Energy Efficiency in RPM. Adam Keech Director, Market Operations PJM January 13, 2015
|
|
- Verity McCarthy
- 5 years ago
- Views:
Transcription
1 Energy Efficiency in RPM Adam Keech Director, Market Operations PJM January 13, 2015
2 PJM Capacity Market PJM Capacity Market Reliability Pricing Model (RPM) PJM secures capacity on behalf of LSEs to satisfy load obligations not satisfied through self-supply. Fixed Resource Requirement Alternative (FRR) (opt-out of RPM) LSE secures capacity to satisfy their load obligation. PJM Capacity Market is designed to ensure adequate availability of resources that can be called upon to ensure the reliability of the electric grid. 2
3 3 Years RPM Structure May Base Residual Auction Sept July 20 months EFORd Fixed 10 months Feb. 3 months June Delivery Year May First Incremental Auction Second Incremental Auction Third Incremental Auction Ongoing Bilateral Market 3
4 What is a Supply Resource in RPM? In RPM, Resources are = Generation Resources Demand Resources (DR) Energy Efficiency Resources (EE) Qualifying Transmission Upgrades (QTU) 4
5 EE MWs Cleared in BRAs Energy Efficiency MW Cleared (in UCAP) in RPM Base Residual Auctions 21% 12% 21% 20% Average of 19% growth in megawatts cleared per year 19% 5
6 Source of EE MWs in PJM Capacity Market Source of EE MW s in PJM Capacity Market Commercial and Industrial lighting upgrades have been the largest source of energy efficiency megawatts in RPM Residential lighting is not far behind, accounting for 40% of MW s The Other category is comprised of HVAC (3%) and Appliance Turn-in (3%) while the remaining 9% is various other sources Although lighting has accounted for the vast majority of energy efficiency megawatts, there is an increasing interest in efficiency of mechanical devices, such as motors or variable frequency drives (VFD s) 6
7 Eligibility Criteria for EE Installation EE installation must be scheduled for completion prior to DY EE installation is not reflected in peak load forecast posted for the BRA for the DY initially offered EE installation exceeds relevant standards at time of installation as known at time of commitment EE installation achieves load reduction during defined EE Performance Hours EE installation is not dispatchable 7
8 EE Resource Timeline EE Resource shall be EE project(s) or portion of EE project(s) in a zone that represents the installations of EE during a defined period of time from June 1 to May 31. EE Resources are eligible to be offered into RPM Auctions as Annual product EE Resource may be eligible to receive Capacity Market (RPM) revenue for up to four consecutive Delivery Years. Installation Period Fully Installed for Summer Eligible DYs June 2014-May /2016, 2016/2017, 2017/2018, 2018/2019 June 2015-May /2017, 2017/2018, 2018/2019, 2019/2020 June 2016-May /2018, 2018/2019, 2019/2020, 2020/2021 June 2017-May /2019, 2019/2020, 2020/2021, 2021/2022 June prior to DY May prior to DY DY DY, DY+1, DY+2, DY+3 8
9 Nominated EE Value Nominated EE Value represents the ICAP Value of an EE Resource. Nominated EE Value is expected average demand reduction (MW) during the defined EE Performance Hours in the Delivery Year. EE Performance Hours are between hour ending 15:00 EPT and hour ending 18:00 EPT during all days from June 1 through August 31, inclusive, of such Delivery year, that is not a weekend or federal holiday. EE value of weather sensitive equipment is based on standard zonal WTHI Measurement & Verification (M&V) Plan describes the method and procedures for determining the Nominated EE Value of an EE Resource and confirming the Nominated EE Value is achieved. The minimum Nominated EE Value accepted is 0.1 MW. 9
10 EE Resource Requirements Submit M&V Plan prior to RPM Auction Single M&V Plan may be submitted to cover multiple EE Resources Single M&V Plan must clearly document the Nominated EE Value of each EE Resource covered in the Plan Establish credit with PJM Credit Department prior to RPM Auction Submit Post-Installation M&V Reports Permit Post- Installation M&V Audit by PJM or Independent Third Party 10
11 Performance Requirement for EE Resources Commitment Compliance demonstrate committed Nominated EE Value in Delivery Year Post-Installation M&V Report May be subject to Post-Installation M&V Audit by PJM or independent Third Party Cost of audit charged to EE Provider Subject to deficiency charges for failure to perform to commitment level. 11
