THE 14TH R EFUELING outage at Diablo

Size: px
Start display at page:

Download "THE 14TH R EFUELING outage at Diablo"

Transcription

1 Two of the new steam generators arriving by barge at Diablo Canyon s intake cove (Photos: PG&E) A four-steam-generator outage at Diablo Canyon-2 BY RICK MICHAL THE 14TH R EFUELING outage at Diablo Canyon s Unit 2 proved to be the plant site s largest and most challenging undertaking. The outage, referred to as 2R14, encompassed the task of replacing all four steam generators, along with thousands of other jobs and the refueling itself. The other jobs included the replacement of the containment recirculation sump screens, a volumetric inspection of the reactor head, pressurizer weld overlays, and a containment integrated leak rate test. The outage, which ran from February 4, 2008, to April 12, 2008, brought more than 3000 workers to the site at peak work time. The outage was so successful that it received an honorable mention for Project of the Year by Power Engineering magazine in its January 2009 issue. The two-unit Diablo Canyon nuclear power plant, located in Avila Beach, Calif., is operated by Pacific Gas & Electric Company (PG&E). Diablo Canyon-1 was in the midst of its own steam generator replacement and refueling outage its 15th outage, referred to as 1R15 in March, when this article was written. The two Diablo Canyon units are Westinghouse pressurized water reactors. Unit 1, rated at 1138 MWe, started commercial operation in May 1985, and Unit 2, rated at 1151 MWe, went commercial in March The steam generators replaced at both units were original plant components. Continued A special delivery system had to be designed and implemented to move steam generators in and out of Diablo Canyon-2 s containment building. New steam generators in on-site temporary storage April 2009 N U C L E A R N E W S 35

2 A failure-proof, seismically qualified single-point lift system (left photo) was used to pick up each steam generator and place it on a heavy transporter (right photo). Preliminary work The process for obtaining regulatory approvals for the Unit 2 outage at the local and state levels and from the Nuclear Regulatory Commission began in 2004, but significant planning started earlier, according to Bob Exner, project manager for the steam generator replacement. It also took a number of years to secure other necessary permits and contracts for plant components and personnel to work the outage. The contract for the fabrication of the steam generators was signed in August The four large components arrived together in the United States from the Equipos Nucleares S.A. factory located in Santander, Spain, and were then delivered, two per barge, at the plant's intake cove in November The components were then stored in temporary buildings for about three months before being installed during 2R14. Travel path Although Diablo Canyon has containment equipment hatches big enough to accommodate a 350-ton, 16-ft by 70-ft steam generator, there were several unique challenges with the travel path for the large components. A hatch transfer system with a turntable had to be designed to allow a steam generator to clear a cubicle wall while going through the hatch, which opens onto the roof of the auxiliary building that houses safety-related operating equipment. A hatch transfer design utilizing a failure-proof, seismically qualified singlepoint lift system was used outside the hatch to pick up each old steam generator. The lift system placed the steam generator on a heavy transporter for the short trip through the fuel-handling building to a temporary outside lift system, where it was lowered to another transporter for the trip to an on-site facility for long-term storage. This was a very challenging travel path, Exner said. It was much more complicated than an average steam generator replacement project. Our contractors designed a unique and innovative system to accommodate the path. The entire team rose to the challenge and moved the steam generators safely and efficiently to storage. At its peak, the steam generator project employed about 1600 people, including PG&E project management and staff, subcontracted craft workers, radiation protection technicians, and additional security forces. Other outage activities employed about 1500 additional staff. Although Diablo Canyon has containment equipment hatches that are big enough to accommodate a 350-ton, 16-ft by 70-ft steam generator, there were several unique challenges with the travel path for the large components. The temporary workers are critical to the outage work we do at the plant, said Jim Becker, Diablo Canyon site vice president. They are also important to our local economy. About half of the outage workers 36 N U C L E A R N E W S April 2009

3 Each old steam generator was delivered by a truck transporter to a railcar, then carted by rail line uphill to the on-site storage building. are from out of the area that means over 1000 individuals are living, eating, and shopping along the central coast of California during what is normally a relatively quiet tourism period. Outage goals Goals established for outage duration, project cost, and total personnel radiation dose were bettered or within target. Financial goals included a duration of 66 days or less, at a cost of $52.3 million or less, not including the cost of the steam generator replacement project. The actual outage duration was 68 days, 22 hours, and the cost was $50 million. (Costs for Unit 2 s steam generator project, including installation, totaled $157 million.) Although the business goal for outage duration was not met, Diablo Canyon was only the fourth plant in the U.S. industry to perform a first-unit steam generator outage in fewer than 70 days, said Jeff Knisley, Diablo Canyon outage manager. All in all, 2R14 was a very successful steam generator replacement outage, and we expect even greater success for 1R15. The overall exposure for 2R14 was 226 person-rem, which was considerably lower than the original goal of less than 257 person-rem. The personal contamination event (PCE) rate for 2R14 was 0.20 PCE per 1000 person-hours, the lowest on record for a steam generator replacement outage in the U.S. industry, according to Knisley. In addition, there were no nuclear safety challenges, significant human performance events (site-level clock reset), or disabling injuries. Preparation work Long before the outage started, an optimization plan identified five major crosscutting issues deemed to have a significant impact on the outage s success. Teams were assigned to each of the five issue areas: craft and labor resources, in-processing and training, radiation protection and decontamination planning, security, and work management. The steam generator replacement project team worked with the contractor and the plant staff to develop working agreements and to schedule development and integration reviews and task reviews. A year prior to the start of the outage, integration meetings and vertical slice schedule reviews closely examined the many activities that would occur simultaneously. The purpose of vertical slice meetings was to integrate the steam generator work and outage activities that could affect both work teams. Outage schedulers, site managers, task managers, lead field engineers, health physics technicians, and other key organizations were asked to participate. The idea behind these meetings was for both job teams to go through a structured schedule review to identify conflicts and resolve all issues prior to the start of the outage. Diablo Canyon also implemented safety and human performance training for all personnel on-site who would be working the outage, including contractors and temporary additional hires. This breakthrough training, according to Exner, included hands-on practice and engaging workers in activities designed to lock in human performance tools such as three-way communication, the two-minute rule (for identifying unanticipated job-site conditions 38 N U C L E A R N E W S April 2009

