Energy and Climate Change Committee Enquiry Progress on Smart Meter Roll Out

Size: px
Start display at page:

Download "Energy and Climate Change Committee Enquiry Progress on Smart Meter Roll Out"

Transcription

1 Energy and Climate Change Committee Enquiry Progress on Smart Meter Roll Out 1. The roll out of smart meters is vitally important to our energy future; therefore we welcome the opportunity to submit evidence to your inquiry. 2. As you are aware Energy Networks Association (ENA) is the industry body representing the UK s Electricity and Gas transmission and distribution networks operators. The following comments are provided by ENA on behalf of its member companies in response to the invitation published on 22 September A number of ENA member companies may have responded individually to your request. The comments in this document are submitted in support of the individual submissions that may have been provided by our member companies. Written Evidence Submitted by Energy Networks Association 4. Networks are preparing to support smart metering roll out to ensure that customers receive a positive experience of installation and over subsequent years if problems arise with individual meters. We will do this by continuing to work closely with DECC, Ofgem, DCC, suppliers, other stakeholders and with each other over throughout the rollout programme. 5. Although Gas and Electricity Network Operators don t have overall responsibility for delivering the smart meter roll out they have an important role to play both during and after the roll out. To put the Network Operator involvement into context we provide some background information in a) and b) below: a. During the roll out - Smart meter installers will need to interact with Network Operator equipment in order to undertake the safe installation of each Gas or Electricity meter. It is likely that in some instances this interaction with Network Operator s equipment will identify issues that need to be attended to by the Network Operator before the meter installation can continue. Network Operators are planning to be ready to respond to an increasing number of these interventions as the roll out progresses in order to ensure that any asset related issues do not unavoidably hold up the progress of the roll out. During the roll out Electricity Network Operators will also start to use the smart metering system to deliver customer benefits. Electricity Network Operators are already planning to develop their IT systems to enable them to use smart metering derived information to enhance their existing processes. These plans will be developed and finalised as information from DCC becomes available in accordance with the Industry Plan. b. After the roll out - Network Operators will be users of the smart metering system and will have access to information derived from smart meters. Although the information available from Gas networks is limited it is expected that this information may assist with network planning and help our Gas Network Operator

2 members make better informed reinforcement decisions in specific location. For Electricity Network Operators the information provided by smart meters will play an important part in the transition to a low carbon future. Our Electricity Network Operator members are proposing to use the information from the smart metering system to help them prepare to manage changes to power flows on electricity networks arising from changes in customer energy usage associated with an increased use of low carbon technologies (e.g. heat pumps, electric vehicles and PV s) and to design their networks more effectively and efficiently. Smart meters also have the potential to enable Network Operators to improve the service they provide to customers during certain types of network faults. 6. We provide the following responses to your questions from a Network Operator perspective. What progress has been made on smart meter roll-out since our last report on this subject? 7. Network Operators are not responsible for the roll out but they are required to support the roll out of smart meters by ensuring that they attend site to resolve any service termination issues which are identified during the meter installation activity. Since July 2013 whilst there has been a marginal increase in the volume of such activity, this has been adequately managed with existing resources. Our Electricity Network Operator members have supported the development of service levels associated with this activity, however visibility of future Supplier roll out plans will be critical to ensure both our Gas and Electricity Distribution Network Operator members are able to continue to deliver the present high level of service. 8. Our members are now developing their IT systems to provide the DCC with the metering registration data it requires to operate and they have also started to procure the systems that interface directly with the DCC smart metering system. To what extent has the Government addressed the concerns we raised about smart-meter roll-out, and the concerns raised by other interested parties since we published our last report? 9. From a Network Operators perspective we were pleased with the Committee s recommendation in the last report for DECC to draw up a co-operation protocol to require Suppliers to work together for a more efficient roll out. To date we have not seen any activity from DECC to achieve closer working by Suppliers. We are aware that the Association of Managing Agents is very keen for Suppliers to co-ordinate their smart meter installations where their customers are located in multi-occupancy buildings. They are seeking a co-ordinated approach to smart meter installations so that all Suppliers install their equipment during the same period and not in an ad hoc fashion over the duration of the programme, each time causing disruption. Network Operators are supportive of Suppliers being encouraged to work together in multi-occupancy buildings as this would help network operators resolve any network related issues that are

3 identified during the course of the smart meter installation in a co-ordinated manner minimising any disruption to customers. What problems have emerged during the foundation stage and how are they been addressed? 10. The meter replacement activity during the foundation stage has given rise to some additional intervention work for Network Operators. We are reliant on smart meter installers reporting network related issues to us promptly and correctly. Incorrect reporting ties up Network Operator resources, increasing costs which are ultimately bourn by customers. In order to minimise incorrect reporting ENA has been working with the Association of Meter Operators to improve the guidance offered to their members. Network Operators are also looking to put in place arrangements for regular collaboration with Suppliers and Meter Operators during the course of the smart meter roll-out so that parties can share their experiences and improve the accuracy of network issue reporting. 11. Network Operators are concerned that should the foundation period be extended there will be a higher proportion of SMETS1 meters installed than originally anticipated. A number of potential customer benefits delivered though Electricity Networks will not be available where SMETS1 meters are installed. Electricity Network Operators are keen to maximise the benefits that can be delivered to customers from the use of the smart metering system and they are actively being encouraged by Ofgem to do so. Electricity Network Operators would therefore prefer to see the number of SMETS1 meters installed kept to a minimum (e.g. no more than 5%). a. Currently, gas distribution networks have responded to no gas calls from customers with smart meters, where upon attendance, the root cause has been due to the meter valve closure. We believe full testing of the interoperability of the meter systems is critical to avoid such instances of no gas to customers, together with appropriate education materials to explain to existing credit customers the potential difference in experience from smart meters with valves to a traditional dumb meter with no meter valve. This educational material should also detail who to contact for what type of issue to ensure the most timely, effective and cost efficient response for customers. What are the remaining challenges (technical, communication or other) associated with launching the mass roll-out of smart meters in 2015, and completing it by 2020? 12. The smart meter programme is very complex programme involving multiple parties which has a relatively short implementation time. From an ENA perspective the technical challenges that still need to be overcome include finalising the detailed specification for the smart meters (GBCS) and the DCC services available to Users (DUGIS) as well as developing the necessary Network Operators systems and procedures to access the DCC services and deliver the benefits to customers. Appreciation of full smart meter benefits for customers is essential, including reduced long term network reinforcement

