IMPROVING OUTAGE PERFORMANCE: THE OUTAGE OPTIMIZATION PROCESS

Size: px
Start display at page:

Download "IMPROVING OUTAGE PERFORMANCE: THE OUTAGE OPTIMIZATION PROCESS"

Transcription

1

2 IMPROVING OUTAGE PERFORMANCE: THE OUTAGE OPTIMIZATION PROCESS Jere LaPlatney VP Outage Optimization Jean-Paul Bombail Outage and Maintenance IB France October 2011

3 AGENDA BACKGROUND OUTAGE OPTIMIZATION PRINCIPLES OUTAGE OPTIMIZATION PROCESS OVERVIEW OUTAGE PREPARATION PHASE OUTAGE EXECUTION PHASE CONCLUSION IMPROVING OUTAGE PERFORMANCE - Jere LaPlatney - 20 octobre p.3

4 BACKGROUND Drivers to improve outage performance: Outage performance has a very large impact on overall station performance metrics for the year (e.g. Industrial, radiological and nuclear safety, budget, capacity factor, etc.) Lost generation costs are high for baseloaded units (highly variable but $750,000 USD/day is a reasonable figure for discussion) Amount and quality of work done affects subsequent cycle CF (Capacity Factor) Effort has its roots in the US during the drive to deregulation in the 1980 s and 90 s This paper provides an overview of the process of Outage Optimization along with some specific examples of some of the key management tools used IMPROVING OUTAGE PERFORMANCE - Jere LaPlatney - 20 octobre p.4

5 OUTAGE OPTIMIZATION PRINCIPLES Outage Optimization vs. Outage Shortening Goal: safe, reliable and cost effective plant operation. PRINCIPLES: Duration is not the sole measure of outage success Outage work must be performed safely from all perspectives: Nuclear, Industrial, and Radiological Scope selection must focus on improving plant material condition to improve reliability All approved outage work must be completed Work must be done cost effectively Post-outage plant reliability is a key measure of outage success Outage Lessons Learned must be effectively implemented to achieve continuous improvement IMPROVING OUTAGE PERFORMANCE - Jere LaPlatney - 20 octobre p.5

6 OUTAGE OPTIMIZATION PROCESS OVERVIEW A planned outage at an NPP is simply a specialized type of project, and the principles of sound project management apply An outage differs slightly from most industrial projects in that the schedule is optimized on duration (Critical Path) rather than the usual cost This is driven by the high financial impact of having a baseload NPP shut down (dependent on market conditions and plant size, typically in excess of $750,000USD/day). IMPROVING OUTAGE PERFORMANCE - Jere LaPlatney - 20 octobre p.6

7 OUTAGE OPTIMIZATION PROCESS OVERVIEW Areas Addressed by Outage Optimization The Tool: Gap Analysis Start With the Critical Path System Windows Manage Work Off Critical Path Reducing Outage Scope: On-line Maintenance IMPROVING OUTAGE PERFORMANCE - Jere LaPlatney - 20 octobre p.7

8 OUTAGE OPTIMIZATION PROCESS OVERVIEW Areas Addressed by Outage Optimization The major areas to be addressed by an Outage Optimization process are: Scope selection and control Outage Preparation Schedule development and optimization Critical Path (Outage Window) optimization Shutdown Risk Management (nuclear safety risk) System Window planning Work documentation preparation, including contingency Work resourcing Outage Execution Outage execution organization Outage execution processes Continuous Improvement (lessons learned) IMPROVING OUTAGE PERFORMANCE - Jere LaPlatney - 20 octobre p.8

9 OUTAGE OPTIMIZATION PROCESS OVERVIEW The Tool: Gap Analysis A generic improvement process, so called Gap Analysis, has been used by many NPP operators to manage the improvement process GAP Analysis consists of five steps which form a continuous improvement cycle: Using benchmarking, identify how current performance compares to best in industry performance, and identify the performance gaps. Starting with the largest gaps, drill down into the detail to identify the specific differences between the NPP s method and the best practice method (commonly referred to as micro-gap analysis) Perform cost/benefit analysis on adopting best practice to the specific NPP Implement the changes identified as appropriate to the NPP. Monitor performance and start over to the next round of improvement The cyclic nature of the process is a result of the fact that making improvements typically results in a new Critical Path, and this can itself be subject to new Gap Analysis. The overall process has been likened to peeling back an onion wherein each round of improvement exposes where the next improvements can be made. IMPROVING OUTAGE PERFORMANCE - Jere LaPlatney - 20 octobre p.9

10 OUTAGE OPTIMIZATION PROCESS OVERVIEW Start With the Critical Path For a Light Water Reactor (LWR) the theoretical critical path for a Refueling Outage is the plant shutdown, refueling and plant restart sequence. These are the absolute minimum activities that must be done to allow another cycle of plant operation. In order to facilitate benchmarking, the Westinghouse Owners Group (WOG) was the first to develop a set of nine Outage Windows for PWRs. These Outage Windows break up the critical path into smaller component parts. AREVA, through the Framatome Owners Group (FROG) has developed its FROG Outage Windows and also collects and shares this benchmarking data on its member s behalf IMPROVING OUTAGE PERFORMANCE - Jere LaPlatney - 20 octobre p.10

11 OUTAGE OPTIMIZATION PROCESS OVERVIEW FROG WINDOW NUMBER FROG MILESTONE NUMBERS OUTAGE MILESTONE DESCRIPTION F 1 FR 00 - FR 10 Off line to Mode 5 (<90 C) F 2 FR 10 - FR 20 Mode 5 (<90 C) to mode 6 (1st RV stud detensioned) F 3 FR 20 - FR 30 Mode 6 (1st RV stud detensioned) to latch the 1st fuel assembly F 4 FR 30 - FR 40 Latch the 1st fuel assembly to last fuel assembly in the fuel building F 5 FR 40 - FR 50 Defueled F 6 FR 50 - FR 60 Latch the 1st fuel assembly in the fuel building to core mapping complete F 7 FR 60 - FR 70 Core mapping complete to complete set of the RV head on the vessel F 8 FR 70 - FR 80 RV head on the vessel to last stud tensioned F 9 FR 80 - FR 90 RV last stud tensioned (mode 5) to start and remain running the first RCS pump F 10 FR 100 -FR 110 Start and remain running the first RCS pump to > 90 C (mode 4) F 11 FR 110 -FR 120 >90 C (mode 4) to RHR isolated or SI aligned (177 C mode 3) F 12 FR FR130 RHR isolated or SI aligned (177 C mode 3)to start dilution for criticality (mode 2) F 13 FR 130 -FR 140 Start dilution for criticality (mode 2) to connection to the grid (on line) END OF THE OUTAGE PERIOD F 14 FR FR 140 Connection to the grid (on line) to full power IMPROVING OUTAGE PERFORMANCE - Jere LaPlatney - 20 octobre p.11