4 before work begins), and place-keeping (a technique used to mark the steps in a procedure, which aids in the prevention of skipping or repeating steps), among others. The training had a very positive impact on personnel and industrial safety during 2R14, Exner said. In other pre-outage work, representatives from the radiation protection team visited vendors and inspected their component mockups in order to gain a better understanding of how work would be done and how radiation dose could be reduced. The RP team also installed additional portal monitors that had faster, more accurate counts for more efficient worker processing through containment. A temporary containment access facility was established on Because of limited on-site parking, the steam generator project team established a busing program to transport about 1000 craft workers per day from off-site temporary PG&E parking lots to the plant. the turbine deck for personnel to prepare for entering containment. Critical path The basic critical path started with the reactor s shutdown in February 2008 and its subsequent defueling and continued through the removal of the four original steam generators, the installation of the four replacement steam generators, and the welding of the primary and secondary piping. The critical path also included the completion of instrumentation and other systems that had been removed and modified, refueling and plant testing, an integrated containment leak rate test, and plant startup. Challenges As with any outage, there were challenges, some of which were technical. The mechanical systems that support the steam generators had to be reworked to accommodate the new steam generators. That, in turn, created challenges for the installation of the replacement steam generators. In addition, when the foot bolts on the steam generators were stuck during the removal phase, management realized that a contingency plan was needed that was more efficient than the one that had been developed for the outage. Instrumentation restoration issues also ended up being more complex than anticipated. Other issues such as a transportation program that brought workers on site from off-site parking lots (more on this later) and a flu outbreak that affected many people in the area put unexpected demands on labor resources. Site security Art Wells, security supervisor for the steam generator replacement project, said that early expectations about site security were ratcheted up following discussions with personnel from other nuclear plants that had been involved in large outages. While we initially expected 200 truckloads of deliveries, realworld experience from other plants reported up to 500, he said. As a result, additional security personnel were added at the plant s main gate and at the plant s vehicle inspection station, where vehicles enter a more secure perimeter around the plant. A dispatch office was established to coordinate all onsite deliveries. For daily in-processing of materials and personnel, the security instrumentation and control staff provided around-the-clock technical coverage to address any issues with security computers or other security equipment. In addition, more security search trains were monitored during peak personnel traffic times to ease the congestion that resulted from more workers being on site. Inside the plant, additional temporary card readers were installed to expedite traffic flow and eliminate hand-logged entries, and additional security personnel and protective measures were installed at key locations. Because of limited on-site parking, the steam generator project team established a busing program to transport about 1000 craft workers per day from off-site temporary PG&E parking lots to the plant, as well as a shuttle service to and from on-site parking lots. Planning well in advance and performing readiness reviews, along with lots of teamwork, made this one of Diablo Canyon s best outages in the history of the plant, Wells said. By the end of the outage, loggable security events amounted to only half the established goal, making it the lowest on record for a Diablo Canyon outage. Continued April 2009 N U C L E A R N E W S 39

5 A steam generator passes through the Diablo Canyon-2 containment equipment hatch. Lessons learned Diablo Canyon is a learning organization, Exner said. We are always looking for ways to improve processes, gain efficiencies, and better allocate resources. Part of that process is to capture lessons learn ed. About 500 lessons learned from the steam generator replacement project are now action items being tracked and applied to benefit the replacement project for Unit 1, which began in January. About 500 lessons learned from the steam generator replacement project are now action items being tracked and applied to benefit the replacement project for Unit 1. Some of the more notable lessons learned implemented even as Unit 1 s outage was in progress are the following: Because tasks such as instrumentation, steam generator supports, structural modification, and restoration were more complicated than anticipated, focus teams made up of PG&E and contract construction management, engineering, planning, and project management personnel were implemented to perform detailed task planning and integration with other work. Construction management teams were brought on site earlier to begin work on the project. Additional cutting and welding equipment and craft resources were provided to allow for parallel work on the steam generators. Specialized tooling was developed for rethreading and reusing stuck foot bolts during the removal of the old steam generators, along with special tooling for resurfacing lateral support bumpers in place to save time and radiation dose. Effective management systems were developed for work package closure. Closing comments Becker, who was also the station director at the time of 2R14, said, Our Unit 2 steam generator replacement outage was our biggest refueling outage to date. The organization s success with this project was directly attributed to the team s dedication and commitment. Outage director Tim King added, 2R14 was a pivotal event in Diablo Canyon history. Replacing the steam generators will help ensure that Unit 2 is able to safely and reliably generate low-cost electricity for the duration of its license. King concluded by saying that with the knowledge and experience gained in 2R14, we are looking forward to improved personnel safety and outage duration during the steam generator replacement in Unit N U C L E A R N E W S April 2009

Fort Calhoun Station

Fort Calhoun Station Fort Calhoun Station Challenges and Successes During Major Equipment Replacement Activities EPRI Meeting January 14, 2009 Randy Hodgson Fort Calhoun Station The Big Outage - NSSSRP What Made this outage

More information

Rick Libra, director of work management at Exelon Nuclear s Three

Rick Libra, director of work management at Exelon Nuclear s Three Interview: Libra T H E N U C L E A R N E W S I N T E RV I E W Rick Libra: A safe and successful outage About 2.5 million person-hours were worked during TMI-1 s recent outage, with no lost-time injuries.

