Single-Phase Meter Installation

Size: px
Start display at page:

Download "Single-Phase Meter Installation"

Transcription

1 Single-Phase Meter Installation S T U D E N T M A N U A L March 31, 2005

2 2 STUDENT TRAINING MANUAL Prerequisites: None Objectives: From memory, you will be able to explain single-phase meter test procedures, calculate consumption costs, as well as perform pre and post meter installation checks. Rationale: The installation of a meter to the customer is the last phase in the construction process. It is important to do this correctly so proper metering is provided to the customer and accurate consumption and billing is provided to the utility. Learning Objectives Describe the application and permit requirements for meter installations. Explain the pre-installation checks required for single-phase meters. Explain the post-installation checks required for single-phase meters. Calculate the consumption and demand costs of a single-phase meter. Demonstrate the procedure used to perform an accuracy test. Explain the procedure used to process a dispute test. Learning Methods Self-learning + On-the-job Self-learning + On-the-job Self-learning + On-the-job Self-learning + On-the-job On-the-Job Demonstration and Practice Self-learning + On-the-job EVALUATION METHODS Written test Written test

3 SINGLE-PHASE METER INSTALLATION 3 Written test Written test On-the-Job Evaluation Written test STUDENT RESOURCES Learning Steps Electric Service Guide Revenue Metering Connection Diagrams 1. Read the Learning Guide. 2. Follow the steps outlined in the Learning Guide. 3. Clarify any questions or concerns you may have. 4. Complete the Practice and Feedback.

4 4 STUDENT TRAINING MANUAL Lesson 1: Application and Permit Requirements for Meter Installations Learning Objective:Describe the application and permit requirements for meter installations. Learning Method:Self-learning + On-the-job Evaluation Method:Written test Application for Service Permits The application for service should be made at the local utility office and should include the following information: Type of service Overhead or underground Single-phase and/or three-phase Supply voltage preferred Site plan, including location of service entrance Date the service is required Connected load and anticipated demand, both single-phase and three-phase Motor schedule Switch gear requirements Special load characteristics - voltage sensitive, motor starting characteristics, computer operations, etc. Applications involving customer owned substations and non-utility generators require additional information as outlined in the Electric Service Guide Any work being completed on a service requires a form. This ensures safety to the home owner, the electrical contractor, and, of course, the utility. There are three forms and a disconnection order which must be considered: Electrical Permit (previously Form J) Form K Form G Electric Service Disconnection Order

5 SINGLE-PHASE METER INSTALLATION 5 Electrical Permit An Electrical Permit is issued by the SaskPower inspection division to electrical contractors or others responsible for permanent or temporary wiring installations, alterations, repair or extensions. Conversions of farm yard distribution from overhead to underground are included. This permit is also required for reconnection of services that have been disconnected for more than one year or disconnected due to fire or flood. This form is an authorization for the utility to provide service to a customer and ensures an inspection of the installation by the SaskPower inspection division. A copy of the Electrical Permit must be sent to the local SaskPower office. The service will be connected once a copy of the Electrical Permit is received from the licensed contractor with the appropriate fees paid. The service must meet proper grounding practices and clearance standards, and must be deemed free of short circuits and other defects.! CAUTION The main switch is to be left open on services requiring connection. An Electrical Permit is required prior to the connection of a temporary service. A separate or additional Electrical Permit is required when transferring the service from temporary to permanent. This form states that everything is intact and the service is ready to be energized. ---Note--- Temporary services must be disconnected after the permanent service is connected. Form K Form G A Form K is a written notice issued by the electrical inspector informing the electrical contractor to make changes to a new service in order to comply with the electrical code. A Form G is a written notice issued by the electrical inspector informing

6 6 STUDENT TRAINING MANUAL the electrical contractor to make changes to an existing service in order to comply with the electrical code. Electric Service Disconnection Order When orders to correct defects or hazards are not complied with, the chief electrical inspector can issue an electrical service disconnection order to cut off the service on a specific date. The utility will disconnect the service on the date specified unless arrangements have been made with the electrical inspection division. Reconnection of the service is made only with the consent of, or instructions from, the chief electrical inspector. All appropriate paper work must be in place.

7 SINGLE-PHASE METER INSTALLATION 7 Lesson 2: Pre-Installation Checks for Single- Phase Meters Learning Objective:Explain the pre-installation checks required for single-phase meters. Learning Method:Self-learning + On-the-job Evaluation Method:Written test Introduction Prior to installing a meter at a new service location, be aware of the following: Final meter height from the finished grade is to be 1.7m Type of meter required (A-base meter, socket meter, demand meter) Measurements Canada seal is intact on the meter (if the seal is broken, the meter must not be used) Secure mounting of the meter socket Electrical Permit in possession Live incoming wires are connected to the line side terminals of the meter socket and customer wires are connected to the load side terminals of the meter socket Loose connections on the line and load side terminals Proper ground connections in the meter socket and at the external ground rod Reference For further information, refer to the Construction Standards manual or the Electric Service Guide.

8 8 STUDENT TRAINING MANUAL Lesson 3: Post-Installation Checks for Single- Phase Meters Learning Objective:Explain the post-installation checks required for single-phase meters. Learning Method:Self-learning + On-the-job Evaluation Method:Written test Introduction Disc Rotation Once a meter is installed, there are three precautionary checks to complete: Disc rotation Light load starting Meter creep Ensure the disc turns in the same direction as the arrow indicates. A reversed rotation indicates the line and load leads in the meter socket are reversed. Light Load Starting A meter that is working properly should start rotating with as little as 15 watts connected to it. To check this, disconnect the service load and connect a 15 watt bulb to the load side of the meter, first on one side of the circuit, then on the other.! CAUTION Ensure that only 120V is provided to the light. Do not hook it up phase-to-phase.

9 SINGLE-PHASE METER INSTALLATION 9 Meter Creep ---Note--- If the meter is to be used, it must start rotating at this point. Meter creep is when a meter turns under no-load conditions. A kwh meter is said to be creeping when the disc makes more than one complete revolution after the load has been removed. ---Note--- If creeping occurs, it is usually in a forward motion and can be mistaken for light load. The following steps should be followed if a meter is suspected of creeping: Turn the main breaker to the Off position or disconnect the load wires from the terminals. If the creeping stops, it is assumed there is a wiring defect in the customer s load. Notify the customer. If the creeping continues, the meter is defective and should be changed immediately. The meter should be sent to the meter repair shop and clearly marked creeping meter. Causes of Meter Creep Incorrect meter adjustment Vibration Supply voltage is too high Magnets (brakes) in the meter are out of line Short circuit in current coils Current leakage in the customer s wiring Stray magnetic forces

