Formerly Chapter E-6.3 Reg 6 (effective March

More information

Ensuring Spent Fuel Pool Safety

Ensuring Spent Fuel Pool Safety Ensuring Spent Fuel Pool Safety Michael Weber Deputy Executive Director for Operations U.S. Nuclear Regulatory Commission American Nuclear Society Meeting June 28, 2011 1 Insights from Fukushima Nuclear

More information

B. Provide liquid-filled secondary substation transformers as indicated on drawings.

B. Provide liquid-filled secondary substation transformers as indicated on drawings. SECTION 26 12 13 PART 1 - GENERAL 1.01 WORK INCLUDED A. Comply with the provisions of Sections 26 05 00. B. Provide liquid-filled secondary substation transformers as indicated on drawings. 1.02 RELATED

More information

Westinghouse Small Modular Reactor. Passive Safety System Response to Postulated Events

Westinghouse Small Modular Reactor. Passive Safety System Response to Postulated Events Westinghouse Small Modular Reactor Passive Safety System Response to Postulated Events Matthew C. Smith Dr. Richard F. Wright Westinghouse Electric Company Westinghouse Electric Company 600 Cranberry Woods

More information

SECTION GROUNDING AND BONDING

SECTION GROUNDING AND BONDING SECTION 16060 PART 1 GENERAL 1.01 DESCRIPTION A. Section includes requirements for an electrical grounding system, including electrodes, grounding rods, connectors, insulators, equipment grounding and

More information

Controlled management of a severe accident

Controlled management of a severe accident July 2015 Considerations concerning the strategy of corium retention in the reactor vessel Foreword Third-generation nuclear reactors are characterised by consideration during design of core meltdown accidents.

More information

Steam Power Station (Thermal Station)

Steam Power Station (Thermal Station) Steam Power Station (Thermal Station) A generating station which converts heat energy into electrical energy through turning water into heated steam is known as a steam power station. A steam power station

More information

Communications Page 1 of 9

Communications Page 1 of 9 Page 1 of 9 Last Update: April 23 rd, 2014 Introduction Design In the design of Telecommunications systems in Purdue facilities, the overall consideration should be to understand and treat telecom as a

More information

Electrical Protection Methods and Devices SAMPLE. Learner Workbook Version 1. Training and Education Support Industry Skills Unit Meadowbank

Electrical Protection Methods and Devices SAMPLE. Learner Workbook Version 1. Training and Education Support Industry Skills Unit Meadowbank Electrical Protection Methods and Devices Learner Workbook Version 1 Training and Education Support Industry Skills Unit Meadowbank Product Code: 5635 Table of Contents Introduction... 5 1. Protection

More information

OperatiOn and safety report Of MOchOvce and BOhunice v2 nuclear power plants

OperatiOn and safety report Of MOchOvce and BOhunice v2 nuclear power plants 2016 OperatiOn and safety report Of MOchOvce and BOhunice v2 nuclear power plants The company is certified according to three management systems: Certificate stn en iso 9001:2008 Quality management system

More information

PHYSICAL FACILITIES Consultant s Handbook Division 27 COMMUNICATIONS 0000 COMMUNICATIONS

PHYSICAL FACILITIES Consultant s Handbook Division 27 COMMUNICATIONS 0000 COMMUNICATIONS 1 Introduction 1.1 In the design of Telecommunications systems in Purdue facilities, the overall consideration should be to understand and treat telecom as a utility. It should be assumed that all new

More information

Research and Application Study on Accident-Based 3D Power Station Simulation Technology

Research and Application Study on Accident-Based 3D Power Station Simulation Technology International Conference on Electromechanical Control Technology and Transportation (ICECTT 2015) Research and Application Study on Accident-Based 3D Power Station Simulation Technology Tie Li, Xiaoming

More information

Hazards. Hazards. Hazards. Effects on the Body. GA Tech Electrical Safety Presentation

