1 Engage Consulting Briefing Note: Smart Metering Implementation Programme: Prospectus Introduction This briefing note summarises the content from the Smart Metering Implementation Programme: Prospectus published on 27 th July We intend it to be used to inform interested stakeholders and to summarise proposed Government policy in a short, easily accessed document. Executive Summary The Government has confirmed that it believes that every home in Great Britain should have a smart meter. To secure the delivery of the benefits, the Government wishes to accelerate significantly the rollout compared to previously published targets. Suppliers will start to install smart meters that meet the minimum requirements ahead of a central data and communications entity being established. DECC s impact assessments have been updated and they show that there remains a strong business case for taking the programme forward, with predicted benefits of 17.8 billion over the next twenty years, and a net benefit of 7.2 billion. Ofgem intends to introduce a package of measures in spring 2011, providing for consumer protections in areas such as remote disconnection, installation of new meters, and interoperability to provide suppliers with the necessary confidence to start installing smart meters and supports customers switching suppliers. A data privacy principle is to be proposed by Ofgem where consumers should be able to choose how their consumption data is used and by whom, except where data is required to fulfil regulated duties. Within customer premises, the metering system will be a smart meter for gas and electricity, a home area network, and a wide area network. For domestic consumers, suppliers will also be required to provide an in-home display (IHD). IHDs will have dual fuel functionality so any second supplier providing gas or electricity in a dual fuel home can use the IHD provided by the first supplier. It will be at any second suppliers discretion whether they wish to provide a second display. A Statement of Requirements document has been produced by Ofgem, covering the requirements of the metering system. The Government s view is that a gas valve should be included in domestic meters. The IHD will display, as a minimum, information in pounds and pence and non-numerically. The technical specifications for the Home Area Network are yet to be defined by Ofgem, but solutions will need to be based on open and interoperable standards for any solution used. Wide area network communications will be managed by the creation of a new central entity to identify and procure the most cost-effective solutions for smart metering data management and communications. The Wide Area Network communications module should be upgradable without the need for the meter to be changed. Energy suppliers are to take on the responsibility for the rollout of smart meters. Ofgem will introduce licence conditions into Suppliers licences to set targets for roll out that will include Engage Consulting Limited Page 1 of 6

2 flexibility in the early stages to enable suppliers to respond to customer demand and learn from experience. In parallel, during the initial stages of rollout, additional measures to increase the effectiveness of the rollout and secure the energy savings will be considered by Ofgem. These could include smart grids, local level consumer engagement, prioritise specific customer groups, assist vulnerable consumers or support energy efficiency initiatives. Ofgem requires responses on a number of key aspects of their consultation by 28 th September The responses on the remaining questions are required by 28 th October Engage Consulting provides consulting and IS services to the energy & utilities sector and has been a leader in smart metering development in Great Britain and Europe. Engage provides independent expert advice to energy retailers, network companies, environmental bodies, metering companies and many others through the supply chain for smart metering. Our services have included involvement with national smart meter programmes, benchmarking on customer behaviour, specialist reporting and business requirements reviews. Contacting Engage: Any questions or further enquiries, then please feel free to contact Peter Goodwin at Engage Consulting; +44 (0) or by at peter.goodwin@engage-consulting.co.uk Engage Consulting Limited Page 2 of 6

3 Confirmed by Government The Government has confirmed its commitment to the rollout of electricity and gas smart meters to all homes in Great Britain, including: Energy suppliers to be responsible under licence for procuring and installing smart meters; Data communications for domestic metering systems will be managed by a central function; Smart meters must comply with a set of high level functional requirements; Domestic customers will be provided with a IHD; and Electricity and gas meters at smaller non-domestic premises will need to have smart functionality within the same timescales as the domestic rollout. Energy suppliers are to take on the responsibility for the rollout of smart meters. Ofgem will introduce licence conditions into Suppliers licences to set targets for roll out that will include flexibility in the early stages to enable suppliers to respond to customer demand and learn from experience. In parallel, during the initial stages of rollout, consideration will be given to additional measures to increase the effectiveness of the rollout and secure the energy savings. These could include building smarter grids, local level consumer engagement, giving priority to specific customer groups, assisting vulnerable consumers or support for energy efficiency initiatives. The Consumer Experience Ofgem is reviewing current safeguards to ensure customers interests remain protected. For example, Ofgem is considering the protections around sales and marketing activities and vulnerable customers in the context of smart metering. Real time information is seen by Ofgem as key to helping consumers understand and optimise their energy use, to help save money and reduce carbon use. Ofgem has stated that smart metering will put an end to estimated bills, promote competition by enabling faster customer switching, and open up new products and services (e.g. energy advice, innovative tariffs, etc.). Minimum functionality requirements of the IHD should include the ability to display: current electricity and gas consumption; historical consumption to enable consumers to compare current and previous usage; information in pounds and pence as well as kilowatts and kilowatt hours, and the display must also present the information in a visual format which is non-numerical that enables customers to easily distinguish between high and low levels of consumption; accurate account balance information; and information for both gas and electricity consumption. Where a customer makes it clear that they do not want an IHD, suppliers will need to make alternative arrangements to provide consumption information. This could be via the customer bill. However, if the customer changes their mind within 12 months and decides that they would like an IHD, they will be entitled to receive one from their supplier, free of charge. Engage Consulting Limited Page 3 of 6