10 10 STUDENT TRAINING MANUAL Lesson 4: Consumption and Demand Costs Learning Objective:Calculate the consumption and demand costs of a single-phase meter. Learning Method:Self-learning + On-the-job Evaluation Method:Written test Introduction The amount of energy used, in turn, becomes a cost to the customer. In order to charge the correct amount, we need to know how to read a meter correctly for kilowatt-hour consumption. How to Read a Meter There are four or five dials which are read to get the kilowatt-hour consumption of the period. A meter is read in the following way: Extreme right-hand dial measures the single units Second dial from the right measures the tens (10s) Third dial from the right measures the hundreds (100s) Fourth dial from the right measures the thousands (1000s)

11 SINGLE-PHASE METER INSTALLATION 11 Fifth dial, if any, would read ten thousands (10,000s) ---Note--- There is also a test dial on the meter which is for test purposes only. Cost of Consumption Using the previous diagram, we can calculate the amount of energy the customer has used since the meter was last read, and by multiplying the cost per kwh, we can determine the amount the customer will be charged. Example: The previous read was By the diagram, we can see that this read is The total amount of energy used is: 7250kWh kWh = 2568kWh If the energy rate is 5.85 cents per kwh, we can determine the cost of consumption. Cost = 2568kWh x 5.85 cents/kwh Cost = cents divided by 100 Cost = $ Therefore, a sum of $ would be applied to this customer s next bill to cover their consumption.

12 12 STUDENT TRAINING MANUAL Rates for Metered Customers Reference There are a number of different rates for energy costs, depending on the type of customer. For further information on rates, refer to the Rates and Policies manual. Demand Energy Meters A demand energy meter is in actual fact, two meters in one body. It is a kilowatt-hour or watt-hour meter which measures energy and a demand meter which measures kva. The demand portion of the meter measures and registers the load on the service installation at any given time. This is necessary to determine what kind of load the customer is inflicting upon the apparatus. For example, if a customer normally draws a load of 50kVA, but requires 200kVA for one hour per day, we have no choice but to supply

13 SINGLE-PHASE METER INSTALLATION 13 Billing Multiplier him with a 200kVA service. To pay for this extra service, the customer is billed an extra amount based on the demand reading of the meter. The demand portion of the meter is constructed so that a pointer advances along a scale to record the present kva demand. A second pointer is integrated into the meter and performs the same function as that of the first pointer. However, the maximum value reached will be retained, and can only be reset by the proper authorities (meter reader, district operator). The maximum value recorded by the demand needle is the value in which the customer is billed. The demand reading is multiplied by the billing multiplier to calculate the total demand. This demand can then be multiplied by the cost per kva. Example: A customer has a demand reading of 800VA on the meter and the billing multiplier for the service is 80. Calculate the demand charge if the customer must pay $13.01 per kva on consumption above 50kVA. Total Demand = Read x Billing Multiplier Total Demand = 800 x 80 Total Demand = 64,000VA or 64kVA Cost = (64-50) x $13.01 Cost = 14 x $13.01 Cost = $ Note--- When reading meters, never forget to reset the demand or peak demand needle as the customer may not reach that maximum level during the next billing period.

14 14 STUDENT TRAINING MANUAL Meter Accuracy In many instances, a customer may believe the meter to be faulty or inaccurate, usually due to high electrical bills. The customer may possibly have a reason for concern; however, most times the problem does not lie with the accuracy of the meter. The following are some possible reasons for high meter readings: Customer load may have increased Faulty equipment such as electric water heaters may draw abnormally high amperages Errors in the meter reading Present reading was read too high Previous reading was read too low If you cannot satisfy the customer as to the explanation of a high power bill, they have the option of disputing the meter through an accuracy test or dispute test. ---Note--- The standards division requires that all meters be calibrated to ensure that an error in registration does not exceed +/- 2% or +/- 1% for electronic meters. A meter involved in a customer initiated dispute must be within +/- 3%. Meters sent to the meter repair shop are tested to an accuracy of +/-.5%. Accuracy Test An accuracy test can be done on site to check the accuracy of a singlephase meter. By performing this test, there is a good possibility of reassuring the customer that the meter is correct and avoiding a dispute test.

15 SINGLE-PHASE METER INSTALLATION 15 Load Check Perform a load check on the service being metered. Calculate the metered load. Check the kh factor of the meter. Simultaneously start counting time (in seconds) and the number of disc revolutions.! CAUTION To ensure consistent accuracy, there must be a minimum of ten disc revolutions over a period of at least 90 seconds (minimum time). Calculate the load recorded on the meter. Meter Accuracy The above calculation will indicate the meter accuracy in percent. A positive number indicates an error in favor of the utility and a negative number indicates an error in favor of the customer. If the meter accuracy test fails to convince the customer that there is not a problem with the meter, the meter can be put through a government dispute test.

16 16 STUDENT TRAINING MANUAL Lesson 5: Perform an Accuracy Test Learning Objective:Demonstrate the procedure used to perform an accuracy test. Learning Method:On-the-Job Demonstration and Practice Evaluation Method:On-the-Job Evaluation

17 SINGLE-PHASE METER INSTALLATION 17 Skills Practice 1. Demonstrate the procedure used to perform an accuracy test. 0. Check all wiring and connections. 0. Ensure the load is constant and purely resistive. 1. Check and record the voltage. 2. Check and record the amps on both legs. 3. Start timing and counting simultaneously. 4. Record the number of disk revolutions (minimum of 10). 5. Record the number of seconds (minimum of 90). 6. Record the kilowatt-hour value. 7. kva calculations completed correctly. 8. kw calculations completed correctly. 9. Accuracy calculations completed correctly.

18 18 STUDENT TRAINING MANUAL Lesson 6: Dispute Test Procedure Learning Objective:Explain the procedure used to process a dispute test. Learning Method:Self-learning + On-the-job Evaluation Method:Written test Introduction If a customer requests a dispute test, collect the specified fee. In the event that the meter fails the dispute test, the fee will be returned, as well as any money resulting from the billing adjustment due to the faulty meter. If the meter tests within + or - 3%, SaskPower keeps the fee as payment for the test. Proceed to change the meter and fill out the necessary paper work. Tag the meter accordingly (dispute test meter) and mail the meter to the meter repair shop. After the dispute meter is received at the meter shop, it is sent to Measurements Canada to be tested. This is a federal government department. Once the meter is tested, the results are sent with one copy going to the metering department and one copy to the customer. The metering department will send a copy to the region office and customer accounts for billing adjustments.

19 SINGLE-PHASE METER INSTALLATION 19 Summary To summarize this module, you have learned: The application and permit requirements for meter installations. The pre-installation checks required for single-phase meters. The post-installation checks required for single-phase meters. To calculate the consumption and demand costs of a single-phase meter. To perform an accuracy test. To process a dispute test. Practice Feedback Review the lesson, ask any questions and complete the self-test. Evaluation When you are ready, complete the final test. You are expected to achieve 100%.