Hazards. Hazards. Hazards. Effects on the Body. GA Tech Electrical Safety Presentation Hazards The direct result can be electrocution. SHOCK. Electric shock occurs when the human body becomes part of the path through which current flows. The indirect result can be injury resulting from a

More information

HPR1000: ADVANCED PWR WITH ACTIVE AND PASSIVE SAFETY FEATURES

HPR1000: ADVANCED PWR WITH ACTIVE AND PASSIVE SAFETY FEATURES HPR1000: ADVANCED PWR WITH ACTIVE AND PASSIVE SAFETY FEATURES D. SONG China Nuclear Power Engineering Co., Ltd. Beijing, China Email: songdy@cnpe.cc J. XING China Nuclear Power Engineering Co., Ltd. Beijing,

More information

National Status on Life Management of NPPs in Finland Meeting of the IAEA TWG-LMNPP February th 2017 Vienna, Jyrki Kohopää

National Status on Life Management of NPPs in Finland Meeting of the IAEA TWG-LMNPP February th 2017 Vienna, Jyrki Kohopää National Status on Life Management of NPPs in Finland 2017 Meeting of the IAEA TWG-LMNPP February 22-24 th 2017 Vienna, Jyrki Kohopää NUCLEAR POWER IN FINLAND Teollisuuden Voima Oyj, Olkiluoto: OL1/2:

More information

UNDERGROUND SERVICES SECONDARY

UNDERGROUND SERVICES SECONDARY Reference UNDERGROUND SERVICES SECONDARY Underground services secondary... U- 1 General requirements for underground service... U- 2 Name of parts for underground service... U- 3 Conduit layouts... U-

More information

THOMAS JEFFERSON UNIVERSITY HOSPITAL STANDARD OPERATING PROCEDURE FOR THE BUILD OUT OF TELECOMMUNICATIONS ROOMS AND ASSOCIATED SPACES

THOMAS JEFFERSON UNIVERSITY HOSPITAL STANDARD OPERATING PROCEDURE FOR THE BUILD OUT OF TELECOMMUNICATIONS ROOMS AND ASSOCIATED SPACES THOMAS JEFFERSON UNIVERSITY HOSPITAL STANDARD OPERATING PROCEDURE FOR THE BUILD OUT OF TELECOMMUNICATIONS ROOMS AND ASSOCIATED SPACES PREPARED BYBALA CONSULTING ENGINEERS, INC FOR THOMAS JEFFERSON UNIVERSITY

More information

Introduction to Level 2 PSA

Introduction to Level 2 PSA Introduction to Level 2 PSA Dr Charles Shepherd Chief Consultant, Corporate Risk Associates CRA PSA/HFA FORUM 13-14 September 2012, Bristol Accident sequences modelled by the PSA INITIATING EVENTS SAFETY

More information

SECTION CHAIN-LINK FENCES AND GATES 02821/1

SECTION CHAIN-LINK FENCES AND GATES 02821/1 SECTION 02821 - CHAIN-LINK FENCES AND GATES 02821/1 PART 1 - GENERAL 1.1 SUMMARY A. This Section includes the following: 1. Chain-Link Fences: 2. Gates: horizontal slide or swing. 3. Fences installed where

More information

Basic Requirements for Residential Electrical Installations

Basic Requirements for Residential Electrical Installations Basic Requirements for Residential Electrical Installations Wayne County Building Department 428 West Liberty Street Wooster, Ohio 44691 Phone: 330-287-5525 Fax: 330-287-5649 This brochure is intended

More information

Public Utility District Number 1 of Snohomish County

Public Utility District Number 1 of Snohomish County Public Utility District Number 1 of Snohomish County Facility Connection Requirements September 29, 2011 1 Revision History: Number Date Description Original Sept. 29, 2011 Document Origination Compilation

More information

Assessment of Electric and Magnetic Field Exposure from Power Generation for Energy UK