12 OUTAGE OPTIMIZATION PROCESS OVERVIEW System Windows Manage Work Off Critical Path The goal of a refueling outage is not only to refuel the reactor in the shortest possible time, but also complete all maintenance that requires plant shutdown conditions to accomplish in order to ensure a breaker to breaker run post outage. The nuclear core must be kept in a controlled, subcritical, cooled configuration at all times with adequate safety system protection and defense in depth. These competing requirements cause most NPPs divide the overall schedule into System Windows which sequence the removal and restoration of plant systems for maintenance while maintaining adequate hardware in service and available for defense in depth. All work must be planned in the System Window (or Windows) in which the correct plant conditions exist to safely remove the component to be maintained. IMPROVING OUTAGE PERFORMANCE - Jere LaPlatney - 20 octobre p.12

13 OUTAGE OPTIMIZATION PROCESS OVERVIEW Reducing Outage Scope: On-line Maintenance Most US plants have chosen to move as much work as possible out of the planned outage period and into the operating period (know as on-line maintenance ) This strategy fully supports outage optimization but reducing overall outage scope thus reducing duration and/or risk to duration while simultaneously supporting reliable plant operation since all maintenance work is done The effect of implementing this philosophy has significantly reduced the outage scope (while maintaining the work in the online period) from a typical value of 5,000 to 8,000 work tasks down to 2,500 to 5,000 work tasks dependent on plant specific considerations IMPROVING OUTAGE PERFORMANCE - Jere LaPlatney - 20 octobre p.13

14 OUTAGE PREPARATION PHASE Outage Preparation Overview Outage Preparation Milestones Performance Indicators Lessons Learned Readiness Reviews Pre-outage Work IMPROVING OUTAGE PERFORMANCE - Jere LaPlatney - 20 octobre p.14

15 OUTAGE PREPARATION PHASE OUTAGE PREPARATION PHASE Outage Preparation Overview Preparation for a Refueling Outage is a long term planning operation 2,500-5,000 maintenance tasks must be planned into a schedule with 8,000 to 13,000 logic linked activities The work packages must be prepared, the work resourced and then resource leveled The entire schedule must be reviewed to ensure that Shutdown Risk Management principles are adhered to and adequate defense-in-depth maintained at all times An Outage Execution organization must be identified, staffed and trained A multitude of detailed preparations must be managed This section will cover some of the more important tools used IMPROVING OUTAGE PERFORMANCE - Jere LaPlatney - 20 octobre p.15

16 OUTAGE PREPARATION PHASE Outage Preparation Milestones The roadmap for the Outage Preparation period is the suite of Outage Preparation Milestones Milestones are a series of logically sequenced actions that the NPP must achieve in order to be ready to go when the plant is shutdown for the outage The Milestones are high level, but contain enough detail to ensure the intent is clear In many cases achievement of later milestones is dependent of timely completion of early milestones IMPROVING OUTAGE PERFORMANCE - Jere LaPlatney - 20 octobre p.16

17 OUTAGE PREPARATION PHASE MILESTONE DATE Issue Outage Milestone Schedule M-18 Set Outage Goals and Identify Major workscope M-16 Select Plant Design changes for the outage M-16 Identify Regulatory Documents needed for startup M-14 Identify detailed outage scope M-13 Identify long lead materials M-12 Establish High Impact Teams (HIT) M-12 Freeze Outage Scope M-10 IMPROVING OUTAGE PERFORMANCE - Jere LaPlatney - 20 octobre p.17

18 Performance Indicators OUTAGE PREPARATION PHASE Timely achievement of the milestones is essential to being prepared on time Performance Indicators are used to track progress. These are simply standard work-off or burn curves wherein planned production is tracked vs. actual production. The advantage of the performance indicators over simple milestones is that adverse trends can be spotted early and recovery plans put in place to ensure that the milestone is achieved on the original schedule thus preserving the accomplishment of subsequent, dependent milestones IMPROVING OUTAGE PERFORMANCE - Jere LaPlatney - 20 octobre p.18

19 OUTAGE PREPARATION PHASE IMPROVING OUTAGE PERFORMANCE - Jere LaPlatney - 20 octobre p.19

20 Lessons Learned OUTAGE PREPARATION PHASE Critical to a successful Outage Optimization campaign, is an effective Lessons Learned program A healthy Lesson Learned program will result in lessons learned being generated each outage Every one of these should be recorded, evaluated and dispositioned prior to the subsequent outage Management should track progress on closing the lessons learned by including it in the set of performance indicators that it routinely monitors Failure to implement an effective lessons learned program will undermine any other efforts to improve outage performance as old problems will continuously return and stop progress IMPROVING OUTAGE PERFORMANCE - Jere LaPlatney - 20 octobre p.20

21 OUTAGE PREPARATION PHASE Readiness Reviews Management involvement in outage preparation is a key element in a successful Outage Optimization project The use of formal Readiness Reviews has become commonplace in the US in recent years Chaired by senior station management Participants include leaders from all plant departments, major contractors, and corporate support staff Typically conducted at dates prior to the outage of t-6, 3, and 1 months Actions are assigned from the meeting and completion of actions is tracked by the Outage Manager, and monitored by senior management IMPROVING OUTAGE PERFORMANCE - Jere LaPlatney - 20 octobre p.21

22 OUTAGE PREPARATION PHASE Pre-outage Work A simple principle applies any pre-outage work not completed becomes outage work and thus threatens successful completion of the outage to plan Pre-outage work typically consists of the following types of tasks: Scaffold erection in accessible areas Temporary power and light installation Temporary accommodation and office space In Service Testing In Service Inspection IMPROVING OUTAGE PERFORMANCE - Jere LaPlatney - 20 octobre p.22

23 OUTAGE EXECUTION PHASE Outage Control Center (OCC) Operations Department Improvements IMPROVING OUTAGE PERFORMANCE - Jere LaPlatney - 20 octobre p.23

24 Outage Control Center (OCC) OUTAGE EXECUTION PHASE The OCC is the nerve center for the outage: monitoring and controlling all the outage work in a proactive fashion personnel representing all site departments as well as major contractors Each individual in the OCC has written roles and responsibilities for monitoring progress and managing problems OCC members are equipped with excellent communication tools The OCC Manager, reports to the Outage Manager Schedules, work off curves, window closure reports and other tools are continuously used to assess where are we? Meetings, or more accurately, briefs are conducted routinely and frequently in the OCC - In a typical 12 hr shift, there are handover meetings at either end as well as briefs every 2-4 hours. IMPROVING OUTAGE PERFORMANCE - Jere LaPlatney - 20 octobre p.24