4 Suppliers will need to consider the requirements of disabled customers when providing an IHD. For example, this may include the use of large display screens and bigger buttons. Customers will also be able to use their own display devices connected to the home area network if they so choose. Consumers will have access to their consumption data stored on their meter free of charge to enable them to compare tariffs, and easily share the data with third parties should they wish to do so. The potential sensitivity of data on consumers energy usage is recognised. Ofgem has proposed that The customer shall choose in which way consumption data shall be used and by whom, with the exception of data required to fulfil regulatory duties. This reflects the important principle that data control rests with the consumer, whilst recognising access for legitimate needs. The industry will be required to put in place a code of practice for the installation process, taking onboard the concerns and risks raised by consumer groups. Ofgem has proposed that suppliers will be prohibited from imposing an upfront charge on customers to cover the costs associated with the installation of a smart meter. The Government s view is that the benefits of including a gas valve in the minimum functional requirements for domestic smart meters and the certainty this brings outweigh those of leaving it to supplier choice. However, for the smaller non-domestic sector gas smart meters will not require a gas valve. Ofgem expects that smart metering functionality will enable other value-added services, such as energy management and access to home automation initiatives. Central Communications Communication of both gas and electricity data to and from smart meters in the domestic sector will be managed centrally. The central function will also provide a basis to simplify and improve industry processes, including change of supplier, and smart grid development. The central communications functions scope will initially be limited to those functions that are essential for the effective transfer of smart metering data, and subsequently take on board meter registration from the network companies and Xoserve. The central communications function will be a new licensed entity, which Ofgem will licence and regulate. Central communication function trialling and testing will be complete by autumn 2013, along with the mandated use of the central communication function for domestic customers. Regulatory Regime Ofgem has proposed that a new regulatory regime will be established to provide arrangements for the introduction and ongoing operation of smart metering. These regulatory arrangements will be introduced using powers under the Energy Act 2008 to amend existing licences and codes, and to create a new licence activity. A new Smart Energy Code will be introduced by Ofgem to govern the operation of the smart metering system. The code will be one code to cover both gas and electricity. Engage Consulting Limited Page 4 of 6

5 Smart Metering Statement of Design Requirements The proposed smart metering system functional requirements are designed to deliver the range of currently identified benefits, and to be able to evolve as the future requirements of smart grids become clearer. The functional requirements shall include: The communications device should be modular or separate so it can be upgraded without replacing the meter; Last gasp" capability, which enables alerts to suppliers or network companies if the supply is interrupted; The meter should have the capability to store at least 12 months of half hourly consumption data, to enable more effective and informed supplier switching and home energy management initiatives; The meters and communications equipment will be able to be upgraded remotely through the download of firmware; Supply License condition mandating rollout will oblige suppliers to install smart meters that comply with the Catalogue and Technical Specifications; these will be incorporated into the Smart Energy Code by Ofgem. This will ensure technical interoperability; The gas valve should form part of the minimum requirements of all smart gas meters in the domestic sector; A single HAN solution is not proposed by Ofgem, in recognition that there may not be a 'one size fits all option'. However there is a requirement that there should only be a single HAN within a customers premise where technically possible; There is a requirement to limit the average power consumption of any mandated equipment in the consumer premise to 2.6W total; The Gas meter communications is expected by Ofgem to be powered by a battery. Ofgem has proposed a functional requirement for a 15 year battery life under normal operating conditions (metrology, communications and valve operations where applicable). It is noted that battery life constraints mean that any battery powered device will need to operate less frequently, for example transmitting every 15 minutes (Gas) rather than every 5 seconds (Electricity) (as proposed for mains powered devices); Ofgem has proposed that the WAN module should be modular or separate from the electricity meter, with digital and physical security measures close to the meter. The programme will seek a level of WAN interoperability during the initial phase to ensure that consumers can switch between suppliers without the need to exchange the WAN module; Meter design variants must also meet minimum functional requirements e.g. able to accommodate the likes of Economy 7 and dynamic teleswitching type tariffs; No requirement for pulse outputs as it is unlikely it would be used when the functionality is already available in an enhanced form; The consumer being present at the premises and acknowledges that certain criteria are met (e.g. appliances are off) when the supply is re-enabled after self or remote disconnection (which is distinct from outages due to supply faults); Pre-payment top up - the functional requirement includes the ability for remote (e.g. over WAN) and local top up; Prepayment configuration - the functional requirements include that smart metering system has to support the emergency credit, overnight credit, friendly credit, debt Engage Consulting Limited Page 5 of 6

6 recovery configuration and safeguards that are supported in token, card or key-based meters currently available. Also included are functionalities for new forms of disconnection such as trickle disconnection and time limited disconnection; Health and Safety - any solution selected will have to meet national and EU obligations on Health and Safety; and Micro-generation - functional requirements include import / export metrology. Next Steps The Government wishes to accelerate significantly the roll out of smart meters compared to previously published targets. They are looking at the potential for shortening both the preparation period and the roll out period. The proposed staged implementation approach is expected by Ofgem to advance the start of the formal mandate by at least a year compared to the alternative approach of waiting until the full smart metering regulatory regime, systems, and central communications has been established. Key milestone dates: Date Spring 2011 Summer 2011 Early 2012 Spring 2012 Summer 2012 Autumn 2012 Spring 2013 Autumn 2013 Milestone Enhanced consumer protections introduced as required Functional requirements and technical specifications confirmed (subject, if required, to the outcome of any EU notification period) Supply licence modifications mandating rollout implemented Regulatory framework relating to DCC (central communications function) implemented Mandated supplier rollout commences DCC licence granted DCC service providers appointed DCC trialling and testing complete & Mandated use of DCC for domestic customers Suppliers may elect to install meters prior to the go live of the central communication function (August 2013), but this will be at their own commercial risk, with any meters not meeting the required technical specifications needing to be replaced. Responses on a number of key aspects of the consultation are required by 28 th September The responses on the remaining questions are required by 28 th October Engage Consulting Limited Page 6 of 6

CER National Smart Metering Programme Policy Implementation Roadmap

CER National Smart Metering Programme Policy Implementation Roadmap CER National Smart Metering Programme Policy Implementation Roadmap DOCUMENT TYPE: REFERENCE: Information Paper CER/15/055 DATE: 31 March 2015 The Commission for Energy Regulation, The Exchange, Belgard

More information

Smart meters, regulation and market development

Smart meters, regulation and market development Smart meters, regulation and market development Colin Sausman, Ofgem EPRG Spring Seminar 25 May 2012 INTRODUCTION 2 Ofgem Our role in general: Independent regulator of gas and electricity markets in GB