Assessment of Electric and Magnetic Field Exposure from Power Generation for Energy UK CRCE/NIR/5/639 Assessment of Electric and Magnetic Field Exposure from Power Generation for Energy UK N A Cridland, A J Lowe, F M Petty, N Northrop and S Jakes Commercial-in-confidence Contract Report

More information

Technical Specification for LV ABC Fuse Switch Disconnectors

Technical Specification for LV ABC Fuse Switch Disconnectors Ergon Energy Corporation Limited Technical Specification for LV ABC Fuse ETS-06-02-02 Check this is the latest Process Zone version before use. Specification ETS 06-02-02 Ver 3 Contents 1. Purpose and

More information

Chapter 2 Energy Produced and Carbon Released from Fossil Fuels and the Amount of Alternative Energy Required as a Replacement

Chapter 2 Energy Produced and Carbon Released from Fossil Fuels and the Amount of Alternative Energy Required as a Replacement Chapter 2 Energy Produced and Carbon Released from Fossil Fuels and the Amount of Alternative Energy Required as a Replacement 2.1 Use and Production of Power and Energy from Fossil Fuels Before we embark

More information

Summary on Fukushima Related Activities in Japan

Summary on Fukushima Related Activities in Japan 0 Keynote Presentation Summary on Fukushima Related Activities in Japan Masashi HIRANO Director-General for Regulatory Standard and Research Nuclear Regulation Authority (NRA) International Conference

More information

Long Beach July 2015 Secondary Network Outages RCE. Summary and Report

Long Beach July 2015 Secondary Network Outages RCE. Summary and Report Long Beach July 2015 Secondary Network Outages RCE Summary and Report 1 P age Table of Contents Background... 3 Root Cause... 5 Chronology... 7 Immediate, Interim, and Corrective Actions... 12 Exhibit

More information

Power Zone Center. Your solution for power distribution and control systems

Power Zone Center. Your solution for power distribution and control systems Power Zone Center Your solution for power distribution and control systems The Strength of One Powerful When you need to install a new power distribution center in your facility, you need it done in fastest

More information

Evaluation of CSST Gas Piping Subjected to Electrical Insult

Evaluation of CSST Gas Piping Subjected to Electrical Insult Evaluation of CSST Gas Piping Subjected to Electrical Insult Rising Tide Consulting, LLC Brian Kraft, PE and Cutting Edge Solutions, LLC Robert Torbin, PE October 2009 The research data presented within

More information

Meetings for Sharing International Knowledge and Experience on Stress Tests

Meetings for Sharing International Knowledge and Experience on Stress Tests Meetings for Sharing International Knowledge and Experience on Stress Tests Presented by: Peter Hughes, Ovidiu Coman, Javier Yllera Department of Nuclear Safety and Security Division of Nuclear Installation

More information

The Value of Customer Reliability to the Utility

The Value of Customer Reliability to the Utility The Value of Customer Reliability to the Utility Interviewing Lee Taylor, Consulting Engineer Presentation to IEEE Working Group on Distribution Reliability June 20, 2006 Montreal Canada Overview Service

More information

Galvanic and Stray Current Corrosion

Galvanic and Stray Current Corrosion Chapter 5 Galvanic and Stray Current Corrosion MElec-Ch5-1 Overview Galvanic Corrosion Understanding Galvanic Corrosion Controlling Galvanic Corrosion Stray Current Corrosion Understanding Stray Current

More information

BUSWAY LOW VOLTAGE (POW-R-WAY III) SECTION SECTION 16466

BUSWAY LOW VOLTAGE (POW-R-WAY III) SECTION SECTION 16466 BUSWAY LOW VOLTAGE (POW-R-WAY III) PART 1 GENERAL 1.01 1.02 SCOPE The Contractor shall furnish and install the busway system including all necessary fittings, hangers and accessories as specified herein

