1 OPTIMISATION OF RAILWAY ASSET LIFE CYCLE PERFORMANCE THROUGH A CONTINIOUS ASSET IMPROVEMENT PROCESS Presented by Jackie vd Westhuizen e-logics Objectives Contextualise relevant asset management definitions and principles. Introduce the railway maintenance management principles focusing on track tamping related to substructure performance. Develop a maintenance decision model/process. Integrate the model into relevant technology to test usability/practicality. Compare results against standard strategies and tactics. Conclude with continuous improvement philosophy. Slide

2 What is asset management? Asset Management can be defined as the holistic approach within an entire business to improve its overall performance. Physical Asset Management has a single objective and that is to increase the value and return delivered by the physical assets. Physical Asset Optimization is a program that is a business initiative focusing on and determined by opportunities to create value in different areas. Holistic approach to realise value from Assets Slide 3 Areas/Opportunities to Create Value Increase stability and quality; Reduce cost; Increase effectiveness and productivity; Flexible and reliable processes; Improve capital effectiveness. Invest at the right time and right location/cost benefit analysis Slide 4

3 The Asset Centric Approach to Asset Management Operate Assets and resources should be planned and controlled to ensure optimal utilisation and profit. Operations planning considers the requirements for movement across the network within the associated constraints. Asset owner Physical Infrastructure Moveable assets and Operation Scheduling Assets Asset Base Integrated Operations and Maintenance Management Optimizing Physical Asset Management Maintain Maintenance of the asset base should ensure the safe, reliable, available and optimal (affordable) cost of the operation of these assets. Asset Care Ensure production capacity Minimize maintenance interference (Maximize Production) Material Management Minimize maintenance cost Increase Operation Profitability Slide 5 What is maintenance management? Maintenance can be defined as the care, correction and servicing of assets and their components, whether physical or functional, for the purpose of ensuring satisfactory operations of the assets and components before failure or major defects occur that will influence the operational ability thereof. In short, maintenance can be called asset care. It ensures the availability, reliability, safety and capacity of assets to deliver either a product or a service, depending on the business objective. Asset care need to provide capacity and ensure availability. Slide 6

4 Influence and Relevance of Maintenance Maintenance Areas/Opportunities to Create Value Reduce incidents; Increase availability and utilisation; Improve quality; Maximize effectiveness; Reduce and minimize failures; Reduce operating and maintenance cost; Reduce spares/inventory. Slide 8

5 Interdependencies of Operations and Asset Management in the Railways Infrastructure Availability Operate Functional Assets Equipment Availability Physical Asset Interface Importance of synergy/partnership (Asset Owner and Asset Care taker) to ensure operational objectives Demand Demand Operational Production Best Performance Breakeven Interruptions (Out-of-service) Operational Production Best Performance Breakeven Improved reliability extends intervals between interruptions and increase availability Time Demand Time Adopted: Mitchell et al. Operational Production Best Performance Breakeven Reduce out-ofservice duration to assist in delivery commitments e.g. Speed Restrictions Slide 10 Time

6 Maintenance Strategy Improvement Path Adopted: Hans Ahlmann High Quality & Performance Mode Hierarchy/Controlled Floworientated Slide 11 Accidental Mode APPLICATION IN RAILWAY MAINTENANCE MANAGEMENT

7 Maintenance Managers Dilemma Where should we work next?? Condition Measures Track Geometry Measures Rail Defects/Flaws/Wear Track & Turnout Inspections Contact Wire Measurements Track Circuit Failures Where and When do I Apply my Maintenance Resources? Work History Mechanised Maintenance Spot Maintenance Maintenance Costs Operational Interference Track Occupation Train Delays Speed Restrictions Slide 13 Maintenance Management Process Work Identification Work Planning Work Scheduling Know the asset and business requirements Asset Condition Monitor Infrastructure Management Data Work History (Feedback & Followup) Sustained Maintenance Work Execution Asset Configuration Emergency, reactive repairs

8 Continuous Improvement Process for an Effective Maintenance Management Asset Management Strategies & Policies (Network Requirements) Condition Assessment 1 Analysis 3 Feedback and Monitor 6 Execution Continuous Improvement 4 5 Planning + Budgeting Resource Scheduling Slide 15 Information Requirements What and where is it? What is its condition? What has it done? What has been done to it? Integration and Analysis Decision Making Setup Maintenance Plan What has it generated? What has it cost? Slide 16

9 Typical System information Flow Survey and create asset register Automated Condition Assessment Visual Condition Assessment Slide 17 Condition Data Track Geometry Slide 18 Slide 18

10 Condition Data Rail Defects Slide 19 Slide 19 Condition Data Rail Wear Slide 0 Slide 0

11 ANALYSIS METHODOLOGY DECISION MAKING MODEL/PROCESS Asset Performance Indicators and Limits Minimum Acceptable Roughness Level (Safety Limit) Roughness Increase (Condition Decrease) Minimum Allowable Roughness Level Cannot get the condition to its original level Rehabilitation Time between maintenance cycles decreases, impact on operations, asset availability and capacity Replacement (Maintenance Limit) Upgrade Time/Traffic (MGT) Slide

12 Routine (Cyclic) Based Maintenance 48 Tamping Interval MGT / year sec tion Current = 18 MGT Tamping interval calculated at once a year Tamping total distance of track Routine Based Tamping Equivalent Tamping Unit Quantity Requirements Distance (Km) Tangent Track Km Curved Track Km Switches Number Total Distance Slide 3 Condition Based Maintenance Identify need Different analysis calculations Development of maintenance algorithm