More information

The Successful use of HDS for Nuclear Power Generating Plant Applications

The Successful use of HDS for Nuclear Power Generating Plant Applications AREVA NP Inc. Metrology Services The Successful use of HDS for Nuclear Power Generating Plant Applications SPAR 2006 Lona Shaw Supervisor, CAD Unit Who is AREVA? > AREVA group has 70,000 + employees world

More information

Scaffold Program Optimization and Dose Reduction Guide

Scaffold Program Optimization and Dose Reduction Guide Scaffold Program Optimization and Dose Reduction Guide Lisa Edwards Program Manager TAC Meeting January, 2010 Background Why? Scaffold Programs are Expensive Typical Single Outage Costs: $1-3 Million Additional

More information

Radiological Services Radiation Protection Technician Development Program

Radiological Services Radiation Protection Technician Development Program Radiological Services Radiation Protection Technician Development Program Revision: 1 Effective Date: 7-25-2018 Table of Contents 1.0 Introduction... 1 1.1 Purpose... 1 1.2 Scope and Applicability... 1

More information

Torness tackles biggest-ever outage

Torness tackles biggest-ever outage EDF Energy s Torness nuclear power station, located in East Lothian, Scotland (Photos: EDF Energy) Torness tackles biggest-ever outage By Dick Kovan The torness-1 advanced gas-cooled reactor (agr) was

More information

Executing the Darlington refurbishment project Year 1

Executing the Darlington refurbishment project Year 1 Outage Management and Plant Maintenance Special Section Executing the Darlington refurbishment project Year 1 The Darlington refurbishment project passed its first major milestone and hit other important

More information

Heavy Component Replacement in Nuclear Power Plants

Heavy Component Replacement in Nuclear Power Plants Heavy Component Replacement in Nuclear Power Plants Steve Sills, Vice President Business Development, SGT Darren Wood, Manager Component Replacements, AREVA Purpose and Process Goal Recent successes and

More information

San Onofre Unit 1 Decommissioning

San Onofre Unit 1 Decommissioning San Onofre Unit 1 Decommissioning Eric M. Goldin, Ph.D., CHP Southern California Edison P. O. Box 128 San Clemente, CA 92674-0128 USA Introduction Nuclear plant decommissioning presents several challenges

More information

Watts Bar Nuclear Plant Unit 2 Completion Project

Watts Bar Nuclear Plant Unit 2 Completion Project Watts Bar Nuclear Plant Unit 2 Completion Project Ninth Quarterly Update to the Estimate to Complete May - July 2014 Published October 2014 Table of Contents Section 1 - Executive Summary... 3 Section

More information

Cook Critical RP Survey Program

Cook Critical RP Survey Program Cook Critical RP Survey Program A New, Systematic Approach To Radiation Protection Program Information Capture Bob Hite - RP, Chemistry, Environmental Director American Electric Power - Cook Nuclear Plant

More information

DURING T H E M O S T recent planned

DURING T H E M O S T recent planned Palo Verde s outage ALARA success: Is it repeatable and beatable? BY MARK FALLON DURING T H E M O S T recent planned refueling outage at Palo Verde Nuclear Generating Station s Unit 1, not only was the

More information

Integrated Head Assembly (IHA) A Comprehensive Solution

Integrated Head Assembly (IHA) A Comprehensive Solution Integrated Head Assembly (IHA) A Comprehensive Solution Innovative best practices. Dependable performance. Proven success reductions of six critical path days. What is the IHA? It is the future. The focus

More information

Watts Bar Nuclear Plant Unit 2 Completion Project

Watts Bar Nuclear Plant Unit 2 Completion Project Watts Bar Nuclear Plant Unit 2 Completion Project Tenth Quarterly Update to the Estimate to Complete August - October Published January 2015 Table of Contents Section 1 - Executive Summary... 3 Section

More information

Turnaround/Shutdown Optimization

Turnaround/Shutdown Optimization Turnaround/Shutdown Optimization A Turnaround (TA) by definition is a planned, periodic event where one or more processing/production units are temporarily removed from service. In the manufacturing sector,

More information

Seismic Damage Information (the 151st Release) (As of 12:00 May 27, 2011)

Seismic Damage Information (the 151st Release) (As of 12:00 May 27, 2011) May 27, 20 Seismic Damage Information (the 5st Release) (As of 2:00 May 27, 20) Fukushima Dai-ichi NPS - The transfer of water in the condenser of Unit 2 to the basement of the turbine building was started

More information

Darlington Refurbishment Project Update

Darlington Refurbishment Project Update Darlington Refurbishment Project Update Pickering Community Advisory Council November 18, 2014 Roy Martin, Project Director Refurbishment Execution Contents Key Initiatives: Regulatory Approvals Productivity

More information

Zion Project Overview S. Chris Baker VP EH&S

Zion Project Overview S. Chris Baker VP EH&S Zion Project Overview S. Chris Baker VP EH&S 1 Agenda Asset Sale Agreement Organization Nuclear Decommissioning Process Overview of Zion Station Decommissioning Schedule Near Term Activities Spent Fuel

More information

6 Preliminary Assessment of Construction Method and Constructability Issues

6 Preliminary Assessment of Construction Method and Constructability Issues 6 Preliminary Assessment of Construction Method and Constructability Issues 6.1 Construction Approach Appendix C includes conceptual designs of the alternatives discussed below. Generally, the conceptual

More information

Tim Borgen is the general training

Tim Borgen is the general training T H E N U C L E A R N E W S I N T E RV I E W Tim Borgen: Monticello s outage training center Xcel Energy converted a shuttered car dealership into a training center for contract outage workers. Tim Borgen

More information

METHODOLOGY FOR ENSURING THE INTEGRATION OF ALARA INTO THE DESIGN OF

METHODOLOGY FOR ENSURING THE INTEGRATION OF ALARA INTO THE DESIGN OF METHODOLOGY FOR ENSURING THE INTEGRATION OF ALARA INTO THE DESIGN OF THE AP1000 TM REACTOR Erik Slobe slobeed@westinghouse.com Westinghouse Electric Company LLC 1000 Westinghouse Drive Cranberry Township,

More information

DIABLO CANYON POWER PLANT DIGITAL PROCESS PROTECTION SYSTEM REPLACEMENT LICENSING EXPERIENCE USING ISG-06

DIABLO CANYON POWER PLANT DIGITAL PROCESS PROTECTION SYSTEM REPLACEMENT LICENSING EXPERIENCE USING ISG-06 DIABLO CANYON POWER PLANT DIGITAL PROCESS PROTECTION SYSTEM REPLACEMENT LICENSING EXPERIENCE USING ISG-06 Kenneth J. Schrader, MSNE Pacific Gas & Electric Co. PO Box 56 Avila Beach, CA 93424 kjse@pge.com