4 costs and an improved service during outages. Extensive early deployment creating two tiers of smart meter users risks frustrating and complicating this communication challenge with customers. ENA and its members are fully supportive of the programme s objectives and have been playing their part in the relevant SMIP transitional governance groups. Delivery of Customer Benefits from Network Operator Use of the Smart Metering System 13. Electricity Network Operators have an obligation and a desire to deliver customer benefits from the use of the smart metering system. ENA and its members are doing all we can to engage with the relevant SMIP stakeholders in order to ensure that the planned Network Operator functionality of the smart metering system is delivered as expected. The customer benefits that can be realised from Electricity Network Operator use of the smart metering system can only be fully realised if the functionality works as expected and is not eroded by technical difficulties, changes in scope, increases in cost, programme delays, poor WAN connectivity etc. 14. Our Gas Distribution Network Operators have been considering the use of the smart metering system to improve both the customer experience and how information could support their network operations. Our Gas Distribution Network members are working with the industry to determining the potential costs and benefits from being able to access this information. Network Operator Capability to Support the Rollout 15. In order for Network Operators to support the Suppliers in their installation activity Network Operators need to have adequate forward visibility of Supplier roll out plans so that they can plan their resources to manage the expected increase in interventions work accordingly. There are some significant factors that are preventing Suppliers from producing reliable and sufficiently detailed rollout plans. These factors include the completion of the SMETS2 specification and greater certainty of when SMETS2 meters will be available in sufficient volumes. How can these challenges be overcome? 16. ENA and its members suggest that: a. DECC continue their efforts to finalise and drive through the completion of the SMETS2 & GBCS specification and that DCC continue to finalise the DUGIS. Completion of these specification in conjunction with all stakeholders should minimise the technical risk that smart meter functionality is not delivered as expected; b. although SMETS2 and DUGIS are not completed suppliers should engage manufacturers in the early preparations for mass production as this will reduce the lead-in time once the specification is completed and minimise the number of SMETS1 meters installed;

5 c. DECC continue to encourage suppliers to share their roll out plans as soon as possible; so that network operators can plan their resources to carry out remedial work efficiently; and d. DECC and Ofgem oversee the programme with much closer oversight of DCC operations to ensure cost efficiencies and minimisation of increases to DCC charges in the future. What are the best approaches to monitoring the mass roll-out of smart meters? 17. We are aware that Ofgem are developing Supplier reporting obligations and have completed their consultation on this. We are also aware that DECC are looking to monitor the roll out with further separate reporting obligations for Suppliers. ENA suggests that government departments co-ordinate their requests for information so that Suppliers only have to provide one set of reporting items that can be used by DECC and Ofgem. Furthermore, ENA consider that Supplier forecast information should be shared with those stakeholders that rely on knowing Supplier plans in order to build their strategy to support the programme; e.g. Network Operators, the DCC and Smart Energy GB. What contribution can smart meters make to expanding the use of Demand Side Response as a means of addressing possible capacity shortages? 18. Smart meters themselves have the functionality to facilitate expanding the use of Demand Side Response (DSR), however there is a need to give careful consideration to the governance and commercial arrangements that will need to be developed in conjunction with all stakeholders including customers. At the moment access to the smart meter functionality that would facilitate DSR is limited to suppliers and they are likely to take the initial lead in developing commercial arrangements with their customers. There is a need to recognise that some DSR actions may have an adverse impact on gas and electricity networks and there is a need to ensure that can the technical and commercial arrangements co-ordinate so that they can co-exist without conflict. It is worth noting that generally the DSR actions that may have an impact on gas and electricity networks are those that would encourage consumers to increase their energy demand at particular time. In the scenario of a generation capacity shortage, it would be likely that DSR actions would encourage the reduction in energy consumption. However the same DSR action may encourage consumers to consume more energy later when the generation capacity shortage has ended, but this may give rise to a network capacity shortage. By way of an example DSR could be used to encourage EV charging to take place after the evening peak to avoid creating a generation capacity issue, but if all EVs where configured to charge in early in the morning this could create network capacity issues particularly in those areas that already have a high penetration of electric space and water heating. It is important that all the implication of DSR for all stakeholders are considered as such arrangement are developed.

6 To realise the full potential benefits of smart meters, is it necessary to introduce time of use pricing for Electricity? 19. Time of use pricing for energy can be used to change customer behaviour and therefore has potential to help manage generation capacity shortages or network capacity shortages. It also has potential to help customers manage their energy bills. Smart metering simply facilitates the delivery of such benefits.