12 Road Ahead Focus to-date of EPSA case has been on DR compensation in PJM s markets. The underlying rationale could impact EE as well. Potential outcomes: 1. Continue with the current model. 2. EE and DR models are restructured to be compliant with new world. PJM Stop-Gap Filing 12
13 PJM Stop Gap Filing Court rejects certiorari DR & EE LSE model effective for future auctions 18/19 BRA & IAs Supply side DR & EE suspended from future auctions Supply side DR & EE already committed remains effective for DY 2014/15, 2015/16, 2016/17 Legal & Policy decisions Final DR State Court accepts certiorari or is undecided by mid-april Operate under existing tariff Supply side DR & EE participates in BRA Stop Gap rules are meant to be transitional to ensure market stability for near-term auctions 13
14 Demand Response & Energy Efficiency: PJM s Stop Gap Proposal vs. Today Capacity market Capacity obligations Who manages? End-use customers Today Supply resource (Similar to generation) Nominate and reduce load per rules Curtailment service provider/load serving entity (any PJM member) PJM Proposal Demand bid (BRA or bilateral, no IAs) Same Load-serving entity (for specific customer) All may participate subject to Same regulatory rules Both PJM and the Relevant Electric Retail Regulatory Authority each may play a role in facilitating a transition to the LSE DR & EE model 14
15 Questions? 15
PJM Manual 18B: Energy Efficiency Measurement & Verification Revision: 03 Effective Date: November 17, Prepared by PJM Forward Market Operations
PJM Manual 18B: Energy Efficiency Measurement & Verification Revision: 03 Effective Date: November 17, 2016 Prepared by PJM Forward Market Operations PJM 2016 Table of Contents Table of Contents Approval...5
More informationEnergy Efficiency Resource Requirements
Energy Efficiency Resource Requirements Theresa Esterly Sr. Lead Engineer, Capacity Market Operations Market Implementation Committee July 12, 2017 www.pjm.com Energy Efficiency (EE) Resource Definition
More informationRPM 301 Performance in Reliability Pricing Model
RPM 301 Performance in Reliability Pricing Model PJM State & Member Training Dept. PJM 2017 Disclaimer: PJM has made all efforts possible to accurately document all information in this presentation. The
More informationPJM briefing. Greater Philadelphia Chapter of the Association of Energy Engineers. PJM Interconnection
PJM briefing Greater Philadelphia Chapter of the Association of Energy Engineers PJM Interconnection Mike Bryson, Executive Director, System Operations Steve Boyle, Director, State Government Affairs January
More informationCapacity Performance Training. March 16, 2015
Capacity Performance Training March 16, 2015 Training Objectives Provide Capacity Market Sellers with information necessary to participate in the Reliability Pricing Model (RPM) under a Capacity Performance
More informationLoad Management Performance Report 2017/2018. (mid Delivery Year update)
Load Management Performance Report 2017/2018 (mid Delivery Year update) January 2018 PJM has made all efforts possible to accurately document all information in this report. However, PJM cannot warrant
More informationPrice Responsive Demand education. DRS May 11 th, 2017
Price Responsive Demand education DRS May 11 th, 2017 PRD Rules became effective 2012, no participation to date Peak Load, MW 1,020 1,000 980 960 940 920 900 PRD vs. Real Time LMP Commit to consume < 900
More informationCapacity Performance Training. June 24, 2015
Capacity Performance Training June 24, 2015 Training Objectives Provide Capacity Market Sellers with information necessary to participate in the Reliability Pricing Model (RPM) under a Capacity Performance
More informationMarket Settlements - Advanced
Market Settlements - Advanced RPM Module PJM State & Member Training Dept. PJM 2017 Capacity vs. Energy Capacity A commitment of a resource to provide energy during PJM emergency under the capped energy
More informationLoad Management Performance Report 2015/2016
Load Management Performance Report 2015/2016 August 2016 PJM has made all efforts possible to accurately document all information in this report. However, PJM cannot warrant or guarantee that the information
More informationWhat is a Capacity Market?
What is a Capacity Market? Mechanism that ensures sufficient generation to meet reliability and peak load needs. Additional potential benefit of capacity markets is the incentive to build new generation.