More information

Sargent & Lundy LLC April 8, 2014

Sargent & Lundy LLC April 8, 2014 Farid M. Berry Vice President & Project Director Sargent & Lundy LLC April 8, 2014 Role of the OWNER S ENGINEER Technical Meeting on Becoming a Knowledgeable Customer Obninsk and Novovoronezh, Russian

More information

Your Checklist Guide for Effortless Crane Hire

Your Checklist Guide for Effortless Crane Hire Your Checklist Guide for Effortless Crane Hire (Plus Frequently Asked Questions) There are 6 key Processes that can make your Crane Hire experience effortless if we work together to manage them efficiently:

More information

Darlington Refurbishment Project Update. Darlington Community Advisory Council October 7, 2014

Darlington Refurbishment Project Update. Darlington Community Advisory Council October 7, 2014 Darlington Refurbishment Project Update Darlington Community Advisory Council October 7, 2014 OPG/Government Joint Objectives for Darlington Refurbishment Provide 30 years of GHG free base-load energy

More information

OSART Good Practices MAINTENANCE Outage management

OSART Good Practices MAINTENANCE Outage management OSART Good Practices MAINTENANCE Outage management Mochovce, Slovakia Mission Date; 4-20 Sep., 2006 Transparent control of the EMO unit outages during preparation and implementation of outage. Responsible

More information

Kesselring Site Refueling and Overhaul of the S8G Prototype

Kesselring Site Refueling and Overhaul of the S8G Prototype Kesselring Site Refueling and Overhaul of the S8G Prototype The Kenneth A. Kesselring Site in West Milton, NY has two operating nuclear propulsion plants (also known as prototypes) that provide hands-on

More information

COFRENTES UNDERVESSEL PROJECT IN RFO 16 (2007) [ Replacement of all the CRDH undervessel piping]

COFRENTES UNDERVESSEL PROJECT IN RFO 16 (2007) [ Replacement of all the CRDH undervessel piping] COFRENTES UNDERVESSEL PROJECT IN RFO 16 (2007) [ Replacement of all the CRDH undervessel piping] IRPA 12 12 th International Congress of the International Radiation Protection Association Buenos Aires,

More information

From right to left: 3 The steam generator is

From right to left: 3 The steam generator is From right to left: 1 The steam generator is transported on SPMTs to the JS500 jack-up system. 2 The JS500 raises the steam generator to the height of the temporary hatch. 3 The steam generator is skidded

More information

CUSTOMER SPOTLIGHT Smoot Brothers

CUSTOMER SPOTLIGHT Smoot Brothers CUSTOMER SPOTLIGHT Smoot Brothers CUSTOMER SPOTLIGHT Smoot Brothers New Sheriff in Town Flat Bed Hauler Turns to Retired Trooper and Zonar to Improve Safety Score I told them they needed a secure, fool-proof

More information

Thinking Inside the Box

Thinking Inside the Box Using steel anchor boxes was the right decision for one of the year s most high-profile bridge projects. Thinking Inside the Box by Hans Hutton, S.E., and Randy Hitt There was much debate over the permanent

More information

Environmental Services World Leader

Environmental Services World Leader FCC Avenida del Camino de Santiago, 40 28050 Madrid Spain www.fcc.es al Services World Leader A global company improving the quality of life of more than 53 million people around the world Poland Romania

More information

Intermodal Transportation of Spent Nuclear Fuel from Office of Civilian Radioactive Waste Management Sites 9328

Intermodal Transportation of Spent Nuclear Fuel from Office of Civilian Radioactive Waste Management Sites 9328 Intermodal Transportation of Spent Nuclear Fuel from Office of Civilian Radioactive Waste Management Sites 9328 ABSTRACT Stephen Schmid Bechtel-SAIC Company, LLC Washington, DC Alexander Thrower U.S. DOE,

More information

Fukushima Daini Independent Review and Walkdown

Fukushima Daini Independent Review and Walkdown Fukushima Daini Independent Review and Walkdown IAEA Experts Meeting on Protection Against Extreme Earthquakes and Tsunamis ------------- September 2012 Authors: John Richards, EPRI Jim Johnson, JJJ &

More information

A REPORT ON CANADA S LARGEST CLEAN POWER PROJECT DARLINGTON REFURBISHMENT

A REPORT ON CANADA S LARGEST CLEAN POWER PROJECT DARLINGTON REFURBISHMENT A REPORT ON CANADA S LARGEST CLEAN POWER PROJECT DARLINGTON REFURBISHMENT AUGUST 2016 READY TO EXECUTE The Darlington Nuclear Generating Station has been safely and reliably producing almost 20 per cent

More information

Property Rooms on the Move. TOPICS IN THIS ISSUE Maximizing Crime Lab Results Leveraging the NGI System Addressing Stress Crime Scene Photography

Property Rooms on the Move. TOPICS IN THIS ISSUE Maximizing Crime Lab Results Leveraging the NGI System Addressing Stress Crime Scene Photography The magazine dedicated exclusively to the technology of evidence collection, processing, and preservation Volume 13, Number 1 January-February 2015 Property Rooms on the Move TOPICS IN THIS ISSUE Maximizing

More information

Reactor Core Internals Replacement of Ikata Units 1 and 2

Reactor Core Internals Replacement of Ikata Units 1 and 2 IAEA-CN-194-1P51 Reactor Core Internals Replacement of Ikata Units 1 and 2 K. Ikeda,T. Ishikawa,T. Miyoshi,T. Takagi Shikoku Electric Power Co., Inc., Takamatsu City, Japan Abstract. This paper presents

More information

Boiling Water Reactor Vessel and Internals (QA)

Boiling Water Reactor Vessel and Internals (QA) Boiling Water Reactor Vessel and Internals (QA) Program Description Program Overview As boiling water reactors have aged, various forms of operation-limiting stress corrosion cracking have appeared, first