Smart Metering Implementation Programme

Smart Metering Implementation Programme Smart Metering Implementation Programme Consultation on Smart Metering Rollout Strategy DCC response 19 th May 2015 DCC PUBLIC Page 1 of 14 1 Executive Summary 1.1 Introduction and background 1. DCC provides

More information

Engage Consulting Briefing Note: Smart Metering Implementation Programme: Prospectus

Engage Consulting Briefing Note: Smart Metering Implementation Programme: Prospectus Engage Consulting Briefing Note: Smart Metering Implementation Programme: Prospectus Introduction This briefing note summarises the content from the Smart Metering Implementation Programme: Prospectus

More information

CBI Response to BEIS Call for Evidence

CBI Response to BEIS Call for Evidence CBI Response to BEIS Call for Evidence Smart, Flexible Power System The CBI welcomes the opportunity to respond to the BEIS Call for Evidence on A Smart, Flexible Energy System. Across the UK, the CBI

More information

Electricity North West Future Challenges. Dr Geraldine Bryson Innovation Implementation Engineer

Electricity North West Future Challenges. Dr Geraldine Bryson Innovation Implementation Engineer Electricity North West Future Challenges Dr Geraldine Bryson Innovation Implementation Engineer 1 Agenda Introducing Electricity North West Low carbon future Innovation & the energy challenge Summary and

More information

CER National Smart Metering Programme Status Update

CER National Smart Metering Programme Status Update CER National Smart Metering Programme Status Update DOCUMENT TYPE: REFERENCE: Information Paper CER/16/126 DATE PUBLISHED: QUERIES TO: 15 April 2016 smartmetering@cer.ie The Commission for Energy Regulation,

More information

Target Operating Model Design Principles. 1. Purpose of the Design Principles

Target Operating Model Design Principles. 1. Purpose of the Design Principles Target Operating Model Design Principles 1. Purpose of the Design Principles 1.1. The SCR Launch Statement sets out our plan to implement an enduring process for HHS for domestic and smaller non-domestic

More information

Gas Engineering Recommendation GER2 Issue A GUIDE FOR INDUSTRY PARTIES REGARDING BUSINESS AS USUAL (BAU) ISSUES RELATING TO SMART METERS

Gas Engineering Recommendation GER2 Issue A GUIDE FOR INDUSTRY PARTIES REGARDING BUSINESS AS USUAL (BAU) ISSUES RELATING TO SMART METERS Gas Engineering Recommendation GER2 Issue 2 2018 A GUIDE FOR INDUSTRY PARTIES REGARDING BUSINESS AS USUAL (BAU) ISSUES RELATING TO SMART METERS 1 2018 Energy Networks Association All rights reserved. No

More information

Risk Management Strategy. Version: V3.0

Risk Management Strategy. Version: V3.0 Risk Management Strategy Version: V3.0 Date: October 2016 Classification: DCC Public Document Control (Document Control Heading) Revision History (Document Control Subtitle) Revision Date Summary of Changes

More information

How to incentivise utilities to adopt low carbon technologies

How to incentivise utilities to adopt low carbon technologies How to incentivise utilities to adopt low carbon technologies Dora Guzeleva Head of Network Policy, Ofgem Metering Billing / CRM 9-11 October 2012 Amsterdam Contents 1. Innovation in Next Price Control

More information

INITIAL ANALYSIS OF ADOPTING A 15-MINUTE SETTLEMENT PERIOD

INITIAL ANALYSIS OF ADOPTING A 15-MINUTE SETTLEMENT PERIOD INITIAL ANALYSIS OF ADOPTING A 15-MINUTE SETTLEMENT PERIOD PURPOSE OF ANALYSIS AND APPROACH FOLLOWED Ofgem has approached ELEXON for our initial analysis of the impacts, costs and benefits to Settlement

More information

Smart meters, regulation and market development

Smart meters, regulation and market development Smart meters, regulation and market development Colin Sausman, Ofgem EPRG Spring Seminar 25 May 2012 INTRODUCTION 2 Ofgem Our role in general: Independent regulator of gas and electricity markets in GB

More information

Electricity System Operator Forward Plan 2018/19

Electricity System Operator Forward Plan 2018/19 Electricity System Operator Forward Plan 2018/19 Contents 1. Our vision 2. An ambitious plan 3. A changing landscape 4. Value for consumers 5. A plan built with our customers and stakeholders 6. Our roles,

More information

CONSULTATION. SMKI and Repository Testing Approach Document. Consultation opens: 12 th March Consultation closes: 10 th April 2015

CONSULTATION. SMKI and Repository Testing Approach Document. Consultation opens: 12 th March Consultation closes: 10 th April 2015 CONSULTATION SMKI and Repository Testing Approach Document Consultation opens: 12 th March 2015 Consultation closes: 10 th April 2015 DCC Public Page 1 of 11 Contents 1 Executive summary... 3 2 Introduction

More information

DCC Operations update. Industry Event 15 th December Dave Broady Operations Director, Smart DCC. DCC Public

DCC Operations update. Industry Event 15 th December Dave Broady Operations Director, Smart DCC. DCC Public DCC Operations update Industry Event 15 th December 2015 Dave Broady Operations Director, Smart DCC DCC Public Service Desk Core Team All staff trained by DCC 100% Availability in year up to 30 th November

More information

Smart Metering Implementation Programme. Consultation on New Smart Energy Code Content

Smart Metering Implementation Programme. Consultation on New Smart Energy Code Content Smart Metering Implementation Programme Consultation on New Smart Energy Code Content Page 1 of 9 Contents 1 Executive Summary... 3 1.1 Introduction and background... 3 1.2 DCC's response... 3 2 Notifying

More information

DCC OPERATIONS UPDATE

DCC OPERATIONS UPDATE DCC OPERATIONS UPDATE 02 February 2016 Dave Broady Operations Director, Smart DCC DCC Public Service Desk Core Team All staff trained by DCC 100% Availability in year up to 31 December 2015 SD has gained

More information

Call for Evidence Green Deal Framework

Call for Evidence Green Deal Framework Call for Evidence Green Deal Framework Energy UK response 30 th November 2017 Introduction Energy UK is the trade association for the GB energy industry with a membership of over 90 suppliers, generators,