20 20 STUDENT TRAINING MANUAL Review Questions 1. An application for service must be made through SaskPower. 2. An application must include a site plan with the location of the service entrance. 3. A written notice to make alterations to a new installation is a: (a) Form K. (b) Form G. (c) Electric Permit. (d) Electric Service Disconnect Order. 4. Authorization to provide service to a customer following an inspection of the installation is a: (a) Form K. (b) Form G. (c) Electric Permit. (d) Electric Service Disconnect Order. 5. Written notice to make alterations to existing wiring is a: (a) Form K. (b) Form G. (c) Electric Permit. (d) Electric Service Disconnect Order. 6. A requirement for reconnection of services which have been disconnected for over one year is a: (a) Form K. (b) Form G. (c) Electric Permit. (d) Electric Service Disconnect Order. 7. A document issued when an order to correct a defect or hazard has not been complied with is a: (a) Form K. (b) Form G.

21 SINGLE-PHASE METER INSTALLATION 21 (c) (d) Electric Permit. Electric Service Disconnect Order. 8. Ensure the meter socket is secure before installing the meter. 9. Verify a Form K has been issued prior to a meter installation. 10. Ensure the Measurements Canada seal has been removed prior to the meter installation. 11. An inspection of the ground connections in the meter socket and ground rod should be completed prior to the meter installation. 12. The final meter height from the finished grade is to be 1.7m. 13. The final meter height from the finished grade is to be 2.0m. 14. Ensure live incoming wires are connected to the load side terminals of the meter socket and the customer wires are connected to the line side terminals of the meter socket. 15. Three items to check after a meter installation are: (a) Proper grounding, proper voltage, and meter creep. (b) Disc rotation, light load starting, and meter creep. (c) Vibration (d) Final grade, Form G, and light load starting. 16. When a meter turns under no load conditions, it is called: (a) Disc rotation. (b) Demand. (c) Meter creep. (d) An energy meter. 17. A meter that is working properly should start rotating with as little as 15 watts connected to it.

22 22 STUDENT TRAINING MANUAL 18. A meter that is working properly should start rotating with as little as 0 watts connected to it. 19. A reversed rotation on the meter disc indicates meter creep. 20. On a five dial meter, the middle dial reads kilowatt-hours by: (a) Tens. (b) Twenties. (c) Hundreds. (d) Thousands. 21. A customer who is metered by a demand meter is billed by a demand reading only. 22. A consumption meter or kilowatt hour meter measures the amount of energy used. 23. A consumption meter or kilowatt hour meter measures the amount of kva used. 24. A demand meter measures the kva required. 25. A demand meter measures the energy required. 26. The standards division requires that all meters be calibrated to ensure that an error in registration does not exceed +/- 2% or +/- 1% for electronic meters. 27. A meter which is involved in a customer initiated dispute must be accurate to within plus or minus: (a).5%. (b) 2%. (c) 3%. (d) 5%. 28. A customer initiated dispute may originate from the use of faulty equipment. 29. A dispute test can be completed with the meter left in its original location.

23 SINGLE-PHASE METER INSTALLATION If a dispute test is required, the meter is sent to the meter repair shop where it is tested and inspected.

24 24 STUDENT TRAINING MANUAL Review Question Solutions 1. T 2. T 3. Form K. 4. Electric Permit. 5. Form G. 6. Electric Permit. 7. Electric Service Disconnect Order. 8. T 9. F 10. F 11. T 12. T 13. F 14. F 15. Disc rotation, light load starting, and meter creep. 16. Meter creep. 17. T 18. F 19. F 20. Hundreds. 21. F 22. T

25 SINGLE-PHASE METER INSTALLATION F 24. T 25. F 26. T 27. 3%. 28. T 29. F 30. F

Basic Service. This Section provides information regarding a. Introduction

Basic Service. This Section provides information regarding a. Introduction Basic Service Introduction This Section provides information regarding a new electric Basic Service for a single phase service less than or equal to 400 amps, and a three phase service less than 50kW.

More information

ELECTRICAL SAFETY Information Bulletin

ELECTRICAL SAFETY Information Bulletin ELECTRICAL SAFETY Information Bulletin January 2014 CEC-2 [rev-8] Page 1 of 8 SUBJECT: Section 2 General Rules CANADIAN ELECTRICAL CODE Administrative Rules The Safety Codes Act and associated regulations

More information

INSTRUCTION MANUAL PHANTOM LOAD MODEL PA For SERIAL NO.

INSTRUCTION MANUAL PHANTOM LOAD MODEL PA For SERIAL NO. INSTRUCTION MANUAL For PHANTOM LOAD MODEL PA-305 SERIAL NO. It is essential that this instruction book be read thoroughly before putting the equipment in service. IMPORTANT The information and data contained

More information

Residential and Farm Customer Guide

Residential and Farm Customer Guide Residential and Farm Customer Guide CONTENTS 1. Who is this Guide for?... 3 2. What service does FortisAlberta provide to Residential and Farm Customers?... 3 3. What are the Terms and Conditions of Electric

More information

ELECTRICAL SAFETY Information Bulletin

ELECTRICAL SAFETY Information Bulletin ELECTRICAL SAFETY Information Bulletin February 2019 Page 1 of 7 2018 CANADIAN ELECTRICAL CODE SUBJECT: Section 2 General rules Administrative The Safety Codes Act and associated regulations, supplemented

More information

Net Energy Metering 2.0 Solar PV Interconnection Handbook. Effective January 1, 2017

Net Energy Metering 2.0 Solar PV Interconnection Handbook. Effective January 1, 2017 Net Energy Metering 2.0 Solar PV Interconnection Handbook Effective January 1, 2017 Overview This Handbook illustrates the steps, processes, and requirements to apply for a Solar Photovoltaic (PV) interconnection

More information

Nashville Electric Service Electric Service Policies

Nashville Electric Service Electric Service Policies Nashville Electric Service Electric Service Policies The Electric Power Board of the Metropolitan Government of Nashville and Davidson County TABLE OF CONTENTS New Service Polices 1.0 General Requirements

More information

CUSTOMER SERVICE POLICIES

CUSTOMER SERVICE POLICIES Resolution U-10670 Effective December 18, 2013 Section Title Page No. 1.0 Statement of General Policy... 2 2.0 Electrical Service... 3 2.1 Electrical Service Availability and Characteristics... 3 2.2 Large-Load

More information

4. GENERAL REQUIREMENTS

4. GENERAL REQUIREMENTS 4. GENERAL REQUIREMENTS 4.1 APPLICATION FOR SERVICE Application for service must be made to, and accepted by, the Company before service will be furnished. At the time of application, the Customer shall

More information

Technical Guideline for. Section 8. Inspection and Approval of Construction

Technical Guideline for. Section 8. Inspection and Approval of Construction Technical Guideline for Section 8. Inspection and Approval of Construction Ontario Regulation 22/04 Electrical Distribution Safety January 12, 2005 Technical Guideline Section 8 General Legal Disclaimer

More information

BULLETIN SUBJECT: GENERAL BULLETIN, 2015 SASK INTERPRETATIONS CORRECTIONS, AND ELECTRIC SERVICE REQUIREMENT CHANGES OR ADDITIONS