More information

Nuclear power plant steam generators

Nuclear power plant steam generators APPLIC ATIONS Prolonging steam generator life with improved sludge removal Poly Tanks for ASCA, CODE, and Rinse Waste 52 Nuclear News October 2015 Luminant teamed with Westinghouse and Dominion Engineering

More information

LESSONS LEARNED THE DONALD C. COOK NUCLEAR PLANT STEAM GENERATOR DISPOSAL PROJECT. W. T. MacRae American Electric Power

LESSONS LEARNED THE DONALD C. COOK NUCLEAR PLANT STEAM GENERATOR DISPOSAL PROJECT. W. T. MacRae American Electric Power LESSONS LEARNED THE DONALD C. COOK NUCLEAR PLANT STEAM GENERATOR DISPOSAL PROJECT W. T. MacRae American Electric Power ABSTRACT The disposal of the Donald C. Cook Nuclear Plant s Unit 1 Steam Generators

More information

Reactor Vessel Removal: Improving Performance Big Rock Point Lessons Learned

Reactor Vessel Removal: Improving Performance Big Rock Point Lessons Learned Reactor Vessel Removal: Improving Performance Big Rock Point Lessons Learned P.T. Daly BNG America, D&D Operations 804 South Illinois Avenue, Oak Ridge, TN 37830 USA ABSTRACT The Big Rock Point (BRP) reactor

More information

6.0 ENGINEERED SAFETY FEATURES

6.0 ENGINEERED SAFETY FEATURES Engineered Safety Features Materials 6.0 ENGINEERED SAFETY FEATURES This chapter of the U.S. EPR Final Safety Analysis Report (FSAR) is incorporated by reference with supplements as identified in the following

More information

D. L. Gillas U. S. Department of Energy, Savannah River Operations Office P. O. Box A, Aiken, SC 29802

D. L. Gillas U. S. Department of Energy, Savannah River Operations Office P. O. Box A, Aiken, SC 29802 PACKAGING AND TRANSPORTATION OF DEPLETED URANIUM FOR DISPOSITION FROM THE ABSTRACT SAVANNAH RIVER SITE D. L. Gillas U. S. Department of Energy, Savannah River Operations Office P. O. Box A, Aiken, SC 29802

More information

Metal Fabricators. Phone DAKA (3252) Fax Serving the Construction Industry and Manufacturers Since 1977

Metal Fabricators. Phone DAKA (3252) Fax Serving the Construction Industry and Manufacturers Since 1977 Metal Fabricators Serving the Construction Industry and Manufacturers Since 1977 Structural Steel, Joists & Deck Miscellaneous & Ornamental Metals, Stairways & Railings OEM Fabrication / Custom Metal Work

More information

International Construction Consulting, LLC. Modularization Overview.

International Construction Consulting, LLC. Modularization Overview. International Construction Consulting, LLC Modularization Overview Presentation Overview 1 Modularization Overview 2 An Alternative Construction Method to Deliver Projects 3 Quick Selection Criteria for

More information

Developing a Low Power/Shutdown PRA for a Small Modular Reactor. Nathan Wahlgren

Developing a Low Power/Shutdown PRA for a Small Modular Reactor. Nathan Wahlgren Developing a Low Power/Shutdown PRA for a Small Modular Reactor Nathan Wahlgren NuScale Power, LLC June 23, 2014 1 Non-Proprietary Overview Probabilistic risk assessment (PRA) has traditionally focused

More information

Design Features, Economics and Licensing of the 4S Reactor

Design Features, Economics and Licensing of the 4S Reactor PSN Number: PSN-2010-0577 Document Number: AFT-2010-000133 rev.000(2) Design Features, Economics and Licensing of the 4S Reactor ANS Annual Meeting June 13 17, 2010 San Diego, California Toshiba Corporation:

More information

Dose Reduction Options for Refueling Tasks EPRI Report:

Dose Reduction Options for Refueling Tasks EPRI Report: Dose Reduction Options for Refueling Tasks EPRI Report: 1025309 Phung Tran, Senior Project Manager Principal Investigators: Paul Saunders, Rick Doty, PhD North American ISOE ALARA Symposium January 7-9,

More information

FRCSE installs spar mill to improve maintenance support to Fleet

FRCSE installs spar mill to improve maintenance support to Fleet Backhoe Operator Andy Fontaine (left) and project supervisor Tim Alkire remove the floor in the FRCSE Manufacturing Division in preparation for laying the concrete foundation to support a state-of-the-art

More information

Success Story ENGINEERED TRANSFER CHUTES HELP TERMINAL MAINTAIN HIGH VOLUME COAL HANDLING

Success Story ENGINEERED TRANSFER CHUTES HELP TERMINAL MAINTAIN HIGH VOLUME COAL HANDLING Success Story ENGINEERED TRANSFER CHUTES HELP TERMINAL MAINTAIN HIGH VOLUME COAL HANDLING Superior Midwest Energy Terminal handles approx. 22 million tons of PRB coal annually, loading approximately 450

More information

Technical Support Organization (TSO) at Chashma Nuclear Power Generating Station (CNPGS) Saeed

Technical Support Organization (TSO) at Chashma Nuclear Power Generating Station (CNPGS) Saeed Technical Support Organization (TSO) at Chashma Nuclear Power Generating Station (CNPGS) Saeed Contents Why TSO Required at CNPGS Purpose Approach for Formation of TSO How TSO was established at CNPGS

More information

Contractor Experience with Precast Bridge Elements in Utah. Eric Wells. Granite Construction

Contractor Experience with Precast Bridge Elements in Utah. Eric Wells. Granite Construction Contractor Experience with Precast Bridge Elements in Utah Utah DOT s Accelerated Bridge Program Contractor s Perspective Eric Wells Area Manager Granite Construction Eric Wells Granite Construction ABC

More information

MFN Docket No

MFN Docket No GE Hitachi Nuclear Energy Richard E. Kingston Vice President, ESBWR Licensing P.O. Box 780 M/C A-65 Wilmington, NC 28402-0780 USA T 910.675.6192 F 910.362.6192 rick.kingston@ge.com MFN 09-169 Docket No.