More information

Strategic Investment Options for Low Carbon Economy in the South Wales. 15th June 2016

Strategic Investment Options for Low Carbon Economy in the South Wales. 15th June 2016 Strategic Investment Options for Low Carbon Economy in the South Wales 15th June 2016 WPD Our Area 4 of 14 Distribution UK Licence Areas 7.8 Million Customers Covers 55,500 Sq Km 220,000km of Network 185,000

More information

P302 Improving the Change of Supplier Meter read process for smart Meters

P302 Improving the Change of Supplier Meter read process for smart Meters Stage 01: What stage is this document in the process? Improving the Change of Supplier Meter read process for smart Meters This Modification proposal proposes changes to the Code and BSCPs to amend the

More information

Energy Networks Association - Response to Call for Evidence from BEIS/Ofgem

Energy Networks Association - Response to Call for Evidence from BEIS/Ofgem The Voice of the Networks A Smart, Flexible Energy System Energy Networks Association - Response to Call for Evidence from BEIS/Ofgem Background Please find below the response from Energy Networks Association

More information

Facilitating Whole Electricity System Outcomes

Facilitating Whole Electricity System Outcomes Facilitating Whole Electricity System Outcomes How the ESO is working with stakeholders to transform the energy landscape The way we generate and use electricity is changing, driven by the challenges of

More information

Operating the Electricity Transmission Networks in 2020

Operating the Electricity Transmission Networks in 2020 Operating the Electricity Transmission Networks in 2020 Initial Consultation JUNE 2009 Why has National Grid published this document? National Grid operates the transmission networks across Great Britain

More information

Citizens Advice Response to DECC s Consultation on Home Area Network (HAN) Implementation of 868MHz and Alternative HAN

Citizens Advice Response to DECC s Consultation on Home Area Network (HAN) Implementation of 868MHz and Alternative HAN Citizens Advice Response to DECC s Consultation on Home Area Network (HAN) Solutions: Implementation of 868MHz and Alternative HAN solutions Introduction The Citizens Advice service provides free, independent,

More information

Outage Protocol: Explanatory note

Outage Protocol: Explanatory note Outage Protocol: Explanatory note This is the version of the outage protocol (previously in section VII of part F of the Electricity Governance Rules 2003) that the Authority is required to publish by

More information

ELEXON response to National Grid s consultation of its System Needs and Product Strategy 18 July 2017

ELEXON response to National Grid s consultation of its System Needs and Product Strategy 18 July 2017 ELEXON response to National Grid s consultation of its System Needs and Product Strategy 18 July 2017 ELEXON sent the following responses to National Grid in relation to its System Needs and Product Strategy

More information

In responding to the consultation, we would like to draw your attention to the following points:

In responding to the consultation, we would like to draw your attention to the following points: Energy Networks Association 4 More London Riverside London SE1 2AU Dear Sir/Madam Open Networks Future Worlds consultation This response to the Open Networks Future Worlds consultation has been prepared

More information

Energy UK response to the Electricity System Operator Forward Plan

Energy UK response to the Electricity System Operator Forward Plan ECC 09-18 Energy UK response to the Electricity System Operator Forward Plan 09 March 2018 About Energy UK Energy UK is the trade association for the GB energy industry with a membership of over 100 suppliers,

More information

Review of Analysis of Network Benefits from Smart Meter Message Flows

Review of Analysis of Network Benefits from Smart Meter Message Flows Review of Analysis of Network Benefits from Smart Meter Message Flows (Including RIIO ED1 and ED2 phasing and categorisation of benefits) 1 st July 2013 Version 1.0 1 Page 2 of 15 Review of Analysis of

More information

UK Power Networks Innovation and future energy systems. Neil Madgwick & Giulia Privitera 3 March 2017

UK Power Networks Innovation and future energy systems. Neil Madgwick & Giulia Privitera 3 March 2017 UK Power Networks Innovation and future energy systems Neil Madgwick & Giulia Privitera 3 March 2017 Agenda Key forces influencing future energy systems The changing role of the Distribution Network Operator

More information

1. How can Ofgem ensure that sharper Cash Out incentives from the Significant Code Review:

1. How can Ofgem ensure that sharper Cash Out incentives from the Significant Code Review: 1. How can Ofgem ensure that sharper Cash Out incentives from the Significant Code Review: encourage generators and suppliers to balance their own positions before gate closure, thus reducing the call

More information

Smart Meter Testing & Trialling Discussion Paper ERA SRSM Group 2.7 7th December 2011

Smart Meter Testing & Trialling Discussion Paper ERA SRSM Group 2.7 7th December 2011 Smart Meter Testing & Trialling Discussion Paper ERA SRSM Group 2.7 7th December 2011 Introduction Recognising the criticality of a successful test and trial phase within the Smart Meter programme the

More information

Ensure your own actions reduce risks to health and safety

Ensure your own actions reduce risks to health and safety Ensure your own actions reduce risks to health and safety UNIT SM 1 Area of competence This unit is designed to demonstrate competence in following the health and safety duties required in the workplace

More information

Position Description: Site Supervisor Reports to: Site Manager/Project Manager

Position Description: Site Supervisor Reports to: Site Manager/Project Manager Position Description: Site Supervisor Reports to: Site Manager/Project Manager Overall Responsibilities Direct onsite supervision of staff and subcontractors. Application of knowledge, skills, tools, and

More information

Open Networks Project 2018 Work Plan Consultation innogy renewables UK response

Open Networks Project 2018 Work Plan Consultation innogy renewables UK response Farina Farrier Energy Networks Association 6th Floor, Dean Bradley House 52 Horseferry Road London SW1P 2AF Fruzsina Kemenes Policy Manager innogy renewablesuk ltd. Email: fruzsina.kemenes@innogy.com Submitted