More information

Smart Metering Implementation Programme

Smart Metering Implementation Programme Smart Metering Implementation Programme Consultation on Smart Metering Rollout Strategy DCC response 19 th May 2015 DCC PUBLIC Page 1 of 14 1 Executive Summary 1.1 Introduction and background 1. DCC provides

More information

Electric Ireland response to CER/15/272 Proposed Decisions on Empowering & Protecting Customers

Electric Ireland response to CER/15/272 Proposed Decisions on Empowering & Protecting Customers Smart Metering Programme Office Commission for Energy Regulation, The Exchange, Belgard Square North, Tallaght, Dublin 24. 22 nd January 2016 response to CER/15/272 Proposed Decisions on Empowering & Protecting

More information

Update on the Smart Meter Upgrade

Update on the Smart Meter Upgrade Update on the Smart Meter Upgrade Information Paper Reference: CER/17/279 Date Published: 21 September 2017 Closing Date: N/A Smart meters are the next generation of electricity and gas meter and are being

More information

European Commission s proposal for a revised Electricity Directive

European Commission s proposal for a revised Electricity Directive European Commission s proposal for a revised Electricity Directive ESMIG proposals for amendments 1 : Article 2 paragraph 18 18. smart metering system means an electronic system that can measure energy

More information

Smart-metering rollout scenarios & CBA BGN Response to CER/10/197 Consultation

Smart-metering rollout scenarios & CBA BGN Response to CER/10/197 Consultation Smart-metering rollout scenarios & CBA BGN Response to CER/10/197 Consultation Table of Contents 1. Introduction... 3 2. Objectives... 4 3. Ownership, display and provision of data... 4 3.1 Gas data granularity...

More information

DEFINITIONS Glossary of Terms SCOPE OF THE CODE In Scope Not in Scope Third Parties...

DEFINITIONS Glossary of Terms SCOPE OF THE CODE In Scope Not in Scope Third Parties... Contents DEFINITIONS... 5 Glossary of Terms... 5 Section A The Code of Practice 1. SCOPE OF THE CODE...10 1.1. In Scope...10 1.2. Not in Scope...10 1.3. Third Parties...11 1.4. Code Structure...11 2. PRE-INSTALLATION...12

More information

A Guide to the Non-Domestic Gas and Electricity Retail Markets

A Guide to the Non-Domestic Gas and Electricity Retail Markets 10 January 2017 A Guide to the Non-Domestic Gas and Electricity Retail Markets Outline This guide sets out the key features of the I&C non-domestic gas and electricity retail markets in Great Britain.

More information

Citizens Advice Response to DECC s Consultation on Home Area Network (HAN) Implementation of 868MHz and Alternative HAN

Citizens Advice Response to DECC s Consultation on Home Area Network (HAN) Implementation of 868MHz and Alternative HAN Citizens Advice Response to DECC s Consultation on Home Area Network (HAN) Solutions: Implementation of 868MHz and Alternative HAN solutions Introduction The Citizens Advice service provides free, independent,

More information

CER National Smart Metering Programme Status Update

CER National Smart Metering Programme Status Update CER National Smart Metering Programme Status Update DOCUMENT TYPE: REFERENCE: Information Paper CER/16/126 DATE PUBLISHED: QUERIES TO: 15 April 2016 smartmetering@cer.ie The Commission for Energy Regulation,

More information

CBI Response to BEIS Call for Evidence

CBI Response to BEIS Call for Evidence CBI Response to BEIS Call for Evidence Smart, Flexible Power System The CBI welcomes the opportunity to respond to the BEIS Call for Evidence on A Smart, Flexible Energy System. Across the UK, the CBI

More information

DEFINITIONS Glossary of Terms Section A The Code of Practice SCOPE OF THE CODE In Scope...

DEFINITIONS Glossary of Terms Section A The Code of Practice SCOPE OF THE CODE In Scope... Contents DEFINITIONS... 5 Glossary of Terms... 5 Section A... 9 The Code of Practice... 9 1. SCOPE OF THE CODE... 10 1.1. In Scope... 10 1.2. Not in Scope... 10 1.3. Third Parties... 11 1.4. Code Structure...

More information

MCE Decision paper. 13 December A National Minimum Functionality for Smart Meters

MCE Decision paper. 13 December A National Minimum Functionality for Smart Meters MCE Decision paper 13 December 2007 A National Minimum Functionality for Smart Meters In April 2007 COAG committed to a national mandated roll-out of electricity smart meters to areas where benefits outweigh

More information

The use of consumers energy consumption data emanating from smart meters is governed by the Data Access Privacy Framework (DAPF).

The use of consumers energy consumption data emanating from smart meters is governed by the Data Access Privacy Framework (DAPF). The Information Commissioner s Office response to the Department of Business, Energy & Industrial Strategy and Ofgem s Call for Evidence on a Smart, Flexible Energy System. The Information Commissioner

More information

Framework for the Provision of Smart Metering Support

Framework for the Provision of Smart Metering Support Framework for the Provision of Smart Metering Support 1. Background 1.1. Smart meters can deliver significant benefits for energy consumers, including accurate billing and the information they need to

More information

COMMISSION STAFF WORKING PAPER

COMMISSION STAFF WORKING PAPER EN EN EN EUROPEAN COMMISSION Brussels, 22 January 2010 COMMISSION STAFF WORKING PAPER INTERPRETATIVE NOTE ON DIRECTIVE 2009/72/EC CONCERNING COMMON RULES FOR THE INTERNAL MARKET IN ELECTRICITY AND DIRECTIVE

More information

Consultation on extending the existing smart meter framework for data access and privacy to Smart-Type Meters and Advanced Meters

Consultation on extending the existing smart meter framework for data access and privacy to Smart-Type Meters and Advanced Meters Consultation on extending the existing smart meter framework for data access and privacy to Smart-Type Meters and Advanced Meters Consultation Contact: Colin Down, Senior Policy Manager Publication date:

More information

Energy and Climate Change Committee Enquiry Progress on Smart Meter Roll Out

Energy and Climate Change Committee Enquiry Progress on Smart Meter Roll Out Energy and Climate Change Committee Enquiry Progress on Smart Meter Roll Out 1. The roll out of smart meters is vitally important to our energy future; therefore we welcome the opportunity to submit evidence

More information

Initial Enrolment Project Feasibility Draft Report Consultation Document

Initial Enrolment Project Feasibility Draft Report Consultation Document Initial Enrolment Project Feasibility Draft Report Consultation Document Date issued: 11/11/2016 Consultation closes: 20/01//2017 Classification: DCC Public Contents 1 Executive Summary... 4 2 Introduction...