13 Condition Based Maintenance: Maintenance Limit Intervention A selection of up to five track geometry condition assessment parameters to calculate a condition index. Each parameter can be multiplied with a weighted average, and the result of these values are added to one another A variable maintenance and/or safety intervention limit utilized to identify all areas that require maintenance. A variable cluster length, this length is utilized to cluster maintenance areas into one group if the areas not requiring maintenance between identified maintenance areas is less than this length. An option to include radius configuration data, to ensure that the result is applied to the extent of the curve. R + profile right = profile left R + alignment left R = profile tamp Ralignment tamp R R alignment right Slide 5 Maintenance Condition Limit From Gräbe and Maree (1997) Standard Deviation = 1.6mm for profile on coal line From frequency plot 86 th percentile profile on Durban line calculated at 4.mm Slide 6

14 Tamping Analysis Intervention Limit Analysis Clustering Analysis Radius Analysis extend Radius Slide 7 Condition Based Maintenance: Condition Performance Index (Rate of Condition Change) A further improvement to the condition based approach compares the rate of change in the geometry measurements. The rate of change is calculated by subtracting consecutive measurements of roughness data. The result can be used to identify areas were deterioration is high. Improvements can also be identified that will highlight effective maintenance. R R = n 1 R n Slide 8

15 Outcomes of different models Maintenance Intervention limit Delta Roughness limit Slide 9 Results comparison Condition Performance Routine Based Distance ( R ) Based Distance Tamping Further Requirements value (arguably more than Requirements the Savings Activity maintenance Equivalent cost saving) are created Equivalent through the additional (%) Type Capacity/Availability Tamping to Operations. The Tamping reduction in the Distance maintenance translates Distance Unit Quantity into 8 days of (km) track occupation. Quantity The same principles will also lead to the (km) Tangent reduction in Material requirements and Track km therefore 4 less inventory Curved Track km Switches Number Total Distance Slide 30

16 Continuous Improvement Process Slide 31 In conclusion Maintenance Management is a fundamental part of optimised asset management. Sound principles, processes with relevant data and tools assist in effective maintenance decision making. Continuous improvement process is the fundamental link for sustainable maintenance management and asset performance optimisation. Slide 3

17 THANK YOU Additional Information What's ideal for substructure management?

18 Layer thickness identification utilising GPR Slide 35 Geometry and DCP/CBR integration Decision Making Slide 36

OPTIMISATION OF RAILWAY ASSET LIFE CYCLE PERFORMANCE THROUGH A CONTINUOUS ASSET IMPROVEMENT PROCESS AS PART OF THE MAINTENANCE MANAGEMENT PROGRAMME

OPTIMISATION OF RAILWAY ASSET LIFE CYCLE PERFORMANCE THROUGH A CONTINUOUS ASSET IMPROVEMENT PROCESS AS PART OF THE MAINTENANCE MANAGEMENT PROGRAMME OPTIMISATION OF RAILWAY ASSET LIFE CYCLE PERFORMANCE THROUGH A CONTINUOUS ASSET IMPROVEMENT PROCESS AS PART OF THE MAINTENANCE MANAGEMENT PROGRAMME N J van der Westhuizen and J van der Westhuizen* e-logics

More information

GRP System FX. The «all in one» railway surveying solution

GRP System FX. The «all in one» railway surveying solution GRP System FX The «all in one» railway surveying solution Rail traffic without limits New challenges for railway construction and operation Borders open, centres of economic activity spread, people and

More information

Analytics for Asset Management

Analytics for Asset Management Analytics for Asset Management Analytics for Asset Management Decision Support (through the application of Analytics) is required by infrastructure organisations in broadly 2 categories: Strategic Decisions

More information

Rudolf Schilder. Track Innovations by Austrian Railways (OEBB)

Rudolf Schilder. Track Innovations by Austrian Railways (OEBB) Rudolf Schilder Track Innovations by Austrian Railways (OEBB) Dr. Rudolf Schilder, former Head of Business Unit Railway Line and Station Management, OEBB-Infrastructure AG (Austrian Railways Infrastructure),

More information

EURAILSCOUT Inspection & Analysis

EURAILSCOUT Inspection & Analysis EURAILSCOUT Inspection & Analysis Your reliable partner to monitor the condition of the railway infrastructure INTRODUCTION To be able to ensure rail traffic safety and reliability, it is absolutely necessary

More information

Automated Condition Assessment as an Aid to Complying With the FTA State of Good Repair Regulations

Automated Condition Assessment as an Aid to Complying With the FTA State of Good Repair Regulations Automated Condition Assessment as an Aid to Complying With the FTA State of Good Repair Regulations 1 Metrolink Overview Commuter Railroad with Mixed Passenger and Freight Traffic 1. Most lines are former

More information

THEFUTURERAILWAY THE INDUSTRY S RAIL TECHNICAL STRATEGY 2012 INFRASTRUCTURE

THEFUTURERAILWAY THE INDUSTRY S RAIL TECHNICAL STRATEGY 2012 INFRASTRUCTURE 33 INFRASTRUCTURE Automated maintenance is quicker, safer and more cost-effective Well-targeted maintenance enables more train paths to be available at night Advanced suspension system minimises noise

More information

A dynamic approach for planning preventive railway maintenance activities

A dynamic approach for planning preventive railway maintenance activities A dynamic approach for planning preventive railway maintenance activities G. Budai 1 & R. Dekker 2 1 Erasmus University Rotterdam, Tinbergen Institute, The Netherlands 2 Erasmus University Rotterdam, The

More information

Vehicle Track Interaction Strategic Model (VTISM) Overview for ICRI Project (Apr-2016)