More information

Scope of Work Bid Package C-8 - West Overhead Doors

Scope of Work Bid Package C-8 - West Overhead Doors Scope of Work Bid Package C-8 - West Overhead Doors CONTRACT DOCUMENTS and REQUIREMENTS The Work of this Agreement shall include but shall not be limited to all labor, fringe benefits, materials, tools,

More information

PRODUCTION FORECAST AND METHODOLOGY NUCLEAR

PRODUCTION FORECAST AND METHODOLOGY NUCLEAR Filed: 0-0- Page of PRODUCTION FORECAST AND METHODOLOGY NUCLEAR 0 0 0.0 PURPOSE This evidence provides the production forecast for the nuclear facilities and a description of the methodology used to derive

More information

Powering Ontario for the next half-century: Refurbishing Darlington

Powering Ontario for the next half-century: Refurbishing Darlington Powering Ontario for the next half-century: Refurbishing Darlington By Colin Hunt, Publisher and Editor, Nuclear Canada Yearbook Introduction and Overview In 2016, Ontario Power Generation (OPG) will commence

More information

VEOLIA ES ALARON L.L.C. SOLUTIONS FOR THE NUCLEAR INDUSTRY

VEOLIA ES ALARON L.L.C. SOLUTIONS FOR THE NUCLEAR INDUSTRY VEOLIA ES ALARON L.L.C. SOLUTIONS FOR THE NUCLEAR INDUSTRY VISION STATEMENT Our Values As a Veolia company, Alaron shares in Veolia s vision. At Veolia Environmental Services North America, our vision

More information

America s Inland Waterways

America s Inland Waterways America s Inland Waterways Original prepared by Steve Little Crounse Corporation Modified by Chuck Knowles Kentucky Transportation Center America s Inland Waterways: An Inland Marine Highway for Freight

More information

Commercial Market Brochure General Line Products and Services

Commercial Market Brochure General Line Products and Services Commercial Market Brochure General Line Products and Services Setting the Standard for Building Safety 2011 American Warehouse Systems One Project - One Vendor Complete Engineered Material Handling Systems

More information

White Paper April 23, 2018

White Paper April 23, 2018 White Paper April 23, 2018 BEST PRACTICES: COORDINATING WITH UNION PACIFIC IN ALTERNATIVE DELIVERY PROJECTS PURPOSE The purpose of this document is to recommend best practices for how public entities can

More information

WM2010 Conference, March 7-11, 2010, Phoenix, AZ MODULAR CONSTRUCTION FOR EVENTUAL DECONSTRUCTION AND DECOMMISSIONING

WM2010 Conference, March 7-11, 2010, Phoenix, AZ MODULAR CONSTRUCTION FOR EVENTUAL DECONSTRUCTION AND DECOMMISSIONING MODULAR CONSTRUCTION FOR EVENTUAL DECONSTRUCTION AND DECOMMISSIONING - 10300 1 ABSTRACT Dr. Jas S. Devgun, Ph.D., CHMM Manager Nuclear Power Technologies Sargent & Lundy LLC 55 E. Monroe St Chicago, IL

More information

WI Revision 14 Safety

WI Revision 14 Safety ACCESS CONTROL MAIN GATE WI29.523 Revision 14 Safety 1.0 PURPOSE To allow only authorised vehicles, persons or materials to enter or exit the Liberty Onesteel Whyalla Main Security Gate. 2.0 SCOPE These

More information

INTERMODAL TRANSPORTATION, USACE STYLE

INTERMODAL TRANSPORTATION, USACE STYLE INTERMODAL TRANSPORTATION, USACE STYLE Author Kenneth M. Grumski MHF Logistical Solutions 129 McCarrell Lane Zelienople, Pennsylvania 16063 Co-author Peter W. Coutts The IT Group 175 East Park Drive, Building

More information

THE GLOBAL GROWTH OF PREVENTION THROUGH DESIGN. Bradley Giles, P.E., CSP, STS Vice President ESH&S, URS Corporation

THE GLOBAL GROWTH OF PREVENTION THROUGH DESIGN. Bradley Giles, P.E., CSP, STS Vice President ESH&S, URS Corporation THE GLOBAL GROWTH OF PREVENTION THROUGH DESIGN Bradley Giles, P.E., CSP, STS Vice President ESH&S, URS Corporation Safety Considerations in Design How it Started Content started in Constructability reviews

More information

EFCOG Waste Management Working Group Packaging and Transportation Subgroup Initiatives

EFCOG Waste Management Working Group Packaging and Transportation Subgroup Initiatives EFCOG Waste Management Working Group Packaging and Transportation Subgroup Initiatives Jim Portsmouth, CHPRC / Hanford Jeff England, SRNL Sydney Gordon, NSTec Mike Waters, CHPRC / Hanford Sonny Goldston

More information

Boiling Water Reactor Vessel and Internals

Boiling Water Reactor Vessel and Internals Boiling Water Reactor Vessel and Internals Program Description Program Overview As boiling water reactors have aged, various forms of operation-limiting stress corrosion cracking have appeared, first in

More information

WM 00 conference, February 27 March 2, 2000, Tucson, AZ

WM 00 conference, February 27 March 2, 2000, Tucson, AZ WM 00 conference, February 27 March 2, 2000, Tucson, AZ REACTOR PRESSURE VESSEL REMOVAL AT A BOILING WATER REACTOR WITH SPENT FUEL IN THE ADJACENT FUEL POOL By Albert A. Freitag, WMG, Inc Greg Harttraft,

More information

Cook Nuclear Plant Unit 1 - Event and Recovery

Cook Nuclear Plant Unit 1 - Event and Recovery Cook Nuclear Plant Unit 1 - Event and Recovery Presented by Gary Hatcher, CIH EEI Spring Occupational Safety and Health Committee Conference April 21-24, 2009 Contents Cook Unit 1 9/20/08 Main Turbine