More information

EAI Response to CER National Smart Metering Programme, Presentation of Energy Usage Information (CSI) and Pay As You Go consultation papers

EAI Response to CER National Smart Metering Programme, Presentation of Energy Usage Information (CSI) and Pay As You Go consultation papers EAI Response to CER National Smart Metering Programme, Presentation of Energy Usage Information (CSI) and Pay As You Go consultation papers Electricity Association of Ireland Retail Working Group 127 Baggot

More information

The potential impact of smart meters on the retail market

The potential impact of smart meters on the retail market The potential impact of smart meters on the retail market EPRG Conference May 16 th 2014 Let s look at the potential impact from some different perspectives Technology Governments / Regulators Impact on

More information

DCC Operations update. Industry Event 15 th December Dave Broady Operations Director, Smart DCC. DCC Public

DCC Operations update. Industry Event 15 th December Dave Broady Operations Director, Smart DCC. DCC Public DCC Operations update Industry Event 15 th December 2015 Dave Broady Operations Director, Smart DCC DCC Public Service Desk Core Team All staff trained by DCC 100% Availability in year up to 30 th November

More information

The Information Commissioner s response to the Competition and Market Authority s Energy market investigation: notice of possible remedies paper.

The Information Commissioner s response to the Competition and Market Authority s Energy market investigation: notice of possible remedies paper. The Information Commissioner s response to the Competition and Market Authority s Energy market investigation: notice of possible remedies paper. The Information Commissioner s role The Information Commissioner

More information

Smart Metering Implementation Programme. Consultation on New Smart Energy Code Content

Smart Metering Implementation Programme. Consultation on New Smart Energy Code Content Smart Metering Implementation Programme Consultation on New Smart Energy Code Content Page 1 of 9 Contents 1 Executive Summary... 3 1.1 Introduction and background... 3 1.2 DCC's response... 3 2 Notifying

More information

DCC OPERATIONS UPDATE

DCC OPERATIONS UPDATE DCC OPERATIONS UPDATE 02 February 2016 Dave Broady Operations Director, Smart DCC DCC Public Service Desk Core Team All staff trained by DCC 100% Availability in year up to 31 December 2015 SD has gained

More information

Smart Meter Testing & Trialling Discussion Paper ERA SRSM Group 2.7 7th December 2011

Smart Meter Testing & Trialling Discussion Paper ERA SRSM Group 2.7 7th December 2011 Smart Meter Testing & Trialling Discussion Paper ERA SRSM Group 2.7 7th December 2011 Introduction Recognising the criticality of a successful test and trial phase within the Smart Meter programme the

More information

Code of Practice. Our Commitment to You

Code of Practice. Our Commitment to You Code of Practice Our Commitment to You Introduction This booklet explains how you can get in touch with us, what to do in case of an electrical emergency, what the special services we provide for vulnerable

More information

Imraan Mohamed Marketing Manager Itron South Africa

Imraan Mohamed Marketing Manager Itron South Africa Imraan Mohamed Marketing Manager Itron South Africa Agenda: Architecture for Smart metering 1. Context : Smart Grids and Smart Metering. 2. The Smart Metering Value Chain. 3. Key Tenents for Smart Metering

More information

Summary: Intervention and Options

Summary: Intervention and Options Title: Energy Bill: Amendment to the Energy Act 2008 powers to implement and direct the rollout of smart meters Lead department or agency: DECC Other departments or agencies: Impact Assessment (IA) IA

More information

Market-wide Half-Hourly Settlement

Market-wide Half-Hourly Settlement PUBLIC Market-wide Half-Hourly Settlement Design Working Group: ELEXON Version 1.0 4 April 2018 CONTENTS EXECUTIVE SUMMARY... 3 INTRODUCTION... 4 1. Ofgem SCR on Market-wide Half-Hourly Settlement... 4

More information

Target Operating Model Design Principles. 1. Purpose of the Design Principles

Target Operating Model Design Principles. 1. Purpose of the Design Principles Target Operating Model Design Principles 1. Purpose of the Design Principles 1.1. The SCR Launch Statement sets out our plan to implement an enduring process for HHS for domestic and smaller non-domestic

More information

UNC 0630R: Review of the consequential changes required in UNC as a result of the Ofgem Switching Programme. UNC Request Workgroup Report

UNC 0630R: Review of the consequential changes required in UNC as a result of the Ofgem Switching Programme. UNC Request Workgroup Report UNC Request Workgroup Report At what stage is this document in the process? UNC 0630R: Review of the consequential changes required in UNC as a result of the Ofgem Switching Programme Purpose of Request:

More information

Smart meter Instructions

Smart meter Instructions Smart meter Instructions What are smart meters? They re energy meters for the 21st century. They can help you keep better track of the energy you use, and they give you all the information you need to

More information

Fixed Price Energy A Guaranteed Deal

Fixed Price Energy A Guaranteed Deal Fixed Price Energy A Guaranteed Deal Fixed Price Energy March 2015 (v2) Offer WithFreedom Prices effective from 29th August 2013 Limited Offer subject to availability and may be withdrawn from sale at

More information

Gazprom Marketing and Trading Retail

Gazprom Marketing and Trading Retail Gazprom Marketing and Trading Retail Gazprom Marketing and Trading Retail (GM&TR) is the energy retail subsidiary of Gazprom Marketing & Trading (GM&T), a 100% subsidiary of OAO Gazprom, the leading global