More informationReliability Pricing Model (RPM) DRAFT Business Rules
Definition and Purpose of Reliability Pricing Model (RPM) 1. The purpose of the RPM is to develop a long term pricing signal for capacity resources and LSE obligations that is consistent with the PJM Regional
More informationPJM. erpm Users Guide. May 20, Version PJM Interconnection
PJM erpm Users Guide May 20, 2010 Version 1.4 2010 PJM Interconnection erpm Users Guide Page i Disclaimer - The PJM erpm User Guide is intended to provide Market Participants and other interested parties
More informationCurrent Language Proposed Revisions Rationale
1. RAA, Schedule 8.1, Paragraph H (Annexation of service territory by Public Power Entity) 2. In the event a Public Power Entity that is an FRR Entity annexes service territory to include load from a Party
More informationCapacity Performance FAQ Response
PJM Interconnection September 15, 2014 This page is intentionally left blank. PJM 2014 www.pjm.com 2 P age Contents FAQ Response Introduction... 4 Capacity Products... 4 Methodology for Establishing Maximum
More informationPJM Organization and Markets. Saudi Delegation Columbus Ohio May 22, 2012
PJM Organization and Markets Saudi Delegation Columbus Ohio May 22, 2012 Agenda Introduction & Governance Energy Markets LMP FTRs/ARRs Two Settlement Virtual Bids Ancillary Capacity - Reliability Pricing
More informationATTACHMENT DD. Reliability Pricing Model
OF NEW SERVICE REQUESTS; R - OATT ATTACHMENT DD ATTACHMENT DD Reliability Pricing Model References to section numbers in this Attachment DD refer to sections of this Attachment DD, unless otherwise specified.
More informationPJM. erpm Users Guide. December 4, Version PJM Interconnection
PJM erpm Users Guide December 4, 2008 Version 0.7 2008 PJM Interconnection erpm Users Guide Page i Disclaimer - The PJM erpm User Guide is intended to provide Market Participants and other interested parties
More informationPJM Manual 18: PJM Capacity Market. Revision: 14 Effective Date: February 23, Prepared by PJM Capacity Market Operations PJM 2012
PJM Manual 18: PJM Capacity Market Revision: 14 Effective Date: February 23, 2012 Prepared by PJM Capacity Market Operations PJM 2012 PJM 2012 i Table of Contents PJM Manual 18: PJM Capacity Market Table
More informationRPM 101 Overview of Reliability Pricing Model
RPM 101 Overview of Reliability Pricing Model PJM 2017 Agenda Introduction Resource Adequacy Demand in RPM Supply in RPM Auction Structure Auction Clearing Resource Clearing Prices CTRs & ICTRs/CTR & ICTR
More informationPJM Manual 18: PJM Capacity Market Revision: 38 Effective Date: July 27, Prepared by Capacity Market Operations
PJM Manual 18: PJM Capacity Market Revision: 38 Effective Date: July 27, 2017 Prepared by Capacity Market Operations PJM 2017 Table of Contents Table of Contents Table of Exhibits...9 Approval...10 Current
More informationCapacity Resource versus Energy Resource
Capacity Resource versus Energy Resource Seasonal Capacity Resource Senior Task Force April 18, 2016 Capacity Resource or Energy Resource? When a new generator connects to PJM s system through the PJM
More informationRESOURCE ADEQUACY PLANNING
RESOURCE ADEQUACY PLANNING CLEAN ENERGY REGULATORY FORUM IV November 8, 2012 Susan Covino, Senior Consultant Emerging Markets 1 Energy Efficiency (EE) Cleared in RPM Auctions RPM Auction Total EE Resources
More informationSummer-Only Demand Response Senior Task Force
Summer-Only Demand Response Senior Task Force Rebecca Carroll Facilitator, SODRSTF Markets & Reliability Committee October 25, 2018 Document Changes Since First Read Manual 19 Clarifying language added
More informationPJM Manual 18: PJM Capacity Market. Revision: 287 Effective Date: January 22, Prepared by PJM Capacity Market Operations
Style Definition: PJM_Normal PJM Manual 18: PJM Capacity Market Revision: 287 Effective Date: January 22, 2015 Prepared by PJM Capacity Market Operations PJM 2015 PJM 2015 i PJM Manual 18: PJM Capacity
More informationReliability Pricing Model (RPM) Overview. April 11, 2005
Reliability Pricing Model (RPM) Overview April 11, 2005 Drivers for Capacity Market Reform Generation Net Revenue Shortfall Inconsistency between capacity pricing and reliability requirements Result has