25 Operations Department Improvements OUTAGE EXECUTION PHASE The basic principle behind the improvements in Operations is the separation of the control of plant function from the maintenance support function which is done by Work Crews Control of the plant is retained in the Control Room with a minimum shift complement, typically on 12 hour shifts. The 12 hour shifts minimize the number of turnovers and thus disruption to outage work, and maximize the continuity of the on shift crews since they turn over with only one other shift. The Work Crews are divided up into groups led by an SRO who are assigned to support specific groups of work - typical areas covered by an Operations Work Crew are: NSSS, BOP, and Electrical systems. Members of the Crew were involved heavily in the Outage Preparation phase in the development of their schedule, safety tagouts, and plant restoration plans IMPROVING OUTAGE PERFORMANCE - Jere LaPlatney - 20 octobre p.25

26 OUTAGE EXECUTION PHASE Operations Department Improvements (continued) Crews report to their SRO who manages them, but gets permission from the Control Room for anything that affect plant operation Work Crew members can be used by the Control Room for evolutions requiring more than the shift complement, such as integrated plant testing Work Crew members isolate and drain systems and hang and remove safety tags, and perform post maintenance retest. Plants who conduct excellent outages have taken the step of resource loading Operations department staff into the schedule IMPROVING OUTAGE PERFORMANCE - Jere LaPlatney - 20 octobre p.26

27 CONCLUSION Improving outage performance is very important to operators of NPPs worldwide. They are able to benefit from the experience of others to improve themselves by initiating an Outage Optimization program at their plants. IMPROVING OUTAGE PERFORMANCE - Jere LaPlatney - 20 octobre p.27

28 The information in this document are AREVA property and are intended solely for the addressees. Reproduction and distribution are prohibited. Thank you IMPROVING OUTAGE PERFORMANCE - Jere LaPlatney - 20 octobre p.28

2.0 SCHEDULE DEVELOPMENT

2.0 SCHEDULE DEVELOPMENT Filed: 0-0- Exhibit D Tab Page of 0 0 0 PROGRAM SCHEDULE.0 OVERVIEW The ability to validate, integrate, oversee and ultimately to retain control over the program schedule is one of the key factors that

More information

Identification Selection Definition Execution. Schedule.

Identification Selection Definition Execution. Schedule. SCHEDULE DEVELOPMENT Schedule development is the identification, definition and sequencing of activities that are required to be performed for successful completion of the project scope. Identification

More information

OSART Good Practices MAINTENANCE Outage management

OSART Good Practices MAINTENANCE Outage management OSART Good Practices MAINTENANCE Outage management Mochovce, Slovakia Mission Date; 4-20 Sep., 2006 Transparent control of the EMO unit outages during preparation and implementation of outage. Responsible

More information

Lessons learned from Angra 1 & Angra 2 NPP s Outages

Lessons learned from Angra 1 & Angra 2 NPP s Outages Lessons learned from Angra 1 & Angra 2 NPP s Outages DO Diretoria de Operação SM.O Superintendência de Manutenção Preparado por: Luciano Junqueira Calixto Email: lucical@eletronuclear.gov.br Angra 1: Angra

More information

Risks Associated with Shutdown in PWRs

Risks Associated with Shutdown in PWRs International Conference Nuclear Option in Countries with Small and Mi Opatija, Croatia, 1996 Risks Associated with Shutdown in PWRs Igor Grlicarev Slovenian Nuclear Safety Administration Vojkova 59, 1113

More information

DRAFT REGULATORY GUIDE DG-1082 ASSESSING AND MANAGING RISK BEFORE MAINTENANCE ACTIVITIES AT NUCLEAR POWER PLANTS

DRAFT REGULATORY GUIDE DG-1082 ASSESSING AND MANAGING RISK BEFORE MAINTENANCE ACTIVITIES AT NUCLEAR POWER PLANTS U.S. NUCLEAR REGULATORY COMMISSION December 1999 OFFICE OF NUCLEAR REGULATORY RESEARCH Division 1 Draft DG-1082 DRAFT REGULATORY GUIDE Contact: W.E. Scott (301) 415-1020 DRAFT REGULATORY GUIDE DG-1082

More information

Executing the Darlington refurbishment project Year 1

Executing the Darlington refurbishment project Year 1 Outage Management and Plant Maintenance Special Section Executing the Darlington refurbishment project Year 1 The Darlington refurbishment project passed its first major milestone and hit other important

More information

EVALUATION OF SAFETY CULTURE IN WANO PRE-STARTUP REVIEWS

EVALUATION OF SAFETY CULTURE IN WANO PRE-STARTUP REVIEWS EVALUATION OF SAFETY CULTURE IN WANO PRE-STARTUP REVIEWS Todd Brumfield World Association of Nuclear Operators (WANO) Atlanta, Georgia, USA ABSTRACT: The requirements for performance of pre-startup reviews

More information

STRATEGIES TO REDUCE PWR INSPECTION TIME

STRATEGIES TO REDUCE PWR INSPECTION TIME FR0200281 STRATEGIES TO REDUCE PWR INSPECTION TIME Javier Guerra (1), Emilio Gonzalez (1) M) Tecnatom S.A. - Spain Key words : Inspection, PWR, Vessel ABSTRACT During last few years, a constant reduction

More information

RECORDS MANAGEMENT FOR BUILDING CLOSURE PROJECTS: FEDERAL FACILITY BEST PRACTICES. W. David Featherman Project Performance Corporation

RECORDS MANAGEMENT FOR BUILDING CLOSURE PROJECTS: FEDERAL FACILITY BEST PRACTICES. W. David Featherman Project Performance Corporation RECORDS MANAGEMENT FOR BUILDING CLOSURE PROJECTS: FEDERAL FACILITY BEST PRACTICES W. David Featherman Project Performance Corporation ABSTRACT This paper presents the results of a benchmarking analysis

More information

Zion Project Overview S. Chris Baker VP EH&S

Zion Project Overview S. Chris Baker VP EH&S Zion Project Overview S. Chris Baker VP EH&S 1 Agenda Asset Sale Agreement Organization Nuclear Decommissioning Process Overview of Zion Station Decommissioning Schedule Near Term Activities Spent Fuel

More information

Turnaround/Shutdown Optimization

Turnaround/Shutdown Optimization Turnaround/Shutdown Optimization A Turnaround (TA) by definition is a planned, periodic event where one or more processing/production units are temporarily removed from service. In the manufacturing sector,

More information

Concepts and Features of ATMEA1 TM as the latest 1100 MWe-class 3-Loop PWR Plant

Concepts and Features of ATMEA1 TM as the latest 1100 MWe-class 3-Loop PWR Plant 8 Concepts and Features of ATMEA1 TM as the latest 1100 MWe-class 3-Loop PWR Plant KOZO TABUCHI *1 MASAYUKI TAKEDA *2 KAZUO TANAKA *2 JUNICHI IMAIZUMI *2 TAKASHI KANAGAWA *3 ATMEA1 TM is a 3-loop 1100