More information

INITIAL ANALYSIS OF ADOPTING A 15-MINUTE SETTLEMENT PERIOD

INITIAL ANALYSIS OF ADOPTING A 15-MINUTE SETTLEMENT PERIOD INITIAL ANALYSIS OF ADOPTING A 15-MINUTE SETTLEMENT PERIOD PURPOSE OF ANALYSIS AND APPROACH FOLLOWED Ofgem has approached ELEXON for our initial analysis of the impacts, costs and benefits to Settlement

More information

GEODE Autumn Seminar Efficient Energy Markets European Regulators Perspective

GEODE Autumn Seminar Efficient Energy Markets European Regulators Perspective GEODE Autumn Seminar Efficient Energy Markets European Regulators Perspective Patricia de Suzzoni, Chair of CEER s Customers and Retail Markets WG Barcelona, 27 November 2014 Introduction: what should

More information

Fixed Price Energy A Guaranteed Deal

Fixed Price Energy A Guaranteed Deal Fixed Price Energy A Guaranteed Deal Fixed Price Energy March 2015 Offer WithFreedom Prices effective from 11th June 2013 Limited Offer subject to availability and may be withdrawn from sale at any time.

More information

By to: Rachel Clark Programme Director, Switching Programme Ofgem 9 Millbank London SW1P 3GE.

By  to: Rachel Clark Programme Director, Switching Programme Ofgem 9 Millbank London SW1P 3GE. By e-mail to: switchingprogramme@ofgem.gov.uk Rachel Clark Programme Director, Switching Programme Ofgem 9 Millbank London SW1P 3GE 3 November 2017 Dear Rachel, We welcome the opportunity to comment on

More information

EAI Response to CER National Smart Metering Programme, Smart Metering High Level Design proposed decision paper

EAI Response to CER National Smart Metering Programme, Smart Metering High Level Design proposed decision paper EAI Response to CER National Smart Metering Programme, Smart Metering High Level Design proposed decision paper Electricity Association of Ireland Retail Working Group 127 Baggot Street Lower Dublin 2

More information

STATEMENT OF CHARGES FOR THE USE OF SP MANWEB METERING SERVICES

STATEMENT OF CHARGES FOR THE USE OF SP MANWEB METERING SERVICES STATEMENT OF CHARGES FOR THE USE OF SP MANWEB METERING SERVICES This statement is effective from 1st November 2008 SP Energy Networks New Alderston House Dove Wynd Strathclyde Business Park Bellshill ML4

More information

Fast-Track to a Digital Platform to Improve Utilities Customer Engagement

Fast-Track to a Digital Platform to Improve Utilities Customer Engagement SAP Brief SAP Extensions SAP Self-Service Accelerator for Utilities by SEW Fast-Track to a Digital Platform to Improve Utilities Customer Engagement SAP Brief Meet utility customer demand for digital Customer

More information

Insight and agility. An updated guide to optimising collections in utilities

Insight and agility. An updated guide to optimising collections in utilities Insight and agility An updated guide to optimising collections in utilities June 2011 Contents 1. Introduction 3 2. A 10 step guide to improving your collections strategy 5 2 - Insight and agility : A

More information

Costs and benefits of introducing competition to residential customers in England A response to Ofwat s emerging findings

Costs and benefits of introducing competition to residential customers in England A response to Ofwat s emerging findings Costs and benefits of introducing competition to residential customers in England A response to Ofwat s emerging findings Consumer Council for Water Response August 2016 1. Introduction 1.1 The Consumer

More information

Compressed Natural Gas for transport Licensing arrangements

Compressed Natural Gas for transport Licensing arrangements Compressed Natural Gas for transport Licensing arrangements DOCUMENT TYPE: REFERENCE: DATE PUBLISHED: CLOSING DATE: RESPONSES TO: Consultation Paper D/15/051 March 25 th 2015 May 8 th 2015 bhussey@cer.ie

More information

Response to Smart Meter Implementation Code of Practice

Response to Smart Meter Implementation Code of Practice Response to Smart Meter Implementation Code of Practice 8 March 2013 Smart Meter Implementation Code of Practice Ombudsman Services consultation response 1 Summary 1.1 About Ombudsman Services The Ombudsman

More information

SP Manweb. Statement of Charges for Metering Services

SP Manweb. Statement of Charges for Metering Services SP Manweb Statement of Charges for Metering Services Effective from 1st April 2018 Version 1.0 SP ENERGY NETWORKS, OCHIL HOUSE, 10 TECHNOLOGY AVENUE, HAMILTON INTERNATIONAL TECHNOLOGY PARK, BLANTYRE, G72

More information

Learnings from the Swedish Market. Mälarenergi Elnät AB

Learnings from the Swedish Market. Mälarenergi Elnät AB Learnings from the Swedish Market Mälarenergi Elnät AB De-regulated market in Sweden Separation between supplier and DSO in 1996 1 TSO, Prox. 170 DSO s and 120 suppliers 1 regulator (same for TSO and DSO)

More information

Santa Clara 2008 PG&E. Associate Project Manager Energy Information Network

Santa Clara 2008 PG&E. Associate Project Manager Energy Information Network PG&E SmartMeter Program Overview Megan O Brien Associate Project Manager Energy Information Network The PG&E SmartMeter Program Automated meter reading for all customers 10 Million meter upgrades A network

More information

EDMI ENERGY CLOUD. The energy management solution / ELECTRICITY /

EDMI ENERGY CLOUD. The energy management solution / ELECTRICITY / EDMI ENERGY CLOUD The energy management solution GAS / ELECTRICITY / WATER 01 Contents 1.0 - EDMI Energy Cloud 2 1.1 - The Status Quo 3 1.2 - The Smart Solution 4 1.3 - Energy Cloud Benefits 5 2.0 - What

More information

Guaranteed Standards of Performance

Guaranteed Standards of Performance Guaranteed Standards of Performance In addition to our commitment to achieve high standards of customer service, Ofgem set out specific standards that we are required to adhere to. These are called our

More information

SP Manweb. Statement of Charges for Metering Services

SP Manweb. Statement of Charges for Metering Services SP Manweb Statement of Charges for Metering Services Effective from 1st April 2013 Version 1.0 SP ENERGY NETWORKS, NEW ALDERSTON HOUSE, DOVE WYND, STRATHCLYDE BUSINESS PARK, BELLSHILL. ML4 3FF Contents