More informationPlanning Committee Recommendations for Summer Capability Verification Tests
Planning Committee Recommendations for Summer Capability Verification Tests Markets and Reliability Committee February 27, 2014 PC Recommendations Manual 21: Rules and Procedures for Determination of Generating
More informationMust-Offer Exception Process Issue
Must-Offer Exception Process Issue Patrick Bruno Sr. Engineer, Capacity Market Operations Market Implementation Committee August 8, 2018 Background Issue brought forward by Exelon to investigate: Possible
More information2013/2014 RPM Base Residual Auction Results
Executive Summary The 2013/2014 Reliability Pricing Model (RPM) Base Residual Auction (BRA) cleared 152,743.3 MW of unforced capacity in the RTO at a Resource Clearing Price of $27.73/MW-day. This MW and
More informationPC Recommendations for Summer Capability Verification Tests
PC Recommendations for Summer Capability Verification Tests MRC January 30, 2014 www.pjm.com www.pjm.com PC Recommendations Manual 21: Rules and Procedures for Determination of Generating Capability M21
More information2017/2018 RPM Base Residual Auction Planning Period Parameters
Introduction The RPM Base Residual Auction (BRA) for the 2017/2018 Delivery Year is scheduled to be conducted in May of 2014. This document describes the 2017/2018 BRA planning period parameters and also
More informationPJM Manual 18: PJM Capacity Market
PJM Manual 18: PJM Capacity Market Revision: 23 Effective Date: June 1, 2014 Prepared by PJM Capacity Market Operations PJM 2014 PJM 2014 i PJM Manual 18: PJM Capacity Market Manual 18: PJM Capacity Market
More informationRelevant Electric Retail Regulatory Authority ( RERRA ) review process of Energy Efficiency resources and FERC Order on Petition of Declaratory Order
Relevant Electric Retail Regulatory Authority ( RERRA ) review process of Energy Efficiency resources and FERC Order on Petition of Declaratory Order Pete Langbein Manager, Demand Response Operations Members
More informationLOAD SERVING ENTITIES PJM REGION
Intra-PJM Tariffs --> RELIABILITY ASSURANCE AGREEMENT PJM Interconnection, L.L.C. Rate Schedule FERC No. 44 RELIABILITY ASSURANCE AGREEMENT Among LOAD SERVING ENTITIES in the PJM REGION Effective Date:
More informationUNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION. PJM Interconnection, L.L.C. : Docket No. ER
UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C. : Docket No. ER19-511-000 MOTION TO ACCEPT LATE-FILED COMMENTS AND COMMENTS OF THE PENNSYLVANIA PUBLIC UTILITY
More informationCapacity Market. Overview RPM Capacity Market. Market Design
Section 4 Capacity Capacity Market Each organization serving PJM load must meet its capacity obligations through the PJM Capacity Market, where load serving entities (LSEs) must pay the locational capacity
More information2008/ 2009 RPM Base Residual Auction Results
Introduction The purpose of this document is to provide additional information for PJM stakeholders regarding the 2008/2009 Reliability Pricing Model (RPM) Base Residual Auction results. The discussion
More informationPJM Capacity Market. October 5, 2011 OPSI Seventh Annual Meeting Andrew L. Ott, Senior Vice President, Market Services
PJM Capacity Market October 5, 2011 OPSI Seventh Annual Meeting Andrew L. Ott, Senior Vice President, Market Services Capacity vs. Energy Capacity A commitment of a resource to provide energy during PJM
More informationComments of the Energy Efficiency Coalition. Regarding PJM s Capacity Performance Proposal
Comments of the Energy Efficiency Coalition Regarding PJM s Capacity Performance Proposal The Energy Efficiency Coalition ( EEC ) is an ad hoc group of PJM members, public interest groups, and energy services
More informationRPM 201 Resource Participation in PJM Capacity Market
RPM 201 Resource Participation in PJM Capacity Market PJM 2017 Agenda Auction structure and key activity timelines Must offer, Offer Caps, MOPR Demand Response Energy Efficiency Commercial Aggregation
More informationUCAP Calculation Comparison