More information

CONSTRUCTION PROJECT TEMPORARY FACILITIES SITING POLICY February 19, 2003

CONSTRUCTION PROJECT TEMPORARY FACILITIES SITING POLICY February 19, 2003 CONSTRUCTION PROJECT TEMPORARY FACILITIES SITING POLICY February 19, 2003 Authority: This policy has been approved by the Vice-Provost for Lands and Buildings. Summary: This policy outlines a procedure

More information

Doseo Pipeline Project Modularization Overview Advantages/Disadvantages & Drivers

Doseo Pipeline Project Modularization Overview Advantages/Disadvantages & Drivers PURPOSE Modularization will be evaluated herein as a cold eyes look into the potential construction technique to be applied to the Doseo Pipeline Project. This analysis will include a review of the drivers

More information

IMPROVING OUTAGE PERFORMANCE: THE OUTAGE OPTIMIZATION PROCESS

IMPROVING OUTAGE PERFORMANCE: THE OUTAGE OPTIMIZATION PROCESS IMPROVING OUTAGE PERFORMANCE: THE OUTAGE OPTIMIZATION PROCESS Jere LaPlatney VP Outage Optimization Jean-Paul Bombail Outage and Maintenance IB France 17-21 October 2011 AGENDA BACKGROUND OUTAGE OPTIMIZATION

More information

Smart Security CyCop Workforce Management Technology

Smart Security CyCop Workforce Management Technology Workforce Management Technology The Next Generation Information Management and Workforce Management Technology Security operations at commercial properties are uniquely challenging. Often fulfilling a

More information

Regulatory Actions and Follow up Measures against Fukushima Accident in Korea

Regulatory Actions and Follow up Measures against Fukushima Accident in Korea Int Conference on Effective Nuclear Regulatory Systems, April 9, 2013, Canada Regulatory Actions and Follow up Measures against Fukushima Accident in Korea Seon Ho SONG* Korea Institute of Nuclear Safety

More information

Risks Associated with Shutdown in PWRs

Risks Associated with Shutdown in PWRs International Conference Nuclear Option in Countries with Small and Mi Opatija, Croatia, 1996 Risks Associated with Shutdown in PWRs Igor Grlicarev Slovenian Nuclear Safety Administration Vojkova 59, 1113

More information

CARPENTER. If you like to. then you may just have a future as a Carpenter. Learn more at BuildYourFutureIndiana.org

CARPENTER. If you like to. then you may just have a future as a Carpenter. Learn more at BuildYourFutureIndiana.org CARPENTER CARPENTER If you like to Be physically active Be creative Be outdoors Solve problems Work under pressure Work with numbers and details then you may just have a future as a Carpenter. Carpenters

More information

Lessons learned from Angra 1 & Angra 2 NPP s Outages

Lessons learned from Angra 1 & Angra 2 NPP s Outages Lessons learned from Angra 1 & Angra 2 NPP s Outages DO Diretoria de Operação SM.O Superintendência de Manutenção Preparado por: Luciano Junqueira Calixto Email: lucical@eletronuclear.gov.br Angra 1: Angra

More information

AIChE Paper Number. Turnaround Planning New Approaches for Petrochemical Plants

AIChE Paper Number. Turnaround Planning New Approaches for Petrochemical Plants AIChE Paper Number Turnaround Planning New Approaches for Petrochemical Plants Samuel Blaser Field Operations Manager AST Turbo AG Robert Felton TurboMachinery Consultant Prepared for Presentation at the

More information

Westinghouse-UK Partnership for Development of a Small Modular Reactor Nuclear Programme

Westinghouse-UK Partnership for Development of a Small Modular Reactor Nuclear Programme Westinghouse-UK Partnership for Development of a Small Modular Reactor Nuclear Programme Simon Marshall UK Business & Project Development Director Nuclear Power Plants 1 The Westinghouse Small Modular

More information

Regulation of Waste Streams from Small Modular Reactors and Advanced Reactors

Regulation of Waste Streams from Small Modular Reactors and Advanced Reactors Regulation of Waste Streams from Small Modular Reactors and Advanced Reactors - 14061 ABSTRACT Anna Hajduk Bradford U.S. Nuclear Regulatory Commission 11545 Rockville Pike Rockville, MD 20852 The U.S.

More information

Opposition to Diablo Canyon Nuclear Power Plant since 1973

Opposition to Diablo Canyon Nuclear Power Plant since 1973 San Luis Obispo Opposition to Diablo Canyon Nuclear Power Plant since 1973 P.O. Box 3608 San Luis Obispo, CA 93403 http://mothersforpeace.org Who Are We? We are a local, non-profit organization concerned

More information

Dominion North Anna Power Station Restart Readiness

Dominion North Anna Power Station Restart Readiness Dominion North Anna Power Station Restart Readiness October 21, 2011 Briefing David A. Heacock, President & Chief Nuclear Officer Eugene S. Grecheck, Vice President, Nuclear Development 1 Dominion Assessment

More information

The ACR : Advanced Design Features for a Short Construction Schedule

The ACR : Advanced Design Features for a Short Construction Schedule Transactions of the 17 th International Conference on Structural Mechanics in Reactor Technology (SMiRT 17) Prague, Czech Republic, August 17 22, 2003 Paper # S01-3 The ACR : Advanced Design Features for

More information

The refurbishment of the Darlington. Darlington station to double its lifetime of service to Ontario By Dick Kovan

The refurbishment of the Darlington. Darlington station to double its lifetime of service to Ontario By Dick Kovan Outage Management Special Section The reactor mock-up with the retubing tooling platform, heavy worktable, and cutting tools. Darlington station to double its lifetime of service to Ontario By Dick Kovan

More information

FIG. 1. Fort St. Vrain Nuclear Generation Station.