More information

Smart Meters The Impact on Customer Service Operations

Smart Meters The Impact on Customer Service Operations Smart Meters The Impact on Customer Service Operations James Barnes Utility Customer Service Administrator City of Tallahassee Utilities Copyright 2010 Accenture All Rights Reserved. Accenture, its logo,

More information

Amendments to input methodologies for electricity distribution services and Transpower New Zealand

Amendments to input methodologies for electricity distribution services and Transpower New Zealand ISBN 978-1-869454-11-1 14.09/12685:14.11/12685 Public version Amendments to input methodologies for electricity distribution services and Transpower New Zealand Incremental Rolling Incentive Scheme Date

More information

UK Case Studies. 4 th July 2013 Steinkjer, Norway. Esther Dudek

UK Case Studies. 4 th July 2013 Steinkjer, Norway. Esther Dudek UK Case Studies 4 th July 2013 Steinkjer, Norway Esther Dudek Presentation Contents Summary of four case studies: The Energy Demand Reduction Trial E.ON Thinking Energy Trial Customer Led Network Revolution

More information

UK Power Networks. Technology Watch (Smart) Networks Context & Innovation. 28 th April, 2015 David Boyer, Smart Networks Policy Lead

UK Power Networks. Technology Watch (Smart) Networks Context & Innovation. 28 th April, 2015 David Boyer, Smart Networks Policy Lead UK Power Networks Technology Watch (Smart) Networks Context & Innovation 28 th April, 2015 David Boyer, Smart Networks Policy Lead UK Power Networks Total % of industry End customers (millions) Service

More information

UoD IT Job Description

UoD IT Job Description UoD IT Job Description Role: Service Delivery Manager (People HERA Grade: 8 Management Systems) Responsible to: Assistant Director (Business Services) Accountable for: Day to day leadership of team members

More information

Operating Margins Report July 2016

Operating Margins Report July 2016 Operating Margins Report July 2016 Introduction In accordance with Special Condition 8C, this document provides an overview of our procurement activities used to secure our Gas Operating Margins (Gas OM)

More information

the electricity consumer Code of Practice

the electricity consumer Code of Practice 3 the electricity consumer Code of Practice contents WHAT IS THE ELECTRICITY CODE? 2 STATEMENT OF PURPOSE 2 STATEMENT OF PRINCIPLES 3 LOCATION OF DEFINITIONS 3 WHO IS COVERED BY THE CODE? 3 WHAT IS A CONSUMER

More information

System Management Action. Flagging Methodology Statement. Version Date: [05 th November 2009]

System Management Action. Flagging Methodology Statement. Version Date: [05 th November 2009] System Management Action Flagging Methodology Statement Version Date: [05 th November 2009] System Management Action Flagging Methodology Statement 1 Version Control Date Version No. Notes 20.3.01 1.0

More information

JOB DESCRIPTION & PERSON SPECIFICATION

JOB DESCRIPTION & PERSON SPECIFICATION JOB DESCRIPTION & PERSON SPECIFICATION HIAL AMSL DAL 1. JOB DETAILS JOB HOLDER JOB TITLE REPORTS TO Vacant ICT Advisor Head of ICT and Digital Transformation 2. JOB PURPOSE The Air Traffic Management 2030

More information

PROJECT BOARD TERMS OF REFERENCE. Roles and Responsibilities

PROJECT BOARD TERMS OF REFERENCE. Roles and Responsibilities PROJECT BOARD TERMS OF REFERENCE Roles and Responsibilities 1 DOCUMENT CONTROL Change Control Table Version Amendment Description Release Date Updated by 0.1 First draft Alignment with new governance framework

More information

CUSC Workgroup Consultation Response Proforma

CUSC Workgroup Consultation Response Proforma CUSC Workgroup Consultation Response Proforma CMP264 Embedded Generation Triad Avoidance Standstill and CMP265 Gross charging of TNUoS for HH demand where Embedded Generation is in the Capacity Market

More information

Support continued transparency for policy and design choices

Support continued transparency for policy and design choices Transpower House 96 The Terrace PO Box 1021, Wellington New Zealand www.transpower.co.nz Catherine.jones@transpower.co.nz 04 590 8624 / 027 5646976 10 October 2017 John Rampton General Manager Market Design

More information

CER National Smart Metering Programme Policy Implementation Roadmap

CER National Smart Metering Programme Policy Implementation Roadmap CER National Smart Metering Programme Policy Implementation Roadmap DOCUMENT TYPE: REFERENCE: Information Paper CER/15/055 DATE: 31 March 2015 The Commission for Energy Regulation, The Exchange, Belgard

More information

The Electricity System Operator Who we are and what we do September 2018 CONFICONFIDNEITA

The Electricity System Operator Who we are and what we do September 2018 CONFICONFIDNEITA The Electricity System Operator Who we are and what we do September 2018 CONFICONFIDNEITA Who we are As the Electricity System Operator (ESO), we operate the National Electricity Transmission System in

More information

Shenzhen Internet of Things Case Study

Shenzhen Internet of Things Case Study Shenzhen Internet of Things Case Study Introduction Supply of water and gas to consumers in Shenzhen has historically been a challenge. However, significant investment in improving the delivery of both

More information

Document History. Originator Section Update Details. Version Date Revision Class

Document History. Originator Section Update Details. Version Date Revision Class Document History Version Date Revision Class Originator Section Update Details 1.0 09/03/2014 N/A Adrian Searle N/A Initial version (ED1 March 2014 resubmission) Contents 1 Executive summary 3 2 Business