More information

277/06 - PRELIMINARY TERRE (P344) IMPLEMENTATION IN ADVANCE OF OFGEM DECISION

277/06 - PRELIMINARY TERRE (P344) IMPLEMENTATION IN ADVANCE OF OFGEM DECISION - PRELIMINARY TERRE (P344) IMPLEMENTATION IN MEETING NAME BSC Panel Meeting Date of meeting 12 April 2018 Paper number Owner/author Purpose of paper Classification Summary Rob Greenoak Decision Public

More information

IRISH WATER A NEW NATIONAL UTILITY

IRISH WATER A NEW NATIONAL UTILITY IRISH WATER A NEW NATIONAL UTILITY UCC: Law and the Environment Conference 2014 Integrated Approaches to Environmental Law and Regulation 3 April 2014 Orla Joyce, Solicitor Irish Water CONTENTS 1. Government

More information

Smart prepayment for a smarter market. Response to Ofgem proposals - October 2015

Smart prepayment for a smarter market. Response to Ofgem proposals - October 2015 Smart prepayment for a smarter market Response to Ofgem proposals - October 2015 Introduction The Citizens Advice Service provides free, confidential and impartial advice to help people resolve their problems.

More information

What next for retail competition in energy?

What next for retail competition in energy? What next for retail competition in energy? Regulatory Policy Institute Annual Competition & Regulation Conference 7 September 2009 Philip Davies Director of Regulatory Affairs British Gas Overview Market

More information

Supplier of Last Resort in Prepayment Electricity. Consultation Paper. An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities

Supplier of Last Resort in Prepayment Electricity. Consultation Paper. An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities An Coimisiún um Rialáil Fóntas Commission for Regulation of Utilities Supplier of Last Resort in Prepayment Electricity Consultation Paper Consultation Paper Reference: CRU17333 Date Published: 07/12/2017

More information

CENTRAL DATA SERVICES PROVIDER ANNUAL CHARGING STATEMENT. For the period 1 st APRIL st MARCH 2019

CENTRAL DATA SERVICES PROVIDER ANNUAL CHARGING STATEMENT. For the period 1 st APRIL st MARCH 2019 CENTRAL DATA SERVICES PROVIDER ANNUAL CHARGING STATEMENT For the period 1 st APRIL 2018 31 st MARCH 2019 Version 2.0 Published 19 September 2018 CDSP Annual Charging Statement 2018/19 Page 1 of 12 1. Introduction

More information

ENERGEX Inverter Energy Systems

ENERGEX Inverter Energy Systems ENERGEX Inverter Energy Systems Connecting Your Inverter Energy System to the ENERGEX Network 8181 13.08.2010 ENERGEX Limited trading as ENERGEX ABN: 40 078 849 055 http://www.energex.com.au Requests and

More information

CER National Smart Metering Programme Rolling out New Services: Time-of-Use Tariffs

CER National Smart Metering Programme Rolling out New Services: Time-of-Use Tariffs CER National Smart Metering Programme Rolling out New Services: Time-of-Use Tariffs DOCUMENT TYPE: REFERENCE: DATE PUBLISHED: Decision CER/15/270 8 December 2015 The Commission for Energy Regulation, The

More information

Consultation on the Transition and Migration Approach Document for DCC s Service for SMETS1 Devices and accompanying changes to the SMETS1 Supporting

Consultation on the Transition and Migration Approach Document for DCC s Service for SMETS1 Devices and accompanying changes to the SMETS1 Supporting Consultation on the Transition and Migration Approach Document for DCC s Service for SMETS1 Devices and accompanying changes to the SMETS1 Supporting Requirements Date: 3 May 2018 Classification: DCC Public

More information

P302 Improving the Change of Supplier Meter read process for smart Meters

P302 Improving the Change of Supplier Meter read process for smart Meters Stage 01: What stage is this document in the process? Improving the Change of Supplier Meter read process for smart Meters This Modification proposal proposes changes to the Code and BSCPs to amend the

More information

Consumer Experiences in the UK: Pathway to Re-regulation? Presentation to QCOSS Forum on deregulating energy prices 24 October 2013

Consumer Experiences in the UK: Pathway to Re-regulation? Presentation to QCOSS Forum on deregulating energy prices 24 October 2013 Presented by Dr Gill Owen Research Program Leader, Consumers and Energy Markets, Monash Sustainability Institute Consumer Experiences in the UK: Pathway to Re-regulation? Presentation to QCOSS Forum on

More information

PUBLIC ELEXON Version February 2016

PUBLIC ELEXON Version February 2016 PUBLIC Recommendations of the BSC Panel s Settlement Reform Advisory Group Improving Half Hourly Settlement for smart metered customers and the impacts of export spill from distributed generation ELEXON

More information

igt Agency Services The relevant extract from GT UNC TPD V6.5 is shown in appendix 1. Final version December 2013 igt Agency Services industry report

igt Agency Services The relevant extract from GT UNC TPD V6.5 is shown in appendix 1. Final version December 2013 igt Agency Services industry report igt Agency Services A report to the gas industry on the costs and benefits identified by the industry associated with the implementation of the igt Agency Services arrangements. igt Agency Services is

More information

September A report for British Gas

September A report for British Gas The The economic value of contribution smart metering of BAE to Systems to the Great UK in Britain 2009 September 2012 A report for British Gas Contents Executive Summary... 1 1 Introduction... 3 1.1 Smart

More information

REVISION NO.: 8 EFFECTIVE: 03/26/18

REVISION NO.: 8 EFFECTIVE: 03/26/18 Distributed Generation Interconnection Process for Residential and Small General Service OVERVIEW REVISION NO.: 8 EFFECTIVE: 03/26/18 Required Steps for ED3 s Distributed Generation Interconnection Process