Vehicle Track Interaction Strategic Model (VTISM) Overview for ICRI Project (Apr-2016) V/T SIC Vehicle / Track System Interface Committee Vehicle Track Interaction Strategic Model (VTISM) Overview for ICRI Project (Apr-2016) Andy Rhodes, Serco Adam Bevan, University of Huddersfield Overview

More information

Describing DSTs Analytics techniques

Describing DSTs Analytics techniques Describing DSTs Analytics techniques This document presents more detailed notes on the DST process and Analytics techniques 23/03/2015 1 SEAMS Copyright The contents of this document are subject to copyright

More information

UT5 Maintenance Allowance. December 2016

UT5 Maintenance Allowance. December 2016 UT5 Maintenance Allowance December 2016 Agenda Time Topic Presenter 11:00 Introduction Prue Mackenzie 11:05 Safety Share Jason Livingston 11:15 Overview Asset Maintenance & Management Jason Livingston

More information

Apprenticeship Standard for High Speed Rail and Infrastructure (HSRI) Advanced Technician

Apprenticeship Standard for High Speed Rail and Infrastructure (HSRI) Advanced Technician Context Health and Safety Apprenticeship Standard for High Speed Rail and Infrastructure (HSRI) Advanced Technician Occupational Profile: High speed rail is a specialist occupational area of work. High

More information

Safe Road System: Maintenance Road Watering Improvement Process.

Safe Road System: Maintenance Road Watering Improvement Process. Safe Road System: Maintenance Road Watering Improvement Process. Presenter: Authors: Abstract David Tulloch David Tulloch RoadSafety Training Services Pty Ltd David Stocker Crash Analysis & Training Consultants

More information

Remote Access to Vehicles and Condition Monitoring. Synopsis. Overview. Open standards PAPER

Remote Access to Vehicles and Condition Monitoring. Synopsis. Overview. Open standards PAPER PAPER g Remote Access to Vehicles and Condition Monitoring Synopsis In order to lower maintenance cost of rolling stock whilst raising the availability of the vehicles continuous knowledge about the state

More information

On the Road to Innovation

On the Road to Innovation On the Road to Innovation The fully integrated solution for the Laser Mapping and the Pavement Surface Inspection PAVE-SCANNER Laser Mobile System PMS-SIT Software Application Prague, Oct. 20-21 2016 ing.

More information

Transactions on the Built Environment vol 34, 1998 WIT Press, ISSN

Transactions on the Built Environment vol 34, 1998 WIT Press,  ISSN Improving the Dutch railway services by network-wide timetable simulation Jurjen S. Hooghiemstra", Dick M. Middelkoop", Maurice J.G. Teunisse^ " Railned, Dept. of Innovation, P.O.Box 2025, 3500 HA Utrecht,

More information

Track Maintenance for High Speed Rail

Track Maintenance for High Speed Rail Track Maintenance for High Speed Rail Railroad Infrastructure Diagnosis and Prognosis David E. Staplin, PE University of Nevada Las Vegas, October 17, 2018 Track Maintenance for High Speed Rail Perspective

More information

Engineering: Past, Present and Future

Engineering: Past, Present and Future Engineering: Past, Present and Future Dave Ferryman Vice President Engineering WRI Conference Montreal, Quebec June 7, 2017-0- CN Network Network Track Miles Mainline Core 8,617 Non core 12,602 Non Mainline

More information

PRINCIPLES OF RELIABILITY ENGINEERING

PRINCIPLES OF RELIABILITY ENGINEERING Training Title PRINCIPLES OF RELIABILITY ENGINEERING Training Duration 5 Days Training Date & Venue Principles of Reliability Engineering 14 18 April $3,750 Doha, Qatar In any of the 5 star hotels. The

More information

2.0 Purpose. 3.0 Work Plan. Page 1 of 7

2.0 Purpose. 3.0 Work Plan. Page 1 of 7 2.0 Purpose The purpose of this document is to present the findings of the field investigation and concept design study, as well as recommend appropriate track relocation and bridge modifications to provide

More information

ExISTING SubSTATION INfORmATIONON

ExISTING SubSTATION INfORmATIONON ExISTING SubSTATION INfORmATIONON drives equipment LIFe extension, modernization, and retrofitting david dolezilek and GeraLdo rocha, Schweitzer Engineering Laboratories, Inc. i. introduction Much of the

More information

Road Maintenance Management

Road Maintenance Management Road Maintenance Management Concepts and Systems Richard Robinson, Uno Danielson and Martin Snaith MACMILLAN Contents Foreword Preface Acknowledgements xii xiv xvi 1 Management Issues 1 1.1 Purpose of

More information

22/06/2012. LCC of Track. Peter Veit

22/06/2012. LCC of Track. Peter Veit 22/06/2012 LCC of Track The best track is the cheapest Peter Veit Graz, Austria University of Technology Quality Behaviour Cost Driver High Quality Strategies Investment Under Sleeper Pads Asphalt Layer

More information

Overview of Technical Skills and Competencies (TSC)

Overview of Technical Skills and Competencies (TSC) Business Risk and Change Business Continuity Innovation Intellectual Property (IP) Data and Statistical Analytics Strategy Planning Strategy Implementation Public Relations Strategic Human Resource Strategic

More information

Field Measurements and Analysis of Concrete Crosstie Bending Moments

Field Measurements and Analysis of Concrete Crosstie Bending Moments Field Measurements and Analysis of Concrete Crosstie Bending Moments 2016 International Crosstie & Fastening System Symposium Urbana, IL 14 June, 2016 Marcus Dersch, Zhengboyang Gao, Riley Edwards, David