More information

Lightning Protection Practice for Large-Extended Photovoltaic Installations

Lightning Protection Practice for Large-Extended Photovoltaic Installations 202 International Conference on ightning Protection (ICP), Vienna, Austria ightning Protection Practice for arge-extended Photovoltaic Installations Dr. Nikolaos Kokkinos Research and Development Department

More information

Section ARMORED MEDIUM VOLTAGE CABLES SHIELDED 3 CONDUCTOR POWER CABLE - INTERLOCKED ARMOR

Section ARMORED MEDIUM VOLTAGE CABLES SHIELDED 3 CONDUCTOR POWER CABLE - INTERLOCKED ARMOR PART 1 - GENERAL Section 26 05 15 SHIELDED 3 CONDUCTOR POWER CABLE - INTERLOCKED ARMOR 1.1 Cable shall be 15 kv, shielded, three conductor with ground, stranded copper, with continuously welded and corrugated

More information

Generator Assessment & Roles During A Restoration

Generator Assessment & Roles During A Restoration Generator Assessment & Roles During A Restoration PJM State & Member Training Dept. PJM 2015 Objectives Students will be able to: Identify the process and requirements for operating during system restoration

More information

Compact Substation Design. Kobus Coetzer TGOOD Africa

Compact Substation Design. Kobus Coetzer TGOOD Africa Compact Substation Design Kobus Coetzer TGOOD Africa 1. 2. 3. 4. TGOOD Electric Compact Substation Design Considerations Project Reference Agenda 1. TGOOD Electric Key Facts Sino German Joint Venture Leading

More information

Top Five Reasons to Implement Distributed Bus Protection

Top Five Reasons to Implement Distributed Bus Protection GE Grid Solutions Top Five Reasons to Implement Distributed Bus Protection White Paper Author: JC Theron g imagination at work 1. Abstract Power systems have evolved in the past few decades due to factors

More information

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C SAFETY EVALUATION REPORT

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C SAFETY EVALUATION REPORT UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 SAFETY EVALUATION REPORT Docket No. 72-1040 HI-STORM UMAX Canister Storage System Holtec International, Inc. Certificate of Compliance

More information

European level recommendations Sect. in NAcP 2 Generic recommendation for WENRA, Finland participates and follows the work.

European level recommendations Sect. in NAcP 2 Generic recommendation for WENRA, Finland participates and follows the work. Cross reference table of ENSREG and Extraordinary CNS recommendations and national actions 1(16) 2.1 European guidance on assessment of natural hazards and margins The peer review Board recommends that

More information

(Condensed from National Electric Code)

(Condensed from National Electric Code) WIRING, SPECIFICATIONS, INSPECTION, AND METER INSTALLATION PROCEDURES FOR RESIDENTIAL CUSTOMERS SERVED BY SOUTHWEST ARKANSAS ELECTRIC COOPERATIVE CORPORATION Effective April 1, 1974 Revised February 3,

More information

Pressurized Thermal Shock Potential at Palisades

Pressurized Thermal Shock Potential at Palisades Pressurized Thermal Shock Potential at Palisades Prepared by Michael J. Keegan Coalition for a Nuclear Free Great Lakes (July 8, 1993, Rekeyed August 3, 2005) History of Embrittlement of Reactor Pressure

More information

RESULTS OF THE GRADUAL UPGRADING AT BOHUNICE WWER - 440/230 NPP

RESULTS OF THE GRADUAL UPGRADING AT BOHUNICE WWER - 440/230 NPP RESULTS OF THE GRADUAL UPGRADING AT BOHUNICE WWER - 440/230 NPP P. Krupa Ingeneer, e-mail: Krupa_Peter@ebo.seas.sk Bohunice NPPs Introduction The centre of upgrading activities in VVER NPP is clearly in