More information

nbn Platform Interfacing Service Module

nbn Platform Interfacing Service Module nbn Platform Interfacing Service Module Wholesale Broadband Agreement This document forms part of NBN Co s Wholesale Broadband Agreement, which is a Standard Form of Access Agreement for the purposes of

More information

Victorian AMI Program Stephen Thomson, AMI Program Director Principal Consultant Marchment Hill Consulting

Victorian AMI Program Stephen Thomson, AMI Program Director Principal Consultant Marchment Hill Consulting Victorian AMI Program Stephen Thomson, AMI Program Director Principal Consultant Marchment Hill Consulting 21 January 2009 Victorian AMI Program Phases 2006 Jul 2007 May 2010 2013 Establishment Phase Involved

More information

Market-wide Half-Hourly Settlement

Market-wide Half-Hourly Settlement PUBLIC Market-wide Half-Hourly Settlement Design Working Group: Draft Skeleton TOMs for ELEXON Version 1.0 6 March 2018 CONTENTS INTRODUCTION... 3 1. Ofgem SCR on Market-wide Half-Hourly Settlement...

More information

Identification of Supply Meter Point pressure tier

Identification of Supply Meter Point pressure tier Stage 01: Modification At what stage is this document in the process? 0526: Identification of Supply Meter Point pressure tier Aims to improve the communication of the Supply Meter Point Pressure Tier

More information

Low Carbon Networks Fund Review and Synthesis

Low Carbon Networks Fund Review and Synthesis Low Carbon Networks Fund Review and Synthesis Damien Frame Keith Bell and Stephen McArthur University of Strathclyde damien.frame@strath.ac.uk The Low Carbon Network Fund 500m 5 Years Ofgem DNOs Electricity

More information

QUALIFICATION HANDBOOK

QUALIFICATION HANDBOOK QUALIFICATION HANDBOOK Level 4 NVQ Diploma in Spectator Safety Management (6852-04) October 2011 Version 1.0 Qualification at a glance Subject area City & Guilds number 6852 Spectator Safety Age group

More information

Response to Consultation on Governance Arrangements for the UPI: Key Criteria and Functions

Response to Consultation on Governance Arrangements for the UPI: Key Criteria and Functions FAO: Financial Stability Board (FSB) and Working Group on UTI and UPI Governance (GUUG) Ms Emma Kalliomaki Managing Director Assoc. of National Numbering Agencies & Derivatives Service Bureau Phone: +46

More information

For clarification, or to submit additional questions and feedback, please contact

For clarification, or to submit additional questions and feedback, please contact Auction Trial for Frequency Response FAQs Last Updated: 12/11/2018 Updates since last version included in green text. For clarification, or to submit additional questions and feedback, please contact commercial.operation@nationalgrid.com.

More information

APGTF Workshop: Managing the Grid of the Future

APGTF Workshop: Managing the Grid of the Future APGTF Workshop: Managing the Grid of the Future Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line.

More information

Upgrading Our Energy System. Smart Systems and Flexibility Plan

Upgrading Our Energy System. Smart Systems and Flexibility Plan Upgrading Our Energy System Smart Systems and Flexibility Plan July 2017 2 Upgrading Our Energy System Upgrading Our Energy System 3 Contents Smart Systems and Flexibility Plan Executive Summary 4 Introduction

More information

This response considers the issues at an overall level, concentrating on the nonnetwork businesses within ScottishPower.

This response considers the issues at an overall level, concentrating on the nonnetwork businesses within ScottishPower. SUBMISSION FROM SCOTTISHPOWER You have already received evidence from our networks business on the matters within their areas of responsibility as a transmission owner and distribution network operator

More information

25 September 2018

25 September 2018 opennetworks@energynetworks.org 25 September 2018 Dear Colleagues, S&C Electric Company response to the ENA Future Worlds Consultation S&C Electric Company welcomes the opportunity to provide a response

More information

Consultation on the Transition and Migration Approach Document for DCC s Service for SMETS1 Devices and accompanying changes to the SMETS1 Supporting

Consultation on the Transition and Migration Approach Document for DCC s Service for SMETS1 Devices and accompanying changes to the SMETS1 Supporting Consultation on the Transition and Migration Approach Document for DCC s Service for SMETS1 Devices and accompanying changes to the SMETS1 Supporting Requirements Date: 3 May 2018 Classification: DCC Public

More information

Consultation on extending the existing smart meter framework for data access and privacy to Smart-Type Meters and Advanced Meters

Consultation on extending the existing smart meter framework for data access and privacy to Smart-Type Meters and Advanced Meters Consultation on extending the existing smart meter framework for data access and privacy to Smart-Type Meters and Advanced Meters Consultation Contact: Colin Down, Senior Policy Manager Publication date:

More information

European Distribution System Operators for Smart Grids. Retail energy market: Supplementary response to the European Commission s public consultation

European Distribution System Operators for Smart Grids. Retail energy market: Supplementary response to the European Commission s public consultation European Distribution System Operators for Smart Grids Retail energy market: Supplementary response to the European Commission s public consultation April 2014 EDSO supplementary response to the European

More information

Market-wide Half-Hourly Settlement

Market-wide Half-Hourly Settlement PUBLIC Market-wide Half-Hourly Settlement Design Working Group: ELEXON Version 1.0 4 April 2018 CONTENTS EXECUTIVE SUMMARY... 3 INTRODUCTION... 4 1. Ofgem SCR on Market-wide Half-Hourly Settlement... 4

More information

Smart-metering rollout scenarios & CBA BGN Response to CER/10/197 Consultation

Smart-metering rollout scenarios & CBA BGN Response to CER/10/197 Consultation Smart-metering rollout scenarios & CBA BGN Response to CER/10/197 Consultation Table of Contents 1. Introduction... 3 2. Objectives... 4 3. Ownership, display and provision of data... 4 3.1 Gas data granularity...