More information

DISTRIBUTION SYSTEM ASSET MANAGEMENT APPROACH

DISTRIBUTION SYSTEM ASSET MANAGEMENT APPROACH EB-0-0 Exhibit D Schedule Page of DISTRIBUTION SYSTEM ASSET MANAGEMENT APPROACH This document provides a summary of THESL s asset management approach. The first two sections introduce the scope of asset

More information

The Evolution of Structures Asset Management in Wisconsin

The Evolution of Structures Asset Management in Wisconsin Dietsche, J.S. The Evolution of Structures Asset Management in Wisconsin April, 0 Word Count: 0 Joshua S. Dietsche Wisconsin Department of Transportation 0 Sheboygan Avenue, Room 0, Madison, WI 0 Phone:

More information

Asset Performance Management from GE Digital. Enabling intelligent asset strategies to optimize performance

Asset Performance Management from GE Digital. Enabling intelligent asset strategies to optimize performance Asset Performance Management from GE Digital Enabling intelligent asset strategies to optimize performance How can you make your operation safer and more reliable while helping to ensure optimal performance

More information

Asset Maintenance Management Unit 1 Introduction to Asset Maintenance Management

Asset Maintenance Management Unit 1 Introduction to Asset Maintenance Management Asset Maintenance Management Unit 1 Introduction to Asset Maintenance Management Summary of Module UNIT 1: Introduction to Asset Maintenance Management UNIT 2: UNIT 3: UNIT 4: UNIT 5: UNIT 6: UNIT 7: UNIT

More information

PROline USB Ultrasonic Testing Instrument and Systems

PROline USB Ultrasonic Testing Instrument and Systems 18th World Conference on Nondestructive Testing, 16-20 April 2012, Durban, South Africa PROline USB Ultrasonic Testing Instrument and Systems Göran Vogt VOGT Ultrasonics GmbH, Burgwedel, Germany, g.vogt@vogt-ultrasonics.de

More information

Low Carbon Railways Zac : Sakdirat Kaewunruen

Low Carbon Railways Zac : Sakdirat Kaewunruen Low Carbon Railways Zac : Sakdirat Kaewunruen BE Hons (Civil), ME, PhD, GCert (Business) MIEAust, CPEng, NPER, RPEQ Senior Lecturer in Railway and Civil Engineering TRANSPORT CO 2 Kaewunruen et al. (2016)

More information

Tools and Techniques for Data Driven Track Maintenance

Tools and Techniques for Data Driven Track Maintenance Tools and Techniques for Data Driven Track Maintenance Julian Stow Institute of Railway Research Graham Shields, Paul Gitsham Omnicom Engineering Overview Introduction Big data Data driven maintenance

More information

Also, the installation and the maintenance of the ballastless track (slab track) are described.

Also, the installation and the maintenance of the ballastless track (slab track) are described. Preface The maintenance of tracks and turnouts to ensure operational safety requires experience in operating processes, the respective work methods and the individual permanent way machines and equipment.

More information

Asset Management Plans for the National Highway System

Asset Management Plans for the National Highway System Asset Management Plans for the National Highway System Stephen Gaj Leader, Asset Management Team Office of Asset Management, Pavements, and Construction FHWA What is Asset Management? From 23 USC 101(a)(2):

More information

Enhanced Tie Condition Inspection Using Hand Held Recording Systems Allan M. Zarembski, Ph.D., P.E. President, ZETA-TECH Associates, Inc.

Enhanced Tie Condition Inspection Using Hand Held Recording Systems Allan M. Zarembski, Ph.D., P.E. President, ZETA-TECH Associates, Inc. Enhanced Tie Condition Inspection Using Hand Held Recording Systems Allan M. Zarembski, Ph.D., P.E. President, ZETA-TECH Associates, Inc. In order to most effectively and efficiently maintain the railroad

More information

Optimal Scheduling of Railroad Track Inspection Activities and Production Teams

Optimal Scheduling of Railroad Track Inspection Activities and Production Teams Optimal of Railroad Track Inspection Activities and Production Teams Fan Peng The William W. Hay Railroad Engineering Seminar Series 11 February 2011 1 Importance of Track Maintenance U.S. Class I railroads

More information

Predix Asset Performance Management. Enabling optimal asset reliability, availability, and performance

Predix Asset Performance Management. Enabling optimal asset reliability, availability, and performance Predix Asset Performance Management Enabling optimal asset reliability, availability, and performance How can you make your operation safer and more reliable while helping to ensure optimal performance

More information

Guidelines for the Application of Asset Management in Railway Infrastructure Organisations

Guidelines for the Application of Asset Management in Railway Infrastructure Organisations Guidelines for the Application of Asset Management in Railway Infrastructure Organisations INTERNATIONAL UNION OF RAILWAYS (UIC) 16 rue Jean Rey - F-75015 PARIS Tel: +33 (0)1 44 49 20 20 Fax: +33 (0)1

More information

Quarterly Maintenance Cost Report

Quarterly Maintenance Cost Report Quarterly Maintenance Cost Report October December 2018 Aurizon Network Table of Contents 1.0 Report Contents... 3 2.0 Network Performance Metrics... 4 2.1 Safety... 4 Injury Reporting Metrics... 4 Major

More information

Rail System and Turnout Services

Rail System and Turnout Services Rail System and Turnout Services Inspection and testing Diagnostics Maintenance Asset management Delivery of standard Vignole-rail turnout Asset management Rails and turnouts in the best possible condition

More information

Standard Practice for Electromagnetic (Eddy-Current) Sorting of Nonferrous Metals 1

Standard Practice for Electromagnetic (Eddy-Current) Sorting of Nonferrous Metals 1 Designation: E 703 98 An American National Standard Standard Practice for Electromagnetic (Eddy-Current) Sorting of Nonferrous Metals 1 This standard is issued under the fixed designation E 703; the number