UCAP Calculation Comparison Dispatchable resources within PJM, NYISO, & MISO September 2017 Draft for Discussion Overview map British Columbia Alberta Manitoba Newfoundland Labrador Ontario Quebec PEI
More informationDemand Response. Overview. Recommendations
Section 6 Demand Response Demand Response Markets require both a supply side and a demand side to function effectively. The demand side of wholesale electricity markets is underdeveloped. Wholesale power
More informationEnergy Efficiency A PJM Demand Management Program
Energy Efficiency A PJM Demand Management Program PJM s Energy Efficiency program pays businesses for permanent load reduction resulting from energy efficiency projects they have completed or will be complete
More informationDemand Response Parity in Wholesale Markets Hinges on FERC 745 Outcome
RESEARCH North America Power and Utilities Energy Efficiency Demand Response Parity in Wholesale Markets Hinges on FERC 745 Outcome Supreme Court Review of Order 745 Key to Demand Response s Future in
More informationFinancial Transmission Rights
PJM Manual 06 Financial Transmission Rights Revision: 12 Effective Date: July 1, 2009 Prepared by Market Simulation Department PJM 2009 PJM Revision 05, Effective Date: 12/30/03 iii Table of Contents PJM
More informationCUSTOMER GUIDE TO PJM BILLING
CUSTOMER GUIDE TO PJM BILLING Billing Line Items include PJM Open Access Tariff (OATT) references, PJM Operating Agreement (OpAgr) references, and PJM Manual references. Reports are available for viewing,
More information2013/2014 RPM Base Residual Auction Planning Period Parameters
Introduction The RPM Base Residual Auction (BRA) for the 2013/2014 Delivery Year is scheduled to be conducted in May of 2010. The planning period parameters to be used as input into the 2013/2014 BRA are
More informationDemand Response. Mathangi Srinivasan. New York Market Orientation Course (NYMOC) Senior Market Trainer, NYISO. March 20-23, 2018 Rensselaer, NY 12144
Demand Response Mathangi Srinivasan Senior Market Trainer, NYISO New York Market Orientation Course (NYMOC) March 20-23, 2018 Rensselaer, NY 12144 1 Demand Response Module Objectives Upon completion of
More informationPJM Emergency DR (Load Management) PJM State & Member Training Dept.
PJM Emergency DR (Load Management) PJM State & Member Training Dept. PJM 2014 Disclaimer: PJM has made all efforts possible to accurately document all information in this presentation. The information
More informationSchedule 9 and 10 PJM /23/2017
Schedule 9 and 10 PJM 2017 Schedule 9 PJM Scheduling, System Control and Dispatch Service How PJM pays its bills Unbundled Those who use the service, pay for it 6 categories plus FERC, NERC, RFC, OPSI,
More informationConcepts for Behind-the- Meter Net Generation
Concepts for Behind-the- Meter Net Generation Pradip Ganesan Donna Pratt New York Independent System Operator Joint Meeting of Installed Capacity, Market Issues and Price Responsive Load Working Groups
More informationPJM Wholesale Markets. Hisham Choueiki, Ph.D., P.E. Ohio PUC Staff October 20-24, 2014 Tbilisi, Georgia
PJM Wholesale Markets Hisham Choueiki, Ph.D., P.E. Ohio PUC Staff October 20-24, 2014 Tbilisi, Georgia PJM RTO Functions Grid Operation Non-discriminatory treatment Monitoring transmission system Reliability
More information2011/2012 RPM Base Residual Auction Results
Executive Summary The 2011/12 Reliability Pricing Model (RPM) Base Residual Auction (BRA) cleared 132,221.5 MW of unforced capacity in the RTO at a uniform Resource Clearing Price of $110.00/MW-day. This
More information2020/2021 RPM Base Residual Auction Planning Period Parameters
Introduction The planning parameters for the 2020/2021 RPM Base Residual Auction (BRA) that is to be conducted in May of 2017 were posted on the PJM RPM website on February 1, 2017. This document describes
More informationPJM Proposal for Incremental Auction Redesign
PJM Proposal for Incremental Auction Redesign Jeff Bastian Manager, Capacity Market Operations Incremental Auction Senior Task Force May 31, 2017 www.pjm.com RPM Depends on Physical Resources RPM is designed
More informationThe 2017/2018 RPM Base Residual Auction: Sensitivity Analyses Revised