More information

Organization and Responsibilities of Internal/External TSO

Organization and Responsibilities of Internal/External TSO Organization and Responsibilities of Internal/External TSO International Conference on Challenges Faced by TSOs in Enhancing Nuclear Safety and Security Beijing, 29 October, 2014 N. Kilic IAEA-NE Content

More information

Efficiency Bulletin: Maximizing the Benefit of Portable Equipment

Efficiency Bulletin: Maximizing the Benefit of Portable Equipment March 23, 2017 Color Code: Green Efficiency Bulletin: 17-10 Maximizing the Benefit of Portable Equipment Utilize portable equipment, including equipment procured as a part of the B.5.b and FLEX programs,

More information

Evaluation of Nuclear Safety Culture During the Pre-Operational Phase

Evaluation of Nuclear Safety Culture During the Pre-Operational Phase Evaluation of Nuclear Safety Culture During the Pre-Operational Phase Todd Brumfield WANO-World Association of Nuclear Operators Formed in 1989 following accident at Chernobyl Has members in more than

More information

Revision 0. PPA AP Procedure Performance Metrics

Revision 0. PPA AP Procedure Performance Metrics Revision 0 Procedure Performance Metrics JANUARY 2016 Page 2 of 18, Revision 0, Procedure Performance Metrics Approved on 1/12/2016 Approved By Bruce Mills, PPA Chairman Notice Neither PPA nor any of its

More information

Maintenance Optimization: A Critical Aspect of the Equipment Reliability Program

Maintenance Optimization: A Critical Aspect of the Equipment Reliability Program Maintenance Optimization: A Critical Aspect of the Equipment Reliability Program Russ Warren, INPO IAEA, Vienna October 2011 Process Overview FEGs and Crit. for Work Management To Work Management To Budgeting

More information

IAEA-TECDOC Probabilistic safety assessments of nuclear power plants for low power and shutdown modes

IAEA-TECDOC Probabilistic safety assessments of nuclear power plants for low power and shutdown modes IAEA-TECDOC-1144 Probabilistic safety assessments of nuclear power plants for low power and shutdown modes March 2000 The originating Section of this publication in the IAEA was: Safety Assessment Section

More information

Torness tackles biggest-ever outage

Torness tackles biggest-ever outage EDF Energy s Torness nuclear power station, located in East Lothian, Scotland (Photos: EDF Energy) Torness tackles biggest-ever outage By Dick Kovan The torness-1 advanced gas-cooled reactor (agr) was

More information

Preparation of NPP Dukovany Periodic Safety Review

Preparation of NPP Dukovany Periodic Safety Review Preparation of NPP Dukovany Periodic Safety Review Dubský Ladislav Petr Vymazal Nuclear Research Institute Řež plc., Czech Republic ČEZ, a.s., Nuclear Division, Dukovany NPP, Czech Republic 1. ABSTRACT

More information

Heavy Component Replacement in Nuclear Power Plants

Heavy Component Replacement in Nuclear Power Plants Heavy Component Replacement in Nuclear Power Plants Steve Sills, Vice President Business Development, SGT Darren Wood, Manager Component Replacements, AREVA Purpose and Process Goal Recent successes and

More information

Technical Support Organization - Organization and Interfaces -

Technical Support Organization - Organization and Interfaces - Technical Support Organization - Organization and Interfaces - IAEA Technical Meeting TM-45318 Vienna, 15-17 May, 2013 Scientific Secretary: A. N. Kilic What is TSO? TSO is an organization with the mission

More information

PRESS CONFERENCE. 3 September Jean-Bernard LÉVY Chairman and CEO. Xavier URSAT Group Senior Executive VP - New Nuclear Projects and Engineering

PRESS CONFERENCE. 3 September Jean-Bernard LÉVY Chairman and CEO. Xavier URSAT Group Senior Executive VP - New Nuclear Projects and Engineering PRESS CONFERENCE 3 September 2015 Jean-Bernard LÉVY Chairman and CEO Xavier URSAT Group Senior Executive VP - New Nuclear Projects and Engineering EDF, A RESPONSIBLE ELECTRICITY COMPANY, A CHAMPION OF

More information

LOCKOUT TAGOUT SAFETY PROGRAM

LOCKOUT TAGOUT SAFETY PROGRAM 1. PURPOSE To establish procedures for affixing appropriate lockout/tagout equipment to energy isolating devices and to otherwise disable machines or equipment to prevent unexpected energization, start

More information

Format and Content of the Safety Analysis Report for Nuclear Power Plants - Core Set -

Format and Content of the Safety Analysis Report for Nuclear Power Plants - Core Set - Format and Content of the Safety Analysis Report for Nuclear Power Plants - Core Set - 2013 Learning Objectives After going through this presentation the participants are expected to be familiar with:

More information

Reactor core comprising small diameter fuel, channels rather that one large pressure vessel.

Reactor core comprising small diameter fuel, channels rather that one large pressure vessel. 1 Reactor core comprising small diameter fuel, channels rather that one large pressure vessel. Allows on-power refueling - extremely high capability factors are possible. The moveable fuel bundles in the

More information

Integrated Head Assembly (IHA) A Comprehensive Solution

Integrated Head Assembly (IHA) A Comprehensive Solution Integrated Head Assembly (IHA) A Comprehensive Solution Innovative best practices. Dependable performance. Proven success reductions of six critical path days. What is the IHA? It is the future. The focus

More information

Integration of Human and Organization Factors in Canada

Integration of Human and Organization Factors in Canada Integration of Human and Organization Factors in Canada Presented to International Atomic Energy Agency Technical Meeting on the Interaction between Individuals Technology and Organization A Systemic Approach

More information

SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES

SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES SECTION: SFPUC INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURE NO: 018 TITLE: SYSTEM TESTING AND START-UP APPROVED:

More information

Watts Bar Nuclear Plant Unit 2 Completion Project

Watts Bar Nuclear Plant Unit 2 Completion Project Watts Bar Nuclear Plant Unit 2 Completion Project Fifth Quarterly Update to the Estimate to Complete May 2013 - July 2013 Published October 2013 Table of Contents Section 1 - Executive Summary... 3 Quarterly

More information

Title: Lockout / Tagout Effective Date: 11/28/2014 Control Number: THG_0008 Revision Number: 1 Date: 10/8/2015 Annual Review Completed: 5/13/2015

Title: Lockout / Tagout Effective Date: 11/28/2014 Control Number: THG_0008 Revision Number: 1 Date: 10/8/2015 Annual Review Completed: 5/13/2015 Title: Lockout / Tagout Effective Date: 11/28/2014 Control Number: THG_0008 Revision Number: 1 Date: 10/8/2015 Annual Review Completed: 5/13/2015 Lockout / Tagout CONTENTS I. PURPOSE II. SCOPE III. DEFINITIONS