More information

Maintenance Planning and Scheduling

Maintenance Planning and Scheduling Maintenance Planning and Scheduling Course Objectives At the end of this course, the learners will understand basic maintenance strategies understand the difference between planning and scheduling and

More information

Platino Fiber Evo: the state of the art of laser technology. For everyone

Platino Fiber Evo: the state of the art of laser technology. For everyone Press release Platino Fiber Evo: the state of the art of laser technology. For everyone Prima Power presents the new version of Platino Fiber, one of the top products of the Turin company. The 2D laser

More information

Asset Management Policy

Asset Management Policy Asset Management Policy January 2018 Introduction Our Asset Management Policy was last published in 2014. It is being updated to reflect our commitment to regularly review and improve all of our Asset

More information

SCRRA's Turnkey Rail Maintenance Service Contract

SCRRA's Turnkey Rail Maintenance Service Contract McGinley 1 SCRRA's Turnkey Rail Maintenance Service Contract Michael E. McGinley, Director of Engineering and Construction, Southern California Regional Rail Authority. Gordon S. Bachinsky, President,

More information

Analyzing and forecasting railway data using linear data analysis

Analyzing and forecasting railway data using linear data analysis Computers in Railways XI 25 Analyzing and forecasting railway data using linear data analysis E. T. Selig, G. M. Cardillo, E. Stephens & A. Smith Bentley Systems, Inc., USA and UK Abstract Railways collect

More information

How to choose the right UPS service approach

How to choose the right UPS service approach White Paper Markets Served Data center & IT By Arthur Mulligan Product Line Manager, Eaton U.S. Power Quality How to choose the right UPS service approach Introduction The old adage of, If it ain t broke,

More information

A Holistic Approach to Railway Infrastructure Asset Management

A Holistic Approach to Railway Infrastructure Asset Management International Journal of Performability Engineering Vol. 11, No. 2, March, 2015, pp. 107-120. RAMS Consultants Printed in India A Holistic Approach to Railway Infrastructure Asset Management DOVILE RAMA*

More information

Using historical data for asset management decision making Craig Knox, ISE Solution Engineering. October 10, 2017

Using historical data for asset management decision making Craig Knox, ISE Solution Engineering. October 10, 2017 Using historical data for asset management decision making Craig Knox, ISE Solution Engineering October 10, 2017 How is asset management different from work management? Process based work management build

More information

A COMPREHENSIVE BRIDGE PRESERVATION PROGRAM TO EXTEND SERVICE LIFE. Bruce Johnson 1

A COMPREHENSIVE BRIDGE PRESERVATION PROGRAM TO EXTEND SERVICE LIFE. Bruce Johnson 1 Abstract A COMPREHENSIVE BRIDGE PRESERVATION PROGRAM TO EXTEND SERVICE LIFE Bruce Johnson 1 Bridges represent a large investment in highway systems. As highway systems age, agencies should optimize the

More information

CLASS/YEAR: II MCA SUB.CODE&NAME: MC7303, SOFTWARE ENGINEERING. 1. Define Software Engineering. Software Engineering: 2. What is a process Framework? Process Framework: UNIT-I 2MARKS QUESTIONS AND ANSWERS

More information

DESTination RAIL NEWS

DESTination RAIL NEWS DESTination RAIL NEWS DESTination RAIL Newsletter Issue number 5 July 2017 SAVE THE DATE: Workshop on the DESTinationRAIL Decision Support Tool (DST) 30th November in Ljubljana DESTinationRAIL Team meet

More information

COOLING OF ROLLS USED IN HOT ROLLING OF LONG PRODUCTS

COOLING OF ROLLS USED IN HOT ROLLING OF LONG PRODUCTS COOLING OF ROLLS USED IN HOT ROLLING OF LONG PRODUCTS M. Raudensky, J. Horsky, P. Kotrbacek, M. Pohanka Brno University of Technology, Heat Transfer and Fluid Flow Laboratory, Technicka 2896/2, 616 69

More information

Pavement Management Systems. Tool for Keeping Pavement Networks in a State of Good Repair. Dr. Nick Vitillo

Pavement Management Systems. Tool for Keeping Pavement Networks in a State of Good Repair. Dr. Nick Vitillo Pavement Management Systems Tool for Keeping Pavement Networks in a State of Good Repair Dr. Nick Vitillo STATE OF GOOD REPAIR In a country, where the majority of the traveling public and companies use

More information

Amberg Rail. The comprehensive solution for railway surveying. Why choose Amberg Rail surveying solutions?

Amberg Rail. The comprehensive solution for railway surveying. Why choose Amberg Rail surveying solutions? Amberg Rail The comprehensive solution for railway surveying Why choose Amberg Rail surveying solutions? Partnership Ease of use Scalability All-in-one Swiss quality AMBERG RAIL For all tasks in railway

More information

A Stochastic Model for Railway Track Asset Management

A Stochastic Model for Railway Track Asset Management A Stochastic Model for Railway Track Asset Management John Andrews 1, Darren Prescott 1 and Florian De Rozières 2 1 - Nottingham Transportation Engineering Centre, University of Nottingham, UK, 2 - Grenoble

More information

Detailed Requirements Document (DRD) Rail Engineering Advanced Technician Level 4 Electrification Knowledge & Skills Content

Detailed Requirements Document (DRD) Rail Engineering Advanced Technician Level 4 Electrification Knowledge & Skills Content Detailed Requirements Document (DRD) Rail Engineering Advanced Technician Level 4 Electrification Knowledge & Skills Content Purpose The purpose of this Detailed Requirements Document (DRD) is to provide