More information

Conventional delivery of services is being upended across industry sectors by technology and customer preferences.

Conventional delivery of services is being upended across industry sectors by technology and customer preferences. 7 December 2015 Ms. Catherine Cussen Queensland Productivity Commission PO Box 12112 George St QLD 4003 Electricity Pricing in Queensland Issues Paper Dear Ms. Cussen The Energy Networks Association (ENA)

More information

Demand Side Engagement Strategy. Version 2.0 Effective Date: 08/02/18

Demand Side Engagement Strategy. Version 2.0 Effective Date: 08/02/18 Demand Side Engagement Strategy Version 2.0 Effective Date: 08/02/18 Document management Version control Date Version Description Author 16/07/2013 0.1 Initial Draft. Y. Jayathilaka 23/07/2013 0.2 Revised

More information

DRAFT ROLE DESCRIPTION Riverina Murray Destination Network, Administrative Assistant

DRAFT ROLE DESCRIPTION Riverina Murray Destination Network, Administrative Assistant DRAFT ROLE DESCRIPTION Riverina Murray Destination Network, Administrative Assistant Location: tbc 1. OVERVIEW The Destination Network (DN) Riverina Murray is one of six DNs recently established across

More information

Insight and agility. An updated guide to optimising collections in utilities

Insight and agility. An updated guide to optimising collections in utilities Insight and agility An updated guide to optimising collections in utilities June 2011 Contents 1. Introduction 3 2. A 10 step guide to improving your collections strategy 5 2 - Insight and agility : A

More information

Load Modifying Resources. Capacity Instruments affecting Resource Availability and Need

Load Modifying Resources. Capacity Instruments affecting Resource Availability and Need Capacity Instruments affecting Resource Availability and Need May 25, 2018 Purpose Statement Review the participation and historic performance of Load Modifying Resources (LMRs) in MISO s Capacity and

More information

Summary: Intervention and Options

Summary: Intervention and Options Title: Energy Bill: Amendment to the Energy Act 2008 powers to implement and direct the rollout of smart meters Lead department or agency: DECC Other departments or agencies: Impact Assessment (IA) IA

More information

RE: ENA Submission on the Electricity Pricing Review

RE: ENA Submission on the Electricity Pricing Review 23 October 2018 Miriam Dean QC Chair Electricity Review Panel C/- Ministry of Business, Innovations and Employment, Wellington By email to:energymarkets@mbie.govt.nz RE: ENA Submission on the Electricity

More information

System Management Action Flagging Methodology Statement

System Management Action Flagging Methodology Statement System Management Action Flagging Methodology Statement Effective Date: 01 April 20172018 Version Number: 910.0 Published in accordance with Standard Condition C16 of National Grid Electricity Transmission

More information

A Guide to the Non-Domestic Gas and Electricity Retail Markets

A Guide to the Non-Domestic Gas and Electricity Retail Markets 10 January 2017 A Guide to the Non-Domestic Gas and Electricity Retail Markets Outline This guide sets out the key features of the I&C non-domestic gas and electricity retail markets in Great Britain.

More information

QUALIFICATION HANDBOOK

QUALIFICATION HANDBOOK Level 2 Certificate in Facilities Services (4429-21) QUALIFICATION HANDBOOK October 2012 Version 2.1 Qualification at a glance Subject area City & Guilds number 4429 Facilities Services Age group approved

More information

Asset Management Policy

Asset Management Policy Asset Management Policy January 2018 Introduction Our Asset Management Policy was last published in 2014. It is being updated to reflect our commitment to regularly review and improve all of our Asset

More information

DCC Draft Development Priorities to

DCC Draft Development Priorities to DCC Draft Development Priorities 2018-19 to 2022-23 Date: December 2017 Classification: DCC Public Table of Contents 1 Executive Summary... 3 2 Introduction... 4 3 Drivers for our development... 7 4 Horizon

More information

Uptime Maintenance and Support Services - Appendix. Dimension Data Australia Pty Limited. Uptime Support Services Agreement

Uptime Maintenance and Support Services - Appendix. Dimension Data Australia Pty Limited. Uptime Support Services Agreement Uptime Support Services Agreement Uptime Maintenance and Support Services - Appendix Dimension Data Australia Pty Limited 27 May 2013 Version 1-01 Appendix A. 1. Definitions and Interpretations 1.1 For

More information

SWITCH OR TRANSFORM THE FUTURE OF THE RETAIL ENERGY MARKET

SWITCH OR TRANSFORM THE FUTURE OF THE RETAIL ENERGY MARKET BRIEFING PAPER JUNE 2015 SWITCH OR TRANSFORM THE FUTURE OF THE RETAIL ENERGY MARKET SIMON SKILLINGS The Competition and Markets Authority (CMA) is currently investigating competition in the GB energy market

More information

System Management Action Flagging Methodology Statement

System Management Action Flagging Methodology Statement System Management Action Flagging Methodology Statement Effective Date: 01 April 2017 Version Number: 9.0 Published in accordance with Standard Condition C16 of National Grid Electricity Transmission Licence

More information

Key Performance Indicators To promote and deliver the Kaplan Way Principles to internal and external stakeholders

Key Performance Indicators To promote and deliver the Kaplan Way Principles to internal and external stakeholders Senior Administrator Location: KSE Liverpool Essential Qualifications if applicable: N/A Excel Specialist Travel Required: Flexible Approach Required Line Manager: KSE Operations Manager Direct Line Reports:

More information

Meter Technical Details for Smart Meters (CP1388) Education Session. Adam Lattimore 20 June 2013