The 2017/2018 RPM Base Residual Auction: Sensitivity Analyses Revised The Independent Market Monitor for PJM August 26, 2014 Monitoring Analytics 2014 www.monitoringanalytics.com This page intentionally
More informationCapacity Performance Proposal. Summary of Key Design Elements
December 3, 2014 This page is intentionally left blank. PJM 2014 1 P a g e Capacity Product Synopsis PJM Interconnection is proposing a single capacity product called Capacity Performance, similar to the
More informationGeneration Capacity Mechanisms and Resource Adequacy Planning
Generation Capacity Mechanisms and Resource Adequacy Planning Jennifer Heintz Public Service Commission of the State of Missouri February 7, 2013 Abu Dhabi, UAE Electricity Markets in the U.S. and Canada
More informationIntermittent Resources in RPM. Sept 21, 2015
Intermittent Resources in RPM Sept 21, 2015 Capacity Resource Capacity Resources must be capable of sustained, predictable operation that allows resource to be available to provide energy and reserves
More informationKey Issues and Consideration in Market Design, Operational and Oversight
Key Issues and Consideration in Market Design, Operational and Oversight Patrick Donlon Amanda Gordon Kathryn Sophy Kenneth Villwock Public Utilities Commission of Ohio & Pennsylvania Public Utilities
More informationResource Capability Testing
Resource Capability Testing Amount of Capacity Available Joe Nieminski ICAP Market Operations Engineer, NYISO Intermediate ICAP Course November 7-8, 2017 Rensselaer, NY 1 Objectives Participants will be
More informationMothball Outages in Capacity Markets
Mothball Outages in Capacity Markets (preliminary review and summary for working group discussion purposes consult relevant ISO directly for latest and detailed legal requirements) September 13, 2017 NYISO
More informationPackage and Design Component Non-Binding Poll Results
Package and Design Component Non-Binding Poll Results Summer Only Demand Response Senior Task Force July 25, 2018 Data Summary Total Unique Responders: 17 Total Companies Represented: 104 2 Package A (PJM)
More information2018/2019 RPM Base Residual Auction Planning Period Parameters
Introduction The planning parameters for the 2018/2019 RPM Base Residual Auction (BRA) that is to be conducted in May of 2015 were posted on the PJM RPM website on January 30, 2015. Two versions of the
More information3.3.1 Cost of New Entry
Section 3: Demand in Reliability Price Model 3.3.1 Cost of New Entry The value for Cost of New Entry (CONE) (in ICAP terms) is determined in accordance with Attachment DD of the Open Access Transmission
More informationCapacity Market. Overview. RPM Capacity Market. Market Design
Section 5 Capacity Capacity Market Each organization serving PJM load must meet its capacity obligations through the PJM Capacity Market, where load serving entities (LSEs) must pay the locational capacity
More informationDesign Alternatives Sheet (DAS) 18 Physical Bilateral Procurement
Design Alternatives Sheet (DAS) 18 Physical Bilateral Procurement Introduction The subject matter discussed within this document forms part of the process for developing a Capacity Market design for Alberta.
More informationWorkshop H. PJM Basics: An Introduction to PJM Interconnection and How its Energy and Capacity Markets Operate
Workshop H PJM Basics: An Introduction to PJM Interconnection and How its Energy and Capacity Markets Operate Tuesday, February 19, 2019 1:45 p.m. to 3 p.m. Biographical Information Adam J. Keech, Executive
More informationPJM Manual 29: Billing. Revision: 26 Effective Date: 11/20/2014. Prepared by Market Settlements Department
PJM Manual 29: Billing Revision: 26 Effective Date: 11/20/2014 Prepared by Market Settlements Department PJM 2012 Table of Contents PJM Manual 29: Billing Table of Contents Table of Contents... ii Approval...
More information2010 State of the Market Report for PJM: Technical Reference for PJM Markets
200 State of the Market Report for PJM: Technical Reference for PJM Markets The Independent Market Monitor for PJM March 0, 20 Monitoring Analytics 20 www.monitoringanalytics.com This page intentionally
More informationRelevant changes will be made to corresponding sections of OA and RAA.