More information

Design Your Safety System for Improved Uptime

Design Your Safety System for Improved Uptime Design Your Safety System for Improved Uptime Chris Brogli - Manager, Safety Business Development Incorporating integrated safety technologies in the design stage can increase machinery availability, reduce

More information

Adaptation of O&M procedures new operating, maintenance and training requirements New Delhi, 16 December 2016 Dr. Oliver Then

Adaptation of O&M procedures new operating, maintenance and training requirements New Delhi, 16 December 2016 Dr. Oliver Then Adaptation of O&M procedures new operating, maintenance and training requirements New Delhi, 16 December 2016 Dr. Oliver Then Agenda 1. Challenges 2. Aspects and consequences of flexible operation 3. Modern

More information

The Importance of Reliability in Facilities

The Importance of Reliability in Facilities SESSION NO.: T2.41 TUESDAY, MARCH 10, 2009 ROOM NO.: 341 The Importance of Reliability in Facilities Ralph Tileston Life Cycle Engineering rtileston@lce.com Overview Why do we think facilities are different?

More information

Investigating railway track asset management using a Markov analysis

Investigating railway track asset management using a Markov analysis Original Article Investigating railway track asset management using a Markov analysis Proc IMechE Part F: J Rail and Rapid Transit 2015, Vol. 229(4) 402 416! IMechE 2013 Reprints and permissions: sagepub.co.uk/journalspermissions.nav

More information

Modelling of Service Reliability Using OpenTrack

Modelling of Service Reliability Using OpenTrack Modelling of Service Reliability Using OpenTrack IT 08 Closing the Loop - Capacity and Quality of Railway Systems January 2008 Photograph copyright Pacific National Corporate Background Plateway Pty Ltd

More information

Concrete Tie Insulator Performance

Concrete Tie Insulator Performance Concrete Tie Insulator Performance Eric Gehringer Director of Track Maintenance AREMA 213 983 Agenda Concrete tie strategy Objectives of research Histogram of insulator design Terminology Failure mechanisms

More information

INVESTMENT PLAN DEVELOPMENT

INVESTMENT PLAN DEVELOPMENT Filed: September 0, 00 EB-00-0 Tab Schedule Page of INVESTMENT PLAN DEVELOPMENT.0 OVERVIEW Hydro One Transmission has four major investment categories: Sustaining, Development, Operations, and Shared Services.

More information

Optimisation of Wheelset Maintenance using Whole System Cost Modelling

Optimisation of Wheelset Maintenance using Whole System Cost Modelling RRUKA Annual Conference, 7 November 2012 1 Optimisation of Wheelset Maintenance using Whole System Cost Modelling Adam Bevan, Institute of Railway Research, University of Huddersfield Paul Molyneux-Berry,

More information

Maintenance intervention optimisation for existing railway bridges

Maintenance intervention optimisation for existing railway bridges Maintenance intervention optimisation for existing railway bridges D. Nielsen CQUniversity Australia, Rockhampton, Queensland, Australia CRC for Rail Innovation, Australia T. McSweeney CQUniversity Australia,

More information

Track desktop assessments for line speed improvements. David Ball, CEng MICE, FPWI

Track desktop assessments for line speed improvements. David Ball, CEng MICE, FPWI Track desktop assessments for line speed improvements David Ball, CEng MICE, FPWI THIS PRESENTATION WILL: Show ways to analyse and scope track works to facilitate raising the line speed from the safety

More information

GAGE RESTRAINT MEASUREMENT What is it Telling Us?

GAGE RESTRAINT MEASUREMENT What is it Telling Us? Carr & Kesler 1 GAGE RESTRAINT MEASUREMENT What is it Telling Us? Gary A. Carr J. Kevin Kesler ENSCO Inc. Springfield, Virginia 22151 ABSTRACT To improve detection of railroad track defects that cause

More information

ecotaurus the EcoHubs Truck Appointment & Unit Status Service

ecotaurus the EcoHubs Truck Appointment & Unit Status Service ecotaurus the EcoHubs Truck Appointment & Unit Status Service ecotaurus: a new breed of software services for green terminals ecotaurus is an innovative e-transport solution for real time truck terminal

More information

CONCEPTUAL DESIGN OF AN AUTOMATED REAL-TIME DATA COLLECTION SYSTEM FOR LABOR-INTENSIVE CONSTRUCTION ACTIVITIES

CONCEPTUAL DESIGN OF AN AUTOMATED REAL-TIME DATA COLLECTION SYSTEM FOR LABOR-INTENSIVE CONSTRUCTION ACTIVITIES CONCEPTUAL DESIGN OF AN AUTOMATED REAL-TIME DATA COLLECTION SYSTEM FOR LABOR-INTENSIVE CONSTRUCTION ACTIVITIES H. Randolph Thomas The Pennsylvania State University Research Building B University Park,

More information

EDDY CURRENT & RAIL MILLING 1 NEW TOOLS IN THE RAIL MANAGEMENT ENGINEER S BOX

EDDY CURRENT & RAIL MILLING 1 NEW TOOLS IN THE RAIL MANAGEMENT ENGINEER S BOX EDDY CURRENT & RAIL MILLING 1 NEW TOOLS IN THE RAIL MANAGEMENT ENGINEER S BOX Sorin L Castravete Senior Asset Engineer (Support) [Track] Route London North East, Network Rail, United Kingdom 1 Network

More information

Performance Measures for Track and Civil Infrastructure

Performance Measures for Track and Civil Infrastructure Discipline: Engineering Category: Procedure Measures for Track and Civil ETP-00-02 Applicability ARTC Wide CRIA (NSW CRN) Document Status Version Date Reviewed Prepared by Reviewed by Endorsed Approved