Meter Technical Details for Smart Meters (CP1388) Education Session. Adam Lattimore 20 June 2013 Meter Technical Details for Smart Meters (CP1388) Education Session Adam Lattimore 20 June 2013 Agenda Smart Metering Journey CP1388 Solution CP1388 Progression & Next Steps Open Discussion Are there any

More information

Position Description: Site Manager Reports to: Project Manager

Position Description: Site Manager Reports to: Project Manager Position Description: Site Manager Reports to: Project Manager Overall Responsibilities To live the organisational values of Creating Opportunities, Building Communities and Empowering Lives. Responsible

More information

Initial Enrolment Project Feasibility Draft Report Consultation Document

Initial Enrolment Project Feasibility Draft Report Consultation Document Initial Enrolment Project Feasibility Draft Report Consultation Document Date issued: 11/11/2016 Consultation closes: 20/01//2017 Classification: DCC Public Contents 1 Executive Summary... 4 2 Introduction...

More information

Planning, Reporting and Regulatory Framework

Planning, Reporting and Regulatory Framework Planning, Reporting and Regulatory Framework Strategic Business Plan 9 February 2018 Planning, Reporting and Regulatory Framework This document describes the key elements and methods of working in our

More information

Smart DCC Ltd. Licence Application Business Plan. Version: Final Redacted. Date: Licence Application Business Plan Final Redacted.

Smart DCC Ltd. Licence Application Business Plan. Version: Final Redacted. Date: Licence Application Business Plan Final Redacted. Smart DCC Ltd Licence Application Business Plan Version: Date: Page 1 of 38 Contents 1 Introduction... 4 1.1 Smart Meter Communication Licence... 4 1.2 The Purpose of the Licence Application Business Plan...

More information

The Statement of the Ex-Ante or Ex-Post Treatment of Modelling Inputs Methodology

The Statement of the Ex-Ante or Ex-Post Treatment of Modelling Inputs Methodology Issue Revision 1 0 The Statement of the Ex-Ante or Ex-Post Treatment of Modelling Inputs Methodology Effective from 1 April 2013 About this Document This document contains one of three methodologies that

More information

277/06 - PRELIMINARY TERRE (P344) IMPLEMENTATION IN ADVANCE OF OFGEM DECISION

277/06 - PRELIMINARY TERRE (P344) IMPLEMENTATION IN ADVANCE OF OFGEM DECISION - PRELIMINARY TERRE (P344) IMPLEMENTATION IN MEETING NAME BSC Panel Meeting Date of meeting 12 April 2018 Paper number Owner/author Purpose of paper Classification Summary Rob Greenoak Decision Public

More information

Tackling Tariff Design. Making distribution network costs work for consumers

Tackling Tariff Design. Making distribution network costs work for consumers Tackling Tariff Design Making distribution network costs work for consumers Contents Introduction 02 What s driving change? 05 Alternative tariff designs 07 Impacts on consumers bills 11 Reflections and

More information

Opportunities & challenges in current markets & gearing up for the future

Opportunities & challenges in current markets & gearing up for the future Session 2: Opportunities & challenges in current markets & gearing up for the future Rosie McGlynn Sara Vaughan Nigel Turvey Peter Bance Energy UK E.ON Western Power Distribution Origami Energy Opportunities

More information

The Clean Growth Strategy included the following key proposals and policies (for full detail under each heading see Appendix):

The Clean Growth Strategy included the following key proposals and policies (for full detail under each heading see Appendix): Collaborative Working on Energy 1. Purpose The purpose of this note is to brief the LEP Finance and Resources meeting on the Joint LEP Energy Strategy which has been developed as a collaborative piece

More information

January 2016 NORTHERN POWERGRID. To find out more, visit

January 2016 NORTHERN POWERGRID. To find out more, visit January 2016 Delivering enhanced understanding of electricity losses To find out more, visit www.northernpowergrid.com/your-powergrid 01 Content 1 Foreword 3 2 Introduction 4 3 Work proposed 5 3.1 understanding

More information

Transport Select Committee Rail Infrastructure Investment Inquiry

Transport Select Committee Rail Infrastructure Investment Inquiry Consultation Response Transport Select Committee Rail Infrastructure Investment Inquiry Tom Ellerton and Jonathan Bray Urban Transport Group Wellington House 40-50 Wellington Street Leeds LS1 2DE 0113

More information

Adapting Distribution Network Planning Practices and Design Standards to Accommodate Distributed Energy Resources

Adapting Distribution Network Planning Practices and Design Standards to Accommodate Distributed Energy Resources 21, rue d Artois, F-75008 PARIS CIGRE US National Committee http : //www.cigre.org 2016 Grid of the Future Symposium Adapting Distribution Network Planning Practices and Design Standards to Accommodate

More information

Electricity Supply Board. National Planning Framework Issues & Choices

Electricity Supply Board. National Planning Framework Issues & Choices Electricity Supply Board National Planning Framework Issues & Choices Submission on behalf of Electricity Supply Board 07/03/2017 Contents 1. INTRODUCTION... 3 2. OVERVIEW OF ESB ACTIVITIES... 3 2.1 Electricity

More information

NIA Project Registration and PEA Document

NIA Project Registration and PEA Document Date of Submission June 2015 NIA Project Registration and PEA Document Notes on Completion: Please refer to the appropriate NIA Governance Document to assist in the completion of this form. The full completed

More information

COTA Tasmania. Submission to inform the development of TasNetworks Direction and Priorities Consultation Paper

COTA Tasmania. Submission to inform the development of TasNetworks Direction and Priorities Consultation Paper 7 September 2017 COTA Tasmania Submission to inform the development of TasNetworks Direction and Priorities Consultation Paper Thank you for the opportunity to provide input to TasNetworks Transmission

More information