PJM Interconnection - Intra-PJM Tariffs - OPEN ACCESS TRANSMISSION TARIFF PJM OPEN ACCESS TRANSMISSION TARIFF Relevant changes will be made to corresponding sections of OA and RAA. Effective Date: 9/17/2010
More informationLOLE is expressed as hours per year with the usual target criteria being (0.1 days/year) or 1- day in 10-years MISO Tariff: Module E-1 - The
1 2 3 4 LOLE is expressed as hours per year with the usual target criteria being (0.1 days/year) or 1- day in 10-years MISO Tariff: Module E-1 - The Transmission Provider will calculate and post the Planning
More informationPJM Markets. Energy and Ancillary Services. PJM State & Member Training Dept. PJM /29/2014
PJM Markets Energy and Ancillary Services PJM State & Member Training Dept. LMP Basics 2 7/17/2013 What is LMP? Locational Marginal Price Pricing method PJM uses to: price energy purchases and sales in
More informationReliability Based Capacity Release Sell Back Curve
Reliability Based Capacity Release Sell Back Curve When PJM held the Transitional Auction for the 2017/2018 Delivery Year, it procured 10,017 MWs of capacity not previously committed. PJM intends to release
More informationBilling Line Items PJM /23/2017
Billing Line Items PJM 2017 Billing Line Items (BLI) PJM 2017 2 Billing Line Items (BLI) ID # Weekly BLI CHARGES ID # 1000 Amount Due for Interest on Past Due Charges Weekly BLI 1100 1 Network Integration
More informationAnalysis of the 2020/2021 RPM Base Residual Auction
Analysis of the 2020/2021 RPM Base Residual Auction The Independent Market Monitor for PJM November 17, 2017 Monitoring Analytics 2017 www.monitoringanalytics.com Introduction This report, prepared by
More informationDemand Response Participation in PJM Markets
Demand Response Participation in PJM Markets Review of PJM Independent Market Monitor s Criticisms and Responses PREPARED FOR Alberta Electric System Operator PREPARED BY Kathleen Spees Hannes Pfeifenberger
More informationAmerican Municipal Power Proposal to the Capacity Construct/Public Power Senior Task Force Executive Summary
American Municipal Power Proposal to the Capacity Construct/Public Power Senior Task Force Executive Summary I. Introduction The genesis of the AMP proposal was in part due to AMP s strong belief that
More informationAnalysis of the 2012/2013 RPM Base Residual Auction
Analysis of the 2012/2013 RPM Base Residual Auction The Independent Market Monitor for PJM August 6, 2009 Monitoring Analytics 2009 www.monitoringanalytics.com Introduction This report, prepared by the
More informationPJM Manual 29: Billing. Revision: 23 Effective Date: January 1, Prepared by Strategic Market Services Department
PJM Manual 29: Billing Revision: 23 Effective Date: January 1, 2012 Prepared by Strategic Market Services Department PJM 2012 Table of Contents PJM Manual 29: Billing Table of Contents Table of Contents...
More informationExpanding Capacity Eligibility
Expanding Capacity Eligibility Zachary T. Smith Manager, Capacity Market Design ICAPWG/MIWG March 7 th, 2019 Agenda Background Installed Capacity Supplier Payment Structure Peak Load Windows Counting MWs
More informationCalifornia Independent System Operator Corporation Fifth Replacement Electronic Tariff
Table of Contents 40. Resource Adequacy Demonstration for all SCs in the CAISO BAA... 3 40.1 Applicability... 3 40.1.1 [Not Used]... 3 40.2 Information Requirements for Resource Adequacy Programs... 3
More informationRecent Development in Reliable Energy Market in the US and Singapore
Recent Development in Reliable Energy Market in the US and Singapore 18-19 th June 2008 Electrical Engineering and Maintenance Forum World Engineering Congress, Bangkok, Thailand Dr. Panida Jirutitijaroen
More informationPJM Resource Adequacy Analysis
PJM Manual 20: PJM Resource Adequacy Analysis Revision: 05 Effective Date: February 1, 2013 Prepared by Resource Adequacy Planning PJM 2013 1 PJM Manual 20: Manual 20: PJM Resource Adequacy Analysis Table
More informationAnalysis of the 2019/2020 RPM Base Residual Auction
Analysis of the 2019/2020 RPM Base Residual Auction The Independent Market Monitor for PJM August 31, 2016 Monitoring Analytics 2016 www.monitoringanalytics.com Introduction This report, prepared by the
More informationManual 21- Revision 13 Rules and Procedures for Determination of Generating Capability Changes