More information

Use of PSA to Support the Safety Management of Nuclear Power Plants

Use of PSA to Support the Safety Management of Nuclear Power Plants S ON IMPLEMENTATION OF THE LEGAL REQUIREMENTS Use of PSA to Support the Safety Management of Nuclear Power Plants РР - 6/2010 ÀÃÅÍÖÈß ÇÀ ßÄÐÅÍÎ ÐÅÃÓËÈÐÀÍÅ BULGARIAN NUCLEAR REGULATORY AGENCY TABLE OF CONTENTS

More information

Lockout/Tagout Program

Lockout/Tagout Program DEPAUL UNIVERSITY Lockout/Tagout Program Environmental Health & Safety November 2017 1 TABLE OF CONTENTS SECTION PAGE NO. 1.0 PURPOSE 2 2.0 SCOPE 2 3.0 RESPONSIBLITIES 2 3.1 FACILITY OPERATIONS 2 3.2 FO

More information

Applicability of EPRI Decommissioning Pre-Planning Manual to International Decommissioning Projects

Applicability of EPRI Decommissioning Pre-Planning Manual to International Decommissioning Projects Applicability of EPRI Decommissioning Pre-Planning Manual to International Decommissioning Projects Leo Lessard Manager, Commercial Decommissioning Operations, AREVA Inc. 16th February 2016 International

More information

OUTAGE OM&A NUCLEAR. 1.0 PURPOSE This evidence presents nuclear outage OM&A costs for the period

OUTAGE OM&A NUCLEAR. 1.0 PURPOSE This evidence presents nuclear outage OM&A costs for the period Filed: 0-0- EB-0-0 Tab Page of 0 OUTAGE OM&A NUCLEAR.0 PURPOSE This evidence presents nuclear outage OM&A costs for the period 0-0..0 OVERVIEW Outage OM&A costs vary year over year depending on the number

More information

EXAMPLE OF SEVERE ACCIDENT MANAGEMENT GUIDELINES VALIDATION AND VERIFICATION USING FULL SCOPE SIMULATOR

EXAMPLE OF SEVERE ACCIDENT MANAGEMENT GUIDELINES VALIDATION AND VERIFICATION USING FULL SCOPE SIMULATOR International Conference Nuclear Energy in Central Europe 2001 Hoteli Bernardin, Portorož, Slovenia, September 10-13, 2001 www: http://www.drustvo-js.si/port2001/ e-mail: PORT2001@ijs.si tel.:+ 386 1 588

More information

Decommissioning Planning for Nuclear Units at the Oskarshamn Site

Decommissioning Planning for Nuclear Units at the Oskarshamn Site PREDEC 2016: Decommissioning Planning for Nuclear Units at the Oskarshamn Site, February 16-18, Lyon, France Decommissioning Planning for Nuclear Units at the Oskarshamn Site Thom RANNEMALM a, Jörgen ERIKSSON

More information

ESSENTIAL SAFETY RESOURCES

ESSENTIAL SAFETY RESOURCES ESSENTIAL SAFETY RESOURCES GS-3023 LOCKOUT / TAGOUT PROGRAM Originator: Safety Advisor s Signature: Type Name Approval: HSE Manager s Signature: Type Name Approval: Operations Manager s Signature: Type

More information

IAEA International Experts Meeting on Severe Accident Management in the Light of the Accident at the Fukushima Daiichi Nuclear Power Plant

IAEA International Experts Meeting on Severe Accident Management in the Light of the Accident at the Fukushima Daiichi Nuclear Power Plant IAEA International Experts Meeting on Severe Accident Management in the Light of the Accident at the Fukushima Daiichi Nuclear Power Plant Enhancements to Severe Accident Management Guidelines to Address

More information

Boiling Water Reactor Vessel and Internals Project (QA)

Boiling Water Reactor Vessel and Internals Project (QA) Boiling Water Reactor Vessel and Internals Project (QA) Program Description Program Overview As boiling water reactors have aged, various forms of operation-limiting stress corrosion cracking have appeared,

More information

FROG Owners Group A Worldwide Network of Experience. April 2012

FROG Owners Group A Worldwide Network of Experience. April 2012 FROG Owners Group A Worldwide Network of Experience April 2012 Origin FROG founded in 1991 Founding Members = utilities operating or building Nuclear Power Plants with Framatome supplying Nuclear Steam

More information

Fatigue Monitoring for Demonstrating

Fatigue Monitoring for Demonstrating Fatigue Monitoring for Demonstrating Fatigue Design Basis Compliance Timothy J. Griesbach Structural Integrity Associates IAEA 2 nd International Symposium on Nuclear Power Plant Life Mgmt. 15-18 October,

More information

IAEA Training in level 1 PSA and PSA applications. Other PSA s. Low power and shutdown PSA

IAEA Training in level 1 PSA and PSA applications. Other PSA s. Low power and shutdown PSA IAEA Training in level 1 PSA and PSA applications Other PSA s Low power and shutdown PSA Content Why shutdown PSA? Definitions Plat damage states and Plant operational states Specific modelling tasks of

More information

Is Green Good Enough? Managing Shutdown Risk in Generation III+ Nuclear Power Plants

Is Green Good Enough? Managing Shutdown Risk in Generation III+ Nuclear Power Plants Is Green Good Enough? Managing Shutdown Risk in Generation III+ Nuclear Power Plants Aaron Moreno Senior Engineer Nathan Larson Principal Engineer Glen Rose, TX Ken Kiper Technical Manager Newfields, NH

More information

DEVELOPMENT OF LOW POWER SHUTDOWN LEVEL 1 PSA MODEL FOR WESTINGHOUSE TYPE REACTORS IN KOREA : OVERVIEW, RESULTS AND INSIGHTS

DEVELOPMENT OF LOW POWER SHUTDOWN LEVEL 1 PSA MODEL FOR WESTINGHOUSE TYPE REACTORS IN KOREA : OVERVIEW, RESULTS AND INSIGHTS DEVELOPMENT OF LOW POWER SHUTDOWN LEVEL 1 PSA MODEL FOR WESTINGHOUSE TYPE REACTORS IN KOREA : OVERVIEW, RESULTS AND INSIGHTS Yong Suk LEE 1, Eden KIM 1,Gunhyo JUNG 1, Seok-won HWANG 2, Ho-jun JEON 2 1

More information

TECHNICAL MEETING ON TECHNICAL SUPPORT ORGANIZATION (TSO) ROLE AND RESPONSIBILITIES May 2013

TECHNICAL MEETING ON TECHNICAL SUPPORT ORGANIZATION (TSO) ROLE AND RESPONSIBILITIES May 2013 TECHNICAL MEETING ON TECHNICAL SUPPORT ORGANIZATION (TSO) ROLE AND RESPONSIBILITIES May 2013 1 MARCH 13 What is TSO? What do we understand as a Technical Support Organization (TSO) in the nuclear business?