BULLETIN SUBJECT: GENERAL BULLETIN, 2015 SASK INTERPRETATIONS CORRECTIONS, AND ELECTRIC SERVICE REQUIREMENT CHANGES OR ADDITIONS SaskPower Electrical Inspections BULLETIN 01-2017 February 15, 2017 TO: LICENSED ELECTRICAL CONTRACTORS ELECTRICAL CONSULTANTS AND ENGINEERS SUBJECT: GENERAL BULLETIN, 2015 SASK INTERPRETATIONS CORRECTIONS,

More information

4. GENERAL REQUIREMENTS

4. GENERAL REQUIREMENTS 4. GENERAL REQUIREMENTS 4.1 APPLICATION FOR SERVICE Application for service must be made to, and accepted by, the Company before service will be furnished. At the time of application, the Customer shall

More information

SECTION GENERAL ELECTRICAL REQUIREMENTS PART 1- GENERAL

SECTION GENERAL ELECTRICAL REQUIREMENTS PART 1- GENERAL 1.01 DESCRIPTION SECTION 16000 GENERAL ELECTRICAL REQUIREMENTS PART 1- GENERAL A. This Section includes the general provisions applicable to electrical work and testing of the completed electrical systems.

More information

Member Service Electric Wiring Guidelines

Member Service Electric Wiring Guidelines Member Service Electric Wiring Guidelines Table of Contents A. Definitions... 2 B. Member Service Wiring Guidelines... 2 C: Meter located on the house from an underground source - pad transformer or j-box....

More information

GPI Conditions of Service - Revision History The following is a summary of key changes made to the document.

GPI Conditions of Service - Revision History The following is a summary of key changes made to the document. Identification of Grimsby Power 1.1 Added licence number. and Service Area 1.1.1 Distribution Overview Added Niagara West Municipal Transformer Station. Added section with general information about servicing,

More information

REVISION NO.: 8 EFFECTIVE: 03/26/18

REVISION NO.: 8 EFFECTIVE: 03/26/18 Distributed Generation Interconnection Process for Residential and Small General Service OVERVIEW REVISION NO.: 8 EFFECTIVE: 03/26/18 Required Steps for ED3 s Distributed Generation Interconnection Process

More information

Unit Substation Transformer Construction Checklist (under 500 kva)

Unit Substation Transformer Construction Checklist (under 500 kva) Unit Substation Transformer Checklist (under 500 kva) Building: Location: Submittal / Approvals Submittal. The above equipment and systems integral to them are complete and ready for functional testing.

More information

Revised October 2017, the information contained in this bulletin supercedes the requirements of all previous bulletins.

Revised October 2017, the information contained in this bulletin supercedes the requirements of all previous bulletins. EB 0901 Revised October 2017, the information contained in this bulletin supercedes the requirements of all previous bulletins. 1. An Electrical Permit must be purchased BEFORE electrical work is carried

More information

Request for Electric and Gas Service Form

Request for Electric and Gas Service Form Request for Electric and Gas Service Form CUSTOMER INFORMATION Name Address City State Zip Telephone Customer Number/Last 4 of SSN/EIN Number Email Current National Grid Account Number If Applicable: Name

More information

Net Energy Metering 2.0 Solar PV Interconnection Handbook. Effective December 1, 2017

Net Energy Metering 2.0 Solar PV Interconnection Handbook. Effective December 1, 2017 Net Energy Metering 2.0 Solar PV Interconnection Handbook Effective December 1, 2017 Important Information The NEM 1.0 solar PV rate is closed. The NEM 2.0 is the current PV rate option available for solar

More information

201 S. Anaheim Blvd. Page No Anaheim, CA RULE NO. 16 SERVICE CONNECTIONS AND FACILITIES ON CUSTOMER'S PREMISES

201 S. Anaheim Blvd. Page No Anaheim, CA RULE NO. 16 SERVICE CONNECTIONS AND FACILITIES ON CUSTOMER'S PREMISES 201 S. Anaheim Blvd. Page No. 3.16.1 A. METER INSTALLATIONS AND MISCELLANEOUS SERVICE EQUIPMENT ON CUSTOMER'S PREMISES. 1. Meter Installations. a. Location. All Meters installed by the Utility shall be

More information

METERING INSTALLATION

METERING INSTALLATION 4.01 METERING SPECIFICATIONS METERING INSTALLATION Metering specifications will be issued to the customer by OPPD. Metering specifications are required before any work is started on all new wiring or additions

More information

Tucson Electric Power Company Rules and Regulations

Tucson Electric Power Company Rules and Regulations Original Sheet No.: 906 A. Priority and Timing of Service Establishments 1. After an Applicant has complied with the Company s application requirements and has been accepted for service by the Company

More information

Travel & Adventure LA Job # V 500 WATTS (5 AMPS) 1000 WATTS (10 AMPS) 2000 WATTS (20 AMPS) V 10

Travel & Adventure LA Job # V 500 WATTS (5 AMPS) 1000 WATTS (10 AMPS) 2000 WATTS (20 AMPS) V 10 WHEN ORDERING ELECTRICAL SERVICES: 1. Check rating plate(s) on item(s) and order outlets accordingly. 2. Lighting outlets supplied with one (1) connection per outlet ordered. 3. Motor outlet supplied with

More information

Delaware Electric Cooperative Generator Interconnection Application Long Form (For Use with Generators Greater than 100 kw)

Delaware Electric Cooperative Generator Interconnection Application Long Form (For Use with Generators Greater than 100 kw) An applicant (Generator Owner) makes application to to install and operate a generating facility greater than 100 kw interconnected with the utility system. Section 1, Applicant Information Directly Interconnected

More information

NEW JERSEY BOARD OF PUBLIC UTILITIES N.J.A.C. 14:4-9 Net Metering and Interconnection Standards for Class I Renewable Energy Systems

NEW JERSEY BOARD OF PUBLIC UTILITIES N.J.A.C. 14:4-9 Net Metering and Interconnection Standards for Class I Renewable Energy Systems NEW JERSEY BOARD OF PUBLIC UTILITIES N.J.A.C. 14:4-9 Net Metering and Interconnection Standards for Class I Renewable Energy Systems SUBCHAPTER 9 NET METERING AND INTERCONNECTION STANDARDS FOR CLASS I

More information

Large Basic Service. This Section applies to members requiring new. Introduction. Service Types

Large Basic Service. This Section applies to members requiring new. Introduction. Service Types Large Basic Service Introduction This Section applies to members requiring new Large Basic electric service installations, greater than 400 amps single phase and greater than 50kW three phase. This Section

More information

1. INTRODUCTION. Operational Excellence Model. 1.1 Purpose. 1.2 Scope. 1.3 Rate Schedule. 1.4 Cooperation

1. INTRODUCTION. Operational Excellence Model. 1.1 Purpose. 1.2 Scope. 1.3 Rate Schedule. 1.4 Cooperation 1. 1.1 Purpose 1.2 Scope The purpose of this book is to present information and specifications relative to the introduction and use of electricity supplied by PSEG Long Island. This book is to be used