FIG. 1. Fort St. Vrain Nuclear Generation Station. Invited Paper XA9848067 FORT ST. VRAIN DECOMMISSIONING PROJECT M. FISHER Public Service Company of Colorado, Denver, Colorado, USA Abstract Public Service Company of Colorado (PSCo), owner of the Fort

More information

Collective Radiation Exposure Performance and Industry Performance Trends

Collective Radiation Exposure Performance and Industry Performance Trends Institute of Nuclear Power Operations Collective Radiation Exposure Performance and Industry Performance Trends 2012 ISOE ALARA Symposium Bill Bullard, Sr. Evaluator. Radiation Protection 2012 Institute

More information

CITY OF TACOMA Tacoma Power & Public Works Engineering

CITY OF TACOMA Tacoma Power & Public Works Engineering CITY OF TACOMA Tacoma Power & Public Works Engineering ADDENDUM NO. 1 DATE: August 22, 2017 REVISIONS TO: Request for Bids Specification No. PE17-0235F Citywide LED Streetlight Installation NOTICE TO ALL

More information

CALIFORNIA HIGHWAY PATROL AGREEMENT

CALIFORNIA HIGHWAY PATROL AGREEMENT 18 One Gateway Plaza Los Angeles, CA 90012-2952 213.922.2000 Tel metro. net PLANNING AND PROGRAMMING COMMITTEE MAY 15, 2013 SUBJECT: ACTION: CALIFORNIA HIGHWAY PATROL AGREEMENT EXECUTE AN AGREEMENT WITH

More information

WM2013 Conference, February 24 28, 2013, Phoenix, Arizona USA. Factors Impacting Decommissioning Costs 13576

WM2013 Conference, February 24 28, 2013, Phoenix, Arizona USA. Factors Impacting Decommissioning Costs 13576 Factors Impacting Decommissioning Costs 13576 Karen Kim*, Richard McGrath* *Electric Power Research Institute, 342 Hillview Ave., Palo Alto, California. USA. kkim@epri.com, rmcgrath@epri.com ABSTRACT The

More information

ReliabilityFirst s Review of Winter Preparedness Following the Polar Vortex

ReliabilityFirst s Review of Winter Preparedness Following the Polar Vortex ReliabilityFirst s Review of Winter Preparedness Following the Polar Vortex Date November 13, 2015 i Table of Contents PREAMBLE AND LIMITATION OF PURPOSE... iii I. RELIABILITYFIRST S WINTERIZATION SURVEY

More information

NUCLEAR REGULATORY COMMISSION. [Docket Nos and ; NRC ] Entergy Nuclear Indian Point Unit 2, LLC

NUCLEAR REGULATORY COMMISSION. [Docket Nos and ; NRC ] Entergy Nuclear Indian Point Unit 2, LLC This document is scheduled to be published in the Federal Register on 07/13/2012 and available online at http://federalregister.gov/a/2012-17110, and on FDsys.gov [7590-01-P] NUCLEAR REGULATORY COMMISSION

More information

1 Transport. Introduction. 1.1 Lorries have empty or part loads

1 Transport. Introduction. 1.1 Lorries have empty or part loads 1 Transport Introduction The way that transportation is managed in relation to construction has a number of implications. Clearly the efficient movement of materials to sites is a fundamental requirement

More information

IAEA SAFETY STANDARDS for protecting people and the environment. Predisposal Management of Radioactive Waste from Nuclear Fuel Cycle Facilities

IAEA SAFETY STANDARDS for protecting people and the environment. Predisposal Management of Radioactive Waste from Nuclear Fuel Cycle Facilities DS447 Date: September 2014 IAEA SAFETY STANDARDS for protecting people and the environment STATUS: SPESS STEP 11 MS comments incorporated Review Committee Member comments due 31 Oct Predisposal Management

More information

STRUCTURAL RADIATION SAFETY AT A NUCLEAR FACILITY

STRUCTURAL RADIATION SAFETY AT A NUCLEAR FACILITY GUIDE YVL C.1 / 15 November 2013 STRUCTURAL RADIATION SAFETY AT A NUCLEAR FACILITY 1 Introduction 3 2 Scope of application 3 3 General design requirements 3 4 Radiation safety aspects in the layout design

More information

Current Activities on the 4S Reactor Deployment

Current Activities on the 4S Reactor Deployment PSN Number: PSN-2010-0586 Document Number: AFT-2010-000134 rev.000(1) Current Activities on the 4S Reactor Deployment The 4th Annual Asia-Pacific Nuclear Energy Forum on Small and Medium Reactors: Benefits

More information

COST AND PERFORMANCE BENEFITS OF DUAL LAMINATE PIPE OVER LINED STEEL

COST AND PERFORMANCE BENEFITS OF DUAL LAMINATE PIPE OVER LINED STEEL COST AND PERFORMANCE BENEFITS OF DUAL LAMINATE PIPE OVER LINED STEEL Kira Townsend Sales and Business Development Manager RPS Composites Inc. Mobile, AL Prepared for Clearwater 2016 40 th Annual International

More information

RESULTS FROM NONDESTRUCTIVE EXAMINATION OF PWR VESSEL INTERNALS. Jack Spanner, EPRI, USA

RESULTS FROM NONDESTRUCTIVE EXAMINATION OF PWR VESSEL INTERNALS. Jack Spanner, EPRI, USA More Info at Open Access Database www.ndt.net/?id=18595 Introduction RESULTS FROM NONDESTRUCTIVE EXAMINATION OF PWR VESSEL INTERNALS Jack Spanner, EPRI, USA This paper describes the initial results obtained

More information

Employee Safety Training Program

Employee Safety Training Program Employee Safety Training Program Line of Business: Workers Compensation, General Liability Risk Control Strategy/Key Issues: Employee training to improve job safety knowledge and reduce the number and

More information

IAEA OSART review-results-list Recommendations

IAEA OSART review-results-list Recommendations Assessment Field Item 1 2 Leadership and for safety Education and training Power station group structure and functions Employee certification training 3 Operation Groups and functions 4 Maintenance and

More information

Driving Business Performance

Driving Business Performance Workforce Scheduling Driving Business Performance How Workforce Scheduling Optimization Aligns the Workforce with Business Demands for Customer Satisfaction and Success While many factors affect an organization

More information

Transporting Spent Nuclear Fuel in the United States:

Transporting Spent Nuclear Fuel in the United States: September 2015 Transporting Spent Nuclear Fuel in the United States: An Assessment of Current Capabilities and Future Challenges This issue brief is one in a series prepared by the Bipartisan Policy Center

More information