More information

Brown University Updated March 11, 2013 Facilities Design & Construction Standards

Brown University Updated March 11, 2013 Facilities Design & Construction Standards SECTION 01 17 90 UTILITY & CRITICAL SYSTEM CONNECTIONS AND INTERRUPTIONS PART 1 - GENERAL 1.1 SUMMARY: A. Brown University operates and maintains extensive campus and building utilities and distribution

More information

City of Saskatoon Business Continuity Internal Audit Report

City of Saskatoon Business Continuity Internal Audit Report www.pwc.com/ca City of Saskatoon Business Continuity Internal Audit Report June 2018 Executive Summary The City of Saskatoon s (the City ) Strategic Risk Register identifies Business Continuity as a high

More information

An annual review of all local Lock Out Tag Out procedures must be accomplished.

An annual review of all local Lock Out Tag Out procedures must be accomplished. Standard Safety Procedure No. 509 Hazardous Energy Control Objective: To safeguard employees, equipment and property from the unexpected energization or startup of machinery and equipment, or the release

More information

Example Pressurized Water Reactor Defense-in-Depth Measures For GSI-191, PWR Sump Performance

Example Pressurized Water Reactor Defense-in-Depth Measures For GSI-191, PWR Sump Performance Example Pressurized Water Reactor Defense-in-Depth Measures For GSI-191, PWR Sump Performance ATTACHMENT Introduction This paper describes a range of defense-in-depth measures that either currently exist

More information

Westinghouse Small Modular Reactor. Passive Safety System Response to Postulated Events

Westinghouse Small Modular Reactor. Passive Safety System Response to Postulated Events Westinghouse Small Modular Reactor Passive Safety System Response to Postulated Events Matthew C. Smith Dr. Richard F. Wright Westinghouse Electric Company Westinghouse Electric Company 600 Cranberry Woods

More information

Occupational Radiation Protection in Nuclear / Fuel Cycle Facilities Summary of the Contributed Papers

Occupational Radiation Protection in Nuclear / Fuel Cycle Facilities Summary of the Contributed Papers Occupational Radiation Protection in Nuclear / Fuel Cycle Facilities Summary of the Contributed Papers H. Burçin OKYAR OECD Nuclear Energy Agency Radiological Protection and Radioactive Waste Management

More information

LOCKOUT / TAGOUT PROGRAM

LOCKOUT / TAGOUT PROGRAM Page: Page 1 of 11 Purpose The purpose of this program is to establish procedures for affixing appropriate lockout/tagout equipment to energy isolating devices and to otherwise disable machines or equipment

More information

APS Cleaning. Environmental Management System. Scope of Certification

APS Cleaning. Environmental Management System. Scope of Certification Environmental Management System Scope of Certification The provision of commercial and industrial cleaning services throughout Queensland. Table of Contents Contents 1. Introduction... 3 1.1. The Environmental

More information

NSr1: UNPLANEND AUTOMATIC SHUTDOWNS PER 7000 HOURS CRITICAL (WANO UA7)

NSr1: UNPLANEND AUTOMATIC SHUTDOWNS PER 7000 HOURS CRITICAL (WANO UA7) 1. Nuclear Performance Indicators NSr1: UNPLANEND AUTOMATIC SHUTDOWNS PER 7000 HOURS CRITICAL (WANO UA7) Values are calculated on annual basis (http://www.wano.info/) to monitor evolution of unplanned

More information

Responsibilities of the operating organization during construction and how to discharge them

Responsibilities of the operating organization during construction and how to discharge them Responsibilities of the operating organization during construction and how to discharge them Importance of an early, defined & strong involvement of the Owner/Operator in a New Build Project IAEA TM on

More information

IT Services Management Service Brief

IT Services Management Service Brief IT Services Management Service Brief Business Impact Analysis Prepared by: Rick Leopoldi June 19, 2002 Copyright 2002. All rights reserved. Duplication of this document or extraction of content is strictly

More information

FRAMATOME S LESSONS LEARNED ON RISK-INFORMED APPLICATIONS (RIA)

FRAMATOME S LESSONS LEARNED ON RISK-INFORMED APPLICATIONS (RIA) FRAMATOME S LESSONS LEARNED ON RISK-INFORMED APPLICATIONS (RIA) THE EXPERIENCE GAINED FROM OLKILUOTO 3 EPR PROJECT PSAM14 Conference Presenter: Hervé Brunelière, Reliability Senior Expert Other authors:

More information

San Onofre Unit 1 Decommissioning

San Onofre Unit 1 Decommissioning San Onofre Unit 1 Decommissioning Eric M. Goldin, Ph.D., CHP Southern California Edison P. O. Box 128 San Clemente, CA 92674-0128 USA Introduction Nuclear plant decommissioning presents several challenges

More information

PRODUCTION FORECAST AND METHODOLOGY NUCLEAR

PRODUCTION FORECAST AND METHODOLOGY NUCLEAR Filed: 0-0- Page of PRODUCTION FORECAST AND METHODOLOGY NUCLEAR 0 0 0.0 PURPOSE This evidence provides the production forecast for the nuclear facilities and a description of the methodology used to derive

More information

SETTING UP A LOAD-MANAGEMENT SYSTEM

SETTING UP A LOAD-MANAGEMENT SYSTEM POWER SYSTEMS TOPICS Power Up With a Load-Management System: SETTING UP A LOAD-MANAGEMENT SYSTEM AUTHOR ISAAC FRAMPTON Senior Staff Engineer Kohler Co. Power Systems Division Part of a -part series INTRODUCTION

More information

Small modular reactors deployment and their applications for embarking countries

Small modular reactors deployment and their applications for embarking countries Small modular reactors deployment and their applications for embarking countries Many developing countries with smaller electricity grids are interested in small modular nuclear reactors (SMRs) as part

More information

Dominion North Anna Power Station Restart Readiness

Dominion North Anna Power Station Restart Readiness Dominion North Anna Power Station Restart Readiness October 21, 2011 Briefing David A. Heacock, President & Chief Nuclear Officer Eugene S. Grecheck, Vice President, Nuclear Development 1 Dominion Assessment

More information

OUTAGE OM&A NUCLEAR. This evidence presents nuclear operations outage OM&A costs for the period

OUTAGE OM&A NUCLEAR. This evidence presents nuclear operations outage OM&A costs for the period Filed: 0-0- Page of.0 PURPOSE OUTAGE OM&A NUCLEAR This evidence presents nuclear operations outage OM&A costs for the period 0-0..0 OVERVIEW Outage OM&A costs vary year over year depending on the number