More information

Portland General Electric Company P.U.C. Oregon No E-18 Original Sheet No. L-1 RULE L SPECIAL TYPES OF ELECTRICITY SERVICE

Portland General Electric Company P.U.C. Oregon No E-18 Original Sheet No. L-1 RULE L SPECIAL TYPES OF ELECTRICITY SERVICE P.U.C. Oregon No E-18 Original Sheet No. L-1 RULE L SPECIAL TYPES OF ELECTRICITY SERVICE 1. Service of Limited Duration (Temporary Service) A. Definition "Service of Limited Duration" or "Temporary Service"

More information

OPERATING PROCEDURE NO. 310

OPERATING PROCEDURE NO. 310 OPERATING PROCEDURE NO. 310 Related Operating Procedures: 310A; 310B; 310C; 310D SUBJECT: Conditions of Service Issued: February 10, 2014 Revised: March 28, 2016 OBJECTIVE: To establish the rules, regulations

More information

Low Voltage Switchgear Construction Checklist (under 500 kva)

Low Voltage Switchgear Construction Checklist (under 500 kva) Low Voltage Switchgear Checklist (under 500 kva) Project: Building: Location: Submittal / Approvals Submittal. The above equipment and systems integral to them are complete and ready for functional testing.

More information

CONTRACTOR S PERMIT APPLICATION for Residential PV Installation with e-inspection CA Health and Safety Code Section V p2s

CONTRACTOR S PERMIT APPLICATION for Residential PV Installation with e-inspection CA Health and Safety Code Section V p2s CONTRACTOR S PERMIT APPLICATION for Residential PV Installation with e-inspection CA Health and Safety Code Section 19825 V 11-10-12 6p2s H:\2012 Permit Masters\v 11-10-12 e-inspection Residential PV Installation

More information

Specifications for the Secondary Installation of Communication Equipment on MLGW Transmission Structures

Specifications for the Secondary Installation of Communication Equipment on MLGW Transmission Structures Page 1 of 7 Specifications for the Secondary Installation of Communication Equipment on MLGW Transmission Structures 1. Request and Approval Procedure 1.1. The telecommunications provider Carrier will

More information

PIKES PEAK PARKING RESTORATION TABLE OF CONTENTS

PIKES PEAK PARKING RESTORATION TABLE OF CONTENTS 23 HEATING, VENTILATING AND AIR CONDITIONING TABLE OF CONTENTS TABLE OF CONTENTS DIVISION 23 HEATING, VENTILATING AND AIR CONDITIONING - Basic HVAC Requirements 238239.19 - Wall and Ceiling Unit Heaters

More information

Applying For New or Revised Electric Service

Applying For New or Revised Electric Service Applying For New or Revised Electric Service Dear Customer: ComEd is happy to assist you in initiating new or revised electric service to your location. Please complete, sign and return the attached service

More information

(2) isolated operation with standby service provided by the Company by means of a doublethrow

(2) isolated operation with standby service provided by the Company by means of a doublethrow P.S.C. NO. 3 ELECTRICITY LEAF: 370 INITIAL EFFECTIVE DATE: April 1, 2012 SERVICE CLASSIFICATION NO. 25 APPLICABLE TO USE OF SERVICE FOR: Sales and delivery of electric power supply provided by the Company,

More information

(Condensed from National Electric Code)

(Condensed from National Electric Code) WIRING, SPECIFICATIONS, INSPECTION, AND METER INSTALLATION PROCEDURES FOR RESIDENTIAL CUSTOMERS SERVED BY SOUTHWEST ARKANSAS ELECTRIC COOPERATIVE CORPORATION Effective April 1, 1974 Revised February 3,

More information

Ensure no person makes contact with the steel pole streetlight or temporary earth electrode while the testing procedures are being undertaken.

Ensure no person makes contact with the steel pole streetlight or temporary earth electrode while the testing procedures are being undertaken. NOTE: SAFETY: Tests must be carried out after the installation, alteration or repair and before putting back to service. At all times maintain suitable clearance to all other electrical equipment and verify

More information

SCHEDULE SS STANDBY SERVICE

SCHEDULE SS STANDBY SERVICE SCHEDULE SS STANDBY SERVICE SHEET NO. 69 A. APPLICABILITY: Applicable to customers with alternate regular source(s) of energy other than electricity from the Company when such sources are connected to

More information

ELECTRICAL SERVICE EXTENSION POLICY

ELECTRICAL SERVICE EXTENSION POLICY I. OBJECTIVE A. To provide a fair and consistent method of extending, upgrading and downgrading power lines and other service facilities within the Mason County PUD No.1 (PUD 1) service area. B. To encourage

More information

RULE NO. 16 SERVICE CONNECTIONS, METERS AND CUSTOMER S FACILITIES

RULE NO. 16 SERVICE CONNECTIONS, METERS AND CUSTOMER S FACILITIES 6100 Neil Road, Reno, Nevada 3rd Revised PUCN Sheet No. 49 Tariff No. Electric No. 1 Cancelling 2nd Revised PUCN Sheet No. 49 A. Service Installation Services shall be installed subject to the requirements

More information

CITY & COUNTY OF DENVER COMMUNITY PLANNING & DEVELOPMENT BUILDING PERMIT POLICY

CITY & COUNTY OF DENVER COMMUNITY PLANNING & DEVELOPMENT BUILDING PERMIT POLICY Page 1 of 5 REFERENCE Denver Building and Fire Code (DBC) Section 131, International Residential Code (IRC) Section M2301, the National Electrical Code (NEC) Articles 690 & 705 PROCEDURE The procedure

More information

Hook-up charges will not be billed, and must be paid in advance. General Information

Hook-up charges will not be billed, and must be paid in advance. General Information UTILITY SERVICES All hook-up charges for utilities will be paid with the issuance of a building permit. Hook-up charges will not be billed, and must be paid in advance. General Information All service

More information

Chapter 3.12 WATER SERVICE CONNECTIONS AND METERS

Chapter 3.12 WATER SERVICE CONNECTIONS AND METERS Chapter 3.12 WATER SERVICE CONNECTIONS AND METERS Sections: 3.12.010 Service connections and meters. 3.12.020 Meter error. 3.12.030 Multiple units. 3.12.040 Temporary service. 3.12.050 Pools and tanks.