More information

PG&E s General Comments on Demand Response Vision Update. January 11, 2008

PG&E s General Comments on Demand Response Vision Update. January 11, 2008 PG&E s General Comments on Demand Response Vision Update January 11, 2008 This document provides PG&E s comments on the draft California Demand Response: A Vision of the Future. The comments are divided

More information

Smart tariffs balancing innovation and complexity. GB Smart Customer Response Trials Workshop May 2011

Smart tariffs balancing innovation and complexity. GB Smart Customer Response Trials Workshop May 2011 Smart tariffs balancing innovation and complexity GB Smart Customer Response Trials Workshop May 2011 zoe.mcleod@consumerfocus.org.uk Smart tariffs potential consumer benefits Smart deals to incentivise

More information

DCC Draft Development Priorities to

DCC Draft Development Priorities to DCC Draft Development Priorities 2018-19 to 2022-23 Date: December 2017 Classification: DCC Public Table of Contents 1 Executive Summary... 3 2 Introduction... 4 3 Drivers for our development... 7 4 Horizon

More information

Supporting Documentation A Changing Industry and Marketplace 0

Supporting Documentation A Changing Industry and Marketplace 0 Supporting Documentation A Changing Industry and Marketplace 0 Ergon Energy s Regulatory Proposal is presented in a number of documents to make it easier for our different stakeholders to access the information

More information

Demand Side Management: Who should take Control?

Demand Side Management: Who should take Control? Demand Side Management: Who should take Control? When a large number of people use their high-energy appliances simultaneously, it can result in a peak in electricity demand and a corresponding rise in

More information

MASSACHUSETTS ELECTRIC COMPANY NANTUCKET ELECTRIC COMPANY TARIFF FOR BASIC SERVICE

MASSACHUSETTS ELECTRIC COMPANY NANTUCKET ELECTRIC COMPANY TARIFF FOR BASIC SERVICE Sheet 1 MASSACHUSETTS ELECTRIC COMPANY NANTUCKET ELECTRIC COMPANY TARIFF FOR BASIC SERVICE 1. General This Tariff may be revised, amended, supplemented or supplanted in whole or in part from time to time

More information

Smart Utility Meters And The Movement Toward Dynamic Pricing: The Need For Effective Consumer Protections

Smart Utility Meters And The Movement Toward Dynamic Pricing: The Need For Effective Consumer Protections Smart Utility Meters And The Movement Toward Dynamic Pricing: The Need For Effective Consumer Protections Janee Briesemeister, AARP John Howat, National Consumer Law Center Jessica Hiemenz National Consumer

More information

This proposal will outline a solution that will enable suppliers to be compliant with the EU three week switching directive.

This proposal will outline a solution that will enable suppliers to be compliant with the EU three week switching directive. Stage 02: What stage is this document in the process? : EU Third package: Three week switching This proposal will outline a solution that will enable suppliers to be compliant with the EU three week switching

More information

What are your general views on the idea of a Scottish publicly owned energy company (POEC)?

What are your general views on the idea of a Scottish publicly owned energy company (POEC)? ECONOMY, ENERGY AND FAIR WORK COMMITTEE PUBLICLY OWNED ENERGY COMPANY INQUIRY SUBMISSION FROM SSE What are your general views on the idea of a Scottish publicly owned energy company (POEC)? SSE is one

More information

Online Fixed Energy A Guaranteed Deal

Online Fixed Energy A Guaranteed Deal Online Fixed Energy A Guaranteed Deal Online Fixed Price Energy October 2014 Offer WithFreedom Prices effective from 20th May 2013 Limited Offer subject to availability and may be withdrawn from sale at

More information

Smart Metering Device Assurance Scheme Operator Services. Request for Proposal 10 th September VERSION: V1.2 Final September 2014

Smart Metering Device Assurance Scheme Operator Services. Request for Proposal 10 th September VERSION: V1.2 Final September 2014 Smart Metering Device Assurance Scheme Operator Services Request for Proposal 10 th September 2014 VERSION: V1.2 Final September 2014 1 P a g e SMDA Scheme Operator RFP THE RESPONDENT SHALL AT ALL TIMES

More information

Retail and Reducing Energy Costs: a Working Group of the Retail Consultation Forum Submission in response to CER Consultation CER/16/031

Retail and Reducing Energy Costs: a Working Group of the Retail Consultation Forum Submission in response to CER Consultation CER/16/031 Retail and Reducing Energy Costs: a Working Group of the Retail Consultation Forum Submission in response to CER Consultation CER/16/031 Review of the Electricity and Gas Supplier s Handbook 25 April 2016

More information

Tackling Tariff Design. Making distribution network costs work for consumers

Tackling Tariff Design. Making distribution network costs work for consumers Tackling Tariff Design Making distribution network costs work for consumers Contents Introduction 02 What s driving change? 05 Alternative tariff designs 07 Impacts on consumers bills 11 Reflections and

More information

CENTRAL DATA SERVICES PROVIDER ANNUAL CHARGING STATEMENT. For the period 1 st APRIL st MARCH 2019

CENTRAL DATA SERVICES PROVIDER ANNUAL CHARGING STATEMENT. For the period 1 st APRIL st MARCH 2019 CENTRAL DATA SERVICES PROVIDER ANNUAL CHARGING STATEMENT For the period 1 st APRIL 2018 31 st MARCH 2019 Version 1.0 Published 31 st January 2018 CDSP Annual Charging Statement 2018/19 Page 1 of 12 1.