More information

The Successful use of HDS for Nuclear Power Generating Plant Applications

The Successful use of HDS for Nuclear Power Generating Plant Applications AREVA NP Inc. Metrology Services The Successful use of HDS for Nuclear Power Generating Plant Applications SPAR 2006 Lona Shaw Supervisor, CAD Unit Who is AREVA? > AREVA group has 70,000 + employees world

More information

NRC INSPECTION MANUAL

NRC INSPECTION MANUAL NRC INSPECTION MANUAL QVIB INSPECTION PROCEDURE 70702 PART 52, INSPECTION OF PREOPERATIONAL TEST PERFORMANCE PROGRAM APPLICABILITY: 2504 70702-01 INSPECTION OBJECTIVES 01.01 To provide guidance for inspection

More information

WM2014 Conference, March 2 6, 2014, Phoenix, Arizona, USA

WM2014 Conference, March 2 6, 2014, Phoenix, Arizona, USA Reactor D&D: AREVA French and German Latest Experiences - 14458 (1) Stephan Krüger, AREVA GmbH, Kaiserleistr. 29, 63067 Offenbach, Germany; stephan.krueger@areva.com (2) Xavier de Brimont, AREVA NC, 1

More information

IBM Service Parts Management

IBM Service Parts Management IBM Global Services IBM Service Parts Management Dr. Grace Lin, Global Sense and Respond Leader IBM Business Consulting Services Member, IBM Academy of Technology VP Practice, Informs Email: gracelin@us.ibm.com

More information

Capacity building supporting long-range sustainable nuclear energy system planning

Capacity building supporting long-range sustainable nuclear energy system planning Capacity building supporting long-range sustainable nuclear energy system planning A key challenge in the 21 st century, as countries expanding their nuclear programmes are joined by those embarking on

More information

Implementation of the Maintenance Improvement Initiative

Implementation of the Maintenance Improvement Initiative Implementation of the Maintenance Improvement Initiative There are two aspects to implementation. First is what is being implemented and the second is how it will be implemented. As discussed below, there

More information

Nuclear Accident in Japan: NRC Early Protective Action Recommendations

Nuclear Accident in Japan: NRC Early Protective Action Recommendations Nuclear Accident in Japan: NRC Early Protective Action Recommendations National Radiological Emergency Preparedness Conference April 18, 2011 Patricia A. Milligan, CHP Senior Technical Advisor for Preparedness

More information

THE 14TH R EFUELING outage at Diablo

THE 14TH R EFUELING outage at Diablo Two of the new steam generators arriving by barge at Diablo Canyon s intake cove (Photos: PG&E) A four-steam-generator outage at Diablo Canyon-2 BY RICK MICHAL THE 14TH R EFUELING outage at Diablo Canyon

More information

ELECTRONIC SHIFT OPERATIONS MANAGEMENT SYSTEM. ABB Ability Asset Suite esoms Work optimisation for power generation.

ELECTRONIC SHIFT OPERATIONS MANAGEMENT SYSTEM. ABB Ability Asset Suite esoms Work optimisation for power generation. ELECTRONIC SHIFT OPERATIONS MANAGEMENT SYSTEM ABB Ability Asset Suite esoms Work optimisation for power generation. 2 ABB ABILITY ASSET SUITE e SOMS ELECTRONIC SHIFT OPERATIONS MANAGEMENT SYSTEM A consistent,

More information

April 25, Rulemaking and Guidance Development Branch Division of New Reactor Licensing Office of New Reactors

April 25, Rulemaking and Guidance Development Branch Division of New Reactor Licensing Office of New Reactors April 25, 2011 MEMORANDUM TO: William F. Burton, Chief Rulemaking and uidance Development Branch Division of New Reactor Licensing Office of New Reactors FROM: Roy K. Mathew, Acting Chief /RA/ Electrical

More information

PROJECT NAME SECTION GENERAL COMMISSIONING REQUIREMENTS

PROJECT NAME SECTION GENERAL COMMISSIONING REQUIREMENTS PART 1 - GENERAL 1.1 SUMMARY A. The Owner has contracted an independent Commissioning Authority. The Commissioning Authority is an independent and knowledgeable third party, hired to verify that the systems

More information

NOT EVERY HYBRID BECOMES A PRIUS: THE CASE AGAINST THE FUSION-FISSION HYBRID CONCEPT

NOT EVERY HYBRID BECOMES A PRIUS: THE CASE AGAINST THE FUSION-FISSION HYBRID CONCEPT NOT EVERY HYBRID BECOMES A PRIUS: THE CASE AGAINST THE FUSION-FISSION HYBRID CONCEPT IAP 2010 DON STEINER PROFESSOR EMERITUS,RPI JANUARY 22, 2010 IN 1997 TOYOTA INTRODUCED ITS HYBRID CAR CALLED THE PRIUS

More information

Westinghouse AP1000. Reactor

Westinghouse AP1000. Reactor Westinghouse AP1000 A Third Generation Nuclear Reactor International Council on Systems Engineering (INCOSE) September 18, 2013 Andrew Drake, PMP Director, AP1000 Engineering Completion Engineering, Equipment

More information

Post-Fukushima Assessment of the AP1000 Plant

Post-Fukushima Assessment of the AP1000 Plant ABSTRACT Post-Fukushima Assessment of the AP1000 Plant Ernesto Boronat de Ferrater Westinghouse Electric Company, LLC Padilla 17-3 Planta 28006, Madrid, Spain boronae@westinghouse.com Bryan N. Friedman,

More information

Flaw indications in the reactor pressure vessels of Doel 3 and Tihange 2

Flaw indications in the reactor pressure vessels of Doel 3 and Tihange 2 Flaw indications in the reactor pressure vessels of Doel 3 and Tihange 2 Progress report 2014 Contents 1. Introduction... 3 2. Historical overview... 3 3. Progress of the mid-term actions in 2014... 6

More information

Network Drives Cleanup

Network Drives Cleanup Network Drives Cleanup The Project With No End Date ARMA Spring Conference April 8, 2015 June 2013 Patricia Zimmerman, CRM Senior Director, Enterprise Records & Information Management UnitedHealth Group

More information

Improvements Needed in Nuclear Power Plant Probabilistic Risk Assessments: Lessons Learned from Fukushima

Improvements Needed in Nuclear Power Plant Probabilistic Risk Assessments: Lessons Learned from Fukushima Improvements Needed in Nuclear Power Plant Probabilistic Risk Assessments: Lessons Learned from Fukushima Mohammad Modarres Professor of Nuclear Engineering Department of Mechanical Engineering University