More information

CITY OF LODI ELECTRIC UTILITY DEPARTMENT RULE AND REGULATION NO. 16 SERVICE CONNECTIONS AND FACILITIES ON CUSTOMER'S PREMISES

CITY OF LODI ELECTRIC UTILITY DEPARTMENT RULE AND REGULATION NO. 16 SERVICE CONNECTIONS AND FACILITIES ON CUSTOMER'S PREMISES RULE AND REGULATION NO. 16 SERVICE CONNECTIONS AND FACILITIES ON CUSTOMER'S PREMISES A. Service in Areas Supplied by Overhead Facilities 1. Below 600 Volts The City will install, own, operate and maintain

More information

Post Office Box 500 Carson, WA Phone (509) Fax (509) Toll Free (800)

Post Office Box 500 Carson, WA Phone (509) Fax (509) Toll Free (800) Public Utility District No. 1 of Skamania County Post Office Box 500 Carson, WA 98610 Phone (509) 427-5126 Fax (509) 427-8416 Toll Free (800) 922-5329 ELECTRIC LINE EXTENSION If you are purchasing property

More information

Long Island Power Authority Seventh Revised Leaf No. 16

Long Island Power Authority Seventh Revised Leaf No. 16 Seventh Revised Leaf No. 16 I. General Information (continued): B. Abbreviations and Definitions (continued): Demand Customer: A Customer who is billed for Demand charges. Demand Meter: The device that

More information

Central Lincoln PUD Single-Family Residential Guidelines & Standards April 21, 2017

Central Lincoln PUD Single-Family Residential Guidelines & Standards April 21, 2017 Central Lincoln PUD Single-Family Residential Guidelines & Standards April 21, 2017 Overview of Hook-Up Procedures: The following is a general outline of how you get a new electrical service for a single-family

More information

Lecture 26 Chapter 23 Circuits Chapter 24 Magnetism

Lecture 26 Chapter 23 Circuits Chapter 24 Magnetism Lecture 26 Chapter 23 Circuits Chapter 24 Magnetism Quiz 4: Monday Nov. 1; Chaps. 22,23,24 Electric Circuit Make electric circuit by connecting voltage source and resistive object(s) together in a loop

More information

New Construction Handbook

New Construction Handbook New Construction Handbook New Construction Services & Engineering Garkane Energy Cooperative 120 W. 300 S Loa, UT 84747 800-747-5403 www.garkaneenergy.com Revised Jun 28, 2018 TABLE OF CONTENTS General

More information

DOWNTOWN UNDERGROUND NETWORK SECONDARY SERVICES GUIDELINES

DOWNTOWN UNDERGROUND NETWORK SECONDARY SERVICES GUIDELINES Guidelines effective March 5, 2007 NES is committed to providing safe, reliable electric service at a reasonable price for all of our customers. These guidelines offer direction for activities relating

More information

COMMERCIAL & INDUSTRIAL AMI METER TESTING SUMMARY

COMMERCIAL & INDUSTRIAL AMI METER TESTING SUMMARY FINAL COMMERCIAL & INDUSTRIAL AMI METER TESTING SUMMARY Black & Veatch Holding Company 2017. All rights reserved. PREPARED FOR SaskPower 19 SEPTEMBER 2017 Commercial & Industrial AMI Meter Testing Summary

More information

Temporary Wiring. Low-Voltage Electrical Safety Orders

Temporary Wiring. Low-Voltage Electrical Safety Orders Temporary Wiring Low-Voltage Electrical Safety Orders 2405.1. Scope. Except as specifically modified in this Article, all other requirements of this Order for permanent wiring shall also apply to temporary

More information

CONDITIONS OF SERVICE

CONDITIONS OF SERVICE 2.3.1 Limitations on the Guaranty of Supply PowerStream will use good utility practice to provide a regular and reliable supply of electricity, within its voltage guidelines referred to in Sections 2.3.4

More information

A12 Single Family Residential Back-up Generator. Address: Date Stamp. Application Requirements:

A12 Single Family Residential Back-up Generator. Address: Date Stamp. Application Requirements: Development & Planning Services A12 Single Family Residential Back-up Date Stamp Address: For the installation of a generator, see below for permit submittal requirements. Application Requirements: Permit

More information

SECTION PROJECT CLOSEOUT

SECTION PROJECT CLOSEOUT PART 1 - GENERAL 1.01 SCOPE OF WORK A. This Section specifies administrative and procedural requirements for project closeout, including but not limited to: 1. Close-out procedures 2. Final cleaning 3.

More information

Name: New Document 1. Class: Date: 87 minutes. Time: 87 marks. Marks: Comments:

Name: New Document 1. Class: Date: 87 minutes. Time: 87 marks. Marks: Comments: New Document Name: Class: Date: Time: 87 minutes Marks: 87 marks Comments: Q. Figure shows a radio. The radio can be powered by connecting the two-core cable to the mains electricity supply. (a) (i) What

More information

Address of Installation Building Permit #

Address of Installation Building Permit # TOWN OF NISKAYUNA NY State Unified Solar Permit Application One Niskayuna Circle, Niskayuna NY 12309 Phone: 518-386-4522 Fax: 518-386-4592 Email: buiding@niskayuna.org The Town of Niskayuna has adopted

More information

BULLETIN LICENSED ELECTRICAL CONTRACTORS. SaskPower Electrical Inspections. June 13, Item #1 Arc-Fault Receptacles, CEC Rule (f)

BULLETIN LICENSED ELECTRICAL CONTRACTORS. SaskPower Electrical Inspections. June 13, Item #1 Arc-Fault Receptacles, CEC Rule (f) SaskPower Electrical Inspections BULLETIN 01-2014 June 13, 2014 TO: LICENSED ELECTRICAL CONTRACTORS SUBJECT: GENERAL BULLETIN Item #1 Arc-Fault Receptacles, CEC Rule 26-722(f) For the purposes of this

More information

UNITED COOPERATIVE SERVICES. SPECIFICATIONS FOR SELF-CONTAINED METER INSTALLATIONS August 2014

UNITED COOPERATIVE SERVICES. SPECIFICATIONS FOR SELF-CONTAINED METER INSTALLATIONS August 2014 UNITED COOPERATIVE SERVICES SPECIFICATIONS FOR SELF-CONTAINED METER INSTALLATIONS August 2014 A member may obtain a new, single phase service from the Cooperative by providing or purchasing a meter loop.

More information

AEL.NP.001 New Connections and Extensions Policy

AEL.NP.001 New Connections and Extensions Policy AEL.NP.001 New Connections and Extensions Policy 10 February 2014 Version 3 Contents Introduction... 3 Amendment Record... 5 1. Technical Requirements for New Connections to the Network... 6 1.1 Method

More information

ISIMET. E Series Enclosure. Custom Assemblies Installation, Maintenance, and Operation Instructions

ISIMET. E Series Enclosure. Custom Assemblies Installation, Maintenance, and Operation Instructions ISIMET E Series Enclosure Custom Assemblies Installation, Maintenance, and Operation Instructions The Custom Assembled E-Series Enclosures is pre-assembled and pre-wired enclosure intended for use with

More information

Electric Service Handbook

Electric Service Handbook Electric Service Handbook Revised August 2017 Contact Information Telephone (253): Electrical Inspection Office 502-8277 7:30 am - 4:30 pm Electrical Inspectors Area Map on Website 7:30 am - 8:30 am Automated

More information

Rule No. 16. Service Extensions Page 1 of 15

Rule No. 16. Service Extensions Page 1 of 15 GOLDEN STATE WATER COMPANY (U 913-E) Revised Cal. P.U.C. Sheet No. 2117-E SAN DIMAS, CALIFORNIA 91773-9016 Canceling Revised Cal. P.U.C. Sheet No. 1018-E Page 1 of 15 APPLICABILITY: This rule is applicable