More information

ACS OTHER PRIMARY EQUIPMENT

ACS OTHER PRIMARY EQUIPMENT ACS OTHER PRIMARY EQUIPMENT Fleet Strategy Document 31/10/2013 Transpower New Zealand Limited 2013. All rights reserved. Page 1 of 70 C O P Y R I G H T 2013 T R A N S P O W E R N E W Z E A L A N D L I

More information

DEVELOPMENT AND APPLICATION OF PROBABILISTIC SAFETY ASSESSMENT PSA IN DAYA BAY NUCLEAR POWER STATION

DEVELOPMENT AND APPLICATION OF PROBABILISTIC SAFETY ASSESSMENT PSA IN DAYA BAY NUCLEAR POWER STATION 18th International Conference on Structural Mechanics in Reactor Technology (SMiRT 18) Beijing, China, August 7-12, 2005 SMiRT18-A01-2 DEVELOPMENT AND APPLICATION OF PROBABILISTIC SAFETY ASSESSMENT PSA

More information

CITY OF GRANDE PRAIRIE

CITY OF GRANDE PRAIRIE Inspection Services CITY OF GRANDE PRAIRIE HOMEOWNER S PERMIITS AND WIRING GUIDE FOR ELECTRICAL INSTALLATIONS 2016 INDEX Page Applying for an Electrical Permit 3 Permit Application Requirements 3 Permit

More information

An assessment by the Radiation and Nuclear Safety Authority on the periodic safety review of Loviisa NPP

An assessment by the Radiation and Nuclear Safety Authority on the periodic safety review of Loviisa NPP Safety assessment 1 (107) An assessment by the Radiation and Nuclear Safety Authority on the periodic safety review of Loviisa NPP Table of Contents Table of Contents... 1 1 Introduction... 4 1.1 Documents

More information

June 7, 2012 PARTIES INTERESTED IN HVAC DUCT ENCLOSURE ASSEMBLIES

June 7, 2012 PARTIES INTERESTED IN HVAC DUCT ENCLOSURE ASSEMBLIES June 7, 2012 TO: PARTIES INTERESTED IN HVAC DUCT ENCLOSURE ASSEMBLIES SUBJECT: Revisions to the Acceptance Criteria for Metallic HVAC Duct Enclosure Assemblies, Subject AC179-0612-R1 (MB/CA) Dear Colleague:

More information

Substation Bus Design: Current Methods Compared with Field Results

Substation Bus Design: Current Methods Compared with Field Results Electrical Transmission and Substation Structures Conference 2009 ASCE 143 Substation Bus Design: Current Methods Compared with Field Results Keith Malmedal Ph.D. P.E. P.Eng. 1 and John Wendelburg P.E.

More information

Unit Substation Transformer Construction Checklist (under 500 kva)

Unit Substation Transformer Construction Checklist (under 500 kva) Unit Substation Transformer Checklist (under 500 kva) Building: Location: Submittal / Approvals Submittal. The above equipment and systems integral to them are complete and ready for functional testing.

More information

Revision 1 RAM ELEVATORS. Elevator Electrical Planning Guide. RAM Manufacturing Ltd

Revision 1 RAM ELEVATORS. Elevator Electrical Planning Guide. RAM Manufacturing Ltd RAM ELEVATORS Elevator Electrical Planning Guide This guide is intended for people with an understanding of electricity. If you are not, please consult a licensed electrician as errors in application of

More information

7. Electrical Facility Ratings

7. Electrical Facility Ratings 7. Electrical Facility Ratings 7.1 Accredited Net Generating Capacity This Section shall be used to determine the annual and seasonal accredited net generating capacity of generators in calculating the

More information

What Are the Qualifications to Conduct Arc Flash Studies? Where Do You Begin?

What Are the Qualifications to Conduct Arc Flash Studies? Where Do You Begin? What Are the Qualifications to Conduct Arc Flash Studies? Where Do You Begin? How to compare apples-to-apples bids. By R. Dee Jones, P.E., AVO Training Institute Electrical Engineering Division Manager/Principal

More information