More information

Asset Management Performance Measures for Privatized Highway Concessions in British Columbia

Asset Management Performance Measures for Privatized Highway Concessions in British Columbia Asset Management Performance Measures for Privatized Highway Concessions in British Columbia Travis Gilbertson Geoplan Opus Consultants Inc. Victoria, British Columbia Canada 1 Outline 1. DBFO Projects

More information

A REVIEW OF ACHIEVABLE EFFICIENCIES AND ASSOCIATED ISSUES UNDER OUTPUT AND PERFORMANCE BASED CONTRACTS

A REVIEW OF ACHIEVABLE EFFICIENCIES AND ASSOCIATED ISSUES UNDER OUTPUT AND PERFORMANCE BASED CONTRACTS A REVIEW OF ACHIEVABLE EFFICIENCIES AND ASSOCIATED ISSUES UNDER OUTPUT AND PERFORMANCE BASED CONTRACTS Authors: Ewan Hunter NZCE, BE (Civil), MIPENZ and Rowan Kyle BE (Civil), B. Ag.Sc MIPENZ Page 1 1.

More information

Optimising asset management:

Optimising asset management: WHITE PAPER Optimising asset management: Four key questions to help water and wastewater organisations align asset maintenance strategies with business objectives. 2 OPTIMISING ASSET PERFORMANCE FOUR KEY

More information

Optimising asset management:

Optimising asset management: WHITE PAPER Optimising asset management: Four key questions to help water and wastewater organisations align asset maintenance strategies with business objectives. 2 OPTIMISING ASSET MANAGEMENT FOUR KEY

More information

State Of Art in Ultrasonic Spotweld Testing Offline & Inline New Materials and Coatings

State Of Art in Ultrasonic Spotweld Testing Offline & Inline New Materials and Coatings ECNDT 2006 - Th.3.4.5 State Of Art in Ultrasonic Spotweld Testing Offline & Inline New Materials and Coatings Göran VOGT, Dirk RIEGER, Carsten KÖHLER, Vogt Werkstoffprüfsysteme, Burgwedel, Deutschland

More information

STRC 7 th Swiss Transport Research Conference. The Swiss experience on the wear of railway switches & crossings. Willem-Jan Zwanenburg, LITEP - EPFL

STRC 7 th Swiss Transport Research Conference. The Swiss experience on the wear of railway switches & crossings. Willem-Jan Zwanenburg, LITEP - EPFL The Swiss experience on the wear of railway switches & crossings Willem-Jan Zwanenburg, LITEP - EPFL Conference paper STRC 2007 STRC 7 th Swiss Transport Research Conference Monte Verità / Ascona, September

More information

Shift2Rail - to deliver the ERRAC vision of the future railway?

Shift2Rail - to deliver the ERRAC vision of the future railway? Shift2Rail - to deliver the ERRAC vision of the future railway? International Railway Summit 17 February 2016, Vienna Prof Andy Doherty ERRAC Chairman CTO Network Rail 1 ERRAC s ROLE ERRAC is the ETP (European

More information

PUMP STATION CONDITION ASSESSMENT PROGRAMS: CASE STUDIES IN NORTH AND SOUTH CAROLINA

PUMP STATION CONDITION ASSESSMENT PROGRAMS: CASE STUDIES IN NORTH AND SOUTH CAROLINA PUMP STATION CONDITION ASSESSMENT PROGRAMS: CASE STUDIES IN NORTH AND SOUTH CAROLINA ABSTRACT Kathryn Benson, PE CH2MHILL; Raleigh, NC kbenson@ch2m.com The most efficient method to assess the condition

More information

Texas Pacifico Transportation South Orient Rail-line Infrastructure Assessment

Texas Pacifico Transportation South Orient Rail-line Infrastructure Assessment Texas Pacifico Transportation South Orient Rail-line Infrastructure Assessment January 2015 Contents Executive Summary i 1. Project Description and Purpose... 1 1.1 Purpose of Project... 1 1.2 Project

More information

United Utilities Integrated Catchment Approach

United Utilities Integrated Catchment Approach United Utilities Integrated Catchment Approach Addressing water issues as part of a catchment based approach Institute of Water Autumn Seminar Thursday 23 rd November 2017 United Utilities Integrated Catchment

More information

Innovative testing of advanced PLCs of sewage water pumping stations

Innovative testing of advanced PLCs of sewage water pumping stations Innovative testing of advanced PLCs of sewage water pumping stations Ivo Pothof, Kees Kooij Industrial Flow Technology, WL Delft Hydraulics P.O. Box 177 2600 MH Delft, The Netherlands ivo.pothof@wldelft.nl,

More information

Process assurance and monitoring in GMA welding Heinz Hackl, Wels

Process assurance and monitoring in GMA welding Heinz Hackl, Wels Process assurance and monitoring in GMA welding Heinz Hackl, Wels INTRODUCTION Today s ever-more stringent demands regarding weldment quality and life-span, intense cost pressure, the rapid propagation

More information

SOLUTIONS FOR THE BUILT WORLD. Assess & Prioritize. Keys to Asset Management. Carl J. Larosche, PE.