More information

SERVICES - SERVICE EQUIPMENT- PANELBOARDS

SERVICES - SERVICE EQUIPMENT- PANELBOARDS NO: D-E3 101110 1 THIS DIRECTIVE SUPERSEDES DIRECTIVES D-E3 070302 5 & D-E3 070302 6 SERVICES - SERVICE EQUIPMENT- PANELBOARDS This Directive is being issued by a provincial safety manager pursuant to

More information

MODEL STANDING OFFER FOR A LOW VOLTAGE BASIC CONNECTION SERVICE. (Effective 1 December 2017)

MODEL STANDING OFFER FOR A LOW VOLTAGE BASIC CONNECTION SERVICE. (Effective 1 December 2017) MODEL STANDING OFFER FOR A LOW VOLTAGE BASIC CONNECTION SERVICE Contents 1 THE PARTIES...3 2 PURPOSE OF THIS DOCUMENT...3 3 INTERPRETATION...3 4 CONTRACT TERM...4 4.1 Commencement of contract...4 4.2 Termination

More information

BUILDING/FIRE/ZONING PERMIT GUIDE

BUILDING/FIRE/ZONING PERMIT GUIDE BUILDING/FIRE/ZONING PERMIT GUIDE Summary Guidelines The following is an instructional guide that will serve to assist you in securing the various permits issued by the Bureau of Code Administration. In

More information

SERVICE ENTRANCES. OPPD S Electrical Service Designer (ESD) shall designate the Point Of Entrance.

SERVICE ENTRANCES. OPPD S Electrical Service Designer (ESD) shall designate the Point Of Entrance. SERVICE ENTRANCES 3.01 POINT OF ENTRANCE General Service The customer, or the customer s electrician, should provide OPPD with a site plan, load schedule, and voltage requirements when requesting service.

More information

Small Scale Solar Permit Application

Small Scale Solar Permit Application Town of Berne Small Scale Solar Permit Application Town of Berne PO Box 57 Berne, NY 12023 (518) 872-1448 2/14/18 PROJECT ELIGIBILITY FOR PERMITTING PROCESS By submitting this application, the applicant

More information

Applying For New or Revised Electric Service. ComEd is happy to assist you in initiating new or revised electric service to your location.

Applying For New or Revised Electric Service. ComEd is happy to assist you in initiating new or revised electric service to your location. ComEd Applying For New or Revised Electric Service ear Customer: ComEd is happy to assist you in initiating new or revised electric service to your location. ComEd must be notified prior to any new construction,

More information

Conveyor Safe Operating Procedures

Conveyor Safe Operating Procedures Conveyor Safe Operating Procedures www.seedforsafety.org 044-22681251. 1 SAFE OPERATING PROCEDURES BEFORE INITIAL START-UP: 1. Lockout / tag out all power. 2. Lubricate all bearings in accordance with

More information

Facility Interconnection Requirements

Facility Interconnection Requirements Facility Interconnection Effective 1/1/2016 1. Purpose Facility Interconnection Facility Interconnection (FAC-001-2) To avoid adverse impacts on the reliability of the Bulk Electric System (BES), RPU documents

More information

Code Change Alert: Permitting of Solar Photovoltaic Systems in Washington State

Code Change Alert: Permitting of Solar Photovoltaic Systems in Washington State Code Change Alert: Permitting of Solar Photovoltaic Systems in Washington State Emergency Rule Regarding Rooftop Solar Photovoltaic Installations On June 13, 2014 the Washington State Building Code Council

More information

Objectives and Task Analysis for a Small Wind Energy System Installer

Objectives and Task Analysis for a Small Wind Energy System Installer North American Board of Certified Energy Practitioners Small Wind Technical Committee Document Approved December 7, 2006 Objectives and Task Analysis for a Small Wind Energy System Installer Introduction

More information

Automated Meters Equal Better Service to CVEA Members

Automated Meters Equal Better Service to CVEA Members Copper Valley Automated Meters Equal Better Service to CVEA Members Above, the photo above depicts the flow of information using automated meters. Opposite, a picture of an automated meter, similar to

More information

Metering Procedures for PA Renewable Energy Credits (MPREC)

Metering Procedures for PA Renewable Energy Credits (MPREC) Metering Procedures for PA 11-80 Renewable Energy Credits (MPREC) Published: 01/01/2015 Revised: 08/08/2017 MPREC REV. 4 1.0 Introduction: A Facility must follow the metering specifications in Tables 1-1

More information

TECHNICAL SPECIFICATIONS & SPECIAL CONDITIONS OF CONTRACT FOR ELECTRICAL WORKS CHAPTER 1 SPECIAL CONDITIONS OF CONTRACT

TECHNICAL SPECIFICATIONS & SPECIAL CONDITIONS OF CONTRACT FOR ELECTRICAL WORKS CHAPTER 1 SPECIAL CONDITIONS OF CONTRACT TECHNICAL SPECIFICATIONS & SPECIAL CONDITIONS OF CONTRACT FOR ELECTRICAL WORKS CHAPTER 1 SPECIAL CONDITIONS OF CONTRACT 1.1 General 1.1.1 These Special Conditions of Contract supplement the General Instructions.

More information

SECTION BASIC ELECTRICAL REQUIREMENTS

SECTION BASIC ELECTRICAL REQUIREMENTS PART 1 - GENERAL 1.1 RELATED DOCUMENTS A. Drawings and general provisions of Contract, including General and Supplementary Conditions, apply to work of this section. 1.2 SUMMARY A. This section specifies

More information

INTERCONNECTION APPLICATION AND AGREEMENT

INTERCONNECTION APPLICATION AND AGREEMENT INTERCONNECTION APPLICATION AND AGREEMENT With Terms and Conditions for Interconnection For a Level 1 Review (Certified Inverter-based Units under 10kW) Mailing Address PSE&G Net Metering 750 Walnut Avenue

More information

POLICY FOR MISCELLANEOUS CUSTOMER CHARGES

POLICY FOR MISCELLANEOUS CUSTOMER CHARGES Effective: February 01, 2016 Page 1 of 6 POLICY FOR MISCELLANEOUS CUSTOMER CHARGES I. INTRODUCTION Within the service area of CPS Energy, CPS Energy will provide services for Customers according to the

More information

Commercial Energy Savings Guide

Commercial Energy Savings Guide Commercial Energy Savings Guide www.touchstoneenergy.coop Commercial Energy Saving Tips This guide provides basic hints on ways to reduce energy costs for business customers. All Touchstone Energy cooperatives

More information

Long Island Power Authority Seventh Revised Leaf No. 16

Long Island Power Authority Seventh Revised Leaf No. 16 Seventh Revised Leaf No. 16 I. General Information (continued): B. Abbreviations and Definitions (continued): Demand Customer: A Customer who is billed for Demand charges. Demand Meter: The device that