Manual 21- Revision 13 Rules and Procedures for Determination of Generating Capability Changes Jerry Bell Resource Adequacy Department Markets and Reliability Committee March 21 st, 2019 Manual 21 changes
More informationRevision: 67. Prepared by
PJM Manual 11: Energy & Ancillary Services Market Revision: 67 Effective Date: June 1, 2014 Prepared by Forward Market PJM 2014 i Section 9: Hourly Scheduling Section 4: Overview of the PJM Synchronized
More informationLoad Serving Entity Definition Refinement Draft Final Proposal
Updated: September 21, 2016 Table of Contents 1. Executive Summary... 4 2. Scope of Initiative... 6 3. Changes to this proposal... 6 4. Stakeholder Engagement... 7 5. Background... 8 Allocation of Congestion
More informationPJM Manual 27: Open Access Transmission Tariff Accounting Revision: 88 Effective Date: November 16, 2017
PJM Manual 27: Open Access Transmission Tariff Accounting Revision: 88 Effective Date: November 16, 2017 Prepared by Market Settlements Development Department PJM 2017 Table of Contents Table of Contents
More informationBTM:NG Initiative Energy Market Design Concepts
BTM:NG Initiative Energy Market Design Concepts Pradip Ganesan Market Product Specialist, Energy Market Design New York Independent System Operator MIWG January 29, 2015 Rensselaer, NY 2014 New York Independent
More informationComparison Matrix of Existing Capacity Market Attributes: RPM & FCM
Comparison Matrix of Existing Capacity Market Attributes: RPM & FCM RPM / PJM FCM / ISO-NE Qualification for Existing Resources Qualification for New Resources Procurement cycle Commitment Term Base Auction
More informationThird Incremental Auction shall mean an Incremental Auction conducted three months before the Delivery Year to which it relates.
Definitions T U - V Tangible Net Worth: Tangible Net Worth shall mean all assets (not including any intangible assets such as goodwill) less all liabilities. Any such calculation may be reduced by PJMSettlement
More informationISO-NE FCM Capacity Market Design Scott M. Harvey. October 9, 2007
ISO-NE FCM Capacity Market Design Scott M. Harvey October 9, 2007 Summary The ISO-NE FCM capacity market design embodies many improvements over the prior ISO-NE capacity market. Five of these improvements
More informationCAPACITY MARKETS 5. Overview. RPM Capacity Market Market Design. Market Structure
2009 Quarterly State of the Market Report for PJM: January through September Section 5 - Capacity Markets Each organization serving PJM load must meet its capacity obligations by acquiring capacity resources
More informationCurrent Approach to FERC Order on Capacity Markets and Public Policies
Current Approach to FERC Order on Capacity Markets and Public Policies Special MRC August 15, 2018 Other Approaches PJM not pursuing an ISO-NE CASPR-Like approach at this time Too many details to resolve
More informationCalifornia Independent System Operator Corporation. California ISO. Import resource adequacy. Department of Market Monitoring
k California Independent System Operator Corporation California ISO Import resource adequacy September 10, 2018 Department of Market Monitoring Summary This report provides an update of analysis and trends
More informationParticipation in the monthly auction and the capability period auction shall consist of:
New York Capacity Market (NYISO Installed Capacity Market) The term Installed Capacity in the ICAP Manual and the NYISO Services Tariff Manual describes the market as opposed to the product. For example,
More informationThe Year to Date in PJM: Operations and Markets
The Year to Date in PJM: Operations and Markets Kerry Stroup Manager, State Government Policy PJM Interconnection OMA Energy Committee July 30, 2014 OMA Energy Committee Presentation Outline PJM s mission:
More informationDistributed Energy Resources Roadmap
Distributed Energy Resources Roadmap Updates Overview James Pigeon Senior Market Design Specialist Distributed Resources Integration MIWG December 19, 2016 Krey Corporate Center - Rensselaer, NY 2000-2016
More informationIntroduction to the PJM Markets
Introduction to the PJM Markets PJM 2015 1 Objectives Students will be able to: Describe some of the basic functions of PJM PJM 2015 The History of PJM EKPC joins PJM 2013 PJM 2015 3 Our Responsibility
More information