More information

10/02/2017 Version pptx. 1

10/02/2017 Version pptx. 1 The Information Commissioner s response to the Department for Business, Energy and Industrial Strategy call for evidence on implementing Midata in the energy sector The Information Commissioner has responsibility

More information

Risk Management Strategy. Version: V3.0

Risk Management Strategy. Version: V3.0 Risk Management Strategy Version: V3.0 Date: October 2016 Classification: DCC Public Document Control (Document Control Heading) Revision History (Document Control Subtitle) Revision Date Summary of Changes

More information

Online Energy Saver. A Discounted Deal

Online Energy Saver. A Discounted Deal Online Energy Saver A Discounted Deal Online Energy Saver 3 Offer Pricing Information 3rd December 2012 Revised Online Energy Saver 3 Offer prices as a result of a change to our standard domestic prices

More information

Smart Metering. Big Data and the Value of Analytics WHITE PAPER

Smart Metering. Big Data and the Value of Analytics WHITE PAPER Smart Metering Big Data and the Value of Analytics WHITE PAPER SAS White Paper Table of Contents Executive Summary.... 1 Smart Metering: What Is It?.... 1 Smart Metering: Why Is It Important?.... 2 Phase

More information

Terms & Conditions. For the Supply of Gas and Electricity to our Domestic Customers

Terms & Conditions. For the Supply of Gas and Electricity to our Domestic Customers Terms & Conditions For the Supply of Gas and Electricity to our Domestic Customers Contents Introduction and definitions... 3 1. About your supply contract... 4 2. Energy tariff and charges... 5 3. Paying

More information

Controlled Load Tariff

Controlled Load Tariff This group will be trialling the use of a controlled load tariff for supplying key loads and ancillary farm equipment. The aim is to understand the implications for farms switching from tariffs with power

More information

CONSUMER ACCESS DEVICES APPLICATIONS FOR DATA IN THE CONSUMER HOME AREA NETWORK (C HAN) AND WIDER MARKET CONSIDERATIONS

CONSUMER ACCESS DEVICES APPLICATIONS FOR DATA IN THE CONSUMER HOME AREA NETWORK (C HAN) AND WIDER MARKET CONSIDERATIONS Bringing power to life. CONSUMER ACCESS DEVICES APPLICATIONS FOR DATA IN THE CONSUMER HOME AREA NETWORK (C HAN) AND WIDER MARKET CONSIDERATIONS A BEAMA practical guide COMPANIES INVOLVED IN THE PREPARATION

More information

What is a prepayment system?

What is a prepayment system? What is a prepayment system? Just a new meter? Just a Point Of Sale terminal? Just a database? 1 What is a prepayment system? All components are linked together to form a complete system! 2 The Wind of

More information

OFG 1044 E Serve Band A roles Glasgow

OFG 1044 E Serve Band A roles Glasgow OFG 1044 E Serve Band A roles Glasgow About us Ofgem is Great Britain s gas and electricity regulator. Our goal is to protect energy customers interests, now and in the future. We make sure competition

More information

Understanding Microgrids

Understanding Microgrids With the increased focus on renewable energy, efficiency and the need to make the business case for the smart grid, a growing number of stakeholders are focusing on smart microgrids as a viable approach

More information

PRYSM ADVANCED METERING INFRASTRUCTURE. Intelligent Digital Solutions for a Smarter India

PRYSM ADVANCED METERING INFRASTRUCTURE. Intelligent Digital Solutions for a Smarter India PRYSM ADVANCED METERING INFRASTRUCTURE Intelligent Digital Solutions for a Smarter India VELANKANI SMART GRID PRODUCTS DRIVING INNOVATIVE ENERGY EFFICIENT SOLUTIONS Smart metering essentially involves

More information

Our Customer Relationship Agreement FIBRE TO THE HOME SERVICE DESCRIPTION

Our Customer Relationship Agreement FIBRE TO THE HOME SERVICE DESCRIPTION Our Customer Relationship Agreement FIBRE TO THE HOME SERVICE DESCRIPTION iinet Limited ACN 068 628 937 Phone: 13 22 58 1/502 Hay Street, Subiaco WA 6008 23 January 2015 Rules of interpretation and capitalised

More information

DCC Business Case for DCC activities during the Transitional Phase of the Switching Programme. Design Baseline 2 Update

DCC Business Case for DCC activities during the Transitional Phase of the Switching Programme. Design Baseline 2 Update DCC Business Case for DCC activities during the Transitional Phase of the Switching Programme Design Baseline 2 Update Version: V3.1.3 Date: 8 February 2018 Author: Classification: Freddie Akompi DCC Public

More information

DCC Business Case for DCC activities during the Transitional Phase of the Switching Programme

DCC Business Case for DCC activities during the Transitional Phase of the Switching Programme DCC Business Case for DCC activities during the Transitional Phase of the Switching Programme Version: V3.0 Date: 29 March 2017 Author: Classification: Aimi Hayman and Bryn Coles DCC Public Document Control

More information

31st January Prices. Your domestic gas and electricity pricing information

31st January Prices. Your domestic gas and electricity pricing information 31st January 2014 Prices Your domestic gas and electricity pricing information How to find your electricity supply area See what supply area you are in by using the map below. 17 18 15 AREA AREA NAME 10

More information

Market-wide Half-Hourly Settlement

Market-wide Half-Hourly Settlement PUBLIC Market-wide Half-Hourly Settlement Design Working Group: Draft Skeleton TOMs for ELEXON Version 1.0 6 March 2018 CONTENTS INTRODUCTION... 3 1. Ofgem SCR on Market-wide Half-Hourly Settlement...

More information

INTRODUCTION. SSE Airtricity welcomes the opportunity to comment on the CER s paper National Smart Metering Programme - Smart Pay As You Go.

INTRODUCTION. SSE Airtricity welcomes the opportunity to comment on the CER s paper National Smart Metering Programme - Smart Pay As You Go. CONSULTATION ON CER NATIONAL SMART METERING PROGRAMME SMART PAY AS YOU GO SSE AIRTRICITY RESPONSE TO THE COMMISSION FOR ENERGY REGULATION 2015 INTRODUCTION SSE Airtricity welcomes the opportunity to comment

More information

EPSU Comments on the Status Review on Regulatory Aspects of Metering (Electricity and Gas), May 2009 REF: E09-RMF-17-03, Version 7, 21 September 2009

EPSU Comments on the Status Review on Regulatory Aspects of Metering (Electricity and Gas), May 2009 REF: E09-RMF-17-03, Version 7, 21 September 2009 EPSU Comments on the Status Review on Regulatory Aspects of Metering (Electricity and Gas), May REF: E09-RMF-17-03, Version 7, 21 September December The European Regulators for Gas and Electricity Group

More information