More information

SUBCOURSE EDITION EN UTILITIES II

SUBCOURSE EDITION EN UTILITIES II SUBCOURSE EDITION EN0389 9 UTILITIES II ARMY CORRESPONDENCE COURSE ENGINEER SUBCOURSE 389-9 UTILITIES II United States Army Engineer School EDITION 9 (NID 906) INTRODUCTION The material in this subcourse

More information

UNDERGROUND SERVICES (RESIDENTIAL) SINGLE FAMILY RESIDENTIAL, DUPLEXES, OR TOWNHOUSES

UNDERGROUND SERVICES (RESIDENTIAL) SINGLE FAMILY RESIDENTIAL, DUPLEXES, OR TOWNHOUSES 7.01 GENERAL UNDERGROUND SERVICES (RESIDENTIAL) SINGLE FAMILY RESIDENTIAL, DUPLEXES, OR TOWNHOUSES Also refer to Chapter 3 (Service Entrances), and Chapter 4 (Metering Installation). OPPD will install,

More information

DISTRIBUTION NETWORK OPERATOR CONNECTION CHARGING METHODOLOGY

DISTRIBUTION NETWORK OPERATOR CONNECTION CHARGING METHODOLOGY DISTRIBUTION NETWORK OPERATOR CONNECTION CHARGING METHODOLOGY Prishtina 2017 Contents 1. Purpose... 4 1.1 Scope... 4 1.2 Definitions and Terms... 4 2. Introduction and Background... 7 2.1 Legal and Regulatory

More information

COUNTY OF RIVERSIDE BUILDING AND SAFETY DEPARTMENT PHOTOVOLTAIC PERMITTING GUIDELINES

COUNTY OF RIVERSIDE BUILDING AND SAFETY DEPARTMENT PHOTOVOLTAIC PERMITTING GUIDELINES COUNTY OF RIVERSIDE BUILDING AND SAFETY DEPARTMENT Mike Lara Building Official PHOTOVOLTAIC PERMITTING GUIDELINES PLANS AND PERMITS In order to minimize installation problems, plans must be provided that

More information

Central Lincoln PUD Commercial Service Guidelines & Standards

Central Lincoln PUD Commercial Service Guidelines & Standards Central Lincoln PUD Commercial Service Guidelines & Standards Overview of Hook-Up Procedures: The following is a general outline of how you get a new electrical service for commercial and other non-residential

More information

Effective June, Eaton-Durham Model # UTRS223ACH. Siemens, Model # SUAS877-PG. (or Landis & Gyr # UAS877-PG) Milbank. Model # U1980-O.

Effective June, Eaton-Durham Model # UTRS223ACH. Siemens, Model # SUAS877-PG. (or Landis & Gyr # UAS877-PG) Milbank. Model # U1980-O. Siemens, Model # SUAS877-PG (or Landis & Gyr # UAS877-PG) Eaton-Durham Model # UTRS223ACH Milbank Midwest Model # U980-O UTRS223AMEP These are some examples of the single meter sockets we require for underground

More information

NY State Unified Solar Permit

NY State Unified Solar Permit PERMIT APPLICATION NY State Unified Solar Permit Unified solar permitting is available statewide for eligible solar photovoltaic (PV) installations. Municipal authorities that adopt the unified permit

More information

Accreditation Audit Checklist (Version 3.0)

Accreditation Audit Checklist (Version 3.0) Accreditation Audit Checklist (Version 3.0) (Based on EASA Std. AR100-2015 and applies for all audits completed after April 1, 2018) Scope The EASA Accreditation Program applies only to three-phase, squirrel-cage

More information

SERVICE CLASSIFICATION NO. 6

SERVICE CLASSIFICATION NO. 6 P.S.C. NO. 3 ELECTRICITY LEAF: 293 ORANGE AND ROCKLAND UTILITIES, INC. REVISION: 2 INITIAL EFFECTIVE DATE: July 19, 2012 SUPERSEDING REVISION: 1 SERVICE CLASSIFICATION NO. 6 APPLICABLE TO USE OF SERVICE

More information

ELECTRICAL INSPECTION BULLETIN (Effective )

ELECTRICAL INSPECTION BULLETIN (Effective ) ELECTRICAL INSPECTION BULLETIN (Effective 2009-02-01) Rule 36-000 Customer Owned High Voltage Installations With the increase in customer own high voltage equipment there appears to be confusion over which

More information

NY State Unified Solar Permit

NY State Unified Solar Permit PERMIT APPLICATION NY State Unified Solar Permit PROJECT ELIGIBILITY FOR UNIFIED PERMITTING PROCESS By submitting this application, the applicant attests that the proposed project meets the established

More information

NY State Unified Solar Permit

NY State Unified Solar Permit VILLAGE OF FARMINGDALE NY State Unified Solar Permit Unified solar permitting is available statewide for eligible solar photovoltaic (PV) installations. Municipal authorities that adopt the unified permit

More information

SECTION LOW-VOLTAGE TRANSFORMERS

SECTION LOW-VOLTAGE TRANSFORMERS PART 1 GENERAL 1.1 DESCRIPTION SECTION 26 22 00 SPEC WRITER NOTE: Use this section only for NCA projects. Delete between // // if not applicable to project. Also, delete any other item or paragraph not

More information

The ESP Handbook. Chapter 15 Obtaining Consumer Usage and Metering Information. Version 7.0 February 1, 2017

The ESP Handbook. Chapter 15 Obtaining Consumer Usage and Metering Information. Version 7.0 February 1, 2017 The ESP Handbook Chapter 15 Obtaining Consumer Usage and Metering Information Version 7.0 February 1, 2017 SCE is committed to providing timely and accurate information to its customers or their authorized

More information

DEPARTMENT OF LICENSING AND REGULATORY AFFAIRS DIRECTOR S OFFICE CONSTRUCTION CODE

DEPARTMENT OF LICENSING AND REGULATORY AFFAIRS DIRECTOR S OFFICE CONSTRUCTION CODE DEPARTMENT OF LICENSING AND REGULATORY AFFAIRS DIRECTOR S OFFICE CONSTRUCTION CODE (By authority conferred on the director of the department of licensing and regulatory affairs by section 4 of 1972 PA

More information

METERING GUIDE PART 1 METERING GENERAL

METERING GUIDE PART 1 METERING GENERAL 1 METERING GUIDE PART 1 METERING GENERAL 2 METERING GUIDE 1 INTRODUCTION 3 PURPOSE OF THIS GUIDE 3 METERING GENERAL 4 ELECTRICITY SUPPLY - INDUSTRY PLAYERS 4 1.1.2 Generators 4 1.1.3 Networks 4 1.1.4 Retailers

More information

BANKNOTE READER BT-11

BANKNOTE READER BT-11 English Jofemar BANKNOTE READER BT-11 User s Manual MNP85ENV00 Rev.02 (2014-01-07) Page 1 of 20 Note WARNING Read these instructions carefully before using the appliance: This symbol means there are more

More information