More information

OPG s Response to Fukushima Event- Update

OPG s Response to Fukushima Event- Update OPG s Response to Fukushima Event- Update Darlington and Pickering Joint Community Advisory Committee Meeting- January 21, 2014 Mark Knutson- Director- Fukushima Support Tho-Dien Le- Projects Design Manager-

More information

Document No: SB002-P3 Revision No: Last Updated: April

Document No: SB002-P3 Revision No: Last Updated: April BRIEF People often are confused with the term - Out-of-Sequence, and use them in inappropriate ways. While we talk about Out-of-Sequence, we also need to discuss the difference between Retained Logic and

More information

FCX Department of Occupational Health and Safety Policy

FCX Department of Occupational Health and Safety Policy FCX Department of Occupational Health and Safety Policy Lockout/Tagout/Tryout (LOTOTO) (Control of Hazardous Energy Sources) Approval Date: 08/29/2014 Original Date: 03/09/2009 Policy # FCX-04 Revision

More information

Benefits of Lean Management in Liquid Waste Operations - One Company's Journey Rodney Blackmon and John Windham Savannah River Remediation, LLC

Benefits of Lean Management in Liquid Waste Operations - One Company's Journey Rodney Blackmon and John Windham Savannah River Remediation, LLC Benefits of Lean Management in Liquid Waste Operations - One Company's Journey 15402 ABSTRACT Rodney Blackmon and John Windham Savannah River Remediation, LLC For Savannah River Remediation, LLC (SRR),

More information

Severe Accident Countermeasures of SFR (on Monju)

Severe Accident Countermeasures of SFR (on Monju) Severe Accident Countermeasures of SFR (on Monju) Mamoru Konomura FBR Plant Engineering Center Japan Atomic Energy Agency 1. Safety Approach of Monju Safety Approaches in early LMFBR There were several

More information

Prairie Island Nuclear Generating Plant. EAL Reference Manual. Revision 9

Prairie Island Nuclear Generating Plant. EAL Reference Manual. Revision 9 Prairie Island Nuclear Generating Plant EAL Reference Manual Notice to Users This document has been prepared for the Prairie Island Nuclear Generating Plant (PINGP). Its purpose is to provide general information

More information

NUCLEAR POWER PLANT OPERATIONS

NUCLEAR POWER PLANT OPERATIONS COURSE NUCLEAR POWER PLANT OPERATIONS May 6-7, 2019 Offices of Morgan, Lewis & Bockius LLP Washington, DC RELATED EVENT: U.S. NUCLEAR REGULATION BASICS (NRC 101) May 7-8, 2019 Washington, DC Very informative,

More information

Westinghouse SMR & Nuclear Fuel Overview

Westinghouse SMR & Nuclear Fuel Overview Westinghouse SMR & Nuclear Fuel Overview Carlos Leipner, Westinghouse VP Latin America Presented at LAS-ANS July 2014 Rio de Janeiro, Brasil 2014 Westinghouse Electric Company LLC, All Rights Reserved.

More information

Ageing Management and Long Term Operation of Nuclear Power Plants

Ageing Management and Long Term Operation of Nuclear Power Plants Ageing Management and Long Term Operation of Nuclear Power Plants Senior Regulators Meeting 17 September 2015 Jan BENS AGENDA Belgian Nuclear Reactor Sites LTO Legal Framework LTO Regulatory Framework

More information

How To Manage a Troubled Project GTC Center for Project Management, All Rights Reserved

How To Manage a Troubled Project GTC Center for Project Management, All Rights Reserved How To Manage a Troubled Project GTC 2007 1 How To Manage a Troubled Project 2 Logistics Start and finish Breaks and lunch Morning: one 15-minute break Lunch: 60 minutes Afternoon: one 15-minute break

More information

Nuclear power plant outages. 1 General 3. 2 General outage requirements 3

Nuclear power plant outages. 1 General 3. 2 General outage requirements 3 GUIDE 9 Jan. 1995 YVL1.13 Nuclear power plant outages 1 General 3 2 General outage requirements 3 2.1 Outage planning 3 2.2 General safety requirements 4 2.3 Physical protection, emergency preparedness

More information

Plant Life Management Canada

Plant Life Management Canada 2017/02/22 TWG on LM for NPP Plant Life Management Canada - Copyright - General Utility Focus/Concerns Expanded focus last few years: Still driven primarily by desire to improve Equipment Reliability Index

More information

STO Navigator Canada Best-Practices Manual

STO Navigator Canada Best-Practices Manual Page 1 / 5 24.1- SCHEDULING METHODOLOGY 24.1.1. PURPOSE The following best-practice guideline provides the STO Project Controls Team with a defined methodology for scheduling, to accurately identify the

More information

Combined Cycle HRSG and Balance of Plant - Program 88

Combined Cycle HRSG and Balance of Plant - Program 88 Program Description Program Overview The design of modern heat recovery steam generators (HRSGs) and balance-of-plant (BOP) systems is a complex interrelationship between many parameters and variables.

More information

HSE Design Reviews and Action Close-out

HSE Design Reviews and Action Close-out HSE Design Reviews and Action Close-out Simon Round, Manager Design HSE, Amec Foster Wheeler, Shinfield Park, Reading, Berkshire RG2 9FW, UK HSE design reviews and the management and close-out of resulting

More information

ISO FDA QSR. ISO and FDA QSR: A Step by Step Guide to Complying with Medical Device QMS Requirements

ISO FDA QSR. ISO and FDA QSR: A Step by Step Guide to Complying with Medical Device QMS Requirements ISO 13485 FDA QSR ISO 13485 and FDA QSR: A Step by Step Guide to Complying with Medical Device QMS Requirements Jon Speer Founder & VP of QA/RA greenlight.guru Table of Contents 1 Introduction 4 QMS Philosophy

More information

PROJECT MANAGEMENT How-to-guide. How to manage HR Projects efficiently

PROJECT MANAGEMENT How-to-guide. How to manage HR Projects efficiently PROJECT MANAGEMENT How-to-guide How to manage HR Projects efficiently Using this Guide Our How-to-Guides, such as the one you are currently reading, are limited in application: each customer can consult

More information

ASSET INTEGRITY INTELLIGENCE MAKING BAD ACTOR ELIMINATION PROGRAMS WORK. RICK HOFFMAN, Sr. Engineering Advisor at Becht Engineering

ASSET INTEGRITY INTELLIGENCE MAKING BAD ACTOR ELIMINATION PROGRAMS WORK. RICK HOFFMAN, Sr. Engineering Advisor at Becht Engineering ASSET INTEGRITY INTELLIGENCE MAKING BAD ACTOR ELIMINATION PROGRAMS WORK RICK HOFFMAN, Sr. Engineering Advisor at Becht Engineering VOLUME 23, ISSUE 4 JULY AUGUST 2017 MAKING BAD ACTOR ELIMINATION PROGRAMS

More information