SOLUTIONS FOR THE BUILT WORLD. Assess & Prioritize. Keys to Asset Management. Carl J. Larosche, PE. SOLUTIONS FOR THE BUILT WORLD Assess & Prioritize Keys to Asset Management Carl J. Larosche, PE www.wje.com Presentation Outline The Case for Asset Management Executive Decision-making Element-based Inspection

More information

Delivering valuable analytics solutions AND landing the benefits Dan Scott, Head of AM Transformation, SEAMS

Delivering valuable analytics solutions AND landing the benefits Dan Scott, Head of AM Transformation, SEAMS Delivering valuable analytics solutions AND landing the benefits Dan Scott, Head of AM Transformation, SEAMS Introduction This session will describe the 7 year journey that London Underground has been

More information

COST EFFECTIVE MEASURE FOR TRACK IMPROVEMENT. Phil Anderson and J. S. Mundrey

COST EFFECTIVE MEASURE FOR TRACK IMPROVEMENT. Phil Anderson and J. S. Mundrey Page 1 of 5 TRANSPORTATION, WATER AND URBAN DEVELOPMENT DEPARTMENT THE WORLD BANK March 1995 Transport No. RW-11 COST EFFECTIVE MEASURE FOR TRACK IMPROVEMENT Phil Anderson and J. S. Mundrey Some developing

More information

DECISION SUPPORT FOR LIFE TIME MANAGEMENT OF HV INFRASTRUCTURES

DECISION SUPPORT FOR LIFE TIME MANAGEMENT OF HV INFRASTRUCTURES DECISION SUPPORT FOR LIFE TIME MANAGEMENT OF HV INFRASTRUCTURES E.Gulski (1), J.J.Smit (1), B. Quak (1), E.R.S.Groot (2) (1) Delft University of Technology, (2) KSANDR The Netherlands e.gulski@ewi.tudelft.nl

More information

Chapter 3: The Scheduling & Chapter 4: The Scheduling and Dispatch Process

Chapter 3: The Scheduling & Chapter 4: The Scheduling and Dispatch Process Chapter 3: The Scheduling & Chapter 4: The Scheduling and Dispatch Process 1 Foreword Our scheduling and dispatch process incorporates a range of activities associated with managing the close to real-time

More information

FOCUS GROUP SESSION 21 JUNE 2018

FOCUS GROUP SESSION 21 JUNE 2018 SERVICE PERFORMANCE: BASELINE TARGETS FOCUS GROUP SESSION 21 JUNE 2018 AGENDA AND PURPOSE FOR FORUM Purpose: An interactive session to discuss and answer any questions on the proposed baseline service

More information

Fundamentals of Asset Management. Step 7. Optimize Operations & Maintenance (O&M) Investment A Hands-On Approach

Fundamentals of Asset Management. Step 7. Optimize Operations & Maintenance (O&M) Investment A Hands-On Approach Fundamentals of Asset Management Step 7. Optimize Operations & Maintenance (O&M) Investment A Hands-On Approach Tom s bad day Fundamentals of Asset Management 2 Fourth of 5 core questions 4. What are my

More information

AEP Guidelines for Transmission Owner Identified Needs

AEP Guidelines for Transmission Owner Identified Needs AEP Guidelines for Transmission Owner January 2017 1 Document Control Document Review and Approval Action Name(s) Title Prepared by: Kevin Killingsworth Principal Engineer, Asset Performance and Renewal

More information

12 The Supply Chain What is the rail industry supply chain?

12 The Supply Chain What is the rail industry supply chain? 12 The Supply Chain Not having the right parts when you need them can be a reason for non-availability of vehicles for service (as the analysis described in Section 6.5 may show). It is a false economy

More information

Enterprise Asset Management. Enterprise Asset Management 1

Enterprise Asset Management. Enterprise Asset Management 1 Enterprise Asset Management 1 Introduction Managing assets effectively is critical to the success of organisations that depend on complex physical assets to deliver services. Increasingly, operators and

More information

Asset Investment Management (AIM) March 2017

Asset Investment Management (AIM) March 2017 Asset Investment Management (AIM) March 2017 AIM Introduction Designed to demonstrate the benefits of different asset management strategies. Requirement to plan and implement different asset management

More information

Maintenance Management

Maintenance Management Maintenance Management 16/11/2016 Emad Elbeltagi 1 Definition Current Practices Types of Failures Agenda Maintenance Strategies Types of Maintenance Repair and Maintenance 16/11/2016 Emad Elbeltagi 2 1

More information

None City Council March 20, C598 - Infrastructure Asset Management Policy

None City Council March 20, C598 - Infrastructure Asset Management Policy CITY POLICY REFERENCE: POLICY NUMBER: C598 ADOPTED BY: None City Council March 20, 2018 SUPERSEDES: New PREPARED BY: Integrated Infrastructure Services DATE: March 2018 TITLE: Policy Statement: C598 -

More information

ABSTRACT 1 INTRODUCTION

ABSTRACT 1 INTRODUCTION ABSTRACT Tube Sheet Runner Sergio Galošić, Matija Vavrouš, Marko Budimir INETEC Institute for Nuclear Technology Dolenica 28, 10250 Zagreb, Croatia sergio.galosic@inetec.hr, matija.vavrous@inetec.hr, marko.budimir@inetec.hr

More information

ESTIMATING MAINTENANCE COSTS FOR MIXED HIGHER SPEED PASSENGER AND FREIGHT RAIL CORRIDORS

ESTIMATING MAINTENANCE COSTS FOR MIXED HIGHER SPEED PASSENGER AND FREIGHT RAIL CORRIDORS Proceedings of the 2010 Joint Rail Conference JRC20104 April April 27-29, 27-29, 2010, 2010, Urbana, Urbana, Illinois, IL, USA JRC2010-36036 JRC2010- ESTIMATING MAINTENANCE COSTS FOR MIXED HIGHER SPEED

More information

Predictive Maintenance 4.0

Predictive Maintenance 4.0 Digitalization Predictive Maintenance 4.0 for Motor/Gearbox Units INCREASING AVAILABILITY AND BOOSTING PRODUCTIVITY Drive Train 4.0 Predictive maintenance expands conventional condition monitoring approaches

More information